CONSTRUCTION MANAGEMENT/GENERAL CONTRACTOR AGREEMENT THIS CONSTRUCTION MANAGEMENT/GENERAL CONTRACTOR AGREEMENT (“Agreement”) is made and entered into as of this 18th day of November, 2025 by and between the Boulder Valley School District RE-2 (hereinafter referred to as the “Owner” or “School District”) and Howell Construction. (hereinafter referred to as the “Construction Manager/General Contractor” or “CM/GC”), for services in connection with the following described Project: BVSD Request For Proposal (“RFP “) No 26-04 titled CM/GC Project Scope #1 – Nederland Elementary School (“Project”) This Agreement shall be performed in conjunction with the services of the Architect for the Project, RB+B Architects. In consideration of the mutual covenants and provisions contained herein, the parties agree as follows: ARTICLE 1 1.1.
1.2. 1.3.
1.4.
Responsibility of CM/GC to Owner: The CM/GC accepts the relationship of trust and confidence established with the Owner by this Agreement. CM/GC covenants with the Owner to furnish its best skill and judgment and to cooperate with the Architect in furthering the interests of the Owner. CM/GC agrees to furnish efficient business administration and superintendence and to use its best efforts to perform the Work in the best and soundest way and in the most expeditious and economical manner consistent with the interests of the Owner. The Construction Team: The CM/GC, the Owner, and the Architect, collectively referred to as the “Construction Team,” shall work from the beginning of design through construction completion. The CM/GC shall provide leadership to the Construction Team on all matters relating to construction. Extent of Agreement: This Agreement together with the General Contract Conditions (“General Conditions”), incorporated herein by reference, RFP 26-04 CM/GC Project Scope #1 – Nederland Elementary School dated August 21, 2025, a copy of which is attached as Exhibit A and the Contractor’s proposal dated September 17, 2025, a copy of which is attached as Exhibit B, represent the entire agreement between the Owner and the CM/GC and supersede all prior negotiations, representations, or agreements. When plans and specifications are complete, they shall be identified as part of the Contract Documents (as defined in the General Contract Conditions). This Agreement shall not be superseded by any provisions of the documents for construction and may be amended only by written instrument executed by both the Owner and the CM/GC. Nothing contained herein shall be deemed to create any contractual relationship between the CM/GC and the Architect, or any of the contractors, subcontractors, or material suppliers on the Project; nor shall anything contained herein be deemed to give any third party any claim or right of action against the Owner or the CM/GC which does not otherwise exist without regard to this Agreement. Contract Documents: The provisions of the General Conditions and all of the “Contract Documents” for the Project as that term is defined therein are incorporated by this reference into this Construction Management/General Contractor Agreement. The intent of the Contract Documents is to include all items and services necessary for the proper execution and completion of the Work. The Contract Documents are complementary, and what is required by any one shall be as binding as if required by all. Work not covered in the Contract Documents shall be required unless it is not consistent therewith and is not reasonably inferable therefrom as being necessary to produce the intended results. Words and abbreviations which have well known technical or trade meanings are used in the Contract Documents in accordance with such recognized meanings. If there are conflicting variances between the Drawings and Specifications, the requirements of the Specifications shall control unless the Architect/Engineer directs otherwise in writing. Numerous exhibits to be developed over a period of
1.5.
time are also to be attached to and made a part of the Contract Documents, some of which may be in conflict with other exhibits or portions of this Agreement. In the event of any conflict between any of them, the greater service, better quality or greater quantity shall be included in the Work, Contract Sum and Guaranteed Maximum Price without additional compensation, to be superseded by applicable Amendments and Change Orders. The Work: The CM/GC shall perform the services set forth in the Method of Payment Matrix attached hereto and incorporated by reference herein as Exhibit A. The initial Work of the CM/GC shall consist of its services in connection with the Design Phase, which shall be parallel and coincidental with the Schematic Design, Design Development, and Construction Document Phases of the Architect’s Services. As the bid packages are prepared and prices are established for the Work to be performed within each respective bid package, the parties contemplate that the work to be performed by the CM/GC shall be adjusted by Amendment or Change Order to this Agreement to place the Work contained within the various bid packages within the Work to be performed by the CM/GC with corresponding adjustments made to the Guaranteed Maximum Price and the Contract Time. ARTICLE 2 Construction Manager/General Contractor Services
The CM/GC’s basic services under this Agreement shall consist of the two (2) phases described below. 2.1. Pre-Construction Estimating Phase: As part of the Pre-Construction Estimating Phase, the CM/GC will: 2.1.1. Site Building, and Constructability Analysis. Perform site, building, and constructability analysis to assist the architectural/engineering team throughout all phases of design. Without limiting the foregoing services, the constructability analysis will include, but not be limited to the systematic evaluation of the design documents prepared by the Architect in each phase of design to identify and resolve potential issues that could (a) impact project cost, schedule, safety, or quality, (b) be in conflict with current code compliance in the building, or (c) interfere with the ability to efficiently construct the work. 2.1.2. Design Advisory Team. Participate in multiple design advisory team meetings with the District and Architect. 2.1.3. Communications with Architect. Communicate regularly with the architectural/engineering team and Owner for input and advice regarding cost and scope of project features, and regarding phasing and scheduling of the Project. 2.1.4.Cost Estimating. Conduct cost estimating of SD, DD, and CD Drawings. 2.2. Design Phase: As part of the Design Phase services, the CM/GC will: 2.2.1. Consultation During Project Development and Design – When applicable and only if this Agreement is executed prior to the completion of development and design, attend regularly scheduled meetings with the Architect during the development of conceptual and preliminary design to advise the Construction Team concerning site use and improvements, selection of materials, building systems, and equipment. Provide recommendations on construction feasibility, availability of materials and labor, time requirements for installation and construction, and factors related to cost including costs of alternative designs or materials, preliminary budgets, and possible economies. 2.2.2. Scheduling - Develop a Project Time Schedule at the end of each design phase that coordinates and integrates the Architect’s design efforts with construction schedules. Provide an electronic copy for the Owner’s review and approval. Update the Project Time Schedule, at intervals required by the Owner, incorporating a detailed schedule for the construction operations of the Project, including realistic activity sequences and durations, allocation of labor and materials, processing of shop drawings and samples, and delivery of products requiring long lead-time procurement. Include the Owner’s occupancy requirements showing portions of the Project having occupancy priority. Provide one hard copy and an electronic copy of the updates for the Owner’s review and approval. 2.2.3. Project Construction Budget – 2
2.2.3.1. Review the Owner’s established Project budget as soon as major program requirements have been identified and update the budget, at intervals required by the Owner, for the Owner’s approval. Prepare an estimate based on a quantity survey of drawings and specifications at the end of the Schematic Design Phase for approval by the Owner as the Project Construction Budget. Update and refine this estimate for Owner’s approval as the development of the drawings and specifications proceeds. Advise the Owner and the Architect if it appears that the Project Construction Budget will not be met and, in that event, make recommendations for corrective action. The Contractor shall submit cost estimates to the Owner for review and acceptance and shall provide copies to the Architect for review and verification. The amount of money appropriated by the Owner for the Project is equal to or in excess of the Project Construction Budget. 2.2.3.2. As the plans and specifications evolve through each design phase, the Contractor will perform cost studies and major estimates of the Cost of the Work using area, volume or similar estimating techniques for Owner’s approval. If the Contractor suggests alternative materials and systems, the Contractor shall provide cost evaluations of those alternative materials and systems. Any alternative materials or systems selected by the Owner, based on the cost evaluations provided by Contractor, shall then be incorporated into the updated budgets. 2.2.3.3. The Contractor’s estimating and budgeting systems and reports shall be flexible to allow comparisons of building systems and components. They shall include a means to provide a variance analysis throughout each budget update starting with the effective date and continuing through the Guaranteed Maximum Price. The format of the estimating system shall include detail sheets for each Work task that reflect unit prices, quantities, and extensions for labor and materials. The Contractor shall establish the estimate in a Construction Specifications Institute (CSI) format in a detailed open book collaborative manner that allows the Owner to make timely and informed decisions. Each budget shall also include a detailed list of relevant clarifications as they relate to the preparation of each budget update, and an updated Project Schedule. Allowances are to be clearly identified within each budget update on a separate summary level report at each design phase 2.2.4. Value Engineering – Provide technical review and analysis of systems and materials being considered in the design to produce the greatest value for the least cost. Contractor’s value engineering duties shall include, but not be limited to, formulating and evaluating alternative designs, systems, and materials; providing cost estimates of alternatives to be evaluated; evaluating alternatives on the basis of costs, time schedules, availability of labor and materials, and construction feasibility, etc.; and assisting the Architect in the preparation of any written report at the end of the Design Phase summarizing the value engineering activities. 2.2.5. Coordination of Contract Documents - Review the drawings and specifications as they are being prepared, identifying conflicts, errors, and omissions and recommending alternative solutions whenever design details affect construction feasibility or schedules without, however, assuming any of the Architect’s customary responsibilities for design. Forward all comments and recommendations in writing to the Architect for response/action. 2.2.6. Construction Planning - Recommend for purchase and expedite the procurement of long-lead items to ensure their delivery by the required dates. 2.2.7. Division of Work - Make recommendations to the Owner and the Architect regarding the division of the Work in the plans and specifications to facilitate the bidding and awarding of subcontractors and to allow for phased construction, taking into consideration such factors as time of performance, availability of labor, overlapping trade jurisdictions, provisions for temporary facilities, and other matters. 2.2.8. Construction Document Review - Perform final review of plans and specifications with the Architect and Owner to eliminate areas of conflict or misinterpretation and to assure proper coordination, accuracy, and completeness. 2.2.9. Labor - Analyze the types, quantity, and availability of appropriate categories of labor required for various phases of the Project. 3
2.2.10. Bidding – Develop and implement subcontractor pre-qualification criteria and a subcontractor prequalification process with the cooperation and approval of the Owner. As working drawings and specifications are completed, establish bidding schedules and conduct pre-bid conferences to familiarize bidders with bidding documents, management techniques, and any special systems, materials, or methods. Obtain a minimum of three (3) competitive subcontractor bids for each part of the Work, pursuant to bidding procedures acceptable to the Owner. If Contractor is unable to procure the minimum three proposals from subcontractors and suppliers, then Contractor shall submit to Owner reasonable data substantiating its efforts to solicit the minimum number along with whatever bids were obtained for Owner’s review. So long as Contractor, in Owner’s sole discretion, exercised commercially reasonable efforts to solicit the minimum number of bids, then Owner may relieve Contractor of the bid number required hereunder. Analyze all bids, review bids with the Owner and Architect, make recommendations for contract awards, and award subcontractors. The Owner anticipates multiple bid packages will be necessary for the Project phasing and scheduling. 2.2.11. Conferences - Conduct pre-construction conferences with successful subcontractors. 2.2.12. Equal Employment Opportunity - Determine applicable requirements for equal employment opportunity programs for inclusion in Project bidding documents. 2.2.13. Project Management Software – CM/GC shall use Software as the primary tool for Project control, communication, and documentation among the Project participants, including, but not limited to Owner, Architect, and CM/GC. CM/GC submittals made using e-Builder® Software shall accurately reflect the Schedule of Values and CM/GC’s cost accounting. 2.2.14. Analysis of Existing Improvements – Services related to investigation, appraisals or valuations of existing conditions, facilities or equipment; or verifying the accuracy of existing drawings or other Ownerfurnished information. Where necessary, make recommendation for selective demolition in order to uncover hidden existing conditions. When approved by Owner, and in accordance with other terms of this Agreement, perform necessary selective demolition and repair/restore affected conditions as needed to maintain a clean and safe environment. The CM/GC shall without exception maintain a safe environment for students, staff, teachers and public that may use the building prior to completion of the work described in the Construction Documents. 2.3. Cooperation with Architect: The Architect, by the terms of its agreement with the Owner, is obligated to provide reasonable cooperation to the CM/GC in the development of estimates of construction costs and the Guaranteed Maximum Price (“GMP”). Conversely, the CM/GC, by the terms of this Construction Agreement is obligated to provide reasonable cooperation to the Architect in the development of construction cost estimates and the GMP. Additionally, both Architect and CM/GC are obligated to reconcile their respective cost estimates at the completion of each design phase of the Work and in setting the GMP in a timely manner so as not to negatively impact the Project Schedule. 2.4. Construction Phase: As part of the Construction Phase services, the CM/GC will: 2.4.1. Project Control - Supervise the Work of the subcontractors and coordinate the Work with the activities and responsibilities of the Owner and Architect in order to complete the Project in accordance with the Owner’s objectives of cost, time, and quality. 2.4.2. Staffing - Maintain a competent full-time staff, approved by the Owner, at the Project site to coordinate, provide overall direction of the Work, and monitor progress of the subcontractors on the Project. 2.4.3. Organization - Establish, document, and communicate on-site organization and lines of authority in order to carry out the overall plans of the Construction Team. 2.4.4. Coordination - Establish and implement procedures for coordination among the Owner, Architect, subcontractors, and the CM/GC with respect to all aspects of the Project. 2.4.5. Scheduling - Schedule and conduct weekly progress meetings at which subcontractors, the Owner, Architect, and the CM/GC can discuss jointly such matters as procedures, progress, problems, and scheduling. Within twenty-one (21) days from acceptance of the Guaranteed Maximum Price, as defined below, submit three (3) copies of a detailed CPM Schedule for the operations of the CM/GC 4
and subcontractors on the Project, including realistic activity sequences and durations, allocation of labor, materials, and costs, processing of shop drawings and samples, delivery of products requiring long lead-time procurement for approval by the Owner, and a specific number of weather delay days per year for the duration of the Project. Include the Owner’s occupancy requirements in all schedules showing portions of the Project having occupancy priority, if any. The contents and format of the CPM Schedule shall be per the requirements stated in the General Contract Conditions. The schedule shall contain detail appropriate for the Project, including (1) the effective date of the Agreement, (2) each major design milestone, (3) timelines for Owner’s approvals, (4) the date of commencement of the Work, (5) interim schedule milestone dates, (6) an apportionment of the Work by construction activity; and (7) the time required for completion of each portion of the Work. Under no circumstance shall the date of substantial completion be adjusted without an executed Change Order. 2.4.6. Schedule Monitoring - Provide regular monitoring of the schedule as construction progresses. The Contractor shall prepare a three (3) week look ahead schedule each week for review with the Owner, focusing on the in-depth detail of the upcoming weeks activities in a manner that reflects the planned day-to-day activities. The Project Schedule shall be revised by the Contractor at least monthly or when directed to do so more frequently by the Owner. All revised Project Schedules must demonstrate updates and or changes from the previously approved Project Schedule. In the event that the Contractor ever presents a schedule that does not provide for substantial completion to be achieved within the Contract Time, the Contractor shall also present a recovery plan that will allow the Contractor to achieve substantial completion by the Contract Time. The Owner will determine if the recovery plan or the revised schedule shall be accepted. If the Owner elects to accept the revised schedule in writing, it shall become the approved Project Schedule that the Owner will rely upon to make commitments and obligations. Receiving revised schedules at a weekly Contractor meeting or in another format shall not be construed as an acceptance by the Owner. Any revision to the approved Project Schedule requires the Owner’s written approval. 2.4.7. Evaluation - Determine the adequacy of the subcontractors’ personnel and equipment and the availability of materials and supplies to meet the schedule. 2.4.8. Cost Control - Develop and implement an effective system of Project cost control, showing actual costs for activities in process and estimates for uncompleted tasks. Revise and refine the initially approved Project Construction Budget, incorporate approved changes as they occur, and develop cash flow reports and forecasts as needed. 2.4.9. Change Orders - Develop and implement a system for the expeditious review and processing of Change Orders as approved by the Owner. Initiate necessary or desirable changes to the Owner and the Architect, review requests for changes, submit recommendations to the Owner and the Architect, and assist in negotiating Change Orders. The Owner shall not issue any change order or other directive that causes its payment obligations to exceed lawful appropriations to cover the cost thereof. 2.4.10. Permits - Secure or assist the Owner in securing all necessary permits, licenses, and inspections for the proper completion and execution of the Work. 2.4.11. Owner’s Consultants - If required, assist the Owner in selecting, retaining, and coordinating professional services of a surveyor, testing laboratories, and any special consultants. 2.4.12. Superintendent - Keep on the Project, during the progress of the Work, a full-time, competent superintendent and any necessary assistants, all satisfactory to the Architect and the Owner. The superintendent shall not be changed except with the consent of the Architect and the Owner, unless the superintendent proves to be unsatisfactory to the CM/GC and ceases to be in its employ. The superintendent shall represent the CM/GC in its absence and all directions given to the superintendent shall be as binding as if given to the CM/GC. The superintendent shall remain on the Project full-time until all Work is complete, including the punch list. The Architect and the Owner shall not be responsible for the acts or omissions of the superintendent or their assistants. 2.4.12.1. The superintendent shall provide full-time, qualified, and efficient supervision of the Work, using their best skill and attention. Carefully study and compare all drawings, specifications, and other 5
instructions and immediately report to the Architect and the Owner any error, inconsistency, or omission which may be discovered. Inspect the Work of the subcontractors at all stages and at substantial completion and final completion and guard the Owner against defects and deficiencies in such Work. The CM/GC shall be responsible to the Owner for the acts and omissions of all his employees and of all subcontractors, their agents, and employees and all other persons performing any of the Work, for which the CM/GC has supervisory or inspection responsibility hereunder. 2.4.12.2. The superintendent shall see that the Work is carried out in accordance with the Contract Documents and in a thorough and first-class manner in every respect. The CM/GC’s superintendent shall establish all lines, levels, and marks necessary to facilitate the operations of all concerned in subcontract work. The superintendent shall lay out the Work in a manner satisfactory to the Architect, making permanent records of all lines and levels required for excavation, grading, and foundations and for all other portions of the Work. The superintendent shall, together with the Architect, authorize the commencement and certify the proper completion of the various stages of construction. The CM/GC shall be responsible for construction means, methods, techniques, sequences, and procedures and for carrying out the Work in accordance with the Contract Documents. 2.4.13. Safety Measures - Establish procedures and measures for the safety of persons and property at and around the site of the Work. Assure compliance with all federal, state, and local statutes, rules, regulations, and orders applicable to the conduct of the Work. 2.4.14. Contract Interpretations - Refer all questions relative to interpretation of design intent to the Architect in writing. Develop and implement an effective system of tracking the status of questions and responses. 2.4.15. Shop Drawings and Samples - In collaboration with the Architect, establish and implement procedures for expediting the processing and approval of shop drawings and samples. 2.4.16. Reports and Project Site Documents - Record the daily progress of the Project in a daily log available to the Owner and the Architect. Submit on a weekly basis written progress reports and summaries of meetings to the Owner and the Architect, including information on the subcontractors’ work and the percentage of completion. The Contractor shall keep detailed daily logs and submit these logs to the Architect and Owner each week at the O/A/C meetings. The detailed written daily logs shall include a description of the Work performed the previous week. Each such daily report shall be prepared and signed by the project manager or superintendent, on behalf of the Contractor. Each report shall at a minimum include the following information for that day concerning the Contractor and each Subcontractor (including each Sub-subcontractor): materials and equipment being installed, number of individuals working, the hours worked, the type and location of the work being performed by each trade and each item of major equipment being used. The report shall also include other information such as temperature and weather recorded during the work period and any significant events occurring on the job site with regard to the Work or the Project. 2.4.17. Record Sets - Maintain at the Project site, on a current basis, records of all necessary contracts, shop drawings, samples, purchases, materials, equipment, material safety data sheets, maintenance and operating manuals and instructions, and any other documents and revisions thereto which arise out of the Agreement or the Work in the format required by the Owner in its sole discretion. CM/GC shall obtain data from subcontractors and maintain a current set of record drawings, specifications, operating manuals, warranties, and guarantees. At the completion of the Project, submit all such documents to the Architect for delivery to the Owner. 2.4.18. Completion – Inspect and determine completion of the Work or designated portions by subcontractors thereof and prepare for the Architect a list of incomplete or unsatisfactory items together with a schedule for their completion in accordance with the General Conditions. 2.4.19. Start-Up and Training - With the Owner’s maintenance personnel and the Architect, direct the checkout of utilities, operating systems, and equipment for readiness and assist in their initial start-up and testing by the subcontractors. Facilitate all training of Owner’s personnel as required.
