BVSD Eisenhower ES GMP Exhibits.pdf (10,245 KB)

Regular Meeting, November 10, 2026 · item 7.6: Amendment to the contract for Eisenhower Elementary School · 104 pages

Open the original file

This is the text extracted from the file, without its layout, tables, or images. Use the original for anything that matters.

Exhibit A Drawings, specifications and documents used to prepare the GMP

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Printed on Thu Oct 15, 2026 at 12:34 pm MDT Job #: 8735 BVSD - Eisenhower ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction

Current Drawings Drawing Number

Drawing Title

Revision

Drawing Date

Received Date

Set

Status

General G001

COVER SHEET

2

08/28/2026

08/28/2026

26.08.28 CD's

Published

G110

FIRST FLOOR CODE PLAN

2

08/28/2026

08/28/2026

26.08.28 CD's

Published

GENERAL NOTES

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

AS101

ARCHITECTURAL SITE PLAN

2

08/28/2026

08/28/2026

26.08.28 CD's

Published

AS500

MONUMENTAL SIGN

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

AD110

FIRST FLOOR DEMOLITION PLAN - OVERALL

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

AD111

FIRST FLOOR DEMO PLAN - AREA 111

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

AD112

FIRST FLOOR DEMO PLAN - AREA 112

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

AD113

FIRST FLOOR DEMO PLAN - AREA 113

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

AD400

KINDERGARTEN ENLARGED DEMO PLAN AND DEMO RCP

2

08/28/2026

08/28/2026

26.08.28 CD's

Published

ACD111

FIRST FLOOR DEMO RCP - AREA 111

0

08/28/2026

08/28/2026

26.08.28 CD's

Published

ACD110

FIRST FLOOR DEMOLITION RCP - OVERALL

0

08/28/2026

08/28/2026

26.08.28 CD's

Published

ACD112

FIRST FLOOR DEMO RCP - AREA 112

0

08/28/2026

08/28/2026

26.08.28 CD's

Published

ACD113

FIRST FLOOR DEMO RCP - AREA 113

0

08/28/2026

08/28/2026

26.08.28 CD's

Published

A110

FIRST FLOOR PLAN - OVERALL

2

08/28/2026

08/28/2026

26.08.28 CD's

Published

A111

FIRST FLOOR PLAN - AREA 111

2

08/28/2026

08/28/2026

26.08.28 CD's

Published

A112

FIRST FLOOR PLAN - AREA 112

2

08/28/2026

08/28/2026

26.08.28 CD's

Published

A113

FIRST FLOOR PLAN - AREA 113

2

08/28/2026

08/28/2026

26.08.28 CD's

Published

AC110

FIRST FLOOR REFLECTED CEILING PLAN - OVERALL

2

08/28/2026

08/28/2026

26.08.28 CD's

Published

AC111

FIRST FLOOR REFLECTED CEILING PLAN - AREA 111

2

08/28/2026

08/28/2026

26.08.28 CD's

Published

Structural S001 Architectural

Page 1 of 4

Printed on Thu Oct 15, 2026 at 12:34 pm MDT Job #: 8735 BVSD - Eisenhower ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction

Drawing Number

Drawing Title

Revision

Drawing Date

Received Date

Set

Status

AC112

FIRST FLOOR REFLECTED CEILING PLAN - AREA 112

2

08/28/2026

08/28/2026

26.08.28 CD's

Published

AC113

FIRST FLOOR REFLECTED CEILING PLAN - AREA 113

2

08/28/2026

08/28/2026

26.08.28 CD's

Published

A160

OVERALL ROOF PLAN

2

08/28/2026

08/28/2026

26.08.28 CD's

Published

A400

KINDERGARTEN ENLARGED FLOOR PLANS

2

08/28/2026

08/28/2026

26.08.28 CD's

Published

A401

ENLARGED PLANS

0

05/15/2026

05/15/2026

26.05.15 - DD's

Published

A420

INTERIOR ELEVATIONS

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

A500

DETAILS

0

08/28/2026

08/28/2026

26.08.28 CD's

Published

A600

DOOR AND WINDOW SCHEDULES

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

ENLARGED INTERIOR FINISH PLAN - KINDERGARTEN

0

08/28/2026

08/28/2026

26.08.28 CD's

Published

SIGNAGE LEGEND & SCHEDULE

0

08/28/2026

08/28/2026

26.08.28 CD's

Published

MD-111

HVAC DEMOLITION PLAN - AREA 111

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

MD-112

HVAC DEMOLITION PLAN - AREA 112

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

MD-121

HVAC ROOF DEMOLITION PLAN - AREA 111

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

MD-122

HVAC ROOF DEMOLITION PLAN - AREA 112

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

M-001

MECHANICAL LEGENDS & NOTES

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

M-002

MECHANICAL SCHEDULES

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

M-111

HVAC PLAN - AREA 111

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

M-112

HVAC PLAN - AREA 112

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

M-121

HVAC ROOF PLAN - AREA 111

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

M-122

HVAC ROOF PLAN - AREA 112

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

M-401

MECHANICAL DETAILS

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

M-501

MECHANICAL CONTROLS

0

08/28/2026

08/28/2026

26.08.28 CD's

Published

Interior I400 Signage SN100 Mechanical

Page 2 of 4

Printed on Thu Oct 15, 2026 at 12:34 pm MDT Job #: 8735 BVSD - Eisenhower ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction

Drawing Number M-502

Drawing Title

Revision

Drawing Date

Received Date

Set

Status

MECHANICAL CONTROLS

0

08/28/2026

08/28/2026

26.08.28 CD's

Published

PD-111

DOMESTIC WATER DEMOLITION PLAN - AREA 111

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

P-001

PLUMBING LEGENDS & NOTES

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

P-111

DOMESTIC WATER PLAN - AREA 111

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

ED-111

LIGHTING DEMOLITION PLAN - AREA 111

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

ED-112

LIGTHING DEMOLITION PLAN - AREA 112

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

ED-113

LIGHTING DEMOLITION PLAN - AREA 113

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

ED-122

ROOF POWER DEMOLTION PLAN - AREA 112

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

ED-121

ROOF POWER DEMOLITION PLAN - AREA 111

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

ED-131

FIRE ALARM DEMOLITION PLAN - AREA 111

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

ED-132

FIRE ALARM DEMOLITION PLAN - AREA 112

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

ED-133

FIRE ALARM DEMOLITION PLAN - AREA 113

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

E-001

ELECTRICAL LEGENDS & NOTES

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

E-002

ELECTRICAL SCHEDULES

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

E-011

ELECTRICAL ONE-LINE DIAGRAM

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

E-101

ELECTRICAL SITE PLAN

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

E-111

LIGHTING PLAN - AREA 111

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

E-112

LIGHTING PLAN - AREA 112

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

E-113

LIGHTING PLAN - AREA 113

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

E-120

POWER PLAN - OVERALL

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

E-121

ROOF POWER PLAN - AREA 111

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

E-122

ROOF POWER PLAN - AREA 112

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

E-131

FIRE ALARM PLAN - AREA 111

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

Plumbing

Electrical

Page 3 of 4

Printed on Thu Oct 15, 2026 at 12:34 pm MDT Job #: 8735 BVSD - Eisenhower ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction

Drawing Number

Drawing Title

Revision

Drawing Date

Received Date

Set

Status

E-132

FIRE ALARM PLAN - AREA 112

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

E-133

FIRE ALARM PLAN - AREA 113

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

E-201

ENLARGED ELECTRICAL PLANS

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

E-202

ENLARGED ELECTRICAL PLANS - KINDERGARTEN

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

E-301

ELECTRICAL PANEL SCHEDULES

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

E-401

ELECTRICAL DETAILS

1

08/28/2026

08/28/2026

26.08.28 CD's

Published

Page 4 of 4

Printed on Thu Oct 15, 2026 at 12:46 pm MDT Job #: 8735 BVSD - Eisenhower ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction

Current Specifications Number

Description

Revision

Issued Date

Received Date

Set

00 - Procurement and Contracting Requirements 00 0103

PROJECT DIRECTORY

0

26.08.28 - CD's

00 0108

TABLE OF CONTENTS

0

26.08.28 - CD's

00 4322

UNIT PRICES FORM

0

26.08.28 - CD's

00 4323

ALTERNATES FORM

0

26.08.28 - CD's

00 5000

CONTRACTING FORMS AND SUPPLEMENTS

0

26.08.28 - CD's

00 7200

GENERAL CONDITIONS

0

26.08.28 - CD's

000107

SEALS PAGE

0

26.08.28 - CD's

000110

COVER PAGE

0

26.08.28 - CD's

01 - General Requirements 01 1000

SUMMARY

0

26.08.28 - CD's

01 2000

PRICE AND PAYMENT PROCEDURES

0

26.08.28 - CD's

01 2200

UNIT PRICES

0

26.08.28 - CD's

01 2300

ALTERNATES

0

26.08.28 - CD's

01 2500

SUBSTITUTION PROCEDURES

0

26.08.28 - CD's

01 3000

ADMINISTRATIVE REQUIREMENTS

0

26.08.28 - CD's

01 3216

CONSTRUCTION PROGRESS SCHEDULE

0

26.08.28 - CD's

01 4000

QUALITY REQUIREMENTS

0

26.08.28 - CD's

01 5000

TEMPORARY FACILITIES AND CONTROLS

0

26.08.28 - CD's

01 5713

TEMPORARY EROSION AND SEDIMENT CONTROL

0

26.08.28 - CD's

01 6000

PRODUCT REQUIREMENTS

0

26.08.28 - CD's

01 6116

VOLATILE ORGANIC COMPOUND (VOC) CONTENT RESTRICTIONS

0

26.08.28 - CD's

01 7000

EXECUTION AND CLOSEOUT REQUIREMENTS

0

26.08.28 - CD's

01 7419

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

0

26.08.28 - CD's

01 7800

CLOSEOUT SUBMITTALS

0

26.08.28 - CD's

01 7900

DEMONSTRATION AND TRAINING

0

26.08.28 - CD's

01 9113

GENERAL COMMISSIONING REQUIREMENTS

0

26.08.28 - CD's

02 - Existing Conditions 02 4100

DEMOLITION

0

26.08.28 - CD's

02 4119

SELECTIVE STRUCTURE DEMOLITION

0

26.08.28 - CD's

03 2000

CONCRETE REINFORCING

0

26.08.28 - CD's

03 3000

CAST-IN-PLACE CONCRETE

0

26.08.28 - CD's

04 0511

MASONRY MORTARING AND GROUTING

0

26.08.28 - CD's

04 2000

UNIT MASONRY

0

26.08.28 - CD's

03 - Concrete

04 - Masonry

05 - Metals

Page 1 of 4

Printed on Thu Oct 15, 2026 at 12:46 pm MDT Job #: 8735 BVSD - Eisenhower ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction

Number

Description

Revision

Issued Date

Received Date

Set

05 1200

STRUCTURAL STEEL FRAMING

0

26.08.28 - CD's

05 4000

COLD-FORMED METAL FRAMING

0

26.08.28 - CD's

05 5133

METAL LADDERS

0

26.08.28 - CD's

06 - Wood, Plastics, and Composites 06 1000

ROUGH CARPENTRY

0

26.08.28 - CD's

06 2000

FINISH CARPENTRY

0

26.08.28 - CD's

07 - Thermal and Moisture Protection 07 0553

FIRE AND SMOKE ASSEMBLY IDENTIFICATION

0

26.08.28 - CD's

07 2100

THERMAL INSULATION

0

26.08.28 - CD's

07 2500

WEATHER BARRIERS

0

26.08.28 - CD's

07 5300

ELASTOMERIC MEMBRANE ROOFING

0

26.08.28 - CD's

07 6200

SHEET METAL FLASHING AND TRIM

0

26.08.28 - CD's

07 9200

JOINT SEALANTS

0

26.08.28 - CD's

08 1113

HOLLOW METAL DOORS AND FRAMES

0

26.08.28 - CD's

08 1416

FLUSH WOOD DOORS

0

26.08.28 - CD's

08 4313

ALUMINUM-FRAMED STOREFRONTS

0

26.08.28 - CD's

08 7100

DOOR HARDWARE

0

26.08.28 - CD's

08 8000

GLAZING

0

26.08.28 - CD's

08 9100

LOUVERS

0

26.08.28 - CD's

09 0561

COMMON WORK RESULTS FOR FLOORING PREPARATION

0

26.08.28 - CD's

09 2116

GYPSUM BOARD ASSEMBLIES

0

26.08.28 - CD's

09 5100

ACOUSTICAL CEILINGS

0

26.08.28 - CD's

09 6500

RESILIENT FLOORING

0

26.08.28 - CD's

09 6566

RESILIENT ATHLETIC FLOORING

0

26.08.28 - CD's

09 6813

TILE CARPETING

0

26.08.28 - CD's

09 9113

EXTERIOR PAINTING

0

26.08.28 - CD's

09 9123

INTERIOR PAINTING

0

26.08.28 - CD's

10 1100

VISUAL DISPLAY UNITS

0

26.08.28 - CD's

10 1400

SIGNAGE

0

26.08.28 - CD's

10 2600

WALL AND DOOR PROTECTION

0

26.08.28 - CD's

MANUFACTURED WOOD CASEWORK

0

26.08.28 - CD's

22 0500

COMMON WORK RESULTS FOR PLUMBING

0

26.08.28 - CD's

22 0513

COMMON MOTOR REQUIREMENTS FOR PLUMBING EQUIPMENT

0

26.08.28 - CD's

22 0519

METERS AND GAUGES FOR PLUMBING PIPING

0

26.08.28 - CD's

22 0523

GENERAL DUTY VALVES FOR PLUMBING

0

26.08.28 - CD's

22 0529

HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT

0

26.08.28 - CD's

08 - Openings

09 - Finishes

10 - Specialties

12 - Furnishings 12 3200 22 - Plumbing

Page 2 of 4

Printed on Thu Oct 15, 2026 at 12:46 pm MDT Job #: 8735 BVSD - Eisenhower ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction

Number

Description

Revision

Issued Date

Received Date

Set

22 0553

IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT

0

26.08.28 - CD's

22 0700

PLUMBING INSULATION

0

26.08.28 - CD's

22 1023

PLUMBING PUMPS

0

26.08.28 - CD's

22 1116

DOMESTIC WATER PIPING

0

26.08.28 - CD's

22 1119

DOMESTIC WATER PIPING SPECIALITIES

0

26.08.28 - CD's

22 1123

FACILITY NATURAL GAS PIPING

0

26.08.28 - CD's

22 3000

WATER HEATERS

0

26.08.28 - CD's

23 - Heating, Ventilating, and Air Conditioning (HVAC) 23 0500

COMMON WORK RESULTS FOR MECHANICAL

0

26.08.28 - CD's

23 0507

MOTORS, DRIVES, MOTOR CONTROLLERS AND ELECTRICAL REQUIRED FOR

0

26.08.28 - CD's

23 0510

BASIC PIPING MATERIALS AND METHODS

0

26.08.28 - CD's

23 0518

PIPING SPECIALITIES

0

26.08.28 - CD's

23 0519

METERS AND GAUGES FOR MECHANCIAL PIPING

0

26.08.28 - CD's

23 0523

GENERAL DUTY VALVES FOR MECHANICAL PIPING

0

26.08.28 - CD's

23 0529

HANGERS AND SUPPORTS FOR MECHANICAL SYSTEMS

0

26.08.28 - CD's

23 0540

VIBRATION CONTROL FOR MECHANICAL PIPING AND EQUIPMENT

0

26.08.28 - CD's

23 0553

IDENTIFICATION FOR MECHANICAL SYSTEMS

0

26.08.28 - CD's

23 0593

TESTING, ADJUSTING, AND BALANCING FOR MECHANICAL

0

26.08.28 - CD's

23 0700

INSULATION FOR MECHANICAL SYSTEMS

0

26.08.28 - CD's

23 0900

INSTRUMENTATION AND CONTROL FOR MECHANICAL SYSTEMS

0

26.08.28 - CD's

23 0993

SEQUENCES OF OPERATION FOR MECHANICAL SYSTEMS

0

26.08.28 - CD's

23 3113

METAL DUCTS

0

26.08.28 - CD's

23 3300

AIR DUCT ACCESSORIES

0

26.08.28 - CD's

23 3600

AIR TERMINAL UNITS

0

26.08.28 - CD's

23 3713

DIFFUSERS, REGISTERS, GRILLES

0

26.08.28 - CD's

23 7443

ROOFTOP HEATING AND COOLING UNITS

0

26.08.28 - CD's

23 8000

DECENTRALIZED HVAC EQUIPMENT

0

26.08.28 - CD's

23 8126

DUCTLESS SPLIT SYSTEMS

0

26.08.28 - CD's

26 0500

COMMON WORK RESULTS FOR ELECTRICAL

0

26.08.28 - CD's

26 0519

LOW VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

0

26.08.28 - CD's

26 0529

HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

0

26.08.28 - CD's

26 0533

RACEWAY AND WIREWAY FOR ELECTRICAL SYSTEMS

0

26.08.28 - CD's

26 0534

CABINETS, BOXES, AND FITTINGS

0

26.08.28 - CD's

26 0553

IDENTIFICATION FOR ELECTRICAL SYSTEMS

0

26.08.28 - CD's

26 0583

WIRING CONNECTIONS

0

26.08.28 - CD's

26 0923

LIGHTING CONTROL DEVICES

0

26.08.28 - CD's

26 2726

LOW VOLTAGE CIRCUIT PROTECTIVE DEVICES

0

26.08.28 - CD's

26 2800

Low-Voltage Circuit Protective Devices

0

26.08.28 - CD's

26 5000

LIGHTING

0

26.08.28 - CD's

26 5200

EMERGENCY LIGHTING

0

26.08.28 - CD's

26 - Electrical

Page 3 of 4

Printed on Thu Oct 15, 2026 at 12:46 pm MDT Job #: 8735 BVSD - Eisenhower ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction

Number

Description

Revision

Issued Date

Received Date

Set

27 - Communications 27 0500

COMMON WORK RESULTS FOR COMMUNICATIONS

0

26.08.28 - CD's

27 0528

PATHWAYS FOR COMMUNICATION SYSTEMS

0

26.08.28 - CD's

27 5123

INTERCOMMUNCATIONS AND PROGRAM SYSTEMS

0

26.08.28 - CD's

0

26.08.28 - CD's

0

26.08.28 - CD's

28 - Electronic Safety and Security 28 3111

FIRE DETECTION AND ALARM

32 - Exterior Improvements 32 1313

CONCRETE PAVING

Page 4 of 4

797 Ventura Street, Aurora, CO 80011 Project: K1225 - BVSD - Eisenhower ES Renovations Owner: BVSD Architect: RTA

Date: Estimator: Project SF: Duration in Months: Estimate #:

10/19/26 Rakshita 59,000 3.00 CD Estimate R1

Project Summary Sheet - Estimated Cost of the Work

Division #0 Division #1 Division #2 Division #3 Division #4 Division #5 Division #6 Division #7 Division #8 Division #9 Division #10 Division #11 Division #12 Division #13 Division #14 Division #21 Division #22 Division #23 Division #25 Division #26 Division #27 Division #28 Division #31 Division #32 Division #33

Procurement and Contracting Requirements General Requirements Existing Conditions Concrete Masonry Metals Wood, Plastics, and Composites Thermal and Moisture Protection Openings Finishes Specialties Equipment Furnishings Special Construction Conveying Equipment Fire Suppression Plumbing Heating, Ventilating and Air Conditioning Integrated Automation Electrical Communications Electronic Safety and Security Earthwork Exterior Improvements Utilities

DD Estimate CD Estimate Difference $103,344 $87,058 ($16,286) $379,492 $354,921 ($24,571) $41,048 $24,845 ($16,203) $26,897 $6,947 ($19,950) $25,423 $4,000 ($21,423) $3,047 $15,086 $12,040 $74,968 $68,317 ($6,651) $35,399 $22,536 ($12,863) $81,257 $79,125 ($2,132) $226,561 $140,615 ($85,946) $12,305 $12,046 ($259) $0 $0 $0 $0 $1,900 $1,900 $0 $0 $0 $0 $0 $0 $0 $30,900 $30,900 $109,128 $0 ($109,128) $491,637 $732,210 $240,573 $0 $0 $0 $497,859 $505,571 $7,712 $272,557 $164,820 ($107,737) $0 $0 $0 $6,467 $4,700 ($1,767) $60,041 $55,925 ($4,116) 0 $0 $0

$1.48

/SF

3.8% of Direct Costs

$6.02

/SF

15.4% of Direct Costs

$0.42

/SF

1.1% of Direct Costs

$0.12

/SF

0.3% of Direct Costs

$0.07

/SF

0.2% of Direct Costs

$0.26

/SF

0.7% of Direct Costs

$1.16

/SF

3.0% of Direct Costs

$0.38

/SF

1.0% of Direct Costs

$1.34

/SF

3.4% of Direct Costs

$2.38

/SF

6.1% of Direct Costs

$0.20

/SF

0.5% of Direct Costs

$0.00

/SF

0.0% of Direct Costs

$0.03

/SF

0.1% of Direct Costs

$0.00

/SF

0.0% of Direct Costs

$0.00

/SF

0.0% of Direct Costs

$0.52

/SF

1.3% of Direct Costs

$0.00

/SF

0.0% of Direct Costs

$12.41

/SF

31.7% of Direct Costs

$0.00

/SF

0.0% of Direct Costs

$8.57

/SF

21.9% of Direct Costs

$2.79

/SF

7.1% of Direct Costs

$0.00

/SF

0.0% of Direct Costs

$0.08

/SF

0.2% of Direct Costs

$0.95

/SF

2.4% of Direct Costs

$0.00

/SF

0.0% of Direct Costs

100.0% of Direct Costs

Subtotal

$2,447,429

$2,311,523

($135,906)

$39.18

/SF

Utility Tap & Devel. Fees Permit Allowance Use Tax Construction Contingency Builders Risk Insurance Comprehensive General Liability Insurance Performance and Payment Bond Escalation Allowance Contractors Fee Preconstruction Services

$0 $0 $0 $195,794 $5,286 $31,719 $17,974 $0 $124,231 $17,500

$0 $0 $0 $77,263 $4,623 $30,905 $17,513 $0 $116,095 $17,500

$0 $0 $0 ($118,532) ($663) ($814) ($461) $0 ($8,137) $0

$0.00

/SF

$0.00

/SF

0.00% of Project

$0.00

/SF

0.00% of Project

$1.31

/SF

3.00% of Project

$0.08

/SF

20.00% of Costs

$0.52

/SF

1.20% of Project

$0.30

/SF

0.68% of Project

$0.00

/SF

0.00% of Project

$1.97

/SF

4.86% of Project

$0.30

/SF

Origianl Contract Amount

$2,575,421

($264,512)

$72.43

/SF

100.0% of Project

Estimated Cost of Construction

CD Estimate R1

$2,839,933

Accepted Alternates A2 : New Flooring in Gymnasium

$153,091

V14 : Lighting Fixtures - Interior - Fluorescent Renewal Priority 1

$286,559

V14 : Lighting Fixtures - Interior - Fluorescent Renewal Priority 2

$38,743

V14 : Lighting Fixtures - Interior - Fluorescent Renewal Priority 3

$238,651

V14 : Lighting Fixtures - Interior - Fluorescent Renewal Priority 4

$62,268

CD w/ Accepted Alternates Original Contract Amount fGMP Amendment New Contract Total

$3,354,733 $ $

17,500.00 $3,337,233 3,354,733

Line

Name

Duration

Start

Finish

BVSD Eisenhower ES

554d

8/1/2025

10/8/2027

Milestones

527d

8/1/2025

8/31/2027

School Milestones

455d

8/1/2025

5/20/2027 8/13/2025 A

1

Summer Break - 2025 (School Back In Session)

9d 8/1/2025 A

2

Thankgiving Break - 2025

3d 11/24/2025 A 11/26/2025 A

3

Winter Break - 2025

8d 12/23/2025 A 1/6/2026 A

4

Spring Break - 2026

5d 3/4/2026 A

3/10/2026 A

5

Summer Break - 2026

73d 6/1/2026 A

9/11/2026 A

6

Thankgiving Break - 2026

3d 11/23/2026

11/25/2026

7

Winter Break - 2026

10d 12/21/2026

1/6/2027

8

Spring Break - 2027

5d 3/15/2027

3/19/2027

9

Summer Break - 2027 - START

5/20/2027

5/20/2027

Project Milestones

280d 10/15/2025 11/20/2026

Preconstruction Milestones

280d 10/15/2025 11/20/2026

10/15/2025 A 10/15/2025 A

2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9

Summer Break - 2025 (School Back In Session)

Thankgiving Break - 2025

Winter Break - 2025

Spring Break - 2026

Summer Break - 2026

Thankgiving Break - 2026

Winter Break - 2026

Spring Break - 2027

Summer Break - 2027 - START

10

Notice to Proceed

11

DAT Meetings

12

Post-Award Meetings

13

DAT Meetings - Finals

70d 8/3/2026 A

11/20/2026

Construction Milestones

461d 11/4/2025

8/31/2027

14

Early Investigations

259d 11/4/2025 A

6/30/2027

15

Mobilization Start

3/16/2027

3/16/2027

16

Abatement Start

5/11/2027

5/11/2027

Abatement Start

17

Demo Start

5/21/2027

5/21/2027

Demo Start

18

Abatement Finish

5/24/2027

5/24/2027

Abatement Finish

19

Demo Finish

5/27/2027

5/27/2027

Demo Finish

20

Rough-in Start

5/28/2027

5/28/2027

Rough-in Start

21

Rough-in Finish

7/8/2027

7/8/2027

Rough-in Finish

22

TCO

7/30/2027

7/30/2027

TCO

23

Owner Move-in Complete

8/9/2027

8/9/2027

Owner Move-in Complete

24

Substantial Completion

8/31/2027

8/31/2027

Notice to Proceed

105d 12/1/2025 A 7/30/2026 A

12/15/2025 A 12/15/2025 A

BVSD Eisenhower ES Master Schedule Boulder Valley School District

DAT Meetings

Post-Award Meetings

DAT Meetings - Finals

Early Investigations

Mobilization Start

Substantial Completion

Job #: BVSD Eisenhower ES

Rev. date: 10/19/2026 12:02:53 PM

Data Date: 10/14/2026

Page 1 of 17

BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks

Line

Name

Duration

Start

Finish

2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9

Preconstruction & Design

441d 8/28/2025

5/26/2027

RFP / RFQ Information

37d 8/28/2025 10/21/2025

25

RFP/RFQ - Issuance of RFP

8/28/2025 A 8/28/2025 A

26

RFP/RFQ - Pre-Proposal Submission

9/8/2025 A

27

RFP/RFQ - Inquiries Due

9/12/2025 A 9/12/2025 A

RFP/RFQ - Inquiries Due

28

RFP/RFQ - Addendum's

9/18/2025 A 9/18/2025 A

RFP/RFQ - Addendum's

29

RFP/RFQ - Submission Deadline

9/25/2025 A 9/25/2025 A

RFP/RFQ - Submission Deadline

30

RFP/RFQ - Evaluation / Award

10/7/2025 A 10/7/2025 A

RFP/RFQ - Evaluation / Award

31

Notice of Award

10/21/2025 A 10/21/2025 A

9/8/2025 A

RFP/RFQ - Issuance of RFP

RFP/RFQ - Pre-Proposal Submission

Notice of Award

Document Development

259d 10/21/2025 10/28/2026

Programming / DAT

239d 10/21/2025 9/30/2026

32

Program - Electrical Upgrades (Design & Precon / Estimating Services/Deliverables)

131d 10/21/2025 A 9/30/2026 A

Program - Electrical Upgrades (Design & Precon / Estimating Services/Deliverables)

33

Program - Mechanical Upgrades (Design & Precon / Estimating Services/Deliverables)

131d 10/21/2025 A 9/30/2026 A

Program - Mechanical Upgrades (Design & Precon / Estimating Services/Deliverables)

34

Program - Roofing Upgrades (Design & Precon / Estimating Services/Deliverables)

131d 10/21/2025 A 9/30/2026 A

Program - Roofing Upgrades (Design & Precon / Estimating Services/Deliverables)

Schematic Design

24d 2/20/2026

35

SD - Drawings 100% (Design & Precon / Estimating Services/Deliverables)

1d 2/20/2026 A 2/20/2026 A

36

SD - Cost Estimating & Constructability Review

10d 3/2/2026 A

37

SD - Estimate Review

8d 3/16/2026 A 3/25/2026 A

SD - Estimate Review

38

Alternates - Parking Lot Resurface, Gym Floor

1d 3/23/2026 A 3/23/2026 A

Alternates - Parking Lot Resurface, Gym Floor

Design Development

84d 2/20/2026

39

DD - Drawings 100% (Design & Precon / Estimating Services/Deliverables)

61d 2/20/2026 A 5/15/2026 A

40

DD - Cost Estimating & Constructability Review

10d 5/15/2026 A 5/29/2026 A

41

DD - Estimate Review

14d 6/1/2026 A

42

Establish IGMP

1d 6/18/2026 A 6/18/2026 A

Construction Documents

3/25/2026

3/13/2026 A

SD - Drawings 100% (Design & Precon / Estimating Services/Deliverables)

SD - Cost Estimating & Constructability Review

6/18/2026

6/18/2026 A

DD - Drawings 100% (Design & Precon / Estimating Services/Deliverables)

DD - Cost Estimating & Constructability Review

DD - Estimate Review

Establish IGMP

116d 5/15/2026 10/28/2026

43

CD - Drawings 100% (Design & Precon / Estimating Services/Deliverables/GMP)

74d 5/15/2026 A 8/28/2026 A

44

CD - Cost Estimating & Constructability Review

10d 8/28/2026 A 9/11/2026 A

45

CD - Estimate Review

19d 9/11/2026 A 10/7/2026 A

CD - Estimate Review

46

Alternates A2 Gym Floor / Lighting V14 1-4 Priorities Accepted

1d 10/14/2026

10/14/2026

Alternates A2 Gym Floor / Lighting V14 1-4 Priorities Accepted

47

Establish FGMP / After Board Meeting

10/28/2026

10/28/2026

BVSD Eisenhower ES Master Schedule Boulder Valley School District

CD - Drawings 100% (Design & Precon / Estimating Services/Deliverables/GMP)

CD - Cost Estimating & Constructability Review

Establish FGMP / After Board Meeting

Job #: BVSD Eisenhower ES

Rev. date: 10/19/2026 12:02:53 PM

Data Date: 10/14/2026

Page 2 of 17

BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks

Line

Name

Duration

Permitting

Start

Finish

113d 8/28/2026

2/10/2027

2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9

48

Permit - Submit to State

28d 8/28/2026 A

11/2/2026

49

Permit - Building (In Hand)

40d 11/3/2026

1/4/2027

50

Permit - Electrical Submit to Dora

40d 11/12/2026

1/13/2027

Permit - Electrical Submit to Dora

51

Permit - Plumbing Submit to Dora

40d 11/12/2026

1/13/2027

Permit - Plumbing Submit to Dora

52

Permit - Alternate - Fire Alarm Submit

20d 11/12/2026

12/11/2026

53

Permit - Alternate - Fire Alarm (In Hand)

40d 12/14/2026

2/10/2027

Permit - Alternate - Fire Alarm (In Hand)

54

Permit - Electrical (In Hand)

20d 1/14/2027

2/10/2027

Permit - Electrical (In Hand)

55

Permit - Plumbing (In Hand)

20d 1/14/2027

2/10/2027

Permit - Plumbing (In Hand)

Contracting & Award

10d 10/29/2026 11/11/2026

Award Trade Partners First Round

5d 10/29/2026 11/4/2026

56

Div - 22 - Plumbing

5d 10/29/2026

11/4/2026

Div - 22 - Plumbing

57

Div - 23 - HVAC

5d 10/29/2026

11/4/2026

Div - 23 - HVAC

58

Div - 26 - Electrical

5d 10/29/2026

11/4/2026

Div - 26 - Electrical

59

Div - 28 - FA Security

5d 10/29/2026

11/4/2026

Div - 28 - FA Security

Permit - Submit to State

Permit - Building (In Hand)

Permit - Alternate - Fire Alarm Submit

Award Trade Partners Second Round

10d 10/29/2026 11/11/2026

60

Div - 02 - Demo

10d 10/29/2026

11/11/2026

Div - 02 - Demo

61

Div - 03 - Concrete

10d 10/29/2026

11/11/2026

Div - 03 - Concrete

62

Div - 04 - Masonry

10d 10/29/2026

11/11/2026

Div - 04 - Masonry

63

Div - 05 - Metal

10d 10/29/2026

11/11/2026

Div - 05 - Metal

64

Div - 07 - Thermal Moisture Prot. (Roofing)

10d 10/29/2026

11/11/2026

Div - 07 - Thermal Moisture Prot. (Roofing)

65

Div - 08 - Openings (Door & Frames & Hardware)

10d 10/29/2026

11/11/2026

Div - 08 - Openings (Door & Frames & Hardware)

66

Div - 09 - Finishes (Drywall & Paint, ACT)

10d 10/29/2026

11/11/2026

Div - 09 - Finishes (Drywall & Paint, ACT)

67

Div - 32 - Ext Imp

10d 10/29/2026

11/11/2026

Div - 32 - Ext Imp

Submittals & Procurement

140d 11/5/2026

5/26/2027

Division 02 - DEMO

50d 11/12/2026 1/27/2027

68

S&P - Div 02 (Div 02 - Contractor Prepare/Submit Shop Drawings)

10d 11/12/2026

11/25/2026

S&P - Div 02 (Div 02 - Contractor Prepare/Submit Shop Drawings)

69

S&P - AP Review (Div 02 - AP Review/Submit Shop Drawings)

10d 11/30/2026

12/11/2026

S&P - AP Review (Div 02 - AP Review/Submit Shop Drawings)

70

S&P - A&E Review (Div 02 - Owner Review/Approve Shop Drawings)

