Exhibits BVSD Fairview High School Amendment Package No. 2.pdf (3,726 KB)

Regular Meeting, November 18, 2025 · item 8.9: Amendment to the contract for Fairview High School · 135 pages

Open the original file

This is the text extracted from the file, without its layout, tables, or images. Use the original for anything that matters.

Exhibit A Drawings, specifications and documents used to prepare the GMP

First Amendment to CM/GC Agreement With Turner Construction Company, dated April 25, 2017

Printed on Mon Nov 3, 2025 at 09:11 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction

Current Drawings Drawing No.

Drawing Title

Revision

Drawing Date

Received Date

Set

Cover Sheet CS-001

COVER SHEET

0

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

G-001

CODE COMPLIANCE - CODE DATA AND LOWER LEVELS

1

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

G-002

CODE COMPLIANCE - CODE DATA AND LOWER LEVELS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

G-003

CODE COMPLIANCE - MIDDLE LEVELS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

G-004

CODE COMPLIANCE - UPPER LEVELS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

L1.0

OVERALL SITE PLAN

4

09/25/2025

25.09.25 - Addendum #1 (09/25/25)

L2.0

SITE DETAILS

3

09/25/2025

25.09.25 - Addendum #1 (09/25/25)

LI1.0

IRRIGATION PLAN

4

09/25/2025

25.09.25 - Addendum #1 (09/25/25)

LI1.1

IRRIGATION PLAN

3

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

LI2.0

IRRIGATION DETAILS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

C0.1

LEGEND NOTES & ABBREVIATIONS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

C0.2

DEMOLITION PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

C0.3

ALTERNATE 5-IS-7 DEMOLITION PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

C1.0

GRADING AND DRAINAGE PLAN

3

10/01/2025

25.10.01 - Addendum #2 (10/01/25)

C1.1

ALTERNATE 5-IS-7 GRADING AND DRAINAGE PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

C2.0

GAS LINE PLAN (SHOWN FOR REFERENCE ONLY)

1

10/01/2025

25.10.01 - Addendum #2 (10/01/25)

C2.1

GAS & ELECTRIC LINE PLAN (SHOWN FOR REFERENCE ONLY)

0

10/01/2025

25.10.01 - Addendum #2 (10/01/25)

C3.0

HORIZONTAL CONTROL PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

C3.1

ALTERNATE 5-IS-7 HORIZONTAL CONTROL PLAN

3

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

CD1.0

GRADING AND DRAINAGE DETAILS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

CD3.0

HORIZONTAL CONTROL DETAILS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

CD3.1

HORIZONTAL CONTROL DETAILS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

CE1.0

EROSION CONTROL PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

CE1.1

ALTERNATE 5-IS-7 EROSION CONTROL PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

CE1.2

EROSION CONTROL DETAILS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

CE1.3

EROSION CONTROL DETAILS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

CE1.4

EROSION CONTROL DETAILS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

S-001

GENERAL NOTES

1

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

S-101A

PARTIAL PLANS AND DETAILS -

3

10/01/2025

25.10.01 - Addendum #2 (10/01/25)

General

Landscape

Civil

Structural

Page 1 of 6

Printed on Mon Nov 3, 2025 at 09:11 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction

Drawing No.

Drawing Title

Revision

Drawing Date

Received Date

Set

S-101B

PARTIAL PLANS AND DETAILS - COMPUTER

2

09/25/2025

25.09.25 - Addendum #1 (09/25/25)

S-101C

PARTIAL PLANS AND DETAILS -

1

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

A-100

OVERALL FLOOR PLANS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

A-101

LOWER LEVEL OVERALL FLOOR PLAN

4

10/01/2025

25.10.01 - Addendum #2 (10/01/25)

A-102

MIDDLE LEVEL OVERALL FLOOR PLAN

3

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

A-103

UPPER LEVEL OVERALL FLOOR PLAN

3

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

A-104

900 LEVEL GYMNASIUM FLOOR PLAN

3

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

A-111

LOWER LEVEL RCP

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

A-112

MIDDLE LEVEL OVERALL RCP

3

10/01/2025

25.10.01 - Addendum #2 (10/01/25)

A-113

UPPER LEVEL OVERALL RCP

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

A-121

PARTIAL ROOF PLAN

4

09/25/2025

25.09.25 - Addendum #1 (09/25/25)

A-201

EXTERIOR BUILDING ELEVATIONS

3

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

A-361

EXTERIOR SECTION DETAILS

4

10/01/2025

25.10.01 - Addendum #2 (10/01/25)

A-415

LARGE SCALE FLOOR PLANS - CTE COMPUTER LAB 225

3

09/25/2025

25.09.25 - Addendum #1 (09/25/25)

A-416

LARGE SCALE FLOOR PLANS - CLASSROOM 317

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

A-417

LARGE SCALE FLOOR PLANS - NEW CHEMISTRY 408 - ENLARGED PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

A-418

LARGE SCALE FLOOR PLANS - LIBRARY 450

3

10/01/2025

25.10.01 - Addendum #2 (10/01/25)

A-451

INTERIOR ELEVATIONS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

A-501

INTERIOR DETAILS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

A-601

DOOR AND WINDOW SCHEDULES

4

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

A-700

ROOM FINISH SCHEDULE &

3

10/01/2025

25.10.01 - Addendum #2 (10/01/25)

A-701

LOWER LEVEL OVERALL FINISH PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

A-702

MIDDLE LEVEL OVERALL FINISHPLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

A-703

UPPER LEVEL OVERALL FINISH PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

AD-100

OVERALL DEMOLITION FLOOR PLANS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

AD-101

LOWER LEVEL FLOOR PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

AD-102

MIDDLE LEVEL DEMOLITION FLOOR PLAN

3

10/01/2025

25.10.01 - Addendum #2 (10/01/25)

AD-103

UPPER LEVEL DEMOLITION FLOOR PLAN

3

10/01/2025

25.10.01 - Addendum #2 (10/01/25)

AD-104

900 LEVEL GYMNASIUM DEMOLITION FLOOR PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

AD-111

OVERALL DEMOLITION RCP

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

AD-112

OVERALL DEMOLITION RCP

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

AD-113

OVERALL DEMOLITION RCP

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

AD-121

PARTIAL DEMOLITION ROOF PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

AD-415

PLANS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

AS-101

ARCHITECTURAL SITE PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

AS-501

ARCHITECTURAL SITE PLAN DETAILS

5

09/25/2025

25.09.25 - Addendum #1 (09/25/25)

Architectural

Fire Protection Page 2 of 6

Printed on Mon Nov 3, 2025 at 09:11 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction

Drawing No.

Drawing Title

Revision

Drawing Date

Received Date

Set

FP-001

FIRE PROTECTION GENERAL INFORMATION

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FP-102

200 LEVEL FIRE PROTECTION PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FP-103

300 LEVEL FIRE PROTECTION PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FP-104.1

400 LEVEL FIRE PROTECTION PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FP-106.1

600 LEVEL FIRE PROTECTION PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FP-106.2

1100 LEVEL CORE FIRE PROTECTION PLANS

0

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FP-109.4

900 LEVEL GYMNASIUM FIRE PROTECTION PLAN

0

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FPD-102

200 LEVEL FIRE PROTECTION DEMOLITION PLAN

1

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FPD-103

300 LEVEL FIRE PROTECTION DEMOLITION PLAN

1

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FPD-104.1

400 LEVEL FIRE PROTECTION DEMOLITION PLAN

1

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FPD-106.1

600 LEVEL FIRE PROTECTION DEMOLITION PLAN

1

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FPD-106.2

1100 LEVEL CORE FIRE PROTECTION DEMOLITION PLANS

0

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FPD-109.4

900 LEVEL GYMNASIUM FIRE PROTECTION DEMOLITION PLAN

1

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

P-001

PLUMBING GENERAL INFORMATION

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

P-002

PLUMBING SCHEDULES

3

10/01/2025

25.10.01 - Addendum #2 (10/01/25)

P-100

PLUMBING SITE PLAN

1

10/01/2025

25.10.01 - Addendum #2 (10/01/25)

P-103

300 LEVEL PLUMBING PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

P-104.1

400 LEVEL PLUMBING PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

P-109.4

900 LEVEL GYMNASIUM PLUMBING PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

P-401

ENLARGED PLUMBING PLANS - 400 LEVEL CHEMISTRY

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

P-402

ENLARGED PLUMBING DEMOLITION PLAN - BOILER ROOM

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

P-403

ENLARGED PLUMBING PLAN - BOILER ROOM

3

10/01/2025

25.10.01 - Addendum #2 (10/01/25)

P-601

PLUMBING DETAILS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

P-602

PLUMBING DETAILS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

P-603

PLUMBING DETAILS

0

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

PD-103

300 LEVEL PLUMBING DEMOLITION PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

M-001

MECHANICAL GENERAL INFORMATION

3

10/01/2025

25.10.01 - Addendum #2 (10/01/25)

M-002

MECHANICAL SCHEDULES

3

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

M-003

MECHANICAL SCHEDULES

3

10/01/2025

25.10.01 - Addendum #2 (10/01/25)

M-004

MECHANICAL COMPLIANCE

0

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

M-102

200 LEVEL MECHANICAL PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

M-103

300 LEVEL MECHANCIAL PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

M-104.1

400 LEVEL MECHANICAL PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

M-106.1

600 LEVEL MECHANCIAL PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

M-106.2

600/1100 LEVEL ADDITION & CORE MECHANCIAL PLANS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

M-109.4

900 LEVEL GYMNASIUM MECHANCIAL PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

Plumbing

Mechanical

Page 3 of 6

Printed on Mon Nov 3, 2025 at 09:11 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction

Drawing No.

Drawing Title

Revision

Drawing Date

Received Date

Set

M-110

1000 LEVEL CORE MECHANCIAL PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

M-140

OVERALL ROOF MECHANCIAL PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

M-401

MECHANICAL SECTIONS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

M-402

MECHANICAL SECTIONS

1

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

M-501

MECHANICAL SCHEMATICS

3

10/01/2025

25.10.01 - Addendum #2 (10/01/25)

M-502

MECHANICAL SCHEMATICS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

M-601

MECHANICAL DETAILS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

M-602

MECHANICAL DETAILS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

MD-102

200 LEVEL MECHANICAL DEMOLITION PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

MD-103

300 LEVEL MECHANICAL DEMOLITION PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

MD-104.1

400 LEVEL MECHANICAL DEMOLITION PLAN

0

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

MD-106.2

600/1100 LEVEL ADDITION & CORE MECHANICAL DEMOLITION PLANS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

MD-109.4

900 LEVEL GYMNASIUM MECHANICAL DEMOLITION PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

MD-110

1000 LEVEL CORE MECHANICAL DEMOLITION PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

MD-140

OVERALL ROOF MECHANICAL DEMOLITION PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

E-001

ELECTRICAL GENERAL INFORMATION

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

E-002

APPEARING HEREIN SHALL NOT BE DUPLICATED, DISCLOSED OR OTHERWISE USED WITHOUT THE WRITTEN CONSENT OF MOA ARCHITECTURE

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

E-003

ELECTRICAL SCHEDULES

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

E-004

ELECRICAL COMCHECK

0

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

E-100

ELECTRICAL SITE PLAN

3

09/25/2025

25.09.25 - Addendum #1 (09/25/25)

E-102

200 LEVEL POWER PLAN

3

09/25/2025

25.09.25 - Addendum #1 (09/25/25)

E-103

300 LEVLE POWER PLANS

0

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

E-104.1

400 LEVEL POWER PLAN

3

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

E-105.2

500 MEZZANINE LEVEL POWER PLAN

0

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

E-106.2

600/1100 LEVEL ADDITION & CORE POWER PLAN

1

07/25/2025

25.07.25 - Progress CD Set (07/25/ 25)

E-109.4

900 LEVEL GYMNASIUM POWER PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

E-110

1000 LEVEL CORE POWER PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

E-140

OVERALL ROOF POWER PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

E-202

200 LEVEL LIGHTING PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

E-203

300 LEVEL LIGHTING PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

E-204.1

400 LEVEL LIGHTING PLAN

3

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

E-206.1

600 LEVEL LIGHTING PLAN

0

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

E-401

ENLARGED ELECTRICAL PLAN - BOILER ROOM

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

E-501

ELECTRICAL ONE-LINE DIAGRAM

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

E-601

ELECTRICAL SCHEDULES

0

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

Electrical

Page 4 of 6

Printed on Mon Nov 3, 2025 at 09:11 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction

Drawing No.

Drawing Title

Revision

Drawing Date

Received Date

Set

E-602

ELECTRICAL SCHEDULES

0

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

E-603

ELECTRICAL SCHEDULES

0

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

ED-102

200 LEVEL POWER DEMOLITION PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

ED-104.1

400 LEVEL POWER DEMOLITION PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

ED-109.4

APPEARING HEREIN SHALL NOT BE DUPLICATED, DISCLOSED OR OTHERWISE USED WITHOUT THE WRITTEN CONSENT OF MOA ARCHITECTURE

0

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

ED-140

OVERALL ROOF POWER DEMOLITION PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

ED-202

200 LEVEL LIGHTING DEMOLITION PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

ED-203

300 LEVEL LIGHTING DEMOLITION PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

ED-204.1

400 LEVEL LIGHTING DEMOLITION PLAN

3

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

ED-206.1

600 LEVLE LIGHTING DEMOLITION PLAN

1

10/01/2025

25.10.01 - Addendum #2 (10/01/25)

ED-401

ENLARGED ELECTRICAL DEMOLITION PLAN - BOILER ROOM

3

10/01/2025

25.10.01 - Addendum #2 (10/01/25)

T-001

COMMUNICATIONS TITLE SHEET

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

T-002

COMMUNICATIONS PROJECT NOTES

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

T-003

COMMUNICATIONS SCHEDULES

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

T-101

100 LEVEL COMMUNICATIONS PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

T-102

200 LEVEL COMMUNICATIONS PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

T-103

300 LEVEL COMMUNICATIONS PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

T-104.1

400 LEVEL COMMUNICATIONS PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

T-104.2

400 LEVEL LIBRARY COMMUNICATIONS PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

T-105.1

500 LEVEL COMMUNICATIONS PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

T-105.2

500 MEZZANINE LEVEL COMMUNICATIONS PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

T-106.1

600 LEVEL COMMUNICATIONS PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

T-106.2

600/1100 LEVEL ADDITION & CORE COMMUNICATIONS PLANS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

T-107

700 LEVEL COMMUNICATIONS PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

T-108.1

800 LEVEL COMMUNICATIONS PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

T-109.1

900 LEVEL COMMUNICATIONS PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

T-109.4

900 LEVEL GYMNASIUM COMMUNICATIONS PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

T-110

1000 LEVEL COMMUNICATIONS PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

T-503

AUDIOVISUAL SYSTEM PLAN

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

T-601

COMMUNICATIONS DETAILS

2

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FA-001

FIRE ALARM GENERAL INFORMATION

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FA-101

100 LEVEL FIRE ALARM PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FA-102

200 LEVEL FIRE ALARM PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FA-103

300 LEVEL FIRE ALARM PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FA-104.1

400 LEVEL FIRE ALARM PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

Telecommunications

Fire Alarm

Page 5 of 6

Printed on Mon Nov 3, 2025 at 09:11 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction

Drawing Date

Received Date

Set

FA-104.2

Drawing No. 400 LEVEL LIBRARY FIRE ALARM PLAN

Drawing Title

Revision 2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FA-105.1

500 LEVEL FIRE ALARM PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FA-105.2

500 MEZZANINE LEVEL FIRE ALARM PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FA-106.1

600 LEVEL FIRE ALARM PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FA-106.2

600/1100 LEVEL ADDITION & CORE FIRE ALARM PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FA-107

700 LEVEL FIRE ALARM PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FA-108.1

800 LEVEL FIRE ALARM PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FA-109.1

900 LEVEL FIRE ALARM PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FA-109.2

900 LEVEL AUDITORIUM FIRE ALARM PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FA-109.4

900 LEVEL GYMNASIUM FIRE ALARM PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FA-110

1100 LEVEL CORE FIRE ALARM PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FAD-101

100 LEVEL FIRE ALARM DEMOLITION PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FAD-102

200 LEVEL FIRE ALARM DEMOLITION PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FAD-103

300 LEVEL FIRE ALARM DEMOLITION PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FAD-104.1

400 LEVEL FIRE ALARM DEMOLITION PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FAD-104.2

400 LEVEL LIBRARY FIRE ALARM DEMOLITION PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FAD-105.1

500 LEVEL FIRE ALARM DEMOLITION PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FAD-105.2

500 MEZZANINE LEVEL FIRE ALARM DEMOLITION PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FAD-106.1

600 LEVEL FIRE ALARM DEMOLITION PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FAD-106.2

600/1100 LEVEL ADDITION & CORE FIRE ALARM DEMOLITION PLANS

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FAD-107

700 LEVEL FIRE ALARM DEMOLITION PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FAD-108.1

800 LEVEL FIRE ALARM DEMOLITION PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FAD-109.1

900 LEVEL FIRE ALARM DEMOLITION PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FAD-109.2

900 LEVEL AUDITORIUM FIRE ALARM DEMOLITION PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FAD-109.4

900 LEVEL GYMNASIUM FIRE ALARM DEMOLITION PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

FAD-110

1000 LEVEL CORE FIRE ALARM DEMOLITION PLAN

2

09/12/2025

09/12/2025

25.09.12 - 100% CD Set (09/12/25)

Page 6 of 6

Printed on Mon Nov 3, 2025 at 09:12 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction

Current Specifications Number

Description

Revision

Issued Date

Received Date

Set

00 - Procurement and Contracting Requirements 00 1000

Performance Bond MOA

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

00 1100

Labor and Material Payment Bond MOA

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

00 1300

Asbestos Management Plan Contractor Responsibility MOA

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

00 1400

Lead Based Paint Contractor Responsibility MOA

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

000107

Seals Page

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

000110

Table of Contents

2

09/12/25

09/12/25

2025-09-12 - 100% CD Set

003100

Available Project Information

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

006000

Project Forms

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

006001

RFI Form

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

006002

Substitution Request Form

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

006003

Proposal Request Form

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

006004

ASI Form

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

006005

Construction Change Directive Form

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

01 - General Requirements 011000

Summary

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

012000

Price and Payment Procedures

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

012100

Allowances

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

012300

Alternates

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

012500

Substitution Procedures

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

013000

Administrative Requirements

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

013216

Construction Progress Schedule

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

014000

Quality Requirements

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

014216

Definitions and Explanations

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

015000

Temporary Facilities and Controls

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

016000

Product Requirements

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

016116

Volatile Organic Compound (VOC) Content Restrictions

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

017000

Execution and Closeout Requirements

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

017419

Construction Waste Management and Disposal

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

017610

Temporary Protective Coverings

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

017800

Closeout Submittals

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

017900

Demonstration and Training

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

02 - Existing Conditions

Page 1 of 6

Printed on Mon Nov 3, 2025 at 09:12 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction

Number 02 41 00

Description

Revision

Issued Date

Received Date

Set

Demoltion JVA

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

030100

Maintenance of Concrete

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

030516

Underslab Vapor Barrier

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

033511

Concrete Floor Finishes

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

040511

Masonry Mortaring and Grouting

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

042000

Unit Masonry

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

Metal Fabrications

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

03 - Concrete

04 - Masonry

05 - Metals 055000

06 - Wood, Plastics, and Composites 061000

Rough Carpentry

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

066100

Cast Polymer Fabrications

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

07 - Thermal and Moisture Protection 070150

Maintenance of Membrane Roofing

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

070553

Fire and Smoke Assembly Identification

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

071113

Bituminous Dampproofing MOA

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

071400

Fluid-Applied Waterproofing

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

071900

Water Repellents MOA

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

072100

Thermal Insulation MOA

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

072119

Foamed-In-Place Insulation

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

072500

Weather Barriers

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

074646

Fiber-Cement Siding

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

075300

Elastomeric Membrane Roofing

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

076200

Sheet Metal Flashing and Trim

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

077100

Roof Specialties

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

078400

Firestopping

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

079200

Joint Sealants

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

08 7100

Door Hardware

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

081113

Hollow Metal Doors and Frames

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

081416

Flush Wood Doors

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

083100

Access Doors and Panels

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

084313

Aluminum-Framed Storefronts

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

088000

Glazing

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

Common Work Results for Flooring Preparation

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

08 - Openings

09 - Finishes 090561

Page 2 of 6

Printed on Mon Nov 3, 2025 at 09:12 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction

