BVSD Board of Education · Document
BVSD Eisenhower ES GMP Exhibits.pdf (10,245 KB)
Regular Meeting, November 10, 2026 · item 7.6: Amendment to the contract for Eisenhower Elementary School · 104 pages
This is the text extracted from the file, without its layout, tables, or images. Use the original for anything that matters.
Exhibit A Drawings, specifications and documents used to prepare the GMP
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Printed on Thu Oct 15, 2026 at 12:34 pm MDT Job #: 8735 BVSD - Eisenhower ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction
Current Drawings Drawing Number
Drawing Title
Revision
Drawing Date
Received Date
Set
Status
General G001
COVER SHEET
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
G110
FIRST FLOOR CODE PLAN
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
GENERAL NOTES
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
AS101
ARCHITECTURAL SITE PLAN
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
AS500
MONUMENTAL SIGN
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
AD110
FIRST FLOOR DEMOLITION PLAN - OVERALL
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
AD111
FIRST FLOOR DEMO PLAN - AREA 111
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
AD112
FIRST FLOOR DEMO PLAN - AREA 112
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
AD113
FIRST FLOOR DEMO PLAN - AREA 113
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
AD400
KINDERGARTEN ENLARGED DEMO PLAN AND DEMO RCP
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
ACD111
FIRST FLOOR DEMO RCP - AREA 111
0
08/28/2026
08/28/2026
26.08.28 CD's
Published
ACD110
FIRST FLOOR DEMOLITION RCP - OVERALL
0
08/28/2026
08/28/2026
26.08.28 CD's
Published
ACD112
FIRST FLOOR DEMO RCP - AREA 112
0
08/28/2026
08/28/2026
26.08.28 CD's
Published
ACD113
FIRST FLOOR DEMO RCP - AREA 113
0
08/28/2026
08/28/2026
26.08.28 CD's
Published
A110
FIRST FLOOR PLAN - OVERALL
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
A111
FIRST FLOOR PLAN - AREA 111
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
A112
FIRST FLOOR PLAN - AREA 112
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
A113
FIRST FLOOR PLAN - AREA 113
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
AC110
FIRST FLOOR REFLECTED CEILING PLAN - OVERALL
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
AC111
FIRST FLOOR REFLECTED CEILING PLAN - AREA 111
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
Structural S001 Architectural
Page 1 of 4
Printed on Thu Oct 15, 2026 at 12:34 pm MDT Job #: 8735 BVSD - Eisenhower ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction
Drawing Number
Drawing Title
Revision
Drawing Date
Received Date
Set
Status
AC112
FIRST FLOOR REFLECTED CEILING PLAN - AREA 112
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
AC113
FIRST FLOOR REFLECTED CEILING PLAN - AREA 113
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
A160
OVERALL ROOF PLAN
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
A400
KINDERGARTEN ENLARGED FLOOR PLANS
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
A401
ENLARGED PLANS
0
05/15/2026
05/15/2026
26.05.15 - DD's
Published
A420
INTERIOR ELEVATIONS
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
A500
DETAILS
0
08/28/2026
08/28/2026
26.08.28 CD's
Published
A600
DOOR AND WINDOW SCHEDULES
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
ENLARGED INTERIOR FINISH PLAN - KINDERGARTEN
0
08/28/2026
08/28/2026
26.08.28 CD's
Published
SIGNAGE LEGEND & SCHEDULE
0
08/28/2026
08/28/2026
26.08.28 CD's
Published
MD-111
HVAC DEMOLITION PLAN - AREA 111
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
MD-112
HVAC DEMOLITION PLAN - AREA 112
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
MD-121
HVAC ROOF DEMOLITION PLAN - AREA 111
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
MD-122
HVAC ROOF DEMOLITION PLAN - AREA 112
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
M-001
MECHANICAL LEGENDS & NOTES
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
M-002
MECHANICAL SCHEDULES
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
M-111
HVAC PLAN - AREA 111
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
M-112
HVAC PLAN - AREA 112
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
M-121
HVAC ROOF PLAN - AREA 111
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
M-122
HVAC ROOF PLAN - AREA 112
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
M-401
MECHANICAL DETAILS
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
M-501
MECHANICAL CONTROLS
0
08/28/2026
08/28/2026
26.08.28 CD's
Published
Interior I400 Signage SN100 Mechanical
Page 2 of 4
Printed on Thu Oct 15, 2026 at 12:34 pm MDT Job #: 8735 BVSD - Eisenhower ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction
Drawing Number M-502
Drawing Title
Revision
Drawing Date
Received Date
Set
Status
MECHANICAL CONTROLS
0
08/28/2026
08/28/2026
26.08.28 CD's
Published
PD-111
DOMESTIC WATER DEMOLITION PLAN - AREA 111
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
P-001
PLUMBING LEGENDS & NOTES
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
P-111
DOMESTIC WATER PLAN - AREA 111
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
ED-111
LIGHTING DEMOLITION PLAN - AREA 111
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
ED-112
LIGTHING DEMOLITION PLAN - AREA 112
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
ED-113
LIGHTING DEMOLITION PLAN - AREA 113
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
ED-122
ROOF POWER DEMOLTION PLAN - AREA 112
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
ED-121
ROOF POWER DEMOLITION PLAN - AREA 111
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
ED-131
FIRE ALARM DEMOLITION PLAN - AREA 111
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
ED-132
FIRE ALARM DEMOLITION PLAN - AREA 112
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
ED-133
FIRE ALARM DEMOLITION PLAN - AREA 113
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-001
ELECTRICAL LEGENDS & NOTES
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-002
ELECTRICAL SCHEDULES
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-011
ELECTRICAL ONE-LINE DIAGRAM
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-101
ELECTRICAL SITE PLAN
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-111
LIGHTING PLAN - AREA 111
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-112
LIGHTING PLAN - AREA 112
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-113
LIGHTING PLAN - AREA 113
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-120
POWER PLAN - OVERALL
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-121
ROOF POWER PLAN - AREA 111
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-122
ROOF POWER PLAN - AREA 112
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-131
FIRE ALARM PLAN - AREA 111
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
Plumbing
Electrical
Page 3 of 4
Printed on Thu Oct 15, 2026 at 12:34 pm MDT Job #: 8735 BVSD - Eisenhower ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction
Drawing Number
Drawing Title
Revision
Drawing Date
Received Date
Set
Status
E-132
FIRE ALARM PLAN - AREA 112
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-133
FIRE ALARM PLAN - AREA 113
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-201
ENLARGED ELECTRICAL PLANS
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-202
ENLARGED ELECTRICAL PLANS - KINDERGARTEN
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-301
ELECTRICAL PANEL SCHEDULES
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-401
ELECTRICAL DETAILS
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
Page 4 of 4
Printed on Thu Oct 15, 2026 at 12:46 pm MDT Job #: 8735 BVSD - Eisenhower ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction
Current Specifications Number
Description
Revision
Issued Date
Received Date
Set
00 - Procurement and Contracting Requirements 00 0103
PROJECT DIRECTORY
0
26.08.28 - CD's
00 0108
TABLE OF CONTENTS
0
26.08.28 - CD's
00 4322
UNIT PRICES FORM
0
26.08.28 - CD's
00 4323
ALTERNATES FORM
0
26.08.28 - CD's
00 5000
CONTRACTING FORMS AND SUPPLEMENTS
0
26.08.28 - CD's
00 7200
GENERAL CONDITIONS
0
26.08.28 - CD's
000107
SEALS PAGE
0
26.08.28 - CD's
000110
COVER PAGE
0
26.08.28 - CD's
01 - General Requirements 01 1000
SUMMARY
0
26.08.28 - CD's
01 2000
PRICE AND PAYMENT PROCEDURES
0
26.08.28 - CD's
01 2200
UNIT PRICES
0
26.08.28 - CD's
01 2300
ALTERNATES
0
26.08.28 - CD's
01 2500
SUBSTITUTION PROCEDURES
0
26.08.28 - CD's
01 3000
ADMINISTRATIVE REQUIREMENTS
0
26.08.28 - CD's
01 3216
CONSTRUCTION PROGRESS SCHEDULE
0
26.08.28 - CD's
01 4000
QUALITY REQUIREMENTS
0
26.08.28 - CD's
01 5000
TEMPORARY FACILITIES AND CONTROLS
0
26.08.28 - CD's
01 5713
TEMPORARY EROSION AND SEDIMENT CONTROL
0
26.08.28 - CD's
01 6000
PRODUCT REQUIREMENTS
0
26.08.28 - CD's
01 6116
VOLATILE ORGANIC COMPOUND (VOC) CONTENT RESTRICTIONS
0
26.08.28 - CD's
01 7000
EXECUTION AND CLOSEOUT REQUIREMENTS
0
26.08.28 - CD's
01 7419
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
0
26.08.28 - CD's
01 7800
CLOSEOUT SUBMITTALS
0
26.08.28 - CD's
01 7900
DEMONSTRATION AND TRAINING
0
26.08.28 - CD's
01 9113
GENERAL COMMISSIONING REQUIREMENTS
0
26.08.28 - CD's
02 - Existing Conditions 02 4100
DEMOLITION
0
26.08.28 - CD's
02 4119
SELECTIVE STRUCTURE DEMOLITION
0
26.08.28 - CD's
03 2000
CONCRETE REINFORCING
0
26.08.28 - CD's
03 3000
CAST-IN-PLACE CONCRETE
0
26.08.28 - CD's
04 0511
MASONRY MORTARING AND GROUTING
0
26.08.28 - CD's
04 2000
UNIT MASONRY
0
26.08.28 - CD's
03 - Concrete
04 - Masonry
05 - Metals
Page 1 of 4
Printed on Thu Oct 15, 2026 at 12:46 pm MDT Job #: 8735 BVSD - Eisenhower ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction
Number
Description
Revision
Issued Date
Received Date
Set
05 1200
STRUCTURAL STEEL FRAMING
0
26.08.28 - CD's
05 4000
COLD-FORMED METAL FRAMING
0
26.08.28 - CD's
05 5133
METAL LADDERS
0
26.08.28 - CD's
06 - Wood, Plastics, and Composites 06 1000
ROUGH CARPENTRY
0
26.08.28 - CD's
06 2000
FINISH CARPENTRY
0
26.08.28 - CD's
07 - Thermal and Moisture Protection 07 0553
FIRE AND SMOKE ASSEMBLY IDENTIFICATION
0
26.08.28 - CD's
07 2100
THERMAL INSULATION
0
26.08.28 - CD's
07 2500
WEATHER BARRIERS
0
26.08.28 - CD's
07 5300
ELASTOMERIC MEMBRANE ROOFING
0
26.08.28 - CD's
07 6200
SHEET METAL FLASHING AND TRIM
0
26.08.28 - CD's
07 9200
JOINT SEALANTS
0
26.08.28 - CD's
08 1113
HOLLOW METAL DOORS AND FRAMES
0
26.08.28 - CD's
08 1416
FLUSH WOOD DOORS
0
26.08.28 - CD's
08 4313
ALUMINUM-FRAMED STOREFRONTS
0
26.08.28 - CD's
08 7100
DOOR HARDWARE
0
26.08.28 - CD's
08 8000
GLAZING
0
26.08.28 - CD's
08 9100
LOUVERS
0
26.08.28 - CD's
09 0561
COMMON WORK RESULTS FOR FLOORING PREPARATION
0
26.08.28 - CD's
09 2116
GYPSUM BOARD ASSEMBLIES
0
26.08.28 - CD's
09 5100
ACOUSTICAL CEILINGS
0
26.08.28 - CD's
09 6500
RESILIENT FLOORING
0
26.08.28 - CD's
09 6566
RESILIENT ATHLETIC FLOORING
0
26.08.28 - CD's
09 6813
TILE CARPETING
0
26.08.28 - CD's
09 9113
EXTERIOR PAINTING
0
26.08.28 - CD's
09 9123
INTERIOR PAINTING
0
26.08.28 - CD's
10 1100
VISUAL DISPLAY UNITS
0
26.08.28 - CD's
10 1400
SIGNAGE
0
26.08.28 - CD's
10 2600
WALL AND DOOR PROTECTION
0
26.08.28 - CD's
MANUFACTURED WOOD CASEWORK
0
26.08.28 - CD's
22 0500
COMMON WORK RESULTS FOR PLUMBING
0
26.08.28 - CD's
22 0513
COMMON MOTOR REQUIREMENTS FOR PLUMBING EQUIPMENT
0
26.08.28 - CD's
22 0519
METERS AND GAUGES FOR PLUMBING PIPING
0
26.08.28 - CD's
22 0523
GENERAL DUTY VALVES FOR PLUMBING
0
26.08.28 - CD's
22 0529
HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT
0
26.08.28 - CD's
08 - Openings
09 - Finishes
10 - Specialties
12 - Furnishings 12 3200 22 - Plumbing
Page 2 of 4
Printed on Thu Oct 15, 2026 at 12:46 pm MDT Job #: 8735 BVSD - Eisenhower ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction
Number
Description
Revision
Issued Date
Received Date
Set
22 0553
IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT
0
26.08.28 - CD's
22 0700
PLUMBING INSULATION
0
26.08.28 - CD's
22 1023
PLUMBING PUMPS
0
26.08.28 - CD's
22 1116
DOMESTIC WATER PIPING
0
26.08.28 - CD's
22 1119
DOMESTIC WATER PIPING SPECIALITIES
0
26.08.28 - CD's
22 1123
FACILITY NATURAL GAS PIPING
0
26.08.28 - CD's
22 3000
WATER HEATERS
0
26.08.28 - CD's
23 - Heating, Ventilating, and Air Conditioning (HVAC) 23 0500
COMMON WORK RESULTS FOR MECHANICAL
0
26.08.28 - CD's
23 0507
MOTORS, DRIVES, MOTOR CONTROLLERS AND ELECTRICAL REQUIRED FOR
0
26.08.28 - CD's
23 0510
BASIC PIPING MATERIALS AND METHODS
0
26.08.28 - CD's
23 0518
PIPING SPECIALITIES
0
26.08.28 - CD's
23 0519
METERS AND GAUGES FOR MECHANCIAL PIPING
0
26.08.28 - CD's
23 0523
GENERAL DUTY VALVES FOR MECHANICAL PIPING
0
26.08.28 - CD's
23 0529
HANGERS AND SUPPORTS FOR MECHANICAL SYSTEMS
0
26.08.28 - CD's
23 0540
VIBRATION CONTROL FOR MECHANICAL PIPING AND EQUIPMENT
0
26.08.28 - CD's
23 0553
IDENTIFICATION FOR MECHANICAL SYSTEMS
0
26.08.28 - CD's
23 0593
TESTING, ADJUSTING, AND BALANCING FOR MECHANICAL
0
26.08.28 - CD's
23 0700
INSULATION FOR MECHANICAL SYSTEMS
0
26.08.28 - CD's
23 0900
INSTRUMENTATION AND CONTROL FOR MECHANICAL SYSTEMS
0
26.08.28 - CD's
23 0993
SEQUENCES OF OPERATION FOR MECHANICAL SYSTEMS
0
26.08.28 - CD's
23 3113
METAL DUCTS
0
26.08.28 - CD's
23 3300
AIR DUCT ACCESSORIES
0
26.08.28 - CD's
23 3600
AIR TERMINAL UNITS
0
26.08.28 - CD's
23 3713
DIFFUSERS, REGISTERS, GRILLES
0
26.08.28 - CD's
23 7443
ROOFTOP HEATING AND COOLING UNITS
0
26.08.28 - CD's
23 8000
DECENTRALIZED HVAC EQUIPMENT
0
26.08.28 - CD's
23 8126
DUCTLESS SPLIT SYSTEMS
0
26.08.28 - CD's
26 0500
COMMON WORK RESULTS FOR ELECTRICAL
0
26.08.28 - CD's
26 0519
LOW VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
0
26.08.28 - CD's
26 0529
HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
0
26.08.28 - CD's
26 0533
RACEWAY AND WIREWAY FOR ELECTRICAL SYSTEMS
0
26.08.28 - CD's
26 0534
CABINETS, BOXES, AND FITTINGS
0
26.08.28 - CD's
26 0553
IDENTIFICATION FOR ELECTRICAL SYSTEMS
0
26.08.28 - CD's
26 0583
WIRING CONNECTIONS
0
26.08.28 - CD's
26 0923
LIGHTING CONTROL DEVICES
0
26.08.28 - CD's
26 2726
LOW VOLTAGE CIRCUIT PROTECTIVE DEVICES
0
26.08.28 - CD's
26 2800
Low-Voltage Circuit Protective Devices
0
26.08.28 - CD's
26 5000
LIGHTING
0
26.08.28 - CD's
26 5200
EMERGENCY LIGHTING
0
26.08.28 - CD's
26 - Electrical
Page 3 of 4
Printed on Thu Oct 15, 2026 at 12:46 pm MDT Job #: 8735 BVSD - Eisenhower ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction
Number
Description
Revision
Issued Date
Received Date
Set
27 - Communications 27 0500
COMMON WORK RESULTS FOR COMMUNICATIONS
0
26.08.28 - CD's
27 0528
PATHWAYS FOR COMMUNICATION SYSTEMS
0
26.08.28 - CD's
27 5123
INTERCOMMUNCATIONS AND PROGRAM SYSTEMS
0
26.08.28 - CD's
0
26.08.28 - CD's
0
26.08.28 - CD's
28 - Electronic Safety and Security 28 3111
FIRE DETECTION AND ALARM
32 - Exterior Improvements 32 1313
CONCRETE PAVING
Page 4 of 4
797 Ventura Street, Aurora, CO 80011 Project: K1225 - BVSD - Eisenhower ES Renovations Owner: BVSD Architect: RTA
Date: Estimator: Project SF: Duration in Months: Estimate #:
10/19/26 Rakshita 59,000 3.00 CD Estimate R1
Project Summary Sheet - Estimated Cost of the Work
Division #0 Division #1 Division #2 Division #3 Division #4 Division #5 Division #6 Division #7 Division #8 Division #9 Division #10 Division #11 Division #12 Division #13 Division #14 Division #21 Division #22 Division #23 Division #25 Division #26 Division #27 Division #28 Division #31 Division #32 Division #33
Procurement and Contracting Requirements General Requirements Existing Conditions Concrete Masonry Metals Wood, Plastics, and Composites Thermal and Moisture Protection Openings Finishes Specialties Equipment Furnishings Special Construction Conveying Equipment Fire Suppression Plumbing Heating, Ventilating and Air Conditioning Integrated Automation Electrical Communications Electronic Safety and Security Earthwork Exterior Improvements Utilities
DD Estimate CD Estimate Difference $103,344 $87,058 ($16,286) $379,492 $354,921 ($24,571) $41,048 $24,845 ($16,203) $26,897 $6,947 ($19,950) $25,423 $4,000 ($21,423) $3,047 $15,086 $12,040 $74,968 $68,317 ($6,651) $35,399 $22,536 ($12,863) $81,257 $79,125 ($2,132) $226,561 $140,615 ($85,946) $12,305 $12,046 ($259) $0 $0 $0 $0 $1,900 $1,900 $0 $0 $0 $0 $0 $0 $0 $30,900 $30,900 $109,128 $0 ($109,128) $491,637 $732,210 $240,573 $0 $0 $0 $497,859 $505,571 $7,712 $272,557 $164,820 ($107,737) $0 $0 $0 $6,467 $4,700 ($1,767) $60,041 $55,925 ($4,116) 0 $0 $0
$1.48
/SF
3.8% of Direct Costs
$6.02
/SF
15.4% of Direct Costs
$0.42
/SF
1.1% of Direct Costs
$0.12
/SF
0.3% of Direct Costs
$0.07
/SF
0.2% of Direct Costs
$0.26
/SF
0.7% of Direct Costs
$1.16
/SF
3.0% of Direct Costs
$0.38
/SF
1.0% of Direct Costs
$1.34
/SF
3.4% of Direct Costs