10d 12/14/2026

12/29/2026

71

S&P - Procurement (Div 02 - Fabricate/Deliver)

20d 12/30/2026

1/27/2027

BVSD Eisenhower ES Master Schedule Boulder Valley School District

S&P - A&E Review (Div 02 - Owner Review/Approve Shop Drawings)

S&P - Procurement (Div 02 - Fabricate/Deliver)

Job #: BVSD Eisenhower ES

Rev. date: 10/19/2026 12:02:53 PM

Data Date: 10/14/2026

Page 3 of 17

BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks

Line

Name

Duration

Start

Finish

2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9

Division 03 - CONCRETE

55d 11/12/2026

2/3/2027

72

S&P - Concrete Rebar - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Concrete Rebar - Subcontractor Submit

73

S&P - Cast-In-Place Concrete - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Cast-In-Place Concrete - Subcontractor Submit

74

S&P - Concrete Rebar - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Concrete Rebar - AP Review/Submit

75

S&P - Cast-In-Place Concrete - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Cast-In-Place Concrete - AP Review/Submit

76

S&P - Concrete Rebar - A&E Review

10d 12/14/2026

12/29/2026

S&P - Concrete Rebar - A&E Review

77

S&P - Cast-In-Place Concrete - A&E Review

10d 12/14/2026

12/29/2026

S&P - Cast-In-Place Concrete - A&E Review

78

S&P - Concrete Rebar Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Concrete Rebar Procurement/Fabricate/Deliver

79

S&P - Cast-In-Place Concrete Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Cast-In-Place Concrete Procurement/Fabricate/Deliver

Division 04 - MASONRY

55d 11/12/2026

2/3/2027

80

S&P - Masonry Mortar and Grout - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Masonry Mortar and Grout - Subcontractor Submit

81

S&P - Unit Masonry / Monument Sign- Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Unit Masonry / Monument Sign- Subcontractor Submit

82

S&P - Masonry Mortar and Grout - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Masonry Mortar and Grout - AP Review/Submit

83

S&P - Unit Masonry / Monument Sign- AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Unit Masonry / Monument Sign- AP Review/Submit

84

S&P - Masonry Mortar and Grout - A&E Review

10d 12/14/2026

12/29/2026

S&P - Masonry Mortar and Grout - A&E Review

85

S&P - Unit Masonry / Monument Sign- A&E Review

10d 12/14/2026

12/29/2026

S&P - Unit Masonry / Monument Sign- A&E Review

86

S&P - Masonry Mortar and Grout Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Masonry Mortar and Grout Procurement/Fabricate/Deliver

87

S&P - Unit Masonry / Monument SignProcurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Unit Masonry / Monument SignProcurement/Fabricate/Deliver

Division 05 - METALS

55d 11/12/2026

2/3/2027

88

S&P - Cold-formed metal framing - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Cold-formed metal framing - Subcontractor Submit

89

S&P - Metal Ladders / Safety Posts - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Metal Ladders / Safety Posts - Subcontractor Submit

90

S&P - Cold-formed metal framing - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Cold-formed metal framing - AP Review/Submit

91

S&P - Metal Ladders / Safety Posts - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Metal Ladders / Safety Posts - AP Review/Submit

92

S&P - Cold-formed metal framing - A&E Review

10d 12/14/2026

12/29/2026

S&P - Cold-formed metal framing - A&E Review

93

S&P - Metal Ladders / Safety Posts - A&E Review

10d 12/14/2026

12/29/2026

S&P - Metal Ladders / Safety Posts - A&E Review

94

S&P - Cold-formed metal framing Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Cold-formed metal framing Procurement/Fabricate/Deliver

95

S&P - Metal Ladders / Safety Posts Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Metal Ladders / Safety Posts Procurement/Fabricate/Deliver

Division 06 - WOOD PLASTICS COMPOSITES

55d 11/12/2026

2/3/2027

96

S&P - Rough Carpentry - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Rough Carpentry - Subcontractor Submit

97

S&P - Rough Carpentry - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Rough Carpentry - AP Review/Submit

BVSD Eisenhower ES Master Schedule Boulder Valley School District

Job #: BVSD Eisenhower ES

Rev. date: 10/19/2026 12:02:53 PM

Data Date: 10/14/2026

Page 4 of 17

BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks

Duration

Start

Finish

2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9

Line

Name

98

S&P - Rough Carpentry - A&E Review

10d 12/14/2026

12/29/2026

99

S&P - Rough Carpentry Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

Division 07 - THERMAL MOISTURE PROTECTION

55d 11/12/2026

2/3/2027

100

S&P - Thermal Insulation - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Thermal Insulation - Subcontractor Submit

101

S&P - Weather Barriers - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Weather Barriers - Subcontractor Submit

102

S&P - Metal Wall Panels - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Metal Wall Panels - Subcontractor Submit

103

S&P - Sheet-Metal Flashing And Trim - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Sheet-Metal Flashing And Trim - Subcontractor Submit

104

S&P - Joint Sealants - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Joint Sealants - Subcontractor Submit

105

S&P - Thermal Insulation - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Thermal Insulation - AP Review/Submit

106

S&P - Weather Barriers - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Weather Barriers - AP Review/Submit

107

S&P - Metal Wall Panels - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Metal Wall Panels - AP Review/Submit

108

S&P - Sheet-Metal Flashing And Trim - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Sheet-Metal Flashing And Trim - AP Review/Submit

109

S&P - Joint Sealants - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Joint Sealants - AP Review/Submit

110

S&P - Thermal Insulation - A&E Review

10d 12/14/2026

12/29/2026

S&P - Thermal Insulation - A&E Review

111

S&P - Weather Barriers - A&E Review

10d 12/14/2026

12/29/2026

S&P - Weather Barriers - A&E Review

112

S&P - Metal Wall Panels - A&E Review

10d 12/14/2026

12/29/2026

S&P - Metal Wall Panels - A&E Review

113

S&P - Sheet-Metal Flashing And Trim - A&E Review

10d 12/14/2026

12/29/2026

S&P - Sheet-Metal Flashing And Trim - A&E Review

114

S&P - Joint Sealants - A&E Review

10d 12/14/2026

12/29/2026

S&P - Joint Sealants - A&E Review

115

S&P - Thermal Insulation Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Thermal Insulation Procurement/Fabricate/Deliver

116

S&P - Weather Barriers Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Weather Barriers Procurement/Fabricate/Deliver

117

S&P - Metal Wall Panels Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Metal Wall Panels Procurement/Fabricate/Deliver

118

S&P - Sheet-Metal Flashing And Trim Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Sheet-Metal Flashing And Trim Procurement/Fabricate/Deliver

119

S&P - Joint Sealants Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Joint Sealants Procurement/Fabricate/Deliver

Division 08 - OPENINGS

55d 11/12/2026

2/3/2027

120

S&P - Hollow-Metal Doors and Frames - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Hollow-Metal Doors and Frames - Subcontractor Submit

121

S&P - Flush Wood Doors - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Flush Wood Doors - Subcontractor Submit

122

S&P - Aluminum Storefronts - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Aluminum Storefronts - Subcontractor Submit

123

S&P - Glazing - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Glazing - Subcontractor Submit

124

S&P - Louvers - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Louvers - Subcontractor Submit

125

S&P - Hollow-Metal Doors and Frames - AP Review/Submit

10d 11/30/2026

12/11/2026

BVSD Eisenhower ES Master Schedule Boulder Valley School District

S&P - Rough Carpentry - A&E Review

S&P - Rough Carpentry Procurement/Fabricate/Deliver

S&P - Hollow-Metal Doors and Frames - AP Review/Submit

Job #: BVSD Eisenhower ES

Rev. date: 10/19/2026 12:02:53 PM

Data Date: 10/14/2026

Page 5 of 17

BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks

Line

Name

Duration

Start

Finish

2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9

126

S&P - Flush Wood Doors - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Flush Wood Doors - AP Review/Submit

127

S&P - Aluminum Storefronts - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Aluminum Storefronts - AP Review/Submit

128

S&P - Glazing - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Glazing - AP Review/Submit

129

S&P - Louvers - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Louvers - AP Review/Submit

130

S&P - Hollow-Metal Doors and Frames - A&E Review

10d 12/14/2026

12/29/2026

S&P - Hollow-Metal Doors and Frames - A&E Review

131

S&P - Flush Wood Doors - A&E Review

10d 12/14/2026

12/29/2026

S&P - Flush Wood Doors - A&E Review

132

S&P - Aluminum Storefronts - A&E Review

10d 12/14/2026

12/29/2026

S&P - Aluminum Storefronts - A&E Review

133

S&P - Glazing - A&E Review

10d 12/14/2026

12/29/2026

S&P - Glazing - A&E Review

134

S&P - Louvers - A&E Review

10d 12/14/2026

12/29/2026

S&P - Louvers - A&E Review

135

S&P - Hollow-Metal Doors and Frames Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Hollow-Metal Doors and Frames Procurement/Fabricate/Deliver

136

S&P - Flush Wood Doors Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Flush Wood Doors Procurement/Fabricate/Deliver

137

S&P - Aluminum Storefronts Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Aluminum Storefronts Procurement/Fabricate/Deliver

138

S&P - Glazing Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Glazing Procurement/Fabricate/Deliver

139

S&P - Louvers Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Louvers Procurement/Fabricate/Deliver

Division 09 - FINISHES

55d 11/12/2026

2/3/2027

140

S&P - Gyp Board Assemblies - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Gyp Board Assemblies - Subcontractor Submit

141

S&P - Acoustical Ceilings - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Acoustical Ceilings - Subcontractor Submit

142

S&P - Wood Athletic Flooring - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Wood Athletic Flooring - Subcontractor Submit

143

S&P - Resilient Flooring - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Resilient Flooring - Subcontractor Submit

144

S&P - Tile Carpeting - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Tile Carpeting - Subcontractor Submit

145

S&P - Exterior & Interior Painting - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Exterior & Interior Painting - Subcontractor Submit

146

S&P - Gyp Board Assemblies - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Gyp Board Assemblies - AP Review/Submit

147

S&P - Acoustical Ceilings - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Acoustical Ceilings - AP Review/Submit

148

S&P - Wood Athletic Flooring - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Wood Athletic Flooring - AP Review/Submit

149

S&P - Resilient Flooring - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Resilient Flooring - AP Review/Submit

150

S&P - Tile Carpeting - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Tile Carpeting - AP Review/Submit

151

S&P - Exterior & Interior Painting - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Exterior & Interior Painting - AP Review/Submit

152

S&P - Gyp Board Assemblies - A&E Review

10d 12/14/2026

12/29/2026

S&P - Gyp Board Assemblies - A&E Review

153

S&P - Acoustical Ceilings - A&E Review

10d 12/14/2026

12/29/2026

S&P - Acoustical Ceilings - A&E Review

154

S&P - Wood Athletic Flooring - A&E Review

10d 12/14/2026

12/29/2026

S&P - Wood Athletic Flooring - A&E Review

BVSD Eisenhower ES Master Schedule Boulder Valley School District

Job #: BVSD Eisenhower ES

Rev. date: 10/19/2026 12:02:53 PM

Data Date: 10/14/2026

Page 6 of 17

BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks

Duration

Start

Finish

2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9

Line

Name

155

S&P - Resilient Flooring - A&E Review

10d 12/14/2026

12/29/2026

S&P - Resilient Flooring - A&E Review

156

S&P - Tile Carpeting - A&E Review

10d 12/14/2026

12/29/2026

S&P - Tile Carpeting - A&E Review

157

S&P - Exterior & Interior Painting - A&E Review

10d 12/14/2026

12/29/2026

S&P - Exterior & Interior Painting - A&E Review

158

S&P - Gyp Board Assemblies Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Gyp Board Assemblies Procurement/Fabricate/Deliver

159

S&P - Acoustical Ceilings Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Acoustical Ceilings Procurement/Fabricate/Deliver

160

S&P - Wood Athletic Flooring Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Wood Athletic Flooring Procurement/Fabricate/Deliver

161

S&P - Resilient Flooring Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Resilient Flooring Procurement/Fabricate/Deliver

162

S&P - Tile Carpeting Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Tile Carpeting Procurement/Fabricate/Deliver

163

S&P - Exterior & Interior Painting Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Exterior & Interior Painting Procurement/Fabricate/Deliver

Division 10 - Specialties

55d 11/12/2026

2/3/2027

164

S&P - Visual Display Units - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Visual Display Units - Subcontractor Submit

165

S&P - Signage - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Signage - Subcontractor Submit

166

S&P - Wall and Door Protection - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Wall and Door Protection - Subcontractor Submit

167

S&P - Visual Display Units - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Visual Display Units - AP Review/Submit

168

S&P - Signage - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Signage - AP Review/Submit

169

S&P - Wall and Door Protection - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Wall and Door Protection - AP Review/Submit

170

S&P - Visual Display Units - A&E Review

10d 12/14/2026

12/29/2026

S&P - Visual Display Units - A&E Review

171

S&P - Signage - A&E Review

10d 12/14/2026

12/29/2026

S&P - Signage - A&E Review

172

S&P - Wall and Door Protection - A&E Review

10d 12/14/2026

12/29/2026

S&P - Wall and Door Protection - A&E Review

173

S&P - Visual Display Units Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Visual Display Units Procurement/Fabricate/Deliver

174

S&P - Signage Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Signage Procurement/Fabricate/Deliver

175

S&P - Wall and Door Protection Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Wall and Door Protection Procurement/Fabricate/Deliver

Division 12 - Furnishing

55d 11/12/2026

2/3/2027

176

S&P - Manufactured Wood Casework - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Manufactured Wood Casework - Subcontractor Submit

177

S&P - Manufactured Wood Casework - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Manufactured Wood Casework - AP Review/Submit

178

S&P - Manufactured Wood Casework - A&E Review

10d 12/14/2026

12/29/2026

S&P - Manufactured Wood Casework - A&E Review

179

S&P - Manufactured Wood Casework Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

Division 22 - PLUMBING

55d 11/5/2026

1/27/2027

180

S&P - Plumbing Valves - Subcontractor Submit

10d 11/5/2026

11/18/2026

S&P - Plumbing Valves - Subcontractor Submit

181

S&P - Plumbing Insulation - Subcontractor Submit

10d 11/5/2026

11/18/2026

S&P - Plumbing Insulation - Subcontractor Submit

BVSD Eisenhower ES Master Schedule Boulder Valley School District

S&P - Manufactured Wood Casework Procurement/Fabricate/Deliver

Job #: BVSD Eisenhower ES

Rev. date: 10/19/2026 12:02:53 PM

Data Date: 10/14/2026

Page 7 of 17

BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks

Line

Name

Duration

Start

Finish

2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9

182

S&P - Domestic-Water Piping - Subcontractor Submit

10d 11/5/2026

11/18/2026

S&P - Domestic-Water Piping - Subcontractor Submit

183

S&P - Domestic-Water Specialties - Subcontractor Submit

10d 11/5/2026

11/18/2026

S&P - Domestic-Water Specialties - Subcontractor Submit

184

S&P - Div 22 (Div 22 - Contractor Prepare/Submit Shop Drawings)

10d 11/5/2026

11/18/2026

S&P - Div 22 (Div 22 - Contractor Prepare/Submit Shop Drawings)

185

S&P - Unit Heater (Div 22 - Contractor Prepare/Submit Shop Drawings)

10d 11/5/2026

11/18/2026

S&P - Unit Heater (Div 22 - Contractor Prepare/Submit Shop Drawings)

186

S&P - Plumbing Valves - AP Review/Submit

10d 11/19/2026

12/4/2026

S&P - Plumbing Valves - AP Review/Submit

187

S&P - Plumbing Insulation - AP Review/Submit

10d 11/19/2026

12/4/2026

S&P - Plumbing Insulation - AP Review/Submit

188

S&P - Domestic-Water Piping - AP Review/Submit

10d 11/19/2026

12/4/2026

S&P - Domestic-Water Piping - AP Review/Submit

189

S&P - Domestic-Water Specialties - AP Review/Submit

10d 11/19/2026

12/4/2026

S&P - Domestic-Water Specialties - AP Review/Submit

190

S&P - AP Review (Div 22 - AP Review/Submit Shop Drawings)

10d 11/19/2026

12/4/2026

S&P - AP Review (Div 22 - AP Review/Submit Shop Drawings)

191

S&P - AP Review (Div 22 - AP Review/Submit Shop Drawings)

10d 11/19/2026

12/4/2026

S&P - AP Review (Div 22 - AP Review/Submit Shop Drawings)

192

S&P - Plumbing Valves - A&E Review

10d 12/7/2026

12/18/2026

S&P - Plumbing Valves - A&E Review

193

S&P - Plumbing Insulation - A&E Review

10d 12/7/2026

12/18/2026

S&P - Plumbing Insulation - A&E Review

194

S&P - Domestic-Water Piping - A&E Review

10d 12/7/2026

12/18/2026

S&P - Domestic-Water Piping - A&E Review

195

S&P - Domestic-Water Specialties - A&E Review

10d 12/7/2026

12/18/2026

S&P - Domestic-Water Specialties - A&E Review

196

S&P - A&E Review (Div 22 - Owner Review/Approve Shop Drawings)

