CMGC Amendment Exhibits A-P Bear Creek ES 11.02.26.pdf (2,959 KB)

Regular Meeting, November 10, 2026 · item 7.13: Amendment to the contract for Bear Creek Elementary School · 96 pages

Open the original file

This is the text extracted from the file, without its layout, tables, or images. Use the original for anything that matters.

Exhibit A Drawings, specifications and documents used to prepare the GMP

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

DOCUMENT LIST •

Bear Creek UA Playground Specifications Bid Set – Dated 10/22/2025 o 01 10 00 - SUPPLEMENTAL GENERAL REQUIREMENTS o 01 14 00 - CONTRACTOR'S USE OF PREMISES o 01 23 00 - ALTERNATES o 01 31 19 - PROJECT MEETINGS o 01 32 33 - PHOTOGRAPHIC DOCUMENTATION o 02 41 00 - DEMOLITION o 11 68 13 - PLAYGROUND EQUIPMENT o 12 93 00 - SITE FURNISHINGS o 31 00 00 - EARTHWORK o 31 10 00 - SITE CLEARING o 31 11 00 - SITE PREPARATION o 32 01 90.33 - PROTECTION/REPAIR OF EXISTING TREES o 32 13 13 - CONCRETE PAVING o 32 15 40 - CRUSHER FINES GRAVEL PATH o 32 17 23 - ASPHALTIC CONCRETE PAVING o 32 17 26 - PAVEMENT MARKINGS o 32 31 13 - CHAIN LINK FENCES o 32 84 00 - IRRIGATION o 32 90 00 - FINE GRADING AND SOIL PREPARATION o 32 92 19 - SEEDING o 32 92 23 - SODDING o 32 93 00 - TREES, SHRUBS, AND GROUND COVERS o 32 93 13 - INERT GROUND COVER MATERIALS o 32 93 50 - LANDSCAPE MAINTENANCE

•

Bear Creek UA Playground Bid Set – Dated 10/22/2025 o GO.0 Cover Page o G0.1 Notes o G0.2 Survey o G1.0 Existing Conditions o L1.2 Overall Site Plan o L1.1 Kindergarten Playground Enlargement o L1.2 Kindergarten Playground Height Enlargement o L2.0 Details

o •

L2.1 Details

26-0925_Bear Creek ES-Documents-CD – Dated 09/25/2026 o G001-COVER SHEET o G110-FIRST FLOOR CODE PLAN o AS101-ARCHITECTURAL SITE PLAN o AD110-FIRST FLOOR DEMOLITION PLAN -OVERALL o ACD110-FIRST FLOOR DEMOLITION RCP o A110-FIRST FLOOR PLAN -OVERALL o AC110-FIRST FLOOR REFLECTED CEILING PLAN -OVERALL o A160-OVERALL ROOF PLAN o A500-DETAILS o M000 - HVAC COVERSHEET o MD111 - MAIN LEVEL DEMOLITION PLAN -HVAC -AREA 111 o MD132 - ROOF DEMOLITION PLAN -HVAC -AREA 111 o M111 - MAIN LEVEL PLAN -HVAC -AREA 111 o M131 - ROOF PLAN -HVAC -AREA 111 o M400 - HVAC DETAILS o M401 - HVAC DETAILS o M500 - HVAC DIAGRAMS o M501 - HVAC DIAGRAMS o M600 - HVAC SCHEDULES o M601 - HVAC SCHEDULES o E000 - ELECTRICAL COVERSHEET o E001 - ELECTRICAL LIGHTING AND SYSTEMS COVERSHEET o ED111 - MAIN LEVEL DEMOLITION PLAN -LIGHTING -AREA 111 o ED112 - MAIN LEVEL DEMOLITION PLAN -LIGHTING -AREA 112 o ED113 - MAIN LEVEL DEMOLITION PLAN -LIGHTING -AREA 113 o ED121 - MAIN LEVEL DEMOLITION PLAN -POWER AND SYSTEMS -AREA 111 o ED122 - MAIN LEVEL DEMOLITION PLAN -POWER AND SYSTEMS -AREA 112 o ED123 - MAIN LEVEL DEMOLITION PLAN -POWER AND SYSTEMS -AREA 113 o ED132 - ROOF DEMOLITION PLAN -POWER AND SYSTEMS -AREA 111 o ED133 - ROOF DEMOLITION PLAN -POWER AND SYSTEMS -AREA 113 o E111 - MAIN LEVEL PLAN -LIGHTING -AREA 111 o E112 - MAIN LEVEL PLAN -LIGHTING -AREA 112 o E113 - MAIN LEVEL PLAN -LIGHTING -AREA 113

o o o o o o o o o o o o o o o o •

E121 - MAIN LEVEL PLAN -POWER AND SYSTEMS -AREA 111 E122 - MAIN LEVEL PLAN -POWER AND SYSTEMS -AREA 112 E123 - MAIN LEVEL PLAN -POWER AND SYSTEMS -AREA 113 E131 - ROOF PLAN -POWER AND SYSTEMS -AREA 111 E132 - ROOF PLAN -POWER AND SYSTEMS -AREA 112 E133 - ROOF PLAN -POWER AND SYSTEMS -AREA 113 E500 - ELECTRICAL DIAGRAMS E600 - ELECTRICAL SCHEDULES E601 - ELECTRICAL COMCHECK E700 - ELECTRICAL PANEL SCHEDULES P000 - PLUMBING COVERSHEET P113 - MAIN LEVEL PLAN -PLUMBING -AREA 113 P400 - PLUMBING DETAILS FS101-KITCHEN EQUIPMENT FS102-KITCHEN PLUMBING / ELECTRICAL FS501-KITCHEN GENERAL NOTES -DETAILS

26_0925_BVSD Bear Creek ES-Project Manual-CD – Dated 09/25/2026 o 00 0000 Spec Cover_VOL1 o 00 0101-RIB-Project Title Page o 00 0103 Project Directory o 00 0107 Seals Page-BEAR CREEK o 00 0110 Table of Contents o 00 4322-RIB-Unit Prices Form o 00 4323-RIB-Alternates Form o 00 4336-RIB-Proposed Subcontractors Form o 00 5000-RIB-Contracting Forms and Supplements o 01 1000-RIB-Summary o 01 2000-RIB-Price and Payment Procedures o 01 2100-RIB-Allowances o 01 2200-RIB-Unit Prices o 01 2300-RIB-Alternates o 01 2500-RIB-Substitution Procedures o 01 3000-RIB-Administrative Requirements o 01 3216-RIB-Construction Progress Schedule o 01 4000-RIB-Quality Requirements

o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o

01 5000-RIB-Temporary Facilities and Controls 01 6000-RIB-Product Requirements 01 6116-RIB-Volatile Organic Compound (VOC) Content Restrictions 01 7000-RIB-Execution and Closeout Requirements 01 7419-RIB-Construction Waste Management and Disposal 01 7800-RIB-Closeout Submittals 01 7900-RIB-Demonstration and Training 01 9113-RIB-General Commissioning Requirements 02 4119-ORTA-SELECTIVE STRUCTURE DEMOLITION 03 3000-RIB-Cast-in-Place Concrete 04 2000-RIB-Unit Masonry 06 1000-RIB-Rough Carpentry 07 0150.19-RIB-Preparation for Re-Roofing 07 3113-RIB-Asphalt Shingles 07 4213-RIB-Metal Wall Panels 07 5400-RIB-Thermoplastic Membrane Roofing 07 6200-RIB-Sheet Metal Flashing and Trim 07 9200-RIB-Joint Sealants 08 6223-RIB-Tubular Skylights 09 0561-RIB-Common Work Results for Flooring Preparation 09 2116-RIB-Gypsum Board Assemblies 09 5100-RIB-Acoustical Ceilings 09 6466-RIB-Wood Athletic Flooring 09 6500-RIB-Resilient Flooring 09 6700-RIB-Fluid-Applied Flooring 09 6813-RIB-Tile Carpeting 09 9123-RIB-Interior Painting 09 9600-RIB-High-Performance Coatings 11 4000 - FOODSERVICE BCES_CD 22 0500 - BASIC PLUMBING REQUIREMENTS 22 0503 - THROUGH PENETRATION FIRESTOPPING 22 0503 - THROUGH PENETRATION FIRESTOPPING 22 0505 - PLUMBING DEMOLITION FOR REMODELING 22 0513 - MOTORS 22 0529 - PLUMBING SUPPORTS AND ANCHORS 22 0530 - ROOF SUPPORT

o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o

22 0553 - PLUMBING IDENTIFICATION 22 0593 - PLUMBING TESTING, ADJUSTING, AND BALANCING 22 0719 - PLUMBING PIPING INSULATION 22 0900 - INSTRUMENTATION 22 1000 - PLUMBING PIPING 22 1023 - NATURAL GAS AND PROPANE PIPING 22 1030 - PLUMBING SPECIALTIES 22 1123 - DOMESTIC WATER PUMPS 22 3000 - PLUMBING EQUIPMENT 22 4000 - PLUMBING FIXTURES 23 0500 - BASIC HVAC REQUIREMENTS 23 0503 - THROUGH PENETRATION FIRESTOPPING 23 0505 - HVAC DEMOLITION FOR REMODELING 23 0513 - MOTORS 23 0529 - HVAC SUPPORTS AND ANCHORS 23 0530 - ROOF SUPPORT AND WIND BRACING 23 0548 - HVAC VIBRATION ISOLATION 23 0553 - HVAC IDENTIFICATION 23 0593 - TESTING, ADJUSTING, AND BALANCING 23 0713 - DUCTWORK INSULATION 23 0719 - HVAC PIPING INSULATION 23 0900 - CONTROLS 23 0913 - INSTRUMENTATION 23 2100 - HYDRONIC PIPING 23 2116 - HYDRONIC SPECIALTIES 23 2300 - REFRIGERATION PIPING AND SPECIALTIES 23 3100 - DUCTWORK 23 3300 - DUCTWORK ACCESSORIES 23 3423 - POWER VENTILATORS 23 3600 - AIR TERMINAL UNITS 23 3700 - AIR INLETS AND OUTLETS 23 5100 - BREECHINGS, CHIMNEYS, AND STACKS 23 7200 - ENERGY RECOVERY DEVICES 23 7413 - ROOFTOP MODULAR AIR HANDLING UNITS 23 7423.13 - GAS FIRED MAKE-UP AIR UNITS 23 8126 - SPLIT SYSTEM AIR CONDITIONING UNITS

o o o o o o o o o o o o o o o o o o o

26 0500 - BASIC ELECTRICAL REQUIREMENTS 26 0503 - THROUGH PENETRATION FIRESTOPPING 26 0505 - ELECTRICAL DEMOLITION FOR REMODELING 26 0513 - WIRE AND CABLE 26 0526 - GROUNDING AND BONDING 26 0527 - SUPPORTING DEVICES 26 0533 - CONDUIT AND BOXES 26 0553 - ELECTRICAL IDENTIFICATION 26 0933 - LIGHTING CONTROL SYSTEMS 26 2200 - DRY TYPE TRANSFORMERS 26 2416 - PANELBOARDS 26 2419 - MOTOR CONTROL 26 2726 - WIRING DEVICES 26 2816 - DISCONNECT SWITCHES 26 5119 - LED LIGHTING 28 3102 - FIRE ALARM AND DETECTION SYSTEMS PERFORMANCE BASED 32 0116-RIB-Flexible Paving Rehabilitation 32 1216-RIB-Asphalt Paving 32 1313-RIB-Concrete Paving

Exhibit B Assumptions and clarifications made in preparing the GMP

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Bear Creek 10/29/2026 100% CD Clarifications

Pricing Clarifications - Bear Creek - Summer 2027 Renovation 100% Construction Documents - Drawings Dated 09/25/2026 DIVISION ONE – GENERAL CLARIFICATIONS

1. This GMP is based on the following documents: a. Bear Creek ES Documents 100% CD Drawings and Project Manual dated 09/25/2026 as generated by RTA Architecture. b. Bear Creek UA Playground Bid Set & Specification dated 10/22/2025 as generated by Design Concepts Architecture. 2. The Contract excludes all utility development fees and all municipal development fees. 3. The Scope of Work excludes all hazardous material sampling, testing and abatement. 4. This guaranteed maximum price is not a line item guaranteed maximum price and cannot be treated as such. 5. Sales tax on consumable materials has been included at 5.33% 6. Use tax allowance has been excluded. 7. Permit & Permit Review fee has been excluded. 8. All dry utility work and associated costs are to be by Owner. Ie. electrical transformer, high voltage lines, primary feeders, gas service to meter, gas meters, internet, fiber lines, phone, and D-marc (demarkation point). 9. We have not included a wind and weather protection allowance. 10. Any utility fees for usage of water and electricity used during construction have been excluded. 11. All third-party commissioning is by Owner. 12. All third-party testing/special inspections will be procured, contracted and managed by Owner

Bear Creek 10/29/2026 100% CD Clarifications

13. Project delays due to understa ed AHJ inspection agencies are considered to be delays outside of the CMGC's control and will be discussed on a case-by-case basis for extensions to project duration and increases to general conditions should they apply. DIVISION TWO – EXISTING CONDITIONS & SITE W ORK

14. Fransen Pittman does not warrant site concrete including walks, patio’s, curb and gutter, drive pans, working done in ROW etc. from cracking spalling or di erential movement where native soils were to remain and be used. 15. Specific requirements limiting moisture or ph of concrete materials, including flowfill are excluded from Scope of Work. 16. Rock excavation and/or blasting is excluded. 17. Perimeter foundation drain has been excluded. 18. Removal, remediation, and haul o of buried debris, contaminated soils, and/or hazardous materials are excluded. 19. The costs of any and all ground water testing, filtration, sediment control, contaminated water haul o , etc. are excluded from the cost of work 20. Removal, excavation and/or trenching of rock or any material that cannot be removed with conventional excavation equipment is excluded. This includes but is not limited to excavation work that requires chipping, drilling, splitting, hammering, or blasting. 21. Landscaping is to be maintained by ownership during the project duration. 22. Any work completed within the ROW will be subject to the overall project warranty. FP and our subcontractors cannot be held accountable beyond the agreed warranty period and that any “defective” items identified by the local municipality will be at the owners financial responsibility. 23. Existing Playground equipment set to be demolished will be demolished per the subcontractors standard procedures. No attempt to salvage or recycle will be made.

Bear Creek 10/29/2026 100% CD Clarifications

24. No patching or painting of any existing playground (set to remain) equipment has been included in this pricing. 25. Pricing is based on 12” of imported soil & standard compaction methods. If additional soil or compaction is needed, they will be subject to change order pricing. 26. Grinding of stump as noted on drawings has been included but demo/grinding of roots has not been included. 27. Existing 4” PVC pipe has been shown for connection at the north playground. No other utilities have been shown or accounted for connection in this area. DIVISION THREE - CONCRETE

28. Architectural precast cap color to be selected from standard color charts. Any existing precast caps to remain may not match exactly. Exact color match has been excluded. 29. Fransen Pittman does not warrant slabs-on-grade and slabs cast on metal decking against cracking that will a ect the aesthetic characteristics of the floor. 30. Fransen Pittman does not warrant site concrete including walks, patio’s, curb and gutter, drive pans, working done in ROW etc. from cracking spalling or di erential movement where native soils were to remain and be used. 31. Specific requirements limiting moisture or ph of concrete materials, including flowfill are excluded from Scope of Work. 32. Special coatings and/or special floor preparations required for concrete due to moisture or ph conditions are excluded from the Scope of Work. 33. Estimate excludes any and all wet concrete curing methods and materials. Concrete to be cured will utilize a curing compound. DIVISION FOUR - MASONRY

Bear Creek 10/29/2026 100% CD Clarifications

34. New masonry brick at Art Patio Scupper may not exactly match color of existing brick. Exact color matching of new masonry brick at Art Patio Scupper has been excluded. DIVISION FIVE - METALS

35. Fransen Pittman excludes this division in its entirety. DIVISION SIX - CARPENTRY

36. All carpentry is limited to roof curb backing, no other carpentry scope has been included. DIVISION SEVEN – M OISTURE PROTECTION

37. Roofing scope limited to repair at TPO where material has detached, nonpenetrating mobile guardrails & roof flashings at mechanical equipment. All other existing roof areas are excluded. 38. Roofing areas located outside the designated scope areas are presumed to be compliant with relevant codes and function properly. If any issues with these systems a ect the scope of work defined in these plans, or if code deficiencies are identified by the AHJ, further investigation, revised pricing, and adjustments to the project schedule may become necessary.

DIVISION EIGHT – DOORS, WINDOWS & GLASS

39. Fransen Pittman excludes this division in its entirety. DIVISION NINE - FINISHES

Bear Creek 10/29/2026 100% CD Clarifications

40. Floor covering prices do not include special high moisture and/or excessive alkalinity adhesives or special floor preparations. 41. Exact Match of new carpet/lvt areas to existing excluded. 42. All patching for Mechanical, Electrical, Plumbing, Fire Alarm & Low Voltage is to be Level 4 drywall finish. Level 5 finishes are excluded. 43. Excludes all acoustic sealants at ceiling tiles 44. Wall assembly have not been provided at time of GMP. All scopes of work assume no conflicts with other MEPF systems or building structure. All scopes assume minimal drywall & painting rework outside the direct scope area. DIVISION TEN - SPECIALTIES

45. Fransen Pittman excludes this division in its entirety. DIVISION ELEVEN - EQUIPMENT

46. Equipment scope limited to (2) bowl prep sink & (3) dry storage shelving units and bid per spec. All other kitchen equipment excluded. Any changes to quantities, site conditions or utility requirements excluded. DIVISION TWELVE - FURNISHINGS DIVISI 47. Fransen Pittman excludes this division in its entirety. DIVISION THIRTEEN – SPECIAL CONSTRUCTION EVEN

48. Fransen Pittman excludes this division in its entirety. DIVISION FOURTEEN – CONVEYING SYSTEMS

49. Fransen Pittman excludes this division in its entirety.

Bear Creek 10/29/2026 100% CD Clarifications

DIVISION TWENTY-ONE - FIRE SUPPRESSION

50. (20) fire sprinkler relocation/adds assumed in Fire sprinkler allowance. Any further quantity is excluded. 51. Any new fire sprinkler heads added will match existing with flexpipe. 52. Main line or branch line relocation is excluded. DIVISION TWENTY-TWO - PLUMBING

53. Plumbing & Hydronic systems located outside the designated scope areas are presumed to be compliant with relevant codes and function properly. If any issues with these systems a ect the scope of work defined in these plans, or if code deficiencies are identified by the AHJ, further investigation, revised pricing, and adjustments to the project schedule may become necessary. 54. Test and balance of new plumbing systems included. All existing plumbing systems are excluded. 55. BIM and 3D coordination excluded. 56. Excludes all seismic requirements. 57. Excludes energy modeling. DIVISION TWENTY-THREE - HVAC

58. The permanent heating/cooling equipment provided as part of the Scope of Work may be used by Fransen Pittman for construction heating/cooling prior to Substantial Completion of the Project. Proper equipment maintenance, as recommended by the manufacturer, shall be implemented by Fransen Pittman. The warranty period on said equipment shall begin when such equipment is put into use during construction. 59. Compete Test & Balance of scope associated equipment included. 60. Duct Cleaning is excluded. 61. BIM and 3D coordination excluded.

