Exhibit A Drawings, specifications and documents used to prepare the GMP

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Printed on Thu Oct 22, 2026 at 03:14 pm MDT

Exhibit A

BVSD Coal Creek ES

Palace Construction

Current Drawings Drawing Number

Drawing Title

Revision

Drawing Date

Received Date

Set

Status

General G000

COVERSHEET

0

09/11/2026

09/11/2026

100% CD Set

Published

G101

OVERALL CODE PLAN

0

09/11/2026

09/11/2026

100% CD Set

Published

C100

GENERAL NOTES

0

09/11/2026

09/11/2026

100% CD Set

Published

C200

PROJECT KEY MAP

0

09/11/2026

09/11/2026

100% CD Set

Published

C201

SITE DEMOLITION PLAN

0

09/11/2026

09/11/2026

100% CD Set

Published

C300

SITE IMPROVEMENTS PLAN

0

09/11/2026

09/11/2026

100% CD Set

Published

A001

GENERAL NOTES, SYMBOLS, & ABBREVIATION

0

09/11/2026

09/11/2026

100% CD Set

Published

A101

OVERALL FLOOR PLAN

0

09/11/2026

09/11/2026

100% CD Set

Published

A101A

FLOOR PLAN - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

A101B

FLOOR PLAN - AREA B

0

09/11/2026

09/11/2026

100% CD Set

Published

A101C

FLOOR PLAN - AREA C

0

09/11/2026

09/11/2026

100% CD Set

Published

A101D

FLOOR PLAN - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

A141

OVERALL ROOF PLAN

0

09/11/2026

09/11/2026

100% CD Set

Published

A151

OVERALL RCP

0

09/11/2026

09/11/2026

100% CD Set

Published

AD101

OVERALL DEMOLITION PLAN

0

09/11/2026

09/11/2026

100% CD Set

Published

AD151

OVERALL DEMOLITION RCP

0

09/11/2026

09/11/2026

100% CD Set

Published

FS101

KITCHEN EQUIPMENT

0

09/11/2026

09/11/2026

100% CD Set

Published

FS102

KITCHEN PLUMBING / ELECTRICAL

0

09/11/2026

09/11/2026

100% CD Set

Published

FS501

KITCHEN GENERAL NOTES - DETAILS

0

09/11/2026

09/11/2026

100% CD Set

Published

Civil

Architectural

Food Service

Page 1 of 4

Printed on Thu Oct 22, 2026 at 03:14 pm MDT

Exhibit A

BVSD Coal Creek ES

Palace Construction

Drawing Number

Drawing Title

Revision

Drawing Date

Received Date

Set

Status

Structural S001

GENERAL NOTES

0

09/11/2026

09/11/2026

100% CD Set

Published

S002

GENERAL NOTES

0

09/11/2026

09/11/2026

100% CD Set

Published

S101

STRUCTURAL FLOOR PLAN

0

09/11/2026

09/11/2026

100% CD Set

Published

S141

STRUCTURAL ROOF PLAN

0

09/11/2026

09/11/2026

100% CD Set

Published

S200

STRUCTURAL DETAILS

0

09/11/2026

09/11/2026

100% CD Set

Published

M000

HVAC COVERSHEET

0

09/11/2026

09/11/2026

100% CD Set

Published

M101A

LEVEL 01 PLAN - HVAC - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

M101D

LEVEL 01 PLAN - HVAC - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

M141A

ROOF PLAN - HVAC - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

M141D

ROOF PLAN - HVAC - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

M400

HVAC DETAILS

0

09/11/2026

09/11/2026

100% CD Set

Published

M500

HVAC DIAGRAMS

0

09/11/2026

09/11/2026

100% CD Set

Published

M501

HVAC DIAGRAMS

0

09/11/2026

09/11/2026

100% CD Set

Published

M600

HVAC SCHEDULES

0

09/11/2026

09/11/2026

100% CD Set

Published

MD101A

LEVEL 01 DEMOLITION PLAN - HVAC - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

MD101D

LEVEL 01 DEMOLITION PLAN - HVAC - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

MD141A

ROOF DEMOLITION PLAN - HVAC - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

MD141D

ROOF DEMOLITION PLAN - HVAC - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

P000

PLUMBING COVERSHEET

0

09/11/2026

09/11/2026

100% CD Set

Published

P101A

LEVEL 01 PLAN - PLUMBING - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

P101B

LEVEL 01 PLAN - PLUMBING - AREA B

0

09/11/2026

09/11/2026

100% CD Set

Published

P101C

LEVEL 01 PLAN - PLUMBING - AREA C

0

09/11/2026

09/11/2026

100% CD Set

Published

Mechanical

Plumbing

Page 2 of 4

Printed on Thu Oct 22, 2026 at 03:14 pm MDT

Exhibit A

BVSD Coal Creek ES Palace Construction

Drawing Number

Drawing Title

Revision

Drawing Date

Received Date

Set

Status

P101D

LEVEL 01 PLAN - PLUMBING - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

P141D

ROOF PLAN - PLUMBING - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

P400

PLUMBING DETAILS

0

09/11/2026

09/11/2026

100% CD Set

Published

P600

PLUMBING SCHEDULES

0

09/11/2026

09/11/2026

100% CD Set

Published

PD101A

LEVEL 01 DEMOLITION PLAN - PLUMBING - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

PD101B

LEVEL 01 DEMOLITION PLAN - PLUMBING - AREA B

0

09/11/2026

09/11/2026

100% CD Set

Published

PD101C

LEVEL 01 DEMOLITION PLAN - PLUMBING - AREA C

0

09/11/2026

09/11/2026

100% CD Set

Published

PD101D

LEVEL 01 DEMOLITION PLAN - PLUMBING - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

PD141D

ROOF DEMOLITION PLAN - PLUMBING - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

E000

ELECTRICAL COVERSHEET

0

09/11/2026

09/11/2026

100% CD Set

Published

E001

ELECTRICAL LIGHTING COVERSHEET

0

09/11/2026

09/11/2026

100% CD Set

Published

E101A

LEVEL 01 PLAN - LIGHTING - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

E101B

LEVEL 01 PLAN - LIGHTING - AREA B

0

09/11/2026

09/11/2026

100% CD Set

Published

E101C

LEVEL 01 PLAN - LIGHTING - AREA C

0

09/11/2026

09/11/2026

100% CD Set

Published

E101D

LEVEL 01 PLAN - LIGHTING - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

E111A

LEVEL 01 PLAN - POWER AND SYSTEMS - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

E111B

LEVEL 01 PLAN - POWER AND SYSTEMS - AREA B

0

09/11/2026

09/11/2026

100% CD Set

Published

E111C

LEVEL 01 PLAN - POWER AND SYSTEMS - AREA C

0

09/11/2026

09/11/2026

100% CD Set

Published

E111D

LEVEL 01 PLAN - POWER AND SYSTEMS - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

E141A

ROOF PLAN - POWER AND SYSTEMS - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

E141D

ROOF PLAN - POWER AND SYSTEMS - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

E400

ELECTRICAL DETAILS

0

09/11/2026

09/11/2026

100% CD Set

Published

E500

ELECTRICAL DIAGRAMS

0

09/11/2026

09/11/2026

100% CD Set

Published

E600

ELECTRICAL SCHEDULES

0

09/11/2026

09/11/2026

100% CD Set

Published

Electrical

Page 3 of 4

Printed on Thu Oct 22, 2026 at 03:14 pm MDT

Exhibit A

BVSD Coal Creek ES

Palace Construction

Drawing Number

Drawing Title

Revision

Drawing Date

Received Date

Set

Status

E700

ELECTRICAL PANEL SCHEDULES

0

09/11/2026

09/11/2026

100% CD Set

Published

E701

ELECTRICAL PANEL SCHEDULES

0

09/11/2026

09/11/2026

100% CD Set

Published

ED101A

LEVEL 01 DEMOLITION PLAN - LIGHTING - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

ED101B

LEVEL 01 DEMOLITION PLAN - LIGHTING - AREA B

0

09/11/2026

09/11/2026

100% CD Set

Published

ED101C

LEVEL 01 DEMOLITION PLAN - LIGHTING - AREA C

0

09/11/2026

09/11/2026

100% CD Set

Published

ED101D

LEVEL 01 DEMOLITION PLAN - LIGHTING - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

ED111A

LEVEL 01 DEMOLITION PLAN - POWER AND SYSTEMS - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

ED111C

LEVEL 01 DEMOLITION PLAN - POWER AND SYSTEMS - AREA C

0

09/11/2026

09/11/2026

100% CD Set

Published

ED111D

LEVEL 01 DEMOLITION PLAN - POWER AND SYSTEMS - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

ED141A

ROOF DEMOLITION PLAN - POWER AND SYSTEMS - AREA A

0

09/11/2026

09/11/2026

100% CD Set

Published

ED141D

ROOF DEMOLITION PLAN - POWER AND SYSTEMS - AREA D

0

09/11/2026

09/11/2026

100% CD Set

Published

Page 4 of 4

Exhibit A

Printed on Fri Oct 23, 2026 at 03:35 pm MDT BVSD Coal Creek ES

Palace Construction

Current Specifications Number

Description

Revision

Issued Date

Received Date

Set

00 - Procurement and Contracting Requirements 00 00 00

COVER SHEET

2

09/11/26

09/11/26

100% CD Set

00 00 02

TABLE OF CONTENTS

2

09/11/26

09/11/26

100% CD Set

00 01 03

PROJECT DIRECTORY

0

09/11/26

09/11/26

100% CD Set

00 01 07

SEALS PAGE

0

09/11/26

09/11/26

100% CD Set

01 - General Requirements 01 10 00

SUMMARY

0

09/11/26

09/11/26

100% CD Set

01 20 00

PRICE AND PAYMENT PROCEDURES

0

09/11/26

09/11/26

100% CD Set

01 21 00

ALLOWANCES

0

09/11/26

09/11/26

100% CD Set

01 22 00

UNIT PRICES

0

09/11/26

09/11/26

100% CD Set

01 23 00

ALTERNATES

0

09/11/26

09/11/26

100% CD Set

01 25 00

SUBSTITUTION PROCEDURES

0

09/11/26

09/11/26

100% CD Set

01 25 00.01

SUBSTITUTION REQUEST FORM

0

09/11/26

09/11/26

100% CD Set

01 30 00

ADMINISTRATIVE REQUIREMENTS

0

09/11/26

09/11/26

100% CD Set

01 30 01

SUBMITTAL REQUIREMENTS

0

09/11/26

09/11/26

100% CD Set

01 30 01.01

SUBMITTAL CHECKLIST

0

09/11/26

09/11/26

100% CD Set

01 30 02

REQUEST FOR INTERPRETATION (RFI) REQUIREMENTS

0

09/11/26

09/11/26

100% CD Set

01 30 03

NON-CONFORMANCE REPORTS

0

09/11/26

09/11/26

100% CD Set

01 31 14

FACILITY SERVICES COORDINATION

0

09/11/26

09/11/26

100% CD Set

01 33 29.07

PROHIBITED CONTENT INSTALLER CERTIFICATION

0

09/11/26

09/11/26

100% CD Set

01 35 53

SECURITY PROCEDURES

0

09/11/26

09/11/26

100% CD Set

01 40 00

QUALITY REQUIREMENTS

0

09/11/26

09/11/26

100% CD Set

01 41 00

REGULATORY REQUIREMENTS

0

09/11/26

09/11/26

100% CD Set

01 42 16

DEFINITIONS

0

09/11/26

09/11/26

100% CD Set

01 42 19

REFERENCE STANDARDS

0

09/11/26

09/11/26

100% CD Set

01 45 33

CODE-REQUIRED SPECIAL INSPECTIONS AND PROCEDURES

0

09/11/26

09/11/26

100% CD Set

01 60 00

PRODUCT REQUIREMENTS

0

09/11/26

09/11/26

100% CD Set

01 61 16

VOLATILE ORGANIC COMPOUND (VOC) CONTENT RESTRICTIONS

0

09/11/26

09/11/26

100% CD Set

01 70 00

EXECUTION AND CLOSEOUT REQUIREMENTS

0

09/11/26

09/11/26

100% CD Set

01 74 19

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

0

09/11/26

09/11/26

100% CD Set

01 78 00

CLOSEOUT SUBMITTALS

0

09/11/26

09/11/26

100% CD Set

01 79 00

DEMONSTRATION AND TRAINING

0

09/11/26

09/11/26

100% CD Set

01 91 13

GENERAL COMMISSIONING REQUIREMENTS

0

09/11/26

09/11/26

100% CD Set

0

09/11/26

09/11/26

100% CD Set

0

09/11/26

09/11/26

100% CD Set

02 - Existing Conditions 02 41 00

DEMOLITION

07 - Thermal and Moisture Protection 07 42 13

METAL WALL PANELS

Page 1 of 4

Printed on Fri Oct 23, 2026 at 03:35 pm MDT

Exhibit A

BVSD Coal Creek ES

Palace Construction

Number

Description

Revision

Issued Date

Received Date

Set

07 53 00

ELASTOMERIC MEMBRANE ROOFING

0

09/11/26

09/11/26

100% CD Set

07 62 00

SHEET METAL FLASHING AND TRIM

0

09/11/26

09/11/26

100% CD Set

07 92 00

JOINT SEALANTS

0

09/11/26

09/11/26

100% CD Set

09 05 61

COMMON WORK RESULTS FOR FLOORING PREPARATION

0

09/11/26

09/11/26

100% CD Set

09 51 00

ACOUSTICAL CEILINGS

0

09/11/26

09/11/26

100% CD Set

09 65 00

RESILIENT FLOORING

0

09/11/26

09/11/26

100% CD Set

09 68 13

TILE CARPETING

0

09/11/26

09/11/26

100% CD Set

09 91 23

INTERIOR PAINTING

0

09/11/26

09/11/26

100% CD Set

FOOD SERVICE EQUIPMENT

0

09/11/26

09/11/26

100% CD Set

22 05 00

BASIC PLUMBING REQUIREMENTS

0

09/11/26

09/11/26

100% CD Set

22 05 03

THROUGH PENETRATION FIRESTOPPING

0

09/11/26

09/11/26

100% CD Set

22 05 05

PLUMBING DEMOLITION FOR REMODELING

0

09/11/26

09/11/26

100% CD Set

22 05 13

MOTORS

0

09/11/26

09/11/26

100% CD Set

22 05 16

PLUMBING EXPANSION COMPENSATION

0

09/11/26

09/11/26

100% CD Set

22 05 29

PLUMBING SUPPORTS AND ANCHORS

0

09/11/26

09/11/26

100% CD Set

22 05 30

ROOF SUPPORT

0

09/11/26

09/11/26

100% CD Set

22 05 53

PLUMBING IDENTIFICATION

0

09/11/26

09/11/26

100% CD Set

22 05 93

PLUMBING TESTING, ADJUSTING, AND BALANCING

0

09/11/26

09/11/26

100% CD Set

22 07 19

PLUMBING PIPING INSULATION

0

09/11/26

09/11/26

100% CD Set

22 09 00

INSTRUMENTATION

0

09/11/26

09/11/26

100% CD Set

22 10 00

PLUMBING PIPING

0

09/11/26

09/11/26

100% CD Set

22 10 23

NATURALGAS AND PROPANE PIPING

0

09/11/26

09/11/26

100% CD Set

22 10 30

PLUMBING SPECIALTIES

0

09/11/26

09/11/26

100% CD Set

22 30 00

PLUMBING EQUIPMENT

0

09/11/26

09/11/26

100% CD Set

22 40 00

PLUMBING FIXTURES

0

09/11/26

09/11/26

100% CD Set

09 - Finishes

11 - Equipment 11 40 00 22 - Plumbing

23 - Heating, Ventilating, and Air Conditioning (HVAC) 23 05 00

BASIC HVAC REQUIREMENTS

0

09/11/26

09/11/26

100% CD Set

23 05 03

THROUGH PENETRATION FIRESTOPPING.

0

09/11/26

09/11/26

100% CD Set

23 05 05

HVAC DEMOLITION FOR REMODELING

0

09/11/26

09/11/26

100% CD Set

23 05 13

MOTORS.

0

09/11/26

09/11/26

100% CD Set

23 05 15

VARIABLE FREQUENCY DRIVES

0

09/11/26

09/11/26

100% CD Set

23 05 29

HVAC SUPPORTS AND ANCHORS

0

09/11/26

09/11/26

100% CD Set

23 05 30

ROOF SUPPORT AND WIND BRACING

0

09/11/26

09/11/26

100% CD Set

23 05 48

HVAC VIBRATION ISOLATION

0

09/11/26

09/11/26

100% CD Set

23 05 53

HVAC IDENTIFIACTION

0

09/11/26

09/11/26

100% CD Set

23 05 93

TESTING, ADJUSTING, AND BALANCING

0

09/11/26

09/11/26

100% CD Set

23 07 13

DUCTWORK INSULATION

0

09/11/26

09/11/26

100% CD Set

23 07 19

HVAC PIPING INSULATION

0

09/11/26

09/11/26

100% CD Set

Page 2 of 4

Printed on Fri Oct 23, 2026 at 03:35 pm MDT

Exhibit A

BVSD Coal Creek ES

Palace Construction

Number

Description

Revision

Issued Date

Received Date

Set

23 09 00

CONTROLS

0

09/11/26

09/11/26

100% CD Set

23 09 13

INSTRUMENTATION.