6
2.4.20. Substantial and Final Completion - Determine substantial and final completion and provide written notice to the Owner and Architect that the Work is ready for inspection. Include with the written notice a copy of the Architect’s punch list signed off by each responsible party. Secure and transmit to the Architect required guarantees, tax affidavits, certificates, releases, bonds, and waivers. Turn over to the Owner all keys and maintenance stocks. 2.4.21. Warranty - During the two (2) year warranty period at no additional cost to the Owner, perform warranty inspections with the Architect and Owner following provision of timely written notice to the Owner to schedule such inspections, and ensure that Work which proves defective or deficient during such time is corrected either by the subcontractors or such other means as shall be required, at no additional cost to the Owner. 2.4.22. Self-Performed Work – Contractor shall be eligible to self-perform work on the Project as established in the GMP. Contractor shall self-perform the work at Cost plus a mark-up of 10% in addition to the Contractor’s overall Fee. The Contractor shall competitively bid Scopes of Work to a minimum of three (3) Subcontractors for each subcontracted scope of Work unless the Owner agrees otherwise in advance in writing. Once bids are received, the Contractor shall share the results of the bidding process with the Owner and make recommendations on the selection of the Subcontractor or material supplier based on cost, schedule, and other factors that will maximize the success of the total Project. For specific major trades, the Contractor must notify the Owner in a timely fashion when it intends to conduct scope confirmation meetings with the final bidders. The Owner may at its sole discretion elect to participate in scope confirmation meetings with the Contractor and the key Subcontractor. For those trades in which the Contractor is qualified to self-perform the Work, bids from the Contractor for self-performed Work must be submitted to the Owner and Architect a minimum of twenty-four (24) hours prior to bid deadline for subcontractors to be considered for award. The subcontractor selected for an award will be the subcontractor whose bid, as presented in the response to the bidding documents, is the most advantageous to the Owner. The Owner is not bound to accept the lowest priced bid if that proposal is not in the best interests of the Owner as determined by the Owner. 2.5. Additional Services: Additional services shall be performed only upon the express, prior written authorization of the Owner and paid for as provided herein. Additional services shall include the following: 2.5.1. Owner-Furnished Equipment - Services related to Owner-furnished equipment, furniture, and furnishings which are not a part of the Work. 2.5.2. Expert Witness - Preparing to serve or serving as an expert witness in connection with any public hearing or legal proceeding. 2.5.3. After Completion - Inspections of and services related to the Project after completion of the services under this Agreement, other than the above-referenced warranty inspections. 2.5.4. Other - Providing any other service not otherwise included in this Agreement. ARTICLE 3 The Owner’s Responsibilities 3.1. 3.2.
Information: The Owner shall provide full information regarding its requirements for the Project. Owner’s Representative: The Owner shall designate a representative who shall be acquainted with the scope of the Work; has authority to approve budgets and adjustments thereto, as contemplated by Section 2.1.3 within the Project Cost Estimate as established by the Board of Education; render decisions; and otherwise furnish information. In addition, the Owner may hire an Owner’s Representative to assist the Owner with the performance of the Project. In the event that the Owner hires an Owner’s Representative, the Owner’s Representative’s duties and responsibilities will be described in a Consultant Agreement between the Owner and the Owner’s Representative, a copy of which will be furnished to the CM/GC. 7
3.3. 3.4. 3.5. 3.6.
3.7.
3.8. 3.9.
Architect: The Owner shall retain an Architect to provide design services and to prepare construction documents for the Project. The Architect’s services, duties, and responsibilities are described in the Agreement between the Owner and the Architect, a copy of which will be furnished to the CM/GC. Professional Services: The Owner shall furnish such legal services as may be necessary for the benefit of the Owner, and such auditing services as it may require. Documentation: The CM/GC will be furnished, without charge, all copies of drawings and specifications reasonably necessary for the execution of the Work. Defects: If the Owner becomes aware of any default or defect in the Project or non-conformance with the Contract Documents, it shall give prompt written notice thereof to the CM/GC. This provision shall not, however, charge the Owner with any obligation to make inspections and shall in no manner be construed to discharge or modify the CM/GC’s obligations to supervise, inspect, and to otherwise complete the Project in accordance with the Contract Documents. Surveys and Special Testing: So far as the Project contemplated by this Agreement may require, the CM/GC shall be entitled to information giving a complete and accurate survey of the building site and the existing grades and lines of streets, pavements, and adjoining properties; information as to the rights, restrictions, easements, surface water courses, boundaries, and contours of the building site; and full information as to existing sanitary sewer, storm sewer, water, gas, and electrical services. The Owner, at its expense, shall furnish all such data, upon request. The Owner likewise shall pay for all borings or test pits and for any mechanical, chemical, or other tests as well as professional verifications and inspections incident to proper appraisal of the site for the contemplated structure. A copy of all reports of such tests and borings shall be filed with the Owner and shall be available to the CM/GC, upon request. Owner’s Expenses: The services, information, surveys, and reports required by Sections 3.3 through 3.5 and 3.7 shall be furnished at the Owner’s expense. Project Management Software: Owner shall provide CM/GC with a license to access Owner’s web-based Trimble Unity Construct Software and shall provide CM/GC one day of training for same. ARTICLE 4 Subcontracts
4.1.
4.2.
4.3.
4.4.
Bidding: All Work, except that portion commonly referred to as “General Condition Costs” set forth in Section 8.2.1, shall be competitively bid pursuant to procedures acceptable to the Owner, except for Work performed by CM/GC as approved by Owner in accordance with Section 4.2. CM/GC shall include miscellaneous scopes of Work not being bid in periodic budget estimates, as well as the proposed GMP prepared by the CM/GC. Such scopes shall be approved by Owner at the time of GMP execution. Award: The CM/GC shall request and receive proposals from subcontractors and subcontracts will be awarded by the CM/GC after the proposals are reviewed by the CM/GC with the Architect and Owner. The CM/GC shall be authorized to submit proposals for portions of the Work only with the prior written consent of the Owner. Substitution: If the Owner refuses to accept a subcontractor recommended by the CM/GC, the CM/GC shall recommend an acceptable substitute. The Guaranteed Maximum Price (GMP), if applicable, shall be increased or decreased by the difference in cost occasioned by such substitution and an appropriate Change Order shall be issued. Forms: The form of the subcontract, including the General and Supplementary Conditions applicable thereto, shall be satisfactory to the Owner, Architect, and the CM/GC. ARTICLE 5 Contract Time Schedule
8
5.1. 5.2. 5.3. 5.4.
5.5.
Schedule: The services and Work to be performed under this Contract shall be in general accordance with the Contract Time Schedule attached hereto as Schedule 1. Time of Completion: This date shall be established at the time the GMP is established or prior to the award of any subcontracts if a GMP is not established. Revision: At the time a GMP is fixed, as provided for in Article 6, a new Contract Time Schedule shall also be established. Delays and Extension of Time: If the CM/GC is delayed at any time in the progress of the Work by any act or neglect of the Owner or the Architect or by any employee of either; or by any separate contractor employed by the Owner; or by changes ordered in the Work; or by labor disputes, fire, unusual delay in transportation, unavoidable casualties, or any causes beyond the CM/GC’s control; or by delay authorized by the Owner, the Contract Time Schedule shall be extended by Change Order for such reasonable time as the Owner may determine. All requests for extension of time or claims for extra costs occasioned by delays or neglect shall be subject to the Owner’s approval and shall be made in writing to the Owner no more than seven (7) days after the occurrence of the delay or event causing the extra costs; otherwise they shall be waived and barred. Liquidated Damages: The CM/GC understands and agrees that the completion of the entire Project within the time specified is an essential feature of this Agreement and that the Owner will sustain substantial damages, the amount of which is not possible to accurately determine at the time of contracting and which may be difficult to prove, if the Work is not so completed. The CM/GC, therefore, agrees to proceed with due diligence, taking all precautions and making all necessary arrangements to ensure the completion of the Work within the prescribed time. The CM/GC further agrees that his failure to fully and finally complete the Work within the time allowed shall be considered a material breach of this Agreement and shall entitle the Owner to collect liquidated damages for the delay in completion in accordance with the General Conditions in the sum of one thousand dollars ($1000.00) per calendar day. ARTICLE 6 Guaranteed Maximum Price
6.1.
6.2. 6.3.
Establishment: When the design, plans, and specifications are sufficiently complete to make the final cost estimates and after subcontract bids have been received, the CM/GC shall prepare and submit for Owner’s review and approval a Guaranteed Maximum Price (“GMP”), guaranteeing the maximum cost to the Owner for the Cost of the Work and the CM/GC’s Fees. Such GMP will be guaranteed by the CM/GC, subject only to modification for Changes in the Work as provided in Article 9 and for additional costs arising from delays caused by the Owner or the Architect. Following acceptance of the GMP by the Owner, the Owner and CM/GC shall execute the Guaranteed Maximum Price Amendment, amending this Construction Agreement, a copy of which will be provided to the Architect. Execution of the Guaranteed Maximum Price Amendment by the CM/GC is a representation that the Contractor has visited the Project site, become generally familiar with local conditions under which the Work is to be performed including but not limited to climatic, geographical and topographic conditions, and correlated personal observations with requirements of the Contract Documents. The CM/GC has assessed and is satisfied with the qualifications, suitability and availability of potential subcontractors and labor, material and equipment suitability and availability to satisfy the requirements of the Contract Documents. Subcontracts: When the CM/GC provides a GMP, the subcontracts will contain the necessary provisions to allow the CM/GC to control the performance of the Work. Savings: To the extent that the final Cost of the Work, as herein defined, and the CM/GC’s Fees are less than the GMP, the savings shall accrue to the Owner.
9
6.4.
Option to Terminate: In the event that the CM/GC and the Owner do not agree on the GMP, then the Owner may terminate this Agreement without signing the GMP. In such event, Owner shall pay CM/GC the Design Phase Fee and Owner shall have no further obligation to CM/GC. 6.5. GMP Proposal: A GMP Proposal to Owner shall include the following, unless the parties mutually agree otherwise: 6.5.1. A proposed GMP; 6.5.2. An itemization of the GMP broken down by detail and accompanied by supporting documentation (including, for example, bid tabulations and estimating take off sheets) which includes but is not limited to the following: 6.5.2.1. All prices received for every item bid before the establishment of the GMP and a total of such bids; 6.5.2.2. The maximum cost of all work to be self-performed by the CM/GC; 6.5.2.3. The CM/GC’s Construction Phase Fee and Design Phase Fee; 6.5.2.4. The General Condition Costs, itemized and with supporting documentation and information in accordance with Section 8.2.1 of the Agreement; 6.5.2.5. The installation cost of items to be procured by Owner and assigned to CM/GC for installation; 6.5.2.6. Cost of Work performed by subcontractors and a list of subcontractors with their respective license numbers; 6.5.2.7. CM/GC GMP Contingency, in accordance with Section 8.2.4 of the Agreement. 6.5.3. A schedule of the list of drawing, specifications, and addenda, including a schedule of Requests for Information asked and answered; 6.5.4. A list of the assumptions and clarifications made by CM/GC in the preparation of the GMP; 6.5.5. A revised Contract Time Schedule, pursuant to Section 5.3 of the Agreement, listing delivery schedule with summary milestone delivery items, itemized breakdown of Work scope, and submittal due dates with responsible party; 6.5.6. The scheduled substantial completion date and final completion date upon which the proposed GMP is based, to the extent said date has not already been established under Section 2.2.20 hereof, and a schedule upon which the scheduled substantial completion date and final completion date are based; 6.5.7. CM/GC Insurance Certificates; 6.5.8. CM/GC Performance Bond; 6.5.9. CM/GC Labor and Materials Payment Bond; 6.5.10. Alternate Prices; 6.5.11. Unit Prices; 6.5.12. If applicable, a list of allowances and a statement of their basis and a statement that, to the best of CM/GC’s knowledge, the cost pertaining to such allowance item is a reasonable estimate taking into account (i) the Project plans and other Contract Documents existing at the time the allowance estimate is made; (ii) the labor and material standards and construction means, methods and techniques prevailing in the industry for projects similar to the Project; and (iii) the level of labor and material costs generally prevailing in the locality of the Project at the time the allowance estimate is made, and allowances shall include the CM/GC’s Fee; 6.5.13. Equipment Rental Rate Schedule; 6.5.14. General Conditions of the Contract with Safety Addendum; 6.5.15. Schedule of Values; 6.5.16. Boulder Valley School District Asbestos Management Plan Contractor Responsibility form; 6.5.17. List of all salaried staff to be assigned and charged to the Cost of the Work as established in the Agreement; 6.5.18. If applicable, a state of Additional Services; 6.5.19. A time limit for acceptance of the GMP Proposal; 6.5.20. A high level Budget Summary; 6.5.21. Approved Labor Burden Rates; 6.5.22. A list of the clarifications and qualifications; 10
6.5.23. A detailed critical path Project Schedule including the dates of substantial completion and final completion; 6.5.24. CM/GC provided equipment along with billable rates; and 6.5.25. All Owner Accepted Alternates. 6.6. Limitation: The GMP shall not exceed the Project Construction Budget with the exception of Ownerapproved changes in the Work. In fixing a GMP, Contractor shall use Value Engineering to identify cost effective changes in the Owner’s specifications that will reduce the GMP without impairing essential functions or characteristics, rebid certain trades, or work with the Architect to bring the Project within the Project Construction Budget. The CM/GC shall not receive any profit or additional fee for work performed to propose a GMP that is within the Project Construction Budget, subject to Owner-approved changes in the Work. ARTICLE 7 Construction Manager/General Contractor’s Fee 7.1.