10d 12/7/2026

12/18/2026

S&P - A&E Review (Div 22 - Owner Review/Approve Shop Drawings)

197

S&P - A&E Review (Div 22 - Owner Review/Approve Shop Drawings)

10d 12/7/2026

12/18/2026

S&P - A&E Review (Div 22 - Owner Review/Approve Shop Drawings)

198

S&P - Plumbing Valves Procurement/Fabricate/Deliver

25d 12/21/2026

1/27/2027

S&P - Plumbing Valves Procurement/Fabricate/Deliver

199

S&P - Plumbing Insulation Procurement/Fabricate/Deliver

25d 12/21/2026

1/27/2027

S&P - Plumbing Insulation Procurement/Fabricate/Deliver

200

S&P - Domestic-Water Piping Procurement/Fabricate/Deliver

25d 12/21/2026

1/27/2027

S&P - Domestic-Water Piping Procurement/Fabricate/Deliver

201

S&P - Domestic-Water Specialties Procurement/Fabricate/Deliver

25d 12/21/2026

1/27/2027

S&P - Domestic-Water Specialties Procurement/Fabricate/Deliver

202

S&P - Procurement (Div 22 - Fabricate/Deliver)

25d 12/21/2026

1/27/2027

S&P - Procurement (Div 22 - Fabricate/Deliver)

203

S&P - Unit Heater Procurement (Div 22 - Fabricate/Deliver)

25d 12/21/2026

1/27/2027

S&P - Unit Heater Procurement (Div 22 - Fabricate/Deliver)

140d 11/5/2026

5/26/2027

Division 23 - HVAC 204

S&P - Motors / VFD / Starters - Subcontractor Submit

10d 11/5/2026

11/18/2026

S&P - Motors / VFD / Starters - Subcontractor Submit

205

S&P - Mechanical Piping - Subcontractor Submit

10d 11/5/2026

11/18/2026

S&P - Mechanical Piping - Subcontractor Submit

206

S&P - Piping Specialties - Subcontractor Submit

10d 11/5/2026

11/18/2026

S&P - Piping Specialties - Subcontractor Submit

207

S&P - Hangers / Supports - Subcontractor Submit

10d 11/5/2026

11/18/2026

S&P - Hangers / Supports - Subcontractor Submit

208

S&P - Metal Ducts - Subcontractor Submit

10d 11/5/2026

11/18/2026

S&P - Metal Ducts - Subcontractor Submit

209

S&P - Duct Accessories - Subcontractor Submit

10d 11/5/2026

11/18/2026

S&P - Duct Accessories - Subcontractor Submit

210

S&P - Air Terminal Units - Subcontractor Submit

10d 11/5/2026

11/18/2026

S&P - Air Terminal Units - Subcontractor Submit

BVSD Eisenhower ES Master Schedule Boulder Valley School District

Job #: BVSD Eisenhower ES

Rev. date: 10/19/2026 12:02:53 PM

Data Date: 10/14/2026

Page 8 of 17

BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks

Line

Name

Duration

Start

Finish

2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9

211

S&P - Diffusers / Registers / Grilles - Subcontractor Submit

10d 11/5/2026

11/18/2026

S&P - Diffusers / Registers / Grilles - Subcontractor Submit

212

S&P - RTU - Libary & Music - Subcontractor Submit

10d 11/5/2026

11/18/2026

S&P - RTU - Libary & Music - Subcontractor Submit

213

S&P - Ductless Split Systems - Subcontractor Submit

10d 11/5/2026

11/18/2026

S&P - Ductless Split Systems - Subcontractor Submit

214

S&P - Motors / VFD / Starters - AP Review/Submit

10d 11/19/2026

12/4/2026

S&P - Motors / VFD / Starters - AP Review/Submit

215

S&P - Mechanical Piping - AP Review/Submit

10d 11/19/2026

12/4/2026

S&P - Mechanical Piping - AP Review/Submit

216

S&P - Piping Specialties - AP Review/Submit

10d 11/19/2026

12/4/2026

S&P - Piping Specialties - AP Review/Submit

217

S&P - Hangers / Supports - AP Review/Submit

10d 11/19/2026

12/4/2026

S&P - Hangers / Supports - AP Review/Submit

218

S&P - Metal Ducts - AP Review/Submit

10d 11/19/2026

12/4/2026

S&P - Metal Ducts - AP Review/Submit

219

S&P - Duct Accessories - AP Review/Submit

10d 11/19/2026

12/4/2026

S&P - Duct Accessories - AP Review/Submit

220

S&P - Air Terminal Units - AP Review/Submit

10d 11/19/2026

12/4/2026

S&P - Air Terminal Units - AP Review/Submit

221

S&P - Diffusers / Registers / Grilles - AP Review/Submit

10d 11/19/2026

12/4/2026

S&P - Diffusers / Registers / Grilles - AP Review/Submit

222

S&P - RTU - Libary & Music - AP Review/Submit

10d 11/19/2026

12/4/2026

S&P - RTU - Libary & Music - AP Review/Submit

223

S&P - Ductless Split Systems - AP Review/Submit

10d 11/19/2026

12/4/2026

S&P - Ductless Split Systems - AP Review/Submit

224

S&P - Motors / VFD / Starters - A&E Review

10d 12/7/2026

12/18/2026

S&P - Motors / VFD / Starters - A&E Review

225

S&P - Mechanical Piping - A&E Review

10d 12/7/2026

12/18/2026

S&P - Mechanical Piping - A&E Review

226

S&P - Piping Specialties - A&E Review

10d 12/7/2026

12/18/2026

S&P - Piping Specialties - A&E Review

227

S&P - Hangers / Supports - A&E Review

10d 12/7/2026

12/18/2026

S&P - Hangers / Supports - A&E Review

228

S&P - Metal Ducts - A&E Review

10d 12/7/2026

12/18/2026

S&P - Metal Ducts - A&E Review

229

S&P - Duct Accessories - A&E Review

10d 12/7/2026

12/18/2026

S&P - Duct Accessories - A&E Review

230

S&P - Air Terminal Units - A&E Review

10d 12/7/2026

12/18/2026

S&P - Air Terminal Units - A&E Review

231

S&P - Diffusers / Registers / Grilles - A&E Review

10d 12/7/2026

12/18/2026

S&P - Diffusers / Registers / Grilles - A&E Review

232

S&P - RTU - Libary & Music - A&E Review

10d 12/7/2026

12/18/2026

S&P - RTU - Libary & Music - A&E Review

233

S&P - Ductless Split Systems - A&E Review

10d 12/7/2026

12/18/2026

S&P - Ductless Split Systems - A&E Review

234

S&P - Motors / VFD / Starters Procurement/Fabricate/Deliver

25d 12/21/2026

1/27/2027

S&P - Motors / VFD / Starters Procurement/Fabricate/Deliver

235

S&P - Mechanical Piping Procurement/Fabricate/Deliver

25d 12/21/2026

1/27/2027

S&P - Mechanical Piping Procurement/Fabricate/Deliver

236

S&P - Piping Specialties Procurement/Fabricate/Deliver

25d 12/21/2026

1/27/2027

S&P - Piping Specialties Procurement/Fabricate/Deliver

237

S&P - Hangers / Supports Procurement/Fabricate/Deliver

25d 12/21/2026

1/27/2027

S&P - Hangers / Supports Procurement/Fabricate/Deliver

238

S&P - Metal Ducts Procurement/Fabricate/Deliver

25d 12/21/2026

1/27/2027

S&P - Metal Ducts Procurement/Fabricate/Deliver

239

S&P - Duct Accessories Procurement/Fabricate/Deliver

25d 12/21/2026

1/27/2027

S&P - Duct Accessories Procurement/Fabricate/Deliver

240

S&P - Air Terminal Units Procurement/Fabricate/Deliver

25d 12/21/2026

1/27/2027

S&P - Air Terminal Units Procurement/Fabricate/Deliver

BVSD Eisenhower ES Master Schedule Boulder Valley School District

Job #: BVSD Eisenhower ES

Rev. date: 10/19/2026 12:02:53 PM

Data Date: 10/14/2026

Page 9 of 17

BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks

Finish

2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9

25d 12/21/2026

1/27/2027

S&P - Diffusers / Registers / Grilles Procurement/Fabricate/Deliver

S&P - RTU - Libary & Music Procurement/Fabricate/Deliver

110d 12/21/2026

5/26/2027

S&P - Ductless Split Systems Procurement/Fabricate/Deliver

60d 12/21/2026

3/17/2027

Line

Name

Duration

241

S&P - Diffusers / Registers / Grilles Procurement/Fabricate/Deliver

242 243

Start

S&P - RTU - Libary & Music Procurement/Fabricate/Deliver

S&P - Ductless Split Systems Procurement/Fabricate/Deliver

Division 26 - ELECTRICAL

90d 11/5/2026

3/17/2027

244

S&P - Conductors And Cables - Subcontractor Submit

10d 11/5/2026

11/18/2026

S&P - Conductors And Cables - Subcontractor Submit

245

S&P - Raceways / Wireways - Subcontractor Submit

10d 11/5/2026

11/18/2026

S&P - Raceways / Wireways - Subcontractor Submit

246

S&P - Cabinets / Boxes / Fittings - Subcontractor Submit

10d 11/5/2026

11/18/2026

S&P - Cabinets / Boxes / Fittings - Subcontractor Submit

247

S&P - Lighting Controls - Subcontractor Submit

10d 11/5/2026

11/18/2026

S&P - Lighting Controls - Subcontractor Submit

248

S&P - Wiring Devices - Subcontractor Submit

10d 11/5/2026

11/18/2026

S&P - Wiring Devices - Subcontractor Submit

249

S&P - Circuit Protective Devices - Subcontractor Submit

10d 11/5/2026

11/18/2026

S&P - Circuit Protective Devices - Subcontractor Submit

250

S&P - Lighting - Subcontractor Submit

10d 11/5/2026

11/18/2026

S&P - Lighting - Subcontractor Submit

251

S&P - Conductors And Cables - AP Review/Submit

10d 11/19/2026

12/4/2026

S&P - Conductors And Cables - AP Review/Submit

252

S&P - Raceways / Wireways - AP Review/Submit

10d 11/19/2026

12/4/2026

S&P - Raceways / Wireways - AP Review/Submit

253

S&P - Cabinets / Boxes / Fittings - AP Review/Submit

10d 11/19/2026

12/4/2026

S&P - Cabinets / Boxes / Fittings - AP Review/Submit

254

S&P - Lighting Controls - AP Review/Submit

10d 11/19/2026

12/4/2026

S&P - Lighting Controls - AP Review/Submit

255

S&P - Wiring Devices - AP Review/Submit

10d 11/19/2026

12/4/2026

S&P - Wiring Devices - AP Review/Submit

256

S&P - Circuit Protective Devices - AP Review/Submit

10d 11/19/2026

12/4/2026

S&P - Circuit Protective Devices - AP Review/Submit

257

S&P - Lighting - AP Review/Submit

10d 11/19/2026

12/4/2026

S&P - Lighting - AP Review/Submit

258

S&P - Conductors And Cables - A&E Review

10d 12/7/2026

12/18/2026

S&P - Conductors And Cables - A&E Review

259

S&P - Raceways / Wireways - A&E Review

10d 12/7/2026

12/18/2026

S&P - Raceways / Wireways - A&E Review

260

S&P - Cabinets / Boxes / Fittings - A&E Review

10d 12/7/2026

12/18/2026

S&P - Cabinets / Boxes / Fittings - A&E Review

261

S&P - Lighting Controls - A&E Review

10d 12/7/2026

12/18/2026

S&P - Lighting Controls - A&E Review

262

S&P - Wiring Devices - A&E Review

10d 12/7/2026

12/18/2026

S&P - Wiring Devices - A&E Review

263

S&P - Circuit Protective Devices - A&E Review

10d 12/7/2026

12/18/2026

S&P - Circuit Protective Devices - A&E Review

264

S&P - Lighting - A&E Review

10d 12/7/2026

12/18/2026

S&P - Lighting - A&E Review

265

S&P - Conductors And Cables Procurement/Fabricate/Deliver

25d 12/21/2026

1/27/2027

S&P - Conductors And Cables Procurement/Fabricate/Deliver

266

S&P - Raceways / Wireways Procurement/Fabricate/Deliver

25d 12/21/2026

1/27/2027

S&P - Raceways / Wireways Procurement/Fabricate/Deliver

267

S&P - Cabinets / Boxes / Fittings Procurement/Fabricate/Deliver

25d 12/21/2026

1/27/2027

S&P - Cabinets / Boxes / Fittings Procurement/Fabricate/Deliver

268

S&P - Lighting Controls Procurement/Fabricate/Deliver

25d 12/21/2026

1/27/2027

S&P - Lighting Controls Procurement/Fabricate/Deliver

269

S&P - Wiring Devices Procurement/Fabricate/Deliver

25d 12/21/2026

1/27/2027

S&P - Wiring Devices Procurement/Fabricate/Deliver

BVSD Eisenhower ES Master Schedule Boulder Valley School District

Job #: BVSD Eisenhower ES

Rev. date: 10/19/2026 12:02:53 PM

Data Date: 10/14/2026

Page 10 of 17

BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks

Line

Name

Duration

Start

Finish

2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9 S&P - Circuit Protective Devices Procurement/Fabricate/Deliver

270

S&P - Circuit Protective Devices Procurement/Fabricate/Deliver

25d 12/21/2026

1/27/2027

271

S&P - Lighting Procurement/Fabricate/Deliver

60d 12/21/2026

3/17/2027

Division 27 - COMMUNICATION

55d 11/12/2026

2/3/2027

272

S&P - Communications Common Work - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Communications Common Work - Subcontractor Submit

273

S&P - Communications Pathways - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Communications Pathways - Subcontractor Submit

274

S&P - Communications Common Work - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Communications Common Work - AP Review/Submit

275

S&P - Communications Pathways - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Communications Pathways - AP Review/Submit

276

S&P - Communications Common Work - A&E Review

10d 12/14/2026

12/29/2026

S&P - Communications Common Work - A&E Review

277

S&P - Communications Pathways - A&E Review

10d 12/14/2026

12/29/2026

S&P - Communications Pathways - A&E Review

278

S&P - Communications Common Work Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Communications Common Work Procurement/Fabricate/Deliver

279

S&P - Communications Pathways Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Communications Pathways Procurement/Fabricate/Deliver

Division 28 - FA SECURITY

55d 2/11/2027

4/28/2027

280

S&P - Fire Detection and Alarm - Subcontractor Submit

10d 2/11/2027

2/24/2027

S&P - Fire Detection and Alarm - Subcontractor Submit

281

S&P - Fire Detection and Alarm - AP Review/Submit

10d 2/25/2027

3/10/2027

S&P - Fire Detection and Alarm - AP Review/Submit

282

S&P - Fire Detection and Alarm - A&E Review

10d 3/11/2027

3/24/2027

S&P - Fire Detection and Alarm - A&E Review

283

S&P - Fire Detection and Alarm Procurement/Fabricate/Deliver

25d 3/25/2027

4/28/2027

Division 32 - EXTERIOR IMPROVEMENTS

55d 11/12/2026

2/3/2027

284

S&P - Concrete Paving - Subcontractor Submit

10d 11/12/2026

11/25/2026

S&P - Concrete Paving - Subcontractor Submit

285

S&P - Concrete Paving - AP Review/Submit

10d 11/30/2026

12/11/2026

S&P - Concrete Paving - AP Review/Submit

286

S&P - Concrete Paving - A&E Review

10d 12/14/2026

12/29/2026

S&P - Concrete Paving - A&E Review

287

S&P - Concrete Paving Procurement/Fabricate/Deliver

25d 12/30/2026

2/3/2027

S&P - Lighting Procurement/Fabricate/Deliver

S&P - Fire Detection and Alarm Procurement/Fabricate/Deliver

S&P - Concrete Paving Procurement/Fabricate/Deliver

Construction

471d 10/21/2025 8/31/2027

Site Mobilization

49d 3/15/2027

5/20/2027

288

Mobilization Start (Week Prior) Spring Break

1d 3/15/2027

3/15/2027

Mobilization Start (Week Prior) Spring Break

289

Mobilization Complete

5d 3/16/2027

3/22/2027

Mobilization Complete

290

Mobilization Start (Summer)

1d 5/20/2027

5/20/2027

Abatement (If NEEDED)

50d 3/16/2027

5/24/2027

291

Abate - Review Impacts

30d 3/16/2027

4/26/2027

292

Abate - Identify Scope

10d 4/27/2027

5/10/2027

293

Abate - Demo / Remove / Inspections / Tear Down

10d 5/11/2027

5/24/2027

BVSD Eisenhower ES Master Schedule Boulder Valley School District

Mobilization Start (Summer)

Abate - Review Impacts

Abate - Identify Scope

Abate - Demo / Remove / Inspections / Tear Down

Job #: BVSD Eisenhower ES

Rev. date: 10/19/2026 12:02:53 PM

Data Date: 10/14/2026

Page 11 of 17

BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks

Line

Name

Duration

Start

Finish

Demolition

161d 10/29/2026 6/18/2027

North Building - Kindergarden - 1X2

149d 10/29/2026

6/2/2027

2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9

294

Demo - North - Review Impacts

5d 3/16/2027

3/22/2027

295

Demo - North - Exterior Replacement Metal Doors & Frame (205,206,159,170A,182)

