BVSD Kohl ES Renovation - CMGC Amendment Exhibits A-P.pdf (4,668 KB)

Regular Meeting, November 10, 2026 · item 7.8: Amendment to the contract for Kohl Elementary School · 92 pages

Open the original file

This is the text extracted from the file, without its layout, tables, or images. Use the original for anything that matters.

Exhibit A Drawings, specifications and documents used to prepare the GMP

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Printed on Thu Oct 22, 2026 at 03:11 pm MDT

EXHIBIT A

BVSD Kohl ES Palace Construction

Current Drawings Drawing Number

Drawing Title

Revision

Drawing Date

Received Date

Set

Status

General G000

COVERSHEET

0

09/11/2026

09/11/2026

100% CD Set

Published

G101

OVERALL CODE PLAN

0

09/11/2026

09/11/2026

100% CD Set

Published

C100

GENERAL NOTES

0

09/11/2026

09/11/2026

100% CD Set

Published

C200

PROJECT KEY MAP

0

09/11/2026

09/11/2026

100% CD Set

Published

C201

SITE DEMOLITION PLAN

0

09/11/2026

09/11/2026

100% CD Set

Published

C300

SITE IMPROVEMENTS PLAN

0

09/11/2026

09/11/2026

100% CD Set

Published

C301

SITE IMPROVEMENTS PLAN

0

09/11/2026

09/11/2026

100% CD Set

Published

C400

CONSTRUCTION DETAILS

0

09/11/2026

09/11/2026

100% CD Set

Published

A001

GENERAL NOTES, SYMBOLS, & ABBREVIATION

0

09/11/2026

09/11/2026

100% CD Set

Published

A002

TYPICAL MOUNTING HEIGHTS SHEET (FLOOR MOUNTED)

0

09/11/2026

09/11/2026

100% CD Set

Published

A101

OVERALL FLOOR PLAN - MAIN LEVEL

0

09/11/2026

09/11/2026

100% CD Set

Published

A101A

FLOOR PLAN - MAIN LEVEL - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

A101B

FLOOR PLAN - MAIN LEVEL - AREA B

0

09/11/2026

09/11/2026

100% CD Set

Published

A101C

FLOOR PLAN - MAIN LEVEL - AREA C

0

09/11/2026

09/11/2026

100% CD Set

Published

A101D

FLOOR PLAN - MAIN LEVEL - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

A141

ROOF PLAN

0

09/11/2026

09/11/2026

100% CD Set

Published

A142

ROOF DETAILS

0

09/11/2026

09/11/2026

100% CD Set

Published

A143

ROOF DETAILS

0

09/11/2026

09/11/2026

100% CD Set

Published

A144

ROOF DETAILS

0

09/11/2026

09/11/2026

100% CD Set

Published

A151

OVERALL RCP - MAIN LEVEL

0

09/11/2026

09/11/2026

100% CD Set

Published

Civil

Architectural

Page 1 of 5

Printed on Thu Oct 22, 2026 at 03:11 pm MDT

EXHIBIT A

BVSD Kohl ES Palace Construction

Drawing Number

Drawing Title

Revision

Drawing Date

Received Date

Set

Status

A600

DOOR SCHEDULE & EXTERIOR DETAILS

0

09/11/2026

09/11/2026

100% CD Set

Published

A721

INT. ELEVATIONS & CASEWORK DETAILS

0

09/11/2026

09/11/2026

100% CD Set

Published

AD101

OVERALL DEMOLITION PLAN

0

09/11/2026

09/11/2026

100% CD Set

Published

AD102

OVERALL DEMOLITION RCP

0

09/11/2026

09/11/2026

100% CD Set

Published

FS101

KITCHEN EQUIPMENT

0

09/11/2026

09/11/2026

100% CD Set

Published

FS102

KITCHEN EXHAUST HOOD

0

09/11/2026

09/11/2026

100% CD Set

Published

FS501

KITCHEN GENERAL NOTES - DETAILS

0

09/11/2026

09/11/2026

100% CD Set

Published

S001

GENERAL NOTES

0

09/11/2026

09/11/2026

100% CD Set

Published

S002

GENERAL NOTES

0

09/11/2026

09/11/2026

100% CD Set

Published

S003

LOAD KEYS

0

09/11/2026

09/11/2026

100% CD Set

Published

S101

STRUCTURAL FLOOR PLAN

0

09/11/2026

09/11/2026

100% CD Set

Published

S141

STRUCTURAL ROOF PLAN

0

09/11/2026

09/11/2026

100% CD Set

Published

S200

STRUCTURAL DETAILS

0

09/11/2026

09/11/2026

100% CD Set

Published

M000

HVAC COVERSHEET

0

09/11/2026

09/11/2026

100% CD Set

Published

M101A

LEVEL 01 PLAN - HVAC - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

M101B

LEVEL 01 PLAN - HVAC - AREA B

0

09/11/2026

09/11/2026

100% CD Set

Published

M101C

LEVEL 01 PLAN - HVAC - AREA C

0

09/11/2026

09/11/2026

100% CD Set

Published

M101D

LEVEL 01 PLAN - HVAC - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

M141A

ROOF PLAN - HVAC - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

M141B

ROOF PLAN - HVAC - AREA B

0

09/11/2026

09/11/2026

100% CD Set

Published

M141C

ROOF PLAN - HVAC - AREA C

0

09/11/2026

09/11/2026

100% CD Set

Published

M141D

ROOF PLAN - HVAC - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

Food Service

Structural

Mechanical

Page 2 of 5

EXHIBIT A

Printed on Thu Oct 22, 2026 at 03:11 pm MDT BVSD Kohl ES

Palace Construction

Drawing Number

Drawing Title

Revision

Drawing Date

Received Date

Set

Status

M142

ROOF PLAN - HVAC - ROOF REPLACEMENT

0

09/11/2026

09/11/2026

100% CD Set

Published

M400

HVAC DETAILS

0

09/11/2026

09/11/2026

100% CD Set

Published

M401

HVAC DETAILS

0

09/11/2026

09/11/2026

100% CD Set

Published

M500

HVAC CONTROLS

0

09/11/2026

09/11/2026

100% CD Set

Published

M501

HVAC CONTROLS

0

09/11/2026

09/11/2026

100% CD Set

Published

M600

HVAC SCHEDULES

0

09/11/2026

09/11/2026

100% CD Set

Published

M601

HVAC SCHEDULES

0

09/11/2026

09/11/2026

100% CD Set

Published

MD101A

LEVEL 01 DEMOLITION PLAN - HVAC - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

MD101B

LEVEL 01 DEMOLITION PLAN - HVAC - AREA B

0

09/11/2026

09/11/2026

100% CD Set

Published

MD101C

LEVEL 01 DEMOLITION PLAN - HVAC - AREA C

0

09/11/2026

09/11/2026

100% CD Set

Published

MD101D

LEVEL 01 DEMOLITION PLAN - HVAC - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

MD141C

ROOF DEMOLITION PLAN - HVAC - AREA C

0

09/11/2026

09/11/2026

100% CD Set

Published

MD141D

ROOF DEMOLITION PLAN - HVAC - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

P000

PLUMBING COVERSHEET

0

09/11/2026

09/11/2026

100% CD Set

Published

P101A

LEVEL 01 PLAN - PLUMBING - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

P101B

LEVEL 01 PLAN - PLUMBING - AREA B

0

09/11/2026

09/11/2026

100% CD Set

Published

P101C

LEVEL 01 PLAN -PLUMBING - AREA C

0

09/11/2026

09/11/2026

100% CD Set

Published

P102C

ROOF PLAN - PLUMBING - ROOF REPLACEMENT

0

09/11/2026

09/11/2026

100% CD Set

Published

P141D

ROOF PLAN - PLUMBING - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

P600

PLUMBING SCHEDULES

0

09/11/2026

09/11/2026

100% CD Set

Published

PD101A

LEVEL 01 DEMOLITION PLAN - PLUMBING - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

PD101B

LEVEL 01 DEMOLITION PLAN - PLUMBING - AREA B

0

09/11/2026

09/11/2026

100% CD Set

Published

PD101C

LEVEL 01 DEMOLITION PLAN - PLUMBING - AREA C

0

09/11/2026

09/11/2026

100% CD Set

Published

PD141D

ROOF DEMOLITION PLAN - PLUMBING - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

Plumbing

Page 3 of 5

EXHIBIT A

Printed on Thu Oct 22, 2026 at 03:11 pm MDT BVSD Kohl ES

Palace Construction

Drawing Number

Drawing Title

Revision

Drawing Date

Received Date

Set

Status

Electrical E000

ELECTRICAL COVERSHEET

0

09/11/2026

09/11/2026

100% CD Set

Published

E001

ELECTRICAL LIGHTING AND SYSTEMS COVERSHEET

0

09/11/2026

09/11/2026

100% CD Set

Published

E101A

LEVEL 01 PLAN - LIGHTING - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

E101B

LEVEL 01 PLAN - LIGHTING - AREA B

0

09/11/2026

09/11/2026

100% CD Set

Published

E101C

LEVEL 01 PLAN - LIGHTING - AREA C

0

09/11/2026

09/11/2026

100% CD Set

Published

E101D

LEVEL 01 PLAN - LIGHTING - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

E111A

LEVEL 01 PLAN - POWER AND SYSTEMS - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

E111B

LEVEL 01 PLAN - POWER AND SYSTEMS - AREA B

0

09/11/2026

09/11/2026

100% CD Set

Published

E111C

LEVEL 01 PLAN - POWER AND SYSTEMS - AREA C

0

09/11/2026

09/11/2026

100% CD Set

Published

E111D

LEVEL 01 PLAN - POWER AND SYSTEMS - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

E141A

ROOF PLAN - POWER AND SYSTEMS - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

E141B

ROOF PLAN - POWER AND SYSTEMS - AREA B

0

09/11/2026

09/11/2026

100% CD Set

Published

E141C

ROOF PLAN - POWER AND SYSTEMS - AREA C

0

09/11/2026

09/11/2026

100% CD Set

Published

E141D

ROOF PLAN - POWER AND SYSTEMS - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

E300

ELECTRICAL ENLARGED PLANS

0

09/11/2026

09/11/2026

100% CD Set

Published

E500

ELECTRICAL DIAGRAMS

0

09/11/2026

09/11/2026

100% CD Set

Published

E600

ELECTRICAL SCHEDULES

0

09/11/2026

09/11/2026

100% CD Set

Published

E700

ELECTRICAL PANEL SCHEDULES

0

09/11/2026

09/11/2026

100% CD Set

Published

ED101A

LEVEL 01 DEMOLITION PLAN - LIGHTING - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

ED101B

LEVEL 01 DEMOLITION PLAN - LIGHTING - AREA B

0

09/11/2026

09/11/2026

100% CD Set

Published

ED101C

LEVEL 01 DEMOLITION PLAN - LIGHTING - AREA C

0

09/11/2026

09/11/2026

100% CD Set

Published

ED101D

LEVEL 01 DEMOLITION PLAN - LIGHTING - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

ED111A

LEVEL 01 DEMOLITION PLAN - POWER AND SYSTEMS - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

ED111B

LEVEL 01 DEMOLITION PLAN - POWER AND SYSTEMS - AREA B

0

09/11/2026

09/11/2026

100% CD Set

Published

Page 4 of 5

EXHIBIT A

Printed on Thu Oct 22, 2026 at 03:11 pm MDT BVSD Kohl ES

Palace Construction

Drawing Number

Drawing Title

Revision

Drawing Date

Received Date

Set

Status

ED111C

LEVEL 01 DEMOLITION PLAN - POWER AND SYSTEMS - AREA C

0

09/11/2026

09/11/2026

100% CD Set

Published

ED111D

LEVEL 01 DEMOLITION PLAN - POWER AND SYSTEMS - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

ED141A

ROOF DEMOLITION PLAN - POWER AND SYSTEMS - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

ED141B

ROOF DEMOLITION PLAN - POWER AND SYSTEMS - AREA B

0

09/11/2026

09/11/2026

100% CD Set

Published

ED141C

ROOF DEMOLITION PLAN - POWER AND SYSTEMS - AREA C

0

09/11/2026

09/11/2026

100% CD Set

Published

ED141D

ROOF DEMOLITION PLAN - POWER AND SYSTEMS - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

Page 5 of 5

Printed on Thu Oct 22, 2026 at 02:58 pm MDT

EXHIBIT A

BVSD Kohl ES Palace Construction

Current Specifications Number

Description

Revision

Issued Date

Received Date

Set

00 - Procurement and Contracting Requirements 00 00 00

COVER PAGE

2

09/11/26

09/11/26

100% CD Set

00 00 02

TABLE OF CONTENTS

2

09/11/26

09/11/26

100% CD Set

00 01 03

PROJECT DIRECTORY

0

09/11/26

09/11/26

100% CD Set

00 01 07

SEALS PAGE

0

09/11/26

09/11/26

100% CD Set

01 - General Requirements 01 10 00

SUMMARY

0

09/11/26

09/11/26

100% CD Set

01 20 00

PRICE AND PAYMENT PROCEDURES

0

09/11/26

09/11/26

100% CD Set

01 21 00

ALLOWANCES

0

09/11/26

09/11/26

100% CD Set

01 22 00

UNIT PRICES

0

09/11/26

09/11/26

100% CD Set

01 23 00

ALTERNATES

0

09/11/26

09/11/26

100% CD Set

01 25 00

SUBSTITUTION PROCEDURES

0

09/11/26

09/11/26

100% CD Set

01 25 00.01

SUBSTITUTION REQUEST FORM

0

09/11/26

09/11/26

100% CD Set

01 30 00

ADMINISTRATIVE REQUIREMENTS

0

09/11/26

09/11/26

100% CD Set

01 30 00.01

LICENSE WAIVER, RELEASE AND INDEMNITY AGREEMENT

0

09/11/26

09/11/26

100% CD Set

01 31 14

FACILITY SERVICES COORDINATION

0

09/11/26

09/11/26

100% CD Set

01 33 29.07

PROHIBITED CONTENT INSTALLER CERTIFICATION

0

09/11/26

09/11/26

100% CD Set

01 35 53

SECURITY PROCEDURES

0

09/11/26

09/11/26

100% CD Set

01 40 00

QUALITY REQUIREMENTS

0

09/11/26

09/11/26

100% CD Set

01 41 00

REGULATORY REQUIREMENTS

0

09/11/26

09/11/26

100% CD Set

01 42 16

DEFINITIONS

0

09/11/26

09/11/26

100% CD Set

01 42 19

REFERENCE STANDARDS

0

09/11/26

09/11/26

100% CD Set

01 45 33

CODE-REQUIRED SPECIAL INSPECTIONS AND PROCEDURES

0

09/11/26

09/11/26

100% CD Set

01 60 00

PRODUCT REQUIREMENTS

0

09/11/26

09/11/26

100% CD Set

01 61 16

VOLATILE ORGANIC COMPOUND (VOC) CONTENT AND RESTRICTIONS

0

09/11/26

09/11/26

100% CD Set

01 70 00

EXECUTION AND CLOSEOUT REQUIREMENTS

0

09/11/26

09/11/26

100% CD Set

01 74 19

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

0

09/11/26

09/11/26

100% CD Set

01 78 00

CLOSEOUT SUBMITTALS

0

09/11/26

09/11/26

100% CD Set

01 79 00

DEMONSTRATION AND TRAINING

0

09/11/26

09/11/26

100% CD Set

01 91 13

GENERAL COMMISSIONING REQUIREMENTS

0

09/11/26

09/11/26

100% CD Set

0

09/11/26

09/11/26

100% CD Set

02 - Existing Conditions 02 41 00

DEMOLITION

06 - Wood, Plastics, and Composites 06 20 00

FINISH CARPENTRY

0

09/11/26

09/11/26

100% CD Set

06 41 00

ARCHITECTURAL WOOD CASEWORK

0

09/11/26

09/11/26

100% CD Set

0

09/11/26

09/11/26

100% CD Set

07 - Thermal and Moisture Protection 07 21 00

THERMAL INSULATION

Page 1 of 4

EXHIBIT A

Printed on Thu Oct 22, 2026 at 02:58 pm MDT BVSD Kohl ES

Palace Construction

Number

Description

Revision

Issued Date

Received Date

Set

07 25 00

WEATHER BARRIERS

0

09/11/26

09/11/26

100% CD Set

07 42 13

METAL WALL PANELS

0

09/11/26

09/11/26

100% CD Set

07 53 23

ADHERED EPDM SINGLE-PLY ROOFING

0

09/11/26

09/11/26

100% CD Set

07 62 00

SHEET METAL FLASHING AND TRIM

0

09/11/26

09/11/26

100% CD Set

07 92 00

JOINT SEALANTS

0

09/11/26

09/11/26

100% CD Set

DOOR HARDWARE

0

09/11/26

09/11/26

100% CD Set

09 05 61

COMMON WORK RESULTS FOR FLOORING PREPARATION

0

09/11/26

09/11/26

100% CD Set

09 21 16

GYPSUM BOARD ASSEMBLIES

0

09/11/26

09/11/26

100% CD Set

09 51 00

ACOUSTICAL CEILINGS

0

09/11/26

09/11/26

100% CD Set

09 65 00

RESILIENT FLOORING

0

09/11/26

09/11/26

100% CD Set

09 68 13

TILE CARPETING

0

09/11/26

09/11/26

100% CD Set

09 91 23

INTERIOR PAINTING

0

09/11/26

09/11/26

100% CD Set

TOILET, BATH, AND LAUNDRY ACCESSORIES

0

09/11/26

09/11/26

100% CD Set

FOOD SERVICE EQUIPMENT

0

09/11/26

09/11/26

100% CD Set

COUNTERTOPS

0

09/11/26

09/11/26

100% CD Set

22 05 00

BASIC PLUMBING REQUIREMENTS

0

09/11/26

09/11/26

100% CD Set

22 05 03

THROUGH PENETRATION FIRESTOPPING

0

09/11/26

09/11/26

100% CD Set

22 05 05

PLUMBING DEMOLITION FOR REMODELING

0

09/11/26

09/11/26

100% CD Set

22 05 13

MOTORS

0

09/11/26

09/11/26

100% CD Set

22 05 16

PLUMBING EXPANSION COMPENSATION

0

09/11/26

09/11/26

100% CD Set

22 05 29

PLUMBING SUPPORTS AND ANCHORS

0

09/11/26

09/11/26

100% CD Set

22 05 30

ROOF SUPPORT

0

09/11/26

09/11/26

100% CD Set

22 05 53

PLUMBING IDENTIFICATION

0

09/11/26

09/11/26

100% CD Set

22 05 93

PLUMBING TESTING, ADJUSTING, AND BALANCING

0

09/11/26

09/11/26

100% CD Set

22 07 19

PLUMBING PIPING INSULATION

0

09/11/26

09/11/26

100% CD Set

22 09 00

INSTRUMENTATION

0

09/11/26

09/11/26

100% CD Set

22 10 00

PLUMBING PIPING

0

09/11/26

09/11/26

100% CD Set

22 10 23

NATURAL GAS AND PROPANE PIPING

0

09/11/26

09/11/26

100% CD Set

22 10 30

PLUMBING SPECIALTIES

0

09/11/26

09/11/26

100% CD Set

22 11 23

DOMESTIC WATER PUMPS

0

09/11/26

09/11/26

100% CD Set

22 30 00

PLUMBING EQUIPMENT

0

09/11/26

09/11/26

100% CD Set

22 40 00

PLUMBING FIXTURES

0

09/11/26

09/11/26

100% CD Set

08 - Openings 08 71 00 09 - Finishes

10 - Specialties 10 28 00 11 - Equipment 11 40 00 12 - Furnishings 12 36 00 22 - Plumbing

23 - Heating, Ventilating, and Air Conditioning (HVAC) 23 05 00

BASIC HVAC REQUIREMENTS

0

09/11/26

09/11/26

100% CD Set

23 05 03

THROUGH PENETRATION FIRESTOPPING .