Number

Description

Revision

Issued Date

Received Date

Set

092116

Gypsum Board Assemblies

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

095100

Acoustical Ceilings

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

096500

Resilient Flooring and Base

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

096813

Tile Carpeting

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

097200

Wall Coverings

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

098430

Sound-Absorbing Wall and Ceiling Units

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

099113

Exterior Painting

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

099123

Interior Painting

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

101100

Visual Display Units

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

101423

Panel Signage

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

102600

Wall and Door Protection

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

104400

Fire Protection Specialties

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

105617

Wall Mounted Standards and Shelving

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

113013

Residential Appliances MOA

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

118129

Facility Fall Protection

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

119900

Miscellaneous Equipment

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

10 - Specialties

11 - Equipment

12 - Furnishings 122400

Window Shades

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

123200

Manufactured Wood Casework

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

123600

Countertops

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

Fire Protection

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

22 0000

Basic Plumbing Requirements BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

22 0500

Common Work Results for Plumbing BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

22 0519

Meters and Gauges for Plumbing Piping BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

22 0523

General-Duty Valves for Plumbing Piping BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

22 0529

Hangers and Supports for Plumbing Piping and Equipment BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

22 0553

Identification for Plumbing Piping and Equipment BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

22 0700

Plumbing Insulation BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

22 1116

Domestic Water Piping BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

22 1119

Domestic Water Piping Specialties BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

22 1316

Sanitary Waste and Vent Piping BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

22 1319

Sanitary Waste Piping Specialties BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

22 1413

Storm Drainage Piping BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

21 - Fire Suppression 21 0500 22 - Plumbing

Page 3 of 6

Printed on Mon Nov 3, 2025 at 09:12 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction

Number

Description

Revision

Issued Date

Received Date

Set

22 3200

Water Heaters BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

22 4000

Plumbing Fixtures BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

22 6600

Laboratory Drainage Systems BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 - Heating, Ventilating, and Air Conditioning (HVAC) 23 0000

Basic Mechanical Requirements BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 0100

M&E Coordination BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 0500

Common Work Results for HVAC BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 0514

Motor Controllers BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 0515

Variable Frequency Controllers BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 0519

Meters and Gauges BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 0529

Supports and Anchors BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 0553

Mechanical Identification BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 0593

Testing, Adjusting, and Balancing BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 0700

Mechanical Insulation BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 0800

Commissioning of HVAC BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 0900

Direct Digital Control Systems BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 0902

Integrated Automation Control Sequence BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 1123

Natural Gas Systems BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 2113

Hydronic Piping BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 2300

Refrigerant Piping BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 3113

Metal Ductwork BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 3300

Ductwork Accessories BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 3413

Air Handling Fans BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 3600

Air Terminals BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 3713

Air Outlets and Inlets BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 6200

Condensing Units BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 7414

Rooftop Heating and Cooling Units BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

23 8200

Terminal Heat Units BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

26 0500

Basic Electrical Requirements BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

26 0510

Electrical Remodeling Provisions BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

26 0519

Building Wire and Cable BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

26 0526

Grounding and Bonding BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

26 0529

Supporting Devices and Seals BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

26 0532

Conduit BCER

1

09/25/25

09/25/25

2025-09-25 - Addendum #1 R1

26 0534

Electrical Boxes and Fittings BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

26 0553

Electrical Identification BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

26 - Electrical

Page 4 of 6

Printed on Mon Nov 3, 2025 at 09:12 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction

Number

Description

Revision

Issued Date

Received Date

Set

26 0580

Equipment Wiring Systems BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

26 0800

Commissioning of Electrical BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

26 0923

Lighting Control Devices BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

26 2416

Panelboards BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

26 2726

Wiring Devices BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

26 2816

Enclosed Switches BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

26 5100

Interior Lighting BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

26 7400

Electrical Communications Systems BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

27 - Communications 27 0010

Basic Communications Requirements BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

27 0020

Contractor Qualifications BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

27 0030

Bidding BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

27 0040

Warranty BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

27 0050

Quality Assurance BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

27 0060

Training BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

27 0405

Common Work - Sleeves, Penetrations, and Firestopping BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

27 0406

Common Work - Hangers and Supports BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

27 0500

Electrical Technology - General Requirements BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

27 0533

Electrical Technology - Conduit and Boxes BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

27 1000

Communications - General Requirements BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

27 1119

Communications - Termination Equipment BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

27 1500

Communications - Horizontal Cabling BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

27 1543

Communications - Faceplates and Connectors BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

27 1619

Communications - Patch Cords BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

27 1710

Communications - Identification BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

27 1720

Communications - Testing BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

27 4000

AudioVisual - General Requirements BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

27 5000

Public Address General Requirements BCER

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

31 00 00

Earthwork JVA

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

31 25 00

Erosion and Sedimentation Controls JVA

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

31 - Earthwork

32 - Exterior Improvements 32 12 00

Flexible Paving JVA

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

32 13 00

Ridid Paving JVA

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

32 9219

Seeding DCLA

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

320190

Operation and Maintenance of Planting

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

323113

Chain Link Fences

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

Page 5 of 6

Printed on Mon Nov 3, 2025 at 09:12 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction

Number

Description

Revision

Issued Date

Received Date

Set

328400

Irrigation

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

329113

Fine Grading and Soiling Preparation

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

329223

Sodding

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

329313

Inert Ground Cover Materials

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

329350

Landscape Maintenance

1

09/12/25

09/12/25

2025-09-12 - 100% CD Set

Storm Drainage Systems JVA

0

09/12/25

09/12/25

2025-09-12 - 100% CD Set

33 - Utilities 33 40 00

Page 6 of 6

Exhibit B Assumptions and clarifications made in preparing the GMP Clarifications in preparing the amendment

Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20

K1224 BVSD - FAIRVIEW HIGH SCHOOL 1515 Greenbriar Blvd., Boulder, CO, 80305 Estimate: CD Estimate Rev. 1

PREPARED FOR:

ARCHITECT / DESIGNER:

BVSD

MOA Architecture

DATE PRINTED: 10/29/2025

Page 1 of 35

Clarifications Report General Clarifications - Any deviation from the prime contract terms may result in different costs and pricing. - Any delays or cost impacts due to pandemics have not been included in the estimate. - Prevailing wages have not been included. - An escalation allowance has not been included. - This is an estimate for the cost of construction, no land fees, architectural fees, legal fees, land development fees, tap fees, etc. have been included. - Sales tax has not been included. - A&P excludes any delegated design that is not listed in the plans or specifications.

Items by Others - All independent testing and inspections, including commissioning - Televisions - Residential Equipment (AP included ranges listed on the plan set) - Land Costs, Legal Fees, or Tap Fees - Architectural and Engineering Fees - Technology – Servers, computers, phones, etc. - Owner contingency - All fees associated with utilities will be paid for by the owner (water, electric, gas) - Any expenses associated with dry utilities and getting them to the site (cable, fiber, power and gas) - Removal or working with hazardous materials, including asbestos and lead abatement as defined by OSHA. - All moving costs - All artwork - purchasing, moving, and installation - Technology - Computers, Servers, phones, etc. – purchasing, moving and installation - Furniture, Desks, chairs, tables, moveable casework – purchasing, moving and installation - Audio / Visual Projectors, Projection Screens, Smart Boards (that are not specifically called out in the plans)

Documents - Drawings dated 09/12/2025 - Specifications dated 09/12/2025 - Addenda 1 dated 09/25/2025 - Addenda 2 dated 10/01/2025 - ACM Map (provided by BVSD) dated 9/23/25

B Shell - An allowance of $10K has been included for up to four (4) curb extensions where existing curbs may not meet minimum height requirements after reroofing.

- An allowance of $20K has been included to address localized roof ponding & drainage corrections. This allowance is intended to cover

limited cricketing, tapered insulation, or minor rework in select areas (approximately 3,700 SF identified as “concerning”) where ponding is

DATE PRINTED: 11/4/2025

B Shell limited cricketing, tapered insulation, or minor rework in select areas (approximately 3,700 SF identified as “concerning”) where ponding is observed.

- One water spray test is include for the entirity window replacement. - Snow removal from roof is not included. - Vacuum & removal of loose gravel from the existing roof surface is included. Cleaning or washing gravel for reuse is not included.

C Interiors - Our sprinkler pricing is contingent on as-builts of the current system being provided by BVSD.

D Services - Alternate 9 - We have assumed it is necessary to turn up and protect sprinkler heads. - An allowance of $32.5K included for cleaning up wires above ceilings with replaced lights to pass above ceiling inspections. - An allowance of 80K per each is included for refurbishing (2) existing RTU's, RTU-904 & RTU-201. Further discussion needs to occur to

define scope. Cleaning of existing diffusers as specifically noted in General Note 8 on Sheets A-111 & A-112 is included in this scope. General cleaning, wiping down, of existing MEP equipment, grilles, or registers (GRDs) beyond that note is excluded from this scope of work

- Fire alarm replacement product was included as Mircom. Bronco has included extra devices past the plans to create a complete system. - Per BVSD & drawings, no additional raceways for security cameras have been included. - Replacing roof drains is not included. Only the strainers are included to be replaced.

E Equipment and Furnishings - Alternate 7 - Structural & foundation modifications have not been included for the new walls at the softball dugouts. - An allowance of $17K has been included for the furnishing & installation of structural supports & hangers required to suspend new ductwork from the existing gym structure.

- Epoxy doors at the cabinets have been priced as laminate. It is not common to have epoxy doors on casework as shown. - The lockable data cabinet per 4/A-415 has been included in base bid.

F Special Construction and Demolition - An allowance of $70K has been included for shoring/access for gym mechanical & structural work.

G Site Preparation - 30 Day Maintenance is include at new sod & turf seed areas. Mowing & trimming of seeded areas is not included at Native Seed areas. - Adding or upgrading the irrigation controller is not included. Existing controller is figured to have capacity to accomodate new irrigation. - Imported topsoil is not included. See add alternate if required. 70/30 sand/compost soil prep for the trenches that are to be seeded is

included. The sod area is at 4 CY/1,000 SF. The native seed area is at 2 CY/1,000 SF instead of 4 CY/1,000 SF so as not to promote weed infestation that could potentially strangle the desirable grasses.

- Per the specifications, an allowance of $35,230 is included to repair/replace a portion of the wood baseball outfield fence.

Z General Requirements - A site security guard has not been included.

DATE PRINTED: 11/4/2025

Z General Requirements - General protection of adjacent surfaces is included for the work shown in the plans.

DATE PRINTED: 11/4/2025

Exhibit C

Itemization ofGMP Cost Itemization of the Dollars requested for long lead equipment and material packages

Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20

797 Ventura Street, Aurora, CO 80011 Project: K1224 BVSD - Fairview High School Owner: BVSD Architect: MOA Architecture

Date: Estimator: Project SF: Duration in Months: Estimate #:

10/29/25 Karra Damiana 261,261 11.00 CD Estimate Rev. 1 Includes Alternates 5 (Tennis Court Drainage), 6 (Softball Backstop Extension), 7 (Softball Improvements), 9 (Replace ACT), 11 (Student Commons Projection Screen/Lightspeed), 12 (Library Lightspeed)

Project Summary Sheet - Estimated Cost of the Work Division #0

Procurement and Contracting Requirements

Division #1

General Requirements

Division #2 Division #3

Existing Conditions Concrete

Division #4

Masonry

Division #5

Wood, Plastics, and Composites Thermal and Moisture Protection

Division #8 Division #9

Openings Finishes

Division #10

Specialties Equipment Furnishings Special Construction Conveying Equipment Fire Suppression Plumbing

Division #23 Division #25

Heating, Ventilating and Air Conditioning Integrated Automation

Division #26

Electrical

Division #27

Difference $0 ($108,994)

$162,407

$303,551

$141,144

$56,977 $40,647

$41,116 $53,670

($15,861) $13,023

$134,085

$149,270

$15,185

$210,323

$332,833

$122,510

$1,318,248 $305,855

$1,138,701 $126,885

($179,547) ($178,970)

$889,745 $47,345

$973,212 $16,784

$83,467 ($30,561)

Metals

Division #6 Division #7

Division #11 Division #12 Division #13 Division #14 Division #21 Division #22

DD Estimate CD Estimate $371,938 $371,938 $798,378 $689,384

Communications

$13,000

$34,450

$21,450

$51,097 $0 $0 $102,155 $906,425 $977,320

$49,497 $0 $0 $150,150 $0 $3,592,743

($1,600) $0 $0 $47,995 ($906,425) $2,615,423

$0 $396,118

$0 $1,154,408

$0 $758,290

$543,207

$602,194

$58,987

$1.42

/SF

3.2% of Direct Costs

$2.64

/SF

5.9% of Direct Costs

$1.16

/SF

2.6% of Direct Costs

$0.16

/SF

0.3% of Direct Costs

$0.21

/SF

0.5% of Direct Costs

$0.57

/SF

1.3% of Direct Costs

$1.27

/SF

2.8% of Direct Costs

$4.36

/SF

9.7% of Direct Costs

$0.49

/SF

1.1% of Direct Costs

$3.73

/SF

8.3% of Direct Costs

$0.06

/SF

0.1% of Direct Costs

$0.13

/SF

0.3% of Direct Costs

$0.19

/SF

0.4% of Direct Costs

$0.00

/SF

0.0% of Direct Costs

$0.00

/SF

0.0% of Direct Costs

$0.57

/SF

1.3% of Direct Costs

$0.00

/SF

0.0% of Direct Costs

$13.75

/SF

30.6% of Direct Costs

$0.00

/SF

0.0% of Direct Costs

$4.42

/SF

9.8% of Direct Costs

$2.30

/SF

5.1% of Direct Costs

Cost Delta Comments from DD's No Change Refinement of GRs Based on Accepted Scope & Schedule Added DD Alternate 2 (RTU 1001/1002, ACCU 1001/1002) to Base Bid; Included $70K Shoring for Gym Floor for Mechanical/Structural Work; ADD ALTERNATE 5 Core Drill Holes ILO Floor Trenches Fully Grouted Walls ILO Partial at Mechanical Enclosure Added Steel Angle at Masonry Screen Wall; Added Steel Channel at Gym Wall Duct Penetrations; Added Tube Steel Column/Post at Pony Walls;Included an Allowance of 17K for Steel Reinforcement/Framing Modifications at Gym for Ductwork Suspension; ADD ALTERNATE 5 Added Additional Blocking at Roof Expansion Joints/Parapet Coping; Added Hilti Attachment of Wood Blocking at Coping; ADD ALTERNATES 7 & 11 Better Buyout; ADD ALTERNATES 5 & 6 Reduced Glazing Scope by 320 SF; Demo of Windows Moved to Division 2; ADD ALTERNATES 7 & 9 Branding Allowance Included with Division 9 Painting/Wallcovering Added Facility Fall Protection Safety Railing at Roof Not Applicable Not Applicable ADD ALTERNATE 9 Moved to Mechanical Added DD Alternate 2 (RTU 1001/1002, ACCU 1001/1002) to Base Bid; Split (2) Large Heaters into (4) Small Heaters; Added Master Mixing Valve (DMV); Added Circulation Pump; Added Balancing Requirements to (E) DW System; New Fin Tube Heater ILO Relocating (E); Int. Overhead Duct Size Increases & Rerouting; Added Supply/Return Ductwork Inside Gym & Reroute Outside Return Ductwork; Rerouting of RTU 901 Underground Gas Line; Added Turbulator to Irrigation Line; Added Natural Gas Connection to Elec. Generator; Pipe Size Changes & Additional Piping in Chem. Rm. Not Applicable Added DD Alternate 4 (North Parking Lot Lighting); Added Panel BRA Swap & Breakers for (E) Panels; Added 205 Fixtures & Controls, Emergency Lighting Circuitry & Relays; Added Alternate 2 (RTU 1001/1002 ACCU 1001/1002) to Base Bid; Added Alternate 3 (Network Equipment Cabinet) to Base Bid; Added more clock/paging devices. ADD ALTERNATES 9, 11, & 12 Added scope to clean-up the existing Main Gym Sound System; ADD ALTERNATES 11 & 12

Division #28

Electronic Safety and Security

Division #31

Earthwork

Division #32 Division #33

$1,113,279

$743,553

($369,726)

$306,882

$462,398

$155,516

$2.85

/SF

6.3% of Direct Costs

$1.77

/SF

3.9% of Direct Costs

$622,338

$767,919

$145,581

$2.94

/SF

6.5% of Direct Costs

$67,308

$4,025

($63,283)

$0.02

/SF

0.0% of Direct Costs

Subtotal

$9,435,077

$11,758,681

$2,323,604

$45.01

/SF

100.0% of Direct Costs

Utility Tap & Devel. Fees Permit Allowance Use Tax Design Contingency Estimate Contingency Construction Contingency Builders Risk Insurance Comprehensive General Liability Insurance Sub Default Insurance Performance and Payment Bond Escalation Allowance Contractors Fee Preconstruction Services

By Owner By Owner By Owner $285,465 $285,465 $342,558 $10,379 $125,604 Not Included $77,646 $342,558 $342,558 $29,924

By Owner By Owner By Owner $0 $0 $352,760 $14,202 $142,021 Not Included $87,795 $0 $525,637 $29,924

$0.00

/SF

$0.00

/SF

0.00% of Project

$0.00

/SF

0.00% of Project

$0.00

/SF

0.00% of Project

$0.00

/SF

0.00% of Project

$1.35

/SF

3.00% of Subtotal

$0.05

/SF

0.11% of Project

$0.54

/SF

1.10% of Project

$11,277,234

$12,911,020

Exterior Improvements Utilities

($285,465) ($285,465) $10,202 $3,823 $16,417

$0.00

/SF

0.00% of Costs

$10,149 ($342,558) $183,079 $0

$0.34

/SF

0.68% of Project

$0.00

/SF

0.00% of Project

$2.01

/SF

4.34% of Subtotal + Contingency

$0.11

/SF

$1,633,786

$49.42

/SF

Estimated Cost of Construction

CD Estimate Rev. 1 Base Contract Amendment 1 Amendment 2

$29,924.00 $2,156,476.37 $10,724,619.63

100.0% of Project

Bronco Carried a Plug Number at DDs to Generally Account for the Scope. At CDs, Bronco Completed a Full Design, & the Cost Decreased Accordingly. Includes Utilities; ADD ALTERNATES 5 & 6 Added Alternate 4 (North Parking Lot Lighting) - Asphalt/Concrete Removal & Patchback; Added Asphalt/Concrete Patchback at Irrigation Improvements; ADD ALTERANTES 5, 6, & 7 Moved to Earthwork