0

09/11/26

09/11/26

100% CD Set

23 21 00

HYDRONIC PIPING

0

09/11/26

09/11/26

100% CD Set

23 21 16

HYDRONIC SPECIALTIES

0

09/11/26

09/11/26

100% CD Set

23 21 23

HVAC PUMPS

0

09/11/26

09/11/26

100% CD Set

23 31 00

DUCTWORK

0

09/11/26

09/11/26

100% CD Set

23 33 00

DUCTWORK ACCESORIES

0

09/11/26

09/11/26

100% CD Set

23 34 23

POWER VENTILATORS

0

09/11/26

09/11/26

100% CD Set

23 37 00

AIR INLETS AND OUTLETS

0

09/11/26

09/11/26

100% CD Set

23 51 00

BREECHINGS, CIMNEYS, AND STACKS

0

09/11/26

09/11/26

100% CD Set

23 52 16

CONDENSING BOILERS

0

09/11/26

09/11/26

100% CD Set

23 73 13

INDOOR MODULAR AIR HANDLING UNITS

0

09/11/26

09/11/26

100% CD Set

23 74 16.12

PACKAGED ROOFTOP AIR CONDITIONING UNOTS 25 TON AND BELOW

0

09/11/26

09/11/26

100% CD Set

23 74 23.13

GAS FIRED MAKE-UP AIR UNITS

0

09/11/26

09/11/26

100% CD Set

26 05 00

BASIC ELECTRICAL REQUIREMENTS

0

09/11/26

09/11/26

100% CD Set

26 05 03

THROUGH PENETRATION FIRESTOPPING..

0

09/11/26

09/11/26

100% CD Set

26 05 05

ELECTRICALDEMOLITION FOR REMODELING

0

09/11/26

09/11/26

100% CD Set

26 05 13

WIRE AND CABLE

0

09/11/26

09/11/26

100% CD Set

26 05 26

GROUNDING AND BONDING

0

09/11/26

09/11/26

100% CD Set

26 05 27

SUPPORTING DEVICES

0

09/11/26

09/11/26

100% CD Set

26 05 33

CONDUIT AND BOXES

0

09/11/26

09/11/26

100% CD Set

26 05 53

ELECTRICAL IDENTIFICATION

0

09/11/26

09/11/26

100% CD Set

26 05 73

POWER SYSTEM STUDY

0

09/11/26

09/11/26

100% CD Set

26 09 33

LIGHTING CONTROL SYSTEM

0

09/11/26

09/11/26

100% CD Set

26 20 00

SERVICE ENTRANCE

0

09/11/26

09/11/26

100% CD Set

26 22 00

DRY TYPE TRANSFORMERS

0

09/11/26

09/11/26

100% CD Set

26 23 00

LOW-VOLTAGE SWITCHGEAR

0

09/11/26

09/11/26

100% CD Set

26 24 16

PANELBOARDS

0

09/11/26

09/11/26

100% CD Set

26 27 26

WIRING DEVICES

0

09/11/26

09/11/26

100% CD Set

26 28 16

DISCONNECT SWITCHES

0

09/11/26

09/11/26

100% CD Set

26 43 00

SURGE PROTECTION DEVICES

0

09/11/26

09/11/26

100% CD Set

26 51 19

LED LIGHTING

0

09/11/26

09/11/26

100% CD Set

FIRE ALARM AND DETECTION SYSTEMS

0

09/11/26

09/11/26

100% CD Set

31 10 00

SITE PREPARATION

0

09/11/26

09/11/26

100% CD Set

31 20 00

TRENCHING, BACKFILLING, AND COMPACTING

0

09/11/26

09/11/26

100% CD Set

31 23 00

EARTHWORK, EXCAVATION, AND BACKFILL

0

09/11/26

09/11/26

100% CD Set

31 25 00

EROSION AND SEDIMENTATION CONTROL

0

09/11/26

09/11/26

100% CD Set

26 - Electrical

28 - Electronic Safety and Security 28 31 00 31 - Earthwork

32 - Exterior Improvements

Page 3 of 4

Exhibit A

Printed on Fri Oct 23, 2026 at 03:35 pm MDT BVSD Coal Creek ES

Palace Construction

Number

Description

Revision

Issued Date

Received Date

Set

32 05 05

SELECTIVE DEMOLITION FOR EXTERIOR IMPROVEMENTS

0

09/11/26

09/11/26

100% CD Set

32 05 23

CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS

0

09/11/26

09/11/26

100% CD Set

32 11 00

AGGREGATE BASE COURSE

0

09/11/26

09/11/26

100% CD Set

32 12 00

HOT MIX ASPHALT PAVEMENT

0

09/11/26

09/11/26

100% CD Set

32 13 00

CONCRETE PAVING

0

09/11/26

09/11/26

100% CD Set

32 13 73

CONCRETE PAVING JOINT SEALANTS

0

09/11/26

09/11/26

100% CD Set

32 16 00

CURBS, GUTTERS, SIDEWALKS, AND DRIVEWAYS

0

09/11/26

09/11/26

100% CD Set

32 17 00

SIGNING, STRIPING, AND STREET MARKING

0

09/11/26

09/11/26

100% CD Set

Page 4 of 4

Exhibit B Assumptions and clarifications made in preparing the GMP

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit B

BVSD Coal Creek ES - Clarifications & Exclusions General Clarifications & Exclusions Below are exclusions, clarifications, and assumptions. In addition to this list, please refer to the comments column within the direct cost worksheet for additional exclusions, assumptions, and clarifications. Estimate is based on the CD Drawings & Project Manual dated 09/11/2026 No Addenda provided prior to this estimate Excludes any Davis Bacon or Prevailing Wages Excludes building permit and plan review fees. Excludes ROW permits and fees. We assume that all site work will be private. Excludes all sales and use taxes for city, county, and state. Excludes any background checks or badging requirements. Excludes 3rd party inspections and testing of any kind. Excludes Furniture, FFE, Equipment Excludes removal or moving of any owner furniture or equipment that would impede our work. Palace and their subcontractors will provide a 2-year workmanship warranty for all scope. Excludes any specific M/WBE requirements or percentages. We have done a good faith effort to invite several M/WBE contractors to bid. Excludes any requirements for commissioning for Energy Star, NGBS, LEED, or similar certifications. Excludes any removal or testing of hazardous materials. Excludes drilling into surfaces identified as ACMs for anchoring purposes. We are not responsible for any delays due to hazardous material removal, which is the responsibility of the owner. Excludes brining any systems up to code that are outside of our scope of work. Excludes costs for power, water, and gas We assume that we can temporarily use the existing power, water and gas from the building during construction Excludes commissioning of any existing systems. Excludes window cleaning. None of our scope of work will cause the existing windows to get dirty. Excludes final/ALTA survey of any of the site improvements

Division 02 - Demo Excludes removal of hazardous materials. We assume owner will remove all hazardous materials. Includes recycling of Fluorescent bulbs and PCB Ballasts only. Light fixture housings to be explored as recycled content.

Division 03 - Concrete Division 04 - Masonry Division 05 - Steel

Exhibit B Division 06 - Rough Carpentry Division 07 - Thermal & Moisture Protection We exclude any repairs to any rated assemblies or sealants that are outside of our scope of work. When we open up ceilings, building inspector may require additional rated sealants to be added to existing conditions to pass inspection. We have priced the drip flashing at the outer edge of the soffit as 22 gauge pre-finished steel. We exclude the removal of the aluminum sill at the exterior soffits shown in detail 2/A151. The existing sill is to remain. We have included the roof patchwork as cold-applied for the built-up roof.

Division 08 - Openings Division 09 - Finishes Division 10 - Specialties Division 11 - Equipment Base bid does not include the replacement of the dishwasher. See Alternate #2B for the cost to replace the dishwasher. We exclude the replacement of the stainless steel countertops adjacent to the dishwasher. We have only included adjustments to the existing tops to accommodate the new dishwasher. Our bid assumes that the steamer is two smaller units that are stacked. It does not include two separate double stacked steamers.

Division 12 - Furnishings Division 13 - Special Construction Division 14 - Conveying Systems Division 21 - Fire Suppression Division 22 - Plumbing We have only included the removal of exposed piping for the condensate line associated with the removal of the mini-split in the electrical room. We will abandon unused condensate piping that is concealed within the walls or ceilings. We assume the existing carrier and plumbing rough-ins will be re-used for the new electric water cooler in Cafeteria/Commons 410 We assume that mega press fittings are an acceptable option for gas piping 2" and below. Gas specific mega press fittings will be used.

Division 23 - Heating, Ventilation & AC We assume raceways will be surface mounted for the new thermostat in electrical room 158 Excludes cleaning of any ducting except newly installed duct.

Division 26 - Electrical No power shown to the new fire damper at Electrical Room 158. We believe this may be needed so we have included a $4,000 allowance for it. We assume that existing boxes and conduits can be used for the upgraded lighting controls in Alternates #8 through #11. We assume that existing conduit can be re-used for the feeder replacements between the electrical panels and the new distribution panel

Exhibit B The specific items that need to maintain power during the electrical service replacement is undetermined at the time of this estimate. We have included a $10,000.00 allowance for temp power needs associated with the electrical service replacement. Excludes supply and install of TV wall mount or enclosure for TV, part of Alternate #3. The alternate only appears to call for the power and data to the new TV location. We assume the conduits and boxes will be surface mounted for the power and data to the new TV location. We assume the conduits and boxes will be surface mounted for the power to the reach-in fridge. We assume the power for the new TV location will come from panel LB.

Divisions 27 & 28 - Low Voltage, Life Safety, Security, We assume that BVSD will remove and re-install all security cameras for the replacement of the exterior soffits. Excludes any new emergency radio or Bi-directional Antenna Amplification systems or testing.

Division 31 - Earthwork Division 32 - Exterior Improvements Excludes local ROW permit for asphalt and site concrete work. We assumed this is private work and won't require any permits.

Division 33 - Utilities

Exhibit C Itemization of the GMP

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit C

BVSD Coal Creek ES - Renovation 801 W Tamarisk St Louisville, CO 80027 100% CD Estimate (GMP) Owner/Developer: Boulder Valley School District RE-2 6500 Arapahoe Road Boulder, CO 80303 Owner Representative: Stephen Henry - BVSD

Designed By: Treanor 1755 Blake St, Suite 400 Denver, CO 80202 Project Start: May-27 Project Finish: Aug-27 Duration in Months:

2.5

Bonding Required: Prevailing Wage Liquidated Damages: Taxes:

Yes No Per Contract Fully Exempt

TOTAL PROJECT COST: $1,791,166 PROJECT Cost per SF: Building SF:

Proposal Date:

$29.19 61,360

October 28, 2026

Prepared By: Palace Construction 7 S. Galapago Street Denver, CO 80223 Andy Del Grosso 720-456-0373 adelgrosso@palaceconst.com

Exhibit C BVSD Coal Creek ES - Renovation 100% CD Estimate (GMP)

COST SUMMARY WORKSHEET Direct Costs 02 00 00 03 00 00 04 00 00 06 00 00 07 00 00 09 00 00 11 00 00 22 00 00 23 00 00 26 00 00 27 00 00 28 00 00 32 00 00 33 00 00

10/28/2026

Gross Built Area: 61,360 SF

Existing Conditions Concrete Masonry Wood, Plastics & Composites Thermal and Moisture Protection Finishes Equipment Plumbing Heating Ventilation Air Conditioning Electrical Communications Electronic Safety & Security Exterior Improvements Utilities

General Requirements

Duration: 4 Months

Cost

$/sf

$44,125 $2,380 $13,900 $7,820 $130,495 $85,852 $70,545 $176,208 $466,229 $356,575 $0 $1,224 $109,894 $1,500 $1,466,747

$0.72

$23.90

$121,988

$1.99

$0 $0 $0 $0 $0

$0.00

$79,437 $0 $0 $79,437

$1.29

$83,409

$1.36

$1,751,581

$28.55

$16,640 $1,576 $21,369 $39,585

$0.27

$1,791,166 $399,197 $2,190,363

$29.19

$0.04 $0.23 $0.13 $2.13 $1.40 $1.15 $2.87 $7.60 $5.81 $0.00 $0.02 $1.79 $0.02

7%

Design, Permit, Taxes Building Permit Plan Review Fee Professional Design Services Use Tax

Contingency & Escalation Contractor Contingency Design Contingency Escalation Allowance

Fee

Not Included, By Owner Not Included, By Owner Not Included, By Others Not Included, By Owner

5.00% 0.00% 0.00%

5.00%

SUBTOTAL Insurances & Fees General Liability Insurance Builders Risk Insurance P&P Bonds

0.95% 0.09% 1.22%

TOTAL PROJECT BASE COST: ANTICIPATED ACCEPTED ALTERNATES ADJUSTED TOTAL WITH ALTERNATES: Alternates ALT 01 ALT 02A ALT 02B ALT 03 ALT 04 ALT 05A ALT 05B ALT 05C ALT 06 ALT 07 ALT 08 ALT 09 ALT 10 ALT 11

$0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $1.29

$0.03 $0.35 $0.65

$6.51 $35.70

Mill & Overlay existing lot, repaint striping Provide New Circuit Power to Existing Reach-in Fridges Provide New Dishwashing Unit in Kitchen Add Data to Alternate TV Location in Lobby New Floor Tile at Kinder Classrooms 100 & 105 New LVT at Corridors 172, 185, & 400 New Carpet Tile at Corridors 172, 185, & 400 New J&J Kinetex Floor Tiles at Corridors 172, 185, & 400 Add Destratification Fans in Gym Stripe Additional Games at Basketball Court Upgrade Classroom Lighting & Controls Upgrade Corridor/Entry Lighting & Controls Upgrade Other Student Space Lighting & Controls Upgrade Staff Area Lighting & Controls

$32,954 $4,836 $32,413 $1,548 $21,486 $29,305 $25,015 $27,978 $30,772 $2,258 $186,822 $39,214 $55,124 $17,062

Total of Anticipated Accepted Alternates (Green Highlighted)

$399,197

Exhibit C DIRECT COST WORKSHEET BVSD Coal Creek ES - Renovation 100% CD Estimate (GMP)

Project: Stage: Code

Cat

000000

Scope of Work

October 28, 2026

Qty

Unit $

Cost

Section

Division

$/sf

Comments

General Notes & Clarifications -

Construction Documents Estimate based on CD plans dated 09/11/2026 Estimate based on CD Project Manual Volumes 1-3 dated 09/11/2026 See comments section below and Exhibit B for assumptions, clarifications, and exclusions.

010000

DIRECT COST GENERAL REQUIREMENTS

015626 015626 E

Temporary Fencing Temp Chain Link Perimeter Fence & Gates

015639 015639 X

Temporary Tree and Plant Protection Tree Protection

1 ls

015713 015713 M 015713 L

Temporary Erosion and Sediment Control Erosion Control BMPs BMP Setup/Maintenance/Cleanup

1 ls 60 hr

$2,500.00 $65.00

$2,500 $3,900

017123 017123 S 017123 S 017123 S 017123 S

Field Engineering Surveying Base Bid Set Control Survey for Demo Survey Bike Pad & Basketball Court

1 ls 1 ls 1 ls 2 ea

$5,975.00 Included --Included --Included ---

$5,975

017419 017419 E 017419 S

Waste Management Waste Disposal Recycling Requirements

5 ea 1 ls

$500.00 $5,000.00

$2,500 $5,000

017423 017423 S 017423 X 017423 S

Final Cleaning Building Final Cleaning Window Cleaning Pressure Wash Sidewalks

$4,500.00 Excluded --$0.25

$4,500

020000

Existing Conditions

024113 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S

Selective Site Demolition Demolition Base Bid Site Demolition Demo Exterior Soffits Demo Existing Plumbing Systems Demo Existing HVAC Systems Demo Existing Electrical Systems Demo Concrete Boiler Housekeeping Pads Demo VCT Flooring & Base at Corridor 174 Grind Adhesives Demo Walk-off Carpet & Base in Vest. 173 Scrape Adhesives Demo Tile Flooring in Vest. 173 Grind Thinset Demo Gyp Ceiling in Electrical 158 Demo Gyp Ceiling in Electrical 146 Demo Ceiling Tiles for New Electrical, Salvage Demo Walls Around Electrical Panels - CMU Demo Walls Around Electrical Panels - Drywall Coring for New Roof Penetrations - 5"

$31,675 $3,840 480 lf

$8.00

$0.06

$3,840

At bike pad, basketball court. Excludes Parking lot $0

1 sf 1 ls 13,840 sf

Excluded

$0.00

---

Does not appear to be necessary $6,400

$0.10

$5,975

$0.10 R&R Engineering

$7,500

$0.12

$7,960

$0.13 No work associated with windows At areas affected by work

$3,460 $12,450 $12,450

1 ls 1 ls 1 ls 1 ls 1 ls 1 ls 240 sf 766 sf 766 sf 168 sf 168 sf 36 sf 36 sf 30 sf 72 sf 300 sf 7 ea 2 ea 4 ea

$7,250.00 Div 32 Div 07 Div 22 Div 23 Div 26 Included Included Included Included Included Included Included Included Included Included Div 04 Included Included