0

09/11/26

09/11/26

100% CD Set

Page 2 of 4

EXHIBIT A

Printed on Thu Oct 22, 2026 at 02:58 pm MDT BVSD Kohl ES

Palace Construction

Number

Description

Revision

Issued Date

Received Date

Set

23 05 05

HVAC DEMOLITION FOR REMODELING

0

09/11/26

09/11/26

100% CD Set

23 05 13

MOTORS .

0

09/11/26

09/11/26

100% CD Set

23 05 15

VARIABLE FREQUENCY DRIVES

0

09/11/26

09/11/26

100% CD Set

23 05 29

HVAC SUPPORTS AND ANCHORS

0

09/11/26

09/11/26

100% CD Set

23 05 30

ROOF SUPPORT AND WIND BRACING

0

09/11/26

09/11/26

100% CD Set

23 05 48

HVAC VIBRATION ISOLATION

0

09/11/26

09/11/26

100% CD Set

23 05 53

HVAC IDENTIFIACTION

0

09/11/26

09/11/26

100% CD Set

23 05 93

TESTING, ADJUSTING, AND BALANCING

0

09/11/26

09/11/26

100% CD Set

23 07 13

DUCTWORK INSULATION

0

09/11/26

09/11/26

100% CD Set

23 07 19

HVAC PIPING INSULATION

0

09/11/26

09/11/26

100% CD Set

23 09 00

CONTROLS

0

09/11/26

09/11/26

100% CD Set

23 09 13

INSTRUMENTATION .

0

09/11/26

09/11/26

100% CD Set

23 21 00

HYDRONIC PIPING

0

09/11/26

09/11/26

100% CD Set

23 21 16

HYDRONIC SPECIALTIES

0

09/11/26

09/11/26

100% CD Set

23 21 23

HVAC PUMPS

0

09/11/26

09/11/26

100% CD Set

23 31 00

DUCTWORK

0

09/11/26

09/11/26

100% CD Set

23 33 00

DUCTWORK ACCESSORIES

0

09/11/26

09/11/26

100% CD Set

23 34 23

POWER VENTILATORS

0

09/11/26

09/11/26

100% CD Set

23 37 00

AIR INLETS AND OUTLETS

0

09/11/26

09/11/26

100% CD Set

23 51 00

BREECHINGS, CHIMNEYS, AND STACKS

0

09/11/26

09/11/26

100% CD Set

23 52 16

CONDENSING BOILERS

0

09/11/26

09/11/26

100% CD Set

23 73 13

INDOOR MODULAR AIR HANDLING UNITS

0

09/11/26

09/11/26

100% CD Set

23 74 16.12

PACKAGED ROOFTOP AIR CONDITIONING UNITS 25 TON AND BELOW

0

09/11/26

09/11/26

100% CD Set

23 74 23.13

GAS FIRED MAKE-UP AIR UNITS

0

09/11/26

09/11/26

100% CD Set

26 05 00

BASIC ELECTRICAL REQUIREMENTS

0

09/11/26

09/11/26

100% CD Set

26 05 03

THROUGH PENETRATION FIRESTOPPING

0

09/11/26

09/11/26

100% CD Set

26 05 05

ELECTRICAL DEMOLITION FOR REMODELING

0

09/11/26

09/11/26

100% CD Set

26 05 13

WIRE AND CABLE

0

09/11/26

09/11/26

100% CD Set

26 05 26

GROUNDING AND BONDING

0

09/11/26

09/11/26

100% CD Set

26 05 27

SUPPORTING DEVICES

0

09/11/26

09/11/26

100% CD Set

26 05 33

CONDUIT AND BOXES

0

09/11/26

09/11/26

100% CD Set

26 05 53

ELECTRICAL IDENTIFICATION

0

09/11/26

09/11/26

100% CD Set

26 05 73

POWER SYSTEM STUDY

0

09/11/26

09/11/26

100% CD Set

26 09 33

LIGHTING CONTROL SYSTEMS

0

09/11/26

09/11/26

100% CD Set

26 20 00

SERVICE ENTRANCE

0

09/11/26

09/11/26

100% CD Set

26 22 00

DRY TYPE TRANSFORMERS

0

09/11/26

09/11/26

100% CD Set

26 23 00

LOW-VOLTAGE SWITCHGEAR

0

09/11/26

09/11/26

100% CD Set

26 24 16

PANELBOARDS

0

09/11/26

09/11/26

100% CD Set

26 27 26

WIRING DEVICES

0

09/11/26

09/11/26

100% CD Set

26 28 16

DISCONNECT SWITCHES

0

09/11/26

09/11/26

100% CD Set

26 - Electrical

Page 3 of 4

EXHIBIT A

Printed on Thu Oct 22, 2026 at 02:58 pm MDT BVSD Kohl ES

Palace Construction

Number

Description

Revision

Issued Date

Received Date

Set

26 43 00

SURGE PROTECTION DEVICES

0

09/11/26

09/11/26

100% CD Set

26 51 19

LED LIGHTING

0

09/11/26

09/11/26

100% CD Set

FIRE ALARM AND DETECTION SYSTEM

0

09/11/26

09/11/26

100% CD Set

31 10 00

SITE PREPARATION

0

09/11/26

09/11/26

100% CD Set

31 20 00

TRENCHING, BACKFILLING, AND COMPACTING

0

09/11/26

09/11/26

100% CD Set

31 23 00

EARTHWORK, EXCAVATION, AND BACKFILL

0

09/11/26

09/11/26

100% CD Set

31 25 00

EROSION AND SEDIMENTATION CONTROL

0

09/11/26

09/11/26

100% CD Set

28 - Electronic Safety and Security 28 31 00 31 - Earthwork

32 - Exterior Improvements 32 05 05

SELECTIVE DEMOLITION FOR EXTERIOR IMPROVEMENTS

0

09/11/26

09/11/26

100% CD Set

32 05 23

CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS

0

09/11/26

09/11/26

100% CD Set

32 11 00

AGGREGATE BASE COURSE

0

09/11/26

09/11/26

100% CD Set

32 12 00

HOT MIX ASPHALT PAVEMENT

0

09/11/26

09/11/26

100% CD Set

32 13 00

CONCRETE PAVING

0

09/11/26

09/11/26

100% CD Set

32 13 73

CONCRETE PAVING JOINT SEALANTS

0

09/11/26

09/11/26

100% CD Set

32 16 00

CURBS, GUTTERS, SIDEWALKS, AND DRIVEWAYS

0

09/11/26

09/11/26

100% CD Set

32 17 00

SIGNING, STRIPING, AND STREET MARKING

0

09/11/26

09/11/26

100% CD Set

Page 4 of 4

Exhibit B Assumptions and clarifications made in preparing the GMP

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit B

BVSD Kohl ES - Clarifications & Exclusions General Clarifications & Exclusions Below are exclusions, clarifications, and assumptions. In addition to this list, please refer to the comments column within the direct cost worksheet for additional exclusions, assumptions, and clarifications. Estimate is based on the CD Drawings & Project Manual dated 09/11/2026 No Addenda provided prior to estimate Excludes any Davis Bacon or Prevailing Wages Excludes building permit and plan review fees. Excludes all sales and use taxes for city, county, and state. Excludes any background checks or badging requirements. Excludes 3rd party inspections and testing of any kind. Excludes Furniture, FFE, Equipment Excludes removal or moving of any owner furniture or equipment that would impede our work. Palace and their subcontractors will provide a 2-year workmanship warranty for all scope. Excludes any specific M/WBE requirements or percentages. We have done a good faith effort to invite several M/WBE contractors to bid. Excludes any requirements for commissioning for Energy Star, NGBS, LEED, or similar certifications. Excludes any removal or testing of hazardous materials. Excludes drilling into surfaces identified as ACMs for anchoring purposes. We are not responsible for any delays due to hazardous material removal, which is the responsibility of the owner. Excludes brining any systems up to code that are outside of our scope of work. Excludes costs for power, water, and gas We assume that we can temporarily use the existing power, water and gas from the building during construction Excludes commissioning of any existing systems. Excludes window cleaning. None of our scope of work will cause the existing windows to get dirty. Excludes final/ALTA survey of any of the site improvements

Division 02 - Demo Excludes removal of hazardous materials. We assume owner will remove all hazardous materials. Includes recycling of Fluorescent bulbs and PCB Ballasts only. Light fixture housings to be explored as recycled content. Excludes recycling of insulation removed from roof. The insulation likely has adhesive attached to it and will be contaminated.

Division 03 - Concrete Division 04 - Masonry Division 05 - Steel

Exhibit B Excludes the steel angle near the head of the opening shown in detail 2/A600. Per conversation with the architect, this is not required.

Division 06 - Rough Carpentry Excludes AWI, WIC, and KCMA certification requirements for P-lam cabinet fabrication and installation. We will meet AWI standards. Excludes AWI Premium Grade standards. We have included AWI Custom Grade standards, including white melamine for the backs of cabinet doors and edge banding of interior shelving. We exclude plastic laminate for the backs of cabinet doors and edge banding of interior shelving. Edgebanding for cabinet doors and drawers to be 3mm PVC in a color that closely matches the P-Lam. Cabinet wood frames and countertop substrates are included as particle board. No plywood has been included.

Division 07 - Thermal & Moisture Protection We exclude any repairs to any rated assemblies or sealants that are outside of our scope of work. When we open up ceilings, building inspector may require additional rated sealants to be added to existing conditions to pass inspection. We are assuming the additional weight requirements per Load Key Legend on S003 have already been included in the new roof systems shown on A141. We have not included any additional Densdeck than what is shown in the roof systems on A141. We are assuming that the existing tectum decking is 2" thick. There will be two patches required in this tectum deck if Alternate #4 is accepted for the AHU replacements. We have priced the curb adjustments per the architectural roof details. We have not included new curbs for existing equipment as suggested on M142.

Division 08 - Openings ADA auto opener has been priced per the electric option.

Division 09 - Finishes We assume existing framing can be re-used for the new gypsum ceilings in the Kinder toilet rooms. No new framing has been included at the Kinder toilet rooms. We exclude the accent logo shown in the flooring in the vestibule. The replacement of the flooring in the cafeteria has been included in Alternate #7. The flooring type included in this alternate is the CU flooring listed in the finish schedule. The flooring priced in Alternate #1B for the clinic is the CU flooring listed on the finish schedule.

Division 10 - Specialties We assumed all toilet room accessories are owner furnished, contractor installed at the kindergarten toilet rooms and for the work room alternates. We assumed that no additional backing is needed for toilet accessories and toilet partitions. Replacements appear to be going back in same location as existing.

Division 11 - Equipment Division 12 - Furnishings Division 13 - Special Construction Division 14 - Conveying Systems Division 21 - Fire Suppression Excludes any fire suppression work for the admin office alternates 1A and 1B. The existing heads appear to be sufficient for the new spaces.

Division 22 - Plumbing Excludes new carriers for plumbing fixtures. We assumed existing carriers will be utilized for the new fixtures. Prior to submittals, we will field verify if existing carriers will work with new fixtures. If not, we will work with the design team to find fixtures that will fit the existing carriers.

Exhibit B Assumes existing rough-ins are sufficient for new fixtures. We exclude increasing the plumbing vent size below the roof deck as shown on 2/P600. Any vent piping that needs to increase in size will be done with no hub connectors above the roof deck. We exclude from our base bid the re-routing of the large gas line on Deck G. Our base bid includes raising it to accommodate the added roof insulation. The re-routing of this gas line has been included in Alternate #4 for the new AHUs.

Division 23 - Heating, Ventilation & AC Assumed existing exhaust fan curb & roof opening can be re-used for replacements associated with Alternates #5 & #6 for the HV unit replacements Excludes cleaning of any ducting except newly installed duct. Assumed that we are only doing a disconnect & reconnect of the existing controls for the existing RTU on Deck H. Albireo does not have record of this unit being a part of the control system and has not included adding any new controls to it. We assume that mega press fittings are an acceptable option for gas piping 2" and below. Gas specific mega press fittings will be used. The removal of RF-146A and RF-146B is only included in Alternate #4 with the replacement of the AHUs. The replacements of EF-160 and EF-165 are only included in Alternates #5 & #6 with the replacements of the HV units.

Division 26 - Electrical Excludes the relocation of Emergency Shutdown push buttons in office 176. This appears as keynote 2203 on E111B, but we believe this scope was removed from the alternate for extending the admin offices. Excludes any rough in support for the paging/ clock/ intercom system. It is not clear on the plans what is needed. Excludes removal and re-installation of the stage lighting for install of new duct silencer associated with the HV-1 replacement in Alternate #5. We have assumed surface mounted EMT for the new circuits to Work Room 177 for Alternate #1B. Some of the walls are CMU and the existing circuits to this space appear to be run in surface mounted EMT. We have assumed surface mounted EMT for the conduits associated with the new ADA door operator and push buttons. Wall finish appears to be Masonry. We exclude relocating any of the existing electrical panels or any other adjustments to create the code required clearances at the electrical panels. We have priced the panel replacements as onefor-one. We assume that existing boxes and conduits can be used for the upgraded lighting controls in Alternates #8 through #11. We assume that existing boxes and conduits can be used for the replacement of the fire alarm system. Excludes light fixture replacements in the gymnasium. There is a Keynote 2110 in that room, but no light fixtures shown. Excludes removing exposed fire alarm conduits and relocating them above ceilings. We intend to re-used existing conduits to the fullest extent possible.

Divisions 27 & 28 - Low Voltage, Life Safety, Security, Excludes any new emergency radio or Bi-directional Antenna Amplification systems or testing. Excludes any FA or electrical work associated with the expulsion hatch at Stage 165. We assume these are not connected to the FA system and can be raised

Division 31 - Earthwork

Division 32 - Exterior Improvements

Division 33 - Utilities

Exhibit C Itemization of the GMP

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit C

BVSD Kohl ES- Renovation 1000 W 10th Ave. Broomfield, CO 80020 CD Estimate (GMP) Owner/Developer: Boulder Valley School District RE-2 6500 Arapahoe Road Boulder, CO 80303 Owner Representative: Stephen Henry - BVSD

Designed By: Treanor 1755 Blake St, Suite 400 Denver, CO 80202 Project Start: May-27 Project Finish: Aug-27 Duration in Months:

2.5

Bonding Required: Prevailing Wage Liquidated Damages: Taxes:

Yes No Per Contract Fully Exempt

TOTAL PROJECT COST: $2,151,600 PROJECT Cost per SF: Building SF:

Proposal Date:

$34.32 62,684

October 28, 2026

Prepared By: Palace Construction 7 S. Galapago Street Denver, CO 80223 Andy Del Grosso 720-456-0373 adelgrosso@palaceconst.com

Exhibit C BVSD Kohl ES- Renovation CD Estimate (GMP)

COST SUMMARY WORKSHEET Direct Costs 02 00 00 07 00 00 08 00 00 09 00 00 10 00 00 11 00 00 21 00 00 22 00 00 23 00 00 26 00 00 27 00 00 28 00 00 32 00 00 33 00 00

Gross Built Area: 62,684 SF

Existing Conditions Thermal and Moisture Protection Openings Finishes Specialties Equipment Fire Suppression Plumbing Heating Ventilation Air Conditioning Electrical Communications Electronic Safety & Security Exterior Improvements Utilities

General Requirements Design, Permit, Taxes Building Permit Plan Review Fee Professional Design Services Use Tax

Contingency & Escalation Contractor Contingency Design Contingency Escalation Allowance

Fee

Cost

$/sf

$43,897 $1,028,533 $7,750 $88,185 $2,800 $76,056 $2,300 $52,418 $119,012 $121,913 $0 $147,734 $61,087 $1,500 $1,753,185

$0.70 $0.12 $1.41 $0.04 $1.21 $0.04 $0.84 $1.90 $1.94 $0.00 $2.36 $0.97 $0.02 $27.97

$155,249

$2.48

Not Included, By Others

$0 $0 $0 $0 $0

$0.00

$95,422 $0 $0 $95,422

$1.52

$100,193

$1.60

$2,104,049

$33.57

$19,988 $1,894 $25,669 $47,551

$0.32

$2,151,600 $1,580,544 $3,732,144

$34.32

Not Included, By Others Not Included, By Others Not Included, By Others

5.00% 0.00% 0.00%

5.00%

Insurances & Bond General Liability Insurance Builders Risk Insurance P&P Bond

$16.41

Duration: 5 Months

SUBTOTAL

0.95% 0.09% 1.22%

TOTAL PROJECT BASE COST: ANTICIPATED ACCEPTED ALTERNATES ADJUSTED TOTAL WITH ALTERNATES: Alternates ALT 01A ALT 01B ALT 02A ALT 02B ALT 02C ALT 03 ALT 04 ALT 05 ALT 06 ALT 07 ALT 08 ALT 09 ALT 10 ALT 11

