BVSD Board of Education · Document
Exhibits BVSD Fairview High School Amendment Package No. 2.pdf (3,726 KB)
Regular Meeting, November 18, 2025 · item 8.9: Amendment to the contract for Fairview High School · 135 pages
This is the text extracted from the file, without its layout, tables, or images. Use the original for anything that matters.
Exhibit A Drawings, specifications and documents used to prepare the GMP
First Amendment to CM/GC Agreement With Turner Construction Company, dated April 25, 2017
Printed on Mon Nov 3, 2025 at 09:11 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction
Current Drawings Drawing No.
Drawing Title
Revision
Drawing Date
Received Date
Set
Cover Sheet CS-001
COVER SHEET
0
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
G-001
CODE COMPLIANCE - CODE DATA AND LOWER LEVELS
1
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
G-002
CODE COMPLIANCE - CODE DATA AND LOWER LEVELS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
G-003
CODE COMPLIANCE - MIDDLE LEVELS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
G-004
CODE COMPLIANCE - UPPER LEVELS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
L1.0
OVERALL SITE PLAN
4
09/25/2025
25.09.25 - Addendum #1 (09/25/25)
L2.0
SITE DETAILS
3
09/25/2025
25.09.25 - Addendum #1 (09/25/25)
LI1.0
IRRIGATION PLAN
4
09/25/2025
25.09.25 - Addendum #1 (09/25/25)
LI1.1
IRRIGATION PLAN
3
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
LI2.0
IRRIGATION DETAILS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
C0.1
LEGEND NOTES & ABBREVIATIONS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
C0.2
DEMOLITION PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
C0.3
ALTERNATE 5-IS-7 DEMOLITION PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
C1.0
GRADING AND DRAINAGE PLAN
3
10/01/2025
25.10.01 - Addendum #2 (10/01/25)
C1.1
ALTERNATE 5-IS-7 GRADING AND DRAINAGE PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
C2.0
GAS LINE PLAN (SHOWN FOR REFERENCE ONLY)
1
10/01/2025
25.10.01 - Addendum #2 (10/01/25)
C2.1
GAS & ELECTRIC LINE PLAN (SHOWN FOR REFERENCE ONLY)
0
10/01/2025
25.10.01 - Addendum #2 (10/01/25)
C3.0
HORIZONTAL CONTROL PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
C3.1
ALTERNATE 5-IS-7 HORIZONTAL CONTROL PLAN
3
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
CD1.0
GRADING AND DRAINAGE DETAILS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
CD3.0
HORIZONTAL CONTROL DETAILS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
CD3.1
HORIZONTAL CONTROL DETAILS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
CE1.0
EROSION CONTROL PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
CE1.1
ALTERNATE 5-IS-7 EROSION CONTROL PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
CE1.2
EROSION CONTROL DETAILS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
CE1.3
EROSION CONTROL DETAILS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
CE1.4
EROSION CONTROL DETAILS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
S-001
GENERAL NOTES
1
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
S-101A
PARTIAL PLANS AND DETAILS -
3
10/01/2025
25.10.01 - Addendum #2 (10/01/25)
General
Landscape
Civil
Structural
Page 1 of 6
Printed on Mon Nov 3, 2025 at 09:11 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction
Drawing No.
Drawing Title
Revision
Drawing Date
Received Date
Set
S-101B
PARTIAL PLANS AND DETAILS - COMPUTER
2
09/25/2025
25.09.25 - Addendum #1 (09/25/25)
S-101C
PARTIAL PLANS AND DETAILS -
1
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
A-100
OVERALL FLOOR PLANS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
A-101
LOWER LEVEL OVERALL FLOOR PLAN
4
10/01/2025
25.10.01 - Addendum #2 (10/01/25)
A-102
MIDDLE LEVEL OVERALL FLOOR PLAN
3
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
A-103
UPPER LEVEL OVERALL FLOOR PLAN
3
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
A-104
900 LEVEL GYMNASIUM FLOOR PLAN
3
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
A-111
LOWER LEVEL RCP
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
A-112
MIDDLE LEVEL OVERALL RCP
3
10/01/2025
25.10.01 - Addendum #2 (10/01/25)
A-113
UPPER LEVEL OVERALL RCP
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
A-121
PARTIAL ROOF PLAN
4
09/25/2025
25.09.25 - Addendum #1 (09/25/25)
A-201
EXTERIOR BUILDING ELEVATIONS
3
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
A-361
EXTERIOR SECTION DETAILS
4
10/01/2025
25.10.01 - Addendum #2 (10/01/25)
A-415
LARGE SCALE FLOOR PLANS - CTE COMPUTER LAB 225
3
09/25/2025
25.09.25 - Addendum #1 (09/25/25)
A-416
LARGE SCALE FLOOR PLANS - CLASSROOM 317
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
A-417
LARGE SCALE FLOOR PLANS - NEW CHEMISTRY 408 - ENLARGED PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
A-418
LARGE SCALE FLOOR PLANS - LIBRARY 450
3
10/01/2025
25.10.01 - Addendum #2 (10/01/25)
A-451
INTERIOR ELEVATIONS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
A-501
INTERIOR DETAILS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
A-601
DOOR AND WINDOW SCHEDULES
4
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
A-700
ROOM FINISH SCHEDULE &
3
10/01/2025
25.10.01 - Addendum #2 (10/01/25)
A-701
LOWER LEVEL OVERALL FINISH PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
A-702
MIDDLE LEVEL OVERALL FINISHPLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
A-703
UPPER LEVEL OVERALL FINISH PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
AD-100
OVERALL DEMOLITION FLOOR PLANS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
AD-101
LOWER LEVEL FLOOR PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
AD-102
MIDDLE LEVEL DEMOLITION FLOOR PLAN
3
10/01/2025
25.10.01 - Addendum #2 (10/01/25)
AD-103
UPPER LEVEL DEMOLITION FLOOR PLAN
3
10/01/2025
25.10.01 - Addendum #2 (10/01/25)
AD-104
900 LEVEL GYMNASIUM DEMOLITION FLOOR PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
AD-111
OVERALL DEMOLITION RCP
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
AD-112
OVERALL DEMOLITION RCP
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
AD-113
OVERALL DEMOLITION RCP
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
AD-121
PARTIAL DEMOLITION ROOF PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
AD-415
PLANS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
AS-101
ARCHITECTURAL SITE PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
AS-501
ARCHITECTURAL SITE PLAN DETAILS
5
09/25/2025
25.09.25 - Addendum #1 (09/25/25)
Architectural
Fire Protection Page 2 of 6
Printed on Mon Nov 3, 2025 at 09:11 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction
Drawing No.
Drawing Title
Revision
Drawing Date
Received Date
Set
FP-001
FIRE PROTECTION GENERAL INFORMATION
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FP-102
200 LEVEL FIRE PROTECTION PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FP-103
300 LEVEL FIRE PROTECTION PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FP-104.1
400 LEVEL FIRE PROTECTION PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FP-106.1
600 LEVEL FIRE PROTECTION PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FP-106.2
1100 LEVEL CORE FIRE PROTECTION PLANS
0
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FP-109.4
900 LEVEL GYMNASIUM FIRE PROTECTION PLAN
0
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FPD-102
200 LEVEL FIRE PROTECTION DEMOLITION PLAN
1
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FPD-103
300 LEVEL FIRE PROTECTION DEMOLITION PLAN
1
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FPD-104.1
400 LEVEL FIRE PROTECTION DEMOLITION PLAN
1
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FPD-106.1
600 LEVEL FIRE PROTECTION DEMOLITION PLAN
1
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FPD-106.2
1100 LEVEL CORE FIRE PROTECTION DEMOLITION PLANS
0
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FPD-109.4
900 LEVEL GYMNASIUM FIRE PROTECTION DEMOLITION PLAN
1
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
P-001
PLUMBING GENERAL INFORMATION
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
P-002
PLUMBING SCHEDULES
3
10/01/2025
25.10.01 - Addendum #2 (10/01/25)
P-100
PLUMBING SITE PLAN
1
10/01/2025
25.10.01 - Addendum #2 (10/01/25)
P-103
300 LEVEL PLUMBING PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
P-104.1
400 LEVEL PLUMBING PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
P-109.4
900 LEVEL GYMNASIUM PLUMBING PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
P-401
ENLARGED PLUMBING PLANS - 400 LEVEL CHEMISTRY
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
P-402
ENLARGED PLUMBING DEMOLITION PLAN - BOILER ROOM
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
P-403
ENLARGED PLUMBING PLAN - BOILER ROOM
3
10/01/2025
25.10.01 - Addendum #2 (10/01/25)
P-601
PLUMBING DETAILS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
P-602
PLUMBING DETAILS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
P-603
PLUMBING DETAILS
0
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
PD-103
300 LEVEL PLUMBING DEMOLITION PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
M-001
MECHANICAL GENERAL INFORMATION
3
10/01/2025
25.10.01 - Addendum #2 (10/01/25)
M-002
MECHANICAL SCHEDULES
3
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
M-003
MECHANICAL SCHEDULES
3
10/01/2025
25.10.01 - Addendum #2 (10/01/25)
M-004
MECHANICAL COMPLIANCE
0
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
M-102
200 LEVEL MECHANICAL PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
M-103
300 LEVEL MECHANCIAL PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
M-104.1
400 LEVEL MECHANICAL PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
M-106.1
600 LEVEL MECHANCIAL PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
M-106.2
600/1100 LEVEL ADDITION & CORE MECHANCIAL PLANS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
M-109.4
900 LEVEL GYMNASIUM MECHANCIAL PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
Plumbing
Mechanical
Page 3 of 6
Printed on Mon Nov 3, 2025 at 09:11 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction
Drawing No.
Drawing Title
Revision
Drawing Date
Received Date
Set
M-110
1000 LEVEL CORE MECHANCIAL PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
M-140
OVERALL ROOF MECHANCIAL PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
M-401
MECHANICAL SECTIONS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
M-402
MECHANICAL SECTIONS
1
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
M-501
MECHANICAL SCHEMATICS
3
10/01/2025
25.10.01 - Addendum #2 (10/01/25)
M-502
MECHANICAL SCHEMATICS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
M-601
MECHANICAL DETAILS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
M-602
MECHANICAL DETAILS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
MD-102
200 LEVEL MECHANICAL DEMOLITION PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
MD-103
300 LEVEL MECHANICAL DEMOLITION PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
MD-104.1
400 LEVEL MECHANICAL DEMOLITION PLAN
0
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
MD-106.2
600/1100 LEVEL ADDITION & CORE MECHANICAL DEMOLITION PLANS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
MD-109.4
900 LEVEL GYMNASIUM MECHANICAL DEMOLITION PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
MD-110
1000 LEVEL CORE MECHANICAL DEMOLITION PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
MD-140
OVERALL ROOF MECHANICAL DEMOLITION PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
E-001
ELECTRICAL GENERAL INFORMATION
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
E-002
APPEARING HEREIN SHALL NOT BE DUPLICATED, DISCLOSED OR OTHERWISE USED WITHOUT THE WRITTEN CONSENT OF MOA ARCHITECTURE
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
E-003
ELECTRICAL SCHEDULES
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
E-004
ELECRICAL COMCHECK
0
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
E-100
ELECTRICAL SITE PLAN
3
09/25/2025
25.09.25 - Addendum #1 (09/25/25)
E-102
200 LEVEL POWER PLAN
3
09/25/2025
25.09.25 - Addendum #1 (09/25/25)
E-103
300 LEVLE POWER PLANS
0
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
E-104.1
400 LEVEL POWER PLAN
3
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
E-105.2
500 MEZZANINE LEVEL POWER PLAN
0
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
E-106.2
600/1100 LEVEL ADDITION & CORE POWER PLAN
1
07/25/2025
25.07.25 - Progress CD Set (07/25/ 25)
E-109.4
900 LEVEL GYMNASIUM POWER PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
E-110
1000 LEVEL CORE POWER PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
E-140
OVERALL ROOF POWER PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
E-202
200 LEVEL LIGHTING PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
E-203
300 LEVEL LIGHTING PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
E-204.1
400 LEVEL LIGHTING PLAN
3
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
E-206.1
600 LEVEL LIGHTING PLAN
0
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
E-401
ENLARGED ELECTRICAL PLAN - BOILER ROOM
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
E-501
ELECTRICAL ONE-LINE DIAGRAM
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
E-601
ELECTRICAL SCHEDULES
0
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
Electrical
Page 4 of 6
Printed on Mon Nov 3, 2025 at 09:11 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction
Drawing No.