$2.38
/SF
6.1% of Direct Costs
$0.20
/SF
0.5% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$0.03
/SF
0.1% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$0.52
/SF
1.3% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$12.41
/SF
31.7% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$8.57
/SF
21.9% of Direct Costs
$2.79
/SF
7.1% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$0.08
/SF
0.2% of Direct Costs
$0.95
/SF
2.4% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
100.0% of Direct Costs
Subtotal
$2,447,429
$2,311,523
($135,906)
$39.18
/SF
Utility Tap & Devel. Fees Permit Allowance Use Tax Construction Contingency Builders Risk Insurance Comprehensive General Liability Insurance Performance and Payment Bond Escalation Allowance Contractors Fee Preconstruction Services
$0 $0 $0 $195,794 $5,286 $31,719 $17,974 $0 $124,231 $17,500
$0 $0 $0 $77,263 $4,623 $30,905 $17,513 $0 $116,095 $17,500
$0 $0 $0 ($118,532) ($663) ($814) ($461) $0 ($8,137) $0
$0.00
/SF
$0.00
/SF
0.00% of Project
$0.00
/SF
0.00% of Project
$1.31
/SF
3.00% of Project
$0.08
/SF
20.00% of Costs
$0.52
/SF
1.20% of Project
$0.30
/SF
0.68% of Project
$0.00
/SF
0.00% of Project
$1.97
/SF
4.86% of Project
$0.30
/SF
Origianl Contract Amount
$2,575,421
($264,512)
$72.43
/SF
100.0% of Project
Estimated Cost of Construction
CD Estimate R1
$2,839,933
Accepted Alternates A2 : New Flooring in Gymnasium
$153,091
V14 : Lighting Fixtures - Interior - Fluorescent Renewal Priority 1
$286,559
V14 : Lighting Fixtures - Interior - Fluorescent Renewal Priority 2
$38,743
V14 : Lighting Fixtures - Interior - Fluorescent Renewal Priority 3
$238,651
V14 : Lighting Fixtures - Interior - Fluorescent Renewal Priority 4
$62,268
CD w/ Accepted Alternates Original Contract Amount fGMP Amendment New Contract Total
$3,354,733 $ $
17,500.00 $3,337,233 3,354,733
Line
Name
Duration
Start
Finish
BVSD Eisenhower ES
554d
8/1/2025
10/8/2027
Milestones
527d
8/1/2025
8/31/2027
School Milestones
455d
8/1/2025
5/20/2027 8/13/2025 A
1
Summer Break - 2025 (School Back In Session)
9d 8/1/2025 A
2
Thankgiving Break - 2025
3d 11/24/2025 A 11/26/2025 A
3
Winter Break - 2025
8d 12/23/2025 A 1/6/2026 A
4
Spring Break - 2026
5d 3/4/2026 A
3/10/2026 A
5
Summer Break - 2026
73d 6/1/2026 A
9/11/2026 A
6
Thankgiving Break - 2026
3d 11/23/2026
11/25/2026
7
Winter Break - 2026
10d 12/21/2026
1/6/2027
8
Spring Break - 2027
5d 3/15/2027
3/19/2027
9
Summer Break - 2027 - START
5/20/2027
5/20/2027
Project Milestones
280d 10/15/2025 11/20/2026
Preconstruction Milestones
280d 10/15/2025 11/20/2026
10/15/2025 A 10/15/2025 A
2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9
Summer Break - 2025 (School Back In Session)
Thankgiving Break - 2025
Winter Break - 2025
Spring Break - 2026
Summer Break - 2026
Thankgiving Break - 2026
Winter Break - 2026
Spring Break - 2027
Summer Break - 2027 - START
10
Notice to Proceed
11
DAT Meetings
12
Post-Award Meetings
13
DAT Meetings - Finals
70d 8/3/2026 A
11/20/2026
Construction Milestones
461d 11/4/2025
8/31/2027
14
Early Investigations
259d 11/4/2025 A
6/30/2027
15
Mobilization Start
3/16/2027
3/16/2027
16
Abatement Start
5/11/2027
5/11/2027
Abatement Start
17
Demo Start
5/21/2027
5/21/2027
Demo Start
18
Abatement Finish
5/24/2027
5/24/2027
Abatement Finish
19
Demo Finish
5/27/2027
5/27/2027
Demo Finish
20
Rough-in Start
5/28/2027
5/28/2027
Rough-in Start
21
Rough-in Finish
7/8/2027
7/8/2027
Rough-in Finish
22
TCO
7/30/2027
7/30/2027
TCO
23
Owner Move-in Complete
8/9/2027
8/9/2027
Owner Move-in Complete
24
Substantial Completion
8/31/2027
8/31/2027
Notice to Proceed
105d 12/1/2025 A 7/30/2026 A
12/15/2025 A 12/15/2025 A
BVSD Eisenhower ES Master Schedule Boulder Valley School District
DAT Meetings
Post-Award Meetings
DAT Meetings - Finals
Early Investigations
Mobilization Start
Substantial Completion
Job #: BVSD Eisenhower ES
Rev. date: 10/19/2026 12:02:53 PM
Data Date: 10/14/2026
Page 1 of 17
BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish
2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9
Preconstruction & Design
441d 8/28/2025
5/26/2027
RFP / RFQ Information
37d 8/28/2025 10/21/2025
25
RFP/RFQ - Issuance of RFP
8/28/2025 A 8/28/2025 A
26
RFP/RFQ - Pre-Proposal Submission
9/8/2025 A
27
RFP/RFQ - Inquiries Due
9/12/2025 A 9/12/2025 A
RFP/RFQ - Inquiries Due
28
RFP/RFQ - Addendum's
9/18/2025 A 9/18/2025 A
RFP/RFQ - Addendum's
29
RFP/RFQ - Submission Deadline
9/25/2025 A 9/25/2025 A
RFP/RFQ - Submission Deadline
30
RFP/RFQ - Evaluation / Award
10/7/2025 A 10/7/2025 A
RFP/RFQ - Evaluation / Award
31
Notice of Award
10/21/2025 A 10/21/2025 A
9/8/2025 A
RFP/RFQ - Issuance of RFP
RFP/RFQ - Pre-Proposal Submission
Notice of Award
Document Development
259d 10/21/2025 10/28/2026
Programming / DAT
239d 10/21/2025 9/30/2026
32
Program - Electrical Upgrades (Design & Precon / Estimating Services/Deliverables)
131d 10/21/2025 A 9/30/2026 A
Program - Electrical Upgrades (Design & Precon / Estimating Services/Deliverables)
33
Program - Mechanical Upgrades (Design & Precon / Estimating Services/Deliverables)
131d 10/21/2025 A 9/30/2026 A
Program - Mechanical Upgrades (Design & Precon / Estimating Services/Deliverables)
34
Program - Roofing Upgrades (Design & Precon / Estimating Services/Deliverables)
131d 10/21/2025 A 9/30/2026 A
Program - Roofing Upgrades (Design & Precon / Estimating Services/Deliverables)
Schematic Design
24d 2/20/2026
35
SD - Drawings 100% (Design & Precon / Estimating Services/Deliverables)
1d 2/20/2026 A 2/20/2026 A
36
SD - Cost Estimating & Constructability Review
10d 3/2/2026 A
37
SD - Estimate Review
8d 3/16/2026 A 3/25/2026 A
SD - Estimate Review
38
Alternates - Parking Lot Resurface, Gym Floor
1d 3/23/2026 A 3/23/2026 A
Alternates - Parking Lot Resurface, Gym Floor
Design Development
84d 2/20/2026
39
DD - Drawings 100% (Design & Precon / Estimating Services/Deliverables)
61d 2/20/2026 A 5/15/2026 A
40
DD - Cost Estimating & Constructability Review
10d 5/15/2026 A 5/29/2026 A
41
DD - Estimate Review
14d 6/1/2026 A
42
Establish IGMP
1d 6/18/2026 A 6/18/2026 A
Construction Documents
3/25/2026
3/13/2026 A
SD - Drawings 100% (Design & Precon / Estimating Services/Deliverables)
SD - Cost Estimating & Constructability Review
6/18/2026
6/18/2026 A
DD - Drawings 100% (Design & Precon / Estimating Services/Deliverables)
DD - Cost Estimating & Constructability Review
DD - Estimate Review
Establish IGMP
116d 5/15/2026 10/28/2026
43
CD - Drawings 100% (Design & Precon / Estimating Services/Deliverables/GMP)
74d 5/15/2026 A 8/28/2026 A
44
CD - Cost Estimating & Constructability Review
10d 8/28/2026 A 9/11/2026 A
45
CD - Estimate Review
19d 9/11/2026 A 10/7/2026 A
CD - Estimate Review
46
Alternates A2 Gym Floor / Lighting V14 1-4 Priorities Accepted
1d 10/14/2026
10/14/2026
Alternates A2 Gym Floor / Lighting V14 1-4 Priorities Accepted
47
Establish FGMP / After Board Meeting
10/28/2026
10/28/2026
BVSD Eisenhower ES Master Schedule Boulder Valley School District
CD - Drawings 100% (Design & Precon / Estimating Services/Deliverables/GMP)
CD - Cost Estimating & Constructability Review
Establish FGMP / After Board Meeting
Job #: BVSD Eisenhower ES
Rev. date: 10/19/2026 12:02:53 PM
Data Date: 10/14/2026
Page 2 of 17
BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks
Line
Name
Duration
Permitting
Start
Finish
113d 8/28/2026
2/10/2027
2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9
48
Permit - Submit to State
28d 8/28/2026 A
11/2/2026
49
Permit - Building (In Hand)
40d 11/3/2026
1/4/2027
50
Permit - Electrical Submit to Dora
40d 11/12/2026
1/13/2027
Permit - Electrical Submit to Dora
51
Permit - Plumbing Submit to Dora
40d 11/12/2026
1/13/2027
Permit - Plumbing Submit to Dora
52
Permit - Alternate - Fire Alarm Submit
20d 11/12/2026
12/11/2026
53
Permit - Alternate - Fire Alarm (In Hand)
40d 12/14/2026
2/10/2027
Permit - Alternate - Fire Alarm (In Hand)
54
Permit - Electrical (In Hand)
20d 1/14/2027
2/10/2027
Permit - Electrical (In Hand)
55
Permit - Plumbing (In Hand)
20d 1/14/2027
2/10/2027
Permit - Plumbing (In Hand)
Contracting & Award
10d 10/29/2026 11/11/2026
Award Trade Partners First Round
5d 10/29/2026 11/4/2026
56
Div - 22 - Plumbing
5d 10/29/2026
11/4/2026
Div - 22 - Plumbing
57
Div - 23 - HVAC
5d 10/29/2026
11/4/2026
Div - 23 - HVAC
58
Div - 26 - Electrical
5d 10/29/2026
11/4/2026
Div - 26 - Electrical
59
Div - 28 - FA Security
5d 10/29/2026
11/4/2026
Div - 28 - FA Security
Permit - Submit to State
Permit - Building (In Hand)
Permit - Alternate - Fire Alarm Submit
Award Trade Partners Second Round
10d 10/29/2026 11/11/2026
60
Div - 02 - Demo
10d 10/29/2026
11/11/2026
Div - 02 - Demo
61
Div - 03 - Concrete
10d 10/29/2026
11/11/2026
Div - 03 - Concrete
62
Div - 04 - Masonry
10d 10/29/2026
11/11/2026
Div - 04 - Masonry
63
Div - 05 - Metal
10d 10/29/2026
11/11/2026
Div - 05 - Metal
64
Div - 07 - Thermal Moisture Prot. (Roofing)
10d 10/29/2026
11/11/2026
Div - 07 - Thermal Moisture Prot. (Roofing)
65
Div - 08 - Openings (Door & Frames & Hardware)
10d 10/29/2026
11/11/2026
Div - 08 - Openings (Door & Frames & Hardware)
66
Div - 09 - Finishes (Drywall & Paint, ACT)
10d 10/29/2026
11/11/2026
Div - 09 - Finishes (Drywall & Paint, ACT)
67
Div - 32 - Ext Imp
10d 10/29/2026
11/11/2026
Div - 32 - Ext Imp
Submittals & Procurement
140d 11/5/2026
5/26/2027
Division 02 - DEMO
50d 11/12/2026 1/27/2027
68
S&P - Div 02 (Div 02 - Contractor Prepare/Submit Shop Drawings)
10d 11/12/2026
11/25/2026
S&P - Div 02 (Div 02 - Contractor Prepare/Submit Shop Drawings)
69
S&P - AP Review (Div 02 - AP Review/Submit Shop Drawings)
10d 11/30/2026
12/11/2026
S&P - AP Review (Div 02 - AP Review/Submit Shop Drawings)
70
S&P - A&E Review (Div 02 - Owner Review/Approve Shop Drawings)
10d 12/14/2026
12/29/2026
71
S&P - Procurement (Div 02 - Fabricate/Deliver)
20d 12/30/2026
1/27/2027
BVSD Eisenhower ES Master Schedule Boulder Valley School District
S&P - A&E Review (Div 02 - Owner Review/Approve Shop Drawings)
S&P - Procurement (Div 02 - Fabricate/Deliver)
Job #: BVSD Eisenhower ES
Rev. date: 10/19/2026 12:02:53 PM
Data Date: 10/14/2026
Page 3 of 17
BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish
2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9
Division 03 - CONCRETE
55d 11/12/2026
2/3/2027
72
S&P - Concrete Rebar - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Concrete Rebar - Subcontractor Submit
73
S&P - Cast-In-Place Concrete - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Cast-In-Place Concrete - Subcontractor Submit
74
S&P - Concrete Rebar - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Concrete Rebar - AP Review/Submit
75
S&P - Cast-In-Place Concrete - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Cast-In-Place Concrete - AP Review/Submit
76
S&P - Concrete Rebar - A&E Review
10d 12/14/2026
12/29/2026
S&P - Concrete Rebar - A&E Review
77
S&P - Cast-In-Place Concrete - A&E Review
10d 12/14/2026
12/29/2026
S&P - Cast-In-Place Concrete - A&E Review
78
S&P - Concrete Rebar Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Concrete Rebar Procurement/Fabricate/Deliver
79
S&P - Cast-In-Place Concrete Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Cast-In-Place Concrete Procurement/Fabricate/Deliver
Division 04 - MASONRY
55d 11/12/2026
2/3/2027
80
S&P - Masonry Mortar and Grout - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Masonry Mortar and Grout - Subcontractor Submit
81
S&P - Unit Masonry / Monument Sign- Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Unit Masonry / Monument Sign- Subcontractor Submit
82
S&P - Masonry Mortar and Grout - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Masonry Mortar and Grout - AP Review/Submit
83
S&P - Unit Masonry / Monument Sign- AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Unit Masonry / Monument Sign- AP Review/Submit
84
S&P - Masonry Mortar and Grout - A&E Review
10d 12/14/2026
12/29/2026
S&P - Masonry Mortar and Grout - A&E Review
85
S&P - Unit Masonry / Monument Sign- A&E Review
10d 12/14/2026
12/29/2026
S&P - Unit Masonry / Monument Sign- A&E Review
86
S&P - Masonry Mortar and Grout Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Masonry Mortar and Grout Procurement/Fabricate/Deliver
87
S&P - Unit Masonry / Monument SignProcurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Unit Masonry / Monument SignProcurement/Fabricate/Deliver
Division 05 - METALS
55d 11/12/2026
2/3/2027
88
S&P - Cold-formed metal framing - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Cold-formed metal framing - Subcontractor Submit
89
S&P - Metal Ladders / Safety Posts - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Metal Ladders / Safety Posts - Subcontractor Submit
90
S&P - Cold-formed metal framing - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Cold-formed metal framing - AP Review/Submit
91
S&P - Metal Ladders / Safety Posts - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Metal Ladders / Safety Posts - AP Review/Submit
92
S&P - Cold-formed metal framing - A&E Review
10d 12/14/2026
12/29/2026
S&P - Cold-formed metal framing - A&E Review
93
S&P - Metal Ladders / Safety Posts - A&E Review
10d 12/14/2026
12/29/2026
S&P - Metal Ladders / Safety Posts - A&E Review
94
S&P - Cold-formed metal framing Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Cold-formed metal framing Procurement/Fabricate/Deliver
95
S&P - Metal Ladders / Safety Posts Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Metal Ladders / Safety Posts Procurement/Fabricate/Deliver
Division 06 - WOOD PLASTICS COMPOSITES
55d 11/12/2026
2/3/2027
96
S&P - Rough Carpentry - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Rough Carpentry - Subcontractor Submit
97
S&P - Rough Carpentry - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Rough Carpentry - AP Review/Submit
BVSD Eisenhower ES Master Schedule Boulder Valley School District
Job #: BVSD Eisenhower ES
Rev. date: 10/19/2026 12:02:53 PM
Data Date: 10/14/2026
Page 4 of 17
BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks
Duration
Start
Finish
2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9
Line
Name
98
S&P - Rough Carpentry - A&E Review
10d 12/14/2026
12/29/2026
99
S&P - Rough Carpentry Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
Division 07 - THERMAL MOISTURE PROTECTION
55d 11/12/2026
2/3/2027
100
S&P - Thermal Insulation - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Thermal Insulation - Subcontractor Submit
101
S&P - Weather Barriers - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Weather Barriers - Subcontractor Submit
102
S&P - Metal Wall Panels - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Metal Wall Panels - Subcontractor Submit
103
S&P - Sheet-Metal Flashing And Trim - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Sheet-Metal Flashing And Trim - Subcontractor Submit
104
S&P - Joint Sealants - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Joint Sealants - Subcontractor Submit
105
S&P - Thermal Insulation - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Thermal Insulation - AP Review/Submit
106
S&P - Weather Barriers - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Weather Barriers - AP Review/Submit
107
S&P - Metal Wall Panels - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Metal Wall Panels - AP Review/Submit
108
S&P - Sheet-Metal Flashing And Trim - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Sheet-Metal Flashing And Trim - AP Review/Submit
109
S&P - Joint Sealants - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Joint Sealants - AP Review/Submit
110
S&P - Thermal Insulation - A&E Review
10d 12/14/2026
12/29/2026
S&P - Thermal Insulation - A&E Review
111
S&P - Weather Barriers - A&E Review
10d 12/14/2026
12/29/2026
S&P - Weather Barriers - A&E Review
112
S&P - Metal Wall Panels - A&E Review
10d 12/14/2026
12/29/2026
S&P - Metal Wall Panels - A&E Review
113
S&P - Sheet-Metal Flashing And Trim - A&E Review
10d 12/14/2026
12/29/2026
S&P - Sheet-Metal Flashing And Trim - A&E Review
114
S&P - Joint Sealants - A&E Review
10d 12/14/2026
12/29/2026
S&P - Joint Sealants - A&E Review
115
S&P - Thermal Insulation Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Thermal Insulation Procurement/Fabricate/Deliver
116
S&P - Weather Barriers Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Weather Barriers Procurement/Fabricate/Deliver
117
S&P - Metal Wall Panels Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Metal Wall Panels Procurement/Fabricate/Deliver
118
S&P - Sheet-Metal Flashing And Trim Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Sheet-Metal Flashing And Trim Procurement/Fabricate/Deliver
119
S&P - Joint Sealants Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Joint Sealants Procurement/Fabricate/Deliver