10/28/2026

$0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $1.52

$0.03 $0.41 $0.76

$25.21 $59.54

Replace Cabinetry in Work Room 173 Admin Area Upgrades Replace Flooring at Corridors with LVT Replace Flooring at Corridors with Carpet Tile Replace Flooring at Corridors with J&J Kinetex Floor Tiles Upgrade Lavatories to Dual Faucet Basins in West Toilets Replace AHUs in Cafeteria Replace HV-1 in Mezzanine Replace HV-2 in Mezzanine Replace Flooring at Cafeteria with Cementitious Urathane Upgrade Lighting & Controls in Classrooms Upgrade Lighting & Controls in Corridors/Entry Upgrade Lighting & Controls in Other Student Space Upgrade Lighting & Controls in Back-of-House

$33,224 $80,654 $91,411 $77,576 $88,629 $62,736 $627,279 $202,119 $220,566 $50,828 $221,319 $42,158 $35,900 $11,092

Total of Anticipated Accepted Alternates (Green Highlighted)

$1,580,544

Exhibit C DIRECT COST WORKSHEET BVSD Kohl ES- Renovation CD Estimate (GMP)

Project: Stage: Code

Cat

000000

Scope of Work

October 28, 2026

Qty

Unit $

Cost

Section

Division

$/sf

Comments

General Notes & Clarifications -

Construction Documents Estimate based on plans dated 09/11/2026 Estimate based on project manual Volumes 1 through 3 dated 09/11/2026 See Sections Below For Specific Exclusions and Clarifications Not Listed Above

-

010000

DIRECT COST GENERAL REQUIREMENTS

015626 015626 E 015626 L

Temporary Fencing Temp Chain Link Perimeter Fence & Gates Move Fencing to Different Roof Sections

620 lf 32 hr

$8.00 $71.00

$4,960 $2,272

015713 015713 M 015713 L

Temporary Erosion and Sediment Control Erosion Control BMPs BMP Maintenance & Cleanup

1 ls 60 hr

$2,500.00 $71.00

$2,500 $4,260

017123 017123 S 017123 S 017123 S 017123 S

Field Engineering Surveying Base Bid Set Control Staking for Demo Staking for Concrete Work

1 ls 1 ls 2 ea 2 ea

$6,800.00 Included --Included --Included ---

$6,800

017419 017419 S 017423 S

Waste Management Waste Disposal Recycling Appropriate Materials

4 ea 1 ls

$500.00 $5,000.00

$2,000 $5,000

017423 017423 S 017423 X 017423 S

Final Cleaning Building Final Cleaning Window Cleaning Pressure Wash Sidewalks

8,500 sf 1 ls 3,500 sf

$0.50

$4,250

020000

Existing Conditions

024113 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 L

Selective Site Demolition Demo Base Bid Demo Carpet at Vestibule Scrape Adhesive Demo VCT at West Door Scrape Adhesive Demo at West Toilet Rms 102A-105A-106A-110A Demo ACT Ceilings (12"x12" on Gyp) Demo Toilets & Lavatories Demo Toilet Accessories Demo ACT Ceilings at Kitchen Hood Demo Kitchen Hood & Grease Ducting Demo Gyp Ceiling in Girls Toilet 130B Misc Demo Support & Clean-up

070000

Thermal & Moisture Protection

072200

Roofing & Roof Accessories

$32,917 $7,232

$0.12

$6,760

$0.11

$6,800

$0.11 R&R Engineering

$7,000

$0.11 Scope to be reviewed

$5,125

$0.08 No work associated with windows

---

Excluded $0.25

$875 $10,980 $10,980

1 ea 305 sf 305 sf 86 sf 86 sf 216 sf 216 sf 15 ea 20 ea 160 sf 1 ls 24 sf 80 hr

$0.53

$5,300.00 Included Included Included Included Included Included Included Included Included Included Included $71.00

$0.18 $0.18 MP Contracting

$5,300 -----------------------

For access to roof drain $5,680 $1,028,533 $1,012,033 Direct Costs

$16.41 $16.14 Page 3

Exhibit C DIRECT COST WORKSHEET BVSD Kohl ES- Renovation CD Estimate (GMP)

Project: Stage: Code

Cat

072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 X 072200 X 072200 X 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 X 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S

October 28, 2026

Scope of Work

Qty

Roofing Base Bid Demo Gravel Surfacing - B, G, H, L Demo River Rock Ballast - N, P, Q Demo Roof Membrane, Insulation, & Base Sheet Demo Edge Metals, Copings, Flashings Demo Metal Roof Panels at Deck R New Roof System - Sections B & L Base Sheet 3.0" Iso Foam Insulation - Adhered Tapered Insulation to Drains - Adhered Tapered Crickets - Adhered 1 Layer of 0.625" Gyp Cover Board - Adhered 60 Mil EPDM - Fully Adhered Raise Abandoned Curb Raise Curbs at Relief Hoods Raise Curbs at Exhaust Fans Raise Curbs at Condenser Units Replace Metal Line-set Shrouds Remove Vents and Patch Deck per Keynote 2 New Roof System - Sections G & H Base Sheet 3.0" Iso Foam Insulation - Adhered Tapered Insulation to Drains - Adhered Tapered Crickets - Adhered 1 Layer of 0.625" Gyp Cover Board - Adhered 60 Mil EPDM - Fully Adhered New Wood Curb for Mini-split Condenser - H Raise Large Gas Pipe at Roof Deck G +/- 6" Raise Exhaust Fan Curbs Flash Replaced RTU Curb at Deck H New RTU Curbs at Deck G New Safety Railing at Deck G Infill at Removed Exhaust Fans at Deck G New Roof - Sections N & P 2 Layers of 0.625" Gyp Substrate Board - Loose 2" Iso Foam Insulation - Loose Lay 3" Iso Foam Insulation - Fasten Through to Deck Tapered Crickets - Adhered 1 Layer of 0.625" Gyp Cover Board - Adhered 60 Mil EPDM - Fully Adhered Raise Exhaust Fan Curbs Raise Relief Hood Curb Raise Explosion Hatch Curbs Remove & Reinstall Explosion Hatches Curbs Added Blocking Under Curbs Remove & Reinstall Explosion Hatches Ballasted Safety Railings at Deck N Removal or Reinstall of Ballasted Antenna New Roof System - Section Q 2 Layers of 0.625" Gyp Substrate Board - Loose 3.0" Iso Foam Insulation - Fasten Through to Deck Tapered Insulation to Drains - Adhered Tapered Crickets - Adhered 1 Layer of 0.625" Gyp Cover Board - Adhered

1 ls 22,617 sf 10,652 sf 33,269 sf 1,448 lf 260 sf 18482 sf 18482 sf 18482 sf 1 ls 1 ls 18482 sf 18482 sf 1 ea 3 ea 2 ea 12 ea 12 ea 1 ls 4135 sf 4135 sf 4135 sf 1 ls 1 ls 4135 sf 4135 sf 1 ea 1 ls 2 ea 1 ea 1 ea 1 ea 1 ea 9619 sf 9619 sf 9619 sf 9619 sf 1 ls 9619 sf 9619 sf 2 ea 1 ea 2 ea 2 ea 2 ea 2 ea 40 lf 2 ea 1033 sf 1033 sf 1033 sf 1 ls 1 ls 1033 sf

Unit $ $987,033.00 Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Div 22 Included Included Excluded Excluded Excluded Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included

Cost

Section

$987,033 -----------------------------------------------------------------------------------------------------------

Division

$/sf

Comments Douglass Colony

Added per site walk. Low side is too low for new system at Deck N. On existing lightweight concrete deck

1/8" per foot for tapered insulation

36" x 36" 24" x 36" 24" x 24" 36" x 36" Existing will be too close to membrane On existing Tectum deck

1/8" per foot for tapered insulation

24" x 36" Piping and Stands to be done by plumbing contractor 36" x 36" Not included in base bid, but part of Alternate #4 Not included in base bid, but part of Alternate #4 Not included in base bid, but part of Alternate #4 On existing metal deck

Assumed they are not connected to Electrical or FA systems.

To be removed by owner's contractor On existing metal deck

1/8" per foot for tapered insulation

Direct Costs

Page 4

Exhibit C DIRECT COST WORKSHEET BVSD Kohl ES- Renovation CD Estimate (GMP)

Project: Stage: Code

Cat

Scope of Work

072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 A

60 Mil EPDM - Fully Adhered Raise Exhaust Fan Curb Raise Vent Hoods New Roof System - Section R 2.0" Iso Foam Insulation - Loose Lay 3.0" Iso Foam Insulation - Fasten Through to Deck Tapered Insulation to Drains - Adhered 1 Layer of 0.625" Gyp Cover Board 60 Mil EPDM - Fully Adhered Adjust Existing Metal Panel For New Term Bar New Metal Drip & Head Flashings Raising All Curbs, Including Added Blocking Flash in Kitchen Exhaust Curb - Deck F - 24"x24" Metal Panel/Flashing Adjustments at Walls New Pipe Supports per Keynotes 1 & 4 Galvanized Metal Curb Caps - 24 GA. Termination Bars w/ Flashings & Sealants All Pre-Finished Metal Flashings All New Wood Nailers/Blocking and Plywood Add Walk Mats at Rooftop Equipment Expansion & Control Joints Remove & Reset Exhaust Fans/Hoods Boots/Flashings for MEP Penetrations Roof Adjustments at Roof Drains Roof Drain Sumps New Metal Shrouds at Condensing Units Adjust/Raise Thru-wall Scuppers Flash New Electrical Stands per Keynote 5 All Sealants Associated With Roof & Metal Flashings 2 Year Workmanship Warranty 20 Year NDL Manufacturer Warranty Allowance - Misc. Unforeseen Roof Repairs

074000 074100 S

Metal Siding, Roofing, Flashing & Accessories Metal Work Associated with Roof

079000 079000 M 079000 M 078400 S

Joint Sealants Building Caulking Site Caulking Firestop/Firecaulk

080000

Openings

080000 080000 S

Doors/Frames/Hardware 179 - ADA Auto Opener, Push Buttons

090000

Finishes

092116 092116 S 092116 S 092116 S

Drywall Drywall Base Bid New Gyp Ceilings at ECE Toilet Rooms Patch Ceiling at Girls Toilet 130B

October 28, 2026

Qty

Unit $

1033 sf 1 ea 3 ea 265 sf 265 sf 265 sf 1 ls 265 sf 265 sf 1 ls 1 ls 1 ls 1 ls 1 ls 1 ls 1 ls 1 ls 1 ls 1 ls 20 ea 1 ls 1 ls 1 ls 10 ea 18 ea 1 ls 1 ls 5 ea 5 ea 1 ls 1 ls 1 ls

Cost

Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included $25,000.00

---------------------------------------------------------------

1 ls

Included

---

1 ls 1 ls 1 ls

$1,500.00 Div 32 --$15,000.00

Section

Division

$/sf

Comments

On existing metal deck

1/8" per foot for tapered insulation

Not shown on roof plan, but shows being replaced on Mech drawings. Where metal wall panels/flashings are too low for new roof thickness

To account for increased thickness

$25,000 $0 Douglass Colony - Included with Roofing number $16,500

$0.26

$1,500 Seal penetrations for new FA system

$15,000 $7,750 $7,750

1 ls

$7,750.00

$0.12 Cutting Edge

$7,750

$88,185 $8,856 1 ls 260 sf 16 sf

$8,856.00 Included --Included ---

$0.12

$8,856

Direct Costs

$1.41 $0.14 Independent Construction

Page 5

Exhibit C DIRECT COST WORKSHEET BVSD Kohl ES- Renovation CD Estimate (GMP)

Project: Stage: Code

Cat

Scope of Work

October 28, 2026

Qty

Unit $

Cost

092116 S

Misc Drywall Patches

1 ls

Included

095100 095100 S 095100 S 095100 S 095100 S 095100 A 095100 L

Acoustical Ceiling System ACT Ceiling Base Bid Remove & Reinstall ACT for Fire Alarm Replacement Remove & Reinstall ACT for Roof Drain Replacement Acoustical Ceiling Modifications at Hood Allowance - Misc. Acoustical Ceiling Repairs ACT Removal & Reinstallation

1 ls 1 ls 1 ls 1 ls 1 ls 60 hr

$3,750.00 Included --Included --Included --$10,000.00 $71.00

096000 096000 S 096000 S 096000 X 096000 S 096000 S 096000 S 096000 L 096000 M

Floor Finishes Flooring Base Bid New Walk-off Carpet in Vestibule Accent Logo in Walk-off Carpet Rubber Base at Vestibule Rubber Transitions at Vestibule Moisture/pH Testing Required by Manufacturer Floor Protection - Labor Floor Protection - Materials

099100 099100 S 099100 S 099100 S 099100 S

Painting Painting Base Bid Paint Ceilings in Kindergarten Toilet Rooms Paint Ceiling in Girls & Boys Restrooms 130 A&B Misc. Paint Patches for FA Replacement

096000 099600 S 099600 S 099600 S

Surface Restoration Surface Restoration Base Bid Miracle Method on Floor Tile Miracle Method on Wall Tile

100000

Specialties

108000 108000 S 108000 S 108000 S 108000 S 108000 S 108000 S

Miscellaneous Specialties Specialties Base Bid New Kinder Toilet Room Accessories - OFCI Toilet Tissue Dispensers Paper Towel Dispenser Soap Dispenser Mirrors 18"x36"

110000

Equipment

114000 114000 S 114000 S 114000 S 113113 S 113113 S 113113 S 113113 S 113113 S 113113 S

Food Service Equipment Food Service Equipment Base Bid Demo Type 1 Kitchen Hood & Supports Disconnect Ansul System from Hood Demo Existing Double Stack Oven Demo Existing Steamer New Type 2 Kitchen Hood New Hangers & Supports per Structural New Double Stack Oven w/ Casters, Gas Manifold, SSI-M Controls

1 ls 34 sy 1 ls 120 lf 27 lf 1 ls 200 hr 9,000 sf

$12,315.00 Included Excluded Included Included $850.00 $71.00 $0.50

Section

Division

$18,010

$0.29

$31,865

$0.51

$3,750

$10,000 $4,260

C3 Interiors

$12,315 ---------

Not to be included per owner request

$850 $14,200 $4,500 $3,250

$3,250.00 Included --Included --Included ---

$3,250

1 ls 240 sf 1,000 sf

$26,204.00 Included --Included ---

$26,204

$0.05 PDP Painting At toilet rooms 102A, 105A, 106A, and 110A Ceiling patched for access to roof drain above

$26,204

$0.42 Miracle Method of Boulder At toilet rooms 102A, 105A, 106A, and 110A At toilet rooms 102A, 105A, 106A, and 110A $2,800

$2,800 $2,800.00 Included Included Included Included Included

$0.04

-----------

OFCI OFCI OFCI CFCI

$76,056 $76,056.00 Included Div 21 Included Included Included Included Included Included

$0.04

$2,800

$76,056

1 ls 1 ea 1 ea 1 ea 1 ea 1 ea 1 ea 1 ea 1 ea

Comments For new FA system Install

---

1 ls 1 ls 1 ls 1 ls

1 ls 4 ea 8 ea 4 ea 4 ea 4 ea

$/sf

$76,056 -----------------

$1.21 $1.21 TriMark

Blodgett - DFG-100 K12 DBL

Direct Costs

Page 6

Exhibit C DIRECT COST WORKSHEET BVSD Kohl ES- Renovation CD Estimate (GMP)

Project: Stage: Code

Cat

Scope of Work

113113 S 113113 S 113113 S

Flex Gas Line New 10 Pan Steamer w/ Filters, Descale Solution, Water Tempering

210000

Fire Suppression

211000 211000 X 211000 S

Active Fire Suppression Systems Building Fire Sprinkler System Disconnect Ansul System from Kitchen Hood

220000

Plumbing

220000 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S

Plumbing Systems Plumbing Base Bid Demo Toilets and Lavatories At Kinder Install New Toilets and Lavatories At Kinder New Mixing Valves at Lavatories Demo Roof Drains Install New Roof Drains Disconnect/Reconnect Gas Oven & Steamer Raise Large Gas Pipe at Roof Deck G New Pipe Supports for This Gas Line Extend Plumbing Vents on Roof Increase Size for All Vents Less Than 3"

230000

HVAC

238000 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S

Heating/Cooling/Air HVAC Base Bid Demo Kitchen Exhaust Fan & Roof Curb Demo Kitchen Hood & Grease Ducting New Kitchen Exhaust Hood - Type 2 New Kitchen Exhaust Fan KEF-2 New Roof Curb New Ductwork For Hood & Fan Re-Locate Supply Diffuser in Kitchen Remove & Replace GRDs at Kinder Toilets HVAC Work Associated with Roof Replacement Disconnect & Remove Roof Condensing Units Reclaim Refrigerant Reconnect & Recharge Condensing Units New Curb for Existing RTU on Deck H - 24" Tall Disconnect & Remove Existing RTU New Curb for Existing RTU on Deck H Re-Install Existing RTU & Reconnect Extend Duct, Controls, Piping for Curb Raise Drain & Fill Water Systems as Required Provide Mechanical Insulation as Necessary Controls for Hood, KEF, MAU Conduits & Boxes for Controls All Hoisting Required for Base & Alternate Scopes

260000

Electrical

October 28, 2026

Qty

Unit $ 1 ea 1 ea 1 ea

Included Included Included

Cost

Section

Division

$2,300 Excluded --$2,300.00

No apparent scope. May be required if Alternate #2 is accepted. $2,300

$52,418 $52,418.00 Included Included Included Included Included Included Included Included Included Included

$0.04 $0.04

$52,418

1 ls 1 ls 1 ls 1 ls 10 ea 10 ea 1 ea 1 ls 1 ls 16 ea 16 ea

$0.84 $0.84 ProCraft At toilet rooms 102A, 105A, 106A, and 110A At toilet rooms 102A, 105A, 106A, and 110A At toilet rooms 102A, 105A, 106A, and 110A

$52,418 --------------------$119,012 $119,012

1 ls 1 ls 1 ls 1 ea 1 ea 1 ls 1 ls 1 ea 8 ea

$119,012.00 Included Div 02 Div 11 Included Included Included Included Included

-----------------

13 ls 13 ls 13 ls 1 ea 1 ea 1 ea 1 ea 1 ea 1 ls 1 ls 1 ls 1 ls 1 ls

Included Included Included Included Included Included Included Included Included Included Included Included Included

---------------------------

Comments T&S BRASS HG-4D-48K-PS Cleveland - 24CEA10.2

------$2,300

1 ls 1 ls

$/sf

$1.90 $1.90 ProCraft

$119,012

By Demo Contractor By food service contractor

Existing SD is in conflict with the increased hood size. At toilet rooms 102A, 105A, 106A, and 110A For raising of curbs

By Albireo By Albireo

$121,913 Direct Costs

$1.94 Page 7

Exhibit C DIRECT COST WORKSHEET BVSD Kohl ES- Renovation CD Estimate (GMP)

