Ned MSHS CMGC Amendment Exhibits.pdf (4,858 KB)

Regular Meeting, November 10, 2026 · item 7.10: Amendment to the contract for Nederland Middle/High School · 95 pages

Open the original file

This is the text extracted from the file, without its layout, tables, or images. Use the original for anything that matters.

Exhibit A Drawings, specifications and documents used to prepare the GMP

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit A - MSHS Drawings List Printed on Mon Oct 26, 2026 at 03:51 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction

Current Drawings Drawing Number

Drawing Title

Revision

Drawing Date

Received Date

Set

Status

General G000

COVER SHEET

0

09/24/2026

09/24/2026

95% CD's

Published

G101

CODE PLANS

0

09/24/2026

09/24/2026

95% CD's

Published

G102

AFTER HOURS CODE PLANS

0

09/24/2026

09/24/2026

95% CD's

Published

G201

COST BREAKOUT SUMMARY - VFA SCHEDULE AND 1ST FLOOR PLAN

0

09/24/2026

09/24/2026

95% CD's

Published

G202

COST BREAKOUT SUMMARY - 2ND FLOOR PLAN, SITE AND ROOF PLAN

0

09/24/2026

09/24/2026

95% CD's

Published

C001

GENERAL LEGEND NOTES AND ABB.

0

09/24/2026

09/24/2026

95% CD's

Published

C100

OVERALL SITE PLAN

0

09/24/2026

09/24/2026

95% CD's

Published

C101

DETAILED SITE PLAN

0

09/24/2026

09/24/2026

95% CD's

Published

C102

DETAILED SITE PLAN

0

09/24/2026

09/24/2026

95% CD's

Published

C103

SITE DETAILS

0

09/24/2026

09/24/2026

95% CD's

Published

C104

EROSION CONTROL PLAN

0

09/24/2026

09/24/2026

95% CD's

Published

C105

DETAILED EROSION CONTROL PLAN

0

09/24/2026

09/24/2026

95% CD's

Published

C106

DETAILED EROSION CONTROL PLAN

0

09/24/2026

09/24/2026

95% CD's

Published

C107

SWMP & EROSION CONTROL DETAILS

0

09/24/2026

09/24/2026

95% CD's

Published

C108

EROSION CONTROL DETAILS

0

09/24/2026

09/24/2026

95% CD's

Published

S001

GENERAL NOTES

0

09/24/2026

09/24/2026

95% CD's

Published

S002

IBC 2021 STATEMENT OF SPECIAL INSPECTION

0

09/24/2026

09/24/2026

95% CD's

Published

S101

LEVEL ONE FRAMING PLAN

0

09/24/2026

09/24/2026

95% CD's

Published

S102

LEVEL TWO FRAMING PLAN

0

09/24/2026

09/24/2026

95% CD's

Published

S103

ROOF FRAMING PLAN

0

09/24/2026

09/24/2026

95% CD's

Published

Civil

Structural

Page 1 of 7

Printed on Mon Oct 26, 2026 at 03:51 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction

Drawing Number

Drawing Title

Revision

Drawing Date

Received Date

Set

Status

S501

TYPICAL DETAILS

0

09/24/2026

09/24/2026

95% CD's

Published

S601

FOUNDATION & ROOF DETAILS

0

09/24/2026

09/24/2026

95% CD's

Published

A001

ARCHITECTURAL GENERAL NOTES

0

09/24/2026

09/24/2026

95% CD's

Published

A002

WALL & ROOF TYPES

0

09/24/2026

09/24/2026

95% CD's

Published

A003

STANDARD DETAILS

0

09/24/2026

09/24/2026

95% CD's

Published

A004

STANDARD MOUNTING HEIGHTS

0

09/24/2026

09/24/2026

95% CD's

Published

A101

LEVEL ONE FLOOR PLAN

0

09/24/2026

09/24/2026

95% CD's

Published

A101a

LEVEL ONE FLOOR PLAN - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

A101b

LEVEL ONE FLOOR PLAN - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

A102

LEVEL TWO FLOOR PLAN

0

09/24/2026

09/24/2026

95% CD's

Published

A102a

LEVEL TWO FLOOR PLAN -AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

A102b

LEVEL TWO FLOOR PLAN -AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

A120

PROJECT MATERIAL SUMMARY

0

09/24/2026

09/24/2026

95% CD's

Published

A121a

LEVEL ONE FINISH PLAN - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

A121b

LEVEL ONE FINISH PLAN - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

A122a

LEVEL TWO FINISH PLAN -AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

A122b

LEVEL TWO FINISH PLAN -AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

A140

PROJECT EQUIPMENT & SIGNAGE SUMMARY

0

09/24/2026

09/24/2026

95% CD's

Published

A141a

LEVEL ONE EQUIPMENT PLAN -AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

A141b

LEVEL ONE EQUIPMENT PLAN -AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

A142a

LEVEL TWO EQUIPMENT PLAN -AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

A142b

LEVEL TWO EQUIPMENT PLAN -AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

A161a

LEVEL ONE REFLECTED CEILING PLAN -AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

A161b

LEVEL ONE REFLECTED CEILING PLAN -AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

Architectural

Page 2 of 7

Printed on Mon Oct 26, 2026 at 03:51 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction

Drawing Number

Drawing Title

Revision

Drawing Date

Received Date

Set

Status

A162a

LEVEL TWO REFLECTED CEILING PLAN -AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

A162b

LEVEL TWO REFLECTED CEILING PLAN -AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

A181a

ROOF PLAN -AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

A181b

ROOF PLAN -AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

A201

EXTERIOR ELEVATIONS

0

09/24/2026

09/24/2026

95% CD's

Published

A221

INTERIOR ELEVATIONS

0

09/24/2026

09/24/2026

95% CD's

Published

A222

INTERIOR ELEVATIONS

0

09/24/2026

09/24/2026

95% CD's

Published

A223

INTERIOR ELEVATIONS

0

09/24/2026

09/24/2026

95% CD's

Published

A224

INTERIOR ELEVATIONS

0

09/24/2026

09/24/2026

95% CD's

Published

A225

INTERIOR ELEVATIONS

0

09/24/2026

09/24/2026

95% CD's

Published

A226

INTERIOR ELEVATIONS

0

09/24/2026

09/24/2026

95% CD's

Published

A227

INTERIOR ELEVATIONS - ALTERNATES

0

09/24/2026

09/24/2026

95% CD's

Published

A401

ENLARGED RESTROOM PLANS & ELEVATIONS

0

09/24/2026

09/24/2026

95% CD's

Published

A402

ENLARGED RESTROOM PLANS & ELEVATIONS

0

09/24/2026

09/24/2026

95% CD's

Published

A403

ENLARGED RESTROOM PLANS & ELEVATIONS

0

09/24/2026

09/24/2026

95% CD's

Published

A421

VERTICAL CIRCULATION

0

09/24/2026

09/24/2026

95% CD's

Published

A501

INTERIOR DETAILS

0

09/24/2026

09/24/2026

95% CD's

Published

A502

THEATER DETAILS

0

09/24/2026

09/24/2026

95% CD's

Published

A521

EXTERIOR DETAILS

0

09/24/2026

09/24/2026

95% CD's

Published

A561

OPENING DETAILS

0

09/24/2026

09/24/2026

95% CD's

Published

A601

OPENING SCHEDULES & FRAME TYPES

0

09/24/2026

09/24/2026

95% CD's

Published

A611

OPENING & FRAME TYPES

0

09/24/2026

09/24/2026

95% CD's

Published

AD101a

LEVEL ONE DEMOLITION PLAN -AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

AD101b

LEVEL ONE DEMOLITION PLAN -AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

AD102a

LEVEL TWO DEMOLITION PLAN -AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

Page 3 of 7

Printed on Mon Oct 26, 2026 at 03:51 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction

Drawing Number

Drawing Title

Revision

Drawing Date

Received Date

Set

Status

AD102b

LEVEL TWO DEMOLITION PLAN -AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

AD161a

LEVEL ONE DEMOLITION REFLECTED CEILING PLAN -AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

AD161b

LEVEL ONE DEMOLITION REFLECTED CEILING PLAN -AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

AD162a

LEVEL TWO DEMOLITION REFLECTED CEILING PLAN -AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

AD162b

LEVEL TWO DEMOLITION REFLECTED CEILING PLAN -AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

P000

PLUMBING COVERSHEET

0

09/24/2026

09/24/2026

95% CD's

Published

P100a

UNDERFLOOR PLAN - PLUMBING - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

P100b

UNDERFLOOR PLAN - PLUMBING - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

P101a

LEVEL ONE PLAN - PLUMBING - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

P101b

LEVEL ONE PLAN - PLUMBING - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

P102a

LEVEL TWO PLAN - PLUMBING - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

P102b

LEVEL TWO PLAN - PLUMBING - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

P103a

ROOF PLAN - PLUMBING - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

P103b

ROOF PLAN - PLUMBING - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

P400

PLUMBING DETAILS

0

09/24/2026

09/24/2026

95% CD's

Published

P401

PLUMBING DETAILS

0

09/24/2026

09/24/2026

95% CD's

Published

P500

PLUMBING DIAGRAMS

0

09/24/2026

09/24/2026

95% CD's

Published

P501

PLUMBING DIAGRAMS

0

09/24/2026

09/24/2026

95% CD's

Published

P600

PLUMBING SCHEDULES

0

09/24/2026

09/24/2026

95% CD's

Published

PD100a

UNDERFLOOR DEMOLITION PLAN - PLUMBING - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

PD100b

UNDERFLOOR DEMOLITION PLAN - PLUMBING - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

PD101a

LEVEL ONE DEMOLITION PLAN - PLUMBING - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

PD101b

LEVEL ONE DEMOLITION PLAN - PLUMBING - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

PD102a

LEVEL TWO DEMOLITION PLAN - PLUMBING - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

Plumbing

Page 4 of 7

Printed on Mon Oct 26, 2026 at 03:51 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction

Drawing Number PD102b

Drawing Title

Revision

Drawing Date

Received Date

Set

Status

LEVEL TWO DEMOLITION PLAN - PLUMBING - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

M000

HVAC COVERSHEET

0

09/24/2026

09/24/2026

95% CD's

Published

M101a

LEVEL ONE PLAN - HVAC - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

M101b

LEVEL ONE PLAN - HVAC - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

M102a

LEVEL TWO PLAN - HVAC - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

M102b

LEVEL TWO PLAN - HVAC - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

M103a

ROOF PLAN - HVAC - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

M103b

ROOF PLAN - HVAC - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

M400

HVAC DETAILS

0

09/24/2026

09/24/2026

95% CD's

Published

M401

HVAC DETAILS

0

09/24/2026

09/24/2026

95% CD's

Published

M402

HVAC DETAILS

0

09/24/2026

09/24/2026

95% CD's

Published

M500

HVAC DIAGRAMS

0

09/24/2026

09/24/2026

95% CD's

Published

M501

HVAC DIAGRAMS

0

09/24/2026

09/24/2026

95% CD's

Published

M502

HVAC DIAGRAMS

0

09/24/2026

09/24/2026

95% CD's

Published

M600

HVAC SCHEDULES

0

09/24/2026

09/24/2026

95% CD's

Published

M601

HVAC SCHEDULES

0

09/24/2026

09/24/2026

95% CD's

Published

M602

HVAC SCHEDULES

0

09/24/2026

09/24/2026

95% CD's

Published

M603

HVAC SCHEDULES

0

09/24/2026

09/24/2026

95% CD's

Published

MD101a

LEVEL ONE DEMOLITION PLAN - HVAC - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

MD101b

LEVEL ONE DEMOLITION PLAN - HVAC - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

MD102a

LEVEL TWO DEMOLITION PLAN - HVAC - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

MD102b

LEVEL TWO DEMOLITION PLAN - HVAC - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

MD103a

ROOF DEMOLITION PLAN - HVAC - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

MD103b

ROOF DEMOLITION PLAN - HVAC - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

Mechanical

Page 5 of 7

Printed on Mon Oct 26, 2026 at 03:51 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction

Drawing Number

Drawing Title

Revision

Drawing Date

Received Date

Set

Status

Electrical E000

ELECTRICAL COVERSHEET

0

09/24/2026

09/24/2026

95% CD's

Published

E001

ELECTRICAL LIGHTING COVERSHEET

0

09/24/2026

09/24/2026

95% CD's

Published

E010

ELECTRICAL SITE PLAN

0

09/24/2026

09/24/2026

95% CD's

Published

E101a

LEVEL ONE PLAN - LIGHTING - AREA A 09/24/2026

0

09/24/2026

09/24/2026

95% CD's

Published

E101b

LEVEL ONE PLAN - LIGHTING - AREA B 09/24/2026

0

09/24/2026

09/24/2026

95% CD's

Published

E102a

LEVEL TWO PLAN - LIGHTING - AREA A 09/24/2026

0

09/24/2026

09/24/2026

95% CD's

Published

E102b

LEVEL TWO PLAN - LIGHTING - AREA B 09/24/2026

0

09/24/2026

09/24/2026

95% CD's

Published

E111a

LEVEL ONE PLAN - POWER - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

E111b

LEVEL ONE PLAN - POWER - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

E112a

LEVEL TWO PLAN - POWER - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

E112b

LEVEL TWO PLAN - POWER - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

E113a

ROOF PLAN - POWER - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

E113b

ROOF PLAN - POWER - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

E300

ELECTRICAL ENLARGED PLANS

0

09/24/2026

09/24/2026

95% CD's

Published

E400

ELECTRICAL DETAILS

0

09/24/2026

09/24/2026

95% CD's

Published

E500

ELECTRICAL DIAGRAMS

0

09/24/2026

09/24/2026

95% CD's

Published

E600

ELECTRICAL SCHEDULES

0

09/24/2026

09/24/2026

95% CD's

Published

E700

ELECTRICAL PANEL SCHEDULES

0

09/24/2026

09/24/2026

95% CD's

Published

ED101a

LEVEL ONE DEMOLITION PLAN - LIGHTING - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

ED101b

LEVEL ONE DEMOLITION PLAN - LIGHTING - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

ED102a

LEVEL TWO DEMOLITION PLAN - LIGHTING - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

ED102b

LEVEL TWO DEMOLITION PLAN - LIGHTING - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

ED111a

LEVEL ONE DEMOLITION PLAN - POWER - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

ED111b

LEVEL ONE DEMOLITION PLAN - POWER - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

Page 6 of 7

Printed on Mon Oct 26, 2026 at 03:51 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction

Drawing Number

Drawing Title

Revision

Drawing Date

Received Date

Set

Status

ED112a

LEVEL TWO DEMOLITION PLAN - POWER - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

ED112b

LEVEL TWO DEMOLITION PLAN - POWER - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

ED113a

ROOF DEMOLITION PLAN - POWER - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

ED113b

ROOF DEMOLITION PLAN - POWER - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

T000

TECHNOLOGY COVERSHEET

0

09/24/2026

09/24/2026

95% CD's

Published

T201a

LEVEL ONE PLAN - TECHNOLOGY - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

T201b

LEVEL ONE PLAN - TECHNOLOGY - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

T202a

LEVEL TWO PLAN - TECHNOLOGY - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

T202b

LEVEL TWO PLAN - TECHNOLOGY - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

T300

TECHNOLOGY ENLARGED PLANS

0

09/24/2026

09/24/2026

95% CD's

Published

T400

TECHNOLOGY DETAILS

0

09/24/2026

09/24/2026

95% CD's

Published

T500

TECHNOLOGY SCHEDULES

0

09/24/2026

09/24/2026

95% CD's

Published

TD101a

LEVEL ONE DEMOLITION PLAN - TECHNOLOGY - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

TD101b

LEVEL ONE DEMOLITION PLAN - TECHNOLOGY - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

TD102a

LEVEL TWO DEMOLITION PLAN - TECHNOLOGY - AREA A

0

09/24/2026

09/24/2026

95% CD's

Published

TD102b

LEVEL TWO DEMOLITION PLAN - TECHNOLOGY - AREA B

0

09/24/2026

09/24/2026

95% CD's

Published

TL000

THEATRICAL LIGHTING COVER SHEET

0

09/24/2026

09/24/2026

95% CD's

Published

TL101

THEATRICAL LIGHTING LAYOUT FLOOR PLAN

0

09/24/2026

09/24/2026

95% CD's

Published

TL161

THEATRICAL LIGHTING LAYOUT RCP

0

09/24/2026

09/24/2026

95% CD's

Published

TL400

THEATRICAL LIGHTING BATTON ELEVATIONS

0

09/24/2026

09/24/2026

95% CD's

Published

TL600

THEATRICAL LIGHTING SCHEDULE & LEGENDS

0

09/24/2026

09/24/2026

95% CD's

Published

TL700

THEATRICAL LIGHTING CONTROL SCHEDULE

0

09/24/2026

09/24/2026

95% CD's

Published

TL800

THEATRICAL LIGHTING OVERALL TOPOLOGY

0

09/24/2026

09/24/2026

95% CD's

Published

TL900

THEATRICAL LIGHTING DIMMING ONELINE

0

09/24/2026

09/24/2026

95% CD's

Published

Telecommunications

Page 7 of 7

Exhibit A - MSHS Specifications List Printed on Tue Oct 27, 2026 at 01:00 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction

Current Specifications Number

Description

Revision

Issued Date

Received Date

Set

00 - Procurement and Contracting Requirements 00 01 10

Table of Contents

0

09/24/26

09/24/26

95% CD's

00 26 00

PROCUREMENT SUBSTITUTION PROCEDURES

0

09/24/26

09/24/26

95% CD's

00 31 00

AVAILABLE PROJECT INFORMATION

0

09/24/26

09/24/26

95% CD's

00 31 26

EXISTING HAZARDOUS MATERIAL INFORMATION

0

09/24/26

09/24/26

95% CD's

00 72 00

GENERAL CONDITIONS

0

09/24/26

09/24/26

95% CD's

01 - General Requirements 01 10 00

SUMMARY

0

09/24/26

09/24/26

95% CD's

01 23 00

ALTERNATES

0

09/24/26

09/24/26

95% CD's

01 25 00

SUBSTITUTION PROCEDURES

0

09/24/26

09/24/26

95% CD's

01 26 00

CONTRACT MODIFICATION PROCEDURES

0

09/24/26

09/24/26

95% CD's

01 29 00

PAYMENT PROCEDURES

0

09/24/26

09/24/26

95% CD's

01 31 00

PROJECT MANAGEMENT AND COORDINATION

0

09/24/26

09/24/26

95% CD's

01 32 00

CONSTRUCTION PROGRESS DOCUMENTATION

0

09/24/26

09/24/26

95% CD's

01 33 00

SUBMITTAL PROCEDURES

0

09/24/26

09/24/26

95% CD's

01 35 43

CARPET RECLAMATION

0

09/24/26

09/24/26

95% CD's

01 40 00

QUALITY REQUIREMENTS

0

09/24/26

09/24/26

95% CD's

01 50 00

TEMPORARY FACILITIES AND CONTROLS

0

09/24/26

09/24/26

95% CD's

01 60 00

PRODUCT REQUIREMENTS

0

09/24/26

09/24/26

95% CD's

01 73 00

EXECUTION

0

09/24/26

09/24/26

95% CD's

01 74 19

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

0

09/24/26

09/24/26

95% CD's

01 77 00

CLOSEOUT PROCEDURES

0

09/24/26

09/24/26

95% CD's

01 78 23

OPERATION AND MAINTENANCE DATA

0

09/24/26

09/24/26

95% CD's

01 78 39

PROJECT RECORD DOCUMENTS

0

09/24/26

09/24/26

95% CD's

01 79 00

DEMONSTRATION AND TRAINING

0

09/24/26

09/24/26

95% CD's

01 81 13

SUSTAINABLE DESIGN

0

09/24/26

09/24/26

95% CD's

01 91 13

GENERAL COMMISSIONING REQUIREMENTS

0

09/24/26

09/24/26

95% CD's

SELECTIVE DEMOLITION

0

09/24/26

09/24/26

95% CD's

03 30 00

CAST-IN-PLACE CONCRETE

0

09/24/26

09/24/26

95% CD's

03 35 46

CONCRETE FINISHING

0

09/24/26

09/24/26

95% CD's

MASONRY

0

09/24/26

09/24/26

95% CD's

05 05 13

SHOP-APPLIED STEEL FINISHES

0

09/24/26

09/24/26

95% CD's

05 31 00

STEEL DECKING

0

09/24/26

09/24/26

95% CD's

02 - Existing Conditions 02 41 19 03 - Concrete

04 - Masonry 04 20 00 05 - Metals

Page 1 of 5

Printed on Tue Oct 27, 2026 at 01:00 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction

Number

Description

Revision

Issued Date

Received Date

Set

05 50 00

METAL FABRICATIONS

0

09/24/26

09/24/26

95% CD's

05 52 13

PIPE AND TUBE RAILINGS

0

09/24/26

09/24/26

95% CD's

06 - Wood, Plastics, and Composites 06 10 00

ROUGH CARPENTRY

0

09/24/26

09/24/26

95% CD's

06 20 23

INTERIOR FINISH CARPENTRY

0

09/24/26

09/24/26

95% CD's

06 36 61

SIMULATED SURFACE COUNTERTOPS

0

09/24/26

09/24/26

95% CD's

06 41 00

ARCHITECTURAL CASEWORK

0

09/24/26

09/24/26

95% CD's

06 64 00

PLASTIC PANELING

0

09/24/26

09/24/26

95% CD's

07 - Thermal and Moisture Protection 07 21 00

THERMAL INSULATION

0

09/24/26

09/24/26

95% CD's

07 51 14

PATCH EXISTING ROOFING

0

09/24/26

09/24/26

95% CD's

07 62 00

SHEET METAL FLASHING AND TRIM

0

09/24/26

09/24/26

95% CD's

07 63 00

FLASHING

0

09/24/26

09/24/26

95% CD's

07 72 00

ROOF ACCESSORIES

0

09/24/26

09/24/26

95% CD's

07 84 13

PENETRATION FIRESTOPPING

0

09/24/26

09/24/26

95% CD's

07 84 43

JOINT FIRESTOPPING

0

09/24/26

09/24/26

95% CD's

07 92 00

JOINT SEALANTS

0

09/24/26

09/24/26

95% CD's

08 11 13

HOLLOW METAL DOORS AND FRAMES

0

09/24/26

09/24/26

95% CD's

08 14 16

FLUSH WOOD DOORS

0

09/24/26

09/24/26

95% CD's

08 31 13

ACCESS DOORS AND FRAMES

0

09/24/26

09/24/26

95% CD's

08 33 23

OVERHEAD COILING DOORS

0

09/24/26

09/24/26

95% CD's

08 41 13

ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

0

09/24/26

09/24/26

95% CD's

08 42 43

SLIDING ENTRANCES

0

09/24/26

09/24/26

95% CD's

08 44 13

GLAZED ALUMINUM CURTAIN WALLS

0

09/24/26

09/24/26

95% CD's

08 45 23

FIBERGLASS-SANDWICH-PANEL ASSEMBLIES

0

09/24/26

09/24/26

95% CD's

08 62 00

UNIT SKYLIGHTS

0

09/24/26

09/24/26

95% CD's

08 71 00

DOOR HARDWARE

0

09/24/26

09/24/26

95% CD's

08 80 00

GLAZING

0

09/24/26

09/24/26

95% CD's

09 29 00

GYPSUM BOARD

0

09/24/26

09/24/26

95% CD's

09 30 00

TILING

0

09/24/26

09/24/26

95% CD's

09 51 13

ACOUSTICAL PANEL CEILINGS

0

09/24/26

09/24/26

95% CD's

09 64 00

WOOD FLOORING

0

09/24/26

09/24/26

95% CD's

09 65 13

RESILIENT BASE AND ACCESSORIES

0

09/24/26

09/24/26

95% CD's

09 65 19

RESILIENT TILE AND PLANK FLOORING

0

09/24/26

09/24/26

95% CD's

09 67 23

RESINOUS FLOORING

0

09/24/26

09/24/26

95% CD's

09 68 13

CARPETING

0

09/24/26

09/24/26

95% CD's

09 72 16

VINYL GRAPHIC FILM

0

09/24/26

09/24/26

95% CD's

09 84 00

ACOUSTIC COMPONENTS

0

09/24/26

09/24/26

95% CD's

09 91 00

PAINTING

0

09/24/26

09/24/26

95% CD's

08 - Openings

09 - Finishes

Page 2 of 5

Printed on Tue Oct 27, 2026 at 01:00 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction

Number

Description

Revision

Issued Date

Received Date

Set

10 - Specialties 10 11 00

VISUAL DISPLAY SURFACES

0

09/24/26

09/24/26

95% CD's

10 12 00

DISPLAY CASES

0

09/24/26

09/24/26

95% CD's

10 14 19

DIMENSIONAL LETTER SIGNAGE

0

09/24/26

09/24/26

95% CD's

10 14 23

PANEL SIGNAGE

0

09/24/26

09/24/26

95% CD's

10 21 13

TOILET COMPARTMENTS

0

09/24/26

09/24/26

95% CD's

10 26 00

WALL AND DOOR PROTECTION

0

09/24/26

09/24/26

95% CD's

10 28 00

TOILET, BATH AND LAUNDRY ACCESSORIES

0

09/24/26

09/24/26

95% CD's

10 51 13

METAL LOCKERS

0

09/24/26

09/24/26

95% CD's

11 31 00

RESIDENTIAL APPLIANCES

0

09/24/26

09/24/26

95% CD's

11 53 13

LABORATORY FUME HOODS

0

09/24/26

09/24/26

95% CD's

11 57 00

VOCATIONAL EQUIPMENT

0

09/24/26

09/24/26

95% CD's

11 66 23

GYMNASIUM EQUIPMENT

0

09/24/26

09/24/26

95% CD's

12 24 13

ROLLER WINDOW SHADES

0

09/24/26

09/24/26

95% CD's

12 35 51

MUSIC EDUCATION STORAGE CASEWORK

0

09/24/26

09/24/26

95% CD's

12 66 00

TELESCOPING STANDS

0

09/24/26

09/24/26

95% CD's

11 - Equipment

12 - Furnishings

21 - Fire Suppression 21 05 00

BASIC FIRE SUPPRESSION REQUIREMENTS

0

09/24/26

09/24/26

95% CD's

21 05 03

THROUGH PENETRATION FIRESTOPPING

0

09/24/26

09/24/26

95% CD's

21 05 05

FIRE SUPPRESSION DEMOLITION FOR REMODELING

0

09/24/26

09/24/26

95% CD's

21 05 29

FIRE SUPPRESSION SUPPORTS AND ANCHORS

0

09/24/26

09/24/26

95% CD's

21 05 53

FIRE SUPPRESSION IDENTIFICATION

0

09/24/26

09/24/26

95% CD's

21 13 02

FIRE PROTECTION SYSTEMS

0

09/24/26

09/24/26

95% CD's

22 05 00

BASIC PLUMBING REQUIREMENTS

1

09/24/26

09/24/26

95% CD's

22 05 03

THROUGH PENETRATION FIRESTOPPING

0

09/24/26

09/24/26

95% CD's

22 05 05

PLUMBING DEMOLITION FOR REMODELING

0

09/24/26

09/24/26

95% CD's

22 05 15

PLUMBING EXPANSION COMPENSATION

0

09/24/26

09/24/26

95% CD's

22 05 29

PLUMBING SUPPORTS AND ANCHORS

0

09/24/26

09/24/26

95% CD's

22 05 53

PLUMBING IDENTIFICATION

0

09/24/26

09/24/26

95% CD's

22 05 93

PLUMBING TESTING, ADJUSTING, AND BALANCING

0

09/24/26

09/24/26

95% CD's

22 07 16

PLUMBING EQUIPMENT INSULATION

0

09/24/26

09/24/26

95% CD's

22 07 19

PLUMBING PIPING INSULATION

0

09/24/26

09/24/26

95% CD's

22 08 00

COMMISSIONING OF PLUMBING

0

09/24/26

09/24/26

95% CD's

22 09 00

INSTRUMENTATION

0

09/24/26

09/24/26

95% CD's

22 10 00

PLUMBING PIPING

0

09/24/26

09/24/26

95% CD's

22 10 30

PLUMBING SPECIALTIES

0

09/24/26

09/24/26

95% CD's

22 15 19

COMPRESSED AIR SYSTEMS

0

09/24/26

09/24/26

95% CD's

22 40 00

PLUMBING FIXTURES

0

09/24/26

09/24/26

95% CD's

22 - Plumbing

Page 3 of 5

Printed on Tue Oct 27, 2026 at 01:00 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction

Number

Description

Revision

Issued Date

Received Date

Set

23 - Heating, Ventilating, and Air Conditioning (HVAC) 23 05 00

BASIC HVAC REQUIREMENTS

0

09/24/26

09/24/26

95% CD's

23 05 03

THROUGH PENETRATION FIRESTOPPING

0

09/24/26

09/24/26

95% CD's

23 05 05

HVAC DEMOLITION FOR REMODELING

0

09/24/26

09/24/26

95% CD's

23 05 13

MOTORS

0

09/24/26

09/24/26

95% CD's

23 05 16

HVAC EXPANSION COMPENSATION

0

09/24/26

09/24/26

95% CD's

23 05 29

HVAC SUPPORTS AND ANCHORS

0

09/24/26

09/24/26

95% CD's

23 05 30

ROOF SUPPORT AND WIND BRACING

0

09/24/26

09/24/26

95% CD's

23 05 48

HVAC VIBRATION ISOLATION

0

09/24/26

09/24/26

95% CD's

23 05 53

HVAC IDENTIFICATION

0

09/24/26

09/24/26

95% CD's

23 05 93

TESTING, ADJUSTING, AND BALANCING

0

09/24/26

09/24/26

95% CD's

23 07 13

DUCTWORK INSULATION

0

09/24/26

09/24/26

95% CD's

23 07 19

HVAC PIPING INSULATION

0

09/24/26

09/24/26

95% CD's

23 08 00

COMMISSIONING OF HVAC

0

09/24/26

09/24/26

95% CD's

26 05 00

BASIC ELECTRICAL REQUIREMENTS

0

09/24/26

09/24/26

95% CD's

26 05 03

THROUGH PENETRATION FIRESTOPPING

0

09/24/26

09/24/26

95% CD's

26 05 05

ELECTRICAL DEMOLITION FOR REMODELING

0

09/24/26

09/24/26

95% CD's

26 05 13

WIRE AND CABLE

0

09/24/26

09/24/26

95% CD's

26 05 26

GROUNDING AND BONDING

0

09/24/26

09/24/26

95% CD's

26 05 27

SUPPORTING DEVICES

0

09/24/26

09/24/26

95% CD's

26 05 33

CONDUIT AND BOXES

0

09/24/26

09/24/26

95% CD's

26 05 53

ELECTRICAL IDENTIFICATION

0

09/24/26

09/24/26

95% CD's

26 08 00

COMMISSIONING OF ELECTRICAL

0

09/24/26

09/24/26

95% CD's

26 09 33

LIGHTING CONTROL SYSTEMS

0

09/24/26

09/24/26

95% CD's

26 22 00

DRY TYPE TRANSFORMERS

0

09/24/26

09/24/26

95% CD's

26 24 16

PANELBOARDS

0

09/24/26

09/24/26

95% CD's

26 27 26

WIRING DEVICES

0

09/24/26

09/24/26

95% CD's

26 28 13

FUSES

0

09/24/26

09/24/26

95% CD's

26 28 16

DISCONNECT SWITCHES

0

09/24/26

09/24/26

95% CD's

26 51 19

LED LIGHTING

0

09/24/26

09/24/26

95% CD's

26 - Electrical

27 - Communications 27 05 00

BASIC COMMUNICATIONS SYSTEMS REQUIREMENTS

0

09/24/26

09/24/26

95% CD's

27 05 28

INTERIOR COMMUNICATION PATHWAYS

0

09/24/26

09/24/26

95% CD's

27 05 53

IDENTIFICATION FOR COMMUNICATION SYSTEMS

0

09/24/26

09/24/26

95% CD's

27 15 00

HORIZONTAL CABLING REQUIREMENTS

0

09/24/26

09/24/26

95% CD's

27 17 10

TESTING

0

09/24/26

09/24/26

95% CD's

27 17 20

STRUCTURED CABLING SYSTEM WARRANTY

0

09/24/26

09/24/26

95% CD's

27 41 00

PROFESSIONAL AUDIO/VIDEO SYSTEM

0

09/24/26

09/24/26

95% CD's

0

09/24/26

09/24/26

95% CD's

28 - Electronic Safety and Security 28 13 00

ELECTRONIC ACCESS CONTROL

Page 4 of 5

Printed on Tue Oct 27, 2026 at 01:00 pm MDT Job #: 250069 BVSD - Nederland Middle/Senior High School 597 Co Hwy 130 Nederland, Colorado 80466 Howell Construction

Number 28 31 02

Description

Revision

Issued Date

Received Date

Set

FIRE ALARM AND DETECTION SYSTEMS PERFORMANCE BASED

0

09/24/26

09/24/26

95% CD's

EARTHWORK

1

09/24/26

09/24/26

95% CD's

31 - Earthwork 31 00 00

32 - Exterior Improvements 32 12 00

FLEXIBLE PAVING

0

09/24/26

09/24/26

95% CD's

32 13 00

RIGID PAVING

0

09/24/26

09/24/26

95% CD's

32 31 00

FENCING

0

09/24/26

09/24/26

95% CD's

Page 5 of 5

Exhibit B Assumptions and clarifications made in preparing the GMP

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

October 27th, 2026 Kris Stoppenhagen Executive Director of Bond Planning & Construction Boulder Valley School District 6500 Arapahoe Rd Boulder, CO 80303 RE:

GMP Pricing BVSD Nederland Elementary & Middle-Senior High School Renovations Nederland Elementary – 1 Sundown Train, Nederland, CO 80466 Nederland Middle-Senior High School – 597 CO HWY 130, Nederland, CO 80466

Dear Mr. Stoppenhagen: Howell Construction is pleased to present our GMP pricing for the BVSD Nederland Elementary & Middle-Senior High School Renovations projects. Our proposal is based on the following general inclusions, exclusions, and clarifications: Document Nederland Elementary School Renovation 100% CD Drawings Nederland Middle-Senior High School Renovation 100% CD Drawings Nederland Middle-Senior High School Renovation & Nederland Elementary School Renovation 100% CD Project Manual RFI Responses

Date

Prepared By

10/8/2026

RB+B Architects

10/8/2026

RB+B Architects

10/8/2026

RB+B Architects

N/A

RB+B Architects

GENERAL INCLUSIONS          

Our pricing is based on a construction duration of 11 weeks for the elementary school and 36 weeks for the middle-senior high school to accommodate for early fire sprinkler installation per approval from BVSD Full time on-site supervision Standard insurance Insurance, General Liability and Builder’s Risk, per RFP Response Payment & Performance Bond per RFP Response General Conditions and Fees per RFP Response Pricing assumes project is 100% tax exempt 3% construction contingency Assumptions and quantities per detailed budget breakdown Please refer to detailed budget for scopes included in various buckets. Howell has tried to interpret the scope as laid out on documents the best we could for the breakouts. Howell will work with BVSD and RB+B to determine if some of the scope needs to shift to different buckets throughout design development.