Drawing Title
Revision
Drawing Date
Received Date
Set
E-602
ELECTRICAL SCHEDULES
0
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
E-603
ELECTRICAL SCHEDULES
0
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
ED-102
200 LEVEL POWER DEMOLITION PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
ED-104.1
400 LEVEL POWER DEMOLITION PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
ED-109.4
APPEARING HEREIN SHALL NOT BE DUPLICATED, DISCLOSED OR OTHERWISE USED WITHOUT THE WRITTEN CONSENT OF MOA ARCHITECTURE
0
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
ED-140
OVERALL ROOF POWER DEMOLITION PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
ED-202
200 LEVEL LIGHTING DEMOLITION PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
ED-203
300 LEVEL LIGHTING DEMOLITION PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
ED-204.1
400 LEVEL LIGHTING DEMOLITION PLAN
3
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
ED-206.1
600 LEVLE LIGHTING DEMOLITION PLAN
1
10/01/2025
25.10.01 - Addendum #2 (10/01/25)
ED-401
ENLARGED ELECTRICAL DEMOLITION PLAN - BOILER ROOM
3
10/01/2025
25.10.01 - Addendum #2 (10/01/25)
T-001
COMMUNICATIONS TITLE SHEET
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
T-002
COMMUNICATIONS PROJECT NOTES
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
T-003
COMMUNICATIONS SCHEDULES
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
T-101
100 LEVEL COMMUNICATIONS PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
T-102
200 LEVEL COMMUNICATIONS PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
T-103
300 LEVEL COMMUNICATIONS PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
T-104.1
400 LEVEL COMMUNICATIONS PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
T-104.2
400 LEVEL LIBRARY COMMUNICATIONS PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
T-105.1
500 LEVEL COMMUNICATIONS PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
T-105.2
500 MEZZANINE LEVEL COMMUNICATIONS PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
T-106.1
600 LEVEL COMMUNICATIONS PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
T-106.2
600/1100 LEVEL ADDITION & CORE COMMUNICATIONS PLANS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
T-107
700 LEVEL COMMUNICATIONS PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
T-108.1
800 LEVEL COMMUNICATIONS PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
T-109.1
900 LEVEL COMMUNICATIONS PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
T-109.4
900 LEVEL GYMNASIUM COMMUNICATIONS PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
T-110
1000 LEVEL COMMUNICATIONS PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
T-503
AUDIOVISUAL SYSTEM PLAN
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
T-601
COMMUNICATIONS DETAILS
2
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FA-001
FIRE ALARM GENERAL INFORMATION
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FA-101
100 LEVEL FIRE ALARM PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FA-102
200 LEVEL FIRE ALARM PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FA-103
300 LEVEL FIRE ALARM PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FA-104.1
400 LEVEL FIRE ALARM PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
Telecommunications
Fire Alarm
Page 5 of 6
Printed on Mon Nov 3, 2025 at 09:11 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction
Drawing Date
Received Date
Set
FA-104.2
Drawing No. 400 LEVEL LIBRARY FIRE ALARM PLAN
Drawing Title
Revision 2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FA-105.1
500 LEVEL FIRE ALARM PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FA-105.2
500 MEZZANINE LEVEL FIRE ALARM PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FA-106.1
600 LEVEL FIRE ALARM PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FA-106.2
600/1100 LEVEL ADDITION & CORE FIRE ALARM PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FA-107
700 LEVEL FIRE ALARM PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FA-108.1
800 LEVEL FIRE ALARM PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FA-109.1
900 LEVEL FIRE ALARM PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FA-109.2
900 LEVEL AUDITORIUM FIRE ALARM PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FA-109.4
900 LEVEL GYMNASIUM FIRE ALARM PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FA-110
1100 LEVEL CORE FIRE ALARM PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FAD-101
100 LEVEL FIRE ALARM DEMOLITION PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FAD-102
200 LEVEL FIRE ALARM DEMOLITION PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FAD-103
300 LEVEL FIRE ALARM DEMOLITION PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FAD-104.1
400 LEVEL FIRE ALARM DEMOLITION PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FAD-104.2
400 LEVEL LIBRARY FIRE ALARM DEMOLITION PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FAD-105.1
500 LEVEL FIRE ALARM DEMOLITION PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FAD-105.2
500 MEZZANINE LEVEL FIRE ALARM DEMOLITION PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FAD-106.1
600 LEVEL FIRE ALARM DEMOLITION PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FAD-106.2
600/1100 LEVEL ADDITION & CORE FIRE ALARM DEMOLITION PLANS
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FAD-107
700 LEVEL FIRE ALARM DEMOLITION PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FAD-108.1
800 LEVEL FIRE ALARM DEMOLITION PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FAD-109.1
900 LEVEL FIRE ALARM DEMOLITION PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FAD-109.2
900 LEVEL AUDITORIUM FIRE ALARM DEMOLITION PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FAD-109.4
900 LEVEL GYMNASIUM FIRE ALARM DEMOLITION PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
FAD-110
1000 LEVEL CORE FIRE ALARM DEMOLITION PLAN
2
09/12/2025
09/12/2025
25.09.12 - 100% CD Set (09/12/25)
Page 6 of 6
Printed on Mon Nov 3, 2025 at 09:12 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction
Current Specifications Number
Description
Revision
Issued Date
Received Date
Set
00 - Procurement and Contracting Requirements 00 1000
Performance Bond MOA
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
00 1100
Labor and Material Payment Bond MOA
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
00 1300
Asbestos Management Plan Contractor Responsibility MOA
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
00 1400
Lead Based Paint Contractor Responsibility MOA
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
000107
Seals Page
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
000110
Table of Contents
2
09/12/25
09/12/25
2025-09-12 - 100% CD Set
003100
Available Project Information
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
006000
Project Forms
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
006001
RFI Form
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
006002
Substitution Request Form
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
006003
Proposal Request Form
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
006004
ASI Form
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
006005
Construction Change Directive Form
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
01 - General Requirements 011000
Summary
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
012000
Price and Payment Procedures
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
012100
Allowances
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
012300
Alternates
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
012500
Substitution Procedures
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
013000
Administrative Requirements
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
013216
Construction Progress Schedule
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
014000
Quality Requirements
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
014216
Definitions and Explanations
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
015000
Temporary Facilities and Controls
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
016000
Product Requirements
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
016116
Volatile Organic Compound (VOC) Content Restrictions
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
017000
Execution and Closeout Requirements
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
017419
Construction Waste Management and Disposal
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
017610
Temporary Protective Coverings
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
017800
Closeout Submittals
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
017900
Demonstration and Training
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
02 - Existing Conditions
Page 1 of 6
Printed on Mon Nov 3, 2025 at 09:12 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction
Number 02 41 00
Description
Revision
Issued Date
Received Date
Set
Demoltion JVA
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
030100
Maintenance of Concrete
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
030516
Underslab Vapor Barrier
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
033511
Concrete Floor Finishes
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
040511
Masonry Mortaring and Grouting
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
042000
Unit Masonry
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
Metal Fabrications
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
03 - Concrete
04 - Masonry
05 - Metals 055000
06 - Wood, Plastics, and Composites 061000
Rough Carpentry
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
066100
Cast Polymer Fabrications
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
07 - Thermal and Moisture Protection 070150
Maintenance of Membrane Roofing
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
070553
Fire and Smoke Assembly Identification
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
071113
Bituminous Dampproofing MOA
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
071400
Fluid-Applied Waterproofing
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
071900
Water Repellents MOA
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
072100
Thermal Insulation MOA
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
072119
Foamed-In-Place Insulation
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
072500
Weather Barriers
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
074646
Fiber-Cement Siding
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
075300
Elastomeric Membrane Roofing
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
076200
Sheet Metal Flashing and Trim
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
077100
Roof Specialties
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
078400
Firestopping
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
079200
Joint Sealants
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
08 7100
Door Hardware
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
081113
Hollow Metal Doors and Frames
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
081416
Flush Wood Doors
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
083100
Access Doors and Panels
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
084313
Aluminum-Framed Storefronts
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
088000
Glazing
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
Common Work Results for Flooring Preparation
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
08 - Openings
09 - Finishes 090561
Page 2 of 6
Printed on Mon Nov 3, 2025 at 09:12 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction
Number
Description
Revision
Issued Date
Received Date
Set
092116
Gypsum Board Assemblies
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
095100
Acoustical Ceilings
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
096500
Resilient Flooring and Base
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
096813
Tile Carpeting
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
097200
Wall Coverings
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
098430
Sound-Absorbing Wall and Ceiling Units
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
099113
Exterior Painting
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
099123
Interior Painting
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
101100
Visual Display Units
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
101423
Panel Signage
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
102600
Wall and Door Protection
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
104400
Fire Protection Specialties
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
105617
Wall Mounted Standards and Shelving
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
113013
Residential Appliances MOA
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
118129
Facility Fall Protection
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
119900
Miscellaneous Equipment
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
10 - Specialties
11 - Equipment
12 - Furnishings 122400
Window Shades
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
123200
Manufactured Wood Casework
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
123600
Countertops
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
Fire Protection
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
22 0000
Basic Plumbing Requirements BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
22 0500
Common Work Results for Plumbing BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
22 0519
Meters and Gauges for Plumbing Piping BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
22 0523
General-Duty Valves for Plumbing Piping BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
22 0529
Hangers and Supports for Plumbing Piping and Equipment BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
22 0553
Identification for Plumbing Piping and Equipment BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
22 0700
Plumbing Insulation BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
22 1116
Domestic Water Piping BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
22 1119
Domestic Water Piping Specialties BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
22 1316
Sanitary Waste and Vent Piping BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
22 1319
Sanitary Waste Piping Specialties BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
22 1413
Storm Drainage Piping BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
21 - Fire Suppression 21 0500 22 - Plumbing
Page 3 of 6
Printed on Mon Nov 3, 2025 at 09:12 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction
Number
Description
Revision
Issued Date
Received Date
Set
22 3200
Water Heaters BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
22 4000
Plumbing Fixtures BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
22 6600
Laboratory Drainage Systems BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 - Heating, Ventilating, and Air Conditioning (HVAC) 23 0000
Basic Mechanical Requirements BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 0100
M&E Coordination BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 0500
Common Work Results for HVAC BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 0514
Motor Controllers BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 0515
Variable Frequency Controllers BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 0519
Meters and Gauges BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 0529
Supports and Anchors BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 0553
Mechanical Identification BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 0593
Testing, Adjusting, and Balancing BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 0700
Mechanical Insulation BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 0800
Commissioning of HVAC BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 0900
Direct Digital Control Systems BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 0902
Integrated Automation Control Sequence BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 1123
Natural Gas Systems BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 2113
Hydronic Piping BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 2300
Refrigerant Piping BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 3113
Metal Ductwork BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 3300
Ductwork Accessories BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 3413
Air Handling Fans BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 3600
Air Terminals BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 3713
Air Outlets and Inlets BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 6200
Condensing Units BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 7414
Rooftop Heating and Cooling Units BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
23 8200
Terminal Heat Units BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
26 0500
Basic Electrical Requirements BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
26 0510
Electrical Remodeling Provisions BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
26 0519
Building Wire and Cable BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
26 0526
Grounding and Bonding BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
26 0529
Supporting Devices and Seals BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
26 0532
Conduit BCER
1
09/25/25
09/25/25
2025-09-25 - Addendum #1 R1
26 0534
Electrical Boxes and Fittings BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
26 0553
Electrical Identification BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
26 - Electrical
Page 4 of 6
Printed on Mon Nov 3, 2025 at 09:12 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction
Number
Description
Revision
Issued Date
Received Date
Set
26 0580
Equipment Wiring Systems BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
26 0800
Commissioning of Electrical BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
26 0923
Lighting Control Devices BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
26 2416
Panelboards BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
26 2726
Wiring Devices BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
26 2816
Enclosed Switches BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
26 5100
Interior Lighting BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
26 7400
Electrical Communications Systems BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
27 - Communications 27 0010
Basic Communications Requirements BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
27 0020
Contractor Qualifications BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
27 0030
Bidding BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
27 0040
Warranty BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
27 0050
Quality Assurance BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
27 0060
Training BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
27 0405
Common Work - Sleeves, Penetrations, and Firestopping BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
27 0406
Common Work - Hangers and Supports BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
27 0500
Electrical Technology - General Requirements BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
27 0533
Electrical Technology - Conduit and Boxes BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
27 1000
Communications - General Requirements BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
27 1119
Communications - Termination Equipment BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
27 1500
Communications - Horizontal Cabling BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
27 1543
Communications - Faceplates and Connectors BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
27 1619
Communications - Patch Cords BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
27 1710
Communications - Identification BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
27 1720
Communications - Testing BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
27 4000
AudioVisual - General Requirements BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
27 5000
Public Address General Requirements BCER
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
31 00 00
Earthwork JVA
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
31 25 00
Erosion and Sedimentation Controls JVA
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
31 - Earthwork
32 - Exterior Improvements 32 12 00
Flexible Paving JVA
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
32 13 00
Ridid Paving JVA
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
32 9219
Seeding DCLA
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
320190
Operation and Maintenance of Planting
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
323113
Chain Link Fences
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
Page 5 of 6
Printed on Mon Nov 3, 2025 at 09:12 pm MST Job #: 8626 K1224-BVSD Fairview HS Remodel 1515 Greenbriar Blvd Boulder, Colorado 80305 Adolfson & Peterson Construction
Number
Description
Revision
Issued Date
Received Date
Set
328400
Irrigation
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
329113
Fine Grading and Soiling Preparation
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
329223
Sodding
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
329313
Inert Ground Cover Materials
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
329350
Landscape Maintenance
1
09/12/25
09/12/25
2025-09-12 - 100% CD Set
Storm Drainage Systems JVA
0
09/12/25
09/12/25
2025-09-12 - 100% CD Set
33 - Utilities 33 40 00
Page 6 of 6
Exhibit B Assumptions and clarifications made in preparing the GMP Clarifications in preparing the amendment
Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20
K1224 BVSD - FAIRVIEW HIGH SCHOOL 1515 Greenbriar Blvd., Boulder, CO, 80305 Estimate: CD Estimate Rev. 1
PREPARED FOR:
ARCHITECT / DESIGNER:
BVSD
MOA Architecture
DATE PRINTED: 10/29/2025
Page 1 of 35
Clarifications Report General Clarifications - Any deviation from the prime contract terms may result in different costs and pricing. - Any delays or cost impacts due to pandemics have not been included in the estimate. - Prevailing wages have not been included. - An escalation allowance has not been included. - This is an estimate for the cost of construction, no land fees, architectural fees, legal fees, land development fees, tap fees, etc. have been included. - Sales tax has not been included. - A&P excludes any delegated design that is not listed in the plans or specifications.