Project: Stage: Code

Cat

Scope of Work

October 28, 2026

Qty

Unit $

Cost

Section

261000 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 X

Electrical Systems Electrical Base Bid Rough-in Support for New FA System Rough-in Support for ADA Door Auto Opener (2) Push Button Locations. Inside & Outside New Lighting in Toilet Rooms Disconnect/Reconnect Kitchen Equipment Disconnect/Reconnect Rooftop Kitchen Exhaust Fan Disconnect/Reconnect Kitchen Hood Disconnect/Reconnect Rooftop Condensing Units Disconnect/Reconnect RTU - Deck H Add J-Box to Accommodate Increased Height Disconnect Service Outlets From Rooftop Curbs Provide Pole & Mount Service Outlet Electrical Work in Admin Area

270000

Communications

271000 X 272000 X

Structured Cabling Data, Voice, AV, PA Communications

280000

Electronic Safety & Security

281300 281300 X

Access Control Card Reader Integration Into New Door Actuator

1 ls

Excluded

283100 283100 S 283100 S 283100 S 283100 S 283100 S 283100 X

Fire Alarm System Fire Alarm Base Bid Demo Existing FA System Design & Permit Submittal to AHJ Permit Fees Install New FA System, Including Voice Evac. Disconnect/Reconnect FA at Roof Explosion Vents

1 ls 1 ls 1 ls 1 ls 1 ls 1 ls

$147,734.00 Included Included Included Included Excluded

320000

Exterior Improvement

321213 321213 S 321213 S 321213 S 321213 S

Asphalt Paving Asphalt Paving Base Bid Patch Full Depth Asphalt 6" 6" ABC Below Concrete Scarify and Recompact 12" Below ABC

1 ea 57 sy 57 sy 513 sf

321723 321723 S 321723 S

Striping & Signage Remove & Reinstall Stop Sign at Area 1 Striping Repairs at Parking Aisles

1 ls 1 ls

$500.00 $750.00

$500 $750

321600 321600 S 321600 S 321600 S 321600 S 321600 S

Site Concrete Site Concrete Base Bid Demo Existing Asphalt & Concrete Saw Cutting as Required Demo Existing Landscape at Areas 1 & 2 Demo Existing Handrail at Area 1

1 ls 2,396 sf 1 ls 160 sf 160 sf

$42,714.00 Included Included Included Included

$42,714

Division

$121,913 1 ls 1 ls 1 ls 1 ls 12 ea 1 ls 1 ea 1 ea 13 ea 1 ea 1 ea 5 ea 5 ea 1 ea

$121,913.44 Included Included Included Included Included Included Included Included Included Included Included Included Excluded

$/sf

Comments

$1.94 Exceed Electrical Contracting

$121,913 ---------------------------

Ovens & Steamer For roof replacement For roof replacement For roof replacement For roof replacement For roof replacement For roof replacement For roof replacement See Alternates 1A & 1B for work in admin area $0

$0.00

$147,734

$2.36

$0 1 ls

Excluded

---

$0 To be done by owner

--$147,734

Exceed Electrical Contracting

$147,734 -----------

Assumed FA system is not connected to smoke vents $61,087 $8,563

$8,563.00 Included --Included --Included ---

$0.97 $0.14 Centennial Asphalt & Concrete

$8,563

$1,250

$0.02 Centennial Asphalt & Concrete Where asphalt is removed and patched

$42,714

$0.68 Centennial Asphalt & Concrete

--------Direct Costs

Page 8

Exhibit C DIRECT COST WORKSHEET BVSD Kohl ES- Renovation CD Estimate (GMP)

Project: Stage: Code

Cat

Scope of Work

321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 X 321600 S

Scarify and Recompact 12" Below ABC 4" Class 6 ABC Below Concrete Saw Cutting Area 1 Sidewalk at Drive Entry Sidewalk at Door Stoop 30" Roll-Over Curb & Gutter Scarify and Recompact 12" Below ABC 4" ABC Below Concrete Raise Fiber Optic Hand Hole Cover Area 2 Sidewalks/Landings at Ramps 30" Vertical Curb & Gutter ADA Ramps Truncated Domes Area 3 Sidewalk at Drive Entry 30" Roll-Over Curb & Gutter Area 4 Sidewalk at Door Footer Below ADA Push Button Pedestal Dowel Into Existing Where Shown Expansion & Control Joints Sealants at Expansion Joints Haul Off Spoils Rebar in Sidewalk as Shown on Structural Drawings ROW Permit & Traffic Control as Required

323113 323113 S 323113 S 323113 S 323113 S 323113 S

October 28, 2026

Qty

Unit $

Cost

2,396 sf 2,396 sf 580 lf

Included Included Included

-------

492 sf 520 sf 99 lf 492 sf 492 sf 520 sf

Included Included Included Included Included Included

-------------

97 sf 27 sf 138 sf 1 ea

Included Included Included Included

---------

197 sf 39 lf

Included Included

-----

76 sf 1 ea 40 ea 40 ea 1 ls 1 ls 1 ls 1 ls

Included Included Included Included Included Included Excluded Included

-----------------

Chain Link Fencing Remove Fencing at Area 1 Remove Fencing at Area 1 New Fencing Behind Curb at Area 1 Remove Fencing at Area 2 New Fencing Behind Curb at Area 2

1 ls 38 lf 38 lf 38 lf 38 lf

$6,060.00 Included Included Included Included

328000 328000 A

Landscaping Allowance - Landscape / Irrigation Repairs

1 ls

$2,500.00

330000

Utilities

335000 335000 S

Other Utilities Private Locates

TOTALS

Section

Division

$6,060

$0.10

$2,500

$0.04

---------

$2,500

$1,500 $750.00

Comments

$6,060

$1,500

2 ea

$/sf

$0.02 $0.02

$1,500

$1,753,185

$1,753,185

Direct Costs

$1,753,185

$27.97

62,684 GSF

Page 9

Exhibit D Contract Schedule to be provided after amendment & change order for the GMP is executed

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit D

Kohl Elementary

10/26/26

*** Palace - All Work ID

Task Mode 1 8 9 10 11 12 13 14 18 19 20 15 16 17 2 3 4 5 6 7 21 22 23 24 25 26 27 52 53 58 59 61 62 60 63 64 65

Name

Duration

Start

Finish

Resource Names4th Quarter Nov

Project Summary Procurement AHUs Submittal Review-2 Weeks AHU-22 to 24 Weeks After Approved Submittal Light Fixtures Submittal Review-2 Weeks Light Fixtures-8 to 12 Weeks After Approved Submittal Kitchen Equipment Submittal Review-2 Weeks Kitchen Equipment-4 to 6 weeks After Approved Submittal HV Units Submittal Review-2 Weeks HV Units-16 to 19 Weeks After Approved Submittal Milestones GMP Executed Notice-To-Proceed Start of Construction Substantial Completion Final Completion Construction Mobilize and BMP Mobilize onsite BMPs SWMP Items Site Temp Construction Fence Traffic Control Building Construction Interior Corridors Demo Existing Lighting - Cor Install New Lighting and Controls - Cor Remove and Replace Fire Alarm Devices - Cor Remove and Replace Fire Alarm Anunciator Panel - Cor Demo Carpet - Cor Remove and Salvage Base - Cor Install New Flooring - Cor

Last Printed: 10/26/26 1:32 PM Kohl Elementary School Schedule 10-26-2026

182 days 135 days 130 days 10 days 120 days 70 days 10 days 60 days 40 days 10 days 30 days 105 days 10 days 95 days 53 days 1 day 1 day 1 day 1 day 1 day 47 days 1 day 1 day 1 day 1 day 1 day 1 day 47 days 43 days 27 days 10 days 10 days 10 days 2 days 5 days 2 days 8 days

11/18/26 11/18/26 11/18/26 11/18/26 12/4/26 2/16/27 2/16/27 3/2/27 4/6/27 4/6/27 4/20/27 12/28/26 12/28/26 1/12/27 5/24/27 5/24/27 5/24/27 5/24/27 7/30/27 8/6/27 5/24/27 5/24/27 5/24/27 5/24/27 5/24/27 5/24/27 5/24/27 5/24/27 5/24/27 5/24/27 5/24/27 5/25/27 5/25/27 6/9/27 6/9/27 6/9/27 6/16/27

8/6/27 6/1/27 5/24/27 12/3/26 5/24/27 5/24/27 3/1/27 5/24/27 6/1/27 4/19/27 6/1/27 5/24/27 1/11/27 5/24/27 8/6/27 5/24/27 5/24/27 5/24/27 7/30/27 8/6/27 7/29/27 5/24/27 5/24/27 5/24/27 5/24/27 5/24/27 5/24/27 7/29/27 7/23/27 6/30/27 6/7/27 6/8/27 6/8/27 6/10/27 6/15/27 6/10/27 6/25/27

Treanor Mechanical Treanor Electrician Treanor Kitchen Treanor Mechanical Palace BVSD Palace Palace Palace

Palace Palace Palace Palace Palace

Electrician Electrician Electrician Electrician Demo Demo Flooring

Dec

1st Quarter Jan Feb

Mar

2nd Quarter Apr May

3rd Quarter Jul Aug

Jun

Sep

4th Quarter Oct Nov

Dec

1st Quarter Jan Feb

Submittal Review-2 Weeks AHU-22 to 24 Weeks After Approved Submittal Submittal Review-2 Weeks Light Fixtures-8 to 12 Weeks After Approved Submittal Submittal Review-2 Weeks

Kitchen Equipment-4 to 6 weeks After Approved Submit Submittal Review-2 Weeks HV Units-16 to 19 Weeks After Approved Submittal GMP Executed Notice-To-Proceed Start of Construction Substantial Completion Final Completion

Mobilize onsite BMPs SWMP Items Site Temp Construction Fence Traffic Control

Demo Existing Lighting - Cor Install New Lighting and Controls - Cor Remove and Replace Fire Alarm Devices - Cor

Remove and Replace Fire Alarm Anunciator Panel - Co Demo Carpet - Cor Remove and Salvage Base - Cor Install New Flooring - Cor

Page 1 of 8

Exhibit D

Kohl Elementary

10/26/26

*** Palace - All Work ID

Task Mode 66 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 92 93 94 95 96 97 98

105 99 102 101 100 103 104 107 91

Name

Duration

Start

Finish

Resource Names4th Quarter Nov

Install Base - Cor Bathrooms Safe off Plumbing - Bat Demo Plumbing Fixtures - Bat Remove and Salvage Bath Accessories - Bat Salvage Ceiling Mounted Devices - Bat Demo Ceiling - Bat Frame New Ceilings - Bat Electrical Rough - Bat Electrical Inspection - Bat Frame Inspection - Bat Install Drywall - Bat Drywall Screw Inspection - Bat Finish Drywall - Bat Miracle Method - Bat Paint Ceilings - Bat Install New Exhaust Grills - Bat Electrical Trim - Bat Plumbing Trim - Bat Install Bath Accessories - Bat Cafeteria Demo Tectum Ceiling Tiles For HVAC - Caf Disconnect Electrical from AHUs Demo Existing AHUs - Caf Demo Existing Coil Packs - Caf Remove Existing Exhaust Fans - Caf Connect Existing Duct to New RTUs - Caf Install Duct Silencers - Caf Remove and Replace Fire Alarm Devices - Caf Connect Hydronic Piping - Caf Mechanical Rough Inspection - Caf Plumbing Rough Inspection - Caf Insulate Hydronic lines - Caf Insulation Inspection - Caf Install Tectum Ceiling Tiles - Caf Remove and Replace lighting - Caf Demo Flooring - Caf

Last Printed: 10/26/26 1:32 PM Kohl Elementary School Schedule 10-26-2026

3 days 31 days 1 day 1 day 1 day 1 day 1 day 3 days 2 days 1 day 1 day 2 days 1 day 5 days 5 days 2 days 1 day 3 days 3 days 2 days 37 days 1 day 1 day 5 days 2 days 5 days 2 days 4 days 1 day 3 days 1 day 1 day 1 day 1 day 1 day 3 days 3 days

6/28/27 5/24/27 5/24/27 5/25/27 5/26/27 5/26/27 5/27/27 5/28/27 6/3/27 6/7/27 6/7/27 6/8/27 6/10/27 6/11/27 6/18/27 6/25/27 6/29/27 6/30/27 6/30/27 7/6/27 5/24/27 5/24/27 5/25/27 5/25/27 5/28/27 6/2/27 6/15/27 6/17/27 6/18/27 6/23/27 6/23/27 6/28/27 6/29/27 6/30/27 7/1/27 7/2/27 7/8/27

6/30/27 Flooring 7/7/27 5/24/27 Plumbing 5/25/27 Plumbing 5/26/27 Demo 5/26/27 Electrician 5/27/27 Demo 6/2/27 Drywall 6/4/27 Electrician 6/7/27 Electrician 6/7/27 Palace 6/9/27 Drywall 6/10/27 Palace 6/17/27 Drywall 6/24/27 Miracle Method 6/28/27 Painter 6/29/27 Mechanical 7/2/27 Electrician 7/2/27 Plumbing 7/7/27 Specialty 7/15/27 5/24/27 Demo 5/25/27 Electrician 6/1/27 Mechanical 6/1/27 Mechanical 6/8/27 Mechanical 6/16/27 Mechanical 6/22/27 Mechainical 6/18/27 Electrician 6/25/27 Plumbing 6/23/27 Palace 6/28/27 Plumbing 6/29/27 Plumbing 6/30/27 Palace 7/1/27 Ceiling Grid & Tile 7/7/27 Electrician 7/12/27 Demo

Dec

1st Quarter Jan Feb

Mar

2nd Quarter Apr May

Jun

3rd Quarter Jul Aug

Sep

Install Base - Cor

4th Quarter Oct Nov

Dec

1st Quarter Jan Feb

Safe off Plumbing - Bat Demo Plumbing Fixtures - Bat Remove and Salvage Bath Accessories - Bat Salvage Ceiling Mounted Devices - Bat Demo Ceiling - Bat Frame New Ceilings - Bat Electrical Rough - Bat Electrical Inspection - Bat Frame Inspection - Bat Install Drywall - Bat Drywall Screw Inspection - Bat Finish Drywall - Bat Miracle Method - Bat Paint Ceilings - Bat Install New Exhaust Grills - Bat Electrical Trim - Bat Plumbing Trim - Bat Install Bath Accessories - Bat Demo Tectum Ceiling Tiles For HVAC - Caf Disconnect Electrical from AHUs Demo Existing AHUs - Caf Demo Existing Coil Packs - Caf Remove Existing Exhaust Fans - Caf Connect Existing Duct to New RTUs - Caf Install Duct Silencers - Caf Remove and Replace Fire Alarm Devices - Caf Connect Hydronic Piping - Caf Mechanical Rough Inspection - Caf Plumbing Rough Inspection - Caf Insulate Hydronic lines - Caf Insulation Inspection - Caf Install Tectum Ceiling Tiles - Caf Remove and Replace lighting - Caf Demo Flooring - Caf

Page 2 of 8

Kohl Elementary

10/26/26

*** Palace - All Work ID

Task Mode

106 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 108 109 110 111 112 113 114 115 116 117 118 119 120 122 123 124 121 54

Name

Duration

Start

Finish

Resource Names4th Quarter Nov

Install New Flooring - Caf Admin Area Demo Flooring - Adm Safe off Plumbing - Adm Safe off Electrical - Adm Demo Sink - Adm Demo Casework - Adm Demo Walls - Adm Remove Existing Door and Frame - Adm R&R Supply Grill and Duct in Work Room 177 - Adm Demo Existing Lighting - Adm Patch Walls and Ceiling - Adm Paint Walls and Ceiling - Adm Install New Lighting and Controls - Adm Remove and Replace Fire Alarm Devices - Adm Install Casework - Adm Install Sink - Adm Install Flooring - Adm Install Base - Adm Kitchen Remove and Salvage Ceiling Tiles and Grid - Kit Disconnect Gas From Kitchen Equipment - Kit Disconnect Electrical From Kitchen Equipment - Kit Disconnect Ansul System From Exhaust Hood - Kit Remove Kitchen Equipment - Kit Demo Kitchen Hood - Kit Install Kitchen Hood Support Framing - Kit Install new Kitchen Hood - Kit Connect Electrical to Kitchen Hood - Kit Electrical Inspection - Kit Mechanical Inspection - Kit Reinstall Grid Ceiling and Tiles - Kit Install New Kitchen Equipment - Kit Connect Gas to New Equipment - Kit Connect Electrical to New Equipment - Kit Remove and Replace Fire Alarm Devices - Kit Classrooms

Last Printed: 10/26/26 1:32 PM Kohl Elementary School Schedule 10-26-2026

3 days 22 days 3 days 1 day 1 day 1 day 2 days 1 day 1 day 1 day 1 day 4 days 2 days 2 days 2 days 2 days 1 day 3 days 2 days 17 days 1 day 1 day 1 day 1 day 1 day 3 days 2 days 4 days 1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day 21 days

7/13/27 5/24/27 5/24/27 5/25/27 5/25/27 5/26/27 5/27/27 6/1/27 6/2/27 6/3/27 6/4/27 6/7/27 6/11/27 6/15/27 6/15/27 6/15/27 6/17/27 6/17/27 6/22/27 5/25/27 5/25/27 5/26/27 5/26/27 5/26/27 5/27/27 5/27/27 6/2/27 6/4/27 6/10/27 6/11/27 6/11/27 6/14/27 6/15/27 6/16/27 6/16/27 6/17/27 6/9/27

7/15/27 Flooring 6/23/27 5/26/27 Demo 5/25/27 Plumbing 5/25/27 Electrician 5/26/27 Plumbing 5/28/27 Demo 6/1/27 Demo 6/2/27 Demo 6/3/27 Mechanical 6/4/27 Electrician 6/10/27 Drywall 6/14/27 Painter 6/16/27 Electrician 6/16/27 Electrician 6/16/27Millwork & Casework 6/17/27 Plumbing 6/21/27 Flooring 6/23/27 Flooring 6/17/27 5/25/27 Demo 5/26/27 Plumbing 5/26/27 Electrician 5/26/27 Fire Alarm 5/27/27 Kitchen 6/1/27 Mechanical 6/3/27 Mechanical 6/9/27 Mechanical 6/10/27 Electrician 6/11/27 Electrician 6/11/27 Palace 6/14/27 Ceiling Grid & Tile 6/15/27 Kitchen 6/16/27 Plumbing 6/16/27 Electrician 6/17/27 Electrician 7/8/27