$0.52

$7,250 -------------------------------------

$0.20 $0.20 MP Contracting See division 32 for site demo items See division 07 metal panel section for soffit demo See division 22 for demo by plumber See division 23 for demo by mechanical See division 26 for demo by electrician

For new exhaust fan ducting For new electrical work CMU demo by mason

Direct Costs

Page 3

Exhibit C DIRECT COST WORKSHEET BVSD Coal Creek ES - Renovation 100% CD Estimate (GMP)

Project: Stage: Code

Cat

Scope of Work

024113 S 024113 S 024113 L

Coring for New Roof Penetrations - 9" Coring for Electrical Wall Penetrations - 5" Demo Assistance & Cleanup

030000

Concrete

033000 033000 S 033000 S 033000 S 033000 S 033000 S 033000 S

Cast-In-Place Concrete Concrete Base Bid 4" Housekeeping Pad at Water Heaters 4" Housekeeping Pads at Boilers (2 @ 74 SF Each) 4" Housekeeping Pad at Expansion Tanks 6x6 W2.1xW2.1 WWR in All Housekeeping Pads Dowels at Perimeter of Pads - #4 at 18" OC

040000

Masonry

042200 042200 S 042200 S 042200 S

Concrete Unit Masonry Masonry Base Bid Demo CMU at Electrical Panels CMU Patches at Electrical Panels

060000

Wood & Composites

061000 061100 M 061100 M 061100 M 061100 M 061100 S 061100 L

Rough Carpentry & Framing Rough Carpentry Base Bid Roof Curb Materials MAU & EF Truss 2x6 Blocking LUS26-2 Hangers MAU Duct Penetration Adjustments Build Roof Curbs & MAU/EF Supports

070000

Thermal & Moisture Protection

072200 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S 072200 S

Roofing & Roof Accessories Roofing Base Bid Patch Holes from Removed Boiler Flues 16" Patch Hole from Removed CU-2 Curb Patch Holes at Elec/Lineset Jacks Patch Holes from Removed Water Heater Flues 6" Remove Curb and Widen at Revised MAU-1 Flash in Curb at New MAU-1 Flash in Curb at New EF 24" Flash in New Boiler Vents 8" Flash in New Water Heater Vents 4" Jack & Flash New Elec & Gas Penetrations Curb Infill at MAU

074000 S 074100 S 074100 S 074100 S 074100 S 074100 S 074100 S 074100 S 074100 X

Metal Siding, Roofing, Flashing & Accessories Metal Panel Base Bid Demo Existing Gyp & Plywood Soffits - Level 1 Metal Soffit Panels - 22 ga - Perforated - Level 1 7/8" Hat Channell at 16" O.C. - 22 GA. Prefinished Drip Flashing Prefinished J Trim at Perimeter Caulk Perimeter Remove and Re-Install CCTV Devices

October 28, 2026

Qty

Unit $ 4 ea 3 ea 80 hr

Cost

Included --Included --$65.00

Section

Division

$2,380 $2,380.00 Included Included Included Included Included

$0.04 Centennial Asphalt & Concrete

-----------

Embedded 3" into existing concrete

$13,900 $13,900.00 Included --Included ---

$0.23 Paul R. Clark Masonry

$7,820

$1,000.00 $1,000.00 $20.00 $20.00 $1,500.00 $65.00

$1,000 $1,000 $1,000 $720 $1,500 $2,600

See curb support detail 3/S200 See curb support detail 3/S200

$17,154 $17,154.00 Included Included Included Included Included Included Included Included Included Included Included

1 ls 2730 sf 2730 sf 1 ls 1 ls 1763 lf 1 ls 1 ls

$96,562.00 Included Included Included Included Included $11,279.00 Excluded

$0.13 $0.13

$130,495

1 ls 2 ea 12 sf 3 ea 2 ea 1 ls 1 ls 1 ls 4 ea 4 ea 6 ea 1 ea

$0.23

$13,900

$7,820 1 ls 1 ls 50 ea 36 ea 1 ls 40 hr

$0.04

$2,380

$13,900

1 ls 7 ea 7 ea

Comments

$5,200 $2,380

1 ls 60 sf 148 sf 30 sf 238 sf 1 ls

$/sf

$2.13 $0.28 Douglass Colony

$17,154 -----------------------

Temp curb cover for MAU

$107,841 $96,562 -----------

Bighorn Metalworks 22 GA. - Berridge Vee Panel - Perforated - Standard Color

$11,279

Black Roofing

--Direct Costs

Page 4

Exhibit C DIRECT COST WORKSHEET BVSD Coal Creek ES - Renovation 100% CD Estimate (GMP)

Project: Stage: Code

Cat

Scope of Work

October 28, 2026

Qty

Unit $

Cost

Section

Division

Repair Damage at Metal Roof Panel ACM Caulk Removal

1 ea 1 ls

Excluded Excluded

079000 079000 M 079000 S 078400 S

Joint Sealants Building Caulking Site Caulking Firestop/Firecaulk

1 ls 1 ls 1 ls

$1,000.00 Div 32 --$4,500.00

-----

090000

Finishes

092116 092116 S 092116 S 092116 S 092116 S

Drywall Drywall Base Bid Drywall Ceiling at Elec. Rm. 146 Drywall Ceiling at Elec. Rm. 158 Wall Patches at MEP Replacements

1 ls 72 sf 72 sf 1 ls

$5,914.00 Included --Included --Included ---

$5,914

095100 095100 S

Acoustical Ceiling System ACT Remove & Replace at Corr. 185

1 ls

$2,000.00

$2,000

096000 096000 S 096000 S 096000 X 096000 S 096000 S 096000 S 096000 S 096000 S 096000 A 096000 L 096000 M

Floor Finishes Flooring Base Bid New LVT at Corridor 174 LVT Inlaid Logo Transitions at New LVT Walk-off Carpet at Vestibule 173 Rubber Base at Corridor 174 & Vest 173 Minor Floor Prep Moisture/pH Testing Required by Manufacturer Allowance - Additonal Flooring Floor Protection - Labor Floor Protection - Materials

1 ls 666 sf 1 ls 57 lf 34 sy 140 lf 970 sf 1 ls 1 ls 160 hr 6,500 sf

$11,238.00 Included Excluded Included Included Included Included Included $50,000.00 $65.00 $0.50

099100 099100 S 099100 S 099100 S 099100 S 099100 S

Painting Painting Base Bid Paint Walls at Replaced Electrical Panels Paint Wall in Cafeteria for EWC Replacement Paint Elec. 146 for Gear Replacement Paint Ceiling in Elec. 158 for EF Replacement

1 ls 1 ls 1 ls 1 ls 1 ls

$3,050.00 Included Included Included Included

110000

Equipment

114000 114000 S 114000 S 114000 S 114000 S 114000 S 114000 S 114000 S 114000 S 114000 S 114000 X 114000 X 114000 X

Food Service Equipment Food Service Equipment Base Bid New Double Stack Ovens w/ Casters, Gas Manifold, SSI-M Controls Flex Gas Line Heated Cabinet w/ Casters & Glass Doors New Double Stack 6 Pan Steamer w/ Equipment Stacking Stand, Drain Pans Demo of Old Equipment, Install of New New Dish Machine New Stainless Steel Tops At Dish Machine New Walk-in Cooler

$5,500

$0.09

$1,000 $4,500

Seal New Penetrations $85,852 $5,914

$1.40 $0.10 Independent Construction

$2,000

$0.03 For electrical feeder replacements

$74,888

$1.22 C3 Interiors

$11,238 ---------------

Logo no longer shown

$50,000 $10,400 $3,250 $3,050

$0.05 PDP Painting Corner-to-Corner of panel walls only Corner-to-Corner of Electric Water Coole wall only Paint Walls and Ceiling Corner-to-Corner of Ceiling only

$3,050 --------$70,545 $70,545

$70,545.00 Included Included Included Included Included Included Included Included Excluded Excluded Excluded

Comments Actual scope needed is undetermined Trace amounts of ACM caulk at soffits.

074100 X 074400 X

1 ls 1 ea 1 ls 1 ea 1 ea 1 ea 1 ls 2 ea 1 ea 1 ea 1 ea 1 ea

$/sf

$70,545 -----------------------

$1.15 $1.15 TriMark Blodgett DFG-100 K12 DBL T&S BRASS HG-4D-48K-PS Cres Cor H-137-WSUA-12D15A Sterling Steamer SP208-14-3

See Alternate #02B Not to be replaced in alternate Not to be included in base bid

Direct Costs

Page 5

Exhibit C DIRECT COST WORKSHEET BVSD Coal Creek ES - Renovation 100% CD Estimate (GMP)

Project: Stage: Code

Cat

Scope of Work

220000

Plumbing

220000 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S

Residential Plumbing Systems Plumbing Base Bid Demo Existing Water Heaters & Storage Tanks Demo Flue & Combustion Air Ducting Demo Recirc Pumps Demo Gas Piping on Roof & in Boiler Room Demo Electric Water Cooler New Water Heaters New Flues & Combustion Air Ducting New Recirc Pumps Revise Water Line & Valves at MAU New Gas Line to MAU New Gas Lines for Boilers & Water Heaters Add Valves and Pressure Regulators Replace Classroom Faucets Add Remote Mixing Valves New Electric Water Cooler Disconnect/Reconnect Gas for Ovens Insulation Where Required Controls For Domestic Water Housekeeping Pad for Water Heaters Housekeeping Pad for Expansion Tank

230000

HVAC

238000 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S

Heating/Cooling/Air HVAC Base Bid Demo Boilers & Associated Flues Demo Circulation Pumps Demo Makeup Air Unit Demo Existing Rooftop Curb Demo FCU-2 and CU-2 Mini-Split Demo Curb & Line Sets New Boilers New Circulation Pumps with VFDs New Boiler Flues and Combustion Air Ducting Roof Terminations Adjust Expansion Tank For New Housekeeping Pad New Neutralization Kit Insulated Blank Off Panel at Abandoned Louvers Break Metal at Existing Louver Opening Tie New Piping Into Existing Primary Loop New Makeup Air Unit MAU-1 New Rooftop Curb Connect to Existing Ductwork & Gas Line Gyp Board Layers in Curb Sealants in Curb New Rooftop Exhaust Fan EF-1 New Rooftop Curb Ductwork From Electrical Room to Fan 18x18 Transfer Grille to Corridor Fire/Smoke Damper Insulation Where Required Flush Hydronic Piping Before Start-up Testing, Adjusting, And Balancing

October 28, 2026

Qty

Unit $

Cost

Section

Division $176,208

$176,208 1 ls 2 ea 2 ea 2 ea 1 ls 1 ls 1 ls 2 ea 2 ea 1 ls 1 ls 1 ls 8 ls 30 ea 30 ea 1 ea 2 ea 1 ls 1 ls 54 sf 9 sf

$176,207.84 Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included included Div 03 Div 03

$2.87 ProCraft

-----------------------------------------

With integral storage tanks

By Concrete Contractor By Concrete Contractor

$466,229 $466,228.72 Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included

Comments

$2.87

$176,208

$466,229

1 ls 2 ea 2 ea 1 ea 1 ea 1 ea 1 ea 1 ls 2 ea 2 ea 2 ea 2 ea 2 ea 2 ea 2 ea 1 ls 1 ea 1 ea 1 ls 10 ea 1 ls 1 ea 1 ea 1 ls 1 ea 1 ea 1 ls 1 ls 1 ls

$/sf

$466,229 ---------------------------------------------------------

$7.60 $7.60 ProCraft

Interior side of louvers. U-value of .055 , +/- 60"x36" each Around perimeter of wall opening

Air transfer is going into rated wall

Direct Costs

Page 6

Exhibit C DIRECT COST WORKSHEET BVSD Coal Creek ES - Renovation 100% CD Estimate (GMP)

Project: Stage: Code

Cat

Scope of Work

238000 S 238000 S 238000 S

New Controls For Boilers, MAU, EF, Domestic Water Conduits & Boxes for Controls All Hoisting Required for Scope

260000

Electrical

261000 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 X 261000 S 261000 S 261000 A 261000 A 261000 X

Residential Electrical Systems Electrical Base Bid Demo Existing Panelboards Demo Existing Switchboard Demo Existing Transformers Demo Existing Feeders to Panels Recycle Demo'd Electrical Gear New Panelboards New Distribution Panel - MDC New Service Disconnect - MSD New Feeders to Panels (Copper) New Feeders & Conduits to MDC (Copper) All New Circuit Breakers at Replaced Panels New Disconnects to Mechanical Equipment New CO Detector in Boiler Room Connect New Gas Equipment to Existing EPOs All New Conductors in EMT MC Cable Only for Whips to Light Fixtures New Conduits for Panel Feeders Power to Mechanical Equipment Power System Studies Allowance - Temp Power for Service Replacement Allowance - Power & FA to Fire Damper Lighting Replacements

270000

Communications

271000 X 272000 X

Structured Cabling Data, AV, CCTV, Paging

280000

Electronic Safety & Security

281000 S 281000 S

Fire Alarm Systems Connect Boiler CO Alarm into FA System

320000

Exterior Improvement

321213 321213 S 321213 S 321213 S 321213 S 321213 S 321213 S 321213 S 321213 S 321213 S 321213 S 321213 S

Asphalt Paving Asphalt Paving Base Bid Mobilization Area 1 - Parking Lot Crack Seal Seal Coat Area 2 - Basketball Court Demo Existing Asphalt - 2" Demo Existing ABC Below Asphalt - 5" Scarify and Recompact 12" of Soil New ABC - 4" New Hot Mixed Asphalt - 3"

October 28, 2026

Qty

Unit $ 1 ls 1 ls 1 ls

Included Included Included

Cost

Section

Division

-------

$356,575 $342,575.08 Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Excluded Included Included $10,000.00 $4,000.00 Excluded

Comments By Albireo By Albireo

$356,575

1 ls 11 ea 1 ea 2 ea 11 ea 11 ea 1 ls 1 ea 1 ea 1 ls 1 ls 1 ls 1 ls 1 ls 1 ls 1 ls 1 ls 1 ls 1 ls 1 ls 1 ls 1 ls 1 ls

$/sf

$5.81 $5.81 Exceed Electrical Contracting

$342,575 ---------------------------------------

TR-EM1, TR-LA

HA, HB, HC, HD, LA, LA1, LB, LC, LD, EM, EM1

$10,000 $4,000

Not shown on drawings, but we believe it will be needed See alternates for lighting replacements

--$0

$0.00

$0 1 ls

Excluded

See Alternate #6 for data line to TV

--$1,224

$0.02

$1,224 1 ls

$1,224.00

Exceed Electrical Contracting

$1,224 $109,894 $36,509

1 ls 1 ls

$36,509.00 Included ---

1,030 lf 13,840 sy

Included Included

-----

540 sy 540 sy 540 sy 540 sy 540 sy

Included Included Included Included Included

-----------

$36,509

$1.79 $0.59 Centennial Asphalt & Concrete

Existing asphalt = 2" HMA + 6" ABC

Direct Costs

Page 7

Exhibit C DIRECT COST WORKSHEET BVSD Coal Creek ES - Renovation 100% CD Estimate (GMP)

Project: Stage: Code

Cat

Scope of Work

321723 321723 S 321723 S 321723 S 321723 S 321723 S 321723 S 321723 S 321723 X

Striping & Signage Striping Base Bid Area 1 - Parking Lot Re-Stripe Parking Spaces Stripe Directional Arrows One-Way Signs Area 1 - Basketball Court Stripe Basketball Lines Other Striping at Basketball Court

321600 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 X 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 L

Site Concrete Site Concrete Base Bid Mobilization Area 3 - Bike Pad Demo Existing Concrete Pad & Haul Off Scarify and Recompact 12" of Soil 4" ABC Below Concrete 5" Concrete Pad Dowel Into Existing ROW Sidewalk At New Electrical Service Demo Sidewalk for Electrical Service Excavate Trench for Underground Feeders Place & Compact 4" ABC Under Conduits Pour Concrete Encasement w/ Rebar Backfill & Compact Trench Haul off Spoils From Trench Pour Back Sidewalk New 6" Concrete Pad for Disconnect Layout & QAQC

323000 323000 S 323000 S 323000 S

Site & Street Furnishings Bike Racks Base Bid Remove & Salvage Existing Bike Racks New Bike Racks - Inverted U - Surface Mount

328000 328000 S 328000 S 328000 A

Landscaping Repair Sod at Access Point to Basketball Court Repair Sod & Irrigation at Bike Pad Replacement Allowance - Landscaping at Electrical Service

330000

Utilities

335000 335000 S

Other Utilities Private Locates

TOTALS

October 28, 2026

Qty

Unit $

Cost

Section

Division

$0 Included Included Included Included Included Included Included Excluded

1 ea 1 ea 1,640 sf 1,640 sf 1,640 sf 1,640 sf 1 ls

$33,442.00 Included Included Included Included Included Included Excluded

$0.00

-----------------

350 sf 1 ls 1 ls 1 ls 1 ls 1 ls 350 sf 12 sf 16 hr

Included Included Included Included Included Included Included Included $65.00

1 ls 1 ls 60 ea

$29,303.00 Included --Included ---

$29,303

$3.00 $1,750.00 $3,500.00

$4,350 $1,750 $3,500

$34,482

$0.56 Centennial Asphalt & Concrete

$33,442 -------------

Not sure if AHJ will allow that from private to public

----------------$1,040 $29,303

$0.48 Ground Solutions

$9,600

$0.16 Between gate and basketball court (west of existing bike pad) At new electrical service disconnect pad installed in berm $1,500