Division 08 - OPENINGS
55d 11/12/2026
2/3/2027
120
S&P - Hollow-Metal Doors and Frames - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Hollow-Metal Doors and Frames - Subcontractor Submit
121
S&P - Flush Wood Doors - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Flush Wood Doors - Subcontractor Submit
122
S&P - Aluminum Storefronts - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Aluminum Storefronts - Subcontractor Submit
123
S&P - Glazing - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Glazing - Subcontractor Submit
124
S&P - Louvers - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Louvers - Subcontractor Submit
125
S&P - Hollow-Metal Doors and Frames - AP Review/Submit
10d 11/30/2026
12/11/2026
BVSD Eisenhower ES Master Schedule Boulder Valley School District
S&P - Rough Carpentry - A&E Review
S&P - Rough Carpentry Procurement/Fabricate/Deliver
S&P - Hollow-Metal Doors and Frames - AP Review/Submit
Job #: BVSD Eisenhower ES
Rev. date: 10/19/2026 12:02:53 PM
Data Date: 10/14/2026
Page 5 of 17
BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish
2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9
126
S&P - Flush Wood Doors - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Flush Wood Doors - AP Review/Submit
127
S&P - Aluminum Storefronts - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Aluminum Storefronts - AP Review/Submit
128
S&P - Glazing - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Glazing - AP Review/Submit
129
S&P - Louvers - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Louvers - AP Review/Submit
130
S&P - Hollow-Metal Doors and Frames - A&E Review
10d 12/14/2026
12/29/2026
S&P - Hollow-Metal Doors and Frames - A&E Review
131
S&P - Flush Wood Doors - A&E Review
10d 12/14/2026
12/29/2026
S&P - Flush Wood Doors - A&E Review
132
S&P - Aluminum Storefronts - A&E Review
10d 12/14/2026
12/29/2026
S&P - Aluminum Storefronts - A&E Review
133
S&P - Glazing - A&E Review
10d 12/14/2026
12/29/2026
S&P - Glazing - A&E Review
134
S&P - Louvers - A&E Review
10d 12/14/2026
12/29/2026
S&P - Louvers - A&E Review
135
S&P - Hollow-Metal Doors and Frames Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Hollow-Metal Doors and Frames Procurement/Fabricate/Deliver
136
S&P - Flush Wood Doors Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Flush Wood Doors Procurement/Fabricate/Deliver
137
S&P - Aluminum Storefronts Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Aluminum Storefronts Procurement/Fabricate/Deliver
138
S&P - Glazing Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Glazing Procurement/Fabricate/Deliver
139
S&P - Louvers Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Louvers Procurement/Fabricate/Deliver
Division 09 - FINISHES
55d 11/12/2026
2/3/2027
140
S&P - Gyp Board Assemblies - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Gyp Board Assemblies - Subcontractor Submit
141
S&P - Acoustical Ceilings - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Acoustical Ceilings - Subcontractor Submit
142
S&P - Wood Athletic Flooring - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Wood Athletic Flooring - Subcontractor Submit
143
S&P - Resilient Flooring - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Resilient Flooring - Subcontractor Submit
144
S&P - Tile Carpeting - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Tile Carpeting - Subcontractor Submit
145
S&P - Exterior & Interior Painting - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Exterior & Interior Painting - Subcontractor Submit
146
S&P - Gyp Board Assemblies - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Gyp Board Assemblies - AP Review/Submit
147
S&P - Acoustical Ceilings - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Acoustical Ceilings - AP Review/Submit
148
S&P - Wood Athletic Flooring - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Wood Athletic Flooring - AP Review/Submit
149
S&P - Resilient Flooring - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Resilient Flooring - AP Review/Submit
150
S&P - Tile Carpeting - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Tile Carpeting - AP Review/Submit
151
S&P - Exterior & Interior Painting - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Exterior & Interior Painting - AP Review/Submit
152
S&P - Gyp Board Assemblies - A&E Review
10d 12/14/2026
12/29/2026
S&P - Gyp Board Assemblies - A&E Review
153
S&P - Acoustical Ceilings - A&E Review
10d 12/14/2026
12/29/2026
S&P - Acoustical Ceilings - A&E Review
154
S&P - Wood Athletic Flooring - A&E Review
10d 12/14/2026
12/29/2026
S&P - Wood Athletic Flooring - A&E Review
BVSD Eisenhower ES Master Schedule Boulder Valley School District
Job #: BVSD Eisenhower ES
Rev. date: 10/19/2026 12:02:53 PM
Data Date: 10/14/2026
Page 6 of 17
BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks
Duration
Start
Finish
2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9
Line
Name
155
S&P - Resilient Flooring - A&E Review
10d 12/14/2026
12/29/2026
S&P - Resilient Flooring - A&E Review
156
S&P - Tile Carpeting - A&E Review
10d 12/14/2026
12/29/2026
S&P - Tile Carpeting - A&E Review
157
S&P - Exterior & Interior Painting - A&E Review
10d 12/14/2026
12/29/2026
S&P - Exterior & Interior Painting - A&E Review
158
S&P - Gyp Board Assemblies Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Gyp Board Assemblies Procurement/Fabricate/Deliver
159
S&P - Acoustical Ceilings Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Acoustical Ceilings Procurement/Fabricate/Deliver
160
S&P - Wood Athletic Flooring Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Wood Athletic Flooring Procurement/Fabricate/Deliver
161
S&P - Resilient Flooring Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Resilient Flooring Procurement/Fabricate/Deliver
162
S&P - Tile Carpeting Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Tile Carpeting Procurement/Fabricate/Deliver
163
S&P - Exterior & Interior Painting Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Exterior & Interior Painting Procurement/Fabricate/Deliver
Division 10 - Specialties
55d 11/12/2026
2/3/2027
164
S&P - Visual Display Units - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Visual Display Units - Subcontractor Submit
165
S&P - Signage - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Signage - Subcontractor Submit
166
S&P - Wall and Door Protection - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Wall and Door Protection - Subcontractor Submit
167
S&P - Visual Display Units - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Visual Display Units - AP Review/Submit
168
S&P - Signage - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Signage - AP Review/Submit
169
S&P - Wall and Door Protection - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Wall and Door Protection - AP Review/Submit
170
S&P - Visual Display Units - A&E Review
10d 12/14/2026
12/29/2026
S&P - Visual Display Units - A&E Review
171
S&P - Signage - A&E Review
10d 12/14/2026
12/29/2026
S&P - Signage - A&E Review
172
S&P - Wall and Door Protection - A&E Review
10d 12/14/2026
12/29/2026
S&P - Wall and Door Protection - A&E Review
173
S&P - Visual Display Units Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Visual Display Units Procurement/Fabricate/Deliver
174
S&P - Signage Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Signage Procurement/Fabricate/Deliver
175
S&P - Wall and Door Protection Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Wall and Door Protection Procurement/Fabricate/Deliver
Division 12 - Furnishing
55d 11/12/2026
2/3/2027
176
S&P - Manufactured Wood Casework - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Manufactured Wood Casework - Subcontractor Submit
177
S&P - Manufactured Wood Casework - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Manufactured Wood Casework - AP Review/Submit
178
S&P - Manufactured Wood Casework - A&E Review
10d 12/14/2026
12/29/2026
S&P - Manufactured Wood Casework - A&E Review
179
S&P - Manufactured Wood Casework Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
Division 22 - PLUMBING
55d 11/5/2026
1/27/2027
180
S&P - Plumbing Valves - Subcontractor Submit
10d 11/5/2026
11/18/2026
S&P - Plumbing Valves - Subcontractor Submit
181
S&P - Plumbing Insulation - Subcontractor Submit
10d 11/5/2026
11/18/2026
S&P - Plumbing Insulation - Subcontractor Submit
BVSD Eisenhower ES Master Schedule Boulder Valley School District
S&P - Manufactured Wood Casework Procurement/Fabricate/Deliver
Job #: BVSD Eisenhower ES
Rev. date: 10/19/2026 12:02:53 PM
Data Date: 10/14/2026
Page 7 of 17
BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish
2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9
182
S&P - Domestic-Water Piping - Subcontractor Submit
10d 11/5/2026
11/18/2026
S&P - Domestic-Water Piping - Subcontractor Submit
183
S&P - Domestic-Water Specialties - Subcontractor Submit
10d 11/5/2026
11/18/2026
S&P - Domestic-Water Specialties - Subcontractor Submit
184
S&P - Div 22 (Div 22 - Contractor Prepare/Submit Shop Drawings)
10d 11/5/2026
11/18/2026
S&P - Div 22 (Div 22 - Contractor Prepare/Submit Shop Drawings)
185
S&P - Unit Heater (Div 22 - Contractor Prepare/Submit Shop Drawings)
10d 11/5/2026
11/18/2026
S&P - Unit Heater (Div 22 - Contractor Prepare/Submit Shop Drawings)
186
S&P - Plumbing Valves - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Plumbing Valves - AP Review/Submit
187
S&P - Plumbing Insulation - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Plumbing Insulation - AP Review/Submit
188
S&P - Domestic-Water Piping - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Domestic-Water Piping - AP Review/Submit
189
S&P - Domestic-Water Specialties - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Domestic-Water Specialties - AP Review/Submit
190
S&P - AP Review (Div 22 - AP Review/Submit Shop Drawings)
10d 11/19/2026
12/4/2026
S&P - AP Review (Div 22 - AP Review/Submit Shop Drawings)
191
S&P - AP Review (Div 22 - AP Review/Submit Shop Drawings)
10d 11/19/2026
12/4/2026
S&P - AP Review (Div 22 - AP Review/Submit Shop Drawings)
192
S&P - Plumbing Valves - A&E Review
10d 12/7/2026
12/18/2026
S&P - Plumbing Valves - A&E Review
193
S&P - Plumbing Insulation - A&E Review
10d 12/7/2026
12/18/2026
S&P - Plumbing Insulation - A&E Review
194
S&P - Domestic-Water Piping - A&E Review
10d 12/7/2026
12/18/2026
S&P - Domestic-Water Piping - A&E Review
195
S&P - Domestic-Water Specialties - A&E Review
10d 12/7/2026
12/18/2026
S&P - Domestic-Water Specialties - A&E Review
196
S&P - A&E Review (Div 22 - Owner Review/Approve Shop Drawings)
10d 12/7/2026
12/18/2026
S&P - A&E Review (Div 22 - Owner Review/Approve Shop Drawings)
197
S&P - A&E Review (Div 22 - Owner Review/Approve Shop Drawings)
10d 12/7/2026
12/18/2026
S&P - A&E Review (Div 22 - Owner Review/Approve Shop Drawings)
198
S&P - Plumbing Valves Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Plumbing Valves Procurement/Fabricate/Deliver
199
S&P - Plumbing Insulation Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Plumbing Insulation Procurement/Fabricate/Deliver
200
S&P - Domestic-Water Piping Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Domestic-Water Piping Procurement/Fabricate/Deliver
201
S&P - Domestic-Water Specialties Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Domestic-Water Specialties Procurement/Fabricate/Deliver
202
S&P - Procurement (Div 22 - Fabricate/Deliver)
25d 12/21/2026
1/27/2027
S&P - Procurement (Div 22 - Fabricate/Deliver)
203
S&P - Unit Heater Procurement (Div 22 - Fabricate/Deliver)
25d 12/21/2026
1/27/2027
S&P - Unit Heater Procurement (Div 22 - Fabricate/Deliver)
140d 11/5/2026
5/26/2027
Division 23 - HVAC 204
S&P - Motors / VFD / Starters - Subcontractor Submit
10d 11/5/2026
11/18/2026
S&P - Motors / VFD / Starters - Subcontractor Submit
205
S&P - Mechanical Piping - Subcontractor Submit
10d 11/5/2026
11/18/2026
S&P - Mechanical Piping - Subcontractor Submit
206
S&P - Piping Specialties - Subcontractor Submit
10d 11/5/2026
11/18/2026
S&P - Piping Specialties - Subcontractor Submit
207
S&P - Hangers / Supports - Subcontractor Submit
10d 11/5/2026
11/18/2026
S&P - Hangers / Supports - Subcontractor Submit
208
S&P - Metal Ducts - Subcontractor Submit
10d 11/5/2026
11/18/2026
S&P - Metal Ducts - Subcontractor Submit
209
S&P - Duct Accessories - Subcontractor Submit
10d 11/5/2026
11/18/2026
S&P - Duct Accessories - Subcontractor Submit
210
S&P - Air Terminal Units - Subcontractor Submit
10d 11/5/2026
11/18/2026
S&P - Air Terminal Units - Subcontractor Submit
BVSD Eisenhower ES Master Schedule Boulder Valley School District
Job #: BVSD Eisenhower ES
Rev. date: 10/19/2026 12:02:53 PM
Data Date: 10/14/2026
Page 8 of 17
BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish
2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9
211
S&P - Diffusers / Registers / Grilles - Subcontractor Submit
10d 11/5/2026
11/18/2026
S&P - Diffusers / Registers / Grilles - Subcontractor Submit
212
S&P - RTU - Libary & Music - Subcontractor Submit
10d 11/5/2026
11/18/2026
S&P - RTU - Libary & Music - Subcontractor Submit
213
S&P - Ductless Split Systems - Subcontractor Submit
10d 11/5/2026
11/18/2026
S&P - Ductless Split Systems - Subcontractor Submit
214
S&P - Motors / VFD / Starters - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Motors / VFD / Starters - AP Review/Submit
215
S&P - Mechanical Piping - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Mechanical Piping - AP Review/Submit
216
S&P - Piping Specialties - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Piping Specialties - AP Review/Submit
217
S&P - Hangers / Supports - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Hangers / Supports - AP Review/Submit
218
S&P - Metal Ducts - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Metal Ducts - AP Review/Submit
219
S&P - Duct Accessories - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Duct Accessories - AP Review/Submit
220
S&P - Air Terminal Units - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Air Terminal Units - AP Review/Submit
221
S&P - Diffusers / Registers / Grilles - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Diffusers / Registers / Grilles - AP Review/Submit
222
S&P - RTU - Libary & Music - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - RTU - Libary & Music - AP Review/Submit
223
S&P - Ductless Split Systems - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Ductless Split Systems - AP Review/Submit
224
S&P - Motors / VFD / Starters - A&E Review
10d 12/7/2026
12/18/2026
S&P - Motors / VFD / Starters - A&E Review
225
S&P - Mechanical Piping - A&E Review
10d 12/7/2026
12/18/2026
S&P - Mechanical Piping - A&E Review
226
S&P - Piping Specialties - A&E Review
10d 12/7/2026
12/18/2026
S&P - Piping Specialties - A&E Review
227
S&P - Hangers / Supports - A&E Review
10d 12/7/2026
12/18/2026
S&P - Hangers / Supports - A&E Review
228
S&P - Metal Ducts - A&E Review
10d 12/7/2026
12/18/2026
S&P - Metal Ducts - A&E Review
229
S&P - Duct Accessories - A&E Review
10d 12/7/2026
12/18/2026
S&P - Duct Accessories - A&E Review
230
S&P - Air Terminal Units - A&E Review
10d 12/7/2026
12/18/2026
S&P - Air Terminal Units - A&E Review
231
S&P - Diffusers / Registers / Grilles - A&E Review
10d 12/7/2026
12/18/2026
S&P - Diffusers / Registers / Grilles - A&E Review
232
S&P - RTU - Libary & Music - A&E Review
10d 12/7/2026
12/18/2026
S&P - RTU - Libary & Music - A&E Review
233
S&P - Ductless Split Systems - A&E Review
10d 12/7/2026
12/18/2026
S&P - Ductless Split Systems - A&E Review
234
S&P - Motors / VFD / Starters Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Motors / VFD / Starters Procurement/Fabricate/Deliver
235
S&P - Mechanical Piping Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Mechanical Piping Procurement/Fabricate/Deliver
236
S&P - Piping Specialties Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Piping Specialties Procurement/Fabricate/Deliver
237
S&P - Hangers / Supports Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Hangers / Supports Procurement/Fabricate/Deliver
238
S&P - Metal Ducts Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Metal Ducts Procurement/Fabricate/Deliver
239
S&P - Duct Accessories Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Duct Accessories Procurement/Fabricate/Deliver
240
S&P - Air Terminal Units Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Air Terminal Units Procurement/Fabricate/Deliver
BVSD Eisenhower ES Master Schedule Boulder Valley School District
Job #: BVSD Eisenhower ES
Rev. date: 10/19/2026 12:02:53 PM
Data Date: 10/14/2026
Page 9 of 17
BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks
Finish
2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9
25d 12/21/2026
1/27/2027
S&P - Diffusers / Registers / Grilles Procurement/Fabricate/Deliver
S&P - RTU - Libary & Music Procurement/Fabricate/Deliver
110d 12/21/2026
5/26/2027
S&P - Ductless Split Systems Procurement/Fabricate/Deliver
60d 12/21/2026
3/17/2027
Line
Name
Duration
241
S&P - Diffusers / Registers / Grilles Procurement/Fabricate/Deliver
242 243
Start
S&P - RTU - Libary & Music Procurement/Fabricate/Deliver
S&P - Ductless Split Systems Procurement/Fabricate/Deliver
Division 26 - ELECTRICAL
90d 11/5/2026
3/17/2027
244
S&P - Conductors And Cables - Subcontractor Submit
10d 11/5/2026
11/18/2026
S&P - Conductors And Cables - Subcontractor Submit
245
S&P - Raceways / Wireways - Subcontractor Submit
10d 11/5/2026
11/18/2026
S&P - Raceways / Wireways - Subcontractor Submit
246
S&P - Cabinets / Boxes / Fittings - Subcontractor Submit
10d 11/5/2026
11/18/2026
S&P - Cabinets / Boxes / Fittings - Subcontractor Submit
247
S&P - Lighting Controls - Subcontractor Submit
10d 11/5/2026
11/18/2026
S&P - Lighting Controls - Subcontractor Submit
248
S&P - Wiring Devices - Subcontractor Submit
10d 11/5/2026
11/18/2026
S&P - Wiring Devices - Subcontractor Submit
249
S&P - Circuit Protective Devices - Subcontractor Submit
10d 11/5/2026
11/18/2026
S&P - Circuit Protective Devices - Subcontractor Submit
250
S&P - Lighting - Subcontractor Submit
10d 11/5/2026
11/18/2026
S&P - Lighting - Subcontractor Submit
251
S&P - Conductors And Cables - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Conductors And Cables - AP Review/Submit
252
S&P - Raceways / Wireways - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Raceways / Wireways - AP Review/Submit
253
S&P - Cabinets / Boxes / Fittings - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Cabinets / Boxes / Fittings - AP Review/Submit
254
S&P - Lighting Controls - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Lighting Controls - AP Review/Submit
255
S&P - Wiring Devices - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Wiring Devices - AP Review/Submit
256
S&P - Circuit Protective Devices - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Circuit Protective Devices - AP Review/Submit
257
S&P - Lighting - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Lighting - AP Review/Submit
258
S&P - Conductors And Cables - A&E Review
10d 12/7/2026
12/18/2026
S&P - Conductors And Cables - A&E Review
259
S&P - Raceways / Wireways - A&E Review
10d 12/7/2026
12/18/2026
S&P - Raceways / Wireways - A&E Review
260
S&P - Cabinets / Boxes / Fittings - A&E Review
10d 12/7/2026
12/18/2026
S&P - Cabinets / Boxes / Fittings - A&E Review
261
S&P - Lighting Controls - A&E Review
10d 12/7/2026
12/18/2026
S&P - Lighting Controls - A&E Review
262
S&P - Wiring Devices - A&E Review
10d 12/7/2026
12/18/2026
S&P - Wiring Devices - A&E Review
263
S&P - Circuit Protective Devices - A&E Review
10d 12/7/2026
12/18/2026
S&P - Circuit Protective Devices - A&E Review
264
S&P - Lighting - A&E Review
10d 12/7/2026
12/18/2026
S&P - Lighting - A&E Review
265
S&P - Conductors And Cables Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Conductors And Cables Procurement/Fabricate/Deliver
266
S&P - Raceways / Wireways Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Raceways / Wireways Procurement/Fabricate/Deliver
267
S&P - Cabinets / Boxes / Fittings Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Cabinets / Boxes / Fittings Procurement/Fabricate/Deliver
268
S&P - Lighting Controls Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Lighting Controls Procurement/Fabricate/Deliver
269
S&P - Wiring Devices Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Wiring Devices Procurement/Fabricate/Deliver
BVSD Eisenhower ES Master Schedule Boulder Valley School District
Job #: BVSD Eisenhower ES
Rev. date: 10/19/2026 12:02:53 PM
Data Date: 10/14/2026
Page 10 of 17
BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish
2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9 S&P - Circuit Protective Devices Procurement/Fabricate/Deliver
270
S&P - Circuit Protective Devices Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
271
S&P - Lighting Procurement/Fabricate/Deliver
60d 12/21/2026
3/17/2027
Division 27 - COMMUNICATION
55d 11/12/2026
2/3/2027
272
S&P - Communications Common Work - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Communications Common Work - Subcontractor Submit
273
S&P - Communications Pathways - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Communications Pathways - Subcontractor Submit
274
S&P - Communications Common Work - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Communications Common Work - AP Review/Submit
275
S&P - Communications Pathways - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Communications Pathways - AP Review/Submit
276
S&P - Communications Common Work - A&E Review
10d 12/14/2026
12/29/2026
S&P - Communications Common Work - A&E Review
277
S&P - Communications Pathways - A&E Review
10d 12/14/2026
12/29/2026
S&P - Communications Pathways - A&E Review
278
S&P - Communications Common Work Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Communications Common Work Procurement/Fabricate/Deliver
279
S&P - Communications Pathways Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Communications Pathways Procurement/Fabricate/Deliver
Division 28 - FA SECURITY
55d 2/11/2027
4/28/2027
280
S&P - Fire Detection and Alarm - Subcontractor Submit
10d 2/11/2027
2/24/2027
S&P - Fire Detection and Alarm - Subcontractor Submit
281
S&P - Fire Detection and Alarm - AP Review/Submit
10d 2/25/2027
3/10/2027
S&P - Fire Detection and Alarm - AP Review/Submit
282
S&P - Fire Detection and Alarm - A&E Review
10d 3/11/2027
3/24/2027
S&P - Fire Detection and Alarm - A&E Review
283
S&P - Fire Detection and Alarm Procurement/Fabricate/Deliver
25d 3/25/2027
4/28/2027
Division 32 - EXTERIOR IMPROVEMENTS
55d 11/12/2026
2/3/2027
284
S&P - Concrete Paving - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Concrete Paving - Subcontractor Submit
285
S&P - Concrete Paving - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Concrete Paving - AP Review/Submit
286
S&P - Concrete Paving - A&E Review
10d 12/14/2026
12/29/2026
S&P - Concrete Paving - A&E Review
287
S&P - Concrete Paving Procurement/Fabricate/Deliver
25d 12/30/2026
2/3/2027
S&P - Lighting Procurement/Fabricate/Deliver
S&P - Fire Detection and Alarm Procurement/Fabricate/Deliver
S&P - Concrete Paving Procurement/Fabricate/Deliver
Construction
471d 10/21/2025 8/31/2027
Site Mobilization
49d 3/15/2027
5/20/2027
288
Mobilization Start (Week Prior) Spring Break
1d 3/15/2027
3/15/2027
Mobilization Start (Week Prior) Spring Break
289
Mobilization Complete
5d 3/16/2027
3/22/2027
Mobilization Complete
290
Mobilization Start (Summer)
1d 5/20/2027
5/20/2027
Abatement (If NEEDED)
50d 3/16/2027
5/24/2027
291
Abate - Review Impacts
30d 3/16/2027
4/26/2027
292
Abate - Identify Scope
10d 4/27/2027
5/10/2027
293
Abate - Demo / Remove / Inspections / Tear Down
10d 5/11/2027
5/24/2027
BVSD Eisenhower ES Master Schedule Boulder Valley School District
Mobilization Start (Summer)
Abate - Review Impacts
Abate - Identify Scope
Abate - Demo / Remove / Inspections / Tear Down
Job #: BVSD Eisenhower ES
Rev. date: 10/19/2026 12:02:53 PM
Data Date: 10/14/2026
Page 11 of 17
BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish
Demolition
161d 10/29/2026 6/18/2027
North Building - Kindergarden - 1X2
149d 10/29/2026
6/2/2027
2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9
294
Demo - North - Review Impacts
5d 3/16/2027
3/22/2027
295
Demo - North - Exterior Replacement Metal Doors & Frame (205,206,159,170A,182)
3d 5/20/2027
5/24/2027
Demo - North - Exterior Replacement Metal Doors & Frame (205,206,159,170A,182)
296
Demo - North - Safe Off Electrical & Mechanical
2d 5/21/2027
5/24/2027
Demo - North - Safe Off Electrical & Mechanical
297
Demo - North - Demo / Remove - Existing Flooring, Casework, Interior Walls & Doors, Markerboards, Projection Screen, Projector, Decor. Wall Covering, Lighting Fixtures
5d 5/21/2027
5/27/2027
Demo - North - Demo / Remove - Existing Flooring, Casework, Interior Walls & Doors, Markerboards, Projection Screen, Projector, Decor. Wall Covering, Lighting Fixtures
298
Demo - Ceiling Grid (Kindergarten, Flex Learning, Corridor 210)
2d 5/21/2027
5/24/2027
Demo - Ceiling Grid (Kindergarten, Flex Learning, Corridor 210)
299
Demo - North - Ceiling Grid (Music, Storage)
2d 5/21/2027
5/24/2027
Demo - North - Ceiling Grid (Music, Storage)
300
Demo - North - Ceiling Grid (Selective, Corridor 188)
2d 5/21/2027
5/24/2027
Demo - North - Ceiling Grid (Selective, Corridor 188)
301
Demo - North - (V14) Light fixtures
8d 5/21/2027
6/2/2027
Demo Alternate - Fire Alarm
10d 3/22/2027
4/2/2027
Demo - North - Alternate - Existing Fire Alarm
10d 3/22/2027
4/2/2027
Demo Alternate - Gym Flooring (ACCEPTED)
4d 10/29/2026 11/3/2026
Demo - North - Alternate - Existing Gym Flooring
4d 10/29/2026
11/3/2026
South Building - Kindergarden - 1X1
51d 3/23/2027
6/2/2027
304
Demo - South - Review Impacts
5d 3/23/2027
3/29/2027
305
Demo - South - Elec. RM - Existing Ladder / Casework
1d 5/21/2027
5/21/2027
306
Demo - South - (V14) Light fixtures
8d 5/21/2027
6/2/2027
Demo - South - (V14) Light fixtures
307
Demo - South - Exterior Replacement Metal Doors & Frame (193,194,149,146,148,138)
3d 5/25/2027
5/27/2027
Demo - South - Exterior Replacement Metal Doors & Frame (193,194,149,146,148,138)
308
Demo - South - MDF - Existing Mini-Split
2d 5/28/2027
6/1/2027
Demo - South - MDF - Existing Mini-Split
Demo Alternate - Fire Alarm
10d
4/5/2027
4/16/2027
Demo - South - Alternate - Existing Fire Alarm
10d
4/5/2027
4/16/2027
East Building - Kindergarden - 1X3
58d 3/30/2027
6/18/2027
310
Demo - East - Review Impacts
5d 3/30/2027
4/5/2027
311
Demo - East - (V14) Light fixtures
8d 5/21/2027
6/2/2027
Demo - East - (V14) Light fixtures
312
Demo - East - Exterior Replacement Metal Doors & Frame (205,206,159)
5d 5/28/2027
6/4/2027
Demo - East - Exterior Replacement Metal Doors & Frame (205,206,159)
313
Demo - East - Demo / Remove - Summer
10d
6/7/2027
6/18/2027
Demo Alternate - Fire Alarm
10d 4/19/2027
4/30/2027
Demo - East - Alternate - Existing Fire Alarm
10d 4/19/2027
4/30/2027
302
303
309
314
Early Site Development
Demo - North - Review Impacts
Demo - North - (V14) Light fixtures
Demo - North - Alternate - Existing Fire Alarm
Demo - North - Alternate - Existing Gym Flooring
Demo - South - Review Impacts
Demo - South - Elec. RM - Existing Ladder / Casework
Demo - South - Alternate - Existing Fire Alarm
Demo - East - Review Impacts
Demo - East - Demo / Remove - Summer
Demo - East - Alternate - Existing Fire Alarm
406d 10/21/2025 5/28/2027
BVSD Eisenhower ES Master Schedule Boulder Valley School District
Job #: BVSD Eisenhower ES
Rev. date: 10/19/2026 12:02:53 PM
Data Date: 10/14/2026
Page 12 of 17
BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish
2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9
247d 10/21/2025 A
5/28/2027
ES - Setup Compound (Construction Fence/Connexs/Dumpster/ETC
1d 3/16/2027
3/16/2027
Utilities (IF NEEDED)
30d
6/1/2027
7/13/2027
317
Util - Review Impacts
15d
6/1/2027
6/21/2027
318
Util - Identify Scope
15d 6/22/2027
7/13/2027
Building Construction
87d 4/29/2027
8/31/2027
Exterior of Building
41d 5/25/2027
7/22/2027
North Building - Kindergarden - 1X2
11d 5/25/2027
6/9/2027
319
EX - Install Exterior Replacement Metal Doors & Frame (205,206,159)
10d 5/25/2027
6/8/2027
320
EX - Pre-Punch
3d 5/25/2027
5/27/2027
EX - Pre-Punch
321
EX - Owner Punch
3d 5/28/2027
6/2/2027
EX - Owner Punch
322
EX - Punch Corrections
5d
6/3/2027
6/9/2027
EX - Punch Corrections
South Building - Kindergarden - 1X1
26d
6/9/2027
7/15/2027
323
EX - Install Exterior Replacement Metal Doors & Frame (193,194,149,146,148,138)
15d
6/9/2027
6/29/2027
EX - Install Exterior Replacement Metal Doors & Frame (193,194,149,146,148,138)
324
EX - Pre-Punch
3d 6/30/2027
7/2/2027
EX - Pre-Punch
325
EX - Owner Punch
3d
7/6/2027
7/8/2027
EX - Owner Punch
326
EX - Punch Corrections
5d
7/9/2027
7/15/2027
EX - Punch Corrections
East Building - Kindergarden - 1X3
16d 6/30/2027
7/22/2027
327
EX - Install Exterior Replacement Metal Doors & Frame (182)
5d 6/30/2027
7/7/2027
EX - Install Exterior Replacement Metal Doors & Frame (182)
328
EX - AP Pre-Punch
3d
7/8/2027
7/12/2027
EX - AP Pre-Punch
329
EX - Owner Punch
3d 7/13/2027
7/15/2027
EX - Owner Punch
330
EX - Punch Corrections
5d 7/16/2027
7/22/2027
EX - Punch Corrections
Roofing
40d 5/21/2027
7/19/2027
331
Roof - Demo - Ladder
2d 5/21/2027
5/24/2027
Roof - Demo - Ladder
332
Roof - Install - Ladder
2d 5/25/2027
5/26/2027
Roof - Install - Ladder
333
Roof - Demo - Roofing
10d 5/28/2027
6/11/2027
334
Roof - Install (2000 SQFT)
10d 6/14/2027
6/25/2027
335
Roof - Demo - RTU
2d 6/14/2027
6/15/2027
Roof - Demo - RTU
336
Roof - Install - RTU
2d 6/16/2027
6/17/2027
Roof - Install - RTU
337
Roof - Pre-Punch
5d 6/28/2027
7/2/2027
Roof - Pre-Punch
315
ES - Investigations
316
BVSD Eisenhower ES Master Schedule Boulder Valley School District
ES - Investigations
ES - Setup Compound (Construction Fence/Connexs/Dumpster/ETC
Util - Review Impacts
Util - Identify Scope
EX - Install Exterior Replacement Metal Doors & Frame (205,206,159)
Roof - Demo - Roofing
Roof - Install (2000 SQFT)
Job #: BVSD Eisenhower ES
Rev. date: 10/19/2026 12:02:53 PM
Data Date: 10/14/2026
Page 13 of 17
BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish
2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9
338
Roof - Owner Walk
5d
7/6/2027
7/12/2027
Roof - Owner Walk
339
Roof - Punch Corrections
5d 7/13/2027
7/19/2027
Roof - Punch Corrections
Interiors / Mechanical / Electrical / Plumbing / Fire Alarm
87d 4/29/2027
8/31/2027
North Building - Kindergarden - 1X2.North Buildling
62d 4/29/2027
7/27/2027
Interior Rough In (Nights & Days)
38d 4/29/2027
6/22/2027
340
IF-RI - North - Electrical - Interior Rough In Activities
20d 5/25/2027
6/22/2027
IF-RI - North - Electrical - Interior Rough In Activities
341
IF-RI - North - Mechanical - Interior Rough In Activities
20d 5/25/2027
6/22/2027
IF-RI - North - Mechanical - Interior Rough In Activities
342
IF-RI - North - Fire Alarm Rough In Activities - Summer
3d 5/25/2027
5/27/2027
343
IF-RI - North - Framing
5d 5/28/2027
6/4/2027
344
IF-RI - North - Electrical Rough In Activities - IN Wall
15d 5/28/2027
6/18/2027
345
IF-RI - North - Technology Rough In
3d 5/28/2027
6/2/2027
IF-RI - North - Technology Rough In
346
IF-RI - North - Blocking Rough In Activities - For Cabinets, Markerboards, TV/Display, Bathroom Accessories, ETC
3d
6/3/2027
6/7/2027
IF-RI - North - Blocking Rough In Activities - For Cabinets, Markerboards, TV/Display, Bathroom Accessories, ETC
347
IF-RI - North - (V14) Light Fixtures Priorities 1-4 Rough In
5d
6/3/2027
6/9/2027
IF-RI - North - (V14) Light Fixtures Priorities 1-4 Rough In
Alternate - Fire Alarm (ACCEPTED)
10d 4/29/2027
5/12/2027
IF-RI - North - Fire Alarm Rough In Activities - Spring Break
10d 4/29/2027
5/12/2027
348
IF-RI - North - Fire Alarm Rough In Activities - Summer
IF-RI - North - Framing
IF-RI - North - Electrical Rough In Activities - IN Wall
IF-RI - North - Fire Alarm Rough In Activities - Spring Break
Interior Finishes
38d
6/3/2027
7/27/2027
349
IF-FIN - North - (V14) Light Fixtures Install
20d
6/3/2027
6/30/2027
350
IF-FIN - North - Drywall Tape Finish
7d
6/8/2027
6/16/2027
IF-FIN - North - Drywall Tape Finish
351
IF-FIN - North - Repair and Paint
5d 6/17/2027
6/23/2027
IF-FIN - North - Repair and Paint
352
IF-FIN - North - ACT Install
5d 6/21/2027
6/25/2027
IF-FIN - North - ACT Install
353
IF-FIN - North - Mechanical GRD's
5d 6/28/2027
7/2/2027
IF-FIN - North - Mechanical GRD's
354
IF-FIN - North - Casework Install
3d 6/30/2027
7/2/2027
IF-FIN - North - Casework Install
355
IF-RI - North - Electrical Trim
7d
7/1/2027
7/12/2027
IF-RI - North - Electrical Trim
356
IF-FIN - North - Pre-Punch
5d
7/6/2027
7/12/2027
IF-FIN - North - Pre-Punch
357
IF-FIN - North - Owner Walk
1d 7/13/2027
7/13/2027
IF-FIN - North - Owner Walk
358
IF-FIN - North - Punch Corrections
10d 7/14/2027
7/27/2027
Alternate - Gym Floor Mitgation (ACCEPTED)
20d 5/20/2027
6/17/2027
ALT - Gym Floor Mitgation
20d 5/20/2027
6/17/2027
South Buidling - Kindergarden - 1X1.South Building
77d 5/13/2027
8/31/2027
Interior Rough In (Nights & Days)
39d 5/13/2027
7/8/2027
359
BVSD Eisenhower ES Master Schedule Boulder Valley School District
IF-FIN - North - (V14) Light Fixtures Install
IF-FIN - North - Punch Corrections
ALT - Gym Floor Mitgation
Job #: BVSD Eisenhower ES
Rev. date: 10/19/2026 12:02:53 PM
