Exhibit A Drawings, specifications and documents used to prepare the GMP
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Printed on Wed Oct 14, 2026 at 04:22 pm MDT Job #: 8736 BVSD - Heatherwood ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction
Current Drawings Drawing Number
Drawing Title
Revision
Drawing Date
Received Date
Set
Status
General G001
COVER SHEET
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
G110
FIRST FLOOR CODE PLAN
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
AS101
ARCHITECTURAL SITE PLAN
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
ACD111
FIRST FLOOR DEMO RCP - AREA 111
0
08/28/2026
08/28/2026
26.08.28 CD's
Published
ACD112
FIRST FLOOR DEMO RCP - AREA 112
0
08/28/2026
08/28/2026
26.08.28 CD's
Published
ACD113
FIRST FLOOR DEMO RCP - AREA 113
0
08/28/2026
08/28/2026
26.08.28 CD's
Published
A110
FIRST FLOOR PLAN - OVERALL
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
A111
FIRST FLOOR PLAN - AREA 111
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
A112
FIRST FLOOR PLAN - AREA 112
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
A113
FIRST FLOOR PLAN - AREA 113
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
AC110
FIRST FLOOR REFLECTED CEILING PLAN - OVERALL
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
AC111
FIRST FLOOR REFLECTED CEILING PLAN - AREA 111
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
AC112
FIRST FLOOR REFLECTED CEILING PLAN - AREA 112
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
AC113
FIRST FLOOR REFLECTED CEILING PLAN - AREA 113
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
A160
OVERALL ROOF PLAN
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
A161
ENLARGED ROOF PLAN
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
A400
ENLARGED PLANS
2
08/28/2026
08/28/2026
26.08.28 CD's
Published
A500
DETAILS
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
A600
DOOR AND WINDOW SCHEDULES
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
Architectural
Structural S001
GENERAL NOTES
Page 1 of 3
Printed on Wed Oct 14, 2026 at 04:22 pm MDT Job #: 8736 BVSD - Heatherwood ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction
Drawing Number
Drawing Title
Revision
Drawing Date
Received Date
Set
Status
Mechanical MD-113
HVAC DEMOLITION PLAN - AREA 113
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
MD-200
HVAC ENLARGED DEMOLITION PLANS
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
M-001
MECHANICAL LEGENDS & NOTES
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
M-002
MECHANICAL SCHEDULES
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
M-003
MECHANICAL CALCULATIONS
0
08/28/2026
08/28/2026
26.08.28 CD's
Published
M-111
HVAC PLAN - AREA 111
0
05/15/2026
05/15/2026
26.05.15 - DD's
Published
M-112
HVAC PLAN - AREA 112
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
M-113
HVAC PLAN - AREA 113
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
M-114
ROOF HVAC PLAN - AREA 113
0
08/28/2026
08/28/2026
26.08.28 CD's
Published
M-200
HVAC ENLARGED PLANS
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
M-401
MECHANICAL DETAILS
0
08/28/2026
08/28/2026
26.08.28 CD's
Published
M-501
MECHANICAL CONTROLS
0
08/28/2026
08/28/2026
26.08.28 CD's
Published
PD-113
PLUMBING DEMOLITION PLAN - AREA 113
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
P-001
PLUMBING LEGENDS & NOTES
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
P-113
PLUMBING PLAN - AREA 113
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
P-131
ROOF PLUMBING PLAN - AREA 111
0
08/28/2026
08/28/2026
26.08.28 CD's
Published
P-132
ROOF PLUMBING PLAN - AREA 112
0
08/28/2026
08/28/2026
26.08.28 CD's
Published
ED-111
LIGHTING DEMOLITION PLAN - AREA 111
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
ED-112
LIGHTING DEMOLITION PLAN - AREA 112
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
ED-113
LIGHTING DEMOLITION PLAN - AREA 113
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-001
ELECTRICAL LEGENDS & NOTES
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-002
ELECTRICAL SCHEDULES
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
Plumbing
Electrical
Page 2 of 3
Printed on Wed Oct 14, 2026 at 04:22 pm MDT Job #: 8736 BVSD - Heatherwood ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction
Drawing Number
Drawing Title
Revision
Drawing Date
Received Date
Set
Status
E-011
ELECTRICAL ONE-LINE DIAGRAM
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-111
LIGHTING PLAN - AREA 111
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-112
LIGHTING PLAN - AREA 112
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-113
LIGHTING PLAN - AREA 113
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-121
OVERALL POWER PLAN - LEVEL 1
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
E-201
ENLARGED ELECTRICAL PLANS
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
FS101
KITCHEN EQUIPMENT
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
FS102
KITCHEN PLUMBING / ELECTRICAL
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
FS104
KITCHEN EXHAUST HOOD
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
FS501
KITCHEN GENERAL NOTES - DETAILS
1
08/28/2026
08/28/2026
26.08.28 CD's
Published
Food Service
Page 3 of 3
Printed on Wed Oct 14, 2026 at 04:38 pm MDT Job #: 8736 BVSD - Heatherwood ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction
Current Specifications Number
Description
Revision
Issued Date
Received Date
Set
00 - Procurement and Contracting Requirements 00 0103
PROJECT DIRECTORY
0
26.08.28 - CD's
00 4322
UNIT PRICES FORM
0
26.08.28 - CD's
00 4323
ALTERNATES FORM
0
26.08.28 - CD's
00 5000
CONTRACTING FORMS AND SUPPLEMENTS
0
26.08.28 - CD's
00 7200
GENERAL CONDITIONS
0
26.08.28 - CD's
000107
SEALS PAGE
0
26.08.28 - CD's
000108
Table of Contents
0
26.08.28 - CD's
000110
Cover Page
0
26.08.28 - CD's
01 - General Requirements 01 1000
SUMMARY
0
26.08.28 - CD's
01 2000
PRICE AND PAYMENT PROCEDURES
0
26.08.28 - CD's
01 2200
UNIT PRICES
0
26.08.28 - CD's
01 2300
ALTERNATES
0
26.08.28 - CD's
01 2500
SUBSTITUTION PROCEDURES
0
26.08.28 - CD's
01 3000
ADMINISTRATIVE REQUIREMENTS
0
26.08.28 - CD's
01 3216
CONSTRUCTION PROGRESS SCHEDULE
0
26.08.28 - CD's
01 4000
QUALITY REQUIREMENTS
0
26.08.28 - CD's
01 5000
TEMPORARY FACILITIES AND CONTROLS
0
26.08.28 - CD's
01 5713
TEMPORARY EROSION AND SEDIMENT CONTROL
0
26.08.28 - CD's
01 6000
PRODUCT REQUIREMENTS
0
26.08.28 - CD's
01 6116
VOLATILE ORGANIC COMPOUND (VOC) CONTENT RESTRICTIONS
0
26.08.28 - CD's
01 7000
EXECUTION AND CLOSEOUT REQUIREMENTS
0
26.08.28 - CD's
01 7419
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
0
26.08.28 - CD's
01 7800
CLOSEOUT SUBMITTALS
0
26.08.28 - CD's
01 7900
DEMONSTRATION AND TRAINING
0
26.08.28 - CD's
01 9113
GENERAL COMMISSIONING REQUIREMENTS
0
26.08.28 - CD's
02 - Existing Conditions 02 4100
DEMOLITION
0
26.08.28 - CD's
02 4119
SELECTIVE STRUCTURE DEMOLITION
0
26.08.28 - CD's
03 2000
CONCRETE REINFORCING
0
26.08.28 - CD's
03 3000
CAST-IN-PLACE CONCRETE
0
26.08.28 - CD's
0
26.08.28 - CD's
0
26.08.28 - CD's
03 - Concrete
06 - Wood, Plastics, and Composites 06 1000
ROUGH CARPENTRY
07 - Thermal and Moisture Protection 07 0150.19
PREPARATION FOR RE-ROOFING
Page 1 of 3
Printed on Wed Oct 14, 2026 at 04:38 pm MDT Job #: 8736 BVSD - Heatherwood ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction
Number
Description
Revision
Issued Date
Received Date
Set
07 0553
FIRE AND SMOKE ASSEMBLY IDENTIFICATION
0
26.08.28 - CD's
07 5300
ELASTOMERIC MEMBRANE ROOFING
0
26.08.28 - CD's
07 6200
SHEET METAL FLASHING AND TRIM
0
26.08.28 - CD's
07 7100
ROOF SPECIALTIES
0
26.08.28 - CD's
07 9200
JOINT SEALANTS
0
26.08.28 - CD's
08 4313
ALUMINUM-FRAMED STOREFRONTS
0
26.08.28 - CD's
08 8000
GLAZING
0
26.08.28 - CD's
087100
DOOR HARDWARE
0
26.08.28 - CD's
09 2116
GYPSUM BOARD ASSEMBLIES
0
26.08.28 - CD's
09 9113
EXTERIOR PAINTING
0
26.08.28 - CD's
09 9123
INTERIOR PAINTING
0
26.08.28 - CD's
FOOD SERVICE EQUIPMENT
0
26.08.28 - CD's
22 0500
COMMON WORK RESULTS FOR PLUMBING
0
26.08.28 - CD's
22 0513
COMMON MOTOR REQUIREMENTS FOR PLUMBING EQUIPMENT
0
26.08.28 - CD's
22 0519
METERS AND GAUGES FOR PLUMBING PIPING
0
26.08.28 - CD's
22 0523
GENERAL DUTY VALVES FOR PLUMBING
0
26.08.28 - CD's
22 0529
HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT
0
26.08.28 - CD's
22 0553
IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT
0
26.08.28 - CD's
22 0700
PLUMBING INSULATION
0
26.08.28 - CD's
22 1023
PLUMBING PUMPS
0
26.08.28 - CD's
22 1116
DOMESTIC WATER PIPING
0
26.08.28 - CD's
22 1119
DOMESTIC WATER PIPING SPECIALITIES
0
26.08.28 - CD's
22 1123
FACILITY NATURAL GAS PIPING
0
26.08.28 - CD's
22 3000
WATER HEATERS
0
26.08.28 - CD's
08 - Openings
09 - Finishes
11 - Equipment 11 4000 22 - Plumbing
23 - Heating, Ventilating, and Air Conditioning (HVAC) 23 0500
COMMON WORK RESULTS FOR MECHANICAL
0
26.08.28 - CD's
23 0507
MOTORS, DRIVES, MOTOR CONTROLLERS AND ELECTRICAL REQUIRED FOR
0
26.08.28 - CD's
23 0510
BASIC PIPING MATERIALS AND METHODS
0
26.08.28 - CD's
23 0518
PIPING SPECIALITIES
0
26.08.28 - CD's
23 0519
METERS AND GAUGES FOR MECHANICAL PIPING
0
26.08.28 - CD's
23 0523
GENERAL DUTY VALVES FOR MECHANICAL PIPING
0
26.08.28 - CD's
23 0529
HANGERS AND SUPPORTS FOR MECHANICAL SYSTEMS
0
26.08.28 - CD's
23 0540
VIBRATION CONTROL FOR MECHANICAL PIPING AND EQUIPMENT
0
26.08.28 - CD's
23 0553
IDENTIFICATION FOR MECHANICAL SYSTEMS
0
26.08.28 - CD's
23 0593
TESTING, ADJUSTING, AND BALANCING FOR MECHANICAL
0
26.08.28 - CD's
23 0700
INSULATION FOR MECHANICAL SYSTEMS
0
26.08.28 - CD's
23 0900
INSTRUMENTATION AND CONTROL FOR MECHANICAL SYSTEMS
0
26.08.28 - CD's
Page 2 of 3
Printed on Wed Oct 14, 2026 at 04:38 pm MDT Job #: 8736 BVSD - Heatherwood ES Renovation 7750 Concord Dr Boulder, Colorado 80301 Adolfson & Peterson Construction
Number
Description
Revision
Issued Date
Received Date
Set
23 0993
SEQUENCES OF OPERATION FOR MECHANICAL SYSTEMS
0
26.08.28 - CD's
23 3113
METAL DUCTS
0
26.08.28 - CD's
23 3300
AIR DUCT ACCESSORIES
0
26.08.28 - CD's
23 3400
HVAC FANS
0
26.08.28 - CD's
23 3600
AIR TERMINAL UNITS
0
26.08.28 - CD's
23 3713
DIFFUSERS, REGISTERS, AND GRILLES
0
26.08.28 - CD's
23 6200
PACKAGED COMPRESSOR AND CONDENSER UNITS
0
26.08.28 - CD's
23 7323
CUSTOM INDOOR CENTRAL STATION AIR HANDLING UNITS
0
26.08.28 - CD's
23 7443
ROOFTOP HEATING AND COOLING UNITS
0
26.08.28 - CD's
23 8000
DECENTRALIZED HVAC EQUIPMENT
0
26.08.28 - CD's
26 0500
COMMON WORK RESULTS FOR ELECTRICAL
0
26.08.28 - CD's
26 0519
LOW VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
0
26.08.28 - CD's
26 0529
HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
0
26.08.28 - CD's
26 0533
RACEWAY AND WIREWAY FOR ELECTRICAL SYSTEMS
0
26.08.28 - CD's
26 0534
CABINETS, BOXES, AND FITTINGS
0
26.08.28 - CD's
26 0553
IDENTIFICATION FOR ELECTRICAL SYSTEMS
0
26.08.28 - CD's
26 0583
WIRING CONNECTIONS
0
26.08.28 - CD's
26 0923
LIGHTING CONTROL DEVICES
0
26.08.28 - CD's
26 2726
LOW VOLTAGE CIRCUIT PROTECTIVE DEVICES
0
26.08.28 - CD's
26 2800
Low-Voltage Circuit Protective Devices
0
26.08.28 - CD's
26 5000
LIGHTING
0
26.08.28 - CD's
26 5200
EMERGENCY LIGHTING
0
26.08.28 - CD's
26 - Electrical
32 - Exterior Improvements 32 1313
CONCRETE PAVING
0
26.08.28 - CD's
32 3113
CHAIN LINK FENCES AND GATES
0
26.08.28 - CD's
Page 3 of 3
Exhibit B Assumptions and clarifications made in preparing the GMP
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
K1225 - BVSD - HEATHERWOOD ES RENOVATIONS 7750 Concord Dr, Boulder, CO , 80301 Estimate: CD Estimate R1
PREPARED FOR:
ARCHITECT / DESIGNER:
BVSD
RTA
DATE PRINTED: 10/15/2026
Clarifications Report General Clarifications -
Prevailing wages have not been included.
-
State, Sales, Use, and County taxes are not included. No taxes (0%) have been carried in our pricing
-
A&P excludes any delegated design that is not listed in the project documents.
Items by Others -
All independent testing and inspections, including commissioning.
-
Technology – Servers, computers, phones, uninterruptible power supply (UPS), etc.
-
Residential Equipment (Kitchen appliances, Fitness Equipment, etc).
-
Land Costs, Legal Fees, or Tap Fees.
-
Architectural and Engineering Fees.
-
Owner contingency.
-
All fees associated with utilities will be paid for by Owner (water, electric, gas).
-
Any expenses associated with dry utilities and getting them to the site (cable, fiber, power and gas).
-
Removal or working with hazardous materials, including asbestos and lead abatement as defined by OSHA.
-
All moving costs.
-
All artwork - purchasing, moving, and installation.
-
Technology - Computers, Servers, phones, etc. – purchasing, moving and installation.
-
Furniture, Desks, chairs, tables, moveable casework – purchasing, moving and installation.
-
Audio / Visual Projectors, Projection Screens, Smart Boards, Televisions.
Documents -
CD Drawings dated - 08.28.2026
-
CD Specification dated - 08.28.2026
-
Addendum 1 dated 09.16.2026
-
RFI responses dated 9.30.2026
C Interiors - Included an allowance of $15K for 3rd party design for wind for rooftop equipment. - Included an allowance of $3K for disconnecting & reconnecting MEP Rooftop Equipment. - We are assuming existing roof is ballasted roof and not included additional steel for the new roof assembly. - We have assumed new sidewalk to be 4in thick concrete paving. - We have not included any Ansual System at the new exhaust hood. - We have not included any intercom scope on this project.
Z General Requirements DATE PRINTED: 10/15/2026
Z General Requirements - A site security guard has not been included. - General protection of adjacent surfaces is included for the work shown in the plans.
