BVSD Board of Education · Document
Ned MSHS CMGC Amendment Exhibits.pdf (4,858 KB)
Regular Meeting, November 10, 2026 · item 7.10: Amendment to the contract for Nederland Middle/High School · 95 pages
This is the text extracted from the file, without its layout, tables, or images. Use the original for anything that matters.
Exhibit A Drawings, specifications and documents used to prepare the GMP
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit A - MSHS Drawings List Printed on Mon Oct 26, 2026 at 03:51 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction
Current Drawings Drawing Number
Drawing Title
Revision
Drawing Date
Received Date
Set
Status
General G000
COVER SHEET
0
09/24/2026
09/24/2026
95% CD's
Published
G101
CODE PLANS
0
09/24/2026
09/24/2026
95% CD's
Published
G102
AFTER HOURS CODE PLANS
0
09/24/2026
09/24/2026
95% CD's
Published
G201
COST BREAKOUT SUMMARY - VFA SCHEDULE AND 1ST FLOOR PLAN
0
09/24/2026
09/24/2026
95% CD's
Published
G202
COST BREAKOUT SUMMARY - 2ND FLOOR PLAN, SITE AND ROOF PLAN
0
09/24/2026
09/24/2026
95% CD's
Published
C001
GENERAL LEGEND NOTES AND ABB.
0
09/24/2026
09/24/2026
95% CD's
Published
C100
OVERALL SITE PLAN
0
09/24/2026
09/24/2026
95% CD's
Published
C101
DETAILED SITE PLAN
0
09/24/2026
09/24/2026
95% CD's
Published
C102
DETAILED SITE PLAN
0
09/24/2026
09/24/2026
95% CD's
Published
C103
SITE DETAILS
0
09/24/2026
09/24/2026
95% CD's
Published
C104
EROSION CONTROL PLAN
0
09/24/2026
09/24/2026
95% CD's
Published
C105
DETAILED EROSION CONTROL PLAN
0
09/24/2026
09/24/2026
95% CD's
Published
C106
DETAILED EROSION CONTROL PLAN
0
09/24/2026
09/24/2026
95% CD's
Published
C107
SWMP & EROSION CONTROL DETAILS
0
09/24/2026
09/24/2026
95% CD's
Published
C108
EROSION CONTROL DETAILS
0
09/24/2026
09/24/2026
95% CD's
Published
S001
GENERAL NOTES
0
09/24/2026
09/24/2026
95% CD's
Published
S002
IBC 2021 STATEMENT OF SPECIAL INSPECTION
0
09/24/2026
09/24/2026
95% CD's
Published
S101
LEVEL ONE FRAMING PLAN
0
09/24/2026
09/24/2026
95% CD's
Published
S102
LEVEL TWO FRAMING PLAN
0
09/24/2026
09/24/2026
95% CD's
Published
S103
ROOF FRAMING PLAN
0
09/24/2026
09/24/2026
95% CD's
Published
Civil
Structural
Page 1 of 7
Printed on Mon Oct 26, 2026 at 03:51 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction
Drawing Number
Drawing Title
Revision
Drawing Date
Received Date
Set
Status
S501
TYPICAL DETAILS
0
09/24/2026
09/24/2026
95% CD's
Published
S601
FOUNDATION & ROOF DETAILS
0
09/24/2026
09/24/2026
95% CD's
Published
A001
ARCHITECTURAL GENERAL NOTES
0
09/24/2026
09/24/2026
95% CD's
Published
A002
WALL & ROOF TYPES
0
09/24/2026
09/24/2026
95% CD's
Published
A003
STANDARD DETAILS
0
09/24/2026
09/24/2026
95% CD's
Published
A004
STANDARD MOUNTING HEIGHTS
0
09/24/2026
09/24/2026
95% CD's
Published
A101
LEVEL ONE FLOOR PLAN
0
09/24/2026
09/24/2026
95% CD's
Published
A101a
LEVEL ONE FLOOR PLAN - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
A101b
LEVEL ONE FLOOR PLAN - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
A102
LEVEL TWO FLOOR PLAN
0
09/24/2026
09/24/2026
95% CD's
Published
A102a
LEVEL TWO FLOOR PLAN -AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
A102b
LEVEL TWO FLOOR PLAN -AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
A120
PROJECT MATERIAL SUMMARY
0
09/24/2026
09/24/2026
95% CD's
Published
A121a
LEVEL ONE FINISH PLAN - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
A121b
LEVEL ONE FINISH PLAN - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
A122a
LEVEL TWO FINISH PLAN -AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
A122b
LEVEL TWO FINISH PLAN -AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
A140
PROJECT EQUIPMENT & SIGNAGE SUMMARY
0
09/24/2026
09/24/2026
95% CD's
Published
A141a
LEVEL ONE EQUIPMENT PLAN -AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
A141b
LEVEL ONE EQUIPMENT PLAN -AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
A142a
LEVEL TWO EQUIPMENT PLAN -AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
A142b
LEVEL TWO EQUIPMENT PLAN -AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
A161a
LEVEL ONE REFLECTED CEILING PLAN -AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
A161b
LEVEL ONE REFLECTED CEILING PLAN -AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
Architectural
Page 2 of 7
Printed on Mon Oct 26, 2026 at 03:51 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction
Drawing Number
Drawing Title
Revision
Drawing Date
Received Date
Set
Status
A162a
LEVEL TWO REFLECTED CEILING PLAN -AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
A162b
LEVEL TWO REFLECTED CEILING PLAN -AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
A181a
ROOF PLAN -AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
A181b
ROOF PLAN -AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
A201
EXTERIOR ELEVATIONS
0
09/24/2026
09/24/2026
95% CD's
Published
A221
INTERIOR ELEVATIONS
0
09/24/2026
09/24/2026
95% CD's
Published
A222
INTERIOR ELEVATIONS
0
09/24/2026
09/24/2026
95% CD's
Published
A223
INTERIOR ELEVATIONS
0
09/24/2026
09/24/2026
95% CD's
Published
A224
INTERIOR ELEVATIONS
0
09/24/2026
09/24/2026
95% CD's
Published
A225
INTERIOR ELEVATIONS
0
09/24/2026
09/24/2026
95% CD's
Published
A226
INTERIOR ELEVATIONS
0
09/24/2026
09/24/2026
95% CD's
Published
A227
INTERIOR ELEVATIONS - ALTERNATES
0
09/24/2026
09/24/2026
95% CD's
Published
A401
ENLARGED RESTROOM PLANS & ELEVATIONS
0
09/24/2026
09/24/2026
95% CD's
Published
A402
ENLARGED RESTROOM PLANS & ELEVATIONS
0
09/24/2026
09/24/2026
95% CD's
Published
A403
ENLARGED RESTROOM PLANS & ELEVATIONS
0
09/24/2026
09/24/2026
95% CD's
Published
A421
VERTICAL CIRCULATION
0
09/24/2026
09/24/2026
95% CD's
Published
A501
INTERIOR DETAILS
0
09/24/2026
09/24/2026
95% CD's
Published
A502
THEATER DETAILS
0
09/24/2026
09/24/2026
95% CD's
Published
A521
EXTERIOR DETAILS
0
09/24/2026
09/24/2026
95% CD's
Published
A561
OPENING DETAILS
0
09/24/2026
09/24/2026
95% CD's
Published
A601
OPENING SCHEDULES & FRAME TYPES
0
09/24/2026
09/24/2026
95% CD's
Published
A611
OPENING & FRAME TYPES
0
09/24/2026
09/24/2026
95% CD's
Published
AD101a
LEVEL ONE DEMOLITION PLAN -AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
AD101b
LEVEL ONE DEMOLITION PLAN -AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
AD102a
LEVEL TWO DEMOLITION PLAN -AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
Page 3 of 7
Printed on Mon Oct 26, 2026 at 03:51 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction
Drawing Number
Drawing Title
Revision
Drawing Date
Received Date
Set
Status
AD102b
LEVEL TWO DEMOLITION PLAN -AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
AD161a
LEVEL ONE DEMOLITION REFLECTED CEILING PLAN -AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
AD161b
LEVEL ONE DEMOLITION REFLECTED CEILING PLAN -AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
AD162a
LEVEL TWO DEMOLITION REFLECTED CEILING PLAN -AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
AD162b
LEVEL TWO DEMOLITION REFLECTED CEILING PLAN -AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
P000
PLUMBING COVERSHEET
0
09/24/2026
09/24/2026
95% CD's
Published
P100a
UNDERFLOOR PLAN - PLUMBING - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
P100b
UNDERFLOOR PLAN - PLUMBING - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
P101a
LEVEL ONE PLAN - PLUMBING - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
P101b
LEVEL ONE PLAN - PLUMBING - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
P102a
LEVEL TWO PLAN - PLUMBING - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
P102b
LEVEL TWO PLAN - PLUMBING - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
P103a
ROOF PLAN - PLUMBING - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
P103b
ROOF PLAN - PLUMBING - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
P400
PLUMBING DETAILS
0
09/24/2026
09/24/2026
95% CD's
Published
P401
PLUMBING DETAILS
0
09/24/2026
09/24/2026
95% CD's
Published
P500
PLUMBING DIAGRAMS
0
09/24/2026
09/24/2026
95% CD's
Published
P501
PLUMBING DIAGRAMS
0
09/24/2026
09/24/2026
95% CD's
Published
P600
PLUMBING SCHEDULES
0
09/24/2026
09/24/2026
95% CD's
Published
PD100a
UNDERFLOOR DEMOLITION PLAN - PLUMBING - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
PD100b
UNDERFLOOR DEMOLITION PLAN - PLUMBING - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
PD101a
LEVEL ONE DEMOLITION PLAN - PLUMBING - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
PD101b
LEVEL ONE DEMOLITION PLAN - PLUMBING - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
PD102a
LEVEL TWO DEMOLITION PLAN - PLUMBING - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
Plumbing
Page 4 of 7
Printed on Mon Oct 26, 2026 at 03:51 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction
Drawing Number PD102b
Drawing Title
Revision
Drawing Date
Received Date
Set
Status
LEVEL TWO DEMOLITION PLAN - PLUMBING - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
M000
HVAC COVERSHEET
0
09/24/2026
09/24/2026
95% CD's
Published
M101a
LEVEL ONE PLAN - HVAC - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
M101b
LEVEL ONE PLAN - HVAC - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
M102a
LEVEL TWO PLAN - HVAC - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
M102b
LEVEL TWO PLAN - HVAC - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
M103a
ROOF PLAN - HVAC - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
M103b
ROOF PLAN - HVAC - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
M400
HVAC DETAILS
0
09/24/2026
09/24/2026
95% CD's
Published
M401
HVAC DETAILS
0
09/24/2026
09/24/2026
95% CD's
Published
M402
HVAC DETAILS
0
09/24/2026
09/24/2026
95% CD's
Published
M500
HVAC DIAGRAMS
0
09/24/2026
09/24/2026
95% CD's
Published
M501
HVAC DIAGRAMS
0
09/24/2026
09/24/2026
95% CD's
Published
M502
HVAC DIAGRAMS
0
09/24/2026
09/24/2026
95% CD's
Published
M600
HVAC SCHEDULES
0
09/24/2026
09/24/2026
95% CD's
Published
M601
HVAC SCHEDULES
0
09/24/2026
09/24/2026
95% CD's
Published
M602
HVAC SCHEDULES
0
09/24/2026
09/24/2026
95% CD's
Published
M603
HVAC SCHEDULES
0
09/24/2026
09/24/2026
95% CD's
Published
MD101a
LEVEL ONE DEMOLITION PLAN - HVAC - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
MD101b
LEVEL ONE DEMOLITION PLAN - HVAC - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
MD102a
LEVEL TWO DEMOLITION PLAN - HVAC - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
MD102b
LEVEL TWO DEMOLITION PLAN - HVAC - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
MD103a
ROOF DEMOLITION PLAN - HVAC - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
MD103b
ROOF DEMOLITION PLAN - HVAC - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
Mechanical
Page 5 of 7
Printed on Mon Oct 26, 2026 at 03:51 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction
Drawing Number
Drawing Title
Revision
Drawing Date
Received Date
Set
Status
Electrical E000
ELECTRICAL COVERSHEET
0
09/24/2026
09/24/2026
95% CD's
Published
E001
ELECTRICAL LIGHTING COVERSHEET
0
09/24/2026
09/24/2026
95% CD's
Published
E010
ELECTRICAL SITE PLAN
0
09/24/2026
09/24/2026
95% CD's
Published
E101a
LEVEL ONE PLAN - LIGHTING - AREA A 09/24/2026
0
09/24/2026
09/24/2026
95% CD's
Published
E101b
LEVEL ONE PLAN - LIGHTING - AREA B 09/24/2026
0
09/24/2026
09/24/2026
95% CD's
Published
E102a
LEVEL TWO PLAN - LIGHTING - AREA A 09/24/2026
0
09/24/2026
09/24/2026
95% CD's
Published
E102b
LEVEL TWO PLAN - LIGHTING - AREA B 09/24/2026
0
09/24/2026
09/24/2026
95% CD's
Published
E111a
LEVEL ONE PLAN - POWER - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
E111b
LEVEL ONE PLAN - POWER - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
E112a
LEVEL TWO PLAN - POWER - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
E112b
LEVEL TWO PLAN - POWER - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
E113a
ROOF PLAN - POWER - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
E113b
ROOF PLAN - POWER - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
E300
ELECTRICAL ENLARGED PLANS
0
09/24/2026
09/24/2026
95% CD's
Published
E400
ELECTRICAL DETAILS
0
09/24/2026
09/24/2026
95% CD's
Published
E500
ELECTRICAL DIAGRAMS
0
09/24/2026
09/24/2026
95% CD's
Published
E600
ELECTRICAL SCHEDULES
0
09/24/2026
09/24/2026
95% CD's
Published
E700
ELECTRICAL PANEL SCHEDULES
0
09/24/2026
09/24/2026
95% CD's
Published
ED101a
LEVEL ONE DEMOLITION PLAN - LIGHTING - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
ED101b
LEVEL ONE DEMOLITION PLAN - LIGHTING - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
ED102a
LEVEL TWO DEMOLITION PLAN - LIGHTING - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
ED102b
LEVEL TWO DEMOLITION PLAN - LIGHTING - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
ED111a
LEVEL ONE DEMOLITION PLAN - POWER - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
ED111b
LEVEL ONE DEMOLITION PLAN - POWER - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
Page 6 of 7
Printed on Mon Oct 26, 2026 at 03:51 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction
Drawing Number
Drawing Title
Revision
Drawing Date
Received Date
Set
Status
ED112a
LEVEL TWO DEMOLITION PLAN - POWER - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
ED112b
LEVEL TWO DEMOLITION PLAN - POWER - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
ED113a
ROOF DEMOLITION PLAN - POWER - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
ED113b
ROOF DEMOLITION PLAN - POWER - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
T000
TECHNOLOGY COVERSHEET
0
09/24/2026
09/24/2026
95% CD's
Published
T201a
LEVEL ONE PLAN - TECHNOLOGY - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
T201b
LEVEL ONE PLAN - TECHNOLOGY - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
T202a
LEVEL TWO PLAN - TECHNOLOGY - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
T202b