$1,500 2 ea

$750.00

Comments

Centennial Asphalt & Concrete

1 ls 1 ls 1 ls 4 ea 4 ea 1 ls 1 ls 1 ls

1,450 sf 1 ls 1 ls

$/sf

$0.02 $0.02

$1,500

$1,466,747

$1,466,747

Direct Costs

$1,466,747

$23.90

61,360 GSF

Page 8

Exhibit D Contract Schedule to be provided after amendment & change order for the GMP is executed

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

10/26/26

Exhibit D ID

Task Mode 1 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 2 3 4 5 6 7 27 28 29 30 31 49 50 51 52 53 54

Name

Coal Creek Elementary *** Palace - All Work Duration

Start

Finish

Resource Names4th Quarter Nov

Project Summary 191 days Procurement 140 days MAU 75 days MAU Submittal Review-2 Weeks 15 days Mau-10 to 12 weeks after approved submittal 60 days Boilers 75 days Boiler Submittal Review-2 Weeks 15 days Boilers-10 to 12 Weeks After Approved Submittal 60 days Water Heaters 75 days Water Heater Submittal Review-2 Weeks 15 days Water Heaters-10 to 12 Weeks After Approved Submittal 60 days Lighting and Controls 75 days Lighting Submittal Review-2 weeks 15 days Lights-8 to 12 Weeks After Approved Submittal 60 days Electrical Gear 140 days Electrical Gear Submittal Review-2 weeks 10 days Electrical Gear-22 to 26 Weeks After Approved Submittal 130 days Kitchen Equipment 75 days Kitchen Equipment Submittal Review-3 Weeks 15 days Kitchen Equipment-10 to 12 Weeks After Approved Submittal 60 days Milestones 51 days GMP Executed 1 day Notice-To-Proceed 1 day Start of Construction 1 day Substantial Completion 1 day Final Completion 1 day Construction 45 days Mobilize and BMP 1 day Mobilize onsite 1 day Site Temp Construction Fence 1 day Traffic Control 1 day Building Construction 45 days Interior 45 days Corridors 40 days Demo Flooring - Cor 6 days Salvage Base For Reuse - Cor 6 days Salvage Existing Television - Cor 1 day

Last Printed: 10/26/26 2:00 PM Coal Creek Elementary schedule 10-26-2026

11/3/26 11/3/26 2/8/27 2/8/27 3/1/27 2/8/27 2/8/27 3/1/27 2/8/27 2/8/27 3/1/27 2/8/27 2/8/27 3/1/27 11/3/26 11/3/26 11/17/26 2/8/27 2/8/27 3/1/27 5/24/27 5/24/27 5/24/27 5/24/27 7/29/27 8/4/27 5/24/27 5/24/27 5/24/27 5/24/27 5/24/27 5/24/27 5/24/27 5/24/27 5/24/27 5/24/27 5/25/27

8/4/27 5/21/27 5/21/27 2/26/27 5/21/27 5/21/27 2/26/27 5/21/27 5/21/27 2/26/27 5/21/27 5/21/27 2/26/27 5/21/27 5/21/27 11/16/26 5/21/27 5/21/27 2/26/27 5/21/27 8/4/27 5/24/27 5/24/27 5/24/27 7/29/27 8/4/27 7/27/27 5/24/27 5/24/27 5/24/27 5/24/27 7/27/27 7/27/27 7/20/27 6/1/27 6/1/27 5/25/27

Dec

1st Quarter Jan Feb

Mar

2nd Quarter Apr May

Jun

3rd Quarter Jul Aug

Sep

Treanor Palace

MAU Submittal Review-2 Weeks

Treanor Palace

Boiler Submittal Review-2 Weeks

Treanor Palace

Water Heater Submittal Review-2 Weeks

Treanor Palace

Lighting Submittal Review-2 weeks

Treanor Palace Treanor Palace

Dec

1st Quarter Jan Feb

Mau-10 to 12 weeks after approved submittal

Boilers-10 to 12 Weeks After Approved Submittal

Water Heaters-10 to 12 Weeks After Approved Submittal

Lights-8 to 12 Weeks After Approved Submittal Electrical Gear Submittal Review-2 weeks Electrical Gear-22 to 26 Weeks After Approved Submittal Kitchen Equipment Submittal Review-3 Weeks

Kitchen Equipment-10 to 12 Weeks After Approved Submit

Palace BVSD Palace Palace Palace

GMP Executed

Palace Palace Palace

Mobilize onsite

Demo Demo Palace

4th Quarter Oct Nov

Notice-To-Proceed Start of Construction Substantial Completion Final Completion

Site Temp Construction Fence Traffic Control

Demo Flooring - Cor Salvage Base For Reuse - Cor Salvage Existing Television - Cor

Page 1 of 4

10/26/26

Exhibit D ID

Task Mode 55 56 57 58 59 60 61 67 68 69 70 79 80 81 85 86 87 88 89 90 82 83 84 91 92 93 94 95 96 97 98

103 104 105 106 107 108

Name

Coal Creek Elementary *** Palace - All Work Duration

Start

Finish

Resource Names4th Quarter Nov

Install Carpet - Cor Install LVT Flooring - Cor Install Walkoff Mat - Cor Install Base - Cor Reinstall Television at New Location - Cor Demo existing light fixtures - Cor Install New Light Fixtures and Controls - Cor Electrical Room 146 Safe Off Electrical - 146 Install Temp Electrical Service - 146 R&R MDC - 146 Kitchen 407 Remove Ceiling Tiles for HVAC Work - Kit Disconnect Duct From Existing MAU - Kit Disconnect Gas From Kitchen Equipment - Kit Disconnect Electrical From Kitchen Equipment - Kit Remove Kitchen Equipment - Kit Install New Kitchen Equipment - Kit Connect gas to new equipment - Kit Connect Electrical to New Equipment - Kit Reconnect Duct to New MAU - Kit Mechanical Inspection - Kit Reinstall Ceiling Tiles - Kit Mechanical Room Demo Existing Boilers - Mech Demo Existing Water Heaters - Mech Form and Pour New Equipment Pads - Mech Concrete Cure Time - Mech Infill Existing Louver Openings Install New Boilers - Mech Install New Water Heaters - Mech Classrooms/Workrooms Demo Existing light Fixtures - CW Install New light Fixtures and Controls - CW Demo Existing Sink Faucets - CW Install New Faucets - CW Install Mixing Valves - CW

Last Printed: 10/26/26 2:00 PM Coal Creek Elementary schedule 10-26-2026

8 days 1 day 1 day 2 days 1 day 15 days 15 days 17 days 1 day 2 days 15 days 24 days 1 day 1 day 1 day 5 days 5 days 2 days 1 day 1 day 1 day 1 day 1 day 33 days 3 days 3 days 2 days 5 days 3 days 10 days 10 days 45 days 25 days 25 days 5 days 5 days 5 days

6/2/27 6/14/27 6/15/27 6/16/27 6/18/27 6/29/27 6/29/27 5/24/27 5/24/27 5/24/27 5/26/27 5/24/27 5/24/27 5/25/27 5/25/27 5/25/27 6/2/27 6/9/27 6/11/27 6/11/27 6/23/27 6/24/27 6/25/27 5/24/27 5/24/27 5/27/27 6/2/27 6/4/27 6/4/27 6/11/27 6/25/27 5/24/27 5/24/27 5/24/27 7/14/27 7/21/27 7/21/27

6/11/27 Flooring 6/14/27 Flooring 6/15/27 Flooring 6/17/27 Flooring 6/18/27 Palace 7/20/27 Electrician 7/20/27 Electrician 6/16/27 5/24/27 Electrician 5/25/27 Electrician 6/16/27 Electrician 6/25/27 5/24/27 Demo 5/25/27 Mechanical 5/25/27 Plumbing 6/1/27 Electrician 6/8/27 Demo 6/10/27 Specialty 6/11/27 Plumbing 6/11/27 Electrician 6/23/27 Mechanical 6/24/27 Palace 6/25/27 Ceiling Grid & Tile 7/9/27 5/26/27 Plumbing 6/1/27 Plumbing 6/3/27 Concrete 6/10/27 Palace 6/8/27 Palace 6/24/27 Plumbing 7/9/27 Plumbing 7/27/27 6/28/27 Electrician 6/28/27 Electrician 7/20/27 Plumbing 7/27/27 Plumbing 7/27/27 Plumbing

Dec

1st Quarter Jan Feb

Mar

2nd Quarter Apr May

Jun

3rd Quarter Jul Aug

Sep

Install Carpet - Cor

4th Quarter Oct Nov

Dec

1st Quarter Jan Feb

Install LVT Flooring - Cor Install Walkoff Mat - Cor Install Base - Cor Reinstall Television at New Location - Cor Demo existing light fixtures - Cor Install New Light Fixtures and Controls - Cor Safe Off Electrical - 146 Install Temp Electrical Service - 146 R&R MDC - 146 Remove Ceiling Tiles for HVAC Work - Kit Disconnect Duct From Existing MAU - Kit Disconnect Gas From Kitchen Equipment - Kit Disconnect Electrical From Kitchen Equipment - Kit Remove Kitchen Equipment - Kit Install New Kitchen Equipment - Kit Connect gas to new equipment - Kit Connect Electrical to New Equipment - Kit Reconnect Duct to New MAU - Kit Mechanical Inspection - Kit Reinstall Ceiling Tiles - Kit Demo Existing Boilers - Mech Demo Existing Water Heaters - Mech Form and Pour New Equipment Pads - Mech Concrete Cure Time - Mech Infill Existing Louver Openings Install New Boilers - Mech Install New Water Heaters - Mech Demo Existing light Fixtures - CW Install New light Fixtures and Controls - CW Demo Existing Sink Faucets - CW Install New Faucets - CW Install Mixing Valves - CW

Page 2 of 4

10/26/26

Exhibit D ID

Task Mode 62 63 64 65 66 73 74 75 71 72 99

100 101 102 76 77 78 109 110 111 112 113 114 116 117 118 119 120 115 121 122 123 124 125 126 127 128

Name

Coal Creek Elementary *** Palace - All Work Duration

Start

Finish

Resource Names4th Quarter Nov

Vestibule 173 Demo Flooring - 173 Salvage Base for Reuse - 173 Install Walkoff Mat - 173 Install Base - 173 Kindergarten 100 and 105 Demo Flooring - 105 Install LVT Flooring - 105 Electrical Panels R&R Electrical Panels - 146 Electrical Room 158 Demo Mini Split System - 158 Install Exhaust Fan and duct work - 158 Install New Electrical Circuit to Exhaust Fan - 158 Cafeteria/Commons 410 Demo Dual Drinking Fountain - 410 Install New Drinking Fountain - 410 Exterior Roof Disconnect Gas From Existing MAU - R Disconnect Electrical From Existing MAU - R Remove Existing MAU - R Structural Framing For New Roof Curbs - R Install New Roof Curbs - R Install New Flashing at Roof Curbs - R Install Drywall and insulation in MAU Roof Curb - R Install New MAU - R Reconnect Electrical to New MAU - R Remove Condensing Unit and Roof Curb - R Install New Exhaust Fan - R Install Boiler and Water Heater Flues Through Roof - R Roofing Repairs - R Soffit Salvage All Fixtures and Devices at Exterior Soffit - Ext Demo Exterior Gyp Board Soffit and Plywood - Ext Repair Damaged Roof Panel - Ext Install Hat Channel at Soffit - Ext

Last Printed: 10/26/26 2:00 PM Coal Creek Elementary schedule 10-26-2026

12 days 1 day 1 day 1 day 1 day 11 days 2 days 3 days 15 days 15 days 4 days 1 day 2 days 1 day 2 days 1 day 1 day 30 days 30 days 1 day 1 day 2 days 5 days 2 days 1 day 2 days 10 days 1 day 1 day 1 day 2 days 5 days 15 days 2 days 3 days 1 day 3 days

6/2/27 6/2/27 6/2/27 6/16/27 6/17/27 6/3/27 6/3/27 6/15/27 6/17/27 6/17/27 6/24/27 6/24/27 6/25/27 6/29/27 7/12/27 7/12/27 7/13/27 5/24/27 5/24/27 5/24/27 5/24/27 5/25/27 5/26/27 6/3/27 6/7/27 6/8/27 6/10/27 6/23/27 6/24/27 6/24/27 6/25/27 6/29/27 6/2/27 6/2/27 6/7/27 6/10/27 6/11/27

6/17/27 6/2/27 6/2/27 6/16/27 6/17/27 6/17/27 6/4/27 6/17/27 7/8/27 7/8/27 6/29/27 6/24/27 6/28/27 6/29/27 7/13/27 7/12/27 7/13/27 7/6/27 7/6/27 5/24/27 5/24/27 5/26/27 6/2/27 6/4/27 6/7/27 6/9/27 6/23/27 6/23/27 6/24/27 6/24/27 6/28/27 7/6/27 6/22/27 6/3/27 6/9/27 6/10/27 6/15/27

Dec

1st Quarter Jan Feb

Mar

2nd Quarter Apr May

Jun

3rd Quarter Jul Aug

Sep

Demo Demo Flooring Flooring

Demo Flooring - 173

Demo Flooring

Demo Flooring - 105

4th Quarter Oct Nov

Install Walkoff Mat - 173 Install Base - 173

Install LVT Flooring - 105 R&R Electrical Panels - 146

Mechanical Mechanical Electrician

Demo Mini Split System - 158

Plumbing Electrician Mechainical Framing Mechainical Roof Framing Mechanical Electrician Mechanical Mechanical Plumbing Roof Electrician Demo Siding Framing

1st Quarter Jan Feb

Salvage Base for Reuse - 173

Electrician

Plumbing Plumbing

Dec

Install Exhaust Fan and duct work - 158 Install New Electrical Circuit to Exhaust Fan - 158 Demo Dual Drinking Fountain - 410 Install New Drinking Fountain - 410

Disconnect Gas From Existing MAU - R Disconnect Electrical From Existing MAU - R Remove Existing MAU - R Structural Framing For New Roof Curbs - R Install New Roof Curbs - R Install New Flashing at Roof Curbs - R Install Drywall and insulation in MAU Roof Curb - R Install New MAU - R Reconnect Electrical to New MAU - R Remove Condensing Unit and Roof Curb - R Install New Exhaust Fan - R

Install Boiler and Water Heater Flues Through Roof Roofing Repairs - R Salvage All Fixtures and Devices at Exterior Soffit - Ext Demo Exterior Gyp Board Soffit and Plywood - Ext Repair Damaged Roof Panel - Ext Install Hat Channel at Soffit - Ext

Page 3 of 4

10/26/26

Exhibit D ID

Task Mode

129 130 32 36 37 38 39 40 41 42 43 44 45 46 47 48 33 34 35 131 132 137 133 136 134 135 138 140 139 141 142 143 144

Name

Coal Creek Elementary *** Palace - All Work Duration

Start

Finish

Resource Names4th Quarter Nov

Install Soffit Panels - Ext Exterior Caulking at Soffit - Ext Site Improvements Area 2 Demo Basketball Court Asphalt - 2 Scarify and Recompact Subgrade - 2 Install Road Base Layer - 2 Asphalt Paving - 2 Basketball Court Striping - 2 Area 3 Remove and Salvage Bike Racks - 3 Demo Concrete Paving - 3 Scarify and Recompact Subgrade - 3 Install Road Base Layer - 3 Pour New Concrete Paving - 3 Install New Bike Racks - 3 Area 1 Crack Seal and Seal Coat Parking Lot - 1 Parking Lot Striping - 1 Project Closeout & Final Inspections Start-up & Inspection Electrical Final Inspections Start-up of Mechanical Systems Mechanical Final Inspections Palace Punch Final Building Clean Plumbing Final Inspections Final Fire Inspections Building Final for CO Punch Lists Owner Punch Walk Complete Owner Punch List Corrections Owner Final Walk & Project Acceptance

Last Printed: 10/26/26 2:00 PM Coal Creek Elementary schedule 10-26-2026

3 days 2 days 10 days 10 days 2 days 1 day 1 day 1 day 1 day 7 days 1 day 1 day 1 day 1 day 1 day 2 days 4 days 3 days 1 day 18 days 14 days 1 day 1 day 1 day 5 days 3 days 1 day 1 day 1 day 5 days 1 day 3 days 1 day

6/16/27 6/21/27 5/25/27 5/25/27 5/25/27 5/27/27 5/28/27 6/1/27 6/8/27 5/25/27 5/25/27 5/26/27 5/27/27 5/28/27 6/1/27 6/2/27 6/2/27 6/2/27 6/7/27 7/12/27 7/12/27 7/21/27 7/12/27 7/13/27 7/19/27 7/26/27 7/28/27 7/28/27 7/29/27 7/29/27 7/29/27 7/30/27 8/4/27

6/18/27 6/22/27 6/8/27 6/8/27 5/26/27 5/27/27 5/28/27 6/1/27 6/8/27 6/3/27 5/25/27 5/26/27 5/27/27 5/28/27 6/1/27 6/3/27 6/7/27 6/4/27 6/7/27 8/4/27 7/29/27 7/21/27 7/12/27 7/13/27 7/23/27 7/28/27 7/28/27 7/28/27 7/29/27 8/4/27 7/29/27 8/3/27 8/4/27