Bear Creek 10/29/2026 100% CD Clarifications

62. Exclude all seismic requirements. 63. Exclude energy modeling language 64. HVAC systems located outside the designated scope areas are presumed to be compliant with relevant codes and function properly. If any issues with these systems a ect the scope of work defined in these plans, or if code deficiencies are identified by the AHJ, further investigation, revised pricing, and adjustments to the project schedule may become necessary. DIVISION TWENTY-SIX - ELECTRICAL

65. Electrical systems located outside the designated scope areas are presumed to be compliant with relevant codes and function properly. If any issues with these systems a ect the scope of work defined in these plans, or if code deficiencies are identified by the AHJ, further investigation, revised pricing, and adjustments to the project schedule may become necessary. 66. Fransen Pittman excludes replacement of all light bulbs used in permanent fixtures during construction regardless of the duration of use. However, all bulbs that are not working or are burnt out at the time of Substantial Completion will be replaced by Fransen Pittman. 67. Fire Alarm is a deferred submittal and final design, and cost will be determined by the AHJ. 68. BIM and 3D coordination excluded or included 69. Exclude all seismic requirements. 70. Exclude energy modeling language DIVISION TWENTY-SEVEN & TWENTY-EIGHT – LOW VOLTAGE

71. Fransen Pittman excludes this division in its entirety.

Exhibit C Itemization of the GMP

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

11/2/2026 1:50 PM

Fransen Pittman General Contractors

BVSD Bear Creek Summer 27 Renovations 100% Construction Documents ESTIMATE DATE: BUILDING AREA IN SQ FT: DRAWINGS PREPARED BY: DRAWINGS ARE DATED:

DIVISION TOTAL

DIVISION RECAP

DIV NO

$ PER S.F.

10/29/26 56500 RTA 9/28/2026

% OF TTL

General Conditions

94,750

$1.68

3.7%

General Requirements, Existing Conditions, Site Work

453,863

$8.03

17.7%

03

Concrete

39,485

$0.70

1.5%

04

Masonry

EXCLUDED

05

Metals

20,143

$0.36

0.8%

06

Carpentry

14,474

$0.26

0.6%

07

Moisture Protection

174,719

$3.09

6.8%

08

Doors, Windows & Glass

09

Finishes

176,925

$3.13

6.9%

10

Specialties

EXCLUDED

11

Equipment

150,121

$2.66

5.9%

12

Furnishings

EXCLUDED

13

Special Construction

EXCLUDED

14

Conveying Systems

EXCLUDED

00 01 02 31 32 33 34

EXCLUDED

21 22 23

Mechanical

613,733

$10.86

24.0%

26 27 28

Electrical & Low Voltage

563,433

$9.97

22.0%

DIRECT COST

2,301,646

$40.74

90.01%

State & Local Tax

5.330%

4,026

$0.07

0.16%

Use Tax Allowance

EXCL

By Owner

Permit & Plan Review Fee Allowance

EXCL

By Owner

Project Fee (on direct cost of work)

5.00%

115,082

$2.04

5.00%

Construction Contingency

2.50%

63,928

$1.13

2.50%

Bidding and Buyout Contingency

0.50%

12,756

$0.23

0.50%

Liability Insurance

1.405%

35,928

$0.64

1.405%

Builder's Risk Insurance Allowance

0.06%

1,588

$0.03

0.06%

Design Contingency

0.00%

0

$0.00

0.000%

22,167

$0.39

0.87%

$2,557,121

$45.26

100.0%

$45.26

100.0%

Performance and Payment Bond

LS

TOTAL COST ACCEPTED TRACKING LOG ITEM (See Exhibit H)

Included Above

GMP TOTAL

$2,557,121

Preconstruction Fee (not included above)

LS

Page 1

$5,256

10/29/2026 1:40 PM

Fransen Pittman General Contractors

Division 00 General Conditions Item Code

ITEM DESCRIPTION

ITEM TOTAL

$ PER S.F.

% OF TTL

10.0 Wks 5.0 Wks 1.0 Inc 1.0 Inc

65,087 26,019 Inc. In Fee Inc. In Fee

$1.15 $0.46

2.5% 1.0%

10 Wks 10 Wks 1 Clar 10 Wks 10 Wks

260 260 Clarification 325 325

$0.00 $0.00

0.0% 0.0%

$0.01 $0.01

0.0% 0.0%

1 Ls Excl Excl 3 Mo 1 LS 1 Mo 1 Ls 1 Ls Excl 1 Ls 1 Ls

150 Excluded Excluded 300 150 1,100 59 450 Excluded 150 115

$0.00

0.0%

$0.01 $0.00 $0.02 $0.00 $0.01

0.0% 0.0% 0.0% 0.0% 0.0%

$0.00 $0.00

0.0% 0.0%

DIVISION 1 TOTALS

94,750

$1.68

3.7%

QUAN

UNIT

01 10 00 ADMINISTRATIVE REQUIREMENTS 01 11 01 01 11 06 01 11 07 01 11 00

Superintendent Project Engineer Project Coordinator - Included in Project Fee Project Manager - Included in Project Fee

01 12 01 01 12 02 01 12 03 01 12 04 01 12 05

Courier Reproductions/Reprographics Progress photographs Field Office Equipment Field Office Supplies

01 21 01 01 21 02 01 21 03 01 21 04 01 21 06 01 22 01 01 22 02 01 22 05 01 22 06 01 22 07 01 22 08

Jobsite telephone/Sup. Cell phone/Radios Electrical, Gas, Water Consumption Costs By Owner Temporary Water By Owner Portable chemical toilets Jobsite IT Office trailer Job sign Temporary storage Weather protection Safety supplies/First Aid Water, ice and cups

01 12 00 FIELD OFFICE EXPENSES

01 21 00, 01 22 00 TEMPORARY FACILITIES

Page 2

10/29/2026 1:40 PM

Fransen Pittman General Contractors

Division 2 Site Work LINE NO.

QUAN

ITEM DESCRIPTION

UNIT

$ PER S.F.

% OF TTL

$0.00

0.0%

$0.02 $0.16 $0.06 $0.14

0.0% 0.4% 0.1% 0.3%

21,773

$0.39

0.9%

43,007 Inc Above Inc Above Inc Above Inc Above Inc Above Inc Above Inc Above Inc Above Inc Above Inc Above 27,906 Inc Above Inc Above Inc Above Inc Above Inc Above Inc Above Inc Above

$0.76

1.7%

$0.49

1.1%

$1.26

2.8%

$0.00

0.0%

51,000 Inc Above Inc Above Inc Above Inc Above Inc Above

$0.90

2.0%

51,000

$0.90

2.0%

40,917 Inc Above Inc Above 8,400 EXCLUDED

$0.72

1.6%

$0.15

0.3%

49,317

$0.87

1.9%

3,185 Inc Above

$0.06

0.1%

3,185

$0.06

0.1%

$0.00

0.0%

$0.56

1.2%

ITEM TOTAL

02 32 00 Geotechnical Investigation 1 02 32 00

By Owner if needed

1 Excl

Geotechnical Investigation

EXCLUDED 0

02 25 10 Site Basic Means & Materials 1 2 3 02 25 10

Safety and security barriers and signage Install and maintain site safety materials Dumpsters and waste management Trash hauling

10 Wks 10 Wks 10 Wks 10 Wks

Site Basic Means & Materials

1,250 9,136 3,250 8,136

02 41 13 Selective Demolition 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 02 41 13

Selective Demo Pkg Site Concrete Demo Architectural Precast Cap - Removal by Mason Demo Concrete Floors Cafeteria-Water Entry Room for Grease Interceptor Kitchen Storage Room Walls & Floor Demo - Trend Log Item #1 Flooring & Wallbase Demo Acoustical Ceiling Demo MEP Haul off only Light Fixture Haul off only Roofing Demo Playground Demo Pkg Concrete Sidewalk - Demo & Haull Off Concrete Ramp - Demo & Haull Off Concrete Curb - Demo & Haul Off Demo of Play Equipment Demo Existing 4' Chain Link Fence EWF - Demo & Haull Off Stump Grinding/Removal

1 LS 595 SF 100 SF 1 LS 60 LF 1 LS 11,010 SF 1,380 SF 1 INCL 1 INCL 1 INCL 1 Excl 610 SF 10 SF 135 LF 3 EA 290 LF 5,660 SF 1 EA

Selective Demolition

70,913

02 58 00 Hazardous Material Remediation 1 02 58 00

Allowance for hazardous material remediation

1 Excl

Hazardous Material Remediation

EXCLUDED 0

31 00 00 Earthwork 1 2 3 4 5 6 31 00 00

Earthwork Allowance 12" Import at Playground & Boulder Areas #1 & #2 Soil Compaction to 95% Crusher Fines Pkg Crusher Fines Import at Boulder Areas #1 & #2 Leveling Existing Crusher Fines

1 LS 5,660 SF 5,660 SF 1 LS 550 SF 122 SF

Earthwork

32 12 00 Asphalt Paving & Patching 1 2 3 4 5 32 12 00

Asphalt Patching Pkg Roto-Mill & Provide 2" Asphalt Overlay Across Existing Play Area Remove 4' Wide Section Down To Base Material, Recompact & Patch Asphalt Temp Access Road Sealcoat existing Asphalt Play Area- See Trend Log

1 Ls 675 Sy 580 Sf 1 Ls 1 Excl

Asphalt Paving & Patching

32 17 23 Pavement Markings 1 2 32 17 23

Pavement Marking Pkg Re-Stripe Asphalt

1 Ls Incl

Pavement Markings

32 17 13 Parking Bumpers 1 32 17 13

Parking Bumpers Excluded

1 Excl

Parking Bumpers

EXCLUDED 0

32 13 13 Site Concrete Material 1 2 3 4 5 6 7 8 9 10 11 12 13 32 13 13

Site Concrete Pkg Replace Site Sidewalk Concrete New Concrete Drain Pan at West Exterior - 3' x 1' Tactile Warning Strip (Truncated Domes) Install Concrete Flooring Patch Back Flooring at Kitchen Storage-See Trend Log Flooring at Cafeteria-Water Entry Room Relocation of existing boulder away from concrete sidewalk Playground Concrete Pkg Playground New Concrete Concrete Edger around existing tree New Concrete Drain Pan at West Exterior - 3' x 1' Relocation of existing boulder away from concrete sidewalk

1 Ls 595 Sf 1 Ea 95 Sf 1 Incl 1 Excl 60 Lf 1 LS 1 Ea 680 SF 63 LF 1 EA 1 LS

Site Concrete Material

32 18 23 Athletic Surfacing Page 3

31,730 Inc Above Inc Above Inc Above Inc Above Inc Above Inc Above 2,970 22,394 Inc Above Inc Above Inc Above 3,828

$0.05 $0.40

0.1% 0.9%

$0.07

0.1%

60,922

$1.08

2.4%

10/29/2026 1:40 PM

Fransen Pittman General Contractors

Division 2 Site Work LINE NO.

1 2 3 4 5 6 7 32 18 23

QUAN

ITEM DESCRIPTION

Synthetic Turf Pkg Nailer Board at Edges (1" Stable @ 3" OC) Synthetic Turf Infill per Specs Safety Foam Pad, 2" Thickness Min Washed/Crushed Gravel (4" Min Thickness) HDPE Pipe

UNIT

1 415 LF 5,120 SF 5,120 SF 5,120 SF 5,120 SF 100 LF

Athletic Surfacing

ITEM TOTAL

$ PER S.F.

% OF TTL

105,065 Inc Above Inc Above Inc Above Inc Above Inc Above Inc Above

$1.86

4.1%

105,065

$1.86

4.1%

25,000 Inc Above Inc Above Inc Above Inc Above

$0.44

1.0%

25,000

$0.44

1.0%

$0.18

0.4%

$0.18

0.4%

$0.19 $0.02

0.4% 0.0%

$0.21

0.5%

$0.14 $0.06 $0.35 $0.15 $0.09

0.3% 0.1% 0.8% 0.3% 0.2%

44,840

$0.79

1.8%

453,863

$8.03

17.7%

32 31 00 Fences & Gates 1 2 3 4 5 32 31 00

Fencing Allowance Demo Existing Fence & Privacy Screen Install New 6', Black Chain Link Fence along Table Mesa Dr. & Playground South Side Install New 6' Privacy Slats with 80% Visability Block Note: Fencing along playground north side to remain as is

1 LS 280 LF 280 LF 280 LF 141 LF

Fences & Gates

32 90 00 Landscaping 1 32 90 00

Landscaping Allowance- Damages During Asphalt & MEP work

1 Allow

Landscaping

10,000 10,000

02 99 01 General Requirements 1 2 02 99 01

Progressive site cleaning Miscellaneous tools

10 Wks 10 Wks

General Requirements

10,849 1,000 11,849

02 99 02 Material Handling 1 2 3 4 5 02 99 02

Labor for material moving during the duration of construction Material buggies and carts for material moving for the duration of construction Furniture Moving Allowance Additional Dumspters for Material Recycling Ticket Processing & Tracking

10 Wks 10 Wks 1 Allow 10 Wks 10 Wks

Material Handling

DIVISION 2 TOTALS

Page 4

8,136 3,250 20,000 8,250 5,204

10/29/2026 1:40 PM

Fransen Pittman General Contractors

Division 3 Concrete LINE NO.

QUAN

ITEM DESCRIPTION

UNIT

ITEM TOTAL

$ PER S.F.

% OF TTL

39,485 Inc Above Inc Above

$0.70

1.5%

39,485

$0.70

1.5%

39,485

$0.70

1.5%

03 45 00 Architectural Precast Concrete Trim 1 2 3 03 45 00

Arch Concrete & Masonry Pkg Architectural Precast Cap, Integral - Remove & Replace Art Patio Scupper - Cut in, Mortar Repair & Toothing

1 Ls 105 Sf 1 Ea

Architectural Precast Concrete Trim

DIVISION 3 TOTALS

Page 5

10/29/2026 1:40 PM

Fransen Pittman General Contractors

Division 5 Steel LINE NO.

QUAN

ITEM DESCRIPTION

UNIT

ITEM TOTAL

$ PER S.F.

% OF TTL

20,143 Inc Above Inc Above Inc Above Inc Above Inc Above Inc Above Inc Above

$0.36

0.8%

20,143

$0.36

0.8%

20,143

$0.36

0.8%

05 51 00 Misc Metals 1 2 3 4 5 6 7 8 05 51 00

Playground Sidewalk Ramp - Handrail Pkg Wall Mounted Handrial 2-1/2" Wall Brackets, 4' OC Free Standing Handrail Top Rail, Mid Rai and Lower Rail Intermediary Posts Embedment - 8" Deep, 6" from edge Seal 1/2" Top

1 LS 23 LF 7 EA 24 LF 1 INC 3 EA 5 EA 5 EA

Misc Metals

DIVISION 5 TOTALS

Page 6

10/29/2026 1:40 PM

Fransen Pittman General Contractors

Division 6 Woods & Plastics LINE NO.

QUAN

ITEM DESCRIPTION

UNIT

ITEM TOTAL

$ PER S.F.

% OF TTL

14,474 Inc Above Inc Above EXCLUDED

$0.26

0.6%

14,474

$0.26

0.6%

14,474

$0.26

0.6%

06 10 00 Rough Carpentry 1 2 3 4 06 10 00

Rough Carpentry Blocking & Backing RTU-4 Roof Curb Blocking & Backing CU-1 Roof Curb Blocking & Backing Walk-in Cooler CU Roof Curb - See Trend Log

1 Ls 1 Incl 1 Incl 1 Excl

Rough Carpentry

DIVISION 6 TOTALS

Page 7

10/29/2026 1:40 PM

Fransen Pittman General Contractors

Division 7 Thermal & Moisture Protection LINE NO.

QUAN

ITEM DESCRIPTION

UNIT

ITEM TOTAL

$ PER S.F.

% OF TTL

24,293 Inc Above Inc Above Inc Above 51,285 88,435 EXCLUDED

$0.43

1.0%

$0.91 $1.57

2.0% 3.5%

164,014

$2.90

6.4%

10,705 Inc Above Inc Above Inc Above Inc Above

$0.19

0.4%

10,705

$0.19

0.4%

174,719

$3.09

6.8%

07 50 00 Flat Roofing 1 2 3 4 5 6 7 07 50 00

Roofing Pkg Repair TPO Roofing Where Transition Material Has Detached Install Non-Penetrating Mobile Roof Guardrails Roof Flashing at Mechanical Equipment Ashalt Shingle Roofing Replacement - Trend Log #3 Asphalt Shingle Roofing Replacement with TPO - Trend Log #4 Clerestory Window Infill- See Trend Log

1 LS 40 SF 50 LF 3 EA 1 LS 1 LS 1 EXCL

Flat Roofing

07 92 00 Joint Sealers 1 2 3 4 5 07 92 00

Building & Joint Sealants Pkg Caulk New Site Work Cut & Re-Caulk Roof Flashings Re-point Sills Masonry Repair of Scupper

1 Ls 1 INCL 1 INCL 1 INCL 1 INCL

Joint Sealers

DIVISION 7 TOTALS

Page 8

10/29/2026 1:40 PM

Fransen Pittman General Contractors

Division 9 Finishes LINE NO.