Dropped to 0% from 2.5% Dropped to 0% from 2.5%

Dropped to 0% from 3%

Detail Report DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS

DETAILED COST: Building 00 Procurement and Contracting Requirements

$371,938

00 72 00 AIA General Conditions 00100 General conditions of the contract

$371,938 1.00 ls

371,938.00

Subtotal 00 72 00 AIA General Conditions

$371,938 $371,938

Subtotal 00 Procurement and Contracting Requirements

$371,938

01 General Requirements

$689,384

01 32 00 Construction Progress Documentation

$6,050

01100 Video Monitoring and documentation 01140 Drone Service

Per RFP Response

Not Included 11.00 mo

550.00

Subtotal 01 32 00 Construction Progress Documentation

$6,050 $6,050

01 33 00 Submittal Procedures

$0

01110 Delivery Costs / Messenger Services

Included

01130 Reproduction Costs

Included

01170 Sustainability Project Requirements

Not Included

Subtotal 01 33 00 Submittal Procedures

$0

01 35 53 Security Procedures 01160 Site Security Cameras and Monitoring

$7,975 11.00 mo

725.00

$7,975

Subtotal 01 35 53 Security Procedures

$7,975

01 45 00 Quality Control

$71,500

01200 Independent testing

Not Included

01210 Soil compaction tests

Not Included

01220 Concrete tests

Not Included

01230 Steel weld test / inspections

Not Included

01240 Contractor Quality Control - FE

11.00 mo

6,500.00

$71,500

01250 Field Quality Control procedures

Included

01260 3rd Party envelope consultant

Not Included

Subtotal 01 45 00 Quality Control

$71,500

01 51 00 Temporary Facilities

$390,309

01270 Temporary electricity - jobsite

DATE PRINTED: 10/29/2025

By Owner

Page 7 of 35

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS

01280 Generators 36kw

Not Included

01290 Fuel for Generator (full load)

Not Included

01300 Generator setup / and Containment

Not Included

01310 Temporary Fire Protection

11.00 mo

432.84

$4,761

01330 Temp Heating Equipment & Labor

Not Included

01340 Temp Heating Fuel

Not Included

01350 Temporary building enclosure for temp heating

Not Included

01360 Temporary lighting

General lighting by EC

01370 Temporary Water

By Owner

01380 Sanitary Facilities

11.00 mo

1,200.00

$13,200

For Subcontractors

01390 Temporary Elevators

Not Included

01400 Temporary Hoists

Not Included

01410 Gradall for Jobsite

11.00 mo

13,500.00

$148,500

01420 Bobcat & Operator for Jobsite

11.00 mo

11,950.00

$131,450

2,650.00 gal

5.00

$13,250

01430 Fuel for equipment 01440 Temporary Cranes

By Division

01450 Temporary scaffolding and platforms

By Division

01460 Temporary Stairs and Ramps

Not Included

01470 Temporary Swing Staging

Not Included

01480 Temporary Access Roads

Not Included

01490 Weather Conditions

4.00 mo

3,228.00

$12,912

Allowance

01500 Haul Routes

By Earthworker

01510 Temporary Parking Areas

By Earthworker

01520 Temporary Air & Noise Barriers

Not Included

01540 Temporary Barricades

By Division 16.00 mo

650.00

$10,400

01620 Technology for DCOW Staff

8,500.00 hr

4.72

$40,160

01620 Temporary interior signage

261,261.00 sf

0.06

$15,676

01560 Temporary Connex(s)

Subtotal 01 51 00 Temporary Facilities

$390,309

01 70 00 Execution and Closeout

$0

01720 Construction Surveying

By Trade

01730 Protection of Adjacent Construction

By Division

Subtotal 01 70 00 Execution and Closeout

$0

01 74 00 Cleaning 01630 Progress Cleaning

DATE PRINTED: 10/29/2025

$213,550 2,873,871.00 sf

0.04

$110,165

Page 8 of 35

DESCRIPTION 01710 Final Clean Building

QTY UOM UNIT PRICE 261,261.00 sf

0.40

Subtotal 01 74 00 Cleaning

TOTAL COST

NOTES / COMMENTS

$103,385 $213,550

01 90 00 Life Cycle Activities

$0

01740 Substructure Commissioning

Not Included

01750 Structure commissioning

Not Included

01760 Exterior enclosure commissioning

Not Included

01770 Roofing Commissioning

Not Included

01780 Systems Commissioning

Not Included

Subtotal 01 90 00 Life Cycle Activities

$0

Subtotal 01 General Requirements

$689,384

02 Existing Conditions

$276,139

02 41 00 Demolition

$276,139

02300 ACM Review - Scissor Lift

1.00 ea

979.00

$979

02300 Demo - SUB

1.00 sub

147,269.00

$147,269

02300 Demo flooring finishes

Included

02300 Remove existing DFH

Included

02300 Remove teachers desk

Included

02302 Demo existing gyp partitions

Included

02302 Demo existing wood framed platform in the NW floor area

Included

02302 Demolish existing casework

Included

02303 Demo ACT & Grid

Included

02304 Remove Wood Door & Transom Panel & Hardware - Salvage

Included

02306 GPR & Core

20.00 ea

150.00

$3,000

02310 Remove exist appliance - salvage

Included

02411 Removal of Existing Windows 02411 Remove Housekeeping Pads 02427 Sawcut & Demo Concrete Roof Deck for New General Exhaust Fan Ducting

Included 1.00 ea

1,341.27

$1,341

02430 MEP Haul Off 02431 Protect Gym Floor for Mechanical Work 02433 Shoring/Access for Gym Mechanical/Structural Work

Included 14,280.00 sf 1.00 allow

3.75

$53,550

70,000.00

$70,000

Allowance

02435 Remove and preserve cord reels

Included

02435 Sawcut & Demo CMU Wall for New General Exhaust Fan Ducting

Included

DATE PRINTED: 10/29/2025

Page 9 of 35

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS

02435 Sawcut 3x3 Openings for Crawlspace Access in Computer Room

Included

02437 Remove mechanical unit supporting steel

Included

Subtotal 02 41 00 Demolition

$276,139

Subtotal 02 Existing Conditions

$276,139

03 Concrete

$41,116

03 35 00 Concrete Finishing

$5,631

03351 Form, Place & Finish Housekeeping Pad (Boiler Rm)

w/ Div. 32 Site Concrete

03353 Concrete Infill @ Floor Openings - 4" Thick x 36" Wide / #3 ep dwls @ 18" (CTE Computer 225)

8.00 lf

525.00

$4,200

03355 Grout Patches @ Plumbing Core Drill Holes (Chemistry 408)

30.00 ea

23.84

$715

03357 Grout Patches @ Conduit Core Drill Holes (CTE Computer 225)

54.00 ea

13.25

$715

Subtotal 03 35 00 Concrete Finishing

$5,631

03 35 43 Polished Concrete Finishing 03510 PC-1 Polished concrete 03511 >Power Requirements 208/3 Phase 50 amp Generator

$35,485 3,816.00 sf

8.91

$33,985

1.00 wk

1,500.00

$1,500

Subtotal 03 35 43 Polished Concrete Finishing

$35,485

Subtotal 03 Concrete

$41,116

05 Metals

$45,600

05 50 00 Metal Fabrications

$45,600

05517 Steel Channel at Gym Wall Duct Penetrations

Included

05519 Tube Steel Column/Posts, at Pony Walls (CTE Computer 225)

Included

05521 Steel Angle Reinforcement/Framing Modifications Around EF-423

Included

05523 Steel Angle Reinforcement/Framing Modifications Around ACCU-1002

Included

05525 Steel Angle Reinforcement/Framing Modifications Around ACCU-1001 05527 Steel Angle Reinforcement/Framing Modifications Around RTU-1001/1002

1.00 ls

4,000.00

$4,000 Not Included

05529 Steel Angle Reinforcement/Framing Modifications at Exterior Window Heads (Windows B,C,D)

Included

05531 Steel Angle Reinforcement/Framing Modifications at Exterior Window Sills (Windows

Included

DATE PRINTED: 10/29/2025

Page 10 of 35

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS

Allowance

B,D) 05533 Steel Reinforcement/Framing Modifications at Gym for Ductwork Suspension

1.00 allow

17,000.00

$17,000

05537 AP Steel Labor & Coordination

6.00 wk

4,100.00

$24,600

Subtotal 05 50 00 Metal Fabrications

$45,600

Subtotal 05 Metals

$45,600

06 Woods, Plastics and Composites

$271,691

06 10 10 Rough Carpentry 06109 Blocking for Projector

$130,835 1.00 ls

2,002.00

$2,002

06109 Wood Blocking at Re-Roof Locations - Labor

See Below

06111 >RTU Curb on Existing BUR Roof (A3/A-361)

175.00 lf

9.67

$1,692

06113 >Roof Expansion Joint (A4/A-361)

75.00 lf

46.14

$3,461

06115 >Exhaust Fan Curb on Existing BUR Roof (B3/A361)

15.00 lf

10.25

$154

1,420.00 lf

42.30

$60,065

06117 >Parapet Coping (C1/A-361) 06119 >>Penetrating Radar to Identify Steel Reinforcing in Precast Wall Panel 06121 >Storefront Sill at Clerestory Window (D3/A-361)

w/ Div. 7 Flashing 52.00 lf

20.00

$1,040

06123 Wood Blocking at Re-Roof Locations - Material

See Below 1,420.00 lf

0.83

$1,176

06127 >Dimensional Lumber, 2x6 (A3, A4, B3/A-361)

490.00 lf

2.08

$1,020

06129 >Dimensional Lumber, 2x8 (D3/A-361)

100.00 lf

2.80

$280

06131 >Dimensional Lumber, 2x10 (C1/A-361)

1,420.00 lf

4.14

$5,880

06133 >Dimensional Lumber, 2x12 (C1/A-361)

150.00 lf

5.87

$880

2,189.00 sf

1.91

$4,180

781.00 ea

35.00

$27,335

06125 >Dimensional Lumber, 1x4 (C1/A-361)

06135 >Plywood, 1/2" (C1/A-361) 06137 >Hilti HAS, 24" OC (C1/A-361)

Alternate 11

06139 >>Hilti HIT-HY 270 Cartridged (C1/A-361)

Included

06141 >>Epoxy (C1/A-361)

Included 8,624.00 lf

1.00

$8,624

06145 Wood for Temporary Windows - Labor

734.00 sf

5.03

$3,692

06147 >Dimensional Lumber, 2x6

658.00 lf

2.08

$1,370

06149 >Plywood, 1/2"

734.00 sf

1.91

$1,402

06151 >Fasteners/Adhesive

658.00 lf

1.00

$658

2,162.77 sf

2.74

$5,926

06143 >Fasteners/Adhesive

06152 Interior Rough Carpentry Subtotal 06 10 10 Rough Carpentry

$130,835

06 22 00 Finish Carpentry

$140,856

DATE PRINTED: 10/29/2025

Page 11 of 35

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

06218 Custom Stainless Shelving w/ Integrated Backsplash 06218 Finish Casework - SUB

NOTES / COMMENTS Included

1.00 sub

139,856.00

$139,856

06219 Solid shelving ILO Wire shelving

Not Included

06220 New SSC-1 Top & Brackets

Included

06220 New SSC-1 Tops - wall mounted

Not Included

06220 PL1 - Base Cabinets (No Epoxy Doors Available)

Included

06220 Wall Mounted Standards and Shelving

Included

06221 EPC-1 Countertop w/ Splash

Included

06221 New base drawers replaced where removed

Not Included

06222 PL2 - Wall Cabinets (w/ Epoxy Doors)

Included

06223 1" Epoxy Pegboard

Included

06224 PL2 - Tall Cabinets

Included

06225 Relocated fume hood

Included

06226 Relocated eye wash station

Included

06285 Wood transom panel

w/ Div 8

06375 SS Wall Caps @ Computer Lab Knee Walls

Included

06376 Simulated Stone Sill at Window Type Q

Included

06495 Protect casework after installation

1.00 ls

500.00

$500

06500 Caulk casework/countertops

1.00 ls

500.00

$500

Subtotal 06 22 00 Finish Carpentry

$140,856

Subtotal 06 Woods, Plastics and Composites

$271,691

07 Thermal and Moisture Protection

$1,124,002

07 20 00 Building Insulation

$0

07213 Glass Fiber Batt Insulation - Unfaced in Flutes Behind Roof Sheathing Board (Details A1,A2,B2/A-361)

w/ Div. 7 Roofing

Subtotal 07 20 00 Building Insulation

$0

07 53 23 Roofing & Roof Insulation

$1,101,047

07301 EPDM Roof at Roof Decks 1 Through 6 - SUB

1.00 sub

07302 > Roof Coring Investigation

1.00 ls

1,040,711.45

$1,040,711

3,160.00

$3,160

07303 > Removal Existing Surface Gravel on Built-Up Roof Assembly

Included

07305 >> Transport to BVSD Facilities for Owner Use (6500 Arapahoe Road)

Included

07307 > Remove & Dispose Existing Wall & Curb Flashings

Included

DATE PRINTED: 10/29/2025

Page 12 of 35

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS

07309 > Sawcut Existing Membrane at 10' O.C.

Included

07311 > Remove/Reinstall Existing Dome Solatubes per C2/A-361, Keynote 172

Included

07313 > Remove/Reinstall Existing Exhaust Fans per C3/A-361, Keynote 173

Included

07315 > Rooftop Curbs Extensions 07318 > Roofing Ponding Correction w/ Tapering or Insulation

4.00 ea

2,500.00

$10,000

Allowance

3,700.00 sf

5.41

$20,000

Allowance

07319 > Install Polyisocyanurate Board Insulation, Mechanically Fastened

Included

07321 > Install Tapered Insulation Sumps 4' in Each Direction from All Roof Drains in the Roof Work Areas

Included

07323 > Install DensDeck Prime Cover Board Set-in Low-rise Adhesive

Included

07325 >> Install DensDeck Prime Cover Board Set-in Low-rise Adhesive at Parapet Wall (Details A1, A2, B1, B2,C1,C2,C3,D2,D3/A-361)

Included

07327 > Supply/ Install New Cast Iron Roof Drain Strainers per Sheet Keynote 181 & D1/A-361

w/ Div. 22 Plumbing

07329 > Supply/ Adhere 60 Mil EPDM Membrane, Black

Included

07331 > Supply/Install Walkway Pads per Reference Keynotes 07 5300.10

Included

07333 > Supply/ Install Grease Containment Assembly per Reference Keynotes 07 5300.23

Included

07335 > Provide 20 Year Warranty

Included

07337 Repair Existing EPDM Expansion Joint Splices per Sheet A-121, Keynote 183

Included

07339 Roof Patch at New Exhaust Fan, EF-423H per Sheet A-121, Keynote 182, Detail B3/A-361

Included

07341 Roof Patches at New Rooftop Units, RTU1001/1002, ACCU-1001/1002 per Sheet A-121, Keynote 185, Detail A3/A-361

Included

07343 Roof Patch at New Concentric Vent Stack/Hot Stack per Sheet A-121, Keynote 80, Detail B4/A361

Included

07345 Roof Cleanup

63,320.00 sf

0.05

$3,166

07347 Facility Fall Protection - Safety Rail (Posts & Railing) per Sheet A-121, Keyonte 11 8129 07349 Safety Measures for Roof Work Perimeter/Openings 07351 Exterior Scaffold Stair Tower

w/ Div. 11 Facility Maintenance Equipment 802.00 lf 4.00 mo

5.00

$4,010

5,000.00

$20,000

07353 Hoisting for Roofing Materials

Included

07355 Snow Removal for Roof Work

Not Included

Subtotal 07 53 23 Roofing & Roof Insulation

DATE PRINTED: 10/29/2025

$1,101,047

Page 13 of 35

DESCRIPTION

QTY UOM UNIT PRICE

07 60 00 Flashing & Sheet Metal

TOTAL COST

NOTES / COMMENTS

$22,295

07601 Flashing - SUB

w/ Div. 7 Roofing

07603 >>Sawcut Existing Fluted Precast Wall Panel

Included

07603 >Flashing at Fluted Precast Wall Panel per Sheet A-121, A1 & A2/A-361

Included

07605 >>>Penetrating Radar to Identify Steel Reinforcing in Precast Wall Panel, GPR

1.00 sub

22,295.00

$22,295

07607 >Coping Flashing at Roof Parapet Detail per B1/A-361

Included

07609 >Flashing Around Existing Mechanical Units per Sheet A-121, Detail D2/A-361

Included

07611 >Flashing Around New Fume Hood Exhaust Fan, EF-423H per Sheet A-121, Keynote 182, Detail B3/A-361

Included

07613 >Flashing Around New Rooftop Units, RTU1001/1002, ACCU-1001/1002 per Sheet A-121, Keynote 185, Detail A3/A-361

Included

07615 >Flashing Around New Concentric Vent Stack/Hot Stack per Sheet A-121, Keynote 80, Detail B4/A-361

Included

07617 >Flashing at Storefront Sill at Clerestory Window - Type Q

Included

Subtotal 07 60 00 Flashing & Sheet Metal

$22,295

07 71 00 Roof Specialties & Accessories

$0

07711 Roof Curbs for RTU-1001/1002, ACC-1001/1002

w/ Div. 23 Mechanical

07713 Expansion Joint Cover per Details A2, A4, & B2/A-361

w/ Div 7 Roofing

Subtotal 07 71 00 Roof Specialties & Accessories

$0

07 92 00 Joint Sealants

$660

07903 Joint Sealant Continuous Along Joint at Existing Fluted Precast Wall (Roof) (Ref. A1/A-361) 07905 Joint Sealant at Exterior Duct Penetrations

w/ Div 7 Roofing 44.00 lf

15.00

Subtotal 07 92 00 Joint Sealants

$660

Subtotal 07 Thermal and Moisture Protection

$1,124,002

08 Openings

$126,885

08 10 00 Doors and Frames 08015 Doors, Frames and Hardware - SUB

$660

$29,762 1.00 sub

26,000.00

$26,000

08015 HM Frame - single 3'-0" x 7'-0"

Included

08035 Doors, Frames and Hardware Install

6.00 ea

552.00

$3,312

08295 Misc welding, grinding, bondo

3.00 ea

150.00

$450

DATE PRINTED: 10/29/2025

Page 14 of 35

DESCRIPTION

QTY UOM UNIT PRICE

Subtotal 08 10 00 Doors and Frames

TOTAL COST

NOTES / COMMENTS

$29,762

08 14 00 Wood Doors

$0

08070 3'-0" x 7'-0" wd door

Included

08071 Drilled Raceways

Included

08071 Wood Transom Panel w/ Lite Kit

Included

Subtotal 08 14 00 Wood Doors

$0

08 41 13 Aluminum Entrances

$96,123

08441 Remove Existing Exterior Storefront 08443 Glazing - SUB

w/ Div. 2 Demolition 1.00 sub

84,861.08

$84,861

08445 Exterior Storefront - Kawneer Thermally Broken, 2" x 4-1/2", Class 1 Natural Anodized, Type IG-1 - Insulating Glass, 1" Thick (Type B)

Included

08447 Exterior Storefront - Kawneer Thermally Broken, 2" x 4-1/2", Class 1 Natural Anodized, Type IG-1 - Insulating Glass, 1" Thick (Type C)

Included

08449 Exterior Storefront - Kawneer Thermally Broken, 2" x 4-1/2", Class 1 Natural Anodized, Type IG-1 - Insulating Glass, 1" Thick (Type D)

Included

08451 Exterior Storefront - Kawneer Thermally Broken, 2" x 4-1/2", Class 1 Natural Anodized, Type IG-1 - Insulating Glass, 1" Thick (Type Q)

Included

08453 Break Metal at Window Type Q per Detail 5/A601

Included

08455 Pre-Finished Galvanized Steel Sheet Metal (Sill Flashing at Types B & D per Detail 1/A-601)

Included

08457 Pre-Finished Galvanized Steel Sheet Metal (Sill Flashing at Clerestory Window Type Q per Detail D3/A-361) - LABOR ONLY (Supplied by Roofer.)

Included

08459 Perimeter Backer Rod & Sealants - 2 Beads/Lines (1,2,3,4,6,7/A-601)

Included

08461 Grout (E) Indentation at Removed (E) Window Sill (Type C)

44.00 lf

37.23

$1,638

08463 Water-Spray Test Per 08 4313 3.04

1.00 ea

8,155.93

$8,156

734.00 sf

2.00

$1,468

08465 Final Clean Glass Subtotal 08 41 13 Aluminum Entrances

$96,123

08 70 00 Hardware

$1,000

08755 Replace door hardware per schedule 08875 Misc. missing hardware Subtotal 08 70 00 Hardware 08 80 00 Glazing

DATE PRINTED: 10/29/2025

Included 1.00 ls

1,000.00

$1,000 $1,000 $0

Page 15 of 35

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

08813 Decorative Plastic Film (WF-1 - Sheet A-401, A700) - 3M Dusted & Frosted, Smooth Frosted Crystal White, VE14704

Included

Subtotal 08 80 00 Glazing

$0

Subtotal 08 Openings

$126,885

09 Finishes

$955,912

09 21 16 Gypsum Board Assemblies 09000 Drywall - SUB

$133,800 1.00 sub

83,800.00

$83,800

09069 FR3 - Furring Wall 09069 Patch & Repair Walls

NOTES / COMMENTS

Included 1.00 ls

50,000.00

$50,000

09069 S4.1 - Shaft Wall, to Deck, Shaft Wall Core Board 1 side, Gyp Other

Included

09070 Gyp Ceiling

Included

09070 Level 5 Finish at WC Locations

Included

09070 P3 - Knee wall for outlets

Included

09070 P3 - Wall Partition, To Deck, 1 layer Gyp both sides

Included

09070 P3a - Wall Partition, To Deck, 1 layer Gyp both sides, Acoustic

Included

09213 Patch Drywall Where New Receptacles Have Been Cut into Drywall at Commons

Included

09215 New 1-HR Fire Rated Shaft Wall for New Exhaust Fan Ducting for Fume Hood (Room 408)

Included Above

09217 DensDeck Prime Cover Board Set-in Low-rise Adhesive at Parapet Wall (Details A1, A2, B1, B2,C1,C2,C3,D2,D3/A-361)

w/ Div. 7 Roofing

09219 >Glass Fiber Batt Insulation - Unfaced in Flutes Behind Roof Sheathing Board (Details A1,A2,B2/A-361)

