CBOC/Bond Board of Education Update | May 26, 2026

Building for Student Success Bond Summer Construction Preview

Summer Construction 2026

~$60 million 13 sites 2

Building for Student Success Update

Project Timeline - Phases 2, 3, & 4 2026 J

F

M

2027 A

M

J

J

A

S

O

N

D

J

F

M

A

M

J

J

A

S

O

N

D

Ph. 2 Construction continues for some projects

Ph. 3 Construction

Ph. 3 Construction 2-year project (FHS)

Ph. 4 Schematic Design Ph. 4 Design Development Ph. 4 Construction Documents Ph. 4 Construction Bidding Ph. 4 Construction

3

Building for Student Success Update

Project Cycle

Construction

Design

ONGOING (Phase 2)

UPCOMING (Phase 3)

BEGINNING (Phase 4)

● Arapahoe Ridge High/ Apex/Transitions/Boulder Universal ● Boulder High ● Monarch High

● Aspen Creek PK-8 ● Birch Elementary ● Centennial Middle ● Crest View Elementary ● Fairview High ● Manhattan Middle ● Mapleton ECC ● Platt Middle ● Southern Hills Middle ● Whittier Elementary

● Bear Creek Elementary ● Coal Creek Elementary ● Community Montessori ● Eisenhower Elementary ● Eldorado PK-8 ● Flatirons Elementary ● Foothill Elementary ● Heatherwood Elementary ● Kohl Elementary ● Mesa Elementary ● Nederland Elementary ● Nederland MS/HS ● Superior Elementary

4

Building for Student Success Update

Phase 2 Projects Status

●

●

Construction continues at 2-year project sites: Monarch, Boulder High, Apex and Arapahoe Ridge High Construction ongoing at Apex/Arapahoe Ridge High School/Boulder Universal/Transitions ○

●

Apex will finish phase 4 in June while at the same time beginning phase 5 which will complete fall of 2026

2024/25 ● Apex/Arapahoe Ridge High/Boulder Universal/Transitions ● Boulder High ● Monarch High

One-year projects (Summer 2025) are completing project closeout 5

Building for Student Success Update

Phase 3 Projects

2025/26

Status

●

Construction to kick-off May 22 after the students leave for summer break

●

UA Playground phase III and BCSIS/High Peaks work put on hold pending BOE declining enrollment decisions ○

BCSIS/HP roof to be replaced under a manufacturer’s warranty claim

○

UA Playground contracts on hold for work to be determined Summer 2027

CONSTRUCTION (Phase 3) ● Aspen Creek PK-8 ● Birch Elementary ● Centennial Middle ● Crest View Elementary ● Fairview High ● Manhattan Middle ● Mapleton ECC ● Platt Middle ● Southern Hills Middle ● Whittier Elementary

6

Building for Student Success Update

Phase 4 Projects Status

●

Design Development phase has been completed or is nearing completion

●

Construction Documents will be issued in September

●

Contractor’s guaranteed maximum price (GMP) will go to the Board in November pending declining enrollment decisions in October

2026/27 DESIGN (Phase 4) ● Bear Creek Elementary ● Coal Creek Elementary ● Community Montessori ● Eisenhower Elementary ● Eldorado PK-8 School ● Flatirons Elementary ● Foothill Elementary ● Heatherwood Elementary ● Kohl Elementary ● Mesa Elementary ● Nederland Elementary ● Nederland MS/HS ● Superior Elementary

7

Building for Student Success Update

New Vista Solar Installation ● Project is complete ● Finalizing metering with Xcel ● The solar array will produce enough power to offset most of New Vista’s electricity use and increase BVSD’s total solar production capacity throughout the district by nearly 19%

8

Building for Student Success Update

Community Bond Oversight Committee ●

Last meeting May 6 ○ Written summary due to snow day

●

Reviewed financial documents

●

○

Expenditures through April: $198M

○

Encumbered: $64M

○

Forecasted remaining expenditures: $132M

Action item for Culinary Center cooling tower 9

Building for Student Success Update

CBOC Action Item Culinary Center Redundant Cooling Tower ●

Transfer $389,250 from Bond Premium

●

Install additional cooling tower to share cooling load and act as backup

10