LEVEL TWO PLAN - TECHNOLOGY - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
T300
TECHNOLOGY ENLARGED PLANS
0
09/24/2026
09/24/2026
95% CD's
Published
T400
TECHNOLOGY DETAILS
0
09/24/2026
09/24/2026
95% CD's
Published
T500
TECHNOLOGY SCHEDULES
0
09/24/2026
09/24/2026
95% CD's
Published
TD101a
LEVEL ONE DEMOLITION PLAN - TECHNOLOGY - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
TD101b
LEVEL ONE DEMOLITION PLAN - TECHNOLOGY - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
TD102a
LEVEL TWO DEMOLITION PLAN - TECHNOLOGY - AREA A
0
09/24/2026
09/24/2026
95% CD's
Published
TD102b
LEVEL TWO DEMOLITION PLAN - TECHNOLOGY - AREA B
0
09/24/2026
09/24/2026
95% CD's
Published
TL000
THEATRICAL LIGHTING COVER SHEET
0
09/24/2026
09/24/2026
95% CD's
Published
TL101
THEATRICAL LIGHTING LAYOUT FLOOR PLAN
0
09/24/2026
09/24/2026
95% CD's
Published
TL161
THEATRICAL LIGHTING LAYOUT RCP
0
09/24/2026
09/24/2026
95% CD's
Published
TL400
THEATRICAL LIGHTING BATTON ELEVATIONS
0
09/24/2026
09/24/2026
95% CD's
Published
TL600
THEATRICAL LIGHTING SCHEDULE & LEGENDS
0
09/24/2026
09/24/2026
95% CD's
Published
TL700
THEATRICAL LIGHTING CONTROL SCHEDULE
0
09/24/2026
09/24/2026
95% CD's
Published
TL800
THEATRICAL LIGHTING OVERALL TOPOLOGY
0
09/24/2026
09/24/2026
95% CD's
Published
TL900
THEATRICAL LIGHTING DIMMING ONELINE
0
09/24/2026
09/24/2026
95% CD's
Published
Telecommunications
Page 7 of 7
Exhibit A - MSHS Specifications List Printed on Tue Oct 27, 2026 at 01:00 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction
Current Specifications Number
Description
Revision
Issued Date
Received Date
Set
00 - Procurement and Contracting Requirements 00 01 10
Table of Contents
0
09/24/26
09/24/26
95% CD's
00 26 00
PROCUREMENT SUBSTITUTION PROCEDURES
0
09/24/26
09/24/26
95% CD's
00 31 00
AVAILABLE PROJECT INFORMATION
0
09/24/26
09/24/26
95% CD's
00 31 26
EXISTING HAZARDOUS MATERIAL INFORMATION
0
09/24/26
09/24/26
95% CD's
00 72 00
GENERAL CONDITIONS
0
09/24/26
09/24/26
95% CD's
01 - General Requirements 01 10 00
SUMMARY
0
09/24/26
09/24/26
95% CD's
01 23 00
ALTERNATES
0
09/24/26
09/24/26
95% CD's
01 25 00
SUBSTITUTION PROCEDURES
0
09/24/26
09/24/26
95% CD's
01 26 00
CONTRACT MODIFICATION PROCEDURES
0
09/24/26
09/24/26
95% CD's
01 29 00
PAYMENT PROCEDURES
0
09/24/26
09/24/26
95% CD's
01 31 00
PROJECT MANAGEMENT AND COORDINATION
0
09/24/26
09/24/26
95% CD's
01 32 00
CONSTRUCTION PROGRESS DOCUMENTATION
0
09/24/26
09/24/26
95% CD's
01 33 00
SUBMITTAL PROCEDURES
0
09/24/26
09/24/26
95% CD's
01 35 43
CARPET RECLAMATION
0
09/24/26
09/24/26
95% CD's
01 40 00
QUALITY REQUIREMENTS
0
09/24/26
09/24/26
95% CD's
01 50 00
TEMPORARY FACILITIES AND CONTROLS
0
09/24/26
09/24/26
95% CD's
01 60 00
PRODUCT REQUIREMENTS
0
09/24/26
09/24/26
95% CD's
01 73 00
EXECUTION
0
09/24/26
09/24/26
95% CD's
01 74 19
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
0
09/24/26
09/24/26
95% CD's
01 77 00
CLOSEOUT PROCEDURES
0
09/24/26
09/24/26
95% CD's
01 78 23
OPERATION AND MAINTENANCE DATA
0
09/24/26
09/24/26
95% CD's
01 78 39
PROJECT RECORD DOCUMENTS
0
09/24/26
09/24/26
95% CD's
01 79 00
DEMONSTRATION AND TRAINING
0
09/24/26
09/24/26
95% CD's
01 81 13
SUSTAINABLE DESIGN
0
09/24/26
09/24/26
95% CD's
01 91 13
GENERAL COMMISSIONING REQUIREMENTS
0
09/24/26
09/24/26
95% CD's
SELECTIVE DEMOLITION
0
09/24/26
09/24/26
95% CD's
03 30 00
CAST-IN-PLACE CONCRETE
0
09/24/26
09/24/26
95% CD's
03 35 46
CONCRETE FINISHING
0
09/24/26
09/24/26
95% CD's
MASONRY
0
09/24/26
09/24/26
95% CD's
05 05 13
SHOP-APPLIED STEEL FINISHES
0
09/24/26
09/24/26
95% CD's
05 31 00
STEEL DECKING
0
09/24/26
09/24/26
95% CD's
02 - Existing Conditions 02 41 19 03 - Concrete
04 - Masonry 04 20 00 05 - Metals
Page 1 of 5
Printed on Tue Oct 27, 2026 at 01:00 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction
Number
Description
Revision
Issued Date
Received Date
Set
05 50 00
METAL FABRICATIONS
0
09/24/26
09/24/26
95% CD's
05 52 13
PIPE AND TUBE RAILINGS
0
09/24/26
09/24/26
95% CD's
06 - Wood, Plastics, and Composites 06 10 00
ROUGH CARPENTRY
0
09/24/26
09/24/26
95% CD's
06 20 23
INTERIOR FINISH CARPENTRY
0
09/24/26
09/24/26
95% CD's
06 36 61
SIMULATED SURFACE COUNTERTOPS
0
09/24/26
09/24/26
95% CD's
06 41 00
ARCHITECTURAL CASEWORK
0
09/24/26
09/24/26
95% CD's
06 64 00
PLASTIC PANELING
0
09/24/26
09/24/26
95% CD's
07 - Thermal and Moisture Protection 07 21 00
THERMAL INSULATION
0
09/24/26
09/24/26
95% CD's
07 51 14
PATCH EXISTING ROOFING
0
09/24/26
09/24/26
95% CD's
07 62 00
SHEET METAL FLASHING AND TRIM
0
09/24/26
09/24/26
95% CD's
07 63 00
FLASHING
0
09/24/26
09/24/26
95% CD's
07 72 00
ROOF ACCESSORIES
0
09/24/26
09/24/26
95% CD's
07 84 13
PENETRATION FIRESTOPPING
0
09/24/26
09/24/26
95% CD's
07 84 43
JOINT FIRESTOPPING
0
09/24/26
09/24/26
95% CD's
07 92 00
JOINT SEALANTS
0
09/24/26
09/24/26
95% CD's
08 11 13
HOLLOW METAL DOORS AND FRAMES
0
09/24/26
09/24/26
95% CD's
08 14 16
FLUSH WOOD DOORS
0
09/24/26
09/24/26
95% CD's
08 31 13
ACCESS DOORS AND FRAMES
0
09/24/26
09/24/26
95% CD's
08 33 23
OVERHEAD COILING DOORS
0
09/24/26
09/24/26
95% CD's
08 41 13
ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
0
09/24/26
09/24/26
95% CD's
08 42 43
SLIDING ENTRANCES
0
09/24/26
09/24/26
95% CD's
08 44 13
GLAZED ALUMINUM CURTAIN WALLS
0
09/24/26
09/24/26
95% CD's
08 45 23
FIBERGLASS-SANDWICH-PANEL ASSEMBLIES
0
09/24/26
09/24/26
95% CD's
08 62 00
UNIT SKYLIGHTS
0
09/24/26
09/24/26
95% CD's
08 71 00
DOOR HARDWARE
0
09/24/26
09/24/26
95% CD's
08 80 00
GLAZING
0
09/24/26
09/24/26
95% CD's
09 29 00
GYPSUM BOARD
0
09/24/26
09/24/26
95% CD's
09 30 00
TILING
0
09/24/26
09/24/26
95% CD's
09 51 13
ACOUSTICAL PANEL CEILINGS
0
09/24/26
09/24/26
95% CD's
09 64 00
WOOD FLOORING
0
09/24/26
09/24/26
95% CD's
09 65 13
RESILIENT BASE AND ACCESSORIES
0
09/24/26
09/24/26
95% CD's
09 65 19
RESILIENT TILE AND PLANK FLOORING
0
09/24/26
09/24/26
95% CD's
09 67 23
RESINOUS FLOORING
0
09/24/26
09/24/26
95% CD's
09 68 13
CARPETING
0
09/24/26
09/24/26
95% CD's
09 72 16
VINYL GRAPHIC FILM
0
09/24/26
09/24/26
95% CD's
09 84 00
ACOUSTIC COMPONENTS
0
09/24/26
09/24/26
95% CD's
09 91 00
PAINTING
0
09/24/26
09/24/26
95% CD's
08 - Openings
09 - Finishes
Page 2 of 5
Printed on Tue Oct 27, 2026 at 01:00 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction
Number
Description
Revision
Issued Date
Received Date
Set
10 - Specialties 10 11 00
VISUAL DISPLAY SURFACES
0
09/24/26
09/24/26
95% CD's
10 12 00
DISPLAY CASES
0
09/24/26
09/24/26
95% CD's
10 14 19
DIMENSIONAL LETTER SIGNAGE
0
09/24/26
09/24/26
95% CD's
10 14 23
PANEL SIGNAGE
0
09/24/26
09/24/26
95% CD's
10 21 13
TOILET COMPARTMENTS
0
09/24/26
09/24/26
95% CD's
10 26 00
WALL AND DOOR PROTECTION
0
09/24/26
09/24/26
95% CD's
10 28 00
TOILET, BATH AND LAUNDRY ACCESSORIES
0
09/24/26
09/24/26
95% CD's
10 51 13
METAL LOCKERS
0
09/24/26
09/24/26
95% CD's
11 31 00
RESIDENTIAL APPLIANCES
0
09/24/26
09/24/26
95% CD's
11 53 13
LABORATORY FUME HOODS
0
09/24/26
09/24/26
95% CD's
11 57 00
VOCATIONAL EQUIPMENT
0
09/24/26
09/24/26
95% CD's
11 66 23
GYMNASIUM EQUIPMENT
0
09/24/26
09/24/26
95% CD's
12 24 13
ROLLER WINDOW SHADES
0
09/24/26
09/24/26
95% CD's
12 35 51
MUSIC EDUCATION STORAGE CASEWORK
0
09/24/26
09/24/26
95% CD's
12 66 00
TELESCOPING STANDS
0
09/24/26
09/24/26
95% CD's
11 - Equipment
12 - Furnishings
21 - Fire Suppression 21 05 00
BASIC FIRE SUPPRESSION REQUIREMENTS
0
09/24/26
09/24/26
95% CD's
21 05 03
THROUGH PENETRATION FIRESTOPPING
0
09/24/26
09/24/26
95% CD's
21 05 05
FIRE SUPPRESSION DEMOLITION FOR REMODELING
0
09/24/26
09/24/26
95% CD's
21 05 29
FIRE SUPPRESSION SUPPORTS AND ANCHORS
0
09/24/26
09/24/26
95% CD's
21 05 53
FIRE SUPPRESSION IDENTIFICATION
0
09/24/26
09/24/26
95% CD's
21 13 02
FIRE PROTECTION SYSTEMS
0
09/24/26
09/24/26
95% CD's
22 05 00
BASIC PLUMBING REQUIREMENTS
1
09/24/26
09/24/26
95% CD's
22 05 03
THROUGH PENETRATION FIRESTOPPING
0
09/24/26
09/24/26
95% CD's
22 05 05
PLUMBING DEMOLITION FOR REMODELING
0
09/24/26
09/24/26
95% CD's
22 05 15
PLUMBING EXPANSION COMPENSATION
0
09/24/26
09/24/26
95% CD's
22 05 29
PLUMBING SUPPORTS AND ANCHORS
0
09/24/26
09/24/26
95% CD's
22 05 53
PLUMBING IDENTIFICATION
0
09/24/26
09/24/26
95% CD's
22 05 93
PLUMBING TESTING, ADJUSTING, AND BALANCING
0
09/24/26
09/24/26
95% CD's
22 07 16
PLUMBING EQUIPMENT INSULATION
0
09/24/26
09/24/26
95% CD's
22 07 19
PLUMBING PIPING INSULATION
0
09/24/26
09/24/26
95% CD's
22 08 00
COMMISSIONING OF PLUMBING
0
09/24/26
09/24/26
95% CD's
22 09 00
INSTRUMENTATION
0
09/24/26
09/24/26
95% CD's
22 10 00
PLUMBING PIPING
0
09/24/26
09/24/26
95% CD's
22 10 30
PLUMBING SPECIALTIES
0
09/24/26
09/24/26
95% CD's
22 15 19
COMPRESSED AIR SYSTEMS
0
09/24/26
09/24/26
95% CD's
22 40 00
PLUMBING FIXTURES
0
09/24/26
09/24/26
95% CD's
22 - Plumbing
Page 3 of 5
Printed on Tue Oct 27, 2026 at 01:00 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction
Number
Description
Revision
Issued Date
Received Date
Set
23 - Heating, Ventilating, and Air Conditioning (HVAC) 23 05 00
BASIC HVAC REQUIREMENTS
0
09/24/26
09/24/26
95% CD's
23 05 03
THROUGH PENETRATION FIRESTOPPING
0
09/24/26
09/24/26
95% CD's
23 05 05
HVAC DEMOLITION FOR REMODELING
0
09/24/26
09/24/26
95% CD's
23 05 13
MOTORS
0
09/24/26
09/24/26
95% CD's
23 05 16
HVAC EXPANSION COMPENSATION
0
09/24/26
09/24/26
95% CD's
23 05 29
HVAC SUPPORTS AND ANCHORS
0
09/24/26
09/24/26
95% CD's
23 05 30
ROOF SUPPORT AND WIND BRACING
0
09/24/26
09/24/26
95% CD's
23 05 48
HVAC VIBRATION ISOLATION
0
09/24/26
09/24/26
95% CD's
23 05 53
HVAC IDENTIFICATION
0
09/24/26
09/24/26
95% CD's
23 05 93
TESTING, ADJUSTING, AND BALANCING
0
09/24/26
09/24/26
95% CD's
23 07 13
DUCTWORK INSULATION
0
09/24/26
09/24/26
95% CD's
23 07 19
HVAC PIPING INSULATION
0
09/24/26
09/24/26
95% CD's
23 08 00
COMMISSIONING OF HVAC
0
09/24/26
09/24/26
95% CD's
26 05 00
BASIC ELECTRICAL REQUIREMENTS
0
09/24/26
09/24/26
95% CD's
26 05 03
THROUGH PENETRATION FIRESTOPPING
0
09/24/26
09/24/26
95% CD's
26 05 05
ELECTRICAL DEMOLITION FOR REMODELING
0
09/24/26
09/24/26
95% CD's
26 05 13
WIRE AND CABLE
0
09/24/26
09/24/26
95% CD's
26 05 26
GROUNDING AND BONDING
0
09/24/26
09/24/26
95% CD's
26 05 27
SUPPORTING DEVICES
0
09/24/26
09/24/26
95% CD's
26 05 33
CONDUIT AND BOXES
0
09/24/26
09/24/26
95% CD's
26 05 53
ELECTRICAL IDENTIFICATION
0
09/24/26
09/24/26
95% CD's
26 08 00
COMMISSIONING OF ELECTRICAL
0
09/24/26
09/24/26
95% CD's
26 09 33
LIGHTING CONTROL SYSTEMS
0
09/24/26
09/24/26
95% CD's
26 22 00
DRY TYPE TRANSFORMERS
0
09/24/26
09/24/26
95% CD's
26 24 16
PANELBOARDS
0
09/24/26
09/24/26
95% CD's
26 27 26
WIRING DEVICES
0
09/24/26
09/24/26
95% CD's
26 28 13
FUSES
0
09/24/26
09/24/26
95% CD's
26 28 16
DISCONNECT SWITCHES
0
09/24/26
09/24/26
95% CD's
26 51 19
LED LIGHTING
0
09/24/26
09/24/26
95% CD's
26 - Electrical
27 - Communications 27 05 00
BASIC COMMUNICATIONS SYSTEMS REQUIREMENTS
0
09/24/26
09/24/26
95% CD's
27 05 28
INTERIOR COMMUNICATION PATHWAYS
0
09/24/26
09/24/26
95% CD's
27 05 53
IDENTIFICATION FOR COMMUNICATION SYSTEMS
0
09/24/26
09/24/26
95% CD's
27 15 00
HORIZONTAL CABLING REQUIREMENTS
0
09/24/26
09/24/26
95% CD's
27 17 10
TESTING
0
09/24/26
09/24/26
95% CD's
27 17 20
STRUCTURED CABLING SYSTEM WARRANTY
0
09/24/26
09/24/26
95% CD's
27 41 00
PROFESSIONAL AUDIO/VIDEO SYSTEM
0
09/24/26
09/24/26
95% CD's
0
09/24/26
09/24/26
95% CD's
28 - Electronic Safety and Security 28 13 00
ELECTRONIC ACCESS CONTROL
Page 4 of 5
Printed on Tue Oct 27, 2026 at 01:00 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction
Number 28 31 02
Description
Revision
Issued Date
Received Date
Set
FIRE ALARM AND DETECTION SYSTEMS PERFORMANCE BASED
0
09/24/26
09/24/26
95% CD's
EARTHWORK
1
09/24/26
09/24/26
95% CD's
31 - Earthwork 31 00 00
32 - Exterior Improvements 32 12 00
FLEXIBLE PAVING
0
09/24/26
09/24/26
95% CD's
32 13 00
RIGID PAVING
0
09/24/26
09/24/26
95% CD's
32 31 00
FENCING
0
09/24/26
09/24/26
95% CD's
Page 5 of 5
Exhibit B Assumptions and clarifications made in preparing the GMP
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
October 27th, 2026 Kris Stoppenhagen Executive Director of Bond Planning & Construction Boulder Valley School District 6500 Arapahoe Rd Boulder, CO 80303 RE:
GMP Pricing BVSD Nederland Elementary & Middle-Senior High School Renovations Nederland Elementary – 1 Sundown Train, Nederland, CO 80466 Nederland Middle-Senior High School – 597 CO HWY 130, Nederland, CO 80466
Dear Mr. Stoppenhagen: Howell Construction is pleased to present our GMP pricing for the BVSD Nederland Elementary & Middle-Senior High School Renovations projects. Our proposal is based on the following general inclusions, exclusions, and clarifications: Document Nederland Elementary School Renovation 100% CD Drawings Nederland Middle-Senior High School Renovation 100% CD Drawings Nederland Middle-Senior High School Renovation & Nederland Elementary School Renovation 100% CD Project Manual RFI Responses
Date
Prepared By
10/8/2026
RB+B Architects
10/8/2026
RB+B Architects
10/8/2026
RB+B Architects
N/A
RB+B Architects
GENERAL INCLUSIONS
Our pricing is based on a construction duration of 11 weeks for the elementary school and 36 weeks for the middle-senior high school to accommodate for early fire sprinkler installation per approval from BVSD Full time on-site supervision Standard insurance Insurance, General Liability and Builder’s Risk, per RFP Response Payment & Performance Bond per RFP Response General Conditions and Fees per RFP Response Pricing assumes project is 100% tax exempt 3% construction contingency Assumptions and quantities per detailed budget breakdown Please refer to detailed budget for scopes included in various buckets. Howell has tried to interpret the scope as laid out on documents the best we could for the breakouts. Howell will work with BVSD and RB+B to determine if some of the scope needs to shift to different buckets throughout design development.
