Attachment A - Applicant's Plan Set and Written Statement
Regular Meeting, October 1, 2026 · item 4A: Consideration of a Site Review application for a proposal to redevelop the Naropa campus at 2106 and 2130 Arapahoe Ave. with approximately 1… · 97 pages
This is the text extracted from the file, without its layout, tables, or images. Use the original for anything that matters.
HUB BOULDER - ARAPAHOE SITE PLAN REVIEW - RESUBMITTAL 03 2130 ARAPAHOE AVE, BOULDER, CO 80302
SITE: 2130 ARAPAHOE AVE. BOULDER, CO 80302
SHEET INDEX 01-GENERAL A 0.0 COVER SHEET A 0.01 HIGH DENSITY ZONING A 0.02 ZONING MAP - RH-1 CU OWNERSHIP A 0.03 EXISTING AND PROPOSED LAND USE A 0.04 EXISTING CONTEXT AROUND SITE A 0.05 EXISTING CONTEXT BUILDING HEIGHT A 0.06 SITE CONTEXT - CU CAMPUS MASTERPLAN 2021 A 0.07 SITE CONTEXT - CU CAMPUS MASTERPLAN 2021 A 0.08 SITE CONNECTIONS AND CIRCULATION A 0.09 SITE CIRCULATION A 0.10 FLOOD DIAGRAMS A 0.11 FLOOD DIAGRAMS A 0.12 SITE ANALYSIS - EXISTING CONDITIONS AND SITE FEATURES A 0.13 EXISTING CONDITIONS STREET VIEWS A 0.14 SOLAR SHADING PLAN A 0.15 SITE SHADOW ANALYSIS A 0.16 MASSING DEVELOPMENT A 0.20 CITY OF BOULDER AREA PLAN 02-CIVIL C1.00
VICINITY MAP
C2.00 C3.00 C4.00
EXISTING CONDITIONS & DEMOLITION PLAN SITE PLAN GRADING PLAN UTILITY PLAN
C5.00 C6.00 C6.10 C6.20 C6.30 C6.40 C6.50 C7.00 C7.10 D1 D2
EASEMENT PLAN OVERALL STORM PLAN DRAINAGE DETAILS DRAINAGE DETAILS DRAINAGE DETAILS DRAINAGE DETAILS DRAINAGE DETAILS TURNING MOVEMENTS TURNING MOVEMENTS EXISTING DRAINAGE PLAN PROPOSED DRAINAGE PLAN
03-LANDSCAPE L001 SITE NOTES L002 OVERALL SITE PLAN L003 TREE INVENTORY LS101 GROUND FLOOR SITE PLAN LS102 SECOND FLOOR SITE PLAN LS103 FOURTH FLOOR SITE PLAN LS201 ENLARGEMENT PLAN LS202 ENLARGEMENT PLAN LS301 SECTIONS LS501 SITE DETAILS LS502 SITE DETAILS LP100 PLANTING NOTES AND SCHEDULE LP101 GROUND FLOOR PLANTING PLAN LP102 SECOND FLOOR PLANTING PLAN LP103 FOURTH FLOOR PLANTING PLAN LP501 PLANTING DETAILS
05-ARCHITECTURAL A 1.00 SITE PLAN A 1.01 SETBACK PLAN A 1.02 ENLARGED PARKING PLANS & INFORMATION A 1.11 LEVEL 1 PLAN A 1.12 LEVEL 2 PLAN A 1.13 LEVEL 3 PLAN A 1.14 LEVEL 4 PLAN A 1.15 ROOF PLAN A 2.00 EXTERIOR NORTH ELEVATION A 2.01 EXTERIOR WEST ELEVATION A 2.02 EXTERIOR SOUTH ELEVATION A 2.03 EXTERIOR EAST ELEVATION A 2.04 EXTERIOR ELEVATIONS - COURTYARD A 2.05 EXTERIOR ELEVATIONS - TOWNHOUSE A 2.06 EXTERIOR ELEVATIONS - ARAPAHOE & CHESTNUT HOUSE A 3.00 BUILDING SECTIONS A 3.01 BUILDING SECTIONS A 9.00 CONCEPTUAL RENDERINGS A 9.01 CONCEPTUAL RENDERINGS A 9.02 CONCEPTUAL SITE EXPERIENCE VIGNETTES A 9.10 DESIGN EXCELLENCE A 9.11 DESIGN EXCELLENCE A 9.12 DESIGN EXCELLENCE A 9.13 DESIGN EXCELLENCE A 9.14 DESIGN EXCELLENCE
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
COVER SHEET
A 0.0
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
PROJECT SITE: 2130 ARAPAHOE AVE.
The majority of the CU campus today is mostly surrounded by zoning districts with FARs greater than 1.0, and much of the surroundings have an FAR of 1.5 or greater. The intent of doing so was to congregate student housing areas adjacent to campus in clearly defined areas and thus limit their impact on single family residential neighborhoods. These zones include the RH-3 (unlimited FAR), RH-5 (1.5 FAR), BMS (1.5 FAR), BT-1 (1.4 FAR), with Site Review approval. Allowing these greater density areas surrounding the campus incentivizes private development to target these zones for student housing projects, while maintaining the city’s purview via the Land Use Code, over the development of these areas.
HIGH DENSITY ZONING DISTRICTS BORDERING UNIVERSITY OF COLORADO PERIMETER HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
HIGH DENSITY ZONING
A 0.01
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
RESIDENCE ONE - ENLARGED ZONING MAP
UNIVERSITY OF COLORADO OWNERSHIP IN RELATION TO LOW DENSITY ZONES
LOW DENSITY ZONING MAP LEGEND:
PROJECT SITE
RH-1 ZONING DISTRICT
RMX-1 ZONING DISTRICT
RH-2 ZONING DISTRICT
UNIVERSITY OWNED PARCELS
There are areas where the city has maintained lower density zoning adjacent to the campus. The most relevant one to this discussion is the area west of Naropa, which today is zoned RH-1, where the density is limited to 0.67 FAR. The purpose of doing so is clearly with the intent of limiting the impacts of larger scale and higher density projects, from impacting Goss-Grove. At an FAR of .67, the RH-1 zoning ostensibly limits the possibility of significant private development between the Public zoned areas, which are nominally owned by CU. It does so because any project of scale would need substantially more development capability (1.5 FAR or greater), than the RH-1 affords. This is particularly true when we take into account that the entire area is within the 100-year floodplain and has to accommodate the additional limitation on development that this requires.
RESIDENCE ONE - AERIAL VIEW OF CONSTRUCTION
Today, CU already owns significant parcels in the RH-1 zone as shown in the map above. While RH-1 zoning prevents the redevelopment of the area between the Public zoning and the properties north of Arapahoe by private developers, it makes no such limitation on development by CU. Pictured to the right is the cleared site prepared for the construction of the Residence One building. Above this is the city’s zoning map with the building site outlined. This map clearly shows that the site significantly overlaps with the RH-1 zone. HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
ZONING MAP - RH-1 CU OWNERSHIP
A 0.02
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
PROJECT SITE: 2130 ARAPAHOE AVE.
CURRENT LAND USE With the departure of Naropa from this site and their needs in mind for the sale of the property, as well as the city’s need for housing, particularly in this location, the Public Zone District no longer makes sense for this property. Specifically considering residential use on this site, while Public Zoning supports an unlimited floor area for any use other than residential, it allows a maximum of 6 dwelling units per acre for residential use. This effectively rules out the purchase of property by a private residential developer. The proposed change is consistent with the policies and overall intent of the Comp Plan, and specifically with the following policies:
PROJECT SITE: 2130 ARAPAHOE AVE.
PROPOSED LAND USE 2.13 Protection of Residential Neighborhoods Adjacent to Non- Residential - Building up the density of housing geared towards CU students immediately adjacent to the University prevents the leakage of student housing into the single-family neighborhoods to the north. This has been the policy of the city for the majority of the campus perimeter. Allowing for significant development of private student housing south of Arapahoe maintains the city’s land use policy and control over that development and does so in a manner that cannot be predicted if the property is purchased and developed by the University.
8.13 Support for Community Facilities - Naropa needs to make this change in their facilities in order to maintain its long-term health and viability. The sale of this land that they have been stewards of for 40 years facilitates the institution's future and sustainability in the Boulder community. 7.07 Mixture of Housing Types - Providing student-oriented housing in structures that are intended for the specific needs of students, and particularly at the CU Campus perimeter is consistent with placing students in an appropriate housing context, allowing for the continuity of family oriented housing and mixed middle income housing in other areas of the city more suited for those needs.
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
EXISTING AND PROPOSED LAND USE
A 0.03
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
23RD ST.
22ND ST.
21ST ST.
GROVE ST.
MARINE ST.
26TH ST.
19TH ST.
20TH ST.
FOLSOM ST.
17TH ST.
18TH ST.
ARAPAHOE AVE.
ATHENS ST.
LOW-DENSITY RESIDENTIAL
HIGH-DENSITY RESIDENTIAL
HOSPITALITY
MID-DENSITY RESIDENTIAL
CAMPUS
COMMERCIAL
BUILDING HEIGHTS 1. 25' 2. 27' 3. 33' 4. 35' 5. 31' 6. 21' 7. 26' 8. 31' 9. 15' 10. 15'
11. 45' 12. 45' 13. 46' 14. 41' 15. 32' 16. 41' 17. 68' 18. 23' 19. 30' 20. 16'
NOT TO SCALE
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
EXISTING CONTEXT AROUND SITE
A 0.04
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
LEGEND 100' PERIMETER FROM PROPERTY LINE HEIGHT OF BUILDING IN FEET
HEIGHT OF EXISTING BUILDINGS AROUND SITE HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
EXISTING CONTEXT BUILDING HEIGHT
A 0.05
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
23RD ST.
22ND ST.
21ST ST.
20TH ST.
19TH ST.
PROJECT SITE: 2130 ARAPAHOE AVE.
CU RESIDENCE ONE UNDER CONSTRUCTION
MILLENNIUM HOTEL REDEVELOPMENT THE STANDARD UNDER CONTRSUTCTION
PROJECT SITE - 2130 ARAPAHOE AVE. RH-1 ZONING DISTRICT NEW AND PROPOSED PRIVATE STUDENT HOUSING NEW AND PROPOSED CU STUDENT HOUSING EXISTING CU BUILDINGS CU RESIDENCE ONE PROJECT SITE
CU CAMPUS MASTER PLAN 2021 - NORTH BOULDER CREEK CAMPUS FRAMEWORK
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
SITE CONTEXT - CU CAMPUS MASTERPLAN 2021
A 0.06
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
CU CAMPUS MASTERPLAN 2021 NORTH BOULDER CREEK FRAMEWORK – BUILDING HEIGHT CONTEXT
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
SITE CONTEXT - CU CAMPUS MASTERPLAN 2021
A 0.07
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
EMMA GOMEZ MARTINEZ PARK
TO PEARL ST.
LEGEND SITE
MCGUCKIN WAY GOSS CIR W.
BIKE ROUTE
GOSS ST.
OPEN GREEN SPACE
RETAIL & GROCERY
GROVE CIR W.
23TH STREET
20TH STREET
BUS STOP
GROVE ST.
BUS ROUTE CAN PROJECT
ARAPAHOE AVE.
PROPOSED CAMPUS WALK CONNECTION
SITE
1/4 MILE
MARINE ST.
1/2 MILE
ROADS
RETAIL & GROCERY
28TH ST.
1/4 MILE
CAMPUS FOLSOM ST.
MARINE ST.
19TH STREET
17TH STREET
ARAPAHOE AVE.
1/2 MILE
MULTI-USE PATH
22TH STREET
GOSS ST.
21TH STREET
18TH STREET
EET
STR
EET
15TH
STR
19TH STREET
16TH
21TH STREET
CANYON BLVD.
ATHENS ST.
GRANDVIEW AVE.
ATHLETICS PRACTICE FIELD
CORDRY CT.
BOULDER CREEK
STADIUM DR.
MACKY DR.
UNIVERSITY AVE.
TAFT DR.
SU ND
OW
N
LN
.
UNIVERSITY HEIGHTS AVE.
PLEASANT ST.
SPRINGDALE LN.
NOT TO SCALE
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
SITE CONNECTIONS AND CIRCULATION
A 0.08
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
PROPOSED PUSH BUTTON CROSSING
PEDESTRIAN CROSSING
ARAPAHOE AVE.
LEGEND PROPERTY LINE BUILDING FOOTPRINT
SLOPED WALK TO MAIN LEVEL
SLOPED WALK TO MAIN LEVEL
BUS STOP PRIVATE VEHICLE ACCESS
MAIN BUILDING
TOWNHOUSE BUILDING
RAMP TO MAIN LEVEL OF ARAPAHOE AND CHESTNUT HOUSE
VEHICLE ENTRY PUBLIC ROAD BIKE ROUTE
LINCOLN HALL ELEVATORS TO ALL OTHER LEVELS
BIKE PARKING SHORT-TERM
SLOPED WALK TO MAIN LEVEL
BIKE PARKING LONG-TERM MULTI-USE PATH PRIVATE WALK ACCESSIBLE ROUTE BUILDING ENTRY
H.C. VAN
H.C. H.C.
BICYCLE STATION ACCESS FROM H.C. PARKING TO MAIN LEVEL
PARKING GARAGE SIDEWALK
MARINE ST. 0
SITE CIRCULATION DIAGRAM
16'
32'
64'
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026 TO CAMPUS
TO CAMPUS
SITE CIRCULATION
A 0.09
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
ARAPAHOE HOUSE BFE = 5313.45 FPE = 5315.45' MIN. FFE = 5315.59'
MAIN BUILDING BFE = 5312.57' FPE = 5314.57' MIN. FFE = 5314.59'
LINCOLN HALL BFE = 5312.24 FPE = 5314.24' MIN. FFE = 5315.58'
TOWNHOUSE BUILDING BFE = 5311.47 FPE = 5313.47' MIN. FFE = 5313.59'
TOWNHOUSE BUILDING LOW POINT = 5308.65
R
CHESTNUT HOUSE BFE = 5313.55 FPE = 5315.45' MIN. FFE = 5315.59'
PROJECT SITE: 2130 ARAPAHOE AVE.
' 25
"
-0
UP
DN
UP
UP
A 0.11 1
UP
COVERED PARKING BFE = 5312.57 FPE = 5314.57' PARKING & STORAGE AREA FFE = 5311.09' (1.48' BELOW BFE, 1.5' MAX. ALLOWED)
1 A 0.10
R '-
25 0"
2 A 0.11
FLOODPLAIN CONTEXT
BASE FLOOD ELEVATION - SITE PLAN
MAIN BUILDING BFE = 5312.57 FPE = 5314.57' MIN. FFE = 5314.59'
MAIN BUILDING LOW POINT = 5306.50
ROOF LEVEL 142' - 4" LEVEL 4 132' - 0" RESIDENTIAL UNITS
RESIDENTIAL UNITS
RESIDENTIAL UNITS
RESIDENTIAL UNITS LEVEL 3 121' - 8"
BIKE PARKING
EXISTING GRADE SHOWN IN GREEN BASE FLOOD ELEVATION & BUILDING LOW POINT - SECTION DIAGRAM
COVERED PARKING
MAX. 18" BELOW PARKING BFE
LEVEL 2 111' - 4" LEVEL 1 100' - 0"
LEVEL 1 @ F.P.E. = 5314' 7 1/8" MAIN BUILDING - BFE 5312' - 6 7/8"
PARKING 96' - 6" BLDG. LOW POINT 5306' - 6"
8' - 1" BUILDING LOW-POINT TO FLOOD PROTECTION ELEVATION
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
FLOOD DIAGRAMS
A 0.10
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
ENCLOSURE OPENING CALCULATIONS AREA OF ENCLOSURE: 28, 019 SF OPENINGS PROVIDED:
117,792 SI
NORTH: 376 SF SOUTH: 442 SF
= =
54,144 SI 63,648 SI
TOTAL: 818 SF
=
117,792 SI
1 SI OF OPENINGS PER 1SF OF ENCLOSED SPACE OPENINGS REQUIRED: 28,019 SI
PER CITY OF BOULDER MUNICIPAL CODE SECTION 9-3-3: REGULATIONS GOVERNING THE ONE HUNDREDYEAR FLOODPLAIN. ENCLOSURES: ENCLOSURES BELOW THE LOWEST FLOOR THAT ARE UNFINISHED OR FLOOD RESISTANT, USABLE SOLELY FOR PARKING OF VEHICLES, CRAWL SPACES, BUILDING ACCESS OR STORAGE, IN AN AREA THAT IS NOT A BASEMENT, AND THAT ARE NOT FLOODPROOFED AS SET FORTH IN THIS SECTION SHALL MEET THE FOLLOWING REQUIREMENTS: (A)COMPLIANCE WITH THE PROVISIONS OF PARAGRAPHS (A)(2), (A)(3), AND (A)(4) OF THIS SECTION; AND (B)DESIGN AND CONSTRUCTION THAT AUTOMATICALLY EQUALIZES HYDROSTATIC FLOOD FORCES ON EXTERIOR WALLS BY ALLOWING FOR THE ENTRY AND EXIT OF FLOODWATERS. I.DESIGNS FOR MEETING THIS REQUIREMENT SHALL MEET OR EXCEED THE FOLLOWING MINIMUM CRITERIA: A MINIMUM OF TWO OPENINGS HAVING A TOTAL NET AREA OF NOT LESS THAN ONE SQUARE INCH FOR EVERY SQUARE FOOT OF ENCLOSED AREA SUBJECT TO FLOODING SHALL BE PROVIDED. THE BOTTOM OF ALL OPENINGS SHALL BE NO HIGHER THAN ONE FOOT ABOVE GRADE. OPENINGS MAY BE EQUIPPED WITH SCREENS, LOUVERS, VALVES, OR OTHER COVERINGS OR DEVICES PROVIDED THAT THEY PERMIT THE AUTOMATIC ENTRY AND EXIT OF FLOODWATERS.
SF: SQUARE FEET SI: SQUARE INCH
II.ANY DESIGNS NOT IN CONFORMANCE WITH SUBPARAGRAPH (B)I. ABOVE SHALL BE CERTIFIED BY A REGISTERED PROFESSIONAL ENGINEER OR LICENSED ARCHITECT AND SHALL CONFORM WITH THE MOST CURRENT FEMA TECHNICAL BULLETIN ON OPENINGS IN FOUNDATION WALLS.
SCREENED OPENINGS: 376 SF LEVEL 2 111' - 4"
LEVEL 1 100' - 0" MAIN BUILDING - BFE 5312' - 6 7/8" 7 1/4"
PARKING 96' - 6"
1
NORTH ELEV - FLOOD VENT DIAGRAM 1/8" = 1'-0"
ROOF LEVEL 142' - 4"
LEVEL 4 132' - 0"
LEVEL 3 121' - 8"
LEVEL 2 111' - 4"
PERFORATED SCREEN OVERHEAD DOOR TO GARAGE
SWING DOOR TO BIKE STORAGE
GARAGE BEYOND
SCREENED OPENINGS: 263 SF LEVEL 1 100' - 0"
OPENING: 209 SF
7 1/4"
MAIN BUILDING - BFE 5312' - 6 7/8"
2
SOUTH ELEV - FLOOD VENT DIAGRAM
PARKING 96' - 6" BLDG. LOW POINT 5306' - 6"
1/8" = 1'-0"
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
FLOOD DIAGRAMS
A 0.11
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
CHESTNUT HOUSE: TO BE RELOCATED ON SITE
ARAPAHOE HOUSE:
LA
ND
RY
MA
DA
RK
UN
(6)
BO
BO
UN
RK
DA
MA
RY
ND
LA
TO BE RELOCATED ON SITE
(4)
TEA HOUSE: TO BE RELOCATED TO NAROPA CAMPUS
HARRY SMITH PRINT SHOP: EXTENSIVE FIRE DAMAGE
JUNIPER COTTAGE: EXTENSIVE FLOOD DAMAGE (15)
(15)
(2)
EXISTING PARKING ON SITE: STANDARD 97 ACCESSIBLE 3 TOTAL 100 (8)
LEGEND
(10)
(10)
H.C. (3) H.C.
(5)
H.C. (4)
(4)
(4)
SITE ANALYSIS - EXISTING CONDITIONS AND SITE FEATURES
(10)
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
SITE ANALYSIS - EXISTING CONDITIONS AND SITE FEATURES
A 0.12
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
ARAPAHOE AVE.
LOOKING WEST ON ARAPAHOE AVE.
LOOKING EAST ON ARAPAHOE AVE.
LOOKING NORTH ON MARINE ST. ALONG ALLEY
LOOKING NORTH IN SOUTH PARKING LOT TOWARDS LINCOLN HALL
MARINE ST.
LOOKING SOUTH ON MARINE ST. TOWARDS CU CAMPUS
LOOKING NORTH ON MULTI-USE PATH TOWARDS ARAPAHOE AVE.
EXISTING STREET VIEWS WITH PROPOSED BUILDING OVERLAY
LOOKING NORTH ON ARAPAHOE AVE. TOWARDS 22ND ST.
NOT TO SCALE
LOOKING EAST ON ARAPAHOE AVE. FROM NW CORNER OF PROPERTY HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
EXISTING CONDITIONS STREET VIEWS
A 0.13
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
RH-2 ZONING DISTRICT RESIDENTIAL-HIGH 2 SOLAR ACCESS AREA II 25' SOLAR FENCE
RMX-1 ZONING DISTRICT RESIDENTIAL-MIXED 1 SOLAR ACCESS AREA II 25' SOLAR FENCE
11
'
1 53
53
ARAPAHOE AVE.
5312'
5312.19'
5311.17'
DISTANCE TO XX' SOLAR FENCE/PROPERTY LINE ADJUSTED SHADOW LENGTH A XXXX.XX'
ROOF ELEMENT TAG USGS ELEVATION
5310.13'
.4'
' (L)
5361.69'
50
RELOCATED ARAPAHOE HOUSE
.9'
5313.22'
(L)
B 5338.07' ARAPAHOE FFE = 5315.59'
53 11 '
10
'
2.3
A
53
(L)
75
.6'
PROPERTY LINE
(L)
5311'
69
5338.07'
P ZONING DISTRICT PUBLIC SOLAR ACCESS AREA III NOT PROTECTED BY SOLAR FENCE
5310.44'
(L)
5313.14' 5313.41'
' 09 53
5312'
0'
5312.33'
5357.09'
D
RH-5 ZONING DISTRICT 1' RESIDENTIAL-HIGH 5 531 SOLAR ACCESS AREA II 25' SOLAR FENCE
TOWNHOUSE BUILDING NEW (3) STORY STUDENT HOUSING TOWNHOUSES
I
TOWNHOUSE FFE = 5313.59'
LINCOLN HALL EXISTING (2) STORY HISTORIC SCHOOL HOUSE TO BE RENOVATED
CHESTNUT FFE = 5315.59'
(L)
RH-1 ZONING DISTRICT RESIDENTIAL-HIGH 2 SOLAR ACCESS AREA II 25' SOLAR FENCE
5363.57'
5309'
MAIN BUILDING NEW (4) STORY STUDENT HOUSING BUILDING
RELOCATED CHESTNUT HOUSE
C 5337.36'
'
10
53
H
'
0.6
5313.24'
CITY OF BOULDER SOLAR SHADING ANALYSIS LEGEND
.1'
64
MAIN BUILDING FFE = 5314.59'
53 11 '
E
53
11
PROPERTY LINE
5361.41'
'
5311.97'
53 09 '
MAIN BUILDING FFE = 5314.59'
(L) .8'
62 5361.42' F
530
5308'
8'
5310 '
(L)
5311'
PARKING GARAGE FFE = 5310.24'
64 .8'
UP
PROPERTY LINE
5361.42' G
531
2'
MAIN BUILDING FFE = 5314.59'
PROPERTY LINE
1
SOLAR SHADING PLAN
0
30'
08
'
'
09
53
53
53 1 15'
PROPERTY LINE
5
0'
MARINE ST. 5311'
7' 30
53
P ZONING DISTRICT PUBLIC 6' 0 SOLAR53ACCESS AREA III NOT PROTECTED BY SOLAR FENCE
07
'
60'
1" = 30'-0"
0.00 - SOLAR SHADING ANALYSIS TABLE ROOF ELEMENT A B C D E F G H I
PROPERTY ZONE DISTRICT RMX-1 RMX-1 RH-1 RH-2 RMX-1 RH-1 RH-1 RH-2 P
SOLAR FENCE HEIGHT 25 25 25 25 25 25 25 25 25
ELEVATION OF ROOF ELEMENT (y) 5338.1 5338.1 5337.4 5355.6 5361.4 5361.4 5361.4 5361.7 5363.6
ELEVATION OF GRADE AT PROPERTY LINE (x) 10AM 2PM 5312.2 5312.9 5312.7 5311.4 5312.2 5312.7 5312.0 5310.4 5310.1
RELATIVE HEIGHT OF ROOF ELEMENT (h) 10AM 2PM 25.9 25.2 24.7 44.2 49.2 48.7 49.5 51.3 53.4
LENGTH OF SHADOW (L) 10AM 2PM 2.3 0.6 -0.9 50.9 64.1 62.8 64.8 69.6 75.4
GENERAL CITY OF BOULDER SOLAR SHADING NOTES: 1. NEGATIVE SHADOW LENGTHS INDICATE ROOF ELEMENTS WHERE THE RELATIVE HEIGHT IS LESS THAN THE SOLAR FENCE HEIGHT . 2. AREAS NORTH OF NORTHERN MOST PROPERTY LINE ARE IN NON-BUILDABLE AREAS (R.O.W./STREET)
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
SOLAR SHADING PLAN
A 0.14
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
PROPOSED ELEMENT "I" 5361.69'
OF SHADOW
6.26' HEIGHT OF SHADOW
NON-BUILDABLE AREA
ARAPAHOE AVE. (R.O.W) NON-BUILDABLE AREA 5310.13'
5310.44'
ELEMENT "H" SHADOW SECTION
2
3/32" = 1'-0"
ELEMENT "I" SHADOW SECTION 3/32" = 1'-0"
RMX-1 ZONING DISTRICT RESIDENTIAL-MIXED 1 SOLAR ACCESS AREA II 25' SOLAR FENCE
ESTIMATED PROPERTY LINE
RMX-1 ZONING DISTRICT RESIDENTIAL-MIXED 1 SOLAR ACCESS AREA II 25' SOLAR FENCE
ELEMENT HEIGHT
OF ADJUSTED SHADOW
53.44' RELATIVE
ESTIMATED PROPERTY LINE 51.25' RELATIVE
75.40' LENGTH
ARAPAHOE AVE. (R.O.W) 8.84' HEIGHT
SOLAR FENCE
25.00'
OF ADJUSTED SHADOW
5363.57'
ELEMENT "I" SHADOW
ELEMENT'S SHADOW HITS PROTECTED SOLAR FENCE AT HEIGHT OF 6.26'. SHADOW IS 18.74' BELOW MAXIMUM HEIGHT
ELEMENT HEIGHT
ELEMENT'S SHADOW HITS PROTECTED SOLAR FENCE AT HEIGHT OF 8.84'. SHADOW IS 16.16' BELOW MAXIMUM HEIGHT
69.60' LENGTH
SHADOW ANALYSIS LEGEND
P ZONING DISTRICT PUBLIC SOLAR ACCESS AREA III NOT PROTECTED BY SOLAR FENCE
SHADOW FROM 35' BUILDING AT SETBACKS SHADOW FROM PROPOSED BUILDING
SHADOW FROM 35' BUILDING AT SETBACKS
APPROX. FOOTPRINT OF NEIGHBORING BUILDINGS
*NOTE: SHADOWS CAST AT 10 A.M. ON DECEMBER 21ST
ARAPAHOE AVE. 5310.44'
5310.13'
PROPERTY LINE RELOCATED ARAPAHOE HOUSE
5361.69' H
RELOCATED CHESTNUT HOUSE
MAIN BUILDING NEW (4) STORY STUDENT HOUSING BUILDING
5363.57'
I
RH-5 ZONING DISTRICT RESIDENTIAL-HIGH 5 SOLAR ACCESS AREA II 25' SOLAR FENCE
PROPOSED ELEMENT "H"
TOWNHOUSE BUILDING NEW (3) STORY STUDENT HOUSING TOWNHOUSES
3 A 0.15
LINCOLN HALL EXISTING (2) STORY HISTORIC SCHOOL HOUSE TO BE RENOVATED
2 A 0.15
PROPERTY LINE
RH-1 ZONING DISTRICT RESIDENTIAL-HIGH 2 SOLAR ACCESS AREA II 25' SOLAR FENCE
2'
PROPERTY LINE 531
3
PROPERTY LINE
ELEMENT "H" SHADOW
25.00' SOLAR FENCE
ESTIMATED PROPERTY LINE
PROPERTY LINE
PROPOSED ELEMENT "H"
PROPERTY LINE
PROPERTY LINE
MARINE ST. 1
SHADOW ANALYSIS 1" = 30'-0"
0
15'
30'
60'
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
SITE SHADOW ANALYSIS
A 0.15
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
1 - EXISTING CONDITIONS The existing site includes approximately 16 buildings organized haphazardly around the Landmarked Lincoln Hall at the center of the site. The buildings are interspersed by green spaces and contain three sycamore trees and one oak tree that are identified as Colorado “Champion” trees. These trees will remain and be protected throughout the construction process.