Determination: In consideration of the performance of this Agreement, the Owner agrees to pay the CM/GC in current funds as compensation for his services a CM/GC’s Fee as set forth in Section 7.1.1 and, if applicable, in Section 7.1.2. 7.1.1. Design Phase Fee - For the performance of the Design Phase services, as defined in Section 2.1, a fee of thirteen thousand twenty-nine dollars ($13,029.00), which shall be paid monthly, in equal proportions, based on the scheduled Design Phase time. 7.1.2. Construction Phase Fee – After Owner’s approval and acceptance of the Guaranteed Maximum Price in accordance with Article 6, CM/GC shall be paid for Work or services performed during the Construction Phase, as defined in Section 2.3, a fee of seven and eighty-four hundredths percent (7.84%) of the Cost of the Work. The Construction Phase Fee shall be due and payable in proportion to the ratio that the monthly payment for the Cost of the Work bears to the total Cost of the Work, subject to retainage as provided in the Contract Documents. Any balance of this fee shall be paid at the time of final payment. 7.1.3. Not Included in Fee. Contractor’s Fee shall not be calculated on the costs associated with insurance premiums, bonds, Subcontractor default insurance, if any, or any lump sum design or preconstruction services fee paid by Contractor. 7.2. Adjustments: Adjustments in Fee shall be made as follows: 7.2.1. Change Orders - For changes in the Work as provided for in Article 9, the CM/GC’s Fee shall not be adjusted unless the change involves a substantial change in the scope of the Work and unless the total accumulated cost of Change Orders exceeds three percent (3%) of the GMP. If changes involve a substantial scope of Work change and the total accumulated cost of Change Orders exceeds three percent (3%) of the GMP, a fee of three percent (3%) of the cost of the change shall be added to the Fee. A “substantial change in the scope of the Work” for purposes of this paragraph is defined as follows: 7.2.1.1. Change Orders involving the purchase of new or additional products of a type and nature not previously specified or contemplated for incorporation into the Work. 7.2.1.2. Change Orders involving the procurement of additional subcontractors, not previously contemplated by the Contract Documents. 7.2.1.3. Changes involving Work in different buildings or at different sites other than as specified in the Contract Documents. 7.2.2. Delays - For delays in the Work, other than for weather, in excess of seven (7) calendar days and which are not the responsibility of the CM/GC, there may be an equitable adjustment in the Fee to compensate the CM/GC for verified and documented increased expenses; provided, however, that CM/GC demonstrates to Owner that the delay in the performance of the portion of the Work had an impact on the Project schedule’s critical path. 11
7.2.3.
Additional Services - Additional services, as described in Section 2.4 shall be computed as follows: Labor: *Direct Personnel Expense (base wage) times 1.58. Expenses: Actual cost. 7.2.4 Adjustments to General Conditions Costs. Adjustments, if any, to General Conditions Costs in a Change Order shall be subject to the limitations set forth in Section 8.2.1.23. 7.3. Items Included in Fee: Included in the CM/GC’s Fee for the Construction Phase are the following: 7.3.1. Profit - Before tax profit. 7.3.2. Overhead - Off-site costs for general management of the Project including: 7.3.2.1. Salaries or other compensation of the CM/GC’s employees at the principal office and branch offices to provide support in scheduling the Work, cost estimating, cost accounting, processing payment requests, processing Change Orders, processing shop drawings/samples, etc. 7.3.2.2. General operating expenses of the CM/GC’s principal and branch offices other than the field office. 7.3.2.3. Any part of the CM/GC’s capital expenses, including interest on the CM/GC’s capital employed for the Work. 7.3.2.4. Costs due to any negligence, or the reckless or intentional act or omission of the CM/GC, any subcontractor, anyone directly or indirectly employed by any of them, or for whose acts any of them may be liable, including, but not limited to, the correction of defective or nonconforming Work, disposal of materials and equipment wrongly supplied, or making good any damage to property. 7.3.2.5. Overhead or general expenses of any kind, except as may be expressly included in Article 8. 7.3.2.6. Costs in excess of the GMP, if any, as set forth in Article 6 and adjusted pursuant to Article 9. 7.3.3. Discretionary Compensation – Bonuses and discretionary compensation paid by Contractor to its personnel. 7.3.4. Risks – Costs arising from unforeseen difficulties that may be encountered during the prosecution of the Work until the final acceptance by the Owner, including all risks of every description connected with the prosecution of the Work and loss or damage arising from the nature of the Work or from the action of the elements. ARTICLE 8 Cost of the Work 8.1.
Definition: The term Cost of the Work shall mean costs necessarily incurred in the proper performance of the Work during either the Design or Construction Phase, and paid by the CM/GC. Such costs shall be at the lowest responsible competitive rates not higher than the standard paid in the locality of the Work except with prior consent of the Owner, and shall include the items set forth below in this Article. The Owner agrees to pay the CM/GC for the Cost of the Work as defined in this Article 8. Such payment shall be in addition to the CM/GC’s Fee stipulated in Article 7. 8.2. Cost Items Included: On-site costs of the Work including General Conditions and the aggregate cost of subcontracts. 8.2.1. General Condition Costs - Those costs for Work outlined in the General Conditions of the Contract that are the responsibility of the CM/GC unless specific items of Work are included in subcontract work. 8.2.1.1. Wages paid for labor in the direct employ of the CM/GC in the performance of the Work as set forth in the GMP Proposal, except that wages paid for labor shall not include Contractor’s Fee, vehicle allowance, cell phones or administrative mark-ups directly within wages, salaries or hourly billing rates. The names, positions, and estimated costs of the individuals for the duration of the Work that are anticipated to be assigned to this Project shall also be specified in the GMP Proposal. 8.2.1.2. Cost of ordinary employee benefits and taxes, such as pension contributions, hospitalization, vacations, medical insurance, assessments, or taxes for such items as unemployment compensation and Social Security, insofar as such cost is based on wages, salaries, or other remuneration paid to employees of the CM/GC and included in the Cost of the Work.
12
8.2.1.3. The proportion of reasonable transportation, traveling, and hotel expenses of the CM/GC or of his officers or employees incurred in discharge of duties connected with the Work, when the necessity for such expenditures is approved in advance by the Owner. 8.2.1.4. Cost of all materials, supplies, and equipment incorporated in the Work, including costs of transportation thereof. 8.2.1.5. Cost, including transportation and maintenance, of all materials, supplies, equipment, and hand tools not owned by the workmen employed by the CM/GC, which are employed or consumed in the performance of the Work and cost less salvage value on such items used but not consumed which remain the property of the CM/GC. 8.2.1.6. Rental charges of all necessary construction machinery and equipment, exclusive of hand tools and other items customarily owned by CM/GC or workers, used at the site of the Work, whether rented from the CM/GC or other, including installation, repairs and replacements, dismantling, removal, costs of lubrication, transportation and delivery costs thereof, at rental charges consistent with those prevailing in the area. All equipment which the CM/GC intends to rent to the Owner and the rates therefor must be approved by the Owner in writing prior to use. 8.2.1.7. Intentionally deleted. 8.2.1.8. Unavoidable sales taxes, if approved in writing in advance by the Owner. 8.2.1.9. Permit fees, licenses, tests, and royalties. 8.2.1.10. Minor expenses such as long distance telephone calls, telephone service at the site, expressage, and similar petty cash items in connection with the Work. 8.2.1.11. Cost of removal of all debris, snow removal, interim and final cleaning. 8.2.1.12. Costs incurred due to an emergency affecting the safety of persons or property, to the extent not compensated by insurance or otherwise, and not attributable to the fault of the CM/GC or his subcontractor. 8.2.1.13. Cost of site security during construction, if requested by the Owner, and the cost of site safety measures, such as fences, signs, and barricades. 8.2.1.14. Cost of computer services as required at the field office. 8.2.1.15. Cost of construction support activities such as Work items included in the General Conditions of the Contract and in the specifications unless they are provided by subcontractors. 8.2.1.16. The cost of adequate, weatherproofed, heated, and well-lighted office space with telephone service at the site of the Work for the use of the CM/GC and the Architect and Owner representatives. 8.2.1.17. The cost of providing and maintaining neat, sanitary, and adequate temporary toilet facilities for all personnel at the construction site. 8.2.1.18. The cost of providing suitable temporary facilities and quarters for workmen when the necessity for such expenditures is approved in advance by the Owner, and of maintaining on premises water-tight storage sheds and tool houses for storage of building materials and tools. The Owner may use the storage sheds and tool houses for the reasonable storage of Owner-provided materials and equipment for the Project at no additional cost. 8.2.1.19. The cost of providing all temporary facilities required to supply all the power, light, water, and heat needed for the proper execution and completion of the Work. Unless provided by subcontractors, the cost of all power, light, water, and heat for the duration of the Work. 8.2.1.20. The cost of providing temporary weather protection and temporary heating as required for the expeditious prosecution of the Work. 8.2.1.21. Other costs incurred in the performance of the Work if and to the extent approved in advance in writing by the Owner. 8.2.1.22. All costs directly incurred in the performance of the Work and not included in the CM/GC Fee as defined in Article 7. 8.2.1.23. General Conditions Costs Limitations. General conditions costs shall be compensated at their direct cost based on documentation submitted by CM/GC substantiating such amounts claimed. The general conditions costs submitted in Contractor’s proposal are considered a “Not-to-Exceed” value and shall 13
be finalized as such in the GMP for each Project. Changes to the general conditions costs must be authorized by Change Order executed by the Owner and issued in accordance with the Contract Documents. Final general conditions/general requirements costs for a Project cannot be transferred to any other Project. 8.2.2. Subcontracts - The cost of Work performed by subcontractors. 8.2.3. Estimates - The CM/GC shall include a detailed and itemized estimate of General Condition costs as a part of each estimate for the Cost of the Work. After the Contract Documents have been completed and before Work is released for bidding, the CM/GC shall prepare an estimate of the Cost of the Work that provides a subtotal of costs for each subcontract package and includes the costs for General Conditions. 8.2.4. Contingency –The CM/GC shall include in the GMP proposal its contingency to cover those costs considered reimbursable as the Cost of the Work but not included in a Change Order. Cost overruns in excess of the amount of the CM/GC Contingency will be borne by the CM/GC, unless the GMP is adjusted pursuant to the terms of the Agreement. CM/GC’s Contingency shall not exceed five percent (5%) of the Guaranteed Maximum Price. 8.2.4.1. The CM/GC shall advise the Architect and the Owner in writing prior to applying a part of the CM/GC Contingency to an item within the Cost of Work. Owner shall issue written approval to CM/GC for application of the amount from the CM/GC Contingency. The CM/GC shall fully document the change on its copy of the Construction Documents that will become part of the record documents. 8.2.4.2. The Owner shall not unreasonably withhold approval of a zero dollar Change Order to utilize the CM/GC’s Contingency so long as (a) the contingency amount accessed does not cause the Guaranteed Maximum Price to be exceeded (b) the CM/GC utilizes the CM/GC’s Contingency for items required for the Project that are not otherwise recoverable as Costs of the Work under the Contract Documents, and (c) the CM/GC’s Contingency is used for any items outlined in clauses 8.2.4.2.1 through 8.2.4.2.3 below: 8.2.4.2.1. Scope of the Work that is unclear, incomplete or conflicting on the Contract Documents but is Work consistent with the Contract Documents and reasonably inferable as being necessary to produce the intended results for a complete Project. 8.2.4.2.2. Additional resources necessary to recover lost time. If overtime is required to maintain the schedule, the CM/GC shall obtain the Owner’s prior written approval before moving forward with such overtime. 8.2.4.2.3. Delays caused by market, labor, material or transportation conditions, labor disputes, abnormal weather or other causes which are costs of the Work but do not justify an increase in the GMP. 8.2.4.3. CM/GC’s Contingency is not available for use by the CM/GC for mistakes that result from Self-Perform Work secured through competitive bidding, mistakes of subcontractors or material suppliers, or any warranty work. The CM/GC’s Contingency is not available for use by the Owner for allowance overruns, changes in the Scope of Work, differing or changed site conditions. 8.2.4.4. The CM/GC shall maintain a complete CM/GC Contingency log acceptance detailing the expenditure of funds from the CM/GC Contingency. Upon final acceptance of Project by Owner, any amounts remaining in the CM/GC Contingency shall be deducted from final payment to, or any monies due, CM/GC. The CM/GC shall report and reconcile the CM/GC’s Contingency to the Owner on a monthly basis. 8.3. Additional Costs: 8.3.1. Cost of the premiums for all bonds and insurance which are required by the Contract Documents. 8.3.2. Payments to the Architect and CM/GC’s Consultants. 8.4. Allowance Log: The CM/GC shall separately track, on no less than a monthly basis, all materials and equipment provided under allowances including, but not limited to, (i) a description of the allowance; (ii) amounts actually spent for each allowance; and (iii) variances between allowance amounts in the Cost of the Work and amounts actually spent.
14
ARTICLE 9 Discounts All discounts for prompt payment shall accrue to the Owner to the extent the Costs of the Work are paid directly by the Owner or from a fund made available by the Owner to the CM/GC for such payments. To the extent the Costs of the Work are paid with funds of the CM/GC, all cash discounts shall accrue to the CM/GC; provided, however, that all costs claimed pursuant to Article 8, billed to the Owner, reflect such discounts. All trade discounts, rebates, and refunds, and all returns from sale of surplus materials and equipment, shall accrue to the Owner, and the CM/GC shall make provisions so that they can be secured. ARTICLE 10 Miscellaneous Provisions 10.1. 10.2.
10.3. 10.4. 10.5.
10.6. 10.7.
10.8.
Assignment: Neither party to this Agreement shall assign its interests herein in whole or in part without the written consent of the other; nor shall the CM/GC assign any moneys due or to become due to him hereunder, without the previous written consent of the Owner Independent Contractor: The CM/GC understands and acknowledges that an employee-employer relationship does not exist between the CM/GC and the Owner. The CM/GC shall perform all Work, using independent judgment and expertise, as an independent CM/GC and not as an employee of the Owner. Neither the CM/GC nor any agent, employee or subcontractor of the CM/GC shall be an agent or employee of the Owner nor shall any of them have any authority, express or implied, to bind the Owner to any agreement or incur any liability or obligation attributable to the Owner. The CM/GC acknowledges that it is not entitled to workers’ compensation or other benefits from the Owner and that the CM/GC is obligated to pay federal and state income tax on any moneys earned from the Owner pursuant to this Construction Agreement. Binding Effect: This Agreement shall be binding upon the heirs, personal representatives, successors, and assigns of the respective parties. Controlling Law: This Agreement is being executed and is to be performed in the State of Colorado, and shall be enforced and construed according to the laws of the State of Colorado. Waiver: No waiver of any breach of any one of the agreements, terms, conditions, or covenants of this Agreement by a party shall be deemed or imply or constitute a waiver of any other agreement, term, condition, or covenant of this Agreement. The failure of a party to insist on strict performance of any agreement, term, condition, or covenant, herein set forth, shall not constitute or be construed as a waiver of such party’s rights thereafter to enforce any other default; neither shall such failure to insist upon strict performance be deemed sufficient grounds to enable the other party to forego or subvert or otherwise disregard any other agreement, term, condition, or covenant of this Agreement. Severability: If any provisions of this Agreement are finally determined by a court of competent jurisdiction to be in violation of any statute or rule of law, then such provisions shall not apply in such instances, but the remaining provisions shall be given effect in accordance with their terms. Notices: Any notices required or permitted under this Agreement shall be deemed given when personally delivered or when deposited in the United States certified mail, postage prepaid and addressed to Owner: Attention: Chief Operations Officer, 6500 East Arapahoe Avenue, Boulder, Colorado 80301, or to the CM/GC at the address set forth below. Counterparts: This Agreement may be executed in several counterparts. Each counterpart shall be deemed an original but all counterparts together shall constitute one and the same instrument. For purposes of executing this Agreement, facsimile or scanned signatures shall be as valid as the original.
15
IN WITNESS WHEREOF, the parties have executed this Agreement on the day and year first above written and shall extend to and bind the parties, their successors, assigns, and personal representatives. CONSTRUCTION MANAGER / GENERAL CONTRACTOR James R. Howell & Co., Inc. dba Howell Construction 8085 E. Harvard Ave., Denver, CO 80231
Legal Name and Address
DISTRICT: BOULDER VALLEY SCHOOL DISTRICT RE-2 6500 Arapahoe, PO Box 9011, Boulder, CO 80303
Kris D Stoppenhagen
Kris D Stoppenhagen (Dec 12, 2025 14:31:50 MST)
Signature of Authorized Officer
Todd Johnston, Operations Manager
Printed Name of Signatory
Kris Stoppenhagen, Executive Director of Bond Planning & Construction Kathleen Sullivan (Dec 11, 2025 16:32:10 MST)
Kathleen Sullivan, Legal Review
16
EXHIBIT A The following 15 pages are the RFP and Addendums
17
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER/GENERAL CONTRACTOR SERVICES RFP 26-04 CM/GC Project Scope #1 – Nederland Elementary School and Nederland Middle-Senior High School August 21, 2025 I. Introduction Boulder Valley School District (District) seeks proposals from prequalified construction managers / general contractors (CMGCs) for CMGC services for the project identified in Attachment A (Project) to this Request for Proposal (RFP). Participation in this RFP shall be by District invitation only. This RFP is to award the two (2) projects to one (1) CMGC (see Attachment A) Please note: Each project will require a separate agreement and costs, budgeting, accounting, etc. must be tracked independently for each project. II. Acceptance of Terms and Conditions, including form CMGC Agreement and General Conditions The District is issuing this RFP to CMGCs who were prequalified in response to the District’s Request for Qualifications No. 23-23 Construction Manager / General Contractor (CMGC Services RFQ). By submitting a proposal in response to this RFP, CMGCs acknowledge and accept that they are still bound by the terms and conditions of the CMGC Services RFQ (except as modified by this RFP) and their statement of qualifications (except as modified in response to this RFP). In order to adhere to the estimated timelines set forth herein, and notwithstanding anything to the contrary in the CMGC Services RFQ and/or the CMGC’s statement of qualifications, the District will not accept modifications to its form CMGC Agreement or the accompanying General Conditions. By submitting a proposal in response to this RFP, CMGC agrees that, if it is selected for an award of contract, it will sign the District’s form CMGC Agreement. The District may reject proposals that do not comply with this requirement. If the successful CMGC and the District are not able to enter into the form CMGC Agreement, then the District may cancel the award and award the contract to another CMGC or exercise any of the rights available to it under this RFP. III. Project Description and Estimated Delivery Schedule A description of the Project, including the school, address, architect, construction budget, and other additional information, is set forth in Attachment A. The successful CMGC shall perform those items set forth in the CMGC Proposal Form (see Attachment B) and CMGC Matrix (see Attachment C). Using proceeds from the District Bond Program, the District will implement the Project in accordance with the District Educational Facilities Master Plan (Master Plan), the Requirement List Report By Priority created by VFA, Inc. (see Attachments D & E), and the Asbestos Hazard Emergency Response Act (AHERA) (see Attachment H) as applicable.