w/ Div. 7 Roofing

09221 Patch & Repair Rigid Insulation & Gyp Board Below Window Sill

Included

09223 Additional Layer of Drywall Around Window Sill

Included

Subtotal 09 21 16 Gypsum Board Assemblies

$133,800

09 24 00 Cement Plastering 09241 Patch & Repair Cement Plaster

$24,210 1,614.00 sf

15.00

$24,210

Subtotal 09 24 00 Cement Plastering

$24,210

09 51 00 Acoustical Ceilings

$223,362

09251 C1 - 2x4 ACT 09251 C1 - 2x4 ACT

DATE PRINTED: 10/29/2025

Included 11,087.00 sf

5.52

$61,200

Alternate 9

Page 16 of 35

DESCRIPTION 09251 Ceilings & Acoustic - SUB

QTY UOM UNIT PRICE 1.00 sub

134,000.00

TOTAL COST

NOTES / COMMENTS

$134,000

09252 C2 - 2x4 ACT vinyl faced

Included

09253 C3 - 2x2 ACT

Included

09511 ACT Tile/Grid Repair due to Window Replacement

Included

09515 ACT Tile/Grid - Demo & Reinstall due to MEP Changes

3,587.00 sf

7.85

Subtotal 09 51 00 Acoustical Ceilings

$223,362

09 65 00 Resilient Flooring 09337 Flooring - SUB

$28,162

$387,412 1.00 sub

376,292.64

$376,293

09337 LVT - 1

Included

09337 Stair Nosing

Included

09461 New 4" base

Included 6.00 ea

115.00

$690

09613 Floor prep and joint grinding

11,790.00 sf

0.79

$9,314

09637 Floor protection

3,718.00 sf

0.30

$1,115

09585 Moisture tests (1/1000sf)

Subtotal 09 65 00 Resilient Flooring

$387,412

09 68 00 Carpet

$0

09413 CPT - 1 - Shaw, 18"x36"

Included

09413 CPT - 1,2,3 @ Library

Included

09414 Accent CPT-2

Included

09416 CPT - 3

Included

Subtotal 09 68 00 Carpet

$0

09 72 00 Wall Coverings

$0

09720 WC-1

Included

Subtotal 09 72 00 Wall Coverings

$0

09 80 00 Acoustic Treatment

$0

09717 AP-1 Acoustic Wall Panels (AV Room)

Included

09717 AP-1B Acoustic Wall Panels (AV Room)

Included

09717 AP-1C Acoustic Wall Panels (AV Room)

Included

09717 AP-1D Acoustic Wall Panels (AV Room)

Included

Subtotal 09 80 00 Acoustic Treatment

$0

09 90 00 Painting and Coating 09700 Branding Graphic Allowance

DATE PRINTED: 10/29/2025

$187,128 1.00 allow

50,000.00

$50,000

Allowance

Page 17 of 35

DESCRIPTION 09700 Paint - SUB

QTY UOM UNIT PRICE 1.00 sub

136,198.00

TOTAL COST

NOTES / COMMENTS

$136,198

09720 Accent wall paint refresh

Included

09720 Prep and paint all walls

Included

09821 Touch up doors & frames

Included

09825 Final touch up at completion of project

3,718.00 sf

0.25

$930

09905 Graffiti Seal at RTU Enclosure

Included

09905 Paint Additional Layer of Drywall Around Window Sill

Included

09907 Paint Patched & Repaired Exterior Plaster

Included

09908 Paint Exposed Ductwork at Gym

Included

Subtotal 09 90 00 Painting and Coating

$187,128

Subtotal 09 Finishes

$955,912

10 Specialties

$16,784

10 11 16 Marker Boards

$5,447

10030 4x4 Marker Board

Included

10030 4x6 Marker Board

Included

10030 Specialties - SUB

1.00 sub

5,447.00

$5,447

Subtotal 10 11 16 Marker Boards

$5,447

10 14 00 Signage

$11,337

10000 Branding Allowance

w/ Div. 9 Painting

10001 Sign Type G Shelter in Place - Allowance

1.00 allow

10,000.00

$10,000

10001 Signage - SUB

1.00 sub

1,337.00

$1,337

Allowance Per Spec. 01 2100 Allowances

10002 Door Number Tags

Included

10003 Office/Classroom ADA Signs

Included

Subtotal 10 14 00 Signage 10 28 00 Toilet & Bath Accessories

$11,337 $0

10360 TA-1 - Soap dispenser

Included

10400 TA-2 - Paper towel dispenser

Included

Subtotal 10 28 00 Toilet & Bath Accessories

$0

10 44 00 Fire Protection Specialties

$0

10685 Fire Protection Specialties Subtotal 10 44 00 Fire Protection Specialties Subtotal 10 Specialties

DATE PRINTED: 10/29/2025

Included $0 $16,784

Page 18 of 35

DESCRIPTION

QTY UOM UNIT PRICE

11 Equipment

$11,050 6.00 ea

1,841.67

Subtotal 11 30 00 Residential Equipment (GE Equipment)

$11,050 $11,050

11 52 00 Audio-Visual Equipment

$0

11205 Projection Screen Unit - Front Projection Type

w/ Div. 27

Subtotal 11 52 00 Audio-Visual Equipment

$0

11 53 00 Laboratory Equipment

$0

11535 Relocated Fume Hood

w/ Div 6

Subtotal 11 53 00 Laboratory Equipment

$0

11 81 00 Facility Maintenance Equipment 11810 Facility Fall Protection - Safety Rail (Posts and Railing)

$23,400 1.00 ls

23,400.00

Subtotal 11 81 00 Facility Maintenance Equipment

$23,400 $23,400

Subtotal 11 Equipment

$34,450

12 Furnishings

$49,497

12 24 00 Window Shades 12241 Window Shade Treatment, Mecho Shade, Ecoveil 1550 Series, Grey (BE 2)

$49,497 1,053.00 sf

47.01

Subtotal 12 24 00 Window Shades

$49,497 $49,497

Subtotal 12 Furnishings

$49,497

21 Fire Suppression

$150,150

21 00 00 Fire Suppression

$150,150

00000 Fire Suppression - SUB

1.00 sub

47,995.00

$47,995

09253 Sprinkler - SUB

1.00 sub

102,155.00

$102,155

09253 Sprinkler Head Adjustment Subtotal 21 00 00 Fire Suppression Subtotal 21 Fire Suppression 22 Plumbing 22 00 00 Plumbing

NOTES / COMMENTS

$34,450

11 30 00 Residential Equipment (GE Equipment) 11000 Electric Range

TOTAL COST

Alternate 9

Included $150,150 $150,150 $0 $0

22001 Plumbing - SUB

w/ Div. 23 Mechanical

DATE PRINTED: 10/29/2025

Page 19 of 35

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS

22011 Plumbing Demo

Included

22013 Plumbing Piping Systems (Domestic Water, Waste, Lab Waste, Vent)

Included

22015 Plumbing Equipment

See Below

22017 >Emergency Gas Shutoff Station

Included

22019 >Emergency Eyewash Station (Relocate)

Included

22021 >Fixtures

See Below

22023 >>Sinks, S-1 (Culinary Arts 317)

Included

22025 >>Sinks, S-2 (Chemistry 408)

Included

22027 >>Sink, S-3 (Culinary Arts 317)

Included

22029 >>Sinks, S-4 (Chemistry 408/421/422)

Included

22031 >>Garbage Disposals, GD-1

Included

22033 >>Gas Turrets, Wall Mount, GT-1

Included

22035 >>Gas Turrets, Deck Mount, GT-2

Included

22037 >>Floor Drain, FD-1 (Eye Wash Station)

Included

22038 >>Roof Drains, RD-1

Not Included

22039 >Gas Domestic Hot Water Heaters, DWH

Included

22045 >Digital Mixing Valve, DMV-1

Included

22047 >Thermostatic Mixing Valve, TMV-1 (Eye Wash Station)

Included

22049 >Domestic Circulating Pump, DCP

Included

22051 >Domestic Water Expansion Tank, DET-1

Included

22053 >Wall Cleanouts

Included

22055 >Balance Valve Assemblies

Included

22057 Insulation, Fire Stopping/Caulking

Included

22059 Test & Balance

Included

22061 Concrete Cutting, Coring, & Xray

Included

22063 Domestic Water Chlorination

Included

22065 Pressure Testing of New Piping

Included

22067 MEP Coordination & QA/QC

w/ Div. 23 Mechanical

Subtotal 22 00 00 Plumbing

$0

Subtotal 22 Plumbing

$0

23 Heating, Ventilating and Air Conditioning

$3,592,743

23 00 00 Heating, Ventilating and Air Conditioning 23001 Mechanical - SUB 23003 Mechanical Demo

DATE PRINTED: 10/29/2025

$3,592,743 1.00 sub

3,328,883.40

$3,328,883

See Below Included

Page 20 of 35

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

23005 HVAC & Mechanical Equipment

NOTES / COMMENTS See Below

23007 >Rooftop Unit, RTU-904 (Refurbish)

1.00 allow

80,000.00

$80,000

Allowance

23009 >Rooftop Unit, RTU-201 (Refurbish)

1.00 allow

80,000.00

$80,000

Allowance

23013 >Rooftop Air Handling Unit, RTU-1001 (HW/DX Heat Pump)

Included

23015 >Rooftop Air Handling Unit, RTU-1002 (HW/DX Heat Pump)

Included

23017 >Air Handling Unit, AHU-901 (Gas Fired)

Included

23019 >Air Cooled Condensing Unit, ACCU-1001

Included

23021 >Air Cooled Condensing Unit, ACCU-1002

Included

23023 >Fin Tube Heater, FTR-1

Included

23025 >Terminal Boxes, Variable Air Volume, VAV's

Included

23027 >Exhaust Fan, EF-423H

Included

23029 >Grilles, Registers, Diffusers, SD-1, RG-1, RG-2

Included

23031 >Hot Water Coil

Included

23033 >Smoke Damper

Included

23035 >Rooftop Solutions Grease Guard

Included

23037 Mechanical Piping (Heating Hot Water, Condensate Waste)

Included

23039 HVAC Ductwork Systems (PVC Coated Flue Hood Exhaust, Boiler Vents, Supply, Return, Exhaust)

Included

23041 Remove & Reinstall Grilles, Registers, & Diffusers

Included

23043 MEP Coordination & QA/QC

3,461,990.00 ls

0.03

Subtotal 23 00 00 Heating, Ventilating and Air Conditioning

$103,860 $3,592,743

Subtotal 23 Heating, Ventilating and Air Conditioning

$3,592,743

26 Electrical

$1,154,408

26 00 00 Electrical 26001 Electrical - SUB

$1,154,408 1.00 sub

1,069,681.22

$1,069,681

26003 >Site Lighting & Power

Included

26005 >Lighting

Included

26007 >Lighting Controls

Included

26009 >Branch Power

Included

26011 >Mechanical Equipment Connections

Included

26013 >Tele/Data Raceways

Included

26015 >Audio Visual Raceways

Included

26017 >Clock/Paging Raceways

Included

DATE PRINTED: 10/29/2025

Page 21 of 35

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS

26019 >Demolition

Included

26021 Temporary Lighting & Power

Included

26023 Fire Caulking/Fire Stopping

Included 32,500.00 allow

1.01

$32,968

293.00 ea

20.00

$5,860

1,004,866.00 ls

0.03

$30,146

26031 Re-support Electrical Above Replaced ACT Ceilings

1.00 ls

8,427.64

$8,428

Alternate 9

26033 Add Outlet for New Projector (Student Commons AV)

1.00 ea

3,987.61

$3,988

Alternate 11

26035 Add Outlet for New Lightspeed System with Media Connector (Library)

1.00 ea

3,337.38

$3,337

Alternate 12

26025 Cleaning Up Above Ceilings 26027 Remove/Reinstall Cover Plates on Electrical Devices & Light Switches 26029 MEP Coordination & QA/QC

Subtotal 26 00 00 Electrical

$1,154,408

Subtotal 26 Electrical

$1,154,408

27 Communications

$602,194

27 51 00 Distributed AV systems 27501 Upgrade Intercom/Public Address System Hybrid, New CAT6, New Classrooms & Head End - SUB

Allowance

$602,194 1.00 sub

419,945.00

$419,945

27503 >Replace All Existing Analog Cabling & Speakers in Corridor & Exterior Including Demo & Analog Cabling

Included

27505 >Exterior Speakers/Horns

Included

27507 >Electrical Scope - Rough-In Backboxes & Conduit

w/ Div. 26 Electrical

27509 Classroom Updated to Standard Teaching Wall. Adding Lightspeed Voice Reinforcement Sys (Rms 222,225,228,317,405,408,411,414,420,421,422, 425,426,430,432)

15.00 ea

2,495.20

$37,428

27511 Structural Cabling - SUB

1.00 sub

53,779.00

$53,779

27513 >Provide CAT 6 Data Jacks (Computer Room 225)

Included

27515 >Provide New Network Equipment Cabinet, Network Data Cables, Fiber to New Cabinet (Computer Room 225)

Included

27517 Audio Mixing Panel with Variety of Connectivity Options & New Wireless Microphone Connectivity (South Gym)

1.00 ls

31,471.00

$31,471

27519 >Audio Shunt for Public Address System 27521 CTE Classroom Remove/Reinstall Projector, Provide New Projection Screen & Relocate Cables & Jacks as Required

DATE PRINTED: 10/29/2025

Included 1.00 ls

7,199.00

$7,199

Page 22 of 35

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS

27523 New Ceiling Mounted Projector, New Drop Down Screen, 5 Speakers (Student Commons)

1.00 ls

47,622.00

$47,622

Alternate 11

27525 Provide Lightspeed T25 Base Staion w/ JBL Pendant Speakers (Library)

1.00 ls

4,750.00

$4,750

Alternate 12

Subtotal 27 51 00 Distributed AV systems

$602,194

Subtotal 27 Communications

$602,194

28 Electronic Safety and Security

$743,553

28 00 00 Electronic Safety and Security 28101 Fire Alarm System - Full System Replacement w/ Voice Evacuation - SUB

$743,553 1.00 sub

722,212.22

$722,212

28103 >New Intelligent, Fully Addressable Fire Alarm System

Included

28105 >Voice Evacuation Occupant Notification

Included

28107 >New FACP w/ Expansion Capability

Included

28109 >New Annunciator in Reception/Waiting Area (801A)

Included

28111 >New Smoke Detectors, Pull Stations, & Duct Detectors

Included

28113 >New Notification Appliances (Speakers, Strobes) Throughout the Building

Included

28115 >Control Modules for Interfacing with HVAC Systems (HVLS Fans)

Included

28117 >UL-Listed Central Station Monitoring

Included

28119 MEP Coordination & QA/QC

711,372.00 ls

0.03

Subtotal 28 00 00 Electronic Safety and Security

$21,341 $743,553

Subtotal 28 Electronic Safety and Security

$743,553

33 Utilities

$4,025

33 41 13 Foundation Drainage

$4,025

33411 Storm Drainage - SUB 33413 Storm Utility GPR

w/ Div. 32 Earthwork 1.00 ls

4,025.00

$4,025

33415 Core Ex. Structure for Storm Sewer

Included

33417 8” PVC Storm Sewer

Included

33419 10” PVC Storm Sewer

Included

33421 12” PVC Storm Sewer

Included

33423 24" Area Drain

Included

33425 Lower Rim of Manhole (MH) & Install Graded Lid

Included

Subtotal 33 41 13 Foundation Drainage

DATE PRINTED: 10/29/2025

$4,025

Page 23 of 35

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

Subtotal 33 Utilities

$4,025

Total Building

$10,250,471

DATE PRINTED: 10/29/2025

NOTES / COMMENTS

Page 24 of 35

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS

DETAILED COST: Site 02 Existing Conditions

$27,412

02 21 00 Surveys

$27,412

02201 Total Stations

4.00 mo

2,643.00

$10,572

02203 Survey - SUB

1.00 sub

15,840.00

$15,840

02205 Calculations & Plan Checks

Included

02207 Control Points & Sawcut

Included

02209 Grading

Included

02211 Storm Sewer

Included

02213 Irrigation Sleeves

Included

02215 Electric Offsets & Grades to Light Poles

Included

02217 Concrete Channel Drain (IS 7)

1.00 ls

1,000.00

$1,000

Alternate 5

02219 Gas Piping Offsets & Grades

Included

02221 Mechanical Enclosure Offsets & Grades

Included

02223 Concrete/Curb, Gutter, & Sidewalks

Included

02225 Concrete/Pans

Included

02227 Restaking

Included

02229 Site Improvement As-Built

Included

Subtotal 02 21 00 Surveys

$27,412

Subtotal 02 Existing Conditions

$27,412

04 Masonry

$53,670

04 20 00 Unit Masonry 04201 Masonry - SUB

$53,670 1.00 sub

53,266.91

$53,267

04203 8" Ground Face Block w/ Integral Water Repellent (Mechanical Enclosure)

Included

04205 >Concrete Stem Wall Instead of CMU Stem Wall (Mechanical Enclosure)

Not Included Per RFI Response

04209 Installation of Embed Plates (Supplied by Misc. Metals) (Mechanical Enclosure)

Included

04211 Misc Cleanup (Mechanical Enclosure)

1,222.00 sf

0.33

Subtotal 04 20 00 Unit Masonry

$403 $53,670

Subtotal 04 Masonry

$53,670

05 Metals

$103,670

05 50 00 Metal Fabrications 05503 Miscellaneous Metals - SUB

DATE PRINTED: 10/29/2025

$103,670 1.00 sub

101,082.73

$101,083

Page 25 of 35

DESCRIPTION 05505 Trench Cover, Galvanized Steel (IS 7)

QTY UOM UNIT PRICE 1.00 ea

2,587.50

TOTAL COST

NOTES / COMMENTS

$2,588

Alternate 5

05507 Steel Railing at ADA Ramp, Exterior, TnemecPrimer (Front of School Drainage Improvement)

Included

05509 >Embed Plates for Steel Railing Surface Attachment, Exterior (Front of School Drainage Improvement) [Supply Only]

Included

05511 Double Enclosure Gate, Exterior (Mechanical Enclosure)

Included

05513 >TS Gate Post to CMU Embed Plates (Mechanical Enclosure) [Supply Only]

Included

05515 Steel Angle at Masonry Screen Wall to Existing Wall, Continuous

Included

05535 Steel Reinforcement/Framing Modifications at Exterior Softball New Walls

Alternate 7 - Not Included

Subtotal 05 50 00 Metal Fabrications

$103,670

Subtotal 05 Metals

$103,670

06 Woods, Plastics and Composites

$61,142

06 10 10 Rough Carpentry 06101 Hardie Plank Siding & Trim (Softball Dugouts) (IS 9)

$31,539 1,512.00 sf

20.03

$30,288

Alternate 7 - Included w/ 09 Drywall

06103 Plywood Siding (Softball Dugouts) (IS 9) 06105 Replace Rotted Wood Fascia at Backside Only (Softball Dugouts) (IS 9)

84.00 lf

14.90

$1,252

06107 Tyvek (Softball Dugouts) (IS 9) $31,539

06 22 00 Finish Carpentry

$29,603 1.00 ls

29,603.00

Subtotal 06 22 00 Finish Carpentry

$29,603

$61,142

07 Thermal and Moisture Protection

$14,698

07 11 00 Bituminous Damproofing

$835 380.00 sf

2.20

$835

07113 Bituminous Dampproofing @ Precast Panel (Mechanical Enclosure) Subtotal 07 11 00 Bituminous Damproofing 07 20 00 Building Insulation

DATE PRINTED: 10/29/2025

Alternate 7

$29,603

Subtotal 06 Woods, Plastics and Composites

07111 Bituminous Dampproofing @ Stem Wall (Mechanical Enclosure)

Alternate 7 Alternate 7 - Included

Subtotal 06 10 10 Rough Carpentry

06000 Dugout Cubbies - MDF

Alternate 7

Included $835 $2,946

Page 26 of 35

DESCRIPTION 07211 Exterior Foundation Wall Insulation @ Precast Panel, 2" (Mechanical Enclosure)

QTY UOM UNIT PRICE 201.00 sf

14.66

TOTAL COST $2,946

Subtotal 07 20 00 Building Insulation

$2,946

07 60 00 Flashing & Sheet Metal

$4,787

07619 >Coping Flashing at Mechanical Screen Wall (20 Gage) (A1,A2,B2/AS-501) 07621 >Flashing at Softball Dugout Bottom of Wall (22 Gage) (1/AS-501)

Included 168.00 lf

28.49

Subtotal 07 60 00 Flashing & Sheet Metal

$4,787

Alternate 7

$4,787

07 92 00 Joint Sealants 07901 Joint Sealant - SUB

NOTES / COMMENTS

$6,130 1.00 sub

4,415.00

$4,415

07907 Joint Sealant Continuous Along Joint at Slab to Structure (Mechanical Enclosure)

Included

07909 Joint Sealant at Sidewalk & Slab Expansion Joints

Included

07911 Joint Sealant at Sidewalk to Chase (IS 7)

1.00 ls

1,400.00

$1,400

Alternate 5

07913 Joint Sealant at Sidewalk (IS 8)

1.00 ls

315.00

$315

Alternate 6

Subtotal 07 92 00 Joint Sealants

$6,130

Subtotal 07 Thermal and Moisture Protection

$14,698

09 Finishes

$17,300

09 21 16 Gypsum Board Assemblies 09211 Exterior 6", 16 GA Metal Stud w/ 3/4" Pressure Treated Plywood Both Sides (Softball Dugouts) (IS 9)