2 - MASSING The new apartment buildings are arranged in a U-shaped configuration that frames Lincoln Hall and preserves the central courtyard, allowing this open space to serve as a landscaped, multifunctional gathering area that reinforces the campus character and preserves the site's Champion Trees. Two 4-story tower elements subtly echo Lincoln Hall’s bell tower creating a dialogue with the historic structure.
3 - ARTICULATION & MATERIALITY The new building designs are intended to thoughtfully blend old and new, using brick cladding on the lower levels to create a visual connection with the historic core, while siding on the upper floors introduces a modern contrast. Recessed entryways and slight setbacks add depth, texture, and a human scale to the overall massing, ensuring the buildings feel approachable and wellintegrated into their surrounding context.
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
MASSING DEVELOPMENT
A 0.16
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
2106 ARAPAHOE AVE. F.A.R. SUMMARY
LVL 2 ARAPAHOE HOUSE 736 SF
SITE AREA = 161,909 SF | PROPOSED ZONING = RH-5 | F.A.R. OF 1.50 ALLOWABLE BUILDING AREA @ 1.50 F.A.R. = 242,863 SF PROPOSED BUILDING AREA = 221,982 SF (F.A.R. 1.37)
LVL 4 TH 1,042 SF LVL 2 LINCOLN HALL 3,419 SF
LVL 2 TH 5,602 SF
CITY OF BOULDER - AREA SCHEDULE (FAR) NAME
ROOF DECK NOT PART OF FAR
LEVEL 1 LVL 1 WEST 24,363 SF LVL 1 TH 5,722 SF LVL 1 EAST 8,412 SF LVL 1 SOUTH 5,333 SF LVL 1 LINCOLN HALL 4,016 SF LVL 1 ARAPAHOE HOUSE 1,174 SF LEVEL 1 CHESTNUT HOUSE 582 SF LEVEL 2 LVL 2 53,687 SF LVL 2 LINCOLN HALL 3,419 SF LVL 2 TH 5,602 SF LVL 2 ARAPAHOE HOUSE 736 SF LVL 2 CHESTNUT HOUSE 488 SF LEVEL 3 LVL 3 54,248 SF LVL 3 TH 4,875 SF LEVEL 4 LVL 4 48,282 SF LVL 4 TH 1,042 SF 221,982 SF
LVL 2 CHESTNUT HOUSE 488 SF
LVL 4 48,282 SF
4
AREA
LVL 2 53,687 SF
LEVEL 4 AREA PLAN
2
1/32" = 1'-0"
LEVEL 2 AREA PLAN 1/32" = 1'-0"
LVL 1 ARAPAHOE HOUSE 1,174 SF LVL 3 TH 4,875 SF
LVL 1 LINCOLN HALL 4,016 SF
LVL 1 TH 5,722 SF
LEVEL 1 CHESTNUT HOUSE 582 SF
LVL 1 EAST 8,412 SF
LVL 1 WEST 24,363 SF
LVL 3 54,248 SF COVERED BICYCLE AND VEHICULAR PARKING NOT PART OF FAR
LVL 1 SOUTH 5,333 SF
3
LEVEL 3 AREA PLAN 1/32" = 1'-0"
1
GROUND LEVEL AREA PLAN 1/32" = 1'-0" 0
24'
48'
96'
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
CITY OF BOULDER AREA PLAN
A 0.20
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
TOTAL UNIT & BED COUNTS BY BUILDING UNIT COUNT
UNIT TYPE
2
1
3
PROPOSED DITCH ACCESS ESMT.
A 2.05
EXISTING CURB CUT FOR MULTI-USE PATH
PROPOSED STORMWATER ESMT.
'
A 2.00
09
11
PROPOSED STORMWATER ESMT.
A 2.00
' 10 53 A 2.00
53
5312'
'
53
08
'
ARAPAHOE AVE.
53
NEW CROSSWALK & PUSH BUTTON, RE: CIVIL
(E) LINCOLN HALL 2BR/1BA FLAT 5BR/4BA FLAT
2
5312' PROPOSED RELOCATED B-CYCLE STATION 5311'
EXISTING BUS STOP & RELOCATED SHELTER
PROPERTY LINE EXISTING DITCH
' 10
RY
'
LA A 2.05
LINCOLN HALL (BUILDING 1) EXISTING (2) STORY HISTORIC SCHOOL HOUSE TO BE RENOVATED
(6)
3
TOWNHOUSE FFE = 5313.59'
PROPOSED DITCH ACCESS ESMT.
4
T
DETENTION POND
1 (14)
CENTRAL AMENITY COURTYARD
3
A 2.04 1
MAIN BUILDING FFE = 5314.59'
'
(8)
(2)
PROPERTY LINE
2
EXISTING MULTI-USE PATH
(14)
1'
(12)
53 09
2
RAIN GARDEN
11 '
SHARED PRIVATE ACCESS53 WALK
PROPOSED LIME GROVE
DN
53 1
1
2
(1)
(1)
H.C. VAN
H.C.
H.C.
(1) EVCL
(1) EVR (1) EVSE
(13 C)
(2) WALL MOUNTED EVSE CHARGERS
(1) EVSE
(3) EVR
(3) EVC
(9)
(3) EVC
(3) EVC
'
5310
1 A 1.02
(2) EVR (2) EVR
(1) EVR (1) EVR
(2) EVC (2) EVC
(3) EVC (3) EVC
(2) EVC (2) EVC
(1) EVCL (1) EVCL
(1) EVCL (1) EVCL
(2) EVCL (2) EVCL
(23)
WALL MOUNTED DUAL EVSE CHARGER
(2)
(3) EVC (3) EVC
(3) EVCL (3) EVCL
(1) EVCL (1) EVCL
8'
530
(3) EVCL (2) EVCL
A 2.03
RAIN GARDEN
TRASH ROOM FFE = 5311.09'
ELEC. ROOM FFE = 5314.59'
RAIN GARDEN
85 12
2 20 120
4 80 519
6
30
3
18
9
48
135
585
BUILDING 2 LEVEL 1 LEVEL 2 LEVEL 3 LEVEL 4
BUILDING 3 LEVEL 1 LEVEL 2 LEVEL 3 LEVEL 4
ARCHITECTURAL SITE PLAN
PROPOSED FIRE ACCESS LANE
224,374 SF
*LINCOLN HALL BASEMENT TO BE BACK-FILLED TO ADDRESS FLOOD PLAIN REGULATIONS
REQUIRED
PROVIDED
RESIDENTIAL: (2) / UNIT @ 135 UNITS
= 270 SPOTS
290
OFFICE: (1) / 1,500 SF @ 1400 SF (4 MINIMUM)
= 4 SPOTS
4
TOTAL:
274 SPOTS
294 SPOTS
SHORT-TERM - 25%
= 68.5 SPOTS
84
LONG-TERM - 75% ELEVATED SPOTS (25% MAX)
= 205.5 SPOTS = 51 SPOTS (MAX)
210 50
= 14 SPOTS
16
EXISTING 17' ACCESS ESMT.
PROVIDED
CITY COMPLIANT STANDARD TYPICAL ADA
49 36 33 3
COMPACT
13
NOT CITY COMPLIANT TANDEM
29 29
TOTAL
78*
TYPE OF STALL
% OF TOTAL PARKING
REQUIRED
PROVIDED
EVSE: EVR: EVC: EVCL:
5% 15% 40% 40%
4 12 31 31
4 12 31 31
PER CITY OF BOULDER ELECTRICAL CODE SECTION 10-6-4 (a) & (b) REQUIREMENTS & COBECC SECTION 405.11, TABLE C405.11, THIS PROJECT PROVIDES THE FOLLOWING EV READY, CAPABLE, AND EVSE INSTALLED PARKING FOR 78 PARKING SPACES: REFER TO ELECTRICAL DRAWINGS FOR LOCATIONS AND SPECS - ELECTRIC VEHICLE SUPPLY EQUIPMENT (EVSE) AN ELECTRIC VEHICLE CHARGING SYSTEM OR DEVICE THAT IS USED TO PROVIDE ELECTRICITY TO A PLUG-IN ELECTRIC OR HYBRID ELECTRIC VEHICLE. - ELECTRIC VEHICLE READY SPACE (EVR) A DESIGNATED VEHICLE PARKING SPACE THAT HAS THE ELECTRIC PANEL CAPACITY, RACEWAY WIRING, RECEPTACLE, AND CIRCUIT OVERPROTECTION DEVICE INSTALLED TO SUPPORT FUTURE IMPLEMENTATION OF EV CHARGING. - ELECTRIC VEHICLE CAPABLE SPACE (EVC) A DESIGNATED VEHICLE PARKING SPACE THAT HAS THE ELECTRIC PANEL CAPACITY AND CONDUIT AND/OR RACEWAY INSTALLED TO SUPPORT FUTURE IMPLEMENTATION OF EV CHARGING. - ELECTRIC VEHICLE CAPABLE LIGHT SPACE (EVCL) A DESIGNATED VEHICLE PARKING SPACE THAT HAS CONDUIT AND/OR RACEWAY INSTALLED TO SUPPORT FUTURE IMPLEMENTATION OF ELECTRIC VEHICLE CHARGING INSTALLATION AND HAS SUFFICIENT PHYSICAL SPACE ADJACENT TO THE EXISTING ELECTRICAL EQUIPMENT FOR FUTURE ELECTRIC UPGRADES.
78
'
RAIN GARDEN
EXISTING CONTOURS
'
PROPERTY LINE
53
07
07
53
09
53 08 '
53 10 '
5,676 SF 5,676 SF 5,431 SF 1,284 SF 18,067 SF
TOTAL GROSS FLOOR AREA
BUILDING FOORPRINT
EASEMENT
"
PROPOSED VACATION OF PUBLIC RIGHT-OF-WAY.
37,899 SF 54,899 SF 54,736 SF 49,364 SF 196,899 SF
SITE LEGEND
-0
PROPOSED 23.4' ACCESS / UTILITY ESMT.
3,699 SF 3,315 SF 7,013 SF
MAIN BUILDING FFE = 5314.59'
EXISTING 25' SANITARY SEWER ESMT.
53
543 SF 543 SF
MECH. ROOM FFE = 5314.59'
PARKING ENTRY
' 25
'
11
53
1,108 SF 744 SF 1,852 SF
BIKE PARKING
TOTAL:
R
MARINE ST.
(E) ARAPAHOE HOUSE LEVEL 1 LEVEL 2
(E) LINCOLN HALL L-1 LINCOLN HALL L-2 LINCOLN HALL
PROPERTY LINE
PROPERTY LINE
3/64" = 1'-0"
17 2
ELECTRICAL VEHICLE REQUIREMENTS
5309.30'
TRASH STAGING
1
95 20
*13.3% OF TOTAL BEDS
BIKE WORK BIKE ENTRY
5312'
PROPERTY LINE PROPOSED PUBLIC ACCESS ESMT.
(20)
A 2.03
(3) EVCL (3) EVCL
T
DOG RUN
19 4
VEHICLE PARKING SUMMARY
EXISTING 14' PEDESTRIAN ESMT.
6.25%
5311'
(2) EVR
(2)
(1) EVSE (1) EVSE (1) EVCL
(1) EVC (1) EVCL (1) EVC (1) EVCL
TURN AROUND
(1)
6.25%
RAIN GARDEN
RAIN GARDEN
(10)
T
10 72 16 80 20 25
TYPE OF SPACE
COVERED PARKING FFE = 5311.09'
PROPOSED STORMWATER ESMT.
5 18 4 20 4 5
GROSS FLOOR AREA
(E) CHESTNUT HOUSE LEVEL 1
ELECTRIC OUTLET SUITABLE SPOTS (3' X 10') - 5%
(2)
PROPOSED EMERGENCY AND MAINTENANCE ACCESS ESMT.
8 10 18
BUILDING & LEVEL
BIKE PARKING CALCULATIONS
MAIN BUILDING FFE = 5314.59'
EXISTING RETAINING WALL
4 2 6
A 2.05
LINCOLN HALL FFE = 5315.58'
A 2.05
BUILDING 3 5BR/5BA TOWNHOUSE 6BR/6BA TOWNHOUSE OVERALL SITE UNIT & BED TOTALS
5309'
TOWNHOUSE BUILDING (BUILDING 3) NEW (3) STORY STUDENT HOUSING TOWNHOUSES
RAIN GARDEN
1/2" / 12"
PROPOSED STORMWATER ESMT.
RAIN GARDEN
1'
531
RY
MAIN BUILDING (BUILDING 2) NEW (4) STORY STUDENT HOUSING BUILDING
0"
UN BO RK ND
DA
UN
MA
BO
(8)
RAIN GARDEN
(14)
'25
R
DA
10 53
RK
-1
TO RH A 2.01
1
LOW POINT = 5308.65
53
PROPOSED LANDMARK BOUNDARY
53 11 '
MA
ENCE A 2.01
DETENTION POND
CHESTNUT FFE = 5315.59'
PROPOSED STORMWATER ESMT.
RAIN GARDEN
ND
LAR F
25' SO RELOCATED CHESTNUT HOUSE
RAIN GARDEN
LA
RELOCATED ARAPAHOE HOUSE
TOWNHOUSE BLDG.
BUILDING 2 2BR/2BA FLAT 4BR/2BA FLAT 4BR/3BA FLAT 4BR/4BA FLAT 5BR/3BA FLAT 5BR/4BA TOWNHOUSE 5BR/4BA FLAT 5BR/5BA TOWNHOUSE 5BR/5BA FLAT 6BR/5BA TOWNHOUSE D.O. 2BR/1BA FLAT D.O. 4BR/2BA FLAT
BED COUNT
GROSS FLOOR AREA
PROPOSED STORMWATER ESMT. 2
1 A 2.02
MAIN BLDG. LOW POINT = 5306.50
'
6 30
5
A 2.02
'
SITE ELEMENT, RE: LANDSCAPE & CIVIL
5307'
WATER-QUALITY / DETENTION EXISTING DITCH
BUILDING ENTRANCES SITE ENTRANCES BIKE RACK
RETAINED CHAMPION TREES
EXISTING MULTI-USE PATH
0
16'
32'
64'
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
SITE PLAN
A 1.00
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
EASEMENT AND SETBACK LEGEND PROPERTY LINE SETBACKS
24' - 10" FROM PROPERTY LINE
NEW CROSSWALK & PUSH BUTTON, RE: CIVIL PROPOSED ROW ENCROACHMENT
ARAPAHOE AVE.
BUILDING FOORPRINT
29' - 1 1/2" FROM PROPERTY LINE
SIDE
5' - 0" TBACK SE D R A Y
EXISTING BUS STOP & RELOCATED SHELTER
39' - 0 1/2" FROM PROPERTY LINE
1' - 8 1/2" FRONT YARD SETBACK
PROPERTY LINE
RY
RAIN GARDEN
DA
RK
BO
UN
MA
RAIN GARDEN
TOWNHOUSE BUILDING (BUILDING 3) NEW (3) STORY STUDENT HOUSING TOWNHOUSES
LINCOLN HALL (BUILDING 1) EXISTING (2) STORY HISTORIC SCHOOL HOUSE TO BE RENOVATED
T
PROPERTY LINE
EXISTING MULTI-USE PATH
RAIN GARDEN
CENTRAL AMENITY COURTYARD
DID NOT BRING IN: -TREES -IRRIGATION VALVES
RAIN GARDEN
RAIN GARDEN
PRIVATE ACCESS WALK
DETENTION POND
-1
TO RH
MAIN BUILDING (BUILDING #2) NEW (4) STORY STUDENT HOUSING BUILDING
LA
RY
ND
DA
UN
MA
RK
BO
RAIN GARDEN
RAIN GARDEN
DETENTION POND
ND
ENCE
LAR F
25' SO RELOCATED CHESTNUT HOUSE
RAIN GARDEN
LA
RELOCATED ARAPAHOE HOUSE
PROPOSED LANDMARK BOUNDARY
EXISTING DITCH
PARKING
1
SETBACK PLAN 3/64" = 1'-0"
10' - 0" REAR YARD SETBACK
MARINE ST.
BIKE ENTRY
61' - 11" FROM PROPERTY LINE
RAIN GARDEN
T
PARKING ENTRY
RAIN GARDEN
14' - 3" FROM PROPERTY LINE
PROPERTY LINE
T
PROPERTY LINE
PROPERTY LINE
PROPOSED FIRE ACCESS LANE
19' - 6" SIDE YARD SETBACK
EXISTING MULTI-USE PATH PROPOSED VACATION OF PUBLIC RIGHT-OF-WAY.
RAIN GARDEN
0
16'
32'
64'
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
SETBACK PLAN
A 1.01
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
6' - 0"
1' - 0" CLR.
BIKE PARKING CALCULATIONS
6' - 0"
3' - 4"
6' - 0"
5' - 0" CLR.
9 U-RACKS = (18) BIKE PARKING SPOTS)
PROVIDED
RESIDENTIAL: (2) / UNIT @ 135 UNITS
= 270 SPOTS
290
OFFICE: (1) / 1,500 SF @ 1400 SF (4 MINIMUM)
= 4 SPOTS
4
TOTAL:
274 SPOTS
294 SPOTS
SHORT-TERM - 25%
= 68.5 SPOTS
84
LONG-TERM - 75% ELEVATED SPOTS (25% MAX)
= 205.5 SPOTS = 51 SPOTS (MAX)
210 50
= 14 SPOTS
16
6' - 0"
LONG-TERM BIKE PARKING SUMMARY
TYP.
5' - 0" CLR.
3' - 6"
6' - 6"
REQUIRED
ELECTRIC OUTLET SUITABLE SPOTS (3' X 10') - 5%
1' - 0" CLR.
5' - 0" CLR.
9 U-RACKS = (18) BIKE PARKING SPOTS)
(18)
BIKE PARKING
*FROM THE CALCULATIONS ABOVE THE REQUIRED NUMBER OF LONG-TERM BIKE PARKING SPOTS ARE 205.5 SPOTS. PROPOSED LONG-TERM BIKE PARKING SUMMARY:
22 U-RACKS = (44) BIKE PARKING SPOTS (18)
25 DERO-DECKER BIKE RACKS: TWO TIERED SYSTEM W/ SPRING ASSISTED LIFT (50 ROLL-IN BIKE PARKING SPOTS) (50 ELEVATED BIKE PARKING SPOTS)
(22)
(22)
STD. U-RACK BICYCLE SPOTS
94
DERO-DECKER TWO TIERED SYSTEM 50 ROLL-IN SPOTS 50 ELEVATED SPOTS
100
3'X10' ELECTRIC BICYCLE SPOTS
16
TOTAL LONG-TERM BICYCLE SPOTS
210
8 U-RACKS = (16) 3'X10' ELECTRIC BIKE PARKING SPOTS. ALL SPOTS TO INCLUDE AN ELECTRICAL OUTLET SUITABLE FOR CHARGING ELECTRIC BIKES, MOUNTED @ +/- 44" A.F.F. (+/-5314.75' USGS, ~2" ABOVE F.P.E. OF 5314.57')
71' - 2 1/2"
(50 ROLL-IN) (50 ELEVATED)
(16 LARGE - EV SPACES)
3' - 0"
10' - 0"
TO GRIP & OPERABLE PARTS
5' - 0" CLR.
DERO DECKER BIKE RACK - PRODUCT INFORMATION 6' - 0"
5311.09' 11" CLR.
11" CLR.
7 U-RACKS = (14) BIKE PARKING SPOTS
1' - 0" CLR.
BIKE WORK
MAIN BUILDING - BFE 5312' - 6 7/8"
PARKING 96' - 6"
2
EV-CHARGING ELEVATION DIAGRAM
1
1/2" = 1'-0"
01-GROUND LEVEL FLOOR PLAN - ENLARGED BIKE PARKING PLAN 3/16" = 1'-0"
SCALE: 1/2" = 1'-0" 0'
1'
2'
4'
8'
SCALE: 3/16" = 1'-0" 0'
2'
6'
12'
21'-4"
PARKING ENTRY
BIKE ENTRY
2' - 0"
MAIN BUILDING - FPE 5314' 6 7/8"
1' - 6"
4' - 0" MAX.
1" MIN. ABOVE F.P.E.
EV CHARGER, MAKE AND MODEL TBD
10' - 0"
TYP.
3' - 6"
3' - 0"
6' - 0" TYP.
(14)
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
ENLARGED PARKING PLANS & INFORMATION
A 1.02
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
BUILDING AREA LEGEND RESIDENTIAL UNITS 3 A 3.01
4 A 3.00
A 2.00
A 2.00
2
1
2 A 3.01
A 2.00
A 2.05
3
2
1 A 3.01
COMMON AREA BACK OF HOUSE BUILDING ENTRANCES
RELOCATED ARAPAHOE HOUSE RETAINED CHAMPION TREES
PROPERTY LINE
FFE = 5315.59'
UNIT & BED COUNTS - LEVEL 1
ARAPAHOE OPERATIONS 1,108 SF
UNIT TYPE B.O.H. /WATER-ENTRY (8) 48 SF FITNESS 2,988 SF
(14)
DW
DW
6BR/6BA TOWNHOUSE 634 SF
BUILDING 2 LEVEL 1 LEVEL 1
DW
TOWNHOUSE FFE = 5313.59' 4
3 A 3.00
ELEV. 123 SF
PACKAGE 240 SF ANNEX 1,527 SF
2BR/1BA FLAT 621 SF
ELEV. 123 SF
2 A 3.00
(14)
1
2
(12)
DW
CENTRAL AMENITY COURTYARD
3
A 2.04
2
TOWNHOUSE UNIT, TRASH ENCLOSURE
OFFICE & SUPPORT 1,400 SF D.O. 4BR/2BA DW FLAT 1,006 SF
D.O. 4BR/2BA DW FLAT 1,006 SF
D.O. 4BR/2BA DW FLAT 1,006 SF
8 8 8
4BR/4BA FLAT 5BR/4BA TOWNHOUSE 5BR/4BA FLAT 5BR/5BA TOWNHOUSE 6BR/5BA TOWNHOUSE D.O. 4BR/2BA FLAT
1 5
4 25
4 4
20 20
2
12
5
20
21 21
101 101
6
30
3
18
9 9 34
48 48 157
MAIN BUILDING FFE = 5314.59'
OVERALL SITE UNIT & BED TOTALS
5BR/5BA TOWNHOUSE 960 SF
STAIR 200 SF
5309.30'
D.O. 4BR/2BA DW FLAT 1,006 SF
5BR/5BA TOWNHOUSE 6BR/6BA TOWNHOUSE
DW
DW
(2) D.O. 4BR/2BA DW FLAT 1,006 SF
5BR/4BA TOWNHOUSE 989 SF DW
4BR/4BA FLAT 1,390 SF
1
5BR/4BA FLAT 1,500 SF
4 4 4
LEVEL 1
MAIL 200 SF
(14)
LEVEL 1
LEVEL 1
1 A 2.05
W/D (8)
LEVEL 1
BUILDING 3 LEVEL 1
2BR/1BA FLAT 621 SF
DW
MAIN BUILDING FFE = 5314.59'
LEVEL 1 LEVEL 1
2BR/1BA FLAT
LEVEL 1
DW
VESTIBULE 110 SF
T
6BR/6BA TOWNHOUSE 635 SF
2BR/1BA FLAT 709 SF
DW
3 A 3.00
A 2.05
LOBBY 1,047 SF LINCOLN HALL FFE = 5315.58'
STAIR 213 SF
LOBBY & COMMONS 929 SF
3
5BR/5BA TOWNHOUSE 627 SF
DW
(6)
DW
2BR/1BA FLAT 702 SF
5BR/5BA TOWNHOUSE 627 SF DW
A 2.05
5BR/5BA TOWNHOUSE 635 SF
DW
B.O.H. /WATER-ENTRY 100 SF
SPA 741 SF
2 A 3.00
A 2.01
DW
6BR/6BA TOWNHOUSE 627 SF
ANNEX 1,890 SF
FFE = 5315.59'
A 2.01
DW
5BR/5BA TOWNHOUSE 628 SF
BED COUNT
PROPERTY LINE
CHESTNUT OPERATIONS 543 SF
5BR/5BA TOWNHOUSE 628 SF
DW
RELOCATED CHESTNUT HOUSE
5BR/5BA TOWNHOUSE 635 SF
(E) LINCOLN HALL L-1 LINCOLN HALL L-1 LINCOLN HALL
UNIT COUNT
1
A 2.03
2
A 2.03
(2) DW
W/D
(1)
(1)
(13 C)
H.C. VAN
H.C.