Data Date: 10/14/2026
Page 14 of 17
BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish
2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9
360
IF-RI - South - Interior Rough In Activities
33d 5/21/2027
7/8/2027
361
IF-RI - South - Mini-Split Rough In Activities (Nights)
5d
6/2/2027
6/8/2027
IF-RI - South - Mini-Split Rough In Activities (Nights)
362
IF-RI - South - (V14) Light Fixtures Priorities 1-4 Rough In
5d
6/3/2027
6/9/2027
IF-RI - South - (V14) Light Fixtures Priorities 1-4 Rough In
Alternate - fire Alarm
10d 5/13/2027
5/26/2027
IF-RI - South - Fire Alarm Rough In Activities - Spring Break
10d 5/13/2027
5/26/2027
Interior Finishes
58d 6/10/2027
8/31/2027
364
IF-FIN - South - (V14) Light Fixtures Install
20d 6/10/2027
7/8/2027
IF-FIN - South - (V14) Light Fixtures Install
365
IF-FIN - South - Repair and Paint
20d 7/20/2027
8/16/2027
IF-FIN - South - Repair and Paint
366
IF-FIN - South - Pre-Punch
5d 8/10/2027
8/16/2027
IF-FIN - South - Pre-Punch
367
IF-FIN - South - Owner Walk
1d 8/17/2027
8/17/2027
IF-FIN - South - Owner Walk
368
IF-FIN - South - Punch Corrections
10d 8/18/2027
8/31/2027
East Building - Kindergarden - 1X3
58d 5/21/2027
8/12/2027
Interior Rough In (Nights & Days)
30d 5/21/2027
7/2/2027
369
IF-RI - East - Interior Rough In Activities (Nights)
30d 5/21/2027
7/2/2027
IF-RI - East - Interior Rough In Activities (Nights)
370
IF-RI - East - (V14) Light Fixtures Priorities 1-4 Rough In
5d
6/3/2027
6/9/2027
IF-RI - East - (V14) Light Fixtures Priorities 1-4 Rough In
Alternate - fire Alarm
10d 5/27/2027
6/10/2027
IF-RI - East - Fire Alarm Rough In Activities - Spring Break
10d 5/27/2027
6/10/2027
Interior Finishes
45d 6/10/2027
8/12/2027
372
IF-FIN - East - (V14) Light Fixtures Install
20d 6/10/2027
7/8/2027
IF-FIN - East - (V14) Light Fixtures Install
373
IF-FIN - East - Repair and Paint
10d
7/8/2027
7/21/2027
IF-FIN - East - Repair and Paint
374
IF-FIN - East - Pre-Punch
5d 7/22/2027
7/28/2027
IF-FIN - East - Pre-Punch
375
IF-FIN - East - Owner Walk
1d 7/29/2027
7/29/2027
IF-FIN - East - Owner Walk
376
IF-FIN - East - Punch Corrections
10d 7/30/2027
8/12/2027
Sitework
44d
6/1/2027
8/2/2027
Parking Lot Repairs
44d
6/1/2027
8/2/2027
377
FS - Identify Scope (Site Investigation & Layout)
5d
6/1/2027
6/7/2027
378
FS - Demo - Selected Potholes
10d
6/8/2027
6/21/2027
379
FS - Repair Selected Potholes
10d 6/22/2027
7/6/2027
FS - Repair Selected Potholes
380
FS - Pre-Punch
2d
7/7/2027
7/8/2027
FS - Pre-Punch
381
FS - Punch
2d
7/9/2027
7/12/2027
FS - Punch
363
371
BVSD Eisenhower ES Master Schedule Boulder Valley School District
IF-RI - South - Interior Rough In Activities
IF-RI - South - Fire Alarm Rough In Activities - Spring Break
IF-FIN - South - Punch Corrections
IF-RI - East - Fire Alarm Rough In Activities - Spring Break
IF-FIN - East - Punch Corrections
FS - Identify Scope (Site Investigation & Layout)
FS - Demo - Selected Potholes
Job #: BVSD Eisenhower ES
Rev. date: 10/19/2026 12:02:53 PM
Data Date: 10/14/2026
Page 15 of 17
BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish
2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9
FS - Punch Corrections
10d 7/20/2027
8/2/2027
Pedestrian Pavement - Concrete Repairs
44d
6/1/2027
8/2/2027
383
FS - Identify Scope (Site Investigation & Layout)
5d
6/1/2027
6/7/2027
384
FS - Demo - Selected Sidewalks
10d
6/8/2027
6/21/2027
385
FS - Repair Selected Sidewalks
15d 6/22/2027
7/13/2027
FS - Repair Selected Sidewalks
386
FS - Pre-Punch
2d 7/14/2027
7/15/2027
FS - Pre-Punch
387
FS - Punch
2d 7/16/2027
7/19/2027
FS - Punch
388
FS - Punch Corrections
10d 7/20/2027
8/2/2027
Final Inspections & Closeout
84d 6/11/2027
10/8/2027
MEP Startup & Commissioning
15d 6/28/2027
7/19/2027
Startup / Test & Balance
13d 6/28/2027
7/15/2027
389
Startup/TAB - Startup / Test & Balance Tasks
12d 6/28/2027
7/14/2027
Startup/TAB - Startup / Test & Balance Tasks
390
North - (V14) Lighting Controls, Programming, Testing
5d
7/1/2027
7/8/2027
North - (V14) Lighting Controls, Programming, Testing
391
South - (V14) Lighting Controls, Programming, Testing
5d
7/9/2027
7/15/2027
South - (V14) Lighting Controls, Programming, Testing
392
East - (V14) Lighting Controls, Programming, Testing
5d
7/9/2027
7/15/2027
East - (V14) Lighting Controls, Programming, Testing
Commissioning
15d 6/28/2027
7/19/2027
CX - Commissioning Tasks
15d 6/28/2027
7/19/2027
Final Project Punchlist
20d 8/10/2027
9/7/2027
394
Punch - Pre-Punch - Final
5d 8/10/2027
8/16/2027
Punch - Pre-Punch - Final
395
Punch - Owner Walk -Final
5d 8/17/2027
8/23/2027
Punch - Owner Walk -Final
396
Punch - Punch Corrections - Final
10d 8/24/2027
9/7/2027
Final Inspections / TCO
35d 6/11/2027
7/30/2027
Final Inspections
35d 6/11/2027
7/30/2027
397
FInsp - Final Fire Alarm Inspection - Fire Department
5d 6/11/2027
6/17/2027
FInsp - Final Fire Alarm Inspection - Fire Department
398
FInsp - Final Plumbing Inspection - State
10d 6/28/2027
7/12/2027
FInsp - Final Plumbing Inspection - State
399
FInsp - Final AHJ Inspections (Mechanical, Framing)
3d
7/6/2027
7/8/2027
FInsp - Final AHJ Inspections (Mechanical, Framing)
400
FInsp - Final Electrical Inspection - State
5d 7/16/2027
7/22/2027
FInsp - Final Electrical Inspection - State
401
FInsp - Final Building Inspection - DFPC
2d 7/23/2027
7/26/2027
FInsp - Final Building Inspection - DFPC
402
Substantial Completion - TCO
4d 7/27/2027
7/30/2027
Substantial Completion - TCO
Owner Move In Activities
73d 6/28/2027
10/8/2027
382
393
BVSD Eisenhower ES Master Schedule Boulder Valley School District
FS - Punch Corrections
FS - Identify Scope (Site Investigation & Layout)
FS - Demo - Selected Sidewalks
FS - Punch Corrections
CX - Commissioning Tasks
Punch - Punch Corrections - Final
Job #: BVSD Eisenhower ES
Rev. date: 10/19/2026 12:02:53 PM
Data Date: 10/14/2026
Page 16 of 17
BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish
Move - Owner Move In Activities
10d 7/27/2027
8/9/2027
Closeout / CO
73d 6/28/2027
10/8/2027
404
Closeout - Start
1d 6/28/2027
6/28/2027
405
Closeout - Owner Training
20d 6/29/2027
7/27/2027
406
Closeout - Final Completion
23d
9/8/2027
10/8/2027
403
2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9
BVSD Eisenhower ES Master Schedule Boulder Valley School District
Move - Owner Move In Activities
Closeout - Start
Closeout - Owner Training
Closeout - Final Completion
Job #: BVSD Eisenhower ES
Rev. date: 10/19/2026 12:02:53 PM
Data Date: 10/14/2026
Page 17 of 17
BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks
Exhibit E Insurance Insurance Certificates to be provided after Certificates amendment & change order for the GMP is executed
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit F Performance Bond to be provided after amendment & change order for the GMP is executed
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit G Labor and Materials Payment Bond to be provided after amendment & change order for the GMP is executed
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit H Alternates prices Alternates prices not used for the amendment
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Allowances Report DESCRIPTION
QTY UOM
UNIT PRICE
1.00 allow
4,000.00
TOTAL COST
NOTES / COMMENTS
04 Masonry 04 20 00 Unit Masonry 04190 Masonry Patch and Repair Allowance
$4,000
Subtotal 04 20 00 Unit Masonry
$4,000
Allowance
$4,000 $4,000
Subtotal 04 Masonry 09 Finishes 09 24 00 Cement Plastering 09205 Patch exterior stucco at new window
$1,200 1.00 allow
1,200.00
Subtotal 09 24 00 Cement Plastering
$1,200
Allowance
$1,200 $1,200
Subtotal 09 Finishes 23 Heating, Ventilating and Air Conditioning 23 00 00 Heating, Ventilating and Air Conditioning 23037 3rd Party Design for Wind Subtotal 23 00 00 Heating, Ventilating and Air Conditioning Subtotal 23 Heating, Ventilating and Air Conditioning
DATE PRINTED: 10/6/2026
$15,000 1.00 allow
15,000.00
$15,000 $15,000 $15,000
Allowance
Exhibit I prices Unit prices not Unit used for this amendment
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit J Allowances
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Allowances Report DESCRIPTION
QTY UOM
UNIT PRICE
1.00 allow
4,000.00
TOTAL COST
NOTES / COMMENTS
04 Masonry 04 20 00 Unit Masonry 04190 Masonry Patch and Repair Allowance
$4,000
Subtotal 04 20 00 Unit Masonry
$4,000
Allowance
$4,000 $4,000
Subtotal 04 Masonry 09 Finishes 09 24 00 Cement Plastering 09205 Patch exterior stucco at new window
$1,200 1.00 allow
1,200.00
Subtotal 09 24 00 Cement Plastering
$1,200
Allowance
$1,200 $1,200
Subtotal 09 Finishes 23 Heating, Ventilating and Air Conditioning 23 00 00 Heating, Ventilating and Air Conditioning 23037 3rd Party Design for Wind Subtotal 23 00 00 Heating, Ventilating and Air Conditioning Subtotal 23 Heating, Ventilating and Air Conditioning
DATE PRINTED: 10/6/2026
$15,000 1.00 allow
15,000.00
$15,000 $15,000 $15,000
Allowance
Exhibit K Not Applicable
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit L Equipment rental rate schedule
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit M General Conditions of the Contract
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
BOULDER VALLEY SCHOOL DISTRICT RE-2 BOULDER, COLORADO
GENERAL CONTRACT CONDITIONS BOND PROGRAM
GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT.................................................................................................... 2 GC 1.00
CONTRACT DOCUMENTS AND DEFINITIONS ............................................................................................................ 1
GC 2.00
REFERENCE STANDARDS .......................................................................................................................................... 2
GC 3.00
DRAWINGS AND SPECIFICATIONS ............................................................................................................................ 2
GC 4.00
ROYALTIES AND PATENTS ........................................................................................................................................ 3
GC 5.00
ITEMS COVERED BY CONTRACT PRICE ..................................................................................................................... 3
GC 6.00
EXECUTION, CORRELATION, INTENT, AND INTERPRETATION OF CONTRACT DOCUMENTS ...................................... 3
GC 7.00
MATERIALS, LABOR, FACILITIES, AND STORAGE....................................................................................................... 4
GC 8.00
PERFORMANCE AND PAYMENT BONDS ................................................................................................................... 5
GC 9.00
PERMITS AND COMPLIANCE WITH STATUTES, RULES, AND REGULATIONS .............................................................. 6
GC 10.00
SURVEYS, BENCHMARKS, MONUMENTS, STAKES, AND MEASUREMENTS ............................................................... 6
GC 11.00
CHANGED CONDITIONS ........................................................................................................................................... 7
GC 12.00
PROTECTION OF PERSONS, WORK AND PROPERTY ................................................................................................. 7
GC 13.00
WORK ON EXISTING BUILDINGS .............................................................................................................................. 8
GC 14.00
CONTRACTOR’S SUPERINTENDENCE AND SUPERVISION .......................................................................................... 8
GC 15.00
SUBSTITUTIONS ....................................................................................................................................................... 9
GC 16.00
SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES ................................................................................................. 9
GC 17.00
CASH ALLOWANCE................................................................................................................................................. 10
GC 18.00
EXPEDITING MATERIALS ........................................................................................................................................ 10
GC 19.00
BLASTING .............................................................................................................................................................. 11
GC 20.00
SOIL TEST REPORT ................................................................................................................................................. 11
GC 21.00
HAZARDOUS MATERIALS ....................................................................................................................................... 11
GC 22.00
DAMAGE TO UTILITIES ........................................................................................................................................... 11
GC 23.00
CHANGES IN THE WORK ........................................................................................................................................ 12
GC 24.00
CLAIMS FOR EXTRA COST....................................................................................................................................... 13
GC 25.00
DELAYS AND EXTENSIONS OF TIME ....................................................................................................................... 13
GC 26.00
ACCESS TO WORK .................................................................................................................................................. 14
GC 27.00
CORRECTION OF WORK ......................................................................................................................................... 14
GC 28.00
OWNER’S RIGHT TO CARRY OUT WORK ................................................................................................................. 16
GC 29.00
OWNER’S RIGHT TO TERMINATE CONTRACT ......................................................................................................... 16
GC 30.00
CONSTRUCTION SCHEDULE AND PROGRESS REPORTS ........................................................................................... 16
GC 31.00
SCHEDULE OF VALUES ........................................................................................................................................... 17
GC 32.00
PAYMENT .............................................................................................................................................................. 17
GC 33.00
INSURANCE ........................................................................................................................................................... 19
GC 34.00
SEPARATE CONTRACTS .......................................................................................................................................... 23
GC 35.00
SUBCONTRACTORS ................................................................................................................................................ 23
GC 36.00
RELATIONS OF CONTRACTOR AND SUBCONTRACTOR ........................................................................................... 24
GC 37.00
CONTRACTORS’ MUTUAL RESPONSIBILITY ............................................................................................................ 25
GC 38.00
CUTTING, PATCHING, AND EXCAVATING ............................................................................................................... 25
GC 39.00
EMPLOYEES ........................................................................................................................................................... 26
GC 40.00
CLEANING UP......................................................................................................................................................... 27
GC 41.00
USE OF PREMISES .................................................................................................................................................. 27
GC 42.00
OCCUPANCY .......................................................................................................................................................... 27
GC 43.00
TEMPORARY OR TRIAL USAGE ............................................................................................................................... 28
GC 44.00
TESTING OF BUILDING SYSTEMS ............................................................................................................................ 28
GC 45.00
LIQUIDATED DAMAGES FOR DELAY IN COMPLETION ............................................................................................. 28