QUAN

ITEM DESCRIPTION

UNIT

ITEM TOTAL

$ PER S.F.

% OF TTL

15,990 Inc Above

$0.28

0.6%

15,990

$0.28

0.6%

22,377 Inc Above Inc Above Inc Above Inc Above Inc Above 10,000

$0.40

0.9%

$0.18

0.4%

32,377

$0.57

1.3%

09 21 16 Gypsum Board Assemblies 1 2 09 21 16

Drywall/Framing Pkg Accent Soffit at Library

1 Ls 400 SF

Gypsum Board Assemblies

09 51 00 Acoustical Ceilings 1 2 3 4 5 6 7 09 51 00

Acoustical Ceiling Pkg Replace Ceiling Tiles & Grid Rms 103A & 103C Rm 122 Salvage Ceiling Tiles Main Office- Rms 102, 102A & 103 Above Ceiling Remediation for Code Compliance

1 Ls 1,380 Sf 690 Sf 840 Sf 880 Sf Incl 1 Allow

Acoustical Ceilings

09 01 60 Flooring Prep 1 09 01 60

Floor core testing for chemical content and moisture content

1 Allow

Flooring Prep

$0.09

0.2%

5,000

$0.09

0.2%

81,772 Inc Above Inc Above Inc Above 2,185

$1.45

3.2%

$0.04

0.1%

83,957

$1.49

3.3%

9,130 Inc Above 2,527 EXCLUDED 15,178 Inc Above Inc Above

$0.16

0.4%

$0.04

0.1%

$0.27

0.6%

$0.47

1.0%

0

$0.00

0.0%

12,765

5,000

09 60 00 Flooring 1 2 3 4 5 09 60 00

Flooring Pkg Install Carpet Tile Replace Rubber Stair Treads & Risers Install LVT Flooring Floor Patching at Walk in Cooler - Trend Log Item #1

1 Ls 11,010 Sf 12 Ea 280 Sf 1 LS

Flooring

09 91 00 Painting 1 2 3 4 5 6 7 09 91 00

Painting Pkg Ceiling Paint at Drywall Patch for MEP work North Playground Handrail Painting Interior Paint Renewal - See Trend log for pricing Exterior High Performance Paint - Trend Log Item #2 Painting exposed/worn metal along east entry on building as shown on AS-101 Painting exposed/worn metal along south face of gym as shown on AS-101

1 LS 1 INCL 1 LS 1 EXCL 1 LS 1 LS 1 LS

Painting

26,835

09 99 01 Flooring Stipulations 1

Fransen Pittman cannot warrant any flooring product without first verifying the substrate material is free of defects, including but not limited to high moisture content or chemical composition compatibility with floor coverings and adhesives. Fransen Pittman’s

1 CLAR

Clarification

2

Flooring is installed based on the results of manufacturer required testing at the time of installation. Fransen Pittman cannot provide a warranty if a product failure occurs and subsequent test results differ from testing at the time of installation.

1 CLAR

Clarification

09 99 01

Flooring Stipulations

09 99 02 Final Clean 1 09 99 02

Final Clean of floors under construction areas

1 LS

Final Clean

DIVISION 9 TOTALS

Page 9

$0.23

0.5%

12,765

$0.23

0.5%

176,925

$3.13

6.9%

10/29/2026 1:40 PM

Fransen Pittman General Contractors

Division 11 Equipment LINE NO.

QUAN

ITEM DESCRIPTION

UNIT

ITEM TOTAL

$ PER S.F.

% OF TTL

$0.23

0.5%

$1.26

2.8%

$1.50

3.3%

$0.63

1.4%

11 40 00 Foodservice Equipment 1

Food Service Equipment Pkg

1 LS

13,189

2

Sink, Vegetable Prep, 2EA 18x18 Sink Bowls- Nationwide Fabrication- 2N1818

1 EA

Inc Above

3

Faucet, 12" Spout- T&S Brass- B-0231

1 EA

Inc Above

4

Dry Storage Racks- Metro Shelving- 2448NK3 (Shelves, 74PK3 (Posts)

3 EA

Inc Above

5

Walk-In Cooler - Utilize current dry storage room for walk-in cooler location- Trend Log Item #1

6

Demo Walls, Flooring & Ceiling of Dry Storage

1 LS

71,421

1 INCL

Inc Above

7

Remove & dispose of existing shelving

1 INCL

Inc Above

8

Patch Existing Walls

1 INCL

Inc Above

9

Patch Epoxy Flooring

1 INCL

Inc Above

10

Install new Walk in cooler with ramp installed on top of existing slab, ~6'x7'- Thermo Kool- Custom

1 INCL

Inc Above

11

Walk-in cooler evaporator coil- Thermo Kool- Custom

1 INCL

Inc Above

12

Walk-in cooler condenser, Remote Mounted- Thermo Kool- Custom

1 INCL

Inc Above

13 12 13 11 40 00

Walk-In Cooler Shelving- Metro Shelving- 1848NK3, 1830NK3, 1836NK3 (Shelves), 74PK3 (Posts)

1 INCL

Inc Above

New Sink, 2 Compartment

1 EA

Inc Above

New Faucet

1 EA

Foodservice Equipment

Inc Above 84,610

11 68 00 Play Field Equip. and Structures 1

Playground Equipment Pkg

1 LS

35,512

2

8' Two Bay Arch Swing, 3 Belts + Baby Swing, Color TBD

1 EA

Inc Above

3

Spin Rocker, Color TBD

1 EA

Inc Above

4

Pitch Perfect, Colors TBD

1 EA

Inc Above

5

Installation

1 INCL

Inc Above

6

Concrete Footings

10 EA

Inc Above

7

Protection of existing play Structures

1 INCL

Inc Above

8

Play Structure

90 LF

Inc Above

9

Tube Structure

30 LF

Inc Above

10

Permitting/Certification

1 INCL

Inc Above Inc Above

11

Freight

1 INCL

12

Playground Permit & PR-01 Set - Constructability & Design Allowance

1 ALLOW

11 68 00

Play Field Equip. and Structures

DIVISION 11 TOTALS

Page 10

$0.53

1.2%

65,512

$1.16

2.6%

150,121

$2.66

5.9%

30,000

10/29/2026 1:40 PM

Fransen Pittman General Contractors

Division 15 Mechanical LINE NO.

QUAN

ITEM DESCRIPTION

UNIT

$ PER S.F.

% OF TTL

$0.19 $0.03

0.4% 0.1%

12,165

$0.22

0.5%

38,982 Inc Above Inc Above Inc Above Inc Above Inc Above

$0.69

1.5%

38,982

$0.69

1.5%

$9.86

21.8%

$0.04

0.1%

$9.90

21.9%

ITEM TOTAL

21 00 00 Fire Suppression 1 2 21 00 00

Fire Protection Systems Turn up, Relocation & Adds Walk in Cooler - Add (1) additional sprinkler

1 Allow 1 LS

Fire Suppression

10,665 1,500

22 00 00 Plumbing 1 2 3 4 5 6 22 00 00

Plumbing Pkg Connect Facuet,12" Sink & 2 Compartment, Stainless Steel By Food Service Vendor Connect Into Existing Domestic Water & Waste Connections Provide & install Indirect Waste Connection to Existing Floor Sink Existing floor drain in kitchen to serve as overflow drain for new faucet Re-connect Condensate Piping for New Split System

1 Ls 1 INCL 1 INCL 1 INCL 1 Clar 1 INCL

Plumbing

23 00 00 HVAC 1

Mechanical Pkg

1 LS

557,323

2

Remove & Replace Roof Top Unit, RTU-4, Curb & Associated Components-Aaon- RNA

1 INCL

Inc Above

3

New Supply air ductwork for RTU-4

1 INCL

Inc Above

4

New Return Air Ductwork for RTU-4

1 INCL

Inc Above

5

New Sound Attenuators for RTU-4

1 INCL

Inc Above

6

Remove & Replace Split System Condensing Unit, AC-1 & CU-1 , Curb & Associated Components

1 INCL

Inc Above

7

New Condensate Piping & Drain Pan for Unit Serving Music Room 122

1 INCL

Inc Above

8

Copper Drain Piping routed to nearest Mop Basin or Floor Sink

1 INCL

Inc Above

9

Exhaust Fan EF-44, 200CFM, Upblast Unit

1 INCL

Inc Above

10

Refrigerant Detection & Exhaust Ductwork Up To Exhaust Fan on Roof

1 INCL

Inc Above

11

Remove & Replace Fin Tube Radiator Control Valves

1 INCL

Inc Above

12

VAV Boxes With Hot Water Reheat Coils

4 INCL

Inc Above

13

Hydronic Piping to Rooftop Unit & VAV Boxes

1 INCL

Inc Above

14

New Supply Air Ductwork for VAV's, Misc sizes

1 INCL

Inc Above

15

Re-Attach Missing Or Loose Fan Shrouds From Existing Exhaust Fans

1 INCL

Inc Above

16

Exhaust Grilles

1 INCL

Inc Above

17

Supply Grilles & Diffusers

1 INCL

Inc Above

18

Return Grills

1 INCL

Inc Above

19

New Associated Temperature Controls

1 INCL

Inc Above

20

Test Adjust & Balance of Associated Equipment

1 INCL

Inc Above

21

Food Service Equipment - Trend Log Item #1

1 LS

22

Evaporator Coil

1 INCL

Condensing Unit

1 INCL

23 23 00 00

HVAC

2,064 Inc Above Inc Above 559,387

21 99 01 Mechanical Systems Coordinator 1

Mechanical Systems Coordinator

21 99 01

Mechanical Systems Coordinator

24 Hours

DIVISION 15 TOTALS

Page 11

$0.06

0.1%

3,199

$0.06

0.1%

613,733

$10.86

24.0%

3,199

10/29/2026 1:40 PM

Fransen Pittman General Contractors

Division 16 Electrical LINE NO.

QUAN

ITEM DESCRIPTION

UNIT

ITEM TOTAL

$ PER S.F.

% OF TTL

42,809 Inc Above

$0.76

1.7%

$3.83

8.5%

26 00 00 Electrical 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 26 00 00

Electrical Pkg Power to New Mechanical Units

1 LS 1 INCL

Demo Existing Circuit. Remove Conduit & Wires Back to Source & Provide New Power Circuit From Existing Panel. New Conduit Wires & Breakers- For MEP Work RTU-4 VAV's EF-44 CU-2 AC-2 Demo Existing Circuit. Remove Conduit & Wires Back to Source RTU-5- Disconnect Only EF-34- Disconnect Only CU-E- Disconnect Only Lighting SOW Priority 1- Trend Log Item #7 Lighting SOW Priority 2- See Trend Log Walk In Cooler connect Power to cooler, condensing unit & exhaust fan - Trend Log #1

1 INCL

Inc Above

1 INCL 1 INCL 1 INCL 1 INCL 1 INCL 1 INCL 1 INCL 1 INCL 1 INCL 1 LS 1 EXCL 1 LS

Inc Above Inc Above Inc Above Inc Above Inc Above Inc Above Inc Above Inc Above Inc Above 216,244 EXCLUDED 5,256

Electrical

$0.09

0.2%

$4.68

10.3%

$5.29

11.7%

299,124

$5.29

11.7%

563,433

$9.97

22.0%

264,309

28 43 00 Fire Alarm Systems 1

Fire Alarm Package

1 LS

299,124

2

Complete NFPA 72 compliant fire alarm system (Silent Knight, Farenhyt, Mircom, no substitutions)

1 INCL

Inc Above

Main Fire Alarm Panel Installed in Main Electrical Room

1 INCL

3 28 43 00

Fire Alarm Systems

DIVISION 16 TOTALS

Page 12

Inc Above

Exhibit D Contract Schedule & change order for the GMP is Contract Schedule to be provided after amendment executed

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

BVSD BEAR CREEK ES RENOVATION ID

Task Name

Duration

Start

Finish Jul

PROJECT MILESTONES 3 4 5

NTP Substantial Completion Project Final Completion ENTITLEMENTS & PERMITTING

8 9

Submit Plans Receive Building Permit PRE-CONSTRUCTION ACTIVITIES DESIGN ACTIVITIES

13 14

GMP Package Subcontractor Buyout PRECON ACTIVITIES

11 16 17 18

22 23 24 25 26 27 28 29 30 31 32 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55

Mon 8/24/26

Fri 7/30/27

5 days 0 days 0 days

Mon 8/24/26 Fri 7/23/27 Fri 7/30/27

Fri 8/28/26 Fri 7/23/27 Fri 7/30/27

100 days

Fri 7/24/26

Mon 12/14/26

100 days 0 days

Fri 7/24/26 Mon 12/14/26 Mon 12/14/26 Mon 12/14/26

213 days

Fri 7/24/26

Mon 5/24/27

32 days

Fri 7/24/26

Mon 9/7/26

21 days 6 days

Fri 7/24/26 Mon 8/31/26

Fri 8/21/26 Mon 9/7/26

0 days

Fri 7/24/26

Fri 7/24/26

Arch Design Documents

0 days

Fri 7/24/26

Fri 7/24/26

PROCUREMENT ACTIVITIES

181 days

Tue 9/8/26

Mon 5/24/27

180 days 51 days 45 days

Tue 9/8/26 Mon 3/15/27 Tue 3/23/27

Fri 5/21/27 Mon 5/24/27 Mon 5/24/27

Mechanical -Submittals/Approvals and Fabrication and Delivery Precast Caps -Submittals/Approvals and Fabrication and Delivery Fire Alarm Devices - Submittals/Approval and Fabrication and Delivery CONSTRUCTION ACTIVITIES

20

239 days

51 days

Mon 5/24/27

Wed 8/4/27

Mobilization

1 day

Mon 5/24/27

Mon 5/24/27

SITEWORK

50 days

Tue 5/25/27

Wed 8/4/27

Layout and Sawcut Sidewalks Selective Site Demo Roto Mill Large Play Area Replace Site Wall Cap Form and Pour Drain Pans/Concrete Walks North Side Overlay Large Play Area Repair Art Patio Masonry Site Wall Scupper Relocate (3) Stones Strip Large Play Area Form and Pour Zero Ramps w/Tactile Warning Strip in South Parking Lot Repair Landscaping

3 days 6 days 4 days 4 days 5 days 2 days 3 days 3 days 2 days 3 days 5 days

Tue 5/25/27 Fri 5/28/27 Tue 6/8/27 Tue 6/8/27 Tue 6/8/27 Mon 6/14/27 Mon 6/14/27 Tue 6/15/27 Wed 6/16/27 Fri 6/18/27 Wed 6/23/27

Thu 5/27/27 Mon 6/7/27 Fri 6/11/27 Fri 6/11/27 Mon 6/14/27 Tue 6/15/27 Wed 6/16/27 Thu 6/17/27 Thu 6/17/27 Tue 6/22/27 Tue 6/29/27

SITEWORK - PLAYGROUND

50 days

Tue 5/25/27

Wed 8/4/27

1 day 1 day 1 day 5 days 5 days 5 days 1 day 2 days 3 days 3 days 1 day 1 day 3 days 15 days 5 days 2 days 10 days 2 days 4 days 15 days 2 days 5 days

Tue 5/25/27 Tue 5/25/27 Tue 5/25/27 Wed 5/26/27 Wed 5/26/27 Wed 5/26/27 Thu 6/3/27 Fri 6/4/27 Tue 6/8/27 Tue 6/8/27 Thu 6/10/27 Fri 6/11/27 Fri 6/11/27 Mon 6/14/27 Wed 6/16/27 Wed 6/23/27 Wed 6/23/27 Fri 6/25/27 Tue 7/6/27 Thu 7/8/27 Thu 7/29/27 Thu 7/29/27

Tue 5/25/27 Tue 5/25/27 Tue 5/25/27 Wed 6/2/27 Wed 6/2/27 Wed 6/2/27 Thu 6/3/27 Mon 6/7/27 Thu 6/10/27 Thu 6/10/27 Thu 6/10/27 Fri 6/11/27 Tue 6/15/27 Fri 7/2/27 Tue 6/22/27 Thu 6/24/27 Wed 7/7/27 Mon 6/28/27 Fri 7/9/27 Wed 7/28/27 Fri 7/30/27 Wed 8/4/27

Identify and Tag Salvage Items Tree Protection Layout Demo and Sawcut Selective Site Demo Selective Playground Demo Remove and Salvage Items to be Reinstalled Layout Sidewalk/Ramp Grade Sidewalk/Ramp Form and Pour Sidewalks Form and Pour Concrete Curb Set Sidewalk Trench Drains Field Measure Site Railings Perforated PVC Pipe Underdrain Fabricate Site Railings Backfill Synthetic Turf Area Reset Existing Benches to Correct Elevation Install New Play Equipment Relocate Boulders Site Railings Install Synthetic Turf System Crusher Fines Install Privacy Slats at Fence Line

Schedule File: 26-1001_BVSD_Bear Creek ES_100%CD Schedule

Aug

Sep

Oct

Nov

Dec

2027 Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

2028 Jan

Feb

Mar

Apr

May

NTP Substantial Completion Project Final Completion Submit Plans Receive Building Permit

GMP Package Subcontractor Buyout Arch Design Documents Mechanical -Submittals/Approvals and Fabrication and Delivery Precast Caps -Submittals/Approvals and Fabrication and Delivery Fire Alarm Devices - Submittals/Approval and Fabrication and Delivery Mobilization Layout and Sawcut Sidewalks Selective Site Demo Roto Mill Large Play Area Replace Site Wall Cap Form and Pour Drain Pans/Concrete Walks North Side Overlay Large Play Area Repair Art Patio Masonry Site Wall Scupper Relocate (3) Stones Strip Large Play Area Form and Pour Zero Ramps w/Tactile Warning Strip in South Parking Lot Repair Landscaping Identify and Tag Salvage Items Tree Protection Layout Demo and Sawcut Selective Site Demo Selective Playground Demo Remove and Salvage Items to be Reinstalled Layout Sidewalk/Ramp Grade Sidewalk/Ramp Form and Pour Sidewalks Form and Pour Concrete Curb Set Sidewalk Trench Drains Field Measure Site Railings Perforated PVC Pipe Underdrain Fabricate Site Railings Backfill Synthetic Turf Area Reset Existing Benches to Correct Elevation Install New Play Equipment Relocate Boulders Site Railings Install Synthetic Turf System Crusher Fines Install Privacy Slats at Fence Line Page 1 of 3