Dec

1st Quarter Jan Feb

Mar

2nd Quarter Apr May

Jun

3rd Quarter Jul Aug

Sep

4th Quarter Oct Nov

Siding Sealants

Install Soffit Panels - Ext

Demo Asphalt Asphalt Asphalt Striping

Demo Basketball Court Asphalt - 2

Demo Demo Concrete Concrete Concrete Specialty

Remove and Salvage Bike Racks - 3

Asphalt Striping

Electrician Mechanical Palace Palace Cleaning Plumbing Palace Palace BVSD Palace BVSD

Dec

1st Quarter Jan Feb

Exterior Caulking at Soffit - Ext

Scarify and Recompact Subgrade - 2 Install Road Base Layer - 2 Asphalt Paving - 2 Basketball Court Striping - 2

Demo Concrete Paving - 3 Scarify and Recompact Subgrade - 3 Install Road Base Layer - 3 Pour New Concrete Paving - 3 Install New Bike Racks - 3 Crack Seal and Seal Coat Parking Lot - 1 Parking Lot Striping - 1

Electrical Final Inspections Start-up of Mechanical Systems Mechanical Final Inspections Palace Punch Final Building Clean Plumbing Final Inspections Final Fire Inspections Building Final for CO Owner Punch Walk Complete Owner Punch List Corrections Owner Final Walk & Project Acceptance

Page 4 of 4

Exhibit E Insurance Certificates to be provided after amendment & change order for the GMP is executed

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit F Performance Bond to be provided after amendment & change order for the GMP is executed

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit G Labor and Materials Payment Bond to be provided after amendment & change order for the GMP is executed

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit H Alternates prices not used for the amendment

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit H Schedule of Alternates Coal Creek Elementary School Renovation

 Alternate No. 01 – Mill and Overlay Sta! Parking Lot  Total added cost to the base cost in the GMP = $32,954.00  Alternate No. 02A – New Electrical Circuit to Existing Reach-in Fridge  Total added cost to the base cost in the GMP = $4,836.00  Alternate No. 02B – Replace Dishwashing Machine in Kitchen  Total added cost to the base cost in the GMP = $32,413.00  Alternate No. 03 – Add Power and Data to New TV Location  Total added cost to the base cost in the GMP = $1,548.00  Alternate No. 04 – Replace Flooring in Kindergarten Classrooms 100 and 105  Total added cost to the base cost in the GMP = $21,486.00  Alternate No. 05A – Replace Corridor Flooring with New LVT  Total added cost to the base cost in the GMP = $29,305.00  Alternate No. 05B – Replace Corridor Flooring with New Carpet Tiles  Total added cost to the base cost in the GMP = $25,015.00  Alternate No. 05C – Replace Corridor Flooring with New J&J Kinetex Flooring  Total added cost to the base cost in the GMP = $27,978.00  Alternate No. 06 – Add Destratification Fans to the Gymnasium  Total added cost to the base cost in the GMP = $30,772.00  Alternate No. 07 – Add Additional Striping to Basketball Court  Total added cost to the base cost in the GMP = $2,258.00 1|Pa ge

Exhibit H  Alternate No. 08 – Replace Lighting and Controls in Classrooms  Total added cost to the base cost in the GMP = $186,822.00  Alternate No. 09 – Replace Lighting and Controls in Corridors and Entry  Total added cost to the base cost in the GMP = $39,214.00  Alternate No. 10 – Replace Lighting and Controls in Other Student Spaces  Total added cost to the base cost in the GMP = $55,124.00  Alternate No. 11 – Replace Lighting and Controls in Sta! Spaces  Total added cost to the base cost in the GMP = $17,062.00

2|Pa ge

Exhibit I Unit prices not used for this amendment

Not Applicable No unit prices provided for this contract

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit J Allowances

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit J Allowances Coal Creek Elementary School Renovation

 Additional Flooring Replacements. = $50,000.00  Temporary Power for Electrical Service Replacement. = $10,000.00  Power & Fire Alarm to New Fire Damper = $4,000.00  Landscape & Irrigation Repairs at New Electric Service = $3,500.00

1|Pa ge

Exhibit K Not Applicable

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit L Equipment rental rate schedule

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit L

PALACE EQUIPMENT RENTAL RATES Unit of Measure Jobsite Trailer Delivery Setup / TieDowns (8) Dismantle/Return

Range/ Notes

2025

2026

2027

Rate

Rate $675 $415 $890 $1,000

Denver Metro Area Denver Metro Area Denver Metro Area

$660 $410 $870 $994

Rate $670 $415 $890 $1,000

Denver Metro Area

$150 $95 $320

$155 $100 $325

$160 $100 $325

$3,963 $2,463 $221 $882

$4,042 $2,513 $232 $882

$4,050 $2,525 $235 $882

$852 $596 $220

$855 $600 $220

per month

Storage Containers 40 Ft Container 20 Ft Container Delivery/Return

per month per month per trip

Skid Steer TR310 Skid Steer Case 60XT Skid Steer Delivery/Return Sweeper Attachment

per month per month per trip per month

Utility Vehicles Gator Utility Vehicle Golf Cart Delivery/Return

per month per month per trip

Denver Metro Area

$827 $579 $200

per Day Per Week per trip

plus fuel cost plus fuel cost Denver Metro Area

$207 $806 $200

$213 $830 $200

$215 $830 $200

per day per week per trip

plus fuel cost plus fuel cost Denver Metro Area

$223 $690 $200

$229 $710 $200

$230 $710 $200

Denver Metro Area

$2,200

$2,300

$2,300

Diesel Air Compressor Delivery/Return Diesel Dingo

Superintendent Truck

plus fuel cost plus fuel cost Denver Metro Area

Water Trailer

per day per week per month

plus fuel cost plus fuel cost plus fuel cost

$145 $450 $900

$145 $450 $900

$145 $450 $900

Dump Trailer

per day per week per month

Denver Metro Area Denver Metro Area Denver Metro Area

$235 $680 $1,380

$235 $680 $1,380

$235 $680 $1,380

plus cost of driver

$212

$233

$235

Intrusive Testing Trailer

Day

450 Trash/Dump Truck

per trip

Exhibit L

PALACE EQUIPMENT RENTAL RATES 2025

2026

2027

Rate

Rate

Rate

$333 $1,089 $2,400

$366 $1,198 $2,400

$370 $1,200 $2,400

per month per month per month

$445 $230 $170

$445 $230 $175

$445 $230 $175

per day per week per month

$85 $398 $1,430

$87 $410 $1,430

$87 $410 $1,430

per day per week per month

$16 $64 $133

$16 $66 $137

$17 $66 $137

per month per trip

$2,700 $380

$2,800 $380

$2,800 $380

per month per month per month per month

$80 $210 $190 $400 $200

$80 $210 $190 $400 $200

$80 $210 $190 $400 $200

Per LF Per LF/Month

$2.35 $0.70

$2.35 $0.70

$2.35 $0.70

Unit of Measure Flat Bed Truck

Scaffold (per section) Stair scaffold Frame scaffold Baker scaffold Temporary Heat Flagero Heater

Concrete Blankets (ea)

Solar powered Trailer w/ 2 Cameras Tower and camera rental delivery / pickup Security Cameras outdoor Bullet Camera Outdoor Dome multi-sensor camera Horn and Alarm Monitoring Onetime installation fee Solar Battery Pole Mount Cell service Temporary Fencing Install/Removal 12 Foot Panels

per day per week per month

Range/ Notes includes fuel, add cost of driver

Exhibit M General Conditions of the Contract

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

BOULDER VALLEY SCHOOL DISTRICT RE-2 BOULDER, COLORADO

GENERAL CONTRACT CONDITIONS BOND PROGRAM

GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT.................................................................................................... 2 GC 1.00

CONTRACT DOCUMENTS AND DEFINITIONS ............................................................................................................ 1

GC 2.00

REFERENCE STANDARDS .......................................................................................................................................... 2

GC 3.00

DRAWINGS AND SPECIFICATIONS ............................................................................................................................ 2

GC 4.00

ROYALTIES AND PATENTS ........................................................................................................................................ 3

GC 5.00

ITEMS COVERED BY CONTRACT PRICE ..................................................................................................................... 3

GC 6.00

EXECUTION, CORRELATION, INTENT, AND INTERPRETATION OF CONTRACT DOCUMENTS ...................................... 3

GC 7.00

MATERIALS, LABOR, FACILITIES, AND STORAGE....................................................................................................... 4

GC 8.00

PERFORMANCE AND PAYMENT BONDS ................................................................................................................... 5

GC 9.00

PERMITS AND COMPLIANCE WITH STATUTES, RULES, AND REGULATIONS .............................................................. 6

GC 10.00

SURVEYS, BENCHMARKS, MONUMENTS, STAKES, AND MEASUREMENTS ............................................................... 6

GC 11.00

CHANGED CONDITIONS ........................................................................................................................................... 7

GC 12.00

PROTECTION OF PERSONS, WORK AND PROPERTY ................................................................................................. 7

GC 13.00

WORK ON EXISTING BUILDINGS .............................................................................................................................. 8

GC 14.00

CONTRACTOR’S SUPERINTENDENCE AND SUPERVISION .......................................................................................... 8

GC 15.00

SUBSTITUTIONS ....................................................................................................................................................... 9

GC 16.00

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES ................................................................................................. 9

GC 17.00

CASH ALLOWANCE................................................................................................................................................. 10

GC 18.00

EXPEDITING MATERIALS ........................................................................................................................................ 10

GC 19.00

BLASTING .............................................................................................................................................................. 11

GC 20.00

SOIL TEST REPORT ................................................................................................................................................. 11

GC 21.00

HAZARDOUS MATERIALS ....................................................................................................................................... 11

GC 22.00

DAMAGE TO UTILITIES ........................................................................................................................................... 11

GC 23.00

CHANGES IN THE WORK ........................................................................................................................................ 12

GC 24.00

CLAIMS FOR EXTRA COST....................................................................................................................................... 13

GC 25.00

DELAYS AND EXTENSIONS OF TIME ....................................................................................................................... 13

GC 26.00

ACCESS TO WORK .................................................................................................................................................. 14

GC 27.00

CORRECTION OF WORK ......................................................................................................................................... 14

GC 28.00

OWNER’S RIGHT TO CARRY OUT WORK ................................................................................................................. 16

GC 29.00

OWNER’S RIGHT TO TERMINATE CONTRACT ......................................................................................................... 16

GC 30.00

CONSTRUCTION SCHEDULE AND PROGRESS REPORTS ........................................................................................... 16

GC 31.00

SCHEDULE OF VALUES ........................................................................................................................................... 17

GC 32.00

PAYMENT .............................................................................................................................................................. 17

GC 33.00

INSURANCE ........................................................................................................................................................... 19

GC 34.00

SEPARATE CONTRACTS .......................................................................................................................................... 23

GC 35.00

SUBCONTRACTORS ................................................................................................................................................ 23

GC 36.00

RELATIONS OF CONTRACTOR AND SUBCONTRACTOR ........................................................................................... 24

GC 37.00

CONTRACTORS’ MUTUAL RESPONSIBILITY ............................................................................................................ 25

GC 38.00

CUTTING, PATCHING, AND EXCAVATING ............................................................................................................... 25

GC 39.00

EMPLOYEES ........................................................................................................................................................... 26

GC 40.00

CLEANING UP......................................................................................................................................................... 27

GC 41.00

USE OF PREMISES .................................................................................................................................................. 27

GC 42.00

OCCUPANCY .......................................................................................................................................................... 27

GC 43.00

TEMPORARY OR TRIAL USAGE ............................................................................................................................... 28

GC 44.00

TESTING OF BUILDING SYSTEMS ............................................................................................................................ 28

GC 45.00

LIQUIDATED DAMAGES FOR DELAY IN COMPLETION ............................................................................................. 28

GC 46.00

ACCEPTANCE AND FINAL PAYMENT ....................................................................................................................... 28

GC 47.00

WARRANTIES ON PORTIONS OF THE WORK .......................................................................................................... 29

GC 48.00

CONTRACTOR’S PROJECT GUARANTEE AFTER COMPLETION ................................................................................. 30

GC 49.00

MISCELLANEOUS KEYS, SWITCHES, ETC. ................................................................................................................ 30

GC 50.00

INDEMNIFICATION ................................................................................................................................................ 30

GC 51.00

LABOR DISPUTES ................................................................................................................................................... 31

GC 52.00

LIMITATION OF ACTIONS ....................................................................................................................................... 31

GC 53.00

PREFERENCE FOR COLORADO LABOR, MATERIALS, AND RESIDENT BIDDERS ........................................................ 31

GC 54.00

SALES AND USE TAX............................................................................................................................................... 31

GC 55.00

LIENS ..................................................................................................................................................................... 32

GC 56.00

OWNER’S INSPECTION OF CONTRACTOR’S RECORDS ............................................................................................ 32

GC 57.00

CERTIFICATION BY CONTRACTOR REGARDING PREMISES ACCESS ......................................................................... 32

GC 58.00

CONTRACTOR SAFETY RESPONSIBILITIES ............................................................................................................... 32

GC 59.00

CONTRACTOR ASBESTOS MANAGEMENT AND LEAD PAINT RESPONSIBILITIES ...................................................... 35

GC 60.00

ARCHITECT’S STATUS AND INSPECTIONS ............................................................................................................... 35

GC 61.00

ORAL STATEMENTS................................................................................................................................................ 35

GC 62.00

PROJECT SIGN ........................................................................................................................................................ 36

GC 63.00

HISTORICAL DATA .................................................................................................................................................. 36

GC 64.00

ASSIGNMENT ......................................................................................................................................................... 36

GC 65.00

TIME OF THE ESSENCE ........................................................................................................................................... 36

GC 66.00

DISPUTES ............................................................................................................................................................... 36

GC 67.00

SURVIVAL .............................................................................................................................................................. 36

GC 1.00

CONTRACT DOCUMENTS AND DEFINITIONS

All Work under the Construction Agreement shall be accomplished in accordance with the Contract Documents, which shall consist of the Request for Qualifications, Request for Proposals, Proposal(s), Notice of Award, Notice to Proceed, Performance Bond, Labor and Material Payment Bond, Construction Agreement, General Contract Conditions, Supplementary Conditions, Asbestos Management Plan Contractor Responsibility Form, Drawings and Specifications, tests and engineering data, approved Change Orders, Contractor’s Requests for Payment, Architect’s Certificates, and all addenda issued by the Owner or Architect prior to execution of the Construction Agreement and all modifications issued by the Owner or Architect after execution of the Construction Agreement. With respect to the Contract Documents, the following definitions and understandings shall control: 1.01 “Contract” or “Contract Documents” shall include all of the items enumerated in GC-1.00 above. 1.02 “Owner” shall mean Boulder Valley School District No. RE-2, and shall include its duly authorized representatives. 1.03 “Contractor” shall mean the corporation, company, partnership, firm, entity, or individual named and designated as such in the Construction Agreement, and any persons or entities acting on its behalf. 1.04 “Subcontractor” shall mean any corporation, partnership, entity, or individual having a direct contract with the Contractor or another subcontractor for performing Work and/or furnishing labor or material on the Project covered by the Contract. 1.05 “Architect” shall mean the corporation, partnership, entity or individual named and designated as “architect” or “engineer” in the Construction Agreement, and any persons or entities acting on the Architect’s behalf and within the scope of the particular duties properly entrusted to them in each case. In the event that there is no Architect on the Project, then “Architect” shall refer to Owner and its duly authorized representative. 1.06 “Notice to Contractor” shall be deemed to have been duly served if made in writing and delivered in person to the individual or to a member of the firm or to an officer of the corporation for which it is intended, or if sent by registered or certified mail, to Contractor’s last known business address. 1.07 “The Work” shall mean the construction and services required by the Contract Documents for completion of the Project, and includes all labor, materials, equipment and services provided or to be provided by the Contractor to fulfill the Contractor’s obligations, whether on or off the Project site, and all labor, materials equipment and services provided or to be provided by subcontractors, sub-subcontractors, or any other entity for whom the Contractor is responsible. 1.08 “The Project” is the total construction designed by the Architect of which the Work performed under the Contract Documents may be the whole or a part. 1.09 The “date of final completion” and “finally completed” shall mean the date when construction is certified by the Architect to be finally completed in accordance with the Contract Documents, as modified by any Change Orders processed under the terms of GC-23.00 below and when the Owner has fully accepted the Project for the use for which it was intended. Such date will be set forth on a letter of acceptance issued by the Owner. 1.010 “Drawings” or “plans” shall mean all (a) drawings furnished by the Owner and/or Architect as a basis for the award of Contract and for construction of the Project; (b) supplementary drawings furnished by the Owner and/or Architect to clarify and to define in greater detail the intent of the Contract drawings and specifications; (c) drawings submitted by the successful Contractor as may be required after the Contract is awarded; (d) drawings furnished by the Owner and/or Architect to the Contractor during the progress of the Work; and (e) engineering data and drawings submitted by the Contractor during the progress of the Work, provided such drawings are acceptable to the Architect and Owner. 1