Items by Others - All independent testing and inspections, including commissioning - Televisions - Residential Equipment (AP included ranges listed on the plan set) - Land Costs, Legal Fees, or Tap Fees - Architectural and Engineering Fees - Technology – Servers, computers, phones, etc. - Owner contingency - All fees associated with utilities will be paid for by the owner (water, electric, gas) - Any expenses associated with dry utilities and getting them to the site (cable, fiber, power and gas) - Removal or working with hazardous materials, including asbestos and lead abatement as defined by OSHA. - All moving costs - All artwork - purchasing, moving, and installation - Technology - Computers, Servers, phones, etc. – purchasing, moving and installation - Furniture, Desks, chairs, tables, moveable casework – purchasing, moving and installation - Audio / Visual Projectors, Projection Screens, Smart Boards (that are not specifically called out in the plans)
Documents - Drawings dated 09/12/2025 - Specifications dated 09/12/2025 - Addenda 1 dated 09/25/2025 - Addenda 2 dated 10/01/2025 - ACM Map (provided by BVSD) dated 9/23/25
B Shell - An allowance of $10K has been included for up to four (4) curb extensions where existing curbs may not meet minimum height requirements after reroofing.
- An allowance of $20K has been included to address localized roof ponding & drainage corrections. This allowance is intended to cover
limited cricketing, tapered insulation, or minor rework in select areas (approximately 3,700 SF identified as “concerning”) where ponding is
DATE PRINTED: 11/4/2025
B Shell limited cricketing, tapered insulation, or minor rework in select areas (approximately 3,700 SF identified as “concerning”) where ponding is observed.
- One water spray test is include for the entirity window replacement. - Snow removal from roof is not included. - Vacuum & removal of loose gravel from the existing roof surface is included. Cleaning or washing gravel for reuse is not included.
C Interiors - Our sprinkler pricing is contingent on as-builts of the current system being provided by BVSD.
D Services - Alternate 9 - We have assumed it is necessary to turn up and protect sprinkler heads. - An allowance of $32.5K included for cleaning up wires above ceilings with replaced lights to pass above ceiling inspections. - An allowance of 80K per each is included for refurbishing (2) existing RTU's, RTU-904 & RTU-201. Further discussion needs to occur to
define scope. Cleaning of existing diffusers as specifically noted in General Note 8 on Sheets A-111 & A-112 is included in this scope. General cleaning, wiping down, of existing MEP equipment, grilles, or registers (GRDs) beyond that note is excluded from this scope of work
- Fire alarm replacement product was included as Mircom. Bronco has included extra devices past the plans to create a complete system. - Per BVSD & drawings, no additional raceways for security cameras have been included. - Replacing roof drains is not included. Only the strainers are included to be replaced.
E Equipment and Furnishings - Alternate 7 - Structural & foundation modifications have not been included for the new walls at the softball dugouts. - An allowance of $17K has been included for the furnishing & installation of structural supports & hangers required to suspend new ductwork from the existing gym structure.
- Epoxy doors at the cabinets have been priced as laminate. It is not common to have epoxy doors on casework as shown. - The lockable data cabinet per 4/A-415 has been included in base bid.
F Special Construction and Demolition - An allowance of $70K has been included for shoring/access for gym mechanical & structural work.
G Site Preparation - 30 Day Maintenance is include at new sod & turf seed areas. Mowing & trimming of seeded areas is not included at Native Seed areas. - Adding or upgrading the irrigation controller is not included. Existing controller is figured to have capacity to accomodate new irrigation. - Imported topsoil is not included. See add alternate if required. 70/30 sand/compost soil prep for the trenches that are to be seeded is
included. The sod area is at 4 CY/1,000 SF. The native seed area is at 2 CY/1,000 SF instead of 4 CY/1,000 SF so as not to promote weed infestation that could potentially strangle the desirable grasses.
- Per the specifications, an allowance of $35,230 is included to repair/replace a portion of the wood baseball outfield fence.
Z General Requirements - A site security guard has not been included.
DATE PRINTED: 11/4/2025
Z General Requirements - General protection of adjacent surfaces is included for the work shown in the plans.
DATE PRINTED: 11/4/2025
Exhibit C
Itemization ofGMP Cost Itemization of the Dollars requested for long lead equipment and material packages
Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20
797 Ventura Street, Aurora, CO 80011 Project: K1224 BVSD - Fairview High School Owner: BVSD Architect: MOA Architecture
Date: Estimator: Project SF: Duration in Months: Estimate #:
10/29/25 Karra Damiana 261,261 11.00 CD Estimate Rev. 1 Includes Alternates 5 (Tennis Court Drainage), 6 (Softball Backstop Extension), 7 (Softball Improvements), 9 (Replace ACT), 11 (Student Commons Projection Screen/Lightspeed), 12 (Library Lightspeed)
Project Summary Sheet - Estimated Cost of the Work Division #0
Procurement and Contracting Requirements
Division #1
General Requirements
Division #2 Division #3
Existing Conditions Concrete
Division #4
Masonry
Division #5
Wood, Plastics, and Composites Thermal and Moisture Protection
Division #8 Division #9
Openings Finishes
Division #10
Specialties Equipment Furnishings Special Construction Conveying Equipment Fire Suppression Plumbing
Division #23 Division #25
Heating, Ventilating and Air Conditioning Integrated Automation
Division #26
Electrical
Division #27
Difference $0 ($108,994)
$162,407
$303,551
$141,144
$56,977 $40,647
$41,116 $53,670
($15,861) $13,023
$134,085
$149,270
$15,185
$210,323
$332,833
$122,510
$1,318,248 $305,855
$1,138,701 $126,885
($179,547) ($178,970)
$889,745 $47,345
$973,212 $16,784
$83,467 ($30,561)
Metals
Division #6 Division #7
Division #11 Division #12 Division #13 Division #14 Division #21 Division #22
DD Estimate CD Estimate $371,938 $371,938 $798,378 $689,384
Communications
$13,000
$34,450
$21,450
$51,097 $0 $0 $102,155 $906,425 $977,320
$49,497 $0 $0 $150,150 $0 $3,592,743
($1,600) $0 $0 $47,995 ($906,425) $2,615,423
$0 $396,118
$0 $1,154,408
$0 $758,290
$543,207
$602,194
$58,987
$1.42
/SF
3.2% of Direct Costs
$2.64
/SF
5.9% of Direct Costs
$1.16
/SF
2.6% of Direct Costs
$0.16
/SF
0.3% of Direct Costs
$0.21
/SF
0.5% of Direct Costs
$0.57
/SF
1.3% of Direct Costs
$1.27
/SF
2.8% of Direct Costs
$4.36
/SF
9.7% of Direct Costs
$0.49
/SF
1.1% of Direct Costs
$3.73
/SF
8.3% of Direct Costs
$0.06
/SF
0.1% of Direct Costs
$0.13
/SF
0.3% of Direct Costs
$0.19
/SF
0.4% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$0.57
/SF
1.3% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$13.75
/SF
30.6% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$4.42
/SF
9.8% of Direct Costs
$2.30
/SF
5.1% of Direct Costs
Cost Delta Comments from DD's No Change Refinement of GRs Based on Accepted Scope & Schedule Added DD Alternate 2 (RTU 1001/1002, ACCU 1001/1002) to Base Bid; Included $70K Shoring for Gym Floor for Mechanical/Structural Work; ADD ALTERNATE 5 Core Drill Holes ILO Floor Trenches Fully Grouted Walls ILO Partial at Mechanical Enclosure Added Steel Angle at Masonry Screen Wall; Added Steel Channel at Gym Wall Duct Penetrations; Added Tube Steel Column/Post at Pony Walls;Included an Allowance of 17K for Steel Reinforcement/Framing Modifications at Gym for Ductwork Suspension; ADD ALTERNATE 5 Added Additional Blocking at Roof Expansion Joints/Parapet Coping; Added Hilti Attachment of Wood Blocking at Coping; ADD ALTERNATES 7 & 11 Better Buyout; ADD ALTERNATES 5 & 6 Reduced Glazing Scope by 320 SF; Demo of Windows Moved to Division 2; ADD ALTERNATES 7 & 9 Branding Allowance Included with Division 9 Painting/Wallcovering Added Facility Fall Protection Safety Railing at Roof Not Applicable Not Applicable ADD ALTERNATE 9 Moved to Mechanical Added DD Alternate 2 (RTU 1001/1002, ACCU 1001/1002) to Base Bid; Split (2) Large Heaters into (4) Small Heaters; Added Master Mixing Valve (DMV); Added Circulation Pump; Added Balancing Requirements to (E) DW System; New Fin Tube Heater ILO Relocating (E); Int. Overhead Duct Size Increases & Rerouting; Added Supply/Return Ductwork Inside Gym & Reroute Outside Return Ductwork; Rerouting of RTU 901 Underground Gas Line; Added Turbulator to Irrigation Line; Added Natural Gas Connection to Elec. Generator; Pipe Size Changes & Additional Piping in Chem. Rm. Not Applicable Added DD Alternate 4 (North Parking Lot Lighting); Added Panel BRA Swap & Breakers for (E) Panels; Added 205 Fixtures & Controls, Emergency Lighting Circuitry & Relays; Added Alternate 2 (RTU 1001/1002 ACCU 1001/1002) to Base Bid; Added Alternate 3 (Network Equipment Cabinet) to Base Bid; Added more clock/paging devices. ADD ALTERNATES 9, 11, & 12 Added scope to clean-up the existing Main Gym Sound System; ADD ALTERNATES 11 & 12
Division #28
Electronic Safety and Security
Division #31
Earthwork
Division #32 Division #33
$1,113,279
$743,553
($369,726)
$306,882
$462,398
$155,516
$2.85
/SF
6.3% of Direct Costs
$1.77
/SF
3.9% of Direct Costs
$622,338
$767,919
$145,581
$2.94
/SF
6.5% of Direct Costs
$67,308
$4,025
($63,283)
$0.02
/SF
0.0% of Direct Costs
Subtotal
$9,435,077
$11,758,681
$2,323,604
$45.01
/SF
100.0% of Direct Costs
Utility Tap & Devel. Fees Permit Allowance Use Tax Design Contingency Estimate Contingency Construction Contingency Builders Risk Insurance Comprehensive General Liability Insurance Sub Default Insurance Performance and Payment Bond Escalation Allowance Contractors Fee Preconstruction Services
By Owner By Owner By Owner $285,465 $285,465 $342,558 $10,379 $125,604 Not Included $77,646 $342,558 $342,558 $29,924
By Owner By Owner By Owner $0 $0 $352,760 $14,202 $142,021 Not Included $87,795 $0 $525,637 $29,924
$0.00
/SF
$0.00
/SF
0.00% of Project
$0.00
/SF
0.00% of Project
$0.00
/SF
0.00% of Project
$0.00
/SF
0.00% of Project
$1.35
/SF
3.00% of Subtotal
$0.05
/SF
0.11% of Project
$0.54
/SF
1.10% of Project
$11,277,234
$12,911,020
Exterior Improvements Utilities
($285,465) ($285,465) $10,202 $3,823 $16,417
$0.00
/SF
0.00% of Costs
$10,149 ($342,558) $183,079 $0
$0.34
/SF
0.68% of Project
$0.00
/SF
0.00% of Project
$2.01
/SF
4.34% of Subtotal + Contingency
$0.11
/SF
$1,633,786
$49.42
/SF
Estimated Cost of Construction
CD Estimate Rev. 1 Base Contract Amendment 1 Amendment 2
$29,924.00 $2,156,476.37 $10,724,619.63
100.0% of Project