BOULDER VALLEY SCHOOL DISTRICT RE-2 REQUEST FOR PROPOSALS NO. 26-04 August 21, 2025
The RFP timeline and estimated delivery schedule for the Project is as follows: Date A) RFP Timeline RFP Issue Date August 21, 2025 August 27, 2025 A pre-proposal submission conference / Walk through / st Etc. will be held at 1 Location: Nederland ES (1 Sundown 2:30 PM MST – 1st Location Trail, Nederland, CO 80466). 2nd Location: Nederland MS- 3:15 PM MST – 2nd Location HS (597 Co Hwy 130, Nederland, CO 80466). Attendance at both locations is Mandatory. If you do not attend both locations your proposal will not be accepted. RFP Inquiries Due RFP Addendum Sent RFP Submission Deadline RFP Evaluation / Award (the team may want clarifying information during this review and may contact you at this time) RFP Finalists Interviews B) Project Milestones (Nederland ES) CMGC Contract Award Post-Award Meetings with Project Manager Design Advisory Team Meetings (Frequency will be determined by project needs. Anticipate 5 meetings for these scopes.) Schematic Design Complete Design Development Complete Design Advisory Team final meeting Construction Documents Complete GMP Amendment to District Board of Education (A complete and signed GMP Amendment is needed as least 10 business days prior to this date) Construction Commences Substantial Completion – Temporary Certificate of Occupancy Construction Final Completion
2
September 3, 2025 @ 10:00 AM MST September 8, 2025 by 3:00 PM MST September 17, 2025 @ 10:00 AM MST September 26, 2025 @10:00 AM MST TBD
October 2025 October 2025 December 2025 – April 2026 (estimated) February 13, 2026 March 16, 2026 August/September 2026 September 14, 2026 October 2026
Spring 2027 August 1, 2027 September 2027
BOULDER VALLEY SCHOOL DISTRICT RE-2 REQUEST FOR PROPOSALS NO. 26-04 August 21, 2025
C) Project Milestones (Nederland MS-HS) CMGC Contract Award Post-Award Meetings with Project Manager Design Advisory Team Meetings (Frequency will be determined by project needs. Anticipate 5 meetings for these scopes.) Schematic Design Complete Design Development Complete Design Advisory Team final meeting Construction Documents Complete GMP Amendment to District Board of Education (A complete and signed GMP Amendment is needed as least 10 business days prior to this date) Construction Commences Substantial Completion – Temporary Certificate of Occupancy Construction Final Completion
3
October 2025 October 2025 December 2025 – April 2026 (estimated) February 13, 2026 March 16, 2026 August/September 2026 September 14, 2026 October 2026
Spring 2027 August 1, 2027 September 2027
BOULDER VALLEY SCHOOL DISTRICT RE-2 REQUEST FOR PROPOSALS NO. 26-04 August 21, 2025
Scheduling Note: This schedule is the District’s best available estimation as of the date of this RFP. It is the District’s desire to accelerate design and construction schedules where reasonably possible, without adverse cost or safety impacts. Scheduling is subject to alternative proposals submitted by CMGC respondent and to joint decisions on phasing and/or accelerating the work. BVSD will consider alternate schedules for specific scopes of work based on the location of these schools. Contractors are encouraged to propose schedule options that support achieving substantial completion (school occupancy) for each project by August 1, 2027. For example, identify any scopes that could be completed ahead of summer 2027. The Project design will be guided by a site-based Design Advisory Team (DAT) that will meet with the selected CMGC, architectural firm (if applicable) and Bond project manager approximately bi-weekly through design development, except over the summer. Firms are requested to familiarize themselves with the revised version of the Bond Program’s Design Advisory Team Guidelines which can be found at: https://bond.bvsd.org/fs/resourcemanager/view/925e7d4a-74a9-43a6-bc90-04c82475c052. IV. Proposal Requirements A. Proposal Format Proposals shall be in the following format and shall adhere to the page limitations, if any: 1) General Information a) Front/Cover Page (1-3 pages) which shall include the following information: i) Firm’s name ii) Firm’s address iii) Date of the submittal iv) The name of the person(s) authorized to make representation for the firm and that person’s mailing address, email address, and telephone number v) Name and phone number of person(s) available to answer evaluation team questions (see Section III A) b) Table of Contents (1 page, optional). c) Completed and fully executed Declaration and Signature Page, see Attachment J (1 page) d) Cover Letter (1 page, optional) e) Material Changes to Prequalification in RFQ 23-23 (pages as needed): i) If material changes have occurred with respect to the information set forth in the Prequalification Statement, please identify all such changes. If there are none, please state “No material Changes to Prequalification” 2) Describe your company’s and team’s experience and approach with this type of project (1-8 pages). a) Describe your understanding of the work required for this project and how you will approach the schedule.
4
BOULDER VALLEY SCHOOL DISTRICT RE-2 REQUEST FOR PROPOSALS NO. 26-04 August 21, 2025
i) Schedule Development - Using the milestones Information from the RFP, project Information from Attachment A, and other information provided to as part of this RFP, describe your approach to meet the schedule and project specific required services ii) Provide a conceptual schedule and phasing plan for each project/school. Due to the location of these projects the CM/GC is encouraged to provide recommendations for schedule modifications. b) Describe your methodology for the following: i) How to streamline communication to ensure the education environment is not impacted ii) Establishing a Guaranteed Maximum Price Special note: Since the RFP is for two projects/schools awarded to the same CMGC please provide clarification in your response outlining how you will fulfill this requirement. 3) Composition of Proposed Team (1-4 pages plus resumes) for each school/project a) Identify the firm’s specific personnel proposed for the project and their participation through the project from pre-construction through completion. i) Indicate the title and assignment, role or area of responsibility of each individual, by name. ii) Identify the person(s) who would attend the Project’s DAT meetings for your firm. iii) Team members resumes (pages as needed but maximum of 1 page per individual) iv) Describe how the team member’s qualifications align with the anticipated services required for delivering the projects successfully. v) Three references per individual for similar type of projects b) The proposed team submitted with this proposal will remain intact for the duration of the project. Please state in your response “Unless a member of the proposed team submitted in this RFP leaves the employment of our company or a change in the team is approved by the BVSD Project Manager and BVSD Executive Director of Bond Planning & Construction in writing the team submitted remain intact for the duration of the project.” If a member of the team changes, BVSD will require resume(s) for new team members and an interview with the full team. Acceptance of the proposed substitution(s) will be at the discretion of BVSD based on evaluation of qualifications. Special note: Since the RFP is for two projects/schools awarded to the same CMGC please provide clarification in your response on whether you will be proposing two teams (one for each school), a single team, or some combination. 4) A Please provide a written acknowledgement that you have reviewed Attachment I “Pay Application Requirement Checklist” and that you will: a) Include all applicable information and backup documentation listed in the Attachment J checklist and as required in the 2022 Bond General Contract Conditions when submitting Pay Applications. b) Submit in a timely manner and Invoices and / or costs submitted on pay applications that are greater than 90 days old may be deducted from payments and subject to independent audit at CM/GC expense. Pay applications for the prior month will be submitted to BVSD by the 15 th day of the current month for review and processing.
5
BOULDER VALLEY SCHOOL DISTRICT RE-2 REQUEST FOR PROPOSALS NO. 26-04 August 21, 2025
5) Fee Proposal (Attachments B1, B2 & C1, C2) submitted on the excel files provided. Vendors shall not reference their fee proposal in their response: a) The CMGC Agreement will be a bonded contract with a Guaranteed Maximum Price to encompass all construction work for the Project. b) Vendor shall provide a Fee Proposal for the Project for which the vendor seeks award on the excel files provided. Submit a fully executed copy of Attachments B1, B2 (CMGC Proposal Form) and breakdown of General Condition costs - Attachments C1, C2 (CMGC Matrix). The Fee Proposal shall be a legally binding offer to perform the CMGC services for the Project for a period of no less than six (6) months from the date of the submission deadline. The District may reject Fee Proposals that exceed available funds, but reserves the right to negotiate a reasonable fee for services within the available funds. The District reserves the right to negotiate the final price for services. c) The Fee Proposal shall include all services requested in this RFP. The District may reject as nonresponsive Fee Proposals that exclude services required in the RFP and its attachments. Fee Proposals shall include all fees, costs and expenses as outlined in the CM/GC Proposal Form set forth in Attachments B1, B2 and CM/GC Matrix set forth in Attachments C1, C2. Estimated proposal prices are not acceptable. B. Submission Method and Deadline 1) Vendors shall submit proposals electronically to Derrell.Walton@bvsd.org. Proposals shall not exceed 25MB in size. To be considered, proposals must be received by the District on or before the time and date provided in Section III A) RFP Timeline. It is the CMGC’s responsibility to ensure that the proposal is received by the District on or before the submission deadline. The District will not consider proposals received after the submission deadline, regardless of the reason. 2) As email delivery issues can occur from time to time, the District strongly recommends that CMGCs attach a read receipt to their submission or send a separate email to request District confirmation of receipt. C. RFP Inquiries 1) CMGCs may submit written inquiries concerning this RFP via email to Derrell.Walton@bvsd.org. CMGCs shall clearly identify written inquiries as “BVSD RFP 26-04” in the subject of the email. To ensure a timely response, written inquiries must be received by the District on or before the time and date provided in Section III A) RFP Timeline. The District will not consider written inquiries received after the deadline, regardless of the reason. 2) Except as set forth above, CMGCs shall not contact District staff directly and may not rely on any verbal statements by District staff that alter the terms and conditions of this RFP. This RFP may be modified only in writing issued by the District’s Director of Procurement or their designee.
6
BOULDER VALLEY SCHOOL DISTRICT RE-2 REQUEST FOR PROPOSALS NO. 26-04 August 21, 2025
D. RFP Mandatory Pre-Proposal Project Walk Through. A Mandatory pre-proposal submission conference will be held at the time, date and location provided in Section III A) RFP Timeline. E. Evaluation Team Phone Calls (IF NEEDED) The Evaluation team may make calls to clarify and / or obtain additional information at the time and date provided in Section III A) RFP Timeline. F.
Finalist Interviews (IF NEEDED). If the district feels that it will be beneficial to hold interviews, the district will invite contractors to the BVSD bond office at the time and date provided in Section III A) RFP Timeline. We generally request the staff who will be assigned to the project attend if available (i.e. pre-construction manager, project manager, superintendent, project engineer)
V. Evaluation Process The District will use the following criteria (in no particular order) to evaluate proposals: A. Adherence to RFP instructions B. Experience of the company and the team proposed, including work on similar PK-12 projects C. Ability to meet the schedule and to provide the project specific required services D. Fee proposed VI. Selection of Proposal and Award of Contract A District evaluator or evaluation team will review proposals, conduct interviews (if necessary) and make a recommendation for an award of contract. The contract for the Project will be awarded to the CMGC whose proposal provides the greatest benefit to the District, as determined by the District in its sole discretion. An award of contract under this RFP is conditioned on approval by the Board of Education and/or District staff in accordance with District policy. VII. General Information A. Confidential/Proprietary Materials. As a reminder, proposals shall become the exclusive property of the District upon District receipt and shall be subject to public inspection and copying in accordance with the Colorado Open Records Act, C.R.S. §§ 24-72-200.1 et seq. In issuing this RFP, the District is not seeking, and strongly discourages CMGCs from submitting, trade secrets or confidential commercial or financial information. If a CMGC nonetheless elects to submit trade secrets or confidential commercial or financial information, then such information shall be submitted as a separate electronic file that is clearly labeled “Confidential” or “Proprietary” (as applicable). CMGCs shall not label their proposals as “Confidential” or “Proprietary.” The District shall not be responsible for disclosing proposals or materials that do not comply with this provision in response to an open records request, even if such proposals are labeled “Confidential” or “Proprietary.” If a CMGC disputes the disclosure of its proposal or materials in response to an open records request, then CMGC, at its sole cost and expense, shall be solely responsible for defending against such disclosure. Neither a response in its entirety,
7
BOULDER VALLEY SCHOOL DISTRICT RE-2 REQUEST FOR PROPOSALS NO. 26-04 August 21, 2025
nor a Fee Proposal will be considered confidential and proprietary. Any information that will be included in a resulting contract cannot be considered confidential. B. Reservation of Rights. The District reserves the right to: 1. Cancel, reissue, amend, close, or reopen this RFP at any time, without cause and without liability or penalty; 2. Request clarification or additional information with respect to one or more proposals; 3. Interview one or more CMGCs with respect to their proposals; 4. Accept or reject all or any part of a CMGC’s proposal; 5. Negotiate changes in the scope of services; 6. Waive formalities or requirements of the RFP with respect to one or more proposals; 7. Engage other vendors to perform additional services for the Project; 8. Schedule and conduct one or more site visits and/or Project meetings; 9. Award the contract, in whole or in part, to the CMGC or CMGCs whose proposal represents the best value to the District, in the District’s sole discretion. By submitting a proposal, CMGCs acknowledge and agree that the proposal with the lowest price will not necessarily be the proposal that represents the best value to the District because a number of factors other than price are relevant in determining the best value, including, without limitation, the factors set forth in Section IV of this RFP. C. News Releases. News releases pertaining to this RFP or any resulting contract shall NOT be made without prior written approval by the District. D. Incurring Costs. The District is not liable for any cost incurred by a firm prior to issuance of a legally executed contract, purchase order, or other authorized acquisition document. No property interest, of any nature, shall occur until a contract is awarded and signed by all concerned parties. E. Certification of Independent Pricing Determination. Except as otherwise disclosed with particularity, through its submission of a proposal, CMGC certifies that the prices and other terms in the proposal have been arrived at independently without any consultation, communication, agreement with, or knowledge of the contents of the proposals of a competing CMGC. For purposes of this paragraph, "consultation, communication, agreement with, or knowledge" does not include knowledge of prices or terms gained through availability of established price lists or catalogues made available to the public by the competing CMGC. No attempt has been made or will be made by the CMGC to induce any other CMGC to submit or not to submit a proposal for the purpose of restricting competition. F. Asbestos Management Plan. The successful CMGC shall be required to sign the Asbestos Management Plan Contractor Responsibility form set forth in Attachment H as a condition of an award of contract.
8
BOULDER VALLEY SCHOOL DISTRICT RE-2 REQUEST FOR PROPOSALS NO. 26-04 August 21, 2025
ATTACHMENT A Project Information and Owner Requirements Project Name Nederland Elementary School 1 Sundown Trail, Nederland, CO 80466 Nederland Middle-Senior High School 597 Co Hwy 130, Nederland, CO 80466
Architect TBD The estimated design completion dates can be found in the Milestones section of the RFP.
Project Schedule Ɣ Design (DAT) meetings and the estimated dates can be found in the RFP Milestones. Ɣ
We anticipate that the construction and renovation related to Nederland ES will be completed by August 1, 2027. Estimated construction dates, if available can be found in the RFP Milestones.
Ɣ
We anticipate that the construction and renovation related to Nederland MS-HS will be completed by August 1, 2027. Estimated construction dates, if available can be found in the RFP Milestones.
Ɣ
Construction duration is estimated to be: o School Name - 6 months o School Name - 6 months (please use this for responding to Attachments B1, B2 and C1, C2).
*** Note: Staffing levels and project duration are based on the assumption that work will begin around spring break and continue outside of school hours until completion. Full-time staffing for the entire duration is not anticipated. ***
Project Construction Budget Nederland Elementary School - $966,838.00 Nederland Middle-Senior High School - $8,136,910.00
Liquidated Damages Liquidated damages for this project will be set at $2000/day.