Nederland Elementary School 

Millwork Howell Construction Since 1935 8085 E. Harvard Ave.  Denver, CO 80231  303-696-5800  www.howelldenver.com

BVSD Nederland Elementary & Middle-Senior High School Renovations GMP Proposal October 27th, 2026 Page 2

 

o Pricing assumes existing millwork to be relocated is in salvageable condition Plumbing & Mechanical o Plumbing and mechanical demolition and safe off o Plumbing fixtures as scheduled o Mechanical equipment as scheduled o Concrete saw cutting / pour back for underslab plumbing o Temperature controls o Test & balance Electrical o Electrical demolition and safe off o Light fixtures as scheduled o Lighting controls o Power and branch circuiting o Fire alarm modifications o Pricing assumes no low voltage cabling / audio visual is required at the Elementary School Earthwork o Includes site demolition Site Concrete o Pricing includes allowance for concrete and masonry retaining wall repair – see below for allowances Asphalt o Includes striping and signage at full depth asphalt replacement areas

Nederland Middle-Senior High School  

   

Demolition o Includes interior demolition – site demolition by earthwork contractor Millwork o Pricing assumes 14ers / Leadership 144 ceiling to be (31) suspended 2” x 8” x 16’ nominal Douglas Fir ceiling joists Glass o Pricing includes windows, curtainwall, and door lites Acoustical Ceilings o Pricing includes allowance to repair damaged / stained / broken ACT throughout the school. Please see below for allowances Flooring o Includes carpet, tile, resilient flooring, resilient base, sealed concrete and fluid applied flooring Wood Flooring o Includes new wood gym flooring Specialties o Alternate #6 locker pricing is based on Penco Gen II Lockers Signage o Pricing includes new code / room signage per schedule on A140 and dimensional letter signage for entry improvements on D3/A201. All other existing room / code signage has been assumed as existing to remain Athletic equipment o Includes basketball and volleyball equipment Howell Construction Since 1935 8085 E. Harvard Ave.  Denver, CO 80231  303-696-5800  www.howelldenver.com

BVSD Nederland Elementary & Middle-Senior High School Renovations GMP Proposal October 27th, 2026 Page 3

 

o Alternate #7 bleacher pricing is based on VersaTract bleachers Fire protection o Includes New wet pipe sprinkler system throughout building, with work starting through the 20262027 school year Plumbing and Mechanical o Plumbing and mechanical demolition and safe off o Plumbing fixtures as scheduled o Mechanical equipment as scheduled o Concrete saw cutting / pour back for underslab plumbing o Temperature controls o Test & balance Electrical o Electrical demolition and safe off o Light fixtures as scheduled o Lighting controls o Power and branch circuiting o Fire alarm modifications Low voltage o Includes low voltage cabling, audio visual, and access control Earthwork o Includes site demolition

ALLOWANCES (Direct Cost Only) - Nederland Elementary School 

Masonry & Concrete Retaining Wall repairs - $40,000

ALLOWANCES (Direct Cost Only) - Nederland Elementary School – Bridge Abutment Hardscape Patchback (Only if alternate #6 is not required): 30,000 ALLOWANCES (Direct Cost Only) – Nederland Middle-Senior High School        

Roof Patching: $10,000 ACT Tile and Grid Renewal at Damaged and Stained Locations: $80,000 WAF-1 Minor Floor Prep: $13,204 Repair Damaged Wall - Plan East Side of Building: $10,000 Repair Damaged Wall - Plan West Side of Building: $10,000 Relocate Fence / Reset Gate: $15,000 Reinstall Elevator Equipment in New Location: $95,282 Add Heat Trace at Chase, Storm Pipe, Outlet Structure and Cobble Swale at Front Entry RDs: $58,500

ALTERNATES 

See Join Log for Alternates Howell Construction Since 1935 8085 E. Harvard Ave.  Denver, CO 80231  303-696-5800  www.howelldenver.com

BVSD Nederland Elementary & Middle-Senior High School Renovations GMP Proposal October 27th, 2026 Page 4

EXCLUSIONS We specifically exclude the following:                    

Hazardous material testing, surveys, removal, handling and disposal Environmental hazards & testing Architectural and engineering design fees Permit and Plan Review Fees Testing and inspection services Seismic requirements Special insurance Consequential damages Owner and design contingencies BIM / 3-D modeling and coordination Rock removal Dewatering Construction Recycling Floor leveling and major floor prep Moisture mitigation in new or existing slabs Building permit and plan check fees State, RTD and SCFD sales tax Furniture moving Supply of residential appliances Boulder County use tax

Thank you for the opportunity to submit our GMP proposal on this exciting project and we look forward to working with the entire team. If you have any questions regarding this information, please feel free to contact me at 720.202.5844. Sincerely, HOWELL CONSTRUCTION SPENCER MOUSSEAU ESTIMATOR O: 303.696.5800 | C: 720.202.5844 SMOUSSEAU@HOWELLDENVER.COM

Howell Construction Since 1935 8085 E. Harvard Ave.  Denver, CO 80231  303-696-5800  www.howelldenver.com

Exhibit C Itemization of the GMP

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Boulder Valley School District Nederland Middle-Senior High School - GMP Pricing Revision 1 - 10.28.26

Nederland Middle-Senior High School Item ID # Category MH-1 Exterior Sealants - Roof Renewal

$

108,581

MH-2

Roof Hatches - Access Renewal

$

17,540

$

48,682

$

57,637

$

17,526

$

(40,112)

MH-3

Roof Hatches - Smoke Vents Renewal

$

15,029

$

41,148

$

24,527

$

23,639

$

(888)

MH-4

Exterior Doors - Pair - Hollow Metal - Glazed - Older Renewal

$

30,090

$

24,506

$

6,512

$

27,139

$

20,627

MH-5 MH-6 MH-7 MH-8 MH-9 MH-10 MH-11

Exterior Doors - Single - Hollow Metal - Glazed Renewal Exterior Windows - Broken Panes and Loosen Seal Steel Windows Renewal Skylights - Monumental Renewal Exterior Coatings - Painted Finish Renewal Exterior metal components - repair/ renewal Cabinet Unit Heater - Electric Renewal

$ $ $ $ $ $ $

15,333 10,199 55,111 200,000 75,000 24,072 11,091

$ $ $ $ $ $

15,308 37,206 94,997 246,516 20,365 6,447 N/A - Scope Eliminated

$ $ $ $ $

11,735 29,803 69,339 298,724 11,575 See MH-21 N/A - Scope Eliminated

$ $ $ $ $ $

16,249 13,130 68,147 281,783 39,302 17,313 N/A - Scope Eliminated

$ $ $ $ $ $

4,513 (16,673) (1,192) (16,941) 27,727 17,313

MH-12

Standpipe System - Wet - Light Hazard Renewal

$

415,380

See MH-23

$

19,363

$

MH-13 MH-14 MH-15 MH-16 MH-17 MH-18 MH-19 MH-20 MH-21 MH-22 MH-23 MH-24 MH-25 MH-26 MH-27 MH-28 MH-29 MH-30 MH-31 MH-32 MH-33 MH-33 MH-33 MH-34 MH-35 MH-36 MH-37 MH-38 MH-39

Backboards - Basketball Renewal Scoreboard - Exterior - Single-Sided - Field Renewal Curbs and Gutters - Concrete - Older Renewal Pedestrian Pavement - Concrete - Cracked and Damaged Sidewalk and Curb Pedestrian Pavement - Concrete - Older Renewal Roadway - Pavement - Asphalt - Service Road Renewal Valley Gutter and Flume - Concrete - Older Renewal Plumbing Fixtures - Non-Accessible Toilet Rooms and Showers - HS Lockers ADA - Stairs - Railings Not Compliant ADA - Student Toilets remaining Fire Protection: Sprinkler Coverage Provide Auditorium Renovation Ceiling Finishes - ACT System - Damaged and Stained Painted Finish or Sealer on Concrete Renewal Painted Finish Renewal Fixed Lockers - Metal - Locker Rooms - HS Lockers Renewal Fixed Lockers - Metal - Locker Rooms - MS Lockers Renewal Fixed Casework - Plastic Laminate Countertops - Older Renewal Laboratory Casework Renewal Wood Flooring - HS Gymnasium Renewal CTE Renovations - Entry Improvements CTE Renovations - First Floor Area B CTE Renovations - Stagecraft / Band Generator enclosure assessment LED lighting upgrade assessment Gym Sound Systems ADD - Exterior Sidewalk ADD- Snow Drift ADD - Signage and Striping Totals

$ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $

5,037 35,035 29,132 28,202 23,359 31,660 56,050 893,882 44,311 350,000 1,750,000 750,000 21,540 4,008 8,013 125,000 282,479 150,000 75,000 125,350

$

49,087 N/A - Scope Eliminated 16,490 See MH-17 $ 45,192 $ 140,075 $ 115,881 $ 1,731,654 $ 91,804 $ 798,086 $ 1,760,663 $ 385,673 $ 120,280 N/A - Scope Eliminated $ 31,653 $ 1,345,121 N/A - Scope Eliminated $ 216,146 $ 61,468 $ 231,940

$

112,761 N/A - Scope Eliminated 18,670 66,469 87,981 73,403 20,791 See MH-28 $ 22,978 $ 999,643 $ 1,565,561 $ 1,355,409 $ 83,907 N/A - Scope Eliminated $ 69,160 $ 3,334,317 N/A - Scope Eliminated N/A - Scope Eliminated See Alternate #4 $ 460,708

$

$

$

$ $ $ $ $

$ $ $ $ $

$ $ $ $ $

$

2,200,000

$

$

$ $ $

17,426 100,000 54,000

$

N/A See Below See Below 8,136,910

# N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A

Category Alternate No. 1: West Parking Lot Mill and Overlay and Striping Alternate No. 2: New Pan and Underdrain at East Parking Alternate No. 3: Remove Stair and Infill Floor at Corridor 130 Alternate No. 4: Science Lab 236 Renovation Alternate No. 5: Elevator Shaft Finish Renewal Alternate No. 6: HS Locker Room Lockers Renewal Alternate No. 7: Replace Bleachers in HS Gym Alternate No. 8: Gym Sound Systems - Option A Alternate No. 8: Gym Sound Systems - Option B Alternate No. 9: Gym HVAC Noise Remedy Voluntary Alternate - Flooring Scope by Acierno ILO Gary Leimer Totals

RFP Original Budget Construction / Hard Costs

SD Budget 5/14/26

DD Budget 8/6/2026

N/A - Scope Eliminated

2,488,543

N/A - Scope Eliminated $ 400,088 $ 86,416 $ 21,800 See Below See Below $ 10,673,236

N/A - Scope Eliminated

-

$

1,607,898

N/A - Scope Eliminated $ 558,723 See Alternate #8 N/A - Scope Eliminated N/A - Scope Eliminated N/A - Scope Eliminated $ 10,967,592

Nederland Middle-Senior High School Construction / Hard Costs 5/14/26

$

CD GMP 10/23/2026 N/A - Scope Eliminated

$

-

-

N/A

N/A $

43,938 N/A - Scope Eliminated 76,274 17,163 53,040 69,193 107,136 See MH-28 $ 77,258 $ 744,405 $ 1,458,620 $ 914,145 $ 96,216 N/A - Scope Eliminated $ $ 1,574,422 N/A - Scope Eliminated N/A - Scope Eliminated See Alternate #4 $ 351,045 $ 41,108 $ 806,652 $ 1,113,096 N/A - Scope Eliminated $ 9,828 See Alternate #8 N/A - Scope Eliminated N/A - Scope Eliminated N/A - Scope Eliminated $ 8,057,767

$

GMP Alternates 135,224.00 53,960.00 78,264.00 129,537.00 24,913.00 158,287.00 87,166.00 37,172.00 42,232.00 290,112.00 22,143.00 1,059,010

$

8/6/2026

-

DD to CD Budget Variance

$ $ $ $ $ $ $ $ $ $ $ $

Base Bid: $8,057,767 Alt 2: $53,960 Alt 3: $78,264 Alt 7: $87,166 Alt 8A: $37,172 Alt 8B: $42,232 Total: $8,356,561

(19,363)

(68,823) N/A 57,604 (49,306) (34,940) (4,210) 86,345 N/A

$ $ $ $ $

54,280 (255,238) (106,941) (441,265) 12,309 N/A

$ $

(69,160) (1,759,894) N/A N/A N/A

$

(109,663)

$

352,958 N/A

$

(548,895) N/A N/A N/A N/A (2,909,827)

-

Nederland Middle-Senior High School 10/28/2026

CSI 010001 013103 013106 015116 015133 015201 015213 015219 015400 015401 017400 017800 023101 024119 024120 033800 042000 051200 061001 062200 075300 076000 078400 079000 081000 081200 083600 084500 088000 088002 090001 090004 092113 092116 095100 096000 096400 099000 100000 101400 113013

Description Drawings/Blueprints Project Engineer / Field Engineer Superintendent Temporary Fire Extinguishers Cell Phone First Aid Station & Supplies Field Office and Furniture - Onsite Office Temporary Sanitation Drinking Water & Cups Truck General Labor/Clean-up Substantial Completion / Punch List Coordination Ground Penetrating Radar (GPR) Selective Demolition Misc. Demolition/Demolition Support Misc. Concrete Core Drill Patching / Infill Masonry Structural Steel Blocking & Backing Millwork Elastomeric Membrane Roofing Roof Patching - Allowance Firestopping Sealants/Caulking Doors, Frames & Hardware Install Doors, Frames, and Hardware Overhead Doors Translucent Walls and Roof Assemblies Glass and Glazing Temporary Closures at Windows Protection of New and Existing Finishes Final Cleaning Weekly Cleaning Framing and Drywall Acoustical Ceilings Flooring LVT Painting Specialties Signage Woodshop Equipment Install

26 Week Construction Duration Square Footage (RSF) 102,168 Current Pricing Total $/SF $ 950 $ 0.01 $ 68,898 $ 0.67 $ 104,500 $ 1.02 $ 931 $ 0.01 $ 570 $ 0.01 $ 811 $ 0.01 $ 2,252 $ 0.02 $ 9,908 $ 0.10 $ 588 $ 0.01 $ 7,206 $ 0.07 $ 11,138 $ 0.11 $ 4,663 $ 0.05 $ 5,000 $ 0.05 $ 262,380 $ 2.57 $ 21,811 $ 0.21 $ 13,771 $ 0.13 $ 73,519 $ 0.72 $ 103,825 $ 1.02 $ 21,280 $ 0.21 $ 124,876 $ 1.22 $ 16,392 $ 0.16 $ 10,000 $ 0.10 $ 23,388 $ 0.23 $ 38,081 $ 0.37 $ 129,033 $ 1.26 $ 25,136 $ 0.25 $ 28,655 $ 0.28 $ 191,554 $ 1.87 $ 123,436 $ 1.21 $ 35,120 $ 0.34 $ 47,380 $ 0.46 $ 35,759 $ 0.35 $ 26,132 $ 0.26 $ 199,895 $ 1.96 $ 188,119 $ 1.84 $ 227,450 $ 2.23 $ 146,981 $ 1.44 $ 195,092 $ 1.91 $ 94,542 $ 0.93 $ 43,572 $ 0.43 $ 12,209 $ 0.12

Nederland Middle-Senior High School 10/28/2026

CSI 116600 Athletic Equipment 122000 Window Treatments 142000 Elevators 211313 Wet-Pipe Sprinkler Systems 230000 Plumbing & Mechanical 230001 Mechanical Cut and Patch 260000 Electrical 260001 Electrical Cut and Patch 271000 IT/Network Cabling 274000 Audio/Video 281300 Access Control - Allowance 311001 Erosion Control 311313 Tree Protection 312300 Earthwork 312301 Misc. Hand Earthwork 321216 Asphalt Paving 321600 Site Concrete Subtotal Contractor's Cost Contingency 3.00% Subtotal General Liability Insurance Builder's Risk Performance Bond Subtotal Fee 4.96%

Description

26 Week Construction Duration Square Footage (RSF) 102,168 Current Pricing Total $/SF $ 25,624 $ 0.25 $ 25,900 $ 0.25 $ 95,282 $ 0.93 $ 1,212,793 $ 11.87 $ 1,811,938 $ 17.73 $ 34,035 $ 0.33 $ 1,087,715 $ 10.65 $ 25,928 $ 0.25 $ 18,688 $ 0.18 $ 27,206 $ 0.27 $ 29,725 $ 0.29 $ 22,725 $ 0.22 $ 9,952 $ 0.10 $ 50,035 $ 0.49 $ 7,337 $ 0.07 $ 38,725 $ 0.38 $ 96,226 $ 0.94 $ 7,296,637 $ 71.42 $ 218,899 $ 2.14 $ 7,515,536 $ 73.56 $ 80,392 $ 0.79 $ 12,059 $ 0.12 $ 69,001 $ 0.68 $ 7,676,988 $ 75.14 $ 380,779 $ 3.73

Grand Total:

$8,057,767 $78.87 /SF

Exhibit D Contract Schedule & change order for the GMP is Contract Schedule to be provided after amendment executed

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

BVSD Nederland ES & MS/HS Renovation - Master CPM Schedule Master Schedule 10/23/2026

Line Activity ID

Name

PROJECT-WIDE PRECONSTRUCTION (BOTH CONTRACTS)

Duration

Start

Finish

2026 2027 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

22d 10/8/2026

11/9/2026

10/8/2026 *

10/8/2026

95% CD Documents Received (ES & MS/HS)

10/8/2026

10/23/2026

GMP Estimate - ES & MS/HS (Howell)

10/23/2026

10/23/2026

GMP Proposals Submitted to BVSD (2 GMPs)

10/26/2026

11/6/2026

BVSD GMP Review, Board Approval & Amendment Execution

11/9/2026

11/9/2026

Notice to Proceed - Both Contracts

NEDERLAND ELEMENTARY SCHOOL (CONTRACT 1)

227d 9/14/2026

8/6/2027

NEDERLAND MIDDLE / SENIOR HIGH SCHOOL (CONTRACT 2)

212d 10/7/2026

8/10/2027

MS/HS - Permits & Buyout

90d 10/8/2026

2/18/2027

1

2

CD Documents Received (ES & MS/HS)

2

3

GMP Estimate - ES & MS/HS (Howell)

3

4

GMP Proposals Submitted to BVSD (2 GMPs)

4

5

BVSD GMP Review, Board Approval & Amendment Execution

5

6

Notice to Proceed - Both Contracts

12d 10d

+

+

6

77

MS/HS - Issue 100% CD / Permit Set

10d

10/8/2026

10/21/2026

7

78

MS/HS - Permit Submit/Intake (DFPC / Town of Nederland)

5d

10/22/2026

10/28/2026

8

79

MS/HS - Permit Plan Review (cont.)