Bronco Carried a Plug Number at DDs to Generally Account for the Scope. At CDs, Bronco Completed a Full Design, & the Cost Decreased Accordingly. Includes Utilities; ADD ALTERNATES 5 & 6 Added Alternate 4 (North Parking Lot Lighting) - Asphalt/Concrete Removal & Patchback; Added Asphalt/Concrete Patchback at Irrigation Improvements; ADD ALTERANTES 5, 6, & 7 Moved to Earthwork
Dropped to 0% from 2.5% Dropped to 0% from 2.5%
Dropped to 0% from 3%
Detail Report DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
DETAILED COST: Building 00 Procurement and Contracting Requirements
$371,938
00 72 00 AIA General Conditions 00100 General conditions of the contract
$371,938 1.00 ls
371,938.00
Subtotal 00 72 00 AIA General Conditions
$371,938 $371,938
Subtotal 00 Procurement and Contracting Requirements
$371,938
01 General Requirements
$689,384
01 32 00 Construction Progress Documentation
$6,050
01100 Video Monitoring and documentation 01140 Drone Service
Per RFP Response
Not Included 11.00 mo
550.00
Subtotal 01 32 00 Construction Progress Documentation
$6,050 $6,050
01 33 00 Submittal Procedures
$0
01110 Delivery Costs / Messenger Services
Included
01130 Reproduction Costs
Included
01170 Sustainability Project Requirements
Not Included
Subtotal 01 33 00 Submittal Procedures
$0
01 35 53 Security Procedures 01160 Site Security Cameras and Monitoring
$7,975 11.00 mo
725.00
$7,975
Subtotal 01 35 53 Security Procedures
$7,975
01 45 00 Quality Control
$71,500
01200 Independent testing
Not Included
01210 Soil compaction tests
Not Included
01220 Concrete tests
Not Included
01230 Steel weld test / inspections
Not Included
01240 Contractor Quality Control - FE
11.00 mo
6,500.00
$71,500
01250 Field Quality Control procedures
Included
01260 3rd Party envelope consultant
Not Included
Subtotal 01 45 00 Quality Control
$71,500
01 51 00 Temporary Facilities
$390,309
01270 Temporary electricity - jobsite
DATE PRINTED: 10/29/2025
By Owner
Page 7 of 35
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
01280 Generators 36kw
Not Included
01290 Fuel for Generator (full load)
Not Included
01300 Generator setup / and Containment
Not Included
01310 Temporary Fire Protection
11.00 mo
432.84
$4,761
01330 Temp Heating Equipment & Labor
Not Included
01340 Temp Heating Fuel
Not Included
01350 Temporary building enclosure for temp heating
Not Included
01360 Temporary lighting
General lighting by EC
01370 Temporary Water
By Owner
01380 Sanitary Facilities
11.00 mo
1,200.00
$13,200
For Subcontractors
01390 Temporary Elevators
Not Included
01400 Temporary Hoists
Not Included
01410 Gradall for Jobsite
11.00 mo
13,500.00
$148,500
01420 Bobcat & Operator for Jobsite
11.00 mo
11,950.00
$131,450
2,650.00 gal
5.00
$13,250
01430 Fuel for equipment 01440 Temporary Cranes
By Division
01450 Temporary scaffolding and platforms
By Division
01460 Temporary Stairs and Ramps
Not Included
01470 Temporary Swing Staging
Not Included
01480 Temporary Access Roads
Not Included
01490 Weather Conditions
4.00 mo
3,228.00
$12,912
Allowance
01500 Haul Routes
By Earthworker
01510 Temporary Parking Areas
By Earthworker
01520 Temporary Air & Noise Barriers
Not Included
01540 Temporary Barricades
By Division 16.00 mo
650.00
$10,400
01620 Technology for DCOW Staff
8,500.00 hr
4.72
$40,160
01620 Temporary interior signage
261,261.00 sf
0.06
$15,676
01560 Temporary Connex(s)
Subtotal 01 51 00 Temporary Facilities
$390,309
01 70 00 Execution and Closeout
$0
01720 Construction Surveying
By Trade
01730 Protection of Adjacent Construction
By Division
Subtotal 01 70 00 Execution and Closeout
$0
01 74 00 Cleaning 01630 Progress Cleaning
DATE PRINTED: 10/29/2025
$213,550 2,873,871.00 sf
0.04
$110,165
Page 8 of 35
DESCRIPTION 01710 Final Clean Building
QTY UOM UNIT PRICE 261,261.00 sf
0.40
Subtotal 01 74 00 Cleaning
TOTAL COST
NOTES / COMMENTS
$103,385 $213,550
01 90 00 Life Cycle Activities
$0
01740 Substructure Commissioning
Not Included
01750 Structure commissioning
Not Included
01760 Exterior enclosure commissioning
Not Included
01770 Roofing Commissioning
Not Included
01780 Systems Commissioning
Not Included
Subtotal 01 90 00 Life Cycle Activities
$0
Subtotal 01 General Requirements
$689,384
02 Existing Conditions
$276,139
02 41 00 Demolition
$276,139
02300 ACM Review - Scissor Lift
1.00 ea
979.00
$979
02300 Demo - SUB
1.00 sub
147,269.00
$147,269
02300 Demo flooring finishes
Included
02300 Remove existing DFH
Included
02300 Remove teachers desk
Included
02302 Demo existing gyp partitions
Included
02302 Demo existing wood framed platform in the NW floor area
Included
02302 Demolish existing casework
Included
02303 Demo ACT & Grid
Included
02304 Remove Wood Door & Transom Panel & Hardware - Salvage
Included
02306 GPR & Core
20.00 ea
150.00
$3,000
02310 Remove exist appliance - salvage
Included
02411 Removal of Existing Windows 02411 Remove Housekeeping Pads 02427 Sawcut & Demo Concrete Roof Deck for New General Exhaust Fan Ducting
Included 1.00 ea
1,341.27
$1,341
02430 MEP Haul Off 02431 Protect Gym Floor for Mechanical Work 02433 Shoring/Access for Gym Mechanical/Structural Work
Included 14,280.00 sf 1.00 allow
3.75
$53,550
70,000.00
$70,000
Allowance
02435 Remove and preserve cord reels
Included
02435 Sawcut & Demo CMU Wall for New General Exhaust Fan Ducting
Included
DATE PRINTED: 10/29/2025
Page 9 of 35
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
02435 Sawcut 3x3 Openings for Crawlspace Access in Computer Room
Included
02437 Remove mechanical unit supporting steel
Included
Subtotal 02 41 00 Demolition
$276,139
Subtotal 02 Existing Conditions
$276,139
03 Concrete
$41,116
03 35 00 Concrete Finishing
$5,631
03351 Form, Place & Finish Housekeeping Pad (Boiler Rm)
w/ Div. 32 Site Concrete
03353 Concrete Infill @ Floor Openings - 4" Thick x 36" Wide / #3 ep dwls @ 18" (CTE Computer 225)
8.00 lf
525.00
$4,200
03355 Grout Patches @ Plumbing Core Drill Holes (Chemistry 408)
30.00 ea
23.84
$715
03357 Grout Patches @ Conduit Core Drill Holes (CTE Computer 225)
54.00 ea
13.25
$715
Subtotal 03 35 00 Concrete Finishing
$5,631
03 35 43 Polished Concrete Finishing 03510 PC-1 Polished concrete 03511 >Power Requirements 208/3 Phase 50 amp Generator
$35,485 3,816.00 sf
8.91
$33,985
1.00 wk
1,500.00
$1,500
Subtotal 03 35 43 Polished Concrete Finishing
$35,485
Subtotal 03 Concrete
$41,116
05 Metals
$45,600
05 50 00 Metal Fabrications
$45,600
05517 Steel Channel at Gym Wall Duct Penetrations
Included
05519 Tube Steel Column/Posts, at Pony Walls (CTE Computer 225)
Included
05521 Steel Angle Reinforcement/Framing Modifications Around EF-423
Included
05523 Steel Angle Reinforcement/Framing Modifications Around ACCU-1002
Included
05525 Steel Angle Reinforcement/Framing Modifications Around ACCU-1001 05527 Steel Angle Reinforcement/Framing Modifications Around RTU-1001/1002
1.00 ls
4,000.00
$4,000 Not Included
05529 Steel Angle Reinforcement/Framing Modifications at Exterior Window Heads (Windows B,C,D)
Included
05531 Steel Angle Reinforcement/Framing Modifications at Exterior Window Sills (Windows
Included
DATE PRINTED: 10/29/2025
Page 10 of 35
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
Allowance
B,D) 05533 Steel Reinforcement/Framing Modifications at Gym for Ductwork Suspension
1.00 allow
17,000.00
$17,000
05537 AP Steel Labor & Coordination
6.00 wk
4,100.00
$24,600
Subtotal 05 50 00 Metal Fabrications
$45,600
Subtotal 05 Metals
$45,600
06 Woods, Plastics and Composites
$271,691
06 10 10 Rough Carpentry 06109 Blocking for Projector
$130,835 1.00 ls
2,002.00
$2,002
06109 Wood Blocking at Re-Roof Locations - Labor
See Below
06111 >RTU Curb on Existing BUR Roof (A3/A-361)
175.00 lf
9.67
$1,692
06113 >Roof Expansion Joint (A4/A-361)
75.00 lf
46.14
$3,461
06115 >Exhaust Fan Curb on Existing BUR Roof (B3/A361)
15.00 lf
10.25
$154
1,420.00 lf
42.30
$60,065
06117 >Parapet Coping (C1/A-361) 06119 >>Penetrating Radar to Identify Steel Reinforcing in Precast Wall Panel 06121 >Storefront Sill at Clerestory Window (D3/A-361)
w/ Div. 7 Flashing 52.00 lf
20.00
$1,040
06123 Wood Blocking at Re-Roof Locations - Material
See Below 1,420.00 lf
0.83
$1,176
06127 >Dimensional Lumber, 2x6 (A3, A4, B3/A-361)
490.00 lf
2.08
$1,020
06129 >Dimensional Lumber, 2x8 (D3/A-361)
100.00 lf
2.80
$280
06131 >Dimensional Lumber, 2x10 (C1/A-361)
1,420.00 lf
4.14
$5,880
06133 >Dimensional Lumber, 2x12 (C1/A-361)
150.00 lf
5.87
$880
2,189.00 sf
1.91
$4,180
781.00 ea
35.00
$27,335
06125 >Dimensional Lumber, 1x4 (C1/A-361)
06135 >Plywood, 1/2" (C1/A-361) 06137 >Hilti HAS, 24" OC (C1/A-361)
Alternate 11
06139 >>Hilti HIT-HY 270 Cartridged (C1/A-361)
Included
06141 >>Epoxy (C1/A-361)
Included 8,624.00 lf
1.00
$8,624
06145 Wood for Temporary Windows - Labor
734.00 sf
5.03
$3,692
06147 >Dimensional Lumber, 2x6
658.00 lf
2.08
$1,370
06149 >Plywood, 1/2"
734.00 sf
1.91
$1,402
06151 >Fasteners/Adhesive
658.00 lf
1.00
$658
2,162.77 sf
2.74
$5,926
06143 >Fasteners/Adhesive
06152 Interior Rough Carpentry Subtotal 06 10 10 Rough Carpentry
$130,835
06 22 00 Finish Carpentry
$140,856
DATE PRINTED: 10/29/2025
Page 11 of 35
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
06218 Custom Stainless Shelving w/ Integrated Backsplash 06218 Finish Casework - SUB
NOTES / COMMENTS Included
1.00 sub
139,856.00
$139,856
06219 Solid shelving ILO Wire shelving
Not Included
06220 New SSC-1 Top & Brackets
Included
06220 New SSC-1 Tops - wall mounted
Not Included
06220 PL1 - Base Cabinets (No Epoxy Doors Available)
Included
06220 Wall Mounted Standards and Shelving
Included
06221 EPC-1 Countertop w/ Splash
Included
06221 New base drawers replaced where removed
Not Included
06222 PL2 - Wall Cabinets (w/ Epoxy Doors)
Included
06223 1" Epoxy Pegboard
Included
06224 PL2 - Tall Cabinets
Included
06225 Relocated fume hood
Included
06226 Relocated eye wash station
Included
06285 Wood transom panel
w/ Div 8
06375 SS Wall Caps @ Computer Lab Knee Walls
Included
06376 Simulated Stone Sill at Window Type Q
Included
06495 Protect casework after installation
1.00 ls
500.00
$500
06500 Caulk casework/countertops
1.00 ls
500.00
$500
Subtotal 06 22 00 Finish Carpentry
$140,856
Subtotal 06 Woods, Plastics and Composites
$271,691
07 Thermal and Moisture Protection
$1,124,002
07 20 00 Building Insulation
$0
07213 Glass Fiber Batt Insulation - Unfaced in Flutes Behind Roof Sheathing Board (Details A1,A2,B2/A-361)
w/ Div. 7 Roofing
Subtotal 07 20 00 Building Insulation
$0
07 53 23 Roofing & Roof Insulation
$1,101,047
07301 EPDM Roof at Roof Decks 1 Through 6 - SUB
1.00 sub
07302 > Roof Coring Investigation
1.00 ls
1,040,711.45
$1,040,711
3,160.00
$3,160
07303 > Removal Existing Surface Gravel on Built-Up Roof Assembly
Included
07305 >> Transport to BVSD Facilities for Owner Use (6500 Arapahoe Road)
Included
07307 > Remove & Dispose Existing Wall & Curb Flashings
Included
DATE PRINTED: 10/29/2025
Page 12 of 35
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
07309 > Sawcut Existing Membrane at 10' O.C.