3d 5/20/2027

5/24/2027

Demo - North - Exterior Replacement Metal Doors & Frame (205,206,159,170A,182)

296

Demo - North - Safe Off Electrical & Mechanical

2d 5/21/2027

5/24/2027

Demo - North - Safe Off Electrical & Mechanical

297

Demo - North - Demo / Remove - Existing Flooring, Casework, Interior Walls & Doors, Markerboards, Projection Screen, Projector, Decor. Wall Covering, Lighting Fixtures

5d 5/21/2027

5/27/2027

Demo - North - Demo / Remove - Existing Flooring, Casework, Interior Walls & Doors, Markerboards, Projection Screen, Projector, Decor. Wall Covering, Lighting Fixtures

298

Demo - Ceiling Grid (Kindergarten, Flex Learning, Corridor 210)

2d 5/21/2027

5/24/2027

Demo - Ceiling Grid (Kindergarten, Flex Learning, Corridor 210)

299

Demo - North - Ceiling Grid (Music, Storage)

2d 5/21/2027

5/24/2027

Demo - North - Ceiling Grid (Music, Storage)

300

Demo - North - Ceiling Grid (Selective, Corridor 188)

2d 5/21/2027

5/24/2027

Demo - North - Ceiling Grid (Selective, Corridor 188)

301

Demo - North - (V14) Light fixtures

8d 5/21/2027

6/2/2027

Demo Alternate - Fire Alarm

10d 3/22/2027

4/2/2027

Demo - North - Alternate - Existing Fire Alarm

10d 3/22/2027

4/2/2027

Demo Alternate - Gym Flooring (ACCEPTED)

4d 10/29/2026 11/3/2026

Demo - North - Alternate - Existing Gym Flooring

4d 10/29/2026

11/3/2026

South Building - Kindergarden - 1X1

51d 3/23/2027

6/2/2027

304

Demo - South - Review Impacts

5d 3/23/2027

3/29/2027

305

Demo - South - Elec. RM - Existing Ladder / Casework

1d 5/21/2027

5/21/2027

306

Demo - South - (V14) Light fixtures

8d 5/21/2027

6/2/2027

Demo - South - (V14) Light fixtures

307

Demo - South - Exterior Replacement Metal Doors & Frame (193,194,149,146,148,138)

3d 5/25/2027

5/27/2027

Demo - South - Exterior Replacement Metal Doors & Frame (193,194,149,146,148,138)

308

Demo - South - MDF - Existing Mini-Split

2d 5/28/2027

6/1/2027

Demo - South - MDF - Existing Mini-Split

Demo Alternate - Fire Alarm

10d

4/5/2027

4/16/2027

Demo - South - Alternate - Existing Fire Alarm

10d

4/5/2027

4/16/2027

East Building - Kindergarden - 1X3

58d 3/30/2027

6/18/2027

310

Demo - East - Review Impacts

5d 3/30/2027

4/5/2027

311

Demo - East - (V14) Light fixtures

8d 5/21/2027

6/2/2027

Demo - East - (V14) Light fixtures

312

Demo - East - Exterior Replacement Metal Doors & Frame (205,206,159)

5d 5/28/2027

6/4/2027

Demo - East - Exterior Replacement Metal Doors & Frame (205,206,159)

313

Demo - East - Demo / Remove - Summer

10d

6/7/2027

6/18/2027

Demo Alternate - Fire Alarm

10d 4/19/2027

4/30/2027

Demo - East - Alternate - Existing Fire Alarm

10d 4/19/2027

4/30/2027

302

303

309

314

Early Site Development

Demo - North - Review Impacts

Demo - North - (V14) Light fixtures

Demo - North - Alternate - Existing Fire Alarm

Demo - North - Alternate - Existing Gym Flooring

Demo - South - Review Impacts

Demo - South - Elec. RM - Existing Ladder / Casework

Demo - South - Alternate - Existing Fire Alarm

Demo - East - Review Impacts

Demo - East - Demo / Remove - Summer

Demo - East - Alternate - Existing Fire Alarm

406d 10/21/2025 5/28/2027

BVSD Eisenhower ES Master Schedule Boulder Valley School District

Job #: BVSD Eisenhower ES

Rev. date: 10/19/2026 12:02:53 PM

Data Date: 10/14/2026

Page 12 of 17

BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks

Line

Name

Duration

Start

Finish

2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9

247d 10/21/2025 A

5/28/2027

ES - Setup Compound (Construction Fence/Connexs/Dumpster/ETC

1d 3/16/2027

3/16/2027

Utilities (IF NEEDED)

30d

6/1/2027

7/13/2027

317

Util - Review Impacts

15d

6/1/2027

6/21/2027

318

Util - Identify Scope

15d 6/22/2027

7/13/2027

Building Construction

87d 4/29/2027

8/31/2027

Exterior of Building

41d 5/25/2027

7/22/2027

North Building - Kindergarden - 1X2

11d 5/25/2027

6/9/2027

319

EX - Install Exterior Replacement Metal Doors & Frame (205,206,159)

10d 5/25/2027

6/8/2027

320

EX - Pre-Punch

3d 5/25/2027

5/27/2027

EX - Pre-Punch

321

EX - Owner Punch

3d 5/28/2027

6/2/2027

EX - Owner Punch

322

EX - Punch Corrections

5d

6/3/2027

6/9/2027

EX - Punch Corrections

South Building - Kindergarden - 1X1

26d

6/9/2027

7/15/2027

323

EX - Install Exterior Replacement Metal Doors & Frame (193,194,149,146,148,138)

15d

6/9/2027

6/29/2027

EX - Install Exterior Replacement Metal Doors & Frame (193,194,149,146,148,138)

324

EX - Pre-Punch

3d 6/30/2027

7/2/2027

EX - Pre-Punch

325

EX - Owner Punch

3d

7/6/2027

7/8/2027

EX - Owner Punch

326

EX - Punch Corrections

5d

7/9/2027

7/15/2027

EX - Punch Corrections

East Building - Kindergarden - 1X3

16d 6/30/2027

7/22/2027

327

EX - Install Exterior Replacement Metal Doors & Frame (182)

5d 6/30/2027

7/7/2027

EX - Install Exterior Replacement Metal Doors & Frame (182)

328

EX - AP Pre-Punch

3d

7/8/2027

7/12/2027

EX - AP Pre-Punch

329

EX - Owner Punch

3d 7/13/2027

7/15/2027

EX - Owner Punch

330

EX - Punch Corrections

5d 7/16/2027

7/22/2027

EX - Punch Corrections

Roofing

40d 5/21/2027

7/19/2027

331

Roof - Demo - Ladder

2d 5/21/2027

5/24/2027

Roof - Demo - Ladder

332

Roof - Install - Ladder

2d 5/25/2027

5/26/2027

Roof - Install - Ladder

333

Roof - Demo - Roofing

10d 5/28/2027

6/11/2027

334

Roof - Install (2000 SQFT)

10d 6/14/2027

6/25/2027

335

Roof - Demo - RTU

2d 6/14/2027

6/15/2027

Roof - Demo - RTU

336

Roof - Install - RTU

2d 6/16/2027

6/17/2027

Roof - Install - RTU

337

Roof - Pre-Punch

5d 6/28/2027

7/2/2027

Roof - Pre-Punch

315

ES - Investigations

316

BVSD Eisenhower ES Master Schedule Boulder Valley School District

ES - Investigations

ES - Setup Compound (Construction Fence/Connexs/Dumpster/ETC

Util - Review Impacts

Util - Identify Scope

EX - Install Exterior Replacement Metal Doors & Frame (205,206,159)

Roof - Demo - Roofing

Roof - Install (2000 SQFT)

Job #: BVSD Eisenhower ES

Rev. date: 10/19/2026 12:02:53 PM

Data Date: 10/14/2026

Page 13 of 17

BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks

Line

Name

Duration

Start

Finish

2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9

338

Roof - Owner Walk

5d

7/6/2027

7/12/2027

Roof - Owner Walk

339

Roof - Punch Corrections

5d 7/13/2027

7/19/2027

Roof - Punch Corrections

Interiors / Mechanical / Electrical / Plumbing / Fire Alarm

87d 4/29/2027

8/31/2027

North Building - Kindergarden - 1X2.North Buildling

62d 4/29/2027

7/27/2027

Interior Rough In (Nights & Days)

38d 4/29/2027

6/22/2027

340

IF-RI - North - Electrical - Interior Rough In Activities

20d 5/25/2027

6/22/2027

IF-RI - North - Electrical - Interior Rough In Activities

341

IF-RI - North - Mechanical - Interior Rough In Activities

20d 5/25/2027

6/22/2027

IF-RI - North - Mechanical - Interior Rough In Activities

342

IF-RI - North - Fire Alarm Rough In Activities - Summer

3d 5/25/2027

5/27/2027

343

IF-RI - North - Framing

5d 5/28/2027

6/4/2027

344

IF-RI - North - Electrical Rough In Activities - IN Wall

15d 5/28/2027

6/18/2027

345

IF-RI - North - Technology Rough In

3d 5/28/2027

6/2/2027

IF-RI - North - Technology Rough In

346

IF-RI - North - Blocking Rough In Activities - For Cabinets, Markerboards, TV/Display, Bathroom Accessories, ETC

3d

6/3/2027

6/7/2027

IF-RI - North - Blocking Rough In Activities - For Cabinets, Markerboards, TV/Display, Bathroom Accessories, ETC

347

IF-RI - North - (V14) Light Fixtures Priorities 1-4 Rough In

5d

6/3/2027

6/9/2027

IF-RI - North - (V14) Light Fixtures Priorities 1-4 Rough In

Alternate - Fire Alarm (ACCEPTED)

10d 4/29/2027

5/12/2027

IF-RI - North - Fire Alarm Rough In Activities - Spring Break

10d 4/29/2027

5/12/2027

348

IF-RI - North - Fire Alarm Rough In Activities - Summer

IF-RI - North - Framing

IF-RI - North - Electrical Rough In Activities - IN Wall

IF-RI - North - Fire Alarm Rough In Activities - Spring Break

Interior Finishes

38d

6/3/2027

7/27/2027

349

IF-FIN - North - (V14) Light Fixtures Install

20d

6/3/2027

6/30/2027

350

IF-FIN - North - Drywall Tape Finish

7d

6/8/2027

6/16/2027

IF-FIN - North - Drywall Tape Finish

351

IF-FIN - North - Repair and Paint

5d 6/17/2027

6/23/2027

IF-FIN - North - Repair and Paint

352

IF-FIN - North - ACT Install

5d 6/21/2027

6/25/2027

IF-FIN - North - ACT Install

353

IF-FIN - North - Mechanical GRD's

5d 6/28/2027

7/2/2027

IF-FIN - North - Mechanical GRD's

354

IF-FIN - North - Casework Install

3d 6/30/2027

7/2/2027

IF-FIN - North - Casework Install

355

IF-RI - North - Electrical Trim

7d

7/1/2027

7/12/2027

IF-RI - North - Electrical Trim

356

IF-FIN - North - Pre-Punch

5d

7/6/2027

7/12/2027

IF-FIN - North - Pre-Punch

357

IF-FIN - North - Owner Walk

1d 7/13/2027

7/13/2027

IF-FIN - North - Owner Walk

358

IF-FIN - North - Punch Corrections

10d 7/14/2027

7/27/2027

Alternate - Gym Floor Mitgation (ACCEPTED)

20d 5/20/2027

6/17/2027

ALT - Gym Floor Mitgation

20d 5/20/2027

6/17/2027

South Buidling - Kindergarden - 1X1.South Building

77d 5/13/2027

8/31/2027

Interior Rough In (Nights & Days)

39d 5/13/2027

7/8/2027

359

BVSD Eisenhower ES Master Schedule Boulder Valley School District

IF-FIN - North - (V14) Light Fixtures Install

IF-FIN - North - Punch Corrections

ALT - Gym Floor Mitgation

Job #: BVSD Eisenhower ES

Rev. date: 10/19/2026 12:02:53 PM

Data Date: 10/14/2026

Page 14 of 17

BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks

Line

Name

Duration

Start

Finish

2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9

360

IF-RI - South - Interior Rough In Activities

33d 5/21/2027

7/8/2027

361

IF-RI - South - Mini-Split Rough In Activities (Nights)

5d

6/2/2027

6/8/2027

IF-RI - South - Mini-Split Rough In Activities (Nights)

362

IF-RI - South - (V14) Light Fixtures Priorities 1-4 Rough In

5d

6/3/2027

6/9/2027

IF-RI - South - (V14) Light Fixtures Priorities 1-4 Rough In

Alternate - fire Alarm

10d 5/13/2027

5/26/2027

IF-RI - South - Fire Alarm Rough In Activities - Spring Break

10d 5/13/2027

5/26/2027

Interior Finishes

58d 6/10/2027

8/31/2027

364

IF-FIN - South - (V14) Light Fixtures Install

20d 6/10/2027

7/8/2027

IF-FIN - South - (V14) Light Fixtures Install

365

IF-FIN - South - Repair and Paint

20d 7/20/2027

8/16/2027

IF-FIN - South - Repair and Paint

366

IF-FIN - South - Pre-Punch

5d 8/10/2027

8/16/2027

IF-FIN - South - Pre-Punch

367

IF-FIN - South - Owner Walk

1d 8/17/2027

8/17/2027

IF-FIN - South - Owner Walk

368

IF-FIN - South - Punch Corrections

10d 8/18/2027

8/31/2027

East Building - Kindergarden - 1X3

58d 5/21/2027

8/12/2027

Interior Rough In (Nights & Days)

30d 5/21/2027

7/2/2027

369

IF-RI - East - Interior Rough In Activities (Nights)

30d 5/21/2027

7/2/2027

IF-RI - East - Interior Rough In Activities (Nights)

370

IF-RI - East - (V14) Light Fixtures Priorities 1-4 Rough In

5d

6/3/2027

6/9/2027

IF-RI - East - (V14) Light Fixtures Priorities 1-4 Rough In

Alternate - fire Alarm

10d 5/27/2027

6/10/2027

IF-RI - East - Fire Alarm Rough In Activities - Spring Break

10d 5/27/2027

6/10/2027

Interior Finishes

45d 6/10/2027

8/12/2027

372

IF-FIN - East - (V14) Light Fixtures Install

20d 6/10/2027

7/8/2027

IF-FIN - East - (V14) Light Fixtures Install

373

IF-FIN - East - Repair and Paint

10d

7/8/2027

7/21/2027

IF-FIN - East - Repair and Paint

374

IF-FIN - East - Pre-Punch

5d 7/22/2027

7/28/2027

IF-FIN - East - Pre-Punch

375

IF-FIN - East - Owner Walk

1d 7/29/2027

7/29/2027

IF-FIN - East - Owner Walk

376

IF-FIN - East - Punch Corrections

10d 7/30/2027

8/12/2027

Sitework

44d

6/1/2027

8/2/2027

Parking Lot Repairs

44d

6/1/2027

8/2/2027

377

FS - Identify Scope (Site Investigation & Layout)

5d

6/1/2027

6/7/2027

378

FS - Demo - Selected Potholes

10d

6/8/2027

6/21/2027

379

FS - Repair Selected Potholes

10d 6/22/2027

7/6/2027

FS - Repair Selected Potholes

380

FS - Pre-Punch

2d

7/7/2027

7/8/2027

FS - Pre-Punch

381

FS - Punch

2d

7/9/2027

7/12/2027

FS - Punch

363

371

BVSD Eisenhower ES Master Schedule Boulder Valley School District

IF-RI - South - Interior Rough In Activities

IF-RI - South - Fire Alarm Rough In Activities - Spring Break

IF-FIN - South - Punch Corrections

IF-RI - East - Fire Alarm Rough In Activities - Spring Break

IF-FIN - East - Punch Corrections

FS - Identify Scope (Site Investigation & Layout)

FS - Demo - Selected Potholes

Job #: BVSD Eisenhower ES

Rev. date: 10/19/2026 12:02:53 PM

Data Date: 10/14/2026

Page 15 of 17

BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks

Line

Name

Duration

Start

Finish

2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9

FS - Punch Corrections

10d 7/20/2027

8/2/2027

Pedestrian Pavement - Concrete Repairs

44d

6/1/2027

8/2/2027

383

FS - Identify Scope (Site Investigation & Layout)