Print Date: Fri 10/2/26 7:41 AM

BVSD BEAR CREEK ES RENOVATION ID

Task Name

Duration

Start

Finish Jul

CORE & SHELL CORE & SHELL - AREA A 57 58 59 60 61 62 63 64 65 66 67 68 69 70

Set up Roof Protection at Core & Shell MEP Safe Off Roof Equipment Roof Area 111 Crane off Existing RTU 4, CU-1 Roof Area 111 Demo Roofing and Install Curb and Dry in for Existing RTU 4 Roof Area 111 Demo Roof and Install Curb and Dry in for new EF-44 Roof Area 111 Set RTU, EF and CU Roof Area 111 Repair TPO Transition Roof Area 111 Reinstall Missing or Loose Fan Shroud MEP Roof Equipment Connections Plumbing Roof Penetrations Area 113 Install Non-Penetration Mobile Roof Guardrails Roof Area 111 Remove and Repair Scupper High Wall Joint Sealant Roof Area 113 Clean Roof Drains & Reinstall Roof Drain Strainers at Core & Shell Roof Final Inspection INTERIOR BUILDOUT

72 73 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94

97 98 99 100 101 102 103 104 105 106 107

Tue 5/25/27

18 days

Tue 5/25/27

Fri 6/18/27

2 days 2 days 1 day 2 days 2 days 1 day 2 days 1 day 5 days 1 day 2 days 2 days 3 days 1 day

Tue 5/25/27 Tue 5/25/27 Wed 6/2/27 Thu 6/3/27 Mon 6/7/27 Wed 6/9/27 Wed 6/9/27 Thu 6/10/27 Thu 6/10/27 Fri 6/11/27 Fri 6/11/27 Fri 6/11/27 Tue 6/15/27 Fri 6/18/27

Wed 5/26/27 Wed 5/26/27 Wed 6/2/27 Fri 6/4/27 Tue 6/8/27 Wed 6/9/27 Thu 6/10/27 Thu 6/10/27 Wed 6/16/27 Fri 6/11/27 Mon 6/14/27 Mon 6/14/27 Thu 6/17/27 Fri 6/18/27

40 days

Tue 5/25/27

Wed 7/21/27

2 days 2 days

Tue 5/25/27 Tue 5/25/27

Wed 5/26/27 Wed 5/26/27

INTERIOR BUILDOUT - AREA 111

33 days

Tue 5/25/27

Mon 7/12/27

2 days 2 days 3 days 3 days 3 days 2 days 5 days 8 days 8 days 1 day 1 day 5 days 2 days 3 days 1 day 2 days 5 days 5 days 4 days 4 days

Tue 5/25/27 Thu 5/27/27 Thu 5/27/27 Thu 5/27/27 Thu 5/27/27 Wed 6/2/27 Wed 6/2/27 Wed 6/2/27 Wed 6/2/27 Mon 6/14/27 Mon 6/14/27 Mon 6/14/27 Tue 6/15/27 Thu 6/17/27 Mon 6/21/27 Tue 6/22/27 Tue 6/22/27 Tue 6/29/27 Wed 7/7/27 Wed 7/7/27

Wed 5/26/27 Fri 5/28/27 Tue 6/1/27 Tue 6/1/27 Tue 6/1/27 Thu 6/3/27 Tue 6/8/27 Fri 6/11/27 Fri 6/11/27 Mon 6/14/27 Mon 6/14/27 Fri 6/18/27 Wed 6/16/27 Mon 6/21/27 Mon 6/21/27 Wed 6/23/27 Mon 6/28/27 Tue 7/6/27 Mon 7/12/27 Mon 7/12/27

33 days

Thu 5/27/27

Wed 7/14/27

2 days 5 days 5 days 4 days 6 days 4 days 1 day 4 days 2 days 4 days 4 days 2 days

Thu 5/27/27 Wed 6/2/27 Wed 6/2/27 Wed 6/9/27 Wed 6/9/27 Thu 6/17/27 Wed 6/23/27 Thu 6/24/27 Wed 6/30/27 Wed 6/30/27 Wed 7/7/27 Tue 7/13/27

Fri 5/28/27 Tue 6/8/27 Tue 6/8/27 Mon 6/14/27 Wed 6/16/27 Tue 6/22/27 Wed 6/23/27 Tue 6/29/27 Thu 7/1/27 Tue 7/6/27 Mon 7/12/27 Wed 7/14/27

36 days

Tue 6/1/27

Wed 7/21/27

Remove Grid Tile Pathways Area 111 Selective ACT Ceiling Demo Area 111 Selective Flooring Demo Area 111 Mechanical Demo Area 111 Fire Alarm Demo Area 111 Install VAV's Above Ceiling Area 111 Demo Floor Grind Area 111 Mechanical Above Ceiling Rough-in Area 111 Fire Alarm Above Ceiling Rough-in Area 111 Mechanical Above Hardlid Final Mechanical Above Ceiling Final Fire Alarm Grid Device Area 111 Hang Drywall Hardlid Area 111 Drywall Finish Hardlid Area 111 Fire Alarm Above Ceiling Final Area 111 Prime and 1st Coat Hardlid Area 111 Grid Tile Area 111 Install Carpet Area 111 Fire Alarm Trim Area 111 Touch up Paint Area 111 Remove Grid Tile Pathways Area 113 Selective Floor Demo Area 113 Fire Alarm Demo Area 113 Demo Grind Floor Area 113 Fire Alarm Above Ceiling Rough-in Area 113 Fire Alarm Grid Device Area 113 Fire Alarm Above Ceiling Final Area 113 Grid Tile Area 113 Install Kitchen Plumbing Fixtures Area 113 Install Carpet Area 113 Fire Alarm Trim Area 113 Touch up Paint Area 113 INTERIOR BUILDOUT - AREA 112

Schedule File: 26-1001_BVSD_Bear Creek ES_100%CD Schedule

Sep

Oct

Nov

Dec

2027 Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

2028 Jan

Feb

Mar

Apr

May

Fri 6/18/27

Safe Off Protect Existing Finishes

INTERIOR BUILDOUT - AREA 113 96

18 days

Aug

Set up Roof Protection at Core & Shell MEP Safe Off Roof Equipment Roof Area 111 Crane off Existing RTU 4, CU-1 Roof Area 111 Demo Roofing and Install Curb and Dry in for Existing RTU 4 Roof Area 111 Demo Roof and Install Curb and Dry in for new EF-44 Roof Area 111 Set RTU, EF and CU Roof Area 111 Repair TPO Transition Roof Area 111 Reinstall Missing or Loose Fan Shroud MEP Roof Equipment Connections Plumbing Roof Penetrations Area 113 Install Non-Penetration Mobile Roof Guardrails Roof Area 111 Remove and Repair Scupper High Wall Joint Sealant Roof Area 113 Clean Roof Drains & Reinstall Roof Drain Strainers at Core & Shell Roof Final Inspection Safe Off Protect Existing Finishes Remove Grid Tile Pathways Area 111 Selective ACT Ceiling Demo Area 111 Selective Flooring Demo Area 111 Mechanical Demo Area 111 Fire Alarm Demo Area 111 Install VAV's Above Ceiling Area 111 Demo Floor Grind Area 111 Mechanical Above Ceiling Rough-in Area 111 Fire Alarm Above Ceiling Rough-in Area 111 Mechanical Above Hardlid Final Mechanical Above Ceiling Final Fire Alarm Grid Device Area 111 Hang Drywall Hardlid Area 111 Drywall Finish Hardlid Area 111 Fire Alarm Above Ceiling Final Area 111 Prime and 1st Coat Hardlid Area 111 Grid Tile Area 111 Install Carpet Area 111 Fire Alarm Trim Area 111 Touch up Paint Area 111 Remove Grid Tile Pathways Area 113 Selective Floor Demo Area 113 Fire Alarm Demo Area 113 Demo Grind Floor Area 113 Fire Alarm Above Ceiling Rough-in Area 113 Fire Alarm Grid Device Area 113 Fire Alarm Above Ceiling Final Area 113 Grid Tile Area 113 Install Kitchen Plumbing Fixtures Area 113 Install Carpet Area 113 Fire Alarm Trim Area 113 Touch up Paint Area 113

Page 2 of 3

Print Date: Fri 10/2/26 7:41 AM

BVSD BEAR CREEK ES RENOVATION ID

Task Name

Duration

Start

Finish Jul

109 110 111 112 113 114 115 116 117 118 119 125 126 127 121 122 123 124 129 130 131 132 133

Remove Grid Tile Pathways Area 112 Selective Floor Demo Area 112 Fire Alarm Demo Area 112 Demo Grind Floor Classroom 141 Area 112 Fire Alarm Above Ceiling Rough-in Area 112 Fire Alarm Grid Device Area 112 Fire Alarm Above Ceiling Final Area 112 Grid Tile Area 112 Install Carpet Area 112 Fire Alarm Trim Area 112 Touch up Paint Area 112

2 days 4 days 4 days 3 days 5 days 5 days 1 day 5 days 2 days 4 days 4 days

Tue 6/1/27 Wed 6/9/27 Wed 6/9/27 Tue 6/15/27 Tue 6/15/27 Tue 6/22/27 Tue 6/29/27 Wed 6/30/27 Thu 7/8/27 Mon 7/12/27 Fri 7/16/27

Wed 6/2/27 Mon 6/14/27 Mon 6/14/27 Thu 6/17/27 Mon 6/21/27 Mon 6/28/27 Tue 6/29/27 Wed 7/7/27 Fri 7/9/27 Thu 7/15/27 Wed 7/21/27

FINAL CLEAN/PUNCH LIST

7 days

Thu 7/22/27

Fri 7/30/27

Final Clean Punch List Complete Punch List

1 day 1 day 5 days

Thu 7/22/27 Fri 7/23/27 Mon 7/26/27

Thu 7/22/27 Fri 7/23/27 Fri 7/30/27

CLOSEOUT/COMMISSIOING

21 days

Thu 6/17/27

Fri 7/16/27

Mechanical Programing Mechanical Start Up Re-Balance EF Mechanical Commissioning

4 days 5 days 4 days 3 days

Thu 6/17/27 Wed 6/23/27 Thu 7/8/27 Wed 7/14/27

Tue 6/22/27 Tue 6/29/27 Tue 7/13/27 Fri 7/16/27

FINAL INSPECTION

5 days

Mon 7/19/27

Fri 7/23/27

Mechanical Final Plumbing Final Fire Alarm Final Life Safety Final Building Final

1 day 1 day 1 day 1 day 0 days

Mon 7/19/27 Tue 7/20/27 Fri 7/23/27 Fri 7/23/27 Fri 7/23/27

Mon 7/19/27 Tue 7/20/27 Fri 7/23/27 Fri 7/23/27 Fri 7/23/27

Schedule File: 26-1001_BVSD_Bear Creek ES_100%CD Schedule

Aug

Sep

Oct

Nov

Dec

2027 Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

2028 Jan

Feb

Mar

Apr

May

Remove Grid Tile Pathways Area 112 Selective Floor Demo Area 112 Fire Alarm Demo Area 112 Demo Grind Floor Classroom 141 Area 112 Fire Alarm Above Ceiling Rough-in Area 112 Fire Alarm Grid Device Area 112 Fire Alarm Above Ceiling Final Area 112 Grid Tile Area 112 Install Carpet Area 112 Fire Alarm Trim Area 112 Touch up Paint Area 112 Final Clean Punch List Complete Punch List Mechanical Programing Mechanical Start Up Re-Balance EF Mechanical Commissioning Mechanical Final Plumbing Final Fire Alarm Final Life Safety Final Building Final

Page 3 of 3

Print Date: Fri 10/2/26 7:41 AM

Exhibit E Insurance Insurance Certificates to be provided after Certificates amendment & change order for the GMP is executed

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit F Performance Bond to be provided after amendment & change order for the GMP is executed

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit G Labor and Materials Payment Bond to be provided after amendment & change order for the GMP is executed

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit H Alternates prices Alternates prices not used for the amendment

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

BVSD Bear Creek

100% CD Estimate: Items As of 10/21/2026, 10:50 AM 12 Items

Filtered by: Status: Accepted, Incorporated, Not Chosen, Pending, Rejected

Cost Impact

Schedule Impact

#16 (Accepted) Owner Alt #1 - Walk In Cooler

$91,452

tbd Accepted No Impact

#17 (Accepted) Owner Alt #2 - Exterior High Performance Paint

$16,856

No Impact tbd

#18 (Accepted) Owner Alt #3 Asphalt Shinge Roof Replacement

$57,014

tbd No Impact

#19 (Accepted) Owner Alt #4 - Asphalt Shingle Roofing Replacement with TPO​

$98,092

tbd No Impact

#20 (Pending) Owner Alt #5 - Clerestory Window Infill

Rejected

$26,815

tbd

#21 (Pending) Owner Alt #6 - Interior Paint Renewal

Rejected

$26,292

tbd

#22 (Accepted) Alt #7 - Interior Lighting Fixture Replacement - Priority 1

$240,121

tbd No Impact

Rejected

$37,629

tbd

Rejected

$50,727

tbd

-$5,674

tbd

$6,913

tbd

$22,409

tbd

#23 (Pending) Alt #8 - Interior Lighting Fixture Replacement - Priority 2 #24 (Pending) Add Alt- Cafeteria/Workroom Lounge Flooring Replacement #25 (Rejected) Alternate Playground Equipment Vendor - GameTime #26 (Pending) Prep & Seal Coat Existing Asphalt Play Area

Rejected

Rejected

#27 (Rejected) Upgrade CPT-1, -2, -3 & -4 from Shaw to Mannington

Rejected

The potential scope / cost changes may modify the construction schedule or duration. Unless noted otherwise, please assume these potential cost changes are only accurate and stable for 30 calendar days. After those 30 days, FP can update pricing based on current market value and/or procurement / schedule timeframes.

Exhibit I prices Unit prices not Unit used for this amendment

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

UNIT PRICING LOG -

Floor Leveling (Per Bag Installed) o $95/Bag + Mobilization Gypsum Wall Board Patch and Repair (Hourly Rate) o $75/HR + Material & Mobilization Ceiling Tile Replacement (Per Carton of Ceiling Tile Installed) o $400/Carton Installed + Mobilization (Armstrong Schoolzone 1714)

Exhibit J Allowances

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

ALLOWANCE LOG -

Landscaping Allowance- Damages During Asphalt & MEP Work: $10,000 Earthwork & Crush Fine Allowance: $51,000 Fence Slat Allowance: $25,000 Furniture Moving Allowance: $20,000 Floor Preparation Allowance: $5,000 Above Ceiling Remediation for Code Compliance: $10,000 Fire Protection Allowance: $10,684 Use Tax Allowance: $0 (To be paid by BVSD as a separate pass-through change order) Builders Risk Insurance Allowance: $1,588 UA Playground Constructability & Design Allowance: $30,000

Exhibit K Not Applicable

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

Exhibit L Equipment rental rate schedule

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

FRANSEN PITTMAN / DOUGLAS COUNTY EQUIPMENT (RELATED PARTY) STANDARD TOOL & RENTAL EQUIPMENT PRICING LIST Last Updated: February 27, 2026 Monthly Rates Unless Indicated Otherwise

2026

Level 4

Description

Monthly Rates

Air Compressor -175-185 CFM

$

1,850.00

Air Compressor -375 CFM Diesel

$

3,250.00

Air Compressor -Electric, Port

$

1,250.00

Air Compressor, Pancake

$

119.00

Air Conditioner 1 Ton Portable

$

2,328.00

Air Conditioner 3.5 Ton

$

3,150.00

Air Conditioner 12 Ton

$

6,100.00

Air Monitor

$

290.00

Appliance Dolly

$

245.00

Auger

$

959.00

Backhoe Loader

$

5,603.00

Barrier Picker/Clamp -12000 Lb

$

1,250.00

Blower - Backpack

$

500.00

Body Harness Kit

$

427.00

Boom - 30' Electric

$

3,675.00

Boom - 40' Electric

$

5,040.00

Boom - 60-66' Electric

$

5,750.00

Boom - 40'-45' Straight DSL 4WD

$

4,600.00

Boom - 60'-65' Straight DSL 4WD

$

5,250.00

Boom - 80'-85' Straight DSL 4WD

$

9,765.00

Boom - 125' Straight DSL 4WD

$

16,800.00

Boom - 45'-50' Articulated DSL 4WD

$

4,750.00

Boom - 60' Articulated DSL

$

5,500.00

Boom - 80-85' Articu w/Jib DSL

$

9,765.00

Boom - 50-59' Compact Crawler Lift - Battery

$

12,500.00

Breaker - Pneumatic 35-90 Lb

$

855.00

Breaker - Electric 40 Lb

$

785.00

Breaker - Electric 60 Lb

$

1,200.00

Brush Cutter 24"

$

1,150.00

Builders Level

$

700.00

Bull Float

$

390.00

Club Car Golf Cart

$

2,250.00

Compact Track Loader

$

4,634.00

Compaction Wheel - 18" Backhoe

$

1,800.00

Compaction Wheel - 24" Backhoe

$

1,900.00

Compaction Wheel - 24" 200 Cla

$

3,100.00

Concrete Bucket

$

2,100.00

Concrete Mixer

$

1,400.00

Concrete Vibrator

$

721.00

Concrete Washout Pan (Ecopan)

$

250.00

Container - 20'-40'

$

340.00

Core Drill

$

1,456.00

Page 1 of 6

FRANSEN PITTMAN / DOUGLAS COUNTY EQUIPMENT (RELATED PARTY) STANDARD TOOL & RENTAL EQUIPMENT PRICING LIST Last Updated: February 27, 2026 Monthly Rates Unless Indicated Otherwise

