Community Bond Oversight Committee | October 14, 2026

Heatherwood Elementary School Action Item

RTU Background ● Units are 27 years old and refurbishment does not guarantee a long term solution ● Condensing units use R-22 refrigerant making refrigerant recharges costly & difficult

CBOC Action Item

2

Project Details ●

AHU & Condensing Units: $567,551

●

LED Lighting Upgrades: $319,490

●

10% Contingency: $98,560

●

Bond Premium Request: $985,601

CBOC Action Item

3

Future risk profile ●

Phase 4 Budgets ○

Smaller projects with inflation dollars anticipated to cover most overages

●

Bond Premium Balance: $5,101,529

●

Program Reserve Balance: $8,000,391

●

Investment Earnings: $9,276,815

●

IT Network - Anticipated E-Rate Reimbursement: $2,444,261

CBOC Action Item

4

Recommendation Move that the Community Bond Oversight Committee recommend the transfer of $985,601in Bond Premium funds to the Heatherwood Elementary School budget for expenditures related to HVAC component replacement, and LED lighting upgrades.