9
BOULDER VALLEY SCHOOL DISTRICT RE-2 REQUEST FOR PROPOSALS NO. 26-04 August 21, 2025
Additional Information Ɣ Please see Critical Needs Plan information at: https://resources.finalsite.net/images/v1665782745/bvsdorg/zuqqioc7dydqf43sk9uv/2022BVSDFacilitiesCritic alNeeds.pdf Ɣ
Billable rates are NOT allowed as part of contract
Ɣ
Design Phase fee will be a fixed amount for the contract and this project
Ɣ
This project qualifies under items 3 through 9 in “Green Building Guiding Principles” https://bond.bvsd.org/green-building
10
BOULDER VALLEY SCHOOL DISTRICT RE-2 REQUEST FOR PROPOSALS NO. 26-04 August 21, 2025
ATTACHMENT B CM/GC Proposal Form - See attached Excel spreadsheet. ATTACHMENT C CM/GC Matrix - See attached Excel spreadsheet. No changes to the matrix are allowed.
11
BOULDER VALLEY SCHOOL DISTRICT RE-2 REQUEST FOR PROPOSALS NO. 26-04 August 21, 2025
ATTACHMENTS D & E Requirement List Report by Priority created by VFA, Inc. See separately attached PDF’s.
12
BOULDER VALLEY SCHOOL DISTRICT RE-2 REQUEST FOR PROPOSALS NO. 26-04 August 21, 2025
ATTACHMENT H Boulder Valley School District Asbestos Management Plan Contractor Responsibility It is the expectation of the Boulder Valley School District that contractors adhere to all AHERA, EPA, and Colorado Department of Public Health and Environment regulations regarding asbestos treatment and management before and during any construction, renovation or maintenance project. To that end, contractors are expected to review the asbestos management plan before the work begins. Any activity that could potentially disturb asbestos containing building materials must be brought to the attention of BVSD Environmental Services Department prior to the start of work, and if the scope of work changes during the course of the project. Environmental Services will identify all areas of concern and facilitate any necessary abatement in order to help make all projects successful. Therefore, contractors and their subcontractors must provide this signature sheet prior to the start of work to ensure they are aware of BVSD expectations and understand their responsibility. I have read and understand the BVSD Asbestos Management Plan for the buildings in which I will be working. I agree not to disturb or damage any asbestos containing building materials (ACBM), which have been identified in the Asbestos Management Plan. In the event the scope of work changes during the course of the project, or our work causes us to encounter building materials that may be ACBM, we agree to notify BVSD Environmental Services immediately. If any identified ACBM is disturbed or damaged as a result of the work, the contractor and/or their subcontractor may be held financially responsible for all related remediation. Company Name: ______________________________________________ Authorized Representative: ______________________________________ Print
______________________________________
Signature ______________________________________ Date: ____________ Drafted and Required by: BOULDER VALLEY SCHOOL DISTRICT ENVIRONMENTAL SERVICES DEPARTMENT
13
BOULDER VALLEY SCHOOL DISTRICT RE-2 REQUEST FOR PROPOSALS NO. 26-04 August 21, 2025
ATTACHMENT J NOTE: THIS PAGE MUST BE COMPLETED AND INCLUDED WITH THE SUBMISSION BOND CONSTRUCTION MANAGER / GENERAL CONTRACTOR SERVICES DECLARATION & SIGNATURE PAGE DECLARATION: I hereby certify that the information provided in this submission made to Boulder Valley School District is true and correct and I am duly authorized to submit this response. No Board of Education member, member of a District board or committee, employee of the District, or any such person’s spouse, child, parent, brother, sister, dependent, or person assuming a relationship being the substantial equivalent of the above, has a direct or indirect financial or personal interest in the proposing firm or this Request except as follows [or state: NONE]: ________________________________________________________________________________________________ ________________________________________________________________________________________________ __________. I hereby certify that the firm has reviewed this Request, the Design Advisory Team Guidelines, and the District’s standard CMGC Agreement with General Conditions and other attachments and accepts the terms and conditions thereof. ____________________________________________ (FIRM NAME)
_____________________________________________ (TYPED NAME OF AUTHORIZED AGENT)
____________________________________________ (STREET ADDRESS)
______________________________________________ (SIGNATURE OF AUTHORIZED AGENT)
____________________________________________ (CITY, STATE AND ZIP CODE)
______________________________________________ (TITLE)
____________________________________________ (TELEPHONE NUMBER)
______________________________________________ (DATE)
____________________________________________ (COMPANY FAX NUMBER)
______________________________________________ (FEDERAL EMPLOYEE IDENTIFICATION NUMBER)
____________________________________________ (EMAIL ADDRESS)
v.2 090618
14
EXHIBIT B The following 27 pages are CMGC response to the RFP
4919-9821-7592, v. 1
18
September 17, 2025
8085 E Harvard Ave Denver, CO 80231 Representative for the Firm and Evaluation Team Questions: Andy Stewart, PE, LEED® AP Vice President C: 303.598.0049 E: astewart@howelldenver.com A: 8085 E Harvard Ave, Denver, CO 80231 THERE ARE NO MATERIAL CHANGES TO THE PREQUALIFICATION.
RFP: CM/GC SERVICES FOR NEDERLAND ELEMENTARY SCHOOL & NEDERLAND MIDDLE-SENIOR HIGH SCHOOL
01 General Information 02 Team Experience & Approach 03 Composition of Proposed Team 04 pay application Acknowledgment CLICK EACH TAB TO PROGRESS 1
TAB 01: GENERAL INFORMATION
BOULDER VALLEY SCHOOL DISTRICT RE-2 REQUEST FOR PROPOSALS NO. 24-20 December 13, 2023
ATTACHMENT G NOTE: THIS PAGE MUST BE COMPLETED AND INCLUDED WITH THE SUBMISSION BOND CONSTRUCTION MANAGER / GENERAL CONTRACTOR SERVICES DECLARATION & SIGNATURE PAGE DECLARATION: I hereby certify that the information provided in this submission made to Boulder Valley School District is true and correct and I am duly authorized to submit this response. No Board of Education member, member of a District board or committee, employee of the District, or any such person’s spouse, child, parent, brother, sister, dependent, or person assuming a relationship being the substantial equivalent of the above, has a direct or indirect financial or personal interest in the proposing firm or this Request except as follows [or state: NONE]: NONE ________________________________________________________________________________________________ ________________________________________________________________________________________________ __________. I hereby certify that the firm has reviewed this Request, the Design Advisory Team Guidelines, and the District’s standard CMGC Agreement with General Conditions and other attachments and accepts the terms and conditions thereof.
HOWELL CONSTRUCTION ____________________________________________ (FIRM NAME)
ANDY STEWART _____________________________________________ (TYPED NAME OF AUTHORIZED AGENT)
8085 E HARVARD AVE ____________________________________________ (STREET ADDRESS)
______________________________________________ _______________________ (SIGNATURE OF AUTHORIZED AGENT)
DENVER, CO 80231 ____________________________________________
VICE PRESIDENT ______________________________________________
(CITY, STATE AND ZIP CODE)
(TITLE)
303.696.5800 ____________________________________________
SEPTEMBER 17, 2025 ______________________________________________
(TELEPHONE NUMBER)
(DATE)
303.696.5801 ____________________________________________
84-1023897 ______________________________________________
(COMPANY FAX NUMBER)
(FEDERAL EMPLOYEE IDENTIFICATION NUMBER)
ASTEWART@HOWELLDENVER.COM ____________________________________________ (EMAIL ADDRESS) v.2 090618
1
September 17, 2025 Derrell Walton Boulder Valley School District (BVSD) derrell.walton@bvsd.org RE: RFP FOR CM/GC SERVICES FOR BOULDER VALLEY SCHOOL DISTRICT NEDERLAND MIDDLE-SENIOR HIGH SCHOOL, AND NEDERLAND ELEMENTARY SCHOOL Dear Mr. Walton and Selection Committee,
What Makes Howell The right fit?
Howell Construction has seen that one of the biggest challenges facing construction projects is limited availability of resources. BVSD is to be commended for getting your CM/GC on board early, allowing the successful CM/GC to plan, budget and value engineer your project, order critical materials for timely delivery, and reserve the labor resources necessary to succeed in the summer of 2027. Howell believes we have the best track record for delivering outcome certainty along the Front Range. Here are a few ways we believe Howell will create outcome certainty for you:
SUMMER WONDER BUILDERS - ZERO LEARNING CURVE. Howell has a deep resume of technical occupied renovation experience on fast-track schedules. We have developed a standard of work and care to ensure our clients’ needs are met. We apply this standard of care to our work in and around occupied K-12 schools, higher education campuses and more. Howell is an experienced school builder for ‘summer wonder’ projects that must be completed between the end of May and the start of school in August. Our most recent ‘summer wonder’ projects were completed for BVSD where we renovated both the Louisville Elementary School and Middle School this past summer.
TRADE PARTNER RELATIONSHIPS - 90 YEARS IN THE MARKET. Howell’s nine decades in the Front Range marketplace gives us a pricing advantage over our competitors due to our deep rooted relationships with the subcontractor community. Usually 80 percent or more of every construction project is built by trade partners. In a busy marketplace, especially during the summer months, Howell is still able to get multiple bids for each trade which can be a challenge to others. Our longstanding relationships with the trade partner community translates to added value for BVSD through increased trade partner participation and more competitive pricing.
PRINCIPAL LEADERSHIP - NO SMALL PROJECTS TEAM. At Howell, we believe principal leadership enables us to deliver our projects with a high degree of customer satisfaction. We DFKLHYHWKLVVXFFHVVE\DVVLJQLQJDSULQFLSDODQGRZQHURIRXU¿UPWROHDGRXUWHDPVIURPSUHFRQVWUXFWLRQWKURXJKSURMHFW FRPSOHWLRQ7RRWKHU¿UPVPXOWLSOHVPDOOSURMHFWVLVVRPHWKLQJWKH\ZRXOGDVVLJQWRDVPDOOSURMHFWVWHDP7KDWLVQRWWKHFDVH at Howell. Principal involvement is not just a marketing strategy at Howell – it’s how we do business!
As a Howell owner and principal, you have my commitment that your project will receive our team’s full attention and adequate resources to ensure our brand promise of ALWAYS GREAT PERFORMANCE. Thank you for your consideration and the opportunity to continue our partnership with BVSD. Should you have any questions or wish to discuss our proposal in further detail, please contact me at 303.598.0049 or via email: astewart@howelldenver.com. Sincerely,
Howell Construction Howell acknowledges receipt of Addendum 1 dated: 09.08.25 Andy Stewart, PE, LEED® AP Vice President Howell Construction
2
Since 1935 8085 E Harvard Ave. J Denver, CO 80231 J 303.696.5800 J www.howelldenver.com
TAB 01: GENERAL INFORMATION
HOWELL CONSTRUCTION IS A COLORADO-BASED, REGIONALLY FOCUSED, FULL-SERVICE GENERAL CONTRACTOR FOUNDED IN 1935. Our experience includes construction manager / general contractor, design-build and general construction for:
PUBLIC SECTOR | GENERAL COMMERCIAL | HEALTHCARE | ADVANCED INDUSTRIES | CORPORATE INTERIORS Howell Construction has been serving the Front Range region since 1935, making public sector projects one of our primary focuses of business in the last decade. Howell has sustained our history of successful project outcomes through a steadfast commitment to quality service for our clients. Howell’s extensive construction expertise and technical skills mean we excel in handling project complexities and meeting aggressive construction schedules. Our mission on every project is to create a client-for-life relationship and to serve our partners in the process. We are proud of the extensive list of School Districts, State Universities, and organizations we work with - most of which are repeat clients. Our passion for building is demonstrated on every project. We focus on our clients’ best interests through open, honest, and transparent communication to ensure ALWAYS GREAT PERFORMANCE.
FIRM REPRESENTATIVE
ADDITIONAL POINT OF CONTACT
Andy Stewart, PE, LEED® AP Vice President C: 303.598.0049 E: astewart@howelldenver.com A: 8085 E Harvard Ave, Denver, CO 80231
Todd Johnston Sr. Precon Manager / Sr. Project Manager C: 303.968.0001 E: tjohnston@howelldenver.com A: 8085 E Harvard Ave, Denver, CO 80231
SUMMER WONDER EXPERTS
PRINCIPAL LEADERSHIP
TRADE PARTNER RELATIONSHIPS
We’re proposing our ‘summer wonder’ A-Team to ensure your projects are completed on-time
PRINCIPAL LEADERSHIP GUIDING OUR PROCESS TO MEET YOUR BOTTOM LINE FOR SCHEDULE AND BUDGET
Deep rooted trade partner relationships will provide bvsd with the best pricing
3
TAB 02: TEAM EXPERIENCE & APPROACH
COMPANY / TEAM EXPERIENCE & APPROACH TO THIS TYPE OF PROJECT Our understanding of this project, based on RFP 26-04 and related documents, is that it includes renovations at both Nederland Elementary School and Nederland Middle-Senior High School, with construction commencing in spring 2027 and substantial completion by August 1, 2027. Our approach emphasizes coordinated scheduling and phasing across both schools to minimize disruption, working closely with BVSD’s Project Manager and school personnel to protect potential academic activities. Above all, we will prioritize the safety of students, staff, and the community while delivering the projects within the established budgets.
BOULDER VALLEY SCHOOL DISTRICT
CASE STUDY: LOUISVILLE ELEMENTARY & MIDDLE SCHOOL RENOVATIONS
Howell was selected by Boulder Valley School District to complete a series of building renovations during the summer of 2025 as part RIWKHGLVWULFW¶VERQGSURJUDP7KHVFRSHLQFOXGHVQHZÀRRULQJWKURXJKRXWDGPLQLVWUDWLYHRI¿FHVFRUULGRUVDQGVWXGHQWUHVWURRPV H[SDQVLRQRIWKHVWDIIUHVWURRPJUHDVHLQWHUFHSWRUUHSODFHPHQWVZRRGFHLOLQJXSJUDGHVDQGLQVWDOODWLRQRIDQHZLQWHUFRPV\VWHP Renovations took place simultaneously across multiple facilities, requiring careful scheduling and coordination. Howell’s team managed ORQJOHDGPDWHULDOVE\VHTXHQFLQJZRUNHI¿FLHQWO\WRHQVXUHDOOXSJUDGHVZHUHFRPSOHWHEHIRUHVWXGHQWVDQGVWDIIUHWXUQHGLQ$XJXVW Proposed Team Member Involvement: Andy Stewart, Jeremy Kellogg, Todd Johnston, Katie Barela
PIPEFITTERS LOCAL #208 APPRENTICESHIP SCHOOL EXPANSION
WELDING LAB: A CTE CASE STUDY +RZHOOFRPSOHWHGWKH6)3LSH¿WWHUV$SSUHQWLFH6FKRRO ([SDQVLRQ D GHVLJQ EXLOG SURMHFW 3LSH¿WWHUV /RFDO 8QLRQ #208 has been providing industry training programs since 1902. This project expanded the existing campus by adding two new buildings consisting of a 5,400 SF lab / shop space and a 5,187 SF pipe welding lab open-air metal structure. Site LPSURYHPHQWV UHTXLUHG LQVWDOOLQJ D VDQG ¿OWUDWLRQ EDVLQ DQG UHORFDWLQJ DQG DGGLQJ QHZ ZDWHU VHZHU HOHFWULFDO DQG ¿UH hydrants in conjunction with the widening of Broadway. As part RIWKLVSURMHFWWKH+RZHOOWHDPZRUNHGZLWK3LSH¿WWHUVWXGHQWV to install the in-slab hydronic radiant heat tubing. 4
TAB 02: TEAM EXPERIENCE & APPROACH BRIGHTON HIGH SCHOOL RENOVATION
CASE STUDY: SUMMER WONDER RENOVATION A school-wide renovation to Brighton High School was needed to accommodate the increased student and staff capacity. The project consisted of ADA upgrades, composite metal panel systems, window replacements, HVAC upgrades, security, and parking lot upgrades. Howell brought on the mechanical contractor and composite metal panel subcontractors early to ensure materials and manpower were reserved in advance of a demanding summer construction market. Working over the summer, Howell successfully put over $4M of work in place between May and August. Proposed Team Member Involvement: Andy Stewart and Katie Barela
Summer Wonder Remodel DENVER JOINT ELECTRICAL TRAINING APPRENTICESHIP COMMITTEE
ELECTRICAL LAB: A CTE CASE STUDY The Denver Joint Electrical Apprenticeship Training Center (DJEATC), sponsored by the Local Union #68 of the International Brotherhood of Electrical Workers (IBEW), wished to renew and expand their current training center in order to better mold the future generations of new electrical apprentices coming into the work force. The project consisted of renovations to interior spaces including classrooms, restrooms and major UHZRUNRIWKHVDQLWDU\DQG¿UHVSULQNOHUXWLOLWLHV7KHH[WHULRU facade was overhauled with new windows and a blackened metal screen to modernize the appearance of the building. Howell also built an addition that included classroom space for apprentices and an elevator, bringing the building up to code. Jeremy Kellogg, your proposed Project Manager, played an integral role in the completion of this project.