Nederland Elementary School
Millwork Howell Construction Since 1935 8085 E. Harvard Ave. Denver, CO 80231 303-696-5800 www.howelldenver.com
BVSD Nederland Elementary & Middle-Senior High School Renovations GMP Proposal October 27th, 2026 Page 2
o Pricing assumes existing millwork to be relocated is in salvageable condition Plumbing & Mechanical o Plumbing and mechanical demolition and safe off o Plumbing fixtures as scheduled o Mechanical equipment as scheduled o Concrete saw cutting / pour back for underslab plumbing o Temperature controls o Test & balance Electrical o Electrical demolition and safe off o Light fixtures as scheduled o Lighting controls o Power and branch circuiting o Fire alarm modifications o Pricing assumes no low voltage cabling / audio visual is required at the Elementary School Earthwork o Includes site demolition Site Concrete o Pricing includes allowance for concrete and masonry retaining wall repair – see below for allowances Asphalt o Includes striping and signage at full depth asphalt replacement areas
Nederland Middle-Senior High School
Demolition o Includes interior demolition – site demolition by earthwork contractor Millwork o Pricing assumes 14ers / Leadership 144 ceiling to be (31) suspended 2” x 8” x 16’ nominal Douglas Fir ceiling joists Glass o Pricing includes windows, curtainwall, and door lites Acoustical Ceilings o Pricing includes allowance to repair damaged / stained / broken ACT throughout the school. Please see below for allowances Flooring o Includes carpet, tile, resilient flooring, resilient base, sealed concrete and fluid applied flooring Wood Flooring o Includes new wood gym flooring Specialties o Alternate #6 locker pricing is based on Penco Gen II Lockers Signage o Pricing includes new code / room signage per schedule on A140 and dimensional letter signage for entry improvements on D3/A201. All other existing room / code signage has been assumed as existing to remain Athletic equipment o Includes basketball and volleyball equipment Howell Construction Since 1935 8085 E. Harvard Ave. Denver, CO 80231 303-696-5800 www.howelldenver.com
BVSD Nederland Elementary & Middle-Senior High School Renovations GMP Proposal October 27th, 2026 Page 3
o Alternate #7 bleacher pricing is based on VersaTract bleachers Fire protection o Includes New wet pipe sprinkler system throughout building, with work starting through the 20262027 school year Plumbing and Mechanical o Plumbing and mechanical demolition and safe off o Plumbing fixtures as scheduled o Mechanical equipment as scheduled o Concrete saw cutting / pour back for underslab plumbing o Temperature controls o Test & balance Electrical o Electrical demolition and safe off o Light fixtures as scheduled o Lighting controls o Power and branch circuiting o Fire alarm modifications Low voltage o Includes low voltage cabling, audio visual, and access control Earthwork o Includes site demolition
ALLOWANCES (Direct Cost Only) - Nederland Elementary School
Masonry & Concrete Retaining Wall repairs - $40,000
ALLOWANCES (Direct Cost Only) - Nederland Elementary School – Bridge Abutment Hardscape Patchback (Only if alternate #6 is not required): 30,000 ALLOWANCES (Direct Cost Only) – Nederland Middle-Senior High School
Roof Patching: $10,000 ACT Tile and Grid Renewal at Damaged and Stained Locations: $80,000 WAF-1 Minor Floor Prep: $13,204 Repair Damaged Wall - Plan East Side of Building: $10,000 Repair Damaged Wall - Plan West Side of Building: $10,000 Relocate Fence / Reset Gate: $15,000 Reinstall Elevator Equipment in New Location: $95,282 Add Heat Trace at Chase, Storm Pipe, Outlet Structure and Cobble Swale at Front Entry RDs: $58,500
ALTERNATES
See Join Log for Alternates Howell Construction Since 1935 8085 E. Harvard Ave. Denver, CO 80231 303-696-5800 www.howelldenver.com
BVSD Nederland Elementary & Middle-Senior High School Renovations GMP Proposal October 27th, 2026 Page 4
EXCLUSIONS We specifically exclude the following:
Hazardous material testing, surveys, removal, handling and disposal Environmental hazards & testing Architectural and engineering design fees Permit and Plan Review Fees Testing and inspection services Seismic requirements Special insurance Consequential damages Owner and design contingencies BIM / 3-D modeling and coordination Rock removal Dewatering Construction Recycling Floor leveling and major floor prep Moisture mitigation in new or existing slabs Building permit and plan check fees State, RTD and SCFD sales tax Furniture moving Supply of residential appliances Boulder County use tax
Thank you for the opportunity to submit our GMP proposal on this exciting project and we look forward to working with the entire team. If you have any questions regarding this information, please feel free to contact me at 720.202.5844. Sincerely, HOWELL CONSTRUCTION SPENCER MOUSSEAU ESTIMATOR O: 303.696.5800 | C: 720.202.5844 SMOUSSEAU@HOWELLDENVER.COM
Howell Construction Since 1935 8085 E. Harvard Ave. Denver, CO 80231 303-696-5800 www.howelldenver.com
Exhibit C Itemization of the GMP
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Boulder Valley School District Nederland Middle-Senior High School - GMP Pricing Revision 1 - 10.28.26
Nederland Middle-Senior High School Item ID # Category MH-1 Exterior Sealants - Roof Renewal
$
108,581
MH-2
Roof Hatches - Access Renewal
$
17,540
$
48,682
$
57,637
$
17,526
$
(40,112)
MH-3
Roof Hatches - Smoke Vents Renewal
$
15,029
$
41,148
$
24,527
$
23,639
$
(888)
MH-4
Exterior Doors - Pair - Hollow Metal - Glazed - Older Renewal
$
30,090
$
24,506
$
6,512
$
27,139
$
20,627
MH-5 MH-6 MH-7 MH-8 MH-9 MH-10 MH-11
Exterior Doors - Single - Hollow Metal - Glazed Renewal Exterior Windows - Broken Panes and Loosen Seal Steel Windows Renewal Skylights - Monumental Renewal Exterior Coatings - Painted Finish Renewal Exterior metal components - repair/ renewal Cabinet Unit Heater - Electric Renewal
$ $ $ $ $ $ $
15,333 10,199 55,111 200,000 75,000 24,072 11,091
$ $ $ $ $ $
15,308 37,206 94,997 246,516 20,365 6,447 N/A - Scope Eliminated
$ $ $ $ $
11,735 29,803 69,339 298,724 11,575 See MH-21 N/A - Scope Eliminated
$ $ $ $ $ $
16,249 13,130 68,147 281,783 39,302 17,313 N/A - Scope Eliminated
$ $ $ $ $ $
4,513 (16,673) (1,192) (16,941) 27,727 17,313
MH-12
Standpipe System - Wet - Light Hazard Renewal
$
415,380
See MH-23
$
19,363
$
MH-13 MH-14 MH-15 MH-16 MH-17 MH-18 MH-19 MH-20 MH-21 MH-22 MH-23 MH-24 MH-25 MH-26 MH-27 MH-28 MH-29 MH-30 MH-31 MH-32 MH-33 MH-33 MH-33 MH-34 MH-35 MH-36 MH-37 MH-38 MH-39
Backboards - Basketball Renewal Scoreboard - Exterior - Single-Sided - Field Renewal Curbs and Gutters - Concrete - Older Renewal Pedestrian Pavement - Concrete - Cracked and Damaged Sidewalk and Curb Pedestrian Pavement - Concrete - Older Renewal Roadway - Pavement - Asphalt - Service Road Renewal Valley Gutter and Flume - Concrete - Older Renewal Plumbing Fixtures - Non-Accessible Toilet Rooms and Showers - HS Lockers ADA - Stairs - Railings Not Compliant ADA - Student Toilets remaining Fire Protection: Sprinkler Coverage Provide Auditorium Renovation Ceiling Finishes - ACT System - Damaged and Stained Painted Finish or Sealer on Concrete Renewal Painted Finish Renewal Fixed Lockers - Metal - Locker Rooms - HS Lockers Renewal Fixed Lockers - Metal - Locker Rooms - MS Lockers Renewal Fixed Casework - Plastic Laminate Countertops - Older Renewal Laboratory Casework Renewal Wood Flooring - HS Gymnasium Renewal CTE Renovations - Entry Improvements CTE Renovations - First Floor Area B CTE Renovations - Stagecraft / Band Generator enclosure assessment LED lighting upgrade assessment Gym Sound Systems ADD - Exterior Sidewalk ADD- Snow Drift ADD - Signage and Striping Totals
$ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $
5,037 35,035 29,132 28,202 23,359 31,660 56,050 893,882 44,311 350,000 1,750,000 750,000 21,540 4,008 8,013 125,000 282,479 150,000 75,000 125,350
$
49,087 N/A - Scope Eliminated 16,490 See MH-17 $ 45,192 $ 140,075 $ 115,881 $ 1,731,654 $ 91,804 $ 798,086 $ 1,760,663 $ 385,673 $ 120,280 N/A - Scope Eliminated $ 31,653 $ 1,345,121 N/A - Scope Eliminated $ 216,146 $ 61,468 $ 231,940
$
112,761 N/A - Scope Eliminated 18,670 66,469 87,981 73,403 20,791 See MH-28 $ 22,978 $ 999,643 $ 1,565,561 $ 1,355,409 $ 83,907 N/A - Scope Eliminated $ 69,160 $ 3,334,317 N/A - Scope Eliminated N/A - Scope Eliminated See Alternate #4 $ 460,708
$
$
$
$ $ $ $ $
$ $ $ $ $
$ $ $ $ $
$
2,200,000
$
$
$ $ $
17,426 100,000 54,000
$
N/A See Below See Below 8,136,910
# N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
Category Alternate No. 1: West Parking Lot Mill and Overlay and Striping Alternate No. 2: New Pan and Underdrain at East Parking Alternate No. 3: Remove Stair and Infill Floor at Corridor 130 Alternate No. 4: Science Lab 236 Renovation Alternate No. 5: Elevator Shaft Finish Renewal Alternate No. 6: HS Locker Room Lockers Renewal Alternate No. 7: Replace Bleachers in HS Gym Alternate No. 8: Gym Sound Systems - Option A Alternate No. 8: Gym Sound Systems - Option B Alternate No. 9: Gym HVAC Noise Remedy Voluntary Alternate - Flooring Scope by Acierno ILO Gary Leimer Totals
RFP Original Budget Construction / Hard Costs
SD Budget 5/14/26
DD Budget 8/6/2026
N/A - Scope Eliminated
2,488,543
N/A - Scope Eliminated $ 400,088 $ 86,416 $ 21,800 See Below See Below $ 10,673,236
N/A - Scope Eliminated
-
$
1,607,898
N/A - Scope Eliminated $ 558,723 See Alternate #8 N/A - Scope Eliminated N/A - Scope Eliminated N/A - Scope Eliminated $ 10,967,592
Nederland Middle-Senior High School Construction / Hard Costs 5/14/26
$
CD GMP 10/23/2026 N/A - Scope Eliminated
$
-
-
N/A
N/A $
43,938 N/A - Scope Eliminated 76,274 17,163 53,040 69,193 107,136 See MH-28 $ 77,258 $ 744,405 $ 1,458,620 $ 914,145 $ 96,216 N/A - Scope Eliminated $ $ 1,574,422 N/A - Scope Eliminated N/A - Scope Eliminated See Alternate #4 $ 351,045 $ 41,108 $ 806,652 $ 1,113,096 N/A - Scope Eliminated $ 9,828 See Alternate #8 N/A - Scope Eliminated N/A - Scope Eliminated N/A - Scope Eliminated $ 8,057,767
$
GMP Alternates 135,224.00 53,960.00 78,264.00 129,537.00 24,913.00 158,287.00 87,166.00 37,172.00 42,232.00 290,112.00 22,143.00 1,059,010
$
8/6/2026
-
DD to CD Budget Variance
$ $ $ $ $ $ $ $ $ $ $ $
Base Bid: $8,057,767 Alt 2: $53,960 Alt 3: $78,264 Alt 7: $87,166 Alt 8A: $37,172 Alt 8B: $42,232 Total: $8,356,561
(19,363)
(68,823) N/A 57,604 (49,306) (34,940) (4,210) 86,345 N/A
$ $ $ $ $
54,280 (255,238) (106,941) (441,265) 12,309 N/A
$ $
(69,160) (1,759,894) N/A N/A N/A
$
(109,663)
$
352,958 N/A
$
(548,895) N/A N/A N/A N/A (2,909,827)
-
Nederland Middle-Senior High School 10/28/2026
CSI 010001 013103 013106 015116 015133 015201 015213 015219 015400 015401 017400 017800 023101 024119 024120 033800 042000 051200 061001 062200 075300 076000 078400 079000 081000 081200 083600 084500 088000 088002 090001 090004 092113 092116 095100 096000 096400 099000 100000 101400 113013
Description Drawings/Blueprints Project Engineer / Field Engineer Superintendent Temporary Fire Extinguishers Cell Phone First Aid Station & Supplies Field Office and Furniture - Onsite Office Temporary Sanitation Drinking Water & Cups Truck General Labor/Clean-up Substantial Completion / Punch List Coordination Ground Penetrating Radar (GPR) Selective Demolition Misc. Demolition/Demolition Support Misc. Concrete Core Drill Patching / Infill Masonry Structural Steel Blocking & Backing Millwork Elastomeric Membrane Roofing Roof Patching - Allowance Firestopping Sealants/Caulking Doors, Frames & Hardware Install Doors, Frames, and Hardware Overhead Doors Translucent Walls and Roof Assemblies Glass and Glazing Temporary Closures at Windows Protection of New and Existing Finishes Final Cleaning Weekly Cleaning Framing and Drywall Acoustical Ceilings Flooring LVT Painting Specialties Signage Woodshop Equipment Install
26 Week Construction Duration Square Footage (RSF) 102,168 Current Pricing Total $/SF $ 950 $ 0.01 $ 68,898 $ 0.67 $ 104,500 $ 1.02 $ 931 $ 0.01 $ 570 $ 0.01 $ 811 $ 0.01 $ 2,252 $ 0.02 $ 9,908 $ 0.10 $ 588 $ 0.01 $ 7,206 $ 0.07 $ 11,138 $ 0.11 $ 4,663 $ 0.05 $ 5,000 $ 0.05 $ 262,380 $ 2.57 $ 21,811 $ 0.21 $ 13,771 $ 0.13 $ 73,519 $ 0.72 $ 103,825 $ 1.02 $ 21,280 $ 0.21 $ 124,876 $ 1.22 $ 16,392 $ 0.16 $ 10,000 $ 0.10 $ 23,388 $ 0.23 $ 38,081 $ 0.37 $ 129,033 $ 1.26 $ 25,136 $ 0.25 $ 28,655 $ 0.28 $ 191,554 $ 1.87 $ 123,436 $ 1.21 $ 35,120 $ 0.34 $ 47,380 $ 0.46 $ 35,759 $ 0.35 $ 26,132 $ 0.26 $ 199,895 $ 1.96 $ 188,119 $ 1.84 $ 227,450 $ 2.23 $ 146,981 $ 1.44 $ 195,092 $ 1.91 $ 94,542 $ 0.93 $ 43,572 $ 0.43 $ 12,209 $ 0.12
Nederland Middle-Senior High School 10/28/2026
CSI 116600 Athletic Equipment 122000 Window Treatments 142000 Elevators 211313 Wet-Pipe Sprinkler Systems 230000 Plumbing & Mechanical 230001 Mechanical Cut and Patch 260000 Electrical 260001 Electrical Cut and Patch 271000 IT/Network Cabling 274000 Audio/Video 281300 Access Control - Allowance 311001 Erosion Control 311313 Tree Protection 312300 Earthwork 312301 Misc. Hand Earthwork 321216 Asphalt Paving 321600 Site Concrete Subtotal Contractor's Cost Contingency 3.00% Subtotal General Liability Insurance Builder's Risk Performance Bond Subtotal Fee 4.96%
Description
26 Week Construction Duration Square Footage (RSF) 102,168 Current Pricing Total $/SF $ 25,624 $ 0.25 $ 25,900 $ 0.25 $ 95,282 $ 0.93 $ 1,212,793 $ 11.87 $ 1,811,938 $ 17.73 $ 34,035 $ 0.33 $ 1,087,715 $ 10.65 $ 25,928 $ 0.25 $ 18,688 $ 0.18 $ 27,206 $ 0.27 $ 29,725 $ 0.29 $ 22,725 $ 0.22 $ 9,952 $ 0.10 $ 50,035 $ 0.49 $ 7,337 $ 0.07 $ 38,725 $ 0.38 $ 96,226 $ 0.94 $ 7,296,637 $ 71.42 $ 218,899 $ 2.14 $ 7,515,536 $ 73.56 $ 80,392 $ 0.79 $ 12,059 $ 0.12 $ 69,001 $ 0.68 $ 7,676,988 $ 75.14 $ 380,779 $ 3.73
Grand Total:
$8,057,767 $78.87 /SF
Exhibit D Contract Schedule & change order for the GMP is Contract Schedule to be provided after amendment executed
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
BVSD Nederland ES & MS/HS Renovation - Master CPM Schedule Master Schedule 10/23/2026
Line Activity ID
Name
PROJECT-WIDE PRECONSTRUCTION (BOTH CONTRACTS)
Duration
Start
Finish
2026 2027 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
22d 10/8/2026
11/9/2026
10/8/2026 *
10/8/2026
95% CD Documents Received (ES & MS/HS)
10/8/2026
10/23/2026
GMP Estimate - ES & MS/HS (Howell)
10/23/2026
10/23/2026
GMP Proposals Submitted to BVSD (2 GMPs)
10/26/2026
11/6/2026
BVSD GMP Review, Board Approval & Amendment Execution
11/9/2026
11/9/2026
Notice to Proceed - Both Contracts
NEDERLAND ELEMENTARY SCHOOL (CONTRACT 1)
227d 9/14/2026
8/6/2027
NEDERLAND MIDDLE / SENIOR HIGH SCHOOL (CONTRACT 2)
212d 10/7/2026
8/10/2027
MS/HS - Permits & Buyout
90d 10/8/2026
2/18/2027
1
2
CD Documents Received (ES & MS/HS)
2
3
GMP Estimate - ES & MS/HS (Howell)
3
4
GMP Proposals Submitted to BVSD (2 GMPs)
4
5
BVSD GMP Review, Board Approval & Amendment Execution
5
6
Notice to Proceed - Both Contracts
12d 10d
+
+
6
77
MS/HS - Issue 100% CD / Permit Set
10d
10/8/2026
10/21/2026
7
78
MS/HS - Permit Submit/Intake (DFPC / Town of Nederland)
5d
10/22/2026
10/28/2026
8
79
MS/HS - Permit Plan Review (cont.)