Dec

1st Quarter Jan Feb

Mar

2nd Quarter Apr May

Jun

3rd Quarter Jul Aug

Sep

4th Quarter Oct Nov

Install New Flooring - Caf

Dec

1st Quarter Jan Feb

Demo Flooring - Adm Safe off Plumbing - Adm Safe off Electrical - Adm Demo Sink - Adm Demo Casework - Adm Demo Walls - Adm Remove Existing Door and Frame - Adm R&R Supply Grill and Duct in Work Room 177 - Adm Demo Existing Lighting - Adm Patch Walls and Ceiling - Adm Paint Walls and Ceiling - Adm Install New Lighting and Controls - Adm Remove and Replace Fire Alarm Devices - Adm Install Casework - Adm Install Sink - Adm Install Flooring - Adm Install Base - Adm Remove and Salvage Ceiling Tiles and Grid - Kit Disconnect Gas From Kitchen Equipment - Kit Disconnect Electrical From Kitchen Equipment - Kit Disconnect Ansul System From Exhaust Hood - Kit Remove Kitchen Equipment - Kit Demo Kitchen Hood - Kit Install Kitchen Hood Support Framing - Kit Install new Kitchen Hood - Kit Connect Electrical to Kitchen Hood - Kit Electrical Inspection - Kit Mechanical Inspection - Kit Reinstall Grid Ceiling and Tiles - Kit Install New Kitchen Equipment - Kit Connect Gas to New Equipment - Kit Connect Electrical to New Equipment - Kit Remove and Replace Fire Alarm Devices - Kit

Page 3 of 8

Exhibit D

Kohl Elementary

10/26/26

*** Palace - All Work ID

Task Mode 55 56 57

156 158 159 157 143 144 145 146 147 148 149 150 154 151 152 153 155 67 69 68 70 160 161 162 164 165 166 167 163 168 169 170 171

Name

Duration

Start

Finish

Resource Names4th Quarter Nov

Demo Existing Lighting - Cla Remove and Replace Fire Alarm Devices - Cla Install New Lighting and Controls - Cla Mechanical 117 Remove and Replace Fire Alarm Panel - 117 Install New Electrical Circuit to Fire Alarm Panel - 117 Electrical Rough Inspection - 117 Storage 164 Remove and Salvage Mezzanine Decking for HVAC Work - 164 Demo Existing AHUs - 164 Install New AHUs - 164 Install Electrical to AHUs - 164 Install Duct Silencer - 164 Connect Hydronic Piping - 164 Mechanical Rough Inspection - 164 Electrical Rough Inspection - 136ss Plumbing Rough Inspection - 164 Insulate Waterlines - 164 Insulation Inspection - 164 Reinstall Mezzanine Decking - 164 Storage and Mechanical Rooms Remove and Replace Fire Alarm Devices - Smr Demo Existing Lighting - Smr Install New Lighting and Controls - Smr Exterior Roof Deck B Demo Roofing - DB Install Edge Blocking - DB Midroof Inspection - DB Install New Roofing - DB Replace Roof Drain - DB Install Metal Facia and Cap - DB Deck F Disconnect Electrical From Kitchen Exhaust Fan - DF Remove Kitchen Exhaust Fan - DF

Last Printed: 10/26/26 1:32 PM Kohl Elementary School Schedule 10-26-2026

20 days 15 days 20 days 2 days 2 days 1 day 1 day 21 days 1 day

6/9/27 6/9/27 6/10/27 6/11/27 6/11/27 6/11/27 6/14/27 6/17/27 6/17/27

7/7/27 6/29/27 7/8/27 6/14/27 6/14/27 6/11/27 6/14/27 7/16/27 6/17/27

Electrician Electrician Electrician

3 days 10 days 3 days 2 days 3 days 1 day 1 day 1 day 1 day 1 day 1 day 12 days 5 days 10 days 10 days 47 days 47 days 11 days 5 days 5 days 1 day 6 days 1 day 5 days 12 days 1 day 1 day

6/18/27 6/23/27 7/8/27 7/8/27 7/8/27 7/12/27 7/12/27 7/13/27 7/14/27 7/15/27 7/16/27 7/8/27 7/8/27 7/9/27 7/12/27 5/24/27 5/24/27 5/24/27 5/24/27 5/24/27 5/24/27 5/24/27 5/26/27 6/2/27 5/26/27 5/26/27 5/27/27

6/22/27 7/7/27 7/12/27 7/9/27 7/12/27 7/12/27 7/12/27 7/13/27 7/14/27 7/15/27 7/16/27 7/23/27 7/14/27 7/22/27 7/23/27 7/29/27 7/29/27 6/8/27 5/28/27 5/28/27 5/24/27 6/1/27 5/26/27 6/8/27 6/11/27 5/26/27 5/27/27

Mechanical Mechanical Electrician Mechanical Plumbing Palace Electrician Plumbing Plumbing Palace Demo

Dec

1st Quarter Jan Feb

Mar

2nd Quarter Apr May

Jun

3rd Quarter Jul Aug

Sep

4th Quarter Oct Nov

Demo Existing Lighting - Cla

Dec

1st Quarter Jan Feb

Remove and Replace Fire Alarm Devices - Cla Install New Lighting and Controls - Cla Remove and Replace Fire Alarm Panel - 117

Electrician Electrician Electrician

Install New Electrical Circuit to Fire Alarm Panel - 117

Demo

Remove and Salvage Mezzanine Decking for HVAC W

Electrician Electrician Electrician

Roof Roof Palace Roof Plumbing Roof Electrician Mechanical

Electrical Rough Inspection - 117

Demo Existing AHUs - 164 Install New AHUs - 164 Install Electrical to AHUs - 164 Install Duct Silencer - 164 Connect Hydronic Piping - 164 Mechanical Rough Inspection - 164 Electrical Rough Inspection - 136ss Plumbing Rough Inspection - 164 Insulate Waterlines - 164 Insulation Inspection - 164 Reinstall Mezzanine Decking - 164 Remove and Replace Fire Alarm Devices - Smr Demo Existing Lighting - Smr Install New Lighting and Controls - Smr

Demo Roofing - DB Install Edge Blocking - DB Midroof Inspection - DB Install New Roofing - DB Replace Roof Drain - DB Install Metal Facia and Cap - DB Disconnect Electrical From Kitchen Exhaust Fan - DF Remove Kitchen Exhaust Fan - DF

Page 4 of 8

Exhibit D

Kohl Elementary

10/26/26

*** Palace - All Work ID 172 173 174 175 176 177 178 181 180 187 188 179 182 184 183 185 189 194 195 196 197 186 191 192 190 198 193 199 200 203 204 205 201 202 206 207 220

Task Mode

Name

Duration

Start

Finish

Resource Names4th Quarter Nov

Install New Kitchen Exhaust Fan Curb - DF Patch roof at Exhaust Fan Curb - Df Install New Exhaust Fan - DF Connect Electrical to Exhaust Fan - DF Deck G Disconnect Electrical From Exhaust Fans - DG Remove Existing Exhaust Fans and Curbs - DG Install Framing For New RTUs - DG Patch Roof at Exhaust Fan Openings - DG Remove Air Intake Hoods - DG Infill Air Intake Openings - DG Frame Inspection - DG Install RTU Curbs - DG Install Drywall and Rigid Insulation Inside Curbs - DG Install Flashing at Curbs - DG Install RTUs - DG Install Safety Rails - DG Demo Roofing - DG Install Edge Blocking - DG Midroof Inspection - DG Install New Roofing - DG Connect Electrical to RTUs - DG Replace Roof Drains - DG Extend Plumbing Vents - DG Raise Gas Line - DG Install Metal Facia and Cap - DG Install Gas Line Supports - DG Deck H Demo Roofing - DH Install Edge Blocking - DH Midroof Inspection - DH Install New Roofing - DH Replace Roof Drains - DH Extend Plumbing Vents - DH Install Metal Facia and Cap - DH Install New Conduit Supports - DH Deck N

Last Printed: 10/26/26 1:32 PM Kohl Elementary School Schedule 10-26-2026

2 days 1 day 1 day 1 day 16 days 1 day 1 day 3 days 1 day 1 day 2 days 1 day 1 day 1 day 1 day 3 days 3 days 5 days 5 days 1 day 5 days 1 day 1 day 1 day 2 days 5 days 1 day 11 days 5 days 5 days 1 day 6 days 1 day 1 day 5 days 1 day 10 days

5/28/27 6/2/27 6/10/27 6/11/27 6/2/27 6/2/27 6/2/27 6/2/27 6/3/27 6/3/27 6/4/27 6/7/27 6/7/27 6/8/27 6/9/27 6/10/27 6/10/27 6/10/27 6/10/27 6/10/27 6/10/27 6/14/27 6/14/27 6/14/27 6/17/27 6/17/27 6/21/27 6/2/27 6/2/27 6/2/27 6/2/27 6/2/27 6/4/27 6/4/27 6/10/27 6/10/27 6/10/27

6/1/27 6/2/27 6/10/27 6/11/27 6/23/27 6/2/27 6/2/27 6/4/27 6/3/27 6/3/27 6/7/27 6/7/27 6/7/27 6/8/27 6/9/27 6/14/27 6/14/27 6/16/27 6/16/27 6/10/27 6/16/27 6/14/27 6/14/27 6/14/27 6/18/27 6/23/27 6/21/27 6/16/27 6/8/27 6/8/27 6/2/27 6/9/27 6/4/27 6/4/27 6/16/27 6/10/27 6/23/27

Mechanical Roof Mechanical Electrician Electrician Mechanical Structural Steel Roof Mechanical Mechanical Palace Mechanical Drywall Roof Mechanical Roof Roof Roof Palace Roof Electrician Plumbing Plumbing Plumbing Roof Plumbing Roof Roof Palace Roof Plumbing Plumbing Roof Electrician

Dec

1st Quarter Jan Feb

Mar

2nd Quarter Apr May

Jun

3rd Quarter Jul Aug

Sep

4th Quarter Oct Nov

Dec

Install New Kitchen Exhaust Fan Curb - DF

1st Quarter Jan Feb

Patch roof at Exhaust Fan Curb - Df Install New Exhaust Fan - DF Connect Electrical to Exhaust Fan - DF Disconnect Electrical From Exhaust Fans - DG Remove Existing Exhaust Fans and Curbs - DG Install Framing For New RTUs - DG Patch Roof at Exhaust Fan Openings - DG Remove Air Intake Hoods - DG Infill Air Intake Openings - DG Frame Inspection - DG Install RTU Curbs - DG Install Drywall and Rigid Insulation Inside Curbs - DG Install Flashing at Curbs - DG Install RTUs - DG Install Safety Rails - DG Demo Roofing - DG Install Edge Blocking - DG Midroof Inspection - DG Install New Roofing - DG Connect Electrical to RTUs - DG Replace Roof Drains - DG Extend Plumbing Vents - DG Raise Gas Line - DG Install Metal Facia and Cap - DG Install Gas Line Supports - DG Demo Roofing - DH Install Edge Blocking - DH Midroof Inspection - DH Install New Roofing - DH Replace Roof Drains - DH Extend Plumbing Vents - DH Install Metal Facia and Cap - DH Install New Conduit Supports - DH

Page 5 of 8

Exhibit D

Kohl Elementary

10/26/26

*** Palace - All Work ID 221 222 227 228 229 223 226 224 225 230 231 232 233 235 241 242 244 234 236 243 237 238 239 240 245 246 247 248 255 257 258 249 250 251 256 252 253

Task Mode

Name

Duration

Start

Finish

Resource Names4th Quarter Nov

Remove Exhaust Fan - DN Midroof Inspection -DN Demo Roofing - DN Install Edge Blocking - DN Install New Roofing - DN Raise Exhaust Fan Curb - DN Install Safety Rails - DN Install Flashing at Curb - DN Reinstall Exhaust Fan - DN Install Metal Facia and Cap - DN Install New Conduit Supports - DN Deck P Disconnect Electrical from Exhaust Fans - DP Raise Fire/Explosion Hatches - DP Demo Roofing - DP Install Edge Blocking - DP Install New Roofing - DP Remove Existing Exhaust Fans - DP Demo Exhaust Fan Curbs - DP Midroof Inspection -DP Install New Exhaust Fan Curbs - DP Install Flashing at Curbs - DP Install New Exhaust Fans - DP Connect Electrical to New Exhaust Fans - DP Install Metal Facia and Cap - DP Install New Conduit Supports - DP Deck Q Midroof Inspection - DQ Demo Roofing - DQ Install Edge Blocking - DQ Install New Roofing - DQ Remove Exhaust Fans - DQ Remove Relief Vents - DQ Extend Curb Heights - DQ Extend Plumbing Vents - DQ Install Flashing at Curbs - DQ Reinstall Exhaust Fans - DQ

Last Printed: 10/26/26 1:32 PM Kohl Elementary School Schedule 10-26-2026

1 day 1 day 5 days 5 days 5 days 1 day 1 day 1 day 1 day 5 days 1 day 17 days 1 day 1 day 8 days 8 days 9 days 1 day 1 day 1 day 1 day 1 day 1 day 1 day 8 days 1 day 10 days 1 day 5 days 5 days 5 days 1 day 1 day 1 day 1 day 1 day 1 day

6/10/27 6/10/27 6/10/27 6/10/27 6/10/27 6/11/27 6/11/27 6/14/27 6/15/27 6/17/27 6/17/27 6/17/27 6/17/27 6/17/27 6/17/27 6/17/27 6/17/27 6/18/27 6/18/27 6/18/27 6/21/27 6/21/27 6/22/27 6/23/27 6/30/27 6/30/27 6/30/27 6/30/27 6/30/27 6/30/27 6/30/27 7/1/27 7/1/27 7/1/27 7/1/27 7/2/27 7/6/27

6/10/27 6/10/27 6/16/27 6/16/27 6/16/27 6/11/27 6/11/27 6/14/27 6/15/27 6/23/27 6/17/27 7/12/27 6/17/27 6/17/27 6/28/27 6/28/27 6/29/27 6/18/27 6/18/27 6/18/27 6/21/27 6/21/27 6/22/27 6/23/27 7/12/27 6/30/27 7/14/27 6/30/27 7/7/27 7/7/27 7/7/27 7/1/27 7/1/27 7/1/27 7/1/27 7/2/27 7/6/27

Mechanical Palace Roof Roof Roof Roof Roof Roof Mechanical Roof Electrician Electrician Roof Roof Roof Roof Mechanical Mechanical Palace Mechanical Roof Mechanical Electrician Roof Electrician Palace Roof Roof Roof Mechanical Mechanical Roof Plumbing Roof Mechanical

Dec

1st Quarter Jan Feb

Mar

2nd Quarter Apr May

Jun

3rd Quarter Jul Aug

Sep

4th Quarter Oct Nov

Remove Exhaust Fan - DN

Dec

1st Quarter Jan Feb

Midroof Inspection -DN Demo Roofing - DN Install Edge Blocking - DN Install New Roofing - DN Raise Exhaust Fan Curb - DN Install Safety Rails - DN Install Flashing at Curb - DN Reinstall Exhaust Fan - DN Install Metal Facia and Cap - DN Install New Conduit Supports - DN Disconnect Electrical from Exhaust Fans - DP Raise Fire/Explosion Hatches - DP Demo Roofing - DP Install Edge Blocking - DP Install New Roofing - DP Remove Existing Exhaust Fans - DP Demo Exhaust Fan Curbs - DP Midroof Inspection -DP Install New Exhaust Fan Curbs - DP Install Flashing at Curbs - DP Install New Exhaust Fans - DP Connect Electrical to New Exhaust Fans - DP Install Metal Facia and Cap - DP Install New Conduit Supports - DP Midroof Inspection - DQ Demo Roofing - DQ Install Edge Blocking - DQ Install New Roofing - DQ Remove Exhaust Fans - DQ Remove Relief Vents - DQ Extend Curb Heights - DQ Extend Plumbing Vents - DQ Install Flashing at Curbs - DQ Reinstall Exhaust Fans - DQ

Page 6 of 8

Exhibit D

Kohl Elementary

10/26/26

*** Palace - All Work ID

Task Mode

254 259 208 209 210 214 217 218 211 212 215 216 213 219 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

Name

Duration

Start

Finish

Resource Names4th Quarter Nov

Reinstall Relief Vents - DQ Install Metal Facia and Cap - DQ Deck L Remove Exhaust Fan - DL Midroof Inspection - DL Demo Roofing - DL Install Edge Blocking - DL Install New Roofing - DL Raise Exhaust Fan Curb -DL Install Flashing at Curb - DL Replace Roof Drains - DL Extend Plumbing Vents - DL Reinstall Exhaust Fan - DL Install Metal Facia and Cap - DL Exterior Improvements Area 1 Locate Existing Utilities - A1 Remove and Salvage Fence - A1 Demo Asphalt and Concrete Paving - A1 Scarify and Recompact Subgrade - A1 Install Roadbase Layer - A1 Form and Pour Sidewalks - A1 Patch Asphalt Reinstall Fence - A1 Parking Lot Striping - A1 Install signs - A1 Area 2 Remove and Salvage Fence - A2 Demo Concrete Sidewalk - A2 Scarify and Recompact Subgrade - A2 Install Roadbase Layer - A2 Form and Pour Sidewalk - A2 Reinstall Fence - A2 Area 3 and 4 Demo Existing Concrete Sidewalk - A34 Scarify and Recompact Subgrade - A34 Install Roadbase Layer - A34

Last Printed: 10/26/26 1:32 PM Kohl Elementary School Schedule 10-26-2026

1 day 5 days 16 days 1 day 1 day 10 days 10 days 10 days 1 day 1 day 1 day 1 day 1 day 6 days 13 days 12 days 1 day 1 day 2 days 1 day 1 day 2 days 1 day 2 days 1 day 1 day 9 days 1 day 1 day 1 day 1 day 2 days 2 days 9 days 5 days 1 day 1 day

7/6/27 7/8/27 7/8/27 7/8/27 7/8/27 7/8/27 7/8/27 7/8/27 7/9/27 7/12/27 7/12/27 7/12/27 7/13/27 7/22/27 5/25/27 5/25/27 5/25/27 5/25/27 5/26/27 5/28/27 6/1/27 6/2/27 6/4/27 6/7/27 6/9/27 6/10/27 5/26/27 5/26/27 5/28/27 6/1/27 6/2/27 6/3/27 6/7/27 6/1/27 6/1/27 6/8/27 6/9/27