60d

10/29/2026

1/28/2027

9

83

MS/HS - Subcontract Buyout & Award

10d

11/9/2026

11/20/2026

10

80

MS/HS - Respond to Permit Comments

5d

1/29/2027

2/4/2027

11

81

MS/HS - Permit Re-Review

10d

2/5/2027

2/18/2027

MS/HS - Permit Re-Review

12

82

MS/HS - Building Permit In-Hand (Main Renovation)

2/18/2027

2/18/2027

MS/HS - Building Permit In-Hand (Main Renovation)

MS/HS - Submittals & Procurement

135d 11/23/2026

6/8/2027

MS/HS - Issue 100% CD / Permit Set MS/HS - Permit Plan Review (DFPC / Town of Nederland) MS/HS - Permit Plan Review (cont.) MS/HS - Subcontract Buyout & Award MS/HS - Respond to Permit Comments

13

85

MS/HS - Prepare Submittals (all trades)

20d

11/23/2026

12/22/2026

MS/HS - Prepare Submittals (all trades)

14

87

MS/HS - HV/AHU Submittal - Prepare (expedited)

5d

11/23/2026

12/1/2026

MS/HS - RTU/AHU Submittal - Prepare (expedited)

15

88

MS/HS - HV/AHU Submittal - A/E Review

15d

12/2/2026

12/22/2026

16

86

MS/HS - A/E Submittal Review

15d

12/23/2026

1/18/2027

17

89

MS/HS - Fab/Deliver HV/AHU Units

80d

12/23/2026

4/19/2027

18

2420

MS/HS - Telescoping Bleachers (Alternate)

100d

1/19/2027

6/8/2027

19

90

MS/HS - Fab/Deliver Monumental Skylights

70d

1/19/2027

4/26/2027

20

91

MS/HS - Fab/Deliver Metal Lockers & Benches

50d

1/19/2027

3/29/2027

21

92

MS/HS - Fab/Deliver Maple Gym Flooring System

40d

1/19/2027

3/15/2027

22

93

MS/HS - Fab/Deliver Dust Collectors & CTE Equipment

60d

1/19/2027

4/12/2027

MS/HS - Fab/Deliver Dust Collectors & CTE Equipment

23

94

MS/HS - Fab/Deliver Theatrical Lighting, Dimming & AV

60d

1/19/2027

4/12/2027

MS/HS - Fab/Deliver Theatrical Lighting, Dimming & AV

24

95

60d

1/19/2027

4/12/2027

MS/HS - Fab/Deliver Panelboards & Transformers

40d

1/19/2027

3/15/2027

MS/HS - Fab/Deliver Panelboards & Transformers MS/HS - Fab/Deliver Plumbing Fixtures, Partitions & 25 96 Accessories Drawn by: J. Kellogg

Dwg No. 00001

MS/HS - RTU/AHU Submittal - A/E Review MS/HS - A/E Submittal Review MS/HS - Fab/Deliver RTU/AHU Units MS/HS - Telescoping Bleachers (Alternate) MS/HS - Fab/Deliver Monumental Skylights MS/HS - Fab/Deliver Metal Lockers & Benches MS/HS - Fab/Deliver Maple Gym Flooring System

MS/HS - Fab/Deliver Plumbing Fixtures, Partitions & Accessories Revision No. 0

1 of 8

BVSD Nederland ES & MS/HS Renovation - Master CPM Schedule Master Schedule 10/23/2026

Line Activity ID

Name

Duration

Start

Finish

2026 2027 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

26

97

MS/HS - Fab/Deliver HM Door/Window Frames

30d

1/19/2027

3/1/2027

27

094

MS/HS - Fab/Deliver Wood Doors & HW

50d

1/19/2027

3/29/2027

MS/HS - Fab/Deliver HM Doors, Frames, Hardware & Steel Windows

28

98

MS/HS - Fab/Deliver Casework & Countertops

50d

1/19/2027

3/29/2027

MS/HS - Fab/Deliver Casework & Countertops

29

99

MS/HS - Fab/Deliver LED Fixtures

40d

1/19/2027

3/15/2027

30

100

MS/HS - All Summer Materials On-Site / Staged

4/26/2027

4/26/2027

MS/HS - Fire Sprinkler Addition - Early Package (Winter 2026-27)

162d 10/7/2026

5/28/2027

Fire Sprinkler - Permits & Procurement

30d 10/7/2026

11/17/2026

MS/HS - Fab/Deliver HM Doors, Frames, Hardware & Steel Windows

MS/HS - Fab/Deliver LED Fixtures MS/HS - All Summer Materials On-Site / Staged

31

103

FS - Sprinkler Design Review, Ned Fire / DFPC (remaining)

20d

10/7/2026 *

11/3/2026

FS - Sprinkler Design Review, Ned Fire / DFPC (remaining)

32

105

FS - Submittals & Review

10d

10/21/2026

11/3/2026

FS - Submittals & Review

33

104

FS - DFPC / Ned Sprinkler & FA Permits In-Hand

11/4/2026

11/4/2026

FS - DFPC / Ned Sprinkler & FA Permits In-Hand

34

106

FS - Fabrication & Delivery

10d

11/4/2026

11/17/2026

Fire Sprinkler - Phase I / II / III (Thanksgiving Break thru 12/30/26).Fire Sprinkler - Phase I (Thanksgiving Break thru 12/30/26)

24d 11/23/2026

12/30/2026

FS - Fabrication & Delivery

35

108

FS Ph I - Mobilize & Stage (Thanksgiving Break)

1d 11/23/2026 *

11/23/2026

FS Ph I - Mobilize & Selective Demo (Thanksgiving Break)

36

109

FS Ph I - Fire Service Entry, Riser & Main Piping

3d

11/23/2026

11/25/2026

FS Ph I - Fire Service Entry, Riser & Main Piping

37

110

FS Ph I - Branch Piping, Phase I Areas

3d

11/23/2026

11/25/2026

FS Ph I - Branch Piping, Phase I Areas

38

111

FS Ph I - Complete (Rough / Mains)

11/25/2026

11/25/2026

FS Ph I - Complete / Work Suspended for January

39

1910 FS Ph II - HS Gym

5d

12/7/2026 *

12/11/2026

40

1920 FS Ph II - MS Gym

5d

12/14/2026

12/18/2026

41

1930 FS Ph III - Admin & Cafeteria

6d

12/21/2026

12/30/2026

Fire Sprinkler - Phase IV / V (Night Shift, 2/1/27 Memorial Day).Fire Sprinkler - Phase II (Night Shift, 2/1/27 - Memorial Day)

85d

2/1/2027

5/28/2027

2/1/2027 *

2/2/2027

FS Ph II - HS Gym FS Ph II - MS Gym FS Ph III - Admin & Cafeteria

42

113

FS Ph IV - Remobilize Night Shift

2d

43

114

FS Ph IV - Branch Piping & Heads - Level 1 Area A

15d

2/3/2027

2/23/2027

44

115

FS Ph IV - Branch Piping & Heads - Level 1 Area B

15d

2/24/2027

3/16/2027

45

116

FS Ph V - Branch Piping & Heads - Level 2 Area A

20d

3/17/2027

4/13/2027

46

117

FS Ph V - Branch Piping & Heads - Level 2 Area B

20d

4/14/2027

5/11/2027

FS Ph II - Branch Piping & Heads - Level 2 Area B

47

119

FS Ph V - Ceiling Restoration & Patch/Paint

5d

5/12/2027

5/18/2027

FS Ph II - Ceiling Restoration & Patch/Paint

48

120

FS Ph V - AHJ Sprinkler Partial Inspections

5d

5/19/2027

5/25/2027

FS Ph II - AHJ Sprinkler Final Inspection

49

121

FS Ph V - Punch & Demobilize Night Shift

3d

5/26/2027

5/28/2027

Drawn by: J. Kellogg

Dwg No. 00001

FS Ph II - Remobilize Night Shift FS Ph II - Branch Piping & Heads - Level 1 Area A FS Ph II - Branch Piping & Heads - Level 1 Area B FS Ph II - Branch Piping & Heads - Level 2 Area A

FS Ph II - Punch & Demobilize Night Shift Revision No. 0

2 of 8

BVSD Nederland ES & MS/HS Renovation - Master CPM Schedule Master Schedule 10/23/2026

Line Activity ID

50

122

Name

Duration

2026 2027 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Start

Finish

5/28/2027

5/28/2027

MS/HS - Summer 2027 Construction (Building Unoccupied)

48d 5/24/2027

8/2/2027

Summer Start-up & Owner Abatement

10d 5/24/2027

6/7/2027

5/24/2027 *

5/24/2027

MS/HS - Summer Work Window Opens (school out) MS/HS - Mobilize, Fencing & Temporary Protection

Early Fire Sprinkler Rough Complete

51

125

MS/HS - Summer Work Window Opens (school out)

52

126

MS/HS - Mobilize, Fencing & Temporary Protection

2d

5/24/2027

5/25/2027

53

127

MS/HS - Owner Abatement Wk 1 - Locker Rooms & Student Toilets (by BVSD)

5d

5/24/2027

5/28/2027

54

128

MS/HS - Owner Abatement Wk 2 - CTE, Auditorium & Remaining (by BVSD)

5d

6/1/2027

6/7/2027

HS Locker Rooms (174 / 187)

37d

6/1/2027

7/22/2027

Fire Sprinkler Addition Complete

MS/HS - Owner Abatement Wk 1 - Locker Rooms & Student Toilets (by BVSD) MS/HS - Owner Abatement Wk 2 - CTE, Auditorium & Remaining (by BVSD)

55

130

Locker Rooms - Selective Demo

4d

6/1/2027

6/4/2027

56

131

Locker Rooms - Sawcut, Trench & Under-slab Plumbing

6d

6/7/2027

6/14/2027

Locker Rooms - Sawcut, Trench & Under-slab Plumbing

57

132

Locker Rooms - Trench Backfill & Slab Patch

2d

6/15/2027

6/16/2027

Locker Rooms - Trench Backfill & Slab Patch

58

133

Locker Rooms - Framing & In-wall MEP Rough-in

6d

6/17/2027

6/24/2027

Locker Rooms - Framing & In-wall MEP Rough-in

59

134

Locker Rooms - In-wall / Above-ceiling Inspections

1d

6/25/2027

6/25/2027

Locker Rooms - In-wall / Above-ceiling Inspections

60

135

Locker Rooms - Backer Board, Waterproofing, Gyp & Tape

2d

6/28/2027

6/29/2027

Locker Rooms - Backer Board, Waterproofing, Gyp & Tape

61

2320 Locker Rooms - Concrete Floor Paint (CFP-1)

3d

6/30/2027

7/2/2027

62

136

Locker Rooms - Wall Tile

5d

7/8/2027

7/14/2027

Locker Rooms - Tile Showers, Walls & Floors

63

137

Locker Rooms - Ceilings & Paint

2d

7/15/2027

7/16/2027

Locker Rooms - Ceilings & Paint

64

138

Locker Rooms - Lockers, Benches & Toilet Partitions

3d

7/15/2027

7/19/2027

Locker Rooms - Lockers, Benches & Toilet Partitions

65

139

Locker Rooms - Plumbing & Electrical Fixture Trim-out

3d

7/20/2027

7/22/2027

ADA Student Toilet Rooms / Concessions / Choir.ADA Student Toilet Rooms

40d 5/26/2027

7/22/2027

Locker Rooms - Selective Demo

Locker Rooms - Concrete Floor Paint (CFP-1)

Locker Rooms - Plumbing & Electrical Fixture Trim-out

66

145

Toilets L2 - Selective Demo

3d

5/26/2027

5/28/2027

67

141

Toilets L1 - Selective Demo

3d

6/1/2027

6/3/2027

Toilets L1 - Selective Demo

68

2040 Toilets L2 - Layout & Frame Partitions

3d

6/1/2027

6/3/2027

Toilets L2 - Plumbing, Framing & MEP Rough-in

69

2010 Toilets L1 - Sawcut/Demo SOG

2d

6/3/2027

6/4/2027

Toilets L1 - Sawcut/Demo SOG

70

146

6d

6/4/2027

6/11/2027

Toilets L2 - Plumbing, Framing & MEP Rough-in

71

2020 Toilets L1 - Undeground Plumbing & Slab Patch

5d

6/7/2027

6/11/2027

Toilets L1 - Undeground Plumbing & Slab Patch

72

2000 Toilets L1 - Layout & Frame Partitions

3d

6/14/2027

6/16/2027

Toilets L1 - Plumbing, Framing & MEP Rough-in

73

2050 Toilets L2 - Hang Gyp Board, Tape/Finish

5d

6/14/2027

6/18/2027

Toilets L2 - Hang Gyp Board, Tape/Finish

74

142

Toilets L1 - MEP Rough-in

6d

6/17/2027

6/24/2027

Toilets L1 - Plumbing, Framing & MEP Rough-in

75

2070 Toilets L2 - Resinous Flooring

3d

6/21/2027

6/23/2027

Toilets L2 - Resinous Flooring

Toilets L2 - MEP Rough-in

Drawn by: J. Kellogg

Dwg No. 00001

Toilets L2 - Selective Demo

Revision No. 0

3 of 8

BVSD Nederland ES & MS/HS Renovation - Master CPM Schedule Master Schedule 10/23/2026

Line Activity ID

Name

Toilets L2 - Tile & Finishes

Duration

2026 2027 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Start

Finish

6d

6/24/2027

7/1/2027

Toilets L2 - Board, Tile & Finishes Toilets L1 - Hang Gyp Board, Tape/Finish

76

147

77

2030 Toilets L1 - Hang Gyp Board, Tape/Finish

5d

6/25/2027

7/1/2027

78

2060 Toilets L1 - Resinous Flooring

3d

7/2/2027

7/7/2027

Toilets L1 - Resinous Flooring

79

148

4d

7/2/2027

7/8/2027

Toilets L2 - Partitions, Fixtures & Accessories

80

2090 Choir/Corridor - Ceiling Grid

2d

7/2/2027

7/6/2027

Choir/Corridor - Ceiling Grid

81

2100 Choir/Corridor - Lights & GRD's

2d

7/7/2027

7/8/2027

Choir/Corridor - Lights & GRD's

82

143

Toilets L1 - Tile & Finishes

6d

7/8/2027

7/15/2027

83

2080 Choir/Corridor L2 - Carpet & Base

2d

7/9/2027

7/12/2027

84

144

4d

7/16/2027

7/21/2027

85

2110 Concession L1 - Ceiling Grid

1d

7/16/2027

7/16/2027

Concession L1 - Ceiling Grid

86

2140 L1 - Re-Install Elevator Equipment, Hydraulic Lines

3d

7/16/2027

7/20/2027

L1 - Re-Install Elevator Equipment, Hydraulic Lines

87

2120 Concession L1 - Lights & GRD's

2d

7/19/2027

7/20/2027

Concession L1 - Lights & GRD's

88

2130 L1/L2 - Signage & Final Trims

2d

7/21/2027

7/22/2027

L1/L2 - Signage & Final Trims

CTE Renovations (Libary, Wellness, Bike Tech).CTE Renovations

40d 5/26/2027

7/22/2027

Toilets L2 - Toilet Partitions, Fixtures & Accessories

Toilets L1 - Toilet Partitions, Fixtures & Accessories

Toilets L1 - Board, Tile & Finishes Choir/Corridor L2 - Carpet & Base Toilets L1 - Partitions, Fixtures & Accessories

89

150

CTE - Selective Demo

3d

5/26/2027

5/28/2027

90

1940 CTE - Layout & Frame Partitions

5d

6/1/2027

6/7/2027

91

151

CTE - MEP Rough-in (Walls)

10d

6/8/2027

6/21/2027

CTE - MEP Rough-in (Dust Collection, Compressed Air, Power)

92

152

CTE - Hang Gyp Board, Tape/Finish

8d

6/11/2027

6/22/2027

CTE - Framing, Gyp Board & Paint

93

1980 CTE - Wall Tile

5d

6/23/2027

6/29/2027

94

1950 CTE - Prime & First Coat Paint

2d

6/23/2027

6/24/2027

95

1960 CTE - Ceiling Grid

3d

6/25/2027

6/29/2027

96

1970 CTE - Light Fixtures & GRD's

3d

6/30/2027

7/2/2027

97

2150 CTE - MEP Inspections & Drop Ceiling Tiles

2d

7/6/2027

7/7/2027

98

154

CTE - Install Carpet, Sealed Concrete

5d

7/6/2027

7/12/2027

99

153

CTE - Set Dust Collectors & Shop Equipment

5d

7/13/2027

7/19/2027

CTE - Set Dust Collectors & Shop Equipment

100

1990 CTE - Wall Covering & Final Paint

3d

7/13/2027

7/15/2027

CTE - Wall Covering & Final Paint

101

156

CTE - Equipment Connections & Trim-out

4d

7/15/2027

7/20/2027

CTE - Equipment Connections & Trim-out

102

155

CTE - Display Cases & Marker Boards

5d

7/16/2027

7/22/2027

CTE - Casework & Countertops

Auditorium, Band, Stagecraft Renovation.Auditorium Renovation

32d

6/8/2027

7/22/2027

Drawn by: J. Kellogg

Dwg No. 00001

CTE - Selective Demo CTE - Layout & Frame Partitions

CTE - Wall Tile CTE - Prime & First Coat Paint CTE - Ceiling Grid CTE - Light Fixtures & GRD's CTE - MEP Inspections & Drop Ceiling Tiles CTE - Resinous Flooring

Revision No. 0

4 of 8

BVSD Nederland ES & MS/HS Renovation - Master CPM Schedule Master Schedule 10/23/2026