H.C.
5BR/4BA FLAT 1,500 SF
COVERED PARKING 28,490 SF
COVERED PARKING FFE = 5311.09'
5BR/5BA TOWNHOUSE 951 SF DW
1 A 1.02
(9)
TURN AROUND
W/D
(1)
5BR/5BA TOWNHOUSE 951 SF DW
5BR/4BA FLAT 1,500 SF
6.25%
(10)
DW
(2)
W/D
DOG RUN
STAIR 172 SF
B.O.H. / TRASH 1,136 SF
DW
BIKE ENTRY
B.O.H. /ELECTRICAL 803 SF
BIKE WORK
ELEC. ROOM FFE = 5314.59'
PARKING ENTRY
DW
T
(20)
B.O.H. 5BR/4BA /MECHANICAL TOWNHOUSE 654 SF 835 SF MAIN BUILDING FFE = 5314.59'
TRASH STAGING
6BR/5BA TOWNHOUSE 1,163 SF
6BR/5BA TOWNHOUSE 1,163 SF
BALCONY
5BR/4BA TOWNHOUSE 848 SF
BALCONY
PROPERTY LINE
5309.30'
5BR/4BA TOWNHOUSE 848 SF
5BR/5BA TOWNHOUSE 968 SF
BALCONY
PROPERTY LINE
3 A 3.01
1
1 A 3.00
DW DW
5BR/4BA FLAT 1,500 SF
5BR/4BA TOWNHOUSE 944 SF
DW
PROPERTY LINE
STORAGE/ SHOP 551 SF
DW
1 A 3.00
DW
DW
T
6.25%
(23)
(2)
1
2
A 2.02
A 2.02
EXISTING MULTI-USE PATH
1 A 3.01 4 A 3.00
01-GROUND LEVEL FLOOR PLAN - OVERALL 1" = 20'-0"
0'
10'
20'
40'
80'
2 A 3.01
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
LEVEL 1 PLAN
A 1.11
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
BUILDING AREA LEGEND RESIDENTIAL UNITS
3 A 3.01
A 2.00
A 2.00
2
1
4 A 3.00
RELOCATED ARAPAHOE HOUSE
A 2.00
A 2.05
3
2
2 A 3.01
COMMON AREA BACK OF HOUSE
1 A 3.01
BUILDING ENTRANCES
PROPERTY LINE
RETAINED CHAMPION TREES
ARAPAHOE OPERATIONS 744 SF
UNIT & BED COUNTS - LEVEL 2 LEVEL
DW
ROOF BELOW
RELOCATED CHESTNUT HOUSE
5BR/5BA TOWNHOUSE 635 SF
DW
5BR/3BA FLAT 1,557 SF
5BR/5BA TOWNHOUSE 628 SF
5BR/5BA TOWNHOUSE 628 SF
6BR/6BA TOWNHOUSE 627 SF
5BR/4BA FLAT 1,628 SF 4 ROOF BELOW
W/D A 2.05
5BR/4BA FLAT 1,591 SF
5BR/4BA FLAT 1,571 SF
3
5BR/5BA TOWNHOUSE 635 SF
5BR/5BA TOWNHOUSE 627 SF
5BR/5BA TOWNHOUSE 627 SF
6BR/6BA TOWNHOUSE 635 SF
A 2.05
2 A 3.00
DW
5BR/4BA FLAT 1,500 SF
DW
W/D 2 A 3.00
(E) LINCOLN HALL L-2 LINCOLN HALL L-2 LINCOLN HALL
6BR/6BA TOWNHOUSE 634 SF
DW
ROOF BELOW
DW
4BR/2BA FLAT 1,199 SF
3
A 2.04
4BR/3BA FLAT 1,258 SF
1
5BR/4BA FLAT 1,500 SF
2
PLANTERS, RE: LANDSCAPE
PLANTERS, RE: LANDSCAPE
ROOF
ROOF PLANTERS, RE: LANDSCAPE
DW
DECK
5BR/5BA FLAT 1,620 SF
DECK
5BR/5BA FLAT 1,620 SF
DECK
5BR/5BA FLAT 1,620 SF
DW
DW
123 123 133
D.O. 4BR/2BA DW FLAT 1,006 SF
5BR/5BA FLAT 1,620 SF
D.O. 4BR/2BA DW FLAT 1,006 SF
4BR/4BA FLAT 1,424 SF
1
A 2.03
2
A 2.03
B.O.H. 98 SF
DW
DW
5BR/4BA FLAT 1,500 SF
27 27 29
5BR/5BA TOWNHOUSE 951 SF
W/D
DECK
DW
B.O.H. 94 SF
4BR/4BA FLAT W/D1,396 SF
DECK
DW
DECK
5BR/4BA FLAT 1,500 SF
W/D
5BR/5BA TOWNHOUSE 948 SF
STAIR 200 SF
ROOF
W/D
2 8 4 12 10 30 45 12
PROPERTY LINE
2
5BR/4BA TOWNHOUSE 968 SF
DW
A 2.01
1
1 2 1 3 2 6 9 3
A 2.05
W/D A 2.01
2BR/2BA FLAT 4BR/2BA FLAT 4BR/3BA FLAT 4BR/4BA FLAT 5BR/3BA FLAT 5BR/4BA FLAT 5BR/5BA FLAT D.O. 4BR/2BA FLAT
1
5BR/3BA FLAT 1,500 SF
W/D
10 10 10
DW
ELEV. 123 SF
CORR. 153 SF
24' - 0"
DW
ELEV. 123 SF
2 2 2
OVERALL SITE UNIT & BED TOTALS 3 A 3.00
BED COUNT
5BR/4BA FLAT
LEVEL 2
STAIR 213 SF 3 A 3.00
BUILDING 2 LEVEL 2 LEVEL 2 LEVEL 2 LEVEL 2 LEVEL 2 LEVEL 2 LEVEL 2 LEVEL 2
UNIT COUNT
UNIT TYPE
DW
DW
DW
DW
DW
5BR/5BA TOWNHOUSE 951 SF
DW
DW
5BR/5BA FLAT 1,576 SF
5BR/5BA FLAT 1,576 SF
W/D
5BR/5BA FLAT 1,576 SF
W/D
5BR/5BA FLAT 1,576 SF
W/D
D.O. 4BR/2BA FLAT 1,006 SF
W/D
5BR/5BA FLAT 1,576 SF
W/D
W/D
4BR/4BA FLAT 1,345 SF
DW
DECK
DW
1 A 3.00
DECK
DECK
DECK
ROOF
5BR/4BA TOWNHOUSE 880 SF
1 A 3.00
ROOF W/D
DN
TRASH 108 SF
DW
5BR/4BA TOWNHOUSE 983 SF
2BR/2BA FLAT 818 SF W/D
4BR/2BA FLAT 1,221 SF
6BR/5BA TOWNHOUSE 983 SF
6BR/5BA TOWNHOUSE 984 SF
5BR/4BA TOWNHOUSE 983 SF
5BR/4BA TOWNHOUSE 981 SF
5BR/5BA TOWNHOUSE 1,118 SF
DW
PLANTERS, RE: LANDSCAPE
PROPERTY LINE
PROPERTY LINE
1
2
A 2.02
A 2.02
3 A 3.01
1
DECK
ROOF
PLANTERS, RE: LANDSCAPE
5BR/4BA FLAT 1,500 SF
PROPERTY LINE
DECK
02-SECOND LEVEL FLOOR PLAN - OVERALL
1 A 3.01 4 A 3.00
2 A 3.01
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
1" = 20'-0"
0'
10'
20'
40'
80'
LEVEL 2 PLAN
A 1.12
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
BUILDING AREA LEGEND RESIDENTIAL UNITS
3 A 3.01
A 2.00
A 2.00
A 2.00
A 2.05
COMMON AREA
2
1
3
2
BACK OF HOUSE
4 A 3.00
RELOCATED ARAPAHOE HOUSE
2 A 3.01
1 A 3.01
BUILDING ENTRANCES
PROPERTY LINE
RETAINED CHAMPION TREES
UNIT & BED COUNTS - LEVEL 3 LEVEL
UNIT COUNT
UNIT TYPE
BED COUNT
DW
RELOCATED CHESTNUT HOUSE
5BR/5BA TOWNHOUSE 600 SF
DW
4BR/3BA FLAT 1,424 SF
5BR/3BA FLAT 1,557 SF
5BR/5BA TOWNHOUSE 593 SF
5BR/5BA TOWNHOUSE 593 SF
6BR/6BA TOWNHOUSE 627 SF
6BR/6BA TOWNHOUSE 634 SF
4
W/D W/D POOL EQUIPMENT ROOM 199 SF
5BR/4BA FLAT 1,500 SF
2 A 3.00
A 2.05
STAIR 213 SF
DW
3 A 3.00
5BR/5BA TOWNHOUSE 600 SF
3
5BR/5BA TOWNHOUSE 593 SF
LEVEL 3 2 A 3.00
LEVEL 3
2 8 2 8 2 5 4 1
4 32 8 32 10 25 20 2
6
24
38 38 38
157 157 157
1
ELEV. 123 SF
A 2.05 DW
DW
6BR/6BA TOWNHOUSE 599 SF
2BR/2BA FLAT 4BR/2BA FLAT 4BR/3BA FLAT 4BR/4BA FLAT 5BR/3BA FLAT 5BR/4BA FLAT 5BR/5BA FLAT D.O. 2BR/1BA FLAT D.O. 4BR/2BA FLAT
OVERALL SITE UNIT & BED TOTALS
3 A 3.00 ELEV. 123 SF
5BR/5BA TOWNHOUSE 593 SF
A 2.05
BUILDING 2 LEVEL 3 LEVEL 3 LEVEL 3 LEVEL 3 LEVEL 3 LEVEL 3 LEVEL 3 LEVEL 3
2BR/2BA FLAT 970 SF
DW
W/D 1 5BR/4BA FLAT 1,500 SF 2
3
A 2.04
4BR/3BA FLAT 1,254 SF
1
DW
A 2.01
2
4BR/2BA FLAT 1,199 SF DW
A 2.01
W/D
DW
D.O. 4BR/2BA FLAT 1,006 SF
PROPERTY LINE
5BR/3BA FLAT 1,500 SF
ROOF BELOW
STAIR 200 SF
ROOF BELOW
1
A 2.03
2
A 2.03
ROOF BELOW DW
5BR/5BA FLAT 1,620 SF
5BR/5BA FLAT 1,620 SF
DW
DW
5BR/5BA FLAT 1,620 SF
W/D 4BR/4BA FLAT 1,424 SF
DW
5BR/4BA FLAT 1,500 SF
B.O.H. 98 SF
DW
B.O.H. 94 SF
5BR/5BA FLAT 1,620 SF
DW
W/D
4BR/4BA FLAT 1,396 SF W/D
D.O. 4BR/2BA DW FLAT 1,006 SF
DW
W/D
D.O. 4BR/2BA DW FLAT 1,006 SF
D.O. 4BR/2BA FLAT 1,006 SF DW
5BR/4BA FLAT 1,500 SF
DW
DW
DW
DW
D.O. 4BR/2BA FLAT 1,006 SF
DW
DW
DW
4BR/4BA FLAT 1,345 SF
4BR/4BA FLAT 1,345 SF
BALCONY
DW
DW
DW
4BR/2BA FLAT 1,221 SF
4BR/2BA FLAT 1,155 SF
4BR/2BA FLAT 1,283 SF
ROOF BELOW
DW
STAIR 172 SF
4BR/2BA FLAT 1,155 SF
4BR/2BA FLAT 1,153 SF
DW
DW
2BR/2BA FLAT 818 SF W/D
4BR/2BA FLAT 1,155 SF
4BR/2BA FLAT 1,153 SF
DW
TRASH 108 SF
1 A 3.00
DW
PROPERTY LINE
ROOF BELOW
ROOF BELOW W/D
D.O. 2BR/1BA FLAT 690 SF DW
5BR/4BA FLAT 1,500 SF
4BR/4BA FLAT 1,345 SF
BALCONY
BALCONY
DW
1 A 3.00
W/D
4BR/4BA FLAT 1,345 SF
W/D
W/D
W/D
W/D
4BR/4BA FLAT 1,345 SF
D.O. 4BR/2BA FLAT 1,006 SF DW
W/D
DW
4BR/4BA FLAT 1,345 SF
BALCONY BALCONY
BALCONY
PROPERTY LINE
PROPERTY LINE
1
2
A 2.02
A 2.02
3 A 3.01
1
03-THIRD LEVEL FLOOR PLAN - OVERALL
1 A 3.01 4 A 3.00
2 A 3.01
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
1" = 20'-0"
0'
10'
20'
40'
80'
LEVEL 3 PLAN
A 1.13
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
BUILDING AREA LEGEND RESIDENTIAL UNITS
3 A 3.01
A 2.00
A 2.00
A 2.00
A 2.05
COMMON AREA
2
1
3
2
BACK OF HOUSE
4 A 3.00
2 A 3.01
1 A 3.01
BUILDING ENTRANCES
PROPERTY LINE
RETAINED CHAMPION TREES
UNIT & BED COUNTS - LEVEL 4 ROOF DECK
LEVEL
ROOF DECK
UP
ROOF DECK
PROPOSED TRELLIS OVERHEAD
HOT TUB 170 SF
POOL 490 SF
6BR/6BA TOWNHOUSE 424 SF
A 2.05
3
LEVEL 4 2 A 3.00
ROOF DECK
DW
DW
A 2.05
2BR/2BA FLAT 4BR/2BA FLAT 4BR/3BA FLAT 4BR/4BA FLAT 5BR/4BA FLAT 5BR/5BA FLAT D.O. 2BR/1BA FLAT D.O. 4BR/2BA FLAT
LEVEL 4 OVERALL SITE UNIT & BED TOTALS
BED COUNT
2 8 1 8 4 4 1
4 32 4 32 20 20 2
6
24
34 34 34
138 138 138
STAIR 213 SF
UP
(6) 7" RISERS +42"
4
6BR/6BA TOWNHOUSE 432 SF
UP
2 A 3.00
6BR/6BA TOWNHOUSE 427 SF
BUILDING 2 LEVEL 4 LEVEL 4 LEVEL 4 LEVEL 4 LEVEL 4 LEVEL 4 LEVEL 4
UNIT COUNT
UNIT TYPE
UP
3 A 3.00
3 A 3.00
1
ELEV. 123 SF
A 2.05
TROPHY ROOM 962 SF
2BR/2BA FLAT 970 SF
DW
A 2.01
2
DW
1
5BR/4BA FLAT 1,484 SF
3
A 2.04
4BR/2BA FLAT 1,199 SF
4BR/3BA FLAT 1,254 SF
1
DW
A 2.01
2
W/D
DW
D.O. 4BR/2BA FLAT 1,006 SF
PROPERTY LINE
DW
ELEV. 123 SF
STAIR 200 SF
DW
5BR/5BA FLAT 1,620 SF
5BR/5BA FLAT 1,620 SF
DW
4BR/4BA FLAT W/D 1,396 SF
5BR/5BA FLAT 1,620 SF
DW
5BR/5BA FLAT 1,620 SF
D.O. 4BR/2BA FLAT 1,006 SF
W/D 4BR/4BA FLAT 1,424 SF B.O.H. 98 SF
DW DW
DW
DW
DW
DW
D.O. 4BR/2BA FLAT 1,006 SF
DW
DW
4BR/4BA FLAT 1,345 SF
4BR/4BA FLAT 1,345 SF
W/D
4BR/4BA FLAT 1,345 SF
W/D
4BR/4BA FLAT 1,345 SF
W/D
D.O. 4BR/2BA FLAT 1,006 SF
W/D
4BR/4BA FLAT 1,345 SF
W/D
4BR/4BA FLAT 1,345 SF
W/D
A 2.03
DW
5BR/4BA FLAT 1,484 SF
2
DW
B.O.H. 94 SF
DW
W/D
D.O. 4BR/2BA DW FLAT 1,006 SF
DW
W/D
D.O. 4BR/2BA DW FLAT 1,006 SF
A 2.03
DW
5BR/4BA FLAT 1,484 SF
1
DW
BALCONY
4BR/2BA FLAT 1,155 SF
4BR/2BA FLAT 1,155 SF
4BR/2BA FLAT 1,153 SF
DW
DW
4BR/2BA FLAT 1,153 SF
4BR/2BA FLAT 1,155 SF
4BR/2BA FLAT 1,283 SF
DW
DW
DW
DW
4BR/2BA FLAT 1,221 SF DW
STAIR 172 SF
TRASH 108 SF
1 A 3.00
DW
PROPERTY LINE
DW
W/D
2BR/2BA FLAT 801 W/DSF
BALCONY
BALCONY
DW
5BR/4BA FLAT 1,484 SF
1 A 3.00
D.O. 2BR/1BA FLAT 690 SF
BALCONY BALCONY
BALCONY
PROPERTY LINE
PROPERTY LINE
3 A 3.01
1
BALCONY
04-FOURTH LEVEL FLOOR PLAN - OVERALL
1
2
A 2.02
A 2.02
4 A 3.00
1 A 3.01 2 A 3.01
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
1" = 20'-0"
0'
10'
20'
40'
80'
LEVEL 4 PLAN
A 1.14
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
ROOF LEGEND
A 2.00
A 2.00
A 2.00
A 2.05
2
1
3
2
3 A 3.01
SLOPE ARROW, ARROW HEAD INDICATES DOWNWARD SLOPE SLOPED ROOFING
2 A 3.01
1 A 3.01
4 A 3.00
ROOF DECKS, BELOW
PROPERTY LINE SOLAR READY ZONE
21' - 2"
8" / 12"
MECHANICAL EQUIPMENT PADS, EXACT LOCATIONS & SIZES TBD
21' - 2"
8" / 12"
8" / 12"
8" / 12"
8" / 12"
8" / 12" 8" / 12"
8" / 12"
MECHANICAL EQUIPMENT SCREEN, EXACT LOCATIONS TBD
A 2.05
2" / 12" 2" / 12"
2" / 12"
2" / 12"
ROOF DECK BELOW
2" / 12"
2" / 12"
2" / 12" 2" / 12"
4 2" / 12"
A 2.05
2" / 12"
3
2 A 3.00
2 A 3.00
3 A 3.00
21' - 2"
3 A 3.00
1
ELEVATOR OVERRUN
WH 1
A 2.01
2
ECC-2
1
2" / 12"
A 2.01
2
PROPERTY LINE
2" / 12"
A 2.05
3
A 2.04 1
2" / 12"
1" / 12"
1" / 12"
2" / 12"
6" / 12"
ROOF HATCH
1
A 2.03
2
A 2.03
MECHANICAL EQUIPMENT SCREEN
PROPERTY LINE
6" / 12"
MECHANICAL EQUIPMENT PADS
1" / 12" 1" / 12"
PROPERTY LINE
PROPERTY LINE
1
2
A 2.02
A 2.02
3 A 3.01
1
05-ROOF PLAN
1" / 12"
2" / 12"
1" / 12"
4 A 3.00
1 A 3.01
2 A 3.01
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
1" = 20'-0"
0'
10'
20'
40'
80'
ROOF PLAN
A 1.15
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
13' - 7"
6' - 0"
6' - 0"
6' - 0"
STEP BACK (3')
STEP BACK (3')
STEP BACK (3')
STEP BACK (3')
FACADE 1 15' - 2"
FACADE 1 15' - 2"
FACADE 1 15' - 2"
FACADE 1 15' - 2"
FACADE 2 32' - 8 1/2"
FACADE 1 18' - 3"
FACADE 1 15' - 2"
FACADE 2 34' - 10"
FACADE LEGEND
STEP BACK (15 - '8") VERTICAL EXPRESSION
VERTICAL EXPRESSION
VERTICAL EXPRESSION
VERTICAL EXPRESSION
FACADE 1
FACADE 2
FACADE 3
107' - 5" TOWNHOUSES (BUILDING 3)
3
NORTH ELEVATION DIAGRAM - EAST
0
8'
16'
32'
2
3/32" = 1'-0"
CHAMPION SYCAMORE TREE BEYOND
NORTH ELEVATION DIAGRAM - WEST 3/32" = 1'-0"
CHAMPION SYCAMORE TREE
1 A 3.01
2 A 3.01
4 A 3.00
3 A 3.01
ELEVATOR OVERRUN MTL-01
WN-02 FC-02
FC-02
FC-01
FC-02
FC-01 GL-01
MP-02 CC-02
MTL-03
BR-02 WN-01 ROOF LINCOLN HALL 124' - 10 3/8"
L-2 LINCOLN HALL 113' - 10 3/8"
LEVEL 2 111' - 4"
L-1 LINCOLN HALL 100' - 11 7/8"
EXISTING MULTIUSE PATH
LEVEL 1 100' - 0" BR-01
BR-01
MP-02
107' - 5"
35' - 0 1/2"
82' - 0"
TOWNHOUSES (BUILDING 3)
54' - 5 1/2"
1 A 3.01
MP-02 MTL-02
98' - 7"
LINCOLN HALL
42' - 8 1/2"
MAIN BUILDING (BUILDING 2)
2 A 3.01
4 A 3.00
42' - 1"
BLDG. LOW POINT 5306' - 6"
ARAPAHOE HOUSE 3 A 3.01
NORTH SITE ELEVATION 1/16" = 1'-0"
8'
16'
32'
64'
2.00 - MATERIAL FINISH SCHEDULE - EXTERIOR MARK AL-01 AL-02 BR-01 BR-02 BR-03 CC-01 CC-02 FC-01 FC-02 FC-03 FC-04 GL-01 MP-01 MP-02 MTL-01 MTL-02 MTL-03 MTL-04 RM-01 RS-01 WN-01 WN-02
DESCRIPTION
FINISH
ALUMNIUM STOREFRONT ALUMINUM STOREFRONT BRICK BASE BRICK BRICK - ACCENT DETAILING EXPOSED CONCRETE CONCRETE CAP & SILL FIBER CEMENT - VERTICAL SIDING FIBER CEMENT PANEL FIBER CEMENT TRIM FIBER CEMENT TRIM GLASS PANEL RAILING METAL ROOF SCREEN PERFORATED METAL PANEL RAILING METAL PARAPET CAP POWDER COATED STEEL METAL WALL CAP METAL WALL CAP MEMBRANE ROOFING ASPHALT SHINGLE ROOFING EXTERIOR WINDOWS & DOORS EXTERIOR WINDOWS & DOORS
GRAY DARK GRAY DARK BROWN RED BLEND MATCH ADJACENT BRICK BOARDFORM TAN DARK GRAY LIGHT GRAY DARK GRAY GRAY CLEAR GRAY LIGHT GRAY DARK GRAY GRAY TAN GRAY LIGHT GRAY DARK GRAY LIGHT GRAY BLACK
ARAPAHOE HOUSE
MATERIAL PALETTE
BRICK | BR-02 RED BLEND
FIBER CEMENT SIDING | FC-02 PANEL - LIGHT GRAY
ACCENT MATERIALS
0'
PRIMARY MATERIALS
1
LEVEL 3 121' - 8"
BR-02
TOWNHOUSE - L-1 99' - 0" TOWNHOUSE - BLDG. LOW PT. 5308' - 7 3/4"
LEVEL 4 132' - 0"
MAX. BUILDING HEIGHT
TOWNHOUSE - L-2 109' - 6"
FC-01
ROOF LEVEL 142' - 4"
54' - 11"
TOWNHOUSE - L-3 120' - 0"
54' - 11"
TOWNHOUSE - L-4 130' - 6"
MAX. BUILDING HEIGHT
TOWNHOUSE - ROOF 141' - 0"
BUILDING 3 CHESTNUT HOUSE
BRICK ACCENT | BR-03 RED BLEND ACCENT PATTERN
LINCOLN HALL
ACCENT METAL | MTL-02 GRAY
BUILDING 2
BRICK BASE | BR-01 DARK BROWN
FIBER CEMENT SIDING | FC-01 VERTICAL - DARK GRAY
ACCENT CAP & SILL | CC-02 TAN
PERFORATED RAILING | MP-02 DARK GRAY
KEY PLAN
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
EXTERIOR NORTH ELEVATION
A 2.00
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
FACDE 1 46' - 9 1/2"
FACADE 2 24' - 11 1/2"
FACADE 1 48' - 1 1/2"
FACADE 2 23' - 10 1/2"
STEP BACK (36')
FACADE 1 48' - 1 1/2"
FACADE 2 23' - 10 1/2"
STEP BACK (36')
FACADE 1 48' - 1 1/2"
STEP BACK (36')
FACADE LEGEND
FACADE 1
FACADE 2
FACADE 3
MAIN ENTRY FACADE 3 23' - 7"
ENTRY FACADE 3 23' - 10 1/2"
ENTRY FACADE 3 23' - 10 1/2"
279' - 7 1/2" MAIN BUILDING (BUILDING 2)
2
0
WEST ELEVATION DIAGRAM
8'
16'
32'
3/32" = 1'-0"
CHAMPION SYCAMORE TREES BEYOND
2 A 3.00
3 A 3.00
1 A 3.00
GL-01
MP-01
CC-02
FC-03
ELEVATOR OVERRUN
BR-02 WN-01
FC-01
FC-01
WN-02
WN-02 MTL-03
BR-03
ROOF LEVEL 142' - 4"
BR-02
AL-01
BR-01
15' - 8 1/2"
MTL-02 47' - 11"
BR-02
ENTRY 23' - 10 1/2"
WN-01
AL-01 48' - 1 1/2"
23' - 10 1/2"
48' - 1 1/2"
23' - 10 1/2"
BR-03
48' - 1 1/2" BR-01
1/16" = 1'-0"
0'
8'
16'
32'
64'
2.00 - MATERIAL FINISH SCHEDULE - EXTERIOR MARK AL-01 AL-02 BR-01 BR-02 BR-03 CC-01 CC-02 FC-01 FC-02 FC-03 FC-04 GL-01 MP-01 MP-02 MTL-01 MTL-02 MTL-03 MTL-04 RM-01 RS-01 WN-01 WN-02
LEVEL 3 121' - 8" LEVEL 2 111' - 4"
LEVEL 1 100' - 0" PARKING 96' - 6" BLDG. LOW POINT 5306' - 6"
1 A 3.00
DESCRIPTION
FINISH
ALUMNIUM STOREFRONT ALUMINUM STOREFRONT BRICK BASE BRICK BRICK - ACCENT DETAILING EXPOSED CONCRETE CONCRETE CAP & SILL FIBER CEMENT - VERTICAL SIDING FIBER CEMENT PANEL FIBER CEMENT TRIM FIBER CEMENT TRIM GLASS PANEL RAILING METAL ROOF SCREEN PERFORATED METAL PANEL RAILING METAL PARAPET CAP POWDER COATED STEEL METAL WALL CAP METAL WALL CAP MEMBRANE ROOFING ASPHALT SHINGLE ROOFING EXTERIOR WINDOWS & DOORS EXTERIOR WINDOWS & DOORS
GRAY DARK GRAY DARK BROWN RED BLEND MATCH ADJACENT BRICK BOARDFORM TAN DARK GRAY LIGHT GRAY DARK GRAY GRAY CLEAR GRAY LIGHT GRAY DARK GRAY GRAY TAN GRAY LIGHT GRAY DARK GRAY LIGHT GRAY BLACK
ARAPAHOE HOUSE
MATERIAL PALETTE
BRICK | BR-02 RED BLEND
FIBER CEMENT SIDING | FC-02 PANEL - LIGHT GRAY
ACCENT MATERIALS
WEST SITE ELEVATION
MAIN BUILDING (BUILDING 2)
3 A 3.00
PRIMARY MATERIALS
1
2 A 3.00
LEVEL 4 132' - 0"
MAX. BUILDING HEIGHT
MARINE ST.