$13,500 756.00 sf

17.86

Subtotal 09 21 16 Gypsum Board Assemblies

$3,800 1.00 ls

3,800.00

$3,800

09903 Paint Cubbies (Softball Dugouts) (IS 9)

Alternate 7 Alternate 7 - Included

Subtotal 09 90 00 Painting and Coating

$3,800

Subtotal 09 Finishes

$17,300

31 Earthwork

$462,398

31 00 00 Earthwork

$343,913

30001 Earthwork - SUB

1.00 sub

30002 Pothole Utilities 30003 Private Locates

DATE PRINTED: 10/29/2025

Alternate 7

$13,500

09 90 00 Painting and Coating 09901 Paint Wood Trim & Underside of Dugout Ceilings (Softball Dugouts) (IS 9)

$13,500

258,855.60

$258,856

24.00 hr

641.84

$15,404

24.00 hr

961.73

$23,082

Page 27 of 35

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

30004 Construction Water

NOTES / COMMENTS Included

30005 Earthwork at Mechanical Pad for Groundmounted Air Handling Unit

See Below

30006 >Remove & Dispose Sidewalk

Included

30007 >Strip Site

Included

30008 >Export Strippings

Included

30009 >Excavate Cut to Fill

Included

30010 >Excavate Cut to Export

Included

30011 >Export Material

Included

30012 >Scarify Site 12" Depth

Included

30013 >Rough Grade Site

Included

30014 >Import & Place Class 6 Below Concrete Walk & Pad

Included

30015 >Excavate & Backfill Screen Wall

Included

30016 Earthwork for Irrigation Improvements 30019 >Protect Exist Trees & Maintain Exist Grades Around Tree Base

See Below 650.00 lf

8.35

$5,428

30020 Earthwork for Visitor Parking Lot - Concrete

See Below

30021 >Remove & Dispose Sidewalk

Included

30022 >Remove & Dispose Curb

Included

30023 >Sawcut for Demo

Included

30024 >Excavate Cut to Export

Included

30025 >Export Material

Included

30026 >Scarify Walks, 12" Depth

Included

30027 >Rough Grade Site

Included

30028 >Import & Place Class 6 Below Concrete Walk & Paving

Included

30029 Earthwork for Visitor Parking Lot - Paving

See Below

30030 >Remove & Dispose Pavement

Included

30031 >Sawcut for Demo

Included

30032 >Excavate Cut to Export

Included

30033 >Export Material

Included

30034 >Scarify Paving, 12" Depth

Included

30035 >Rough Grade Site

Included

30036 Earthwork for Front of School Drainage Improvement

See Below

30037 >Protect Exist Trees & Maintain Exist Grades Around Tree Base

364.00 lf

8.35

$3,039

30038 >Protect Exist Railing

243.00 lf

8.35

$2,029

DATE PRINTED: 10/29/2025

Page 28 of 35

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS

30039 >Remove & Dispose Sidewalk/Ribbon Curb

Included

30040 >Strip Site

Included

30041 >Export Strippings

Included

30042 >Excavate Cut to Fill

Included

30043 >Excavate Cut to Export

Included

30044 >Export Material

Included

30045 >Scarify Site, 12" Depth

Included

30046 >Rough Grade Site

Included

30047 >Import & Place Class 6 Below Concrete Walk

Included

30048 >Regrade/Finish Site to +/- .1'

Included

30049 >Respread Removed Topsoil

Included

30050 Earthwork for New Gas Line in Loading Dock Area

See Below

30051 >Sawcut for Demo

Included

30052 >Remove & Dispose Pavement

Included

30053 >Remove & Dispose Sidewalk

Included

30054 >Remove & Dispose Curb

Included

30055 >Excavate Cut to Export

Included

30056 >Export Material

Included

30057 >Scarify Paving & Walks, 12" Depth

Included

30058 >Rough Grade Site

Included

30059 >Import & Place Class 6 Below Concrete Walk

Included

30071 Earthwork for Staff Parking Lot New Lights

See Below

30073 >Sawcut for Demo

Included

30074 >Remove & Dispose Pavement

Included

30075 >Remove & Dispose Sidewalk

Included

30076 >Remove & Dispose Curb

Included

30077 >Excavate Cut to Export

Included

30078 >Export Material

Included

30079 >Scarify Paving & Walks, 12" Depth

Included

30080 >Rough Grade Site

Included

30081 >Import & Place Class 6 Below Concrete Walk

Included

30082 Earthwork at Tennis Courts (IS 7)

1.00 ls

25,890.66

$25,891

Alternate 5 - See Below

30083 >Relocate Exist Boulders to Allow Conc Channel Installation (IS 7)

4.00 ea

62.88

$252

Alternate 5

30084 >Protect Exist Tennis Fence (IS 7)

175.00 lf

8.35

$1,461

Alternate 5

30085 >Protect Exist Boulder Retaining Wall (IS 7)

42.00 lf

8.35

$351

Alternate 5

DATE PRINTED: 10/29/2025

Page 29 of 35

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS

30086 >Remove & Dispose Underdrain (IS 7)

Alternate 5 - Included

30087 >Remove & Dispose Concrete Walk (IS 7)

Alternate 5 - Included

30088 >Remove & Dispose Curb & Gutter (IS 7)

Alternate 5 - Included

30089 >Strip Site (IS 7)

Alternate 5 - Included

30090 >Export Strippings (IS 7)

Alternate 5 - Included

30091 >Scarify Site, 12" Depth (IS 7)

Alternate 5 - Included

30092 >Rough Grade Site (IS 7)

Alternate 5 - Included

30093 >Excavate & Backfill Trickle Channel (IS 7)

Alternate 5 - Included

30094 Earthwork at Softball Backstop (IS 8)

1.00 ls

8,121.24

$8,121

Alternate 6

30095 >Excavate, Remove, & Dispose Fence Posts & Footings/Caissons (IS 8)

Alternate 6 - w/ Div. 32 Fencing

30096 >Sawcut for Demo Concrete Paving/Sidewalk (IS 8)

Alternate 6 - Included

30097 >Remove & Disppose Concrete Paving/Sidewalk (IS 8)

Alternate 6 - Included

30098 >Scarify Below Concrete Walk, 12" Depth (IS 8)

Alternate 6 - Included

30099 >Furnish & Install 6" Class 6 Road Base Below Concrete Walk (IS 8)

Alternate 6 - Included

Subtotal 31 00 00 Earthwork

$343,913

31 25 00 Erosion and Sedimentation Controls 31201 Temporary Fencing (Installation/Removal/Maintenance) (Trailer Complex/Lay Down Area)

$118,485 756.00 lf

11.00

$8,316

1,521.00 lf

9.00

$13,689

31205 Temporary Fencing (Installation/Removal/Maintenance) (IS 7)

400.00 lf

9.00

$3,600

31207 Concrete Washout Area (CWA), 1.5 CY Pump Pan

36.00 ea

227.50

$8,190

31209 Concrete Washout Area (CWA), 5.5 CY Container

12.00 ea

417.50

$5,010

31211 Concrete Washout Area (CWA), 1.5 CY Pump Pan (IS 7)

6.00 ea

227.50

$1,365

31213 Area Inlet Protection (IP)

7.00 ea

740.00

$5,180

31215 Rock Socks (RS)

26.00 ea

148.00

$3,848

31217 Rock Socks (RS) (IS 7)

30.00 ea

148.00

$4,440

31219 Sediment Control Logs (SCL) (Temp. Fencing)

1,521.00 lf

4.28

$6,513

31221 Sediment Control Logs (SCL) (Temp. Fencing) (IS 7)

454.00 lf

4.28

$1,944

31223 Sediment Control Logs (SCL) (Swale, Mechanical Enclosure)

161.00 lf

4.28

$689

31225 Vehicle Tracking Control (VTC)

112.00 ea

287.51

$32,201

31203 Temporary Fencing (Installation/Removal/Maintenance)

DATE PRINTED: 10/29/2025

Alternate 5

Alternate 5

Alternate 5

Alternate 5

Page 30 of 35

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS Alternate 5

31227 Vehicle Tracking Control (VTC) (IS 7)

16.00 ea

287.51

$4,600

31229 SRM - Small Projects - 1-5 Acres

11.00 mo

900.00

$9,900

31319 Storm Water Engineering

11.00 mo

818.18

$9,000

Subtotal 31 25 00 Erosion and Sedimentation Controls

$118,485

Subtotal 31 Earthwork

$462,398

32 Exterior Improvements

$767,919

32 12 00 Flexible Paving 32001 Asphalt - SUB

$160,144 1.00 sub

147,256.00

$147,256

32003 Visitor Front Parking Lot

See Below - Included

32005 >Asphalt "T" Patch

Included

32007 >Asphalt Standard Duty Paving

Included

32009 >>Remove & Dispose of Pavement Section

w/ Div. 31 Earthwork

32011 >>Scarify & Re-compact Top 12" Subgrade

Included

32013 >>Furnish & Install 6" Class 6 Road Base

Included

32015 >>Furnish & Install 5" Asphalt

Included

32017 Loading Dock Lot for Gas Line

See Below - Included

32019 >Asphalt "T" Patch

Included

32021 >Asphalt Standard Duty Paving

Included

32023 >>Remove & Dispose of Pavement Section

w/ Div. 31 Earthwork

32025 >>Scarify & Re-compact Top 12" Subgrade

w/ Div. 22 Plumbing

32027 >>Furnish & Install 6" Class 6 Road Base

72.00 sy

28.47

$2,050

32029 >>Furnish & Install 5" Asphalt

Included

32031 >>Furnish & Install 5" Asphalt

Included

32033 Staff Lot for Electrical Line

See Below - Included

32035 >Asphalt "T" Patch

Included

32037 >Asphalt Standard Duty Paving

Included

32039 >>Remove & Dispose of Pavement Section

w/ Div. 31 Earthwork

32041 >>Scarify & Re-compact Top 12" Subgrade

w/ Div. 26 Electrical

32043 >>Furnish & Install 6" Class 6 Road Base

333.00 sy

19.69

$6,558

32045 Asphalt Patch at Visitor Lot due to Irrigation Improvements

62.00 lf

40.00

$2,480

32047 Asphalt Adjustment Index Cost for Liquid Asphalt (Binder)

3.00 tn

600.00

$1,800

Subtotal 32 12 00 Flexible Paving

$160,144

32 13 00 Rigid Paving

$197,586

DATE PRINTED: 10/29/2025

Page 31 of 35

DESCRIPTION 32110 Concrete - SUB

QTY UOM UNIT PRICE 1.00 sub

123,676.83

TOTAL COST

NOTES / COMMENTS

$123,677

32111 Visitor Front Parking Lot

See Below

32112 >Concrete Pavement/ADA Parking, 5" w/ Fibermesh

Included

32113 >Curb & Gutter, 24" w/ Fibermesh

Included

32114 >ADA Ramp, Type 2B

Included

32115 >>ADA Curb Wall, 6"x6" w/ Fibermesh

Included

32116 >>ADA Dome Detectable Panel, 24" Wide

Included

32117 Front of School Drainage Improvement

See Below

32118 >Concrete Ramp, 5" w/ Fibermesh

Included

32119 >Mowband, 6"x8" w/ Fibermesh, (1) #3 Rebar Cont. Plus Drainage Cut Outs

Included

32120 >>Additional Mowband Due to Ramp Alignment

101.00 lf

30.00

$3,030

32121 >Concrete Collars w/ Fibermesh, (1) #4 Rebar Ring, 6" Wide x 24" Dia, 8" Min. Deep

4.00 ea

400.00

$1,600

32122 Mechanical Pad

See Below

32123 >Mechanical Pad, 5", w/ Fibermesh, #4 Horiz @ 18"OCEW Chaired to Mid-Depth of Slab

Included

32124 >Concrete Curb, 8"x8", w/ Fibermesh, (1) #5 Horiz Top Bar

Included

32125 >>Weep Holes, Supply & Layout

12.00 ea

64.60

$775

32126 >Concrete Housekeeping Pad, 4", w/ Fibermesh, Reinf w/ #4 Dowels @ 18"OC at Perimeter, #4 Horiz @ 18"OC Chaired to Mid-Depth of Slab

Included

32127 >>Turn Down Edge at Gate Threshold w/ #4 Rebar x4' @ 12" OC w/ Std Hook

Included

32128 >Continuous Footing at Screenwall, 60"W x 12"D, Fibermesh, w/ (5)#6 Cont Long T&B, #6 Trans @ 12"OC T&B, #6 L Bar @ 12" OC

Included

Not Included Per RFI Response

32129 >Concrete Stem Wall 32130 >Sidewalk Near Mechanical Pad, 5" w/ Fibermesh

Included

32131 >New Concrete Channel/Splash Block, 24" Wide, 6" Thick w/ Fibermesh

Included

32132 New Gas

See Below

32133 >Replace Concrete Sidewalk

Included

32134 >Replace Concrete Curb & Gutter

10.00 lf

50.00

$500

32135 >Concrete Infill @ Trench for Underground Gas Piping into Boiler Room

25.00 lf

50.00

$1,250

32136 >Concrete Housekeeping Pad in Boiler Room, 4" Thick w/ Fibermesh, #4 Epoxy Set Dowels @ Perimeter @ 18" OC 32137 New Electric Line & Light Pole Bases

DATE PRINTED: 10/29/2025

Included

See Below

Page 32 of 35

DESCRIPTION 32138 >Replace Concrete Sidewalk

QTY UOM UNIT PRICE 120.00 sf

18.00

TOTAL COST

NOTES / COMMENTS

$2,160

32139 >Replace Concrete Curb & Gutter

Included

32140 >Concrete Pole Mounted Light Foundation/Base

Included

32141 >Drilling for Light Pole Base Foundations

9.00 ea

800.00

$7,200

32142 Irrigation Improvements

See Below

32143 >Replace Concrete Sidewalk

375.00 sf

18.00

$6,750

32144 >Replace Concrete Curb & Gutter

10.00 lf

30.00

$300

32145 Drainage Channel by Tennis Courts (IS 7) - SUB

1.00 sub

18,336.99

$18,337

32146 >Concrete Channel, 18" Wide, 6" Thick w/ Fibermesh (IS 7)

Alternate 5 - See Below Alternate 5 - Included

1.00 ls

750.00

$750

Alternate 5

32148 Concrete Sidewalk Replacement (IS 8)

245.00 sf

18.00

$4,410

Alternate 6

32149 Concrete Material Increase After 4/1/26

165.00 cy

6.87

$1,134

32150 Concrete Foreman

5.00 wk

3,667.75

$18,339

32151 Concrete Foreman (IS 7)

1.00 wk

3,667.75

$3,668

Alternate 5

32152 Concrete Foreman (IS 8)

1.00 wk

3,667.75

$3,668

Alternate 6

541.00 sy

0.07

$39

32147 >>Add Concrete Step/Drop (IS 7)

32153 Sweep/Clean Sitework Prior to Turnover Subtotal 32 13 00 Rigid Paving

$197,586

32 17 00 Paving Specialties 32271 Pavement Marking & Signage - SUB

$3,136 1.00 sub

3,135.50

$3,136

32273 Lines, 4", White

Included

32275 Handicap Symbol, Blue/White (1-10)

Included

32277 Handicap Sign on Unistrut Post (R7-8)

Included

32279 Van Accessible Sign (R7-8a)

Included

32281 Wheelchair Access Aisle, Absolutely No Parking Sign (R7-8bL & R7-8BR)

Included

Subtotal 32 17 00 Paving Specialties

$3,136

32 31 00 Fences and Gates

$52,174

32301 Repair/Replace Portion of Wood Baseball Outfield Fence

1.00 allow

35,230.00

$35,230

Allowance Per Spec. 01 2100 Allowances

32303 Remove/Replace Chain Link & Posts, 20' (Softball Backstop) (IS 8)

30.00 lf

398.47

$11,954

Alternate 6

32305 >Engineering (IS 8)

1.00 ls

2,500.00

$2,500

Alternate 6

32307 >Remove/Reinstall Backstop Kick Board (IS 8)

30.00 lf

40.00

$1,200

Alternate 6

32309 Remove Chain Link Fencing (IS 9)

84.00 lf

15.36

$1,290

Alternate 7

Subtotal 32 31 00 Fences and Gates

DATE PRINTED: 10/29/2025

$52,174

Page 33 of 35

DESCRIPTION

QTY UOM UNIT PRICE

32 90 00 Planting 32900 Landscape & Irrigation - SUB

TOTAL COST

NOTES / COMMENTS

$354,880 1.00 sub

282,897.31

$282,897

32901 Front of School Drainage Improvement

See Below

32902 >Irrigation System - Sod

Included

32903 >New Sod, Texas Hybrid Bluegrass

Included

32904 >Rock Mulch - 1-1/2". 4" Depth

Included

32905 >Soil Prep - Sod

Included Not Included. See Add Alternate.

32906 >Amended Topsoil, 6" Depth - Sod 32907 >Supply Water for Seeded Areas (Water twice per day for 3 months for 7 minutes) (Nonreclaimed Water)

8,844.00 sf

0.11

$973

32908 Improve Irrigation

See Below

32909 >Irrigation System - Turf Seed

Included

32910 >Sawcut Concrete Sidewalk/Asphalt Paving

Included

32911 >Remove & Disppose Concrete Sidewalk/Asphalt Paving

Included

32912 >Repair all Sod Damaged by Irrigation Improvements with 1/4" of 30% Sand & 70% Compost Mixture & Bluegrass Turf Seed

Included

Not Included. See Add Alternate.

32913 >Amended Topsoil, 6" Depth - Turf 32914 >Supply Water for Seeded Areas (Water twice per day for 3 months for 7 minutes) (Nonreclaimed Water)

148,620.00 sf

0.11

$16,348

32915 Tennis Court Landscape Improvement

See Below

32916 >Irrigation System - Native Seed

Included

32917 >New Native Seed

Included

32918 >Soil Prep - Native Seed

Included Not Included. See Add Alternate.

32919 >Amended Topsoil, 6" Depth - Native Seed 32920 >Supply Water for Seeded Areas (Water twice per day for 3 months for 7 minutes) (Nonreclaimed Water) (IS 2)

16,921.00 sf

0.11

$1,861

32921 Landscape Improvement at New Mechanical Enclosure

See Below

32922 >Irrigation System - Native Seed

Included

32923 >New Native Seed

Included

32924 >Soil Prep - Native Seed

Included Not Included. See Add Alternate.

32925 >Amended Topsoil, 6" Depth - Native Seed 32926 >Rock Mulch - 1-1/2". 4" Depth 32927 >Supply Water for Seeded Areas (Water twice per day for 3 months for 7 minutes) (NonDATE PRINTED: 10/29/2025

Included 1,202.00 sf

0.11

$132

Page 34 of 35

DESCRIPTION per day for 3 months for 7 minutes) (Nonreclaimed Water)

QTY UOM UNIT PRICE

TOTAL COST

32928 30 Day Maintenance at Sod & Turf Seed 32930 Landscape & Irrigation Repair by Tennis Courts New Drainage Channel (IS 7) - SUB

NOTES / COMMENTS

Included 1.00 sub

29,668.47

$29,668

Alternate 5 - See Below

32931 >Irrigation System - Native Seed (IS 7)

Alternate 5 - Included

32932 >New Native Seed (IS 7)

Alternate 5 - Included

32933 >Soil Prep - Native Seed (IS 7)

Alternate 5 - Included

32934 >Amended Topsoil, 6" Depth - Native Seed (IS 7) 32935 >Grouted Cobble (IS 7) 32936 >Supply Water for Seeded Areas (Water twice per day for 3 months for 7 minutes) (Nonreclaimed Water) (IS 7) 32937 Irrigation System Repair Allowance (IS 8)

8,625.00 sf

1.25

$10,786

Alternate 5

179.00 sf

35.00

$6,265

Alternate 5

8,625.00 sf

0.11

$949

Alternate 5

5,000.00

$5,000

Alternate 6

1.00 allow

Subtotal 32 90 00 Planting

$354,880

Subtotal 32 Exterior Improvements

$767,919

Total Site

DATE PRINTED: 10/29/2025

$1,508,210

Page 35 of 35

Exhibit D

Contract Time Schedule Itemization ofGMP Cost Itemization of the Dollars requested for long lead equipment and material packages

Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20

RE: Schedule Narrative – October 2025 Schedule Update Narrative October 17, 2025 BVSD – Fairview High School 1515 Greenbriar Blvd. Boulder CO. 80305 The following is a schedule narrative for the BVSD – Fairview Highschool [Boulder Valley RFP 25-04 CMGC Project Scope #1 - Fairview High School 10.17.2025.pdf] is attached.