5d

6/1/2027

6/7/2027

384

FS - Demo - Selected Sidewalks

10d

6/8/2027

6/21/2027

385

FS - Repair Selected Sidewalks

15d 6/22/2027

7/13/2027

FS - Repair Selected Sidewalks

386

FS - Pre-Punch

2d 7/14/2027

7/15/2027

FS - Pre-Punch

387

FS - Punch

2d 7/16/2027

7/19/2027

FS - Punch

388

FS - Punch Corrections

10d 7/20/2027

8/2/2027

Final Inspections & Closeout

84d 6/11/2027

10/8/2027

MEP Startup & Commissioning

15d 6/28/2027

7/19/2027

Startup / Test & Balance

13d 6/28/2027

7/15/2027

389

Startup/TAB - Startup / Test & Balance Tasks

12d 6/28/2027

7/14/2027

Startup/TAB - Startup / Test & Balance Tasks

390

North - (V14) Lighting Controls, Programming, Testing

5d

7/1/2027

7/8/2027

North - (V14) Lighting Controls, Programming, Testing

391

South - (V14) Lighting Controls, Programming, Testing

5d

7/9/2027

7/15/2027

South - (V14) Lighting Controls, Programming, Testing

392

East - (V14) Lighting Controls, Programming, Testing

5d

7/9/2027

7/15/2027

East - (V14) Lighting Controls, Programming, Testing

Commissioning

15d 6/28/2027

7/19/2027

CX - Commissioning Tasks

15d 6/28/2027

7/19/2027

Final Project Punchlist

20d 8/10/2027

9/7/2027

394

Punch - Pre-Punch - Final

5d 8/10/2027

8/16/2027

Punch - Pre-Punch - Final

395

Punch - Owner Walk -Final

5d 8/17/2027

8/23/2027

Punch - Owner Walk -Final

396

Punch - Punch Corrections - Final

10d 8/24/2027

9/7/2027

Final Inspections / TCO

35d 6/11/2027

7/30/2027

Final Inspections

35d 6/11/2027

7/30/2027

397

FInsp - Final Fire Alarm Inspection - Fire Department

5d 6/11/2027

6/17/2027

FInsp - Final Fire Alarm Inspection - Fire Department

398

FInsp - Final Plumbing Inspection - State

10d 6/28/2027

7/12/2027

FInsp - Final Plumbing Inspection - State

399

FInsp - Final AHJ Inspections (Mechanical, Framing)

3d

7/6/2027

7/8/2027

FInsp - Final AHJ Inspections (Mechanical, Framing)

400

FInsp - Final Electrical Inspection - State

5d 7/16/2027

7/22/2027

FInsp - Final Electrical Inspection - State

401

FInsp - Final Building Inspection - DFPC

2d 7/23/2027

7/26/2027

FInsp - Final Building Inspection - DFPC

402

Substantial Completion - TCO

4d 7/27/2027

7/30/2027

Substantial Completion - TCO

Owner Move In Activities

73d 6/28/2027

10/8/2027

382

393

BVSD Eisenhower ES Master Schedule Boulder Valley School District

FS - Punch Corrections

FS - Identify Scope (Site Investigation & Layout)

FS - Demo - Selected Sidewalks

FS - Punch Corrections

CX - Commissioning Tasks

Punch - Punch Corrections - Final

Job #: BVSD Eisenhower ES

Rev. date: 10/19/2026 12:02:53 PM

Data Date: 10/14/2026

Page 16 of 17

BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks

Line

Name

Duration

Start

Finish

Move - Owner Move In Activities

10d 7/27/2027

8/9/2027

Closeout / CO

73d 6/28/2027

10/8/2027

404

Closeout - Start

1d 6/28/2027

6/28/2027

405

Closeout - Owner Training

20d 6/29/2027

7/27/2027

406

Closeout - Final Completion

23d

9/8/2027

10/8/2027

403

2025 2026 2027 2028 2029 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 4 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 13 27 10 24 8 22 5 19 3 17 31 14 28 11 25 9 23 6 20 4 18 1 15 29 12 26 12 26 9

BVSD Eisenhower ES Master Schedule Boulder Valley School District

Move - Owner Move In Activities

Closeout - Start

Closeout - Owner Training

Closeout - Final Completion

Job #: BVSD Eisenhower ES

Rev. date: 10/19/2026 12:02:53 PM

Data Date: 10/14/2026

Page 17 of 17

BVSD Eisenhower ES Progressed 10.19.26 Filter: No Summary Tasks

Exhibit E Insurance Insurance Certificates to be provided after Certificates amendment & change order for the GMP is executed

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit F Performance Bond to be provided after amendment & change order for the GMP is executed

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit G Labor and Materials Payment Bond to be provided after amendment & change order for the GMP is executed

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit H Alternates prices Alternates prices not used for the amendment

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Allowances Report DESCRIPTION

QTY UOM

UNIT PRICE

1.00 allow

4,000.00

TOTAL COST

NOTES / COMMENTS

04 Masonry 04 20 00 Unit Masonry 04190 Masonry Patch and Repair Allowance

$4,000

Subtotal 04 20 00 Unit Masonry

$4,000

Allowance

$4,000 $4,000

Subtotal 04 Masonry 09 Finishes 09 24 00 Cement Plastering 09205 Patch exterior stucco at new window

$1,200 1.00 allow

1,200.00

Subtotal 09 24 00 Cement Plastering

$1,200

Allowance

$1,200 $1,200

Subtotal 09 Finishes 23 Heating, Ventilating and Air Conditioning 23 00 00 Heating, Ventilating and Air Conditioning 23037 3rd Party Design for Wind Subtotal 23 00 00 Heating, Ventilating and Air Conditioning Subtotal 23 Heating, Ventilating and Air Conditioning

DATE PRINTED: 10/6/2026

$15,000 1.00 allow

15,000.00

$15,000 $15,000 $15,000

Allowance

Exhibit I prices Unit prices not Unit used for this amendment

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit J Allowances

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Allowances Report DESCRIPTION

QTY UOM

UNIT PRICE

1.00 allow

4,000.00

TOTAL COST

NOTES / COMMENTS

04 Masonry 04 20 00 Unit Masonry 04190 Masonry Patch and Repair Allowance

$4,000

Subtotal 04 20 00 Unit Masonry

$4,000

Allowance

$4,000 $4,000

Subtotal 04 Masonry 09 Finishes 09 24 00 Cement Plastering 09205 Patch exterior stucco at new window

$1,200 1.00 allow

1,200.00

Subtotal 09 24 00 Cement Plastering

$1,200

Allowance

$1,200 $1,200

Subtotal 09 Finishes 23 Heating, Ventilating and Air Conditioning 23 00 00 Heating, Ventilating and Air Conditioning 23037 3rd Party Design for Wind Subtotal 23 00 00 Heating, Ventilating and Air Conditioning Subtotal 23 Heating, Ventilating and Air Conditioning

DATE PRINTED: 10/6/2026

$15,000 1.00 allow

15,000.00

$15,000 $15,000 $15,000

Allowance

Exhibit K Not Applicable

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit L Equipment rental rate schedule

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit M General Conditions of the Contract

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

BOULDER VALLEY SCHOOL DISTRICT RE-2 BOULDER, COLORADO

GENERAL CONTRACT CONDITIONS BOND PROGRAM

GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT.................................................................................................... 2 GC 1.00

CONTRACT DOCUMENTS AND DEFINITIONS ............................................................................................................ 1

GC 2.00

REFERENCE STANDARDS .......................................................................................................................................... 2

GC 3.00

DRAWINGS AND SPECIFICATIONS ............................................................................................................................ 2

GC 4.00

ROYALTIES AND PATENTS ........................................................................................................................................ 3

GC 5.00

ITEMS COVERED BY CONTRACT PRICE ..................................................................................................................... 3

GC 6.00

EXECUTION, CORRELATION, INTENT, AND INTERPRETATION OF CONTRACT DOCUMENTS ...................................... 3

GC 7.00

MATERIALS, LABOR, FACILITIES, AND STORAGE....................................................................................................... 4

GC 8.00

PERFORMANCE AND PAYMENT BONDS ................................................................................................................... 5

GC 9.00

PERMITS AND COMPLIANCE WITH STATUTES, RULES, AND REGULATIONS .............................................................. 6

GC 10.00

SURVEYS, BENCHMARKS, MONUMENTS, STAKES, AND MEASUREMENTS ............................................................... 6

GC 11.00

CHANGED CONDITIONS ........................................................................................................................................... 7

GC 12.00

PROTECTION OF PERSONS, WORK AND PROPERTY ................................................................................................. 7

GC 13.00

WORK ON EXISTING BUILDINGS .............................................................................................................................. 8

GC 14.00

CONTRACTOR’S SUPERINTENDENCE AND SUPERVISION .......................................................................................... 8

GC 15.00

SUBSTITUTIONS ....................................................................................................................................................... 9

GC 16.00

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES ................................................................................................. 9

GC 17.00

CASH ALLOWANCE................................................................................................................................................. 10

GC 18.00

EXPEDITING MATERIALS ........................................................................................................................................ 10

GC 19.00

BLASTING .............................................................................................................................................................. 11

GC 20.00

SOIL TEST REPORT ................................................................................................................................................. 11

GC 21.00

HAZARDOUS MATERIALS ....................................................................................................................................... 11

GC 22.00

DAMAGE TO UTILITIES ........................................................................................................................................... 11

GC 23.00

CHANGES IN THE WORK ........................................................................................................................................ 12

GC 24.00

CLAIMS FOR EXTRA COST....................................................................................................................................... 13

GC 25.00

DELAYS AND EXTENSIONS OF TIME ....................................................................................................................... 13

GC 26.00

ACCESS TO WORK .................................................................................................................................................. 14

GC 27.00

CORRECTION OF WORK ......................................................................................................................................... 14

GC 28.00

OWNER’S RIGHT TO CARRY OUT WORK ................................................................................................................. 16

GC 29.00

OWNER’S RIGHT TO TERMINATE CONTRACT ......................................................................................................... 16

GC 30.00

CONSTRUCTION SCHEDULE AND PROGRESS REPORTS ........................................................................................... 16

GC 31.00

SCHEDULE OF VALUES ........................................................................................................................................... 17

GC 32.00

PAYMENT .............................................................................................................................................................. 17

GC 33.00

INSURANCE ........................................................................................................................................................... 19

GC 34.00

SEPARATE CONTRACTS .......................................................................................................................................... 23

GC 35.00

SUBCONTRACTORS ................................................................................................................................................ 23

GC 36.00

RELATIONS OF CONTRACTOR AND SUBCONTRACTOR ........................................................................................... 24

GC 37.00

CONTRACTORS’ MUTUAL RESPONSIBILITY ............................................................................................................ 25

GC 38.00

CUTTING, PATCHING, AND EXCAVATING ............................................................................................................... 25

GC 39.00

EMPLOYEES ........................................................................................................................................................... 26

GC 40.00

CLEANING UP......................................................................................................................................................... 27

GC 41.00

USE OF PREMISES .................................................................................................................................................. 27

GC 42.00

OCCUPANCY .......................................................................................................................................................... 27

GC 43.00

TEMPORARY OR TRIAL USAGE ............................................................................................................................... 28

GC 44.00

TESTING OF BUILDING SYSTEMS ............................................................................................................................ 28

GC 45.00

LIQUIDATED DAMAGES FOR DELAY IN COMPLETION ............................................................................................. 28

GC 46.00

ACCEPTANCE AND FINAL PAYMENT ....................................................................................................................... 28

GC 47.00

WARRANTIES ON PORTIONS OF THE WORK .......................................................................................................... 29

GC 48.00

CONTRACTOR’S PROJECT GUARANTEE AFTER COMPLETION ................................................................................. 30

GC 49.00

MISCELLANEOUS KEYS, SWITCHES, ETC. ................................................................................................................ 30

GC 50.00

INDEMNIFICATION ................................................................................................................................................ 30

GC 51.00

LABOR DISPUTES ................................................................................................................................................... 31

GC 52.00

LIMITATION OF ACTIONS ....................................................................................................................................... 31

GC 53.00

PREFERENCE FOR COLORADO LABOR, MATERIALS, AND RESIDENT BIDDERS ........................................................ 31

GC 54.00

SALES AND USE TAX............................................................................................................................................... 31

GC 55.00

LIENS ..................................................................................................................................................................... 32

GC 56.00

OWNER’S INSPECTION OF CONTRACTOR’S RECORDS ............................................................................................ 32

GC 57.00

CERTIFICATION BY CONTRACTOR REGARDING PREMISES ACCESS ......................................................................... 32

GC 58.00

CONTRACTOR SAFETY RESPONSIBILITIES ............................................................................................................... 32

GC 59.00

CONTRACTOR ASBESTOS MANAGEMENT AND LEAD PAINT RESPONSIBILITIES ...................................................... 35

GC 60.00

ARCHITECT’S STATUS AND INSPECTIONS ............................................................................................................... 35

GC 61.00

ORAL STATEMENTS................................................................................................................................................ 35

GC 62.00

PROJECT SIGN ........................................................................................................................................................ 36

GC 63.00

HISTORICAL DATA .................................................................................................................................................. 36

GC 64.00

ASSIGNMENT ......................................................................................................................................................... 36

GC 65.00

TIME OF THE ESSENCE ........................................................................................................................................... 36

GC 66.00

DISPUTES ............................................................................................................................................................... 36

GC 67.00

SURVIVAL .............................................................................................................................................................. 36

GC 1.00

CONTRACT DOCUMENTS AND DEFINITIONS

All Work under the Construction Agreement shall be accomplished in accordance with the Contract Documents, which shall consist of the Request for Qualifications, Request for Proposals, Proposal(s), Notice of Award, Notice to Proceed, Performance Bond, Labor and Material Payment Bond, Construction Agreement, General Contract Conditions, Supplementary Conditions, Asbestos Management Plan Contractor Responsibility Form, Drawings and Specifications, tests and engineering data, approved Change Orders, Contractor’s Requests for Payment, Architect’s Certificates, and all addenda issued by the Owner or Architect prior to execution of the Construction Agreement and all modifications issued by the Owner or Architect after execution of the Construction Agreement. With respect to the Contract Documents, the following definitions and understandings shall control: 1.01 “Contract” or “Contract Documents” shall include all of the items enumerated in GC-1.00 above. 1.02 “Owner” shall mean Boulder Valley School District No. RE-2, and shall include its duly authorized representatives. 1.03 “Contractor” shall mean the corporation, company, partnership, firm, entity, or individual named and designated as such in the Construction Agreement, and any persons or entities acting on its behalf. 1.04 “Subcontractor” shall mean any corporation, partnership, entity, or individual having a direct contract with the Contractor or another subcontractor for performing Work and/or furnishing labor or material on the Project covered by the Contract. 1.05 “Architect” shall mean the corporation, partnership, entity or individual named and designated as “architect” or “engineer” in the Construction Agreement, and any persons or entities acting on the Architect’s behalf and within the scope of the particular duties properly entrusted to them in each case. In the event that there is no Architect on the Project, then “Architect” shall refer to Owner and its duly authorized representative. 1.06 “Notice to Contractor” shall be deemed to have been duly served if made in writing and delivered in person to the individual or to a member of the firm or to an officer of the corporation for which it is intended, or if sent by registered or certified mail, to Contractor’s last known business address. 1.07 “The Work” shall mean the construction and services required by the Contract Documents for completion of the Project, and includes all labor, materials, equipment and services provided or to be provided by the Contractor to fulfill the Contractor’s obligations, whether on or off the Project site, and all labor, materials equipment and services provided or to be provided by subcontractors, sub-subcontractors, or any other entity for whom the Contractor is responsible. 1.08 “The Project” is the total construction designed by the Architect of which the Work performed under the Contract Documents may be the whole or a part. 1.09 The “date of final completion” and “finally completed” shall mean the date when construction is certified by the Architect to be finally completed in accordance with the Contract Documents, as modified by any Change Orders processed under the terms of GC-23.00 below and when the Owner has fully accepted the Project for the use for which it was intended. Such date will be set forth on a letter of acceptance issued by the Owner. 1.010 “Drawings” or “plans” shall mean all (a) drawings furnished by the Owner and/or Architect as a basis for the award of Contract and for construction of the Project; (b) supplementary drawings furnished by the Owner and/or Architect to clarify and to define in greater detail the intent of the Contract drawings and specifications; (c) drawings submitted by the successful Contractor as may be required after the Contract is awarded; (d) drawings furnished by the Owner and/or Architect to the Contractor during the progress of the Work; and (e) engineering data and drawings submitted by the Contractor during the progress of the Work, provided such drawings are acceptable to the Architect and Owner. 1

1.011 “Specifications” are the written technical information concerning materials, components, systems, equipment, and manner of installation as indicated on the drawings or plans and which state the quality, performance, and characteristics to be achieved by application of construction methods. 1.012 “Change Order” shall mean a written order to the Contractor signed by the Owner or its authorized agent issued after the execution of the Construction Agreement, authorizing a change in the Work and/or adjustment in the Guaranteed Maximum Price (“GMP”) or the contract time schedule. Each adjustment in the GMP resulting from a Change Order shall clearly separate the amount attributable to the Cost of the Work and the Contractor’s Fee. 1.013 “day” or “days” shall mean calendar days. In computing a period of days, when the ending date is not specified, the first day is excluded and the last day is included. If any deadline falls on a Saturday, Sunday, or federal or Colorado state holiday, such deadline will be extended to the next day that is not a Saturday, Sunday or federal or Colorado state holiday. GC 2.00

REFERENCE STANDARDS

2.01 Reference to the standards of any technical society, organization, or association, or to codes of local or state authorities, shall mean the latest standard, code, specification, or tentative standard adopted and published as of the date of execution of the Construction Agreement, unless specifically stated otherwise. GC 3.00