2026

Level 4

Description

Monthly Rates

Data Vault

$

1,250.00

Delivery Vehicle - per deliver/ per pickup

$

350.00

Demo Hammer

$

1,967.00

Door & Hardware Vehicle - daily rate

$

90.00

Door Cart

$

150.00

Door Protector

$

50.00

Drill Press

$

1,150.00

Drywall Cart

$

500.00

Fan - 24"

$

140.00

Fan - 36"

$

322.00

Fan - 42"

$

371.00

Fan - Carpet

$

154.00

Fan-Confined Space Blower, 8"

$

385.00

Fire Extinguisher

$

70.00

FLIR Inspection Camera

$

580.00

Floor Buffer

$

1,500.00

Floor Scraper - Ride on

$

8,950.00

Forklift - 5,000 Lb

$

2,250.00

Forklift - Reach 5,001-5,500 Lb 16'-20'

$

3,555.00

Forklift - Reach 6,000 Lb 42'

$

4,702.00

Forklift - Reach 8,000 Lb 44'

$

4,780.00

Forklift - Reach 10,000 Lb 54'

$

6,040.00

Forklift - Reach 12,000 Lb 55'

$

7,214.00

Forklift Attachment - Jib

$

800.00

Forklift Attachment-Trash Hop

$

850.00

Forklift Trash Hopper

$

2,289.00

Fuel Cube - 50 Gallon

$

567.00

Fuel Cube -100 Gallon

$

630.00

Fuel Cube -500 Gallon

$

950.00

Gang Box - Small

$

3,750.00

Gang Box - Large

$

6,250.00

Generator - 5-10 KW

$

1,448.00

Generator - 20-59 KW - Towable

$

2,350.00

Generator - 90-120 KW-Towable

$

4,750.00

Grinder - Walk-Behind

$

4,750.00

Harrow

$

2,155.00

Heater- Convection 200K BTU

$

750.00

Heater- Forced Air 170K

$

750.00

Heater- Forced Air 250K - 400K

$

2,750.00

Heater- Forced Air 500K

$

3,750.00

Heater- Indirect 300,000 BTU

$

3,550.00

Heater- Indirect 500,000 BTU

$

3,750.00

Page 2 of 6

FRANSEN PITTMAN / DOUGLAS COUNTY EQUIPMENT (RELATED PARTY) STANDARD TOOL & RENTAL EQUIPMENT PRICING LIST Last Updated: February 27, 2026 Monthly Rates Unless Indicated Otherwise

2026

Level 4

Description

Monthly Rates

Heater- Indirect 1,000,000 BTU

$

8,250.00

Heater- Towable 500,000 BTU

$

3,820.00

Heater- Towable 1,000,000 BTU

$

8,250.00

Heater- Ground Thaw

$

14,250.00

Hoist - Chain Fall

$

734.00

Jackhammer

$

1,967.00

Jamb Protector

$

50.00

Ladder - Extension

$

150.00

Ladder

$

100.00

Lift - Self Prop & Pusharound 10'-30'

$

1,100.00

Lift - Self Prop & Pusharound 40'

$

1,800.00

Light Cart - 1,000 Watt

$

1,300.00

Light Tower - 4000 Watt Diesel

$

1,450.00

Man Lift

$

975.00

Manometer-Pressure Recorder

$

400.00

Material Lift - 24 - 26'

$

950.00

Media Blaster

$

1,500.00

Mini Ex Attachment - Bucket

$

203.00

Mini Ex Attachment - Compactor

$

2,500.00

Mini Excavator- 3000-5999 Lb

$

3,300.00

Mini Excavator- 6000-6999 Lb

$

3,500.00

Mini Excavator- 7000-7500 Lb

$

4,500.00

Mini Excavator- 7501-11000 Lb

$

5,000.00

Mini Excavator- 18000-19900 Lb

$

6,500.00

Mobile Fall Protection Cart

$

1,155.00

Motar Mixer - Gas 9 Cubic Ft

$

1,400.00

Mower - Riding 42"

$

650.00

Mower - Walk Behind 21"

$

406.00

Mower/Trimmer - Walk Behind

$

717.00

Nailer - Framing

$

475.00

Negative Air Machine

$

875.00

Office Trailer

$

2,500.00

Pallet Jack

$

743.00

Parapet Anchor

$

294.00

Planer

$

300.00

Plate Compactors

$

2,000.00

Porto-Power/Chain Fall

$

350.00

Power Buggy, 16 Cu. Ft.

$

2,280.00

Pressure Washer - Cold

$

1,500.00

Pressure Washer - Hot

$

2,150.00

Engineer Cell Phone

$

125.00

Project Manager Cell Phone

$

125.00

Page 3 of 6

FRANSEN PITTMAN / DOUGLAS COUNTY EQUIPMENT (RELATED PARTY) STANDARD TOOL & RENTAL EQUIPMENT PRICING LIST Last Updated: February 27, 2026 Monthly Rates Unless Indicated Otherwise

2026

Level 4

Description

Monthly Rates

Project Supt Cell Phone

$

125.00

Project Engineer Vehicle

$

1,100.00

Project Manager Vehicle

$

1,700.00

Project Supt Vehicle

$

1,700.00

Project Senior Supt Vehicle

$

1,975.00

Pump - Hydrostat Test 300 - 500 PSI

$

1,500.00

Pump - Hydrostat Test 10,000 PSI

$

2,750.00

Pump - 2" Sump

$

650.00

Pump- Submersible 3/4" 110V Ele

$

450.00

Pump- Submersible 2" 110V Elec

$

650.00

Pump- Submersible 3" 110V Elec

$

900.00

Pump - Trash

$

1,300.00

Radio

$

125.00

Rammer

$

1,040.00

Raptor - License Reader

$

1,200.00

Rebar Bender/Cutter

$

450.00

Rebar Cutter - Electric

$

975.00

Road Plate

$

375.00

Roll-A-Lift Pair 6000 Lb

$

1,000.00

Roller Kit - Machine Skates 8

$

675.00

Roller - Ride-On 36"

$

2,576.00

Roller - Ride-On SD 47"

$

6,250.00

Roller - Ride-On SD 56"

$

6,751.00

Roller - Ride-On SD 66"

$

7,214.00

Roller - Ride-On SD 84"

$

9,443.00

Roller - Trench Pad Foot Dd

$

3,200.00

Rotating Laser

$

1,183.00

Roust-A-Bout - 15' 1500Lb

$

2,076.00

Safety Vehicle - daily rate

$

75.00

Saw - Beam Saw

$

1,010.00

Saw - Chainsaw 14"

$

224.00

Saw - Chainsaw 18"

$

450.00

Saw - Chopsaw

$

126.00

Saw - Concrete Saw W/B

$

1,134.00

Saw - Cut-Off Electric 14"

$

945.00

Saw - Demo Saw 14"

$

2,967.00

Saw - Mitre Saw 14"

$

518.00

Saw - Table Saw 10"

$

413.00

Scabbler - Pneumatic 5 Head

$

3,500.00

Scaffold - 5'X5'X7'

$

862.00

Scaffold - Perry Single Section

$

400.00

Scaffold - Utility Package

$

608.00

Page 4 of 6

FRANSEN PITTMAN / DOUGLAS COUNTY EQUIPMENT (RELATED PARTY) STANDARD TOOL & RENTAL EQUIPMENT PRICING LIST Last Updated: February 27, 2026 Monthly Rates Unless Indicated Otherwise

2026

Level 4

Description

Monthly Rates

Scarifier - Concrete W/B 8"

$

4,393.00

Scissor Lift - 12-20' Electric

$

1,175.00

Scissor Lift - 26-33' Electric or 4WD

$

2,265.00

Scissor Lift - 40-43' Electric or 4WD

$

2,468.00

Security System - Camera

$

853.00

Self Retracting Lifeline 33'

$

350.00

Seeder

$

750.00

Sewer Scope

$

730.00

Shot Blaster- w/Vac and Magnet

$

5,500.00

Silt Fence Plow

$

650.00

Skid Attach - Auger

$

1,900.00

Skid Attach - Breaker

$

2,074.00

Skid Attach - Breaker 1000Lb

$

3,780.00

Skid Attach - Brush Mower 72"

$

2,143.00

Skid Attach - Dirt Scarifier

$

2,076.00

Skid Attach - Forks

$

650.00

Skid Attach - GrappleBuckt 66"

$

933.00

Skid Attach - Harrow Disc

$

2,155.00

Skid Attach - Hydraulic Breakr

$

5,000.00

Skid Attach - Post Dr

$

1,400.00

Skid Attach - Rock Bucket

$

821.00

Skid Attach - Seeder w/Crimp

$

2,155.00

Skid Attach - Smooth Bucket

$

821.00

Skid Attach - Snow Blade 84"

$

1,400.00

Skid Attach - Sweeper & Hopper

$

1,400.00

Skid Attach - Trencher 48"

$

1,724.00

Skidsteer Loader - 1750-2200 Lb

$

3,150.00

Skidsteer Loader - 3200 Lb

$

4,017.00

Slab Grabber Rail System

$

70.00

Snowblower

$

931.00

Sprayer - Cure

$

130.00

Starlink System

$

86.00

Stick/ Wire Feeder

$

371.00

Storage Trailer - 40'

$

1,000.00

Storage Trailer - 45'

$

1,200.00

Surveyor Vehicle - daily rate

$

75.00

Tattle Tale (Alarm System)

$

350.00

Temporary Fence Panels per Linear Foot

$

1.50

Temporary Lighting System

$

150.00

Temporary Lighting Sys-LED Cordless

$

200.00

Temporary Power Distribution Box

$

650.00

Theodolite / Digital Transit

$

455.00

Page 5 of 6

FRANSEN PITTMAN / DOUGLAS COUNTY EQUIPMENT (RELATED PARTY) STANDARD TOOL & RENTAL EQUIPMENT PRICING LIST Last Updated: February 27, 2026 Monthly Rates Unless Indicated Otherwise

2026

Level 4

Description

Monthly Rates

Threader

$

2,155.00

Tile Stripper - W/B,110 V Elec

$

2,181.00

Torch - Oxygen/Acetlyene

$

320.00

Total Station:Trimble

$

4,000.00

Tractor Diesel - 35 To 40 Hp

$

5,098.00

Tractor Loader-Landscape/Skip

$

4,843.00

Trackout Control Mats

$

350.00

Trailer - Dump

$

1,300.00

Trailer - Tilt

$

1,300.00

Trailer - Tilt Single Axle

$

1,300.00

Trailer - Vacuum, 500 Gal.

$

9,500.00

Trash Buggy

$

375.00

Trash Chute

$

190.00

Trash Chute - 30"X48"L Section

$

295.00

Trash Chute - Hopper

$

295.00

Trash Chute-Parapet Outrigger

$

276.00

Trencher - Ride-On 30-39Hp

$

3,550.00

Trencher - Walk Behind

$

1,995.00

Truck - Water 2000 Gallon

$

7,328.00

Truck - Dump Single Axle 5 Yd

$

6,141.00

Two Wheel Dolly

$

95.00

Utility Cart

$

150.00

Utility Vehicle - 4X4

$

1,738.00

Warehouse Vehicle - daily rate

$

75.00

Warranty Vehicle - daily rate

$

340.00

Warranty Manager Vehicle - daily rate

$

340.00

Water Cooler

$

35.00

Water Meter

$

1,653.00

Water Tote - 330 Gallon

$

180.00

Water Trailer - 500 Gallon

$

1,361.00

Weather Protection Blanket

$

90.00

Weed Trimmer/Whacker

$

210.00

Welders 180 Amp - Portable Gas

$

1,375.00

Wheel Loader - 1 Yd

$

6,034.00

Wheel Loader - 2 3/4 - 3 1/2 Yd

$

9,688.00

These rates subject to adjustment at the beginning of every calendar quarter. Makeup of bill rates not subject to audit.

Page 6 of 6

Exhibit M General Conditions of the Contract

6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org

BOULDER VALLEY SCHOOL DISTRICT RE-2 BOULDER, COLORADO

GENERAL CONTRACT CONDITIONS BOND PROGRAM

GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT.................................................................................................... 2 GC 1.00

CONTRACT DOCUMENTS AND DEFINITIONS ............................................................................................................ 1

GC 2.00

REFERENCE STANDARDS .......................................................................................................................................... 2

GC 3.00

DRAWINGS AND SPECIFICATIONS ............................................................................................................................ 2

GC 4.00

ROYALTIES AND PATENTS ........................................................................................................................................ 3

GC 5.00

ITEMS COVERED BY CONTRACT PRICE ..................................................................................................................... 3

GC 6.00

EXECUTION, CORRELATION, INTENT, AND INTERPRETATION OF CONTRACT DOCUMENTS ...................................... 3

GC 7.00

MATERIALS, LABOR, FACILITIES, AND STORAGE....................................................................................................... 4

GC 8.00

PERFORMANCE AND PAYMENT BONDS ................................................................................................................... 5

GC 9.00

PERMITS AND COMPLIANCE WITH STATUTES, RULES, AND REGULATIONS .............................................................. 6

GC 10.00

SURVEYS, BENCHMARKS, MONUMENTS, STAKES, AND MEASUREMENTS ............................................................... 6

GC 11.00

CHANGED CONDITIONS ........................................................................................................................................... 7

GC 12.00

PROTECTION OF PERSONS, WORK AND PROPERTY ................................................................................................. 7

GC 13.00

WORK ON EXISTING BUILDINGS .............................................................................................................................. 8

GC 14.00

CONTRACTOR’S SUPERINTENDENCE AND SUPERVISION .......................................................................................... 8

GC 15.00

SUBSTITUTIONS ....................................................................................................................................................... 9

GC 16.00

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES ................................................................................................. 9

GC 17.00

CASH ALLOWANCE................................................................................................................................................. 10

GC 18.00

EXPEDITING MATERIALS ........................................................................................................................................ 10

GC 19.00

BLASTING .............................................................................................................................................................. 11

GC 20.00

SOIL TEST REPORT ................................................................................................................................................. 11

GC 21.00

HAZARDOUS MATERIALS ....................................................................................................................................... 11

GC 22.00

DAMAGE TO UTILITIES ........................................................................................................................................... 11

GC 23.00

CHANGES IN THE WORK ........................................................................................................................................ 12

GC 24.00

CLAIMS FOR EXTRA COST....................................................................................................................................... 13

GC 25.00

DELAYS AND EXTENSIONS OF TIME ....................................................................................................................... 13

GC 26.00

ACCESS TO WORK .................................................................................................................................................. 14

GC 27.00

CORRECTION OF WORK ......................................................................................................................................... 14

GC 28.00

OWNER’S RIGHT TO CARRY OUT WORK ................................................................................................................. 16

GC 29.00

OWNER’S RIGHT TO TERMINATE CONTRACT ......................................................................................................... 16

GC 30.00

CONSTRUCTION SCHEDULE AND PROGRESS REPORTS ........................................................................................... 16

GC 31.00

SCHEDULE OF VALUES ........................................................................................................................................... 17

GC 32.00

PAYMENT .............................................................................................................................................................. 17

GC 33.00

INSURANCE ........................................................................................................................................................... 19

GC 34.00

SEPARATE CONTRACTS .......................................................................................................................................... 23

GC 35.00

SUBCONTRACTORS ................................................................................................................................................ 23

GC 36.00

RELATIONS OF CONTRACTOR AND SUBCONTRACTOR ........................................................................................... 24

GC 37.00

CONTRACTORS’ MUTUAL RESPONSIBILITY ............................................................................................................ 25

GC 38.00

CUTTING, PATCHING, AND EXCAVATING ............................................................................................................... 25

GC 39.00

EMPLOYEES ........................................................................................................................................................... 26

GC 40.00

CLEANING UP......................................................................................................................................................... 27

GC 41.00

USE OF PREMISES .................................................................................................................................................. 27

GC 42.00

OCCUPANCY .......................................................................................................................................................... 27

GC 43.00

TEMPORARY OR TRIAL USAGE ............................................................................................................................... 28

GC 44.00

TESTING OF BUILDING SYSTEMS ............................................................................................................................ 28

GC 45.00

LIQUIDATED DAMAGES FOR DELAY IN COMPLETION ............................................................................................. 28

GC 46.00

ACCEPTANCE AND FINAL PAYMENT ....................................................................................................................... 28

GC 47.00

WARRANTIES ON PORTIONS OF THE WORK .......................................................................................................... 29

GC 48.00

CONTRACTOR’S PROJECT GUARANTEE AFTER COMPLETION ................................................................................. 30

GC 49.00

MISCELLANEOUS KEYS, SWITCHES, ETC. ................................................................................................................ 30

GC 50.00

INDEMNIFICATION ................................................................................................................................................ 30

GC 51.00

LABOR DISPUTES ................................................................................................................................................... 31

GC 52.00

LIMITATION OF ACTIONS ....................................................................................................................................... 31

GC 53.00

PREFERENCE FOR COLORADO LABOR, MATERIALS, AND RESIDENT BIDDERS ........................................................ 31

GC 54.00

SALES AND USE TAX............................................................................................................................................... 31

GC 55.00

LIENS ..................................................................................................................................................................... 32

GC 56.00

OWNER’S INSPECTION OF CONTRACTOR’S RECORDS ............................................................................................ 32

GC 57.00

CERTIFICATION BY CONTRACTOR REGARDING PREMISES ACCESS ......................................................................... 32

GC 58.00

CONTRACTOR SAFETY RESPONSIBILITIES ............................................................................................................... 32

GC 59.00

CONTRACTOR ASBESTOS MANAGEMENT AND LEAD PAINT RESPONSIBILITIES ...................................................... 35

GC 60.00

ARCHITECT’S STATUS AND INSPECTIONS ............................................................................................................... 35

GC 61.00

ORAL STATEMENTS................................................................................................................................................ 35

GC 62.00

PROJECT SIGN ........................................................................................................................................................ 36

GC 63.00

HISTORICAL DATA .................................................................................................................................................. 36

GC 64.00

ASSIGNMENT ......................................................................................................................................................... 36