Included
07311 > Remove/Reinstall Existing Dome Solatubes per C2/A-361, Keynote 172
Included
07313 > Remove/Reinstall Existing Exhaust Fans per C3/A-361, Keynote 173
Included
07315 > Rooftop Curbs Extensions 07318 > Roofing Ponding Correction w/ Tapering or Insulation
4.00 ea
2,500.00
$10,000
Allowance
3,700.00 sf
5.41
$20,000
Allowance
07319 > Install Polyisocyanurate Board Insulation, Mechanically Fastened
Included
07321 > Install Tapered Insulation Sumps 4' in Each Direction from All Roof Drains in the Roof Work Areas
Included
07323 > Install DensDeck Prime Cover Board Set-in Low-rise Adhesive
Included
07325 >> Install DensDeck Prime Cover Board Set-in Low-rise Adhesive at Parapet Wall (Details A1, A2, B1, B2,C1,C2,C3,D2,D3/A-361)
Included
07327 > Supply/ Install New Cast Iron Roof Drain Strainers per Sheet Keynote 181 & D1/A-361
w/ Div. 22 Plumbing
07329 > Supply/ Adhere 60 Mil EPDM Membrane, Black
Included
07331 > Supply/Install Walkway Pads per Reference Keynotes 07 5300.10
Included
07333 > Supply/ Install Grease Containment Assembly per Reference Keynotes 07 5300.23
Included
07335 > Provide 20 Year Warranty
Included
07337 Repair Existing EPDM Expansion Joint Splices per Sheet A-121, Keynote 183
Included
07339 Roof Patch at New Exhaust Fan, EF-423H per Sheet A-121, Keynote 182, Detail B3/A-361
Included
07341 Roof Patches at New Rooftop Units, RTU1001/1002, ACCU-1001/1002 per Sheet A-121, Keynote 185, Detail A3/A-361
Included
07343 Roof Patch at New Concentric Vent Stack/Hot Stack per Sheet A-121, Keynote 80, Detail B4/A361
Included
07345 Roof Cleanup
63,320.00 sf
0.05
$3,166
07347 Facility Fall Protection - Safety Rail (Posts & Railing) per Sheet A-121, Keyonte 11 8129 07349 Safety Measures for Roof Work Perimeter/Openings 07351 Exterior Scaffold Stair Tower
w/ Div. 11 Facility Maintenance Equipment 802.00 lf 4.00 mo
5.00
$4,010
5,000.00
$20,000
07353 Hoisting for Roofing Materials
Included
07355 Snow Removal for Roof Work
Not Included
Subtotal 07 53 23 Roofing & Roof Insulation
DATE PRINTED: 10/29/2025
$1,101,047
Page 13 of 35
DESCRIPTION
QTY UOM UNIT PRICE
07 60 00 Flashing & Sheet Metal
TOTAL COST
NOTES / COMMENTS
$22,295
07601 Flashing - SUB
w/ Div. 7 Roofing
07603 >>Sawcut Existing Fluted Precast Wall Panel
Included
07603 >Flashing at Fluted Precast Wall Panel per Sheet A-121, A1 & A2/A-361
Included
07605 >>>Penetrating Radar to Identify Steel Reinforcing in Precast Wall Panel, GPR
1.00 sub
22,295.00
$22,295
07607 >Coping Flashing at Roof Parapet Detail per B1/A-361
Included
07609 >Flashing Around Existing Mechanical Units per Sheet A-121, Detail D2/A-361
Included
07611 >Flashing Around New Fume Hood Exhaust Fan, EF-423H per Sheet A-121, Keynote 182, Detail B3/A-361
Included
07613 >Flashing Around New Rooftop Units, RTU1001/1002, ACCU-1001/1002 per Sheet A-121, Keynote 185, Detail A3/A-361
Included
07615 >Flashing Around New Concentric Vent Stack/Hot Stack per Sheet A-121, Keynote 80, Detail B4/A-361
Included
07617 >Flashing at Storefront Sill at Clerestory Window - Type Q
Included
Subtotal 07 60 00 Flashing & Sheet Metal
$22,295
07 71 00 Roof Specialties & Accessories
$0
07711 Roof Curbs for RTU-1001/1002, ACC-1001/1002
w/ Div. 23 Mechanical
07713 Expansion Joint Cover per Details A2, A4, & B2/A-361
w/ Div 7 Roofing
Subtotal 07 71 00 Roof Specialties & Accessories
$0
07 92 00 Joint Sealants
$660
07903 Joint Sealant Continuous Along Joint at Existing Fluted Precast Wall (Roof) (Ref. A1/A-361) 07905 Joint Sealant at Exterior Duct Penetrations
w/ Div 7 Roofing 44.00 lf
15.00
Subtotal 07 92 00 Joint Sealants
$660
Subtotal 07 Thermal and Moisture Protection
$1,124,002
08 Openings
$126,885
08 10 00 Doors and Frames 08015 Doors, Frames and Hardware - SUB
$660
$29,762 1.00 sub
26,000.00
$26,000
08015 HM Frame - single 3'-0" x 7'-0"
Included
08035 Doors, Frames and Hardware Install
6.00 ea
552.00
$3,312
08295 Misc welding, grinding, bondo
3.00 ea
150.00
$450
DATE PRINTED: 10/29/2025
Page 14 of 35
DESCRIPTION
QTY UOM UNIT PRICE
Subtotal 08 10 00 Doors and Frames
TOTAL COST
NOTES / COMMENTS
$29,762
08 14 00 Wood Doors
$0
08070 3'-0" x 7'-0" wd door
Included
08071 Drilled Raceways
Included
08071 Wood Transom Panel w/ Lite Kit
Included
Subtotal 08 14 00 Wood Doors
$0
08 41 13 Aluminum Entrances
$96,123
08441 Remove Existing Exterior Storefront 08443 Glazing - SUB
w/ Div. 2 Demolition 1.00 sub
84,861.08
$84,861
08445 Exterior Storefront - Kawneer Thermally Broken, 2" x 4-1/2", Class 1 Natural Anodized, Type IG-1 - Insulating Glass, 1" Thick (Type B)
Included
08447 Exterior Storefront - Kawneer Thermally Broken, 2" x 4-1/2", Class 1 Natural Anodized, Type IG-1 - Insulating Glass, 1" Thick (Type C)
Included
08449 Exterior Storefront - Kawneer Thermally Broken, 2" x 4-1/2", Class 1 Natural Anodized, Type IG-1 - Insulating Glass, 1" Thick (Type D)
Included
08451 Exterior Storefront - Kawneer Thermally Broken, 2" x 4-1/2", Class 1 Natural Anodized, Type IG-1 - Insulating Glass, 1" Thick (Type Q)
Included
08453 Break Metal at Window Type Q per Detail 5/A601
Included
08455 Pre-Finished Galvanized Steel Sheet Metal (Sill Flashing at Types B & D per Detail 1/A-601)
Included
08457 Pre-Finished Galvanized Steel Sheet Metal (Sill Flashing at Clerestory Window Type Q per Detail D3/A-361) - LABOR ONLY (Supplied by Roofer.)
Included
08459 Perimeter Backer Rod & Sealants - 2 Beads/Lines (1,2,3,4,6,7/A-601)
Included
08461 Grout (E) Indentation at Removed (E) Window Sill (Type C)
44.00 lf
37.23
$1,638
08463 Water-Spray Test Per 08 4313 3.04
1.00 ea
8,155.93
$8,156
734.00 sf
2.00
$1,468
08465 Final Clean Glass Subtotal 08 41 13 Aluminum Entrances
$96,123
08 70 00 Hardware
$1,000
08755 Replace door hardware per schedule 08875 Misc. missing hardware Subtotal 08 70 00 Hardware 08 80 00 Glazing
DATE PRINTED: 10/29/2025
Included 1.00 ls
1,000.00
$1,000 $1,000 $0
Page 15 of 35
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
08813 Decorative Plastic Film (WF-1 - Sheet A-401, A700) - 3M Dusted & Frosted, Smooth Frosted Crystal White, VE14704
Included
Subtotal 08 80 00 Glazing
$0
Subtotal 08 Openings
$126,885
09 Finishes
$955,912
09 21 16 Gypsum Board Assemblies 09000 Drywall - SUB
$133,800 1.00 sub
83,800.00
$83,800
09069 FR3 - Furring Wall 09069 Patch & Repair Walls
NOTES / COMMENTS
Included 1.00 ls
50,000.00
$50,000
09069 S4.1 - Shaft Wall, to Deck, Shaft Wall Core Board 1 side, Gyp Other
Included
09070 Gyp Ceiling
Included
09070 Level 5 Finish at WC Locations
Included
09070 P3 - Knee wall for outlets
Included
09070 P3 - Wall Partition, To Deck, 1 layer Gyp both sides
Included
09070 P3a - Wall Partition, To Deck, 1 layer Gyp both sides, Acoustic
Included
09213 Patch Drywall Where New Receptacles Have Been Cut into Drywall at Commons
Included
09215 New 1-HR Fire Rated Shaft Wall for New Exhaust Fan Ducting for Fume Hood (Room 408)
Included Above
09217 DensDeck Prime Cover Board Set-in Low-rise Adhesive at Parapet Wall (Details A1, A2, B1, B2,C1,C2,C3,D2,D3/A-361)
w/ Div. 7 Roofing
09219 >Glass Fiber Batt Insulation - Unfaced in Flutes Behind Roof Sheathing Board (Details A1,A2,B2/A-361)
w/ Div. 7 Roofing
09221 Patch & Repair Rigid Insulation & Gyp Board Below Window Sill
Included
09223 Additional Layer of Drywall Around Window Sill
Included
Subtotal 09 21 16 Gypsum Board Assemblies
$133,800
09 24 00 Cement Plastering 09241 Patch & Repair Cement Plaster
$24,210 1,614.00 sf
15.00
$24,210
Subtotal 09 24 00 Cement Plastering
$24,210
09 51 00 Acoustical Ceilings
$223,362
09251 C1 - 2x4 ACT 09251 C1 - 2x4 ACT
DATE PRINTED: 10/29/2025
Included 11,087.00 sf
5.52
$61,200
Alternate 9
Page 16 of 35
DESCRIPTION 09251 Ceilings & Acoustic - SUB
QTY UOM UNIT PRICE 1.00 sub
134,000.00
TOTAL COST
NOTES / COMMENTS
$134,000
09252 C2 - 2x4 ACT vinyl faced
Included
09253 C3 - 2x2 ACT
Included
09511 ACT Tile/Grid Repair due to Window Replacement
Included
09515 ACT Tile/Grid - Demo & Reinstall due to MEP Changes
3,587.00 sf
7.85
Subtotal 09 51 00 Acoustical Ceilings
$223,362
09 65 00 Resilient Flooring 09337 Flooring - SUB
$28,162
$387,412 1.00 sub
376,292.64
$376,293
09337 LVT - 1
Included
09337 Stair Nosing
Included
09461 New 4" base
Included 6.00 ea
115.00
$690
09613 Floor prep and joint grinding
11,790.00 sf
0.79
$9,314
09637 Floor protection
3,718.00 sf
0.30
$1,115
09585 Moisture tests (1/1000sf)
Subtotal 09 65 00 Resilient Flooring
$387,412
09 68 00 Carpet
$0
09413 CPT - 1 - Shaw, 18"x36"
Included
09413 CPT - 1,2,3 @ Library
Included
09414 Accent CPT-2
Included
09416 CPT - 3
Included
Subtotal 09 68 00 Carpet
$0
09 72 00 Wall Coverings
$0
09720 WC-1
Included
Subtotal 09 72 00 Wall Coverings
$0
09 80 00 Acoustic Treatment
$0
09717 AP-1 Acoustic Wall Panels (AV Room)
Included
09717 AP-1B Acoustic Wall Panels (AV Room)
Included
09717 AP-1C Acoustic Wall Panels (AV Room)
Included
09717 AP-1D Acoustic Wall Panels (AV Room)
Included
Subtotal 09 80 00 Acoustic Treatment
$0
09 90 00 Painting and Coating 09700 Branding Graphic Allowance
DATE PRINTED: 10/29/2025
$187,128 1.00 allow
50,000.00
$50,000
Allowance
Page 17 of 35
DESCRIPTION 09700 Paint - SUB
QTY UOM UNIT PRICE 1.00 sub
136,198.00
TOTAL COST
NOTES / COMMENTS
$136,198
09720 Accent wall paint refresh
Included
09720 Prep and paint all walls
Included
09821 Touch up doors & frames
Included
09825 Final touch up at completion of project
3,718.00 sf
0.25
$930
09905 Graffiti Seal at RTU Enclosure
Included
09905 Paint Additional Layer of Drywall Around Window Sill
Included
09907 Paint Patched & Repaired Exterior Plaster
Included
09908 Paint Exposed Ductwork at Gym
Included
Subtotal 09 90 00 Painting and Coating
$187,128
Subtotal 09 Finishes
$955,912
10 Specialties
$16,784
10 11 16 Marker Boards
$5,447
10030 4x4 Marker Board
Included