DATE PRINTED: 10/15/2026
Exhibit C Itemization of the GMP
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
797 Ventura Street, Aurora, CO 80011 Project: K1225 - BVSD - Heatherwood ES Renovations Owner: BVSD Architect: RTA
Date: Estimator: Project SF: Duration in Months: Estimate #:
10/16/26 Rakshita 59,980 3.00 CD R1
Project Summary Sheet - Estimated Cost of the Work
Division #0 Division #1 Division #2 Division #3 Division #4 Division #5 Division #6 Division #7 Division #8 Division #9 Division #10 Division #11 Division #12 Division #13 Division #14 Division #21 Division #22 Division #23 Division #25 Division #26 Division #27 Division #28 Division #31 Division #32 Division #33
Procurement and Contracting Requirements General Requirements Existing Conditions Concrete Masonry Metals Wood, Plastics, and Composites Thermal and Moisture Protection Openings Finishes Specialties Equipment Furnishings Special Construction Conveying Equipment Fire Suppression Plumbing Heating, Ventilating and Air Conditioning Integrated Automation Electrical Communications Electronic Safety and Security Earthwork Exterior Improvements Utilities
DD Estimate CD Estimate Difference $103,344 $87,058 ($16,286) $282,508 $258,739 ($23,769) $107,146 $17,280 ($89,866) $0 $4,485 $4,485 $0 $0 $0 $7,280 $0 ($7,280) $5,171 $25,784 $20,613 $482,184 $182,921 ($299,263) $0 $0 $0 $98,348 $46,612 ($51,737) $0 $0 $0 $68,135 $766,739 $698,604 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,330 $11,330 $15,496 $0 ($15,496) $2,360,643 $2,029,219 ($331,424) $0 $0 $0 $263,532 $150,161 ($113,371) $0 $0 $0 $0 $0 $0 $23,833 $4,750 ($19,083) $121,594 $108,945 ($12,649) $0 $0 $0
$1.45
/SF
2.4% of Direct Costs
$4.31
/SF
7.0% of Direct Costs
$0.29
/SF
0.5% of Direct Costs
$0.07
/SF
0.1% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$0.43
/SF
0.7% of Direct Costs
$3.05
/SF
5.0% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$0.78
/SF
1.3% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$12.78
/SF
20.8% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$0.19
/SF
0.3% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$33.83
/SF
54.9% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$2.50
/SF
4.1% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$0.08
/SF
0.1% of Direct Costs
$1.82
/SF
2.9% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
100.0% of Direct Costs
Subtotal
$3,939,213
$3,694,023
($245,191)
$61.59
/SF
Utility Tap & Devel. Fees Permit Allowance Use Tax Construction Contingency Builders Risk Insurance Comprehensive General Liability Insurance Performance and Payment Bond Escalation Allowance Contractors Fee Preconstruction Services
$0 $0 $0 $315,137 $8,509 $45,644 $28,930 $0 $199,954 $17,500
$0 $0 $0 $123,142 $7,388 $49,257 $27,912 $0 $185,514 $17,500
$0 $0 $0 ($191,995) ($1,121) $3,612 ($1,017) $0 ($14,440) $0
$0.00
/SF
$0.00
/SF
0.00% of Project
$0.00
/SF
0.00% of Project
$2.05
/SF
3.00% of Project
$0.12
/SF
0.20% of Costs
$0.82
/SF
1.20% of Project
$0.47
/SF
0.68% of Project
$0.00
/SF
0.00% of Project
$3.09
/SF
4.86% of Project
$0.29
/SF
Orignal contract amount
$4,554,888
$4,104,736
($450,151)
$80.83
/SF
100.0% of Project
Estimated Cost of Construction
CD R1 Accepted Alternates
$41,352
A1 : Floor Sink Replacement in Dishwashing 138
$4,124
A2 : South Fence and Gates Replacement
$252,734
V18a : REQ-88403 Lighting Fixtures – Interior – Troffer Renewal Priority 1 V18b : REQ-88403 Lighting Fixtures – Interior – Troffer Renewal Priority 2
$88,823
V18c : REQ-88403 Lighting Fixtures – Interior – Troffer Renewal Priority 3
$257,899
V18d : REQ-88403 Lighting Fixtures – Interior – Troffer Renewal Priority 4
$58,726
V18e : REQ-88403 Lighting Fixtures – Interior – Troffer Renewal Priority 5
$39,619
CD w/ Accepted Alternates Original Contact Amount fGMP Amendment Total Contract Amount
$4,848,013 $ 17,500.00 $4,830,513 $4,848,013
Detail Report DESCRIPTION
QTY UOM UNIT PRICE
00 Procurement and Contracting Requirements
NOTES / COMMENTS
$87,058
00 72 00 AIA General Conditions 00100 General conditions of the contract
TOTAL COST
$87,058 1.00 ls
87,058.00
Subtotal 00 72 00 AIA General Conditions
$87,058
Per RFP Response
$87,058
Subtotal 00 Procurement and Contracting Requirements
$87,058
01 General Requirements
$258,739
01 32 00 Construction Progress Documentation
$0
01100 Video Monitoring and documentation
Not Included
01140 360-degree Site Photos
Included
Subtotal 01 32 00 Construction Progress Documentation
$0
01 33 00 Submittal Procedures
$0
01110 Delivery Costs / Messenger Services
Included
01130 Reproduction Costs
Included
01170 Sustainability Project Requirements
Not Included
Subtotal 01 33 00 Submittal Procedures
$0
01 35 53 Security Procedures
$0
01160 Site Security Cameras and Monitoring
Not Included
Subtotal 01 35 53 Security Procedures
$0
01 45 00 Quality Control
$0
01200 Independent testing
Not Included
01210 Soil compaction tests
Not Included
01220 Concrete tests
Not Included
01230 Steel weld test / inspections
Not Included
01250 Field Quality Control procedures
Included
01260 3rd Party envelope consultant
Not Included
Subtotal 01 45 00 Quality Control
$0
01 51 00 Temporary Facilities 01270 Screening Around Temp Fencing
$36,750 1,000.00 lf
1.00
$1,000
01270 Temporary electricity - jobsite 01270 Temporary Fencing
DATE PRINTED: 10/15/2026
By Owner 1,000.00 lf
9.00
$9,000
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
01280 Generators 36kw
Not Included
01290 Fuel for Generator (full load)
Not Included
01300 Generator setup / and Containment
Not Included
01310 Temporary Fire Protection
3.00 mo
375.00
$1,125
01330 Temp Heating Equipment & Labor
Not Included
01340 Temp Heating Fuel
Not Included
01350 Temporary building enclosure for temp heating
Not Included
01360 Temporary lighting
General lighting by EC
01370 Temporary Water
By Owner
01380 Sanitary Facilities
3.00 mo
4,085.00
$12,255
For Subcontractors
01390 Temporary Elevators
Not Included
01400 Temporary Hoists
Not Included
01410 Gradall for Jobsite
Not Included
01420 Bobcat & Operator for Jobsite
Not Included
01430 Fuel for equipment
Not Included
01440 Temporary Cranes
By Division
01450 Temporary scaffolding and platforms
By Division
01460 Temporary Stairs and Ramps
Not Included
01470 Temporary Swing Staging
Not Included
01480 Temporary Access Roads
Not Included
01490 Weather Conditions
Not Included
01500 Dumpsters
18.00 ea
550.00
$9,900
01510 Temporary Parking Areas
By Earthworker
01520 Temporary Air & Noise Barriers
Not Included
01540 Temporary Barricades
By Division
01560 Temporary Connex(s) 01620 Temporary interior signage
3.00 mo
650.00
$1,950
59,980.00 sf
0.03
$1,520
Subtotal 01 51 00 Temporary Facilities
$36,750
01 70 00 Execution and Closeout 01630 AP Labor
$190,376 1.00 ls
190,376.00
$190,376
01720 Construction Surveying
By Trade
01730 Protection of Adjacent Construction
By Division
Subtotal 01 70 00 Execution and Closeout
$190,376
01 74 00 Cleaning 01630 Progress Cleaning Material
DATE PRINTED: 10/15/2026
$31,613 456,126.00 sf
0.00
$1,520
DESCRIPTION 01710 Final Clean Building
QTY UOM UNIT PRICE 59,980.00 sf
0.50
Subtotal 01 74 00 Cleaning
TOTAL COST
NOTES / COMMENTS
$30,093 $31,613
01 90 00 Life Cycle Activities
$0
01740 Substructure Commissioning
Not Included
01750 Structure commissioning
Not Included
01760 Exterior enclosure commissioning
Not Included
01770 Roofing Commissioning
Not Included
01780 Systems Commissioning
Not Included
Subtotal 01 90 00 Life Cycle Activities
$0
Subtotal 01 General Requirements
$258,739
02 Existing Conditions
$17,280
02 41 00 Demolition
$17,280
0000 Demolition Scope of Work
1.00 sub
17,280.00
$17,280
02105 Demo Walk-in Cooler w/ Refrigeration system
With Div 11
02235 Demolish door & frame in gyp partition wall
Not Anticipated
02235 Demolish gyp Ceiling
Included
02255 Demo Existing Hood
Included
02255 Demo Related Ductwork and Exhaust fan
Included
02395 Demo ACT for the Kitchen Hood
Included
02395 Remove Salvage ACT for Exhaust Fan Scope
Included
02395 Saw Cut Slab
Included
Subtotal 02 41 00 Demolition
$17,280
Subtotal 02 Existing Conditions
$17,280
03 Concrete
$4,485
03 11 00 Concrete Forming 03050 Concrete Scope of Work
$4,485 1.00 ea
4,485.00
$4,485
03050 Infill Concrete Slab for the New Boilers
Included
03050 Reinforcement
Included
03050 Remove Spoils
Included
03050 Vapor Barrier
Included
Subtotal 03 11 00 Concrete Forming Subtotal 03 Concrete
DATE PRINTED: 10/15/2026
$4,485 $4,485
DESCRIPTION
QTY UOM UNIT PRICE
06 Woods, Plastics and Composites
TOTAL COST $25,784
06 10 10 Rough Carpentry
$25,784
06019 Mechanical Curb Extentions
204.00 lf
18.80
$3,835
06019 Protect Existing Flooring in the Kitchen
200.00 sf
0.91
$182
06019 Protect Roof access areas/ Interior Walls
5,682.00 sf
0.91
$5,171
06019 Rough Carpentry at Roof
2,390.00 sf
1.10
$2,629
06019 Temp Roof at Penthouse
2,390.00 sf
2.53
$6,047
07213 Interior Rough Carpentry
4,000.00 sf
1.98
$7,920
Subtotal 06 10 10 Rough Carpentry
$25,784
Subtotal 06 Woods, Plastics and Composites
$25,784
07 Thermal and Moisture Protection
$182,921
07 53 23 Roofing & Roof Insulation 0000 Roofing Scope of Work
NOTES / COMMENTS
$181,637 1.00 sub
177,675.00
$177,675
02195 Demolish Built up roof Gravel and Deck
Included
02195 Remove and Replace Roof Drains at Built Up Roof Replacement
Included
02195 Remove Metal Gutter
Included
02195 Remove Roof Walk Pad
Included
02265 Demolish Penthouse Roof for Access to MZ
Included
02265 Temp Roof for the Penthouse
w/ Div 6
05420 Safety Measures for Roof Work Perimeter/Openings
631.00 lf
5.00
$3,155
07335 90 mil EPDM fully adhered
Included
07335 Flashing and Caulking
Included
07335 Scaffolding for Roof Access
Not Included
07335 Tapered Insulation at Existing DayLight Device
Included
07370 Add for tapered insulation
Included
07370 Provide Extended Wind Warranty
Included
07370 Roof Cleanup
16,144.00 sf
0.05
$807
07390 Roof expansion joint
Included
07405 Rubber roof walk pads 2' x 2'
Included
Subtotal 07 53 23 Roofing & Roof Insulation
$181,637
07 60 00 Flashing & Sheet Metal
$1,099
07465 Curb flashing / Counterflashing at Exhaust 07480 Misc. flashing and terminations
DATE PRINTED: 10/15/2026
Included 140.00 lf
7.85
$1,099
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
07480 New Sheet Metal Gutter
Included
Subtotal 07 60 00 Flashing & Sheet Metal
$1,099
07 71 00 Roof Specialties & Accessories 07540 Concrete Splash Block
NOTES / COMMENTS
$185 1.00 ea
185.00
Subtotal 07 71 00 Roof Specialties & Accessories
$185 $185
Subtotal 07 Thermal and Moisture Protection
$182,921
08 Openings
$0
08 10 00 Doors and Frames
$0
08010 Exterior Door and HM Frame with hardware
Not Included
08015 14x14 Door Window
With Div 11
Subtotal 08 10 00 Doors and Frames
$0
Subtotal 08 Openings
$0
09 Finishes
$46,612
09 21 16 Gypsum Board Assemblies 00000 Drywall Scope of Work
$5,500 1.00 sub
5,500.00
$5,500
09065 Minor Patch and Repair drywall Ceiling at Hood 09065 Patch and Repair drywall at Kitchen Subtotal 09 21 16 Gypsum Board Assemblies
$5,500
09 51 00 Acoustical Ceilings 02395 Acoustic Ceiling Scope of Work
$25,262 1.00 ls
3,700.00
$3,700
02395 Reinstall Existing ACT for Exhaust Fan Scope 09065 Patch and Repair ACT/ Drywall Ceilings for RTU Replacement
Included 3,885.00 sf
5.55
$21,562
09253 Integral Insulated Ceiling
With Div 11
09253 Remove And Reinstall New ACT at Kitchen
Included
Subtotal 09 51 00 Acoustical Ceilings
$25,262
09 60 00 Flooring
$0
00000 Integral Insulated Floors
With Div 11
Subtotal 09 60 00 Flooring
$0
09 65 00 Resilient Flooring 09637 Floor protection
DATE PRINTED: 10/15/2026
$6,500 10,000.00 sf
0.65
$6,500
DESCRIPTION
QTY UOM UNIT PRICE
Subtotal 09 65 00 Resilient Flooring
TOTAL COST
NOTES / COMMENTS
$6,500
09 90 00 Painting and Coating
$9,350
0000 Paint Scope of work
1.00 sub
7,850.00
$7,850
09720 Misc Touch up at completion
1.00 ls
1,500.00
$1,500
09720 Paint and Touch up at Kitchen - Exhaust, Hood and Walk in 09720 Painting penthouse - exterior only 09720 Touch up Doors and Frames at Penthouse Subtotal 09 90 00 Painting and Coating
$9,350
Subtotal 09 Finishes
$46,612
11 Equipment
$766,739
11 40 00 Food Service Equipment 0000 Food Service Scope of Work
$66,739 1.00 sub
66,739.00
$66,739
11185 Ansul System - Fire suppression - Connections
Not Included
11185 Exhaust Hood System - Kitchen - Commercial Renewal
With Div 23
11400 compliant with all current IECC requirements
Included
11400 Install new walk-in cooler Subtotal 11 40 00 Food Service Equipment
$66,739
11 68 13 Playground Equipment 00000 UA Playground Improvements
$700,000 1.00 allow
700,000.00
Subtotal 11 68 13 Playground Equipment
$700,000 $700,000
Subtotal 11 Equipment
$766,739
21 Fire Suppression
$11,330
21 00 00 Fire Suppression 00000 Fire Suppression Scope of Work Subtotal 21 00 00 Fire Suppression Subtotal 21 Fire Suppression 22 Plumbing 22 00 00 Plumbing
Allowance
$11,330 1.00 ls
11,330.00
$11,330 $11,330 $11,330 $0 $0
22235 Overflow Drain
With Div 23
22235 Roof drains
With Div 23
DATE PRINTED: 10/15/2026
DESCRIPTION
QTY UOM UNIT PRICE
Subtotal 22 00 00 Plumbing
$0
23 Heating, Ventilating and Air Conditioning
$2,029,219
23 00 00 Heating, Ventilating and Air Conditioning
$2,029,219 1.00 sub
1,994,219.00
$1,994,219
23005 Evacuate refrigerants - In the Walkin
Included
23005 New Refrigeration line sets and refrigerants 23043 MEP Scope Integration
NOTES / COMMENTS
$0
Subtotal 22 Plumbing
00000 Mechanical Scope of Work
TOTAL COST
With Div 11 1.00 ls
20,000.00
$20,000
23140 Air Handling Unit - MZ-01 thru MZ-04 - VAV Renewal
Included
23160 Demo Existing Water Heater Storage Tank
Included
23160 Haul off - Water heater
Included
23160 New Storage Tank for Kitchen Water Heater
Included
23160 Piping Configuration
Included
23160 Remove and Replace Building Domestic Water Heater
Included
23160 Remove and Replace Kitchen Domestic Water Heater
Included
23215 Air-Cooled Condensing Unit - MZ-1 thru MZ-04 40 Tons Renewal
Included
23260 3rd Party Design for Wind
1.00 allow
15,000.00
$15,000
Allowance
23260 Condensing Piping for Walk In Cooler/ Freezer
Included
23260 Fire wrap , makeup air unit - Exhaust Hood
Included
23260 Install new ductwork fully welded, stainless-steel - Exhaust Hood
Included
23260 New Exhaust Hood
Included
Subtotal 23 00 00 Heating, Ventilating and Air Conditioning
$2,029,219
Subtotal 23 Heating, Ventilating and Air Conditioning
$2,029,219
26 Electrical
$150,161
26 00 00 Electrical
$150,161
00000 Electrical Scope of Work
1.00 sub
137,161.00
$137,161
23160 Disconnections/ Reconnections for Roof Replacement
1.00 allow
3,000.00
$3,000
Allowance
23160 Electrical Connections - Water Heater and Storage Tank
Included
26005 Electrical Connection - For Walk in Freezer
Included
26005 Electrical Connections - Exhaust Hood
Included
DATE PRINTED: 10/15/2026
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
26005 Electrical Connections for MZs and CUs
Included
26005 Lighting Fixtures - Walk In Freezer 26029 MEP Scope Integration
with Refrigeration 1.00 ls
10,000.00
Subtotal 26 00 00 Electrical
$10,000 $150,161
Subtotal 26 Electrical
$150,161
27 Communications
$0
27 51 00 Distributed AV systems
$0
27045 Intercom System
Not Included
Subtotal 27 51 00 Distributed AV systems
$0
Subtotal 27 Communications
$0
31 Earthwork
$4,750
31 00 00 Earthwork 0000 Exterior Demolition of Work
NOTES / COMMENTS
$4,750 1.00 sub
4,750.00
$4,750
31295 Grind Down High Point Areas in Concrete Sidewalk