GC 46.00
ACCEPTANCE AND FINAL PAYMENT ....................................................................................................................... 28
GC 47.00
WARRANTIES ON PORTIONS OF THE WORK .......................................................................................................... 29
GC 48.00
CONTRACTOR’S PROJECT GUARANTEE AFTER COMPLETION ................................................................................. 30
GC 49.00
MISCELLANEOUS KEYS, SWITCHES, ETC. ................................................................................................................ 30
GC 50.00
INDEMNIFICATION ................................................................................................................................................ 30
GC 51.00
LABOR DISPUTES ................................................................................................................................................... 31
GC 52.00
LIMITATION OF ACTIONS ....................................................................................................................................... 31
GC 53.00
PREFERENCE FOR COLORADO LABOR, MATERIALS, AND RESIDENT BIDDERS ........................................................ 31
GC 54.00
SALES AND USE TAX............................................................................................................................................... 31
GC 55.00
LIENS ..................................................................................................................................................................... 32
GC 56.00
OWNER’S INSPECTION OF CONTRACTOR’S RECORDS ............................................................................................ 32
GC 57.00
CERTIFICATION BY CONTRACTOR REGARDING PREMISES ACCESS ......................................................................... 32
GC 58.00
CONTRACTOR SAFETY RESPONSIBILITIES ............................................................................................................... 32
GC 59.00
CONTRACTOR ASBESTOS MANAGEMENT AND LEAD PAINT RESPONSIBILITIES ...................................................... 35
GC 60.00
ARCHITECT’S STATUS AND INSPECTIONS ............................................................................................................... 35
GC 61.00
ORAL STATEMENTS................................................................................................................................................ 35
GC 62.00
PROJECT SIGN ........................................................................................................................................................ 36
GC 63.00
HISTORICAL DATA .................................................................................................................................................. 36
GC 64.00
ASSIGNMENT ......................................................................................................................................................... 36
GC 65.00
TIME OF THE ESSENCE ........................................................................................................................................... 36
GC 66.00
DISPUTES ............................................................................................................................................................... 36
GC 67.00
SURVIVAL .............................................................................................................................................................. 36
GC 1.00
CONTRACT DOCUMENTS AND DEFINITIONS
All Work under the Construction Agreement shall be accomplished in accordance with the Contract Documents, which shall consist of the Request for Qualifications, Request for Proposals, Proposal(s), Notice of Award, Notice to Proceed, Performance Bond, Labor and Material Payment Bond, Construction Agreement, General Contract Conditions, Supplementary Conditions, Asbestos Management Plan Contractor Responsibility Form, Drawings and Specifications, tests and engineering data, approved Change Orders, Contractor’s Requests for Payment, Architect’s Certificates, and all addenda issued by the Owner or Architect prior to execution of the Construction Agreement and all modifications issued by the Owner or Architect after execution of the Construction Agreement. With respect to the Contract Documents, the following definitions and understandings shall control: 1.01 “Contract” or “Contract Documents” shall include all of the items enumerated in GC-1.00 above. 1.02 “Owner” shall mean Boulder Valley School District No. RE-2, and shall include its duly authorized representatives. 1.03 “Contractor” shall mean the corporation, company, partnership, firm, entity, or individual named and designated as such in the Construction Agreement, and any persons or entities acting on its behalf. 1.04 “Subcontractor” shall mean any corporation, partnership, entity, or individual having a direct contract with the Contractor or another subcontractor for performing Work and/or furnishing labor or material on the Project covered by the Contract. 1.05 “Architect” shall mean the corporation, partnership, entity or individual named and designated as “architect” or “engineer” in the Construction Agreement, and any persons or entities acting on the Architect’s behalf and within the scope of the particular duties properly entrusted to them in each case. In the event that there is no Architect on the Project, then “Architect” shall refer to Owner and its duly authorized representative. 1.06 “Notice to Contractor” shall be deemed to have been duly served if made in writing and delivered in person to the individual or to a member of the firm or to an officer of the corporation for which it is intended, or if sent by registered or certified mail, to Contractor’s last known business address. 1.07 “The Work” shall mean the construction and services required by the Contract Documents for completion of the Project, and includes all labor, materials, equipment and services provided or to be provided by the Contractor to fulfill the Contractor’s obligations, whether on or off the Project site, and all labor, materials equipment and services provided or to be provided by subcontractors, sub-subcontractors, or any other entity for whom the Contractor is responsible. 1.08 “The Project” is the total construction designed by the Architect of which the Work performed under the Contract Documents may be the whole or a part. 1.09 The “date of final completion” and “finally completed” shall mean the date when construction is certified by the Architect to be finally completed in accordance with the Contract Documents, as modified by any Change Orders processed under the terms of GC-23.00 below and when the Owner has fully accepted the Project for the use for which it was intended. Such date will be set forth on a letter of acceptance issued by the Owner. 1.010 “Drawings” or “plans” shall mean all (a) drawings furnished by the Owner and/or Architect as a basis for the award of Contract and for construction of the Project; (b) supplementary drawings furnished by the Owner and/or Architect to clarify and to define in greater detail the intent of the Contract drawings and specifications; (c) drawings submitted by the successful Contractor as may be required after the Contract is awarded; (d) drawings furnished by the Owner and/or Architect to the Contractor during the progress of the Work; and (e) engineering data and drawings submitted by the Contractor during the progress of the Work, provided such drawings are acceptable to the Architect and Owner. 1
1.011 “Specifications” are the written technical information concerning materials, components, systems, equipment, and manner of installation as indicated on the drawings or plans and which state the quality, performance, and characteristics to be achieved by application of construction methods. 1.012 “Change Order” shall mean a written order to the Contractor signed by the Owner or its authorized agent issued after the execution of the Construction Agreement, authorizing a change in the Work and/or adjustment in the Guaranteed Maximum Price (“GMP”) or the contract time schedule. Each adjustment in the GMP resulting from a Change Order shall clearly separate the amount attributable to the Cost of the Work and the Contractor’s Fee. 1.013 “day” or “days” shall mean calendar days. In computing a period of days, when the ending date is not specified, the first day is excluded and the last day is included. If any deadline falls on a Saturday, Sunday, or federal or Colorado state holiday, such deadline will be extended to the next day that is not a Saturday, Sunday or federal or Colorado state holiday. GC 2.00
REFERENCE STANDARDS
2.01 Reference to the standards of any technical society, organization, or association, or to codes of local or state authorities, shall mean the latest standard, code, specification, or tentative standard adopted and published as of the date of execution of the Construction Agreement, unless specifically stated otherwise. GC 3.00
DRAWINGS AND SPECIFICATIONS
3.01 Ownership of Drawings. All drawings, specifications, and copies thereof furnished by the Architect are the property of the Architect and the Owner, whether or not the Work for which they are made is performed, and are not to be used on other Work except by written agreement with the Architect and the Owner. 3.02 Figured Dimensions to Govern. Dimensions and elevations shown on the drawings shall be accurately followed. No Work shown on the drawings, the dimensions of which are not indicated, shall be executed until necessary dimensions have been obtained from the Architect. 3.03 Contractor to Check Drawings and Schedules. The Contractor shall check and verify all dimensions, elevations, and quantities shown on the drawings and furnished to it by the Architect, and shall notify the Architect of any discrepancy between the drawings and the conditions on the ground, or any error or omission in drawings, or in the layout as given by stakes, points, or instructions that it may discover. Before ordering any material or doing any Work, the Contractor shall verify all measurements concerning the Project and shall be responsible for the correctness of same. No extra charge or compensation shall be allowed on account of any difference between actual dimensions and the measurements indicated on the drawings. Any difference that may be found shall be submitted to the Architect for consideration and written determination before proceeding with the Work. The Contractor shall not be allowed to take advantage of any error or omission in the drawings or Contract Documents. Full written instructions shall be furnished by the Architect should such error or omission be discovered, and the Contractor shall carry out such instructions as if originally specified. 3.04 Detail Drawings and Instructions. The Architect shall furnish with reasonable promptness additional instructions, by means of drawings or otherwise, necessary for the proper execution of the Work. All such drawings and instructions shall be consistent with the Contract Documents. The Work shall be executed in conformity with the Architect’s drawings and instructions, and the Contractor shall do no Work without proper drawings and instructions. 3.05 Drawings and Specifications Available on the Site. The Contractor shall maintain at the Project site for the Owner and the Architect a Project record set of drawings, including addenda, approved shop drawings, Change Orders, and other modifications, with all changes or deviations from the original drawings neatly marked thereon in a contrasting color. The Contractor shall also maintain a Project record set of specifications at the 2
Project site, noting therein by appropriate section the names, models, and other distinguishing characteristics of the materials actually incorporated into the Work. This Project record set of drawings and specifications shall be updated daily as the Project progresses and shall be made available to the Owner and Architect for inspection at all times. Upon final completion of the Work and before final payment, three (3) copies and one (1) electronic of this Project record set of drawings and specifications shall be delivered to the Owner. One (1) copy of this Project record set of drawings and specification shall be delivered to the Architect. 3.06 Laws and Regulations. The Contractor shall give all notices and comply with all laws, ordinances, rules, and regulations bearing on the conduct of the Work as drawn and specified. If the Contractor observes that the drawings and specifications are at variance therewith, it shall promptly notify the Architect in writing, and any necessary adjustments shall be made as provided in the Contract for changes in the Work. If the Contractor performs any Work knowing it to be contrary to such laws, ordinances, rules, or regulations without giving the required notice to the Architect and receiving a written directive to proceed, it shall bear all costs arising therefrom and to correct and/or remedy same. GC 4.00
ROYALTIES AND PATENTS
The Contractor shall pay all royalties and license fees. The Contractor shall defend all suits or claims for infringement of patent rights and shall hold the Owner harmless from any and all liability or loss on account thereof. If the Contractor has information that the process or article specified involves the infringement of a patent, it shall be responsible for any and all liability or loss resulting therefrom unless it promptly furnishes such information to the Architect in writing. GC 5.00
ITEMS COVERED BY CONTRACT PRICE
5.01 Items Supplied by Owner. Owner shall supply the following items for the Project: a. Building Permit; b. Initial Survey; c. Materials Testing Including Soil Testing; d. Third Party Inspections; e. Commissioning; and f. Test and Balance as Required for Commissioning. 5.02 Items Supplied by Contractor. Unless specifically stated otherwise, the Contractor shall accept the compensation stated in the Construction Agreement as full payment for furnishing all the materials, transportation, apparatus, temporary structures, equipment, services, fuel, energy, light, water, labor and tools, and all other things necessary for the complete and proper execution of the Work contemplated by or reasonably implied from the Contract Documents, within the time limits indicated therein. Such amount shall include any loss or damage resulting from the nature of the Work, from the elements or from any unforeseen difficulties that may be encountered; all risks of every description connected with the prosecution of the Work; all expenses incurred in consequence of any suspension or discontinuance of the Work; and all other amounts necessary for completing the Work pursuant to the Contract Documents within the time limits indicated therein. GC 6.00
EXECUTION, CORRELATION, INTENT, AND INTERPRETATION OF CONTRACT DOCUMENTS
6.01 Execution. The Construction Agreement and other Contract Documents shall be signed in multiple copies as directed by the Owner. Within ten (10) days of Notice of Award, the Contractor shall submit to the Owner a minimum of five (5) fully executed original sets of the Construction Agreement; Performance Bond, and Labor and Material Payment Bond with original Power of Attorney; and certificates of required insurance coverage. The date of the Contract for purposes of these documents shall be the date of the Notice of Award letter. The Owner shall execute the Construction Agreement, assemble all copies, and distribute the Contract Documents. The Contractor shall not commence the Work until it receives the Notice to Proceed. All bonds and insurance 3