10030 4x6 Marker Board
Included
10030 Specialties - SUB
1.00 sub
5,447.00
$5,447
Subtotal 10 11 16 Marker Boards
$5,447
10 14 00 Signage
$11,337
10000 Branding Allowance
w/ Div. 9 Painting
10001 Sign Type G Shelter in Place - Allowance
1.00 allow
10,000.00
$10,000
10001 Signage - SUB
1.00 sub
1,337.00
$1,337
Allowance Per Spec. 01 2100 Allowances
10002 Door Number Tags
Included
10003 Office/Classroom ADA Signs
Included
Subtotal 10 14 00 Signage 10 28 00 Toilet & Bath Accessories
$11,337 $0
10360 TA-1 - Soap dispenser
Included
10400 TA-2 - Paper towel dispenser
Included
Subtotal 10 28 00 Toilet & Bath Accessories
$0
10 44 00 Fire Protection Specialties
$0
10685 Fire Protection Specialties Subtotal 10 44 00 Fire Protection Specialties Subtotal 10 Specialties
DATE PRINTED: 10/29/2025
Included $0 $16,784
Page 18 of 35
DESCRIPTION
QTY UOM UNIT PRICE
11 Equipment
$11,050 6.00 ea
1,841.67
Subtotal 11 30 00 Residential Equipment (GE Equipment)
$11,050 $11,050
11 52 00 Audio-Visual Equipment
$0
11205 Projection Screen Unit - Front Projection Type
w/ Div. 27
Subtotal 11 52 00 Audio-Visual Equipment
$0
11 53 00 Laboratory Equipment
$0
11535 Relocated Fume Hood
w/ Div 6
Subtotal 11 53 00 Laboratory Equipment
$0
11 81 00 Facility Maintenance Equipment 11810 Facility Fall Protection - Safety Rail (Posts and Railing)
$23,400 1.00 ls
23,400.00
Subtotal 11 81 00 Facility Maintenance Equipment
$23,400 $23,400
Subtotal 11 Equipment
$34,450
12 Furnishings
$49,497
12 24 00 Window Shades 12241 Window Shade Treatment, Mecho Shade, Ecoveil 1550 Series, Grey (BE 2)
$49,497 1,053.00 sf
47.01
Subtotal 12 24 00 Window Shades
$49,497 $49,497
Subtotal 12 Furnishings
$49,497
21 Fire Suppression
$150,150
21 00 00 Fire Suppression
$150,150
00000 Fire Suppression - SUB
1.00 sub
47,995.00
$47,995
09253 Sprinkler - SUB
1.00 sub
102,155.00
$102,155
09253 Sprinkler Head Adjustment Subtotal 21 00 00 Fire Suppression Subtotal 21 Fire Suppression 22 Plumbing 22 00 00 Plumbing
NOTES / COMMENTS
$34,450
11 30 00 Residential Equipment (GE Equipment) 11000 Electric Range
TOTAL COST
Alternate 9
Included $150,150 $150,150 $0 $0
22001 Plumbing - SUB
w/ Div. 23 Mechanical
DATE PRINTED: 10/29/2025
Page 19 of 35
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
22011 Plumbing Demo
Included
22013 Plumbing Piping Systems (Domestic Water, Waste, Lab Waste, Vent)
Included
22015 Plumbing Equipment
See Below
22017 >Emergency Gas Shutoff Station
Included
22019 >Emergency Eyewash Station (Relocate)
Included
22021 >Fixtures
See Below
22023 >>Sinks, S-1 (Culinary Arts 317)
Included
22025 >>Sinks, S-2 (Chemistry 408)
Included
22027 >>Sink, S-3 (Culinary Arts 317)
Included
22029 >>Sinks, S-4 (Chemistry 408/421/422)
Included
22031 >>Garbage Disposals, GD-1
Included
22033 >>Gas Turrets, Wall Mount, GT-1
Included
22035 >>Gas Turrets, Deck Mount, GT-2
Included
22037 >>Floor Drain, FD-1 (Eye Wash Station)
Included
22038 >>Roof Drains, RD-1
Not Included
22039 >Gas Domestic Hot Water Heaters, DWH
Included
22045 >Digital Mixing Valve, DMV-1
Included
22047 >Thermostatic Mixing Valve, TMV-1 (Eye Wash Station)
Included
22049 >Domestic Circulating Pump, DCP
Included
22051 >Domestic Water Expansion Tank, DET-1
Included
22053 >Wall Cleanouts
Included
22055 >Balance Valve Assemblies
Included
22057 Insulation, Fire Stopping/Caulking
Included
22059 Test & Balance
Included
22061 Concrete Cutting, Coring, & Xray
Included
22063 Domestic Water Chlorination
Included
22065 Pressure Testing of New Piping
Included
22067 MEP Coordination & QA/QC
w/ Div. 23 Mechanical
Subtotal 22 00 00 Plumbing
$0
Subtotal 22 Plumbing
$0
23 Heating, Ventilating and Air Conditioning
$3,592,743
23 00 00 Heating, Ventilating and Air Conditioning 23001 Mechanical - SUB 23003 Mechanical Demo
DATE PRINTED: 10/29/2025
$3,592,743 1.00 sub
3,328,883.40
$3,328,883
See Below Included
Page 20 of 35
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
23005 HVAC & Mechanical Equipment
NOTES / COMMENTS See Below
23007 >Rooftop Unit, RTU-904 (Refurbish)
1.00 allow
80,000.00
$80,000
Allowance
23009 >Rooftop Unit, RTU-201 (Refurbish)
1.00 allow
80,000.00
$80,000
Allowance
23013 >Rooftop Air Handling Unit, RTU-1001 (HW/DX Heat Pump)
Included
23015 >Rooftop Air Handling Unit, RTU-1002 (HW/DX Heat Pump)
Included
23017 >Air Handling Unit, AHU-901 (Gas Fired)
Included
23019 >Air Cooled Condensing Unit, ACCU-1001
Included
23021 >Air Cooled Condensing Unit, ACCU-1002
Included
23023 >Fin Tube Heater, FTR-1
Included
23025 >Terminal Boxes, Variable Air Volume, VAV's
Included
23027 >Exhaust Fan, EF-423H
Included
23029 >Grilles, Registers, Diffusers, SD-1, RG-1, RG-2
Included
23031 >Hot Water Coil
Included
23033 >Smoke Damper
Included
23035 >Rooftop Solutions Grease Guard
Included
23037 Mechanical Piping (Heating Hot Water, Condensate Waste)
Included
23039 HVAC Ductwork Systems (PVC Coated Flue Hood Exhaust, Boiler Vents, Supply, Return, Exhaust)
Included
23041 Remove & Reinstall Grilles, Registers, & Diffusers
Included
23043 MEP Coordination & QA/QC
3,461,990.00 ls
0.03
Subtotal 23 00 00 Heating, Ventilating and Air Conditioning
$103,860 $3,592,743
Subtotal 23 Heating, Ventilating and Air Conditioning
$3,592,743
26 Electrical
$1,154,408
26 00 00 Electrical 26001 Electrical - SUB
$1,154,408 1.00 sub
1,069,681.22
$1,069,681
26003 >Site Lighting & Power
Included
26005 >Lighting
Included
26007 >Lighting Controls
Included
26009 >Branch Power
Included
26011 >Mechanical Equipment Connections
Included
26013 >Tele/Data Raceways
Included
26015 >Audio Visual Raceways
Included
26017 >Clock/Paging Raceways
Included
DATE PRINTED: 10/29/2025
Page 21 of 35
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
26019 >Demolition
Included
26021 Temporary Lighting & Power
Included
26023 Fire Caulking/Fire Stopping
Included 32,500.00 allow
1.01
$32,968
293.00 ea
20.00
$5,860
1,004,866.00 ls
0.03
$30,146
26031 Re-support Electrical Above Replaced ACT Ceilings
1.00 ls
8,427.64
$8,428
Alternate 9
26033 Add Outlet for New Projector (Student Commons AV)
1.00 ea
3,987.61
$3,988
Alternate 11
26035 Add Outlet for New Lightspeed System with Media Connector (Library)
1.00 ea
3,337.38
$3,337
Alternate 12
26025 Cleaning Up Above Ceilings 26027 Remove/Reinstall Cover Plates on Electrical Devices & Light Switches 26029 MEP Coordination & QA/QC
Subtotal 26 00 00 Electrical
$1,154,408
Subtotal 26 Electrical
$1,154,408
27 Communications
$602,194
27 51 00 Distributed AV systems 27501 Upgrade Intercom/Public Address System Hybrid, New CAT6, New Classrooms & Head End - SUB
Allowance
$602,194 1.00 sub
419,945.00
$419,945
27503 >Replace All Existing Analog Cabling & Speakers in Corridor & Exterior Including Demo & Analog Cabling
Included
27505 >Exterior Speakers/Horns
Included
27507 >Electrical Scope - Rough-In Backboxes & Conduit
w/ Div. 26 Electrical
27509 Classroom Updated to Standard Teaching Wall. Adding Lightspeed Voice Reinforcement Sys (Rms 222,225,228,317,405,408,411,414,420,421,422, 425,426,430,432)
15.00 ea
2,495.20
$37,428
27511 Structural Cabling - SUB
1.00 sub
53,779.00
$53,779
27513 >Provide CAT 6 Data Jacks (Computer Room 225)
Included
27515 >Provide New Network Equipment Cabinet, Network Data Cables, Fiber to New Cabinet (Computer Room 225)
Included
27517 Audio Mixing Panel with Variety of Connectivity Options & New Wireless Microphone Connectivity (South Gym)
1.00 ls
31,471.00
$31,471
27519 >Audio Shunt for Public Address System 27521 CTE Classroom Remove/Reinstall Projector, Provide New Projection Screen & Relocate Cables & Jacks as Required
DATE PRINTED: 10/29/2025
Included 1.00 ls
7,199.00
$7,199
Page 22 of 35
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
27523 New Ceiling Mounted Projector, New Drop Down Screen, 5 Speakers (Student Commons)
1.00 ls
47,622.00
$47,622
Alternate 11
27525 Provide Lightspeed T25 Base Staion w/ JBL Pendant Speakers (Library)
1.00 ls
4,750.00
$4,750
Alternate 12
Subtotal 27 51 00 Distributed AV systems
$602,194
Subtotal 27 Communications
$602,194
28 Electronic Safety and Security
$743,553
28 00 00 Electronic Safety and Security 28101 Fire Alarm System - Full System Replacement w/ Voice Evacuation - SUB
$743,553 1.00 sub
722,212.22
$722,212
28103 >New Intelligent, Fully Addressable Fire Alarm System
Included
28105 >Voice Evacuation Occupant Notification
Included
28107 >New FACP w/ Expansion Capability
Included
28109 >New Annunciator in Reception/Waiting Area (801A)
Included
28111 >New Smoke Detectors, Pull Stations, & Duct Detectors
Included
28113 >New Notification Appliances (Speakers, Strobes) Throughout the Building
Included
28115 >Control Modules for Interfacing with HVAC Systems (HVLS Fans)
Included
28117 >UL-Listed Central Station Monitoring
Included
28119 MEP Coordination & QA/QC
711,372.00 ls
0.03
Subtotal 28 00 00 Electronic Safety and Security
$21,341 $743,553
Subtotal 28 Electronic Safety and Security
$743,553
33 Utilities
$4,025
33 41 13 Foundation Drainage
$4,025
33411 Storm Drainage - SUB 33413 Storm Utility GPR
w/ Div. 32 Earthwork 1.00 ls
4,025.00
$4,025
33415 Core Ex. Structure for Storm Sewer
Included
33417 8” PVC Storm Sewer
Included
33419 10” PVC Storm Sewer
Included
33421 12” PVC Storm Sewer
Included
33423 24" Area Drain
Included
33425 Lower Rim of Manhole (MH) & Install Graded Lid
Included
Subtotal 33 41 13 Foundation Drainage
DATE PRINTED: 10/29/2025
$4,025
Page 23 of 35
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
Subtotal 33 Utilities
$4,025
Total Building
$10,250,471
DATE PRINTED: 10/29/2025
NOTES / COMMENTS
Page 24 of 35
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
DETAILED COST: Site 02 Existing Conditions
$27,412
02 21 00 Surveys
$27,412
02201 Total Stations
4.00 mo
2,643.00
$10,572
02203 Survey - SUB