GC 65.00

TIME OF THE ESSENCE ........................................................................................................................................... 36

GC 66.00

DISPUTES ............................................................................................................................................................... 36

GC 67.00

SURVIVAL .............................................................................................................................................................. 36

GC 1.00

CONTRACT DOCUMENTS AND DEFINITIONS

All Work under the Construction Agreement shall be accomplished in accordance with the Contract Documents, which shall consist of the Request for Qualifications, Request for Proposals, Proposal(s), Notice of Award, Notice to Proceed, Performance Bond, Labor and Material Payment Bond, Construction Agreement, General Contract Conditions, Supplementary Conditions, Asbestos Management Plan Contractor Responsibility Form, Drawings and Specifications, tests and engineering data, approved Change Orders, Contractor’s Requests for Payment, Architect’s Certificates, and all addenda issued by the Owner or Architect prior to execution of the Construction Agreement and all modifications issued by the Owner or Architect after execution of the Construction Agreement. With respect to the Contract Documents, the following definitions and understandings shall control: 1.01 “Contract” or “Contract Documents” shall include all of the items enumerated in GC-1.00 above. 1.02 “Owner” shall mean Boulder Valley School District No. RE-2, and shall include its duly authorized representatives. 1.03 “Contractor” shall mean the corporation, company, partnership, firm, entity, or individual named and designated as such in the Construction Agreement, and any persons or entities acting on its behalf. 1.04 “Subcontractor” shall mean any corporation, partnership, entity, or individual having a direct contract with the Contractor or another subcontractor for performing Work and/or furnishing labor or material on the Project covered by the Contract. 1.05 “Architect” shall mean the corporation, partnership, entity or individual named and designated as “architect” or “engineer” in the Construction Agreement, and any persons or entities acting on the Architect’s behalf and within the scope of the particular duties properly entrusted to them in each case. In the event that there is no Architect on the Project, then “Architect” shall refer to Owner and its duly authorized representative. 1.06 “Notice to Contractor” shall be deemed to have been duly served if made in writing and delivered in person to the individual or to a member of the firm or to an officer of the corporation for which it is intended, or if sent by registered or certified mail, to Contractor’s last known business address. 1.07 “The Work” shall mean the construction and services required by the Contract Documents for completion of the Project, and includes all labor, materials, equipment and services provided or to be provided by the Contractor to fulfill the Contractor’s obligations, whether on or off the Project site, and all labor, materials equipment and services provided or to be provided by subcontractors, sub-subcontractors, or any other entity for whom the Contractor is responsible. 1.08 “The Project” is the total construction designed by the Architect of which the Work performed under the Contract Documents may be the whole or a part. 1.09 The “date of final completion” and “finally completed” shall mean the date when construction is certified by the Architect to be finally completed in accordance with the Contract Documents, as modified by any Change Orders processed under the terms of GC-23.00 below and when the Owner has fully accepted the Project for the use for which it was intended. Such date will be set forth on a letter of acceptance issued by the Owner. 1.010 “Drawings” or “plans” shall mean all (a) drawings furnished by the Owner and/or Architect as a basis for the award of Contract and for construction of the Project; (b) supplementary drawings furnished by the Owner and/or Architect to clarify and to define in greater detail the intent of the Contract drawings and specifications; (c) drawings submitted by the successful Contractor as may be required after the Contract is awarded; (d) drawings furnished by the Owner and/or Architect to the Contractor during the progress of the Work; and (e) engineering data and drawings submitted by the Contractor during the progress of the Work, provided such drawings are acceptable to the Architect and Owner. 1

1.011 “Specifications” are the written technical information concerning materials, components, systems, equipment, and manner of installation as indicated on the drawings or plans and which state the quality, performance, and characteristics to be achieved by application of construction methods. 1.012 “Change Order” shall mean a written order to the Contractor signed by the Owner or its authorized agent issued after the execution of the Construction Agreement, authorizing a change in the Work and/or adjustment in the Guaranteed Maximum Price (“GMP”) or the contract time schedule. Each adjustment in the GMP resulting from a Change Order shall clearly separate the amount attributable to the Cost of the Work and the Contractor’s Fee. 1.013 “day” or “days” shall mean calendar days. In computing a period of days, when the ending date is not specified, the first day is excluded and the last day is included. If any deadline falls on a Saturday, Sunday, or federal or Colorado state holiday, such deadline will be extended to the next day that is not a Saturday, Sunday or federal or Colorado state holiday. GC 2.00

REFERENCE STANDARDS

2.01 Reference to the standards of any technical society, organization, or association, or to codes of local or state authorities, shall mean the latest standard, code, specification, or tentative standard adopted and published as of the date of execution of the Construction Agreement, unless specifically stated otherwise. GC 3.00

DRAWINGS AND SPECIFICATIONS

3.01 Ownership of Drawings. All drawings, specifications, and copies thereof furnished by the Architect are the property of the Architect and the Owner, whether or not the Work for which they are made is performed, and are not to be used on other Work except by written agreement with the Architect and the Owner. 3.02 Figured Dimensions to Govern. Dimensions and elevations shown on the drawings shall be accurately followed. No Work shown on the drawings, the dimensions of which are not indicated, shall be executed until necessary dimensions have been obtained from the Architect. 3.03 Contractor to Check Drawings and Schedules. The Contractor shall check and verify all dimensions, elevations, and quantities shown on the drawings and furnished to it by the Architect, and shall notify the Architect of any discrepancy between the drawings and the conditions on the ground, or any error or omission in drawings, or in the layout as given by stakes, points, or instructions that it may discover. Before ordering any material or doing any Work, the Contractor shall verify all measurements concerning the Project and shall be responsible for the correctness of same. No extra charge or compensation shall be allowed on account of any difference between actual dimensions and the measurements indicated on the drawings. Any difference that may be found shall be submitted to the Architect for consideration and written determination before proceeding with the Work. The Contractor shall not be allowed to take advantage of any error or omission in the drawings or Contract Documents. Full written instructions shall be furnished by the Architect should such error or omission be discovered, and the Contractor shall carry out such instructions as if originally specified. 3.04 Detail Drawings and Instructions. The Architect shall furnish with reasonable promptness additional instructions, by means of drawings or otherwise, necessary for the proper execution of the Work. All such drawings and instructions shall be consistent with the Contract Documents. The Work shall be executed in conformity with the Architect’s drawings and instructions, and the Contractor shall do no Work without proper drawings and instructions. 3.05 Drawings and Specifications Available on the Site. The Contractor shall maintain at the Project site for the Owner and the Architect a Project record set of drawings, including addenda, approved shop drawings, Change Orders, and other modifications, with all changes or deviations from the original drawings neatly marked thereon in a contrasting color. The Contractor shall also maintain a Project record set of specifications at the 2

Project site, noting therein by appropriate section the names, models, and other distinguishing characteristics of the materials actually incorporated into the Work. This Project record set of drawings and specifications shall be updated daily as the Project progresses and shall be made available to the Owner and Architect for inspection at all times. Upon final completion of the Work and before final payment, three (3) copies and one (1) electronic of this Project record set of drawings and specifications shall be delivered to the Owner. One (1) copy of this Project record set of drawings and specification shall be delivered to the Architect. 3.06 Laws and Regulations. The Contractor shall give all notices and comply with all laws, ordinances, rules, and regulations bearing on the conduct of the Work as drawn and specified. If the Contractor observes that the drawings and specifications are at variance therewith, it shall promptly notify the Architect in writing, and any necessary adjustments shall be made as provided in the Contract for changes in the Work. If the Contractor performs any Work knowing it to be contrary to such laws, ordinances, rules, or regulations without giving the required notice to the Architect and receiving a written directive to proceed, it shall bear all costs arising therefrom and to correct and/or remedy same. GC 4.00

ROYALTIES AND PATENTS

The Contractor shall pay all royalties and license fees. The Contractor shall defend all suits or claims for infringement of patent rights and shall hold the Owner harmless from any and all liability or loss on account thereof. If the Contractor has information that the process or article specified involves the infringement of a patent, it shall be responsible for any and all liability or loss resulting therefrom unless it promptly furnishes such information to the Architect in writing. GC 5.00

ITEMS COVERED BY CONTRACT PRICE

5.01 Items Supplied by Owner. Owner shall supply the following items for the Project: a. Building Permit; b. Initial Survey; c. Materials Testing Including Soil Testing; d. Third Party Inspections; e. Commissioning; and f. Test and Balance as Required for Commissioning. 5.02 Items Supplied by Contractor. Unless specifically stated otherwise, the Contractor shall accept the compensation stated in the Construction Agreement as full payment for furnishing all the materials, transportation, apparatus, temporary structures, equipment, services, fuel, energy, light, water, labor and tools, and all other things necessary for the complete and proper execution of the Work contemplated by or reasonably implied from the Contract Documents, within the time limits indicated therein. Such amount shall include any loss or damage resulting from the nature of the Work, from the elements or from any unforeseen difficulties that may be encountered; all risks of every description connected with the prosecution of the Work; all expenses incurred in consequence of any suspension or discontinuance of the Work; and all other amounts necessary for completing the Work pursuant to the Contract Documents within the time limits indicated therein. GC 6.00

EXECUTION, CORRELATION, INTENT, AND INTERPRETATION OF CONTRACT DOCUMENTS

6.01 Execution. The Construction Agreement and other Contract Documents shall be signed in multiple copies as directed by the Owner. Within ten (10) days of Notice of Award, the Contractor shall submit to the Owner a minimum of five (5) fully executed original sets of the Construction Agreement; Performance Bond, and Labor and Material Payment Bond with original Power of Attorney; and certificates of required insurance coverage. The date of the Contract for purposes of these documents shall be the date of the Notice of Award letter. The Owner shall execute the Construction Agreement, assemble all copies, and distribute the Contract Documents. The Contractor shall not commence the Work until it receives the Notice to Proceed. All bonds and insurance 3

certificates shall be submitted to the Owner prior to the award of the first subcontract. 6.02 Correlation. By executing the Construction Agreement, the Contractor represents that it has visited the Project site, familiarized itself with the local conditions under which the Work is to be performed, and correlated its observations with the requirements of the Contract Documents. 6.03 Intent. The intention of the Contract Documents is to include all labor and materials, tools, equipment, construction equipment, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution and completion of the Work. Materials or Work described in words that, as applied, have a well-known technical or trade meaning shall be held to refer to such recognized meaning. The organization of the specifications into divisions, sections, and articles, as the case may be, and the arrangement of drawings shall not control the Contractor in dividing the Work among subcontractors or in establishing the extent of Work to be performed by any trade. It is intended that even though Work is not covered under any heading, division, section, article, branch, class, or trade of the specifications, it shall nevertheless be supplied if it is required elsewhere in the Contract Documents or is reasonably inferable therefrom as being necessary to produce the intended results. The specifications and drawings are intended to supplement but not necessarily duplicate each other. Any Work exhibited in the one and not in the other shall be executed as if it had been set forth in both, so that the Work will be constructed according to the complete design as determined by the Architect. 6.04 Interpretation. Should anything necessary for a clear understanding of the Work be omitted from the specifications and drawings, or should the requirements appear to be in conflict, the Contractor shall secure written interpretations or instructions from the Architect before proceeding with the Work affected thereby. The Contractor shall secure written interpretations or instructions by submitting the Owner’s form Request for Interpretation to the Architect. Oral requests shall not be acknowledged by the Architect or Owner. Additional costs incurred by the Owner as a result of unnecessary requests made by the Contractor, as determined by the Owner, shall be the responsibility of the Contractor. It is understood and agreed that the Work shall be performed according to the true intent of the Contract Documents. 6.05 Conflict in Interpretation. In the case of discrepancy or in the event of a conflict between the different Contract Documents, the documents shall take precedence in the following order: a. Change Orders; b. Written Amendments to Construction Agreement (including, if applicable, the GMP); c. Construction Agreement; d. General Conditions; e. Drawings and specifications; and f. Bid Documents, including addenda. Where two or more of the Contract Documents are complementary, the more detailed provision shall control over the more general provision. GC 7.00

MATERIALS, LABOR, FACILITIES, AND STORAGE

7.01 Contractor’s Responsibility. Unless otherwise agreed in writing, the Contractor shall provide and pay for all materials, labor, tools, equipment, machinery, transportation, and other facilities necessary for the proper execution and completion of the Work. The Contractor shall provide and pay for all the temporary facilities required to supply all the power, light, water, and heat needed by it and its subcontractors for their Work and shall install and maintain all such facilities in such manner as to protect the public and workers and to conform with any applicable laws and regulations. If temporary heat and/or protection is required for the expeditious prosecution of the Work and before the permanent heating apparatus is available for use, the temporary heating apparatus shall be installed and operated in such a manner that the finish Work and/or construction will not be damaged thereby. Unless otherwise specified, the Contractor shall pay for all the power, light, and water used by it and its subcontractors, without regard to whether such items are metered by temporary or permanent meters. The cutoff date on permanent meters shall be either the agreed date of full occupancy by 4

the Owner or the date of final acceptance of the Project, whichever shall be the earlier date. Upon completion of the Work, the Contractor shall remove all surplus materials, tools and such temporary facilities and structures, furnished by the contractor from the Project site. All debris and rubbish caused by the operations of the contractor shall be removed, and the area occupied during construction activities shall be restored to its original condition, within 48 hours of project completion, unless otherwise directed by the municipality or owner’s representative. 7.02 Materials. Unless otherwise specified, all materials shall be new and both Workmanship and materials shall be of the highest quality. The Contractor shall furnish satisfactory evidence to the Owner as to the kind and quality of materials. Samples shall be furnished, when specified, and the Work shall be in accordance with those samples that have been approved. 7.03 Toilet Facilities. The Contractor shall provide and maintain, in a neat and sanitary condition, adequate temporary toilet facilities for the use of any and all employees engaged on the Work, in strict compliance with the requirements of all applicable codes, regulations, laws, and ordinances. In no event may present toilet facilities of any existing building at the site of the Work be used by employees of the Contractor or its subcontractors. Upon final completion of the Work, the Contractor shall remove all such temporary facilities from the site and disinfect the premises. 7.04 Facilities and Storage. The Contractor shall provide suitable temporary facilities and quarters for workers, as needed, and shall maintain on premises water-tight storage sheds or tool houses for storage of building materials and tools that could be damaged by weather. The Contractor shall allow space for the erection of sheds and provide similar facilities for storage by subcontractors of their materials and tools. Storage of materials shall be confined to the site. These facilities or quarters shall further provide for protection against theft and damage of building materials and tools. Upon final completion of the Work, the Contractor shall remove all such temporary facilities from the site. 7.05 Office Space. The Contractor shall provide adequate, weatherproofed, heated and well- lighted office space at the site of the Work, for use by the Architect and the Owner and their representatives. The Contractor shall also provide telephone service at such office, which shall be available for use by the Architect, the Owner, and their representatives without charge, except for toll calls. 7.06 Quality and Location of Facilities. All of the foregoing facilities shall be of a quality and placed in locations acceptable to the Architect and the Owner. GC 8.00

PERFORMANCE AND PAYMENT BONDS

8.01 Required Bonds. The Contractor shall, within ten (10) days from the Notice of Award furnish bonds to the Owner in the full amount of the contract price, covering both the faithful performance of the Contract and the payment of all obligations for labor and materials arising thereunder, on such customary forms as the Owner may prescribe and with such sureties as it may approve. The amount of the bonds shall be increased, if necessary, to reflect approved changes in the Work that result in an increase in the total cost of the Work plus the Contractor’s fees. Such bonds shall be duly executed by a qualified surety licensed to do business in the State of Colorado, conditioned upon the true and faithful performance of the Contract, and shall provide that if the Contractor or its subcontractors fail to duly pay for any labor, materials, or other supplies used or consumed by such Contractor or its subcontractors in the performance of the Work contracted to be done, the surety will pay the same in an amount not exceeding the sum specified in the bond, as adjusted by approved Change Orders, and together with interest as provided by law. The performance bond shall additionally guarantee that the Contractor shall remedy any omissions, correct any and all defects, and adjust and make operable all component parts of Work falling under the requirements of the Contract that may be called to the Contractor’s attention within a period of twenty-four (24) months following the date of the letter of acceptance.