7/6/27 7/14/27 7/29/27 7/8/27 7/8/27 7/21/27 7/21/27 7/21/27 7/9/27 7/12/27 7/12/27 7/12/27 7/13/27 7/29/27 6/11/27 6/10/27 5/25/27 5/25/27 5/27/27 5/28/27 6/1/27 6/3/27 6/4/27 6/8/27 6/9/27 6/10/27 6/8/27 5/26/27 5/28/27 6/1/27 6/2/27 6/4/27 6/8/27 6/11/27 6/7/27 6/8/27 6/9/27

Dec

1st Quarter Jan Feb

Mar

2nd Quarter Apr May

Jun

3rd Quarter Jul Aug

Sep

4th Quarter Oct Nov

Mechanical Roof

Reinstall Relief Vents - DQ

Mechanical Palace Roof Roof Roof Roof Roof Plumbing Plumbing Mechanical Roof

Remove Exhaust Fan - DL

1st Quarter Jan Feb

Install Metal Facia and Cap - DQ

Midroof Inspection - DL Demo Roofing - DL Install Edge Blocking - DL Install New Roofing - DL Raise Exhaust Fan Curb -DL Install Flashing at Curb - DL Replace Roof Drains - DL Extend Plumbing Vents - DL Reinstall Exhaust Fan - DL Install Metal Facia and Cap - DL

Palace Fence Concrete Concrete Concrete Concrete Asphalt Fence Striping Site Signage

Locate Existing Utilities - A1

Fence Concrete Concrete Concrete Concrete Fence

Remove and Salvage Fence - A2

Concrete Concrete Concrete

Dec

Remove and Salvage Fence - A1 Demo Asphalt and Concrete Paving - A1 Scarify and Recompact Subgrade - A1 Install Roadbase Layer - A1 Form and Pour Sidewalks - A1 Patch Asphalt Reinstall Fence - A1 Parking Lot Striping - A1 Install signs - A1

Demo Concrete Sidewalk - A2 Scarify and Recompact Subgrade - A2 Install Roadbase Layer - A2 Form and Pour Sidewalk - A2 Reinstall Fence - A2 Demo Existing Concrete Sidewalk - A34 Scarify and Recompact Subgrade - A34 Install Roadbase Layer - A34

Page 7 of 8

Exhibit D

Kohl Elementary

10/26/26

*** Palace - All Work ID

Task Mode 51

260 261 265 266 268 262 269 272 271 264 267 270 263 273 274 275 276 277 278

Name

Duration

Start

Finish

Resource Names4th Quarter Nov

Form and Pour Sidewalk - A34 Project Closeout & Final Inspections Start-up & Inspection Kitchen Equipment Start-up Start-up of Mechanical Systems Fire Alarm & Sprinkler Testing Palace Punch Mechanical Final Inspection Fire Alarm Final Plumbing Final Inspection Lighting Control Programming Final Building Clean Electrical Final Inspection Roof Final Inspection Building Final for CO Final Fire Inspection Punch Lists Owner Punch Walk Complete Owner Punch List Corrections Owner Final Walk & Project Acceptance

Last Printed: 10/26/26 1:32 PM Kohl Elementary School Schedule 10-26-2026

2 days 36 days 31 days 1 day 3 days 2 days 5 days 1 day 2 days 1 day 3 days 5 days 1 day 1 day 1 day 1 day 5 days 1 day 3 days 1 day

6/10/27 6/17/27 6/17/27 6/17/27 7/14/27 7/15/27 7/19/27 7/19/27 7/19/27 7/20/27 7/26/27 7/26/27 7/29/27 7/30/27 7/30/27 7/30/27 8/2/27 8/2/27 8/3/27 8/6/27

6/11/27 8/6/27 7/30/27 6/17/27 7/16/27 7/16/27 7/23/27 7/19/27 7/20/27 7/20/27 7/28/27 7/30/27 7/29/27 7/30/27 7/30/27 7/30/27 8/6/27 8/2/27 8/5/27 8/6/27

Dec

1st Quarter Jan Feb

Mar

2nd Quarter Apr May

Jun

3rd Quarter Jul Aug

Sep

4th Quarter Oct Nov

Concrete

Form and Pour Sidewalk - A34

Kitchen Mechanical Fire Alarm Palace Mechanical Fire Alarm Plumbing Electrician Cleaning Electrician Palace Palace Palace

Kitchen Equipment Start-up

BVSD Palace BVSD

Dec

1st Quarter Jan Feb

Start-up of Mechanical Systems Fire Alarm & Sprinkler Testing Palace Punch Mechanical Final Inspection Fire Alarm Final Plumbing Final Inspection Lighting Control Programming Final Building Clean Electrical Final Inspection Roof Final Inspection Building Final for CO Final Fire Inspection Owner Punch Walk Complete Owner Punch List Corrections Owner Final Walk & Project Acceptance

Page 8 of 8

Exhibit E Insurance Certificates to be provided after amendment & change order for the GMP is executed

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit F Performance Bond to be provided after amendment & change order for the GMP is executed

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit G Labor and Materials Payment Bond to be provided after amendment & change order for the GMP is executed

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit H Alternates prices not used for the amendment

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit H Schedule of Alternates Kohl Elementary School Renovation

 Alternate No. 01A – Replace Casework and Plumbing in Work Room 173  Total added cost to the base cost in the GMP = $33,224.00  Alternate No. 01B – Admin Area Upgrades  Total added cost to the base cost in the GMP = $80,654.00  Alternate No. 02A – Replace Corridor Flooring with New LVT  Total added cost to the base cost in the GMP = $91,411.00  Alternate No. 02B – Replace Corridor Flooring with New Carpet Tiles  Total added cost to the base cost in the GMP = $77,576.00  Alternate No. 02C – Replace Corridor Flooring with New J&J Kinetex Flooring  Total added cost to the base cost in the GMP = $88,629.00  Alternate No. 03 – Replace Single Sinks at ECE Toilets with Dual Sink Basin  Total added cost to the base cost in the GMP = $62,736.00  Alternate No. 04 – Replace AHUs in Cafeteria  Total added cost to the base cost in the GMP = $627,279.00  Alternate No. 05 – Replace HV-1 in Mezzanine  Total added cost to the base cost in the GMP = $202,119.00  Alternate No. 06 – Replace HV-2 in Mezzanine  Total added cost to the base cost in the GMP = $220,566.00  Alternate No. 07 – Replace Cafeteria Flooring with New Cementitious Urethane Flooring  Total added cost to the base cost in the GMP = $50,828.00 1|Pa ge

Exhibit H

 Alternate No. 08 – Replace Lighting and Controls in Classrooms  Total added cost to the base cost in the GMP = $221,319.00  Alternate No. 09 – Replace Lighting and Controls in Corridors and Entry  Total added cost to the base cost in the GMP = $42,158.00  Alternate No. 10 – Replace Lighting and Controls in Other Student Spaces  Total added cost to the base cost in the GMP = $35,900.00  Alternate No. 11 – Replace Lighting and Controls in Back-of-House Spaces  Total added cost to the base cost in the GMP = $11,092.00

2|Pa ge

Exhibit I Unit prices not used for this amendment

Not Applicable No unit prices provided for this contract

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit J Allowances

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit J Allowances Kohl Elementary School Renovation

 Miscellaneous Unforeseen Roof Repairs. = $25,000.00  Miscellaneous Acoustic Ceiling Repairs. = $10,000.00  Landscape/Irrigation Repairs Due to Concrete Replacements = $2,500.00

1|Pa ge

Exhibit K Not Applicable

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit L Equipment rental rate schedule

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit L

PALACE EQUIPMENT RENTAL RATES Unit of Measure Jobsite Trailer Delivery Setup / TieDowns (8) Dismantle/Return

Range/ Notes

2025

2026

2027

Rate

Rate $675 $415 $890 $1,000

Denver Metro Area Denver Metro Area Denver Metro Area

$660 $410 $870 $994

Rate $670 $415 $890 $1,000

Denver Metro Area

$150 $95 $320

$155 $100 $325

$160 $100 $325

$3,963 $2,463 $221 $882

$4,042 $2,513 $232 $882

$4,050 $2,525 $235 $882

$852 $596 $220

$855 $600 $220

per month

Storage Containers 40 Ft Container 20 Ft Container Delivery/Return

per month per month per trip

Skid Steer TR310 Skid Steer Case 60XT Skid Steer Delivery/Return Sweeper Attachment

per month per month per trip per month

Utility Vehicles Gator Utility Vehicle Golf Cart Delivery/Return

per month per month per trip

Denver Metro Area

$827 $579 $200

per Day Per Week per trip

plus fuel cost plus fuel cost Denver Metro Area

$207 $806 $200

$213 $830 $200

$215 $830 $200

per day per week per trip

plus fuel cost plus fuel cost Denver Metro Area

$223 $690 $200

$229 $710 $200

$230 $710 $200

Denver Metro Area

$2,200

$2,300

$2,300

Diesel Air Compressor Delivery/Return Diesel Dingo

Superintendent Truck

plus fuel cost plus fuel cost Denver Metro Area

Water Trailer

per day per week per month

plus fuel cost plus fuel cost plus fuel cost

$145 $450 $900

$145 $450 $900

$145 $450 $900

Dump Trailer

per day per week per month

Denver Metro Area Denver Metro Area Denver Metro Area

$235 $680 $1,380

$235 $680 $1,380

$235 $680 $1,380

plus cost of driver

$212

$233

$235

Intrusive Testing Trailer

Day

450 Trash/Dump Truck

per trip

Exhibit L

PALACE EQUIPMENT RENTAL RATES 2025

2026

2027

Rate

Rate

Rate

$333 $1,089 $2,400

$366 $1,198 $2,400

$370 $1,200 $2,400

per month per month per month

$445 $230 $170

$445 $230 $175

$445 $230 $175

per day per week per month

$85 $398 $1,430

$87 $410 $1,430

$87 $410 $1,430

per day per week per month

$16 $64 $133

$16 $66 $137

$17 $66 $137

per month per trip

$2,700 $380

$2,800 $380

$2,800 $380

per month per month per month per month

$80 $210 $190 $400 $200

$80 $210 $190 $400 $200

$80 $210 $190 $400 $200

Per LF Per LF/Month

$2.35 $0.70

$2.35 $0.70

$2.35 $0.70

Unit of Measure Flat Bed Truck

Scaffold (per section) Stair scaffold Frame scaffold Baker scaffold Temporary Heat Flagero Heater

Concrete Blankets (ea)

Solar powered Trailer w/ 2 Cameras Tower and camera rental delivery / pickup Security Cameras outdoor Bullet Camera Outdoor Dome multi-sensor camera Horn and Alarm Monitoring Onetime installation fee Solar Battery Pole Mount Cell service Temporary Fencing Install/Removal 12 Foot Panels

per day per week per month

Range/ Notes includes fuel, add cost of driver

Exhibit M General Conditions of the Contract

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

BOULDER VALLEY SCHOOL DISTRICT RE-2 BOULDER, COLORADO

GENERAL CONTRACT CONDITIONS BOND PROGRAM

GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT.................................................................................................... 2 GC 1.00

CONTRACT DOCUMENTS AND DEFINITIONS ............................................................................................................ 1

GC 2.00

REFERENCE STANDARDS .......................................................................................................................................... 2

GC 3.00

DRAWINGS AND SPECIFICATIONS ............................................................................................................................ 2

GC 4.00

ROYALTIES AND PATENTS ........................................................................................................................................ 3

GC 5.00

ITEMS COVERED BY CONTRACT PRICE ..................................................................................................................... 3

GC 6.00

EXECUTION, CORRELATION, INTENT, AND INTERPRETATION OF CONTRACT DOCUMENTS ...................................... 3

GC 7.00

MATERIALS, LABOR, FACILITIES, AND STORAGE....................................................................................................... 4

GC 8.00

PERFORMANCE AND PAYMENT BONDS ................................................................................................................... 5

GC 9.00

PERMITS AND COMPLIANCE WITH STATUTES, RULES, AND REGULATIONS .............................................................. 6

GC 10.00

SURVEYS, BENCHMARKS, MONUMENTS, STAKES, AND MEASUREMENTS ............................................................... 6

GC 11.00

CHANGED CONDITIONS ........................................................................................................................................... 7

GC 12.00

PROTECTION OF PERSONS, WORK AND PROPERTY ................................................................................................. 7

GC 13.00

WORK ON EXISTING BUILDINGS .............................................................................................................................. 8

GC 14.00

CONTRACTOR’S SUPERINTENDENCE AND SUPERVISION .......................................................................................... 8

GC 15.00

SUBSTITUTIONS ....................................................................................................................................................... 9

GC 16.00

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES ................................................................................................. 9

GC 17.00

CASH ALLOWANCE................................................................................................................................................. 10

GC 18.00

EXPEDITING MATERIALS ........................................................................................................................................ 10

GC 19.00

BLASTING .............................................................................................................................................................. 11

GC 20.00

SOIL TEST REPORT ................................................................................................................................................. 11

GC 21.00

HAZARDOUS MATERIALS ....................................................................................................................................... 11

GC 22.00

DAMAGE TO UTILITIES ........................................................................................................................................... 11

GC 23.00

CHANGES IN THE WORK ........................................................................................................................................ 12

GC 24.00

CLAIMS FOR EXTRA COST....................................................................................................................................... 13

GC 25.00

DELAYS AND EXTENSIONS OF TIME ....................................................................................................................... 13

GC 26.00

ACCESS TO WORK .................................................................................................................................................. 14

GC 27.00

CORRECTION OF WORK ......................................................................................................................................... 14

GC 28.00

OWNER’S RIGHT TO CARRY OUT WORK ................................................................................................................. 16

GC 29.00

OWNER’S RIGHT TO TERMINATE CONTRACT ......................................................................................................... 16

GC 30.00

CONSTRUCTION SCHEDULE AND PROGRESS REPORTS ........................................................................................... 16

GC 31.00

SCHEDULE OF VALUES ........................................................................................................................................... 17

GC 32.00

PAYMENT .............................................................................................................................................................. 17

GC 33.00

INSURANCE ........................................................................................................................................................... 19

GC 34.00

SEPARATE CONTRACTS .......................................................................................................................................... 23

GC 35.00

SUBCONTRACTORS ................................................................................................................................................ 23

GC 36.00

RELATIONS OF CONTRACTOR AND SUBCONTRACTOR ........................................................................................... 24

GC 37.00

CONTRACTORS’ MUTUAL RESPONSIBILITY ............................................................................................................ 25

GC 38.00

CUTTING, PATCHING, AND EXCAVATING ............................................................................................................... 25

GC 39.00

EMPLOYEES ........................................................................................................................................................... 26

GC 40.00

CLEANING UP......................................................................................................................................................... 27

GC 41.00

USE OF PREMISES .................................................................................................................................................. 27

GC 42.00

OCCUPANCY .......................................................................................................................................................... 27

GC 43.00

TEMPORARY OR TRIAL USAGE ............................................................................................................................... 28

GC 44.00

TESTING OF BUILDING SYSTEMS ............................................................................................................................ 28

GC 45.00

LIQUIDATED DAMAGES FOR DELAY IN COMPLETION ............................................................................................. 28

GC 46.00

ACCEPTANCE AND FINAL PAYMENT ....................................................................................................................... 28

GC 47.00

WARRANTIES ON PORTIONS OF THE WORK .......................................................................................................... 29

GC 48.00

CONTRACTOR’S PROJECT GUARANTEE AFTER COMPLETION ................................................................................. 30

GC 49.00

MISCELLANEOUS KEYS, SWITCHES, ETC. ................................................................................................................ 30

GC 50.00

INDEMNIFICATION ................................................................................................................................................ 30

GC 51.00

LABOR DISPUTES ................................................................................................................................................... 31

GC 52.00

LIMITATION OF ACTIONS ....................................................................................................................................... 31

GC 53.00

PREFERENCE FOR COLORADO LABOR, MATERIALS, AND RESIDENT BIDDERS ........................................................ 31

GC 54.00

SALES AND USE TAX............................................................................................................................................... 31

GC 55.00

LIENS ..................................................................................................................................................................... 32

GC 56.00

OWNER’S INSPECTION OF CONTRACTOR’S RECORDS ............................................................................................ 32

GC 57.00

CERTIFICATION BY CONTRACTOR REGARDING PREMISES ACCESS ......................................................................... 32

GC 58.00

CONTRACTOR SAFETY RESPONSIBILITIES ............................................................................................................... 32

GC 59.00

CONTRACTOR ASBESTOS MANAGEMENT AND LEAD PAINT RESPONSIBILITIES ...................................................... 35

GC 60.00

ARCHITECT’S STATUS AND INSPECTIONS ............................................................................................................... 35

GC 61.00

ORAL STATEMENTS................................................................................................................................................ 35

GC 62.00

PROJECT SIGN ........................................................................................................................................................ 36

GC 63.00

HISTORICAL DATA .................................................................................................................................................. 36

GC 64.00

ASSIGNMENT ......................................................................................................................................................... 36

GC 65.00

TIME OF THE ESSENCE ........................................................................................................................................... 36

GC 66.00

DISPUTES ............................................................................................................................................................... 36

GC 67.00

SURVIVAL .............................................................................................................................................................. 36