ARAPAHOE AVE.
54' - 11"
WN-01
BUILDING 3 CHESTNUT HOUSE
BRICK ACCENT | BR-03 RED BLEND ACCENT PATTERN
LINCOLN HALL
ACCENT METAL | MTL-02 GRAY
BUILDING 2
BRICK BASE | BR-01 DARK BROWN
FIBER CEMENT SIDING | FC-01 VERTICAL - DARK GRAY
ACCENT CAP & SILL | CC-02 TAN
PERFORATED RAILING | MP-02 DARK GRAY
KEY PLAN
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
EXTERIOR WEST ELEVATION
A 2.01
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
FACADE LEGEND
FACADE 1 FACADE 2 43' - 11 1/2"
FACADE 1 27' - 2 1/2"
FACADE 2 19' - 3"
55' - 4"
FACADE 1 27' - 2 1/2"
19' - 3"
FACADE 2 19' - 3"
FACADE 2 19' - 6 1/2"
23' - 0"
BALCONY STEP BACK (48')
FACADE 1 27' - 2 1/2"
FACADE 2 23' - 4 1/2"
BALCONY STEP BACK (48')
VERTICAL EXPRESSION
FACADE 2
0
SOUTH ELEVATION DIAGRAM
8'
16'
FACADE 3 31' - 0"
FACADE 3 22' - 7"
GARAGE
BIKE STORAGE
32'
3/32" = 1'-0"
3 A 3.01
4 A 3.00
2 A 3.01
1 A 3.01
CHAMPION SYCAMORE TREE BEYOND
MP-01
MP-01
WN-02
FC-03 WN-02
WN-02
BR-02
MTL-03
WN-01
BR-02 WN-01
34' - 11 1/2"
9' - 1 1/2"
MTL-02
46' - 6"
FC-01
30' - 8 1/2"
22' - 7"
19' - 9 1/2"
27' - 4 1/2"
4 A 3.00
2 A 3.01
LEVEL 3 121' - 8" LEVEL 2 111' - 4"
LEVEL 1 100' - 0" PARKING 96' - 6"
BR-01
MP-02
MAIN BUILDING (BUILDING 2)
LEVEL 4 132' - 0"
23' - 2"
MTL-02
BR-01 MP-02
3 A 3.01
178' - 11 1/2"
ROOF LEVEL 142' - 4"
54' - 11" MAX. BUILDING HEIGHT
FC-01
EXISTING MULTIUSE PATH
FC-03
BR-01
1 A 3.01
BLDG. LOW POINT 5306' - 6"
MTL-02
SOUTH SITE ELEVATION 1/16" = 1'-0"
0'
8'
16'
32'
64'
2.00 - MATERIAL FINISH SCHEDULE - EXTERIOR MARK AL-01 AL-02 BR-01 BR-02 BR-03 CC-01 CC-02 FC-01 FC-02 FC-03 FC-04 GL-01 MP-01 MP-02 MTL-01 MTL-02 MTL-03 MTL-04 RM-01 RS-01 WN-01 WN-02
DESCRIPTION
FINISH
ALUMNIUM STOREFRONT ALUMINUM STOREFRONT BRICK BASE BRICK BRICK - ACCENT DETAILING EXPOSED CONCRETE CONCRETE CAP & SILL FIBER CEMENT - VERTICAL SIDING FIBER CEMENT PANEL FIBER CEMENT TRIM FIBER CEMENT TRIM GLASS PANEL RAILING METAL ROOF SCREEN PERFORATED METAL PANEL RAILING METAL PARAPET CAP POWDER COATED STEEL METAL WALL CAP METAL WALL CAP MEMBRANE ROOFING ASPHALT SHINGLE ROOFING EXTERIOR WINDOWS & DOORS EXTERIOR WINDOWS & DOORS
GRAY DARK GRAY DARK BROWN RED BLEND MATCH ADJACENT BRICK BOARDFORM TAN DARK GRAY LIGHT GRAY DARK GRAY GRAY CLEAR GRAY LIGHT GRAY DARK GRAY GRAY TAN GRAY LIGHT GRAY DARK GRAY LIGHT GRAY BLACK
ARAPAHOE HOUSE
MATERIAL PALETTE PRIMARY MATERIALS
1
MECHANICAL SCREEN
MP-02
FC-01
PPRIVATE ACCESS WALK
ELEVATOR OVERRUN
FC-02
RS-01
CHAMPION SYCAMORE TREE BEYOND
BRICK | BR-02 RED BLEND
FIBER CEMENT SIDING | FC-02 PANEL - LIGHT GRAY
ACCENT MATERIALS
2
FACADE 3
BUILDING 3 CHESTNUT HOUSE
BRICK ACCENT | BR-03 RED BLEND ACCENT PATTERN
LINCOLN HALL
ACCENT METAL | MTL-02 GRAY
BUILDING 2
BRICK BASE | BR-01 DARK BROWN
FIBER CEMENT SIDING | FC-01 VERTICAL - DARK GRAY
ACCENT CAP & SILL | CC-02 TAN
PERFORATED RAILING | MP-02 DARK GRAY
KEY PLAN
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
EXTERIOR SOUTH ELEVATION
A 2.02
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
FACADE 3 7' - 3 1/2" STEP BACK (20') FACADE 2 129' - 5" FACADE 1 25' - 2"
FACADE 1 25' - 0"
FACADE 1 25' - 2"
7' - 4"
VERTICAL EXPRESSION
7' - 3"
VERTICAL EXPRESSION
7' - 3"
VERTICAL EXPRESSION
7' - 3"
FACADE 1 25' - 0"
FACADE 3 25' - 4 1/2"
VERTICAL EXPRESSION
FACADE 3 28' - 4"
FACADE LEGEND
FACADE 1 ENTRY STEP BACK (9')
ENTRY STEP BACK (9')
ENTRY STEP BACK (9')
ENTRY STEP BACK (9')
7' - 10"
7' - 10"
7' - 10"
7' - 10"
FACADE 2
FACADE 3
2
0
EAST ELEVATION DIAGRAM
8'
16'
32'
3/32" = 1'-0"
CHAMPION SYCAMORE TREES BEYOND
1 A 3.00
2 A 3.00
MTL-03
CHAMPION RED OAK TREE
FC-03 MP-01
RS-01
WN-02
LEVEL 1 100' - 0" PARKING 96' - 6" BLDG. LOW POINT 5306' - 6"
MP-02
WN-02
TOWNHOUSE - ROOF 141' - 0"
MTL-03
FC-03
WN-01
MP-02
BR-03
MP-02
BR-01
BR-01
FC-01 WN-02
WN-01
BR-03
183' - 3"
31' - 5 1/2"
TOWNHOUSE - L-4 130' - 6"
TOWNHOUSE - L-3 120' - 0"
TOWNHOUSE - L-2 109' - 6"
TOWNHOUSE - L-1 99' - 0" TOWNHOUSE - BLDG. LOW PT. 5308' - 7 3/4"
BR-01
TOWNHOUSES (BUILDING 3)
MAIN BUILDING (BUILDING 2)
1 A 3.00
62' - 1 1/2"
54' - 11"
BR-02
WN-01
BR-02
2 A 3.00
EAST SITE ELEVATION 1/16" = 1'-0"
8'
16'
32'
64' 2.00 - MATERIAL FINISH SCHEDULE - EXTERIOR MARK AL-01 AL-02 BR-01 BR-02 BR-03 CC-01 CC-02 FC-01 FC-02 FC-03 FC-04 GL-01 MP-01 MP-02 MTL-01 MTL-02 MTL-03 MTL-04 RM-01 RS-01 WN-01 WN-02
DESCRIPTION
FINISH
ALUMNIUM STOREFRONT ALUMINUM STOREFRONT BRICK BASE BRICK BRICK - ACCENT DETAILING EXPOSED CONCRETE CONCRETE CAP & SILL FIBER CEMENT - VERTICAL SIDING FIBER CEMENT PANEL FIBER CEMENT TRIM FIBER CEMENT TRIM GLASS PANEL RAILING METAL ROOF SCREEN PERFORATED METAL PANEL RAILING METAL PARAPET CAP POWDER COATED STEEL METAL WALL CAP METAL WALL CAP MEMBRANE ROOFING ASPHALT SHINGLE ROOFING EXTERIOR WINDOWS & DOORS EXTERIOR WINDOWS & DOORS
GRAY DARK GRAY DARK BROWN RED BLEND MATCH ADJACENT BRICK BOARDFORM TAN DARK GRAY LIGHT GRAY DARK GRAY GRAY CLEAR GRAY LIGHT GRAY DARK GRAY GRAY TAN GRAY LIGHT GRAY DARK GRAY LIGHT GRAY BLACK
ARAPAHOE HOUSE
MATERIAL PALETTE
BRICK | BR-02 RED BLEND
FIBER CEMENT SIDING | FC-02 PANEL - LIGHT GRAY
ACCENT MATERIALS
0'
PRIMARY MATERIALS
1
FC-02
FC-02
MAX. BUILDING HEIGHT
LEVEL 2 111' - 4"
RS-01
WN-02
FC-01
ARAPAHOE AVE.
LEVEL 3 121' - 8"
54' - 10 3/4"
LEVEL 4 132' - 0"
MAX. BUILDING HEIGHT
ROOF LEVEL 142' - 4"
PROPOSED MULTIUSE PATH / MARINE ST.
FC-02
BUILDING 3 CHESTNUT HOUSE
BRICK ACCENT | BR-03 RED BLEND ACCENT PATTERN
LINCOLN HALL
ACCENT METAL | MTL-02 GRAY
BUILDING 2
BRICK BASE | BR-01 DARK BROWN
FIBER CEMENT SIDING | FC-01 VERTICAL - DARK GRAY
ACCENT CAP & SILL | CC-02 TAN
PERFORATED RAILING | MP-02 DARK GRAY
KEY PLAN
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
EXTERIOR EAST ELEVATION
A 2.03
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
3 A 3.00
MTL-01
ROOF LEVEL 142' - 4"
FC-01
RS-01
WN-02
FC-01
FC-03
2 A 3.00
MTL-02
AL-01
GL-01
ROOF LEVEL 142' - 4"
MTL-02 WN-01 BR-02
LEVEL 4 132' - 0"
LEVEL 3 121' - 8"
LEVEL 3 121' - 8"
LEVEL 2 111' - 4"
LEVEL 2 111' - 4"
LEVEL 1 100' - 0"
LEVEL 1 100' - 0"
PARKING 96' - 6" BLDG. LOW POINT 5306' - 6"
BR-01
MAX. BUILDING HEIGHT
MTL-03
LEVEL 4 132' - 0"
54' - 10 7/8"
WN-02
PARKING 96' - 6" BLDG. LOW POINT 5306' - 6"
WN-01
BR-02
BR-02
AL-01
BR-01
BR-03
MTL-02
3 A 3.00
3
WEST ELEVATION - COURTYARD
2
1/16" = 1'-0"
2 A 3.00
EAST ELEVATION - COURTYARD 1/16" = 1'-0"
1 A 3.01
2 A 3.01
4 A 3.00
3 A 3.01
DASHED LIGHT LINE REPRESENTS BUILDING IN FOREGROUND
MP-01
WN-02 FC-03 FC-02
MTL-01 WN-02 FC-01 ROOF LEVEL 142' - 4"
FC-01 WN-02
54' - 11"
BR-02
WN-01 BR-03
LEVEL 4 132' - 0"
MAX. BUILDING HEIGHT
MTL-03
LEVEL 3 121' - 8" LEVEL 2 111' - 4"
BR-01
LEVEL 1 100' - 0"
MP-02 WN-01
1 A 3.01
BR-01
WN-01
FC-02
4 A 3.00
2 A 3.01
3 A 3.01
NORTH SITE ELEVATION - COURTYARD 0'
8'
16'
32'
64' 2.00 - MATERIAL FINISH SCHEDULE - EXTERIOR MARK AL-01 AL-02 BR-01 BR-02 BR-03 CC-01 CC-02 FC-01 FC-02 FC-03 FC-04 GL-01 MP-01 MP-02 MTL-01 MTL-02 MTL-03 MTL-04 RM-01 RS-01 WN-01 WN-02
DESCRIPTION
FINISH
ALUMNIUM STOREFRONT ALUMINUM STOREFRONT BRICK BASE BRICK BRICK - ACCENT DETAILING EXPOSED CONCRETE CONCRETE CAP & SILL FIBER CEMENT - VERTICAL SIDING FIBER CEMENT PANEL FIBER CEMENT TRIM FIBER CEMENT TRIM GLASS PANEL RAILING METAL ROOF SCREEN PERFORATED METAL PANEL RAILING METAL PARAPET CAP POWDER COATED STEEL METAL WALL CAP METAL WALL CAP MEMBRANE ROOFING ASPHALT SHINGLE ROOFING EXTERIOR WINDOWS & DOORS EXTERIOR WINDOWS & DOORS
GRAY DARK GRAY DARK BROWN RED BLEND MATCH ADJACENT BRICK BOARDFORM TAN DARK GRAY LIGHT GRAY DARK GRAY GRAY CLEAR GRAY LIGHT GRAY DARK GRAY GRAY TAN GRAY LIGHT GRAY DARK GRAY LIGHT GRAY BLACK
ARAPAHOE HOUSE
MATERIAL PALETTE
BRICK | BR-02 RED BLEND
FIBER CEMENT SIDING | FC-02 PANEL - LIGHT GRAY
ACCENT MATERIALS
1/16" = 1'-0"
PRIMARY MATERIALS
1
BR-02
MTL-02
PARKING 96' - 6" BLDG. LOW POINT 5306' - 6"
3 CHESTNUT HOUSE
BRICK ACCENT | BR-03 RED BLEND ACCENT PATTERN
ACCENT METAL | MTL-02 GRAY
2
BUILDING 3
LINCOLN HALL
1 BUILDING 2
BRICK BASE | BR-01 DARK BROWN
FIBER CEMENT SIDING | FC-01 VERTICAL - DARK GRAY
ACCENT CAP & SILL | CC-02 TAN
PERFORATED RAILING | MP-02 DARK GRAY
KEY PLAN
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
EXTERIOR ELEVATIONS - COURTYARD
A 2.04
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
CHAMPION SYCAMORE TREE BEYOND
1 A 3.01
2 A 3.00
RS-01
FC-03
FC-03
FC-02
54' - 11"
WN-01
TOWNHOUSE - L-4 130' - 6"
TOWNHOUSE - L-4 130' - 6"
TOWNHOUSE - L-3 120' - 0"
TOWNHOUSE - L-3 120' - 0"
TOWNHOUSE - L-2 109' - 6"
TOWNHOUSE - L-2 109' - 6"
TOWNHOUSE - L-1 - 0" TOWNHOUSE - 99' BLDG. LOW PT. 5308' - 7 3/4"
MP-02
TOWNHOUSE - L-1 99' - 0" TOWNHOUSE - BLDG. LOW PT. 5308' - 7 3/4"
EXISTING MULTIUSE PATH
MTL-03
TOWNHOUSE - ROOF 141' - 0" MAX. BUILDING HEIGHT
MP-02
TOWNHOUSE - ROOF 141' - 0"
54' - 11"
FC-02
MAX. BUILDING HEIGHT
CHAMPION RED OAK TREE
FC-02
MTL-03
WN-01
BR-02
FC-02
BR-02
TOWNHOUSES (BUILDING 3)
BR-01
TOWNHOUSES (BUILDING 3)
2 A 3.00
4
1 A 3.01
TOWNHOUSE - EAST ELEVATION
2
1/16" = 1'-0"
TOWNHOUSE - NORTH ELEVATION 1/16" = 1'-0"
1 A 3.01
2 A 3.00 MP-02 FC-03 FC-02 WN-02
54' - 11"
WN-02 MTL-03 BR-02 WN-01
TOWNHOUSE - L-4 130' - 6"
FC-03 54' - 11"
FC-02
MAX. BUILDING HEIGHT
RS-01
FC-02
TOWNHOUSE - L-3 120' - 0"
BR-02 TOWNHOUSE - L-2 109' - 6" WN-01
TOWNHOUSE - L-1 99' - 0" TOWNHOUSE - BLDG. LOW PT. 5308' - 7 3/4"
1
1/16" = 1'-0"
16'
32'
TOWNHOUSE - L-2 109' - 6"
64'
TOWNHOUSE - SOUTH ELEVATION 1/16" = 1'-0"
2.00 - MATERIAL FINISH SCHEDULE - EXTERIOR MARK AL-01 AL-02 BR-01 BR-02 BR-03 CC-01 CC-02 FC-01 FC-02 FC-03 FC-04 GL-01 MP-01 MP-02 MTL-01 MTL-02 MTL-03 MTL-04 RM-01 RS-01 WN-01 WN-02
DESCRIPTION
FINISH
ALUMNIUM STOREFRONT ALUMINUM STOREFRONT BRICK BASE BRICK BRICK - ACCENT DETAILING EXPOSED CONCRETE CONCRETE CAP & SILL FIBER CEMENT - VERTICAL SIDING FIBER CEMENT PANEL FIBER CEMENT TRIM FIBER CEMENT TRIM GLASS PANEL RAILING METAL ROOF SCREEN PERFORATED METAL PANEL RAILING METAL PARAPET CAP POWDER COATED STEEL METAL WALL CAP METAL WALL CAP MEMBRANE ROOFING ASPHALT SHINGLE ROOFING EXTERIOR WINDOWS & DOORS EXTERIOR WINDOWS & DOORS
GRAY DARK GRAY DARK BROWN RED BLEND MATCH ADJACENT BRICK BOARDFORM TAN DARK GRAY LIGHT GRAY DARK GRAY GRAY CLEAR GRAY LIGHT GRAY DARK GRAY GRAY TAN GRAY LIGHT GRAY DARK GRAY LIGHT GRAY BLACK
ARAPAHOE HOUSE
MATERIAL PALETTE
BRICK | BR-02 RED BLEND
FIBER CEMENT SIDING | FC-02 PANEL - LIGHT GRAY
ACCENT MATERIALS
TOWNHOUSE - WEST ELEVATION 8'
TOWNHOUSE - L-3 120' - 0"
1 A 3.01
PRIMARY MATERIALS
0'
TOWNHOUSE - L-4 130' - 6"
TOWNHOUSE - L-1 99' - 0" TOWNHOUSE - BLDG. LOW PT. 5308' - 7 3/4"
2 A 3.00
3
MAX. BUILDING HEIGHT
TOWNHOUSE - ROOF 141' - 0"
3 CHESTNUT HOUSE
BRICK ACCENT | BR-03 RED BLEND ACCENT PATTERN
2 BUILDING 3
LINCOLN HALL
4
1
ACCENT METAL | MTL-02 GRAY
BUILDING 2
BRICK BASE | BR-01 DARK BROWN
FIBER CEMENT SIDING | FC-01 VERTICAL - DARK GRAY
ACCENT CAP & SILL | CC-02 TAN
PERFORATED RAILING | MP-02 DARK GRAY
KEY PLAN
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
EXTERIOR ELEVATIONS - TOWNHOUSE
A 2.05
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
3 A 3.01
2 A 3.00
1 A 3.00
ROOF LEVEL 142' - 4"
ROOF LEVEL 142' - 4"
CORR. LEVEL 4 132' - 0" 5BR/4BA FLAT
CORR.
5BR/5BA FLAT
D.O. 4BR/2BA FLAT
5BR/5BA FLAT
D.O. 4BR/2BA FLAT
LEVEL 3 121' - 8" 5BR/4BA FLAT
CORR.
5BR/5BA FLAT
LEVEL 4 132' - 0" LEVEL 3 121' - 8"
D.O. 4BR/2BA FLAT
LEVEL 2 111' - 4" VESTIBULE
LOBBY & COMMONS
LEVEL 2 111' - 4" D.O. 4BR/2BA FLAT
CORR.
COVERED PARKING
LEVEL 1 100' - 0"
STORAGE/ SHOP
B.O.H. /MECHANICAL
LEVEL 1 100' - 0" PARKING 96' - 6" BLDG. LOW POINT 5306' - 6"
BLDG. LOW POINT 5306' - 6" 3 A 3.01
5BR/4BA FLAT
5BR/5BA TOWNHOUSE 2BR/1BA FLAT
SPA
FITNESS
5BR/4BA FLAT
LOBBY
6BR/6BA TOWNHOUSE
2BR/1BA FLAT
LINCOLN HALL
3 A 3.01
4 A 3.00
10' - 6"
TOWNHOUSE - L-4 130' - 6"
TOWNHOUSE - L-3 120' - 0"
TOWNHOUSE - L-2 109' - 6" TOWNHOUSE - L-1 99' - 0"
2 A 3.01
TOWNHOUSES (BUILDING 3)
BASEMENT INFILL
1 A 3.01
EAST-WEST SITE SECTION 1/16" = 1'-0"
4 A 3.00
2 A 3.01
1 A 3.01
5BR/4BA FLAT
4BR/4BA FLAT
4BR/4BA FLAT
4BR/4BA FLAT
4BR/4BA FLAT
4BR/4BA FLAT
4BR/4BA FLAT
5BR/4BA FLAT
4BR/4BA FLAT
4BR/4BA FLAT
4BR/4BA FLAT
4BR/4BA FLAT
4BR/4BA FLAT
4BR/4BA FLAT
5BR/4BA FLAT
4BR/4BA FLAT
5BR/5BA FLAT
5BR/5BA FLAT
5BR/5BA FLAT
5BR/5BA FLAT
5BR/5BA FLAT
COVERED PARKING
STORAGE/ SHOP
D.O. 2BR/1BA FLAT 5BR/4BA TOWNHOUSE 5BR/4BA TOWNHOUSE
COVERED PARKING
3' - 6"
5BR/4BA FLAT
D.O. 2BR/1BA FLAT
3 A 3.01
4 A 3.00
1 A 3.01
2 A 3.01
ROOF LEVEL 142' - 4" 54' - 11" MAX. BUILDING HEIGHT
SHARED CAMPUS WALK
3 A 3.01
1
5BR/5BA TOWNHOUSE
TOWNHOUSE - ROOF 141' - 0"
TOWNHOUSE - BLDG. LOW PT. 5308' - 7 3/4"
MAIN BUILDING (BUILDING 2)
2
5BR/5BA TOWNHOUSE
10' - 4" 10' - 4" 10' - 4"
BLDG. LOW POINT 5306' - 6"
5BR/4BA FLAT
5BR/4BA FLAT
11' - 4"
LEVEL 1 100' - 0"
POOL EQUIPMENT ROOM
5BR/4BA FLAT
ANNEX
1 A 3.01
8' - 1"
11' - 4"
LEVEL 2 111' - 4"
2 A 3.01
54' - 11" MAX. BUILDING HEIGHT
10' - 4"
LEVEL 3 121' - 8"
4 A 3.00
10' - 6"
10' - 4"
LEVEL 4 132' - 0"
SHARED CAMPUS WALK
3 A 3.01
1/16" = 1'-0"
10' - 6"
1/16" = 1'-0"
NORTH SOUTH SITE SECTION
10' - 6"
4
EXISTING MULTIUSE PATH
EAST-WEST SECTION @ MAIN ENTRY
1 A 3.00
EXISTING MULTIUSE PATH
3
2 A 3.00
LEVEL 4 132' - 0" LEVEL 3 121' - 8" LEVEL 2 111' - 4" LEVEL 1 100' - 0" PARKING 96' - 6"
BLDG. LOW POINT 5306' - 6"
EAST-WEST SITE SECTION 1" = 20'-0"
0'
8'
16'
32'
64'
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
BUILDING SECTIONS
A 3.00
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
1 A 3.00
ARAPAHOE AVE.