Summary: This updated schedule reflects revisions to the DD schedule and aligns with the bi-weekly OAC dashboard timelines. It outlines the project timeline from preconstruction to construction activities and provides key milestone dates during preconstruction to allow for a successful construction phase during the summer of 2026 and 2027. AP has been actively identifying long-lead procurement items starting at the Schematic Design phase. In collaboration with trade partners, AP has gathered lead times, submittal preparation costs, and material release costs.

Description of Activities on the most Critical Path The current critical path for summer of 2026 work is driven by certain areas of work. Room 408 is currently on the critical path due to the contractor coordination required in that space. Also, the Commons RTU replacement is shown on the critical path due to the level of work in the ceilings above and the installation of finishes throughout those corridors. The 200 level corridor upgrades are on the critical path for summer of 27 due to the access that is required around this space for the computer lab work that would take priority during the first summer. Currently all of these areas are on track to hit their targeted turn over dates.

Monthly Progress Description The schedule has been updated, and activities have been adjusted to reflect the latest CD documents. Tasks have been progressed since the previous update.

Current/Anticipated Problem Areas and/or Delaying Factors BVSD & AP have preordered long lead time material as noted in the Amendment 1 procurement change order. AP is tracking all long lead time material with the master schedule for completion to meet the required schedule.

Revisions to the Project Schedule The updates made to establish a targeted flow through the building, and items and areas have been adjusted to maximize the efficiency of the first summer opportunity of work.

Narrative Review To recap the attached schedule and the above update: •

Overall, the attached schedule provides a road map for the design and construction of the BVSDFairview High School. As more planning, coordination, and construction scope is defined and developed, the schedule will continue to reflect these changes and updates.

•

The current schedule has an anticipated construction completion date of August 1st 2027 with milestone completion dates for TCO by August 1st 2026.

•

The team is tracking numerous important dates: document release, funding package dates, and material release dates. AP will continue to update the team in forthcoming narratives and OAC meetings

•

Lastly, the schedule changes and modifications outlined above help to more accurately show how the project is being built and ways that BVSD,MOA, AP and their subcontractors are working to maintain or improve the project completion date.

Please feel free to contact me with any questions or comments regarding this update or anything else within the Project. Thank you, Logan Dickerman Superintendent Adolfson & Peterson Construction 720.456.1992 ldickerman@a-p.com

Line

Name

Duration

BVSD - Fairview High School

APC

Start

Finish

A 12

S 9

2024 O N 7 4

D 2

2025 J F M A M J J 30 27 24 24 21 19 16 14

781d 16.62

8/12/2024

446d 21.94

8/12/2024

5/18/2026

RFP / RFQ Information

49d 100.00

8/12/2024

10/18/2024

1

RFP Issued to Contractor

1d 100.00

8/12/2024 A

8/12/2024 A

2

RFP Site Walk

1d 100.00

8/22/2024 A

8/22/2024 A

3

RFP Inquiries Due

1d 100.00

9/4/2024 A

9/4/2024 A

4

RFP Addendum Sent

1d 100.00

9/12/2024 A

9/12/2024 A

5

RFP Submission Deadline

1d 100.00

10/3/2024 A

10/3/2024 A

6

RFP Evaluation

1d 100.00

10/11/2024 A 10/11/2024 A

RFP Evaluation

7

CMGC Contract Award

1d 100.00

10/18/2024 A 10/18/2024 A

CMGC Contract Award

Preconstruction

Document Development

390d 72.30

Schematic Design

A 11

S 8

O 6

2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13

10/21/2024

5/7/2026

150d 100.00 10/21/2024

5/27/2025

73d 100.00

1/7/2025 A

4/17/2025 A

SD- Early VFA Investigation and Verification

10

SD- Schematic Design Pricing/ Constructibility Review

23d 100.00

2/17/2025 A

3/19/2025 A

SD- Schematic Design Pricing/ Constructibility Review

11

SD- BVSD DAT & Facility Page Flip

1d 100.00

2/17/2025 A

2/17/2025 A

12

SD- Schematic Design Bid Leveling/ Review Meeting

1d 100.00

3/10/2025 A

3/10/2025 A

SD- Schematic Design Bid Leveling/ Review Meeting

13

SD- Schematic Design - Budget/ Constructibility Corrections

4d 100.00

3/11/2025 A

3/14/2025 A

SD- Schematic Design - Budget/ Constructibility Corrections

14

SD- Early Procurement Package Creation By AP

30d 100.00

3/17/2025 A

4/25/2025 A

15

SD- Early Procurement Package Review with BVSD

15d 100.00

4/28/2025 A

5/16/2025 A

16

SD- Early Procurement Package Issuance to Board

5d 100.00

5/20/2025 A

5/27/2025 A

63d 100.00

4/18/2025

7/17/2025

20d 100.00

4/18/2025 A

5/15/2025 A

28d 100.00

5/16/2025 A

6/25/2025 A

1d 100.00

5/16/2025 A

5/16/2025 A

1d 100.00

6/25/2025 A

6/25/2025 A

DD- Design Development - Pricing/ Constructibility Internal Review

9d 100.00

6/26/2025 A

7/9/2025 A

DD- Design Development - Budget/ Constructibility Corrections

1d 100.00

7/17/2025 A

7/17/2025 A

20 21 22

DD- Design Development - Pricing/ Constructibility Internal Review DD- Design Development - Budget/ Constructibility Corrections DD- Design Development - Final Procurement Package Allocation Review to start Long Lead Submittals Owner Items - Xcel Upgrades

SD- BVSD DAT & Facility Page Flip

SD- Early Procurement Package Creation By AP

SD- Early Procurement Package Review with BVSD

SD- Early Procurement Package Issuance to Board

DD- Design Development - Design Development Complete

DD- Design Development - Pricing/ Constructibility Review

DD- BVSD DAT & Facility Page Flip

DD- Design Development - Final Procurement Package Allocation Review to start Long Lead Submittals

170d 17.65

9/5/2025

5/7/2026

XU-BVSD Application Creation/ Submission

10d 100.00

9/5/2025 A

9/18/2025 A

24

XU-BVSD Application Approval

60d 33.33

9/19/2025 A

12/15/2025

25

XU-Xcel Design and Review Time

60d

12/16/2025

3/12/2026

XU-Xcel Design and Review Time

26

XU-Xcel Approval

30d

3/13/2026

4/23/2026

XU-Xcel Approval

27

XU-Install New Gas Line/ Meter

10d

4/24/2026

5/7/2026

5/30/2025

12/26/2025 10/21/2025

145d 64.13

Procurement Package

101d 95.16

5/30/2025

28

C&A-PP-Board Approval

5d 100.00

5/30/2025 A

6/5/2025 A

29

C&A-PP-BVSD Contract Execution to AP

10d 100.00

6/6/2025 A

8/14/2025 A

30

C&A-PP-AP Contract Execution to Procurement Package Subs

47d 93.62

8/15/2025 A

10/21/2025

30d

11/11/2025 12/26/2025

FGMP

2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12

SD- Schematic Design Complete

23

Contracting & Award

S 6

RFP Submission Deadline

SD- Early VFA Investigation and Verification

DD- BVSD DAT & Facility Page Flip

A 9

RFP Addendum Sent

9

19

2027 D J F M A M J J 30 28 25 22 22 19 17 14 12

RFP Inquiries Due

10/21/2024 A 2/14/2025 A

DD- Design Development - Design Development Complete DD- Design Development - Pricing/ Constructibility Review

N 2

RFP Site Walk

79d 100.00

18

O 5

RFP Issued to Contractor

SD- Schematic Design Complete

17

S 7

9/14/2027

8

Design Development

A 10

Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School

XU-BVSD Application Creation/ Submission

XU-BVSD Application Approval

XU-Install New Gas Line/ Meter

C&A-PP-Board Approval

C&A-PP-BVSD Contract Execution to AP

C&A-PP-AP Contract Execution to Procurement Package Subs

Job #: Fairview High School

Rev. date: 10/17/2025 12:41:15 PM

Data Date: 10/17/2025

Page 1 of 13

3. Print View Filter: No Summary Tasks

J 10

A 7

S 4

Line

Name

Duration

APC

Start

Finish

31

C&A-FGMP-Board Approval

5d

11/11/2025

11/17/2025

32

C&A-FGMP-BVSD Contract Execution to AP

10d

11/18/2025

12/3/2025

33

C&A-FGMP-AP Contract Execution to Procurement Package Subs

15d

12/4/2025

12/26/2025

8d 100.00

7/14/2025

7/23/2025

Early Verification and Coordination

A 12

S 9

2024 O N 7 4

D 2

2025 J F M A M J J 30 27 24 24 21 19 16 14

A 11

S 8

O 6

2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13

2d 100.00

7/14/2025 A

7/15/2025 A

EI-Design/Sub Kick off Meeting

EI-Onsite Review of Electrical Scope/ Lighting Study

2d 100.00

7/16/2025 A

7/17/2025 A

EI-Onsite Review of Electrical Scope/ Lighting Study

36

EI-Onsite Review of Mechanical Scope

2d 100.00

7/18/2025 A

7/21/2025 A

EI-Onsite Review of Mechanical Scope

37

EI-Onsite Review of Remaining Scope

2d 100.00

7/22/2025 A

7/23/2025 A

EI-Onsite Review of Remaining Scope

124d 86.40

5/16/2025

11/10/2025

38

CD- Construction Documents and Drawings Complete

83d 100.00

5/16/2025 A

9/12/2025 A

39

CD- Construction Documents - Pricing Review

25d 96.00

9/15/2025 A

10/17/2025

40

CD- BVSD DAT & Facility Page Flip

1d 100.00

9/15/2025 A

9/15/2025 A

41

CD- Construction Documents - FGMP Review with BVSD PM

1d

10/20/2025

10/20/2025

CD- Construction Documents - FGMP Review with BVSD PM

42

CD- Construction Documents - FGMP Corrections

5d

10/21/2025

10/27/2025

CD- Construction Documents - FGMP Corrections

43

CD- Construction Documents - Final FGMP Amendment to District Board of Education Submission

10d

10/28/2025

11/10/2025

145d 11.71

9/15/2025

4/10/2026

Building Permit Review and Issuance

125d 19.20

9/15/2025 A

3/13/2026

45

Remaining Permit Approval

40d

1/6/2026

3/2/2026

40d

46

Local AHJ Permit Review and Issuance Long Lead Submittals & Procurement Submittals & Procurement - Fire Alarm Equipment Submittals & Procurement - Fire Alarm Equipment

2/16/2026

4/10/2026

197d 5.89

8/7/2025

5/18/2026

130d

10/22/2025

4/28/2026

130d

10/22/2025

4/28/2026

Building Permit Review and Issuance

Remaining Permit Approval

Local AHJ Permit Review and Issuance

11/18/2025

S&P - FA - Subcontractor Submittals

48

S&P - FA - AP Review

5d

11/19/2025

11/25/2025

S&P - FA - AP Review

49

S&P - FA - AHJ Review and Approval

15d

11/26/2025

12/18/2025

50

S&P - FA - A/E Review and Approval

10d

12/19/2025

1/6/2026

51

S&P - FA - Procurement

80d

1/7/2026

4/28/2026

75d

12/29/2025

4/13/2026

S&P - FA - AHJ Review and Approval

S&P - FA - A/E Review and Approval

S&P - FA - Procurement

75d

12/29/2025

4/13/2026

52

S&P - PA - Subcontractor Submittals

20d

12/29/2025

1/26/2026

S&P - PA - Subcontractor Submittals

53

S&P - PA - AP Review

5d

1/27/2026

2/2/2026

S&P - PA - AP Review

54

S&P - PA - A/E Review and Approval

10d

2/3/2026

2/16/2026

S&P - PA - A/E Review and Approval

55

S&P - PA - Procurement

40d

2/17/2026

4/13/2026

S&P - PA - Procurement

8/7/2025

4/30/2026

Submittals & Procurement - Gym RTU 901 Aaon

185d 18.67

8/7/2025

4/30/2026

56

S&P - RTU - Subcontractor Submittals

10d 100.00

8/7/2025 A

9/10/2025 A

S&P - RTU - Subcontractor Submittals

57

S&P - RTU - AP Review

1d 100.00

9/10/2025 A

9/10/2025 A

S&P - RTU - AP Review

58

S&P - RTU - A/E Review and Approval

12d 100.00

9/10/2025 A

9/25/2025 A

59

S&P - RTU - Procurement

143d 5.59

10/7/2025 A

4/30/2026

185d 15.09

8/7/2025

4/30/2026

Submittals & Procurement - Commons HVAC 1001 Aaon

Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School

2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12

CD- Construction Documents - Final FGMP Amendment to District Board of Education Submission

10/22/2025

185d 17.26

S 6

CD- Construction Documents - Pricing Review

20d

Submittals & Procurement - RTUs

A 9

CD- BVSD DAT & Facility Page Flip

S&P - FA - Subcontractor Submittals

Submittals & Procurement - PA Equipment

2027 D J F M A M J J 30 28 25 22 22 19 17 14 12

CD- Construction Documents and Drawings Complete

47

Submittals & Procurement - AV Equipment

N 2

C&A-FGMP-AP Contract Execution to Procurement Package Subs

EI-Design/Sub Kick off Meeting

Permitting

O 5

C&A-FGMP-BVSD Contract Execution to AP

35

44

S 7

C&A-FGMP-Board Approval

34

Construction Documents

A 10

S&P - RTU - A/E Review and Approval

S&P - RTU - Procurement

Job #: Fairview High School

Rev. date: 10/17/2025 12:41:15 PM

Data Date: 10/17/2025

Page 2 of 13

3. Print View Filter: No Summary Tasks

J 10

A 7

S 4

Line

Name

Duration

APC

Start

Finish

A 12

S 9

2024 O N 7 4

D 2

2025 J F M A M J J 30 27 24 24 21 19 16 14

A 11

S 8

O 6

2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13

60

S&P - RTU - Subcontractor Submittals

3d 100.00

8/7/2025 A

9/10/2025 A

S&P - RTU - Subcontractor Submittals

61

S&P - RTU - AP Review

1d 100.00

9/10/2025 A

9/10/2025 A

S&P - RTU - AP Review

62

S&P - RTU - A/E Review and Approval

12d 100.00

9/10/2025 A

9/25/2025 A

63

S&P - RTU - Procurement

143d 5.59

10/7/2025 A

4/30/2026

185d 15.09

8/7/2025

4/30/2026

Submittals & Procurement - Commons HVAC 1002 Aaon S&P - RTU - Subcontractor Submittals

3d 100.00

8/7/2025 A

9/10/2025 A

S&P - RTU - Subcontractor Submittals

S&P - RTU - AP Review

1d 100.00

9/10/2025 A

9/10/2025 A

S&P - RTU - AP Review

66

S&P - RTU - A/E Review and Approval

12d 100.00

9/10/2025 A

9/25/2025 A

67

S&P - RTU - Procurement

143d 5.59

10/7/2025 A

4/30/2026

140d 31.82

8/7/2025

2/26/2026

S&P - RTU - Subcontractor Submittals

22d 100.00

8/7/2025 A

9/10/2025 A

S&P - RTU - Subcontractor Submittals

S&P - RTU - AP Review

1d 100.00

9/10/2025 A

9/10/2025 A

S&P - RTU - AP Review

70

S&P - RTU - A/E Review and Approval

12d 100.00

9/10/2025 A

9/25/2025 A

71

S&P - RTU - Procurement

97d 7.22

10/8/2025 A

2/26/2026

85d

12/29/2025

4/27/2026

S&P - RTU- Subcontractor Submittals

10d

12/29/2025

1/12/2026

S&P - RTU- Subcontractor Submittals

S&P - RTU - AP Review

5d

1/13/2026

1/19/2026

S&P - RTU - AP Review

74

S&P - RTU- A/E Review and Approval

10d

1/20/2026

2/2/2026

75

S&P - RTU - Procurement

60d

2/3/2026

4/27/2026

135d

10/22/2025

5/5/2026

S&P - RTU - Procurement

135d

10/22/2025

5/5/2026

S&P - EDE - Subcontractor Submittals

20d

10/22/2025

11/18/2025

S&P - EDE - Subcontractor Submittals

77

S&P - EDE- AP Review

5d

11/19/2025

11/25/2025

S&P - EDE- AP Review

78

S&P - EDE - A/E Review and Approval

10d

11/26/2025

12/11/2025

79

S&P - EDE - Procurement

100d

12/12/2025

5/5/2026

55d

12/29/2025

3/16/2026

S&P - EDE - A/E Review and Approval

S&P - EDE - Procurement

80

S&P - EDE - Subcontractor Submittals

10d

12/29/2025

1/12/2026

S&P - EDE - Subcontractor Submittals

81

S&P - EDE- AP Review

5d

1/13/2026

1/19/2026

S&P - EDE- AP Review

82

S&P - EDE - A/E Review and Approval

10d

1/20/2026

2/2/2026

83

S&P - EDE - Procurement

30d

2/3/2026

3/16/2026

85d

12/29/2025

4/27/2026

S&P - EDE - A/E Review and Approval

S&P - EDE - Procurement

84

S&P - EDE - Subcontractor Submittals

10d

12/29/2025

1/12/2026

S&P - EDE - Subcontractor Submittals

85

S&P - EDE- AP Review

5d

1/13/2026

1/19/2026

S&P - EDE- AP Review

86

S&P - EDE - A/E Review and Approval

10d

1/20/2026

2/2/2026

87

S&P - EDE - Procurement

60d

2/3/2026

4/27/2026

100d

12/29/2025

5/18/2026

S&P - EDE - A/E Review and Approval

S&P - EDE - Procurement

100d

12/29/2025

5/18/2026

88

S&P - SB- Subcontractor Submittals

10d

12/29/2025

1/12/2026

S&P - SB- Subcontractor Submittals

89

S&P - SB- AP Review

5d

1/13/2026

1/19/2026

S&P - SB- AP Review

90

S&P - SB- A/E Review and Approval

10d

1/20/2026

2/2/2026

Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School

2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12

S&P - RTU- A/E Review and Approval

76

Submittals & Procurement - Scoreboards

S 6

S&P - RTU - Procurement

73

Submittals & Procurement - Scoreboards - NOT IN SCOPE

A 9

S&P - RTU - A/E Review and Approval

72

Submittals & Procurement - Centaurus Lighting Control Equipment

2027 D J F M A M J J 30 28 25 22 22 19 17 14 12

S&P - RTU - Procurement

69

Submittals & Procurement - Centaurus LED Lighting

N 2

S&P - RTU - A/E Review and Approval

68

Submittals & Procurement - Electrical Distribution Equipment Submittals & Procurement - Main Distribution Panel Board - BRA

O 5

S&P - RTU - Procurement

65

Submittals & Procurement - RTU Controls

S 7

S&P - RTU - A/E Review and Approval

64

Submittals & Procurement - Commons HVAC 1001 & 1002 ACCU

A 10

S&P - SB- A/E Review and Approval

Job #: Fairview High School

Rev. date: 10/17/2025 12:41:16 PM

Data Date: 10/17/2025

Page 3 of 13

3. Print View Filter: No Summary Tasks

J 10

A 7

S 4

Line 91

Name

Duration

S&P - SB- Procurement Submittals & Procurement - Division 8 Submittals & Procurement - Aluminum Windows