5

8.02 Additional Bond Requirements. The premium for all bonds shall be paid by the Contractor and included in the bid price in the bid proposal. The Owner will accept and approve bonds written by sureties legally authorized to write such bonds in the State of Colorado, provided such surety companies are rated in Best’s Insurance Guide (latest edition), not lower than A- or have Best’s Financial Rating of at least X. If, at any time a surety on such a bond becomes irresponsible or loses its right to do business in the State of Colorado, new bonds shall be provided by an alternate surety licensed to do business in the State and meeting the requirements of this Section 8.00. GC 9.00

PERMITS AND COMPLIANCE WITH STATUTES, RULES, AND REGULATIONS

9.01 Permits. Any local permits, governmental fees, and licenses necessary for the proper execution and completion of the Work shall be secured and paid for by the Contractor. Owner will pay for and secure building permit from Colorado Division of Fire Prevention and Control. Easements for permanent structures or permanent changes in existing facilities shall be secured and paid for by the Owner, unless otherwise specified in writing. The Owner is generally exempt from paying any fee for any building permit issued by any building departments or agencies located in Boulder, Broomfield, and Gilpin Counties, and the Contractor shall see that no building permit fee is paid. The Owner shall negotiate and provide for all electrical, gas, water, and sewer mains for the Contractor’s connections. The Contractor shall arrange with the utility company for actual connection, make necessary connections, and pay for all associated inspection fees and permits as required by any government agency. In addition, the Contractor shall furnish all material and items required to complete all connections. The Contractor shall call for all inspections on a timely basis by any agency having jurisdiction over the Work. 9.02 Compliance with Statutes, Rules and Regulations. The Contractor and all subcontractors shall comply with all applicable federal and state statutes, rules, regulations, and directives of the State Division of Fire Prevention and Control, and other governmental body having jurisdiction over the work to be performed. If any of the provisions of the Contract Documents are in conflict therewith, such portions shall be considered stricken and the applicable statute, ordinance, regulation, or ruling substituted therefor. All such cases of apparent conflict coming to the attention of any party shall immediately be called to the attention of the Owner. The Contractor shall strictly observe and comply with all federal and state laws pertaining to the employment and payment of labor. GC 10.00

SURVEYS, BENCHMARKS, MONUMENTS, STAKES, AND MEASUREMENTS

10.01 Surveys. As provided by the Owner, the Contractor shall obtain from the Architect a copy of all surveys describing property lines, elevation benchmarks, physical characteristics, and utility locations. 10.02 Benchmarks. The Contractor shall properly stake out the Work and provide and rigidly set benchmarks and batter boards as necessary for the proper performance of the Work. The Contractor shall remain responsible for their maintenance and their accuracy. A permanent benchmark, approved as to location and type by the Architect, from which all grades are to be taken, shall be established near the site of the Work by the Contractor. From this benchmark the Contractor shall ascertain all grades and levels to Project buildings as needed. The Contract Documents shall include all necessary information to establish the benchmark. 10.03 Preservation of Monuments and Stakes. The Contractor shall carefully preserve all monuments, benchmarks, property markers, reference points, and stakes. In case of the destruction thereof, the Contractor shall be charged with the expense of replacement and shall be responsible for any mistake or loss of time that may be caused. Permanent monuments and/or benchmarks that must be removed or disturbed shall be protected until properly referenced for relocation. The Contractor shall furnish all materials, labor and assistance for the proper replacement of such monuments and benchmarks. 10.04 Measurements. Before ordering any material or performing any Work, the Contractor shall verify all measurements on the Project and shall be responsible for the accuracy of same. No extra charge or 6

compensation shall be allowed because of any difference between actual dimensions and the measurements indicated in the drawings or specifications. Any discrepancies shall be submitted to the Architect and Owner for consideration before proceeding with the Work. GC 11.00

CHANGED CONDITIONS

The Contractor shall promptly, and before such conditions are disturbed, notify the Owner and the Architect in writing of: (1) sub-surface or latent physical conditions at the Project site differing materially from those indicated in the Contract Documents, or (2) unknown physical conditions at the Project site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in Work of the character provided for in the Contract Documents. The Owner and the Architect shall promptly investigate the conditions, and if the Owner finds that such conditions do so materially differ and cause an increase or decrease in the cost of or the time required for performance of the Work, an equitable adjustment shall be made and the Contract modified in writing accordingly. Any claim of the Contractor for adjustment hereunder shall not be allowed unless it has given notice as required. GC 12.00

PROTECTION OF PERSONS, WORK AND PROPERTY

12.01 Building Exits and Barricades. During the course of construction, the Contractor shall keep all required building exits free and unimpeded. Such exits shall not be closed at any time for any reason while the building is occupied or at any time when the building is unoccupied, except after written approval is given by the Owner and proper warning and directional signs are posted. Barricades shall be erected so that traffic is separated and protected from the construction. 12.02 Precautions. The Contractor shall take all necessary precautions to ensure the safety of all employees and other persons on the Project or who may be affected by the Contractor’s Work thereon. The Contractor shall also take all necessary precautions to protect the Work and all temporary facilities, as well as materials, tools, and equipment incorporated therein or to be incorporated therein from damage or destruction, whether in storage on or off the Project site and whether in the custody or control of the Contractor or any of its subcontractors. The Contractor shall also take all necessary precautions to protect all property at the Project site and adjacent thereto not designated for removal, relocation or replacement, including trees, shrubs, lawns, walks, pavements, roadways, structures, and utilities. 12.03 OSHA Compliance. The Contractor shall comply with all applicable provisions of the Occupational Safety and Health Administration (“OSHA”) and all laws, ordinances, rules, regulations, and orders of all governmental agencies or authorities having jurisdiction to protect the safety of employees and/or other persons who may be affected by the Work. The Contractor shall erect and maintain all necessary safeguards to protect workers on the Project site and the owners and users of adjacent property, and shall post danger signs and other warnings against hazards created by the Work including but not limited to protruding nails, hoists, well holes, elevator shafts, hatchways, scaffolding, window openings, stairways, excavations, and falling materials. The Contractor shall designate a responsible employee at the Project site as a safety officer to ensure the Contractor’s compliance with this section. Said employee shall be the Contractor’s superintendent unless otherwise designated in writing by the Contractor to the Owner and the Architect. 12.04 Contractor’s Liability. The Contractor shall be liable for all injury, damage or loss to any person or property caused in whole or in part by the Contractor, any of its subcontractors, or any person employed by or under the direction of the Contractor or any of its subcontractors. To the extent possible and unless otherwise directed by the Owner or Architect, the Contractor shall promptly repair, pay for or otherwise remedy any such injury, damage or loss and shall indemnify and hold harmless the Owner against any and all liability, claims, damages, losses and expenses arising therefrom. The terms of this section shall not apply in the case of injury, damage or loss proximately caused by the acts or omissions of the Owner and/or Architect and not attributable to any fault or negligence of the Contractor.

7

12.05 Emergencies. In the event of an emergency that threatens the safety or life of any person or threatens to damage or destroy the Project and/or any Work, materials, equipment or property thereon or to be used thereon, the Contractor shall act at its discretion to prevent such injury, death, damage or destruction. The Contractor shall immediately notify the Owner and Architect in writing of any such emergency and any action taken by the Contractor in response thereto. Any compensation due the Contractor for such emergency action shall be determined by agreement of the Contractor, Owner and Architect, and an appropriate Change Order shall be issued therefor. GC 13.00

WORK ON EXISTING BUILDINGS

13.01 Protection of Occupants. In addition to all other requirements of the Contract Documents, if the Work involves an addition or alteration to an existing building, the Contractor shall erect and maintain during the progress of the Work suitable dustproof partitions to protect such building and the occupants thereof. If necessary, in the Owner’s or Contractor’s judgment or pursuant to manufacturer’s directives or recommendations in order to protect occupants from noxious fumes, odors, or hazardous substances, the Contractor may be required to provide additional ventilation and/or work different or extended hours to avoid disruption to other activities within the existing building. Contractor shall protect and keep from harm all occupants of an existing building from construction activities, and shall include a safe pathway into and out of the school. 13.02 Partitions and Scheduling. If any portions of an existing building are to be remodeled or repaired, such portions shall be adequately partitioned off with dustproof partitions and well ventilated. All remodeling Work shall be scheduled and submitted to the Owner and Architect for approval. The various contractors shall schedule their Work jointly, in order that each may accomplish its Work within such existing building in an orderly fashion during regular school vacation periods where possible, or in such a manner as to permit full use of the building and without impairment of any existing facilities. 13.03 Existing Systems. Existing building systems, such as fire alarm, temperature controls and air distribution, security systems, public announcement systems, irrigation systems, and the like, shall be demonstrated and noted by Owner to the Contractor as operational prior to Contractor’s commencing the Work and Contractor may participate in observation of such systems. Such systems are the responsibility of the Contractor to maintain in pre-construction condition. GC 14.00

CONTRACTOR’S SUPERINTENDENCE AND SUPERVISION

14.01 Superintendent. During the progress of the Work, the Contractor shall ensure that a competent superintendent and any necessary assistants, all satisfactory to the Architect and the Owner, are on the Project site at all times while Work is in progress. The superintendent shall not be changed by the Contractor except with the written consent of the Architect and the Owner, unless the superintendent ceases to be in the Contractor’s employ. The superintendent shall represent the Contractor on the Project and all directions given to him/her shall be as binding as if given to the Contractor. The Architect and the Owner shall not be responsible for the acts or omissions of the superintendent or his/her assistants. 14.02 Supervision. The Contractor shall provide full-time, qualified, and efficient supervision of the Work, using competent skill and attention. The Contractor is responsible for determining and supervising all temporary and permanent erection and construction sequences, techniques, means, or methods. The Contractor shall direct, schedule, coordinate the Work to ensure that all parts fit together properly and in accordance with the Contract Documents. The Contractor shall carefully study and compare all Contract Documents and other instructions and shall at once report to the Architect and the Owner any error, inconsistency, or omission that Contractor may discover. 14.03 Additional Supervision Duties. The Contractor shall see that the Work is carried out in accordance with the Contract Documents and in a thorough and first-class manner in every respect. The Contractor shall 8

provide engineering, surveying, and coordination to accurately establish all lines, levels, and marks necessary to facilitate the operations of all parties involved in the Contractor’s Work. The Contractor shall lay out the Work in a manner satisfactory to the Architect, making permanent records of all lines and levels required for excavation, grading, and foundations, and for all other parts of the Work. The Contractor shall be responsible for the commencement and the proper completion of the various stages and sequences of construction. The Contractor shall strictly adhere to the approved construction schedule. GC 15.00

SUBSTITUTIONS

The Contractor shall be held to have used in its base proposal and to furnish under the Contract those items of equipment and/or materials that are specifically identified in the plans and specifications by a manufacturer’s name, model, or catalog number. Items of equipment and/or materials of the Contractor’s choice may be offered as alternates to the items named in the plans and specifications by submitting, with the proposal and on the form provided, identifying data on the articles proposed together with a statement of the amount of addition or deduction from the base bid if the bidder’s alternate is accepted. Prior approval by the Architect is not required on items submitted as alternate bids. After execution of the Construction Agreement, substitution of equipment and/or materials of makes other than those specifically named in the Contract Documents may be approved by the Owner so long as the equipment or material proposed for substitution in the opinion of the Owner is just as suitable as the equipment and/or materials named in the plans and specifications so far as performance, construction, efficiency, and utility are concerned. A request for substitution shall ordinarily be required to be based upon one or more of the following grounds: the specified equipment or material is no longer available, a substitution will improve lead time, quality will be improved (documented detail required), or the Owner will incur substantial savings. All requests for substitution must be submitted in writing with supporting documentation by or through the Contractor to the Architect for initial review and recommendation before being submitted to the Owner for evaluation and final approval. In the absence of the Owner’s written approval, no substitution of equipment or materials shall be allowed for any items specified in the Contract Documents. In case of a difference in price, occurring as a result of an approved substitution, the Owner shall receive all benefit of the difference in cost involved in the substitution. All approved substitutions shall be documented by the issuance of a formal Change Order as provided in these General Conditions. GC 16.00

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

16.01 Shop Drawings. “Shop drawings” are drawings, diagrams, illustrations, schedules, performance charts, brochures, manufacturer’s literature, and other data that are prepared by the Contractor or any subcontractor, manufacturer, supplier, or distributor, and that illustrate some portion of the Work. Shop drawings shall be submitted in both hard copy and electronic format. 16.02 Samples. “Samples” are physical examples furnished by the Contractor to the Owner and/or Architect to illustrate materials, finishes, equipment, or Workmanship, and to establish standards by which the Work will be judged. 16.03 Product Data. “Product data” are illustrations, standard schedules, performance charts, instructions, brochures, diagrams and other information furnished by the Contractor to illustrate materials or equipment for some portion of the Work. Product data shall be submitted in both hard copy and electronic format. 16.04 Contractor’s Obligations. The Contractor shall review, approve, stamp an then submit to the Architect shop drawings, product data, samples, and similar submittals required by the Contract Documents with reasonable promptness and in such a sequence as to cause no delay in the Work or in the activities of the Owner or of separate contractors. Shop drawings, product data, samples, and similar submittal required by the Contract Documents shall properly identify specified items. At the time of submission, the Contractor shall inform the Architect in writing of any deviation in the shop drawings, product data, or samples from the requirements of the Contract Documents. Substitutions will be allowed only in accordance with the provisions of GC-15.00. The number of copies and format of submittal shall be as required by the Architect, but, at a 9

minimum, shall include three (3) copies and one (1) electronic copy of the original shop drawings and product data for the Owner. 16.05 Verification. By approving and submitting shop drawings, product data, and samples, the Contractor thereby represents that it has determined and verified all field measurements, field construction criteria, dimensions, elevations, quantities, materials, catalog numbers, and similar data, as shown on the drawings and specifications furnished by the Architect, or will do so, and that it has checked and coordinated each shop drawing, product data, and sample with the requirements of the Work and of the Contract Documents. 16.06 Architect /Owner Review. The Architect shall review and approve shop drawings, product data, and samples with reasonable promptness so as to cause no delay, but only for conformance with the design concept of the Project and with the information given in the Contract Documents. The Architect’s approval of a separate item shall not indicate approval of any assembly in which the item functions. Upon the final completion of the Work, the Contractor shall furnish to the Architect two corrected copies of all shop or setting drawings showing the as-built condition of the Work. The Architect, after review, shall submit one of these copies to the Owner. 16.07 Corrections. The Contractor shall make any corrections required by the Architect and shall resubmit the required number of corrected copies of shop drawings or new samples until approved by the Architect. The Contractor shall direct specific attention in a separate writing or on resubmitted shop drawings to revisions other than the corrections requested by the Architect on previous submissions. 16.08 Contractor’s Responsibility. The Architect’s approval of shop drawings, product data, or samples shall not relieve the Contractor of responsibility for any deviation from the requirements of the Contract Documents unless the Contractor has informed the Architect in writing of such deviation at the time of submittal and the Architect has given written approval of the specific deviation. The Architect’s approval shall also not relieve the Contractor from responsibility for errors or omissions in the shop drawings, product data, or samples. 16.09 Architect Approval Required. No portion of the Work requiring the submission of a shop drawing, product data, or sample shall be commenced until such submittal has been approved in writing by the Architect. All such portions of the Work shall be in accordance with approved shop drawings, product data, and samples. All material finishes and samples shall be approved at one time. The Contractor shall submit all items requiring approval of finishes, color, material, etc., with sufficient lead time to allow simultaneous consideration and preparation of complete finish color schedule. No approvals of single items shall be considered. 16.010 Copies to Owner. When shop drawings, product data, samples or similar submittals have been approved and stamped by both Contractor and Architect, Contractor shall immediately forward an electronic copy of each to the Owner. GC 17.00

CASH ALLOWANCE

The Contractor shall include in the Contract sum all allowances named in the Contract Documents and shall cause the work so covered to be done by such Contractors and for such sums as the Owner may direct, the Contract sum being adjusted in conformity therewith. The Contractor declares that the Contract sum includes such sums for expenses and profit on account of cash allowances as he deems proper. No demand for expenses or profit other than those included in the Contract sum shall be allowed. The Contractor shall not be required to employ for any such work persons against whom he has filed a lien or has a reasonable objection due to previous legal claims. GC 18.00

EXPEDITING MATERIALS 10

The Contractor shall, immediately after receipt of the Notice of Award and approval of its list of subcontractors and material suppliers, place orders for all equipment, materials, and supplies required for the Work. The Contractor shall, when requested, submit to the Architect evidence that such orders have been placed. The Contractor shall exercise due diligence in seeing that all equipment, materials, and supplies are delivered well in advance of the time they are needed on the Project and shall properly store and protect same at its expense and in accordance with these General Conditions, either at the Project site or elsewhere as approved by the Architect. GC 19.00

BLASTING

No explosives of any nature except for those normally employed in powder actuated tools, .38 caliber or smaller, shall be employed or used on the Project site except with the express and specific prior written approval of the Architect and the Owner and any appropriate governmental authorities, in each instance. The Contractor shall notify the Architect of need for such approval three (3) days prior to the proposed use of such explosives. GC 20.00

SOIL TEST REPORT

The Owner may arrange for a separate consultant to conduct field and laboratory soil investigations on the Project site and to prepare a report of its findings. Such a report, if prepared, shall be available for review by the Contractor in the Architect’s office. Such data is offered solely for reference and is not to be considered a part of the Contract Documents. The data contained in any such document prepared for the Owner by a separate consultant is believed to be reliable; however, the Owner and Architect do not guarantee its accuracy or completeness. All applicable subcontractors shall be fully familiar with the contents of such reports, if prepared, and shall consider and evaluate them in the performance of their contracts and the Work. GC 21.00

HAZARDOUS MATERIALS

21.01 Responsibility and Reporting. Unless otherwise provided in the Contract Documents, the Contractor shall have no responsibility for the presence, handling, removal or disposal of hazardous materials in any form at the Project site, including but not limited to asbestos, asbestos products, polychlorinated biphenyl (PCB), lead, or other hazardous materials. Prior to its commencement or continuation of any portion of the Work, the Contractor shall provide notice to the Owner of the presence, location, amount and condition of any known or suspected hazardous materials that are discovered at the Project site. Such notice shall be in writing and shall be submitted no more than twenty-four (24) hours after the presence of such materials becomes known or suspected. 21.02 Contractor’s Obligations. In the event hazardous materials become known or suspected by the Contractor as described in GC-21.01 above, the Contractor shall not proceed with or continue the Work until it has received written authorization from the Owner. If the Contractor proceeds with the Work without said authorization, it assumes any and all responsibility and liability for contamination and cleanup at the Project site according to applicable federal and state laws, and for any death or personal injury, including but not limited to medical expenses that may be incurred by any individual as a result of exposure to hazardous materials on the Project site. 21.03 Owner’s Obligations. In the event hazardous materials are identified or encountered during the course of the Project, the Owner at its expense shall take reasonable actions to properly and safely deal with such materials. 21.04 Management Plan. The Contractor acknowledges that it and its employees, agents and subcontractors have the responsibility of being fully informed of the Owner’s Management Plan as it relates to buildings located at the Project site and shall consult with the Owner about how such Plan addresses suspected or active asbestos-containing material areas within such buildings. GC 22.00

DAMAGE TO UTILITIES 11

22.01 Adequate Precautions. The Contractor shall take adequate precautions to protect existing utilities on and off the Project site and avoid damage thereto. The Contractor shall repair or replace or have repaired or replaced at its expense any damage to streets, water, sewer, light, power, cable, or telephone lines or fiber network that are damaged by reason of the Contractor’s Work. 22.02 Location. The location and extent of underground utilities, fiber network, cables and conduit indicated on the drawings are not guaranteed. This information is shown only for such use as bidders and contractors may choose to make of it. The Contractor shall check with all public utility companies for locations and shall comply with their regulations regarding such utilities in performing the Work. 22.03 Protection from Damage. The Contractor shall adequately protect active underground utilities from damage, and if damaged shall immediately effect all necessary repairs. Removal or relocation of active underground utilities shall be done only as indicated on the drawings. If such utilities are in use, they shall be maintained in continuous service. If not indicated on the drawings or not known to exist, the Contractor shall report discovery of such utilities to the Architect and shall not proceed further until directed to do so. 22.04 Inactive or Abandoned Utilities. Inactive or abandoned utilities, whether or not they are indicated on the drawings, shall be recorded as to location and depth and shall be removed for a distance of not less than three (3) feet from the outside line of all concrete Work unless otherwise required by regulations. Ends shall be capped or plugged. There shall be no adjustment of the Contract amount for Work due to inactive or abandoned utilities. GC 23.00

CHANGES IN THE WORK

23.01 Change Orders. The Owner, without invalidating the Agreement, may order changes in the Work within the general scope of the Project consisting of additions, deletions, or other revisions. Under such circumstances, the GMP, if applicable and established, and the Contract Time Schedule shall be adjusted accordingly. All such changes in the Work shall be authorized by Change Order. No Change Order or other form of order or directive by the Owner or Architect requiring additional compensable Work to be performed, which causes the aggregate amount payable under the Contract Documents to exceed the amount appropriated for the original Agreement, shall be issued unless the Contractor is given written assurance by the Owner that lawful appropriations to cover the costs of the additional Work have been made. Any claim of the Contractor for adjustment under this section must be asserted in writing within ten (10) days from the date of the Contractor’s receipt of the Change Order. 23.02 Minor Changes. The Architect shall have authority to order minor changes in the Work not involving an adjustment in the GMP or an extension of the Contract Time Schedule and not inconsistent with the intent of the Contract Documents. Such changes may be effected by field order or by other written order. Such changes shall be binding on the Owner and the Contractor. In any emergency affecting the safety of persons or property, the Contractor shall act, at his discretion, to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in this Article. 23.03 Price Differential. The cost or credit resulting from a change in the Work shall be determined in one or more of the following ways: a. By estimate, with a detailed cost breakdown as set forth in GC-23.03(c) below, and acceptance in a lump sum, with a maximum combined markup to the Owner, for the Contractor and all affected subcontractors, not to exceed a total of fifteen percent (15%). b. By unit prices named in the Contract or subsequently agreed upon. c. If the parties are unable to agree on one of the above methods, then the amount shall be determined by force account under the following formula: i. The actual cost of all direct labor performed (including foremen employed continuously on the Work, but not the salary, or any part thereof, of the Contractor’s superintendent) and the actual 12

ii. iii. iv. v.

vi.