60d
10/29/2026
1/28/2027
9
83
MS/HS - Subcontract Buyout & Award
10d
11/9/2026
11/20/2026
10
80
MS/HS - Respond to Permit Comments
5d
1/29/2027
2/4/2027
11
81
MS/HS - Permit Re-Review
10d
2/5/2027
2/18/2027
MS/HS - Permit Re-Review
12
82
MS/HS - Building Permit In-Hand (Main Renovation)
2/18/2027
2/18/2027
MS/HS - Building Permit In-Hand (Main Renovation)
MS/HS - Submittals & Procurement
135d 11/23/2026
6/8/2027
MS/HS - Issue 100% CD / Permit Set MS/HS - Permit Plan Review (DFPC / Town of Nederland) MS/HS - Permit Plan Review (cont.) MS/HS - Subcontract Buyout & Award MS/HS - Respond to Permit Comments
13
85
MS/HS - Prepare Submittals (all trades)
20d
11/23/2026
12/22/2026
MS/HS - Prepare Submittals (all trades)
14
87
MS/HS - HV/AHU Submittal - Prepare (expedited)
5d
11/23/2026
12/1/2026
MS/HS - RTU/AHU Submittal - Prepare (expedited)
15
88
MS/HS - HV/AHU Submittal - A/E Review
15d
12/2/2026
12/22/2026
16
86
MS/HS - A/E Submittal Review
15d
12/23/2026
1/18/2027
17
89
MS/HS - Fab/Deliver HV/AHU Units
80d
12/23/2026
4/19/2027
18
2420
MS/HS - Telescoping Bleachers (Alternate)
100d
1/19/2027
6/8/2027
19
90
MS/HS - Fab/Deliver Monumental Skylights
70d
1/19/2027
4/26/2027
20
91
MS/HS - Fab/Deliver Metal Lockers & Benches
50d
1/19/2027
3/29/2027
21
92
MS/HS - Fab/Deliver Maple Gym Flooring System
40d
1/19/2027
3/15/2027
22
93
MS/HS - Fab/Deliver Dust Collectors & CTE Equipment
60d
1/19/2027
4/12/2027
MS/HS - Fab/Deliver Dust Collectors & CTE Equipment
23
94
MS/HS - Fab/Deliver Theatrical Lighting, Dimming & AV
60d
1/19/2027
4/12/2027
MS/HS - Fab/Deliver Theatrical Lighting, Dimming & AV
24
95
60d
1/19/2027
4/12/2027
MS/HS - Fab/Deliver Panelboards & Transformers
40d
1/19/2027
3/15/2027
MS/HS - Fab/Deliver Panelboards & Transformers MS/HS - Fab/Deliver Plumbing Fixtures, Partitions & 25 96 Accessories Drawn by: J. Kellogg
Dwg No. 00001
MS/HS - RTU/AHU Submittal - A/E Review MS/HS - A/E Submittal Review MS/HS - Fab/Deliver RTU/AHU Units MS/HS - Telescoping Bleachers (Alternate) MS/HS - Fab/Deliver Monumental Skylights MS/HS - Fab/Deliver Metal Lockers & Benches MS/HS - Fab/Deliver Maple Gym Flooring System
MS/HS - Fab/Deliver Plumbing Fixtures, Partitions & Accessories Revision No. 0
1 of 8
BVSD Nederland ES & MS/HS Renovation - Master CPM Schedule Master Schedule 10/23/2026
Line Activity ID
Name
Duration
Start
Finish
2026 2027 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
26
97
MS/HS - Fab/Deliver HM Door/Window Frames
30d
1/19/2027
3/1/2027
27
094
MS/HS - Fab/Deliver Wood Doors & HW
50d
1/19/2027
3/29/2027
MS/HS - Fab/Deliver HM Doors, Frames, Hardware & Steel Windows
28
98
MS/HS - Fab/Deliver Casework & Countertops
50d
1/19/2027
3/29/2027
MS/HS - Fab/Deliver Casework & Countertops
29
99
MS/HS - Fab/Deliver LED Fixtures
40d
1/19/2027
3/15/2027
30
100
MS/HS - All Summer Materials On-Site / Staged
4/26/2027
4/26/2027
MS/HS - Fire Sprinkler Addition - Early Package (Winter 2026-27)
162d 10/7/2026
5/28/2027
Fire Sprinkler - Permits & Procurement
30d 10/7/2026
11/17/2026
MS/HS - Fab/Deliver HM Doors, Frames, Hardware & Steel Windows
MS/HS - Fab/Deliver LED Fixtures MS/HS - All Summer Materials On-Site / Staged
31
103
FS - Sprinkler Design Review, Ned Fire / DFPC (remaining)
20d
10/7/2026 *
11/3/2026
FS - Sprinkler Design Review, Ned Fire / DFPC (remaining)
32
105
FS - Submittals & Review
10d
10/21/2026
11/3/2026
FS - Submittals & Review
33
104
FS - DFPC / Ned Sprinkler & FA Permits In-Hand
11/4/2026
11/4/2026
FS - DFPC / Ned Sprinkler & FA Permits In-Hand
34
106
FS - Fabrication & Delivery
10d
11/4/2026
11/17/2026
Fire Sprinkler - Phase I / II / III (Thanksgiving Break thru 12/30/26).Fire Sprinkler - Phase I (Thanksgiving Break thru 12/30/26)
24d 11/23/2026
12/30/2026
FS - Fabrication & Delivery
35
108
FS Ph I - Mobilize & Stage (Thanksgiving Break)
1d 11/23/2026 *
11/23/2026
FS Ph I - Mobilize & Selective Demo (Thanksgiving Break)
36
109
FS Ph I - Fire Service Entry, Riser & Main Piping
3d
11/23/2026
11/25/2026
FS Ph I - Fire Service Entry, Riser & Main Piping
37
110
FS Ph I - Branch Piping, Phase I Areas
3d
11/23/2026
11/25/2026
FS Ph I - Branch Piping, Phase I Areas
38
111
FS Ph I - Complete (Rough / Mains)
11/25/2026
11/25/2026
FS Ph I - Complete / Work Suspended for January
39
1910 FS Ph II - HS Gym
5d
12/7/2026 *
12/11/2026
40
1920 FS Ph II - MS Gym
5d
12/14/2026
12/18/2026
41
1930 FS Ph III - Admin & Cafeteria
6d
12/21/2026
12/30/2026
Fire Sprinkler - Phase IV / V (Night Shift, 2/1/27 Memorial Day).Fire Sprinkler - Phase II (Night Shift, 2/1/27 - Memorial Day)
85d
2/1/2027
5/28/2027
2/1/2027 *
2/2/2027
FS Ph II - HS Gym FS Ph II - MS Gym FS Ph III - Admin & Cafeteria
42
113
FS Ph IV - Remobilize Night Shift
2d
43
114
FS Ph IV - Branch Piping & Heads - Level 1 Area A
15d
2/3/2027
2/23/2027
44
115
FS Ph IV - Branch Piping & Heads - Level 1 Area B
15d
2/24/2027
3/16/2027
45
116
FS Ph V - Branch Piping & Heads - Level 2 Area A
20d
3/17/2027
4/13/2027
46
117
FS Ph V - Branch Piping & Heads - Level 2 Area B
20d
4/14/2027
5/11/2027
FS Ph II - Branch Piping & Heads - Level 2 Area B
47
119
FS Ph V - Ceiling Restoration & Patch/Paint
5d
5/12/2027
5/18/2027
FS Ph II - Ceiling Restoration & Patch/Paint
48
120
FS Ph V - AHJ Sprinkler Partial Inspections
5d
5/19/2027
5/25/2027
FS Ph II - AHJ Sprinkler Final Inspection
49
121
FS Ph V - Punch & Demobilize Night Shift
3d
5/26/2027
5/28/2027
Drawn by: J. Kellogg
Dwg No. 00001
FS Ph II - Remobilize Night Shift FS Ph II - Branch Piping & Heads - Level 1 Area A FS Ph II - Branch Piping & Heads - Level 1 Area B FS Ph II - Branch Piping & Heads - Level 2 Area A
FS Ph II - Punch & Demobilize Night Shift Revision No. 0
2 of 8
BVSD Nederland ES & MS/HS Renovation - Master CPM Schedule Master Schedule 10/23/2026
Line Activity ID
50
122
Name
Duration
2026 2027 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Start
Finish
5/28/2027
5/28/2027
MS/HS - Summer 2027 Construction (Building Unoccupied)
48d 5/24/2027
8/2/2027
Summer Start-up & Owner Abatement
10d 5/24/2027
6/7/2027
5/24/2027 *
5/24/2027
MS/HS - Summer Work Window Opens (school out) MS/HS - Mobilize, Fencing & Temporary Protection
Early Fire Sprinkler Rough Complete
51
125
MS/HS - Summer Work Window Opens (school out)
52
126
MS/HS - Mobilize, Fencing & Temporary Protection
2d
5/24/2027
5/25/2027
53
127
MS/HS - Owner Abatement Wk 1 - Locker Rooms & Student Toilets (by BVSD)
5d
5/24/2027
5/28/2027
54
128
MS/HS - Owner Abatement Wk 2 - CTE, Auditorium & Remaining (by BVSD)
5d
6/1/2027
6/7/2027
HS Locker Rooms (174 / 187)
37d
6/1/2027
7/22/2027
Fire Sprinkler Addition Complete
MS/HS - Owner Abatement Wk 1 - Locker Rooms & Student Toilets (by BVSD) MS/HS - Owner Abatement Wk 2 - CTE, Auditorium & Remaining (by BVSD)
55
130
Locker Rooms - Selective Demo
4d
6/1/2027
6/4/2027
56
131
Locker Rooms - Sawcut, Trench & Under-slab Plumbing
6d
6/7/2027
6/14/2027
Locker Rooms - Sawcut, Trench & Under-slab Plumbing
57
132
Locker Rooms - Trench Backfill & Slab Patch
2d
6/15/2027
6/16/2027
Locker Rooms - Trench Backfill & Slab Patch
58
133
Locker Rooms - Framing & In-wall MEP Rough-in
6d
6/17/2027
6/24/2027
Locker Rooms - Framing & In-wall MEP Rough-in
59
134
Locker Rooms - In-wall / Above-ceiling Inspections
1d
6/25/2027
6/25/2027
Locker Rooms - In-wall / Above-ceiling Inspections
60
135
Locker Rooms - Backer Board, Waterproofing, Gyp & Tape
2d
6/28/2027
6/29/2027
Locker Rooms - Backer Board, Waterproofing, Gyp & Tape
61
2320 Locker Rooms - Concrete Floor Paint (CFP-1)
3d
6/30/2027
7/2/2027
62
136
Locker Rooms - Wall Tile
5d
7/8/2027
7/14/2027
Locker Rooms - Tile Showers, Walls & Floors
63
137
Locker Rooms - Ceilings & Paint
2d
7/15/2027
7/16/2027
Locker Rooms - Ceilings & Paint
64
138
Locker Rooms - Lockers, Benches & Toilet Partitions
3d
7/15/2027
7/19/2027
Locker Rooms - Lockers, Benches & Toilet Partitions
65
139
Locker Rooms - Plumbing & Electrical Fixture Trim-out
3d
7/20/2027
7/22/2027
ADA Student Toilet Rooms / Concessions / Choir.ADA Student Toilet Rooms
40d 5/26/2027
7/22/2027
Locker Rooms - Selective Demo
Locker Rooms - Concrete Floor Paint (CFP-1)
Locker Rooms - Plumbing & Electrical Fixture Trim-out
66
145
Toilets L2 - Selective Demo
3d
5/26/2027
5/28/2027
67
141
Toilets L1 - Selective Demo
3d
6/1/2027
6/3/2027
Toilets L1 - Selective Demo
68
2040 Toilets L2 - Layout & Frame Partitions
3d
6/1/2027
6/3/2027
Toilets L2 - Plumbing, Framing & MEP Rough-in
69
2010 Toilets L1 - Sawcut/Demo SOG
2d
6/3/2027
6/4/2027
Toilets L1 - Sawcut/Demo SOG
70
146
6d
6/4/2027
6/11/2027
Toilets L2 - Plumbing, Framing & MEP Rough-in
71
2020 Toilets L1 - Undeground Plumbing & Slab Patch
5d
6/7/2027
6/11/2027
Toilets L1 - Undeground Plumbing & Slab Patch
72
2000 Toilets L1 - Layout & Frame Partitions
3d
6/14/2027
6/16/2027
Toilets L1 - Plumbing, Framing & MEP Rough-in
73
2050 Toilets L2 - Hang Gyp Board, Tape/Finish
5d
6/14/2027
6/18/2027
Toilets L2 - Hang Gyp Board, Tape/Finish
74
142
Toilets L1 - MEP Rough-in
6d
6/17/2027
6/24/2027
Toilets L1 - Plumbing, Framing & MEP Rough-in
75
2070 Toilets L2 - Resinous Flooring
3d
6/21/2027
6/23/2027
Toilets L2 - Resinous Flooring
Toilets L2 - MEP Rough-in
Drawn by: J. Kellogg
Dwg No. 00001
Toilets L2 - Selective Demo
Revision No. 0
3 of 8
BVSD Nederland ES & MS/HS Renovation - Master CPM Schedule Master Schedule 10/23/2026
Line Activity ID
Name
Toilets L2 - Tile & Finishes
Duration
2026 2027 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Start
Finish
6d
6/24/2027
7/1/2027
Toilets L2 - Board, Tile & Finishes Toilets L1 - Hang Gyp Board, Tape/Finish
76
147
77
2030 Toilets L1 - Hang Gyp Board, Tape/Finish
5d
6/25/2027
7/1/2027
78
2060 Toilets L1 - Resinous Flooring
3d
7/2/2027
7/7/2027
Toilets L1 - Resinous Flooring
79
148
4d
7/2/2027
7/8/2027
Toilets L2 - Partitions, Fixtures & Accessories
80
2090 Choir/Corridor - Ceiling Grid
2d
7/2/2027
7/6/2027
Choir/Corridor - Ceiling Grid
81
2100 Choir/Corridor - Lights & GRD's
2d
7/7/2027
7/8/2027
Choir/Corridor - Lights & GRD's
82
143
Toilets L1 - Tile & Finishes
6d
7/8/2027
7/15/2027
83
2080 Choir/Corridor L2 - Carpet & Base
2d
7/9/2027
7/12/2027
84
144
4d
7/16/2027
7/21/2027
85
2110 Concession L1 - Ceiling Grid
1d
7/16/2027
7/16/2027
Concession L1 - Ceiling Grid
86
2140 L1 - Re-Install Elevator Equipment, Hydraulic Lines
3d
7/16/2027
7/20/2027
L1 - Re-Install Elevator Equipment, Hydraulic Lines
87
2120 Concession L1 - Lights & GRD's
2d
7/19/2027
7/20/2027
Concession L1 - Lights & GRD's
88
2130 L1/L2 - Signage & Final Trims
2d
7/21/2027
7/22/2027
L1/L2 - Signage & Final Trims
CTE Renovations (Libary, Wellness, Bike Tech).CTE Renovations
40d 5/26/2027
7/22/2027
Toilets L2 - Toilet Partitions, Fixtures & Accessories
Toilets L1 - Toilet Partitions, Fixtures & Accessories
Toilets L1 - Board, Tile & Finishes Choir/Corridor L2 - Carpet & Base Toilets L1 - Partitions, Fixtures & Accessories
89
150
CTE - Selective Demo
3d
5/26/2027
5/28/2027
90
1940 CTE - Layout & Frame Partitions
5d
6/1/2027
6/7/2027
91
151
CTE - MEP Rough-in (Walls)
10d
6/8/2027
6/21/2027
CTE - MEP Rough-in (Dust Collection, Compressed Air, Power)
92
152
CTE - Hang Gyp Board, Tape/Finish
8d
6/11/2027
6/22/2027
CTE - Framing, Gyp Board & Paint
93
1980 CTE - Wall Tile
5d
6/23/2027
6/29/2027
94
1950 CTE - Prime & First Coat Paint
2d
6/23/2027
6/24/2027
95
1960 CTE - Ceiling Grid
3d
6/25/2027
6/29/2027
96
1970 CTE - Light Fixtures & GRD's
3d
6/30/2027
7/2/2027
97
2150 CTE - MEP Inspections & Drop Ceiling Tiles
2d
7/6/2027
7/7/2027
98
154
CTE - Install Carpet, Sealed Concrete
5d
7/6/2027
7/12/2027
99
153
CTE - Set Dust Collectors & Shop Equipment
5d
7/13/2027
7/19/2027
CTE - Set Dust Collectors & Shop Equipment
100
1990 CTE - Wall Covering & Final Paint
3d
7/13/2027
7/15/2027
CTE - Wall Covering & Final Paint
101
156
CTE - Equipment Connections & Trim-out
4d
7/15/2027
7/20/2027
CTE - Equipment Connections & Trim-out
102
155
CTE - Display Cases & Marker Boards
5d
7/16/2027
7/22/2027
CTE - Casework & Countertops
Auditorium, Band, Stagecraft Renovation.Auditorium Renovation
32d
6/8/2027
7/22/2027
Drawn by: J. Kellogg
Dwg No. 00001
CTE - Selective Demo CTE - Layout & Frame Partitions
CTE - Wall Tile CTE - Prime & First Coat Paint CTE - Ceiling Grid CTE - Light Fixtures & GRD's CTE - MEP Inspections & Drop Ceiling Tiles CTE - Resinous Flooring
Revision No. 0
4 of 8
BVSD Nederland ES & MS/HS Renovation - Master CPM Schedule Master Schedule 10/23/2026
Line Activity ID
Name
Duration
Start
Finish
2026 2027 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
103
158
Aud/Band/SC - Selective Demo
2d
6/8/2027
6/9/2027
104
2160 Aud/Band/SC - Frame New Partitions
3d
6/10/2027
6/14/2027
Aud/Band/SC - Frame New Partitions
105
2180 Auditorium - Frame Stage Extension/Stairs
3d
6/10/2027
6/14/2027
Auditorium - Frame Stage Extension/Stairs
106
2170 Aud/Band/SC - In-Wall MEP
5d
6/15/2027
6/21/2027
Aud/Band/SC - In-Wall MEP
107
2181 Auditorium - Sheath & Paint Stage Extension
4d
6/15/2027
6/18/2027
Auditorium - Sheath & Paint Stage Extension
108
2280 Auditorium - Stair Treads & Nosings
2d
6/21/2027
6/22/2027
Auditorium - Stair Treads & Nosings
109
2190 Aud/Band/SC - Hang Gyp Board, Tape/Finish
8d
6/22/2027
7/1/2027
CTE - Framing, Gyp Board & Paint
110
2290 Auditorium - Install Hand Rails & Paint
3d
6/23/2027
6/25/2027
Auditorium - Install Hand Rails & Paint
111
159
Auditorium - Theatrical Rigging, Lighting & Dimming
5d
6/23/2027
6/29/2027
Auditorium - Theatrical Rigging, Lighting & Dimming
112
160
Auditorium - Acoustic Panels, Ceilings & Paint
6d
6/29/2027
7/7/2027
Auditorium - Acoustic Panels, Ceilings & Paint
113
161
Auditorium - AV System Install & Programming
5d
6/30/2027
7/7/2027
Auditorium - AV System Install & Programming
114
2200 Aud/Band/SC - Prime & First Coat Paint
2d
7/2/2027
7/6/2027
Aud/Band/SC - Prime & First Coat Paint
115
2201 Aud/Band/SC - Install Casework
3d
7/7/2027
7/9/2027
Aud/Band/SC - Install Casework
116
2210 Aud/Band/SC - Ceiling Grid
2d
7/7/2027
7/8/2027
Aud/Band/SC - Ceiling Grid
117
162
Auditorium - Flooring & Final Finishes
4d
7/8/2027
7/13/2027
Auditorium - Flooring & Final Finishes
118
2220 Aud/Band/SC - Light Fixtures & GRD's
3d
7/9/2027
7/13/2027
Aud/Band/SC - Light Fixtures & GRD's
119
2202 Aud/Band/SC - Install Sinks
2d
7/12/2027
7/13/2027