Included
31295 Remove Existing Concrete Sidewalk
Included
32270 Fine grading/subgrade prep for new Sidewalk
w/ Div 32
Subtotal 31 00 00 Earthwork
$4,750
Subtotal 31 Earthwork
$4,750
32 Exterior Improvements
$108,945
32 13 00 Rigid Paving 00000 Rigid Paving Scope of Work 32036 Cones/ Tapes to protect the area
$37,266 1.00 sub 2,387.00 sf
19,878.00
$19,878
1.08
$2,578
32036 New Concrete Sidewalk
Included
32036 Remove Soil and Organic Matter from Sidewalk Joints and Reseal Joints 32036 Route and Seal Cracks in Concrete Paving 32036 Route and Seal Cracks in Concrete Sidewalk
Included 1.00 sub
14,810.00
Subtotal 32 13 00 Rigid Paving
$37,266
32 31 00 Fences and Gates 0000 Fencing Scope of Work
$14,810
$41,679 1.00 sub
41,679.00
$41,679
32516 New Chainlink Fence 32516 Remove Chainlink Fence
DATE PRINTED: 10/15/2026
Included
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
32516 Straighten Existing Posts and Re-Tension Existing Fabric on Chainlink
Included
Subtotal 32 31 00 Fences and Gates
$41,679
32 90 00 Planting
$30,000
32036 Landscaping and Asphalt and Repair Allowance for Fence Replacement
1.00 allow
5,000.00
$5,000
32036 Landscaping and Site Concrete Repair Allowance for Crane
1.00 allow
25,000.00
$25,000
Subtotal 32 90 00 Planting
$30,000
Subtotal 32 Exterior Improvements
$108,945
DATE PRINTED: 10/15/2026
NOTES / COMMENTS
Exhibit D Contract Schedule & change order for the GMP is Contract Schedule to be provided after amendment executed
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Line
Name
Duration
Start
Finish 4
BVSD Heatherwood ES
550d
8/1/2025
10/4/2027
Milestones
520d
8/1/2025
8/20/2027
School Milestones
512d
8/1/2025
8/11/2027
8/1/2025 A
8/13/2025 A
1
Summer Break - 2025 (School Back In Session)
9d
2
Thankgiving Break - 2025
3d 11/24/2025 A 11/26/2025 A
3
Winter Break - 2025
8d 12/23/2025 A
1/6/2026 A
4
Spring Break - 2026
5d 3/16/2026 A
3/20/2026 A
5
Summer Break - 2026
15d 5/21/2026 A
8/13/2026 A
6
Thankgiving Break - 2026
4d 11/23/2026
11/30/2026
7
Winter Break - 2026
10d 12/22/2026
1/7/2027
8
Spring Break - 2027
5d
3/23/2027
3/29/2027
9
Summer Break - 2027 - START
5/20/2027
5/20/2027
10
8/11/2027
8/11/2027
8/1/2025
10/26/2026
313d
8/1/2025
10/26/2026
150d
8/1/2025 A
10/26/2026
Summer Break - 2027 - FINISH Project Milestones Preconstruction Milestones
11
DAT Meetings - Finals
12
Notice to Proceed
13
DAT Meetings
14
Post-Award Meetings Construction Milestones
313d
2025 2026 2027 2028 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14
Summer Break - 2025 (School Back In Session) Thankgiving Break - 2025
Winter Break - 2025 Spring Break - 2026
Summer Break - 2026
Thankgiving Break - 2026 Winter Break - 2026
Spring Break - 2027 Summer Break - 2027 - START
Summer Break - 2027 - FINISH
DAT Meetings - Finals
10/15/2025 A 10/15/2025 A
Notice to Proceed
123d 12/1/2025 A 10/14/2026 A
DAT Meetings
12/15/2025 A 12/15/2025 A 454d
11/4/2025
Post-Award Meetings
8/20/2027
256d 11/4/2025 A
7/1/2027
Mobilization Start
3/24/2027
3/24/2027
Mobilization Start
Rough-in Start
3/24/2027
3/24/2027
Rough-in Start
18
Abatement Start
5/19/2027
5/19/2027
19
Abatement Finish
5/25/2027
5/25/2027
Abatement Finish
20
Rough-in Finish
5/25/2027
5/25/2027
Rough-in Finish
21
Demo Start
5/26/2027
5/26/2027
Demo Start
22
Demo Finish
7/7/2027
7/7/2027
Demo Finish
23
TCO
7/30/2027
7/30/2027
TCO
24
Owner Move-in Complete
8/9/2027
8/9/2027
15
Early Investigations
16 17
25
Substantial Completion Preconstruction & Design
456d
RFP / RFQ Information
33d
8/20/2027
8/20/2027
8/28/2025
6/17/2027
8/28/2025
10/15/2025
26
RFP/RFQ - Issuance of RFP
8/28/2025 A 8/28/2025 A
27
RFP/RFQ - Pre-Proposal Submission
9/8/2025 A
9/8/2025 A
Early Investigations
Abatement Start
Owner Move-in Complete
Substantial Completion
RFP/RFQ - Issuance of RFP
RFP/RFQ - Pre-Proposal Submission
BVSD Heattherwood ES Proposal Schedule Boulder Valley School District
Job #: BVSD Heatherwood ES Rev. date: 10/19/2026 11:56:11 AM
Data Date: 10/15/2026
Page 1 of 14
BVSD Heatherwood ES Progress 10/15/26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish 4
2025 2026 2027 2028 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14
28
RFP/RFQ - Inquiries Due
9/12/2025 A 9/12/2025 A
RFP/RFQ - Inquiries Due
29
RFP/RFQ - Addendum's
9/18/2025 A 9/18/2025 A
RFP/RFQ - Addendum's
30
RFP/RFQ - Submission Deadline
9/25/2025 A 9/25/2025 A
31
RFP/RFQ - Evaluation / Award
10/7/2025 A 10/7/2025 A
32
Notice of Award
10/15/2025 A 10/15/2025 A
Document Development
34 35
RFP/RFQ - Evaluation / Award Notice of Award
249d 10/21/2025 10/15/2026
Programming / DAT 33
RFP/RFQ - Submission Deadline
78d 10/21/2025
Program - Electrical Upgrades (Design & Precon / Estimating Services/Deliverables) Program - Mechanical Upgrades (Design & Precon / Estimating Services/Deliverables) Program - Roofing Upgrades (Design & Precon / Estimating Services/Deliverables) Schematic Design
2/12/2026
78d 10/21/2025 A 2/12/2026 A
Program - Electrical Upgrades (Design & Precon / Estimating Services/Deliverables)
78d 10/21/2025 A 2/12/2026 A
Program - Mechanical Upgrades (Design & Precon / Estimating Services/Deliverables)
78d 10/21/2025 A 2/12/2026 A
Program - Roofing Upgrades (Design & Precon / Estimating Services/Deliverables)
129d
2/20/2026
8/21/2026
36
SD - Drawings 100% (Design & Precon / Estimating Services/Deliverables)
1d 2/20/2026 A
2/20/2026 A
37
SD - Cost Estimating & Constructability Review
16d 2/20/2026 A
3/13/2026 A
38
SD - Estimate Review
8d 3/16/2026 A
3/25/2026 A
15d
8/3/2026 A
8/21/2026 A
SD - Alternates - AREA 111 - Carpet or Resilient, Weatherstripping, New Height Walls, Casework
15d
8/3/2026 A
8/21/2026 A
SD - Alternates - AREA 112 - Carpet or Resilient, Weatherstripping, New Height Walls, Casework, Wind Tunnel Effect, Mech. Balancing, Vestibule, Ext. Wall Demo
15d
8/3/2026 A
8/21/2026 A
SD - Alternates - AREA 113 - Carpet or Resilient, Weatherstripping, New Sound Walls, Casework, Repair Floor Sink
84d
39
40
41
SD - Alternates - AREA 111 - Carpet or Resilient, Weatherstripping, New Height Walls, Casework SD - Alternates - AREA 112 - Carpet or Resilient, Weatherstripping, New Height Walls, Casework, Wind Tunnel Effect, Mech. Balancing, Vestibule, Ext. Wall Demo SD - Alternates - AREA 113 - Carpet or Resilient, Weatherstripping, New Sound Walls, Casework, Repair Floor Sink
2/20/2026
6/18/2026
42
Design Development DD - Drawings 100% (Design & Precon / Estimating Services/Deliverables)
61d 2/20/2026 A
5/15/2026 A
43
DD - Cost Estimating & Constructability Review
10d 5/15/2026 A
5/29/2026 A
44
DD - Estimate Review
14d 5/29/2026 A
6/17/2026 A
45
Establish IGMP
SD - Drawings 100% (Design & Precon / Estimating Services/Deliverables)
SD - Cost Estimating & Constructability Review
SD - Estimate Review
DD - Drawings 100% (Design & Precon / Estimating Services/Deliverables) DD - Cost Estimating & Constructability Review
DD - Estimate Review
6/18/2026 A 6/18/2026 A
Construction Documents
106d
5/15/2026
10/15/2026
Establish IGMP
46
CD - Drawings 100% (Design & Precon / Estimating Services/Deliverables/GMP)
74d 5/15/2026 A
8/28/2026 A
47
CD - Cost Estimating & Constructability Review
10d 8/28/2026 A
9/11/2026 A
48
CD - Estimate Review
19d 9/11/2026 A
10/7/2026 A
CD - Estimate Review
49
Establish FGMP
10/15/2026
10/15/2026
Establish FGMP
8/28/2026
1/27/2027
Permitting
103d
CD - Drawings 100% (Design & Precon / Estimating Services/Deliverables/GMP) CD - Cost Estimating & Constructability Review
50
Permit - Submit to State
5d 8/28/2026 A
10/19/2026
51
Permit - Building (In Hand)
40d 10/19/2026
12/16/2026
52
Permit - Electrical Submit to Dora
40d 10/29/2026
12/29/2026
Permit - Electrical Submit to Dora
53
Permit - Plumbing Submit to Dora
40d 10/29/2026
12/29/2026
Permit - Plumbing Submit to Dora
54
Permit - Electrical (In Hand)
20d 12/30/2026
1/27/2027
Permit - Electrical (In Hand)
55
Permit - Plumbing (In Hand)
20d 12/30/2026
1/27/2027
Permit - Plumbing (In Hand)
BVSD Heattherwood ES Proposal Schedule Boulder Valley School District
Permit - Submit to State Permit - Building (In Hand)
Job #: BVSD Heatherwood ES Rev. date: 10/19/2026 11:56:11 AM
Data Date: 10/15/2026
Page 2 of 14
BVSD Heatherwood ES Progress 10/15/26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish 4
Contracting & Award
15d 10/15/2026
Award Early Trades 56 57
2025 2026 2027 2028 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14
11/4/2026
10d 10/15/2026 10/28/2026 10d 10/15/2026
AW - Div 23 - HVAC/Plumbing AW - Div 26 - Electrical Award Trades
10/28/2026
AW - Div 23 - HVAC/Plumbing
AW - Div 26 - Electrical
10d 10/15/2026
10/28/2026
15d 10/15/2026
11/4/2026
58
AW - Div 03 - Concrete
15d 10/15/2026
11/4/2026
AW - Div 03 - Concrete
59
AW - Div 05 - Metals
15d 10/15/2026
11/4/2026
AW - Div 05 - Metals
60
AW - Div 06 - Wood & Plastics
15d 10/15/2026
11/4/2026
AW - Div 06 - Wood & Plastics
61
AW - Div 07 - Thermal Insulation
15d 10/15/2026
11/4/2026
AW - Div 07 - Thermal Insulation
62
AW - Div 08 - Openings
15d 10/15/2026
11/4/2026
AW - Div 08 - Openings
63
AW - Div 09 - Finshes
15d 10/15/2026
11/4/2026
AW - Div 09 - Finshes
64
AW - Div 11 - Food Service
15d 10/15/2026
11/4/2026
AW - Div 11 - Food Service
Submittals & Procurement
170d 10/15/2026
6/17/2027
55d
11/5/2026
1/27/2027
Division 03 65
S&P - Concrete Rebar - Subcontractor Submit
10d
11/5/2026
11/18/2026
S&P - Concrete Rebar - Subcontractor Submit
66
S&P - Cast-In-Place Concrete - Subcontractor Submit
10d
11/5/2026
11/18/2026
S&P - Cast-In-Place Concrete - Subcontractor Submit
67
S&P - Concrete Rebar - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Concrete Rebar - AP Review/Submit
68
S&P - Cast-In-Place Concrete - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Cast-In-Place Concrete - AP Review/Submit
69
S&P - Concrete Rebar - A&E Review
10d
12/7/2026
12/18/2026
S&P - Concrete Rebar - A&E Review
70
S&P - Cast-In-Place Concrete - A&E Review
10d
12/7/2026
12/18/2026
S&P - Cast-In-Place Concrete - A&E Review
71
S&P - Concrete Rebar Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Concrete Rebar Procurement/Fabricate/Deliver
72
S&P - Cast-In-Place Concrete Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Cast-In-Place Concrete Procurement/Fabricate/Deliver
80d
11/5/2026
3/3/2027
10d
11/5/2026
11/18/2026
S&P - Metals (Div 05 - Contractor Prepare/Submit Shop Drawings)
10d 11/19/2026
12/4/2026
S&P - AP Review (Div 05 - AP Review/Submit Shop Drawings)
12/7/2026
12/18/2026
50d 12/21/2026
3/3/2027
Division 05 73 74 75 76
S&P - Metals (Div 05 - Contractor Prepare/Submit Shop Drawings) S&P - AP Review (Div 05 - AP Review/Submit Shop Drawings) S&P - A&E Review (Div 05 - Owner Review/Approve Shop Drawings) S&P - Metals Procurement (Div 07 - Fabricate/Deliver) Division 06
10d
55d
11/5/2026
1/27/2027
11/5/2026
11/18/2026
S&P - A&E Review (Div 05 - Owner Review/Approve Shop Drawings) S&P - Metals Procurement (Div 07 - Fabricate/Deliver)
77
S&P - Rough Carpentry - Subcontractor Submit
10d
78
S&P - Rough Carpentry - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Rough Carpentry - AP Review/Submit
79
S&P - Rough Carpentry - A&E Review
10d
12/7/2026
12/18/2026
S&P - Rough Carpentry - A&E Review
80
S&P - Rough Carpentry Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
95d 10/15/2026
3/3/2027
Division 07
S&P - Rough Carpentry - Subcontractor Submit
S&P - Rough Carpentry Procurement/Fabricate/Deliver
81
S&P - Fire And Smoke Assembly ID - Subcontractor Submit
10d 10/15/2026
10/28/2026
S&P - Fire And Smoke Assembly ID - Subcontractor Submit
82
S&P - Fire And Smoke Assembly ID - AP Review/Submit
10d 10/29/2026
11/11/2026
S&P - Fire And Smoke Assembly ID - AP Review/Submit
BVSD Heattherwood ES Proposal Schedule Boulder Valley School District
Job #: BVSD Heatherwood ES Rev. date: 10/19/2026 11:56:11 AM
Data Date: 10/15/2026
Page 3 of 14
BVSD Heatherwood ES Progress 10/15/26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish 4
2025 2026 2027 2028 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14
83
S&P - Prep For Re-Roofing - Subcontractor Submit
10d
11/5/2026
11/18/2026
S&P - Prep For Re-Roofing - Subcontractor Submit
84
S&P - EPDM Roofing - Subcontractor Submit
10d
11/5/2026
11/18/2026
S&P - EPDM Roofing - Subcontractor Submit
85
S&P - Roofing Specialties - Subcontractor Submit
10d
11/5/2026
11/18/2026
S&P - Roofing Specialties - Subcontractor Submit
86
S&P - Sheet-Metal Flashing And Trim - Subcontractor Submit
10d
11/5/2026
11/18/2026
S&P - Sheet-Metal Flashing And Trim - Subcontractor Submit
87
S&P - Joint Sealants - Subcontractor Submit
10d
11/5/2026
11/18/2026
S&P - Joint Sealants - Subcontractor Submit
88
S&P - Fire And Smoke Assembly ID - A&E Review
10d 11/12/2026
11/25/2026
S&P - Fire And Smoke Assembly ID - A&E Review
89
S&P - Prep For Re-Roofing - - AP Review
10d 11/19/2026
12/4/2026
S&P - Prep For Re-Roofing - - AP Review
90
S&P - EPDM Roofing - - AP Review
10d 11/19/2026
12/4/2026
S&P - EPDM Roofing - - AP Review
91
S&P - Roofing Specialties - - AP Review
10d 11/19/2026
12/4/2026
S&P - Roofing Specialties - - AP Review
92
S&P - Sheet-Metal Flashing And Trim - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Sheet-Metal Flashing And Trim - AP Review/Submit
93
S&P - Joint Sealants - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Joint Sealants - AP Review/Submit
94
S&P - Fire And Smoke Assembly ID Procurement/Fabricate/Deliver
25d 11/30/2026
1/6/2027
95
S&P - Prep For Re-Roofing - A&E Review
10d
12/7/2026
12/18/2026
S&P - Prep For Re-Roofing - A&E Review
96
S&P - EPDM Roofing - A&E Review
10d
12/7/2026
12/18/2026
S&P - EPDM Roofing - A&E Review
97
S&P - Roofing Specialties - A&E Review
10d
12/7/2026
12/18/2026
S&P - Roofing Specialties - A&E Review
98
S&P - Sheet-Metal Flashing And Trim - A&E Review
10d
12/7/2026
12/18/2026
S&P - Sheet-Metal Flashing And Trim - A&E Review S&P - Joint Sealants - A&E Review
S&P - Fire And Smoke Assembly ID Procurement/Fabricate/Deliver
99
S&P - Joint Sealants - A&E Review
10d
12/7/2026
12/18/2026
100
S&P - Prep For Re-Roofing Procurement/Fabricate/Deliver
50d 12/21/2026
3/3/2027
S&P - Prep For Re-Roofing - Procurement/Fabricate/Deliver
101
S&P - EPDM Roofing - Procurement/Fabricate/Deliver
50d 12/21/2026
3/3/2027
S&P - EPDM Roofing - Procurement/Fabricate/Deliver
50d 12/21/2026
3/3/2027
S&P - Roofing Specialties - Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Sheet-Metal Flashing And Trim Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Joint Sealants Procurement/Fabricate/Deliver
70d
11/5/2026
2/17/2027
102 103 104
S&P - Roofing Specialties Procurement/Fabricate/Deliver S&P - Sheet-Metal Flashing And Trim Procurement/Fabricate/Deliver S&P - Joint Sealants Procurement/Fabricate/Deliver Division 08
105
S&P - Aluminum Storefronts - Subcontractor Submit
10d
11/5/2026
11/18/2026
S&P - Aluminum Storefronts - Subcontractor Submit
106
S&P - Glazing - Subcontractor Submit
10d
11/5/2026
11/18/2026
S&P - Glazing - Subcontractor Submit
107
S&P - Door Hardware - Subcontractor Submit
10d
11/5/2026
11/18/2026
S&P - Door Hardware - Subcontractor Submit
108
S&P - Aluminum Storefronts - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Aluminum Storefronts - AP Review/Submit
109
S&P - Glazing - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Glazing - AP Review/Submit
110
S&P - Door Hardware - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Door Hardware - AP Review/Submit