Line Activity ID

Name

Duration

Start

Finish

2026 2027 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

103

158

Aud/Band/SC - Selective Demo

2d

6/8/2027

6/9/2027

104

2160 Aud/Band/SC - Frame New Partitions

3d

6/10/2027

6/14/2027

Aud/Band/SC - Frame New Partitions

105

2180 Auditorium - Frame Stage Extension/Stairs

3d

6/10/2027

6/14/2027

Auditorium - Frame Stage Extension/Stairs

106

2170 Aud/Band/SC - In-Wall MEP

5d

6/15/2027

6/21/2027

Aud/Band/SC - In-Wall MEP

107

2181 Auditorium - Sheath & Paint Stage Extension

4d

6/15/2027

6/18/2027

Auditorium - Sheath & Paint Stage Extension

108

2280 Auditorium - Stair Treads & Nosings

2d

6/21/2027

6/22/2027

Auditorium - Stair Treads & Nosings

109

2190 Aud/Band/SC - Hang Gyp Board, Tape/Finish

8d

6/22/2027

7/1/2027

CTE - Framing, Gyp Board & Paint

110

2290 Auditorium - Install Hand Rails & Paint

3d

6/23/2027

6/25/2027

Auditorium - Install Hand Rails & Paint

111

159

Auditorium - Theatrical Rigging, Lighting & Dimming

5d

6/23/2027

6/29/2027

Auditorium - Theatrical Rigging, Lighting & Dimming

112

160

Auditorium - Acoustic Panels, Ceilings & Paint

6d

6/29/2027

7/7/2027

Auditorium - Acoustic Panels, Ceilings & Paint

113

161

Auditorium - AV System Install & Programming

5d

6/30/2027

7/7/2027

Auditorium - AV System Install & Programming

114

2200 Aud/Band/SC - Prime & First Coat Paint

2d

7/2/2027

7/6/2027

Aud/Band/SC - Prime & First Coat Paint

115

2201 Aud/Band/SC - Install Casework

3d

7/7/2027

7/9/2027

Aud/Band/SC - Install Casework

116

2210 Aud/Band/SC - Ceiling Grid

2d

7/7/2027

7/8/2027

Aud/Band/SC - Ceiling Grid

117

162

Auditorium - Flooring & Final Finishes

4d

7/8/2027

7/13/2027

Auditorium - Flooring & Final Finishes

118

2220 Aud/Band/SC - Light Fixtures & GRD's

3d

7/9/2027

7/13/2027

Aud/Band/SC - Light Fixtures & GRD's

119

2202 Aud/Band/SC - Install Sinks

2d

7/12/2027

7/13/2027

Aud/Band/SC - Install Sinks

120

2230 Aud/Band/SC - MEP Inspections & Drop Ceiling Tiles

2d

7/14/2027

7/15/2027

Aud/Band/SC - MEP Inspections & Drop Ceiling Tiles

Drawn by: J. Kellogg

Dwg No. 00001

Auditorium - Selective Demo

Revision No. 0

5 of 8

BVSD Nederland ES & MS/HS Renovation - Master CPM Schedule Master Schedule 10/23/2026

Line Activity ID

Name

Duration

Start

Finish

2026 2027 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

121

2240 Aud/Band/SC - Install Carpet, Sealed Concrete

3d

7/14/2027

7/16/2027

CTE - Resinous Flooring

122

163

2d

7/14/2027

7/15/2027

Auditorium - Theatrical/AV Testing & Owner Demo

123

2250 Aud/Band/SC - Final Paint

2d

7/19/2027

7/20/2027

Aud/Band/SC - Final Paint

124

2260 Stage Craft - Install Shop Equipment

2d

7/19/2027

7/20/2027

Stage Craft - Install Shop Equipment

125

2270 Stage Craft - Power Connections to Shop Equipment

2d

7/21/2027

7/22/2027

Stage Craft - Power Connections to Shop Equipment

36d 5/26/2027

7/16/2027

3d

5/26/2027

5/28/2027

Gym - Remove & Store Bleachers (Base Bid)

Auditorium - Theatrical/AV Testing & Owner Demo

HS Gymnasium - Wood Floor, Backboards & Bleachers

126

165

Gym - Remove & Store Bleachers (Base Bid)

127

2300 Gym - Demo Wall & Frame New Door Opening

2d

5/26/2027

5/27/2027

Gym - Demo Wall & Frame New Door Opening

128

169

Gym - Acclimate Maple Flooring On-Site

5d

5/26/2027

6/2/2027

Gym - Acclimate Maple Flooring On-Site

129

166

Gym - Replace Basketball Backboards

3d

6/1/2027

6/3/2027

Gym - Replace Basketball Backboards

130

167

Gym - Demo Existing Wood Floor

4d

6/4/2027

6/9/2027

Gym - Demo Existing Wood Floor

131

168

Gym - Substrate Prep & Moisture Testing

3d

6/10/2027

6/14/2027

132

170

Gym - Install Sleepers/Subfloor & Maple Flooring

8d

6/15/2027

6/24/2027

133

171

Gym - Sand, Seal, Game Lines & Finish Coats

8d

6/25/2027

7/7/2027

134

172

Gym - Finish Cure

3d

7/8/2027

7/12/2027

135

173

Gym - Reinstall Bleachers

4d

7/13/2027

7/16/2027

Envelope & Roof

16d 5/26/2027

6/17/2027

136

175

Envelope - Replace Monumental Skylights

10d

5/26/2027

6/9/2027

137

176

Envelope - Roof Hatches & Smoke Vents

4d

5/26/2027

6/1/2027

Drawn by: J. Kellogg

Dwg No. 00001

Gym - Substrate Prep & Moisture Testing Gym - Install Sleepers/Subfloor & Maple Flooring Gym - Sand, Seal, Game Lines & Finish Coats Gym - Finish Cure Gym - Reinstall Bleachers

Envelope - Replace Monumental Skylights Envelope - Roof Hatches & Smoke Vents Revision No. 0

6 of 8

BVSD Nederland ES & MS/HS Renovation - Master CPM Schedule Master Schedule 10/23/2026

Line Activity ID

Name

Duration

Start

Finish

2026 2027 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

138

177

Envelope - Steel Windows & Glazing Repairs

8d

5/26/2027

6/7/2027

Envelope - Steel Windows & Glazing Repairs

139

178

Envelope - Exterior Doors & Hardware

3d

6/8/2027

6/10/2027

Envelope - Exterior Doors & Hardware

140

180

ADA Stair Railing Modifications

4d

6/8/2027

6/11/2027

ADA Stair Railing Modifications

141

179

Envelope - Exterior Coatings & Metal Repairs

5d

6/11/2027

6/17/2027

HVAC - HV/AHU Replacement.HVAC - RTU/AHU Replacement

38d 5/26/2027

7/20/2027

Envelope - Exterior Coatings & Metal Repairs

142

182

HVAC - Disconnect & Remove Existing Units

3d

5/26/2027

5/28/2027

143

183

HVAC - Curb Adapters & Structural Supports

3d

6/1/2027

6/3/2027

144

194

HVAC - Install New HV/AHU's (Band/Stagecraft)

10d

6/1/2027

6/14/2027

145

184

HVAC - Crane Set New RTU/AHU/EF/CU Units

2d

6/4/2027

6/7/2027

146

185

HVAC - Duct, Piping & Power Connections

10d

6/8/2027

6/21/2027

HVAC - Duct, Piping & Power Connections

147

186

HVAC - Controls / BAS Integration

5d

6/22/2027

6/28/2027

HVAC - Controls / BAS Integration

148

187

HVAC - Start-up, Testing & TAB

5d

6/29/2027

7/6/2027

149

188

MS/HS - Commissioning (HVAC/Plumbing/Electrical)

10d

7/7/2027

7/20/2027

Electrical, Lighting & Low Voltage

28d 5/26/2027

7/6/2027

HVAC - Disconnect & Remove Existing Units HVAC - Curb Adapters & Structural Supports HVAC - Install New HV/AHU's (Band/Stagecraft) HVAC - Crane Set New RTU/AHU Units

HVAC - Start-up, Testing & TAB MS/HS - Commissioning (HVAC/Plumbing/Electrical)

150

190

Electrical - Panel/Transformer Replacement & Shutdowns

4d

5/26/2027

6/1/2027

151

191

Electrical - LED Lighting Upgrades

15d

6/8/2027

6/28/2027

Electrical - LED Lighting Upgrades

152

193

Technology / Low Voltage Cabling

20d

6/8/2027

7/6/2027

Technology / Low Voltage

153

192

Fire Alarm Modifications & Testing

5d

6/29/2027

7/6/2027

Fire Alarm Modifications & Testing

Sitework

17d 5/26/2027

6/18/2027

Drawn by: J. Kellogg

Dwg No. 00001

Electrical - Panel/Transformer Replacement & Shutdowns

Revision No. 0

7 of 8

BVSD Nederland ES & MS/HS Renovation - Master CPM Schedule Master Schedule 10/23/2026

Line Activity ID

Name

Duration

Start

Finish

2026 2027 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

154

198

Site - Erosion & Traffic Control

1d

5/26/2027

5/26/2027

155

199

Site - Demo Concrete & Asphalt

4d

5/27/2027

6/2/2027

Site - Demo Concrete & Asphalt

156

2340 Site - Fence Relocations

5d

5/27/2027

6/3/2027

Site - Fence Relocations

157

200

Site - Curb & Gutter, Valley Gutters & Flumes

5d

6/3/2027

6/9/2027

Site - Curb & Gutter, Valley Gutters & Flumes

158

201

Site - Sidewalks & Pedestrian Pavement

6d

6/7/2027

6/14/2027

Site - Sidewalks & Pedestrian Pavement

159

202

Site - Service Road Asphalt Paving

3d

6/10/2027

6/14/2027

Site - Service Road Asphalt Paving

160

203

Site - Striping & Signage

2d

6/15/2027

6/16/2027

Site - Striping & Restoration

161

2350 Site - Replace Luminaire Heads

2d

6/17/2027

6/18/2027

Site - Replace Luminaire Heads

MS/HS Completion

6d 7/23/2027

8/2/2027

Site - Erosion & Traffic Control

162

205

MS/HS - AHJ Final Inspections

6d

7/23/2027

7/30/2027

MS/HS - AHJ Final Inspections

163

206

MS/HS - Final Clean & Pre-Punch Walk

3d

7/23/2027

7/27/2027

MS/HS - Final Clean & Pre-Punch Walk

164

207

MS/HS - Substantial Completion / TCO

8/2/2027

8/2/2027

MS/HS - Closeout

17d 7/19/2027

8/10/2027

MS/HS - Substantial Completion / TCO

165

211

MS/HS - O&M Manuals, Warranties & Record Documents

15d

7/19/2027

8/6/2027

MS/HS - O&M Manuals, Warranties & Record Documents

166

210

MS/HS - Punch Walk & Corrections

10d

7/28/2027

8/10/2027

MS/HS - Punch List Corrections

167

212

MS/HS - Owner Training & Demonstration

5d

8/2/2027

8/6/2027

MS/HS - Owner Training & Demonstration

168

213

MS/HS - Final Completion

8/10/2027

8/10/2027

MS/HS - Final Completion

Milestone Appearances Start Milestone Drawn by: J. Kellogg

Dwg No. 00001

Revision No. 0

8 of 8

Exhibit E Insurance Insurance Certificates to be provided after Certificates amendment & change order for the GMP is executed

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Client#: 1086501

ACORD

HOWELCON3 DATE (MM/DD/YYYY)

CERTIFICATE OF LIABILITY INSURANCE

TM

10/30/2026

THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER. IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must have ADDITIONAL INSURED provisions or be endorsed. If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer any rights to the certificate holder in lieu of such endorsement(s). CONTACT NAME: PHONE (A/C, No, Ext): 800 873-8500 E-MAIL ADDRESS: den.contractors@usi.com

PRODUCER

USI Insurance Services, LLC 4600 S. Ulster Street, Suite 1200 Denver, CO 80237 800 873-8500

INSURER(S) AFFORDING COVERAGE

NAIC #

11150 25674 30830 17370

INSURER A : Arch Insurance Company

INSURED

INSURER B : Travelers Property Cas. Co. of America

Howell Construction James R. Howell & Co., Inc. dba 8085 East Harvard Ave Denver, CO 80231 COVERAGES

FAX (A/C, No):

INSURER C : Arch Indemnity Insurance Company INSURER D : Nautilus Insurance Company INSURER E : INSURER F :

CERTIFICATE NUMBER:

REVISION NUMBER:

THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. INSR LTR

TYPE OF INSURANCE

A

COMMERCIAL GENERAL LIABILITY

X

CLAIMS-MADE

ADDL SUBR INSR WVD

X

POLICY NUMBER

X ZAGLB1209400

X OCCUR

POLICY EFF POLICY EXP (MM/DD/YYYY) (MM/DD/YYYY)

LIMITS

09/01/2026 09/01/2027 EACH OCCURRENCE DAMAGE TO RENTED PREMISES (Ea occurrence)

GEN'L AGGREGATE LIMIT APPLIES PER: PROX JECT POLICY LOC

$ 15,000

PERSONAL & ADV INJURY

$ 2,000,000

GENERAL AGGREGATE

$ 4,000,000

PRODUCTS - COMP/OP AGG

$ 4,000,000 $

X

AUTOMOBILE LIABILITY

X ZACAT9386100

SINGLE LIMIT 09/01/2026 09/01/2027 COMBINED (Ea accident)

X ANY AUTO X

OWNED AUTOS ONLY HIRED AUTOS ONLY

$ 350,000

MED EXP (Any one person)

OTHER:

A

$ 2,000,000

BODILY INJURY (Per person)

X

SCHEDULED AUTOS NON-OWNED AUTOS ONLY

$ 2,000,000 $

BODILY INJURY (Per accident) $ PROPERTY DAMAGE (Per accident)

$ $

B

X

UMBRELLA LIAB EXCESS LIAB

C

X

X

OCCUR

X CUPD256077326NF

09/01/2026 09/01/2027 EACH OCCURRENCE

CLAIMS-MADE

X RETENTION $10000 DED WORKERS COMPENSATION AND EMPLOYERS' LIABILITY Y/N ANY PROPRIETOR/PARTNER/EXECUTIVE OFFICER/MEMBER EXCLUDED? N N/A (Mandatory in NH) If yes, describe under DESCRIPTION OF OPERATIONS below

D Pollution Liab Professional Liab

$ 10,000,000 $ 10,000,000

AGGREGATE

$

X ZAWCI1182300

09/01/2026 09/01/2027 X

PER STATUTE

E.L. EACH ACCIDENT

OTHER $ 2,000,000

E.L. DISEASE - EA EMPLOYEE $ 2,000,000

CPP203567415

E.L. DISEASE - POLICY LIMIT $ 2,000,000 09/01/2026 09/01/2027 $2,000,000 Ea Claim $2,000,000 Aggregate $25,000 Retention

DESCRIPTION OF OPERATIONS / LOCATIONS / VEHICLES (ACORD 101, Additional Remarks Schedule, may be attached if more space is required)

Excess Liability: Insurer: Allianz Global Risks US Insurance Co. Policy number: USL03086526 Effective 09/01/2026 to 09/01/2027 Limits: $15,000,000 Each Occurrence $15,000,000 Aggregate (See Attached Descriptions) CERTIFICATE HOLDER

CANCELLATION

Boulder Valley School District No. RE2 6500 Arapahoe Road Boulder, CO 80301

SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN ACCORDANCE WITH THE POLICY PROVISIONS. AUTHORIZED REPRESENTATIVE

© 1988-2015 ACORD CORPORATION. All rights reserved. ACORD 25 (2016/03)

1 of 2 #S56402842/M55443956

The ACORD name and logo are registered marks of ACORD

BXFZP

DESCRIPTIONS (Continued from Page 1) RE: Project #2 - Nederland Middle-Senior High School. The General Liability and Automobile Liability policies include an automatic Additional Insured endorsement that provides Additional Insured status to the Boulder Valley School District No. RE2, only when there is a written contract that requires such status, and only with regard to work performed by or on behalf of the named insured. The General Liability and Automobile Liability policies contains a special endorsement with Primary and Noncontributory wording, when required by written contract. The General Liability, Automobile Liability and Workers Compensation policies include a Waiver of Subrogation endorsement in favor of the Certificate Holder as referenced above.

SAGITTA 25.3 (2016/03)

2 of 2

#S56402842/M55443956

COMMERCIAL GENERAL LIABILITY CG 20 33 12 19

THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

ADDITIONAL INSURED – OWNERS, LESSEES OR CONTRACTORS – AUTOMATIC STATUS WHEN REQUIRED IN A WRITTEN CONSTRUCTION AGREEMENT WITH YOU This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART A. Section II – Who Is An Insured is amended to include as an additional insured any person or organization for whom you are performing operations when you and such person or organization have agreed in writing in a contract or agreement that such person or organization be added as an additional insured on your policy. Such person or organization is an additional insured only with respect to liability for "bodily injury", "property damage" or "personal and advertising injury" caused, in whole or in part, by: 1. Your acts or omissions; or 2. The acts or omissions of those acting on your behalf;

B. With respect to the insurance afforded to these additional insureds, the following additional exclusions apply:

in the performance of your ongoing operations for the additional insured.

b. Supervisory, inspection, architectural or engineering activities.

However, the insurance additional insured:

This exclusion applies even if the claims against any insured allege negligence or other wrongdoing in the supervision, hiring, employment, training or monitoring of others by that insured, if the "occurrence" which caused the "bodily injury" or "property damage", or the offense which caused the "personal and advertising injury", involved the rendering of or the failure to render any professional architectural, engineering or surveying services.

afforded

to

such

1. Only applies to the extent permitted by law; and 2. Will not be broader than that which you are required by the contract or agreement to provide for such additional insured. A person's or organization's status as an additional insured under this endorsement ends when your operations for that additional insured are completed.

CG 20 33 12 19

This insurance does not apply to: 1. "Bodily injury", "property damage" or "personal and advertising injury" arising out of the rendering of, or the failure to render, any professional architectural, engineering or surveying services, including: a. The preparing, approving, or failing to prepare or approve, maps, shop drawings, opinions, reports, surveys, field orders, change orders or drawings and specifications; or

© Insurance Services Office, Inc., 2018

Page 1 of 2

POLICY NUMBER:

COMMERCIAL GENERAL LIABILITY CG 20 37 07 04

THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

ADDITIONAL INSURED – OWNERS, LESSEES OR CONTRACTORS – COMPLETED OPERATIONS This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART SCHEDULE Name Of Additional Insured Person(s) Or Organization(s):

ALL PARTIES WHERE REQUIRED BY A WRITTEN CONTRACT OR WRITTEN AGREEMENT THAT REQUIRE THIS EDITION DATE.

Location And Description Of Completed Operations ALL LOCATIONS WHERE REQUIRED BY A WRITTEN CONTRACT OR WRITTEN AGREEMENT THAT REQUIRE THIS EDITION DATE.

Information required to complete this Schedule, if not shown above, will be shown in the Declarations. Section II – Who Is An Insured is amended to include as an additional insured the person(s) or organization(s) shown in the Schedule, but only with respect to liability for "bodily injury" or "property damage" caused, in whole or in part, by "your work" at the location designated and described in the schedule of this endorsement performed for that additional insured and included in the "productscompleted operations hazard".