Aud/Band/SC - Install Sinks
120
2230 Aud/Band/SC - MEP Inspections & Drop Ceiling Tiles
2d
7/14/2027
7/15/2027
Aud/Band/SC - MEP Inspections & Drop Ceiling Tiles
Drawn by: J. Kellogg
Dwg No. 00001
Auditorium - Selective Demo
Revision No. 0
5 of 8
BVSD Nederland ES & MS/HS Renovation - Master CPM Schedule Master Schedule 10/23/2026
Line Activity ID
Name
Duration
Start
Finish
2026 2027 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
121
2240 Aud/Band/SC - Install Carpet, Sealed Concrete
3d
7/14/2027
7/16/2027
CTE - Resinous Flooring
122
163
2d
7/14/2027
7/15/2027
Auditorium - Theatrical/AV Testing & Owner Demo
123
2250 Aud/Band/SC - Final Paint
2d
7/19/2027
7/20/2027
Aud/Band/SC - Final Paint
124
2260 Stage Craft - Install Shop Equipment
2d
7/19/2027
7/20/2027
Stage Craft - Install Shop Equipment
125
2270 Stage Craft - Power Connections to Shop Equipment
2d
7/21/2027
7/22/2027
Stage Craft - Power Connections to Shop Equipment
36d 5/26/2027
7/16/2027
3d
5/26/2027
5/28/2027
Gym - Remove & Store Bleachers (Base Bid)
Auditorium - Theatrical/AV Testing & Owner Demo
HS Gymnasium - Wood Floor, Backboards & Bleachers
126
165
Gym - Remove & Store Bleachers (Base Bid)
127
2300 Gym - Demo Wall & Frame New Door Opening
2d
5/26/2027
5/27/2027
Gym - Demo Wall & Frame New Door Opening
128
169
Gym - Acclimate Maple Flooring On-Site
5d
5/26/2027
6/2/2027
Gym - Acclimate Maple Flooring On-Site
129
166
Gym - Replace Basketball Backboards
3d
6/1/2027
6/3/2027
Gym - Replace Basketball Backboards
130
167
Gym - Demo Existing Wood Floor
4d
6/4/2027
6/9/2027
Gym - Demo Existing Wood Floor
131
168
Gym - Substrate Prep & Moisture Testing
3d
6/10/2027
6/14/2027
132
170
Gym - Install Sleepers/Subfloor & Maple Flooring
8d
6/15/2027
6/24/2027
133
171
Gym - Sand, Seal, Game Lines & Finish Coats
8d
6/25/2027
7/7/2027
134
172
Gym - Finish Cure
3d
7/8/2027
7/12/2027
135
173
Gym - Reinstall Bleachers
4d
7/13/2027
7/16/2027
Envelope & Roof
16d 5/26/2027
6/17/2027
136
175
Envelope - Replace Monumental Skylights
10d
5/26/2027
6/9/2027
137
176
Envelope - Roof Hatches & Smoke Vents
4d
5/26/2027
6/1/2027
Drawn by: J. Kellogg
Dwg No. 00001
Gym - Substrate Prep & Moisture Testing Gym - Install Sleepers/Subfloor & Maple Flooring Gym - Sand, Seal, Game Lines & Finish Coats Gym - Finish Cure Gym - Reinstall Bleachers
Envelope - Replace Monumental Skylights Envelope - Roof Hatches & Smoke Vents Revision No. 0
6 of 8
BVSD Nederland ES & MS/HS Renovation - Master CPM Schedule Master Schedule 10/23/2026
Line Activity ID
Name
Duration
Start
Finish
2026 2027 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
138
177
Envelope - Steel Windows & Glazing Repairs
8d
5/26/2027
6/7/2027
Envelope - Steel Windows & Glazing Repairs
139
178
Envelope - Exterior Doors & Hardware
3d
6/8/2027
6/10/2027
Envelope - Exterior Doors & Hardware
140
180
ADA Stair Railing Modifications
4d
6/8/2027
6/11/2027
ADA Stair Railing Modifications
141
179
Envelope - Exterior Coatings & Metal Repairs
5d
6/11/2027
6/17/2027
HVAC - HV/AHU Replacement.HVAC - RTU/AHU Replacement
38d 5/26/2027
7/20/2027
Envelope - Exterior Coatings & Metal Repairs
142
182
HVAC - Disconnect & Remove Existing Units
3d
5/26/2027
5/28/2027
143
183
HVAC - Curb Adapters & Structural Supports
3d
6/1/2027
6/3/2027
144
194
HVAC - Install New HV/AHU's (Band/Stagecraft)
10d
6/1/2027
6/14/2027
145
184
HVAC - Crane Set New RTU/AHU/EF/CU Units
2d
6/4/2027
6/7/2027
146
185
HVAC - Duct, Piping & Power Connections
10d
6/8/2027
6/21/2027
HVAC - Duct, Piping & Power Connections
147
186
HVAC - Controls / BAS Integration
5d
6/22/2027
6/28/2027
HVAC - Controls / BAS Integration
148
187
HVAC - Start-up, Testing & TAB
5d
6/29/2027
7/6/2027
149
188
MS/HS - Commissioning (HVAC/Plumbing/Electrical)
10d
7/7/2027
7/20/2027
Electrical, Lighting & Low Voltage
28d 5/26/2027
7/6/2027
HVAC - Disconnect & Remove Existing Units HVAC - Curb Adapters & Structural Supports HVAC - Install New HV/AHU's (Band/Stagecraft) HVAC - Crane Set New RTU/AHU Units
HVAC - Start-up, Testing & TAB MS/HS - Commissioning (HVAC/Plumbing/Electrical)
150
190
Electrical - Panel/Transformer Replacement & Shutdowns
4d
5/26/2027
6/1/2027
151
191
Electrical - LED Lighting Upgrades
15d
6/8/2027
6/28/2027
Electrical - LED Lighting Upgrades
152
193
Technology / Low Voltage Cabling
20d
6/8/2027
7/6/2027
Technology / Low Voltage
153
192
Fire Alarm Modifications & Testing
5d
6/29/2027
7/6/2027
Fire Alarm Modifications & Testing
Sitework
17d 5/26/2027
6/18/2027
Drawn by: J. Kellogg
Dwg No. 00001
Electrical - Panel/Transformer Replacement & Shutdowns
Revision No. 0
7 of 8
BVSD Nederland ES & MS/HS Renovation - Master CPM Schedule Master Schedule 10/23/2026
Line Activity ID
Name
Duration
Start
Finish
2026 2027 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
154
198
Site - Erosion & Traffic Control
1d
5/26/2027
5/26/2027
155
199
Site - Demo Concrete & Asphalt
4d
5/27/2027
6/2/2027
Site - Demo Concrete & Asphalt
156
2340 Site - Fence Relocations
5d
5/27/2027
6/3/2027
Site - Fence Relocations
157
200
Site - Curb & Gutter, Valley Gutters & Flumes
5d
6/3/2027
6/9/2027
Site - Curb & Gutter, Valley Gutters & Flumes
158
201
Site - Sidewalks & Pedestrian Pavement
6d
6/7/2027
6/14/2027
Site - Sidewalks & Pedestrian Pavement
159
202
Site - Service Road Asphalt Paving
3d
6/10/2027
6/14/2027
Site - Service Road Asphalt Paving
160
203
Site - Striping & Signage
2d
6/15/2027
6/16/2027
Site - Striping & Restoration
161
2350 Site - Replace Luminaire Heads
2d
6/17/2027
6/18/2027
Site - Replace Luminaire Heads
MS/HS Completion
6d 7/23/2027
8/2/2027
Site - Erosion & Traffic Control
162
205
MS/HS - AHJ Final Inspections
6d
7/23/2027
7/30/2027
MS/HS - AHJ Final Inspections
163
206
MS/HS - Final Clean & Pre-Punch Walk
3d
7/23/2027
7/27/2027
MS/HS - Final Clean & Pre-Punch Walk
164
207
MS/HS - Substantial Completion / TCO
8/2/2027
8/2/2027
MS/HS - Closeout
17d 7/19/2027
8/10/2027
MS/HS - Substantial Completion / TCO
165
211
MS/HS - O&M Manuals, Warranties & Record Documents
15d
7/19/2027
8/6/2027
MS/HS - O&M Manuals, Warranties & Record Documents
166
210
MS/HS - Punch Walk & Corrections
10d
7/28/2027
8/10/2027
MS/HS - Punch List Corrections
167
212
MS/HS - Owner Training & Demonstration
5d
8/2/2027
8/6/2027
MS/HS - Owner Training & Demonstration
168
213
MS/HS - Final Completion
8/10/2027
8/10/2027
MS/HS - Final Completion
Milestone Appearances Start Milestone Drawn by: J. Kellogg
Dwg No. 00001
Revision No. 0
8 of 8
Exhibit E Insurance Insurance Certificates to be provided after Certificates amendment & change order for the GMP is executed
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Client#: 1086501
ACORD
HOWELCON3 DATE (MM/DD/YYYY)
CERTIFICATE OF LIABILITY INSURANCE
TM
10/30/2026
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER. IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must have ADDITIONAL INSURED provisions or be endorsed. If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer any rights to the certificate holder in lieu of such endorsement(s). CONTACT NAME: PHONE (A/C, No, Ext): 800 873-8500 E-MAIL ADDRESS: den.contractors@usi.com
PRODUCER
USI Insurance Services, LLC 4600 S. Ulster Street, Suite 1200 Denver, CO 80237 800 873-8500
INSURER(S) AFFORDING COVERAGE
NAIC #
11150 25674 30830 17370
INSURER A : Arch Insurance Company
INSURED
INSURER B : Travelers Property Cas. Co. of America
Howell Construction James R. Howell & Co., Inc. dba 8085 East Harvard Ave Denver, CO 80231 COVERAGES
FAX (A/C, No):
INSURER C : Arch Indemnity Insurance Company INSURER D : Nautilus Insurance Company INSURER E : INSURER F :
CERTIFICATE NUMBER:
REVISION NUMBER:
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. INSR LTR
TYPE OF INSURANCE
A
COMMERCIAL GENERAL LIABILITY
X
CLAIMS-MADE
ADDL SUBR INSR WVD
X
POLICY NUMBER
X ZAGLB1209400
X OCCUR
POLICY EFF POLICY EXP (MM/DD/YYYY) (MM/DD/YYYY)
LIMITS
09/01/2026 09/01/2027 EACH OCCURRENCE DAMAGE TO RENTED PREMISES (Ea occurrence)
GEN'L AGGREGATE LIMIT APPLIES PER: PROX JECT POLICY LOC
$ 15,000
PERSONAL & ADV INJURY
$ 2,000,000
GENERAL AGGREGATE
$ 4,000,000
PRODUCTS - COMP/OP AGG
$ 4,000,000 $
X
AUTOMOBILE LIABILITY
X ZACAT9386100
SINGLE LIMIT 09/01/2026 09/01/2027 COMBINED (Ea accident)
X ANY AUTO X
OWNED AUTOS ONLY HIRED AUTOS ONLY
$ 350,000
MED EXP (Any one person)
OTHER:
A
$ 2,000,000
BODILY INJURY (Per person)
X
SCHEDULED AUTOS NON-OWNED AUTOS ONLY
$ 2,000,000 $
BODILY INJURY (Per accident) $ PROPERTY DAMAGE (Per accident)
$ $
B
X
UMBRELLA LIAB EXCESS LIAB
C
X
X
OCCUR
X CUPD256077326NF
09/01/2026 09/01/2027 EACH OCCURRENCE
CLAIMS-MADE
X RETENTION $10000 DED WORKERS COMPENSATION AND EMPLOYERS' LIABILITY Y/N ANY PROPRIETOR/PARTNER/EXECUTIVE OFFICER/MEMBER EXCLUDED? N N/A (Mandatory in NH) If yes, describe under DESCRIPTION OF OPERATIONS below
D Pollution Liab Professional Liab
$ 10,000,000 $ 10,000,000
AGGREGATE
$
X ZAWCI1182300
09/01/2026 09/01/2027 X
PER STATUTE
E.L. EACH ACCIDENT
OTHER $ 2,000,000
E.L. DISEASE - EA EMPLOYEE $ 2,000,000
CPP203567415
E.L. DISEASE - POLICY LIMIT $ 2,000,000 09/01/2026 09/01/2027 $2,000,000 Ea Claim $2,000,000 Aggregate $25,000 Retention
DESCRIPTION OF OPERATIONS / LOCATIONS / VEHICLES (ACORD 101, Additional Remarks Schedule, may be attached if more space is required)
Excess Liability: Insurer: Allianz Global Risks US Insurance Co. Policy number: USL03086526 Effective 09/01/2026 to 09/01/2027 Limits: $15,000,000 Each Occurrence $15,000,000 Aggregate (See Attached Descriptions) CERTIFICATE HOLDER
CANCELLATION
Boulder Valley School District No. RE2 6500 Arapahoe Road Boulder, CO 80301
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN ACCORDANCE WITH THE POLICY PROVISIONS. AUTHORIZED REPRESENTATIVE
© 1988-2015 ACORD CORPORATION. All rights reserved. ACORD 25 (2016/03)
1 of 2 #S56402842/M55443956
The ACORD name and logo are registered marks of ACORD
BXFZP
DESCRIPTIONS (Continued from Page 1) RE: Project #2 - Nederland Middle-Senior High School. The General Liability and Automobile Liability policies include an automatic Additional Insured endorsement that provides Additional Insured status to the Boulder Valley School District No. RE2, only when there is a written contract that requires such status, and only with regard to work performed by or on behalf of the named insured. The General Liability and Automobile Liability policies contains a special endorsement with Primary and Noncontributory wording, when required by written contract. The General Liability, Automobile Liability and Workers Compensation policies include a Waiver of Subrogation endorsement in favor of the Certificate Holder as referenced above.
SAGITTA 25.3 (2016/03)
2 of 2
#S56402842/M55443956
COMMERCIAL GENERAL LIABILITY CG 20 33 12 19
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
ADDITIONAL INSURED – OWNERS, LESSEES OR CONTRACTORS – AUTOMATIC STATUS WHEN REQUIRED IN A WRITTEN CONSTRUCTION AGREEMENT WITH YOU This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART A. Section II – Who Is An Insured is amended to include as an additional insured any person or organization for whom you are performing operations when you and such person or organization have agreed in writing in a contract or agreement that such person or organization be added as an additional insured on your policy. Such person or organization is an additional insured only with respect to liability for "bodily injury", "property damage" or "personal and advertising injury" caused, in whole or in part, by: 1. Your acts or omissions; or 2. The acts or omissions of those acting on your behalf;
B. With respect to the insurance afforded to these additional insureds, the following additional exclusions apply:
in the performance of your ongoing operations for the additional insured.
b. Supervisory, inspection, architectural or engineering activities.
However, the insurance additional insured:
This exclusion applies even if the claims against any insured allege negligence or other wrongdoing in the supervision, hiring, employment, training or monitoring of others by that insured, if the "occurrence" which caused the "bodily injury" or "property damage", or the offense which caused the "personal and advertising injury", involved the rendering of or the failure to render any professional architectural, engineering or surveying services.
afforded
to
such
1. Only applies to the extent permitted by law; and 2. Will not be broader than that which you are required by the contract or agreement to provide for such additional insured. A person's or organization's status as an additional insured under this endorsement ends when your operations for that additional insured are completed.
CG 20 33 12 19
This insurance does not apply to: 1. "Bodily injury", "property damage" or "personal and advertising injury" arising out of the rendering of, or the failure to render, any professional architectural, engineering or surveying services, including: a. The preparing, approving, or failing to prepare or approve, maps, shop drawings, opinions, reports, surveys, field orders, change orders or drawings and specifications; or
© Insurance Services Office, Inc., 2018
Page 1 of 2
POLICY NUMBER:
COMMERCIAL GENERAL LIABILITY CG 20 37 07 04
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
ADDITIONAL INSURED – OWNERS, LESSEES OR CONTRACTORS – COMPLETED OPERATIONS This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART SCHEDULE Name Of Additional Insured Person(s) Or Organization(s):
ALL PARTIES WHERE REQUIRED BY A WRITTEN CONTRACT OR WRITTEN AGREEMENT THAT REQUIRE THIS EDITION DATE.
Location And Description Of Completed Operations ALL LOCATIONS WHERE REQUIRED BY A WRITTEN CONTRACT OR WRITTEN AGREEMENT THAT REQUIRE THIS EDITION DATE.
Information required to complete this Schedule, if not shown above, will be shown in the Declarations. Section II – Who Is An Insured is amended to include as an additional insured the person(s) or organization(s) shown in the Schedule, but only with respect to liability for "bodily injury" or "property damage" caused, in whole or in part, by "your work" at the location designated and described in the schedule of this endorsement performed for that additional insured and included in the "productscompleted operations hazard".