111
S&P - Aluminum Storefronts - A&E Review
10d
12/7/2026
12/18/2026
S&P - Aluminum Storefronts - A&E Review
112
S&P - Glazing - A&E Review
10d
12/7/2026
12/18/2026
S&P - Glazing - A&E Review
113
S&P - Door Hardware - A&E Review
10d
12/7/2026
12/18/2026
S&P - Door Hardware - A&E Review
114
S&P - Aluminum Storefronts Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Aluminum Storefronts Procurement/Fabricate/Deliver
115
S&P - Glazing Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Glazing Procurement/Fabricate/Deliver
116
S&P - Door Hardware - Procurement/Fabricate/Deliver
40d 12/21/2026
2/17/2027
BVSD Heattherwood ES Proposal Schedule Boulder Valley School District
S&P - Door Hardware - Procurement/Fabricate/Deliver
Job #: BVSD Heatherwood ES Rev. date: 10/19/2026 11:56:11 AM
Data Date: 10/15/2026
Page 4 of 14
BVSD Heatherwood ES Progress 10/15/26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish 4
Division 09
2025 2026 2027 2028 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14
55d
11/5/2026
1/27/2027
117
S&P - Gyp Board Assemblies - Subcontractor Submit
10d
11/5/2026
11/18/2026
S&P - Gyp Board Assemblies - Subcontractor Submit
118
S&P - Exterior & Interior Painting - Subcontractor Submit
10d
11/5/2026
11/18/2026
S&P - Exterior & Interior Painting - Subcontractor Submit
119
S&P - Gyp Board Assemblies - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Gyp Board Assemblies - AP Review/Submit
120
S&P - Exterior & Interior Painting - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Exterior & Interior Painting - AP Review/Submit
121
S&P - Gyp Board Assemblies - A&E Review
10d
12/7/2026
12/18/2026
S&P - Gyp Board Assemblies - A&E Review
122
S&P - Exterior & Interior Painting - A&E Review
10d
12/7/2026
12/18/2026
S&P - Exterior & Interior Painting - A&E Review
25d 12/21/2026
1/27/2027
S&P - Gyp Board Assemblies Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Exterior & Interior Painting Procurement/Fabricate/Deliver
55d
11/5/2026
1/27/2027
123 124
S&P - Gyp Board Assemblies Procurement/Fabricate/Deliver S&P - Exterior & Interior Painting Procurement/Fabricate/Deliver Division 11
125
S&P - Food Service Equipment - Subcontractor Submit
10d
11/5/2026
11/18/2026
126
S&P - Food Service Equipment - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Food Service Equipment - AP Review/Submit
127
S&P - Food Service Equipment - A&E Review
10d
12/7/2026
12/18/2026
S&P - Food Service Equipment - A&E Review
128
S&P - Food Service Equipment Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
70d 10/29/2026
2/10/2027
10d 10/29/2026
11/11/2026
S&P - Common Motor Requirements For Plumbing - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Meters And Guages For Plumbing - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Hangers And Support For Plumbing - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - ID for Plumbing Piping & Equipment - Subcontractor Submit
Division 22 129 130 131 132
S&P - Common Motor Requirements For Plumbing Subcontractor Submit S&P - Meters And Guages For Plumbing - Subcontractor Submit S&P - Hangers And Support For Plumbing - Subcontractor Submit S&P - ID for Plumbing Piping & Equipment Subcontractor Submit
S&P - Food Service Equipment - Subcontractor Submit
S&P - Food Service Equipment Procurement/Fabricate/Deliver
133
S&P - Plumbing Insulation - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Plumbing Insulation - Subcontractor Submit
134
S&P - Domestic-Water Piping - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Domestic-Water Piping - Subcontractor Submit
135
S&P - Plumbing Pumps - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Plumbing Pumps - Subcontractor Submit
136
S&P - Facility Natural Gas Piping - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Facility Natural Gas Piping - Subcontractor Submit
137
S&P - Water Heaters - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Water Heaters - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Domestic-Water Piping Specialties - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Common Motor Requirements For Plumbing - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Meters And Guages For Plumbing - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Hangers And Support For Plumbing - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - ID for Plumbing Piping & Equipment - AP Review/Submit
138 139 140 141 142
S&P - Domestic-Water Piping Specialties - Subcontractor Submit S&P - Common Motor Requirements For Plumbing - AP Review/Submit S&P - Meters And Guages For Plumbing - AP Review/Submit S&P - Hangers And Support For Plumbing - AP Review/Submit S&P - ID for Plumbing Piping & Equipment - AP Review/Submit
143
S&P - Plumbing Insulation - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Plumbing Insulation - AP Review/Submit
144
S&P - Domestic-Water Piping - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Domestic-Water Piping - AP Review/Submit
145
S&P - Plumbing Pumps - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Plumbing Pumps - AP Review/Submit
146
S&P - Facility Natural Gas Piping - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Facility Natural Gas Piping - AP Review/Submit
147
S&P - Water Heaters - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Water Heaters - AP Review/Submit
148
S&P - Domestic-Water Piping Specialties - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Domestic-Water Piping Specialties - AP Review/Submit
BVSD Heattherwood ES Proposal Schedule Boulder Valley School District
Job #: BVSD Heatherwood ES Rev. date: 10/19/2026 11:56:11 AM
Data Date: 10/15/2026
Page 5 of 14
BVSD Heatherwood ES Progress 10/15/26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish 4
2025 2026 2027 2028 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14
149
S&P - Common Motor Requirements For Plumbing - A&E Review
10d 11/30/2026
12/11/2026
S&P - Common Motor Requirements For Plumbing - A&E Review
150
S&P - Meters And Guages For Plumbing - A&E Review
10d 11/30/2026
12/11/2026
S&P - Meters And Guages For Plumbing - A&E Review
151
S&P - Hangers And Support For Plumbing - A&E Review
10d 11/30/2026
12/11/2026
S&P - Hangers And Support For Plumbing - A&E Review
152
S&P - ID for Plumbing Piping & Equipment - A&E Review
10d 11/30/2026
12/11/2026
S&P - ID for Plumbing Piping & Equipment - A&E Review
153
S&P - Plumbing Insulation - A&E Review
10d 11/30/2026
12/11/2026
S&P - Plumbing Insulation - A&E Review
154
S&P - Domestic-Water Piping - A&E Review
10d 11/30/2026
12/11/2026
S&P - Domestic-Water Piping - A&E Review
155
S&P - Plumbing Pumps - A&E Review
10d 11/30/2026
12/11/2026
S&P - Plumbing Pumps - A&E Review
156
S&P - Facility Natural Gas Piping - A&E Review
10d 11/30/2026
12/11/2026
S&P - Facility Natural Gas Piping - A&E Review
157
S&P - Water Heaters - A&E Review
10d 11/30/2026
12/11/2026
S&P - Water Heaters - A&E Review
158
S&P - Domestic-Water Piping Specialties - A&E Review
10d 11/30/2026
12/11/2026
S&P - Domestic-Water Piping Specialties - A&E Review
25d 12/14/2026
1/20/2027
S&P - Common Motor Requirements For Plumbing Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - Meters And Guages For Plumbing Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - Hangers And Support For Plumbing Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - ID for Plumbing Piping & Equipment Procurement/Fabricate/Deliver
159 160 161 162
S&P - Common Motor Requirements For Plumbing Procurement/Fabricate/Deliver S&P - Meters And Guages For Plumbing Procurement/Fabricate/Deliver S&P - Hangers And Support For Plumbing Procurement/Fabricate/Deliver S&P - ID for Plumbing Piping & Equipment Procurement/Fabricate/Deliver
163
S&P - Plumbing Insulation Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - Plumbing Insulation Procurement/Fabricate/Deliver
164
S&P - Domestic-Water Piping Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - Domestic-Water Piping Procurement/Fabricate/Deliver
165
S&P - Plumbing Pumps Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - Plumbing Pumps Procurement/Fabricate/Deliver
166
S&P - Facility Natural Gas Piping Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - Facility Natural Gas Piping Procurement/Fabricate/Deliver
167
S&P - Water Heaters Procurement/Fabricate/Deliver
40d 12/14/2026
2/10/2027
168
S&P - Domestic-Water Piping Specialties Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
160d 10/29/2026
6/17/2027
10d 10/29/2026
11/11/2026
S&P - Motors, Drives, Controllers & Electrical - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Basic Piping Materials & Methods - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Piping Specialties - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Meter & Gauges For Mechanical Piping - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - General Duty Valve For Mechanical Piping - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Hangers & Supports For Mechanical Systems - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Vibration Controls For Mechanical - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - IDent. For Mechanical Systems - Subcontractor Submit
Division 23 169 170 171 172 173 174 175 176
S&P - Motors, Drives, Controllers & Electrical Subcontractor Submit S&P - Basic Piping Materials & Methods - Subcontractor Submit S&P - Piping Specialties - Subcontractor Submit S&P - Meter & Gauges For Mechanical Piping Subcontractor Submit S&P - General Duty Valve For Mechanical Piping Subcontractor Submit S&P - Hangers & Supports For Mechanical Systems Subcontractor Submit S&P - Vibration Controls For Mechanical - Subcontractor Submit S&P - IDent. For Mechanical Systems - Subcontractor Submit S&P - Instrumentation & Controls For Mechanical Subcontractor Submit
S&P - Water Heaters Procurement/Fabricate/Deliver S&P - Domestic-Water Piping Specialties - Procurement/Fabricate/Deliver
10d 10/29/2026
11/11/2026
S&P - Instrumentation & Controls For Mechanical - Subcontractor Submit
178
S&P - S.O.O For Mechanical - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - S.O.O For Mechanical - Subcontractor Submit
179
S&P - Metal Ducts - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Metal Ducts - Subcontractor Submit
180
S&P - Air Duct Accessories - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Air Duct Accessories - Subcontractor Submit
181
S&P - Diffusers, Registers, Griles - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Diffusers, Registers, Griles - Subcontractor Submit
182
S&P - Packaged Compressor & Condenser Units Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Packaged Compressor & Condenser Units - Subcontractor Submit
177
BVSD Heattherwood ES Proposal Schedule Boulder Valley School District
Job #: BVSD Heatherwood ES Rev. date: 10/19/2026 11:56:11 AM
Data Date: 10/15/2026
Page 6 of 14
BVSD Heatherwood ES Progress 10/15/26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish 4
183 184 185 186 187 188 189 190 191 192
S&P - Custom Indoor Central Station Air Handling Units Subcontractor Submit S&P - Rooftop Heating & Cooling Units - Subcontractor Submit S&P - Decentralized HVAC Equipment - Subcontractor Submit S&P - Motors, Drives, Controllers & Electrical - AP Review/Submit S&P - Basic Piping Materials & Methods - AP Review/Submit S&P - Piping Specialties - AP Review/Submit S&P - Meter & Gauges For Mechanical Piping - AP Review/Submit S&P - General Duty Valve For Mechanical Piping - AP Review/Submit S&P - Hangers & Supports For Mechanical Systems - AP Review/Submit S&P - Vibration Controls For Mechanical - AP Review/Submit
2025 2026 2027 2028 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14
10d 10/29/2026
11/11/2026
S&P - Custom Indoor Central Station Air Handling Units - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Rooftop Heating & Cooling Units - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Decentralized HVAC Equipment - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Motors, Drives, Controllers & Electrical - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Basic Piping Materials & Methods - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Piping Specialties - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Meter & Gauges For Mechanical Piping - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - General Duty Valve For Mechanical Piping - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Hangers & Supports For Mechanical Systems - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Vibration Controls For Mechanical - AP Review/Submit
193
S&P - IDent. For Mechanical Systems - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - IDent. For Mechanical Systems - AP Review/Submit
194
S&P - Instrumentation & Controls For Mechanical - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Instrumentation & Controls For Mechanical - AP Review/Submit
195
S&P - S.O.O For Mechanical - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - S.O.O For Mechanical - AP Review/Submit
196
S&P - Metal Ducts - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Metal Ducts - AP Review/Submit
197
S&P - Air Duct Accessories - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Air Duct Accessories - AP Review/Submit
198
S&P - Diffusers, Registers, Griles - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Diffusers, Registers, Griles - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Packaged Compressor & Condenser Units - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Custom Indoor Central Station Air Handling Units - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Rooftop Heating & Cooling Units - AP Review/Submit S&P - Decentralized HVAC Equipment - AP Review/Submit
199 200 201
S&P - Packaged Compressor & Condenser Units - AP Review/Submit S&P - Custom Indoor Central Station Air Handling Units AP Review/Submit S&P - Rooftop Heating & Cooling Units - AP Review/Submit
202
S&P - Decentralized HVAC Equipment - AP Review/Submit
10d 11/12/2026
11/25/2026
203
S&P - Motors, Drives, Controllers & Electrical - A&E Review
10d 11/30/2026
12/11/2026
S&P - Motors, Drives, Controllers & Electrical - A&E Review
204
S&P - Basic Piping Materials & Methods - A&E Review
10d 11/30/2026
12/11/2026
S&P - Basic Piping Materials & Methods - A&E Review
205
S&P - Piping Specialties - A&E Review
10d 11/30/2026
12/11/2026
S&P - Piping Specialties - A&E Review
10d 11/30/2026
12/11/2026
S&P - Meter & Gauges For Mechanical Piping - A&E Review
10d 11/30/2026
12/11/2026
S&P - General Duty Valve For Mechanical Piping - A&E Review
206 207
S&P - Meter & Gauges For Mechanical Piping - A&E Review S&P - General Duty Valve For Mechanical Piping - A&E Review S&P - Hangers & Supports For Mechanical Systems - A&E Review
10d 11/30/2026
12/11/2026
S&P - Hangers & Supports For Mechanical Systems - A&E Review
209
S&P - Vibration Controls For Mechanical - A&E Review
10d 11/30/2026
12/11/2026
S&P - Vibration Controls For Mechanical - A&E Review
210
S&P - IDent. For Mechanical Systems - A&E Review
10d 11/30/2026
12/11/2026
S&P - IDent. For Mechanical Systems - A&E Review
211
S&P - TAB - Subcontractor Submit
10d 11/30/2026
12/11/2026
S&P - TAB - Subcontractor Submit
212
S&P - Insulation For Mechanical - Subcontractor Submit
10d 11/30/2026
12/11/2026
S&P - Insulation For Mechanical - Subcontractor Submit