certificates shall be submitted to the Owner prior to the award of the first subcontract. 6.02 Correlation. By executing the Construction Agreement, the Contractor represents that it has visited the Project site, familiarized itself with the local conditions under which the Work is to be performed, and correlated its observations with the requirements of the Contract Documents. 6.03 Intent. The intention of the Contract Documents is to include all labor and materials, tools, equipment, construction equipment, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution and completion of the Work. Materials or Work described in words that, as applied, have a well-known technical or trade meaning shall be held to refer to such recognized meaning. The organization of the specifications into divisions, sections, and articles, as the case may be, and the arrangement of drawings shall not control the Contractor in dividing the Work among subcontractors or in establishing the extent of Work to be performed by any trade. It is intended that even though Work is not covered under any heading, division, section, article, branch, class, or trade of the specifications, it shall nevertheless be supplied if it is required elsewhere in the Contract Documents or is reasonably inferable therefrom as being necessary to produce the intended results. The specifications and drawings are intended to supplement but not necessarily duplicate each other. Any Work exhibited in the one and not in the other shall be executed as if it had been set forth in both, so that the Work will be constructed according to the complete design as determined by the Architect. 6.04 Interpretation. Should anything necessary for a clear understanding of the Work be omitted from the specifications and drawings, or should the requirements appear to be in conflict, the Contractor shall secure written interpretations or instructions from the Architect before proceeding with the Work affected thereby. The Contractor shall secure written interpretations or instructions by submitting the Owner’s form Request for Interpretation to the Architect. Oral requests shall not be acknowledged by the Architect or Owner. Additional costs incurred by the Owner as a result of unnecessary requests made by the Contractor, as determined by the Owner, shall be the responsibility of the Contractor. It is understood and agreed that the Work shall be performed according to the true intent of the Contract Documents. 6.05 Conflict in Interpretation. In the case of discrepancy or in the event of a conflict between the different Contract Documents, the documents shall take precedence in the following order: a. Change Orders; b. Written Amendments to Construction Agreement (including, if applicable, the GMP); c. Construction Agreement; d. General Conditions; e. Drawings and specifications; and f. Bid Documents, including addenda. Where two or more of the Contract Documents are complementary, the more detailed provision shall control over the more general provision. GC 7.00
MATERIALS, LABOR, FACILITIES, AND STORAGE
7.01 Contractor’s Responsibility. Unless otherwise agreed in writing, the Contractor shall provide and pay for all materials, labor, tools, equipment, machinery, transportation, and other facilities necessary for the proper execution and completion of the Work. The Contractor shall provide and pay for all the temporary facilities required to supply all the power, light, water, and heat needed by it and its subcontractors for their Work and shall install and maintain all such facilities in such manner as to protect the public and workers and to conform with any applicable laws and regulations. If temporary heat and/or protection is required for the expeditious prosecution of the Work and before the permanent heating apparatus is available for use, the temporary heating apparatus shall be installed and operated in such a manner that the finish Work and/or construction will not be damaged thereby. Unless otherwise specified, the Contractor shall pay for all the power, light, and water used by it and its subcontractors, without regard to whether such items are metered by temporary or permanent meters. The cutoff date on permanent meters shall be either the agreed date of full occupancy by 4
the Owner or the date of final acceptance of the Project, whichever shall be the earlier date. Upon completion of the Work, the Contractor shall remove all surplus materials, tools and such temporary facilities and structures, furnished by the contractor from the Project site. All debris and rubbish caused by the operations of the contractor shall be removed, and the area occupied during construction activities shall be restored to its original condition, within 48 hours of project completion, unless otherwise directed by the municipality or owner’s representative. 7.02 Materials. Unless otherwise specified, all materials shall be new and both Workmanship and materials shall be of the highest quality. The Contractor shall furnish satisfactory evidence to the Owner as to the kind and quality of materials. Samples shall be furnished, when specified, and the Work shall be in accordance with those samples that have been approved. 7.03 Toilet Facilities. The Contractor shall provide and maintain, in a neat and sanitary condition, adequate temporary toilet facilities for the use of any and all employees engaged on the Work, in strict compliance with the requirements of all applicable codes, regulations, laws, and ordinances. In no event may present toilet facilities of any existing building at the site of the Work be used by employees of the Contractor or its subcontractors. Upon final completion of the Work, the Contractor shall remove all such temporary facilities from the site and disinfect the premises. 7.04 Facilities and Storage. The Contractor shall provide suitable temporary facilities and quarters for workers, as needed, and shall maintain on premises water-tight storage sheds or tool houses for storage of building materials and tools that could be damaged by weather. The Contractor shall allow space for the erection of sheds and provide similar facilities for storage by subcontractors of their materials and tools. Storage of materials shall be confined to the site. These facilities or quarters shall further provide for protection against theft and damage of building materials and tools. Upon final completion of the Work, the Contractor shall remove all such temporary facilities from the site. 7.05 Office Space. The Contractor shall provide adequate, weatherproofed, heated and well- lighted office space at the site of the Work, for use by the Architect and the Owner and their representatives. The Contractor shall also provide telephone service at such office, which shall be available for use by the Architect, the Owner, and their representatives without charge, except for toll calls. 7.06 Quality and Location of Facilities. All of the foregoing facilities shall be of a quality and placed in locations acceptable to the Architect and the Owner. GC 8.00
PERFORMANCE AND PAYMENT BONDS
8.01 Required Bonds. The Contractor shall, within ten (10) days from the Notice of Award furnish bonds to the Owner in the full amount of the contract price, covering both the faithful performance of the Contract and the payment of all obligations for labor and materials arising thereunder, on such customary forms as the Owner may prescribe and with such sureties as it may approve. The amount of the bonds shall be increased, if necessary, to reflect approved changes in the Work that result in an increase in the total cost of the Work plus the Contractor’s fees. Such bonds shall be duly executed by a qualified surety licensed to do business in the State of Colorado, conditioned upon the true and faithful performance of the Contract, and shall provide that if the Contractor or its subcontractors fail to duly pay for any labor, materials, or other supplies used or consumed by such Contractor or its subcontractors in the performance of the Work contracted to be done, the surety will pay the same in an amount not exceeding the sum specified in the bond, as adjusted by approved Change Orders, and together with interest as provided by law. The performance bond shall additionally guarantee that the Contractor shall remedy any omissions, correct any and all defects, and adjust and make operable all component parts of Work falling under the requirements of the Contract that may be called to the Contractor’s attention within a period of twenty-four (24) months following the date of the letter of acceptance.
5
8.02 Additional Bond Requirements. The premium for all bonds shall be paid by the Contractor and included in the bid price in the bid proposal. The Owner will accept and approve bonds written by sureties legally authorized to write such bonds in the State of Colorado, provided such surety companies are rated in Best’s Insurance Guide (latest edition), not lower than A- or have Best’s Financial Rating of at least X. If, at any time a surety on such a bond becomes irresponsible or loses its right to do business in the State of Colorado, new bonds shall be provided by an alternate surety licensed to do business in the State and meeting the requirements of this Section 8.00. GC 9.00
PERMITS AND COMPLIANCE WITH STATUTES, RULES, AND REGULATIONS
9.01 Permits. Any local permits, governmental fees, and licenses necessary for the proper execution and completion of the Work shall be secured and paid for by the Contractor. Owner will pay for and secure building permit from Colorado Division of Fire Prevention and Control. Easements for permanent structures or permanent changes in existing facilities shall be secured and paid for by the Owner, unless otherwise specified in writing. The Owner is generally exempt from paying any fee for any building permit issued by any building departments or agencies located in Boulder, Broomfield, and Gilpin Counties, and the Contractor shall see that no building permit fee is paid. The Owner shall negotiate and provide for all electrical, gas, water, and sewer mains for the Contractor’s connections. The Contractor shall arrange with the utility company for actual connection, make necessary connections, and pay for all associated inspection fees and permits as required by any government agency. In addition, the Contractor shall furnish all material and items required to complete all connections. The Contractor shall call for all inspections on a timely basis by any agency having jurisdiction over the Work. 9.02 Compliance with Statutes, Rules and Regulations. The Contractor and all subcontractors shall comply with all applicable federal and state statutes, rules, regulations, and directives of the State Division of Fire Prevention and Control, and other governmental body having jurisdiction over the work to be performed. If any of the provisions of the Contract Documents are in conflict therewith, such portions shall be considered stricken and the applicable statute, ordinance, regulation, or ruling substituted therefor. All such cases of apparent conflict coming to the attention of any party shall immediately be called to the attention of the Owner. The Contractor shall strictly observe and comply with all federal and state laws pertaining to the employment and payment of labor. GC 10.00
SURVEYS, BENCHMARKS, MONUMENTS, STAKES, AND MEASUREMENTS
10.01 Surveys. As provided by the Owner, the Contractor shall obtain from the Architect a copy of all surveys describing property lines, elevation benchmarks, physical characteristics, and utility locations. 10.02 Benchmarks. The Contractor shall properly stake out the Work and provide and rigidly set benchmarks and batter boards as necessary for the proper performance of the Work. The Contractor shall remain responsible for their maintenance and their accuracy. A permanent benchmark, approved as to location and type by the Architect, from which all grades are to be taken, shall be established near the site of the Work by the Contractor. From this benchmark the Contractor shall ascertain all grades and levels to Project buildings as needed. The Contract Documents shall include all necessary information to establish the benchmark. 10.03 Preservation of Monuments and Stakes. The Contractor shall carefully preserve all monuments, benchmarks, property markers, reference points, and stakes. In case of the destruction thereof, the Contractor shall be charged with the expense of replacement and shall be responsible for any mistake or loss of time that may be caused. Permanent monuments and/or benchmarks that must be removed or disturbed shall be protected until properly referenced for relocation. The Contractor shall furnish all materials, labor and assistance for the proper replacement of such monuments and benchmarks. 10.04 Measurements. Before ordering any material or performing any Work, the Contractor shall verify all measurements on the Project and shall be responsible for the accuracy of same. No extra charge or 6
compensation shall be allowed because of any difference between actual dimensions and the measurements indicated in the drawings or specifications. Any discrepancies shall be submitted to the Architect and Owner for consideration before proceeding with the Work. GC 11.00
CHANGED CONDITIONS
The Contractor shall promptly, and before such conditions are disturbed, notify the Owner and the Architect in writing of: (1) sub-surface or latent physical conditions at the Project site differing materially from those indicated in the Contract Documents, or (2) unknown physical conditions at the Project site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in Work of the character provided for in the Contract Documents. The Owner and the Architect shall promptly investigate the conditions, and if the Owner finds that such conditions do so materially differ and cause an increase or decrease in the cost of or the time required for performance of the Work, an equitable adjustment shall be made and the Contract modified in writing accordingly. Any claim of the Contractor for adjustment hereunder shall not be allowed unless it has given notice as required. GC 12.00
PROTECTION OF PERSONS, WORK AND PROPERTY
12.01 Building Exits and Barricades. During the course of construction, the Contractor shall keep all required building exits free and unimpeded. Such exits shall not be closed at any time for any reason while the building is occupied or at any time when the building is unoccupied, except after written approval is given by the Owner and proper warning and directional signs are posted. Barricades shall be erected so that traffic is separated and protected from the construction. 12.02 Precautions. The Contractor shall take all necessary precautions to ensure the safety of all employees and other persons on the Project or who may be affected by the Contractor’s Work thereon. The Contractor shall also take all necessary precautions to protect the Work and all temporary facilities, as well as materials, tools, and equipment incorporated therein or to be incorporated therein from damage or destruction, whether in storage on or off the Project site and whether in the custody or control of the Contractor or any of its subcontractors. The Contractor shall also take all necessary precautions to protect all property at the Project site and adjacent thereto not designated for removal, relocation or replacement, including trees, shrubs, lawns, walks, pavements, roadways, structures, and utilities. 12.03 OSHA Compliance. The Contractor shall comply with all applicable provisions of the Occupational Safety and Health Administration (“OSHA”) and all laws, ordinances, rules, regulations, and orders of all governmental agencies or authorities having jurisdiction to protect the safety of employees and/or other persons who may be affected by the Work. The Contractor shall erect and maintain all necessary safeguards to protect workers on the Project site and the owners and users of adjacent property, and shall post danger signs and other warnings against hazards created by the Work including but not limited to protruding nails, hoists, well holes, elevator shafts, hatchways, scaffolding, window openings, stairways, excavations, and falling materials. The Contractor shall designate a responsible employee at the Project site as a safety officer to ensure the Contractor’s compliance with this section. Said employee shall be the Contractor’s superintendent unless otherwise designated in writing by the Contractor to the Owner and the Architect. 12.04 Contractor’s Liability. The Contractor shall be liable for all injury, damage or loss to any person or property caused in whole or in part by the Contractor, any of its subcontractors, or any person employed by or under the direction of the Contractor or any of its subcontractors. To the extent possible and unless otherwise directed by the Owner or Architect, the Contractor shall promptly repair, pay for or otherwise remedy any such injury, damage or loss and shall indemnify and hold harmless the Owner against any and all liability, claims, damages, losses and expenses arising therefrom. The terms of this section shall not apply in the case of injury, damage or loss proximately caused by the acts or omissions of the Owner and/or Architect and not attributable to any fault or negligence of the Contractor.