5
TAB 02: TEAM EXPERIENCE & APPROACH
SUMMER WONDER PROJECT EXPERIENCE Over the past several years, Howell has completed many ‘summer wonder’ projects for multiple Colorado public school districts. These IDVWWUDFNHGSURMHFWVKDYHLQFOXGHGPHFKDQLFDOV\VWHPXSJUDGHVDFFHVVLELOLW\LPSURYHPHQWVLQWHULRU¿QLVKHVKDUGVFDSHVODQGVFDSLQJ and renovations of existing conditions. Through this experience, we will apply our lessons-learned, and best practices to your Nederland Elementary and Middle - Senior High School. » Boulder Valley Schools - Louisville Elementary & Middle School » Denver Public Schools - Beach Court Elementary Elevator Reno Renovations » Denver Public Schools - Garden Place Elementary Mechanical » Littleton Public Schools - Peabody Elementary Improvements Upgrades » Holyoke Jr./Sr. High School Renovation » Littleton Public Schools - Centennial Elementary Renovation » Littleton Public Schools - Whitman Turf Field Upgrades » Brighton High School Expansion / Renovation » International School of Denver Renovations » Littleton Public Schools - Secured Vestibules » Littleton Public Schools - Heritage High School Fence Upgrades » Denver Public Schools - Gilpin Elementary Pipe Replacement
HOLYOKE JR./SR. HIGH SCHOOL
CASE STUDY: SUMMER WONDER RENOVATION Howell was selected to provide design-build services to the Holyoke Jr./ Sr. High School. The project was fast-tracked through design for a May – August ‘summer wonder’ construction duration. This high school renovation scope was spread throughout most of the school. Renovated areas LQFOXGHG D QHZ VHFXUH HQWU\ YHVWLEXOH DGPLQLVWUDWLRQ RI¿FHV ZDUPLQJ kitchen, training room, junior high locker rooms, senior high locker rooms, FRDFK DQG UHIHUHH RI¿FHVORFNHUVUHVWURRPV ZHLJKW URRP DQG ZUHVWOLQJ room. A new full-service elevator and rooftop mechanical equipment were also included. We utilized a performance spec to fast-track procurement of the elevator ahead of the completed design documents to ensure timely delivery and installation of the elevator. We took a similar approach to athletic lockers, knowing the time frame for construction would be in competition with schools across the country for the same resources. Proposed Team Member Involvement: Andy Stewart, Katie Barela
LITTLETON PUBLIC SCHOOL DISTRICT
CASE STUDY: SIMULTANEOUS SUMMER WONDER RENOVATION Howell was selected by Littleton Public Schools for a phased upgrade to the secure entrances at multiple schools. Phases I and II occurred during the summer of 2022 and upgraded security at six schools. Upgrades included door upgrades, ballistic glass, the addition of cameras, microphones, DFFHVVFRQWUROVDQG¿QLVKHV Phases III and IV were completed during the summer of 2023 and included seven schools with VLPLODU VHFXULW\ DQG ¿QLVK XSJUDGHV :RUN RQ WKH VFKRROV RFFXUUHG VLPXOWDQHRXVO\ ZLWK WKUHH Howell superintendents covering multiple schools at a time. Our team mitigated long lead item GHOD\VE\SULRULWL]LQJWKHXSJUDGHVWKDWFRXOGEHFRPSOHWHGZLWKWKHPDWHULDOVRQKDQGDQGLGHQWL¿HG temporary solutions for the missing materials. Proposed Team Member Involvement: Jeremy Kellogg 6
12.25
Q2 2026
Q3 2026
Preconstruction Dec 25 - Dec 26
Preconstruction: Dec 25 - Dec 26
Q1 2026
MILESTONE SCHEDULE
Nederland Elementary School
Nederland MiddleSenior high school
1.27
2.27
3.27
Procurement: Sept 26 - March 27
4.27
2/27 - 5/27
6.27
interior work
Phase 2 Exterior work
5.21 - 7.31
8.27
5.21 - 7.31
5.21 - 7.31
5.21 - 7.20
7.27
Construction 5/21 - 8/1
interior work
Exterior work
Mobilization: 5.21.27
5.27
summer Break 05.20.27- 08/27
7
TAB 02: TEAM EXPERIENCE & APPROACH
Construction 2/27- 7/27
Phase 1 Exterior work
Mobilization: 2.21.27
Procurement: Sept 26 - March 27
Q4 2026
Spring break 3.15.27 - 3.19.27
TAB 02: TEAM EXPERIENCE & APPROACH
PROJECT APPROACH EARLY PROCUREMENT OF RESOURCES Our approach emphasizes early coordination, proactive subcontractor engagement, and disciplined schedule management. Upon contract DZDUGLQ2FWREHUZHZLOOLPPHGLDWHO\HVWDEOLVKFRPPXQLFDWLRQSURWRFROVZLWK%96'DQGEHJLQVXEFRQWUDFWRUSUHTXDOL¿FDWLRQDQG long-lead procurement planning. Regular Design Advisory Team meetings through Spring 2026 will guide constructability reviews, cost modeling, and phasing strategies, culminating in a Guaranteed Maximum Price submission in October 2026. Construction will commence in Spring 2027, sequenced to minimize disruption to school operations, with both campuses reaching substantial completion by August DQG¿QDOFORVHRXWLQ6HSWHPEHU7KURXJKRXWZHZLOOSULRULWL]HHDUO\WUDGHSDUWQHUFRPPLWPHQWVSURDFWLYHULVNPDQDJHPHQWDQG integration of BVSD’s Green Building Guiding Principles to ensure a timely, cost-effective, and sustainable project.
NEDERLAND ELEMENTARY SCHOOL
NEDERLAND MIDDLE-SENIOR HIGH SCHOOL
DUMPSTER PORTALETS MATERIAL LAY DOWN
DUMPSTER MATERIAL LAY DOWN CONSTRUCTION FENCE AT PRE-K PLAYGROUND
PORTALETS
%HFDXVHRIWKHSUR[LPLW\RI\RXUWZRVFKRROVZHDUHFRQ¿GHQWLQRXUDELOLW\WRH[HFXWHERWKMREVZLWKWKHVDPHVXSHULQWHQGHQW2XULQLWLDO GHVLUHLVWRWDNHIRXUWR¿YHSDUNLQJVSRWVLQERWKSDUNLQJORWVIRURXUFRYHUHGGXPSVWHUDQGSRUWDOHWVIRUFRQVWUXFWLRQSHUVRQQHOXVH,I either of the schools are utilized for summer school programs, we will work with BVSD in determining the best space for construction personnel to park and enter the buildings.
PROJECT KEYS TO SUCCESS
Early onboarding of Key Subcontractors
8
Early Procurement of Mechanical Items
Advanced Communication of 2026 Summer School Activities
Prompt Contractor Engagement during Preconstruction
TAB 02: TEAM EXPERIENCE & APPROACH
METHOD TO STREAMLINE COMMUNICATION Howell will have the same exact team working on both schools at once, streamlining communication so there is no lost knowledge between the two. With the same Senior Preconstruction Manager and Senior Estimator, Howell will be able to simultaneously attend DAT and OAC meetings to keep both projects on track for a successful completion. Each school district has different requirements for communication with their respective communities and personnel. We are eager to adapt to BVSD’s communication requirements to ensure the education environment is not impacted throughout construction as we did this past summer on the Louisville ES and MS renovations.
FIELD COMMUNICATIONS 'XULQJWKHLQLWLDOVFKHGXOHGHYHORSPHQWRXUWHDPZLOOHQJDJHNH\VXEFRQWUDFWRUVWRGLVFXVVVHTXHQFLQJDQGVFRSHGXUDWLRQVDQGGH¿QH the detailed activity breakdown necessary to closely track progress throughout the construction process.
LEAN CONSTRUCTION Critical milestones will be established in the initial construction schedule. LEAN Pull Scheduling techniques will be utilized by involving NH\RQVLWHWUDGHSHUVRQQHOWRYDOLGDWHDQGVWUHDPOLQHVFKHGXOHGDFWLYLWLHVIRUSURSHUÀRZDQGPDQSRZHUDOORFDWLRQIRUZRUNOHDGLQJXSWR each critical milestone. Once the scope is pulled to the select milestone, the overall construction schedule will be updated and distributed WRDOOWUDGHSDUWQHUVIRU¿QDOUHYLHZDQGEX\LQ Once on site, proposed superintendent, Nate Lerma, will conduct 15-minute, all trades required, Daily Huddles for both schools where visual scheduling and open communication practices are implemented to create a plan for the day. BVSD personnel are encouraged WRDWWHQG'DLO\+XGGOHV7KLVLVZKHUHWKHWHDPFDQLGHQWLI\DQ\FRRUGLQDWLRQFRQÀLFWVWKDWPD\UHTXLUHWKHWUDGHV¶DWWHQWLRQDQGSODQ for any deliveries or logistics that could impact their work throughout the day. This Daily Huddle practice has proved to increase trade engagement on the project and foster better communication amongst the teams on site. The Daily Huddles take a load off weekly subcontractor meetings allowing focus on the three-week schedule, upcoming client or project site constraints, safety performance on the project, and any other big picture items that would affect the project in the longer term.
15-Minute all Trades Daily Huddles
Weekly OAC Meetings
Daily Communication with BVSD Facilities
9
TAB 02: TEAM EXPERIENCE & APPROACH
METHOD TO ASSEMBLE A GUARANTEED MAXIMUM PRICE (GMP) Because Howell is a locally-based contractor, creating and maintaining long-term relationships is our greatest priority, and our list of repeat clients speaks to our success in this area. We believe the most important factor that helps keep Howell aligned with our clients is establishing extremely high levels of trust. We have been told by many clients and designers that Howell’s process for budget creation, scheduling, project controls, Trade Partner selection and billing sets the standard for the open-book approach. We are very familiar with your type of project delivery and we have developed an approach that increases our GMP accuracy with each subsequent design package, allowing us to predict where the overall project cost will be.
1.
Advertise to QualiÀed and Approved Trade Partners :KHQELGSDFNDJHVDUHUHDG\ZHZLOODGYHUWLVHWKHSURMHFWWRTXDOL¿HGDQGDSSURYHGWUDGHSDUWQHUVWKURXJKRXU%XLOGLQJ&RQQHFWHG system. This is our primary trade partner communication tool for questions, project information, deadlines, addenda, and bid submission.
Project Take-off
2.
Once the project is advertised and documents are out to subcontractors, we start with a thorough itemized take-off of the project. We use those quantities to check against our subcontractor pricing and to expose any scope gaps in the trade numbers we are receiving.
3.
Bid Tabulations We have our estimate hyperlinked to the bid tabulation worksheets. As trade partner numbers come in we start building a tab IRUWKDWWUDGHDQGEHJLQDVHULHVRIFRQYHUVDWLRQVWRFRQ¿UPHDFKVXEFRQWUDFWRUKDVWKHUHTXLUHGVFRSH2QFHZHVHOHFWWKH trade partners for that trade, the numbers start populating into our master estimate.
Bid Book )URPWKLVSRLQWZHEXLOGRXU%LG%RRNVGHWDLOHGELQGHUVWKDWLQFOXGHRXUHVWLPDWHFODUL¿FDWLRQVWUHQGORJRI proposed alternates, schedule, and all the bid tabulations with copies of the trade partner quotes. This methodology produces a transparent process between Howell and BVSD. Our process provides accountability and complete understanding of the project costs as well as excellent controls to help the team meet your budget expectations.
4.
Littleton Public Schools
CASE STUDY: VALUE ENGINEERING EFFORTS
Update 09/04/13
Bid Package #3 - New Elementary School #2 SD Cost Trend Log March 10, 2020 SD Budget = $37,785,388.00 Item #
Est. Value
SCOPE MODIFICATIONS
Status
Comments/Notes
Pending Adds
Pending Deducts
Approved
Rejected
The Littleton Public Schools Gudy Gaskill Elementary School is the perfect example of the Howell team providing preconstruction efforts to ensure the best value for our clients. This project was a CM/GC delivery, and at each design milestone, Howell presented the owner and the design team with a trend log accompanying the budget. At the Schematic Design phase, our project budget was approximately $37M, a number that included all client wants. Accompanying this EXGJHW ZDV D WUHQG ORJ WKDW LGHQWL¿HG YDOXH HQJLQHHULQJ RSWLRQV totaling $3.7M. At the Design Development stage, our budget WRWDOHG 0 DQG WKH DFFRPSDQ\LQJ WUHQG ORJ LGHQWL¿HG DQRWKHU potential $3.3M in savings options. At the iGMP budget, our number came in at $30M, a reduction in $7M. It is important to note that all suggested VE items were provided to the client and design team and were discussed in detail to determine if the alternate would maintain design intent in addition to saving money. Both the design team and the owner approved all VE options before the changes Items in green indicate approved value engineering options. 1et savings of ,5,9 are reÀected in this Trend /og. were made. 1.0
Subcontractors "sharpening" pencils at CD Bidding
2.0
Reduce asbestos Abatement allowance to $500K
$
(973,026.74) Target 3% of Subcontractor Costs
Pending
$
(270,285.21) Pending until confirmed with testing and sub pricing
Approved
3.0
Site Concrete - Decrease Concrete Pavement Drive from 8" to 6"
$
(23,763.48) Leave 8" at service drive. 6" elsewhere.
Rejected
4.0
Site Concrete - Decrease Sidewalk Thickness from 6" to 5"
$
(32,728.57) Explore going to 4" thick with fiber mesh.
Pending
5.0
6.0
Polished Concrete: Eliminate polished/stained concrete and provide LVT
$
(68,620.01)
Assumed $5.50/sf for LVT (materials & installation) 3/3/20 - LVT will be an alternate on drawings, base bid to remain Polished/stained
$
(20,938.45)
Provide groundface CMU veneer in lieu of brick veneer
$
(97,209.70) 3/3/20 - Pending school district decision
Eliminate Soldier Coursing at brick veneer
9.0
Provide wide flange steel beams in lieu of glu-lam beams at LMC, Entry & Commons
$
(206,884.95) 3/3/20 - Pending direction of LPS
10.0
Reduce building height to 14' Floor to Floor
$
(276,642.31)
11.0
Build Millwork Platforms in lieu of Stone Veneer Platforms
$
(33,488.34) Includes all platforms (LMC, Entry Corridor & under Main Stairs) Pending Littleton Public Schools
Update 09/04/13
12.0
13.0
TBD
Eliminate all stone veneer platform seating & provide furniture items Vinyl wallcovering mural in lieu of wood CNC cut mural in LMC
$
14.0
Eliminate Wood Wall/Ceiling at Corridor by LMC
$
(46,272.83)
15.0
Casework quantities to match Ames
$
(111,033.16)
16.0
Add cubbie quantities to each classroom to meet requirements
17.0
18.0
($23,763)
($68,620)
Pending
($20,938)
Pending
3/3/20 - Dependant on district response to CMU Veneer vs. Brick. Approximate value if item#7 is not accepted - ($40,435)
Pending
($97,210)
TBD
Approved
Floor to Floor at 14'0" in lieu of 15', reduce other areas by 1' as well. 2/25/20 - Proceed
($206,885)
Approved
($276,642)
($33,488)
If all platforms are eliminated and #11 is not accepted, approximate savings Pending TBD Bid Package #3 - New Elementary School #2 ($61,000). Does not include the cost of furniture.
(4,529.98)
TBD
($270,285)
($32,729)
Pending
Eliminate stain at polished concrete
7.0
8.0
TBD
($973,027)
Pending SD Cost Trend Log
March 10, 2020
($4,530)
Pending
3/3/20 - Only accounts for casework assumptions not specialty millwork or cubbies added. Cubbies assumed in SD budget are way under count of quantity at Ames.
Approved
Pending DD design, may include new tackboards as well. What is required?
Pending
($46,273)
($111,033)
SD Budget = $37,785,388.00
TBD
Item # Est. Value SCOPE MODIFICATIONS This will eliminate the spray foam Comments/Notes insulation at all veneer locations. Quantity based $ (44,499.76) Approved Provide 2-1/2" Rigid Insulation at all Building Envelope Systems on reduced height building Provide Berridge Vee Panel at exterior soffitsGlass in lieuSectional of 35.0 canopy (35,028.96) Eliminate Doors$at Classrooms provide windows (73,410.54)and Approved Team exploring alternate $ wood look spec, this is to change to metal panel system Certainteed Wood Look system $ (7,160.40) Will be included as an alternate in DD Drawings Window Film at Group Rooms in Learning Communities $ 68,730.28 Ames is at a minimum of 72 mil, is there a LPS standard? Pending
Status ($44,500)
20.0
37.0 TBD Storefront to HM $Specifications Pending DDchanging design. skin Some of the larger spanning openings should remain storefront. (37,839.93) Original HCM alternate, please see Rejected Provide storefront in lieu of curtain wall at Modify buildingInterior envelope item #31 for savings ratios
21.0
included Eliminate wall tile at corridors and paintedHowell drywall & cornerin SD Budget per page flip concerns. No longer needed if matching $ provide (3,459.65) Approved Eliminate 2nd Floor Security Film38.0 on South Elevation $ (106,097.75) Tile will be included on drawings as an alternate standards of Ames guards
$68,730
Standard anodized aluminum finish on curtain walland andinstall interior Furnish non-fire rated acoustical ceiling tile in lieu of fire rated $ (20,757.90) 39.0 storefront in lieu of two coat finish tile for C1 and C2
$
(21,622.82) Fire-rated tile not needed, mold resistant tilePending needed in Kitchen
23.0
$ Eliminate 50% Mullions on South40.0 Elevation and Commons Eliminate 3Form Shape Sail count
$
(82,166.70) Make an alternate for DD set
24.0
Pending
Approved
($7,027)
Approved
($24,866) Pending ($115,509) Pending ($5,225) Approved
33.0
34.0
Dalyte in lieu of Kalwall
25.0
26.0 27.0
28.0
29.0 30.0
31.0
32.0
52.0
Pending
Approved
new product on school. Howell to see what projects have (1,498,610.25) Target Savings on Mechanical/Plumbing System 3/3/20 - Prefer not to test $ $ (12,649.35) Rejected been in town and how long have they been installed. Convenience outlets only, try to reduce by (2) per classroom. Current design is per $ (14,271.06) LPS standard and page flip.