213
S&P - Instrumentation & Controls For Mechanical - A&E Review
10d 11/30/2026
12/11/2026
S&P - Instrumentation & Controls For Mechanical - A&E Review
214
S&P - S.O.O For Mechanical - A&E Review
10d 11/30/2026
12/11/2026
S&P - S.O.O For Mechanical - A&E Review
215
S&P - Metal Ducts - A&E Review
10d 11/30/2026
12/11/2026
S&P - Metal Ducts - A&E Review
216
S&P - Air Duct Accessories - A&E Review
10d 11/30/2026
12/11/2026
S&P - Air Duct Accessories - A&E Review
217
S&P - Diffusers, Registers, Griles - A&E Review
10d 11/30/2026
12/11/2026
S&P - Diffusers, Registers, Griles - A&E Review
208
BVSD Heattherwood ES Proposal Schedule Boulder Valley School District
Job #: BVSD Heatherwood ES Rev. date: 10/19/2026 11:56:11 AM
Data Date: 10/15/2026
Page 7 of 14
BVSD Heatherwood ES Progress 10/15/26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish 4
218 219
S&P - Packaged Compressor & Condenser Units - A&E Review S&P - Custom Indoor Central Station Air Handling Units A&E Review
2025 2026 2027 2028 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14
10d 11/30/2026
12/11/2026
S&P - Packaged Compressor & Condenser Units - A&E Review
10d 11/30/2026
12/11/2026
S&P - Custom Indoor Central Station Air Handling Units - A&E Review
220
S&P - Rooftop Heating & Cooling Units - A&E Review
10d 11/30/2026
12/11/2026
S&P - Rooftop Heating & Cooling Units - A&E Review
221
S&P - Decentralized HVAC Equipment - A&E Review
10d 11/30/2026
12/11/2026
S&P - Decentralized HVAC Equipment - A&E Review
40d 12/14/2026
2/10/2027
25d 12/14/2026
1/20/2027
S&P - Basic Piping Materials & Methods Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - Piping Specialties Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - Meter & Gauges For Mechanical Piping Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - General Duty Valve For Mechanical Piping Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - Hangers & Supports For Mechanical Systems Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - Vibration Controls For Mechanical Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - IDent. For Mechanical Systems Procurement/Fabricate/Deliver
222 223 224 225 226 227 228 229
S&P - Motors, Drives, Controllers & Electrical Procurement/Fabricate/Deliver S&P - Basic Piping Materials & Methods Procurement/Fabricate/Deliver S&P - Piping Specialties Procurement/Fabricate/Deliver S&P - Meter & Gauges For Mechanical Piping Procurement/Fabricate/Deliver S&P - General Duty Valve For Mechanical Piping Procurement/Fabricate/Deliver S&P - Hangers & Supports For Mechanical Systems Procurement/Fabricate/Deliver S&P - Vibration Controls For Mechanical Procurement/Fabricate/Deliver S&P - IDent. For Mechanical Systems Procurement/Fabricate/Deliver
S&P - Motors, Drives, Controllers & Electrical Procurement/Fabricate/Deliver
230
S&P - TAB - AP Review/Submit
10d 12/14/2026
12/29/2026
S&P - TAB - AP Review/Submit
231
S&P - Insulation For Mechanical - AP Review/Submit
10d 12/14/2026
12/29/2026
S&P - Insulation For Mechanical - AP Review/Submit
25d 12/14/2026
1/20/2027
S&P - Instrumentation & Controls For Mechanical Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - S.O.O For Mechanical Procurement/Fabricate/Deliver
232 233
S&P - Instrumentation & Controls For Mechanical Procurement/Fabricate/Deliver S&P - S.O.O For Mechanical Procurement/Fabricate/Deliver
234
S&P - Metal Ducts Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - Metal Ducts Procurement/Fabricate/Deliver
235
S&P - Air Duct Accessories Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - Air Duct Accessories Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - Diffusers, Registers, Griles Procurement/Fabricate/Deliver
12/14/2026
6/17/2027
236 237 238 239 240
S&P - Diffusers, Registers, Griles Procurement/Fabricate/Deliver S&P - Packaged Compressor & Condenser Units Procurement/Fabricate/Deliver S&P - Custom Indoor Central Station Air Handling Units Procurement/Fabricate/Deliver S&P - Rooftop Heating & Cooling Units Procurement/Fabricate/Deliver S&P - Decentralized HVAC Equipment Procurement/Fabricate/Deliver
130d
80d 12/14/2026
4/7/2027
12/14/2026
6/17/2027
25d 12/14/2026
1/20/2027
130d
S&P - Packaged Compressor & Condenser Units Procurement/Fabricate/Deliver
S&P - Custom Indoor Central Station Air Handling Units Procurement/Fabricate/Deliver S&P - Rooftop Heating & Cooling Units Procurement/Fabricate/Deliver
S&P - Decentralized HVAC Equipment Procurement/Fabricate/Deliver
241
S&P - TAB - A&E Review
10d 12/30/2026
1/13/2027
S&P - TAB - A&E Review
242
S&P - Insulation For Mechanical - A&E Review
10d 12/30/2026
1/13/2027
S&P - Insulation For Mechanical - A&E Review
243
S&P - TAB Procurement/Fabricate/Deliver
25d
1/14/2027
2/17/2027
S&P - TAB Procurement/Fabricate/Deliver
244
S&P - Insulation For Mechanical Procurement/Fabricate/Deliver
25d
1/14/2027
2/17/2027
S&P - Insulation For Mechanical Procurement/Fabricate/Deliver
90d 10/29/2026
3/10/2027
10d 10/29/2026
11/11/2026
S&P - Low Voltage Electrical Power Conductors And Cable - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Hangers & Supports For Electrical Systems - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Raceway & Wireway For Electrical Systems - Subcontractor Submit
Division 26 245 246 247
S&P - Low Voltage Electrical Power Conductors And Cable - Subcontractor Submit S&P - Hangers & Supports For Electrical Systems Subcontractor Submit S&P - Raceway & Wireway For Electrical Systems Subcontractor Submit
248
S&P - Cabinets, Boxes, Fittings - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Cabinets, Boxes, Fittings - Subcontractor Submit
249
S&P - ID For Electrical Systems - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - ID For Electrical Systems - Subcontractor Submit
250
S&P - Wiring Connections - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Wiring Connections - Subcontractor Submit
251
S&P - Lighting Control Devices - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Lighting Control Devices - Subcontractor Submit
BVSD Heattherwood ES Proposal Schedule Boulder Valley School District
Job #: BVSD Heatherwood ES Rev. date: 10/19/2026 11:56:11 AM
Data Date: 10/15/2026
Page 8 of 14
BVSD Heatherwood ES Progress 10/15/26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish 4
2025 2026 2027 2028 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14
252
S&P - LV Circuit Protective Devices - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - LV Circuit Protective Devices - Subcontractor Submit
253
S&P - Lighting - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - Lighting - Subcontractor Submit
254
S&P - EM Lighting - Subcontractor Submit
10d 10/29/2026
11/11/2026
S&P - EM Lighting - Subcontractor Submit
10d 11/12/2026
11/25/2026
S&P - Low Voltage Electrical Power Conductors And Cable - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Hangers & Supports For Electrical Systems - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Raceway & Wireway For Electrical Systems - AP Review/Submit
255 256 257
S&P - Low Voltage Electrical Power Conductors And Cable - AP Review/Submit S&P - Hangers & Supports For Electrical Systems - AP Review/Submit S&P - Raceway & Wireway For Electrical Systems - AP Review/Submit
258
S&P - Cabinets, Boxes, Fittings - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Cabinets, Boxes, Fittings - AP Review/Submit
259
S&P - ID For Electrical Systems - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - ID For Electrical Systems - AP Review/Submit
260
S&P - Wiring Connections - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Wiring Connections - AP Review/Submit
261
S&P - Lighting Control Devices - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Lighting Control Devices - AP Review/Submit
262
S&P - LV Circuit Protective Devices - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - LV Circuit Protective Devices - AP Review/Submit
263
S&P - Lighting - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - Lighting - AP Review/Submit
264
S&P - EM Lighting - AP Review/Submit
10d 11/12/2026
11/25/2026
S&P - EM Lighting - AP Review/Submit
10d 11/30/2026
12/11/2026
S&P - Low Voltage Electrical Power Conductors And Cable - A&E Review
10d 11/30/2026
12/11/2026
S&P - Hangers & Supports For Electrical Systems - A&E Review
10d 11/30/2026
12/11/2026
S&P - Raceway & Wireway For Electrical Systems - A&E Review
265 266 267
S&P - Low Voltage Electrical Power Conductors And Cable - A&E Review S&P - Hangers & Supports For Electrical Systems - A&E Review S&P - Raceway & Wireway For Electrical Systems - A&E Review
268
S&P - Cabinets, Boxes, Fittings - A&E Review
10d 11/30/2026
12/11/2026
S&P - Cabinets, Boxes, Fittings - A&E Review
269
S&P - ID For Electrical Systems - A&E Review
10d 11/30/2026
12/11/2026
S&P - ID For Electrical Systems - A&E Review
270
S&P - Wiring Connections - A&E Review
10d 11/30/2026
12/11/2026
S&P - Wiring Connections - A&E Review
271
S&P - Lighting Control Devices - A&E Review
10d 11/30/2026
12/11/2026
S&P - Lighting Control Devices - A&E Review
272
S&P - LV Circuit Protective Devices - A&E Review
10d 11/30/2026
12/11/2026
S&P - LV Circuit Protective Devices - A&E Review
273
S&P - Lighting - A&E Review
10d 11/30/2026
12/11/2026
S&P - Lighting - A&E Review
274
S&P - EM Lighting - A&E Review
10d 11/30/2026
12/11/2026
S&P - EM Lighting - A&E Review
25d 12/14/2026
1/20/2027
S&P - Low Voltage Electrical Power Conductors And Cable Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - Hangers & Supports For Electrical Systems Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - Raceway & Wireway For Electrical Systems Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - Cabinets, Boxes, Fittings Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - ID For Electrical Systems Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - Wiring Connections Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - Lighting Control Devices Procurement/Fabricate/Deliver
25d 12/14/2026
1/20/2027
S&P - LV Circuit Protective Devices Procurement/Fabricate/Deliver
275 276 277 278 279 280 281 282
S&P - Low Voltage Electrical Power Conductors And Cable Procurement/Fabricate/Deliver S&P - Hangers & Supports For Electrical Systems Procurement/Fabricate/Deliver S&P - Raceway & Wireway For Electrical Systems Procurement/Fabricate/Deliver S&P - Cabinets, Boxes, Fittings Procurement/Fabricate/Deliver S&P - ID For Electrical Systems Procurement/Fabricate/Deliver S&P - Wiring Connections Procurement/Fabricate/Deliver S&P - Lighting Control Devices Procurement/Fabricate/Deliver S&P - LV Circuit Protective Devices Procurement/Fabricate/Deliver
283
S&P - Lighting Procurement/Fabricate/Deliver
60d 12/14/2026
3/10/2027
S&P - Lighting Procurement/Fabricate/Deliver
284
S&P - EM Lighting Procurement/Fabricate/Deliver
60d 12/14/2026
3/10/2027
S&P - EM Lighting Procurement/Fabricate/Deliver
55d
11/5/2026
1/27/2027
10d
11/5/2026
11/18/2026
Division 32 285
S&P - Concrete Paving - Subcontractor Submit
BVSD Heattherwood ES Proposal Schedule Boulder Valley School District
S&P - Concrete Paving - Subcontractor Submit
Job #: BVSD Heatherwood ES Rev. date: 10/19/2026 11:56:11 AM
Data Date: 10/15/2026
Page 9 of 14
BVSD Heatherwood ES Progress 10/15/26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish 4
2025 2026 2027 2028 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14
286
S&P - Chain Link Fences and Gates - Subcontractor Submit
10d
11/5/2026
11/18/2026
287
S&P - Concrete Paving - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Concrete Paving - AP Review/Submit
288
S&P - Chain Link Fences and Gates - AP Review/Submit
10d 11/19/2026
12/4/2026
S&P - Chain Link Fences and Gates - AP Review/Submit
289
S&P - Concrete Paving - A&E Review
10d
12/7/2026
12/18/2026
S&P - Concrete Paving - A&E Review
290
S&P - Chain Link Fences and Gates - A&E Review
10d
12/7/2026
12/18/2026
S&P - Chain Link Fences and Gates - A&E Review
291
S&P - Concrete Paving Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Concrete Paving Procurement/Fabricate/Deliver
292
S&P - Chain Link Fences and Gates Procurement/Fabricate/Deliver
25d 12/21/2026
1/27/2027
S&P - Chain Link Fences and Gates Procurement/Fabricate/Deliver
Construction
474d 10/21/2025
9/3/2027
Site Mobilization
46d
3/23/2027
5/25/2027
293
Mobilization Start (Week Prior)
1d
3/23/2027
3/23/2027
294
Mobilization Complete
5d
3/24/2027
3/30/2027
295
Mobilization Start (Summer)
1d
5/25/2027
5/25/2027 5/25/2027
Abatement (If NEEDED)
45d
3/24/2027
296
Abate - Review Impacts
30d
3/24/2027
5/4/2027
297
Abate - Identify Scope
10d
5/5/2027
5/18/2027
298
Abate - Demo / Remove / Inspections / Tear Down
5d
5/19/2027
5/25/2027
164d 10/15/2026
6/9/2027
55d
3/24/2027
6/9/2027
Demolition North Building - AREA 111
S&P - Chain Link Fences and Gates - Subcontractor Submit
Mobilization Start (Week Prior)
Mobilization Complete Mobilization Start (Summer)
Abate - Review Impacts Abate - Identify Scope
Abate - Demo / Remove / Inspections / Tear Down
299
Demo - North - Review Impacts
5d
3/24/2027
3/30/2027
Demo - North - Review Impacts
300
Demo - North - Identify Scope
5d
3/31/2027
4/6/2027
Demo - North - Identify Scope
301
Demo - North - Demo / Existing Air Devices
10d
5/26/2027
6/9/2027
Demo - North - Demo / Existing Air Devices
302
Demo - North - (V18) Light fixtures
9d
5/26/2027
6/8/2027
Demo - North - (V18) Light fixtures
North - Alternate - Carpet Replacement
5d
5/26/2027
6/2/2027
North - Alternate - Wall Replacement
2d
5/26/2027
5/27/2027
5d
North - Alternate - Casework Replacement South Building - AREA 112
5/26/2027
6/2/2027
163d 10/15/2026
6/8/2027
+
+
+ + +
+
303
Demo - South - Review Impacts
5d
3/24/2027
3/30/2027
Demo - South - Review Impacts
304
Demo - South - Identify Scope
5d
3/31/2027
4/6/2027
Demo - South - Identify Scope
305
Demo - South - Demo / Remove - Summer
10d
4/7/2027
4/20/2027
306
Demo - South - (V18) Light fixtures
9d
5/26/2027
307
6/8/2027
South - Alternate Carpet Replacement
15d 10/15/2026
South - Alternate Wall Replacement
2d 10/15/2026 10/16/2026
South - Alternate Casework Replacement
5d 10/15/2026 10/21/2026
East Building - AREA 113 Demo - East - Review Impacts & Safe Offs
Demo - South - (V18) Light fixtures
11/4/2026
163d 10/15/2026
6/8/2027
5/25/2027
6/1/2027
5d
Demo - South - Demo / Remove - Summer
BVSD Heattherwood ES Proposal Schedule Boulder Valley School District
+
+
+ + +
+
Demo - East - Review Impacts & Safe Offs
Job #: BVSD Heatherwood ES Rev. date: 10/19/2026 11:56:11 AM
Data Date: 10/15/2026
Page 10 of 14
BVSD Heatherwood ES Progress 10/15/26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish 4
2025 2026 2027 2028 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14
308
Demo - East - Kitchen Hood & Ansul System
5d
5/26/2027
6/2/2027
Demo - East - Kitchen Hood & Ansul System
309
Demo - East - Exhaust Fan, Ductwork, Makeup Air Unit
5d
5/26/2027
6/2/2027
Demo - East - Exhaust Fan, Ductwork, Makeup Air Unit
310
Demo - East - (V18) Light fixtures
9d
5/26/2027
6/8/2027
Demo - East - (V18) Light fixtures
311
Demo - East - Walk In Cooler
5d
5/27/2027
6/3/2027
Demo - East - Walk In Cooler
East - Alternate Carpet Replacement
15d 10/15/2026
East - Alternate Wall Replacement
2d 10/15/2026 10/16/2026
East - Alternate Casework Replacement
5d 10/15/2026 10/21/2026
Early Site Development 312
ES - Investigations