7
12.05 Emergencies. In the event of an emergency that threatens the safety or life of any person or threatens to damage or destroy the Project and/or any Work, materials, equipment or property thereon or to be used thereon, the Contractor shall act at its discretion to prevent such injury, death, damage or destruction. The Contractor shall immediately notify the Owner and Architect in writing of any such emergency and any action taken by the Contractor in response thereto. Any compensation due the Contractor for such emergency action shall be determined by agreement of the Contractor, Owner and Architect, and an appropriate Change Order shall be issued therefor. GC 13.00
WORK ON EXISTING BUILDINGS
13.01 Protection of Occupants. In addition to all other requirements of the Contract Documents, if the Work involves an addition or alteration to an existing building, the Contractor shall erect and maintain during the progress of the Work suitable dustproof partitions to protect such building and the occupants thereof. If necessary, in the Owner’s or Contractor’s judgment or pursuant to manufacturer’s directives or recommendations in order to protect occupants from noxious fumes, odors, or hazardous substances, the Contractor may be required to provide additional ventilation and/or work different or extended hours to avoid disruption to other activities within the existing building. Contractor shall protect and keep from harm all occupants of an existing building from construction activities, and shall include a safe pathway into and out of the school. 13.02 Partitions and Scheduling. If any portions of an existing building are to be remodeled or repaired, such portions shall be adequately partitioned off with dustproof partitions and well ventilated. All remodeling Work shall be scheduled and submitted to the Owner and Architect for approval. The various contractors shall schedule their Work jointly, in order that each may accomplish its Work within such existing building in an orderly fashion during regular school vacation periods where possible, or in such a manner as to permit full use of the building and without impairment of any existing facilities. 13.03 Existing Systems. Existing building systems, such as fire alarm, temperature controls and air distribution, security systems, public announcement systems, irrigation systems, and the like, shall be demonstrated and noted by Owner to the Contractor as operational prior to Contractor’s commencing the Work and Contractor may participate in observation of such systems. Such systems are the responsibility of the Contractor to maintain in pre-construction condition. GC 14.00
CONTRACTOR’S SUPERINTENDENCE AND SUPERVISION
14.01 Superintendent. During the progress of the Work, the Contractor shall ensure that a competent superintendent and any necessary assistants, all satisfactory to the Architect and the Owner, are on the Project site at all times while Work is in progress. The superintendent shall not be changed by the Contractor except with the written consent of the Architect and the Owner, unless the superintendent ceases to be in the Contractor’s employ. The superintendent shall represent the Contractor on the Project and all directions given to him/her shall be as binding as if given to the Contractor. The Architect and the Owner shall not be responsible for the acts or omissions of the superintendent or his/her assistants. 14.02 Supervision. The Contractor shall provide full-time, qualified, and efficient supervision of the Work, using competent skill and attention. The Contractor is responsible for determining and supervising all temporary and permanent erection and construction sequences, techniques, means, or methods. The Contractor shall direct, schedule, coordinate the Work to ensure that all parts fit together properly and in accordance with the Contract Documents. The Contractor shall carefully study and compare all Contract Documents and other instructions and shall at once report to the Architect and the Owner any error, inconsistency, or omission that Contractor may discover. 14.03 Additional Supervision Duties. The Contractor shall see that the Work is carried out in accordance with the Contract Documents and in a thorough and first-class manner in every respect. The Contractor shall 8
provide engineering, surveying, and coordination to accurately establish all lines, levels, and marks necessary to facilitate the operations of all parties involved in the Contractor’s Work. The Contractor shall lay out the Work in a manner satisfactory to the Architect, making permanent records of all lines and levels required for excavation, grading, and foundations, and for all other parts of the Work. The Contractor shall be responsible for the commencement and the proper completion of the various stages and sequences of construction. The Contractor shall strictly adhere to the approved construction schedule. GC 15.00
SUBSTITUTIONS
The Contractor shall be held to have used in its base proposal and to furnish under the Contract those items of equipment and/or materials that are specifically identified in the plans and specifications by a manufacturer’s name, model, or catalog number. Items of equipment and/or materials of the Contractor’s choice may be offered as alternates to the items named in the plans and specifications by submitting, with the proposal and on the form provided, identifying data on the articles proposed together with a statement of the amount of addition or deduction from the base bid if the bidder’s alternate is accepted. Prior approval by the Architect is not required on items submitted as alternate bids. After execution of the Construction Agreement, substitution of equipment and/or materials of makes other than those specifically named in the Contract Documents may be approved by the Owner so long as the equipment or material proposed for substitution in the opinion of the Owner is just as suitable as the equipment and/or materials named in the plans and specifications so far as performance, construction, efficiency, and utility are concerned. A request for substitution shall ordinarily be required to be based upon one or more of the following grounds: the specified equipment or material is no longer available, a substitution will improve lead time, quality will be improved (documented detail required), or the Owner will incur substantial savings. All requests for substitution must be submitted in writing with supporting documentation by or through the Contractor to the Architect for initial review and recommendation before being submitted to the Owner for evaluation and final approval. In the absence of the Owner’s written approval, no substitution of equipment or materials shall be allowed for any items specified in the Contract Documents. In case of a difference in price, occurring as a result of an approved substitution, the Owner shall receive all benefit of the difference in cost involved in the substitution. All approved substitutions shall be documented by the issuance of a formal Change Order as provided in these General Conditions. GC 16.00
SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
16.01 Shop Drawings. “Shop drawings” are drawings, diagrams, illustrations, schedules, performance charts, brochures, manufacturer’s literature, and other data that are prepared by the Contractor or any subcontractor, manufacturer, supplier, or distributor, and that illustrate some portion of the Work. Shop drawings shall be submitted in both hard copy and electronic format. 16.02 Samples. “Samples” are physical examples furnished by the Contractor to the Owner and/or Architect to illustrate materials, finishes, equipment, or Workmanship, and to establish standards by which the Work will be judged. 16.03 Product Data. “Product data” are illustrations, standard schedules, performance charts, instructions, brochures, diagrams and other information furnished by the Contractor to illustrate materials or equipment for some portion of the Work. Product data shall be submitted in both hard copy and electronic format. 16.04 Contractor’s Obligations. The Contractor shall review, approve, stamp an then submit to the Architect shop drawings, product data, samples, and similar submittals required by the Contract Documents with reasonable promptness and in such a sequence as to cause no delay in the Work or in the activities of the Owner or of separate contractors. Shop drawings, product data, samples, and similar submittal required by the Contract Documents shall properly identify specified items. At the time of submission, the Contractor shall inform the Architect in writing of any deviation in the shop drawings, product data, or samples from the requirements of the Contract Documents. Substitutions will be allowed only in accordance with the provisions of GC-15.00. The number of copies and format of submittal shall be as required by the Architect, but, at a 9
minimum, shall include three (3) copies and one (1) electronic copy of the original shop drawings and product data for the Owner. 16.05 Verification. By approving and submitting shop drawings, product data, and samples, the Contractor thereby represents that it has determined and verified all field measurements, field construction criteria, dimensions, elevations, quantities, materials, catalog numbers, and similar data, as shown on the drawings and specifications furnished by the Architect, or will do so, and that it has checked and coordinated each shop drawing, product data, and sample with the requirements of the Work and of the Contract Documents. 16.06 Architect /Owner Review. The Architect shall review and approve shop drawings, product data, and samples with reasonable promptness so as to cause no delay, but only for conformance with the design concept of the Project and with the information given in the Contract Documents. The Architect’s approval of a separate item shall not indicate approval of any assembly in which the item functions. Upon the final completion of the Work, the Contractor shall furnish to the Architect two corrected copies of all shop or setting drawings showing the as-built condition of the Work. The Architect, after review, shall submit one of these copies to the Owner. 16.07 Corrections. The Contractor shall make any corrections required by the Architect and shall resubmit the required number of corrected copies of shop drawings or new samples until approved by the Architect. The Contractor shall direct specific attention in a separate writing or on resubmitted shop drawings to revisions other than the corrections requested by the Architect on previous submissions. 16.08 Contractor’s Responsibility. The Architect’s approval of shop drawings, product data, or samples shall not relieve the Contractor of responsibility for any deviation from the requirements of the Contract Documents unless the Contractor has informed the Architect in writing of such deviation at the time of submittal and the Architect has given written approval of the specific deviation. The Architect’s approval shall also not relieve the Contractor from responsibility for errors or omissions in the shop drawings, product data, or samples. 16.09 Architect Approval Required. No portion of the Work requiring the submission of a shop drawing, product data, or sample shall be commenced until such submittal has been approved in writing by the Architect. All such portions of the Work shall be in accordance with approved shop drawings, product data, and samples. All material finishes and samples shall be approved at one time. The Contractor shall submit all items requiring approval of finishes, color, material, etc., with sufficient lead time to allow simultaneous consideration and preparation of complete finish color schedule. No approvals of single items shall be considered. 16.010 Copies to Owner. When shop drawings, product data, samples or similar submittals have been approved and stamped by both Contractor and Architect, Contractor shall immediately forward an electronic copy of each to the Owner. GC 17.00
CASH ALLOWANCE
The Contractor shall include in the Contract sum all allowances named in the Contract Documents and shall cause the work so covered to be done by such Contractors and for such sums as the Owner may direct, the Contract sum being adjusted in conformity therewith. The Contractor declares that the Contract sum includes such sums for expenses and profit on account of cash allowances as he deems proper. No demand for expenses or profit other than those included in the Contract sum shall be allowed. The Contractor shall not be required to employ for any such work persons against whom he has filed a lien or has a reasonable objection due to previous legal claims. GC 18.00
EXPEDITING MATERIALS 10
The Contractor shall, immediately after receipt of the Notice of Award and approval of its list of subcontractors and material suppliers, place orders for all equipment, materials, and supplies required for the Work. The Contractor shall, when requested, submit to the Architect evidence that such orders have been placed. The Contractor shall exercise due diligence in seeing that all equipment, materials, and supplies are delivered well in advance of the time they are needed on the Project and shall properly store and protect same at its expense and in accordance with these General Conditions, either at the Project site or elsewhere as approved by the Architect. GC 19.00
BLASTING
No explosives of any nature except for those normally employed in powder actuated tools, .38 caliber or smaller, shall be employed or used on the Project site except with the express and specific prior written approval of the Architect and the Owner and any appropriate governmental authorities, in each instance. The Contractor shall notify the Architect of need for such approval three (3) days prior to the proposed use of such explosives. GC 20.00
SOIL TEST REPORT
The Owner may arrange for a separate consultant to conduct field and laboratory soil investigations on the Project site and to prepare a report of its findings. Such a report, if prepared, shall be available for review by the Contractor in the Architect’s office. Such data is offered solely for reference and is not to be considered a part of the Contract Documents. The data contained in any such document prepared for the Owner by a separate consultant is believed to be reliable; however, the Owner and Architect do not guarantee its accuracy or completeness. All applicable subcontractors shall be fully familiar with the contents of such reports, if prepared, and shall consider and evaluate them in the performance of their contracts and the Work. GC 21.00
HAZARDOUS MATERIALS
21.01 Responsibility and Reporting. Unless otherwise provided in the Contract Documents, the Contractor shall have no responsibility for the presence, handling, removal or disposal of hazardous materials in any form at the Project site, including but not limited to asbestos, asbestos products, polychlorinated biphenyl (PCB), lead, or other hazardous materials. Prior to its commencement or continuation of any portion of the Work, the Contractor shall provide notice to the Owner of the presence, location, amount and condition of any known or suspected hazardous materials that are discovered at the Project site. Such notice shall be in writing and shall be submitted no more than twenty-four (24) hours after the presence of such materials becomes known or suspected. 21.02 Contractor’s Obligations. In the event hazardous materials become known or suspected by the Contractor as described in GC-21.01 above, the Contractor shall not proceed with or continue the Work until it has received written authorization from the Owner. If the Contractor proceeds with the Work without said authorization, it assumes any and all responsibility and liability for contamination and cleanup at the Project site according to applicable federal and state laws, and for any death or personal injury, including but not limited to medical expenses that may be incurred by any individual as a result of exposure to hazardous materials on the Project site. 21.03 Owner’s Obligations. In the event hazardous materials are identified or encountered during the course of the Project, the Owner at its expense shall take reasonable actions to properly and safely deal with such materials. 21.04 Management Plan. The Contractor acknowledges that it and its employees, agents and subcontractors have the responsibility of being fully informed of the Owner’s Management Plan as it relates to buildings located at the Project site and shall consult with the Owner about how such Plan addresses suspected or active asbestos-containing material areas within such buildings. GC 22.00
DAMAGE TO UTILITIES 11
22.01 Adequate Precautions. The Contractor shall take adequate precautions to protect existing utilities on and off the Project site and avoid damage thereto. The Contractor shall repair or replace or have repaired or replaced at its expense any damage to streets, water, sewer, light, power, cable, or telephone lines or fiber network that are damaged by reason of the Contractor’s Work. 22.02 Location. The location and extent of underground utilities, fiber network, cables and conduit indicated on the drawings are not guaranteed. This information is shown only for such use as bidders and contractors may choose to make of it. The Contractor shall check with all public utility companies for locations and shall comply with their regulations regarding such utilities in performing the Work. 22.03 Protection from Damage. The Contractor shall adequately protect active underground utilities from damage, and if damaged shall immediately effect all necessary repairs. Removal or relocation of active underground utilities shall be done only as indicated on the drawings. If such utilities are in use, they shall be maintained in continuous service. If not indicated on the drawings or not known to exist, the Contractor shall report discovery of such utilities to the Architect and shall not proceed further until directed to do so. 22.04 Inactive or Abandoned Utilities. Inactive or abandoned utilities, whether or not they are indicated on the drawings, shall be recorded as to location and depth and shall be removed for a distance of not less than three (3) feet from the outside line of all concrete Work unless otherwise required by regulations. Ends shall be capped or plugged. There shall be no adjustment of the Contract amount for Work due to inactive or abandoned utilities. GC 23.00
CHANGES IN THE WORK
23.01 Change Orders. The Owner, without invalidating the Agreement, may order changes in the Work within the general scope of the Project consisting of additions, deletions, or other revisions. Under such circumstances, the GMP, if applicable and established, and the Contract Time Schedule shall be adjusted accordingly. All such changes in the Work shall be authorized by Change Order. No Change Order or other form of order or directive by the Owner or Architect requiring additional compensable Work to be performed, which causes the aggregate amount payable under the Contract Documents to exceed the amount appropriated for the original Agreement, shall be issued unless the Contractor is given written assurance by the Owner that lawful appropriations to cover the costs of the additional Work have been made. Any claim of the Contractor for adjustment under this section must be asserted in writing within ten (10) days from the date of the Contractor’s receipt of the Change Order. 23.02 Minor Changes. The Architect shall have authority to order minor changes in the Work not involving an adjustment in the GMP or an extension of the Contract Time Schedule and not inconsistent with the intent of the Contract Documents. Such changes may be effected by field order or by other written order. Such changes shall be binding on the Owner and the Contractor. In any emergency affecting the safety of persons or property, the Contractor shall act, at his discretion, to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in this Article. 23.03 Price Differential. The cost or credit resulting from a change in the Work shall be determined in one or more of the following ways: a. By estimate, with a detailed cost breakdown as set forth in GC-23.03(c) below, and acceptance in a lump sum, with a maximum combined markup to the Owner, for the Contractor and all affected subcontractors, not to exceed a total of fifteen percent (15%). b. By unit prices named in the Contract or subsequently agreed upon. c. If the parties are unable to agree on one of the above methods, then the amount shall be determined by force account under the following formula: i. The actual cost of all direct labor performed (including foremen employed continuously on the Work, but not the salary, or any part thereof, of the Contractor’s superintendent) and the actual 12
ii. iii. iv. v.
vi.
GC 24.00