5BR/3BA FLAT
5BR/4BA FLAT
5BR/3BA FLAT
5BR/3BA FLAT
5BR/4BA FLAT
5BR/3BA FLAT
LOBBY & COMMONS
ANNEX
ANNEX
5BR/4BA FLAT
5BR/4BA FLAT
5BR/4BA FLAT
5BR/4BA FLAT
5BR/4BA FLAT
5BR/4BA FLAT
5BR/4BA FLAT
5BR/4BA FLAT
5BR/4BA FLAT
5BR/4BA FLAT
5BR/4BA FLAT
5BR/4BA FLAT
5BR/4BA FLAT
5BR/4BA FLAT
10' - 4"
5BR/4BA FLAT
2BR/2BA FLAT
2BR/2BA FLAT
2BR/2BA FLAT
B.O.H. /ELECTRICAL
LEVEL 4 132' - 0"
10' - 4"
5BR/4BA FLAT
LEVEL 3 121' - 8"
10' - 4"
TROPHY ROOM
POOL DECK
ROOF LEVEL 142' - 4"
LEVEL 2 111' - 4"
11' - 4"
3 A 3.00
MARINE ST.
2 A 3.00
LEVEL 1 100' - 0" PARKING 96' - 6" BLDG. LOW POINT 5306' - 6"
2 A 3.00
1 A 3.00
1 A 3.00
5BR/5BA FLAT
4BR/4BA FLAT
4BR/2BA FLAT
4BR/2BA FLAT
ARAPAHOE AVE.
5BR/5BA FLAT 5BR/4BA FLAT 5BR/5BA FLAT
5BR/5BA FLAT
LOBBY COVERED PARKING
D.O. 4BR/2BA FLAT
10' - 4"
2 A 3.00
10' - 4"
1/16" = 1'-0"
3 A 3.00
6BR/5BA TOWNHOUSE
10' - 4"
NORTH SOUTH SITE SECTION
6BR/5BA TOWNHOUSE
11' - 4"
3
1/16" = 1'-0"
1 A 3.00
2 A 3.00
1 A 3.00
D.O. 4BR/2BA FLAT
D.O. 4BR/2BA FLAT
D.O. 2BR/1BA FLAT
D.O. 4BR/2BA FLAT
D.O. 4BR/2BA FLAT
D.O. 4BR/2BA FLAT
D.O. 2BR/1BA FLAT
5BR/5BA TOWNHOUSE
5BR/5BA TOWNHOUSE
5BR/5BA TOWNHOUSE
5BR/4BA TOWNHOUSE
4BR/2BA FLAT
4BR/2BA FLAT
5BR/5BA TOWNHOUSE
3' - 6"
TOWNHOUSE - L-1 99' - 0" TOWNHOUSE - BLDG. LOW PT. 5308' - 7 3/4"
5BR/4BA TOWNHOUSE
D.O. 4BR/2BA FLAT
11' - 4"
TOWNHOUSE - L-2 109' - 6"
2BR/2BA FLAT
6BR/6BA TOWNHOUSE
10' - 6"
ARAPAHOE AVE.
TOWNHOUSE - L-3 120' - 0"
2BR/2BA FLAT
10' - 6"
TOWNHOUSE - L-4 130' - 6"
10' - 6"
10' - 6"
TOWNHOUSE - ROOF 141' - 0"
2 A 3.00
10' - 4"
NORTH SOUTH SITE SECTION
TOWNHOUSES (BUILDING 3)
MAIN BUILDING (BUILDING 2)
2 A 3.00
1
LEVEL 4 132' - 0" LEVEL 3 121' - 8" LEVEL 2 111' - 4" LEVEL 1 100' - 0" PARKING 96' - 6" BLDG. LOW POINT 5306' - 6"
MAIN BUILDING (BUILDING 2)
10' - 4"
LINCOLN HALL
10' - 4"
2
3' - 6"
INFILLED BASEMENT
ROOF LEVEL 142' - 4"
ROOF LEVEL 142' - 4" LEVEL 4 132' - 0" LEVEL 3 121' - 8" LEVEL 2 111' - 4" LEVEL 1 100' - 0" PARKING 96' - 6" BLDG. LOW POINT 5306' - 6"
1 A 3.00
NORTH SOUTH SITE SECTION 1/16" = 1'-0"
0'
8'
16'
32'
64'
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
BUILDING SECTIONS
A 3.01
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
BRICK | BR-02 RED BLEND
FIBER CEMENT SIDING | FC-02 PANEL - LIGHT GRAY
BRICK BASE | BR-01 DARK BROWN
FIBER CEMENT SIDING | FC-01 VERTICAL - DARK GRAY
ACCENT MATERIALS
PRIMARY MATERIALS
MATERIAL PALETTE
BRICK ACCENT | BR-03 RED BLEND ACCENT PATTERN
ACCENT METAL | MTL-02 GRAY
ACCENT CAP & SILL | CC-02 TAN
PERFORATED RAILING | MP-02 DARK GRAY
CONTEXT & DESIGN INSPIRATION
VIEW A: CONCEPTUAL RENDERING - VIEW FROM NORTH-EAST ALONG ARAPAHOE AVE
LINCOLN HALL
MARINE COURT - NEIGHBORING CU STUDENT HOUSING
STATE OF COLORADO CHAMPION TREES
B
VIEW B: CONCEPTUAL RENDERING - VIEW OF CAMPUS WALK FROM NORTH-WEST
A
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
CONCEPTUAL RENDERINGS
A 9.00
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
BRICK | BR-02 RED BLEND
FIBER CEMENT SIDING | FC-02 PANEL - LIGHT GRAY
BRICK BASE | BR-01 DARK BROWN
FIBER CEMENT SIDING | FC-01 VERTICAL - DARK GRAY
ACCENT MATERIALS
PRIMARY MATERIALS
MATERIAL PALETTE
BRICK ACCENT | BR-03 RED BLEND ACCENT PATTERN
ACCENT METAL | MTL-02 GRAY
ACCENT CAP & SILL | CC-02 TAN
PERFORATED RAILING | MP-02 DARK GRAY
DESIGN INSPIRATION & PRECEDENTS EXPRESSIVE ROOF FORMS
TIMELESS DETAILING & MATERIALS
UNIVERSITY OF COLORADO ENGINEERING BUILDING - BOULDER, CO ARCHITECTURAL ASSOCIATES OF COLORADO
MOXY HOTEL - BOULDER, CO SAR+ ARCHITECTS
DESIGN INSPIRATION & PRECEDENT IMAGERY
VIEW A: CONCEPTUAL RENDERING - VIEW FROM SOUTH-WEST
AMSTERDAM CANAL HOUSES
UNIVERSITY OF COLORADO, CASE BUILDING OZ ARCHITECTURE
CAMPUS WALKS
LOCUST WALK, UNIVERSITY OF PENNSYLVANIA
WARDENBURG DRIVE, UNIVERSITY OF COLORADO BOULDER
B
VIEW B: CONCEPTUAL RENDERING - VIEW OF ENTRY FROM SHARED CAMPUS WALK
A HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
CONCEPTUAL RENDERINGS
A 9.01
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
VIEW A: CONCEPTUAL RENDERING - COURTYARD VIEW
VIEW B: CONCEPTUAL RENDERING - VIEW FROM ARAPAHOE INTO COURTYARD
B
D
A C
VIEW C: CONCEPTUAL RENDERING - VIEW FROM EAST MULTI-USE PATH
VIEW D: CONCEPTUAL RENDERING - VIEW FROM NORTHEAST ON ARAPAHOE AVE
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
CONCEPTUAL SITE EXPERIENCE VIGNETTES
A 9.02
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
POWDER COATED STEEL CHANNEL AT CANOPY EDGE
3' - 4"
BRICK VENEER
FINISHED CEILING
BRICK | BR-02 RED BLEND
FIBER CEMENT SIDING | FC-02 PANEL - LIGHT GRAY
BRICK BASE | BR-01 DARK BROWN
FIBER CEMENT SIDING | FC-01 VERTICAL - DARK GRAY
ACCENT MATERIALS
MEMBRANE ROOFING OVER CANOPY FRAMING, RE: STRUCT.
6"
PRECAST CONCRETE CAP
PRIMARY MATERIALS
MATERIAL PALETTE
BRICK ACCENT | BR-03 RED BLEND ACCENT PATTERN
ACCENT METAL | MTL-02 GRAY
ACCENT CAP & SILL | CC-02 TAN
PERFORATED RAILING | MP-02 DARK GRAY
GLASS & ALUMINUM GUARDRAIL
6' - 0" RAILING
8' - 0"
ROOF DECK
PREFINISHED METAL FLASHING AT RAILING/ OPENIING
CONCRETE PAVERS ON PEDESTALS, OVER COVER BOARD AND TAPERED INSULATION - SLOPE TO DRAIN
CONCRETE SLAB, RE: STRUCT
2.00 - MATERIAL FINISH SCHEDULE - EXTERIOR MARK
3' - 0"
RECESSED BRICK VENEER
2' - 4"
1" RECESS FROM FACE
DESIGN INSPIRATION & CONTEXT
TRELLIS
LEVEL 4 132' - 0"
MTL-02
EXISTING LINCOLN HALL DESIGN INSPIRATION TO BE CARRIED THROUGHOUT PROPOSED DESIGN -VERTICAL WINDOW STACK -WHITE WINDOW FRAME WITH BRICK EXTERIOR -BRICK WINDOW HEADER -WHITE TRIM DETAILS THROUGHOUT -BRICK REVEAL DETAILING AT BUILDING BASE
9' - 4"
ALUMINUM STOREFRONT
GL-01
10' - 4"
POWDER COATED STEEL CHANNEL, RE: STRUCT
CC-02 PREFINISHED METAL SILL FLASHING AT STOREFRONT, TYP
BR-02
2' - 4"
DECK
WN-01
FINISH
ALUMNIUM STOREFRONT ALUMINUM STOREFRONT BRICK BASE BRICK BRICK - ACCENT DETAILING EXPOSED CONCRETE CONCRETE CAP & SILL FIBER CEMENT - VERTICAL SIDING FIBER CEMENT PANEL FIBER CEMENT TRIM FIBER CEMENT TRIM GLASS PANEL RAILING METAL ROOF SCREEN PERFORATED METAL PANEL RAILING METAL PARAPET CAP POWDER COATED STEEL METAL WALL CAP METAL WALL CAP MEMBRANE ROOFING ASPHALT SHINGLE ROOFING EXTERIOR WINDOWS & DOORS EXTERIOR WINDOWS & DOORS
GRAY DARK GRAY DARK BROWN RED BLEND MATCH ADJACENT BRICK BOARDFORM TAN DARK GRAY LIGHT GRAY DARK GRAY GRAY CLEAR GRAY LIGHT GRAY DARK GRAY GRAY TAN GRAY LIGHT GRAY DARK GRAY LIGHT GRAY BLACK
LEVEL 3 121' - 8"
BR-03
MTL-02
8' - 0"
ALUMINUM STOREFRONT
9' - 4"
POWDER COATED STEEL CHANNEL, RE: STRUCT
RM-01
POWDER COATED STEEL CHANNEL, RE: STRUCT
1' - 0"
BRICK VENEER,TYP 2' - 4"
ROOF
1' - 0"
BRICK VENEER,TYP
AL-01 AL-02 BR-01 BR-02 BR-03 CC-01 CC-02 FC-01 FC-02 FC-03 FC-04 GL-01 MP-01 MP-02 MTL-01 MTL-02 MTL-03 MTL-04 RM-01 RS-01 WN-01 WN-02
DESCRIPTION
LEVEL 2 111' - 4"
DROPPED GYP CEILING
MTL-02
10' - 0"
AL-01
ARAPAHOE HOUSE
11' - 4"
ALUMINUM STOREFRONT
1
SLAB ON GRADE, RE: STRUCT
CHESTNUT HOUSE
BUILDING 3 LINCOLN HALL
MTL-04 BRICK VENEER BASE OVER CONCRETE FOUNDATION, RE: STRUCT
BR-01
LEVEL 1 100' - 0"
BUILDING 2 1/2" INSET BRICK REVEAL SLOPE SITE WORK AWAY FROM BUILDING, RE: CIVIL
CC-01
3D SECTION KEY PLAN
2
NW CORNER @ ROOF DECK
Not To Scale
1
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
WALL SECTION @ ROOF DECK 3/8" = 1'-0"
0
2'
4'
8'
DESIGN EXCELLENCE
A 9.10
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
CONCRETE POOL PER MFR., TILE FINISH TYP. 6' - 0" A.F.F.
GLASS AND METAL RAILING
FIBER CEMENT SIDING | FC-02 PANEL - LIGHT GRAY
BRICK BASE | BR-01 DARK BROWN
FIBER CEMENT SIDING | FC-01 VERTICAL - DARK GRAY
BRICK ACCENT | BR-03 RED BLEND ACCENT PATTERN
ACCENT METAL | MTL-02 GRAY
ACCENT CAP & SILL | CC-02 TAN
PERFORATED RAILING | MP-02 DARK GRAY
CONCRETE PAVERS, ON PEDESTALS, OVER COVER BOARD AND TAPERED INSULATION SLOPE TO DRAIN
7' - 4"
POOL
4' - 0"
1' - 6"
6"
PRECAST CONCRETE CAP
BRICK | BR-02 RED BLEND
ACCENT MATERIALS
PRIMARY MATERIALS
MATERIAL PALETTE
2.00 - MATERIAL FINISH SCHEDULE - EXTERIOR 2' - 0"
CONCRETE SLAB, RE: STRUCT
MARK LEVEL 4 132' - 0"
AL-01 AL-02 BR-01 BR-02 BR-03 CC-01 CC-02 FC-01 FC-02 FC-03 FC-04 GL-01 MP-01 MP-02 MTL-01 MTL-02 MTL-03 MTL-04 RM-01 RS-01 WN-01 WN-02
BRICK HEADER
7' - 4"
PREFINISHED METAL SILL FLASHING AT WINDOWS, TYP GL-01
POOL
3' - 0"
1' - 0"
BRICK ACCENT PANEL, TYP
CC-02
ECK
BR-02
9' - 4"
SCHEDULED WINDOW
D ROOF
LEVEL 3 121' - 8"
DESCRIPTION
FINISH
ALUMNIUM STOREFRONT ALUMINUM STOREFRONT BRICK BASE BRICK BRICK - ACCENT DETAILING EXPOSED CONCRETE CONCRETE CAP & SILL FIBER CEMENT - VERTICAL SIDING FIBER CEMENT PANEL FIBER CEMENT TRIM FIBER CEMENT TRIM GLASS PANEL RAILING METAL ROOF SCREEN PERFORATED METAL PANEL RAILING METAL PARAPET CAP POWDER COATED STEEL METAL WALL CAP METAL WALL CAP MEMBRANE ROOFING ASPHALT SHINGLE ROOFING EXTERIOR WINDOWS & DOORS EXTERIOR WINDOWS & DOORS
GRAY DARK GRAY DARK BROWN RED BLEND MATCH ADJACENT BRICK BOARDFORM TAN DARK GRAY LIGHT GRAY DARK GRAY GRAY CLEAR GRAY LIGHT GRAY DARK GRAY GRAY TAN GRAY LIGHT GRAY DARK GRAY LIGHT GRAY BLACK
7' - 4"
WN-01
9' - 4"
SCHEDULED WINDOW
BR-02 WN-01
BR-03 BR-03
SLOPE TO DRAIN
1' - 0"
MEMBRANE ROOFING OVER TAPERED INSULATION POWDER COATED STEEL CHANNEL, RE: STRUCT
RM-01
LEVEL 2 111' - 4"
ALUMINUM STOREFRONT
11' - 4"
DROPPED GYP CEILING
MTL-02
ARAPAHOE HOUSE
PERFORATED METAL PANEL RAILING AL-01
SLAB ON GRADE, RE: STRUCT
MP-02
CONCRETE CAP
MTL-04
BRICK VENEER BASE OVER CONCRETE FOUNDATION, RE: STRUCT
BR-01
2
SLAB ON GRADE, RE: STRUCT
LEVEL 1 100' - 0"
BUILDING 3 CHESTNUT HOUSE
LINCOLN HALL
1/2" INSET BRICK REVEAL
3'-0" MIN
SLOPE SITE WORK AWAY FROM BUILDING, RE: CIVIL
BUILDING 2
CONCRETE FOUNDATION, RE: STRUCT
2
SECTION THROUGH ROOF DECK POOL
Not To Scale
1
3D SECTION KEY PLAN
WALL SECTION @ ROOF DECK POOL 3/8" = 1'-0"
0
2'
4'
8'
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
DESIGN EXCELLENCE
A 9.11
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
ROOF LEVEL 142' - 4"
FIBER CEMENT FASCIA, TYP FIBER CEMENT SIDING
BRICK | BR-02 RED BLEND
FIBER CEMENT SIDING | FC-02 PANEL - LIGHT GRAY
BRICK BASE | BR-01 DARK BROWN
FIBER CEMENT SIDING | FC-01 VERTICAL - DARK GRAY
ACCENT MATERIALS
ASPHALT SHINGLE ROOF, OVER PREFABRICATED TRUSS FRAMING, RE: STRUCT.
PRIMARY MATERIALS
MATERIAL PALETTE
BRICK ACCENT | BR-03 RED BLEND ACCENT PATTERN
ACCENT METAL | MTL-02 GRAY
ACCENT CAP & SILL | CC-02 TAN
PERFORATED RAILING | MP-02 DARK GRAY
7' - 7 1/2"
10' - 4"
SCHEDULED WINDOW
2.00 - MATERIAL FINISH SCHEDULE - EXTERIOR
1' - 0" MATERIAL OFFSET
MARK
TAN METAL CAP AT BRICK WALL LEVEL 4 132' - 0"
3' - 0"
RS-01
AL-01 AL-02 BR-01 BR-02 BR-03 CC-01 CC-02 FC-01 FC-02 FC-03 FC-04 GL-01 MP-01 MP-02 MTL-01 MTL-02 MTL-03 MTL-04 RM-01 RS-01 WN-01 WN-02
BRICK HEADER
10' - 4"
SCHEDULED WINDOW
FC-03
7' - 4"
FC-01 WN-02
PREFINISHED METAL SILL FLASHING AT WINDOWS, TYP
FC-03 MTL-03
DESCRIPTION
FINISH
ALUMNIUM STOREFRONT ALUMINUM STOREFRONT BRICK BASE BRICK BRICK - ACCENT DETAILING EXPOSED CONCRETE CONCRETE CAP & SILL FIBER CEMENT - VERTICAL SIDING FIBER CEMENT PANEL FIBER CEMENT TRIM FIBER CEMENT TRIM GLASS PANEL RAILING METAL ROOF SCREEN PERFORATED METAL PANEL RAILING METAL PARAPET CAP POWDER COATED STEEL METAL WALL CAP METAL WALL CAP MEMBRANE ROOFING ASPHALT SHINGLE ROOFING EXTERIOR WINDOWS & DOORS EXTERIOR WINDOWS & DOORS
GRAY DARK GRAY DARK BROWN RED BLEND MATCH ADJACENT BRICK BOARDFORM TAN DARK GRAY LIGHT GRAY DARK GRAY GRAY CLEAR GRAY LIGHT GRAY DARK GRAY GRAY TAN GRAY LIGHT GRAY DARK GRAY LIGHT GRAY BLACK
3' - 0"
LEVEL 3 121' - 8"
BRICK HEADER
BR-02 WN-01
7' - 4"
10' - 4"
SCHEDULED WINDOW
LEVEL 2 111' - 4" 4' - 0"
BRICK VENEER
BRICK HEADER
SLAB ON GRADE, RE: STRUCT.
MTL-04
PLANTING AT RAIN GARDEN, RE: LANDSCAPE
7' - 4"
WN-01
11' - 4"
SCHEDULED WINDOW
BR-03
ARAPAHOE HOUSE
CC-01
8"
BUILDING 3 1"
SH
AR
ED
PR
IVA T
EA
CC
ESS
LEVEL 1 100' - 0"
LK
CONCRETE FOUNDATION, RE: SRUCT
2
TYPICAL SECTION @ WEST WING
Not To Scale
1
0
BUILDING 2
3D SECTION KEY PLAN
TYP. WALL SECTION @ WEST WING 3/8" = 1'-0"
LINCOLN HALL
3
BOARD FORMED CONCRETE WALL
WA
CHESTNUT HOUSE
2'
4'
8'
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
DESIGN EXCELLENCE
A 9.12
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
PRIMARY MATERIALS
FIBER CEMENT PANEL SIDING
FIBER CEMENT SOFFIT
FIBER CEMENT SIDING | FC-02 PANEL - LIGHT GRAY
BRICK BASE | BR-01 DARK BROWN
FIBER CEMENT SIDING | FC-01 VERTICAL - DARK GRAY
4' - 0"
8' - 0"
BALCONY
FIBER CEMENT SIDING AT BALCONY INTERIOR
4' - 0" RAILING
MARK AL-01 AL-02 BR-01 BR-02 BR-03 CC-01 CC-02 FC-01 FC-02 FC-03 FC-04 GL-01 MP-01 MP-02 MTL-01 MTL-02 MTL-03 MTL-04 RM-01 RS-01 WN-01 WN-02
2' - 4"
LEVEL 4 132' - 0"
1' - 0 1/2"
RS-01
SCHEDULED WINDOW 4' - 0"
FC-01
PERFORATED METAL PANEL RAILING
WN-02
4' - 0" RAILING
8' - 0"
FC-03
BALCONY
10' - 4"
MTL-01
FC-03
FIBER CEMENT PANEL SIDING
WN-02
ACCENT CAP & SILL | CC-02 TAN
PERFORATED RAILING | MP-02 DARK GRAY
DESCRIPTION
FINISH
ALUMNIUM STOREFRONT ALUMINUM STOREFRONT BRICK BASE BRICK BRICK - ACCENT DETAILING EXPOSED CONCRETE CONCRETE CAP & SILL FIBER CEMENT - VERTICAL SIDING FIBER CEMENT PANEL FIBER CEMENT TRIM FIBER CEMENT TRIM GLASS PANEL RAILING METAL ROOF SCREEN PERFORATED METAL PANEL RAILING METAL PARAPET CAP POWDER COATED STEEL METAL WALL CAP METAL WALL CAP MEMBRANE ROOFING ASPHALT SHINGLE ROOFING EXTERIOR WINDOWS & DOORS EXTERIOR WINDOWS & DOORS
GRAY DARK GRAY DARK BROWN RED BLEND MATCH ADJACENT BRICK BOARDFORM TAN DARK GRAY LIGHT GRAY DARK GRAY GRAY CLEAR GRAY LIGHT GRAY DARK GRAY GRAY TAN GRAY LIGHT GRAY DARK GRAY LIGHT GRAY BLACK
LEVEL 3 121' - 8"
2' - 4"
FC-02
ACCENT METAL | MTL-02 GRAY
2.00 - MATERIAL FINISH SCHEDULE - EXTERIOR
PERFORATED METAL PANEL RAILING, TYP
COMPOSITE DECKING
BRICK ACCENT | BR-03 RED BLEND ACCENT PATTERN
4"
SCHEDULED WINDOW
BRICK | BR-02 RED BLEND
ACCENT MATERIALS
MATERIAL PALETTE
ASPHALT SHINGLE ROOF, OVER PREFABRICATED TRUSS FRAMING, RE: STRUCT.
SCHEDULED WINDOW
INTERIOR SPACE
8"
7' - 4"
FC-02
10' - 4"
MP-02
LEVEL 2 111' - 4"
FIBER CEMENT PANEL SIDING
PLANTER, RE: LANDSCAPE
BR-02
1' - 7"
POWDER COATED STEEL CHANNEL, RE: STRUCT
MTL-03
FIBER CEMENT SOFFIT
FC-03
FIBER CEMENT PANEL SIDING
BALCONY 11' - 4"
WN-02
BRICK VENEER WALL BEYOND BR-02
SCHEDULED WINDOW
WN-01
PERFORATED METAL PANEL RAILING
ARAPAHOE HOUSE
BUILDING 3 CHESTNUT HOUSE
FC-02 MTL-04
SLAB ON GRADE, RE: STRUCT
WN-01
BR-01
LEVEL 1 100' - 0"
CONCRETE CAP
BUILDING 2
1/2" INSET BRICK REVEAL BRICK VENEER BASE OVER CONCRETE FOUNDATION, RE: STRUCT
CONCRETE FOUNDATION, RE: STRUCT
SLOPE SITE WORK AWAY FROM BUILDING, RE: CIVIL
2
SECTION THROUGH SOUTH BALCONIES
Not To Scale
LINCOLN HALL
1
3D SECTION KEY PLAN
WALL SECTION @ SOUTH BALCONY 3/8" = 1'-0"
0
2'
4'
8'
4
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
DESIGN EXCELLENCE
A 9.13
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
METAL PANEL MECHANICAL SCREEN MOUNTED ON HSS, RE: STRUCT
PREFINISHED METAL COPING W/ CONTINUOUS CLEAT, SEAL MEMBRANE ROOFING TO COPING AND PARAPET
SLOPE TO DRAIN
7' - 4"
10' - 4"
4' - 0"
ROOF LEVEL 142' - 4"
BRICK | BR-02 RED BLEND
FIBER CEMENT SIDING | FC-02 PANEL - LIGHT GRAY
BRICK BASE | BR-01 DARK BROWN
FIBER CEMENT SIDING | FC-01 VERTICAL - DARK GRAY
ACCENT MATERIALS
MEMBRANE ROOFING OVER PREFABRICATED TRUSS FRAMING, RE: STRUCT.