DRAWINGS AND SPECIFICATIONS

3.01 Ownership of Drawings. All drawings, specifications, and copies thereof furnished by the Architect are the property of the Architect and the Owner, whether or not the Work for which they are made is performed, and are not to be used on other Work except by written agreement with the Architect and the Owner. 3.02 Figured Dimensions to Govern. Dimensions and elevations shown on the drawings shall be accurately followed. No Work shown on the drawings, the dimensions of which are not indicated, shall be executed until necessary dimensions have been obtained from the Architect. 3.03 Contractor to Check Drawings and Schedules. The Contractor shall check and verify all dimensions, elevations, and quantities shown on the drawings and furnished to it by the Architect, and shall notify the Architect of any discrepancy between the drawings and the conditions on the ground, or any error or omission in drawings, or in the layout as given by stakes, points, or instructions that it may discover. Before ordering any material or doing any Work, the Contractor shall verify all measurements concerning the Project and shall be responsible for the correctness of same. No extra charge or compensation shall be allowed on account of any difference between actual dimensions and the measurements indicated on the drawings. Any difference that may be found shall be submitted to the Architect for consideration and written determination before proceeding with the Work. The Contractor shall not be allowed to take advantage of any error or omission in the drawings or Contract Documents. Full written instructions shall be furnished by the Architect should such error or omission be discovered, and the Contractor shall carry out such instructions as if originally specified. 3.04 Detail Drawings and Instructions. The Architect shall furnish with reasonable promptness additional instructions, by means of drawings or otherwise, necessary for the proper execution of the Work. All such drawings and instructions shall be consistent with the Contract Documents. The Work shall be executed in conformity with the Architect’s drawings and instructions, and the Contractor shall do no Work without proper drawings and instructions. 3.05 Drawings and Specifications Available on the Site. The Contractor shall maintain at the Project site for the Owner and the Architect a Project record set of drawings, including addenda, approved shop drawings, Change Orders, and other modifications, with all changes or deviations from the original drawings neatly marked thereon in a contrasting color. The Contractor shall also maintain a Project record set of specifications at the 2

Project site, noting therein by appropriate section the names, models, and other distinguishing characteristics of the materials actually incorporated into the Work. This Project record set of drawings and specifications shall be updated daily as the Project progresses and shall be made available to the Owner and Architect for inspection at all times. Upon final completion of the Work and before final payment, three (3) copies and one (1) electronic of this Project record set of drawings and specifications shall be delivered to the Owner. One (1) copy of this Project record set of drawings and specification shall be delivered to the Architect. 3.06 Laws and Regulations. The Contractor shall give all notices and comply with all laws, ordinances, rules, and regulations bearing on the conduct of the Work as drawn and specified. If the Contractor observes that the drawings and specifications are at variance therewith, it shall promptly notify the Architect in writing, and any necessary adjustments shall be made as provided in the Contract for changes in the Work. If the Contractor performs any Work knowing it to be contrary to such laws, ordinances, rules, or regulations without giving the required notice to the Architect and receiving a written directive to proceed, it shall bear all costs arising therefrom and to correct and/or remedy same. GC 4.00

ROYALTIES AND PATENTS

The Contractor shall pay all royalties and license fees. The Contractor shall defend all suits or claims for infringement of patent rights and shall hold the Owner harmless from any and all liability or loss on account thereof. If the Contractor has information that the process or article specified involves the infringement of a patent, it shall be responsible for any and all liability or loss resulting therefrom unless it promptly furnishes such information to the Architect in writing. GC 5.00

ITEMS COVERED BY CONTRACT PRICE

5.01 Items Supplied by Owner. Owner shall supply the following items for the Project: a. Building Permit; b. Initial Survey; c. Materials Testing Including Soil Testing; d. Third Party Inspections; e. Commissioning; and f. Test and Balance as Required for Commissioning. 5.02 Items Supplied by Contractor. Unless specifically stated otherwise, the Contractor shall accept the compensation stated in the Construction Agreement as full payment for furnishing all the materials, transportation, apparatus, temporary structures, equipment, services, fuel, energy, light, water, labor and tools, and all other things necessary for the complete and proper execution of the Work contemplated by or reasonably implied from the Contract Documents, within the time limits indicated therein. Such amount shall include any loss or damage resulting from the nature of the Work, from the elements or from any unforeseen difficulties that may be encountered; all risks of every description connected with the prosecution of the Work; all expenses incurred in consequence of any suspension or discontinuance of the Work; and all other amounts necessary for completing the Work pursuant to the Contract Documents within the time limits indicated therein. GC 6.00

EXECUTION, CORRELATION, INTENT, AND INTERPRETATION OF CONTRACT DOCUMENTS

6.01 Execution. The Construction Agreement and other Contract Documents shall be signed in multiple copies as directed by the Owner. Within ten (10) days of Notice of Award, the Contractor shall submit to the Owner a minimum of five (5) fully executed original sets of the Construction Agreement; Performance Bond, and Labor and Material Payment Bond with original Power of Attorney; and certificates of required insurance coverage. The date of the Contract for purposes of these documents shall be the date of the Notice of Award letter. The Owner shall execute the Construction Agreement, assemble all copies, and distribute the Contract Documents. The Contractor shall not commence the Work until it receives the Notice to Proceed. All bonds and insurance 3

certificates shall be submitted to the Owner prior to the award of the first subcontract. 6.02 Correlation. By executing the Construction Agreement, the Contractor represents that it has visited the Project site, familiarized itself with the local conditions under which the Work is to be performed, and correlated its observations with the requirements of the Contract Documents. 6.03 Intent. The intention of the Contract Documents is to include all labor and materials, tools, equipment, construction equipment, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution and completion of the Work. Materials or Work described in words that, as applied, have a well-known technical or trade meaning shall be held to refer to such recognized meaning. The organization of the specifications into divisions, sections, and articles, as the case may be, and the arrangement of drawings shall not control the Contractor in dividing the Work among subcontractors or in establishing the extent of Work to be performed by any trade. It is intended that even though Work is not covered under any heading, division, section, article, branch, class, or trade of the specifications, it shall nevertheless be supplied if it is required elsewhere in the Contract Documents or is reasonably inferable therefrom as being necessary to produce the intended results. The specifications and drawings are intended to supplement but not necessarily duplicate each other. Any Work exhibited in the one and not in the other shall be executed as if it had been set forth in both, so that the Work will be constructed according to the complete design as determined by the Architect. 6.04 Interpretation. Should anything necessary for a clear understanding of the Work be omitted from the specifications and drawings, or should the requirements appear to be in conflict, the Contractor shall secure written interpretations or instructions from the Architect before proceeding with the Work affected thereby. The Contractor shall secure written interpretations or instructions by submitting the Owner’s form Request for Interpretation to the Architect. Oral requests shall not be acknowledged by the Architect or Owner. Additional costs incurred by the Owner as a result of unnecessary requests made by the Contractor, as determined by the Owner, shall be the responsibility of the Contractor. It is understood and agreed that the Work shall be performed according to the true intent of the Contract Documents. 6.05 Conflict in Interpretation. In the case of discrepancy or in the event of a conflict between the different Contract Documents, the documents shall take precedence in the following order: a. Change Orders; b. Written Amendments to Construction Agreement (including, if applicable, the GMP); c. Construction Agreement; d. General Conditions; e. Drawings and specifications; and f. Bid Documents, including addenda. Where two or more of the Contract Documents are complementary, the more detailed provision shall control over the more general provision. GC 7.00

MATERIALS, LABOR, FACILITIES, AND STORAGE

7.01 Contractor’s Responsibility. Unless otherwise agreed in writing, the Contractor shall provide and pay for all materials, labor, tools, equipment, machinery, transportation, and other facilities necessary for the proper execution and completion of the Work. The Contractor shall provide and pay for all the temporary facilities required to supply all the power, light, water, and heat needed by it and its subcontractors for their Work and shall install and maintain all such facilities in such manner as to protect the public and workers and to conform with any applicable laws and regulations. If temporary heat and/or protection is required for the expeditious prosecution of the Work and before the permanent heating apparatus is available for use, the temporary heating apparatus shall be installed and operated in such a manner that the finish Work and/or construction will not be damaged thereby. Unless otherwise specified, the Contractor shall pay for all the power, light, and water used by it and its subcontractors, without regard to whether such items are metered by temporary or permanent meters. The cutoff date on permanent meters shall be either the agreed date of full occupancy by 4

the Owner or the date of final acceptance of the Project, whichever shall be the earlier date. Upon completion of the Work, the Contractor shall remove all surplus materials, tools and such temporary facilities and structures, furnished by the contractor from the Project site. All debris and rubbish caused by the operations of the contractor shall be removed, and the area occupied during construction activities shall be restored to its original condition, within 48 hours of project completion, unless otherwise directed by the municipality or owner’s representative. 7.02 Materials. Unless otherwise specified, all materials shall be new and both Workmanship and materials shall be of the highest quality. The Contractor shall furnish satisfactory evidence to the Owner as to the kind and quality of materials. Samples shall be furnished, when specified, and the Work shall be in accordance with those samples that have been approved. 7.03 Toilet Facilities. The Contractor shall provide and maintain, in a neat and sanitary condition, adequate temporary toilet facilities for the use of any and all employees engaged on the Work, in strict compliance with the requirements of all applicable codes, regulations, laws, and ordinances. In no event may present toilet facilities of any existing building at the site of the Work be used by employees of the Contractor or its subcontractors. Upon final completion of the Work, the Contractor shall remove all such temporary facilities from the site and disinfect the premises. 7.04 Facilities and Storage. The Contractor shall provide suitable temporary facilities and quarters for workers, as needed, and shall maintain on premises water-tight storage sheds or tool houses for storage of building materials and tools that could be damaged by weather. The Contractor shall allow space for the erection of sheds and provide similar facilities for storage by subcontractors of their materials and tools. Storage of materials shall be confined to the site. These facilities or quarters shall further provide for protection against theft and damage of building materials and tools. Upon final completion of the Work, the Contractor shall remove all such temporary facilities from the site. 7.05 Office Space. The Contractor shall provide adequate, weatherproofed, heated and well- lighted office space at the site of the Work, for use by the Architect and the Owner and their representatives. The Contractor shall also provide telephone service at such office, which shall be available for use by the Architect, the Owner, and their representatives without charge, except for toll calls. 7.06 Quality and Location of Facilities. All of the foregoing facilities shall be of a quality and placed in locations acceptable to the Architect and the Owner. GC 8.00

PERFORMANCE AND PAYMENT BONDS

8.01 Required Bonds. The Contractor shall, within ten (10) days from the Notice of Award furnish bonds to the Owner in the full amount of the contract price, covering both the faithful performance of the Contract and the payment of all obligations for labor and materials arising thereunder, on such customary forms as the Owner may prescribe and with such sureties as it may approve. The amount of the bonds shall be increased, if necessary, to reflect approved changes in the Work that result in an increase in the total cost of the Work plus the Contractor’s fees. Such bonds shall be duly executed by a qualified surety licensed to do business in the State of Colorado, conditioned upon the true and faithful performance of the Contract, and shall provide that if the Contractor or its subcontractors fail to duly pay for any labor, materials, or other supplies used or consumed by such Contractor or its subcontractors in the performance of the Work contracted to be done, the surety will pay the same in an amount not exceeding the sum specified in the bond, as adjusted by approved Change Orders, and together with interest as provided by law. The performance bond shall additionally guarantee that the Contractor shall remedy any omissions, correct any and all defects, and adjust and make operable all component parts of Work falling under the requirements of the Contract that may be called to the Contractor’s attention within a period of twenty-four (24) months following the date of the letter of acceptance.

5

8.02 Additional Bond Requirements. The premium for all bonds shall be paid by the Contractor and included in the bid price in the bid proposal. The Owner will accept and approve bonds written by sureties legally authorized to write such bonds in the State of Colorado, provided such surety companies are rated in Best’s Insurance Guide (latest edition), not lower than A- or have Best’s Financial Rating of at least X. If, at any time a surety on such a bond becomes irresponsible or loses its right to do business in the State of Colorado, new bonds shall be provided by an alternate surety licensed to do business in the State and meeting the requirements of this Section 8.00. GC 9.00

PERMITS AND COMPLIANCE WITH STATUTES, RULES, AND REGULATIONS

9.01 Permits. Any local permits, governmental fees, and licenses necessary for the proper execution and completion of the Work shall be secured and paid for by the Contractor. Owner will pay for and secure building permit from Colorado Division of Fire Prevention and Control. Easements for permanent structures or permanent changes in existing facilities shall be secured and paid for by the Owner, unless otherwise specified in writing. The Owner is generally exempt from paying any fee for any building permit issued by any building departments or agencies located in Boulder, Broomfield, and Gilpin Counties, and the Contractor shall see that no building permit fee is paid. The Owner shall negotiate and provide for all electrical, gas, water, and sewer mains for the Contractor’s connections. The Contractor shall arrange with the utility company for actual connection, make necessary connections, and pay for all associated inspection fees and permits as required by any government agency. In addition, the Contractor shall furnish all material and items required to complete all connections. The Contractor shall call for all inspections on a timely basis by any agency having jurisdiction over the Work. 9.02 Compliance with Statutes, Rules and Regulations. The Contractor and all subcontractors shall comply with all applicable federal and state statutes, rules, regulations, and directives of the State Division of Fire Prevention and Control, and other governmental body having jurisdiction over the work to be performed. If any of the provisions of the Contract Documents are in conflict therewith, such portions shall be considered stricken and the applicable statute, ordinance, regulation, or ruling substituted therefor. All such cases of apparent conflict coming to the attention of any party shall immediately be called to the attention of the Owner. The Contractor shall strictly observe and comply with all federal and state laws pertaining to the employment and payment of labor. GC 10.00

SURVEYS, BENCHMARKS, MONUMENTS, STAKES, AND MEASUREMENTS

10.01 Surveys. As provided by the Owner, the Contractor shall obtain from the Architect a copy of all surveys describing property lines, elevation benchmarks, physical characteristics, and utility locations. 10.02 Benchmarks. The Contractor shall properly stake out the Work and provide and rigidly set benchmarks and batter boards as necessary for the proper performance of the Work. The Contractor shall remain responsible for their maintenance and their accuracy. A permanent benchmark, approved as to location and type by the Architect, from which all grades are to be taken, shall be established near the site of the Work by the Contractor. From this benchmark the Contractor shall ascertain all grades and levels to Project buildings as needed. The Contract Documents shall include all necessary information to establish the benchmark. 10.03 Preservation of Monuments and Stakes. The Contractor shall carefully preserve all monuments, benchmarks, property markers, reference points, and stakes. In case of the destruction thereof, the Contractor shall be charged with the expense of replacement and shall be responsible for any mistake or loss of time that may be caused. Permanent monuments and/or benchmarks that must be removed or disturbed shall be protected until properly referenced for relocation. The Contractor shall furnish all materials, labor and assistance for the proper replacement of such monuments and benchmarks. 10.04 Measurements. Before ordering any material or performing any Work, the Contractor shall verify all measurements on the Project and shall be responsible for the accuracy of same. No extra charge or 6

compensation shall be allowed because of any difference between actual dimensions and the measurements indicated in the drawings or specifications. Any discrepancies shall be submitted to the Architect and Owner for consideration before proceeding with the Work. GC 11.00

CHANGED CONDITIONS

The Contractor shall promptly, and before such conditions are disturbed, notify the Owner and the Architect in writing of: (1) sub-surface or latent physical conditions at the Project site differing materially from those indicated in the Contract Documents, or (2) unknown physical conditions at the Project site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in Work of the character provided for in the Contract Documents. The Owner and the Architect shall promptly investigate the conditions, and if the Owner finds that such conditions do so materially differ and cause an increase or decrease in the cost of or the time required for performance of the Work, an equitable adjustment shall be made and the Contract modified in writing accordingly. Any claim of the Contractor for adjustment hereunder shall not be allowed unless it has given notice as required. GC 12.00

PROTECTION OF PERSONS, WORK AND PROPERTY

12.01 Building Exits and Barricades. During the course of construction, the Contractor shall keep all required building exits free and unimpeded. Such exits shall not be closed at any time for any reason while the building is occupied or at any time when the building is unoccupied, except after written approval is given by the Owner and proper warning and directional signs are posted. Barricades shall be erected so that traffic is separated and protected from the construction. 12.02 Precautions. The Contractor shall take all necessary precautions to ensure the safety of all employees and other persons on the Project or who may be affected by the Contractor’s Work thereon. The Contractor shall also take all necessary precautions to protect the Work and all temporary facilities, as well as materials, tools, and equipment incorporated therein or to be incorporated therein from damage or destruction, whether in storage on or off the Project site and whether in the custody or control of the Contractor or any of its subcontractors. The Contractor shall also take all necessary precautions to protect all property at the Project site and adjacent thereto not designated for removal, relocation or replacement, including trees, shrubs, lawns, walks, pavements, roadways, structures, and utilities. 12.03 OSHA Compliance. The Contractor shall comply with all applicable provisions of the Occupational Safety and Health Administration (“OSHA”) and all laws, ordinances, rules, regulations, and orders of all governmental agencies or authorities having jurisdiction to protect the safety of employees and/or other persons who may be affected by the Work. The Contractor shall erect and maintain all necessary safeguards to protect workers on the Project site and the owners and users of adjacent property, and shall post danger signs and other warnings against hazards created by the Work including but not limited to protruding nails, hoists, well holes, elevator shafts, hatchways, scaffolding, window openings, stairways, excavations, and falling materials. The Contractor shall designate a responsible employee at the Project site as a safety officer to ensure the Contractor’s compliance with this section. Said employee shall be the Contractor’s superintendent unless otherwise designated in writing by the Contractor to the Owner and the Architect. 12.04 Contractor’s Liability. The Contractor shall be liable for all injury, damage or loss to any person or property caused in whole or in part by the Contractor, any of its subcontractors, or any person employed by or under the direction of the Contractor or any of its subcontractors. To the extent possible and unless otherwise directed by the Owner or Architect, the Contractor shall promptly repair, pay for or otherwise remedy any such injury, damage or loss and shall indemnify and hold harmless the Owner against any and all liability, claims, damages, losses and expenses arising therefrom. The terms of this section shall not apply in the case of injury, damage or loss proximately caused by the acts or omissions of the Owner and/or Architect and not attributable to any fault or negligence of the Contractor.