1.011 “Specifications” are the written technical information concerning materials, components, systems, equipment, and manner of installation as indicated on the drawings or plans and which state the quality, performance, and characteristics to be achieved by application of construction methods. 1.012 “Change Order” shall mean a written order to the Contractor signed by the Owner or its authorized agent issued after the execution of the Construction Agreement, authorizing a change in the Work and/or adjustment in the Guaranteed Maximum Price (“GMP”) or the contract time schedule. Each adjustment in the GMP resulting from a Change Order shall clearly separate the amount attributable to the Cost of the Work and the Contractor’s Fee. 1.013 “day” or “days” shall mean calendar days. In computing a period of days, when the ending date is not specified, the first day is excluded and the last day is included. If any deadline falls on a Saturday, Sunday, or federal or Colorado state holiday, such deadline will be extended to the next day that is not a Saturday, Sunday or federal or Colorado state holiday. GC 2.00

REFERENCE STANDARDS

2.01 Reference to the standards of any technical society, organization, or association, or to codes of local or state authorities, shall mean the latest standard, code, specification, or tentative standard adopted and published as of the date of execution of the Construction Agreement, unless specifically stated otherwise. GC 3.00

DRAWINGS AND SPECIFICATIONS

3.01 Ownership of Drawings. All drawings, specifications, and copies thereof furnished by the Architect are the property of the Architect and the Owner, whether or not the Work for which they are made is performed, and are not to be used on other Work except by written agreement with the Architect and the Owner. 3.02 Figured Dimensions to Govern. Dimensions and elevations shown on the drawings shall be accurately followed. No Work shown on the drawings, the dimensions of which are not indicated, shall be executed until necessary dimensions have been obtained from the Architect. 3.03 Contractor to Check Drawings and Schedules. The Contractor shall check and verify all dimensions, elevations, and quantities shown on the drawings and furnished to it by the Architect, and shall notify the Architect of any discrepancy between the drawings and the conditions on the ground, or any error or omission in drawings, or in the layout as given by stakes, points, or instructions that it may discover. Before ordering any material or doing any Work, the Contractor shall verify all measurements concerning the Project and shall be responsible for the correctness of same. No extra charge or compensation shall be allowed on account of any difference between actual dimensions and the measurements indicated on the drawings. Any difference that may be found shall be submitted to the Architect for consideration and written determination before proceeding with the Work. The Contractor shall not be allowed to take advantage of any error or omission in the drawings or Contract Documents. Full written instructions shall be furnished by the Architect should such error or omission be discovered, and the Contractor shall carry out such instructions as if originally specified. 3.04 Detail Drawings and Instructions. The Architect shall furnish with reasonable promptness additional instructions, by means of drawings or otherwise, necessary for the proper execution of the Work. All such drawings and instructions shall be consistent with the Contract Documents. The Work shall be executed in conformity with the Architect’s drawings and instructions, and the Contractor shall do no Work without proper drawings and instructions. 3.05 Drawings and Specifications Available on the Site. The Contractor shall maintain at the Project site for the Owner and the Architect a Project record set of drawings, including addenda, approved shop drawings, Change Orders, and other modifications, with all changes or deviations from the original drawings neatly marked thereon in a contrasting color. The Contractor shall also maintain a Project record set of specifications at the 2

Project site, noting therein by appropriate section the names, models, and other distinguishing characteristics of the materials actually incorporated into the Work. This Project record set of drawings and specifications shall be updated daily as the Project progresses and shall be made available to the Owner and Architect for inspection at all times. Upon final completion of the Work and before final payment, three (3) copies and one (1) electronic of this Project record set of drawings and specifications shall be delivered to the Owner. One (1) copy of this Project record set of drawings and specification shall be delivered to the Architect. 3.06 Laws and Regulations. The Contractor shall give all notices and comply with all laws, ordinances, rules, and regulations bearing on the conduct of the Work as drawn and specified. If the Contractor observes that the drawings and specifications are at variance therewith, it shall promptly notify the Architect in writing, and any necessary adjustments shall be made as provided in the Contract for changes in the Work. If the Contractor performs any Work knowing it to be contrary to such laws, ordinances, rules, or regulations without giving the required notice to the Architect and receiving a written directive to proceed, it shall bear all costs arising therefrom and to correct and/or remedy same. GC 4.00

ROYALTIES AND PATENTS

The Contractor shall pay all royalties and license fees. The Contractor shall defend all suits or claims for infringement of patent rights and shall hold the Owner harmless from any and all liability or loss on account thereof. If the Contractor has information that the process or article specified involves the infringement of a patent, it shall be responsible for any and all liability or loss resulting therefrom unless it promptly furnishes such information to the Architect in writing. GC 5.00

ITEMS COVERED BY CONTRACT PRICE

5.01 Items Supplied by Owner. Owner shall supply the following items for the Project: a. Building Permit; b. Initial Survey; c. Materials Testing Including Soil Testing; d. Third Party Inspections; e. Commissioning; and f. Test and Balance as Required for Commissioning. 5.02 Items Supplied by Contractor. Unless specifically stated otherwise, the Contractor shall accept the compensation stated in the Construction Agreement as full payment for furnishing all the materials, transportation, apparatus, temporary structures, equipment, services, fuel, energy, light, water, labor and tools, and all other things necessary for the complete and proper execution of the Work contemplated by or reasonably implied from the Contract Documents, within the time limits indicated therein. Such amount shall include any loss or damage resulting from the nature of the Work, from the elements or from any unforeseen difficulties that may be encountered; all risks of every description connected with the prosecution of the Work; all expenses incurred in consequence of any suspension or discontinuance of the Work; and all other amounts necessary for completing the Work pursuant to the Contract Documents within the time limits indicated therein. GC 6.00

EXECUTION, CORRELATION, INTENT, AND INTERPRETATION OF CONTRACT DOCUMENTS

6.01 Execution. The Construction Agreement and other Contract Documents shall be signed in multiple copies as directed by the Owner. Within ten (10) days of Notice of Award, the Contractor shall submit to the Owner a minimum of five (5) fully executed original sets of the Construction Agreement; Performance Bond, and Labor and Material Payment Bond with original Power of Attorney; and certificates of required insurance coverage. The date of the Contract for purposes of these documents shall be the date of the Notice of Award letter. The Owner shall execute the Construction Agreement, assemble all copies, and distribute the Contract Documents. The Contractor shall not commence the Work until it receives the Notice to Proceed. All bonds and insurance 3

certificates shall be submitted to the Owner prior to the award of the first subcontract. 6.02 Correlation. By executing the Construction Agreement, the Contractor represents that it has visited the Project site, familiarized itself with the local conditions under which the Work is to be performed, and correlated its observations with the requirements of the Contract Documents. 6.03 Intent. The intention of the Contract Documents is to include all labor and materials, tools, equipment, construction equipment, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution and completion of the Work. Materials or Work described in words that, as applied, have a well-known technical or trade meaning shall be held to refer to such recognized meaning. The organization of the specifications into divisions, sections, and articles, as the case may be, and the arrangement of drawings shall not control the Contractor in dividing the Work among subcontractors or in establishing the extent of Work to be performed by any trade. It is intended that even though Work is not covered under any heading, division, section, article, branch, class, or trade of the specifications, it shall nevertheless be supplied if it is required elsewhere in the Contract Documents or is reasonably inferable therefrom as being necessary to produce the intended results. The specifications and drawings are intended to supplement but not necessarily duplicate each other. Any Work exhibited in the one and not in the other shall be executed as if it had been set forth in both, so that the Work will be constructed according to the complete design as determined by the Architect. 6.04 Interpretation. Should anything necessary for a clear understanding of the Work be omitted from the specifications and drawings, or should the requirements appear to be in conflict, the Contractor shall secure written interpretations or instructions from the Architect before proceeding with the Work affected thereby. The Contractor shall secure written interpretations or instructions by submitting the Owner’s form Request for Interpretation to the Architect. Oral requests shall not be acknowledged by the Architect or Owner. Additional costs incurred by the Owner as a result of unnecessary requests made by the Contractor, as determined by the Owner, shall be the responsibility of the Contractor. It is understood and agreed that the Work shall be performed according to the true intent of the Contract Documents. 6.05 Conflict in Interpretation. In the case of discrepancy or in the event of a conflict between the different Contract Documents, the documents shall take precedence in the following order: a. Change Orders; b. Written Amendments to Construction Agreement (including, if applicable, the GMP); c. Construction Agreement; d. General Conditions; e. Drawings and specifications; and f. Bid Documents, including addenda. Where two or more of the Contract Documents are complementary, the more detailed provision shall control over the more general provision. GC 7.00

MATERIALS, LABOR, FACILITIES, AND STORAGE

7.01 Contractor’s Responsibility. Unless otherwise agreed in writing, the Contractor shall provide and pay for all materials, labor, tools, equipment, machinery, transportation, and other facilities necessary for the proper execution and completion of the Work. The Contractor shall provide and pay for all the temporary facilities required to supply all the power, light, water, and heat needed by it and its subcontractors for their Work and shall install and maintain all such facilities in such manner as to protect the public and workers and to conform with any applicable laws and regulations. If temporary heat and/or protection is required for the expeditious prosecution of the Work and before the permanent heating apparatus is available for use, the temporary heating apparatus shall be installed and operated in such a manner that the finish Work and/or construction will not be damaged thereby. Unless otherwise specified, the Contractor shall pay for all the power, light, and water used by it and its subcontractors, without regard to whether such items are metered by temporary or permanent meters. The cutoff date on permanent meters shall be either the agreed date of full occupancy by 4

the Owner or the date of final acceptance of the Project, whichever shall be the earlier date. Upon completion of the Work, the Contractor shall remove all surplus materials, tools and such temporary facilities and structures, furnished by the contractor from the Project site. All debris and rubbish caused by the operations of the contractor shall be removed, and the area occupied during construction activities shall be restored to its original condition, within 48 hours of project completion, unless otherwise directed by the municipality or owner’s representative. 7.02 Materials. Unless otherwise specified, all materials shall be new and both Workmanship and materials shall be of the highest quality. The Contractor shall furnish satisfactory evidence to the Owner as to the kind and quality of materials. Samples shall be furnished, when specified, and the Work shall be in accordance with those samples that have been approved. 7.03 Toilet Facilities. The Contractor shall provide and maintain, in a neat and sanitary condition, adequate temporary toilet facilities for the use of any and all employees engaged on the Work, in strict compliance with the requirements of all applicable codes, regulations, laws, and ordinances. In no event may present toilet facilities of any existing building at the site of the Work be used by employees of the Contractor or its subcontractors. Upon final completion of the Work, the Contractor shall remove all such temporary facilities from the site and disinfect the premises. 7.04 Facilities and Storage. The Contractor shall provide suitable temporary facilities and quarters for workers, as needed, and shall maintain on premises water-tight storage sheds or tool houses for storage of building materials and tools that could be damaged by weather. The Contractor shall allow space for the erection of sheds and provide similar facilities for storage by subcontractors of their materials and tools. Storage of materials shall be confined to the site. These facilities or quarters shall further provide for protection against theft and damage of building materials and tools. Upon final completion of the Work, the Contractor shall remove all such temporary facilities from the site. 7.05 Office Space. The Contractor shall provide adequate, weatherproofed, heated and well- lighted office space at the site of the Work, for use by the Architect and the Owner and their representatives. The Contractor shall also provide telephone service at such office, which shall be available for use by the Architect, the Owner, and their representatives without charge, except for toll calls. 7.06 Quality and Location of Facilities. All of the foregoing facilities shall be of a quality and placed in locations acceptable to the Architect and the Owner. GC 8.00

PERFORMANCE AND PAYMENT BONDS

8.01 Required Bonds. The Contractor shall, within ten (10) days from the Notice of Award furnish bonds to the Owner in the full amount of the contract price, covering both the faithful performance of the Contract and the payment of all obligations for labor and materials arising thereunder, on such customary forms as the Owner may prescribe and with such sureties as it may approve. The amount of the bonds shall be increased, if necessary, to reflect approved changes in the Work that result in an increase in the total cost of the Work plus the Contractor’s fees. Such bonds shall be duly executed by a qualified surety licensed to do business in the State of Colorado, conditioned upon the true and faithful performance of the Contract, and shall provide that if the Contractor or its subcontractors fail to duly pay for any labor, materials, or other supplies used or consumed by such Contractor or its subcontractors in the performance of the Work contracted to be done, the surety will pay the same in an amount not exceeding the sum specified in the bond, as adjusted by approved Change Orders, and together with interest as provided by law. The performance bond shall additionally guarantee that the Contractor shall remedy any omissions, correct any and all defects, and adjust and make operable all component parts of Work falling under the requirements of the Contract that may be called to the Contractor’s attention within a period of twenty-four (24) months following the date of the letter of acceptance.

5

8.02 Additional Bond Requirements. The premium for all bonds shall be paid by the Contractor and included in the bid price in the bid proposal. The Owner will accept and approve bonds written by sureties legally authorized to write such bonds in the State of Colorado, provided such surety companies are rated in Best’s Insurance Guide (latest edition), not lower than A- or have Best’s Financial Rating of at least X. If, at any time a surety on such a bond becomes irresponsible or loses its right to do business in the State of Colorado, new bonds shall be provided by an alternate surety licensed to do business in the State and meeting the requirements of this Section 8.00. GC 9.00

PERMITS AND COMPLIANCE WITH STATUTES, RULES, AND REGULATIONS

9.01 Permits. Any local permits, governmental fees, and licenses necessary for the proper execution and completion of the Work shall be secured and paid for by the Contractor. Owner will pay for and secure building permit from Colorado Division of Fire Prevention and Control. Easements for permanent structures or permanent changes in existing facilities shall be secured and paid for by the Owner, unless otherwise specified in writing. The Owner is generally exempt from paying any fee for any building permit issued by any building departments or agencies located in Boulder, Broomfield, and Gilpin Counties, and the Contractor shall see that no building permit fee is paid. The Owner shall negotiate and provide for all electrical, gas, water, and sewer mains for the Contractor’s connections. The Contractor shall arrange with the utility company for actual connection, make necessary connections, and pay for all associated inspection fees and permits as required by any government agency. In addition, the Contractor shall furnish all material and items required to complete all connections. The Contractor shall call for all inspections on a timely basis by any agency having jurisdiction over the Work. 9.02 Compliance with Statutes, Rules and Regulations. The Contractor and all subcontractors shall comply with all applicable federal and state statutes, rules, regulations, and directives of the State Division of Fire Prevention and Control, and other governmental body having jurisdiction over the work to be performed. If any of the provisions of the Contract Documents are in conflict therewith, such portions shall be considered stricken and the applicable statute, ordinance, regulation, or ruling substituted therefor. All such cases of apparent conflict coming to the attention of any party shall immediately be called to the attention of the Owner. The Contractor shall strictly observe and comply with all federal and state laws pertaining to the employment and payment of labor. GC 10.00

SURVEYS, BENCHMARKS, MONUMENTS, STAKES, AND MEASUREMENTS

10.01 Surveys. As provided by the Owner, the Contractor shall obtain from the Architect a copy of all surveys describing property lines, elevation benchmarks, physical characteristics, and utility locations. 10.02 Benchmarks. The Contractor shall properly stake out the Work and provide and rigidly set benchmarks and batter boards as necessary for the proper performance of the Work. The Contractor shall remain responsible for their maintenance and their accuracy. A permanent benchmark, approved as to location and type by the Architect, from which all grades are to be taken, shall be established near the site of the Work by the Contractor. From this benchmark the Contractor shall ascertain all grades and levels to Project buildings as needed. The Contract Documents shall include all necessary information to establish the benchmark. 10.03 Preservation of Monuments and Stakes. The Contractor shall carefully preserve all monuments, benchmarks, property markers, reference points, and stakes. In case of the destruction thereof, the Contractor shall be charged with the expense of replacement and shall be responsible for any mistake or loss of time that may be caused. Permanent monuments and/or benchmarks that must be removed or disturbed shall be protected until properly referenced for relocation. The Contractor shall furnish all materials, labor and assistance for the proper replacement of such monuments and benchmarks. 10.04 Measurements. Before ordering any material or performing any Work, the Contractor shall verify all measurements on the Project and shall be responsible for the accuracy of same. No extra charge or 6

compensation shall be allowed because of any difference between actual dimensions and the measurements indicated in the drawings or specifications. Any discrepancies shall be submitted to the Architect and Owner for consideration before proceeding with the Work. GC 11.00

CHANGED CONDITIONS

The Contractor shall promptly, and before such conditions are disturbed, notify the Owner and the Architect in writing of: (1) sub-surface or latent physical conditions at the Project site differing materially from those indicated in the Contract Documents, or (2) unknown physical conditions at the Project site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in Work of the character provided for in the Contract Documents. The Owner and the Architect shall promptly investigate the conditions, and if the Owner finds that such conditions do so materially differ and cause an increase or decrease in the cost of or the time required for performance of the Work, an equitable adjustment shall be made and the Contract modified in writing accordingly. Any claim of the Contractor for adjustment hereunder shall not be allowed unless it has given notice as required. GC 12.00

PROTECTION OF PERSONS, WORK AND PROPERTY

12.01 Building Exits and Barricades. During the course of construction, the Contractor shall keep all required building exits free and unimpeded. Such exits shall not be closed at any time for any reason while the building is occupied or at any time when the building is unoccupied, except after written approval is given by the Owner and proper warning and directional signs are posted. Barricades shall be erected so that traffic is separated and protected from the construction. 12.02 Precautions. The Contractor shall take all necessary precautions to ensure the safety of all employees and other persons on the Project or who may be affected by the Contractor’s Work thereon. The Contractor shall also take all necessary precautions to protect the Work and all temporary facilities, as well as materials, tools, and equipment incorporated therein or to be incorporated therein from damage or destruction, whether in storage on or off the Project site and whether in the custody or control of the Contractor or any of its subcontractors. The Contractor shall also take all necessary precautions to protect all property at the Project site and adjacent thereto not designated for removal, relocation or replacement, including trees, shrubs, lawns, walks, pavements, roadways, structures, and utilities. 12.03 OSHA Compliance. The Contractor shall comply with all applicable provisions of the Occupational Safety and Health Administration (“OSHA”) and all laws, ordinances, rules, regulations, and orders of all governmental agencies or authorities having jurisdiction to protect the safety of employees and/or other persons who may be affected by the Work. The Contractor shall erect and maintain all necessary safeguards to protect workers on the Project site and the owners and users of adjacent property, and shall post danger signs and other warnings against hazards created by the Work including but not limited to protruding nails, hoists, well holes, elevator shafts, hatchways, scaffolding, window openings, stairways, excavations, and falling materials. The Contractor shall designate a responsible employee at the Project site as a safety officer to ensure the Contractor’s compliance with this section. Said employee shall be the Contractor’s superintendent unless otherwise designated in writing by the Contractor to the Owner and the Architect. 12.04 Contractor’s Liability. The Contractor shall be liable for all injury, damage or loss to any person or property caused in whole or in part by the Contractor, any of its subcontractors, or any person employed by or under the direction of the Contractor or any of its subcontractors. To the extent possible and unless otherwise directed by the Owner or Architect, the Contractor shall promptly repair, pay for or otherwise remedy any such injury, damage or loss and shall indemnify and hold harmless the Owner against any and all liability, claims, damages, losses and expenses arising therefrom. The terms of this section shall not apply in the case of injury, damage or loss proximately caused by the acts or omissions of the Owner and/or Architect and not attributable to any fault or negligence of the Contractor.