313
ES - Setup Compound (Construction Fence/Connexs/Dumpster/ETC
314 315
407d 10/21/2025 244d 10/21/2025 A
11/4/2026
+
+ + +
+
6/1/2027 6/1/2027
ES - Investigations
1d
3/24/2027
3/24/2027
ES - Setup Compound (Construction Fence/Connexs/Dumpster/ETC
Utilities (IF NEEDED)
30d
6/2/2027
7/14/2027
Util - Review Impacts
15d
6/2/2027
6/22/2027
Util - Identify Scope
15d
6/23/2027
7/14/2027
Building Construction
106d
3/24/2027
8/20/2027
35d
6/2/2027
7/21/2027 6/22/2027
Foundation & Substructure 316
FS - Identify Scope
15d
6/2/2027
317
FS - Demo Scope
10d
6/23/2027
7/7/2027
318
FS - Repair Foundations
10d
7/8/2027
7/21/2027
35d
6/2/2027
7/21/2027 6/22/2027
Superstructure 319
Super - Identify Scope
15d
6/2/2027
320
Super - Demo for Scope
10d
6/23/2027
7/7/2027
321
Super - Install & Repair from Scope
10d
7/8/2027
7/21/2027
50d
6/11/2027
8/20/2027
25d
6/11/2027
7/16/2027
10d
6/11/2027
6/24/2027
Roofing North Building - Area 111 322
+
Roof - Demo - Roof to Deck, Metal Gutter, Walk Pad
Util - Review Impacts
Util - Identify Scope
FS - Identify Scope FS - Demo Scope
FS - Repair Foundations
Super - Identify Scope
Super - Demo for Scope Super - Install & Repair from Scope
Roof - Demo - Roof to Deck, Metal Gutter, Walk Pad
Roof - Install (4800 SQFT)
15d
6/25/2027
7/16/2027
South Building - Area 112
35d
6/11/2027
7/30/2027
324
Roof - Demo - Roof to Deck
10d
6/11/2027
6/24/2027
Roof - Demo - Roof to Deck
325
Roof - RTU's Removal and Roof Structure
5d
6/18/2027
6/24/2027
Roof - RTU's Removal and Roof Structure
326
Roof - Install (1100 SQFT)
15d
6/25/2027
7/16/2027
Roof - Install (1100 SQFT)
327
Roof - RTU's Install
15d
6/25/2027
7/16/2027
Roof - RTU's Install
328
Roof - RTU's Install Roof Structure
5d
7/19/2027
7/23/2027
329
Roof - Paint Walls
5d
7/26/2027
7/30/2027
15d
8/2/2027
8/20/2027
5d
8/2/2027
8/6/2027
323
Roof Punch 330
Roof - Pre-Punch
BVSD Heattherwood ES Proposal Schedule Boulder Valley School District
Roof - Install (4800 SQFT)
Roof - RTU's Install Roof Structure
Roof - Paint Walls
Roof - Pre-Punch
Job #: BVSD Heatherwood ES Rev. date: 10/19/2026 11:56:11 AM
Data Date: 10/15/2026
Page 11 of 14
BVSD Heatherwood ES Progress 10/15/26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish 4
331
Roof - Owner Walk
5d
8/9/2027
8/13/2027
332
Roof - Punch Corrections
5d
8/16/2027
8/20/2027
Interiors / Mechanical / Electrical / Plumbing
106d
3/24/2027
8/20/2027
North Building - AREA 111.North Buildling
86d
3/24/2027
7/23/2027
Interior Rough In (Nights & Days)
60d
3/24/2027
6/16/2027
333
IF-RI - North - Interior Rough In Activities - Nights
45d
3/24/2027
5/25/2027
334
IF-RI - North - Interior Rough In Activities - Summers
10d
5/26/2027
6/9/2027
335
IF-RI - North - (V18) Light Fixtures Priorities 1-5 Rough In (310)
2025 2026 2027 2028 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 Roof - Owner Walk Roof - Punch Corrections
IF-RI - North - Interior Rough In Activities - Nights IF-RI - North - Interior Rough In Activities - Summers
6d
6/9/2027
6/16/2027
Interior Finishes
46d
5/19/2027
7/23/2027
336
IF-FIN - North - Repair and Paint
25d
5/19/2027
6/23/2027
337
IF-FIN - North - (V18) Light Fixtures Install
15d
6/17/2027
7/8/2027
IF-FIN - North - (V18) Light Fixtures Install
338
IF-FIN - North - Pre-Punch
10d
6/24/2027
7/8/2027
IF-FIN - North - Pre-Punch
339
IF-FIN - North - Owner Walk
1d
7/9/2027
7/9/2027
IF-FIN - North - Owner Walk
340
IF-FIN - North - Punch Corrections
10d
7/12/2027
7/23/2027
Alternate - Wall Replacement
19d
5/28/2027
6/24/2027
Alternate - Casework Replacement
10d
6/25/2027
7/9/2027
Alternate - Carpet Replacement
10d
7/12/2027
7/23/2027
106d
3/24/2027
8/20/2027
South Buidling - AREA 112.South Building
IF-RI - North - (V18) Light Fixtures Priorities 1-5 Rough In (310)
IF-FIN - North - Repair and Paint
IF-FIN - North - Punch Corrections
+
+ +
+ +
+
Interior Rough In (Nights & Days)
60d
3/24/2027
6/16/2027
341
IF-RI - South - Interior Rough In Activities (Nights)
45d
3/24/2027
5/25/2027
IF-RI - South - Interior Rough In Activities (Nights)
342
IF-RI - South - Interior Rough In Activities
10d
5/26/2027
6/9/2027
IF-RI - South - Interior Rough In Activities
343
IF-RI - South - (V18) Light Fixtures Priorities 1-5 Rough In (310)
6d
6/9/2027
6/16/2027
Interior Finishes
61d
5/26/2027
8/20/2027
344
IF-FIN - South - Vestibule Storefront
10d
5/26/2027
6/9/2027
345
IF-FIN - South - Repair and Paint
30d
6/10/2027
7/22/2027
IF-FIN - South - Repair and Paint
346
IF-FIN - South - (V18) Light Fixtures Install
15d
6/17/2027
7/8/2027
IF-FIN - South - (V18) Light Fixtures Install
347
IF-FIN - South - Pre-Punch
10d
7/23/2027
8/5/2027
IF-FIN - South - Pre-Punch
348
IF-FIN - South - Owner Walk
1d
8/6/2027
8/6/2027
IF-FIN - South - Owner Walk
349
IF-FIN - South - Punch Corrections
10d
8/9/2027
8/20/2027
East Building - AREA 113
350 351 352
IF-RI - South - (V18) Light Fixtures Priorities 1-5 Rough In (310)
IF-FIN - South - Vestibule Storefront
IF-FIN - South - Punch Corrections
36d
6/4/2027
7/26/2027
Interior Rough In (Nights & Days)
10d
6/4/2027
6/17/2027
IF-RI - East - Kitchen Hood Rough In
10d
6/4/2027
6/17/2027
10d
6/4/2027
6/17/2027
IF-RI - East - Kitchen Walk In Cooler Rough In Activities
6d
6/9/2027
6/16/2027
IF-RI - East - (V18) Light Fixtures Priorities 1-5 Rough In (310)
27d
6/17/2027
7/26/2027
IF-RI - East - Kitchen Walk In Cooler Rough In Activities IF-RI - East - (V18) Light Fixtures Priorities 1-5 Rough In (310) Interior Finishes
BVSD Heattherwood ES Proposal Schedule Boulder Valley School District
IF-RI - East - Kitchen Hood Rough In
Job #: BVSD Heatherwood ES Rev. date: 10/19/2026 11:56:11 AM
Data Date: 10/15/2026
Page 12 of 14
BVSD Heatherwood ES Progress 10/15/26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish 4
2025 2026 2027 2028 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14
353
IF-FIN - East - (V18) Light Fixtures Install
15d
6/17/2027
7/8/2027
354
IF-FIN - East - Repair and Paint
10d
6/18/2027
7/1/2027
IF-FIN - East - Repair and Paint
355
IF-FIN - East - Pre-Punch
5d
7/2/2027
7/9/2027
IF-FIN - East - Pre-Punch
356
IF-FIN - East - Owner Walk
1d
7/12/2027
7/12/2027
IF-FIN - East - Owner Walk
357
IF-FIN - East - Punch Corrections
10d
7/13/2027
7/26/2027
75d
5/20/2027
9/3/2027
FS - Identify Scope
10d
6/2/2027
6/15/2027
Sitework Demo
23d
5/20/2027
6/22/2027
5d
5/20/2027
5/26/2027
FS - Demo Grind Uneven Sidewalk Concrete(V1)(10LF)
5d
5/20/2027
5/26/2027
FS - Demo Route and Seal Cracks in Concrete Sidewalk (V1)(104LF)
5d
5/20/2027
5/26/2027
FS - Demo Route and Seal Cracks in Concrete Paving (V1)(77LF)
5d
5/20/2027
5/26/2027
FS - Remove Soil & Organic Matter From Sidewalk Joints and Sidewalk (V1)
FS - Demo - Losen Existing Post & RE-Tension Existing Fabric Chainlink Fence (V2)(800LF)
Sitework 358
359 360 361 362
FS - Demo Grind Uneven Sidewalk Concrete(V1)(10LF) FS - Demo Route and Seal Cracks in Concrete Sidewalk (V1)(104LF) FS - Demo Route and Seal Cracks in Concrete Paving (V1)(77LF) FS - Remove Soil & Organic Matter From Sidewalk Joints and Sidewalk (V1) FS - Demo - Losen Existing Post & RE-Tension Existing Fabric Chainlink Fence (V2)(800LF)
IF-FIN - East - (V18) Light Fixtures Install
IF-FIN - East - Punch Corrections
FS - Identify Scope
5d
5/20/2027
5/26/2027
364
FS - Demo - Grind Uneven Concrete Joints (V1)(18LF)
5d
5/20/2027
5/26/2027
365
FS - Demo - Damaged Sidewalk At Existing Tree Wells (V1)(318SF)
1d
5/20/2027
5/20/2027
366
FS - Demo Perimeter 3 Gates Fence (A2)
5d
5/20/2027
5/26/2027
FS - Demo Perimeter 3 Gates Fence (A2)
367
FS - Demo Playgroundd
5d
6/16/2027
6/22/2027
FS - Demo Playgroundd
368
FS - Demo Pedestrain Pavement (V1)(761SF)
5d
6/16/2027
6/22/2027
FS - Demo Pedestrain Pavement (V1)(761SF)
369
FS - Demo Perimeter Fence (V2)(200LF)
5d
6/16/2027
6/22/2027
FS - Demo Perimeter Fence (V2)(200LF)
363
Sitework Install
FS - Demo - Grind Uneven Concrete Joints (V1)(18LF) FS - Demo - Damaged Sidewalk At Existing Tree Wells (V1)(318SF)
42d
5/21/2027
7/21/2027
370
FS - Replace Damaged Sidewalk At Existing Tree Wells (V1)(318SF)
1d
5/21/2027
5/21/2027
371
FS - Grind Uneven Sidewalk Concrete (V1)(10LF)
5d
5/27/2027
6/3/2027
FS - Grind Uneven Sidewalk Concrete (V1)(10LF)
5d
5/27/2027
6/3/2027
FS - Route and Seal Cracks in Concrete Sidewalk (V1) (104LF)
5d
5/27/2027
6/3/2027
FS - Route and Seal Cracks in Concrete Paving (V1) (77LF)
5d
5/27/2027
6/3/2027
FS - Seal Sidewalk Joints and Sidewalks From Soil & Organic Matter
372 373 374
FS - Route and Seal Cracks in Concrete Sidewalk (V1) (104LF) FS - Route and Seal Cracks in Concrete Paving (V1) (77LF) FS - Seal Sidewalk Joints and Sidewalks From Soil & Organic Matter FS - Tighten Existing Post & RE-Tension Existing Fabric Chainlink Fence (V2)(800LF)
FS - Replace Damaged Sidewalk At Existing Tree Wells (V1)(318SF)
5d
5/27/2027
6/3/2027
FS - Tighten Existing Post & RE-Tension Existing Fabric Chainlink Fence (V2)(800LF)
376
FS - Grind Uneven Concrete Joints (V1)(18)
5d
5/27/2027
6/3/2027
FS - Grind Uneven Concrete Joints (V1)(18)
377
FS - Repair Perimeter 3 Gates Fence (A2)
20d
5/27/2027
6/24/2027
378
FS - Grind Trip Hazard At Top Of Stair Railing (V1)
1d
6/4/2027
6/4/2027
379
FS - Repair Playground
20d
6/23/2027
7/21/2027
FS - Repair Playground
380
FS - Prep/Form/Pour Pedestrain Pavement (V1)(761SF)
20d
6/23/2027
7/21/2027
FS - Prep/Form/Pour Pedestrain Pavement (V1)(761SF)
381
FS - Repair Perimeter Fence (V2)(200LF)
20d
6/23/2027
7/21/2027
FS - Repair Perimeter Fence (V2)(200LF)
Sitework Punch
32d
7/22/2027
9/3/2027
382
FS - Pre-Punch
5d
7/22/2027
7/28/2027
FS - Pre-Punch
383
FS - Punch
5d
7/29/2027
8/4/2027
FS - Punch
375
BVSD Heattherwood ES Proposal Schedule Boulder Valley School District
FS - Repair Perimeter 3 Gates Fence (A2) FS - Grind Trip Hazard At Top Of Stair Railing (V1)
Job #: BVSD Heatherwood ES Rev. date: 10/19/2026 11:56:11 AM
Data Date: 10/15/2026
Page 13 of 14
BVSD Heatherwood ES Progress 10/15/26 Filter: No Summary Tasks
Line
Name
Duration
Start
Finish 4
384
FS - Punch Corrections
10d
8/23/2027
9/3/2027
Final Inspections & Closeout
55d
7/19/2027
10/4/2027
MEP Startup & Commissioning
10d
7/19/2027
7/30/2027
Startup / Test & Balance
5d
7/19/2027
7/23/2027
2025 2026 2027 2028 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb 18 1 15 29 13 27 10 24 8 22 5 19 2 16 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21 4 18 1 15 1 15 29 12 26 10 24 7 21 5 19 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 FS - Punch Corrections
385
Startup/TAB - Startup / Test & Balance Tasks
5d
7/19/2027
7/23/2027
Startup/TAB - Startup / Test & Balance Tasks
386
North - (V18) Lighting Controls, Programming, Testing
5d
7/19/2027
7/23/2027
North - (V18) Lighting Controls, Programming, Testing
387
South - (V18) Lighting Controls, Programming, Testing
5d
7/19/2027
7/23/2027
South - (V18) Lighting Controls, Programming, Testing
East - (V18) Lighting Controls, Programming, Testing
388
East - (V18) Lighting Controls, Programming, Testing Commissioning
5d
7/19/2027
7/23/2027
10d
7/19/2027
7/30/2027
10d
7/19/2027
7/30/2027
Final Project Punchlist
20d
8/2/2027
8/27/2027
390
Punch - Pre-Punch - Final
5d
8/2/2027
8/6/2027
391
Punch - Owner Walk -Final
5d
8/9/2027
8/13/2027
392
Punch - Punch Corrections - Final
10d
8/16/2027
8/27/2027
10d
7/19/2027
7/30/2027
389
CX - Commissioning Tasks
Final Inspections / TCO Final Inspections
CX - Commissioning Tasks
Punch - Pre-Punch - Final
Punch - Owner Walk -Final
Punch - Punch Corrections - Final
10d
7/19/2027
7/30/2027
393
FInsp - Final Plumbing Inspection
5d
7/19/2027
7/23/2027
FInsp - Final Plumbing Inspection
394
FInsp - Final AHJ Inspection
2d
7/26/2027
7/27/2027
FInsp - Final AHJ Inspection
395
FInsp - Final Electrical Inspection
3d
7/26/2027
7/28/2027
FInsp - Final Electrical Inspection
396
FInsp - Final Electrical Inspection - State
3d
7/26/2027
7/28/2027
FInsp - Final Electrical Inspection - State
397
FInsp - Final Building Inspection
2d
7/29/2027
7/30/2027
FInsp - Final Building Inspection
398
Substantial Completion - TCO
1d
7/30/2027
7/30/2027
Substantial Completion - TCO
55d
7/19/2027
10/4/2027
6d
8/2/2027
8/9/2027
Owner Move In Activities 399
Move - Owner Move In Activities Closeout / CO
55d
7/19/2027
10/4/2027
400
Closeout - Start
1d
7/19/2027
7/19/2027
401
Closeout - Owner Training
20d
7/20/2027
8/16/2027
402
Closeout - Final Completion
20d
9/7/2027
10/4/2027
BVSD Heattherwood ES Proposal Schedule Boulder Valley School District
Move - Owner Move In Activities
Closeout - Start Closeout - Owner Training
Closeout - Final Completion
Job #: BVSD Heatherwood ES Rev. date: 10/19/2026 11:56:11 AM
Data Date: 10/15/2026
Page 14 of 14
BVSD Heatherwood ES Progress 10/15/26 Filter: No Summary Tasks
Exhibit E Insurance Insurance Certificates to be provided after Certificates amendment & change order for the GMP is executed
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit F Performance Bond to be provided after amendment & change order for the GMP is executed
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit G Labor and Materials Payment Bond to be provided after amendment & change order for the GMP is executed
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit H Alternates prices Alternates prices not used for the amendment
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
BVSD Heatherwood Renovation Price option List
Alternate
Status
Pending Cost Reduction
Pending Cost Addition
Accepted Cost
Rejected Cost
Comments
Decision Date
Alternates A1 : Floor Sink Replacement in Dishwashing 138
Accepted
In Base Bid
10.12.26
A2 : South Fence and Gates Replacement
Accepted
In Base Bid
10.12.26
A3 : “Wind Tunnel” Effect Mitigation in Corridor 202 V18a : REQ-88403 Lighting Fixtures – Interior – Troffer Renewal Priority 1 V18b : REQ-88403 Lighting Fixtures – Interior – Troffer Renewal Priority 2 V18c : REQ-88403 Lighting Fixtures – Interior – Troffer Renewal Priority 3 V18d : REQ-88403 Lighting Fixtures – Interior – Troffer Renewal Priority 4 V18e : REQ-88403 Lighting Fixtures – Interior – Troffer Renewal Priority 5
Pending Accepted Accepted Accepted Accepted Accepted
In Base Bid In Base Bid In Base Bid In Base Bid In Base Bid
10.12.26 10.12.26 10.12.26 10.12.26 10.12.26
$83,493
Exhibit I prices Unit prices not Unit used for this amendment This exhibit is not applicable at this time.
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit J Allowances
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Allowances Report DESCRIPTION
QTY UOM
UNIT PRICE
1.00 allow
700,000.00
TOTAL COST
NOTES / COMMENTS
11 Equipment 11 68 13 Playground Equipment 00000 UA Playground Improvements
$700,000
Subtotal 11 68 13 Playground Equipment
$700,000
Allowance
$700,000 $700,000
Subtotal 11 Equipment 23 Heating, Ventilating and Air Conditioning 23 00 00 Heating, Ventilating and Air Conditioning 23260 3rd Party Design for Wind
$15,000 1.00 allow
15,000.00
Subtotal 23 00 00 Heating, Ventilating and Air Conditioning
$15,000
Allowance
$15,000 $15,000
Subtotal 23 Heating, Ventilating and Air Conditioning 26 Electrical 26 00 00 Electrical 23160 Disconnections/ Reconnections for Roof Replacement Subtotal 26 00 00 Electrical Subtotal 26 Electrical
$3,000 1.00 allow
3,000.00
$3,000
Allowance
$3,000 $3,000
Allowance 11 68 13 Playground Equipment is a stated allowance for the project. AP has received the UA playground 100% CD drawings and specifications for review and pricing.