GC 1.00

CONTRACT DOCUMENTS AND DEFINITIONS

All Work under the Construction Agreement shall be accomplished in accordance with the Contract Documents, which shall consist of the Request for Qualifications, Request for Proposals, Proposal(s), Notice of Award, Notice to Proceed, Performance Bond, Labor and Material Payment Bond, Construction Agreement, General Contract Conditions, Supplementary Conditions, Asbestos Management Plan Contractor Responsibility Form, Drawings and Specifications, tests and engineering data, approved Change Orders, Contractor’s Requests for Payment, Architect’s Certificates, and all addenda issued by the Owner or Architect prior to execution of the Construction Agreement and all modifications issued by the Owner or Architect after execution of the Construction Agreement. With respect to the Contract Documents, the following definitions and understandings shall control: 1.01 “Contract” or “Contract Documents” shall include all of the items enumerated in GC-1.00 above. 1.02 “Owner” shall mean Boulder Valley School District No. RE-2, and shall include its duly authorized representatives. 1.03 “Contractor” shall mean the corporation, company, partnership, firm, entity, or individual named and designated as such in the Construction Agreement, and any persons or entities acting on its behalf. 1.04 “Subcontractor” shall mean any corporation, partnership, entity, or individual having a direct contract with the Contractor or another subcontractor for performing Work and/or furnishing labor or material on the Project covered by the Contract. 1.05 “Architect” shall mean the corporation, partnership, entity or individual named and designated as “architect” or “engineer” in the Construction Agreement, and any persons or entities acting on the Architect’s behalf and within the scope of the particular duties properly entrusted to them in each case. In the event that there is no Architect on the Project, then “Architect” shall refer to Owner and its duly authorized representative. 1.06 “Notice to Contractor” shall be deemed to have been duly served if made in writing and delivered in person to the individual or to a member of the firm or to an officer of the corporation for which it is intended, or if sent by registered or certified mail, to Contractor’s last known business address. 1.07 “The Work” shall mean the construction and services required by the Contract Documents for completion of the Project, and includes all labor, materials, equipment and services provided or to be provided by the Contractor to fulfill the Contractor’s obligations, whether on or off the Project site, and all labor, materials equipment and services provided or to be provided by subcontractors, sub-subcontractors, or any other entity for whom the Contractor is responsible. 1.08 “The Project” is the total construction designed by the Architect of which the Work performed under the Contract Documents may be the whole or a part. 1.09 The “date of final completion” and “finally completed” shall mean the date when construction is certified by the Architect to be finally completed in accordance with the Contract Documents, as modified by any Change Orders processed under the terms of GC-23.00 below and when the Owner has fully accepted the Project for the use for which it was intended. Such date will be set forth on a letter of acceptance issued by the Owner. 1.010 “Drawings” or “plans” shall mean all (a) drawings furnished by the Owner and/or Architect as a basis for the award of Contract and for construction of the Project; (b) supplementary drawings furnished by the Owner and/or Architect to clarify and to define in greater detail the intent of the Contract drawings and specifications; (c) drawings submitted by the successful Contractor as may be required after the Contract is awarded; (d) drawings furnished by the Owner and/or Architect to the Contractor during the progress of the Work; and (e) engineering data and drawings submitted by the Contractor during the progress of the Work, provided such drawings are acceptable to the Architect and Owner. 1

1.011 “Specifications” are the written technical information concerning materials, components, systems, equipment, and manner of installation as indicated on the drawings or plans and which state the quality, performance, and characteristics to be achieved by application of construction methods. 1.012 “Change Order” shall mean a written order to the Contractor signed by the Owner or its authorized agent issued after the execution of the Construction Agreement, authorizing a change in the Work and/or adjustment in the Guaranteed Maximum Price (“GMP”) or the contract time schedule. Each adjustment in the GMP resulting from a Change Order shall clearly separate the amount attributable to the Cost of the Work and the Contractor’s Fee. 1.013 “day” or “days” shall mean calendar days. In computing a period of days, when the ending date is not specified, the first day is excluded and the last day is included. If any deadline falls on a Saturday, Sunday, or federal or Colorado state holiday, such deadline will be extended to the next day that is not a Saturday, Sunday or federal or Colorado state holiday. GC 2.00

REFERENCE STANDARDS

2.01 Reference to the standards of any technical society, organization, or association, or to codes of local or state authorities, shall mean the latest standard, code, specification, or tentative standard adopted and published as of the date of execution of the Construction Agreement, unless specifically stated otherwise. GC 3.00

DRAWINGS AND SPECIFICATIONS

3.01 Ownership of Drawings. All drawings, specifications, and copies thereof furnished by the Architect are the property of the Architect and the Owner, whether or not the Work for which they are made is performed, and are not to be used on other Work except by written agreement with the Architect and the Owner. 3.02 Figured Dimensions to Govern. Dimensions and elevations shown on the drawings shall be accurately followed. No Work shown on the drawings, the dimensions of which are not indicated, shall be executed until necessary dimensions have been obtained from the Architect. 3.03 Contractor to Check Drawings and Schedules. The Contractor shall check and verify all dimensions, elevations, and quantities shown on the drawings and furnished to it by the Architect, and shall notify the Architect of any discrepancy between the drawings and the conditions on the ground, or any error or omission in drawings, or in the layout as given by stakes, points, or instructions that it may discover. Before ordering any material or doing any Work, the Contractor shall verify all measurements concerning the Project and shall be responsible for the correctness of same. No extra charge or compensation shall be allowed on account of any difference between actual dimensions and the measurements indicated on the drawings. Any difference that may be found shall be submitted to the Architect for consideration and written determination before proceeding with the Work. The Contractor shall not be allowed to take advantage of any error or omission in the drawings or Contract Documents. Full written instructions shall be furnished by the Architect should such error or omission be discovered, and the Contractor shall carry out such instructions as if originally specified. 3.04 Detail Drawings and Instructions. The Architect shall furnish with reasonable promptness additional instructions, by means of drawings or otherwise, necessary for the proper execution of the Work. All such drawings and instructions shall be consistent with the Contract Documents. The Work shall be executed in conformity with the Architect’s drawings and instructions, and the Contractor shall do no Work without proper drawings and instructions. 3.05 Drawings and Specifications Available on the Site. The Contractor shall maintain at the Project site for the Owner and the Architect a Project record set of drawings, including addenda, approved shop drawings, Change Orders, and other modifications, with all changes or deviations from the original drawings neatly marked thereon in a contrasting color. The Contractor shall also maintain a Project record set of specifications at the 2

Project site, noting therein by appropriate section the names, models, and other distinguishing characteristics of the materials actually incorporated into the Work. This Project record set of drawings and specifications shall be updated daily as the Project progresses and shall be made available to the Owner and Architect for inspection at all times. Upon final completion of the Work and before final payment, three (3) copies and one (1) electronic of this Project record set of drawings and specifications shall be delivered to the Owner. One (1) copy of this Project record set of drawings and specification shall be delivered to the Architect. 3.06 Laws and Regulations. The Contractor shall give all notices and comply with all laws, ordinances, rules, and regulations bearing on the conduct of the Work as drawn and specified. If the Contractor observes that the drawings and specifications are at variance therewith, it shall promptly notify the Architect in writing, and any necessary adjustments shall be made as provided in the Contract for changes in the Work. If the Contractor performs any Work knowing it to be contrary to such laws, ordinances, rules, or regulations without giving the required notice to the Architect and receiving a written directive to proceed, it shall bear all costs arising therefrom and to correct and/or remedy same. GC 4.00

ROYALTIES AND PATENTS

The Contractor shall pay all royalties and license fees. The Contractor shall defend all suits or claims for infringement of patent rights and shall hold the Owner harmless from any and all liability or loss on account thereof. If the Contractor has information that the process or article specified involves the infringement of a patent, it shall be responsible for any and all liability or loss resulting therefrom unless it promptly furnishes such information to the Architect in writing. GC 5.00

ITEMS COVERED BY CONTRACT PRICE

5.01 Items Supplied by Owner. Owner shall supply the following items for the Project: a. Building Permit; b. Initial Survey; c. Materials Testing Including Soil Testing; d. Third Party Inspections; e. Commissioning; and f. Test and Balance as Required for Commissioning. 5.02 Items Supplied by Contractor. Unless specifically stated otherwise, the Contractor shall accept the compensation stated in the Construction Agreement as full payment for furnishing all the materials, transportation, apparatus, temporary structures, equipment, services, fuel, energy, light, water, labor and tools, and all other things necessary for the complete and proper execution of the Work contemplated by or reasonably implied from the Contract Documents, within the time limits indicated therein. Such amount shall include any loss or damage resulting from the nature of the Work, from the elements or from any unforeseen difficulties that may be encountered; all risks of every description connected with the prosecution of the Work; all expenses incurred in consequence of any suspension or discontinuance of the Work; and all other amounts necessary for completing the Work pursuant to the Contract Documents within the time limits indicated therein. GC 6.00

EXECUTION, CORRELATION, INTENT, AND INTERPRETATION OF CONTRACT DOCUMENTS

6.01 Execution. The Construction Agreement and other Contract Documents shall be signed in multiple copies as directed by the Owner. Within ten (10) days of Notice of Award, the Contractor shall submit to the Owner a minimum of five (5) fully executed original sets of the Construction Agreement; Performance Bond, and Labor and Material Payment Bond with original Power of Attorney; and certificates of required insurance coverage. The date of the Contract for purposes of these documents shall be the date of the Notice of Award letter. The Owner shall execute the Construction Agreement, assemble all copies, and distribute the Contract Documents. The Contractor shall not commence the Work until it receives the Notice to Proceed. All bonds and insurance 3

certificates shall be submitted to the Owner prior to the award of the first subcontract. 6.02 Correlation. By executing the Construction Agreement, the Contractor represents that it has visited the Project site, familiarized itself with the local conditions under which the Work is to be performed, and correlated its observations with the requirements of the Contract Documents. 6.03 Intent. The intention of the Contract Documents is to include all labor and materials, tools, equipment, construction equipment, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution and completion of the Work. Materials or Work described in words that, as applied, have a well-known technical or trade meaning shall be held to refer to such recognized meaning. The organization of the specifications into divisions, sections, and articles, as the case may be, and the arrangement of drawings shall not control the Contractor in dividing the Work among subcontractors or in establishing the extent of Work to be performed by any trade. It is intended that even though Work is not covered under any heading, division, section, article, branch, class, or trade of the specifications, it shall nevertheless be supplied if it is required elsewhere in the Contract Documents or is reasonably inferable therefrom as being necessary to produce the intended results. The specifications and drawings are intended to supplement but not necessarily duplicate each other. Any Work exhibited in the one and not in the other shall be executed as if it had been set forth in both, so that the Work will be constructed according to the complete design as determined by the Architect. 6.04 Interpretation. Should anything necessary for a clear understanding of the Work be omitted from the specifications and drawings, or should the requirements appear to be in conflict, the Contractor shall secure written interpretations or instructions from the Architect before proceeding with the Work affected thereby. The Contractor shall secure written interpretations or instructions by submitting the Owner’s form Request for Interpretation to the Architect. Oral requests shall not be acknowledged by the Architect or Owner. Additional costs incurred by the Owner as a result of unnecessary requests made by the Contractor, as determined by the Owner, shall be the responsibility of the Contractor. It is understood and agreed that the Work shall be performed according to the true intent of the Contract Documents. 6.05 Conflict in Interpretation. In the case of discrepancy or in the event of a conflict between the different Contract Documents, the documents shall take precedence in the following order: a. Change Orders; b. Written Amendments to Construction Agreement (including, if applicable, the GMP); c. Construction Agreement; d. General Conditions; e. Drawings and specifications; and f. Bid Documents, including addenda. Where two or more of the Contract Documents are complementary, the more detailed provision shall control over the more general provision. GC 7.00

MATERIALS, LABOR, FACILITIES, AND STORAGE

7.01 Contractor’s Responsibility. Unless otherwise agreed in writing, the Contractor shall provide and pay for all materials, labor, tools, equipment, machinery, transportation, and other facilities necessary for the proper execution and completion of the Work. The Contractor shall provide and pay for all the temporary facilities required to supply all the power, light, water, and heat needed by it and its subcontractors for their Work and shall install and maintain all such facilities in such manner as to protect the public and workers and to conform with any applicable laws and regulations. If temporary heat and/or protection is required for the expeditious prosecution of the Work and before the permanent heating apparatus is available for use, the temporary heating apparatus shall be installed and operated in such a manner that the finish Work and/or construction will not be damaged thereby. Unless otherwise specified, the Contractor shall pay for all the power, light, and water used by it and its subcontractors, without regard to whether such items are metered by temporary or permanent meters. The cutoff date on permanent meters shall be either the agreed date of full occupancy by 4

the Owner or the date of final acceptance of the Project, whichever shall be the earlier date. Upon completion of the Work, the Contractor shall remove all surplus materials, tools and such temporary facilities and structures, furnished by the contractor from the Project site. All debris and rubbish caused by the operations of the contractor shall be removed, and the area occupied during construction activities shall be restored to its original condition, within 48 hours of project completion, unless otherwise directed by the municipality or owner’s representative. 7.02 Materials. Unless otherwise specified, all materials shall be new and both Workmanship and materials shall be of the highest quality. The Contractor shall furnish satisfactory evidence to the Owner as to the kind and quality of materials. Samples shall be furnished, when specified, and the Work shall be in accordance with those samples that have been approved. 7.03 Toilet Facilities. The Contractor shall provide and maintain, in a neat and sanitary condition, adequate temporary toilet facilities for the use of any and all employees engaged on the Work, in strict compliance with the requirements of all applicable codes, regulations, laws, and ordinances. In no event may present toilet facilities of any existing building at the site of the Work be used by employees of the Contractor or its subcontractors. Upon final completion of the Work, the Contractor shall remove all such temporary facilities from the site and disinfect the premises. 7.04 Facilities and Storage. The Contractor shall provide suitable temporary facilities and quarters for workers, as needed, and shall maintain on premises water-tight storage sheds or tool houses for storage of building materials and tools that could be damaged by weather. The Contractor shall allow space for the erection of sheds and provide similar facilities for storage by subcontractors of their materials and tools. Storage of materials shall be confined to the site. These facilities or quarters shall further provide for protection against theft and damage of building materials and tools. Upon final completion of the Work, the Contractor shall remove all such temporary facilities from the site. 7.05 Office Space. The Contractor shall provide adequate, weatherproofed, heated and well- lighted office space at the site of the Work, for use by the Architect and the Owner and their representatives. The Contractor shall also provide telephone service at such office, which shall be available for use by the Architect, the Owner, and their representatives without charge, except for toll calls. 7.06 Quality and Location of Facilities. All of the foregoing facilities shall be of a quality and placed in locations acceptable to the Architect and the Owner. GC 8.00

PERFORMANCE AND PAYMENT BONDS

8.01 Required Bonds. The Contractor shall, within ten (10) days from the Notice of Award furnish bonds to the Owner in the full amount of the contract price, covering both the faithful performance of the Contract and the payment of all obligations for labor and materials arising thereunder, on such customary forms as the Owner may prescribe and with such sureties as it may approve. The amount of the bonds shall be increased, if necessary, to reflect approved changes in the Work that result in an increase in the total cost of the Work plus the Contractor’s fees. Such bonds shall be duly executed by a qualified surety licensed to do business in the State of Colorado, conditioned upon the true and faithful performance of the Contract, and shall provide that if the Contractor or its subcontractors fail to duly pay for any labor, materials, or other supplies used or consumed by such Contractor or its subcontractors in the performance of the Work contracted to be done, the surety will pay the same in an amount not exceeding the sum specified in the bond, as adjusted by approved Change Orders, and together with interest as provided by law. The performance bond shall additionally guarantee that the Contractor shall remedy any omissions, correct any and all defects, and adjust and make operable all component parts of Work falling under the requirements of the Contract that may be called to the Contractor’s attention within a period of twenty-four (24) months following the date of the letter of acceptance.

5

8.02 Additional Bond Requirements. The premium for all bonds shall be paid by the Contractor and included in the bid price in the bid proposal. The Owner will accept and approve bonds written by sureties legally authorized to write such bonds in the State of Colorado, provided such surety companies are rated in Best’s Insurance Guide (latest edition), not lower than A- or have Best’s Financial Rating of at least X. If, at any time a surety on such a bond becomes irresponsible or loses its right to do business in the State of Colorado, new bonds shall be provided by an alternate surety licensed to do business in the State and meeting the requirements of this Section 8.00. GC 9.00

PERMITS AND COMPLIANCE WITH STATUTES, RULES, AND REGULATIONS

9.01 Permits. Any local permits, governmental fees, and licenses necessary for the proper execution and completion of the Work shall be secured and paid for by the Contractor. Owner will pay for and secure building permit from Colorado Division of Fire Prevention and Control. Easements for permanent structures or permanent changes in existing facilities shall be secured and paid for by the Owner, unless otherwise specified in writing. The Owner is generally exempt from paying any fee for any building permit issued by any building departments or agencies located in Boulder, Broomfield, and Gilpin Counties, and the Contractor shall see that no building permit fee is paid. The Owner shall negotiate and provide for all electrical, gas, water, and sewer mains for the Contractor’s connections. The Contractor shall arrange with the utility company for actual connection, make necessary connections, and pay for all associated inspection fees and permits as required by any government agency. In addition, the Contractor shall furnish all material and items required to complete all connections. The Contractor shall call for all inspections on a timely basis by any agency having jurisdiction over the Work. 9.02 Compliance with Statutes, Rules and Regulations. The Contractor and all subcontractors shall comply with all applicable federal and state statutes, rules, regulations, and directives of the State Division of Fire Prevention and Control, and other governmental body having jurisdiction over the work to be performed. If any of the provisions of the Contract Documents are in conflict therewith, such portions shall be considered stricken and the applicable statute, ordinance, regulation, or ruling substituted therefor. All such cases of apparent conflict coming to the attention of any party shall immediately be called to the attention of the Owner. The Contractor shall strictly observe and comply with all federal and state laws pertaining to the employment and payment of labor. GC 10.00

SURVEYS, BENCHMARKS, MONUMENTS, STAKES, AND MEASUREMENTS

10.01 Surveys. As provided by the Owner, the Contractor shall obtain from the Architect a copy of all surveys describing property lines, elevation benchmarks, physical characteristics, and utility locations. 10.02 Benchmarks. The Contractor shall properly stake out the Work and provide and rigidly set benchmarks and batter boards as necessary for the proper performance of the Work. The Contractor shall remain responsible for their maintenance and their accuracy. A permanent benchmark, approved as to location and type by the Architect, from which all grades are to be taken, shall be established near the site of the Work by the Contractor. From this benchmark the Contractor shall ascertain all grades and levels to Project buildings as needed. The Contract Documents shall include all necessary information to establish the benchmark. 10.03 Preservation of Monuments and Stakes. The Contractor shall carefully preserve all monuments, benchmarks, property markers, reference points, and stakes. In case of the destruction thereof, the Contractor shall be charged with the expense of replacement and shall be responsible for any mistake or loss of time that may be caused. Permanent monuments and/or benchmarks that must be removed or disturbed shall be protected until properly referenced for relocation. The Contractor shall furnish all materials, labor and assistance for the proper replacement of such monuments and benchmarks. 10.04 Measurements. Before ordering any material or performing any Work, the Contractor shall verify all measurements on the Project and shall be responsible for the accuracy of same. No extra charge or 6

compensation shall be allowed because of any difference between actual dimensions and the measurements indicated in the drawings or specifications. Any discrepancies shall be submitted to the Architect and Owner for consideration before proceeding with the Work. GC 11.00