($106,098) ($21,623)
($82,167)
TBD
TBD
($5,628)
($44,111) Approved
Rejected
($36,898)
$104,458
($14,660)
Approved ($14,595) Approved ($113,304) Rejected
($24,326)
($33,154)
($9,225)
($97,692) Approved
($2,487)
Pending ($39,083)
($99,361)
Approved ($11,893)
Approved
($14,428)
($1,498,610)
($12,649)
53.0
Reduce convenience power receptable counts in classrooms
54.0
Pedestrian Lighting
$
(16,217.11) Target reduction of 50%
Approved
($16,217)
55.0
AV Reduction per 3/3/20 meeting
$
(452,360.13) Eliminates group rooms & accounts for OFOI displays
Approved
($452,360)
56.0
Eliminate Synthetic Turf Field and provided sodded/irrigated field
$
(273,871.62) Per LPS direction, this scope will be included.
Rejected
57.0
Costs for premanufactured bridge at North Retention area
58.0 59.0
60.0
SCOPE MODIFICATION SUBTOTAL:
TBD
Bridge will be deleted per stormwater directives. Need to dial in final dollar.
Rejected
Pending
TBD
Not Used
TBD
Not Used
TBD
Not Used
($5,405,732)
($14,271)
($273,872)
TBD
$68,730
($1,403,961)
(Has been saved from original scope)
Net Deduct from original
SD Budget
($3,753,649)
($3,753,649)
($3,753,649)
Revised Price = $34,031,739
10
Rejected
($35,029)
($7,160)
TBD ($37,840)
($3,460) Approved
($20,758)
$ (24,866.24) Will be included as an alternate in DD Drawings Approved Eliminate horizontal mullion extension on south elevation If item #40 is not accepeted and 50% of Sails are to remain in scope, approximate 41.0 TBD Reduce 3Form Shape Sail count savings of ($41,000) Provide Low-E double pane glazing at punched windows in lieu of $ (115,509.09) Matching Ames standard, includes 1st floor windows only Approved School Guard (SG-5) glazing 42.0 TBD Modify C3 Ceiling Specification to2x4 in lieu of 1x4 Pending alternate specification $ (5,224.52) Matching Ames window heights Approved Reduce window height from 7'4" to 6'8" at all punched type windows 43.0 $ (5,628.42) Minimize Gyp Ceilings where possible Matching Ames standards, eliminated operable windows in Work Rooms, Restrooms, $ (44,110.55) Approved Provide two Operable Windows per Classroom Flooring quantity revisions: Decrease wall/floor tileand (restroom sizes),not needed other spaces 44.0 $ (36,898.26) provide LVT in Learning Communities & Group Rooms School Guard assumed in SD budget. 45.0 104,457.66 Utilize Dow Thermamax system$at Building Envelope Rejected Eliminate (4) Exterior Kinder Doors (14,660.27) 3/3/20 - Pending direction $from LPS as was discussed in DAG meeting. 3/10 - Reqd per code $ (24,325.67) Will be included as an alternate in DD Drawings 46.0 Eliminate Operable wall between Commons and the Stage $ (14,595.40) 3/3/20 - BOH Stairs will be decreased in scope in DD's Approved Eliminate Polishing Concrete Pans at Exit Stairs 47.0 $ (33,154.26) Will be included as an alternate in DD Drawings Eliminate Shade Shelter at Intermediate/Primary Play Areas Approved Target Savings on cost per door leaf at CD bidding $ (113,303.56) SD Budget at roughly $2,800/leaf, Ames right at $2,000/leaf $ (9,225.37) Are appliances Owner furnished? 48.0 Eliminate Appliances Goal to reduce curtainwall 1500 sf and increase metal panels, storefront, or veneer Approved Modify exterior skin finish ratios 49.0 (97,691.89) (2,486.62)curtainwall needs to be decreased 1,700 Lower required seats at Gym $ Bleachers to (180) 3/3/20 - Found an error in $area calculation, sf to achieve these savings. Target reduction of 1,500 sf per meeting. 50.0 $ (99,361.17) Utilize Miracle Playground equipment in lieu of Henderson equpment Approved Glass OH Doors at Exterior in lieu of Folding Glass Partitions $ (39,083.24) Furnish and install Hunter Douglas manual and motorized shades in lieu $ (14,427.82) Substitute to spec provided in SD Package,Approved 51.0 Glass Partitions acceptable to team (1) Interior OH Door in lieu of Folding $ (11,892.55) of Mecho Shades
(7,027.42)
Pending Deducts
Approved
19.0
22.0
Pending Adds
Rejected ($73,411)
36.0 Provide 80 mil roof in lieu of 60 mil
($316,852)
TAB 03: COMPOSITION OF PROPOSED TEAM
PROPOSED PROJECT TEAM We are proposing the same project team for each school. Jeremy Kellogg, Project Manager, and Rudy Cornejo, Superintendent, will split their time as needed between Nederland Elementary School and Middle-Senior High School.
Andy Stewart, PE, LEED® AP Principal-in-Charge Design: 10% Construction: As Needed
PRECONSTRUCTION
CONSTRUCTION
Todd Johnston Senior Preconstruction Manager
Todd Johnston Senior Project Manager
Design: 30%
Construction: 10%
Katie Barela, LEED® AP Senior Estimator
Jeremy Kellogg Project Manager
Design: 40% Construction: As Needed
Design: As Needed Construction: 100%
Rudy Cornejo Superintendent Design: As Needed Construction: 100%
Unless a member of the proposed team submitted in this RFP leaves the employment of our company or a change in the team is approved by the BVSD Project Manager and BVSD Director of Bond Planning & Engineering in writing, the team submitted will remain intact for the duration of the project.
11
TAB 03: COMPOSITION OF PROPOSED TEAM
ANDY STEWART, PE, LEED® AP PRINCIPAL-IN-CHARGE Andy is a strong leader who drives creative collaboration within the entire project team. His clear communication and attention to detail are vital when setting up projects for success. He is adept at identifying solutions to complex problems and values in-depth early planning to minimize potential risks and ensure positive outcomes.
Ten Years with Howell Contact 303.598.0049 astewart@howelldenver.com CertiÀcations » LEED Accredited Professional » Professional Civil Engineer Colorado License Number 29699
As Principal-in-charge, Andy takes an active role on all of his projects. He works closely with his clients and design team members throughout the preconstruction and construction phases to develop a comprehensive plan and locate value-added opportunities.
ROLES & RESPONSIBILITIES » Involved during the design and preconstruction effort » Oversight of coordination between construction and design teams » Management of preconstruction planning, value engineering, constructibility and project budget review » Operational oversight, support and back-up during execution of the project » Contract review » Monitoring and ensuring client satisfaction » Monitoring and enhancing teamwork and relationships
SELECT EXPERIENCE *BVSD Louisville Elementary School & Middle School Renovations $3.8M / 69k SF
Littleton Public Schools Gudy Gaskill Elementary $31M / 90k SF
*Holyoke Jr/Sr High School Improvements $4.3M / 8k SF
Revive Church Interior / Exterior Renovations $7.4M / 30k SF
*Brighton High School Renovation $4.3M / 210k SF
Auraria Higher Ed. Campus Lockers / Bleachers Renovation $6M / 10k SF
*Calhan School District PK-12 Renovation & Addition $2.5M / 35k SF
Al Meiklejohn Elementary School $10M / 60k SF
Meeker School District Elementary Reconstruction $2.5M / 40k SF
Cherry Hills Community Church Middle School Addition $8M / 15k SF
Denver Christian Schools K-12 Renovation $12M / 150k SF
Sheridan School District RJ-1 PK-12 Reno / Addition BEST Grant $20.5M / 102k SF
Denver Christian Schools Gymnasium Addition $3.5M / 4k SF
Metropolitan State University Brewing Science Lab $1.8M / 5k SF
*Elbert County School District Roof Replacement $1M / 15k SF
CU Denver Building 500 5th Floor West Renovation $2.4M / 13k SF
*Lamar School District HVAC Upgrades $2.9M / 150k SF
Bluff Lake Nature Center $6M / 8.5k SF
*CU Denver Lynx Connect $3.8M / 15k SF
12
*Indicates Summer Wonder Project
TAB 03: COMPOSITION OF PROPOSED TEAM
TODD JOHNSTON SENIOR PRECONSTRUCTION MANAGER / SENIOR PROJECT MANAGER Todd takes pride in his ability to collaborate with his clients to understand their needs and exceed their expectations. He has built his career around executing large projects, including simultaneous multiÀRRUUHQRYDWLRQVVFKRROXSJUDGHVKRVSLWDOVUHVRUWVDQGUHVLGHQWLDOSURMHFWV7KURXJKRXWKLVWLPH in the construction industry, Todd has gained extensive knowledge of the requirements of working on complex, fast-paced, and technically-intensive projects. 11 Years with Howell Contact 303.968.0001 tjohnston@howelldenver.com
Todd’s role on your project as a Preconstruction Manager includes directing and overseeing the Howell estimating team, project planning and contract review. As Senior Project Manager, Todd will oversee and assist Jeremy Kellogg and Nate Lerma throughout the course of construction.
ROLES & RESPONSIBILITIES » Communication point during design phase and preconstruction effort » Primary point of contact during contract negotiation and preconstruction phase » Senior project oversight throughout construction » Assist client and design team with overall project schedule and budget during the design phase » Preconstruction planning, value engineering, constructability review, subcontractor selection, and materials procurement » Contract and billing management
SELECT EXPERIENCE *BVSD Louisville Elementary School & Middle School Renovations $3.8M / 69k SF
City and County of Denver Wastewater Building Improvements $4.3M / 45k SF
Littleton Public Schools Gudy Gaskill Elementary $31M / 90k SF
Boys and Girls Club Suncor New Building $4.1M / 28k SF
*Littleton Public Schools Heritage High School Turf Field $2.4M / 129k SF
6RXUFH*DV2I¿FH:DUHKRXVHDQG:HOGLQJ6KRS $3.1M / 19k SF
*Littleton Public Schools Whitman Turf Field $495K / 88k SF
Denver Health Green Gateway Site Improvements $7.6M / 153k SF
Littleton Public Schools District Stadium Renovation $6.2M / 200k SF
0LFURVRIW'7&2I¿FH7, $4M / 18k SF
Littleton Public Schools Twain Production Kitchen $2M / 3k SF
DigitalGlobe Far West Data Center $4.8M / 10k SF
CU Anschutz Central Utility Plant Expansion $25M / 80k SF
DigitalGlobe Westminster HQ TI $17.7M / 350k SF
Western Union Project Hometown HQ TI $55M / 350k SF
*Indicates Summer Wonder Project
13
TAB 03: COMPOSITION OF PROPOSED TEAM
JEREMY KELLOGG PROJECT MANAGER Jeremy is an extremely personable Project Manager who takes pride in his ability to build and maintain relationships. He is responsible for seeing projects through to successful completion and leading his team in achieving this goal. Jeremy has vast experience working on occupied education campuses, and believes daily communication amongst all stakeholders is key to a successful project completion.
15 Years with Howell
Jeremy’s military experience, serving six years in the US Marine Corps Reserves makes him both a strong leader and an excellent team player.
ROLES & RESPONSIBILITIES Contact 303.956.5340 jkellogg@howelldenver.com CertiÀcations » OSHA 30-Hour
» Principal communication point during design and preconstruction efforts » Primary point of contact during contract negotiation and preconstruction phase » Project oversight throughout construction » Assist client and design team with overall project schedule and budget during the design phase » Preconstruction planning, value engineering, constructability review, subcontractor selection, and material procurement » Contract and billing management
SELECT EXPERIENCE *BVSD Louisville Elementary School & Middle School Renovations $3.8M / 69k SF
Western Union Project Hometown - Tufts $14.4M / 100k SF
Littleton Public Schools Gudy Gaskill Elementary $31M / 90k SF
Vail Resorts HQ TI $5.5M / 35k SF
*Littleton Public Schools Secured Vestibules $422K / 2k SF
Phoenix Financial Group Addition and TI $1.9M / 20k SF
Littleton Public Schools District Stadium Renovation $6.2M / 200k SF
Prestige Imports - Porsche Dealership Lakewood $27M / 22k SF
%HKDYLRU$QDO\VW&HUWL¿FDWLRQ%RDUG1HZ%XLOGLQJ $7.7M / 2 Acres
Colorado Department of Human Services F1 & F2 Renovation $15.8M / 23k SF
ENT Credit Union New Branch $2.4M / 1 Acre
Cricket Village Center Station 3rd & 4th Floor TI $1.6M / 47k SF
Bluff Lake Nature Center $6M / 8.5k SF
Perkins Coie, LLP, Law Firm TI $4.8M / 30k SF
Vectra Bank Centennial Branch New Build $2.5M / 10k SF
14
*Indicates Summer Wonder Project
TAB 03: COMPOSITION OF PROPOSED TEAM
RUDY CORNEJO SUPERINTENDENT 5XG\LVUHVSRQVLEOHIRUPDQDJLQJWKHGDLO\DFWLYLWLHVRIDOOWUDGHVRQVLWHDQGFRRUGLQDWLQJ¿HOG operations from project start-up through project close-out. Additionally, Rudy schedules the trade partner labor force and material suppliers along with coordinating LQVSHFWLRQVZLWKEXLOGLQJLQVSHFWRUV+HDQWLFLSDWHVDQGVROYHVRQVLWHFRQVWUXFWLRQFRQÀLFWVKDQGOHV daily communication and collaboratively works with the project team to deliver a successful project. 9 Years with Howell
ROLES & RESPONSIBILITIES Contact 720.415.0146 rcornejo@howelldenver.com CertiÀcations » OSHA 30-Hour
» Execution of project » Daily on-site communication and coordination with client » Day-to-day coordination, supervision, and scheduling of subcontractors and suppliers » Job site safety and cleanliness » Quality control assurances » Coordination with building inspectors » $QWLFLSDWLRQDQGVROYLQJRQVLWHFRQVWUXFWLRQFRQÀLFWV » Punch list completion » Maintain as-built drawings for the project
SELECT EXPERIENCE *BVSD Louisville Elementary School & Middle School Renovations $3.8M / 69k SF Prestige Imports - Porsche Dealership Lakewood $29M / 65k SF DHHA Main Campus Redevelopment $5M / 153k SF Vehicle Vault Condominiums $8M / 50k SF ENT Credit Union Highlands Ranch Renovation $20K / 7k SF ENT Credit Union Aurora $620K / 1k SF ENT Credit Union Thornton New Branch $3.2M / 5k SF Maxar Technologies Tango Laboratory Renovation $214K / 1k SF Maxar Technologies Newton Laboratory Renovation $789K / 3k SF
Maxar Technologies Longmont Tenant Improvement $358K / 100 SF Shea Properties Headquarters Renovation $3.6M / 18k SF 8&+HDOWK1RUWK¿HOG0HGLFDO2I¿FH%XLOGLQJ7HQDQW,PSURYHPHQW $1.4M / 10k SF Mountain View Pain Clinic Renovation $545K / 4k SF UCHealth Highlands Ranch Hospital CT 1 & 2 Renovation $422K / 5k SF Battelle Hangar Renovation $570K / 2k SF &RQ¿GHQWLDO6&,)&OLHQW7HQDQW,PSURYHPHQW $1.5M / 3k SF UCHealth HRH OR Expansion $6.3M / 13.2k SF
*Indicates Summer Wonder Project
15
TAB 03: COMPOSITION OF PROPOSED TEAM
KATIE BARELA, LEED® AP
DAT MEETING ATTENDEE
SENIOR ESTIMATOR .DWLHKDVVXFFHVVIXOO\FRPSOHWHGYDULRXVRFFXSLHGFDPSXVSURMHFWVZLWKFULWLFDOVFKHGXOHVDQG¿QLWH occupancy dates. She is very detail-oriented and believes accurate estimating plays a crucial role in the success of every project. Her approach to estimating is to be involved in every aspect of the preconstruction phase to ensure the correct costs are included early-on in the budgeting process.