PRIMARY MATERIALS
MATERIAL PALETTE
SCHEDULED WINDOW
ACCENT CAP & SILL | CC-02 TAN
PERFORATED RAILING | MP-02 DARK GRAY
MARK AL-01 AL-02 BR-01 BR-02 BR-03 CC-01 CC-02 FC-01 FC-02 FC-03 FC-04 GL-01 MP-01 MP-02 MTL-01 MTL-02 MTL-03 MTL-04 RM-01 RS-01 WN-01 WN-02
3' - 0"
LEVEL 4 132' - 0"
FIBER CEMENT PANEL SIDING MP-01 SCHEDULED WINDOW
7' - 4"
10' - 4"
MTL-01
FC-02
8"
1' - 3" MATERIAL OFFSET METAL CAP AT BRICK WALL, SLOPE TO EXTERIOR
DESCRIPTION
FINISH
ALUMNIUM STOREFRONT ALUMINUM STOREFRONT BRICK BASE BRICK BRICK - ACCENT DETAILING EXPOSED CONCRETE CONCRETE CAP & SILL FIBER CEMENT - VERTICAL SIDING FIBER CEMENT PANEL FIBER CEMENT TRIM FIBER CEMENT TRIM GLASS PANEL RAILING METAL ROOF SCREEN PERFORATED METAL PANEL RAILING METAL PARAPET CAP POWDER COATED STEEL METAL WALL CAP METAL WALL CAP MEMBRANE ROOFING ASPHALT SHINGLE ROOFING EXTERIOR WINDOWS & DOORS EXTERIOR WINDOWS & DOORS
GRAY DARK GRAY DARK BROWN RED BLEND MATCH ADJACENT BRICK BOARDFORM TAN DARK GRAY LIGHT GRAY DARK GRAY GRAY CLEAR GRAY LIGHT GRAY DARK GRAY GRAY TAN GRAY LIGHT GRAY DARK GRAY LIGHT GRAY BLACK
LEVEL 3 121' - 8"
1' - 3"
2' - 4"
BRICK VENEER
ACCENT METAL | MTL-02 GRAY
2.00 - MATERIAL FINISH SCHEDULE - EXTERIOR
PREFINISHED METAL SILL FLASHING AT WINDOWS, TYP
WN-02
BRICK ACCENT | BR-03 RED BLEND ACCENT PATTERN
FC-03
STEEL LINTEL, RE: STRUCT. 10' - 4"
FIBER CEMENT SOFFIT BRICK VENEER WALL BEYOND 7' - 4"
FIBER CEMENT VERTICAL SIDING WALL BEYOND SCHEDULED WINDOW PREFINISHED METAL SILL FLASHING AT WINDOWS, TYP
MTL-03
LEVEL 2 111' - 4"
BR-02
3' - 4"
19' - 4"
FIBER CEMENT VERTICAL SIDING
WN-01
SCHEDULED ENTRY DOOR 11' - 4"
SLAB ON GRADE, RE: STRUCT
FC-01
ARAPAHOE HOUSE
7' - 4"
PERFORATED METAL PANEL RAILING CONCRETE CAP
BUILDING 3
4' - 0" AFF
BRICK VENEER BASE OVER CONCRETE FOUNDATION, RE: STRUCT
8"
6"
INSET BRICK DETAILING PLANTING, RE: LANDSCAPE
LINCOLN HALL
LEVEL 1 100' - 0"
8"
MTL-04
CHESTNUT HOUSE
3' - 6 1/2"
BR-01
BUILDING 2
VARIES
1" INSET PANEL
SLOPE SITE WORK AWAY FROM BUILDING, RE: CIVIL
5
3D SECTION KEY PLAN
CONCRETE FOUNDATION, RE: STRUCT BR-01
2
SECTION THROUGH EAST ENTRY PORCH
Not To Scale
BR-03
1
WALL SECTION @ EAST ENTRY PORCH 3/8" = 1'-0" 0 2'
4'
8'
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW 07.29.2026
DESIGN EXCELLENCE
A 9.14
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
OPEN SPACE
LINCOLN HALL
2
USEABLE AREAS
NORTH
4TH FLOOR AMENITY DECK PLAN
0
1" = 30'-0"
15'
30'
60'
SCALE: 1" = 30'-0"
LX201
LINCOLN HALL
LX202
LX101
MARINE STREET
1
OVERALL SITE PLAN 1" = 30'-0"
MULTI-USE PATH
ARAPAHOE AVENUE
NORTH
0
15'
30'
60'
SCALE: 1" = 30'-0"
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW
OVERALL SITE PLAN
07.29.2026
L002
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
NOTES: 1. TREES LABELED AS N/A* ON THE PLAN WERE EITHER NOT PRESENT DURING THE TREE INVENTORY , TOO SMALL, OR A MULTI-STEMMED SHRUB FORM AND NOT A TREE. 2. A COMPREHENSIVE TREE PRESERVATION PLAN WILL BE INCLUDED WITH THE NEXT SUBMITTAL PHASE, TECHNICAL DOCUMENTS. THIS PRESERVATION PLAN WILL DETAIL THE PLANS FOR PROTECTION AND CARE OF EXISTING CHAMPION TREES AND EXISTING RIGHT-OF-WAY TREES WITHIN THE PROJECT BOUNDARY AS WELL AS TREES ON ADJACENT PROPERTIES THAT MAY BE IMPACTED BY CONSTRUCTION ACTIVITY WITHIN THEIR DRIP LINE. THE PLAN WILL OUTLINE MEASURES SUCH AS SCHEDULED TREE WATERING TO REDUCE CONSTRUCTION-RELATED STRESS, INSTALLATION AND MAINTENANCE OF TREE PROTECTION FENCING AT CRITICAL ROOT ZONE LIMITS, AND ONGOING TREE HEALTH MONITORING BY QUALIFIED PROFESSIONALS. IT WILL ALSO OUTLINE TREE PROTECTION STRATEGIES INTEGRATED INTO CONSTRUCTION PHASING TO PREVENT IMPACTS FROM CONSTRUCTION ACTIVITIES.
TREE INVENTORY: ARBORIST: SCOTT GRIMES ISA CERTIFIED ARBORIST NUMBER: RM-2410 AM CITY OF BOULDER LICENSE NUMBER: S20952825-0001 COMPANY: COLORADO TREE CONSULTANTS DATE CONDUCTED: TREES 1-8 | 12 DECEMBER 2024 TREES 9-69 | 7 JANUARY 2026 TREES 70 & 71 | 21 MAY 2026 TREES A:1-14 | 21 MAY 2026
ARAPAHOE AVENUE
70
71 28
54
N/A* 49
44
N/A*
48
29
27
42 N/A*
47
43
26
7
50
46 45
41
24 2223 N/A* 21 N/A*
N/A*
N/A* N/A* N/A* N/A* N/A* 20 38 19
37
63
N/A* N/A*
A-10
N/A* 57
53 N/A* N/A* N/A*
58
A-9 64 8
LINCOLN HALL
4
5 39
62
56
55
N/A*
40
N/A*
60
59
A-11
6
51 52
N/A* 25
61
36
N/A*
35 34 33
MULTI-USE PATH
A-1
3
A-8 N/A*
17 N/A*
18
A-7
16
67
32
68
31 2
N/A* 15 N/A* N/A*
65
30
A-6
1
14
13
69 12
11
66
10
MARINE STREET
A-3
9
A-4
A-5
A-2
1
TREE INVENTORY 1" = 30'-0"
NORTH
0
15'
30'
60'
SCALE: 1" = 30'-0"
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW
TREE INVENTORY
07.29.2026
L003
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
CODE
DESCRIPTION
LAYOUT LEGEND
1 - PAVING & SURFACING 1-01 1-02 513'-8"
1-04 1-07
EXISTING TREE TO REMAIN EXISTING TREE TO REMAIN EXISTING DITCH TO REMAIN
1-08
5-01
3-03
ARAPAHOE AVENUE
1-11
BUS STOP
2-01 1-08
CONCERETE PAVING (SEE CIVIL) COLORED CONCRETE STAIRS CRUSHER FINES STONE STEPPERS CONCRETE EDGER
2 - WALLS & FENCES 8'
8'
2-05
DETENTION, RE: CIVIL WATER QUALITY, RE: CIVIL EXISTING MULTI-USE PATH TRANSFORMER
4'
EXISTING TREE TO REMAIN DETENTION, RE: CIVIL WATER QUALITY, RE: CIVIL RELOCATED ARAPAHOE HOUSE RELOCATED CHESTNUT HOUSE
2-01
9'-10"
4 LS301
2-06
CONCRETE SEAT STEPS DOG RUN FENCE DOG RUN GATE
3 - METALS
7'-9"
3-01 3-03
STAIR HANDRAIL STEEL EDGER
1
EXISTING WALLS TO REMAIN
LS301
20' PRIVATE DRIVE
1-01 3
4'
16' 31'-8"
18'-6"
5-04
5-06
18'-6"
6'
11 LS 50 1
4'
4'
LS301
5-01
EXISTING CHAMPION TREES
3'
MAIN BUILDING ENTRY
5 - FURNISHINGS
5-01
5-06
5-04 29'-3"
8'-7"
5-06
1-04
DETENTION, RE: CIVIL WATER QUALITY, RE: CIVIL
HAMMOCK AND POST BIKE RACK
7 - ELECTRICAL 320'-1"
1-08
BENCH
7-01
LIGHT BOLLARD
3-01
MULTI-USE PATH
2 LS301
5-01 1-07
147'-6"
1-02 TRANSFORMERS
1-11 2-05
22'-6"
WATER QUALITY, RE: CIVIL
2-06 19'-7"
5'
1-01
5'-5"
29'-3" 20'
TRELLIS SCREEN, RE: ARCHITECTURE RAINGARDEN, RE: CIVIL
23'-4"
MARINE STREET
LEVEL SPREADER, RE: CIVIL PRIVATE PATIO, RE: ARCHITECTURE GARAGE PEDESTRIAN ENTRANCE MAINTENANCE PAD
7-01
GARAGE BIKE/AUTO ENTRANCE
1-02 RAINGARDEN, RE: CIVIL
KEY MAP
LX202 LX201
150'-1"
476'-7"
1
LANDSCAPE SITE PLAN
0
1" = 30'-0"
SCALE: 1" = 30'-0"
15'
30'
60'
LX101
SCALE: N.T.S.
NORTH NORTH
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW
GROUND FLOOR SITE PLAN
07.29.2026
LS101
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
REFERENCE NOTES SCHEDULE CODE
LA OUT LEGEND
DESCRIPTION
2 - WALLS & FENCES 2-04
LANDSCAPE PLANTER
ARAPAHOE AVENUE
ARAPAHOE OPERATIONS
RELOCATED ARAPAHOE HOUSE RELOCATED CHESTNUT HOUSE
5BR/3BA FLAT
5BR/5BA TOWNHOUSE
5BR/5BA TOWNHOUSE
5BR/5BA TOWNHOUSE
6BR/6BA TOWNHOUSE
5BR/5BA TOWNHOUSE
5BR/5BA TOWNHOUSE
5BR/5BA TOWNHOUSE
6BR/6BA TOWNHOUSE
6BR/6BA TOWNHOUSE
5BR/4BA FLAT
STAIR
LINCOLN HALL5BR/4BA FLAT
5BR/4BA FLAT
CORR. ELEV.
ELEV.
5BR/3BA FLAT
5BR/4BA TOWNHOUSE 4BR/2BA FLAT
4BR/3BA FLAT
MULTI-USE PATH
5BR/4BA FLAT
5BR/4BA FLAT 5BR/5BA TOWNHOUSE CORR.
UP STAIR DN
5BR/4BA FLAT D.O. 4BR/2BA FLAT
2-04
5BR/5BA FLAT
5BR/5BA FLAT
5BR/5BA FLAT
4BR/4BA FLAT
5BR/5BA FLAT
B.O.H.
CORR.
5BR/4BA FLAT
5BR/5BA FLAT
5BR/5BA FLAT
5BR/5BA FLAT
5BR/5BA FLAT
5BR/5BA FLAT
5BR/4BA TOWNHOUSE
5BR/4BA FLAT
TRASH
2BR/2BA FLAT
STAIR
5BR/5BA TOWNHOUSE
CORR.
D.O. 4BR/2BA FLAT
4BR/4BA FLAT
CORR.
PRIVATE DECK TOPPING RE: ARCHITECTURE PATIO HOT TUB RE: ARCHITECTURE PATIO PARTITIONS RE: ARCHITECTURE
4BR/4BA FLAT
D.O. 4BR/2BA FLAT
CORR.
B.O.H.
5BR/5BA TOWNHOUSE
5BR/4BA TOWNHOUSE
6BR/5BA TOWNHOUSE
6BR/5BA TOWNHOUSE
5BR/4BA TOWNHOUSE
5BR/4BA TOWNHOUSE
5BR/5BA TOWNHOUSE
4BR/2BA FLAT
MARINE STREET
KEY MAP
LX202 LX201
1
SECOND FLOOR SITE PLAN
0
1" = 30'-0"
SCALE: 1" = 30'-0"
15'
30'
60'
LX101
SCALE: N.T.S.
NORTH NORTH
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW
SECOND FLOOR SITE PLAN
07.29.2026
LS102
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
REFERENCE NOTES SCHEDULE CODE
LAYOUT LEGEND
DESCRIPTION
2 - WALLS & FENCES 2-04 CODE
ARAPAHOE AVENUE
LANDSCAPE PLANTER DESCRIPTION
5 - FURNISHINGS 5-07 5-12 5-17
5-13
5-15 4TH FLOOR PRIVATE PATIO RE: ARCHITECTURE
5-13
5-15 5-16
5-16
5-17
4TH FLOOR STRUCTURE RE: ARCHITECTURE 4TH FLOOR SPA RE: ARCHITECTURE
5-07 4TH FLOOR POOL RE: ARCHITECTURE
CAFE TABLE AND CHAIRS CHAISE LOUNGE LOUNGE CHAIR HARVEST TABLE FIREPIT OUTDOOR KITCHEN
2-04 FINAL FURNISHINGS TO BE DETERMINED
5-12 2-04
MULTI-USE PATH
LINCOLN HALL
AMENITY DECK TOPPING
MARINE STREET
KEY MAP
LX202 LX201
1
FOURTH FLOOR SITE PLAN
0
1" = 30'-0"
SCALE: 1" = 30'-0"
15'
30'
60'
LX101
SCALE: N.T.S.
NORTH NORTH
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW
FOURTH FLOOR SITE PLAN
07.29.2026
LS103
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
CODE
DESCRIPTION
LAYOUT LEGEND
1 - PAVING & SURFACING 1-02 1-03 1-04 1-06 1-09
3-01
1-10
1-04 5-01
COLORED CONCRETE UNIT PAVERS STAIRS CONCRETE RAMP 2 OR LESS STAIRS CONCRETE CURB (SEE CIVIL)
2 - WALLS & FENCES
5-06
2-02 2-04
2-04 3-03
PLANTER BENCH LANDSCAPE PLANTER
3 - METALS
1-02
3-01 1-06
3-03
STAIR HANDRAIL STEEL EDGER
1-09
5 - FURNISHINGS 5-01 2-02
5-06
BENCH BIKE RACK
2-04
1-04
1-03
3 LS301
1-10 2-04 WATER QUALITY, RE: CIVIL
1-03
5-06
KEY MAP
LX202 LX201
1
BUILDING ENTRY ENLARGEMENT
0
1" = 10'-0"
SCALE: 1" = 10'-0"
5'
10'
20'
LX101
SCALE: N.T.S.
NORTH NORTH
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW
ENLARGEMENT PLAN
07.29.2026
LS201
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
LA OUT LEGEND 5-03 3-03
5-01 1-08 5-02 6-01 2-02 2-04
3-01
5-06
1-04
5-03
3-02
1-01
1-06
5-02 EXISTING WALL TO REMAIN EXISTING BRICK WALK TO REMAIN EXISTING TREE TO REMAIN 5-07 5-04 5-01 1-08
7-02 5-07 5-02 1-04 3-01 2-01 1-02 5-06 1-01 EXISTING CHAMPION TREES GAME LAWN PRIVATE PATIO
1
COURTYARD ENLARGEMENT
0
1" = 10'-0"
SCALE: 1" = 10'-0"
5'
10'
20'
NORTH
CODE
1 - PAVING & SURFACING 1-01 1-02 1-04 1-06 1-08
KEY MAP
DESCRIPTION
CONCERETE PAVING (SEE CIVIL) COLORED CONCRETE STAIRS CONCRETE RAMP STONE STEPPERS
2 - WALLS & FENCES 2-01 2-02 2-04
CONCRETE SEAT STEPS PLANTER BENCH LANDSCAPE PLANTER
3 - METALS 3-01 3-02 3-03
5 - FURNISHINGS STAIR HANDRAIL RAMP HANDRAIL STEEL EDGER
5-01 5-02 5-03 5-04 5-06 5-07
BENCH CIRCULAR BENCH EGG CHAIR
6 - PLUMBING 6-01
CHASE DRAIN WITH STONE COVER LX202 LX201
7 - ELECTRICAL 7-02
TIVOLI LIGHT STRING AND POST
HAMMOCK AND POST BIKE RACK
LX101
SCALE: N.T.S.
CAFE TABLE AND CHAIRS NORTH
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW
ENLARGEMENT PLAN
07.29.2026
LS202
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
07.29.2026
1 4" 1 2"
NOTE: PRE-MIX CRUSHER FINES WITH STABILIZER AND WATER TO MANUFACTURER'S RECOMMENDATION PRIOR TO INSTALLATION AND COMPACTION. COMPACT PREMIXED CRUSHER FINES AND ADJACENT PAVING STABILIZER IN (2) - 2" LIFTS TO 95% SPD
AGGREGATE BASE COURSE, COMPACT TO 95% SPD
AS APPROVED BY LANDSCAPE ARCHITECT
AS APPROVED BY LANDSCAPE ARCHITECT
CONCRETE PAVING (PEDESTRIAN)
2
1" = 1'-0"
SAND FINISH CONCRETE PAVING
EXPANSION, CONTROL, & DECORATIVE JOINTS
3
1" = 1'-0"
1 1/2" = 1'-0"
SAND SETTING BED UNIT PAVERS 1" - 121" 3" MIN. 28
UNDISTURBED SUBGRADE
PAVER EDGE RESTRAINT, RE: SPECS. INSTALL PER MANUFACTURER'S RECOMMENDATION
1.8% MAX. CROSS SLOPE
8" TYP.
GEOTEXTILE FABRIC, TURN UP AT SIDES AT CURBS, CONCRETE BANDS OR PLANTING AREAS AGGREGATE BASE COURSE, COMPACT TO 95% SPD
6"
1" - 121"
6"
COMPACT SUBGRADE TO 95% SPD
AGGREGATE BASE COURSE, COMPACT TO 95% SPD
VARIES RE: PLANS 1 4"
SAND SETTING BED
CRUSHER FINES, RE: DETAILS 8" MIN
1 8" SAND SWEPT JOINTS
8"
1" = 1'-0"
3 8" RADIUS, ALL TOP EDGES
2 83" MIN. FOR
STEPPER ADJACENT SURFACE, RE: MATERIAL PLANS CLASS 6 ROAD BASE
EDGING
COMPACT SUBGRADE, RE: SPECS
SPLICING STEEL STAKE, 14" LONG MIN., 30" O.C.
1 8" x 6" DEEP HOT ROLLED STEEL
NOTES: 1.
ADJACENT CONDITION SOD, GRAVEL, ETC.
SAW CUT SCORE JOINTS INTO CONCRETE CURB @ 10' O.C.
PLANTING AREA
COMPACT SUBGRADE TO 95% SPD
COMPACT SUBGRADE TO 95% SPD
6
GEOTEXTILE FABRIC, TURN UP AT SIDES AT CURBS, CONCRETE BANDS OR PLANTING AREAS
CONCRETE CURB
7
1" = 1'-0"
STONE STEPPER 1" = 1'-0"
8
STEEL EDGER 1 1/2" = 1'-0"
WITH PAVER EDGE RESTRAINT
UNIT PAVERS ON SAND BASE
HANDRAIL
3 4"
CONCRETE STEPS WITH SAND FINISH, SEE PLAN FOR NUMBER OF RISERS
1'
1'-6"
2' TYP.
6" 10"
FINISH GRADE
1'
2% MIN.
10
EXPANSION JOINT COMPACTED SUBGRADE #4 REBAR
CONCRETE STEPS - 2 TREADS OR LESS 1/2" = 1'-0"
8"
11
5'
3" MIN. CLR, TYP.
3'
SCALE: 1"=1'-0"
#4 REBAR AT 12" O.C. EACH WAY #4 REBAR AT STAIR NOSE, MIN 3" CLEAR COMPACT SUBGRADE TO 95% SPD
1/2" = 1'-0"
1'-6"
1.8%
11"
CONCRETE STAIRS
5 " R 16
2'
1"
TYP.
6"
12" TREAD
1 8"/FT
3'
ADJACENT CONCRETE PAVING
SECTION FOR STEPS 2 TREADS OR LESS
1'
EXPANSION JOINT, TYP.
EXPANSION JOINT, TYP.
6"
+/- 6" RE: GRADING PLAN
1" = 1'-0"
1 2" RADIUS, TYP.
9
CRUSHER FINES PAVING
#5 HORIZONTAL REBAR, CONTINUOUS, CENTERED IN BAND.
UNIT PAVERS
5
GEOTEXTILE FABRIC, TURN UP AT EDGES
MULCH - FLUSH WITH TOP OF EDGE
1 8" SAND SWEPT JOINTS
ADJACENT TO CONCRETE
4
6" STEEL EDGING, FLUSH WITH GRADE
TOP OF EDGER, FLUSH WITH ADJACENT SIDEWALKS UNLESS OTHERWISE NOTED
CONCRETE PAVING WITH THICKENED EDGE
1' MIN.
AGGREGATE BASE COURSE, COMPACT TO 95% SPD
DECORATIVE JOINT
NOTE: 1. WHERE PAVERS MEET CONCRETE PAVING: TOP OF PAVER SURFACE SHALL BE FLUSH WITH TOP OF CONCRETE SURFACE
1.8% MAX. CROSS SLOPE
1.8% MAX. CROSS SLOPE
NOTES: 1. ALL EDGES: 41" RADIUS TOOLED EDGE, TYP. 2. PROVIDE 1.5% SLOPE MIN. UNLESS OTHERWISE NOTED ON THE GRADING PLAN. MAX 1.8% CROSS SLOPE. 3. EXPANSION JOINTS AT 30'-0" O.C. MAXIMUM, AT SIDEWALK INTERSECTIONS AND WHERE CONCRETE PAVING ABUTS STRUCTURES, UNLESS OTHERWISE NOTED. 4. SEE LAYOUT PLAN FOR EXPANSION AND CONTROL JOINT LOCATIONS. CONTROL JOINT
PEDESTRIAN, 3 41" MIN. FOR VEHICULAR
2'-0"
1 " 2
1 4" WIDE SAW-CUT JOINT
4"
1 4" WIDE SAW-CUT JOINT
6"
COMPACT SUBGRADE TO 95% SPD
EXPANSION JOINT
SIDE SLOPE 3:1 MAX
1 2"
FIBER REINFORCED MESH AGGREGATE BASE COURSE, COMPACT TO 95% SPD
PREFORMED EXP. JOINT MATERIAL W/ SNAP-CAP
3" 3"
1
4"
SEPARATION BETWEEN FINISHED SURFACES. ADJUST PLANTING SOIL MIX AS REQUIRED. WELDED WIRE MESH
NOTES: 1. PROVIDE 1.5% SLOPE MIN. UNLESS OTHERWISE NOTED. MAX 1.8% CROSS SLOPE. 2. EXPANSION JOINTS AT 30'-0" O.C. MAXIMUM, AT SIDEWALK INTERSECTIONS AND WHERE CONCRETE PAVING ABUTS STRUCTURES, UNLESS OTHERWISE NOTED. 3. CONTROL JOINTS AT 6'-0" O.C. MAXIMUM. 4. SEE PLAN FOR EXPANSION AND CONTROL JOINT LOCATIONS.
1 2"
12" MIN.
1/3 OF CONCRETE DEPTH
1 2" VERTICAL
COMPACT SUBGRADE TO 95% SPD
R 1" 4
SEALANT 41" BELOW SURFACE, COLOR TO BE APPROVED BY LANDSCAPE ARCHITECT.
4" MIN. CONCRETE PAVING, INTEGRAL COLOR, SAND FINISH, RE: SPECS
4"
4"
VARIES - SEE LAYOUT PLAN
6" MIN.
CONCRETE PAVING, SEE PLANS AND SPECS FOR FINISH AND COLOR 1 4" RADIUS TOOLED EDGE PLANTED AREA / TURF F.G.
CONCRETE SEAT STEPS SECTION 1/2" = 1'-0"
12
STAIR HANDRAIL 1" = 1'-0"
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW
SITE DETAILS
07.29.2026
LS501
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
NOTES: 1. HANDRAIL AND RAMP TO COMPLY WITH CURRENT ADA STANDARDS. 2. CONTRACTOR TO PREPARE HANDRAIL SHOP DRAWINGS FOR REVIEW AND APPROVAL BY LANDSCAPE ARCHITECT PRIOR TO FABRICATION THAT MEET ADA GUIDELINES.