DATE PRINTED: 10/15/2026
Exhibit K Not Applicable
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit L Equipment rental rate schedule
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit M General Conditions of the Contract
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
BOULDER VALLEY SCHOOL DISTRICT RE-2 BOULDER, COLORADO
GENERAL CONTRACT CONDITIONS BOND PROGRAM
GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT.................................................................................................... 2 GC 1.00
CONTRACT DOCUMENTS AND DEFINITIONS ............................................................................................................ 1
GC 2.00
REFERENCE STANDARDS .......................................................................................................................................... 2
GC 3.00
DRAWINGS AND SPECIFICATIONS ............................................................................................................................ 2
GC 4.00
ROYALTIES AND PATENTS ........................................................................................................................................ 3
GC 5.00
ITEMS COVERED BY CONTRACT PRICE ..................................................................................................................... 3
GC 6.00
EXECUTION, CORRELATION, INTENT, AND INTERPRETATION OF CONTRACT DOCUMENTS ...................................... 3
GC 7.00
MATERIALS, LABOR, FACILITIES, AND STORAGE....................................................................................................... 4
GC 8.00
PERFORMANCE AND PAYMENT BONDS ................................................................................................................... 5
GC 9.00
PERMITS AND COMPLIANCE WITH STATUTES, RULES, AND REGULATIONS .............................................................. 6
GC 10.00
SURVEYS, BENCHMARKS, MONUMENTS, STAKES, AND MEASUREMENTS ............................................................... 6
GC 11.00
CHANGED CONDITIONS ........................................................................................................................................... 7
GC 12.00
PROTECTION OF PERSONS, WORK AND PROPERTY ................................................................................................. 7
GC 13.00
WORK ON EXISTING BUILDINGS .............................................................................................................................. 8
GC 14.00
CONTRACTOR’S SUPERINTENDENCE AND SUPERVISION .......................................................................................... 8
GC 15.00
SUBSTITUTIONS ....................................................................................................................................................... 9
GC 16.00
SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES ................................................................................................. 9
GC 17.00
CASH ALLOWANCE................................................................................................................................................. 10
GC 18.00
EXPEDITING MATERIALS ........................................................................................................................................ 10
GC 19.00
BLASTING .............................................................................................................................................................. 11
GC 20.00
SOIL TEST REPORT ................................................................................................................................................. 11
GC 21.00
HAZARDOUS MATERIALS ....................................................................................................................................... 11
GC 22.00
DAMAGE TO UTILITIES ........................................................................................................................................... 11
GC 23.00
CHANGES IN THE WORK ........................................................................................................................................ 12
GC 24.00
CLAIMS FOR EXTRA COST....................................................................................................................................... 13
GC 25.00
DELAYS AND EXTENSIONS OF TIME ....................................................................................................................... 13
GC 26.00
ACCESS TO WORK .................................................................................................................................................. 14
GC 27.00
CORRECTION OF WORK ......................................................................................................................................... 14
GC 28.00
OWNER’S RIGHT TO CARRY OUT WORK ................................................................................................................. 16
GC 29.00
OWNER’S RIGHT TO TERMINATE CONTRACT ......................................................................................................... 16
GC 30.00
CONSTRUCTION SCHEDULE AND PROGRESS REPORTS ........................................................................................... 16
GC 31.00
SCHEDULE OF VALUES ........................................................................................................................................... 17
GC 32.00
PAYMENT .............................................................................................................................................................. 17
GC 33.00
INSURANCE ........................................................................................................................................................... 19
GC 34.00
SEPARATE CONTRACTS .......................................................................................................................................... 23
GC 35.00
SUBCONTRACTORS ................................................................................................................................................ 23
GC 36.00
RELATIONS OF CONTRACTOR AND SUBCONTRACTOR ........................................................................................... 24
GC 37.00
CONTRACTORS’ MUTUAL RESPONSIBILITY ............................................................................................................ 25
GC 38.00
CUTTING, PATCHING, AND EXCAVATING ............................................................................................................... 25
GC 39.00
EMPLOYEES ........................................................................................................................................................... 26
GC 40.00
CLEANING UP......................................................................................................................................................... 27
GC 41.00
USE OF PREMISES .................................................................................................................................................. 27
GC 42.00
OCCUPANCY .......................................................................................................................................................... 27
GC 43.00
TEMPORARY OR TRIAL USAGE ............................................................................................................................... 28
GC 44.00
TESTING OF BUILDING SYSTEMS ............................................................................................................................ 28
GC 45.00
LIQUIDATED DAMAGES FOR DELAY IN COMPLETION ............................................................................................. 28
GC 46.00
ACCEPTANCE AND FINAL PAYMENT ....................................................................................................................... 28
GC 47.00
WARRANTIES ON PORTIONS OF THE WORK .......................................................................................................... 29
GC 48.00
CONTRACTOR’S PROJECT GUARANTEE AFTER COMPLETION ................................................................................. 30
GC 49.00
MISCELLANEOUS KEYS, SWITCHES, ETC. ................................................................................................................ 30
GC 50.00
INDEMNIFICATION ................................................................................................................................................ 30
GC 51.00
LABOR DISPUTES ................................................................................................................................................... 31
GC 52.00
LIMITATION OF ACTIONS ....................................................................................................................................... 31
GC 53.00
PREFERENCE FOR COLORADO LABOR, MATERIALS, AND RESIDENT BIDDERS ........................................................ 31
GC 54.00
SALES AND USE TAX............................................................................................................................................... 31
GC 55.00
LIENS ..................................................................................................................................................................... 32
GC 56.00
OWNER’S INSPECTION OF CONTRACTOR’S RECORDS ............................................................................................ 32
GC 57.00
CERTIFICATION BY CONTRACTOR REGARDING PREMISES ACCESS ......................................................................... 32
GC 58.00
CONTRACTOR SAFETY RESPONSIBILITIES ............................................................................................................... 32
GC 59.00
CONTRACTOR ASBESTOS MANAGEMENT AND LEAD PAINT RESPONSIBILITIES ...................................................... 35
GC 60.00
ARCHITECT’S STATUS AND INSPECTIONS ............................................................................................................... 35
GC 61.00
ORAL STATEMENTS................................................................................................................................................ 35
GC 62.00
PROJECT SIGN ........................................................................................................................................................ 36
GC 63.00
HISTORICAL DATA .................................................................................................................................................. 36
GC 64.00
ASSIGNMENT ......................................................................................................................................................... 36
GC 65.00
TIME OF THE ESSENCE ........................................................................................................................................... 36
GC 66.00
DISPUTES ............................................................................................................................................................... 36
GC 67.00
SURVIVAL .............................................................................................................................................................. 36
GC 1.00
CONTRACT DOCUMENTS AND DEFINITIONS
All Work under the Construction Agreement shall be accomplished in accordance with the Contract Documents, which shall consist of the Request for Qualifications, Request for Proposals, Proposal(s), Notice of Award, Notice to Proceed, Performance Bond, Labor and Material Payment Bond, Construction Agreement, General Contract Conditions, Supplementary Conditions, Asbestos Management Plan Contractor Responsibility Form, Drawings and Specifications, tests and engineering data, approved Change Orders, Contractor’s Requests for Payment, Architect’s Certificates, and all addenda issued by the Owner or Architect prior to execution of the Construction Agreement and all modifications issued by the Owner or Architect after execution of the Construction Agreement. With respect to the Contract Documents, the following definitions and understandings shall control: 1.01 “Contract” or “Contract Documents” shall include all of the items enumerated in GC-1.00 above. 1.02 “Owner” shall mean Boulder Valley School District No. RE-2, and shall include its duly authorized representatives. 1.03 “Contractor” shall mean the corporation, company, partnership, firm, entity, or individual named and designated as such in the Construction Agreement, and any persons or entities acting on its behalf. 1.04 “Subcontractor” shall mean any corporation, partnership, entity, or individual having a direct contract with the Contractor or another subcontractor for performing Work and/or furnishing labor or material on the Project covered by the Contract. 1.05 “Architect” shall mean the corporation, partnership, entity or individual named and designated as “architect” or “engineer” in the Construction Agreement, and any persons or entities acting on the Architect’s behalf and within the scope of the particular duties properly entrusted to them in each case. In the event that there is no Architect on the Project, then “Architect” shall refer to Owner and its duly authorized representative. 1.06 “Notice to Contractor” shall be deemed to have been duly served if made in writing and delivered in person to the individual or to a member of the firm or to an officer of the corporation for which it is intended, or if sent by registered or certified mail, to Contractor’s last known business address. 1.07 “The Work” shall mean the construction and services required by the Contract Documents for completion of the Project, and includes all labor, materials, equipment and services provided or to be provided by the Contractor to fulfill the Contractor’s obligations, whether on or off the Project site, and all labor, materials equipment and services provided or to be provided by subcontractors, sub-subcontractors, or any other entity for whom the Contractor is responsible. 1.08 “The Project” is the total construction designed by the Architect of which the Work performed under the Contract Documents may be the whole or a part. 1.09 The “date of final completion” and “finally completed” shall mean the date when construction is certified by the Architect to be finally completed in accordance with the Contract Documents, as modified by any Change Orders processed under the terms of GC-23.00 below and when the Owner has fully accepted the Project for the use for which it was intended. Such date will be set forth on a letter of acceptance issued by the Owner. 1.010 “Drawings” or “plans” shall mean all (a) drawings furnished by the Owner and/or Architect as a basis for the award of Contract and for construction of the Project; (b) supplementary drawings furnished by the Owner and/or Architect to clarify and to define in greater detail the intent of the Contract drawings and specifications; (c) drawings submitted by the successful Contractor as may be required after the Contract is awarded; (d) drawings furnished by the Owner and/or Architect to the Contractor during the progress of the Work; and (e) engineering data and drawings submitted by the Contractor during the progress of the Work, provided such drawings are acceptable to the Architect and Owner. 1
1.011 “Specifications” are the written technical information concerning materials, components, systems, equipment, and manner of installation as indicated on the drawings or plans and which state the quality, performance, and characteristics to be achieved by application of construction methods. 1.012 “Change Order” shall mean a written order to the Contractor signed by the Owner or its authorized agent issued after the execution of the Construction Agreement, authorizing a change in the Work and/or adjustment in the Guaranteed Maximum Price (“GMP”) or the contract time schedule. Each adjustment in the GMP resulting from a Change Order shall clearly separate the amount attributable to the Cost of the Work and the Contractor’s Fee. 1.013 “day” or “days” shall mean calendar days. In computing a period of days, when the ending date is not specified, the first day is excluded and the last day is included. If any deadline falls on a Saturday, Sunday, or federal or Colorado state holiday, such deadline will be extended to the next day that is not a Saturday, Sunday or federal or Colorado state holiday. GC 2.00
REFERENCE STANDARDS
2.01 Reference to the standards of any technical society, organization, or association, or to codes of local or state authorities, shall mean the latest standard, code, specification, or tentative standard adopted and published as of the date of execution of the Construction Agreement, unless specifically stated otherwise. GC 3.00
DRAWINGS AND SPECIFICATIONS
3.01 Ownership of Drawings. All drawings, specifications, and copies thereof furnished by the Architect are the property of the Architect and the Owner, whether or not the Work for which they are made is performed, and are not to be used on other Work except by written agreement with the Architect and the Owner. 3.02 Figured Dimensions to Govern. Dimensions and elevations shown on the drawings shall be accurately followed. No Work shown on the drawings, the dimensions of which are not indicated, shall be executed until necessary dimensions have been obtained from the Architect. 3.03 Contractor to Check Drawings and Schedules. The Contractor shall check and verify all dimensions, elevations, and quantities shown on the drawings and furnished to it by the Architect, and shall notify the Architect of any discrepancy between the drawings and the conditions on the ground, or any error or omission in drawings, or in the layout as given by stakes, points, or instructions that it may discover. Before ordering any material or doing any Work, the Contractor shall verify all measurements concerning the Project and shall be responsible for the correctness of same. No extra charge or compensation shall be allowed on account of any difference between actual dimensions and the measurements indicated on the drawings. Any difference that may be found shall be submitted to the Architect for consideration and written determination before proceeding with the Work. The Contractor shall not be allowed to take advantage of any error or omission in the drawings or Contract Documents. Full written instructions shall be furnished by the Architect should such error or omission be discovered, and the Contractor shall carry out such instructions as if originally specified. 3.04 Detail Drawings and Instructions. The Architect shall furnish with reasonable promptness additional instructions, by means of drawings or otherwise, necessary for the proper execution of the Work. All such drawings and instructions shall be consistent with the Contract Documents. The Work shall be executed in conformity with the Architect’s drawings and instructions, and the Contractor shall do no Work without proper drawings and instructions. 3.05 Drawings and Specifications Available on the Site. The Contractor shall maintain at the Project site for the Owner and the Architect a Project record set of drawings, including addenda, approved shop drawings, Change Orders, and other modifications, with all changes or deviations from the original drawings neatly marked thereon in a contrasting color. The Contractor shall also maintain a Project record set of specifications at the 2
Project site, noting therein by appropriate section the names, models, and other distinguishing characteristics of the materials actually incorporated into the Work. This Project record set of drawings and specifications shall be updated daily as the Project progresses and shall be made available to the Owner and Architect for inspection at all times. Upon final completion of the Work and before final payment, three (3) copies and one (1) electronic of this Project record set of drawings and specifications shall be delivered to the Owner. One (1) copy of this Project record set of drawings and specification shall be delivered to the Architect. 3.06 Laws and Regulations. The Contractor shall give all notices and comply with all laws, ordinances, rules, and regulations bearing on the conduct of the Work as drawn and specified. If the Contractor observes that the drawings and specifications are at variance therewith, it shall promptly notify the Architect in writing, and any necessary adjustments shall be made as provided in the Contract for changes in the Work. If the Contractor performs any Work knowing it to be contrary to such laws, ordinances, rules, or regulations without giving the required notice to the Architect and receiving a written directive to proceed, it shall bear all costs arising therefrom and to correct and/or remedy same. GC 4.00
ROYALTIES AND PATENTS
The Contractor shall pay all royalties and license fees. The Contractor shall defend all suits or claims for infringement of patent rights and shall hold the Owner harmless from any and all liability or loss on account thereof. If the Contractor has information that the process or article specified involves the infringement of a patent, it shall be responsible for any and all liability or loss resulting therefrom unless it promptly furnishes such information to the Architect in writing. GC 5.00
ITEMS COVERED BY CONTRACT PRICE
5.01 Items Supplied by Owner. Owner shall supply the following items for the Project: a. Building Permit; b. Initial Survey; c. Materials Testing Including Soil Testing; d. Third Party Inspections; e. Commissioning; and f. Test and Balance as Required for Commissioning. 5.02 Items Supplied by Contractor. Unless specifically stated otherwise, the Contractor shall accept the compensation stated in the Construction Agreement as full payment for furnishing all the materials, transportation, apparatus, temporary structures, equipment, services, fuel, energy, light, water, labor and tools, and all other things necessary for the complete and proper execution of the Work contemplated by or reasonably implied from the Contract Documents, within the time limits indicated therein. Such amount shall include any loss or damage resulting from the nature of the Work, from the elements or from any unforeseen difficulties that may be encountered; all risks of every description connected with the prosecution of the Work; all expenses incurred in consequence of any suspension or discontinuance of the Work; and all other amounts necessary for completing the Work pursuant to the Contract Documents within the time limits indicated therein. GC 6.00
EXECUTION, CORRELATION, INTENT, AND INTERPRETATION OF CONTRACT DOCUMENTS
6.01 Execution. The Construction Agreement and other Contract Documents shall be signed in multiple copies as directed by the Owner. Within ten (10) days of Notice of Award, the Contractor shall submit to the Owner a minimum of five (5) fully executed original sets of the Construction Agreement; Performance Bond, and Labor and Material Payment Bond with original Power of Attorney; and certificates of required insurance coverage. The date of the Contract for purposes of these documents shall be the date of the Notice of Award letter. The Owner shall execute the Construction Agreement, assemble all copies, and distribute the Contract Documents. The Contractor shall not commence the Work until it receives the Notice to Proceed. All bonds and insurance 3
certificates shall be submitted to the Owner prior to the award of the first subcontract. 6.02 Correlation. By executing the Construction Agreement, the Contractor represents that it has visited the Project site, familiarized itself with the local conditions under which the Work is to be performed, and correlated its observations with the requirements of the Contract Documents. 6.03 Intent. The intention of the Contract Documents is to include all labor and materials, tools, equipment, construction equipment, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution and completion of the Work. Materials or Work described in words that, as applied, have a well-known technical or trade meaning shall be held to refer to such recognized meaning. The organization of the specifications into divisions, sections, and articles, as the case may be, and the arrangement of drawings shall not control the Contractor in dividing the Work among subcontractors or in establishing the extent of Work to be performed by any trade. It is intended that even though Work is not covered under any heading, division, section, article, branch, class, or trade of the specifications, it shall nevertheless be supplied if it is required elsewhere in the Contract Documents or is reasonably inferable therefrom as being necessary to produce the intended results. The specifications and drawings are intended to supplement but not necessarily duplicate each other. Any Work exhibited in the one and not in the other shall be executed as if it had been set forth in both, so that the Work will be constructed according to the complete design as determined by the Architect. 6.04 Interpretation. Should anything necessary for a clear understanding of the Work be omitted from the specifications and drawings, or should the requirements appear to be in conflict, the Contractor shall secure written interpretations or instructions from the Architect before proceeding with the Work affected thereby. The Contractor shall secure written interpretations or instructions by submitting the Owner’s form Request for Interpretation to the Architect. Oral requests shall not be acknowledged by the Architect or Owner. Additional costs incurred by the Owner as a result of unnecessary requests made by the Contractor, as determined by the Owner, shall be the responsibility of the Contractor. It is understood and agreed that the Work shall be performed according to the true intent of the Contract Documents. 6.05 Conflict in Interpretation. In the case of discrepancy or in the event of a conflict between the different Contract Documents, the documents shall take precedence in the following order: a. Change Orders; b. Written Amendments to Construction Agreement (including, if applicable, the GMP); c. Construction Agreement; d. General Conditions; e. Drawings and specifications; and f. Bid Documents, including addenda. Where two or more of the Contract Documents are complementary, the more detailed provision shall control over the more general provision. GC 7.00
MATERIALS, LABOR, FACILITIES, AND STORAGE
7.01 Contractor’s Responsibility. Unless otherwise agreed in writing, the Contractor shall provide and pay for all materials, labor, tools, equipment, machinery, transportation, and other facilities necessary for the proper execution and completion of the Work. The Contractor shall provide and pay for all the temporary facilities required to supply all the power, light, water, and heat needed by it and its subcontractors for their Work and shall install and maintain all such facilities in such manner as to protect the public and workers and to conform with any applicable laws and regulations. If temporary heat and/or protection is required for the expeditious prosecution of the Work and before the permanent heating apparatus is available for use, the temporary heating apparatus shall be installed and operated in such a manner that the finish Work and/or construction will not be damaged thereby. Unless otherwise specified, the Contractor shall pay for all the power, light, and water used by it and its subcontractors, without regard to whether such items are metered by temporary or permanent meters. The cutoff date on permanent meters shall be either the agreed date of full occupancy by 4
the Owner or the date of final acceptance of the Project, whichever shall be the earlier date. Upon completion of the Work, the Contractor shall remove all surplus materials, tools and such temporary facilities and structures, furnished by the contractor from the Project site. All debris and rubbish caused by the operations of the contractor shall be removed, and the area occupied during construction activities shall be restored to its original condition, within 48 hours of project completion, unless otherwise directed by the municipality or owner’s representative. 7.02 Materials. Unless otherwise specified, all materials shall be new and both Workmanship and materials shall be of the highest quality. The Contractor shall furnish satisfactory evidence to the Owner as to the kind and quality of materials. Samples shall be furnished, when specified, and the Work shall be in accordance with those samples that have been approved. 7.03 Toilet Facilities. The Contractor shall provide and maintain, in a neat and sanitary condition, adequate temporary toilet facilities for the use of any and all employees engaged on the Work, in strict compliance with the requirements of all applicable codes, regulations, laws, and ordinances. In no event may present toilet facilities of any existing building at the site of the Work be used by employees of the Contractor or its subcontractors. Upon final completion of the Work, the Contractor shall remove all such temporary facilities from the site and disinfect the premises. 7.04 Facilities and Storage. The Contractor shall provide suitable temporary facilities and quarters for workers, as needed, and shall maintain on premises water-tight storage sheds or tool houses for storage of building materials and tools that could be damaged by weather. The Contractor shall allow space for the erection of sheds and provide similar facilities for storage by subcontractors of their materials and tools. Storage of materials shall be confined to the site. These facilities or quarters shall further provide for protection against theft and damage of building materials and tools. Upon final completion of the Work, the Contractor shall remove all such temporary facilities from the site. 7.05 Office Space. The Contractor shall provide adequate, weatherproofed, heated and well- lighted office space at the site of the Work, for use by the Architect and the Owner and their representatives. The Contractor shall also provide telephone service at such office, which shall be available for use by the Architect, the Owner, and their representatives without charge, except for toll calls. 7.06 Quality and Location of Facilities. All of the foregoing facilities shall be of a quality and placed in locations acceptable to the Architect and the Owner. GC 8.00
PERFORMANCE AND PAYMENT BONDS
8.01 Required Bonds. The Contractor shall, within ten (10) days from the Notice of Award furnish bonds to the Owner in the full amount of the contract price, covering both the faithful performance of the Contract and the payment of all obligations for labor and materials arising thereunder, on such customary forms as the Owner may prescribe and with such sureties as it may approve. The amount of the bonds shall be increased, if necessary, to reflect approved changes in the Work that result in an increase in the total cost of the Work plus the Contractor’s fees. Such bonds shall be duly executed by a qualified surety licensed to do business in the State of Colorado, conditioned upon the true and faithful performance of the Contract, and shall provide that if the Contractor or its subcontractors fail to duly pay for any labor, materials, or other supplies used or consumed by such Contractor or its subcontractors in the performance of the Work contracted to be done, the surety will pay the same in an amount not exceeding the sum specified in the bond, as adjusted by approved Change Orders, and together with interest as provided by law. The performance bond shall additionally guarantee that the Contractor shall remedy any omissions, correct any and all defects, and adjust and make operable all component parts of Work falling under the requirements of the Contract that may be called to the Contractor’s attention within a period of twenty-four (24) months following the date of the letter of acceptance.