CG 20 37 07 04

© ISO Properties, Inc., 2004

Page 1 of 1

COMMERCIAL GENERAL LIABILITY CG 20 01 12 19

THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

PRIMARY AND NONCONTRIBUTORY – OTHER INSURANCE CONDITION This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART LIQUOR LIABILITY COVERAGE PART PRODUCTS/COMPLETED OPERATIONS LIABILITY COVERAGE PART The following is added to the Other Insurance Condition and supersedes any provision to the contrary: Primary And Noncontributory Insurance This insurance is primary to and will not seek contribution from any other insurance available to an additional insured under your policy provided that:

(2) You have agreed in writing in a contract or agreement that this insurance would be primary and would not seek contribution from any other insurance available to the additional insured.

(1) The additional insured is a Named Insured under such other insurance; and

CG 20 01 12 19

© Insurance Services Office, Inc., 2018

Page 1 of 1

POLICY NUMBER: 99GLB$%$%$00

COMMERCIAL GENERAL LIABILITY CG 24 04 12 19

THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

WAIVER OF TRANSFER OF RIGHTS OF RECOVERY AGAINST OTHERS TO US (WAIVER OF SUBROGATION) This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART ELECTRONIC DATA LIABILITY COVERAGE PART LIQUOR LIABILITY COVERAGE PART POLLUTION LIABILITY COVERAGE PART DESIGNATED SITES POLLUTION LIABILITY LIMITED COVERAGE PART DESIGNATED SITES PRODUCTS/COMPLETED OPERATIONS LIABILITY COVERAGE PART RAILROAD PROTECTIVE LIABILITY COVERAGE PART UNDERGROUND STORAGE TANK POLICY DESIGNATED TANKS SCHEDULE Name Of Person(s) Or Organization(s): AS AGREED PER WRITTEN CONTRACT OR WRITTEN AGREEMENT

Information required to complete this Schedule, if not shown above, will be shown in the Declarations. The following is added to Paragraph 8. Transfer Of Rights Of Recovery Against Others To Us of Section IV – Conditions: We waive any right of recovery against the person(s) or organization(s) shown in the Schedule above because of payments we make under this Coverage Part. Such waiver by us applies only to the extent that the insured has waived its right of recovery against such person(s) or organization(s) prior to loss. This endorsement applies only to the person(s) or organization(s) shown in the Schedule above.

CG 24 04 12 19

© Insurance Services Office, Inc., 2018

Page 1 of 1

THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. ADDITIONAL INSURED - BLANKET This endorsement modifies insurance provided under the following: AUTO DEALERS COVERAGE FORM BUSINESS AUTO COVERAGE FORM MOTOR CARRIER COVERAGE FORM Under Covered Autos Liability Coverage, the Who is An Insured provision is amended to include as an "insured" the person or organization who is required under a written contract to be included as an "insured" under this policy, but only with respect to their legal liability for your acts or omissions or the act or omissions of a person for whom Covered Autos Liability Coverage is afforded under this policy. All other terms and conditions of this policy remain unchanged.

Endorsement Number: Policy Number: 99CAT$%$%$00 Named Insured: SAMPLE

AUTO POLICY FOR GCI

This endorsement is effective on the inception date of this Policy unless otherwise stated herein: Endorsement Effective Date: 9/1/2026

00 CA0115 00 10 13

Page 1 of 1

COMMERCIAL AUTO CA 04 49 11 16

THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

PRIMARY AND NONCONTRIBUTORY – OTHER INSURANCE CONDITION This endorsement modifies insurance provided under the following: AUTO DEALERS COVERAGE FORM BUSINESS AUTO COVERAGE FORM MOTOR CARRIER COVERAGE FORM With respect to coverage provided by this endorsement, the provisions of the Coverage Form apply unless modified by the endorsement. A. The following is added to the Other Insurance Condition in the Business Auto Coverage Form and the Other Insurance – Primary And Excess Insurance Provisions in the Motor Carrier Coverage Form and supersedes any provision to the contrary: This Coverage Form's Covered Autos Liability Coverage is primary to and will not seek contribution from any other insurance available to an "insured" under your policy provided that: 1. Such "insured" is a Named Insured under such other insurance; and 2. You have agreed in writing in a contract or agreement that this insurance would be primary and would not seek contribution from any other insurance available to such "insured".

CA 04 49 11 16

B. The following is added to the Other Insurance Condition in the Auto Dealers Coverage Form and supersedes any provision to the contrary: This Coverage Form's Covered Autos Liability Coverage and General Liability Coverages are primary to and will not seek contribution from any other insurance available to an "insured" under your policy provided that: 1. Such "insured" is a Named Insured under such other insurance; and 2. You have agreed in writing in a contract or agreement that this insurance would be primary and would not seek contribution from any other insurance available to such "insured".

© Insurance Services Office, Inc., 2016

Page 1 of 1

POLICY NUMBER: 99CAT$%$%$00

COMMERCIAL AUTO CA 04 44 10 13

THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

WAIVER OF TRANSFER OF RIGHTS OF RECOVERY AGAINST OTHERS TO US (WAIVER OF SUBROGATION) This endorsement modifies insurance provided under the following: AUTO DEALERS COVERAGE FORM BUSINESS AUTO COVERAGE FORM MOTOR CARRIER COVERAGE FORM With respect to coverage provided by this endorsement, the provisions of the Coverage Form apply unless modified by the endorsement. This endorsement changes the policy effective on the inception date of the policy unless another date is indicated below. Named Insured: Endorsement Effective Date: SCHEDULE Name(s) Of Person(s) Or Organization(s):

ANY PERSON OR ORGANIZATION WHERE WAIVER OF OUR RIGHT TO RECOVER IS PERMITTED BY LAW AND IS REQUIRED BY WRITTEN CONTRACT PROVIDED SUCH CONTRACT WAS EXECUTED PRIOR TO THE LOSS.

Information required to complete this Schedule, if not shown above, will be shown in the Declarations. The Transfer Of Rights Of Recovery Against Others To Us condition does not apply to the person(s) or organization(s) shown in the Schedule, but only to the extent that subrogation is waived prior to the ‘‘accident’’ or the ‘‘loss’’ under a contract with that person or organization.

CA 04 44 10 13

Insurance Services Office, Inc., 2011

Page 1 of 1

WORKERS COMPENSATION AND EMPLOYERS LIABILITY INSURANCE POLICY

WC 00 03 13 (Ed. 4-84)

POLICY NUMBER: 99WCI$%$%$00 WAIVER OF OUR RIGHT TO RECOVER FROM OTHERS ENDORSEMENT

We have the right to recover our payments from anyone liable for an injury covered by this policy. We will not enforce our right against the person or organization named in the Schedule. (This agreement applies only to the extent that you perform work under a written contract that requires you to obtain this agreement from us.) This agreement shall not operate directly or indirectly to benefit anyone not named in the Schedule. Schedule

ANY PERSON OR ORGANIZATION WHERE WAIVER OF OUR RIGHT TO RECOVER IS PERMITTED BY LAW AND IS REQUIRED BY WRITTEN CONTRACT PROVIDED SUCH CONTRACT WAS EXECUTED PRIOR TO DATE OF LOSS.

This endorsement changes the policy to which it is attached and is effective on the date issued unless otherwise stated. (The information below is required only when this endorsement is issued subsequent to preparation of the policy.) Endorsement Effective 09/01/2026

Policy No. 99WCI$%$%$00

Insured SAMPLE WC POLICY FOR GCI Insurance Company ARCH INDEMNITY INSURANCE COMPANY DATE OF ISSUE: 07-15-26

WC 00 03 13 (Ed. 4-84)  1983 National Council on Compensation Insurance.

Countersigned By

Endorsement No. Premium INCL.

Exhibit F Performance Bond to be provided after amendment & change order for the GMP is executed

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit G Labor and Materials Payment Bond to be provided after amendment & change order for the GMP is executed

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit H Alternates prices Alternates prices not used for the amendment # N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A

Category Alternate No. 1: West Parking Lot Mill and Overlay and Striping Alternate No. 2: New Pan and Underdrain at East Parking Alternate No. 3: Remove Stair and Infill Floor at Corridor 130 Alternate No. 4: Science Lab 236 Renovation Alternate No. 5: Elevator Shaft Finish Renewal Alternate No. 6: HS Locker Room Lockers Renewal Alternate No. 7: Replace Bleachers in HS Gym Alternate No. 8: Gym Sound Systems - Option A Alternate No. 8: Gym Sound Systems - Option B Alternate No. 9: Gym HVAC Noise Remedy Voluntary Alternate - Flooring Scope by Acierno ILO Gary Leimer Totals

Nederland Middle-Senior High School Construction / Hard Costs 5/14/26

$

-

$

8/6/2026

-

$

-

$ $ $ $ $ $ $ $ $ $ $ $

GMP Alternates 135,224.00 53,960.00 78,264.00 129,537.00 24,913.00 158,287.00 87,166.00 37,172.00 42,232.00 290,112.00 22,143.00 1,059,010

$

Total: $298,794

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

-

Exhibit I prices Unit prices not Unit used for this amendment

Not Applicable

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit J Allowances ALLOWANCES (Direct Cost Only) - Nederland Elementary School 

Masonry & Concrete Retaining Wall repairs - $40,000

ALLOWANCES (Direct Cost Only) - Nederland Elementary School – Bridge Abutment Hardscape Patchback (Only if alternate #6 is not required): 30,000 ALLOWANCES (Direct Cost Only) – Nederland Middle-Senior High School        

Roof Patching: $10,000 ACT Tile and Grid Renewal at Damaged and Stained Locations: $80,000 WAF-1 Minor Floor Prep: $13,204 Repair Damaged Wall - Plan East Side of Building: $10,000 Repair Damaged Wall - Plan West Side of Building: $10,000 Relocate Fence / Reset Gate: $15,000 Reinstall Elevator Equipment in New Location: $95,282 Add Heat Trace at Chase, Storm Pipe, Outlet Structure and Cobble Swale at Front Entry RDs: $58,500

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit K Not Applicable

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit L Equipment rental rate schedule

Equipment rental rate sheet to be provided after amendment and change order for the GMP is executed

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit M General Conditions of the Contract

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

BOULDER VALLEY SCHOOL DISTRICT RE-2 BOULDER, COLORADO

GENERAL CONTRACT CONDITIONS BOND PROGRAM

GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT.................................................................................................... 2 GC 1.00

CONTRACT DOCUMENTS AND DEFINITIONS ............................................................................................................ 1

GC 2.00

REFERENCE STANDARDS .......................................................................................................................................... 2

GC 3.00

DRAWINGS AND SPECIFICATIONS ............................................................................................................................ 2

GC 4.00

ROYALTIES AND PATENTS ........................................................................................................................................ 3

GC 5.00

ITEMS COVERED BY CONTRACT PRICE ..................................................................................................................... 3

GC 6.00

EXECUTION, CORRELATION, INTENT, AND INTERPRETATION OF CONTRACT DOCUMENTS ...................................... 3

GC 7.00

MATERIALS, LABOR, FACILITIES, AND STORAGE....................................................................................................... 4

GC 8.00

PERFORMANCE AND PAYMENT BONDS ................................................................................................................... 5

GC 9.00

PERMITS AND COMPLIANCE WITH STATUTES, RULES, AND REGULATIONS .............................................................. 6

GC 10.00

SURVEYS, BENCHMARKS, MONUMENTS, STAKES, AND MEASUREMENTS ............................................................... 6

GC 11.00

CHANGED CONDITIONS ........................................................................................................................................... 7

GC 12.00

PROTECTION OF PERSONS, WORK AND PROPERTY ................................................................................................. 7

GC 13.00

WORK ON EXISTING BUILDINGS .............................................................................................................................. 8

GC 14.00

CONTRACTOR’S SUPERINTENDENCE AND SUPERVISION .......................................................................................... 8

GC 15.00

SUBSTITUTIONS ....................................................................................................................................................... 9

GC 16.00

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES ................................................................................................. 9

GC 17.00

CASH ALLOWANCE................................................................................................................................................. 10

GC 18.00

EXPEDITING MATERIALS ........................................................................................................................................ 10

GC 19.00

BLASTING .............................................................................................................................................................. 11

GC 20.00

SOIL TEST REPORT ................................................................................................................................................. 11

GC 21.00

HAZARDOUS MATERIALS ....................................................................................................................................... 11

GC 22.00

DAMAGE TO UTILITIES ........................................................................................................................................... 11

GC 23.00

CHANGES IN THE WORK ........................................................................................................................................ 12

GC 24.00

CLAIMS FOR EXTRA COST....................................................................................................................................... 13

GC 25.00

DELAYS AND EXTENSIONS OF TIME ....................................................................................................................... 13

GC 26.00

ACCESS TO WORK .................................................................................................................................................. 14

GC 27.00

CORRECTION OF WORK ......................................................................................................................................... 14

GC 28.00

OWNER’S RIGHT TO CARRY OUT WORK ................................................................................................................. 16

GC 29.00

OWNER’S RIGHT TO TERMINATE CONTRACT ......................................................................................................... 16

GC 30.00

CONSTRUCTION SCHEDULE AND PROGRESS REPORTS ........................................................................................... 16

GC 31.00

SCHEDULE OF VALUES ........................................................................................................................................... 17

GC 32.00

PAYMENT .............................................................................................................................................................. 17

GC 33.00

INSURANCE ........................................................................................................................................................... 19

GC 34.00

SEPARATE CONTRACTS .......................................................................................................................................... 23

GC 35.00

SUBCONTRACTORS ................................................................................................................................................ 23

GC 36.00

RELATIONS OF CONTRACTOR AND SUBCONTRACTOR ........................................................................................... 24

GC 37.00

CONTRACTORS’ MUTUAL RESPONSIBILITY ............................................................................................................ 25

GC 38.00

CUTTING, PATCHING, AND EXCAVATING ............................................................................................................... 25

GC 39.00

EMPLOYEES ........................................................................................................................................................... 26

GC 40.00

CLEANING UP......................................................................................................................................................... 27

GC 41.00

USE OF PREMISES .................................................................................................................................................. 27

GC 42.00

OCCUPANCY .......................................................................................................................................................... 27

GC 43.00

TEMPORARY OR TRIAL USAGE ............................................................................................................................... 28

GC 44.00

TESTING OF BUILDING SYSTEMS ............................................................................................................................ 28

GC 45.00

LIQUIDATED DAMAGES FOR DELAY IN COMPLETION ............................................................................................. 28

GC 46.00

ACCEPTANCE AND FINAL PAYMENT ....................................................................................................................... 28

GC 47.00

WARRANTIES ON PORTIONS OF THE WORK .......................................................................................................... 29

GC 48.00

CONTRACTOR’S PROJECT GUARANTEE AFTER COMPLETION ................................................................................. 30

GC 49.00

MISCELLANEOUS KEYS, SWITCHES, ETC. ................................................................................................................ 30

GC 50.00

INDEMNIFICATION ................................................................................................................................................ 30

GC 51.00

LABOR DISPUTES ................................................................................................................................................... 31

GC 52.00

LIMITATION OF ACTIONS ....................................................................................................................................... 31

GC 53.00

PREFERENCE FOR COLORADO LABOR, MATERIALS, AND RESIDENT BIDDERS ........................................................ 31

GC 54.00

SALES AND USE TAX............................................................................................................................................... 31

GC 55.00

LIENS ..................................................................................................................................................................... 32

GC 56.00

OWNER’S INSPECTION OF CONTRACTOR’S RECORDS ............................................................................................ 32

GC 57.00

CERTIFICATION BY CONTRACTOR REGARDING PREMISES ACCESS ......................................................................... 32

GC 58.00

CONTRACTOR SAFETY RESPONSIBILITIES ............................................................................................................... 32

GC 59.00

CONTRACTOR ASBESTOS MANAGEMENT AND LEAD PAINT RESPONSIBILITIES ...................................................... 35

GC 60.00

ARCHITECT’S STATUS AND INSPECTIONS ............................................................................................................... 35

GC 61.00

ORAL STATEMENTS................................................................................................................................................ 35

GC 62.00

PROJECT SIGN ........................................................................................................................................................ 36

GC 63.00

HISTORICAL DATA .................................................................................................................................................. 36

GC 64.00

ASSIGNMENT ......................................................................................................................................................... 36

GC 65.00

TIME OF THE ESSENCE ........................................................................................................................................... 36

GC 66.00

DISPUTES ............................................................................................................................................................... 36

GC 67.00

SURVIVAL .............................................................................................................................................................. 36

GC 1.00

CONTRACT DOCUMENTS AND DEFINITIONS

All Work under the Construction Agreement shall be accomplished in accordance with the Contract Documents, which shall consist of the Request for Qualifications, Request for Proposals, Proposal(s), Notice of Award, Notice to Proceed, Performance Bond, Labor and Material Payment Bond, Construction Agreement, General Contract Conditions, Supplementary Conditions, Asbestos Management Plan Contractor Responsibility Form, Drawings and Specifications, tests and engineering data, approved Change Orders, Contractor’s Requests for Payment, Architect’s Certificates, and all addenda issued by the Owner or Architect prior to execution of the Construction Agreement and all modifications issued by the Owner or Architect after execution of the Construction Agreement. With respect to the Contract Documents, the following definitions and understandings shall control: 1.01 “Contract” or “Contract Documents” shall include all of the items enumerated in GC-1.00 above. 1.02 “Owner” shall mean Boulder Valley School District No. RE-2, and shall include its duly authorized representatives. 1.03 “Contractor” shall mean the corporation, company, partnership, firm, entity, or individual named and designated as such in the Construction Agreement, and any persons or entities acting on its behalf. 1.04 “Subcontractor” shall mean any corporation, partnership, entity, or individual having a direct contract with the Contractor or another subcontractor for performing Work and/or furnishing labor or material on the Project covered by the Contract. 1.05 “Architect” shall mean the corporation, partnership, entity or individual named and designated as “architect” or “engineer” in the Construction Agreement, and any persons or entities acting on the Architect’s behalf and within the scope of the particular duties properly entrusted to them in each case. In the event that there is no Architect on the Project, then “Architect” shall refer to Owner and its duly authorized representative. 1.06 “Notice to Contractor” shall be deemed to have been duly served if made in writing and delivered in person to the individual or to a member of the firm or to an officer of the corporation for which it is intended, or if sent by registered or certified mail, to Contractor’s last known business address. 1.07 “The Work” shall mean the construction and services required by the Contract Documents for completion of the Project, and includes all labor, materials, equipment and services provided or to be provided by the Contractor to fulfill the Contractor’s obligations, whether on or off the Project site, and all labor, materials equipment and services provided or to be provided by subcontractors, sub-subcontractors, or any other entity for whom the Contractor is responsible. 1.08 “The Project” is the total construction designed by the Architect of which the Work performed under the Contract Documents may be the whole or a part. 1.09 The “date of final completion” and “finally completed” shall mean the date when construction is certified by the Architect to be finally completed in accordance with the Contract Documents, as modified by any Change Orders processed under the terms of GC-23.00 below and when the Owner has fully accepted the Project for the use for which it was intended. Such date will be set forth on a letter of acceptance issued by the Owner. 1.010 “Drawings” or “plans” shall mean all (a) drawings furnished by the Owner and/or Architect as a basis for the award of Contract and for construction of the Project; (b) supplementary drawings furnished by the Owner and/or Architect to clarify and to define in greater detail the intent of the Contract drawings and specifications; (c) drawings submitted by the successful Contractor as may be required after the Contract is awarded; (d) drawings furnished by the Owner and/or Architect to the Contractor during the progress of the Work; and (e) engineering data and drawings submitted by the Contractor during the progress of the Work, provided such drawings are acceptable to the Architect and Owner. 1