7" MIN.
6"
4" MIN.
CONCRETE THICKENED EDGE
2 VARIES, RE GRADING PLAN
ADJACENT SURFACE, SEE PLANS 2' 24" WIDE CUT SANDSTONE, 6' LENGTH TYP. GUILLOTINE CUT ALL SIDES. RE: PLANS FOR LAYOUT
EXPANSION JOINT
2'
1'-6"
COMPACT ANGULAR GRAVEL TO 95% SPD
6"
HANDRAIL AT RAMP 1" = 1'-0"
C.I.P CONCRETE WALL, BOARD FORM FINISH 1 2" RADIUS ALL EDGES 4" MIN. WOOD MULCH
8" 3" MIN.
8"
PLANTING SOIL CONCRETE RAMP CAST IN 2"X.5" JOINTS ON FACE AND TOP @ 3' O.C., TYP.
ADJACENT PLANTING AREA WITHIN PLANTER
#5 REBAR, CONT. W/ #5 REBAR TIE 16" O.C.
FILTER FABRIC, TURN UP 2" 6'
6"
1/2" MORTAR JOINT TYP. IN ALL LOCATIONS WHERE STONE CAP PIECE ABUTS CONCRETE OR ANOTHER CAP
1'-9"
2'
TYPICAL SECTION
3"
(2) #6 CONT. #5 @ 18" EA. FACE (2) #6 CONT. 1'-6"
SANDSTONE BENCH 3/4" = 1'-0"
4
3/4" = 1'-0"
1'-221"
SANTOPRENE NO-SCRATCH
CMU PLANTER WALL
2'
1121"
2"
1) CORE DRILL 3" DIA MIN. HOLES 10" DEEP 2) PREPARE HOLES WITH ANCHORING CEMENT SUCH AS KWIXSET OR SUPER POR-ROK. 3) FOLLOW MANUFACTURERS DIRECTIONS REGARDING BLOWING OUT DUST AND REMOVING ANY EXCESS WATER 4) PLACE BIKE RACK INTO CORRECT LOCATION AND ADD ANCHORING CEMENT 5) WIPE AWAY EXCESS BEFORE IT HARDENS
1'-6"
AGGREGATED BASE COURSE, COMPACT TO 95% SPD CONCRETE FOOTING PER STRUCTURAL DWGS.
RECESSED LED LIGHTING 2"x4" SELECT REDWOOD GRADE A
7
ANCHOR STEEL FRAME INTO CMU WALL
3/4" = 1'-0"
(0.469" DIA) 2x FOR 83" REBAR 6"
STEEL FRAME
CUSTOM PLANTER BENCH - CMU WALL
1'-2"
4"
1'-6"
3"
NOTES:
221"
PLAN
BUILT IN SEAT - 2"x6" SELECT REDWOOD GRADE A
ADJACENT CRUSHER FINES PAVING GEOTEXTILE FABRIC, TURN UP AT EDGES
6"
NOTES: 1. CONTRACTOR SHALL SUBMIT FULL SHOP DRAWINGS FOR LANDSCAPE ARCHITECT REVIEW AND APPROVAL PRIOR TO FABRICATION. 2. CONTRACTOR SHALL HAVE SHOP DRAWINGS REVIEWED AND APPROVED BY LICENSED STRUCTURAL ENGINEER.
NOT TO SCALE
1/2" = 1'-0"
TAPERED 14' TALL TIVOLI LIGHT POLE, RE: ELEC DWGS
BASE PLATE WITH ANCHOR BOLTS
CONCRETE SEATWALL WITH BENCH TOP
5
POWDER COATED BLACK, SW 6993
CONDUIT CONNECTION, RE: ELEC DWGS
TIVOLI STRING LIGHT
BUILT IN CONCRETE PLANTER
2'-9"
ANGLED TOP
NOTES: STRING LIGHT COLOR: WARM WHITE (2700 KELVIN) LIGHT SPACING: 12"
6
(3) #6 CONT.
3"
2'
2'-9"
3
1'-9"' WIDE X 3" THICK SANDSTONE CAP
1'-6" MIN.
C.I.P. CONCRETE FOOTER COMPACT SUBGRADE TO 95% SPD
SECTION PLAN
1" 12
1'
1'
3" MIN
WATERPROOF BACK SIDE OF WALL
1'-6" TYP
3' MIN.
EXPANSION JOINT, TYP.
1'-3"
UNDISTURBED SUBGRADE
1/2" = 1'-0"
COMPACT SUB-GRADE TO 95% SPD
E
THICKENED EDGE CONCRETE AT TOP AND BOTTOM OF RAMP, TYP. 12" SLIP DOWEL WITH EXPANSION JOINT, TYP.
COMPACT SUBGRADE TO 95% SPD
COMPACT SUBGRADE TO 95% SPD
CONCRETE RAMP
INTERMEDIATE POSTS
12:1 MAX SLOP
1'-6"
CONCRETE THICKENED EDGE (TYP)
2'
ADJACENT PAVING, SEE PLANS.
ADJACENT SURFACE, SEE PLANS
12:1 MAX
1
2" MIN. EDGE OF CONCRETE TO HANDRAIL BASEPLATE, ALL SIDES, TYP.
EXTEND HANDRAIL 12" BEYOND TOP AND BOTTOM OF RAMP
BOTTOM OF RAMP
EQ.
CONCRETE PAVEMENT
12" SLIP DOWEL WITH 1 2" EXPANSION JOINT
CONTINUOUS 3', TYP.
EQ.
1'
1'
TOP OF RAMP
EQ.
SLOPE HANDRAIL TO MATCH SLOPE OF PAVEMENT
ELEVATION
8
6" (6" DIA) CONCRETE FOOTER, CORE DRILLED
ISOMETRIC VIEW
MANUFACTURER: SPORTWORKS, INC. PRODUCT: WESTPORT NO SCRATCH, EMBEDDED BIKE RACK SIZE: 14.5"L x 3"W x 33"H COLOR/FINISH: STAINLESS STEEL QUANTITY: REFER TO DRAWINGS SPACING: 2'-6" O.C. TYPICAL CONTACT: 1.888.661.0555
BIKE RACK - WESTPORT NO SCRATCH, EMBEDDED 3/4" = 1'-0"
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW
SITE DETAILS
07.29.2026
LS502
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
PLANTING NOTES 1. All plant materials shall meet or exceed current American Standard for Nursery Stock (ANSI Z60.1-2004) and the Colorado Nursery Act and accompanying Rules and Regulations.
12. See details and specifications for staking method, plant pit dimensions, and backfill requirements.
23. Contractor is to familiarize themself with the layout, grading, and civil engineering documents to coordinate actual location of trees and shrubs.
2. All plants will be balled and burlapped or container grown. Bare root or spaded plants will not be accepted. 3. Supply all plant material in quantities sufficient to complete the planting bed as shown on the drawings.
13. Landscape Contractor shall provide per-unit costs for every size of plant materials, and by type, as called out on planting plans. Unit cost to include the plant material itself and installation, including all labor, amendments, fertilizers, etc., as detailed and specified for each size.
4. All plants will be inspected and approved by the Owner's Representative prior to delivery to the site.
14. Landscape Contractor is responsible to do their own quantity takeoffs for all plant materials and sizes shown on plans.
24. Maintenance Statement: All landscaping shown on this plan shall be maintained in a neat and adequate manner. Required maintenance activities shall include, but not limited to, mowing of lawns, trimming of hedges, adequate irrigation, replacement of dead, diseased or unsightly landscaping, removal of weeds from planted areas, and appropriate pruning of plant materials.
5. Any proposed substitutions of plant species shall be approved by the Landscape Architect prior to delivery to the site.
15. The Landscape Contractor shall be responsible for positive drainage throughout the site with accurately set flow lines. No low spots or ponding of surface water will be accepted in final work.
6. Obtain Landscape Architects approval of finish grading prior to the start of planting.
16. Coordinate installation of large plant material with installation of wall footings, bridge abutments and pavements. Any damage to improvements by others is the responsibility of the Landscape Contractor.
7. Stake locations of all proposed trees and edges of new planting beds for approval by the Landscape Architect 48 hours prior to the commencement of planting. 8. Landscape Contractor shall be responsible for becoming aware of all underground utilities, pipes, and structures. The Landscape Contractor shall be held responsible for contacting all utility companies for field location of underground utility lines prior to any excavation. Landscape Contractor shall take sole responsibility for any cost of utility repair due to damage caused by his operations.
17. The Landscape Contractor shall allow for the addition of specified quantities of soil amendments, conditioners and mulch in soil preparation and finish grading.
9. Do not willfully proceed with construction as designed when it is obvious that unknown obstructions and/or grade differences exist that may not have been known during design. Such conditions shall be immediately brought to the attention of the Landscape Architect. The Landscape Contractor shall assume full responsibility for all necessary revisions due to failure to give such notification.
19. The Landscape Contractor shall verify soil test at his expense prior to planting and will follow test recommendations and Landscape Architect's approval for soil amendments.
18. Imported soil shall be used to supplement the existing soil as necessary to meet the finish grade requirements at planting areas.
21. The Landscape Contractor shall be responsible to furnish and install amended or imported soil in any planting areas as necessary to achieve the specified finish planting grades unless otherwise noted on plans or specs. 22. The Landscape Architect reserves the right to adjust the location of plant material during installation as appropriate to the project. For trees in the right-of-way by Builder or Contractor, adjustments of 5'-0" or more must have prior authorization of Landscape Architect.
11. See specifications for planting requirements, soil preparation testing, materials, and execution. Arrange for visit of Landscape Architect for review and approval a minimum of 48 hours prior to installation.
26. Take all dimensions perpendicular to any reference line, centerline, or back of curb. 27. Written dimensions supersede scaled dimensions. Do not scale drawings, if there is a question regarding dimension, contact Landscape Architect for verification. 28. All landscaped areas shall be irrigated with an automatic irrigation system. Lawn areas will be sprayed and shrubs will be drip irrigated. Natural areas, such as those with prairie types of grasses and native shrub species, are designed to irrigate through grow-in and then be shut off except during severe drought. Contractor shall be responsible for taps, backflow prevention and winterization systems, sleeving under paved areas and all sprinkler system components necessary for a fully functional system. Trees shall be on a separate zone from turf. 29. Street Trees shall be placed 5'-0" min from buried utilities.
20. The Landscape Contractor shall receive the specified subgrade elevation, of +/- one tenth of a foot below finish grade.
10. Landscape Contractor shall be responsible for any coordination with subcontractors as required to accomplish planting operations.
25. Take dimensions from back of curb, center line of trees, and centerline of light pole bases, unless otherwise noted.
30. All proposed landscaping in the right-of-way shall be per City Standards. Trees to be in accordance with current City Standards including approved species; family, genus and species, quantity and percentage limits; and limitations on the quantity of same-species trees in a row. Installation of trees in right-of-way to be per City detail. 31. Proposed trees in the right-of-way shall be pre-approved by the Landscape Architect and shall be a minimum of 20' from property corners at intersections, 20' from street lights, outside of 30' corner sight triangles and 10' from edge of driveways, alleys and hydrants.
PLANT SCHEDULE SYMBOL
CODE
QTY
BOTANICAL / COMMON NAME
CONT
WATER USE
TREES
SHRUBS ACE SNS
AME SHD
AME UTA
BET OCC
CAT WES
CER EAS
CRA CHR
EXI COX
GLE LOC
GYM KYC
6
ACER NEGUNDO 'SENSATION' SENSATION BOX ELDER
4
AMELANCHIER CANADENSIS SHADBLOW SERVICEBERRY
8
AMELANCHIER UTAHENSIS UTAH SERVICEBERRY
4
BETULA OCCIDENTALIS WATER BIRCH (30'HT)
3
CATALPA SPECIOSA WESTERN CATALPA (65'HT)
1
CERCIS CANADENSIS EASTERN REDBUD MULTI-TRUNK (25'HT)
2.5" CAL
2" CAL.
2" CAL
2.5" CAL
2.5" CAL
CRATAEGUS CHRYSOCARPA FIREBERRY HAWTHORN
11
EXI EXISTING TREE PROTECT IN PLACE
VARIES
GLEDITSIA TRIACANTHOS INERMIS 'SHADEMASTER' SHADEMASTER HONEYLOCUST (50'HT.)
2.5" CAL
GYMNOCLADUS DIOICUS ESPRESSO KENTUCKY COFFEETREE (SEEDLESS, 55'HT)
2.5" CAL
2
AMO NAN
146
ARC MAN
116
ARCTOSTAPHYLOS X COLORADENSIS MOCK BEARBERRY MANZANITA (1'HT)
5 GAL
LOW - MEDIUM LOW
CLE SWA
18
CLEMATIS TERNIFLORA CLEMATIS `SWEET AUTUMN`
5 GAL
LOW
ATR CAN
12
ATRIPLEX CANESCENS FOURWING SALTBUSH
5 GAL
VERY LOW LOW MEDIUM
LON HON
15
LONICERA PERICLYMENUM WOODBINE
5 GAL
LOW LOW - MEDIUM
CER WES
7
8` HT.
VERY LOW LOW MEDIUM
PAR QUI
4
PARTHENOCISSUS QUINQUEFOLIA VIRGINIA CREEPER
5 GAL
LOW LOW - MEDIUM
CHA FER
37
5 GAL
VERY LOW LOW LOW
ERI AIH
83
5 GAL
VERY LOW LOW LOW
EXT SHR
117
EXISTING SHRUB MIX
EXISTING
MAH REP
543
CODE
QTY
BOTANICAL / COMMON NAME
POT CIN
11
TUR BLU
8,792 SF
BLUEGRASS LAWN
55
NAT SHO
2,840 SF
NAT DET
11,627 SF
MEDIUM LOW
MEDIUM LOW
LOW - MEDIUM LOW
MEDIUM HIGH MEDIUM
MEDIUM -LOW HIGH
PRU PAW 8` CLUMP
1
5
VINES AMORPHA NANA DWARF LEADPLANT (2-3')
MEDIUMMEDIUM
2" CAL.
LOW
N/A
LOW - MEDIUM LOW
MAL THU
11
PIN BRI
4
PINUS ARISTATA BRISTLECONE PINE
PIN EDU
6
PINUS EDULIS PINYON PINE
8` HT
LOW
PRU CHO
4
PRUNUS VIRGINIANA SUCKER PUNCH SUCKER PUNCH CHOKECHERRY (25'HT)
2" CAL.
VERY LOW - MEDIUM MEDIUM
4
PYRUS CALLERYANA 'AUTUMN BLAZE' AUTUMN BLAZE CALLERY PEAR (30'HT)
13
QUERCUS GAMBELII GAMBEL OAK
2" CAL.
MEDIUM LOW
8` HT
LOW
ERICAMERIA NAUSEOSA SSP. NAUSEOSA DWARF BLUE RABBITBRUSH MAHONIA REPENS CREEPING OREGON GRAPE (1'HT)
MEDIUM LOW
CAM TRU
15
CAMPSIS RADICANS TRUMPET VINE
5 GAL
LOW LOW - MEDIUM
5 GAL
LOW
POTENTILLA FRUTICOSA SHRUBBY CINQUEFOIL (3'HT)
5 GAL
MEDIUM LOW
PRUNUS PUMILA VAR. BESSEYI SAND CHERRY (2'HT)
5 GAL
LOW
5 GAL
LOW VERY LOW LOW
5 GAL
LOW VERY LOW LOW
RHUS AROMATICA 'AUTUMN AMBER' FRAGRANT SUMAC RHUS GLABRA SMOOTH SUMAC (3'HT)
LOW
RHU ARO
54
RHU SMO
71
SYM SNO
90
SYMPHORICARPOS ALBUS COMMON SNOWBERRY (4'HT)
5 GAL
LOW
VER REA
228
VERONICA X 'REAVIS' CRYSTAL RIVER VERONICA
5 GAL
LOW - MEDIUM LOW
ACH HYM
173
1 GAL
LOW
LOW
BOU BLO
276
1 GAL
LOW
LOW
SOR NUT
225
1 GAL
LOW - MEDIUM LOW
SOR IND
44
1 GAL
LOW - MEDIUM LOW
SPO HET
126
SPOROBOLUS HETEROLEPIS PRAIRIE DROPSEED
1 GAL
LOW
LOW
LOW
LOW
SHRUB AREAS
SYMBOL
LOW MEDIUM WATER USE
GROUND COVERS
NATIVE SEED MIX SHORTGRASS AREA NATIVE SEED MIX DETENTION AREA
HIGH LOW LOW
GRASSES
MEDIUM LOW
MALUS 'THUNDERCHILD' THUNDERCHILD CRABAPPLE (20'HT)
CERCIS OCCIDENTALIS WESTERN REDBUD MULTI-TRUNK CHAMAEBATIARIA MILLEFOLIUM FERNBUSH (5'HT)
5 GAL
MEDIUM
ACHNATHERUM HYMENOIDES INDIAN RICEGRASS BOUTELOUA GRACILIS 'BLONDE AMBITION' BLONDE AMBITION BLUE GRAMA (2'HT) SORGHASTRUM NUTANS INDIAN GRASS SORGHASTRUM NUTANS INDIAN GRASS (5'HT)
PERENNIAL WATER QUALITY MEDIUM
MUH GM3
135
MUHLENBERGIA REVERCHONII UNDAUNTED ROSE MUHLY GRASS PUND01S
1 GAL
RAT CO3
119
RATIBIDA COLUMNIFERA PRAIRIE CONEFLOWER
1 GAL
ACH YAR
11
ACHILLEA MILLEFOLIUM COMMON YARROW 'TERRA COTTA' (2'HT)
1 GAL
GAI ARI
36
GAILLARDIA ARISTATA BLANKET FLOWER
1 GAL
PHL CAS
19
PHLOMIS CASHMERIANA CASHMERE SAGE
1 GAL
RAT COL
36
RATIBIDA COLUMNIFERA PRAIRIE CONEFLOWER
1 GAL
LOW
SAL GAR
15
SALVIA OFFICINALIS GARDEN SAGE
1 GAL
LOW LOW - MEDIUM
AMO FR3
54
AMORPHA FRUTICOSA VAR. ANGUSTIFOLIA FALSE INDIGO
5 GAL
LOW - MEDIUM LOW
PRU BE3
43
PRUNUS PUMILA VAR. BESSEYI SAND CHERRY
5 GAL
LOW
LOW
PERENNIALS PYR AUT
QUE GA2
2.5" CAL
2.5" CAL
LOW - MEDIUM MEDIUM
LOW - MEDIUM LOW
LOW
LOW LOW
LOW
LOW
SHRUBS WATER QUALITY
LOW
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW
PLANTING SCHEDULE AND NOTES
07.29.2026
LP100
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
LAYOUT LEGEND PLANT SCHEDULE SYMBOL
CODE
QTY SHRUBS
TREES ACE SNS
AME ALN EXISTING TREE TO REMAIN EXISTING TREE TO REMAIN EXISTING DITCH TO REMAIN
AME SHD
3
EXISTING TREES TO REMAIN DETENTION, RE: CIVIL WATER QUALITY, RE: CIVIL RELOCATED ARAPAHOE HOUSE RELOCATED CHESTNUT HOUSE
DETENTION, RE: CIVIL WATER QUALITY, RE: CIVIL EXISTING MULTI-USE PATH TRANSFORMER
AME UTA
8
BET OCC
4
CAT WES
CER EAS
CRA CHR
EXISTING WALLS TO REMAIN
PRIVATE DRIVE
EXI COX
3
1
EXISTING CHAMPION TREES
GLE LOC
GYM KYC
MAL THU
MULTI-USE PATH
DETENTION, RE: CIVIL WATER QUALITY, RE: CIVIL
11
TRANSFORMERS
11
PIN EDU
6
QUE GA2
ATR CAN
12
BER LYR
20
CER WES
7
CHA FER
37
COR DOG
14
ERI AIH
83
ERI BUC
21
LYS NUM
83
MAH REP
571
POT CIN
11
PRU PAW
55
RHU ARO
54
RHU SMO
71
SYM SNO
90
SYR LIL
10
VER REA
228
2
4
PYR AUT
116
5
PIN BRI
PRU CHO
ARC MAN
1
LINCOLN HALL
MAIN BUILDING ENTRY
146
4
ARAPAHOE AVENUE BUS STOP
AMO NAN
6
GRASSES
VINES ACH HYM
173
CAM TRU
15
BOU BLO
297
CLE SWA
18
CAL KOR
28
LON HON
15
SOR NUT
225
PAR QUI
4
SOR IND
44
SPO HET
126
SPO DRO
20
4
4
13 PERENNIAL WATER QUALITY MUH GM3
WATER QUALITY, RE: CIVIL
RAT CO3
SHRUB AREAS
SYMBOL
EXT SHR
117
CODE
QTY
GROUND COVERS TUR BLU
8,792 SF
NAT SHO
2,840 SF
NAT DET
11,627 SF
135 119
PERENNIALS ACH YAR
11
GAI ARI
36
HEU SNO
48
PHL CAS
19
RAT COL
36
SAL GAR
15
MARINE STREET TRELLIS SCREEN, RE: ARCHITECTURE DETENTION, RE: CIVIL
PRIVATE PATIO, RE: ARCHITECTURE GARAGE PEDESTRIAN ENTRANCE MAINTENANCE PAD GARAGE BIKE/AUTO ENTRANCE
WATER QUALITY, RE: CIVIL
KEY MAP
LX202
1
LANDSCAPE PLANTING PLAN
0
1" = 30'-0"
SCALE: 1" = 30'-0"
NORTH
15'
30'
60'
LX201
SHRUBS WATER QUALITY AMO FR3
54
PRU BE3
43
LX101
NORTH
SCALE: N.T.S.
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW
GROUND FLOOR PLANTING PLAN
07.29.2026
LP101
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
ARAPAHOE AVENUE
PLANT SCHEDULE SECOND FLOOR
RELOCATED ARAPAHOE HOUSE RELOCATED CHESTNUT HOUSE
SYMBOL
CODE
QTY
BOTANICAL / COMMON NAME
CONT
COR DOG
14
CORNUS SERICEA 'ARCTIC FIRE' ARCTIC FIRE DOGWOOD (3'HT)
5 GAL
ERI BUC
21
ERIOGONUM WRIGHTII VAR. WRIGHTII WRIGHT'S BUCKWHEAT (20"HT)
5 GAL
LYS NUM
66
LYSIMACHIA NUMMULARIA CREEPING JENNY (4")
1 GAL
MAH REP
28
MAHONIA REPENS CREEPING MAHONIA (1'HT)
1 GAL
SYR LIL
6
SYRINGA MEYERI 'PALIBIN' DWARF KOREAN LILAC (4'HT)
5 GAL
CAL KOR
28
CALAMAGROSTIS BRACHYTRICHA KOREAN FEATHER REED GRASS (3'HT)
1 GAL
SPO DRO
20
SPOROBOLUS HETEROLEPIS PRAIRIE DROPSEED (28"HT)
1 GAL
48
HEUCHERA SANGUINEA 'SNOW ANGEL' 1 GAL SNOW ANGEL CORAL BELLS (6-15"HT)
SHRUBS
MULTI-USE PATH
LINCOLN HALL
GRASSES UP DN
PERENNIALS HEU SNO
PRIVATE DECK TOPPING RE: ARCHITECTURE PATIO HOT TUB RE: ARCHITECTURE PATIO PARTITIONS RE: ARCHITECTURE
MARINE STREET
KEY MAP
LX202 LX201
1
SECOND FLOOR PLANTING PLAN
0
1" = 30'-0"
SCALE: 1" = 30'-0"
15'
30'
60'
LX101
SCALE: N.T.S.
NORTH NORTH
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW
SECOND FLOOR PLANTING PLAN
07.29.2026
LP102
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
ARAPAHOE AVENUE
PLANT SCHEDULE FOURTH FLOOR SYMBOL
CODE
QTY
BOTANICAL / COMMON NAME
CONT
AME ALN
3
AMELANCHIER ALNIFOLIA SASKATOON SERVICEBERRY (10'HT)
8` CLUMP
BER LYR
20
BERLANDIERA LYRATA CHOCOLATE FLOWER (18"HT)
5 GAL
LYS NUM
17
LYSIMACHIA NUMMULARIA CREEPING JENNY (4")
1 GAL
SYR LIL
4
SYRINGA MEYERI 'PALIBIN' DWARF KOREAN LILAC (4'HT)
5 GAL
21
BOUTELOUA GRACILIS 'BLONDE AMBITION' BLONDE AMBITION BLUE GRAMA (2'HT)
1 GAL
TREES 4TH FLOOR STRUCTURE RE: ARCHITECTURE 4TH FLOOR SPA RE: ARCHITECTURE
SHRUBS
LINCOLN HALL
MULTI-USE PATH
4TH FLOOR POOL RE: ARCHITECTURE RAMP RE: ARCHITECTURE
GRASSES BOU BLO
MARINE STREET
KEY MAP
LX202 LX201
1
FOURTH FLOOR PLANTING PLAN
0
1" = 30'-0"
SCALE: 1" = 30'-0"
15'
30'
60'
LX101
SCALE: N.T.S.
NORTH NORTH
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW
FOURTH FLOOR PLANTING PLAN
07.29.2026
LP103
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
TREE FENCING SHALL BE A MINIMUM OF 4' HIGH ORANGE POLYETHYLENE LAMINAR SAFETY NETTING
NW
NW
CANOPY DRIP LINE
PROTECTIVE FENCING DURING CONSTRUCTION
POSTS SETTING TO 2' IN GROUND MADE OF DURABLE METAL "T" OR EQUIVALENT
EVERGREEN TREE
TREES 3'' CLP TREES UNDER AND UP 3'' CLP STAKING PLAN
DECIDUOUS TREE
OPPOSITE SIDE SAME OPPOSITE SIDE SAME
AERATION BEFORE, DURING AND AFTER CONSTRUCTION
NOTES: 1. WRAP TRUNK WITH 4'' TREE WRAP PER SPECIFICATIONS. 2. SEE SPECS FOR PLANTING OF VINES AND GROUND COVERS. 3. DETAIL IS TYPICAL IN INTENT ONLY.