7

12.05 Emergencies. In the event of an emergency that threatens the safety or life of any person or threatens to damage or destroy the Project and/or any Work, materials, equipment or property thereon or to be used thereon, the Contractor shall act at its discretion to prevent such injury, death, damage or destruction. The Contractor shall immediately notify the Owner and Architect in writing of any such emergency and any action taken by the Contractor in response thereto. Any compensation due the Contractor for such emergency action shall be determined by agreement of the Contractor, Owner and Architect, and an appropriate Change Order shall be issued therefor. GC 13.00

WORK ON EXISTING BUILDINGS

13.01 Protection of Occupants. In addition to all other requirements of the Contract Documents, if the Work involves an addition or alteration to an existing building, the Contractor shall erect and maintain during the progress of the Work suitable dustproof partitions to protect such building and the occupants thereof. If necessary, in the Owner’s or Contractor’s judgment or pursuant to manufacturer’s directives or recommendations in order to protect occupants from noxious fumes, odors, or hazardous substances, the Contractor may be required to provide additional ventilation and/or work different or extended hours to avoid disruption to other activities within the existing building. Contractor shall protect and keep from harm all occupants of an existing building from construction activities, and shall include a safe pathway into and out of the school. 13.02 Partitions and Scheduling. If any portions of an existing building are to be remodeled or repaired, such portions shall be adequately partitioned off with dustproof partitions and well ventilated. All remodeling Work shall be scheduled and submitted to the Owner and Architect for approval. The various contractors shall schedule their Work jointly, in order that each may accomplish its Work within such existing building in an orderly fashion during regular school vacation periods where possible, or in such a manner as to permit full use of the building and without impairment of any existing facilities. 13.03 Existing Systems. Existing building systems, such as fire alarm, temperature controls and air distribution, security systems, public announcement systems, irrigation systems, and the like, shall be demonstrated and noted by Owner to the Contractor as operational prior to Contractor’s commencing the Work and Contractor may participate in observation of such systems. Such systems are the responsibility of the Contractor to maintain in pre-construction condition. GC 14.00

CONTRACTOR’S SUPERINTENDENCE AND SUPERVISION

14.01 Superintendent. During the progress of the Work, the Contractor shall ensure that a competent superintendent and any necessary assistants, all satisfactory to the Architect and the Owner, are on the Project site at all times while Work is in progress. The superintendent shall not be changed by the Contractor except with the written consent of the Architect and the Owner, unless the superintendent ceases to be in the Contractor’s employ. The superintendent shall represent the Contractor on the Project and all directions given to him/her shall be as binding as if given to the Contractor. The Architect and the Owner shall not be responsible for the acts or omissions of the superintendent or his/her assistants. 14.02 Supervision. The Contractor shall provide full-time, qualified, and efficient supervision of the Work, using competent skill and attention. The Contractor is responsible for determining and supervising all temporary and permanent erection and construction sequences, techniques, means, or methods. The Contractor shall direct, schedule, coordinate the Work to ensure that all parts fit together properly and in accordance with the Contract Documents. The Contractor shall carefully study and compare all Contract Documents and other instructions and shall at once report to the Architect and the Owner any error, inconsistency, or omission that Contractor may discover. 14.03 Additional Supervision Duties. The Contractor shall see that the Work is carried out in accordance with the Contract Documents and in a thorough and first-class manner in every respect. The Contractor shall 8

provide engineering, surveying, and coordination to accurately establish all lines, levels, and marks necessary to facilitate the operations of all parties involved in the Contractor’s Work. The Contractor shall lay out the Work in a manner satisfactory to the Architect, making permanent records of all lines and levels required for excavation, grading, and foundations, and for all other parts of the Work. The Contractor shall be responsible for the commencement and the proper completion of the various stages and sequences of construction. The Contractor shall strictly adhere to the approved construction schedule. GC 15.00

SUBSTITUTIONS

The Contractor shall be held to have used in its base proposal and to furnish under the Contract those items of equipment and/or materials that are specifically identified in the plans and specifications by a manufacturer’s name, model, or catalog number. Items of equipment and/or materials of the Contractor’s choice may be offered as alternates to the items named in the plans and specifications by submitting, with the proposal and on the form provided, identifying data on the articles proposed together with a statement of the amount of addition or deduction from the base bid if the bidder’s alternate is accepted. Prior approval by the Architect is not required on items submitted as alternate bids. After execution of the Construction Agreement, substitution of equipment and/or materials of makes other than those specifically named in the Contract Documents may be approved by the Owner so long as the equipment or material proposed for substitution in the opinion of the Owner is just as suitable as the equipment and/or materials named in the plans and specifications so far as performance, construction, efficiency, and utility are concerned. A request for substitution shall ordinarily be required to be based upon one or more of the following grounds: the specified equipment or material is no longer available, a substitution will improve lead time, quality will be improved (documented detail required), or the Owner will incur substantial savings. All requests for substitution must be submitted in writing with supporting documentation by or through the Contractor to the Architect for initial review and recommendation before being submitted to the Owner for evaluation and final approval. In the absence of the Owner’s written approval, no substitution of equipment or materials shall be allowed for any items specified in the Contract Documents. In case of a difference in price, occurring as a result of an approved substitution, the Owner shall receive all benefit of the difference in cost involved in the substitution. All approved substitutions shall be documented by the issuance of a formal Change Order as provided in these General Conditions. GC 16.00

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

16.01 Shop Drawings. “Shop drawings” are drawings, diagrams, illustrations, schedules, performance charts, brochures, manufacturer’s literature, and other data that are prepared by the Contractor or any subcontractor, manufacturer, supplier, or distributor, and that illustrate some portion of the Work. Shop drawings shall be submitted in both hard copy and electronic format. 16.02 Samples. “Samples” are physical examples furnished by the Contractor to the Owner and/or Architect to illustrate materials, finishes, equipment, or Workmanship, and to establish standards by which the Work will be judged. 16.03 Product Data. “Product data” are illustrations, standard schedules, performance charts, instructions, brochures, diagrams and other information furnished by the Contractor to illustrate materials or equipment for some portion of the Work. Product data shall be submitted in both hard copy and electronic format. 16.04 Contractor’s Obligations. The Contractor shall review, approve, stamp an then submit to the Architect shop drawings, product data, samples, and similar submittals required by the Contract Documents with reasonable promptness and in such a sequence as to cause no delay in the Work or in the activities of the Owner or of separate contractors. Shop drawings, product data, samples, and similar submittal required by the Contract Documents shall properly identify specified items. At the time of submission, the Contractor shall inform the Architect in writing of any deviation in the shop drawings, product data, or samples from the requirements of the Contract Documents. Substitutions will be allowed only in accordance with the provisions of GC-15.00. The number of copies and format of submittal shall be as required by the Architect, but, at a 9

minimum, shall include three (3) copies and one (1) electronic copy of the original shop drawings and product data for the Owner. 16.05 Verification. By approving and submitting shop drawings, product data, and samples, the Contractor thereby represents that it has determined and verified all field measurements, field construction criteria, dimensions, elevations, quantities, materials, catalog numbers, and similar data, as shown on the drawings and specifications furnished by the Architect, or will do so, and that it has checked and coordinated each shop drawing, product data, and sample with the requirements of the Work and of the Contract Documents. 16.06 Architect /Owner Review. The Architect shall review and approve shop drawings, product data, and samples with reasonable promptness so as to cause no delay, but only for conformance with the design concept of the Project and with the information given in the Contract Documents. The Architect’s approval of a separate item shall not indicate approval of any assembly in which the item functions. Upon the final completion of the Work, the Contractor shall furnish to the Architect two corrected copies of all shop or setting drawings showing the as-built condition of the Work. The Architect, after review, shall submit one of these copies to the Owner. 16.07 Corrections. The Contractor shall make any corrections required by the Architect and shall resubmit the required number of corrected copies of shop drawings or new samples until approved by the Architect. The Contractor shall direct specific attention in a separate writing or on resubmitted shop drawings to revisions other than the corrections requested by the Architect on previous submissions. 16.08 Contractor’s Responsibility. The Architect’s approval of shop drawings, product data, or samples shall not relieve the Contractor of responsibility for any deviation from the requirements of the Contract Documents unless the Contractor has informed the Architect in writing of such deviation at the time of submittal and the Architect has given written approval of the specific deviation. The Architect’s approval shall also not relieve the Contractor from responsibility for errors or omissions in the shop drawings, product data, or samples. 16.09 Architect Approval Required. No portion of the Work requiring the submission of a shop drawing, product data, or sample shall be commenced until such submittal has been approved in writing by the Architect. All such portions of the Work shall be in accordance with approved shop drawings, product data, and samples. All material finishes and samples shall be approved at one time. The Contractor shall submit all items requiring approval of finishes, color, material, etc., with sufficient lead time to allow simultaneous consideration and preparation of complete finish color schedule. No approvals of single items shall be considered. 16.010 Copies to Owner. When shop drawings, product data, samples or similar submittals have been approved and stamped by both Contractor and Architect, Contractor shall immediately forward an electronic copy of each to the Owner. GC 17.00

CASH ALLOWANCE

The Contractor shall include in the Contract sum all allowances named in the Contract Documents and shall cause the work so covered to be done by such Contractors and for such sums as the Owner may direct, the Contract sum being adjusted in conformity therewith. The Contractor declares that the Contract sum includes such sums for expenses and profit on account of cash allowances as he deems proper. No demand for expenses or profit other than those included in the Contract sum shall be allowed. The Contractor shall not be required to employ for any such work persons against whom he has filed a lien or has a reasonable objection due to previous legal claims. GC 18.00

EXPEDITING MATERIALS 10

The Contractor shall, immediately after receipt of the Notice of Award and approval of its list of subcontractors and material suppliers, place orders for all equipment, materials, and supplies required for the Work. The Contractor shall, when requested, submit to the Architect evidence that such orders have been placed. The Contractor shall exercise due diligence in seeing that all equipment, materials, and supplies are delivered well in advance of the time they are needed on the Project and shall properly store and protect same at its expense and in accordance with these General Conditions, either at the Project site or elsewhere as approved by the Architect. GC 19.00

BLASTING

No explosives of any nature except for those normally employed in powder actuated tools, .38 caliber or smaller, shall be employed or used on the Project site except with the express and specific prior written approval of the Architect and the Owner and any appropriate governmental authorities, in each instance. The Contractor shall notify the Architect of need for such approval three (3) days prior to the proposed use of such explosives. GC 20.00

SOIL TEST REPORT

The Owner may arrange for a separate consultant to conduct field and laboratory soil investigations on the Project site and to prepare a report of its findings. Such a report, if prepared, shall be available for review by the Contractor in the Architect’s office. Such data is offered solely for reference and is not to be considered a part of the Contract Documents. The data contained in any such document prepared for the Owner by a separate consultant is believed to be reliable; however, the Owner and Architect do not guarantee its accuracy or completeness. All applicable subcontractors shall be fully familiar with the contents of such reports, if prepared, and shall consider and evaluate them in the performance of their contracts and the Work. GC 21.00

HAZARDOUS MATERIALS

21.01 Responsibility and Reporting. Unless otherwise provided in the Contract Documents, the Contractor shall have no responsibility for the presence, handling, removal or disposal of hazardous materials in any form at the Project site, including but not limited to asbestos, asbestos products, polychlorinated biphenyl (PCB), lead, or other hazardous materials. Prior to its commencement or continuation of any portion of the Work, the Contractor shall provide notice to the Owner of the presence, location, amount and condition of any known or suspected hazardous materials that are discovered at the Project site. Such notice shall be in writing and shall be submitted no more than twenty-four (24) hours after the presence of such materials becomes known or suspected. 21.02 Contractor’s Obligations. In the event hazardous materials become known or suspected by the Contractor as described in GC-21.01 above, the Contractor shall not proceed with or continue the Work until it has received written authorization from the Owner. If the Contractor proceeds with the Work without said authorization, it assumes any and all responsibility and liability for contamination and cleanup at the Project site according to applicable federal and state laws, and for any death or personal injury, including but not limited to medical expenses that may be incurred by any individual as a result of exposure to hazardous materials on the Project site. 21.03 Owner’s Obligations. In the event hazardous materials are identified or encountered during the course of the Project, the Owner at its expense shall take reasonable actions to properly and safely deal with such materials. 21.04 Management Plan. The Contractor acknowledges that it and its employees, agents and subcontractors have the responsibility of being fully informed of the Owner’s Management Plan as it relates to buildings located at the Project site and shall consult with the Owner about how such Plan addresses suspected or active asbestos-containing material areas within such buildings. GC 22.00

DAMAGE TO UTILITIES 11

22.01 Adequate Precautions. The Contractor shall take adequate precautions to protect existing utilities on and off the Project site and avoid damage thereto. The Contractor shall repair or replace or have repaired or replaced at its expense any damage to streets, water, sewer, light, power, cable, or telephone lines or fiber network that are damaged by reason of the Contractor’s Work. 22.02 Location. The location and extent of underground utilities, fiber network, cables and conduit indicated on the drawings are not guaranteed. This information is shown only for such use as bidders and contractors may choose to make of it. The Contractor shall check with all public utility companies for locations and shall comply with their regulations regarding such utilities in performing the Work. 22.03 Protection from Damage. The Contractor shall adequately protect active underground utilities from damage, and if damaged shall immediately effect all necessary repairs. Removal or relocation of active underground utilities shall be done only as indicated on the drawings. If such utilities are in use, they shall be maintained in continuous service. If not indicated on the drawings or not known to exist, the Contractor shall report discovery of such utilities to the Architect and shall not proceed further until directed to do so. 22.04 Inactive or Abandoned Utilities. Inactive or abandoned utilities, whether or not they are indicated on the drawings, shall be recorded as to location and depth and shall be removed for a distance of not less than three (3) feet from the outside line of all concrete Work unless otherwise required by regulations. Ends shall be capped or plugged. There shall be no adjustment of the Contract amount for Work due to inactive or abandoned utilities. GC 23.00

CHANGES IN THE WORK

23.01 Change Orders. The Owner, without invalidating the Agreement, may order changes in the Work within the general scope of the Project consisting of additions, deletions, or other revisions. Under such circumstances, the GMP, if applicable and established, and the Contract Time Schedule shall be adjusted accordingly. All such changes in the Work shall be authorized by Change Order. No Change Order or other form of order or directive by the Owner or Architect requiring additional compensable Work to be performed, which causes the aggregate amount payable under the Contract Documents to exceed the amount appropriated for the original Agreement, shall be issued unless the Contractor is given written assurance by the Owner that lawful appropriations to cover the costs of the additional Work have been made. Any claim of the Contractor for adjustment under this section must be asserted in writing within ten (10) days from the date of the Contractor’s receipt of the Change Order. 23.02 Minor Changes. The Architect shall have authority to order minor changes in the Work not involving an adjustment in the GMP or an extension of the Contract Time Schedule and not inconsistent with the intent of the Contract Documents. Such changes may be effected by field order or by other written order. Such changes shall be binding on the Owner and the Contractor. In any emergency affecting the safety of persons or property, the Contractor shall act, at his discretion, to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in this Article. 23.03 Price Differential. The cost or credit resulting from a change in the Work shall be determined in one or more of the following ways: a. By estimate, with a detailed cost breakdown as set forth in GC-23.03(c) below, and acceptance in a lump sum, with a maximum combined markup to the Owner, for the Contractor and all affected subcontractors, not to exceed a total of fifteen percent (15%). b. By unit prices named in the Contract or subsequently agreed upon. c. If the parties are unable to agree on one of the above methods, then the amount shall be determined by force account under the following formula: i. The actual cost of all direct labor performed (including foremen employed continuously on the Work, but not the salary, or any part thereof, of the Contractor’s superintendent) and the actual 12

ii. iii. iv. v.

vi.