1.00 sub
15,840.00
$15,840
02205 Calculations & Plan Checks
Included
02207 Control Points & Sawcut
Included
02209 Grading
Included
02211 Storm Sewer
Included
02213 Irrigation Sleeves
Included
02215 Electric Offsets & Grades to Light Poles
Included
02217 Concrete Channel Drain (IS 7)
1.00 ls
1,000.00
$1,000
Alternate 5
02219 Gas Piping Offsets & Grades
Included
02221 Mechanical Enclosure Offsets & Grades
Included
02223 Concrete/Curb, Gutter, & Sidewalks
Included
02225 Concrete/Pans
Included
02227 Restaking
Included
02229 Site Improvement As-Built
Included
Subtotal 02 21 00 Surveys
$27,412
Subtotal 02 Existing Conditions
$27,412
04 Masonry
$53,670
04 20 00 Unit Masonry 04201 Masonry - SUB
$53,670 1.00 sub
53,266.91
$53,267
04203 8" Ground Face Block w/ Integral Water Repellent (Mechanical Enclosure)
Included
04205 >Concrete Stem Wall Instead of CMU Stem Wall (Mechanical Enclosure)
Not Included Per RFI Response
04209 Installation of Embed Plates (Supplied by Misc. Metals) (Mechanical Enclosure)
Included
04211 Misc Cleanup (Mechanical Enclosure)
1,222.00 sf
0.33
Subtotal 04 20 00 Unit Masonry
$403 $53,670
Subtotal 04 Masonry
$53,670
05 Metals
$103,670
05 50 00 Metal Fabrications 05503 Miscellaneous Metals - SUB
DATE PRINTED: 10/29/2025
$103,670 1.00 sub
101,082.73
$101,083
Page 25 of 35
DESCRIPTION 05505 Trench Cover, Galvanized Steel (IS 7)
QTY UOM UNIT PRICE 1.00 ea
2,587.50
TOTAL COST
NOTES / COMMENTS
$2,588
Alternate 5
05507 Steel Railing at ADA Ramp, Exterior, TnemecPrimer (Front of School Drainage Improvement)
Included
05509 >Embed Plates for Steel Railing Surface Attachment, Exterior (Front of School Drainage Improvement) [Supply Only]
Included
05511 Double Enclosure Gate, Exterior (Mechanical Enclosure)
Included
05513 >TS Gate Post to CMU Embed Plates (Mechanical Enclosure) [Supply Only]
Included
05515 Steel Angle at Masonry Screen Wall to Existing Wall, Continuous
Included
05535 Steel Reinforcement/Framing Modifications at Exterior Softball New Walls
Alternate 7 - Not Included
Subtotal 05 50 00 Metal Fabrications
$103,670
Subtotal 05 Metals
$103,670
06 Woods, Plastics and Composites
$61,142
06 10 10 Rough Carpentry 06101 Hardie Plank Siding & Trim (Softball Dugouts) (IS 9)
$31,539 1,512.00 sf
20.03
$30,288
Alternate 7 - Included w/ 09 Drywall
06103 Plywood Siding (Softball Dugouts) (IS 9) 06105 Replace Rotted Wood Fascia at Backside Only (Softball Dugouts) (IS 9)
84.00 lf
14.90
$1,252
06107 Tyvek (Softball Dugouts) (IS 9) $31,539
06 22 00 Finish Carpentry
$29,603 1.00 ls
29,603.00
Subtotal 06 22 00 Finish Carpentry
$29,603
$61,142
07 Thermal and Moisture Protection
$14,698
07 11 00 Bituminous Damproofing
$835 380.00 sf
2.20
$835
07113 Bituminous Dampproofing @ Precast Panel (Mechanical Enclosure) Subtotal 07 11 00 Bituminous Damproofing 07 20 00 Building Insulation
DATE PRINTED: 10/29/2025
Alternate 7
$29,603
Subtotal 06 Woods, Plastics and Composites
07111 Bituminous Dampproofing @ Stem Wall (Mechanical Enclosure)
Alternate 7 Alternate 7 - Included
Subtotal 06 10 10 Rough Carpentry
06000 Dugout Cubbies - MDF
Alternate 7
Included $835 $2,946
Page 26 of 35
DESCRIPTION 07211 Exterior Foundation Wall Insulation @ Precast Panel, 2" (Mechanical Enclosure)
QTY UOM UNIT PRICE 201.00 sf
14.66
TOTAL COST $2,946
Subtotal 07 20 00 Building Insulation
$2,946
07 60 00 Flashing & Sheet Metal
$4,787
07619 >Coping Flashing at Mechanical Screen Wall (20 Gage) (A1,A2,B2/AS-501) 07621 >Flashing at Softball Dugout Bottom of Wall (22 Gage) (1/AS-501)
Included 168.00 lf
28.49
Subtotal 07 60 00 Flashing & Sheet Metal
$4,787
Alternate 7
$4,787
07 92 00 Joint Sealants 07901 Joint Sealant - SUB
NOTES / COMMENTS
$6,130 1.00 sub
4,415.00
$4,415
07907 Joint Sealant Continuous Along Joint at Slab to Structure (Mechanical Enclosure)
Included
07909 Joint Sealant at Sidewalk & Slab Expansion Joints
Included
07911 Joint Sealant at Sidewalk to Chase (IS 7)
1.00 ls
1,400.00
$1,400
Alternate 5
07913 Joint Sealant at Sidewalk (IS 8)
1.00 ls
315.00
$315
Alternate 6
Subtotal 07 92 00 Joint Sealants
$6,130
Subtotal 07 Thermal and Moisture Protection
$14,698
09 Finishes
$17,300
09 21 16 Gypsum Board Assemblies 09211 Exterior 6", 16 GA Metal Stud w/ 3/4" Pressure Treated Plywood Both Sides (Softball Dugouts) (IS 9)
$13,500 756.00 sf
17.86
Subtotal 09 21 16 Gypsum Board Assemblies
$3,800 1.00 ls
3,800.00
$3,800
09903 Paint Cubbies (Softball Dugouts) (IS 9)
Alternate 7 Alternate 7 - Included
Subtotal 09 90 00 Painting and Coating
$3,800
Subtotal 09 Finishes
$17,300
31 Earthwork
$462,398
31 00 00 Earthwork
$343,913
30001 Earthwork - SUB
1.00 sub
30002 Pothole Utilities 30003 Private Locates
DATE PRINTED: 10/29/2025
Alternate 7
$13,500
09 90 00 Painting and Coating 09901 Paint Wood Trim & Underside of Dugout Ceilings (Softball Dugouts) (IS 9)
$13,500
258,855.60
$258,856
24.00 hr
641.84
$15,404
24.00 hr
961.73
$23,082
Page 27 of 35
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
30004 Construction Water
NOTES / COMMENTS Included
30005 Earthwork at Mechanical Pad for Groundmounted Air Handling Unit
See Below
30006 >Remove & Dispose Sidewalk
Included
30007 >Strip Site
Included
30008 >Export Strippings
Included
30009 >Excavate Cut to Fill
Included
30010 >Excavate Cut to Export
Included
30011 >Export Material
Included
30012 >Scarify Site 12" Depth
Included
30013 >Rough Grade Site
Included
30014 >Import & Place Class 6 Below Concrete Walk & Pad
Included
30015 >Excavate & Backfill Screen Wall
Included
30016 Earthwork for Irrigation Improvements 30019 >Protect Exist Trees & Maintain Exist Grades Around Tree Base
See Below 650.00 lf
8.35
$5,428
30020 Earthwork for Visitor Parking Lot - Concrete
See Below
30021 >Remove & Dispose Sidewalk
Included
30022 >Remove & Dispose Curb
Included
30023 >Sawcut for Demo
Included
30024 >Excavate Cut to Export
Included
30025 >Export Material
Included
30026 >Scarify Walks, 12" Depth
Included
30027 >Rough Grade Site
Included
30028 >Import & Place Class 6 Below Concrete Walk & Paving
Included
30029 Earthwork for Visitor Parking Lot - Paving
See Below
30030 >Remove & Dispose Pavement
Included
30031 >Sawcut for Demo
Included
30032 >Excavate Cut to Export
Included
30033 >Export Material
Included
30034 >Scarify Paving, 12" Depth
Included
30035 >Rough Grade Site
Included
30036 Earthwork for Front of School Drainage Improvement
See Below
30037 >Protect Exist Trees & Maintain Exist Grades Around Tree Base
364.00 lf
8.35
$3,039
30038 >Protect Exist Railing
243.00 lf
8.35
$2,029
DATE PRINTED: 10/29/2025
Page 28 of 35
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
30039 >Remove & Dispose Sidewalk/Ribbon Curb
Included
30040 >Strip Site
Included
30041 >Export Strippings
Included
30042 >Excavate Cut to Fill
Included
30043 >Excavate Cut to Export
Included
30044 >Export Material
Included
30045 >Scarify Site, 12" Depth
Included
30046 >Rough Grade Site
Included
30047 >Import & Place Class 6 Below Concrete Walk
Included
30048 >Regrade/Finish Site to +/- .1'
Included
30049 >Respread Removed Topsoil
Included
30050 Earthwork for New Gas Line in Loading Dock Area
See Below
30051 >Sawcut for Demo
Included
30052 >Remove & Dispose Pavement
Included
30053 >Remove & Dispose Sidewalk
Included
30054 >Remove & Dispose Curb
Included
30055 >Excavate Cut to Export
Included
30056 >Export Material
Included
30057 >Scarify Paving & Walks, 12" Depth
Included
30058 >Rough Grade Site
Included
30059 >Import & Place Class 6 Below Concrete Walk
Included
30071 Earthwork for Staff Parking Lot New Lights
See Below
30073 >Sawcut for Demo
Included
30074 >Remove & Dispose Pavement
Included
30075 >Remove & Dispose Sidewalk
Included
30076 >Remove & Dispose Curb
Included
30077 >Excavate Cut to Export
Included
30078 >Export Material
Included
30079 >Scarify Paving & Walks, 12" Depth
Included
30080 >Rough Grade Site
Included
30081 >Import & Place Class 6 Below Concrete Walk
Included
30082 Earthwork at Tennis Courts (IS 7)
1.00 ls
25,890.66
$25,891
Alternate 5 - See Below
30083 >Relocate Exist Boulders to Allow Conc Channel Installation (IS 7)
4.00 ea
62.88
$252
Alternate 5
30084 >Protect Exist Tennis Fence (IS 7)
175.00 lf
8.35
$1,461
Alternate 5
30085 >Protect Exist Boulder Retaining Wall (IS 7)
42.00 lf
8.35
$351
Alternate 5
DATE PRINTED: 10/29/2025
Page 29 of 35
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
30086 >Remove & Dispose Underdrain (IS 7)
Alternate 5 - Included
30087 >Remove & Dispose Concrete Walk (IS 7)
Alternate 5 - Included
30088 >Remove & Dispose Curb & Gutter (IS 7)
Alternate 5 - Included
30089 >Strip Site (IS 7)
Alternate 5 - Included
30090 >Export Strippings (IS 7)
Alternate 5 - Included
30091 >Scarify Site, 12" Depth (IS 7)
Alternate 5 - Included
30092 >Rough Grade Site (IS 7)
Alternate 5 - Included
30093 >Excavate & Backfill Trickle Channel (IS 7)
Alternate 5 - Included
30094 Earthwork at Softball Backstop (IS 8)
1.00 ls
8,121.24
$8,121
Alternate 6
30095 >Excavate, Remove, & Dispose Fence Posts & Footings/Caissons (IS 8)
Alternate 6 - w/ Div. 32 Fencing
30096 >Sawcut for Demo Concrete Paving/Sidewalk (IS 8)
Alternate 6 - Included
30097 >Remove & Disppose Concrete Paving/Sidewalk (IS 8)
Alternate 6 - Included
30098 >Scarify Below Concrete Walk, 12" Depth (IS 8)
Alternate 6 - Included
30099 >Furnish & Install 6" Class 6 Road Base Below Concrete Walk (IS 8)
Alternate 6 - Included
Subtotal 31 00 00 Earthwork
$343,913
31 25 00 Erosion and Sedimentation Controls 31201 Temporary Fencing (Installation/Removal/Maintenance) (Trailer Complex/Lay Down Area)
$118,485 756.00 lf
11.00
$8,316
1,521.00 lf
9.00
$13,689
31205 Temporary Fencing (Installation/Removal/Maintenance) (IS 7)
400.00 lf
9.00
$3,600
31207 Concrete Washout Area (CWA), 1.5 CY Pump Pan
36.00 ea
227.50