1.011 “Specifications” are the written technical information concerning materials, components, systems, equipment, and manner of installation as indicated on the drawings or plans and which state the quality, performance, and characteristics to be achieved by application of construction methods. 1.012 “Change Order” shall mean a written order to the Contractor signed by the Owner or its authorized agent issued after the execution of the Construction Agreement, authorizing a change in the Work and/or adjustment in the Guaranteed Maximum Price (“GMP”) or the contract time schedule. Each adjustment in the GMP resulting from a Change Order shall clearly separate the amount attributable to the Cost of the Work and the Contractor’s Fee. 1.013 “day” or “days” shall mean calendar days. In computing a period of days, when the ending date is not specified, the first day is excluded and the last day is included. If any deadline falls on a Saturday, Sunday, or federal or Colorado state holiday, such deadline will be extended to the next day that is not a Saturday, Sunday or federal or Colorado state holiday. GC 2.00

REFERENCE STANDARDS

2.01 Reference to the standards of any technical society, organization, or association, or to codes of local or state authorities, shall mean the latest standard, code, specification, or tentative standard adopted and published as of the date of execution of the Construction Agreement, unless specifically stated otherwise. GC 3.00

DRAWINGS AND SPECIFICATIONS

3.01 Ownership of Drawings. All drawings, specifications, and copies thereof furnished by the Architect are the property of the Architect and the Owner, whether or not the Work for which they are made is performed, and are not to be used on other Work except by written agreement with the Architect and the Owner. 3.02 Figured Dimensions to Govern. Dimensions and elevations shown on the drawings shall be accurately followed. No Work shown on the drawings, the dimensions of which are not indicated, shall be executed until necessary dimensions have been obtained from the Architect. 3.03 Contractor to Check Drawings and Schedules. The Contractor shall check and verify all dimensions, elevations, and quantities shown on the drawings and furnished to it by the Architect, and shall notify the Architect of any discrepancy between the drawings and the conditions on the ground, or any error or omission in drawings, or in the layout as given by stakes, points, or instructions that it may discover. Before ordering any material or doing any Work, the Contractor shall verify all measurements concerning the Project and shall be responsible for the correctness of same. No extra charge or compensation shall be allowed on account of any difference between actual dimensions and the measurements indicated on the drawings. Any difference that may be found shall be submitted to the Architect for consideration and written determination before proceeding with the Work. The Contractor shall not be allowed to take advantage of any error or omission in the drawings or Contract Documents. Full written instructions shall be furnished by the Architect should such error or omission be discovered, and the Contractor shall carry out such instructions as if originally specified. 3.04 Detail Drawings and Instructions. The Architect shall furnish with reasonable promptness additional instructions, by means of drawings or otherwise, necessary for the proper execution of the Work. All such drawings and instructions shall be consistent with the Contract Documents. The Work shall be executed in conformity with the Architect’s drawings and instructions, and the Contractor shall do no Work without proper drawings and instructions. 3.05 Drawings and Specifications Available on the Site. The Contractor shall maintain at the Project site for the Owner and the Architect a Project record set of drawings, including addenda, approved shop drawings, Change Orders, and other modifications, with all changes or deviations from the original drawings neatly marked thereon in a contrasting color. The Contractor shall also maintain a Project record set of specifications at the 2

Project site, noting therein by appropriate section the names, models, and other distinguishing characteristics of the materials actually incorporated into the Work. This Project record set of drawings and specifications shall be updated daily as the Project progresses and shall be made available to the Owner and Architect for inspection at all times. Upon final completion of the Work and before final payment, three (3) copies and one (1) electronic of this Project record set of drawings and specifications shall be delivered to the Owner. One (1) copy of this Project record set of drawings and specification shall be delivered to the Architect. 3.06 Laws and Regulations. The Contractor shall give all notices and comply with all laws, ordinances, rules, and regulations bearing on the conduct of the Work as drawn and specified. If the Contractor observes that the drawings and specifications are at variance therewith, it shall promptly notify the Architect in writing, and any necessary adjustments shall be made as provided in the Contract for changes in the Work. If the Contractor performs any Work knowing it to be contrary to such laws, ordinances, rules, or regulations without giving the required notice to the Architect and receiving a written directive to proceed, it shall bear all costs arising therefrom and to correct and/or remedy same. GC 4.00

ROYALTIES AND PATENTS

The Contractor shall pay all royalties and license fees. The Contractor shall defend all suits or claims for infringement of patent rights and shall hold the Owner harmless from any and all liability or loss on account thereof. If the Contractor has information that the process or article specified involves the infringement of a patent, it shall be responsible for any and all liability or loss resulting therefrom unless it promptly furnishes such information to the Architect in writing. GC 5.00

ITEMS COVERED BY CONTRACT PRICE

5.01 Items Supplied by Owner. Owner shall supply the following items for the Project: a. Building Permit; b. Initial Survey; c. Materials Testing Including Soil Testing; d. Third Party Inspections; e. Commissioning; and f. Test and Balance as Required for Commissioning. 5.02 Items Supplied by Contractor. Unless specifically stated otherwise, the Contractor shall accept the compensation stated in the Construction Agreement as full payment for furnishing all the materials, transportation, apparatus, temporary structures, equipment, services, fuel, energy, light, water, labor and tools, and all other things necessary for the complete and proper execution of the Work contemplated by or reasonably implied from the Contract Documents, within the time limits indicated therein. Such amount shall include any loss or damage resulting from the nature of the Work, from the elements or from any unforeseen difficulties that may be encountered; all risks of every description connected with the prosecution of the Work; all expenses incurred in consequence of any suspension or discontinuance of the Work; and all other amounts necessary for completing the Work pursuant to the Contract Documents within the time limits indicated therein. GC 6.00

EXECUTION, CORRELATION, INTENT, AND INTERPRETATION OF CONTRACT DOCUMENTS

6.01 Execution. The Construction Agreement and other Contract Documents shall be signed in multiple copies as directed by the Owner. Within ten (10) days of Notice of Award, the Contractor shall submit to the Owner a minimum of five (5) fully executed original sets of the Construction Agreement; Performance Bond, and Labor and Material Payment Bond with original Power of Attorney; and certificates of required insurance coverage. The date of the Contract for purposes of these documents shall be the date of the Notice of Award letter. The Owner shall execute the Construction Agreement, assemble all copies, and distribute the Contract Documents. The Contractor shall not commence the Work until it receives the Notice to Proceed. All bonds and insurance 3

certificates shall be submitted to the Owner prior to the award of the first subcontract. 6.02 Correlation. By executing the Construction Agreement, the Contractor represents that it has visited the Project site, familiarized itself with the local conditions under which the Work is to be performed, and correlated its observations with the requirements of the Contract Documents. 6.03 Intent. The intention of the Contract Documents is to include all labor and materials, tools, equipment, construction equipment, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution and completion of the Work. Materials or Work described in words that, as applied, have a well-known technical or trade meaning shall be held to refer to such recognized meaning. The organization of the specifications into divisions, sections, and articles, as the case may be, and the arrangement of drawings shall not control the Contractor in dividing the Work among subcontractors or in establishing the extent of Work to be performed by any trade. It is intended that even though Work is not covered under any heading, division, section, article, branch, class, or trade of the specifications, it shall nevertheless be supplied if it is required elsewhere in the Contract Documents or is reasonably inferable therefrom as being necessary to produce the intended results. The specifications and drawings are intended to supplement but not necessarily duplicate each other. Any Work exhibited in the one and not in the other shall be executed as if it had been set forth in both, so that the Work will be constructed according to the complete design as determined by the Architect. 6.04 Interpretation. Should anything necessary for a clear understanding of the Work be omitted from the specifications and drawings, or should the requirements appear to be in conflict, the Contractor shall secure written interpretations or instructions from the Architect before proceeding with the Work affected thereby. The Contractor shall secure written interpretations or instructions by submitting the Owner’s form Request for Interpretation to the Architect. Oral requests shall not be acknowledged by the Architect or Owner. Additional costs incurred by the Owner as a result of unnecessary requests made by the Contractor, as determined by the Owner, shall be the responsibility of the Contractor. It is understood and agreed that the Work shall be performed according to the true intent of the Contract Documents. 6.05 Conflict in Interpretation. In the case of discrepancy or in the event of a conflict between the different Contract Documents, the documents shall take precedence in the following order: a. Change Orders; b. Written Amendments to Construction Agreement (including, if applicable, the GMP); c. Construction Agreement; d. General Conditions; e. Drawings and specifications; and f. Bid Documents, including addenda. Where two or more of the Contract Documents are complementary, the more detailed provision shall control over the more general provision. GC 7.00

MATERIALS, LABOR, FACILITIES, AND STORAGE

7.01 Contractor’s Responsibility. Unless otherwise agreed in writing, the Contractor shall provide and pay for all materials, labor, tools, equipment, machinery, transportation, and other facilities necessary for the proper execution and completion of the Work. The Contractor shall provide and pay for all the temporary facilities required to supply all the power, light, water, and heat needed by it and its subcontractors for their Work and shall install and maintain all such facilities in such manner as to protect the public and workers and to conform with any applicable laws and regulations. If temporary heat and/or protection is required for the expeditious prosecution of the Work and before the permanent heating apparatus is available for use, the temporary heating apparatus shall be installed and operated in such a manner that the finish Work and/or construction will not be damaged thereby. Unless otherwise specified, the Contractor shall pay for all the power, light, and water used by it and its subcontractors, without regard to whether such items are metered by temporary or permanent meters. The cutoff date on permanent meters shall be either the agreed date of full occupancy by 4

the Owner or the date of final acceptance of the Project, whichever shall be the earlier date. Upon completion of the Work, the Contractor shall remove all surplus materials, tools and such temporary facilities and structures, furnished by the contractor from the Project site. All debris and rubbish caused by the operations of the contractor shall be removed, and the area occupied during construction activities shall be restored to its original condition, within 48 hours of project completion, unless otherwise directed by the municipality or owner’s representative. 7.02 Materials. Unless otherwise specified, all materials shall be new and both Workmanship and materials shall be of the highest quality. The Contractor shall furnish satisfactory evidence to the Owner as to the kind and quality of materials. Samples shall be furnished, when specified, and the Work shall be in accordance with those samples that have been approved. 7.03 Toilet Facilities. The Contractor shall provide and maintain, in a neat and sanitary condition, adequate temporary toilet facilities for the use of any and all employees engaged on the Work, in strict compliance with the requirements of all applicable codes, regulations, laws, and ordinances. In no event may present toilet facilities of any existing building at the site of the Work be used by employees of the Contractor or its subcontractors. Upon final completion of the Work, the Contractor shall remove all such temporary facilities from the site and disinfect the premises. 7.04 Facilities and Storage. The Contractor shall provide suitable temporary facilities and quarters for workers, as needed, and shall maintain on premises water-tight storage sheds or tool houses for storage of building materials and tools that could be damaged by weather. The Contractor shall allow space for the erection of sheds and provide similar facilities for storage by subcontractors of their materials and tools. Storage of materials shall be confined to the site. These facilities or quarters shall further provide for protection against theft and damage of building materials and tools. Upon final completion of the Work, the Contractor shall remove all such temporary facilities from the site. 7.05 Office Space. The Contractor shall provide adequate, weatherproofed, heated and well- lighted office space at the site of the Work, for use by the Architect and the Owner and their representatives. The Contractor shall also provide telephone service at such office, which shall be available for use by the Architect, the Owner, and their representatives without charge, except for toll calls. 7.06 Quality and Location of Facilities. All of the foregoing facilities shall be of a quality and placed in locations acceptable to the Architect and the Owner. GC 8.00

PERFORMANCE AND PAYMENT BONDS

8.01 Required Bonds. The Contractor shall, within ten (10) days from the Notice of Award furnish bonds to the Owner in the full amount of the contract price, covering both the faithful performance of the Contract and the payment of all obligations for labor and materials arising thereunder, on such customary forms as the Owner may prescribe and with such sureties as it may approve. The amount of the bonds shall be increased, if necessary, to reflect approved changes in the Work that result in an increase in the total cost of the Work plus the Contractor’s fees. Such bonds shall be duly executed by a qualified surety licensed to do business in the State of Colorado, conditioned upon the true and faithful performance of the Contract, and shall provide that if the Contractor or its subcontractors fail to duly pay for any labor, materials, or other supplies used or consumed by such Contractor or its subcontractors in the performance of the Work contracted to be done, the surety will pay the same in an amount not exceeding the sum specified in the bond, as adjusted by approved Change Orders, and together with interest as provided by law. The performance bond shall additionally guarantee that the Contractor shall remedy any omissions, correct any and all defects, and adjust and make operable all component parts of Work falling under the requirements of the Contract that may be called to the Contractor’s attention within a period of twenty-four (24) months following the date of the letter of acceptance.

5

8.02 Additional Bond Requirements. The premium for all bonds shall be paid by the Contractor and included in the bid price in the bid proposal. The Owner will accept and approve bonds written by sureties legally authorized to write such bonds in the State of Colorado, provided such surety companies are rated in Best’s Insurance Guide (latest edition), not lower than A- or have Best’s Financial Rating of at least X. If, at any time a surety on such a bond becomes irresponsible or loses its right to do business in the State of Colorado, new bonds shall be provided by an alternate surety licensed to do business in the State and meeting the requirements of this Section 8.00. GC 9.00

PERMITS AND COMPLIANCE WITH STATUTES, RULES, AND REGULATIONS

9.01 Permits. Any local permits, governmental fees, and licenses necessary for the proper execution and completion of the Work shall be secured and paid for by the Contractor. Owner will pay for and secure building permit from Colorado Division of Fire Prevention and Control. Easements for permanent structures or permanent changes in existing facilities shall be secured and paid for by the Owner, unless otherwise specified in writing. The Owner is generally exempt from paying any fee for any building permit issued by any building departments or agencies located in Boulder, Broomfield, and Gilpin Counties, and the Contractor shall see that no building permit fee is paid. The Owner shall negotiate and provide for all electrical, gas, water, and sewer mains for the Contractor’s connections. The Contractor shall arrange with the utility company for actual connection, make necessary connections, and pay for all associated inspection fees and permits as required by any government agency. In addition, the Contractor shall furnish all material and items required to complete all connections. The Contractor shall call for all inspections on a timely basis by any agency having jurisdiction over the Work. 9.02 Compliance with Statutes, Rules and Regulations. The Contractor and all subcontractors shall comply with all applicable federal and state statutes, rules, regulations, and directives of the State Division of Fire Prevention and Control, and other governmental body having jurisdiction over the work to be performed. If any of the provisions of the Contract Documents are in conflict therewith, such portions shall be considered stricken and the applicable statute, ordinance, regulation, or ruling substituted therefor. All such cases of apparent conflict coming to the attention of any party shall immediately be called to the attention of the Owner. The Contractor shall strictly observe and comply with all federal and state laws pertaining to the employment and payment of labor. GC 10.00

SURVEYS, BENCHMARKS, MONUMENTS, STAKES, AND MEASUREMENTS

10.01 Surveys. As provided by the Owner, the Contractor shall obtain from the Architect a copy of all surveys describing property lines, elevation benchmarks, physical characteristics, and utility locations. 10.02 Benchmarks. The Contractor shall properly stake out the Work and provide and rigidly set benchmarks and batter boards as necessary for the proper performance of the Work. The Contractor shall remain responsible for their maintenance and their accuracy. A permanent benchmark, approved as to location and type by the Architect, from which all grades are to be taken, shall be established near the site of the Work by the Contractor. From this benchmark the Contractor shall ascertain all grades and levels to Project buildings as needed. The Contract Documents shall include all necessary information to establish the benchmark. 10.03 Preservation of Monuments and Stakes. The Contractor shall carefully preserve all monuments, benchmarks, property markers, reference points, and stakes. In case of the destruction thereof, the Contractor shall be charged with the expense of replacement and shall be responsible for any mistake or loss of time that may be caused. Permanent monuments and/or benchmarks that must be removed or disturbed shall be protected until properly referenced for relocation. The Contractor shall furnish all materials, labor and assistance for the proper replacement of such monuments and benchmarks. 10.04 Measurements. Before ordering any material or performing any Work, the Contractor shall verify all measurements on the Project and shall be responsible for the accuracy of same. No extra charge or 6

compensation shall be allowed because of any difference between actual dimensions and the measurements indicated in the drawings or specifications. Any discrepancies shall be submitted to the Architect and Owner for consideration before proceeding with the Work. GC 11.00

CHANGED CONDITIONS

The Contractor shall promptly, and before such conditions are disturbed, notify the Owner and the Architect in writing of: (1) sub-surface or latent physical conditions at the Project site differing materially from those indicated in the Contract Documents, or (2) unknown physical conditions at the Project site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in Work of the character provided for in the Contract Documents. The Owner and the Architect shall promptly investigate the conditions, and if the Owner finds that such conditions do so materially differ and cause an increase or decrease in the cost of or the time required for performance of the Work, an equitable adjustment shall be made and the Contract modified in writing accordingly. Any claim of the Contractor for adjustment hereunder shall not be allowed unless it has given notice as required. GC 12.00

PROTECTION OF PERSONS, WORK AND PROPERTY

12.01 Building Exits and Barricades. During the course of construction, the Contractor shall keep all required building exits free and unimpeded. Such exits shall not be closed at any time for any reason while the building is occupied or at any time when the building is unoccupied, except after written approval is given by the Owner and proper warning and directional signs are posted. Barricades shall be erected so that traffic is separated and protected from the construction. 12.02 Precautions. The Contractor shall take all necessary precautions to ensure the safety of all employees and other persons on the Project or who may be affected by the Contractor’s Work thereon. The Contractor shall also take all necessary precautions to protect the Work and all temporary facilities, as well as materials, tools, and equipment incorporated therein or to be incorporated therein from damage or destruction, whether in storage on or off the Project site and whether in the custody or control of the Contractor or any of its subcontractors. The Contractor shall also take all necessary precautions to protect all property at the Project site and adjacent thereto not designated for removal, relocation or replacement, including trees, shrubs, lawns, walks, pavements, roadways, structures, and utilities. 12.03 OSHA Compliance. The Contractor shall comply with all applicable provisions of the Occupational Safety and Health Administration (“OSHA”) and all laws, ordinances, rules, regulations, and orders of all governmental agencies or authorities having jurisdiction to protect the safety of employees and/or other persons who may be affected by the Work. The Contractor shall erect and maintain all necessary safeguards to protect workers on the Project site and the owners and users of adjacent property, and shall post danger signs and other warnings against hazards created by the Work including but not limited to protruding nails, hoists, well holes, elevator shafts, hatchways, scaffolding, window openings, stairways, excavations, and falling materials. The Contractor shall designate a responsible employee at the Project site as a safety officer to ensure the Contractor’s compliance with this section. Said employee shall be the Contractor’s superintendent unless otherwise designated in writing by the Contractor to the Owner and the Architect. 12.04 Contractor’s Liability. The Contractor shall be liable for all injury, damage or loss to any person or property caused in whole or in part by the Contractor, any of its subcontractors, or any person employed by or under the direction of the Contractor or any of its subcontractors. To the extent possible and unless otherwise directed by the Owner or Architect, the Contractor shall promptly repair, pay for or otherwise remedy any such injury, damage or loss and shall indemnify and hold harmless the Owner against any and all liability, claims, damages, losses and expenses arising therefrom. The terms of this section shall not apply in the case of injury, damage or loss proximately caused by the acts or omissions of the Owner and/or Architect and not attributable to any fault or negligence of the Contractor.