CG 20 37 07 04
© ISO Properties, Inc., 2004
Page 1 of 1
COMMERCIAL GENERAL LIABILITY CG 20 01 12 19
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
PRIMARY AND NONCONTRIBUTORY – OTHER INSURANCE CONDITION This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART LIQUOR LIABILITY COVERAGE PART PRODUCTS/COMPLETED OPERATIONS LIABILITY COVERAGE PART The following is added to the Other Insurance Condition and supersedes any provision to the contrary: Primary And Noncontributory Insurance This insurance is primary to and will not seek contribution from any other insurance available to an additional insured under your policy provided that:
(2) You have agreed in writing in a contract or agreement that this insurance would be primary and would not seek contribution from any other insurance available to the additional insured.
(1) The additional insured is a Named Insured under such other insurance; and
CG 20 01 12 19
© Insurance Services Office, Inc., 2018
Page 1 of 1
POLICY NUMBER: 99GLB$%$%$00
COMMERCIAL GENERAL LIABILITY CG 24 04 12 19
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
WAIVER OF TRANSFER OF RIGHTS OF RECOVERY AGAINST OTHERS TO US (WAIVER OF SUBROGATION) This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART ELECTRONIC DATA LIABILITY COVERAGE PART LIQUOR LIABILITY COVERAGE PART POLLUTION LIABILITY COVERAGE PART DESIGNATED SITES POLLUTION LIABILITY LIMITED COVERAGE PART DESIGNATED SITES PRODUCTS/COMPLETED OPERATIONS LIABILITY COVERAGE PART RAILROAD PROTECTIVE LIABILITY COVERAGE PART UNDERGROUND STORAGE TANK POLICY DESIGNATED TANKS SCHEDULE Name Of Person(s) Or Organization(s): AS AGREED PER WRITTEN CONTRACT OR WRITTEN AGREEMENT
Information required to complete this Schedule, if not shown above, will be shown in the Declarations. The following is added to Paragraph 8. Transfer Of Rights Of Recovery Against Others To Us of Section IV – Conditions: We waive any right of recovery against the person(s) or organization(s) shown in the Schedule above because of payments we make under this Coverage Part. Such waiver by us applies only to the extent that the insured has waived its right of recovery against such person(s) or organization(s) prior to loss. This endorsement applies only to the person(s) or organization(s) shown in the Schedule above.
CG 24 04 12 19
© Insurance Services Office, Inc., 2018
Page 1 of 1
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. ADDITIONAL INSURED - BLANKET This endorsement modifies insurance provided under the following: AUTO DEALERS COVERAGE FORM BUSINESS AUTO COVERAGE FORM MOTOR CARRIER COVERAGE FORM Under Covered Autos Liability Coverage, the Who is An Insured provision is amended to include as an "insured" the person or organization who is required under a written contract to be included as an "insured" under this policy, but only with respect to their legal liability for your acts or omissions or the act or omissions of a person for whom Covered Autos Liability Coverage is afforded under this policy. All other terms and conditions of this policy remain unchanged.
Endorsement Number: Policy Number: 99CAT$%$%$00 Named Insured: SAMPLE
AUTO POLICY FOR GCI
This endorsement is effective on the inception date of this Policy unless otherwise stated herein: Endorsement Effective Date: 9/1/2026
00 CA0115 00 10 13
Page 1 of 1
COMMERCIAL AUTO CA 04 49 11 16
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
PRIMARY AND NONCONTRIBUTORY – OTHER INSURANCE CONDITION This endorsement modifies insurance provided under the following: AUTO DEALERS COVERAGE FORM BUSINESS AUTO COVERAGE FORM MOTOR CARRIER COVERAGE FORM With respect to coverage provided by this endorsement, the provisions of the Coverage Form apply unless modified by the endorsement. A. The following is added to the Other Insurance Condition in the Business Auto Coverage Form and the Other Insurance – Primary And Excess Insurance Provisions in the Motor Carrier Coverage Form and supersedes any provision to the contrary: This Coverage Form's Covered Autos Liability Coverage is primary to and will not seek contribution from any other insurance available to an "insured" under your policy provided that: 1. Such "insured" is a Named Insured under such other insurance; and 2. You have agreed in writing in a contract or agreement that this insurance would be primary and would not seek contribution from any other insurance available to such "insured".
CA 04 49 11 16
B. The following is added to the Other Insurance Condition in the Auto Dealers Coverage Form and supersedes any provision to the contrary: This Coverage Form's Covered Autos Liability Coverage and General Liability Coverages are primary to and will not seek contribution from any other insurance available to an "insured" under your policy provided that: 1. Such "insured" is a Named Insured under such other insurance; and 2. You have agreed in writing in a contract or agreement that this insurance would be primary and would not seek contribution from any other insurance available to such "insured".
© Insurance Services Office, Inc., 2016
Page 1 of 1
POLICY NUMBER: 99CAT$%$%$00
COMMERCIAL AUTO CA 04 44 10 13
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
WAIVER OF TRANSFER OF RIGHTS OF RECOVERY AGAINST OTHERS TO US (WAIVER OF SUBROGATION) This endorsement modifies insurance provided under the following: AUTO DEALERS COVERAGE FORM BUSINESS AUTO COVERAGE FORM MOTOR CARRIER COVERAGE FORM With respect to coverage provided by this endorsement, the provisions of the Coverage Form apply unless modified by the endorsement. This endorsement changes the policy effective on the inception date of the policy unless another date is indicated below. Named Insured: Endorsement Effective Date: SCHEDULE Name(s) Of Person(s) Or Organization(s):
ANY PERSON OR ORGANIZATION WHERE WAIVER OF OUR RIGHT TO RECOVER IS PERMITTED BY LAW AND IS REQUIRED BY WRITTEN CONTRACT PROVIDED SUCH CONTRACT WAS EXECUTED PRIOR TO THE LOSS.
Information required to complete this Schedule, if not shown above, will be shown in the Declarations. The Transfer Of Rights Of Recovery Against Others To Us condition does not apply to the person(s) or organization(s) shown in the Schedule, but only to the extent that subrogation is waived prior to the ‘‘accident’’ or the ‘‘loss’’ under a contract with that person or organization.
CA 04 44 10 13
Insurance Services Office, Inc., 2011
Page 1 of 1
WORKERS COMPENSATION AND EMPLOYERS LIABILITY INSURANCE POLICY
WC 00 03 13 (Ed. 4-84)
POLICY NUMBER: 99WCI$%$%$00 WAIVER OF OUR RIGHT TO RECOVER FROM OTHERS ENDORSEMENT
We have the right to recover our payments from anyone liable for an injury covered by this policy. We will not enforce our right against the person or organization named in the Schedule. (This agreement applies only to the extent that you perform work under a written contract that requires you to obtain this agreement from us.) This agreement shall not operate directly or indirectly to benefit anyone not named in the Schedule. Schedule
ANY PERSON OR ORGANIZATION WHERE WAIVER OF OUR RIGHT TO RECOVER IS PERMITTED BY LAW AND IS REQUIRED BY WRITTEN CONTRACT PROVIDED SUCH CONTRACT WAS EXECUTED PRIOR TO DATE OF LOSS.
This endorsement changes the policy to which it is attached and is effective on the date issued unless otherwise stated. (The information below is required only when this endorsement is issued subsequent to preparation of the policy.) Endorsement Effective 09/01/2026
Policy No. 99WCI$%$%$00
Insured SAMPLE WC POLICY FOR GCI Insurance Company ARCH INDEMNITY INSURANCE COMPANY DATE OF ISSUE: 07-15-26
WC 00 03 13 (Ed. 4-84) 1983 National Council on Compensation Insurance.
Countersigned By
Endorsement No. Premium INCL.
Exhibit F Performance Bond to be provided after amendment & change order for the GMP is executed
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit G Labor and Materials Payment Bond to be provided after amendment & change order for the GMP is executed
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit H Alternates prices Alternates prices not used for the amendment # N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
Category Alternate No. 1: West Parking Lot Mill and Overlay and Striping Alternate No. 2: New Pan and Underdrain at East Parking Alternate No. 3: Remove Stair and Infill Floor at Corridor 130 Alternate No. 4: Science Lab 236 Renovation Alternate No. 5: Elevator Shaft Finish Renewal Alternate No. 6: HS Locker Room Lockers Renewal Alternate No. 7: Replace Bleachers in HS Gym Alternate No. 8: Gym Sound Systems - Option A Alternate No. 8: Gym Sound Systems - Option B Alternate No. 9: Gym HVAC Noise Remedy Voluntary Alternate - Flooring Scope by Acierno ILO Gary Leimer Totals
Nederland Middle-Senior High School Construction / Hard Costs 5/14/26
$
-
$
8/6/2026
-
$
-
$ $ $ $ $ $ $ $ $ $ $ $
GMP Alternates 135,224.00 53,960.00 78,264.00 129,537.00 24,913.00 158,287.00 87,166.00 37,172.00 42,232.00 290,112.00 22,143.00 1,059,010
$
Total: $298,794
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
-
Exhibit I prices Unit prices not Unit used for this amendment
Not Applicable
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit J Allowances ALLOWANCES (Direct Cost Only) - Nederland Elementary School
Masonry & Concrete Retaining Wall repairs - $40,000
ALLOWANCES (Direct Cost Only) - Nederland Elementary School – Bridge Abutment Hardscape Patchback (Only if alternate #6 is not required): 30,000 ALLOWANCES (Direct Cost Only) – Nederland Middle-Senior High School
Roof Patching: $10,000 ACT Tile and Grid Renewal at Damaged and Stained Locations: $80,000 WAF-1 Minor Floor Prep: $13,204 Repair Damaged Wall - Plan East Side of Building: $10,000 Repair Damaged Wall - Plan West Side of Building: $10,000 Relocate Fence / Reset Gate: $15,000 Reinstall Elevator Equipment in New Location: $95,282 Add Heat Trace at Chase, Storm Pipe, Outlet Structure and Cobble Swale at Front Entry RDs: $58,500
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit K Not Applicable
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit L Equipment rental rate schedule
Equipment rental rate sheet to be provided after amendment and change order for the GMP is executed
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit M General Conditions of the Contract
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
BOULDER VALLEY SCHOOL DISTRICT RE-2 BOULDER, COLORADO
GENERAL CONTRACT CONDITIONS BOND PROGRAM
GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT.................................................................................................... 2 GC 1.00
CONTRACT DOCUMENTS AND DEFINITIONS ............................................................................................................ 1
GC 2.00
REFERENCE STANDARDS .......................................................................................................................................... 2
GC 3.00
DRAWINGS AND SPECIFICATIONS ............................................................................................................................ 2
GC 4.00
ROYALTIES AND PATENTS ........................................................................................................................................ 3
GC 5.00
ITEMS COVERED BY CONTRACT PRICE ..................................................................................................................... 3
GC 6.00
EXECUTION, CORRELATION, INTENT, AND INTERPRETATION OF CONTRACT DOCUMENTS ...................................... 3
GC 7.00
MATERIALS, LABOR, FACILITIES, AND STORAGE....................................................................................................... 4
GC 8.00
PERFORMANCE AND PAYMENT BONDS ................................................................................................................... 5
GC 9.00
PERMITS AND COMPLIANCE WITH STATUTES, RULES, AND REGULATIONS .............................................................. 6
GC 10.00
SURVEYS, BENCHMARKS, MONUMENTS, STAKES, AND MEASUREMENTS ............................................................... 6
GC 11.00
CHANGED CONDITIONS ........................................................................................................................................... 7
GC 12.00
PROTECTION OF PERSONS, WORK AND PROPERTY ................................................................................................. 7
GC 13.00
WORK ON EXISTING BUILDINGS .............................................................................................................................. 8
GC 14.00
CONTRACTOR’S SUPERINTENDENCE AND SUPERVISION .......................................................................................... 8
GC 15.00
SUBSTITUTIONS ....................................................................................................................................................... 9
GC 16.00
SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES ................................................................................................. 9
GC 17.00
CASH ALLOWANCE................................................................................................................................................. 10
GC 18.00
EXPEDITING MATERIALS ........................................................................................................................................ 10
GC 19.00
BLASTING .............................................................................................................................................................. 11
GC 20.00
SOIL TEST REPORT ................................................................................................................................................. 11
GC 21.00
HAZARDOUS MATERIALS ....................................................................................................................................... 11
GC 22.00
DAMAGE TO UTILITIES ........................................................................................................................................... 11
GC 23.00
CHANGES IN THE WORK ........................................................................................................................................ 12
GC 24.00
CLAIMS FOR EXTRA COST....................................................................................................................................... 13
GC 25.00
DELAYS AND EXTENSIONS OF TIME ....................................................................................................................... 13
GC 26.00
ACCESS TO WORK .................................................................................................................................................. 14
GC 27.00
CORRECTION OF WORK ......................................................................................................................................... 14
GC 28.00
OWNER’S RIGHT TO CARRY OUT WORK ................................................................................................................. 16
GC 29.00
OWNER’S RIGHT TO TERMINATE CONTRACT ......................................................................................................... 16
GC 30.00
CONSTRUCTION SCHEDULE AND PROGRESS REPORTS ........................................................................................... 16
GC 31.00
SCHEDULE OF VALUES ........................................................................................................................................... 17
GC 32.00
PAYMENT .............................................................................................................................................................. 17
GC 33.00
INSURANCE ........................................................................................................................................................... 19
GC 34.00
SEPARATE CONTRACTS .......................................................................................................................................... 23
GC 35.00
SUBCONTRACTORS ................................................................................................................................................ 23
GC 36.00
RELATIONS OF CONTRACTOR AND SUBCONTRACTOR ........................................................................................... 24
GC 37.00
CONTRACTORS’ MUTUAL RESPONSIBILITY ............................................................................................................ 25
GC 38.00
CUTTING, PATCHING, AND EXCAVATING ............................................................................................................... 25
GC 39.00
EMPLOYEES ........................................................................................................................................................... 26
GC 40.00
CLEANING UP......................................................................................................................................................... 27
GC 41.00
USE OF PREMISES .................................................................................................................................................. 27
GC 42.00
OCCUPANCY .......................................................................................................................................................... 27
GC 43.00
TEMPORARY OR TRIAL USAGE ............................................................................................................................... 28
GC 44.00
TESTING OF BUILDING SYSTEMS ............................................................................................................................ 28
GC 45.00
LIQUIDATED DAMAGES FOR DELAY IN COMPLETION ............................................................................................. 28
GC 46.00
ACCEPTANCE AND FINAL PAYMENT ....................................................................................................................... 28
GC 47.00
WARRANTIES ON PORTIONS OF THE WORK .......................................................................................................... 29
GC 48.00
CONTRACTOR’S PROJECT GUARANTEE AFTER COMPLETION ................................................................................. 30
GC 49.00
MISCELLANEOUS KEYS, SWITCHES, ETC. ................................................................................................................ 30
GC 50.00
INDEMNIFICATION ................................................................................................................................................ 30
GC 51.00
LABOR DISPUTES ................................................................................................................................................... 31
GC 52.00
LIMITATION OF ACTIONS ....................................................................................................................................... 31
GC 53.00
PREFERENCE FOR COLORADO LABOR, MATERIALS, AND RESIDENT BIDDERS ........................................................ 31
GC 54.00
SALES AND USE TAX............................................................................................................................................... 31
GC 55.00
LIENS ..................................................................................................................................................................... 32
GC 56.00
OWNER’S INSPECTION OF CONTRACTOR’S RECORDS ............................................................................................ 32
GC 57.00
CERTIFICATION BY CONTRACTOR REGARDING PREMISES ACCESS ......................................................................... 32
GC 58.00
CONTRACTOR SAFETY RESPONSIBILITIES ............................................................................................................... 32
GC 59.00
CONTRACTOR ASBESTOS MANAGEMENT AND LEAD PAINT RESPONSIBILITIES ...................................................... 35
GC 60.00
ARCHITECT’S STATUS AND INSPECTIONS ............................................................................................................... 35
GC 61.00
ORAL STATEMENTS................................................................................................................................................ 35
GC 62.00
PROJECT SIGN ........................................................................................................................................................ 36
GC 63.00
HISTORICAL DATA .................................................................................................................................................. 36
GC 64.00
ASSIGNMENT ......................................................................................................................................................... 36
GC 65.00
TIME OF THE ESSENCE ........................................................................................................................................... 36
GC 66.00
DISPUTES ............................................................................................................................................................... 36
GC 67.00
SURVIVAL .............................................................................................................................................................. 36
GC 1.00
CONTRACT DOCUMENTS AND DEFINITIONS
All Work under the Construction Agreement shall be accomplished in accordance with the Contract Documents, which shall consist of the Request for Qualifications, Request for Proposals, Proposal(s), Notice of Award, Notice to Proceed, Performance Bond, Labor and Material Payment Bond, Construction Agreement, General Contract Conditions, Supplementary Conditions, Asbestos Management Plan Contractor Responsibility Form, Drawings and Specifications, tests and engineering data, approved Change Orders, Contractor’s Requests for Payment, Architect’s Certificates, and all addenda issued by the Owner or Architect prior to execution of the Construction Agreement and all modifications issued by the Owner or Architect after execution of the Construction Agreement. With respect to the Contract Documents, the following definitions and understandings shall control: 1.01 “Contract” or “Contract Documents” shall include all of the items enumerated in GC-1.00 above. 1.02 “Owner” shall mean Boulder Valley School District No. RE-2, and shall include its duly authorized representatives. 1.03 “Contractor” shall mean the corporation, company, partnership, firm, entity, or individual named and designated as such in the Construction Agreement, and any persons or entities acting on its behalf. 1.04 “Subcontractor” shall mean any corporation, partnership, entity, or individual having a direct contract with the Contractor or another subcontractor for performing Work and/or furnishing labor or material on the Project covered by the Contract. 1.05 “Architect” shall mean the corporation, partnership, entity or individual named and designated as “architect” or “engineer” in the Construction Agreement, and any persons or entities acting on the Architect’s behalf and within the scope of the particular duties properly entrusted to them in each case. In the event that there is no Architect on the Project, then “Architect” shall refer to Owner and its duly authorized representative. 1.06 “Notice to Contractor” shall be deemed to have been duly served if made in writing and delivered in person to the individual or to a member of the firm or to an officer of the corporation for which it is intended, or if sent by registered or certified mail, to Contractor’s last known business address. 1.07 “The Work” shall mean the construction and services required by the Contract Documents for completion of the Project, and includes all labor, materials, equipment and services provided or to be provided by the Contractor to fulfill the Contractor’s obligations, whether on or off the Project site, and all labor, materials equipment and services provided or to be provided by subcontractors, sub-subcontractors, or any other entity for whom the Contractor is responsible. 1.08 “The Project” is the total construction designed by the Architect of which the Work performed under the Contract Documents may be the whole or a part. 1.09 The “date of final completion” and “finally completed” shall mean the date when construction is certified by the Architect to be finally completed in accordance with the Contract Documents, as modified by any Change Orders processed under the terms of GC-23.00 below and when the Owner has fully accepted the Project for the use for which it was intended. Such date will be set forth on a letter of acceptance issued by the Owner. 1.010 “Drawings” or “plans” shall mean all (a) drawings furnished by the Owner and/or Architect as a basis for the award of Contract and for construction of the Project; (b) supplementary drawings furnished by the Owner and/or Architect to clarify and to define in greater detail the intent of the Contract drawings and specifications; (c) drawings submitted by the successful Contractor as may be required after the Contract is awarded; (d) drawings furnished by the Owner and/or Architect to the Contractor during the progress of the Work; and (e) engineering data and drawings submitted by the Contractor during the progress of the Work, provided such drawings are acceptable to the Architect and Owner. 1