5
8.02 Additional Bond Requirements. The premium for all bonds shall be paid by the Contractor and included in the bid price in the bid proposal. The Owner will accept and approve bonds written by sureties legally authorized to write such bonds in the State of Colorado, provided such surety companies are rated in Best’s Insurance Guide (latest edition), not lower than A- or have Best’s Financial Rating of at least X. If, at any time a surety on such a bond becomes irresponsible or loses its right to do business in the State of Colorado, new bonds shall be provided by an alternate surety licensed to do business in the State and meeting the requirements of this Section 8.00. GC 9.00
PERMITS AND COMPLIANCE WITH STATUTES, RULES, AND REGULATIONS
9.01 Permits. Any local permits, governmental fees, and licenses necessary for the proper execution and completion of the Work shall be secured and paid for by the Contractor. Owner will pay for and secure building permit from Colorado Division of Fire Prevention and Control. Easements for permanent structures or permanent changes in existing facilities shall be secured and paid for by the Owner, unless otherwise specified in writing. The Owner is generally exempt from paying any fee for any building permit issued by any building departments or agencies located in Boulder, Broomfield, and Gilpin Counties, and the Contractor shall see that no building permit fee is paid. The Owner shall negotiate and provide for all electrical, gas, water, and sewer mains for the Contractor’s connections. The Contractor shall arrange with the utility company for actual connection, make necessary connections, and pay for all associated inspection fees and permits as required by any government agency. In addition, the Contractor shall furnish all material and items required to complete all connections. The Contractor shall call for all inspections on a timely basis by any agency having jurisdiction over the Work. 9.02 Compliance with Statutes, Rules and Regulations. The Contractor and all subcontractors shall comply with all applicable federal and state statutes, rules, regulations, and directives of the State Division of Fire Prevention and Control, and other governmental body having jurisdiction over the work to be performed. If any of the provisions of the Contract Documents are in conflict therewith, such portions shall be considered stricken and the applicable statute, ordinance, regulation, or ruling substituted therefor. All such cases of apparent conflict coming to the attention of any party shall immediately be called to the attention of the Owner. The Contractor shall strictly observe and comply with all federal and state laws pertaining to the employment and payment of labor. GC 10.00
SURVEYS, BENCHMARKS, MONUMENTS, STAKES, AND MEASUREMENTS
10.01 Surveys. As provided by the Owner, the Contractor shall obtain from the Architect a copy of all surveys describing property lines, elevation benchmarks, physical characteristics, and utility locations. 10.02 Benchmarks. The Contractor shall properly stake out the Work and provide and rigidly set benchmarks and batter boards as necessary for the proper performance of the Work. The Contractor shall remain responsible for their maintenance and their accuracy. A permanent benchmark, approved as to location and type by the Architect, from which all grades are to be taken, shall be established near the site of the Work by the Contractor. From this benchmark the Contractor shall ascertain all grades and levels to Project buildings as needed. The Contract Documents shall include all necessary information to establish the benchmark. 10.03 Preservation of Monuments and Stakes. The Contractor shall carefully preserve all monuments, benchmarks, property markers, reference points, and stakes. In case of the destruction thereof, the Contractor shall be charged with the expense of replacement and shall be responsible for any mistake or loss of time that may be caused. Permanent monuments and/or benchmarks that must be removed or disturbed shall be protected until properly referenced for relocation. The Contractor shall furnish all materials, labor and assistance for the proper replacement of such monuments and benchmarks. 10.04 Measurements. Before ordering any material or performing any Work, the Contractor shall verify all measurements on the Project and shall be responsible for the accuracy of same. No extra charge or 6
compensation shall be allowed because of any difference between actual dimensions and the measurements indicated in the drawings or specifications. Any discrepancies shall be submitted to the Architect and Owner for consideration before proceeding with the Work. GC 11.00
CHANGED CONDITIONS
The Contractor shall promptly, and before such conditions are disturbed, notify the Owner and the Architect in writing of: (1) sub-surface or latent physical conditions at the Project site differing materially from those indicated in the Contract Documents, or (2) unknown physical conditions at the Project site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in Work of the character provided for in the Contract Documents. The Owner and the Architect shall promptly investigate the conditions, and if the Owner finds that such conditions do so materially differ and cause an increase or decrease in the cost of or the time required for performance of the Work, an equitable adjustment shall be made and the Contract modified in writing accordingly. Any claim of the Contractor for adjustment hereunder shall not be allowed unless it has given notice as required. GC 12.00
PROTECTION OF PERSONS, WORK AND PROPERTY
12.01 Building Exits and Barricades. During the course of construction, the Contractor shall keep all required building exits free and unimpeded. Such exits shall not be closed at any time for any reason while the building is occupied or at any time when the building is unoccupied, except after written approval is given by the Owner and proper warning and directional signs are posted. Barricades shall be erected so that traffic is separated and protected from the construction. 12.02 Precautions. The Contractor shall take all necessary precautions to ensure the safety of all employees and other persons on the Project or who may be affected by the Contractor’s Work thereon. The Contractor shall also take all necessary precautions to protect the Work and all temporary facilities, as well as materials, tools, and equipment incorporated therein or to be incorporated therein from damage or destruction, whether in storage on or off the Project site and whether in the custody or control of the Contractor or any of its subcontractors. The Contractor shall also take all necessary precautions to protect all property at the Project site and adjacent thereto not designated for removal, relocation or replacement, including trees, shrubs, lawns, walks, pavements, roadways, structures, and utilities. 12.03 OSHA Compliance. The Contractor shall comply with all applicable provisions of the Occupational Safety and Health Administration (“OSHA”) and all laws, ordinances, rules, regulations, and orders of all governmental agencies or authorities having jurisdiction to protect the safety of employees and/or other persons who may be affected by the Work. The Contractor shall erect and maintain all necessary safeguards to protect workers on the Project site and the owners and users of adjacent property, and shall post danger signs and other warnings against hazards created by the Work including but not limited to protruding nails, hoists, well holes, elevator shafts, hatchways, scaffolding, window openings, stairways, excavations, and falling materials. The Contractor shall designate a responsible employee at the Project site as a safety officer to ensure the Contractor’s compliance with this section. Said employee shall be the Contractor’s superintendent unless otherwise designated in writing by the Contractor to the Owner and the Architect. 12.04 Contractor’s Liability. The Contractor shall be liable for all injury, damage or loss to any person or property caused in whole or in part by the Contractor, any of its subcontractors, or any person employed by or under the direction of the Contractor or any of its subcontractors. To the extent possible and unless otherwise directed by the Owner or Architect, the Contractor shall promptly repair, pay for or otherwise remedy any such injury, damage or loss and shall indemnify and hold harmless the Owner against any and all liability, claims, damages, losses and expenses arising therefrom. The terms of this section shall not apply in the case of injury, damage or loss proximately caused by the acts or omissions of the Owner and/or Architect and not attributable to any fault or negligence of the Contractor.
7
12.05 Emergencies. In the event of an emergency that threatens the safety or life of any person or threatens to damage or destroy the Project and/or any Work, materials, equipment or property thereon or to be used thereon, the Contractor shall act at its discretion to prevent such injury, death, damage or destruction. The Contractor shall immediately notify the Owner and Architect in writing of any such emergency and any action taken by the Contractor in response thereto. Any compensation due the Contractor for such emergency action shall be determined by agreement of the Contractor, Owner and Architect, and an appropriate Change Order shall be issued therefor. GC 13.00
WORK ON EXISTING BUILDINGS
13.01 Protection of Occupants. In addition to all other requirements of the Contract Documents, if the Work involves an addition or alteration to an existing building, the Contractor shall erect and maintain during the progress of the Work suitable dustproof partitions to protect such building and the occupants thereof. If necessary, in the Owner’s or Contractor’s judgment or pursuant to manufacturer’s directives or recommendations in order to protect occupants from noxious fumes, odors, or hazardous substances, the Contractor may be required to provide additional ventilation and/or work different or extended hours to avoid disruption to other activities within the existing building. Contractor shall protect and keep from harm all occupants of an existing building from construction activities, and shall include a safe pathway into and out of the school. 13.02 Partitions and Scheduling. If any portions of an existing building are to be remodeled or repaired, such portions shall be adequately partitioned off with dustproof partitions and well ventilated. All remodeling Work shall be scheduled and submitted to the Owner and Architect for approval. The various contractors shall schedule their Work jointly, in order that each may accomplish its Work within such existing building in an orderly fashion during regular school vacation periods where possible, or in such a manner as to permit full use of the building and without impairment of any existing facilities. 13.03 Existing Systems. Existing building systems, such as fire alarm, temperature controls and air distribution, security systems, public announcement systems, irrigation systems, and the like, shall be demonstrated and noted by Owner to the Contractor as operational prior to Contractor’s commencing the Work and Contractor may participate in observation of such systems. Such systems are the responsibility of the Contractor to maintain in pre-construction condition. GC 14.00
CONTRACTOR’S SUPERINTENDENCE AND SUPERVISION
14.01 Superintendent. During the progress of the Work, the Contractor shall ensure that a competent superintendent and any necessary assistants, all satisfactory to the Architect and the Owner, are on the Project site at all times while Work is in progress. The superintendent shall not be changed by the Contractor except with the written consent of the Architect and the Owner, unless the superintendent ceases to be in the Contractor’s employ. The superintendent shall represent the Contractor on the Project and all directions given to him/her shall be as binding as if given to the Contractor. The Architect and the Owner shall not be responsible for the acts or omissions of the superintendent or his/her assistants. 14.02 Supervision. The Contractor shall provide full-time, qualified, and efficient supervision of the Work, using competent skill and attention. The Contractor is responsible for determining and supervising all temporary and permanent erection and construction sequences, techniques, means, or methods. The Contractor shall direct, schedule, coordinate the Work to ensure that all parts fit together properly and in accordance with the Contract Documents. The Contractor shall carefully study and compare all Contract Documents and other instructions and shall at once report to the Architect and the Owner any error, inconsistency, or omission that Contractor may discover. 14.03 Additional Supervision Duties. The Contractor shall see that the Work is carried out in accordance with the Contract Documents and in a thorough and first-class manner in every respect. The Contractor shall 8
provide engineering, surveying, and coordination to accurately establish all lines, levels, and marks necessary to facilitate the operations of all parties involved in the Contractor’s Work. The Contractor shall lay out the Work in a manner satisfactory to the Architect, making permanent records of all lines and levels required for excavation, grading, and foundations, and for all other parts of the Work. The Contractor shall be responsible for the commencement and the proper completion of the various stages and sequences of construction. The Contractor shall strictly adhere to the approved construction schedule. GC 15.00
SUBSTITUTIONS
The Contractor shall be held to have used in its base proposal and to furnish under the Contract those items of equipment and/or materials that are specifically identified in the plans and specifications by a manufacturer’s name, model, or catalog number. Items of equipment and/or materials of the Contractor’s choice may be offered as alternates to the items named in the plans and specifications by submitting, with the proposal and on the form provided, identifying data on the articles proposed together with a statement of the amount of addition or deduction from the base bid if the bidder’s alternate is accepted. Prior approval by the Architect is not required on items submitted as alternate bids. After execution of the Construction Agreement, substitution of equipment and/or materials of makes other than those specifically named in the Contract Documents may be approved by the Owner so long as the equipment or material proposed for substitution in the opinion of the Owner is just as suitable as the equipment and/or materials named in the plans and specifications so far as performance, construction, efficiency, and utility are concerned. A request for substitution shall ordinarily be required to be based upon one or more of the following grounds: the specified equipment or material is no longer available, a substitution will improve lead time, quality will be improved (documented detail required), or the Owner will incur substantial savings. All requests for substitution must be submitted in writing with supporting documentation by or through the Contractor to the Architect for initial review and recommendation before being submitted to the Owner for evaluation and final approval. In the absence of the Owner’s written approval, no substitution of equipment or materials shall be allowed for any items specified in the Contract Documents. In case of a difference in price, occurring as a result of an approved substitution, the Owner shall receive all benefit of the difference in cost involved in the substitution. All approved substitutions shall be documented by the issuance of a formal Change Order as provided in these General Conditions. GC 16.00
SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
16.01 Shop Drawings. “Shop drawings” are drawings, diagrams, illustrations, schedules, performance charts, brochures, manufacturer’s literature, and other data that are prepared by the Contractor or any subcontractor, manufacturer, supplier, or distributor, and that illustrate some portion of the Work. Shop drawings shall be submitted in both hard copy and electronic format. 16.02 Samples. “Samples” are physical examples furnished by the Contractor to the Owner and/or Architect to illustrate materials, finishes, equipment, or Workmanship, and to establish standards by which the Work will be judged. 16.03 Product Data. “Product data” are illustrations, standard schedules, performance charts, instructions, brochures, diagrams and other information furnished by the Contractor to illustrate materials or equipment for some portion of the Work. Product data shall be submitted in both hard copy and electronic format. 16.04 Contractor’s Obligations. The Contractor shall review, approve, stamp an then submit to the Architect shop drawings, product data, samples, and similar submittals required by the Contract Documents with reasonable promptness and in such a sequence as to cause no delay in the Work or in the activities of the Owner or of separate contractors. Shop drawings, product data, samples, and similar submittal required by the Contract Documents shall properly identify specified items. At the time of submission, the Contractor shall inform the Architect in writing of any deviation in the shop drawings, product data, or samples from the requirements of the Contract Documents. Substitutions will be allowed only in accordance with the provisions of GC-15.00. The number of copies and format of submittal shall be as required by the Architect, but, at a 9