APC

Start

Finish

75d

2/3/2026

5/18/2026

115d

10/22/2025

4/7/2026

A 12

S 9

2024 O N 7 4

D 2

2025 J F M A M J J 30 27 24 24 21 19 16 14

A 11

S 8

O 6

2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13

110d

10/22/2025

3/31/2026

S&P - D8- Subcontractor Submittals

20d

10/22/2025

11/18/2025

S&P - D8- Subcontractor Submittals

93

S&P - D8 - AP Review

5d

11/19/2025

11/25/2025

S&P - D8 - AP Review

94

S&P - D8- A/E Review and Approval

15d

11/26/2025

12/18/2025

95

S&P - D8 - Procurement

70d

12/19/2025

3/31/2026

115d

10/22/2025

4/7/2026

S&P - D8- Subcontractor Submittals

20d

10/22/2025

11/18/2025

S&P - D8- Subcontractor Submittals

S&P - D8 - AP Review

5d

11/19/2025

11/25/2025

S&P - D8 - AP Review

98

S&P - D8- A/E Review and Approval

15d

11/26/2025

12/18/2025

99

S&P - D8 - Procurement

75d

12/19/2025

4/7/2026

135d

10/22/2025

5/5/2026

135d

10/22/2025

5/5/2026

20d

10/22/2025

11/18/2025

S&P - WH- Subcontractor Submittals

101

S&P - WH - AP Review

5d

11/19/2025

11/25/2025

S&P - WH - AP Review

102

S&P - WH- A/E Review and Approval

10d

11/26/2025

12/11/2025

103

S&P - WH- Procurement

100d

12/12/2025

5/5/2026

114d

10/22/2025

4/6/2026

114d

10/22/2025

4/6/2026

20d

10/22/2025

11/18/2025

S&P - CW- Subcontractor Submittals

105

S&P - CW- AP Review

5d

11/19/2025

11/25/2025

S&P - CW- AP Review

106

S&P - CW- A/E Review and Approval

10d

11/26/2025

12/11/2025

107

S&P - CW- Procurement

70d

12/29/2025

4/6/2026

110d

10/22/2025

3/31/2026

S&P - CW- A/E Review and Approval

S&P - CW- Procurement

Submittals & Procurement - Graphics

110d

10/22/2025

3/31/2026

108

S&P - Graphic- Subcontractor Submittals

20d

10/22/2025

11/18/2025

S&P - Graphic- Subcontractor Submittals

109

S&P - Graphic- AP Review

5d

11/19/2025

11/25/2025

S&P - Graphic- AP Review

110

S&P - Graphic- A/E Review and Approval

20d

11/26/2025

12/29/2025

111

S&P - Graphic- Procurement

65d

12/30/2025

3/31/2026

105d

10/22/2025

3/24/2026

Submittals & Procurement - Fume Hoods

S&P - Graphic- A/E Review and Approval

S&P - Graphic- Procurement

105d

10/22/2025

3/24/2026

112

S&P - FH- Subcontractor Submittals

20d

10/22/2025

11/18/2025

S&P - FH- Subcontractor Submittals

113

S&P - FH- AP Review

5d

11/19/2025

11/25/2025

S&P - FH- AP Review

114

S&P - FH- A/E Review and Approval

20d

11/26/2025

12/29/2025

115

S&P - FH- Procurement

60d

12/30/2025

3/24/2026

95d

12/29/2025

5/11/2026

Submittals & Procurement - All Other Submittals 116

S&P - Other - Subcontractor Submittals

20d

12/29/2025

1/26/2026

117

S&P - Other - AP Review

10d

1/27/2026

2/9/2026

118

S&P - Other - A/E Review and Approval

15d

2/10/2026

3/2/2026

Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School

2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12

S&P - WH- Procurement

S&P - CW- Subcontractor Submittals

Submittals & Procurement - Fume Hoods - Not in scope

S 6

S&P - WH- A/E Review and Approval

104

Submittals & Procurement - Graphics

A 9

S&P - D8 - Procurement

S&P - WH- Subcontractor Submittals

Submittals & Procurement - Casework

2027 D J F M A M J J 30 28 25 22 22 19 17 14 12

S&P - D8- A/E Review and Approval

100

Submittals & Procurement - Casework

N 2

S&P - D8 - Procurement

97

Submittals & Procurement - Water Heaters and Boilers

O 5

S&P - D8- A/E Review and Approval

96

Submittals & Procurement - Water Heaters

S 7

S&P - SB- Procurement

92

Submittals & Procurement - Hollow Metal Doors, Frames, Hardware

A 10

S&P - FH- A/E Review and Approval

S&P - FH- Procurement

S&P - Other - Subcontractor Submittals

S&P - Other - AP Review

S&P - Other - A/E Review and Approval

Job #: Fairview High School

Rev. date: 10/17/2025 12:41:16 PM

Data Date: 10/17/2025

Page 4 of 13

3. Print View Filter: No Summary Tasks

J 10

A 7

S 4

Line 119

Name

Duration

S&P - Other - Procurement

APC

Finish

3/3/2026

5/11/2026

146d 50.00

5/13/2025

12/9/2025

50d

Board Dates

Start

120

1st May Board Date

1d 100.00

5/13/2025 A

5/13/2025 A

121

2nd May Board Date

1d 100.00

5/27/2025 A

5/27/2025 A

122

Only November Board Date

1d

11/11/2025 *

11/11/2025

123

Only December Board Date

1d

12/9/2025 *

12/9/2025

Owner Key Dates

579d 33.33

4/18/2025

8/2/2027

124

2025 Spring Break

5d 100.00

4/18/2025 A

4/24/2025 A

125

2025 End of School Year

1d 100.00

5/27/2025 A

5/27/2025 A

126

2025/2026 School Year Begin

1d 100.00

8/8/2025 A

8/8/2025 A

127

2026 Spring Break

5d

3/23/2026 *

3/27/2026

128

2026 End of School Year

1d

5/26/2026 *

5/26/2026

129

2026/2027 School Year Begins

1d

8/3/2026 *

8/3/2026

130

2027 Spring Break

5d

3/29/2027 *

4/2/2027

131

2027 End of School Year

1d

5/27/2027 *

5/27/2027

132

2027/2028 School Year Begins

1d

8/2/2027 *

8/2/2027

376d

3/23/2026

9/14/2027

5d

4/27/2026

5/1/2026

5d

4/27/2026

5/1/2026

332d

3/23/2026

7/13/2027

320d

4/8/2026

7/13/2027

320d

4/8/2026

7/13/2027

320d

4/8/2026

7/13/2027

4/8/2026

4/8/2026

Construction Site Mobilization 133

Mob - Site mobilization Intierior Finish and Fittout Cooridors Cooridor Upgrades 200 Level Cooridor Upgrades

A 12

S 9

2024 O N 7 4

D 2

2025 J F M A M J J 30 27 24 24 21 19 16 14

A 11

S 8

O 6

2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13

A 10

S 7

O 5

N 2

2027 D J F M A M J J 30 28 25 22 22 19 17 14 12

A 9

S 6

2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12

S&P - Other - Procurement

1st May Board Date

2nd May Board Date

Only November Board Date

Only December Board Date

2025 Spring Break

2025 End of School Year

2025/2026 School Year Begin

2026 Spring Break

2026 End of School Year

2026/2027 School Year Begins

2027 Spring Break

2027 End of School Year

2027/2028 School Year Begins

Mob - Site mobilization

134

IFF-200COR-ALT Replace Doors*

135

IFF-200COR-Abatement of Flooring (PH 2)

5d

5/27/2027

6/3/2027

IFF-200COR-Abatement of Flooring (PH 2)