CHANGED CONDITIONS

The Contractor shall promptly, and before such conditions are disturbed, notify the Owner and the Architect in writing of: (1) sub-surface or latent physical conditions at the Project site differing materially from those indicated in the Contract Documents, or (2) unknown physical conditions at the Project site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in Work of the character provided for in the Contract Documents. The Owner and the Architect shall promptly investigate the conditions, and if the Owner finds that such conditions do so materially differ and cause an increase or decrease in the cost of or the time required for performance of the Work, an equitable adjustment shall be made and the Contract modified in writing accordingly. Any claim of the Contractor for adjustment hereunder shall not be allowed unless it has given notice as required. GC 12.00

PROTECTION OF PERSONS, WORK AND PROPERTY

12.01 Building Exits and Barricades. During the course of construction, the Contractor shall keep all required building exits free and unimpeded. Such exits shall not be closed at any time for any reason while the building is occupied or at any time when the building is unoccupied, except after written approval is given by the Owner and proper warning and directional signs are posted. Barricades shall be erected so that traffic is separated and protected from the construction. 12.02 Precautions. The Contractor shall take all necessary precautions to ensure the safety of all employees and other persons on the Project or who may be affected by the Contractor’s Work thereon. The Contractor shall also take all necessary precautions to protect the Work and all temporary facilities, as well as materials, tools, and equipment incorporated therein or to be incorporated therein from damage or destruction, whether in storage on or off the Project site and whether in the custody or control of the Contractor or any of its subcontractors. The Contractor shall also take all necessary precautions to protect all property at the Project site and adjacent thereto not designated for removal, relocation or replacement, including trees, shrubs, lawns, walks, pavements, roadways, structures, and utilities. 12.03 OSHA Compliance. The Contractor shall comply with all applicable provisions of the Occupational Safety and Health Administration (“OSHA”) and all laws, ordinances, rules, regulations, and orders of all governmental agencies or authorities having jurisdiction to protect the safety of employees and/or other persons who may be affected by the Work. The Contractor shall erect and maintain all necessary safeguards to protect workers on the Project site and the owners and users of adjacent property, and shall post danger signs and other warnings against hazards created by the Work including but not limited to protruding nails, hoists, well holes, elevator shafts, hatchways, scaffolding, window openings, stairways, excavations, and falling materials. The Contractor shall designate a responsible employee at the Project site as a safety officer to ensure the Contractor’s compliance with this section. Said employee shall be the Contractor’s superintendent unless otherwise designated in writing by the Contractor to the Owner and the Architect. 12.04 Contractor’s Liability. The Contractor shall be liable for all injury, damage or loss to any person or property caused in whole or in part by the Contractor, any of its subcontractors, or any person employed by or under the direction of the Contractor or any of its subcontractors. To the extent possible and unless otherwise directed by the Owner or Architect, the Contractor shall promptly repair, pay for or otherwise remedy any such injury, damage or loss and shall indemnify and hold harmless the Owner against any and all liability, claims, damages, losses and expenses arising therefrom. The terms of this section shall not apply in the case of injury, damage or loss proximately caused by the acts or omissions of the Owner and/or Architect and not attributable to any fault or negligence of the Contractor.

7

12.05 Emergencies. In the event of an emergency that threatens the safety or life of any person or threatens to damage or destroy the Project and/or any Work, materials, equipment or property thereon or to be used thereon, the Contractor shall act at its discretion to prevent such injury, death, damage or destruction. The Contractor shall immediately notify the Owner and Architect in writing of any such emergency and any action taken by the Contractor in response thereto. Any compensation due the Contractor for such emergency action shall be determined by agreement of the Contractor, Owner and Architect, and an appropriate Change Order shall be issued therefor. GC 13.00

WORK ON EXISTING BUILDINGS

13.01 Protection of Occupants. In addition to all other requirements of the Contract Documents, if the Work involves an addition or alteration to an existing building, the Contractor shall erect and maintain during the progress of the Work suitable dustproof partitions to protect such building and the occupants thereof. If necessary, in the Owner’s or Contractor’s judgment or pursuant to manufacturer’s directives or recommendations in order to protect occupants from noxious fumes, odors, or hazardous substances, the Contractor may be required to provide additional ventilation and/or work different or extended hours to avoid disruption to other activities within the existing building. Contractor shall protect and keep from harm all occupants of an existing building from construction activities, and shall include a safe pathway into and out of the school. 13.02 Partitions and Scheduling. If any portions of an existing building are to be remodeled or repaired, such portions shall be adequately partitioned off with dustproof partitions and well ventilated. All remodeling Work shall be scheduled and submitted to the Owner and Architect for approval. The various contractors shall schedule their Work jointly, in order that each may accomplish its Work within such existing building in an orderly fashion during regular school vacation periods where possible, or in such a manner as to permit full use of the building and without impairment of any existing facilities. 13.03 Existing Systems. Existing building systems, such as fire alarm, temperature controls and air distribution, security systems, public announcement systems, irrigation systems, and the like, shall be demonstrated and noted by Owner to the Contractor as operational prior to Contractor’s commencing the Work and Contractor may participate in observation of such systems. Such systems are the responsibility of the Contractor to maintain in pre-construction condition. GC 14.00

CONTRACTOR’S SUPERINTENDENCE AND SUPERVISION

14.01 Superintendent. During the progress of the Work, the Contractor shall ensure that a competent superintendent and any necessary assistants, all satisfactory to the Architect and the Owner, are on the Project site at all times while Work is in progress. The superintendent shall not be changed by the Contractor except with the written consent of the Architect and the Owner, unless the superintendent ceases to be in the Contractor’s employ. The superintendent shall represent the Contractor on the Project and all directions given to him/her shall be as binding as if given to the Contractor. The Architect and the Owner shall not be responsible for the acts or omissions of the superintendent or his/her assistants. 14.02 Supervision. The Contractor shall provide full-time, qualified, and efficient supervision of the Work, using competent skill and attention. The Contractor is responsible for determining and supervising all temporary and permanent erection and construction sequences, techniques, means, or methods. The Contractor shall direct, schedule, coordinate the Work to ensure that all parts fit together properly and in accordance with the Contract Documents. The Contractor shall carefully study and compare all Contract Documents and other instructions and shall at once report to the Architect and the Owner any error, inconsistency, or omission that Contractor may discover. 14.03 Additional Supervision Duties. The Contractor shall see that the Work is carried out in accordance with the Contract Documents and in a thorough and first-class manner in every respect. The Contractor shall 8

provide engineering, surveying, and coordination to accurately establish all lines, levels, and marks necessary to facilitate the operations of all parties involved in the Contractor’s Work. The Contractor shall lay out the Work in a manner satisfactory to the Architect, making permanent records of all lines and levels required for excavation, grading, and foundations, and for all other parts of the Work. The Contractor shall be responsible for the commencement and the proper completion of the various stages and sequences of construction. The Contractor shall strictly adhere to the approved construction schedule. GC 15.00

SUBSTITUTIONS

The Contractor shall be held to have used in its base proposal and to furnish under the Contract those items of equipment and/or materials that are specifically identified in the plans and specifications by a manufacturer’s name, model, or catalog number. Items of equipment and/or materials of the Contractor’s choice may be offered as alternates to the items named in the plans and specifications by submitting, with the proposal and on the form provided, identifying data on the articles proposed together with a statement of the amount of addition or deduction from the base bid if the bidder’s alternate is accepted. Prior approval by the Architect is not required on items submitted as alternate bids. After execution of the Construction Agreement, substitution of equipment and/or materials of makes other than those specifically named in the Contract Documents may be approved by the Owner so long as the equipment or material proposed for substitution in the opinion of the Owner is just as suitable as the equipment and/or materials named in the plans and specifications so far as performance, construction, efficiency, and utility are concerned. A request for substitution shall ordinarily be required to be based upon one or more of the following grounds: the specified equipment or material is no longer available, a substitution will improve lead time, quality will be improved (documented detail required), or the Owner will incur substantial savings. All requests for substitution must be submitted in writing with supporting documentation by or through the Contractor to the Architect for initial review and recommendation before being submitted to the Owner for evaluation and final approval. In the absence of the Owner’s written approval, no substitution of equipment or materials shall be allowed for any items specified in the Contract Documents. In case of a difference in price, occurring as a result of an approved substitution, the Owner shall receive all benefit of the difference in cost involved in the substitution. All approved substitutions shall be documented by the issuance of a formal Change Order as provided in these General Conditions. GC 16.00

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

16.01 Shop Drawings. “Shop drawings” are drawings, diagrams, illustrations, schedules, performance charts, brochures, manufacturer’s literature, and other data that are prepared by the Contractor or any subcontractor, manufacturer, supplier, or distributor, and that illustrate some portion of the Work. Shop drawings shall be submitted in both hard copy and electronic format. 16.02 Samples. “Samples” are physical examples furnished by the Contractor to the Owner and/or Architect to illustrate materials, finishes, equipment, or Workmanship, and to establish standards by which the Work will be judged. 16.03 Product Data. “Product data” are illustrations, standard schedules, performance charts, instructions, brochures, diagrams and other information furnished by the Contractor to illustrate materials or equipment for some portion of the Work. Product data shall be submitted in both hard copy and electronic format. 16.04 Contractor’s Obligations. The Contractor shall review, approve, stamp an then submit to the Architect shop drawings, product data, samples, and similar submittals required by the Contract Documents with reasonable promptness and in such a sequence as to cause no delay in the Work or in the activities of the Owner or of separate contractors. Shop drawings, product data, samples, and similar submittal required by the Contract Documents shall properly identify specified items. At the time of submission, the Contractor shall inform the Architect in writing of any deviation in the shop drawings, product data, or samples from the requirements of the Contract Documents. Substitutions will be allowed only in accordance with the provisions of GC-15.00. The number of copies and format of submittal shall be as required by the Architect, but, at a 9

minimum, shall include three (3) copies and one (1) electronic copy of the original shop drawings and product data for the Owner. 16.05 Verification. By approving and submitting shop drawings, product data, and samples, the Contractor thereby represents that it has determined and verified all field measurements, field construction criteria, dimensions, elevations, quantities, materials, catalog numbers, and similar data, as shown on the drawings and specifications furnished by the Architect, or will do so, and that it has checked and coordinated each shop drawing, product data, and sample with the requirements of the Work and of the Contract Documents. 16.06 Architect /Owner Review. The Architect shall review and approve shop drawings, product data, and samples with reasonable promptness so as to cause no delay, but only for conformance with the design concept of the Project and with the information given in the Contract Documents. The Architect’s approval of a separate item shall not indicate approval of any assembly in which the item functions. Upon the final completion of the Work, the Contractor shall furnish to the Architect two corrected copies of all shop or setting drawings showing the as-built condition of the Work. The Architect, after review, shall submit one of these copies to the Owner. 16.07 Corrections. The Contractor shall make any corrections required by the Architect and shall resubmit the required number of corrected copies of shop drawings or new samples until approved by the Architect. The Contractor shall direct specific attention in a separate writing or on resubmitted shop drawings to revisions other than the corrections requested by the Architect on previous submissions. 16.08 Contractor’s Responsibility. The Architect’s approval of shop drawings, product data, or samples shall not relieve the Contractor of responsibility for any deviation from the requirements of the Contract Documents unless the Contractor has informed the Architect in writing of such deviation at the time of submittal and the Architect has given written approval of the specific deviation. The Architect’s approval shall also not relieve the Contractor from responsibility for errors or omissions in the shop drawings, product data, or samples. 16.09 Architect Approval Required. No portion of the Work requiring the submission of a shop drawing, product data, or sample shall be commenced until such submittal has been approved in writing by the Architect. All such portions of the Work shall be in accordance with approved shop drawings, product data, and samples. All material finishes and samples shall be approved at one time. The Contractor shall submit all items requiring approval of finishes, color, material, etc., with sufficient lead time to allow simultaneous consideration and preparation of complete finish color schedule. No approvals of single items shall be considered. 16.010 Copies to Owner. When shop drawings, product data, samples or similar submittals have been approved and stamped by both Contractor and Architect, Contractor shall immediately forward an electronic copy of each to the Owner. GC 17.00

CASH ALLOWANCE

The Contractor shall include in the Contract sum all allowances named in the Contract Documents and shall cause the work so covered to be done by such Contractors and for such sums as the Owner may direct, the Contract sum being adjusted in conformity therewith. The Contractor declares that the Contract sum includes such sums for expenses and profit on account of cash allowances as he deems proper. No demand for expenses or profit other than those included in the Contract sum shall be allowed. The Contractor shall not be required to employ for any such work persons against whom he has filed a lien or has a reasonable objection due to previous legal claims. GC 18.00

EXPEDITING MATERIALS 10

The Contractor shall, immediately after receipt of the Notice of Award and approval of its list of subcontractors and material suppliers, place orders for all equipment, materials, and supplies required for the Work. The Contractor shall, when requested, submit to the Architect evidence that such orders have been placed. The Contractor shall exercise due diligence in seeing that all equipment, materials, and supplies are delivered well in advance of the time they are needed on the Project and shall properly store and protect same at its expense and in accordance with these General Conditions, either at the Project site or elsewhere as approved by the Architect. GC 19.00

BLASTING

No explosives of any nature except for those normally employed in powder actuated tools, .38 caliber or smaller, shall be employed or used on the Project site except with the express and specific prior written approval of the Architect and the Owner and any appropriate governmental authorities, in each instance. The Contractor shall notify the Architect of need for such approval three (3) days prior to the proposed use of such explosives. GC 20.00

SOIL TEST REPORT

The Owner may arrange for a separate consultant to conduct field and laboratory soil investigations on the Project site and to prepare a report of its findings. Such a report, if prepared, shall be available for review by the Contractor in the Architect’s office. Such data is offered solely for reference and is not to be considered a part of the Contract Documents. The data contained in any such document prepared for the Owner by a separate consultant is believed to be reliable; however, the Owner and Architect do not guarantee its accuracy or completeness. All applicable subcontractors shall be fully familiar with the contents of such reports, if prepared, and shall consider and evaluate them in the performance of their contracts and the Work. GC 21.00

HAZARDOUS MATERIALS

21.01 Responsibility and Reporting. Unless otherwise provided in the Contract Documents, the Contractor shall have no responsibility for the presence, handling, removal or disposal of hazardous materials in any form at the Project site, including but not limited to asbestos, asbestos products, polychlorinated biphenyl (PCB), lead, or other hazardous materials. Prior to its commencement or continuation of any portion of the Work, the Contractor shall provide notice to the Owner of the presence, location, amount and condition of any known or suspected hazardous materials that are discovered at the Project site. Such notice shall be in writing and shall be submitted no more than twenty-four (24) hours after the presence of such materials becomes known or suspected. 21.02 Contractor’s Obligations. In the event hazardous materials become known or suspected by the Contractor as described in GC-21.01 above, the Contractor shall not proceed with or continue the Work until it has received written authorization from the Owner. If the Contractor proceeds with the Work without said authorization, it assumes any and all responsibility and liability for contamination and cleanup at the Project site according to applicable federal and state laws, and for any death or personal injury, including but not limited to medical expenses that may be incurred by any individual as a result of exposure to hazardous materials on the Project site. 21.03 Owner’s Obligations. In the event hazardous materials are identified or encountered during the course of the Project, the Owner at its expense shall take reasonable actions to properly and safely deal with such materials. 21.04 Management Plan. The Contractor acknowledges that it and its employees, agents and subcontractors have the responsibility of being fully informed of the Owner’s Management Plan as it relates to buildings located at the Project site and shall consult with the Owner about how such Plan addresses suspected or active asbestos-containing material areas within such buildings. GC 22.00

DAMAGE TO UTILITIES 11

22.01 Adequate Precautions. The Contractor shall take adequate precautions to protect existing utilities on and off the Project site and avoid damage thereto. The Contractor shall repair or replace or have repaired or replaced at its expense any damage to streets, water, sewer, light, power, cable, or telephone lines or fiber network that are damaged by reason of the Contractor’s Work. 22.02 Location. The location and extent of underground utilities, fiber network, cables and conduit indicated on the drawings are not guaranteed. This information is shown only for such use as bidders and contractors may choose to make of it. The Contractor shall check with all public utility companies for locations and shall comply with their regulations regarding such utilities in performing the Work. 22.03 Protection from Damage. The Contractor shall adequately protect active underground utilities from damage, and if damaged shall immediately effect all necessary repairs. Removal or relocation of active underground utilities shall be done only as indicated on the drawings. If such utilities are in use, they shall be maintained in continuous service. If not indicated on the drawings or not known to exist, the Contractor shall report discovery of such utilities to the Architect and shall not proceed further until directed to do so. 22.04 Inactive or Abandoned Utilities. Inactive or abandoned utilities, whether or not they are indicated on the drawings, shall be recorded as to location and depth and shall be removed for a distance of not less than three (3) feet from the outside line of all concrete Work unless otherwise required by regulations. Ends shall be capped or plugged. There shall be no adjustment of the Contract amount for Work due to inactive or abandoned utilities. GC 23.00

CHANGES IN THE WORK

23.01 Change Orders. The Owner, without invalidating the Agreement, may order changes in the Work within the general scope of the Project consisting of additions, deletions, or other revisions. Under such circumstances, the GMP, if applicable and established, and the Contract Time Schedule shall be adjusted accordingly. All such changes in the Work shall be authorized by Change Order. No Change Order or other form of order or directive by the Owner or Architect requiring additional compensable Work to be performed, which causes the aggregate amount payable under the Contract Documents to exceed the amount appropriated for the original Agreement, shall be issued unless the Contractor is given written assurance by the Owner that lawful appropriations to cover the costs of the additional Work have been made. Any claim of the Contractor for adjustment under this section must be asserted in writing within ten (10) days from the date of the Contractor’s receipt of the Change Order. 23.02 Minor Changes. The Architect shall have authority to order minor changes in the Work not involving an adjustment in the GMP or an extension of the Contract Time Schedule and not inconsistent with the intent of the Contract Documents. Such changes may be effected by field order or by other written order. Such changes shall be binding on the Owner and the Contractor. In any emergency affecting the safety of persons or property, the Contractor shall act, at his discretion, to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in this Article. 23.03 Price Differential. The cost or credit resulting from a change in the Work shall be determined in one or more of the following ways: a. By estimate, with a detailed cost breakdown as set forth in GC-23.03(c) below, and acceptance in a lump sum, with a maximum combined markup to the Owner, for the Contractor and all affected subcontractors, not to exceed a total of fifteen percent (15%). b. By unit prices named in the Contract or subsequently agreed upon. c. If the parties are unable to agree on one of the above methods, then the amount shall be determined by force account under the following formula: i. The actual cost of all direct labor performed (including foremen employed continuously on the Work, but not the salary, or any part thereof, of the Contractor’s superintendent) and the actual 12

ii. iii. iv. v.

vi.

GC 24.00