19 Years with Howell Contact 303.241.3971 kbarela@howelldenver.com CertiÀcations » LEED Accredited Professional
Katie enjoys working in collaboration with the owner and design team to discover cost-saving opportunities while maintaining design intent. She thoroughly understands Howell’s open-book process and is committed to helping our clients understand exactly how their dollars are being spent.
ROLES & RESPONSIBILITIES » Communication point during preconstruction » Preconstruction planning, value engineering, and constructibility » Initial project scheduling and budgeting » Procurement of long lead materials and subcontractor selection » Safety pre-planning with Jeremy Kellogg and Nate Lerma » On-going resource during construction
SELECT EXPERIENCE *BVSD Louisville Elementary School & Middle School Renovations $3.8M / 69k SF
Western Union Project Hometown HQ TI $55M / 350k SF
Littleton Public Schools Gudy Gaskill Elementary $31M / 90k SF
Eagle Elementary School Gymnasium Addition $1.5M / 10k SF
*Littleton Public Schools Secured Vestibules $422K / 2k SF
*Clear Creek Middle School Renovation $1.5M / 65k SF
Littleton Public Schools District Stadium Renovation $6.2M / 200k SF
*Wheeling Elementary School Administration Renovation $500K / 3k SF
*Littleton Public Schools Turf Field Projects $800K / 88k SF
*International School of Denver $930K / 20k SF
*Brighton High School 27J Renovation $4.7M / 210k SF
*Holyoke Jr/Sr High School Improvements BEST Grant $4.3M / 8k SF
*Denver Public Schools Beach Court & Gilpin Elementary Upgrades $1.6M / 5k SF
Comcast Spotlight TI - Building A Expansion $2M / 24k SF
Denver Health Gipson Eastside Clinic Renovation $6M / 58k SF
*Indicates Summer Wonder Project
16
TAB 03: COMPOSITION OF PROPOSED TEAM
TEAM MEMBER QUALIFICATIONS ALIGNMENT Howell has a deep resume of occupied renovations and additions experience on fast-track schedules. We understand the nature of ‘summer wonder’ school projects and the consequences of an untimely completion. Some of our ‘summer wonder’ clients include BVSD, Brighton 27J, Denver Public Schools, Holyoke RE-1J, International School of Denver, and Littleton Public Schools. We have a tremendous track record of project outcomes for these clients, completing all projects within the summer time frames and established budgets.
ANTICIPATED SERVICES REQUIRED FOR PROJECT SUCCESS 2YHUWKHODVW\HDUVZHKDYHOHDUQHGWKHG\QDPLFVRIDQRFFXSLHGFDPSXVUHQRYDWLRQDUHVLJQL¿FDQWO\GLIIHUHQWWKDQWKHYDULDEOHVRI your average education improvement project. These dynamics include: » Early on-boarding of key trades » Increased communication to ensure project success » Timely procurement of long lead mechanical items » Project success is even more critical with the visibility of the District, stakeholders, and students The Nederland Elementary School and Middle - Senior High School projects will require a seasoned general contractor that not only XQGHUVWDQGV WKHVH G\QDPLFV EXW KDV D SURYHQ WUDFN UHFRUG RI VXFFHVVIXOO\ PDQDJLQJ WKHP LQ DGGLWLRQ WR WKH QRUPDO GLI¿FXOWLHV LQ FRQVWUXFWLRQ%DVHGRQRXUH[WHQVLYHH[SHULHQFHZLWKWKHVHW\SHVRIIDVWWUDFNSURMHFWVZHKDYHLGHQWL¿HGNH\DUHDVRIIRFXVWKDWZLOO allow our team to deliver successful outcome certainty for BVSD. Build a Highly Functional, Collaborative Team Communication and high-levels of trust are critical in your project. By fostering a culture of high trust and collaboration, you enable the team to support each other throughout to project - even as challenges present themselves. By ZRUNLQJDVDWHDPDQG¿QGLQJVROXWLRQVWKDWEHQH¿WWKHSURMHFWWHDPDQGFDPSXVDVDZKROHZHFDQPLWLJDWH any potential challenges. Value Engineering - Preconstruction Planning Howell recommends participating in design and budget meetings immediately upon project award. This participation will allow for our team to listen in on any design changes that could impact the overall cost budget. In these PHHWLQJV+RZHOOZLOO¿QGDQGUHFRPPHQGDQ\YDOXHHQJLQHHULQJLGHDVWKDWZRXOGEHEHQH¿FLDOWR%96'ZKLOHVWLOO maintaining design intent. Staying On-track with Critical Design Milestones A phased design and construction approach may enable the team to start a project on time, but all too often the end date is not accelerated due to construction material procurement and permitting complications. In order to complete this project on time and within budget, aggressive yet achievable goals for design and construction objectives are of utmost importance. Designing and pre-ordering long lead materials and equipment will be essential to the success of this project.
17
TAB 03: COMPOSITION OF PROPOSED TEAM
PROJECT TEAM MEMBER REFERENCES Littleton Public Schools partners with many of the same general contractors on your pre-approved list, and we encourage you to review our references. LPS has shared that Howell’s teams have consistently out-performed other contractors while delivering multiple projects within their current bond program. In addition, our performance with Boulder Valley School District this previous summer highlighted our ability to complete projects on time and with a seamless, well-coordinated construction process.
ANDY STEWART, PE, LEED® AP Principal-in-Charge » Martha Nelson, Metro State University of Denver / 410.913.2499 » Kerry Abernathy, Flintrock Construction / 719.323.9940 » Adele Willson, Hord Coplan Macht / 303.378.9663
TODD JOHNSTON Sr. Preconstruction Manager / Sr. Project Manager » Greg Martin, Jacobs Engineering Group / 720.660.3913 » Mike Lopez, Jacobs Engineering Group / 303.771.1024 » Brad Leitner, Littleton Public School District / 303.347.3413
JEREMY KELLOGG Project Manager » Henry Stephen, Boulder Valley School District / 720.561.5953 » Brad Leitner, Littleton Public School District / 303.347.3413 » Greg Martin, Jacobs Engineering Group / 720.660.3913
RUDY CORNEJO Superintendent » Henry Stephen, Boulder Valley School District / 303.324.0983 » Nick Aden, UCHealth / 760.579.9886 » Eric Glatt, Task Project Manager / 720.660.7328
KATIE BARELA, LEED® AP Sr. Estimator » Henry Stephen, Boulder Valley School District / 720.561.5953 » Greg Martin, Jacobs Engineering Group / 720.660.3913 » Brad Leitner, Littleton Public Schools / 303.347.3413
18
TAB 04: ATTACHMENT H ACKNOWLEDGMENT
PAY APPLICATION REQUIREMENT CHECKLIST Howell has reviewed Attachment I as well as the backup documentation on Attachment J “Pay Application Requirement Checklist” and we will: a. Include all applicable information and backup documentation listed in the Attachment J checklist and as required in the 2022 Bond General Contract Conditions when submitting Pay Applications, and b. Submit in a timely manner any invoices and / or costs submitted on pay applications that are greater than 90 days old may be deducted from payments and subject to independent audit at CM/GC expense. Pay Applications for the prior month will be submitted to BVSD by the 15th day of the current month for review and processing.
19
Nederland Elementary School Construction Budget = $966,838.00 CMGC
CMGC to complete the highlighted fields by (date) Howell Construction 8085 E. Harvard Ave Denver, CO 80231
The Fee Proposal requested on this form is based on the construction budget in the amount of $966,838.00 and construction duration of 6 months.
Date Prepared
Prepared by: Andy Stewart Date: 9/17/25
Contract Form
Boulder Valley School District Standard Form of Agreement Between Boulder Valley School District RE-2 and Construction Manager / General Contractor where the CM/GC is also the Contractor
Fee Proposal Table and Clarifications Contract Reference
Description
Article 7.1.1 and Matrix
Design Phase Fee (Fixed Fee Amount)
Article 7.1.2 and Matrix
Construction Phase Fee (as expressed as a % of the Construction Budget)
Article 8.2.1 and Matrix
General Conditions (proposing firms to provide detailed estimate in support on Attachment C)
General Contract Conditions & Matrix -- IMPORTANT NOTE - Do NOT include the dollar or percentage amounts from these insurance lines in the line above.
Workers Compensation Insurance
GC 33.00
To be included in DPE Multiplier
General Liability & All Other Insurances required but not noted below
GC 33.00
1.00%
Builder's Risk Insurance
GC 33.00
Bond Rate (P&P)
GC 8.00
0.15% 0.9600%
Amount of Fee expressed as a percentage of $966,838.00
$
13,029 7.84% Total Dollar Value of General Conditions
$
80,163
Personnel Assigned to the Project (all salaried staff shall be included in GC's) 1.58
Article 7
Direct Personnel Expense Multiplier - (shall be greater than 1)
Article 8
Names of All Salaried Personnel Assigned to Project
Position
Years of Experience
Andy Stewart
Principal in Charge
36
Todd Johnston
Senior Precon / Project Manager
25
Jeremy Kellogg
Project Manager
15
Katie Barela
Senior Estimator
25
Rudy Cornejo
Superintendent
12
Identify the following Pre-Construction Personnel assigned to this project
Please complete your firms recommended Contingencies per each stage of the project development leading to a GMP Contingency Schematic Design 100% Design Development Design Contingency 2% 2% Bidding/Escalation Contingency 3% 3% Construction Contingency 5% 5% Total Contingency 10% 10%
Construction Documents (GMP) 0% 0% 5% 5%
COMMENTS / ADDITIONAL CONSIDERATONS Insert additional financial considerations and any exceptions taken to the contract and proposal form presented.
NOTES:
BVSD CLARIFICATIONS: (1) CM/GC shall be authorized to submit proposals for portions of the work only with the prior written consent of the Owner. Self-performed work shall be performed on cost of work basis as defined in Article 8.
Boulder Valley School District RE-2 Billable rates are NOT allowed as part of contract. Boulder Valley School District RE-2 GENERAL CONDITIONS MATRIX
CM/GC
Required of Required of Owner Arch
Required of CM/GC
Contractor Cost Attachment C - Construction Manager / General Contractor Fee Structure
Design Phase Fee
Construction Phase Fee
Cost of the Work Article 8 of the Contract General Conditions
A.
PROJECT MANAGEMENT
1
Architectural Consultant Selection
2
Civil Consultant Selection
3
Structural Consultant Selection
4
Mechanical Consultant Selection
5
Electrical Consultant Selection
6
Special Consultant Selection
7
Surveyor Selection
8
Review Design Concepts
9
Develop Bid Packages (if req'd)
10
Site Use Recommendations
11
Material Selection Recommendations
12
Building Systems Recommendations
13
Building Equipment Recommendations (Movable)
14
Building Equipment Recommendations (Fixed)
15
Coordinate Owner-Supplied Fixed Equipment
16
Coordinate Owner-Supplied Movable Equipment
17
Construction Feasibility Recommendations
18
Construction Scheduling Recommendations
19
Life cycle Costing Analysis
20
Informal Value Engineering
21
Formal Value Engineering
22
Labor Availibility Review (Subcontractors)
23
Material Availability Review
24
Equipment Availability Review
25
Subcontractor Availability Review
26
Use of Owner's Project Mgmt Software (e-Builder)
B.
PROJECT COST CONTROL
1
Total Project Cost Budget
2
Construction Cost Budget
3
Preliminary Cost Estimate
4
Schematic Design Cost Estimate
5
Design Development Cost Estimate
6
GMP Proposal
7
Bid Package Estimates
8
Construction Cash Flow Projections
9
Material Surveys & Trade Contractor Estimates
10
Set-Up Cost Accounting
11
Set-Up Reporting Methods
12
Set-Up Payment Procedure
13
Set-Up Change Order Procedure
14
Prepare Change Order Cost Estimates
15
Verify Correctness of Qty & Prices of All COs
16
Continued Project Cost Monitoring
C.
PROJECT SCHEDULING
1
Preconstruction Activity Schedule (Bar Chart)
2
Construction Activity Schedule (CPM Set-Up)
3
Construction Activity Schedule (CPM Updates)
4
Shop Drawing & Submittal Schedule/Procedure
5
Exterior Skin/Typ. Unit Mock-Up
6
Short-Interval Schedules
7
Occupancy Schedule
D.
SUBCONTRACTOR SELECTION/PURCHASING
1
Set Prequalification Criteria
2
Recommend Subcontractor Selection Methods
3
Recommend Subcontractor Award Methods
4
Develop Subcontractor Interest
5
Local / Regional Subcontractor Solicitation
6
Bid Advertisements
7
Project Briefing / Open House Meeting
8
Prepare Bidding Schedules
9
Issue Plans, Specifications & Addenda
10
Receive Bids
11
Analyze Bids
Subcontracts
x x x x x x x x x x x x x x x x
x x x x x x x x x x x x
x x x x x x x x x
x
x
x x x x x x x x x
x x
x x x x x x x
x x x x x x x
x x x x x x x x x x x
Page 1 of 6
x x
Contractor notes and Explanations
Boulder Valley School District RE-2 Billable rates are NOT allowed as part of contract. Boulder Valley School District RE-2 GENERAL CONDITIONS MATRIX
CM/GC
Required of Required of Owner Arch
Required of CM/GC
Contractor Cost Attachment C - Construction Manager / General Contractor Fee Structure
Design Phase Fee
Construction Phase Fee
Cost of the Work Article 8 of the Contract General Conditions
12
Recommend Award
x
13
Determine Local Manpower Availability
x
14
Prepare Subcontracts & Supplier Contracts
15
Administration of Subcontracts
E.
CONTRACT DOCUMENT COORDINATION
1
Constructibility Review & Recommendations
2
Responsbility for Temporary Facilities
3
Review For Jurisdictional Overlap
4
Review For Inclusion of All Work
5
Review for Adequately Phased Construction
6
Identify Long-Lead Items
7
Review For Install. of Owner Supplied Fixed Equip.
8
Apply For Building Permits
9
Obtain Building Permits
F.
GENERAL CONTRACTOR OFF-SITE STAFF & SERVICES
1
Corporate Executives
2
Principal In Charge
3
Project Executive in Charge
4
Operations Manager
5
Project Coordinator / Assistants
6
Legal (Basic Service)
7
Accounting
8
Sr. Project Manager
9
Project Manager
10
Project Engineer(s)
11
Mechanical & Electrical Coordinator
12
BIM / Virtual Design Manager
14
Safety Manager
15
EEO Officer
16
Secretarial
17
Preconstruction Services
18
Project Estimating
19
Project Accounting
20
Project Data Processing
21
Project Scheduling
22
Project Purchasing
23
Basic Legal Services
24
Home Office Operating Expenses
25
Value Engineering
26
Subcontractor Payment Systems (i.e. Textura)
27
Employee Bonuses
G.
GENERAL CONTRACTOR ON-SITE STAFF & SERVICES
1
Sr. Project Manager
2
Project Manager
3
Operations Manager
4
Safety Manager
5
Project Superintendent(s)
6
Project Engineer(s) (if required)_
7
Mechanical & Electrical Coordinator (if required)
8
Quality Control Engineer (if required)
9
Scheduler (if required)
10
Weekly Safety Audits
11
Timekeeper (if required)
12
Project Estimator(s)
13
Project Assistant(s)/Project Coordinator(s) (if required)
14
Clerical support (if required)
15
Safety Engineer
16
EEO Officer (if required)
17
Field Accounting (if required)
18
Data Processing (if required)
19
Engineering & Layout (Initial)
20
Field Engineer (Line & Grade)
21
Registered Surveyor
22
Security Guard/Watchman Service (if required)
Subcontracts
x x
x x x x x x x x x
x x x x x x x x x x x x x x x x x x x x x x x x
x x
x
x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x
$ $
x x x x x x x x x x x x x x x x
Page 2 of 6
25,500 24,133
Contractor notes and Explanations
Boulder Valley School District RE-2 Billable rates are NOT allowed as part of contract. Boulder Valley School District RE-2 GENERAL CONDITIONS MATRIX
CM/GC
Required of Required of Owner Arch
Required of CM/GC
Contractor Cost Attachment C - Construction Manager / General Contractor Fee Structure
Design Phase Fee
Construction Phase Fee
Cost of the Work Article 8 of the Contract General Conditions
23
Personal Computer (if required)
24
Fax Machine (if required)
25
Copier (if required)
26
Electronic Plan Tables
27
Ipads
28
Computer IT Support Costs
29
Employee Bonuses
H.
TRAVEL AND LODGING
1
Off-Site Travel Cost
2
Off-Site Staff Transportation
3
On-Site Project Manager Transportation
4
Superintendent's Transportation
5
Engineer's Transportation
6
Project Staff Moving Expense
7
Project Staff Subsistence Costs
I.
QUALITY CONTROL/WARRANTY
1
Implement Quality Control Plan For Construction
2
Quality Control Responsibility
3
Quality Control Inspection Responsibility
4
Field Inspector
5
Inspector's Office
6
Inspector's Transportation
7
Inspector's Equipment
8
Testing & Inspections
9
Special Inspection Consultants
10
Special Testing Consultants
11
Concrete Testing
12
Masonry Testing
13
Compaction Testing
14
Welding Testing
15
Soils Investigations/Geotechnical Reports
16
Environmental Testing
17
Environmental Cleanup Coordination
18
Special Testing Services
19
Project Progress Photographs
20