GC 24.00

materials furnished for and used in such Work, less all available cash, trade, or other discounts. Rental for the use of such items of equipment as have an individual value in excess of One Thousand Dollars ($1,000); provided, however, that the amount of such rental charge and the length of time and probable cost of the use of such equipment shall have been authorized in writing by the Owner. All proportionate sums paid for royalties, permits, and inspection fees. All proportionate premiums for public liability insurance, workers’ compensation, and other proper and necessary insurance, as well as all applicable payroll taxes. Either a predetermined lump sum; fixed fee; or a fee of fifteen percent (15%), which fee shall be applied to the total of GC-23.03(c)(i), GC-23.03(c)(ii) and GC-23.03(c)(iii) only, and shall constitute full compensation to the Contractor and all its subcontractors for all costs and expenses, including all overhead and profit, which are not otherwise enumerated in this GC-23.03(c). The Contractor shall keep and present, in such manner as the Owner may direct, an accurate accounting of all the fees and costs described in this GC-23.03(c), together with all supporting vouchers and other documentation, all subject to audit by the Owner. CLAIMS FOR EXTRA COST

If the Contractor claims that any instructions by drawings or otherwise, after the date of the Construction Agreement, involve extra costs under this Contract that were not included in the original bid, or require an extension in the construction schedule, the Contractor shall give the Owner and the Architect written notice thereof no later than ten (10) days after the receipt of such instructions, and in any event before proceeding to execute the Work, except in an emergency endangering life or property, and the procedure shall then be as provided for changes in the Work. No such claim shall be valid unless so made. Any change in the Contract amount or construction schedule must be authorized by Change Order. GC 25.00

DELAYS AND EXTENSIONS OF TIME

25.01 Delays and Extensions of Time. If the Contractor is delayed at any time in the progress of the Work by the negligence or other improper act of the Owner or the Architect, or by any employee of either, or by any separate contractor employed by the Owner, or by changes ordered in the Work, or by any other cause that the Owner determines may justify the delay, then the completion date shall be extended by Change Order for such reasonable time as the Owner may determine. a.

Extension of the Contract completion time will be considered for delays due to weather conditions only when such conditions have had a material, adverse impact upon the critical path of the construction schedule, are more severe and extended than those reflected by the ten (10) year average for the month as evidenced by climatological data, U.S. Department of Commerce, for the area where the Project is located, and only if a request for such an extension of time is received within seven (7) days of the first date of each delay. Extensions of time due to weather or other allowable reasons will be granted on the basis of 1.4 calendar days’ credit for every working day lost with each separate extension figured to the nearest whole calendar day.

b.

All Contractor requests for extension of time shall be subject to the Owner’s approval and shall be made in writing to the Owner no more than seven (7) days after the occurrence causing the delay; otherwise they shall be deemed waived. Any request for extension of time for a change in the Work or for any occurrence allegedly causing a delay as provided for herein must be substantiated by demonstrating the effect of the change or occurrence on the critical path of the construction schedule.

c.

If no schedule or agreement is made stating the dates upon which written interpretations or detail drawings shall be furnished, then no claim for delay shall be allowed on account of failure to furnish such interpretations or detail drawings until fifteen (15) days after demand is made for them, and then only if such claim is reasonable.

13

d.

Should the time for completion of the Contract be extended, the Owner reserves the right to occupy any part of the structure upon written notice to the Contractor from the Architect or the Owner, but only after the Architect has made a thorough inspection, accompanied by the Contractor’s superintendent, to note any defects in workmanship or materials that are the responsibility of the Contractor. Such inspection shall not be deemed to modify any other Contract requirements or provisions relating to observations, inspections or acceptance of the Work. Any such partial occupancy shall not be deemed a waiver of any provision for liquidated damages for delay in final completion.

e.

When the whole or a portion of the Work is suspended for any reason, the Contractor shall properly cover over, secure, and protect all Work as may be susceptible to damage in the absence of such action.

25.02 Article Not Exclusive. This GC-25.00 does not exclude the recovery of damages by the Owner for delay under other provisions of the Contract Documents. GC 26.00

ACCESS TO WORK

26.01 Access. The Architect, the Owner, and their representatives shall at all times have access to the Work wherever it is in preparation or progress, and the Contractor shall provide proper facilities for such access so that the Architect may perform its functions under the Contract Documents. 26.02 Inspection. If the specifications, the Architect’s instructions, laws, ordinances, or any public authority require any Work to be specially tested or approved, the Contractor shall give the Architect timely notice of its readiness for such testing or approval by the Architect or inspection by another authority, and if the inspection is by another authority, of the date fixed for such inspection. All required certificates of inspection shall be secured by the Contractor. If any Work is covered up without approval or consent of the Architect, it must, if required by the Architect, be uncovered for examination at the Contractor’s expense. 26.03 Reinspection. Reinspection of questioned Work may be ordered by the Owner, and if so ordered, the Work must be uncovered by the Contractor. If such Work is found to be in accordance with the Contract Documents, the Owner shall pay the cost of reinspection and replacement. If such Work is found not to be in accordance with the Contract Documents, the Contractor shall pay such cost. 26.04 Testing. Materials incorporated into the Project shall be subject to routine tests as required to ensure their compliance with the specifications. Such tests may include, but shall not necessarily be restricted to, the following: concrete (primary mix design, slump tests, cylinder compressions tests, and air entrainment tests); steel (tensile tests); welds (field inspection and x-ray examination); soils (sub-soil investigation, physical analysis, and compaction tests); asphalt pavement (physical analysis and compaction tests); and roofing samples cut from in-place built-up roof. Any other basic materials for which standard laboratory test procedures have been established may also be included if doubt as to their quality should arise. Any testing contemplated by this section shall be done at the discretion of the Owner, who shall bear all costs, unless otherwise provided in the Contract Documents. The Contractor shall be held responsible for providing samples of sufficient size for test purposes and for cooperating with the Owner or its representative in obtaining and preparing samples for tests. All tests shall be in accordance with standard test procedures and shall be performed by persons or firms selected by the Owner. Contractor shall schedule and coordinate all tests and inspections directly with the owner’s testing and / or inspection agency. Contractor shall give the architect and owner 48 hours’ notice of when and where tests and inspections are to be made so that the architect may be present for such procedures. GC 27.00

CORRECTION OF WORK

27.01 Correction of Work Before and After Completion. The Architect or Owner has the authority to reject Work that is defective or otherwise does not conform to the Contract Documents. The Contractor, following written demand, shall promptly correct all Work rejected by the Architect or Owner as defective or as 14

otherwise failing to conform to the Contract Documents, whether observed before or after the date of final completion and whether or not fabricated, installed, or completed. The Contractor shall bear all costs of correcting such rejected Work, including the cost of the Architect’s and/or Owner’s consultant’s additional services necessitated thereby. If the Contractor proceeds to build in or cover the item that has been rejected, the Contractor shall be totally responsible for the cost of removal and replacement of said item and removal and replacement of all necessary Work surrounding or covering the item. 27.02 Tests to Determine Conformance. Whenever in the opinion of the Architect or the Owner tests are essential to assure the professional evaluation of the Work that is subject to being rejected or condemned, the necessary number of tests shall be performed by consultants designated by the Owner. The recommendation of such consultants shall be final and all parties to the Contract shall comply with the methods and extent of the corrections submitted in writing to the Owner and the Architect by such consultants. The cost of the tests shall become the Contractor’s responsibility when corrections of any nature are recommended by the consultant to the investigated Work; otherwise, the Owner shall pay for all tests performed. Should such special testing, inspection, or approval be caused by the Contractor’s failure to follow the requirements of the Contract Documents or required tests under GC-26.04 indicating conditions not in conformance with the Contract Documents, the costs of such additional testing, inspection, or approval shall be borne by the Contractor, regardless of the results. 27.03 Removal of Rejected Work. The Contractor shall promptly remove from the Project site all Work rejected by the Architect or Owner as failing to conform to the Contract Documents, whether or not the Work is physically incorporated. Thereafter, the Contractor shall promptly replace and re-execute such Work in accordance with the Contract Documents and without expense to the Owner. The Contractor shall further bear the expense of making good all Work of other contractors and/or subcontractors destroyed or damaged by such removal or replacement, and shall bear the expense of making good all of its Work and the Work of its subcontractors found to be defective by such removal or replacement. If the Contractor does not remove such rejected Work within a reasonable time, fixed by written notice from the Owner through the Architect, the Owner may remove it and may store the material at the expense of the Contractor. If the Contractor does not pay the expenses of such removal and storage within ten (10) days’ time thereafter, the Owner may, upon ten (10) days’ written notice, sell such materials at auction or at private sale. In such case, the Owner shall account to the Contractor for the net proceeds thereof, after deducting all the costs and expenses that should have been borne by the Contractor, including compensation for additional Architect or consultant services. If the net proceeds of sale do not cover all costs that the Contractor should have borne, the difference shall be charged to the Contractor and an appropriate Change Order shall be issued. If the payments then or thereafter due the Contractor are not sufficient to cover such amount, the Contractor shall pay the difference to the Owner. In addition, the Owner shall have any other remedies that may be available to it. 27.04 Correction of Work After Final Payment. Neither the final estimate or payment, nor any provision in the Contract Documents, shall relieve the Contractor of responsibility for faulty materials or workmanship and, unless otherwise specified, the Contractor shall remedy any defects due thereto and pay for any damage to other Work or property resulting therefrom, which appear within a period of two (2) years from the date of final completion and acceptance. This warranty shall be in addition to and not in lieu of all other remedies available to the Owner. 27.05 Failure to Correct the Work. If the Contractor fails to correct defective or nonconforming Work, the Owner may correct it and otherwise proceed against the Contractor for the cost thereof in accordance with the provisions of these General Conditions. 27.06 Deductions for Uncorrected Work. If the Owner deems it inexpedient to correct Work that has been damaged, is defective or has not been done in accordance with the Contract Documents, then an appropriate deduction from the price shall be made and reflected by a Change Order or, if the amount is determined after final payment, it shall be paid by the Contractor. 15

27.07 Additional Obligations. The obligations of the Contractor to correct the Work shall be in addition to, and not in lieu of, any other obligations imposed upon it by law, special guarantees, warranties, or other rights of the Owner. GC 28.00

OWNER’S RIGHT TO CARRY OUT WORK

If the Contractor should neglect to prosecute the Work properly or fail to perform any requirement of the Contract Documents, the Owner, after three (3) working days’ written notice to the Contractor, may, without prejudice to any other remedy it may have, make good such deficiencies and may deduct the reasonable cost thereof from the payment then or thereafter due the Contractor. In the event such Work is performed by the Owner, the Owner’s employees, or by persons other than the Contractor at the Owner’s request, the Owner shall not be liable to the Contractor for inconvenience expense or subsequent cost of removal of such Work. The amount to be deducted as the cost of doing the Work shall include the cost of the Architect’s additional services made necessary by such default. If the payments then or thereafter due the Contractor are not sufficient to cover such amount, the Contractor shall pay the difference to the Owner. GC 29.00

OWNER’S RIGHT TO TERMINATE CONTRACT

29.01 Termination for Cause. If the Contractor should be adjudged bankrupt; or if it should make a general assignment for the benefit of its creditors without approval of the Owner; or if a receiver should be appointed on account of its insolvency; or if it should refuse or should fail, except in cases for which extension of time is provided, to supply enough properly skilled workers, competent supervision and superintendence of the Work, proper materials, or competent management of the Project; of if it should fail to make prompt payment to subcontractors or for material or labor; or disregard any laws, ordinances, or the instructions of the Architect or Owner; or otherwise be guilty of a material violation of any provision of the Contract Documents; then the Owner, when in its sole opinion sufficient cause exists to justify such action, may, without prejudice to any other right or remedy and after giving the Contractor, and its surety, if any, seven (7) days’ written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, tools, and appliances thereon and finish the Work by whatever method the Owner may deem expedient. In such case the Contractor shall not be entitled to receive any further payment until the Work is finally completed and accepted by the Owner. If the unpaid balance of the Contract amount exceeds the expense of completing the Work, including the cost of additional architectural, engineering, managerial, consultant, and administrative services, such excess shall be paid to the Contractor. If such expense exceeds such unpaid balance, the Contractor shall pay the difference to the Owner and the Owner shall be justified in withholding payment of any unpaid amounts. The expense incurred by the Owner, as herein provided, and the damages incurred through the Contractor’s default, shall be determined by the Owner. The Contractor will not be reimbursed for any anticipated profit. 29.02 Termination Without Cause. Should conditions arise that in the Owner’s opinion make it necessary or advisable to discontinue Work under the Contract Documents, the Owner may terminate the Contract in whole or in part without cause or fault by the Contractor by giving seven (7) days’ written notice to the Contractor. The notice shall specify the date and extent to which the Contract is terminated. Upon any such termination, the Owner shall take possession of the Project site and all or any part of the materials and equipment delivered or en route to the site. In the event of termination without cause under this section, the Contractor shall be equitably paid for all Work properly completed, based upon the approved schedules of values. GC 30.00

CONSTRUCTION SCHEDULE AND PROGRESS REPORTS

30.01 Construction Schedule. The Contractor shall submit, within ten (10) days after the date of the notice of award in a format acceptable to the Owner, an overall timetable of the construction schedule for the Project. This schedule shall start with the date of the notice of award, and the completion date shall be a date that will enable the Owner to accept the Work on the date specified in the Construction Agreement. The 16

schedule shall portray fully a timetable representing the various elements in the schedule of values and shall provide for the expeditious and practicable execution of the Work. The time shown between the starting and completion dates of the various elements within the schedule shall represent one hundred percent (100%) completion of each element. Additional detailed schedules of separate elements of the Work such as commissioning, test and balance, and owner training, may be requested at the Owner’s discretion. No request for payment shall be accepted by the Owner until this schedule has been submitted as required herein. This schedule shall be revised from time to time during the course of the Work when the actual progress, in the opinion of the Architect or the Owner, varies materially from that previously approved. 30.02 Monthly Progress Reports. The Contractor shall submit monthly progress reports with each request for payment. Basically, these reports shall reflect the Contractor’s “Work in place” progress and shall be certified by the Contractor as to the date and contents of such “Work in place” progress report. If requested by the Owner, the monthly progress reports shall also include representative photographs of the actual Work in place. Such reports shall depict progress and percentage of completion, consistent with the values and amounts contained on the counterpart request for payment. The subcontractors shall be supplied copies of the Contractor’s approved schedule. These subcontractors shall develop a similar schedule based on their respective Work. Failure to submit an approved schedule or monthly progress report shall be deemed cause to reject requests for payment. 30.03 Scheduling. The Contractor shall schedule all Work so as to reduce to a minimum any disruption in the use of the existing facilities and interruptions of utility service of any type. Where electrical or mechanical Work performed under this Contract will necessitate interruptions of service to existing facilities, the Contractor shall furnish and install temporary service to such facilities or perform such Work at such times when said existing utilities are not in normal use. The Contractor shall bear the cost of all overtime or inconvenience resulting therefrom. Any remodeling work which may interrupt normal building functions, especially periodic standardized testing, shall be scheduled and coordinated with the Owner at least 1 week prior. 30.04 Noise Ordinance Violation. The Contractor shall at all times comply with the local noise ordinance requirements relating to the Work. To the extent there are any violations of any applicable noise ordinances imposed on the Owner as a direct or indirect result of the Contractor’s Work, then the Contractor shall reimburse the Owner for any sums paid or due and payable by the Owner as a result of such violations. The Owner reserves the right to deduct any expenses incurred by the Owner as a result of any noise ordinance violations by the Contractor from any amount due to the Contractor under this Construction Agreement or, at its option, to collect such sum directly from the Contractor or its surety GC 31.00

SCHEDULE OF VALUES