GC 24.00

materials furnished for and used in such Work, less all available cash, trade, or other discounts. Rental for the use of such items of equipment as have an individual value in excess of One Thousand Dollars ($1,000); provided, however, that the amount of such rental charge and the length of time and probable cost of the use of such equipment shall have been authorized in writing by the Owner. All proportionate sums paid for royalties, permits, and inspection fees. All proportionate premiums for public liability insurance, workers’ compensation, and other proper and necessary insurance, as well as all applicable payroll taxes. Either a predetermined lump sum; fixed fee; or a fee of fifteen percent (15%), which fee shall be applied to the total of GC-23.03(c)(i), GC-23.03(c)(ii) and GC-23.03(c)(iii) only, and shall constitute full compensation to the Contractor and all its subcontractors for all costs and expenses, including all overhead and profit, which are not otherwise enumerated in this GC-23.03(c). The Contractor shall keep and present, in such manner as the Owner may direct, an accurate accounting of all the fees and costs described in this GC-23.03(c), together with all supporting vouchers and other documentation, all subject to audit by the Owner. CLAIMS FOR EXTRA COST

If the Contractor claims that any instructions by drawings or otherwise, after the date of the Construction Agreement, involve extra costs under this Contract that were not included in the original bid, or require an extension in the construction schedule, the Contractor shall give the Owner and the Architect written notice thereof no later than ten (10) days after the receipt of such instructions, and in any event before proceeding to execute the Work, except in an emergency endangering life or property, and the procedure shall then be as provided for changes in the Work. No such claim shall be valid unless so made. Any change in the Contract amount or construction schedule must be authorized by Change Order. GC 25.00

DELAYS AND EXTENSIONS OF TIME

25.01 Delays and Extensions of Time. If the Contractor is delayed at any time in the progress of the Work by the negligence or other improper act of the Owner or the Architect, or by any employee of either, or by any separate contractor employed by the Owner, or by changes ordered in the Work, or by any other cause that the Owner determines may justify the delay, then the completion date shall be extended by Change Order for such reasonable time as the Owner may determine. a.

Extension of the Contract completion time will be considered for delays due to weather conditions only when such conditions have had a material, adverse impact upon the critical path of the construction schedule, are more severe and extended than those reflected by the ten (10) year average for the month as evidenced by climatological data, U.S. Department of Commerce, for the area where the Project is located, and only if a request for such an extension of time is received within seven (7) days of the first date of each delay. Extensions of time due to weather or other allowable reasons will be granted on the basis of 1.4 calendar days’ credit for every working day lost with each separate extension figured to the nearest whole calendar day.

b.

All Contractor requests for extension of time shall be subject to the Owner’s approval and shall be made in writing to the Owner no more than seven (7) days after the occurrence causing the delay; otherwise they shall be deemed waived. Any request for extension of time for a change in the Work or for any occurrence allegedly causing a delay as provided for herein must be substantiated by demonstrating the effect of the change or occurrence on the critical path of the construction schedule.

c.

If no schedule or agreement is made stating the dates upon which written interpretations or detail drawings shall be furnished, then no claim for delay shall be allowed on account of failure to furnish such interpretations or detail drawings until fifteen (15) days after demand is made for them, and then only if such claim is reasonable.

13

d.

Should the time for completion of the Contract be extended, the Owner reserves the right to occupy any part of the structure upon written notice to the Contractor from the Architect or the Owner, but only after the Architect has made a thorough inspection, accompanied by the Contractor’s superintendent, to note any defects in workmanship or materials that are the responsibility of the Contractor. Such inspection shall not be deemed to modify any other Contract requirements or provisions relating to observations, inspections or acceptance of the Work. Any such partial occupancy shall not be deemed a waiver of any provision for liquidated damages for delay in final completion.

e.

When the whole or a portion of the Work is suspended for any reason, the Contractor shall properly cover over, secure, and protect all Work as may be susceptible to damage in the absence of such action.

25.02 Article Not Exclusive. This GC-25.00 does not exclude the recovery of damages by the Owner for delay under other provisions of the Contract Documents. GC 26.00

ACCESS TO WORK

26.01 Access. The Architect, the Owner, and their representatives shall at all times have access to the Work wherever it is in preparation or progress, and the Contractor shall provide proper facilities for such access so that the Architect may perform its functions under the Contract Documents. 26.02 Inspection. If the specifications, the Architect’s instructions, laws, ordinances, or any public authority require any Work to be specially tested or approved, the Contractor shall give the Architect timely notice of its readiness for such testing or approval by the Architect or inspection by another authority, and if the inspection is by another authority, of the date fixed for such inspection. All required certificates of inspection shall be secured by the Contractor. If any Work is covered up without approval or consent of the Architect, it must, if required by the Architect, be uncovered for examination at the Contractor’s expense. 26.03 Reinspection. Reinspection of questioned Work may be ordered by the Owner, and if so ordered, the Work must be uncovered by the Contractor. If such Work is found to be in accordance with the Contract Documents, the Owner shall pay the cost of reinspection and replacement. If such Work is found not to be in accordance with the Contract Documents, the Contractor shall pay such cost. 26.04 Testing. Materials incorporated into the Project shall be subject to routine tests as required to ensure their compliance with the specifications. Such tests may include, but shall not necessarily be restricted to, the following: concrete (primary mix design, slump tests, cylinder compressions tests, and air entrainment tests); steel (tensile tests); welds (field inspection and x-ray examination); soils (sub-soil investigation, physical analysis, and compaction tests); asphalt pavement (physical analysis and compaction tests); and roofing samples cut from in-place built-up roof. Any other basic materials for which standard laboratory test procedures have been established may also be included if doubt as to their quality should arise. Any testing contemplated by this section shall be done at the discretion of the Owner, who shall bear all costs, unless otherwise provided in the Contract Documents. The Contractor shall be held responsible for providing samples of sufficient size for test purposes and for cooperating with the Owner or its representative in obtaining and preparing samples for tests. All tests shall be in accordance with standard test procedures and shall be performed by persons or firms selected by the Owner. Contractor shall schedule and coordinate all tests and inspections directly with the owner’s testing and / or inspection agency. Contractor shall give the architect and owner 48 hours’ notice of when and where tests and inspections are to be made so that the architect may be present for such procedures. GC 27.00

CORRECTION OF WORK

27.01 Correction of Work Before and After Completion. The Architect or Owner has the authority to reject Work that is defective or otherwise does not conform to the Contract Documents. The Contractor, following written demand, shall promptly correct all Work rejected by the Architect or Owner as defective or as 14

otherwise failing to conform to the Contract Documents, whether observed before or after the date of final completion and whether or not fabricated, installed, or completed. The Contractor shall bear all costs of correcting such rejected Work, including the cost of the Architect’s and/or Owner’s consultant’s additional services necessitated thereby. If the Contractor proceeds to build in or cover the item that has been rejected, the Contractor shall be totally responsible for the cost of removal and replacement of said item and removal and replacement of all necessary Work surrounding or covering the item. 27.02 Tests to Determine Conformance. Whenever in the opinion of the Architect or the Owner tests are essential to assure the professional evaluation of the Work that is subject to being rejected or condemned, the necessary number of tests shall be performed by consultants designated by the Owner. The recommendation of such consultants shall be final and all parties to the Contract shall comply with the methods and extent of the corrections submitted in writing to the Owner and the Architect by such consultants. The cost of the tests shall become the Contractor’s responsibility when corrections of any nature are recommended by the consultant to the investigated Work; otherwise, the Owner shall pay for all tests performed. Should such special testing, inspection, or approval be caused by the Contractor’s failure to follow the requirements of the Contract Documents or required tests under GC-26.04 indicating conditions not in conformance with the Contract Documents, the costs of such additional testing, inspection, or approval shall be borne by the Contractor, regardless of the results. 27.03 Removal of Rejected Work. The Contractor shall promptly remove from the Project site all Work rejected by the Architect or Owner as failing to conform to the Contract Documents, whether or not the Work is physically incorporated. Thereafter, the Contractor shall promptly replace and re-execute such Work in accordance with the Contract Documents and without expense to the Owner. The Contractor shall further bear the expense of making good all Work of other contractors and/or subcontractors destroyed or damaged by such removal or replacement, and shall bear the expense of making good all of its Work and the Work of its subcontractors found to be defective by such removal or replacement. If the Contractor does not remove such rejected Work within a reasonable time, fixed by written notice from the Owner through the Architect, the Owner may remove it and may store the material at the expense of the Contractor. If the Contractor does not pay the expenses of such removal and storage within ten (10) days’ time thereafter, the Owner may, upon ten (10) days’ written notice, sell such materials at auction or at private sale. In such case, the Owner shall account to the Contractor for the net proceeds thereof, after deducting all the costs and expenses that should have been borne by the Contractor, including compensation for additional Architect or consultant services. If the net proceeds of sale do not cover all costs that the Contractor should have borne, the difference shall be charged to the Contractor and an appropriate Change Order shall be issued. If the payments then or thereafter due the Contractor are not sufficient to cover such amount, the Contractor shall pay the difference to the Owner. In addition, the Owner shall have any other remedies that may be available to it. 27.04 Correction of Work After Final Payment. Neither the final estimate or payment, nor any provision in the Contract Documents, shall relieve the Contractor of responsibility for faulty materials or workmanship and, unless otherwise specified, the Contractor shall remedy any defects due thereto and pay for any damage to other Work or property resulting therefrom, which appear within a period of two (2) years from the date of final completion and acceptance. This warranty shall be in addition to and not in lieu of all other remedies available to the Owner. 27.05 Failure to Correct the Work. If the Contractor fails to correct defective or nonconforming Work, the Owner may correct it and otherwise proceed against the Contractor for the cost thereof in accordance with the provisions of these General Conditions. 27.06 Deductions for Uncorrected Work. If the Owner deems it inexpedient to correct Work that has been damaged, is defective or has not been done in accordance with the Contract Documents, then an appropriate deduction from the price shall be made and reflected by a Change Order or, if the amount is determined after final payment, it shall be paid by the Contractor. 15

27.07 Additional Obligations. The obligations of the Contractor to correct the Work shall be in addition to, and not in lieu of, any other obligations imposed upon it by law, special guarantees, warranties, or other rights of the Owner. GC 28.00

OWNER’S RIGHT TO CARRY OUT WORK

If the Contractor should neglect to prosecute the Work properly or fail to perform any requirement of the Contract Documents, the Owner, after three (3) working days’ written notice to the Contractor, may, without prejudice to any other remedy it may have, make good such deficiencies and may deduct the reasonable cost thereof from the payment then or thereafter due the Contractor. In the event such Work is performed by the Owner, the Owner’s employees, or by persons other than the Contractor at the Owner’s request, the Owner shall not be liable to the Contractor for inconvenience expense or subsequent cost of removal of such Work. The amount to be deducted as the cost of doing the Work shall include the cost of the Architect’s additional services made necessary by such default. If the payments then or thereafter due the Contractor are not sufficient to cover such amount, the Contractor shall pay the difference to the Owner. GC 29.00

OWNER’S RIGHT TO TERMINATE CONTRACT

29.01 Termination for Cause. If the Contractor should be adjudged bankrupt; or if it should make a general assignment for the benefit of its creditors without approval of the Owner; or if a receiver should be appointed on account of its insolvency; or if it should refuse or should fail, except in cases for which extension of time is provided, to supply enough properly skilled workers, competent supervision and superintendence of the Work, proper materials, or competent management of the Project; of if it should fail to make prompt payment to subcontractors or for material or labor; or disregard any laws, ordinances, or the instructions of the Architect or Owner; or otherwise be guilty of a material violation of any provision of the Contract Documents; then the Owner, when in its sole opinion sufficient cause exists to justify such action, may, without prejudice to any other right or remedy and after giving the Contractor, and its surety, if any, seven (7) days’ written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, tools, and appliances thereon and finish the Work by whatever method the Owner may deem expedient. In such case the Contractor shall not be entitled to receive any further payment until the Work is finally completed and accepted by the Owner. If the unpaid balance of the Contract amount exceeds the expense of completing the Work, including the cost of additional architectural, engineering, managerial, consultant, and administrative services, such excess shall be paid to the Contractor. If such expense exceeds such unpaid balance, the Contractor shall pay the difference to the Owner and the Owner shall be justified in withholding payment of any unpaid amounts. The expense incurred by the Owner, as herein provided, and the damages incurred through the Contractor’s default, shall be determined by the Owner. The Contractor will not be reimbursed for any anticipated profit. 29.02 Termination Without Cause. Should conditions arise that in the Owner’s opinion make it necessary or advisable to discontinue Work under the Contract Documents, the Owner may terminate the Contract in whole or in part without cause or fault by the Contractor by giving seven (7) days’ written notice to the Contractor. The notice shall specify the date and extent to which the Contract is terminated. Upon any such termination, the Owner shall take possession of the Project site and all or any part of the materials and equipment delivered or en route to the site. In the event of termination without cause under this section, the Contractor shall be equitably paid for all Work properly completed, based upon the approved schedules of values. GC 30.00

CONSTRUCTION SCHEDULE AND PROGRESS REPORTS

30.01 Construction Schedule. The Contractor shall submit, within ten (10) days after the date of the notice of award in a format acceptable to the Owner, an overall timetable of the construction schedule for the Project. This schedule shall start with the date of the notice of award, and the completion date shall be a date that will enable the Owner to accept the Work on the date specified in the Construction Agreement. The 16

schedule shall portray fully a timetable representing the various elements in the schedule of values and shall provide for the expeditious and practicable execution of the Work. The time shown between the starting and completion dates of the various elements within the schedule shall represent one hundred percent (100%) completion of each element. Additional detailed schedules of separate elements of the Work such as commissioning, test and balance, and owner training, may be requested at the Owner’s discretion. No request for payment shall be accepted by the Owner until this schedule has been submitted as required herein. This schedule shall be revised from time to time during the course of the Work when the actual progress, in the opinion of the Architect or the Owner, varies materially from that previously approved. 30.02 Monthly Progress Reports. The Contractor shall submit monthly progress reports with each request for payment. Basically, these reports shall reflect the Contractor’s “Work in place” progress and shall be certified by the Contractor as to the date and contents of such “Work in place” progress report. If requested by the Owner, the monthly progress reports shall also include representative photographs of the actual Work in place. Such reports shall depict progress and percentage of completion, consistent with the values and amounts contained on the counterpart request for payment. The subcontractors shall be supplied copies of the Contractor’s approved schedule. These subcontractors shall develop a similar schedule based on their respective Work. Failure to submit an approved schedule or monthly progress report shall be deemed cause to reject requests for payment. 30.03 Scheduling. The Contractor shall schedule all Work so as to reduce to a minimum any disruption in the use of the existing facilities and interruptions of utility service of any type. Where electrical or mechanical Work performed under this Contract will necessitate interruptions of service to existing facilities, the Contractor shall furnish and install temporary service to such facilities or perform such Work at such times when said existing utilities are not in normal use. The Contractor shall bear the cost of all overtime or inconvenience resulting therefrom. Any remodeling work which may interrupt normal building functions, especially periodic standardized testing, shall be scheduled and coordinated with the Owner at least 1 week prior. 30.04 Noise Ordinance Violation. The Contractor shall at all times comply with the local noise ordinance requirements relating to the Work. To the extent there are any violations of any applicable noise ordinances imposed on the Owner as a direct or indirect result of the Contractor’s Work, then the Contractor shall reimburse the Owner for any sums paid or due and payable by the Owner as a result of such violations. The Owner reserves the right to deduct any expenses incurred by the Owner as a result of any noise ordinance violations by the Contractor from any amount due to the Contractor under this Construction Agreement or, at its option, to collect such sum directly from the Contractor or its surety GC 31.00

SCHEDULE OF VALUES

Progress payments shall be made on the valuation of the Work done. Before beginning work and prior to the first Application for Payment, the Contractor shall submit to the Architect and the Owner a complete, itemized schedule of the values of the various parts of the Work, aggregating the total sum of the Contract and separating material costs from other costs . Such schedule shall include the material costs of all subcontractors under the Contractor and the costs of all materials to be taken from the Contractor’s or subcontractors’ own stocks of material. The schedule of values shall be supported by such evidence as to its correctness as the Architect and/or the Owner may direct. Each item on the schedule of values shall include its proper share of overhead and profit. The schedule of values shall be used for the estimates and progress payments provided for in these General Conditions. Along with such schedule of values, the Contractor shall submit a schedule of estimated monthly application amounts to be submitted over the course of the Project to assist the Owner in arranging payments. GC 32.00 32.01

PAYMENT Certificates for Payment. No request for payment shall be submitted to the Owner until and unless it 17