TRUNK PLUMB AND STRAIGHT 8" GREEN STEEL TEE POSTS WITH BLADE ON TREE SIDE
SECTION
MULCHED, SOD-FREE BASE AROUND TREES PER SPECIFICATIONS
FENCE LOCATION AT DRIP LINE OR 15' FROM TRUNK, WHICHEVER IS GREATER AND SHALL ENCLOSE TREE
SEE SECTION
RUN DOUBLE STRAND 12 GAUGE WIRE THROUGH GROMMETS IN 2'' NYLON STRAP. RUN WIRE TO POST AND TWIST FOR SLIGHT TENSION PROTECTIVE CAP SECURED TO STAKE DECIDUOUS SHRUB
PLANT PIT TWO TIMES LARGER THAN BALL DIAMETER ROOT BALL TO BE 2'' ABOVE FINISHED GRADE
BACKFILL FINISH GRADE WITH SOD OR MULCH, SEE PLAN BALL
PLAN
EVERGREEN SHRUB
BACKFILL
BALL
PLANT PIT TWO TIMES LARGER THAN BALL DIAMETER. ROOT BALL TO BE 1'' ABOVE FINISHED GRADE
UNDISTURBED SUBGRADE REMOVE ALL FOREIGN MATERIALS FROM TRUNK AND BALL FOLD BACK TOP HALF OF UNTREATED BURLAP
1
PROTECTED ROOT ZONE AND DRIP LINE
2
1" = 1"
TREE AND SHRUB PLANTING DETAIL
3
NOT TO SCALE
TREE STAKING AND GUYING PLAN 1/2" = 1'-0"
SET ORNAMENTAL GRASS TO SPECIFIED TRIANGULAR SPACING RE: PLANT SCHEDULE
PLANT CROWN 1" ABOVE FINISH GRADE 3" DEEP WOOD MULCH RE: SPECS
P
R
12"
P
P
EDGE OF HARDSCAPE, WALL, PLANTER BED OR HEADER (REFERENCE PLANS)
1 2P
P
NOTE:INCORPORATE LIQUID ROOT STIMULANT AS PART OF PLANTING OPERATION
P
2 X ROOTBALL DIAMETER
1 2P
FOR TRIANGULAR SPACING OF SHRUBS, PERENNIALS AND GROUNDCOVERS. SEE PLANT SPACING DISTANCE.
P
PLANTING MIX SCARIFY SIDES OF HOLE PRIOR TO BACK-FILLING REMOVE PLANT FROM CONTAINER OR PEEL BACK BURLAP AND REMOVE TWINE / WIRE FROM ROOT BALL AFTER 23 BURIED IN PIT. PLACE ON UNDISTURBED SUBGRADE
4
SHRUB PLANTING 1/2" = 1'-0"
5
ORNAMENTAL GRASS PLANTING 1" = 1'-0"
6
SHRUB AND PERENNIAL SPACING
P TRIANGULAR 4" 6" 8" 10" 12" 18" 24" 30" 3' 4' 5' 6'
R ROW 3 7 16" 5 14" 7" 8 3 4" 10 3 8" 1'-3 5 8" 1'-8 3 4" 2'-2" 2'-7" 3'-5 12" 4'-4" 5'-2 3 8"
AREA PER PLANT SQ.FT. .096 .22 .385 .60 .87 1.95 3.46 5.42 7.80 13.84 21.65 31.20
3/8" = 1'-0"
HUB BOULDER - ARAPAHOE | 2130 ARAPAHOE AVE. | SITE PLAN REVIEW
PLANTING DETAILS
07.29.2026
LP501
2505 Walnut Street | Suite 200 | Boulder, CO 80302 | 303.442.4422 | www.sophersparn.com
Attachment B - Site Review Written Statement
MEMORANDUM To: From: Project: Date:
Charles Ferro, Land Use Review Manager - CITY OF BOULDER Adrian Sopher - SOPHER SPARN ARCHITECTS LLC HUB BOULDER ARAPAHOE – 2130 Arapahoe Avenue 21 January 2026 Revised 15 April 2026 Revised 27 May 2026Revised 5 August 2026
Re: WRITTEN STATEMENT – Site Plan Review Submittal This document is a written statement describing the proposed student housing rental project, located at 2130 Arapahoe Avenue Boulder, CO. This document outlines how the application meets all applicable review criteria and is being submitted for the City of Boulder’s Site Review application requirements.
PROJECT VISION The proposed project envisions the thoughtful transformation of the current Naropa University campus into a vibrant, purpose-built community for student living. Centered around the historic Lincoln Hall, the design respects the past while creating a forward-looking environment tailored to student life. Framed by a U-shaped configuration of contemporary new buildings, the project will offer approximately 135 residential units in a variety of 2 to 6-bedroom layout, supporting both individual and shared living preferences. More than just housing, the development is designed to foster connection, wellness, and academic focus. A host of on-site amenities including a pool deck, a fitness room, and a dedicated study lobby - will be housed within the larger of the new buildings, offering students a holistic live-learn experience just steps from home. Located along Arapahoe Avenue, directly adjacent to future planned university housing and just north of the CU Boulder campus, the site is ideally positioned to serve the next generation of students. This redevelopment aspires to create not only a place to live, but a true community hub—integrating architectural heritage with modern student needs in a dynamic and enduring way.
Attachment B - Site Review Written Statement 8/11/2026 WrtnStmnt_2130 Arapahoe_08-05-26 Page 2 of 40
Anticipated Development Schedule (All dates are targets and subject to change) Site Review Completion: Tec Doc Review Completion: Building Permit Issued: Construction Start: Construction Completion:
September 2026 August 2027 February 2028 February 2028 February 2030
PLANNING CONSIDERATIONS Land Use Map Change The property at 2130 Arapahoe Avenue has historically served as a Naropa University campus. Naropa has decided to sell the property due to changing institutional needs and a shift toward hybrid and virtual learning, reducing the need for continued use of this site. During the 2015–2016 Boulder Valley Comprehensive Plan update, the site’s Land Use designation was changed to Public based on the assumption of Naropa’s long-term occupancy as an educational institution. City staff and City Council supported the designation at that time to recognize the campus’s public-serving function. Naropa’s departure represents a material change from the conditions that supported the public designation. The applicant therefore requests a Land Use Map Change from Public to High Density Residential. A more detailed description of the request is provided in the Written Statement submitted with the Rezoning application (LUR2025-00034).
The site is located adjacent to the University of Colorado campus in an area identified for higher-density residential growth, particularly student-oriented housing. Redevelopment of the site for multifamily residential use would align with the city’s strategy of concentrating on student housing near campus and reducing pressure on nearby lower-density neighborhoods, including Goss-Grove. The existing Public Land Use designation limits residential development to six dwelling units per acre, making multifamily housing infeasible on this site. A High-Density Residential designation better reflects current conditions, supports city housing objectives, and is consistent with surrounding land use patterns and BVCP growth policies.
Rezoning With Naropa University’s departure from the site and the city’s identified need for housing—particularly in this location adjacent to the University of Colorado—the existing Public Zone District is no longer appropriate. While Public zoning allows unlimited floor area for nonresidential uses, it limits residential development to six dwelling units per acre, resulting in significant underutilization of the property and making multifamily housing infeasible. Upon approval of the requested Land Use Map Change to High Density Residential, the current public zoning would no longer be consistent with the Boulder Valley Comprehensive Plan map. Rezoning the property to RH-5 is therefore necessary to bring the zoning into conformance and to support the city’s housing goals for this area
Attachment B - Site Review Written Statement 8/11/2026 WrtnStmnt_2130 Arapahoe_08-05-26 Page 3 of 40
south of Arapahoe Avenue. A more detailed description of the request is provided in the Written Statement submitted with the Rezoning application (LUR2025-00034). The RH-5 zoning designation, allowing up to 1.5 FAR, aligns with the city’s long-standing strategy of concentrating on student housing near the CU campus while limiting impacts on nearby single-family neighborhoods. This designation is consistent with surrounding high-density zoning districts and with recent and planned development associated with the University of Colorado Campus Master Plan. In summary, rezoning the property from Public to RH-5 High Density Residential supports the proposed land use, responds to evolving conditions in the campus-adjacent area, and is consistent with Boulder Valley Comprehensive Plan policies and city housing objectives.
Floodplain Impacts The entire site is in the 100yr floodplain, which requires the finished floor to be raised at least 2’ above the Base Flood Elevation (BFE) in some areas this resulted in a finished floor that is almost 6’ above the grade. See separate flood narrative for further information.
Public Right of Way Vacation The applicant is requesting a Vacation of a portion of the Public Right of Way where Marine Street dead ends into the applicant’s property.
The portion of the Marine Street right-of-way proposed for vacation is no longer necessary to serve its original public purpose. Originally dedicated for vehicular access and related infrastructure, changes in site configuration, surrounding development, and circulation patterns have rendered this segment functionally obsolete. It does not provide through access, is not needed for vehicular circulation, and is not required to support pedestrian, bicycle, or transit connectivity. Existing public streets, sidewalks, and multimodal facilities adequately serve the area. The right-of-way contains a sanitary sewer easement, which would be retained, ensuring continued city access and utility function. Vacation of this portion of the Marine Street right-of-way is consistent with the Boulder Valley Comprehensive Plan and the city’s land use regulations and satisfies the criteria under Section 8-6-9(c)(3)(B) by providing a greater public benefit than retaining the property in its current condition. Vacation allows for a more cohesive and functional site design that supports efficient land use, compatible infill development, and high-quality urban design. Incorporating the vacated area into the adjacent property clarifies the transition between the public street and private access drive and enables improved building access and streetscape design. In contrast, retaining the right-of-way results in an underutilized and fragmented area that does not meaningfully serve a public purpose and detracts from the overall functionality and visual quality of the corridor.
Attachment B - Site Review Written Statement 8/11/2026 WrtnStmnt_2130 Arapahoe_08-05-26 Page 4 of 40
EXISTING CONDITIONS The 2130 Arapahoe Avenue property in Boulder is currently one of the two campus locations of Naropa University, a private, nonprofit liberal arts institution. The existing site includes approximately 16 buildings organized haphazardly around the Landmarked Lincoln Hall at the center of the site. At the time of Concept Review, City Landmark Staff identified that two of the existing buildings, Arapahoe House and Chestnut House, had the potential for Landmark Designation Eligibility. These buildings are proposed to be relocated to the west edge of the site to accommodate the new shared campus walk designed to align with 21st street. And a separate Landmark Alteration Certificate Application has been submitted see HIS2026-00046 & HIS2026-00045. The buildings are interspersed by green spaces and contain three sycamore trees and one oak tree that are identified as Colorado “Champion” trees. These trees will remain and be protected throughout the construction process. The proposed redevelopment will maintain several of the open lawn areas and various paths through the site, to maintain a campus like feel. Currently, an internal private drive connects Arapahoe Avenue south to Grandview Avenue and to the parking lots on the south side of the property. The proposed redevelopment will include removing the existing surface parking and relocating the private drive to the west.
SITE DESIGN The proposed site design is guided by a clear set of principles that emphasize connectivity, sensitivity to context, and a strong campus identity. First and foremost, the layout and circulation patterns are intentionally organized to foster a campus-like atmosphere, creating meaningful connections between the University of Colorado campus to the south and the Goss Grove neighborhood to the north. A primary focus of the design is the respectful integration of Lincoln Hall and the preservation of the site's Champion Trees. The new apartment building is arranged in a U-shaped configuration that frames Lincoln Hall and preserves the central courtyard, allowing this open space to serve as a landscaped, multifunctional gathering area that reinforces the campus character. The new building footprints are carefully placed to respect the historic northern boundary established by the Chestnut House and Administration Hall, ensuring that no new massing extends much further north along Arapahoe Avenue than these existing structures. Along the northern edge of the site, a 3- to 4-story walk-up style townhome building has been introduced to reflect the scale and residential rhythm of the adjacent Goss Grove neighborhood. Meanwhile, the west wing of the apartment building features ground-level amenity spaces oriented toward Arapahoe Avenue, activating the public realm and fostering
Attachment B - Site Review Written Statement 8/11/2026 WrtnStmnt_2130 Arapahoe_08-05-26 Page 5 of 40
engagement with the broader community. To support pedestrian connectivity, a shared campus walk runs along the west side of the apartment building. This pathway offers direct access to the main building entry, establishes a link to the CU campus, and connects northward to Pearl Street via 21st Street, through a proposed new pedestrian activated crossing at Arapahoe Avenue - strengthening the site’s integration into the urban fabric.
BUILDING DESIGN The design of the new buildings is intended to reference and complement the landmarked Lincoln Hall, as well as relate to the residential neighborhoods to the north through a thoughtful interpretation of massing and materials resulting in a context-sensitive development. Lincoln Hall was constructed in 1903 by Boulder architect Watson Vernon and served as the Lincoln School for decades. It is a prime example of school buildings constructed in Boulder around the turn of the century. Designed mostly in the colonial revival/Late Victorian Institutional style, it has a strongly symmetrical form with a projecting front entry bay crowned by a central tower capped with a conical roof. The main material is red brick accented by light colored stone sills and trim and the double hung sash windows are arranged in pairs in a uniform grid pattern.
Attachment B - Site Review Written Statement 8/11/2026 WrtnStmnt_2130 Arapahoe_08-05-26 Page 6 of 40
The Townhome and Main Buildings flanking either side of the historic structure embody a contemporary infill approach with modern influences. Their design is intended to thoughtfully blend old and new, using brick cladding on the lower levels to create a visual connection with the historic core, while cementitious siding on the upper floors introduces a sleek, modern contrast. The rooflines are flat with angular gabled forms, subtly echoing the peaks of traditional houses but with a minimalist, refined execution. The façades are composed of rhythmic vertical bays, defined by consistent window groupings, contrasting and complementary materials, creating a sense of order and visual interest. Recessed entryways with protruding porch elements add depth, and a human scale to the overall massing, ensuring the buildings feel approachable and well-integrated into their surrounding context.
VIEW LOOKING SOUTH FROM ARAPAHOE AVE
VIEW FROM ARAPAHOE - SITE PERMIABILITY
The west wing of the main building facing Arapahoe Avenue contains the primary amenity spaces for the development, including a communal lobby space, fitness center, and leasing office on the main level. An outdoor pool deck and interior gathering space is located on the 4th level of this wing and has expansive views to the west and north. Extensive glazing on the ground floor introduces transparency and activates the pedestrian level, while metal accents at window frames and railings provide a contemporary contrast to the traditional red brick. The main building entrance is defined by a protruding canopy, supported on one edge by a decorative slat wall element, and extra tall entry doors surrounded by glazing.
Attachment B - Site Review Written Statement 8/11/2026 WrtnStmnt_2130 Arapahoe_08-05-26 Page 7 of 40
The south and east wings of the Main building contain residential units on the ground level at the perimeter, and three levels above the parking garage which is located centrally and internal to the building. These elevations are articulated into a series of stepped volumes, creating variation in depth and scale along the long façade, which helps to break down the mass and introduce a more pedestrian-friendly scale. Large vertical windows are grouped in consistent bays, bringing in natural light and reinforcing a clean, vertical rhythm. The integration of balconies and recesses further animates the exterior, offering private outdoor space and visual depth.
VIEW LOOKING SOUTHEAST FROM ARAPAHOE AVE
PARKING/VEHICULAR ACCESS Primary vehicular access to the site is currently provided from Arapahoe Avenue via 20th Street and Marine Street. A secondary, private drive aligned with Grandview Avenue functions primarily as a pedestrian and bicycle route, offering limited, service access to a few campus buildings while connecting Arapahoe Avenue to the southern portion of the site and the CU campus beyond. The proposed site plan maintains the historic vehicular circulation pattern via 20th and Marine Streets for primary parking access, while introducing key improvements to enhance connectivity and reduce traffic conflicts. Notably, the existing private drive aligned with Grandview Avenue is proposed to be relocated westward to align with 21st Street. This strategic shift will simplify traffic flow along Arapahoe Avenue, strengthen connections to downtown Boulder, and reinforce a more intuitive campus circulation.
Attachment B - Site Review Written Statement 8/11/2026 WrtnStmnt_2130 Arapahoe_08-05-26 Page 8 of 40
While this relocated shared campus walk will serve as the main vehicular access point to the development’s primary entry, it is intentionally designed as a shared, pedestrian-prioritized space. Vehicular access will be limited to one way southbound only, and no left turns allowed from Arapahoe. Design elements will discourage through traffic and emphasize a safe, walkable environment.
Figure 1: CAMPUS WALK EXAMPLES
As noted previously, another key improvement proposed is the vacating a portion of the Marine Street right-ofway. Which is intended to clarify the transition between the public street and private access drive and enable improved building access and streetscape design. The project is intended to be a student housing facility located .5 mile from the CU campus (10 min walk, 5 min bike ride), .3 miles from the shopping center on Arapahoe & Folsom Street (5 min walk, 3 min bike ride) and 1 mile from Pearl Street (15 min walk, 5 min bike ride). These are just a few examples of how the site location and use support the parking amounts proposed. The applicant has built several other student housing developments of comparable size and has determined that the optimal number of parking spaces is 15% of the bed count and typically the parking is used more for long-term storage than daily trips.
Attachment B - Site Review Written Statement 8/11/2026 WrtnStmnt_2130 Arapahoe_08-05-26 Page 9 of 40
BICYCLE PARKING & ACCESS The proposed development has multiple existing and proposed bicycle friendly access points. From the north, a new pedestrian/bike activated signalized crossing aligned with 21st street provides access from the Goss Grove Neighborhood, and along the east edge of the site there is an existing multiuse path. Primary access to long term bicycle parking is through designated and secure entry into the parking garage at the south side of the site, which is the most direct route to the CU campus.
Bicycle parking requirements per Table 9-4 are 2 spaces per residential unit, with 75% required to be long term, and 25% short term. The project has a total of 135 units, so 274 bicycle parking spaces are required. To support student housing use and further reduce the need for vehicle parking, additional spaces above the required will be provided.
Attachment B - Site Review Written Statement 8/11/2026 WrtnStmnt_2130 Arapahoe_08-05-26 Page 10 of 40
EMERGENCY VEHICLE ACCESS Emergency and fire access to the site has been carefully integrated into the overall design to ensure safety, efficiency, and ease of response. The primary access point for emergency vehicles will be via the shared campus walk along the west side of the site. This drive has been engineered to accommodate fire trucks, including sufficient width and clearance for vehicle maneuvering and the deployment of outriggers, if required. It also provides direct access to the building’s main lobby—an ideal location for assisting residents and facilitating swift emergency response. To enhance coverage, an additional fire access lane is proposed along the southern edge of the site as an extension of Marine Street. This route offers improved access to the southeast corner of the development, ensuring emergency personnel can reach all areas of the building quickly and effectively.
Attachment B - Site Review Written Statement 8/11/2026 WrtnStmnt_2130 Arapahoe_08-05-26 Page 11 of 40
(1) 2015 BOULDER VALLEY COMPREHENSIVE PLAN (BVCP) CRITERIA (A) BVCP Land Use Map and Policies: The proposed project is consistent with the BVCP land use map and, on balance, with the goals and policies of the BVCP particularly those that address the built environment. In applying this, the approving authority shall consistently interpret and apply this criterion and consider whether a particular goal or policy is intended to be applied to individual development projects or is to guide city policy decisions, such as regulatory actions. The BVCP does not prioritize goals and policies, and no project must satisfy one particular goal or policy or all of them. Specific examples of how the proposed project is consistent with the BVCP Map and on balance with the goals and policies are provided below: 2.10 Preservation & Support for Residential Neighborhoods: The city will seek appropriate building scale and compatible character in new development or redevelopment, appropriately sized and sensitively designed streets and desired public facilities and mixed commercial uses. The proposed development is designed to preserve and reinforce the existing campus character while remaining compatible with the surrounding residential neighborhoods. Building scale and massing are carefully calibrated to respect the context, with maintained setbacks along Arapahoe Avenue that preserve visual openness, existing landscape patterns, and the established streetscape rhythm. Generous greenspace is integrated throughout the site to support a campus-like environment, provide buffers to adjacent uses, and enhance neighborhood livability. The townhome building is intentionally designed to relate to the nearby single-family residential neighborhood through its residential scale, articulated façades, and individual units with direct access to the street via front porches. This approach promotes a familiar neighborhood pattern, encourages pedestrian activity, and creates a clear transition between campus-oriented development and surrounding residential uses. Streets, open spaces, and building orientations are sensitively designed to support walkability and reinforce neighborhood character 2.25 Improve Mobility Grid & Connections: The walkability, bike ability and transit access should be improved in parts of the city that need better connectivity and mobility, for example, in East Boulder. This should be achieved by coordinating and integrating land use and transportation planning and will occur through both public investment and private development. The proposed development maintains the existing walking, biking and bus connections that exist today to the CU Campus to the south and the retail centers to the east. The connection to downtown has been improved by relocating the shared campus walk to align with 21st street, and installing a pedestrian activated crossing. 21st street has an established pedestrian and biking route through the Goss-Grove neighborhood, to a pedestrian activated crossing at Canyon, and on to Pearl Street. 2.36 Physical Design for People: The city and county will take all reasonable steps to ensure that public and private development and redevelopment be designed in a manner that is sensitive to social, health and psychological needs. Broadly defined, this will include factors such as accessibility to those with limited mobility; provision of coordinated facilities for pedestrians, bicyclists and bus-riders; provision of functional landscaping and open space; and the appropriate scale and massing of buildings related to neighborhood context. The proposed development is designed with a strong emphasis on human-scaled environments that support social interaction, health, and overall well-being. Universal accessibility is integrated throughout the site, with barrier-free pedestrian routes, compliant building entries, and accessible connections to transit, ensuring mobility for users of all abilities. See accessible routes added to the circulation diagram on A009. The project provides coordinated and clearly defined facilities for pedestrians, bicyclists, and bus riders, including enhanced sidewalks, shared-use paths, bicycle connections, and convenient access to nearby transit stops. These elements promote active transportation, reduce reliance on vehicles, and support daily physical activity. Functional landscaping and thoughtfully distributed open spaces are incorporated to provide areas for gathering, recreation, and respite, while also contributing to visual comfort, shade, and environmental quality.
Attachment B - Site Review Written Statement 8/11/2026 WrtnStmnt_2130 Arapahoe_08-05-26 Page 12 of 40
Building scale and massing are carefully calibrated to respond to the surrounding neighborhood context, with articulated façades, appropriate setbacks, and transitions in height that reinforce a pedestrian-friendly character. Collectively, these design strategies create a cohesive, inclusive, and people-centered environment that supports the social, physical, and psychological needs of the community. 2.37 Environmentally Sensitive Urban Design: For capital improvements and private development, the city and county will strive to ensure that buildings, streets, utilities and other infrastructure are located and designed to protect natural systems, minimize energy use, reduce urban heat island effects and air and water pollution and support clean energy generation. The project is designed with a strong focus on environmental stewardship, particularly in preserving existing natural assets and minimizing ecological disruption. Several mature trees on the site were evaluated by a certified arborist, whose recommendations guided the design process. As a result, five significant trees will be preserved, and the placement of new buildings was carefully planned to avoid intrusion into their canopy and root zones as much as possible. To further reduce environmental impact, all resident parking will be located within an on-grade garage beneath the main apartment building. This strategy consolidates impervious surfaces, minimizes heat island effects, and maintains more open, landscaped areas throughout the site. Additional sustainability measures include enhanced stormwater management, with new detention areas planned for both the north and south ends of the property. These systems will be supported by water quality raingardens strategically placed across the site and planted with bio retentive species to naturally filter runoff. Landscaping will feature drought-tolerant, low-water-use plants to reduce long-term irrigation needs and promote climate resilience. 2.41 Enhanced Design for all Projects b. The Context: Projects should become a coherent part of the neighborhood in which they are placed. Special attention will be given to protecting and enhancing the quality of established residential areas that are adjacent to business areas. The context surrounding the proposed development is dominated by CU student Housing to the South, and the Goss-Grove Neighborhood to the north. While the scale, density, and building height of the project most closely aligns with the existing and proposed student housing, efforts have been made to relate to the Goss Grove neighborhood across Arapahoe through the incorporation of protruding porch elements, residentially scaled roof forms, and complementary materials. See also the response to 2.10. c. Relationship to the public realm: Projects should relate positively to public streets, plazas, sidewalks, paths and natural features. Buildings and landscaped areas—not parking lots—should present a well-designed face to the public realm, should not block access to sunlight and should be sensitive to important public view corridors. Future strip commercial development will be discouraged. Buildings along Arapahoe Avenue maintain established setbacks and are oriented to face the street, creating a consistent and pedestrian-supportive street edge while preserving access to sunlight and avoiding obstruction of important public view corridors. Long-term parking is fully enclosed within the building, and limited shortterm parking is screened with landscaping to ensure that buildings and landscaped areas—not parking—define the public experience. The sitting and massing respect significant natural features, including the landmarked Lincoln Hall and existing champion trees, allowing these elements to remain prominent and visible within the public realm. Entrances and amenity spaces are strategically located to activate sidewalks and the proposed campus walk. See Section (3) Building Siting and Design Criteria of the site review requirements for additional detail. e. Transportation connections. Projects should provide a complete network of vehicle, bicycle and pedestrian connections both internal to the project and connecting to adjacent properties, streets and paths, including dedication of public rights-of-way and easements where required. Internal circulation prioritizes safe and direct pedestrian and bicycle movement through a system of connected paths that link buildings, open spaces, and key access points, while also tying directly into the existing multiuse path along the east edge of the property. These connections strengthen access to the University of Colorado
Attachment B - Site Review Written Statement 8/11/2026 WrtnStmnt_2130 Arapahoe_08-05-26 Page 13 of 40