1.011 “Specifications” are the written technical information concerning materials, components, systems, equipment, and manner of installation as indicated on the drawings or plans and which state the quality, performance, and characteristics to be achieved by application of construction methods. 1.012 “Change Order” shall mean a written order to the Contractor signed by the Owner or its authorized agent issued after the execution of the Construction Agreement, authorizing a change in the Work and/or adjustment in the Guaranteed Maximum Price (“GMP”) or the contract time schedule. Each adjustment in the GMP resulting from a Change Order shall clearly separate the amount attributable to the Cost of the Work and the Contractor’s Fee. 1.013 “day” or “days” shall mean calendar days. In computing a period of days, when the ending date is not specified, the first day is excluded and the last day is included. If any deadline falls on a Saturday, Sunday, or federal or Colorado state holiday, such deadline will be extended to the next day that is not a Saturday, Sunday or federal or Colorado state holiday. GC 2.00
REFERENCE STANDARDS
2.01 Reference to the standards of any technical society, organization, or association, or to codes of local or state authorities, shall mean the latest standard, code, specification, or tentative standard adopted and published as of the date of execution of the Construction Agreement, unless specifically stated otherwise. GC 3.00
DRAWINGS AND SPECIFICATIONS
3.01 Ownership of Drawings. All drawings, specifications, and copies thereof furnished by the Architect are the property of the Architect and the Owner, whether or not the Work for which they are made is performed, and are not to be used on other Work except by written agreement with the Architect and the Owner. 3.02 Figured Dimensions to Govern. Dimensions and elevations shown on the drawings shall be accurately followed. No Work shown on the drawings, the dimensions of which are not indicated, shall be executed until necessary dimensions have been obtained from the Architect. 3.03 Contractor to Check Drawings and Schedules. The Contractor shall check and verify all dimensions, elevations, and quantities shown on the drawings and furnished to it by the Architect, and shall notify the Architect of any discrepancy between the drawings and the conditions on the ground, or any error or omission in drawings, or in the layout as given by stakes, points, or instructions that it may discover. Before ordering any material or doing any Work, the Contractor shall verify all measurements concerning the Project and shall be responsible for the correctness of same. No extra charge or compensation shall be allowed on account of any difference between actual dimensions and the measurements indicated on the drawings. Any difference that may be found shall be submitted to the Architect for consideration and written determination before proceeding with the Work. The Contractor shall not be allowed to take advantage of any error or omission in the drawings or Contract Documents. Full written instructions shall be furnished by the Architect should such error or omission be discovered, and the Contractor shall carry out such instructions as if originally specified. 3.04 Detail Drawings and Instructions. The Architect shall furnish with reasonable promptness additional instructions, by means of drawings or otherwise, necessary for the proper execution of the Work. All such drawings and instructions shall be consistent with the Contract Documents. The Work shall be executed in conformity with the Architect’s drawings and instructions, and the Contractor shall do no Work without proper drawings and instructions. 3.05 Drawings and Specifications Available on the Site. The Contractor shall maintain at the Project site for the Owner and the Architect a Project record set of drawings, including addenda, approved shop drawings, Change Orders, and other modifications, with all changes or deviations from the original drawings neatly marked thereon in a contrasting color. The Contractor shall also maintain a Project record set of specifications at the 2
Project site, noting therein by appropriate section the names, models, and other distinguishing characteristics of the materials actually incorporated into the Work. This Project record set of drawings and specifications shall be updated daily as the Project progresses and shall be made available to the Owner and Architect for inspection at all times. Upon final completion of the Work and before final payment, three (3) copies and one (1) electronic of this Project record set of drawings and specifications shall be delivered to the Owner. One (1) copy of this Project record set of drawings and specification shall be delivered to the Architect. 3.06 Laws and Regulations. The Contractor shall give all notices and comply with all laws, ordinances, rules, and regulations bearing on the conduct of the Work as drawn and specified. If the Contractor observes that the drawings and specifications are at variance therewith, it shall promptly notify the Architect in writing, and any necessary adjustments shall be made as provided in the Contract for changes in the Work. If the Contractor performs any Work knowing it to be contrary to such laws, ordinances, rules, or regulations without giving the required notice to the Architect and receiving a written directive to proceed, it shall bear all costs arising therefrom and to correct and/or remedy same. GC 4.00
ROYALTIES AND PATENTS
The Contractor shall pay all royalties and license fees. The Contractor shall defend all suits or claims for infringement of patent rights and shall hold the Owner harmless from any and all liability or loss on account thereof. If the Contractor has information that the process or article specified involves the infringement of a patent, it shall be responsible for any and all liability or loss resulting therefrom unless it promptly furnishes such information to the Architect in writing. GC 5.00
ITEMS COVERED BY CONTRACT PRICE
5.01 Items Supplied by Owner. Owner shall supply the following items for the Project: a. Building Permit; b. Initial Survey; c. Materials Testing Including Soil Testing; d. Third Party Inspections; e. Commissioning; and f. Test and Balance as Required for Commissioning. 5.02 Items Supplied by Contractor. Unless specifically stated otherwise, the Contractor shall accept the compensation stated in the Construction Agreement as full payment for furnishing all the materials, transportation, apparatus, temporary structures, equipment, services, fuel, energy, light, water, labor and tools, and all other things necessary for the complete and proper execution of the Work contemplated by or reasonably implied from the Contract Documents, within the time limits indicated therein. Such amount shall include any loss or damage resulting from the nature of the Work, from the elements or from any unforeseen difficulties that may be encountered; all risks of every description connected with the prosecution of the Work; all expenses incurred in consequence of any suspension or discontinuance of the Work; and all other amounts necessary for completing the Work pursuant to the Contract Documents within the time limits indicated therein. GC 6.00
EXECUTION, CORRELATION, INTENT, AND INTERPRETATION OF CONTRACT DOCUMENTS
6.01 Execution. The Construction Agreement and other Contract Documents shall be signed in multiple copies as directed by the Owner. Within ten (10) days of Notice of Award, the Contractor shall submit to the Owner a minimum of five (5) fully executed original sets of the Construction Agreement; Performance Bond, and Labor and Material Payment Bond with original Power of Attorney; and certificates of required insurance coverage. The date of the Contract for purposes of these documents shall be the date of the Notice of Award letter. The Owner shall execute the Construction Agreement, assemble all copies, and distribute the Contract Documents. The Contractor shall not commence the Work until it receives the Notice to Proceed. All bonds and insurance 3
certificates shall be submitted to the Owner prior to the award of the first subcontract. 6.02 Correlation. By executing the Construction Agreement, the Contractor represents that it has visited the Project site, familiarized itself with the local conditions under which the Work is to be performed, and correlated its observations with the requirements of the Contract Documents. 6.03 Intent. The intention of the Contract Documents is to include all labor and materials, tools, equipment, construction equipment, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution and completion of the Work. Materials or Work described in words that, as applied, have a well-known technical or trade meaning shall be held to refer to such recognized meaning. The organization of the specifications into divisions, sections, and articles, as the case may be, and the arrangement of drawings shall not control the Contractor in dividing the Work among subcontractors or in establishing the extent of Work to be performed by any trade. It is intended that even though Work is not covered under any heading, division, section, article, branch, class, or trade of the specifications, it shall nevertheless be supplied if it is required elsewhere in the Contract Documents or is reasonably inferable therefrom as being necessary to produce the intended results. The specifications and drawings are intended to supplement but not necessarily duplicate each other. Any Work exhibited in the one and not in the other shall be executed as if it had been set forth in both, so that the Work will be constructed according to the complete design as determined by the Architect. 6.04 Interpretation. Should anything necessary for a clear understanding of the Work be omitted from the specifications and drawings, or should the requirements appear to be in conflict, the Contractor shall secure written interpretations or instructions from the Architect before proceeding with the Work affected thereby. The Contractor shall secure written interpretations or instructions by submitting the Owner’s form Request for Interpretation to the Architect. Oral requests shall not be acknowledged by the Architect or Owner. Additional costs incurred by the Owner as a result of unnecessary requests made by the Contractor, as determined by the Owner, shall be the responsibility of the Contractor. It is understood and agreed that the Work shall be performed according to the true intent of the Contract Documents. 6.05 Conflict in Interpretation. In the case of discrepancy or in the event of a conflict between the different Contract Documents, the documents shall take precedence in the following order: a. Change Orders; b. Written Amendments to Construction Agreement (including, if applicable, the GMP); c. Construction Agreement; d. General Conditions; e. Drawings and specifications; and f. Bid Documents, including addenda. Where two or more of the Contract Documents are complementary, the more detailed provision shall control over the more general provision. GC 7.00
MATERIALS, LABOR, FACILITIES, AND STORAGE
7.01 Contractor’s Responsibility. Unless otherwise agreed in writing, the Contractor shall provide and pay for all materials, labor, tools, equipment, machinery, transportation, and other facilities necessary for the proper execution and completion of the Work. The Contractor shall provide and pay for all the temporary facilities required to supply all the power, light, water, and heat needed by it and its subcontractors for their Work and shall install and maintain all such facilities in such manner as to protect the public and workers and to conform with any applicable laws and regulations. If temporary heat and/or protection is required for the expeditious prosecution of the Work and before the permanent heating apparatus is available for use, the temporary heating apparatus shall be installed and operated in such a manner that the finish Work and/or construction will not be damaged thereby. Unless otherwise specified, the Contractor shall pay for all the power, light, and water used by it and its subcontractors, without regard to whether such items are metered by temporary or permanent meters. The cutoff date on permanent meters shall be either the agreed date of full occupancy by 4
the Owner or the date of final acceptance of the Project, whichever shall be the earlier date. Upon completion of the Work, the Contractor shall remove all surplus materials, tools and such temporary facilities and structures, furnished by the contractor from the Project site. All debris and rubbish caused by the operations of the contractor shall be removed, and the area occupied during construction activities shall be restored to its original condition, within 48 hours of project completion, unless otherwise directed by the municipality or owner’s representative. 7.02 Materials. Unless otherwise specified, all materials shall be new and both Workmanship and materials shall be of the highest quality. The Contractor shall furnish satisfactory evidence to the Owner as to the kind and quality of materials. Samples shall be furnished, when specified, and the Work shall be in accordance with those samples that have been approved. 7.03 Toilet Facilities. The Contractor shall provide and maintain, in a neat and sanitary condition, adequate temporary toilet facilities for the use of any and all employees engaged on the Work, in strict compliance with the requirements of all applicable codes, regulations, laws, and ordinances. In no event may present toilet facilities of any existing building at the site of the Work be used by employees of the Contractor or its subcontractors. Upon final completion of the Work, the Contractor shall remove all such temporary facilities from the site and disinfect the premises. 7.04 Facilities and Storage. The Contractor shall provide suitable temporary facilities and quarters for workers, as needed, and shall maintain on premises water-tight storage sheds or tool houses for storage of building materials and tools that could be damaged by weather. The Contractor shall allow space for the erection of sheds and provide similar facilities for storage by subcontractors of their materials and tools. Storage of materials shall be confined to the site. These facilities or quarters shall further provide for protection against theft and damage of building materials and tools. Upon final completion of the Work, the Contractor shall remove all such temporary facilities from the site. 7.05 Office Space. The Contractor shall provide adequate, weatherproofed, heated and well- lighted office space at the site of the Work, for use by the Architect and the Owner and their representatives. The Contractor shall also provide telephone service at such office, which shall be available for use by the Architect, the Owner, and their representatives without charge, except for toll calls. 7.06 Quality and Location of Facilities. All of the foregoing facilities shall be of a quality and placed in locations acceptable to the Architect and the Owner. GC 8.00
PERFORMANCE AND PAYMENT BONDS
8.01 Required Bonds. The Contractor shall, within ten (10) days from the Notice of Award furnish bonds to the Owner in the full amount of the contract price, covering both the faithful performance of the Contract and the payment of all obligations for labor and materials arising thereunder, on such customary forms as the Owner may prescribe and with such sureties as it may approve. The amount of the bonds shall be increased, if necessary, to reflect approved changes in the Work that result in an increase in the total cost of the Work plus the Contractor’s fees. Such bonds shall be duly executed by a qualified surety licensed to do business in the State of Colorado, conditioned upon the true and faithful performance of the Contract, and shall provide that if the Contractor or its subcontractors fail to duly pay for any labor, materials, or other supplies used or consumed by such Contractor or its subcontractors in the performance of the Work contracted to be done, the surety will pay the same in an amount not exceeding the sum specified in the bond, as adjusted by approved Change Orders, and together with interest as provided by law. The performance bond shall additionally guarantee that the Contractor shall remedy any omissions, correct any and all defects, and adjust and make operable all component parts of Work falling under the requirements of the Contract that may be called to the Contractor’s attention within a period of twenty-four (24) months following the date of the letter of acceptance.
5
8.02 Additional Bond Requirements. The premium for all bonds shall be paid by the Contractor and included in the bid price in the bid proposal. The Owner will accept and approve bonds written by sureties legally authorized to write such bonds in the State of Colorado, provided such surety companies are rated in Best’s Insurance Guide (latest edition), not lower than A- or have Best’s Financial Rating of at least X. If, at any time a surety on such a bond becomes irresponsible or loses its right to do business in the State of Colorado, new bonds shall be provided by an alternate surety licensed to do business in the State and meeting the requirements of this Section 8.00. GC 9.00
PERMITS AND COMPLIANCE WITH STATUTES, RULES, AND REGULATIONS
9.01 Permits. Any local permits, governmental fees, and licenses necessary for the proper execution and completion of the Work shall be secured and paid for by the Contractor. Owner will pay for and secure building permit from Colorado Division of Fire Prevention and Control. Easements for permanent structures or permanent changes in existing facilities shall be secured and paid for by the Owner, unless otherwise specified in writing. The Owner is generally exempt from paying any fee for any building permit issued by any building departments or agencies located in Boulder, Broomfield, and Gilpin Counties, and the Contractor shall see that no building permit fee is paid. The Owner shall negotiate and provide for all electrical, gas, water, and sewer mains for the Contractor’s connections. The Contractor shall arrange with the utility company for actual connection, make necessary connections, and pay for all associated inspection fees and permits as required by any government agency. In addition, the Contractor shall furnish all material and items required to complete all connections. The Contractor shall call for all inspections on a timely basis by any agency having jurisdiction over the Work. 9.02 Compliance with Statutes, Rules and Regulations. The Contractor and all subcontractors shall comply with all applicable federal and state statutes, rules, regulations, and directives of the State Division of Fire Prevention and Control, and other governmental body having jurisdiction over the work to be performed. If any of the provisions of the Contract Documents are in conflict therewith, such portions shall be considered stricken and the applicable statute, ordinance, regulation, or ruling substituted therefor. All such cases of apparent conflict coming to the attention of any party shall immediately be called to the attention of the Owner. The Contractor shall strictly observe and comply with all federal and state laws pertaining to the employment and payment of labor. GC 10.00
SURVEYS, BENCHMARKS, MONUMENTS, STAKES, AND MEASUREMENTS
10.01 Surveys. As provided by the Owner, the Contractor shall obtain from the Architect a copy of all surveys describing property lines, elevation benchmarks, physical characteristics, and utility locations. 10.02 Benchmarks. The Contractor shall properly stake out the Work and provide and rigidly set benchmarks and batter boards as necessary for the proper performance of the Work. The Contractor shall remain responsible for their maintenance and their accuracy. A permanent benchmark, approved as to location and type by the Architect, from which all grades are to be taken, shall be established near the site of the Work by the Contractor. From this benchmark the Contractor shall ascertain all grades and levels to Project buildings as needed. The Contract Documents shall include all necessary information to establish the benchmark. 10.03 Preservation of Monuments and Stakes. The Contractor shall carefully preserve all monuments, benchmarks, property markers, reference points, and stakes. In case of the destruction thereof, the Contractor shall be charged with the expense of replacement and shall be responsible for any mistake or loss of time that may be caused. Permanent monuments and/or benchmarks that must be removed or disturbed shall be protected until properly referenced for relocation. The Contractor shall furnish all materials, labor and assistance for the proper replacement of such monuments and benchmarks. 10.04 Measurements. Before ordering any material or performing any Work, the Contractor shall verify all measurements on the Project and shall be responsible for the accuracy of same. No extra charge or 6
compensation shall be allowed because of any difference between actual dimensions and the measurements indicated in the drawings or specifications. Any discrepancies shall be submitted to the Architect and Owner for consideration before proceeding with the Work. GC 11.00
CHANGED CONDITIONS
The Contractor shall promptly, and before such conditions are disturbed, notify the Owner and the Architect in writing of: (1) sub-surface or latent physical conditions at the Project site differing materially from those indicated in the Contract Documents, or (2) unknown physical conditions at the Project site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in Work of the character provided for in the Contract Documents. The Owner and the Architect shall promptly investigate the conditions, and if the Owner finds that such conditions do so materially differ and cause an increase or decrease in the cost of or the time required for performance of the Work, an equitable adjustment shall be made and the Contract modified in writing accordingly. Any claim of the Contractor for adjustment hereunder shall not be allowed unless it has given notice as required. GC 12.00
PROTECTION OF PERSONS, WORK AND PROPERTY
12.01 Building Exits and Barricades. During the course of construction, the Contractor shall keep all required building exits free and unimpeded. Such exits shall not be closed at any time for any reason while the building is occupied or at any time when the building is unoccupied, except after written approval is given by the Owner and proper warning and directional signs are posted. Barricades shall be erected so that traffic is separated and protected from the construction. 12.02 Precautions. The Contractor shall take all necessary precautions to ensure the safety of all employees and other persons on the Project or who may be affected by the Contractor’s Work thereon. The Contractor shall also take all necessary precautions to protect the Work and all temporary facilities, as well as materials, tools, and equipment incorporated therein or to be incorporated therein from damage or destruction, whether in storage on or off the Project site and whether in the custody or control of the Contractor or any of its subcontractors. The Contractor shall also take all necessary precautions to protect all property at the Project site and adjacent thereto not designated for removal, relocation or replacement, including trees, shrubs, lawns, walks, pavements, roadways, structures, and utilities. 12.03 OSHA Compliance. The Contractor shall comply with all applicable provisions of the Occupational Safety and Health Administration (“OSHA”) and all laws, ordinances, rules, regulations, and orders of all governmental agencies or authorities having jurisdiction to protect the safety of employees and/or other persons who may be affected by the Work. The Contractor shall erect and maintain all necessary safeguards to protect workers on the Project site and the owners and users of adjacent property, and shall post danger signs and other warnings against hazards created by the Work including but not limited to protruding nails, hoists, well holes, elevator shafts, hatchways, scaffolding, window openings, stairways, excavations, and falling materials. The Contractor shall designate a responsible employee at the Project site as a safety officer to ensure the Contractor’s compliance with this section. Said employee shall be the Contractor’s superintendent unless otherwise designated in writing by the Contractor to the Owner and the Architect. 12.04 Contractor’s Liability. The Contractor shall be liable for all injury, damage or loss to any person or property caused in whole or in part by the Contractor, any of its subcontractors, or any person employed by or under the direction of the Contractor or any of its subcontractors. To the extent possible and unless otherwise directed by the Owner or Architect, the Contractor shall promptly repair, pay for or otherwise remedy any such injury, damage or loss and shall indemnify and hold harmless the Owner against any and all liability, claims, damages, losses and expenses arising therefrom. The terms of this section shall not apply in the case of injury, damage or loss proximately caused by the acts or omissions of the Owner and/or Architect and not attributable to any fault or negligence of the Contractor.