7

12.05 Emergencies. In the event of an emergency that threatens the safety or life of any person or threatens to damage or destroy the Project and/or any Work, materials, equipment or property thereon or to be used thereon, the Contractor shall act at its discretion to prevent such injury, death, damage or destruction. The Contractor shall immediately notify the Owner and Architect in writing of any such emergency and any action taken by the Contractor in response thereto. Any compensation due the Contractor for such emergency action shall be determined by agreement of the Contractor, Owner and Architect, and an appropriate Change Order shall be issued therefor. GC 13.00

WORK ON EXISTING BUILDINGS

13.01 Protection of Occupants. In addition to all other requirements of the Contract Documents, if the Work involves an addition or alteration to an existing building, the Contractor shall erect and maintain during the progress of the Work suitable dustproof partitions to protect such building and the occupants thereof. If necessary, in the Owner’s or Contractor’s judgment or pursuant to manufacturer’s directives or recommendations in order to protect occupants from noxious fumes, odors, or hazardous substances, the Contractor may be required to provide additional ventilation and/or work different or extended hours to avoid disruption to other activities within the existing building. Contractor shall protect and keep from harm all occupants of an existing building from construction activities, and shall include a safe pathway into and out of the school. 13.02 Partitions and Scheduling. If any portions of an existing building are to be remodeled or repaired, such portions shall be adequately partitioned off with dustproof partitions and well ventilated. All remodeling Work shall be scheduled and submitted to the Owner and Architect for approval. The various contractors shall schedule their Work jointly, in order that each may accomplish its Work within such existing building in an orderly fashion during regular school vacation periods where possible, or in such a manner as to permit full use of the building and without impairment of any existing facilities. 13.03 Existing Systems. Existing building systems, such as fire alarm, temperature controls and air distribution, security systems, public announcement systems, irrigation systems, and the like, shall be demonstrated and noted by Owner to the Contractor as operational prior to Contractor’s commencing the Work and Contractor may participate in observation of such systems. Such systems are the responsibility of the Contractor to maintain in pre-construction condition. GC 14.00

CONTRACTOR’S SUPERINTENDENCE AND SUPERVISION

14.01 Superintendent. During the progress of the Work, the Contractor shall ensure that a competent superintendent and any necessary assistants, all satisfactory to the Architect and the Owner, are on the Project site at all times while Work is in progress. The superintendent shall not be changed by the Contractor except with the written consent of the Architect and the Owner, unless the superintendent ceases to be in the Contractor’s employ. The superintendent shall represent the Contractor on the Project and all directions given to him/her shall be as binding as if given to the Contractor. The Architect and the Owner shall not be responsible for the acts or omissions of the superintendent or his/her assistants. 14.02 Supervision. The Contractor shall provide full-time, qualified, and efficient supervision of the Work, using competent skill and attention. The Contractor is responsible for determining and supervising all temporary and permanent erection and construction sequences, techniques, means, or methods. The Contractor shall direct, schedule, coordinate the Work to ensure that all parts fit together properly and in accordance with the Contract Documents. The Contractor shall carefully study and compare all Contract Documents and other instructions and shall at once report to the Architect and the Owner any error, inconsistency, or omission that Contractor may discover. 14.03 Additional Supervision Duties. The Contractor shall see that the Work is carried out in accordance with the Contract Documents and in a thorough and first-class manner in every respect. The Contractor shall 8

provide engineering, surveying, and coordination to accurately establish all lines, levels, and marks necessary to facilitate the operations of all parties involved in the Contractor’s Work. The Contractor shall lay out the Work in a manner satisfactory to the Architect, making permanent records of all lines and levels required for excavation, grading, and foundations, and for all other parts of the Work. The Contractor shall be responsible for the commencement and the proper completion of the various stages and sequences of construction. The Contractor shall strictly adhere to the approved construction schedule. GC 15.00

SUBSTITUTIONS

The Contractor shall be held to have used in its base proposal and to furnish under the Contract those items of equipment and/or materials that are specifically identified in the plans and specifications by a manufacturer’s name, model, or catalog number. Items of equipment and/or materials of the Contractor’s choice may be offered as alternates to the items named in the plans and specifications by submitting, with the proposal and on the form provided, identifying data on the articles proposed together with a statement of the amount of addition or deduction from the base bid if the bidder’s alternate is accepted. Prior approval by the Architect is not required on items submitted as alternate bids. After execution of the Construction Agreement, substitution of equipment and/or materials of makes other than those specifically named in the Contract Documents may be approved by the Owner so long as the equipment or material proposed for substitution in the opinion of the Owner is just as suitable as the equipment and/or materials named in the plans and specifications so far as performance, construction, efficiency, and utility are concerned. A request for substitution shall ordinarily be required to be based upon one or more of the following grounds: the specified equipment or material is no longer available, a substitution will improve lead time, quality will be improved (documented detail required), or the Owner will incur substantial savings. All requests for substitution must be submitted in writing with supporting documentation by or through the Contractor to the Architect for initial review and recommendation before being submitted to the Owner for evaluation and final approval. In the absence of the Owner’s written approval, no substitution of equipment or materials shall be allowed for any items specified in the Contract Documents. In case of a difference in price, occurring as a result of an approved substitution, the Owner shall receive all benefit of the difference in cost involved in the substitution. All approved substitutions shall be documented by the issuance of a formal Change Order as provided in these General Conditions. GC 16.00

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

16.01 Shop Drawings. “Shop drawings” are drawings, diagrams, illustrations, schedules, performance charts, brochures, manufacturer’s literature, and other data that are prepared by the Contractor or any subcontractor, manufacturer, supplier, or distributor, and that illustrate some portion of the Work. Shop drawings shall be submitted in both hard copy and electronic format. 16.02 Samples. “Samples” are physical examples furnished by the Contractor to the Owner and/or Architect to illustrate materials, finishes, equipment, or Workmanship, and to establish standards by which the Work will be judged. 16.03 Product Data. “Product data” are illustrations, standard schedules, performance charts, instructions, brochures, diagrams and other information furnished by the Contractor to illustrate materials or equipment for some portion of the Work. Product data shall be submitted in both hard copy and electronic format. 16.04 Contractor’s Obligations. The Contractor shall review, approve, stamp an then submit to the Architect shop drawings, product data, samples, and similar submittals required by the Contract Documents with reasonable promptness and in such a sequence as to cause no delay in the Work or in the activities of the Owner or of separate contractors. Shop drawings, product data, samples, and similar submittal required by the Contract Documents shall properly identify specified items. At the time of submission, the Contractor shall inform the Architect in writing of any deviation in the shop drawings, product data, or samples from the requirements of the Contract Documents. Substitutions will be allowed only in accordance with the provisions of GC-15.00. The number of copies and format of submittal shall be as required by the Architect, but, at a 9

minimum, shall include three (3) copies and one (1) electronic copy of the original shop drawings and product data for the Owner. 16.05 Verification. By approving and submitting shop drawings, product data, and samples, the Contractor thereby represents that it has determined and verified all field measurements, field construction criteria, dimensions, elevations, quantities, materials, catalog numbers, and similar data, as shown on the drawings and specifications furnished by the Architect, or will do so, and that it has checked and coordinated each shop drawing, product data, and sample with the requirements of the Work and of the Contract Documents. 16.06 Architect /Owner Review. The Architect shall review and approve shop drawings, product data, and samples with reasonable promptness so as to cause no delay, but only for conformance with the design concept of the Project and with the information given in the Contract Documents. The Architect’s approval of a separate item shall not indicate approval of any assembly in which the item functions. Upon the final completion of the Work, the Contractor shall furnish to the Architect two corrected copies of all shop or setting drawings showing the as-built condition of the Work. The Architect, after review, shall submit one of these copies to the Owner. 16.07 Corrections. The Contractor shall make any corrections required by the Architect and shall resubmit the required number of corrected copies of shop drawings or new samples until approved by the Architect. The Contractor shall direct specific attention in a separate writing or on resubmitted shop drawings to revisions other than the corrections requested by the Architect on previous submissions. 16.08 Contractor’s Responsibility. The Architect’s approval of shop drawings, product data, or samples shall not relieve the Contractor of responsibility for any deviation from the requirements of the Contract Documents unless the Contractor has informed the Architect in writing of such deviation at the time of submittal and the Architect has given written approval of the specific deviation. The Architect’s approval shall also not relieve the Contractor from responsibility for errors or omissions in the shop drawings, product data, or samples. 16.09 Architect Approval Required. No portion of the Work requiring the submission of a shop drawing, product data, or sample shall be commenced until such submittal has been approved in writing by the Architect. All such portions of the Work shall be in accordance with approved shop drawings, product data, and samples. All material finishes and samples shall be approved at one time. The Contractor shall submit all items requiring approval of finishes, color, material, etc., with sufficient lead time to allow simultaneous consideration and preparation of complete finish color schedule. No approvals of single items shall be considered. 16.010 Copies to Owner. When shop drawings, product data, samples or similar submittals have been approved and stamped by both Contractor and Architect, Contractor shall immediately forward an electronic copy of each to the Owner. GC 17.00

CASH ALLOWANCE

The Contractor shall include in the Contract sum all allowances named in the Contract Documents and shall cause the work so covered to be done by such Contractors and for such sums as the Owner may direct, the Contract sum being adjusted in conformity therewith. The Contractor declares that the Contract sum includes such sums for expenses and profit on account of cash allowances as he deems proper. No demand for expenses or profit other than those included in the Contract sum shall be allowed. The Contractor shall not be required to employ for any such work persons against whom he has filed a lien or has a reasonable objection due to previous legal claims. GC 18.00

EXPEDITING MATERIALS 10

The Contractor shall, immediately after receipt of the Notice of Award and approval of its list of subcontractors and material suppliers, place orders for all equipment, materials, and supplies required for the Work. The Contractor shall, when requested, submit to the Architect evidence that such orders have been placed. The Contractor shall exercise due diligence in seeing that all equipment, materials, and supplies are delivered well in advance of the time they are needed on the Project and shall properly store and protect same at its expense and in accordance with these General Conditions, either at the Project site or elsewhere as approved by the Architect. GC 19.00

BLASTING

No explosives of any nature except for those normally employed in powder actuated tools, .38 caliber or smaller, shall be employed or used on the Project site except with the express and specific prior written approval of the Architect and the Owner and any appropriate governmental authorities, in each instance. The Contractor shall notify the Architect of need for such approval three (3) days prior to the proposed use of such explosives. GC 20.00

SOIL TEST REPORT

The Owner may arrange for a separate consultant to conduct field and laboratory soil investigations on the Project site and to prepare a report of its findings. Such a report, if prepared, shall be available for review by the Contractor in the Architect’s office. Such data is offered solely for reference and is not to be considered a part of the Contract Documents. The data contained in any such document prepared for the Owner by a separate consultant is believed to be reliable; however, the Owner and Architect do not guarantee its accuracy or completeness. All applicable subcontractors shall be fully familiar with the contents of such reports, if prepared, and shall consider and evaluate them in the performance of their contracts and the Work. GC 21.00

HAZARDOUS MATERIALS

21.01 Responsibility and Reporting. Unless otherwise provided in the Contract Documents, the Contractor shall have no responsibility for the presence, handling, removal or disposal of hazardous materials in any form at the Project site, including but not limited to asbestos, asbestos products, polychlorinated biphenyl (PCB), lead, or other hazardous materials. Prior to its commencement or continuation of any portion of the Work, the Contractor shall provide notice to the Owner of the presence, location, amount and condition of any known or suspected hazardous materials that are discovered at the Project site. Such notice shall be in writing and shall be submitted no more than twenty-four (24) hours after the presence of such materials becomes known or suspected. 21.02 Contractor’s Obligations. In the event hazardous materials become known or suspected by the Contractor as described in GC-21.01 above, the Contractor shall not proceed with or continue the Work until it has received written authorization from the Owner. If the Contractor proceeds with the Work without said authorization, it assumes any and all responsibility and liability for contamination and cleanup at the Project site according to applicable federal and state laws, and for any death or personal injury, including but not limited to medical expenses that may be incurred by any individual as a result of exposure to hazardous materials on the Project site. 21.03 Owner’s Obligations. In the event hazardous materials are identified or encountered during the course of the Project, the Owner at its expense shall take reasonable actions to properly and safely deal with such materials. 21.04 Management Plan. The Contractor acknowledges that it and its employees, agents and subcontractors have the responsibility of being fully informed of the Owner’s Management Plan as it relates to buildings located at the Project site and shall consult with the Owner about how such Plan addresses suspected or active asbestos-containing material areas within such buildings. GC 22.00

DAMAGE TO UTILITIES 11

22.01 Adequate Precautions. The Contractor shall take adequate precautions to protect existing utilities on and off the Project site and avoid damage thereto. The Contractor shall repair or replace or have repaired or replaced at its expense any damage to streets, water, sewer, light, power, cable, or telephone lines or fiber network that are damaged by reason of the Contractor’s Work. 22.02 Location. The location and extent of underground utilities, fiber network, cables and conduit indicated on the drawings are not guaranteed. This information is shown only for such use as bidders and contractors may choose to make of it. The Contractor shall check with all public utility companies for locations and shall comply with their regulations regarding such utilities in performing the Work. 22.03 Protection from Damage. The Contractor shall adequately protect active underground utilities from damage, and if damaged shall immediately effect all necessary repairs. Removal or relocation of active underground utilities shall be done only as indicated on the drawings. If such utilities are in use, they shall be maintained in continuous service. If not indicated on the drawings or not known to exist, the Contractor shall report discovery of such utilities to the Architect and shall not proceed further until directed to do so. 22.04 Inactive or Abandoned Utilities. Inactive or abandoned utilities, whether or not they are indicated on the drawings, shall be recorded as to location and depth and shall be removed for a distance of not less than three (3) feet from the outside line of all concrete Work unless otherwise required by regulations. Ends shall be capped or plugged. There shall be no adjustment of the Contract amount for Work due to inactive or abandoned utilities. GC 23.00

CHANGES IN THE WORK

23.01 Change Orders. The Owner, without invalidating the Agreement, may order changes in the Work within the general scope of the Project consisting of additions, deletions, or other revisions. Under such circumstances, the GMP, if applicable and established, and the Contract Time Schedule shall be adjusted accordingly. All such changes in the Work shall be authorized by Change Order. No Change Order or other form of order or directive by the Owner or Architect requiring additional compensable Work to be performed, which causes the aggregate amount payable under the Contract Documents to exceed the amount appropriated for the original Agreement, shall be issued unless the Contractor is given written assurance by the Owner that lawful appropriations to cover the costs of the additional Work have been made. Any claim of the Contractor for adjustment under this section must be asserted in writing within ten (10) days from the date of the Contractor’s receipt of the Change Order. 23.02 Minor Changes. The Architect shall have authority to order minor changes in the Work not involving an adjustment in the GMP or an extension of the Contract Time Schedule and not inconsistent with the intent of the Contract Documents. Such changes may be effected by field order or by other written order. Such changes shall be binding on the Owner and the Contractor. In any emergency affecting the safety of persons or property, the Contractor shall act, at his discretion, to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in this Article. 23.03 Price Differential. The cost or credit resulting from a change in the Work shall be determined in one or more of the following ways: a. By estimate, with a detailed cost breakdown as set forth in GC-23.03(c) below, and acceptance in a lump sum, with a maximum combined markup to the Owner, for the Contractor and all affected subcontractors, not to exceed a total of fifteen percent (15%). b. By unit prices named in the Contract or subsequently agreed upon. c. If the parties are unable to agree on one of the above methods, then the amount shall be determined by force account under the following formula: i. The actual cost of all direct labor performed (including foremen employed continuously on the Work, but not the salary, or any part thereof, of the Contractor’s superintendent) and the actual 12

ii. iii. iv. v.

vi.

GC 24.00