136

IFF-200COR-MEP Safe off of Ceilings

2d

6/4/2027

6/7/2027

IFF-200COR-MEP Safe off of Ceilings

137

IFF-200COR-Demo Existing ACT

2d

6/8/2027

6/9/2027

IFF-200COR-Demo Existing ACT

138

IFF-200COR-Install new ACT

3d

6/10/2027

6/14/2027

IFF-200COR-Install new ACT

139

IFF-200COR-MEP Device Ceilings

3d

6/15/2027

6/17/2027

IFF-200COR-MEP Device Ceilings

140

IFF-200COR-White out Ceilings

1d

6/18/2027

6/18/2027

IFF-200COR-White out Ceilings

141

IFF-200COR-Install new Flooring

3d

6/21/2027

6/23/2027

IFF-200COR-Install new Flooring

142

IFF-200COR-Paint Walls

3d

6/24/2027

6/28/2027

IFF-200COR-Paint Walls

143

IFF-200COR-Install Base

2d

6/29/2027

6/30/2027

IFF-200COR-Install Base

144

IFF-200COR-Final Clean

8d

7/1/2027

7/13/2027

30d

5/26/2026

7/7/2026

300 Level Cooridor Upgrades

IFF-200COR-ALT Replace Doors*

IFF-200COR-Final Clean

145

IFF-300COR-Clean Demo Flooring

3d

5/26/2026

5/28/2026

IFF-300COR-Clean Demo Flooring

146

IFF-300COR-MEP Safe off of Ceilings

2d

5/29/2026

6/1/2026

IFF-300COR-MEP Safe off of Ceilings

147

IFF-300COR-Demo Existing ACT

2d

6/2/2026

6/3/2026

IFF-300COR-Demo Existing ACT

148

IFF-300COR-Install new ACT

3d

6/4/2026

6/8/2026

IFF-300COR-Install new ACT

149

IFF-300COR-MEP Device Ceilings

3d

6/9/2026

6/11/2026

IFF-300COR-MEP Device Ceilings

150

IFF-300COR-Install new Flooring

3d

6/12/2026

6/16/2026

IFF-300COR-Install new Flooring

Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School

Job #: Fairview High School

Rev. date: 10/17/2025 12:41:16 PM

Data Date: 10/17/2025

Page 5 of 13

3. Print View Filter: No Summary Tasks

J 10

A 7

S 4

Line

Name

Duration

APC

Start

Finish

A 12

S 9

2024 O N 7 4

D 2

2025 J F M A M J J 30 27 24 24 21 19 16 14

A 11

S 8

O 6

2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13

A 10

S 7

O 5

N 2

151

IFF-300COR-White out Ceilings

1d

6/17/2026

6/17/2026

IFF-300COR-White out Ceilings

152

IFF-300COR-Paint Walls

3d

6/18/2026

6/22/2026

IFF-300COR-Paint Walls

153

IFF-300COR-Install Base

2d

6/23/2026

6/24/2026

IFF-300COR-Install Base

154

IFF-300COR-Final Clean

8d

6/25/2026

7/7/2026

31d

5/29/2026

7/13/2026

400 Level Cooridor Upgrades

2027 D J F M A M J J 30 28 25 22 22 19 17 14 12

IFF-400COR-Clean Demo Flooring

3d

5/29/2026

6/2/2026

IFF-400COR-Clean Demo Flooring

156

IFF-400COR-MEP Safe off of Ceilings

2d

6/3/2026

6/4/2026

IFF-400COR-MEP Safe off of Ceilings

157

IFF-400COR-Demo Existing ACT

2d

6/5/2026

6/8/2026

IFF-400COR-Demo Existing ACT

158

IFF-400COR-Install new ACT

3d

6/9/2026

6/11/2026

IFF-400COR-Install new ACT

159

IFF-400COR-MEP Device Ceilings

3d

6/12/2026

6/16/2026

IFF-400COR-MEP Device Ceilings

160

IFF-400COR-Install new Flooring

4d

6/17/2026

6/22/2026

IFF-400COR-Install new Flooring

161

IFF-400COR-White out Ceilings

1d

6/23/2026

6/23/2026

IFF-400COR-White out Ceilings

162

IFF-400COR-Paint Walls

3d

6/24/2026

6/26/2026

IFF-400COR-Paint Walls

163

IFF-400COR-Install Base

2d

6/29/2026

6/30/2026

IFF-400COR-Install Base

164

IFF-400COR-Final Clean

8d

7/1/2026

7/13/2026

37d

5/29/2026

7/21/2026

IFF-600COR-Clean Demo Flooring

3d

5/29/2026

6/2/2026

IFF-600COR-Clean Demo Flooring

166

IFF-600COR-MEP Safe off of Ceilings

2d

6/3/2026

6/4/2026

IFF-600COR-MEP Safe off of Ceilings

167

IFF-600COR-Demo Existing ACT

2d

6/5/2026

6/8/2026

IFF-600COR-Demo Existing ACT

168

IFF-600COR-Install new ACT

5d

6/9/2026

6/15/2026

IFF-600COR-Install new ACT

169

IFF-600COR-MEP Device Ceilings

3d

6/16/2026

6/18/2026

IFF-600COR-MEP Device Ceilings

170

IFF-600COR-Install new Flooring

3d

6/19/2026

6/23/2026

IFF-600COR-Install new Flooring

171

IFF-600COR-White out Ceilings

1d

6/24/2026

6/24/2026

IFF-600COR-White out Ceilings

172

IFF-600COR-Replace Doors

5d

6/25/2026

7/1/2026

IFF-600COR-Replace Doors

173

IFF-600COR-Paint Walls

3d

7/2/2026

7/7/2026

IFF-600COR-Paint Walls

174

IFF-600COR-Install Base

2d

7/8/2026

7/9/2026

IFF-600COR-Install Base

175

IFF-600COR-Final Clean

8d

7/10/2026

7/21/2026

IFF-600COR-Final Clean

42d

5/26/2026

7/23/2026

176

IFF-900COR-Clean Demo Flooring

3d

5/26/2026

5/28/2026

177

IFF-900COR-Install new Flooring

8d

7/9/2026

7/20/2026

IFF-900COR-Install new Flooring

178

IFF-900COR-Install Base

5d

7/16/2026

7/22/2026

IFF-900COR-Install Base

179

IFF-900COR-Final Clean

1d

7/23/2026

7/23/2026

IFF-900COR-Final Clean

270d

5/26/2026

6/17/2027

200 Level Classroom Improvements Room 225 & 228 - Classroom Improvements

IFF-900COR-Clean Demo Flooring

40d

5/26/2026

7/21/2026

180

IFF-225&228-Owner Move

1d

5/26/2026

5/26/2026

IFF-225&228-Owner Move

181

IFF-225&228-MEP Safe off

1d

5/27/2026

5/27/2026

IFF-225&228-MEP Safe off

182

IFF-225&228-Clean Demo flooring, Platform, Ceilings, Gyp

2d

5/28/2026

5/29/2026

IFF-225&228-Clean Demo flooring, Platform, Ceilings, Gyp

183

IFF-225&228-Abatement of Window Walls

4d

5/28/2026

6/2/2026

IFF-225&228-Abatement of Window Walls

184

IFF-225&228-Cut Access Hole In Slab

2d

6/1/2026

6/2/2026

IFF-225&228-Cut Access Hole In Slab

185

IFF-225&228-Install Kneewall Supports

3d

6/3/2026

6/5/2026

IFF-225&228-Install Kneewall Supports

186

IFF-225&228-Install Crawlspace Raceways

2d

6/3/2026

6/4/2026

IFF-225&228-Install Crawlspace Raceways

Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School

2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12

IFF-400COR-Final Clean

165

900 Level Cooridor Upgrades

S 6

IFF-300COR-Final Clean

155

600 Level Cooridor Upgrades

A 9

Job #: Fairview High School

Rev. date: 10/17/2025 12:41:16 PM

Data Date: 10/17/2025

Page 6 of 13

3. Print View Filter: No Summary Tasks

J 10

A 7

S 4

Line

Name

Duration

APC

Start

Finish

A 12

S 9

2024 O N 7 4

D 2

2025 J F M A M J J 30 27 24 24 21 19 16 14

A 11

S 8

O 6

2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13

A 10

S 7

O 5

N 2

2027 D J F M A M J J 30 28 25 22 22 19 17 14 12

187

IFF-225&228-Frame New Walls

2d

6/8/2026

6/9/2026

IFF-225&228-Frame New Walls

188

IFF-225&228-MEP rough In

4d

6/10/2026

6/15/2026

IFF-225&228-MEP rough In

189

IFF-225&228-H/T/F Gyp

6d

6/16/2026

6/23/2026

IFF-225&228-H/T/F Gyp

190

IFF-225&228-Prime and First Coat

1d

6/24/2026

6/24/2026

IFF-225&228-Prime and First Coat

191

IFF-225&228-Install ACT Ceilings

1d

6/25/2026

6/25/2026

IFF-225&228-Install ACT Ceilings

192

IFF-225&228-MEP Trim Out Walls & Ceilings

4d

6/26/2026

7/1/2026

IFF-225&228-MEP Trim Out Walls & Ceilings

193

IFF-225&228-White out Ceiling

1d

7/2/2026

7/2/2026

IFF-225&228-White out Ceiling

194

IFF-225&228-Polish Concrete

6d

7/6/2026

7/13/2026

IFF-225&228-Polish Concrete

195

IFF-225&228-Final Paint Walls

2d

7/14/2026

7/15/2026

IFF-225&228-Final Paint Walls

196

IFF-225&228-Install Base

1d

7/16/2026

7/16/2026

IFF-225&228-Install Base

197

IFF-225&228-Final Clean

3d

7/17/2026

7/21/2026

IFF-225&228-Final Clean

27d

5/27/2026

7/2/2026

Room 222- Classroom Improvements

A 9

S 6

2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12

198

IFF-222-Owner Move

1d

5/27/2026

5/27/2026

IFF-222-Owner Move

199

IFF-222-Abatement of Flooring

4d

5/28/2026

6/2/2026

IFF-222-Abatement of Flooring

200

IFF-222-MEP Ceiling Safe Off

1d

6/3/2026

6/3/2026

IFF-222-MEP Ceiling Safe Off

201

IFF-222-Demo Ceiling

2d

6/4/2026

6/5/2026

IFF-222-Demo Ceiling

202

IFF-222-Clean Gyp Demo

2d

6/8/2026

6/9/2026

IFF-222-Clean Gyp Demo

203

IFF-222-Set new Door Frame

2d

6/10/2026

6/11/2026

IFF-222-Set new Door Frame

204

IFF-222-H/T/F Gyp

5d

6/12/2026

6/18/2026

IFF-222-H/T/F Gyp

205

IFF-222-Install New ACT

2d

6/19/2026

6/22/2026

IFF-222-Install New ACT

206

IFF-222-MEP Ceiling Rough in

3d

6/23/2026

6/25/2026

IFF-222-MEP Ceiling Rough in

207

IFF-222-White out Ceilings

1d

6/26/2026

6/26/2026

IFF-222-White out Ceilings

208

IFF-222-Install New Carpet & Base

3d

6/29/2026

7/1/2026

IFF-222-Install New Carpet & Base

209

IFF-222-Final Clean

1d

7/2/2026

7/2/2026

IFF-222-Final Clean

Room 214- Classroom Improvements

10d

6/4/2027

6/17/2027

210

IFF-214-Clean Demo Gyp and Door Frame

1d

6/4/2027

6/4/2027

IFF-214-Clean Demo Gyp and Door Frame

211

IFF-214-Reinstall Door Frame

2d

6/7/2027

6/8/2027

IFF-214-Reinstall Door Frame

212

IFF-214-H/T/F Gyp

5d

6/9/2027

6/15/2027

IFF-214-H/T/F Gyp

213

IFF-214-Final Paint Interior

2d

6/16/2027

6/17/2027

IFF-214-Final Paint Interior

Room 212- Classroom Improvements

10d

6/4/2027

6/17/2027

214

IFF-212-Clean Demo Gyp and Door Frame

1d

6/4/2027

6/4/2027

IFF-212-Clean Demo Gyp and Door Frame

215

IFF-212-Reinstall Door Frame

2d

6/7/2027

6/8/2027

IFF-212-Reinstall Door Frame

216

IFF-212-H/T/F Gyp

5d

6/9/2027

6/15/2027

IFF-212-H/T/F Gyp

217

IFF-212-Final Paint Interior

2d

6/16/2027

6/17/2027

IFF-212-Final Paint Interior

36d

5/26/2026

7/15/2026

300 Level Classroom Improvements

36d

5/26/2026

7/15/2026

218

Room 317 - Classroom Improvements IFF-317-Owner Move

2d

5/26/2026

5/27/2026

IFF-317-Owner Move

219

IFF-317-MEP Safe Off

1d

5/28/2026

5/28/2026

IFF-317-MEP Safe Off

220

IFF-317-Clean Demo Gyp, Casework, Floor

4d

5/29/2026

6/3/2026

IFF-317-Clean Demo Gyp, Casework, Floor

221

IFF-317-Install ACT

2d

6/4/2026

6/5/2026

IFF-317-Install ACT

222

IFF-317-MEP Rough in Ceilings and Walls

5d

6/8/2026

6/12/2026

IFF-317-MEP Rough in Ceilings and Walls

Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School

Job #: Fairview High School

Rev. date: 10/17/2025 12:41:16 PM

Data Date: 10/17/2025

Page 7 of 13

3. Print View Filter: No Summary Tasks

J 10

A 7

S 4

Line

Name

Duration

APC

Start

Finish

A 12

S 9

2024 O N 7 4

D 2

2025 J F M A M J J 30 27 24 24 21 19 16 14

A 11

S 8

O 6

2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13

A 10

S 7

O 5

N 2

223

IFF-317-H/T/F Gyp

8d

6/15/2026

6/24/2026

IFF-317-H/T/F Gyp

224

IFF-317-Prime and First Coat

2d

6/25/2026

6/26/2026

IFF-317-Prime and First Coat

225

IFF-317-Install Casework

3d

6/29/2026

7/1/2026

IFF-317-Install Casework

226

IFF-317-MEP Trim Out

3d

7/2/2026

7/7/2026

IFF-317-MEP Trim Out

227

IFF-317-Install LVT

3d

7/8/2026

7/10/2026

IFF-317-Install LVT

228

IFF-317-Final Paint

1d

7/13/2026

7/13/2026

IFF-317-Final Paint

229

IFF-317-Install Base

1d

7/14/2026

7/14/2026

IFF-317-Install Base

230

IFF-317-Final Clean

1d

7/15/2026

7/15/2026

IFF-317-Final Clean

42d

5/26/2026

7/23/2026

400 Level Classroom Improvements Room 408 - Science Classroom Improvements

2027 D J F M A M J J 30 28 25 22 22 19 17 14 12

42d

5/26/2026

7/23/2026

231

IFF-408-Owner Move

1d

5/26/2026

5/26/2026

IFF-408-Owner Move

232

IFF-408-MEP Safe off

1d

5/27/2026

5/27/2026

IFF-408-MEP Safe off

233

IFF-408- Clean Demo Casework and Gyp & Ceiling

3d

5/28/2026

6/1/2026

IFF-408- Clean Demo Casework and Gyp & Ceiling

234

IFF-408-Abatement of Flooring and Tops

6d

6/2/2026

6/9/2026

IFF-408-Abatement of Flooring and Tops

235

IFF-408-MEP Rough in & Hood Prep

5d

6/10/2026

6/16/2026

IFF-408-MEP Rough in & Hood Prep

236

IFF-Build Chase Wall

4d

6/17/2026

6/22/2026

IFF-Build Chase Wall

237

IFF-408-H/T/F Gyp

4d

6/23/2026

6/26/2026

IFF-408-H/T/F Gyp

238

IFF-408-Prime and First Coat

1d

6/29/2026

6/29/2026

IFF-408-Prime and First Coat

239

IFF-408-Install ACT

1d

6/30/2026

6/30/2026

IFF-408-Install ACT

240

IFF-408-MEP Ceiling Trim Out

3d

7/1/2026

7/6/2026

IFF-408-MEP Ceiling Trim Out

241

IFF-408-White out Ceiling

1d

7/7/2026

7/7/2026

IFF-408-White out Ceiling

242

IFF-408-Install Casework & Hood

3d

7/8/2026

7/10/2026

IFF-408-Install Casework & Hood

243

IFF-408-MEP Trim Out

3d

7/8/2026

7/10/2026

IFF-408-MEP Trim Out

244

IFF-408-Polish Flooring

6d

7/13/2026

7/20/2026

IFF-408-Polish Flooring

245

IFF-408-Final Clean

3d

7/21/2026

7/23/2026

IFF-408-Final Clean

26d

5/26/2026

6/30/2026

Room 420 - Science Classroom Improvements 246

IFF-420-Owner Move

1d

5/26/2026

5/26/2026

IFF-420-Owner Move

247

IFF-420-MEP Safe/ Disconnect Hood

2d

5/27/2026

5/28/2026

IFF-420-MEP Safe/ Disconnect Hood

248

IFF-420-MEP Safe off of Ceiling Devices

1d

5/29/2026

5/29/2026

IFF-420-MEP Safe off of Ceiling Devices

249

IFF-420-Demo Ceiling in Room

1d

6/1/2026

6/1/2026

IFF-420-Demo Ceiling in Room

250

IFF-420-Demo Duct Above Ceiling

2d

6/2/2026

6/3/2026

IFF-420-Demo Duct Above Ceiling

251

IFF-420-Patch Roof Penetration

2d

6/4/2026

6/5/2026

IFF-420-Patch Roof Penetration

252

IFF-420-Install Grid

2d

6/8/2026

6/9/2026

IFF-420-Install Grid

253

IFF-420-MEP Install Ceiling Devices

3d

6/10/2026

6/12/2026

IFF-420-MEP Install Ceiling Devices

254

IFF-420-White Out Ceiling

2d

6/15/2026

6/16/2026

IFF-420-White Out Ceiling

255

IFF-420-Final Clean

10d

6/17/2026

6/30/2026

IFF-420-Final Clean

14d

5/27/2026

6/15/2026

Room 414- Science Classroom Improvements 256

IFF-414-Swap out Lights

3d

5/27/2026

5/29/2026

IFF-414-Swap out Lights

257

IFF-414-Electrical rough in for Teaching Wall

3d

6/1/2026

6/3/2026

IFF-414-Electrical rough in for Teaching Wall

258

IFF-414-AV Teaching wall hook ups

3d

6/4/2026

6/8/2026

IFF-414-AV Teaching wall hook ups

259

IFF-414-Final Clean

5d

6/9/2026

6/15/2026

IFF-414-Final Clean

Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School

Job #: Fairview High School

Rev. date: 10/17/2025 12:41:16 PM

Data Date: 10/17/2025

Page 8 of 13

A 9

S 6

2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12

3. Print View Filter: No Summary Tasks

J 10

A 7

S 4

Line

Name

Duration

Room 421- Science Classroom Improvements

APC

Start

Finish

A 12

S 9

2024 O N 7 4

D 2

2025 J F M A M J J 30 27 24 24 21 19 16 14

A 11

S 8

O 6

2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13

A 10

S 7

O 5

N 2

2027 D J F M A M J J 30 28 25 22 22 19 17 14 12

12d

5/27/2026

6/11/2026

260

IFF-421-Swap out Lights

3d

5/27/2026

5/29/2026

IFF-421-Swap out Lights

261

IFF-421-Electrical rough in for Teaching Wall

3d

6/1/2026

6/3/2026

IFF-421-Electrical rough in for Teaching Wall

262

IFF-421-AV Teaching wall hook ups

3d

6/4/2026

6/8/2026

IFF-421-AV Teaching wall hook ups

263

IFF-421-Lower Counter Top

2d

6/9/2026

6/10/2026

IFF-421-Lower Counter Top

264

IFF-421-Final Clean

1d

6/11/2026

6/11/2026

IFF-421-Final Clean

11d

5/26/2026

6/9/2026

Room 422- Science Classroom Improvements 265

IFF-422-Lower Counter Top

2d

5/26/2026

5/27/2026

IFF-422-Lower Counter Top

266

IFF-422-Swap out Lights

3d

5/27/2026

5/29/2026

IFF-422-Swap out Lights

267

IFF-422-Electrical rough in for Teaching Wall

3d

6/1/2026

6/3/2026

IFF-422-Electrical rough in for Teaching Wall

268

IFF-422-AV Teaching wall hook ups

3d

6/4/2026

6/8/2026

IFF-422-AV Teaching wall hook ups

269

IFF-422-Final Clean

1d

6/9/2026

6/9/2026

IFF-422-Final Clean

7d

6/1/2026

6/9/2026

Room 424- Science Classroom Improvements 270

IFF-424-Electrical rough in for Teaching Wall

3d

6/1/2026

6/3/2026

IFF-424-Electrical rough in for Teaching Wall

271

IFF-424-AV Teaching wall hook ups

3d

6/4/2026

6/8/2026

IFF-424-AV Teaching wall hook ups

272

IFF-424-Final Clean

1d

6/9/2026

6/9/2026

IFF-424-Final Clean

9d

6/1/2026

6/11/2026

Room 430- Science Classroom Improvements 273

IFF-430-Swap out Lights

2d

6/1/2026

6/2/2026

IFF-430-Swap out Lights

274

IFF-430-Electrical rough in for Teaching Wall

3d

6/3/2026

6/5/2026

IFF-430-Electrical rough in for Teaching Wall

275

IFF-430-AV Teaching wall hook ups

3d

6/8/2026

6/10/2026

IFF-430-AV Teaching wall hook ups

276

IFF-430-Final Clean

1d

6/11/2026

6/11/2026

IFF-430-Final Clean

9d

6/1/2026

6/11/2026

Room 432- Science Classroom Improvements 277

IFF-432-Swap out Lights

2d

6/1/2026

6/2/2026

IFF-432-Swap out Lights

278

IFF-432-Electrical rough in for Teaching Wall

3d

6/3/2026

6/5/2026

IFF-432-Electrical rough in for Teaching Wall

279

IFF-432-AV Teaching wall hook ups

3d

6/8/2026

6/10/2026

IFF-432-AV Teaching wall hook ups

280

IFF-432-Final Clean

1d

6/11/2026

6/11/2026

IFF-432-Final Clean

7d

6/3/2026

6/11/2026

Room 425- Science Classroom Improvements 281

IFF-435-Electrical rough in for Teaching Wall

3d

6/3/2026

6/5/2026

IFF-435-Electrical rough in for Teaching Wall

282

IFF-435-AV Teaching wall hook ups

3d

6/8/2026

6/10/2026

IFF-435-AV Teaching wall hook ups

283

IFF-435-Final Clean

1d

6/11/2026

6/11/2026

IFF-435-Final Clean

7d

6/3/2026

6/11/2026

Room 426- Science Classroom Improvements 284

IFF-426-Electrical rough in for Teaching Wall

3d

6/3/2026

6/5/2026

IFF-426-Electrical rough in for Teaching Wall

285

IFF-426-AV Teaching wall hook ups

3d

6/8/2026

6/10/2026

IFF-426-AV Teaching wall hook ups

286

IFF-426-Final Clean

1d

6/11/2026

6/11/2026

IFF-426-Final Clean

11d

6/3/2026

6/17/2026

Room 402- Science Classroom Improvements 287

IFF-402-Swap out Lights

2d

6/3/2026

6/4/2026

IFF-402-Swap out Lights

288

IFF-402-Electrical rough in for Teaching Wall

3d

6/5/2026

6/9/2026

IFF-402-Electrical rough in for Teaching Wall

289

IFF-402-AV Teaching wall hook ups

3d

6/10/2026

6/12/2026

IFF-402-AV Teaching wall hook ups

290

IFF-402-Lower Counter Top

2d

6/15/2026

6/16/2026

IFF-402-Lower Counter Top

291

IFF-402-Final Clean

1d

6/17/2026

6/17/2026

IFF-402-Final Clean

11d

6/3/2026

6/17/2026

Room 405- Science Classroom Improvements

Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School

Job #: Fairview High School

Rev. date: 10/17/2025 12:41:16 PM

Data Date: 10/17/2025

Page 9 of 13

A 9

S 6

2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12

3. Print View Filter: No Summary Tasks

J 10

A 7

S 4

Line

Name

Duration

APC

Start

Finish

A 12

S 9

2024 O N 7 4

D 2

2025 J F M A M J J 30 27 24 24 21 19 16 14

A 11

S 8

O 6

2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13

A 10

S 7

O 5

N 2

2027 D J F M A M J J 30 28 25 22 22 19 17 14 12

292

IFF-405-Swap out Lights

2d

6/3/2026

6/4/2026

IFF-405-Swap out Lights

293

IFF-405-Electrical rough in for Teaching Wall

3d

6/5/2026

6/9/2026

IFF-405-Electrical rough in for Teaching Wall

294

IFF-405-AV Teaching wall hook ups

3d

6/10/2026

6/12/2026

IFF-405-AV Teaching wall hook ups

295

IFF-405-Lower Counter Top

2d

6/15/2026

6/16/2026

IFF-405-Lower Counter Top

296

IFF-405-Final Clean

1d

6/17/2026

6/17/2026

IFF-405-Final Clean

9d

6/5/2026

6/17/2026

Room 411- Science Classroom Improvements 297

IFF-411-Swap out Lights

2d

6/5/2026

6/8/2026

IFF-411-Swap out Lights

298

IFF-411-Electrical rough in for Teaching Wall

3d

6/9/2026

6/11/2026

IFF-411-Electrical rough in for Teaching Wall

299

IFF-411-AV Teaching wall hook ups

3d

6/12/2026

6/16/2026

IFF-411-AV Teaching wall hook ups

300

IFF-411-Final Clean

1d

6/17/2026

6/17/2026

IFF-411-Final Clean

Library Improvements

19d

5/26/2026

6/19/2026

301

IFF-LI-Owner Move Furnature

8d

5/26/2026

6/4/2026

IFF-LI-Owner Move Furnature

302

IFF-LI-Clean Demo Existing Carpet

5d

6/5/2026

6/11/2026

IFF-LI-Clean Demo Existing Carpet

303

IFF-LI-Install New Carpet

5d

6/12/2026

6/18/2026

IFF-LI-Install New Carpet

304

IFF-LI- Final Clean

1d

6/19/2026

6/19/2026

IFF-LI- Final Clean

37d

5/26/2026

7/16/2026

900 Level - Senior Lounge Improvements

37d

5/26/2026

7/16/2026

305

RTU Replacement - Commons 1001 & 1002 IFF-MU-Owner Move

1d

5/26/2026

5/26/2026

IFF-MU-Owner Move

306

IFF-MU-MEP Safeoff RTU's

2d

5/27/2026

5/28/2026

IFF-MU-MEP Safeoff RTU's

307

IFF-MU-Install Scaffolding

3d

5/27/2026

5/29/2026

IFF-MU-Install Scaffolding

308

IFF-MU-Demo Ceilings Below RTU's

3d

6/1/2026

6/3/2026

IFF-MU-Demo Ceilings Below RTU's

309

IFF-MU-Demo Existing Duct and Move MEP

3d

6/4/2026

6/8/2026

IFF-MU-Demo Existing Duct and Move MEP

310

IFF-MU-Demo Old RTU's & ACCU's

1d

6/9/2026

6/9/2026

IFF-MU-Demo Old RTU's & ACCU's

311

IFF-MU-Install Supporting Steel

5d

6/10/2026

6/16/2026

IFF-MU-Install Supporting Steel

312

IFF-MU-Set New RTU's

1d

6/17/2026

6/17/2026

IFF-MU-Set New RTU's

313

IFF-MU-Set New ACCU

1d

6/18/2026

6/18/2026

IFF-MU-Set New ACCU

314

IFF-MU-MEP connections to new Units

4d

6/19/2026

6/24/2026

IFF-MU-MEP connections to new Units

315

IFF-MU-Install New Duct Below Unit

8d

6/25/2026

7/7/2026

IFF-MU-Install New Duct Below Unit

316

IFF-MU-Install Ceiling Grid

2d

7/8/2026

7/9/2026

IFF-MU-Install Ceiling Grid

317

IFF-MU-MEP Device Ceiling

2d

7/10/2026

7/13/2026

IFF-MU-MEP Device Ceiling

318

IFF-MU-White Out Ceiling

2d

7/14/2026

7/15/2026

IFF-MU-White Out Ceiling

319

IFF-MU-Final Clean

1d

7/16/2026

7/16/2026

IFF-MU-Final Clean

69d

3/23/2026

6/26/2026

Gymnasium Improvements

69d

3/23/2026

6/26/2026

320

Gymnasium Improvements - RTU 901 IFF-GYM-Install New Gas Line

5d

3/23/2026

3/27/2026

IFF-GYM-Install New Gas Line

321

IFF-GYM-Grade and Prep for RTU Pad

5d

3/30/2026

4/3/2026

IFF-GYM-Grade and Prep for RTU Pad

322

IFF-GYM-F/R/P Footers for RTU

4d

4/6/2026

4/9/2026

IFF-GYM-F/R/P Footers for RTU

323

IFF-GYM-Lay Block to 100

4d

4/10/2026

4/15/2026

IFF-GYM-Lay Block to 100

324

IFF-GYM-F/R/P Pad

2d

4/16/2026

4/17/2026

IFF-GYM-F/R/P Pad

325

IFF-GYM-Build Masonry Enclosure

6d

4/20/2026

4/27/2026

IFF-GYM-Build Masonry Enclosure

326

IFF-GYM-Set Gym RTU 901

1d

5/8/2026

5/8/2026

IFF-GYM-Set Gym RTU 901

Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School

Job #: Fairview High School

Rev. date: 10/17/2025 12:41:16 PM

Data Date: 10/17/2025

Page 10 of 13

A 9

S 6

2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12

3. Print View Filter: No Summary Tasks

J 10

A 7

S 4

Line

Name

Duration

APC

Start

Finish

A 12

S 9

2024 O N 7 4

D 2

2025 J F M A M J J 30 27 24 24 21 19 16 14

A 11

S 8

O 6

2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13

A 10

S 7

O 5

N 2

2027 D J F M A M J J 30 28 25 22 22 19 17 14 12

327

IFF-GYM- Electrical & Control Connections to RTU 901

8d

5/11/2026

5/20/2026

IFF-GYM- Electrical & Control Connections to RTU 901

328

IFF-GYM-Demo Existing MEP

2d

5/21/2026

5/22/2026

IFF-GYM-Demo Existing MEP

329

IFF-GYM-Install Flooring Protection

3d

5/26/2026

5/28/2026

IFF-GYM-Install Flooring Protection

330

IFF-GYM- Demo Old RTUs & Structure

5d

5/26/2026

6/1/2026

IFF-GYM- Demo Old RTUs & Structure

331

IFF-GYM- Cut & Reinforce for Duct Penetrations

6d

5/29/2026

6/5/2026

IFF-GYM- Cut & Reinforce for Duct Penetrations

332

IFF-GYM-Install New Duct for 901

7d

6/8/2026

6/16/2026

IFF-GYM-Install New Duct for 901

333

IFF-GYM-Install Removed MEP

3d

6/17/2026

6/19/2026

IFF-GYM-Install Removed MEP

334

IFF-GYM-Remove Floor Protection

3d

6/22/2026

6/24/2026

IFF-GYM-Remove Floor Protection

335

IFF-GYM-Final Clean

2d

6/25/2026

6/26/2026

IFF-GYM-Final Clean

84d

3/23/2026

7/20/2026

Electrical Upgrades

13d

5/27/2026

6/12/2026

336

Electrical Upgrades - BRA IFF-EU-Shut Down and Safeoff MDC

2d

5/27/2026

5/28/2026

IFF-EU-Shut Down and Safeoff MDC

337

IFF-EU-Demo BRA

2d

5/29/2026

6/1/2026

IFF-EU-Demo BRA

338

IFF-EU-Install New BRA

5d

6/2/2026

6/8/2026

IFF-EU-Install New BRA

339

IFF-EU-Test and Inspect

3d

6/9/2026

6/11/2026

IFF-EU-Test and Inspect

340

IFF-EU-Energize MDC

1d

6/12/2026

6/12/2026

IFF-EU-Energize MDC

Fire Alarm Upgrades

46d

4/29/2026

7/2/2026

341

IFF-FAU-Early Fire Alarm Wire Pull (Spring Break Start Night Work)

20d

4/29/2026

5/27/2026

IFF-FAU-Early Fire Alarm Wire Pull (Spring Break Start Night Work)

342

IFF-FAU-EM Battery Pack Replacements (Night Work)

10d

5/13/2026

5/27/2026

IFF-FAU-EM Battery Pack Replacements (Night Work)

343

IFF-FAU-Install New Devices

5d

5/28/2026

6/3/2026

IFF-FAU-Install New Devices

344

IFF-FAU-Demo Old Panel

5d

5/28/2026

6/3/2026

IFF-FAU-Demo Old Panel

345

IFF-FAU-Install New Panel and Terminate

10d

6/4/2026

6/17/2026

IFF-FAU-Install New Panel and Terminate

346

IFF-FAU-Program Panel

5d

6/18/2026

6/24/2026

IFF-FAU-Program Panel

347

IFF-FAU-Test Fire Alarm Panel

6d

6/25/2026

7/2/2026

PA Sound System Upgrades

84d

3/23/2026

7/20/2026

IFF-EU-Pull new Wire for Speakers (Spring Break Start Night work)

10d

3/23/2026

4/3/2026

349

IFF-EU-Install New Speakers

1d

5/26/2026

5/26/2026

IFF-EU-Install New Speakers

350

IFF-EU-Install New Head End

2d

5/27/2026

5/28/2026

IFF-EU-Install New Head End

351

IFF-EU-Test New Head End and Speakers

6d

5/29/2026

6/5/2026

352

IFF-EU-Final Clean

30d

6/8/2026

7/20/2026

Mechanical Upgrades

22d

5/26/2026

6/24/2026

2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12

IFF-EU-Pull new Wire for Speakers (Spring Break Start Night work)

IFF-EU-Test New Head End and Speakers

IFF-EU-Final Clean

22d

5/26/2026

6/24/2026

353

IFF-WHR-MEP Safeoff Water Heaters

2d

5/26/2026

5/27/2026

IFF-WHR-MEP Safeoff Water Heaters

354

IFF-WHR-Demo Existing Water Heaters

5d

5/28/2026

6/3/2026

IFF-WHR-Demo Existing Water Heaters

355

IFF-WHR-Install New Water Heaters and Associated Piping

2d

6/4/2026

6/5/2026

IFF-WHR-Install New Water Heaters and Associated Piping

356

IFF-WHR-Hook up Electrical

6d

6/8/2026

6/15/2026

IFF-WHR-Hook up Electrical

357

IFF-WHR-Hook up Controls

2d

6/16/2026

6/17/2026

IFF-WHR-Hook up Controls

358

IFF-WHR- Test Controls

5d

6/18/2026

6/24/2026

IFF-WHR- Test Controls

Exterior Facaad Improvements

42d

5/26/2026

7/23/2026

800 Level - Exterior Windows

42d

5/26/2026

7/23/2026

Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School

S 6

IFF-FAU-Test Fire Alarm Panel

348

Water Heater Replacement

A 9

Job #: Fairview High School

Rev. date: 10/17/2025 12:41:16 PM

Data Date: 10/17/2025

Page 11 of 13

3. Print View Filter: No Summary Tasks

J 10

A 7

S 4

Line

Name

Duration

APC

Start

Finish

A 12

S 9

2024 O N 7 4

D 2

2025 J F M A M J J 30 27 24 24 21 19 16 14

A 11

S 8

O 6