7
12.05 Emergencies. In the event of an emergency that threatens the safety or life of any person or threatens to damage or destroy the Project and/or any Work, materials, equipment or property thereon or to be used thereon, the Contractor shall act at its discretion to prevent such injury, death, damage or destruction. The Contractor shall immediately notify the Owner and Architect in writing of any such emergency and any action taken by the Contractor in response thereto. Any compensation due the Contractor for such emergency action shall be determined by agreement of the Contractor, Owner and Architect, and an appropriate Change Order shall be issued therefor. GC 13.00
WORK ON EXISTING BUILDINGS
13.01 Protection of Occupants. In addition to all other requirements of the Contract Documents, if the Work involves an addition or alteration to an existing building, the Contractor shall erect and maintain during the progress of the Work suitable dustproof partitions to protect such building and the occupants thereof. If necessary, in the Owner’s or Contractor’s judgment or pursuant to manufacturer’s directives or recommendations in order to protect occupants from noxious fumes, odors, or hazardous substances, the Contractor may be required to provide additional ventilation and/or work different or extended hours to avoid disruption to other activities within the existing building. Contractor shall protect and keep from harm all occupants of an existing building from construction activities, and shall include a safe pathway into and out of the school. 13.02 Partitions and Scheduling. If any portions of an existing building are to be remodeled or repaired, such portions shall be adequately partitioned off with dustproof partitions and well ventilated. All remodeling Work shall be scheduled and submitted to the Owner and Architect for approval. The various contractors shall schedule their Work jointly, in order that each may accomplish its Work within such existing building in an orderly fashion during regular school vacation periods where possible, or in such a manner as to permit full use of the building and without impairment of any existing facilities. 13.03 Existing Systems. Existing building systems, such as fire alarm, temperature controls and air distribution, security systems, public announcement systems, irrigation systems, and the like, shall be demonstrated and noted by Owner to the Contractor as operational prior to Contractor’s commencing the Work and Contractor may participate in observation of such systems. Such systems are the responsibility of the Contractor to maintain in pre-construction condition. GC 14.00
CONTRACTOR’S SUPERINTENDENCE AND SUPERVISION
14.01 Superintendent. During the progress of the Work, the Contractor shall ensure that a competent superintendent and any necessary assistants, all satisfactory to the Architect and the Owner, are on the Project site at all times while Work is in progress. The superintendent shall not be changed by the Contractor except with the written consent of the Architect and the Owner, unless the superintendent ceases to be in the Contractor’s employ. The superintendent shall represent the Contractor on the Project and all directions given to him/her shall be as binding as if given to the Contractor. The Architect and the Owner shall not be responsible for the acts or omissions of the superintendent or his/her assistants. 14.02 Supervision. The Contractor shall provide full-time, qualified, and efficient supervision of the Work, using competent skill and attention. The Contractor is responsible for determining and supervising all temporary and permanent erection and construction sequences, techniques, means, or methods. The Contractor shall direct, schedule, coordinate the Work to ensure that all parts fit together properly and in accordance with the Contract Documents. The Contractor shall carefully study and compare all Contract Documents and other instructions and shall at once report to the Architect and the Owner any error, inconsistency, or omission that Contractor may discover. 14.03 Additional Supervision Duties. The Contractor shall see that the Work is carried out in accordance with the Contract Documents and in a thorough and first-class manner in every respect. The Contractor shall 8
provide engineering, surveying, and coordination to accurately establish all lines, levels, and marks necessary to facilitate the operations of all parties involved in the Contractor’s Work. The Contractor shall lay out the Work in a manner satisfactory to the Architect, making permanent records of all lines and levels required for excavation, grading, and foundations, and for all other parts of the Work. The Contractor shall be responsible for the commencement and the proper completion of the various stages and sequences of construction. The Contractor shall strictly adhere to the approved construction schedule. GC 15.00
SUBSTITUTIONS
The Contractor shall be held to have used in its base proposal and to furnish under the Contract those items of equipment and/or materials that are specifically identified in the plans and specifications by a manufacturer’s name, model, or catalog number. Items of equipment and/or materials of the Contractor’s choice may be offered as alternates to the items named in the plans and specifications by submitting, with the proposal and on the form provided, identifying data on the articles proposed together with a statement of the amount of addition or deduction from the base bid if the bidder’s alternate is accepted. Prior approval by the Architect is not required on items submitted as alternate bids. After execution of the Construction Agreement, substitution of equipment and/or materials of makes other than those specifically named in the Contract Documents may be approved by the Owner so long as the equipment or material proposed for substitution in the opinion of the Owner is just as suitable as the equipment and/or materials named in the plans and specifications so far as performance, construction, efficiency, and utility are concerned. A request for substitution shall ordinarily be required to be based upon one or more of the following grounds: the specified equipment or material is no longer available, a substitution will improve lead time, quality will be improved (documented detail required), or the Owner will incur substantial savings. All requests for substitution must be submitted in writing with supporting documentation by or through the Contractor to the Architect for initial review and recommendation before being submitted to the Owner for evaluation and final approval. In the absence of the Owner’s written approval, no substitution of equipment or materials shall be allowed for any items specified in the Contract Documents. In case of a difference in price, occurring as a result of an approved substitution, the Owner shall receive all benefit of the difference in cost involved in the substitution. All approved substitutions shall be documented by the issuance of a formal Change Order as provided in these General Conditions. GC 16.00
SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
16.01 Shop Drawings. “Shop drawings” are drawings, diagrams, illustrations, schedules, performance charts, brochures, manufacturer’s literature, and other data that are prepared by the Contractor or any subcontractor, manufacturer, supplier, or distributor, and that illustrate some portion of the Work. Shop drawings shall be submitted in both hard copy and electronic format. 16.02 Samples. “Samples” are physical examples furnished by the Contractor to the Owner and/or Architect to illustrate materials, finishes, equipment, or Workmanship, and to establish standards by which the Work will be judged. 16.03 Product Data. “Product data” are illustrations, standard schedules, performance charts, instructions, brochures, diagrams and other information furnished by the Contractor to illustrate materials or equipment for some portion of the Work. Product data shall be submitted in both hard copy and electronic format. 16.04 Contractor’s Obligations. The Contractor shall review, approve, stamp an then submit to the Architect shop drawings, product data, samples, and similar submittals required by the Contract Documents with reasonable promptness and in such a sequence as to cause no delay in the Work or in the activities of the Owner or of separate contractors. Shop drawings, product data, samples, and similar submittal required by the Contract Documents shall properly identify specified items. At the time of submission, the Contractor shall inform the Architect in writing of any deviation in the shop drawings, product data, or samples from the requirements of the Contract Documents. Substitutions will be allowed only in accordance with the provisions of GC-15.00. The number of copies and format of submittal shall be as required by the Architect, but, at a 9
minimum, shall include three (3) copies and one (1) electronic copy of the original shop drawings and product data for the Owner. 16.05 Verification. By approving and submitting shop drawings, product data, and samples, the Contractor thereby represents that it has determined and verified all field measurements, field construction criteria, dimensions, elevations, quantities, materials, catalog numbers, and similar data, as shown on the drawings and specifications furnished by the Architect, or will do so, and that it has checked and coordinated each shop drawing, product data, and sample with the requirements of the Work and of the Contract Documents. 16.06 Architect /Owner Review. The Architect shall review and approve shop drawings, product data, and samples with reasonable promptness so as to cause no delay, but only for conformance with the design concept of the Project and with the information given in the Contract Documents. The Architect’s approval of a separate item shall not indicate approval of any assembly in which the item functions. Upon the final completion of the Work, the Contractor shall furnish to the Architect two corrected copies of all shop or setting drawings showing the as-built condition of the Work. The Architect, after review, shall submit one of these copies to the Owner. 16.07 Corrections. The Contractor shall make any corrections required by the Architect and shall resubmit the required number of corrected copies of shop drawings or new samples until approved by the Architect. The Contractor shall direct specific attention in a separate writing or on resubmitted shop drawings to revisions other than the corrections requested by the Architect on previous submissions. 16.08 Contractor’s Responsibility. The Architect’s approval of shop drawings, product data, or samples shall not relieve the Contractor of responsibility for any deviation from the requirements of the Contract Documents unless the Contractor has informed the Architect in writing of such deviation at the time of submittal and the Architect has given written approval of the specific deviation. The Architect’s approval shall also not relieve the Contractor from responsibility for errors or omissions in the shop drawings, product data, or samples. 16.09 Architect Approval Required. No portion of the Work requiring the submission of a shop drawing, product data, or sample shall be commenced until such submittal has been approved in writing by the Architect. All such portions of the Work shall be in accordance with approved shop drawings, product data, and samples. All material finishes and samples shall be approved at one time. The Contractor shall submit all items requiring approval of finishes, color, material, etc., with sufficient lead time to allow simultaneous consideration and preparation of complete finish color schedule. No approvals of single items shall be considered. 16.010 Copies to Owner. When shop drawings, product data, samples or similar submittals have been approved and stamped by both Contractor and Architect, Contractor shall immediately forward an electronic copy of each to the Owner. GC 17.00
CASH ALLOWANCE
The Contractor shall include in the Contract sum all allowances named in the Contract Documents and shall cause the work so covered to be done by such Contractors and for such sums as the Owner may direct, the Contract sum being adjusted in conformity therewith. The Contractor declares that the Contract sum includes such sums for expenses and profit on account of cash allowances as he deems proper. No demand for expenses or profit other than those included in the Contract sum shall be allowed. The Contractor shall not be required to employ for any such work persons against whom he has filed a lien or has a reasonable objection due to previous legal claims. GC 18.00
EXPEDITING MATERIALS 10
The Contractor shall, immediately after receipt of the Notice of Award and approval of its list of subcontractors and material suppliers, place orders for all equipment, materials, and supplies required for the Work. The Contractor shall, when requested, submit to the Architect evidence that such orders have been placed. The Contractor shall exercise due diligence in seeing that all equipment, materials, and supplies are delivered well in advance of the time they are needed on the Project and shall properly store and protect same at its expense and in accordance with these General Conditions, either at the Project site or elsewhere as approved by the Architect. GC 19.00
BLASTING
No explosives of any nature except for those normally employed in powder actuated tools, .38 caliber or smaller, shall be employed or used on the Project site except with the express and specific prior written approval of the Architect and the Owner and any appropriate governmental authorities, in each instance. The Contractor shall notify the Architect of need for such approval three (3) days prior to the proposed use of such explosives. GC 20.00
SOIL TEST REPORT
The Owner may arrange for a separate consultant to conduct field and laboratory soil investigations on the Project site and to prepare a report of its findings. Such a report, if prepared, shall be available for review by the Contractor in the Architect’s office. Such data is offered solely for reference and is not to be considered a part of the Contract Documents. The data contained in any such document prepared for the Owner by a separate consultant is believed to be reliable; however, the Owner and Architect do not guarantee its accuracy or completeness. All applicable subcontractors shall be fully familiar with the contents of such reports, if prepared, and shall consider and evaluate them in the performance of their contracts and the Work. GC 21.00
HAZARDOUS MATERIALS
21.01 Responsibility and Reporting. Unless otherwise provided in the Contract Documents, the Contractor shall have no responsibility for the presence, handling, removal or disposal of hazardous materials in any form at the Project site, including but not limited to asbestos, asbestos products, polychlorinated biphenyl (PCB), lead, or other hazardous materials. Prior to its commencement or continuation of any portion of the Work, the Contractor shall provide notice to the Owner of the presence, location, amount and condition of any known or suspected hazardous materials that are discovered at the Project site. Such notice shall be in writing and shall be submitted no more than twenty-four (24) hours after the presence of such materials becomes known or suspected. 21.02 Contractor’s Obligations. In the event hazardous materials become known or suspected by the Contractor as described in GC-21.01 above, the Contractor shall not proceed with or continue the Work until it has received written authorization from the Owner. If the Contractor proceeds with the Work without said authorization, it assumes any and all responsibility and liability for contamination and cleanup at the Project site according to applicable federal and state laws, and for any death or personal injury, including but not limited to medical expenses that may be incurred by any individual as a result of exposure to hazardous materials on the Project site. 21.03 Owner’s Obligations. In the event hazardous materials are identified or encountered during the course of the Project, the Owner at its expense shall take reasonable actions to properly and safely deal with such materials. 21.04 Management Plan. The Contractor acknowledges that it and its employees, agents and subcontractors have the responsibility of being fully informed of the Owner’s Management Plan as it relates to buildings located at the Project site and shall consult with the Owner about how such Plan addresses suspected or active asbestos-containing material areas within such buildings. GC 22.00
DAMAGE TO UTILITIES 11
22.01 Adequate Precautions. The Contractor shall take adequate precautions to protect existing utilities on and off the Project site and avoid damage thereto. The Contractor shall repair or replace or have repaired or replaced at its expense any damage to streets, water, sewer, light, power, cable, or telephone lines or fiber network that are damaged by reason of the Contractor’s Work. 22.02 Location. The location and extent of underground utilities, fiber network, cables and conduit indicated on the drawings are not guaranteed. This information is shown only for such use as bidders and contractors may choose to make of it. The Contractor shall check with all public utility companies for locations and shall comply with their regulations regarding such utilities in performing the Work. 22.03 Protection from Damage. The Contractor shall adequately protect active underground utilities from damage, and if damaged shall immediately effect all necessary repairs. Removal or relocation of active underground utilities shall be done only as indicated on the drawings. If such utilities are in use, they shall be maintained in continuous service. If not indicated on the drawings or not known to exist, the Contractor shall report discovery of such utilities to the Architect and shall not proceed further until directed to do so. 22.04 Inactive or Abandoned Utilities. Inactive or abandoned utilities, whether or not they are indicated on the drawings, shall be recorded as to location and depth and shall be removed for a distance of not less than three (3) feet from the outside line of all concrete Work unless otherwise required by regulations. Ends shall be capped or plugged. There shall be no adjustment of the Contract amount for Work due to inactive or abandoned utilities. GC 23.00
CHANGES IN THE WORK
23.01 Change Orders. The Owner, without invalidating the Agreement, may order changes in the Work within the general scope of the Project consisting of additions, deletions, or other revisions. Under such circumstances, the GMP, if applicable and established, and the Contract Time Schedule shall be adjusted accordingly. All such changes in the Work shall be authorized by Change Order. No Change Order or other form of order or directive by the Owner or Architect requiring additional compensable Work to be performed, which causes the aggregate amount payable under the Contract Documents to exceed the amount appropriated for the original Agreement, shall be issued unless the Contractor is given written assurance by the Owner that lawful appropriations to cover the costs of the additional Work have been made. Any claim of the Contractor for adjustment under this section must be asserted in writing within ten (10) days from the date of the Contractor’s receipt of the Change Order. 23.02 Minor Changes. The Architect shall have authority to order minor changes in the Work not involving an adjustment in the GMP or an extension of the Contract Time Schedule and not inconsistent with the intent of the Contract Documents. Such changes may be effected by field order or by other written order. Such changes shall be binding on the Owner and the Contractor. In any emergency affecting the safety of persons or property, the Contractor shall act, at his discretion, to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in this Article. 23.03 Price Differential. The cost or credit resulting from a change in the Work shall be determined in one or more of the following ways: a. By estimate, with a detailed cost breakdown as set forth in GC-23.03(c) below, and acceptance in a lump sum, with a maximum combined markup to the Owner, for the Contractor and all affected subcontractors, not to exceed a total of fifteen percent (15%). b. By unit prices named in the Contract or subsequently agreed upon. c. If the parties are unable to agree on one of the above methods, then the amount shall be determined by force account under the following formula: i. The actual cost of all direct labor performed (including foremen employed continuously on the Work, but not the salary, or any part thereof, of the Contractor’s superintendent) and the actual 12
ii. iii. iv. v.
vi.
GC 24.00