7

12.05 Emergencies. In the event of an emergency that threatens the safety or life of any person or threatens to damage or destroy the Project and/or any Work, materials, equipment or property thereon or to be used thereon, the Contractor shall act at its discretion to prevent such injury, death, damage or destruction. The Contractor shall immediately notify the Owner and Architect in writing of any such emergency and any action taken by the Contractor in response thereto. Any compensation due the Contractor for such emergency action shall be determined by agreement of the Contractor, Owner and Architect, and an appropriate Change Order shall be issued therefor. GC 13.00

WORK ON EXISTING BUILDINGS

13.01 Protection of Occupants. In addition to all other requirements of the Contract Documents, if the Work involves an addition or alteration to an existing building, the Contractor shall erect and maintain during the progress of the Work suitable dustproof partitions to protect such building and the occupants thereof. If necessary, in the Owner’s or Contractor’s judgment or pursuant to manufacturer’s directives or recommendations in order to protect occupants from noxious fumes, odors, or hazardous substances, the Contractor may be required to provide additional ventilation and/or work different or extended hours to avoid disruption to other activities within the existing building. Contractor shall protect and keep from harm all occupants of an existing building from construction activities, and shall include a safe pathway into and out of the school. 13.02 Partitions and Scheduling. If any portions of an existing building are to be remodeled or repaired, such portions shall be adequately partitioned off with dustproof partitions and well ventilated. All remodeling Work shall be scheduled and submitted to the Owner and Architect for approval. The various contractors shall schedule their Work jointly, in order that each may accomplish its Work within such existing building in an orderly fashion during regular school vacation periods where possible, or in such a manner as to permit full use of the building and without impairment of any existing facilities. 13.03 Existing Systems. Existing building systems, such as fire alarm, temperature controls and air distribution, security systems, public announcement systems, irrigation systems, and the like, shall be demonstrated and noted by Owner to the Contractor as operational prior to Contractor’s commencing the Work and Contractor may participate in observation of such systems. Such systems are the responsibility of the Contractor to maintain in pre-construction condition. GC 14.00

CONTRACTOR’S SUPERINTENDENCE AND SUPERVISION

14.01 Superintendent. During the progress of the Work, the Contractor shall ensure that a competent superintendent and any necessary assistants, all satisfactory to the Architect and the Owner, are on the Project site at all times while Work is in progress. The superintendent shall not be changed by the Contractor except with the written consent of the Architect and the Owner, unless the superintendent ceases to be in the Contractor’s employ. The superintendent shall represent the Contractor on the Project and all directions given to him/her shall be as binding as if given to the Contractor. The Architect and the Owner shall not be responsible for the acts or omissions of the superintendent or his/her assistants. 14.02 Supervision. The Contractor shall provide full-time, qualified, and efficient supervision of the Work, using competent skill and attention. The Contractor is responsible for determining and supervising all temporary and permanent erection and construction sequences, techniques, means, or methods. The Contractor shall direct, schedule, coordinate the Work to ensure that all parts fit together properly and in accordance with the Contract Documents. The Contractor shall carefully study and compare all Contract Documents and other instructions and shall at once report to the Architect and the Owner any error, inconsistency, or omission that Contractor may discover. 14.03 Additional Supervision Duties. The Contractor shall see that the Work is carried out in accordance with the Contract Documents and in a thorough and first-class manner in every respect. The Contractor shall 8

provide engineering, surveying, and coordination to accurately establish all lines, levels, and marks necessary to facilitate the operations of all parties involved in the Contractor’s Work. The Contractor shall lay out the Work in a manner satisfactory to the Architect, making permanent records of all lines and levels required for excavation, grading, and foundations, and for all other parts of the Work. The Contractor shall be responsible for the commencement and the proper completion of the various stages and sequences of construction. The Contractor shall strictly adhere to the approved construction schedule. GC 15.00

SUBSTITUTIONS

The Contractor shall be held to have used in its base proposal and to furnish under the Contract those items of equipment and/or materials that are specifically identified in the plans and specifications by a manufacturer’s name, model, or catalog number. Items of equipment and/or materials of the Contractor’s choice may be offered as alternates to the items named in the plans and specifications by submitting, with the proposal and on the form provided, identifying data on the articles proposed together with a statement of the amount of addition or deduction from the base bid if the bidder’s alternate is accepted. Prior approval by the Architect is not required on items submitted as alternate bids. After execution of the Construction Agreement, substitution of equipment and/or materials of makes other than those specifically named in the Contract Documents may be approved by the Owner so long as the equipment or material proposed for substitution in the opinion of the Owner is just as suitable as the equipment and/or materials named in the plans and specifications so far as performance, construction, efficiency, and utility are concerned. A request for substitution shall ordinarily be required to be based upon one or more of the following grounds: the specified equipment or material is no longer available, a substitution will improve lead time, quality will be improved (documented detail required), or the Owner will incur substantial savings. All requests for substitution must be submitted in writing with supporting documentation by or through the Contractor to the Architect for initial review and recommendation before being submitted to the Owner for evaluation and final approval. In the absence of the Owner’s written approval, no substitution of equipment or materials shall be allowed for any items specified in the Contract Documents. In case of a difference in price, occurring as a result of an approved substitution, the Owner shall receive all benefit of the difference in cost involved in the substitution. All approved substitutions shall be documented by the issuance of a formal Change Order as provided in these General Conditions. GC 16.00

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

16.01 Shop Drawings. “Shop drawings” are drawings, diagrams, illustrations, schedules, performance charts, brochures, manufacturer’s literature, and other data that are prepared by the Contractor or any subcontractor, manufacturer, supplier, or distributor, and that illustrate some portion of the Work. Shop drawings shall be submitted in both hard copy and electronic format. 16.02 Samples. “Samples” are physical examples furnished by the Contractor to the Owner and/or Architect to illustrate materials, finishes, equipment, or Workmanship, and to establish standards by which the Work will be judged. 16.03 Product Data. “Product data” are illustrations, standard schedules, performance charts, instructions, brochures, diagrams and other information furnished by the Contractor to illustrate materials or equipment for some portion of the Work. Product data shall be submitted in both hard copy and electronic format. 16.04 Contractor’s Obligations. The Contractor shall review, approve, stamp an then submit to the Architect shop drawings, product data, samples, and similar submittals required by the Contract Documents with reasonable promptness and in such a sequence as to cause no delay in the Work or in the activities of the Owner or of separate contractors. Shop drawings, product data, samples, and similar submittal required by the Contract Documents shall properly identify specified items. At the time of submission, the Contractor shall inform the Architect in writing of any deviation in the shop drawings, product data, or samples from the requirements of the Contract Documents. Substitutions will be allowed only in accordance with the provisions of GC-15.00. The number of copies and format of submittal shall be as required by the Architect, but, at a 9

minimum, shall include three (3) copies and one (1) electronic copy of the original shop drawings and product data for the Owner. 16.05 Verification. By approving and submitting shop drawings, product data, and samples, the Contractor thereby represents that it has determined and verified all field measurements, field construction criteria, dimensions, elevations, quantities, materials, catalog numbers, and similar data, as shown on the drawings and specifications furnished by the Architect, or will do so, and that it has checked and coordinated each shop drawing, product data, and sample with the requirements of the Work and of the Contract Documents. 16.06 Architect /Owner Review. The Architect shall review and approve shop drawings, product data, and samples with reasonable promptness so as to cause no delay, but only for conformance with the design concept of the Project and with the information given in the Contract Documents. The Architect’s approval of a separate item shall not indicate approval of any assembly in which the item functions. Upon the final completion of the Work, the Contractor shall furnish to the Architect two corrected copies of all shop or setting drawings showing the as-built condition of the Work. The Architect, after review, shall submit one of these copies to the Owner. 16.07 Corrections. The Contractor shall make any corrections required by the Architect and shall resubmit the required number of corrected copies of shop drawings or new samples until approved by the Architect. The Contractor shall direct specific attention in a separate writing or on resubmitted shop drawings to revisions other than the corrections requested by the Architect on previous submissions. 16.08 Contractor’s Responsibility. The Architect’s approval of shop drawings, product data, or samples shall not relieve the Contractor of responsibility for any deviation from the requirements of the Contract Documents unless the Contractor has informed the Architect in writing of such deviation at the time of submittal and the Architect has given written approval of the specific deviation. The Architect’s approval shall also not relieve the Contractor from responsibility for errors or omissions in the shop drawings, product data, or samples. 16.09 Architect Approval Required. No portion of the Work requiring the submission of a shop drawing, product data, or sample shall be commenced until such submittal has been approved in writing by the Architect. All such portions of the Work shall be in accordance with approved shop drawings, product data, and samples. All material finishes and samples shall be approved at one time. The Contractor shall submit all items requiring approval of finishes, color, material, etc., with sufficient lead time to allow simultaneous consideration and preparation of complete finish color schedule. No approvals of single items shall be considered. 16.010 Copies to Owner. When shop drawings, product data, samples or similar submittals have been approved and stamped by both Contractor and Architect, Contractor shall immediately forward an electronic copy of each to the Owner. GC 17.00

CASH ALLOWANCE

The Contractor shall include in the Contract sum all allowances named in the Contract Documents and shall cause the work so covered to be done by such Contractors and for such sums as the Owner may direct, the Contract sum being adjusted in conformity therewith. The Contractor declares that the Contract sum includes such sums for expenses and profit on account of cash allowances as he deems proper. No demand for expenses or profit other than those included in the Contract sum shall be allowed. The Contractor shall not be required to employ for any such work persons against whom he has filed a lien or has a reasonable objection due to previous legal claims. GC 18.00

EXPEDITING MATERIALS 10

The Contractor shall, immediately after receipt of the Notice of Award and approval of its list of subcontractors and material suppliers, place orders for all equipment, materials, and supplies required for the Work. The Contractor shall, when requested, submit to the Architect evidence that such orders have been placed. The Contractor shall exercise due diligence in seeing that all equipment, materials, and supplies are delivered well in advance of the time they are needed on the Project and shall properly store and protect same at its expense and in accordance with these General Conditions, either at the Project site or elsewhere as approved by the Architect. GC 19.00

BLASTING

No explosives of any nature except for those normally employed in powder actuated tools, .38 caliber or smaller, shall be employed or used on the Project site except with the express and specific prior written approval of the Architect and the Owner and any appropriate governmental authorities, in each instance. The Contractor shall notify the Architect of need for such approval three (3) days prior to the proposed use of such explosives. GC 20.00

SOIL TEST REPORT

The Owner may arrange for a separate consultant to conduct field and laboratory soil investigations on the Project site and to prepare a report of its findings. Such a report, if prepared, shall be available for review by the Contractor in the Architect’s office. Such data is offered solely for reference and is not to be considered a part of the Contract Documents. The data contained in any such document prepared for the Owner by a separate consultant is believed to be reliable; however, the Owner and Architect do not guarantee its accuracy or completeness. All applicable subcontractors shall be fully familiar with the contents of such reports, if prepared, and shall consider and evaluate them in the performance of their contracts and the Work. GC 21.00

HAZARDOUS MATERIALS

21.01 Responsibility and Reporting. Unless otherwise provided in the Contract Documents, the Contractor shall have no responsibility for the presence, handling, removal or disposal of hazardous materials in any form at the Project site, including but not limited to asbestos, asbestos products, polychlorinated biphenyl (PCB), lead, or other hazardous materials. Prior to its commencement or continuation of any portion of the Work, the Contractor shall provide notice to the Owner of the presence, location, amount and condition of any known or suspected hazardous materials that are discovered at the Project site. Such notice shall be in writing and shall be submitted no more than twenty-four (24) hours after the presence of such materials becomes known or suspected. 21.02 Contractor’s Obligations. In the event hazardous materials become known or suspected by the Contractor as described in GC-21.01 above, the Contractor shall not proceed with or continue the Work until it has received written authorization from the Owner. If the Contractor proceeds with the Work without said authorization, it assumes any and all responsibility and liability for contamination and cleanup at the Project site according to applicable federal and state laws, and for any death or personal injury, including but not limited to medical expenses that may be incurred by any individual as a result of exposure to hazardous materials on the Project site. 21.03 Owner’s Obligations. In the event hazardous materials are identified or encountered during the course of the Project, the Owner at its expense shall take reasonable actions to properly and safely deal with such materials. 21.04 Management Plan. The Contractor acknowledges that it and its employees, agents and subcontractors have the responsibility of being fully informed of the Owner’s Management Plan as it relates to buildings located at the Project site and shall consult with the Owner about how such Plan addresses suspected or active asbestos-containing material areas within such buildings. GC 22.00

DAMAGE TO UTILITIES 11

22.01 Adequate Precautions. The Contractor shall take adequate precautions to protect existing utilities on and off the Project site and avoid damage thereto. The Contractor shall repair or replace or have repaired or replaced at its expense any damage to streets, water, sewer, light, power, cable, or telephone lines or fiber network that are damaged by reason of the Contractor’s Work. 22.02 Location. The location and extent of underground utilities, fiber network, cables and conduit indicated on the drawings are not guaranteed. This information is shown only for such use as bidders and contractors may choose to make of it. The Contractor shall check with all public utility companies for locations and shall comply with their regulations regarding such utilities in performing the Work. 22.03 Protection from Damage. The Contractor shall adequately protect active underground utilities from damage, and if damaged shall immediately effect all necessary repairs. Removal or relocation of active underground utilities shall be done only as indicated on the drawings. If such utilities are in use, they shall be maintained in continuous service. If not indicated on the drawings or not known to exist, the Contractor shall report discovery of such utilities to the Architect and shall not proceed further until directed to do so. 22.04 Inactive or Abandoned Utilities. Inactive or abandoned utilities, whether or not they are indicated on the drawings, shall be recorded as to location and depth and shall be removed for a distance of not less than three (3) feet from the outside line of all concrete Work unless otherwise required by regulations. Ends shall be capped or plugged. There shall be no adjustment of the Contract amount for Work due to inactive or abandoned utilities. GC 23.00

CHANGES IN THE WORK

23.01 Change Orders. The Owner, without invalidating the Agreement, may order changes in the Work within the general scope of the Project consisting of additions, deletions, or other revisions. Under such circumstances, the GMP, if applicable and established, and the Contract Time Schedule shall be adjusted accordingly. All such changes in the Work shall be authorized by Change Order. No Change Order or other form of order or directive by the Owner or Architect requiring additional compensable Work to be performed, which causes the aggregate amount payable under the Contract Documents to exceed the amount appropriated for the original Agreement, shall be issued unless the Contractor is given written assurance by the Owner that lawful appropriations to cover the costs of the additional Work have been made. Any claim of the Contractor for adjustment under this section must be asserted in writing within ten (10) days from the date of the Contractor’s receipt of the Change Order. 23.02 Minor Changes. The Architect shall have authority to order minor changes in the Work not involving an adjustment in the GMP or an extension of the Contract Time Schedule and not inconsistent with the intent of the Contract Documents. Such changes may be effected by field order or by other written order. Such changes shall be binding on the Owner and the Contractor. In any emergency affecting the safety of persons or property, the Contractor shall act, at his discretion, to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in this Article. 23.03 Price Differential. The cost or credit resulting from a change in the Work shall be determined in one or more of the following ways: a. By estimate, with a detailed cost breakdown as set forth in GC-23.03(c) below, and acceptance in a lump sum, with a maximum combined markup to the Owner, for the Contractor and all affected subcontractors, not to exceed a total of fifteen percent (15%). b. By unit prices named in the Contract or subsequently agreed upon. c. If the parties are unable to agree on one of the above methods, then the amount shall be determined by force account under the following formula: i. The actual cost of all direct labor performed (including foremen employed continuously on the Work, but not the salary, or any part thereof, of the Contractor’s superintendent) and the actual 12

ii. iii. iv. v.

vi.

GC 24.00