$8,190
31209 Concrete Washout Area (CWA), 5.5 CY Container
12.00 ea
417.50
$5,010
31211 Concrete Washout Area (CWA), 1.5 CY Pump Pan (IS 7)
6.00 ea
227.50
$1,365
31213 Area Inlet Protection (IP)
7.00 ea
740.00
$5,180
31215 Rock Socks (RS)
26.00 ea
148.00
$3,848
31217 Rock Socks (RS) (IS 7)
30.00 ea
148.00
$4,440
31219 Sediment Control Logs (SCL) (Temp. Fencing)
1,521.00 lf
4.28
$6,513
31221 Sediment Control Logs (SCL) (Temp. Fencing) (IS 7)
454.00 lf
4.28
$1,944
31223 Sediment Control Logs (SCL) (Swale, Mechanical Enclosure)
161.00 lf
4.28
$689
31225 Vehicle Tracking Control (VTC)
112.00 ea
287.51
$32,201
31203 Temporary Fencing (Installation/Removal/Maintenance)
DATE PRINTED: 10/29/2025
Alternate 5
Alternate 5
Alternate 5
Alternate 5
Page 30 of 35
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS Alternate 5
31227 Vehicle Tracking Control (VTC) (IS 7)
16.00 ea
287.51
$4,600
31229 SRM - Small Projects - 1-5 Acres
11.00 mo
900.00
$9,900
31319 Storm Water Engineering
11.00 mo
818.18
$9,000
Subtotal 31 25 00 Erosion and Sedimentation Controls
$118,485
Subtotal 31 Earthwork
$462,398
32 Exterior Improvements
$767,919
32 12 00 Flexible Paving 32001 Asphalt - SUB
$160,144 1.00 sub
147,256.00
$147,256
32003 Visitor Front Parking Lot
See Below - Included
32005 >Asphalt "T" Patch
Included
32007 >Asphalt Standard Duty Paving
Included
32009 >>Remove & Dispose of Pavement Section
w/ Div. 31 Earthwork
32011 >>Scarify & Re-compact Top 12" Subgrade
Included
32013 >>Furnish & Install 6" Class 6 Road Base
Included
32015 >>Furnish & Install 5" Asphalt
Included
32017 Loading Dock Lot for Gas Line
See Below - Included
32019 >Asphalt "T" Patch
Included
32021 >Asphalt Standard Duty Paving
Included
32023 >>Remove & Dispose of Pavement Section
w/ Div. 31 Earthwork
32025 >>Scarify & Re-compact Top 12" Subgrade
w/ Div. 22 Plumbing
32027 >>Furnish & Install 6" Class 6 Road Base
72.00 sy
28.47
$2,050
32029 >>Furnish & Install 5" Asphalt
Included
32031 >>Furnish & Install 5" Asphalt
Included
32033 Staff Lot for Electrical Line
See Below - Included
32035 >Asphalt "T" Patch
Included
32037 >Asphalt Standard Duty Paving
Included
32039 >>Remove & Dispose of Pavement Section
w/ Div. 31 Earthwork
32041 >>Scarify & Re-compact Top 12" Subgrade
w/ Div. 26 Electrical
32043 >>Furnish & Install 6" Class 6 Road Base
333.00 sy
19.69
$6,558
32045 Asphalt Patch at Visitor Lot due to Irrigation Improvements
62.00 lf
40.00
$2,480
32047 Asphalt Adjustment Index Cost for Liquid Asphalt (Binder)
3.00 tn
600.00
$1,800
Subtotal 32 12 00 Flexible Paving
$160,144
32 13 00 Rigid Paving
$197,586
DATE PRINTED: 10/29/2025
Page 31 of 35
DESCRIPTION 32110 Concrete - SUB
QTY UOM UNIT PRICE 1.00 sub
123,676.83
TOTAL COST
NOTES / COMMENTS
$123,677
32111 Visitor Front Parking Lot
See Below
32112 >Concrete Pavement/ADA Parking, 5" w/ Fibermesh
Included
32113 >Curb & Gutter, 24" w/ Fibermesh
Included
32114 >ADA Ramp, Type 2B
Included
32115 >>ADA Curb Wall, 6"x6" w/ Fibermesh
Included
32116 >>ADA Dome Detectable Panel, 24" Wide
Included
32117 Front of School Drainage Improvement
See Below
32118 >Concrete Ramp, 5" w/ Fibermesh
Included
32119 >Mowband, 6"x8" w/ Fibermesh, (1) #3 Rebar Cont. Plus Drainage Cut Outs
Included
32120 >>Additional Mowband Due to Ramp Alignment
101.00 lf
30.00
$3,030
32121 >Concrete Collars w/ Fibermesh, (1) #4 Rebar Ring, 6" Wide x 24" Dia, 8" Min. Deep
4.00 ea
400.00
$1,600
32122 Mechanical Pad
See Below
32123 >Mechanical Pad, 5", w/ Fibermesh, #4 Horiz @ 18"OCEW Chaired to Mid-Depth of Slab
Included
32124 >Concrete Curb, 8"x8", w/ Fibermesh, (1) #5 Horiz Top Bar
Included
32125 >>Weep Holes, Supply & Layout
12.00 ea
64.60
$775
32126 >Concrete Housekeeping Pad, 4", w/ Fibermesh, Reinf w/ #4 Dowels @ 18"OC at Perimeter, #4 Horiz @ 18"OC Chaired to Mid-Depth of Slab
Included
32127 >>Turn Down Edge at Gate Threshold w/ #4 Rebar x4' @ 12" OC w/ Std Hook
Included
32128 >Continuous Footing at Screenwall, 60"W x 12"D, Fibermesh, w/ (5)#6 Cont Long T&B, #6 Trans @ 12"OC T&B, #6 L Bar @ 12" OC
Included
Not Included Per RFI Response
32129 >Concrete Stem Wall 32130 >Sidewalk Near Mechanical Pad, 5" w/ Fibermesh
Included
32131 >New Concrete Channel/Splash Block, 24" Wide, 6" Thick w/ Fibermesh
Included
32132 New Gas
See Below
32133 >Replace Concrete Sidewalk
Included
32134 >Replace Concrete Curb & Gutter
10.00 lf
50.00
$500
32135 >Concrete Infill @ Trench for Underground Gas Piping into Boiler Room
25.00 lf
50.00
$1,250
32136 >Concrete Housekeeping Pad in Boiler Room, 4" Thick w/ Fibermesh, #4 Epoxy Set Dowels @ Perimeter @ 18" OC 32137 New Electric Line & Light Pole Bases
DATE PRINTED: 10/29/2025
Included
See Below
Page 32 of 35
DESCRIPTION 32138 >Replace Concrete Sidewalk
QTY UOM UNIT PRICE 120.00 sf
18.00
TOTAL COST
NOTES / COMMENTS
$2,160
32139 >Replace Concrete Curb & Gutter
Included
32140 >Concrete Pole Mounted Light Foundation/Base
Included
32141 >Drilling for Light Pole Base Foundations
9.00 ea
800.00
$7,200
32142 Irrigation Improvements
See Below
32143 >Replace Concrete Sidewalk
375.00 sf
18.00
$6,750
32144 >Replace Concrete Curb & Gutter
10.00 lf
30.00
$300
32145 Drainage Channel by Tennis Courts (IS 7) - SUB
1.00 sub
18,336.99
$18,337
32146 >Concrete Channel, 18" Wide, 6" Thick w/ Fibermesh (IS 7)
Alternate 5 - See Below Alternate 5 - Included
1.00 ls
750.00
$750
Alternate 5
32148 Concrete Sidewalk Replacement (IS 8)
245.00 sf
18.00
$4,410
Alternate 6
32149 Concrete Material Increase After 4/1/26
165.00 cy
6.87
$1,134
32150 Concrete Foreman
5.00 wk
3,667.75
$18,339
32151 Concrete Foreman (IS 7)
1.00 wk
3,667.75
$3,668
Alternate 5
32152 Concrete Foreman (IS 8)
1.00 wk
3,667.75
$3,668
Alternate 6
541.00 sy
0.07
$39
32147 >>Add Concrete Step/Drop (IS 7)
32153 Sweep/Clean Sitework Prior to Turnover Subtotal 32 13 00 Rigid Paving
$197,586
32 17 00 Paving Specialties 32271 Pavement Marking & Signage - SUB
$3,136 1.00 sub
3,135.50
$3,136
32273 Lines, 4", White
Included
32275 Handicap Symbol, Blue/White (1-10)
Included
32277 Handicap Sign on Unistrut Post (R7-8)
Included
32279 Van Accessible Sign (R7-8a)
Included
32281 Wheelchair Access Aisle, Absolutely No Parking Sign (R7-8bL & R7-8BR)
Included
Subtotal 32 17 00 Paving Specialties
$3,136
32 31 00 Fences and Gates
$52,174
32301 Repair/Replace Portion of Wood Baseball Outfield Fence
1.00 allow
35,230.00
$35,230
Allowance Per Spec. 01 2100 Allowances
32303 Remove/Replace Chain Link & Posts, 20' (Softball Backstop) (IS 8)
30.00 lf
398.47
$11,954
Alternate 6
32305 >Engineering (IS 8)
1.00 ls
2,500.00
$2,500
Alternate 6
32307 >Remove/Reinstall Backstop Kick Board (IS 8)
30.00 lf
40.00
$1,200
Alternate 6
32309 Remove Chain Link Fencing (IS 9)
84.00 lf
15.36
$1,290
Alternate 7
Subtotal 32 31 00 Fences and Gates
DATE PRINTED: 10/29/2025
$52,174
Page 33 of 35
DESCRIPTION
QTY UOM UNIT PRICE
32 90 00 Planting 32900 Landscape & Irrigation - SUB
TOTAL COST
NOTES / COMMENTS
$354,880 1.00 sub
282,897.31
$282,897
32901 Front of School Drainage Improvement
See Below
32902 >Irrigation System - Sod
Included
32903 >New Sod, Texas Hybrid Bluegrass
Included
32904 >Rock Mulch - 1-1/2". 4" Depth
Included
32905 >Soil Prep - Sod
Included Not Included. See Add Alternate.
32906 >Amended Topsoil, 6" Depth - Sod 32907 >Supply Water for Seeded Areas (Water twice per day for 3 months for 7 minutes) (Nonreclaimed Water)
8,844.00 sf
0.11
$973
32908 Improve Irrigation
See Below
32909 >Irrigation System - Turf Seed
Included
32910 >Sawcut Concrete Sidewalk/Asphalt Paving
Included
32911 >Remove & Disppose Concrete Sidewalk/Asphalt Paving
Included
32912 >Repair all Sod Damaged by Irrigation Improvements with 1/4" of 30% Sand & 70% Compost Mixture & Bluegrass Turf Seed
Included
Not Included. See Add Alternate.
32913 >Amended Topsoil, 6" Depth - Turf 32914 >Supply Water for Seeded Areas (Water twice per day for 3 months for 7 minutes) (Nonreclaimed Water)
148,620.00 sf
0.11
$16,348
32915 Tennis Court Landscape Improvement
See Below
32916 >Irrigation System - Native Seed
Included
32917 >New Native Seed
Included
32918 >Soil Prep - Native Seed
Included Not Included. See Add Alternate.
32919 >Amended Topsoil, 6" Depth - Native Seed 32920 >Supply Water for Seeded Areas (Water twice per day for 3 months for 7 minutes) (Nonreclaimed Water) (IS 2)
16,921.00 sf
0.11
$1,861
32921 Landscape Improvement at New Mechanical Enclosure
See Below
32922 >Irrigation System - Native Seed
Included
32923 >New Native Seed
Included
32924 >Soil Prep - Native Seed
Included Not Included. See Add Alternate.
32925 >Amended Topsoil, 6" Depth - Native Seed 32926 >Rock Mulch - 1-1/2". 4" Depth 32927 >Supply Water for Seeded Areas (Water twice per day for 3 months for 7 minutes) (NonDATE PRINTED: 10/29/2025
Included 1,202.00 sf
0.11
$132
Page 34 of 35
DESCRIPTION per day for 3 months for 7 minutes) (Nonreclaimed Water)
QTY UOM UNIT PRICE
TOTAL COST
32928 30 Day Maintenance at Sod & Turf Seed 32930 Landscape & Irrigation Repair by Tennis Courts New Drainage Channel (IS 7) - SUB
NOTES / COMMENTS
Included 1.00 sub
29,668.47
$29,668
Alternate 5 - See Below
32931 >Irrigation System - Native Seed (IS 7)
Alternate 5 - Included
32932 >New Native Seed (IS 7)
Alternate 5 - Included
32933 >Soil Prep - Native Seed (IS 7)
Alternate 5 - Included
32934 >Amended Topsoil, 6" Depth - Native Seed (IS 7) 32935 >Grouted Cobble (IS 7) 32936 >Supply Water for Seeded Areas (Water twice per day for 3 months for 7 minutes) (Nonreclaimed Water) (IS 7) 32937 Irrigation System Repair Allowance (IS 8)
8,625.00 sf
1.25
$10,786
Alternate 5
179.00 sf
35.00
$6,265
Alternate 5
8,625.00 sf
0.11
$949
Alternate 5
5,000.00
$5,000
Alternate 6
1.00 allow
Subtotal 32 90 00 Planting
$354,880
Subtotal 32 Exterior Improvements
$767,919
Total Site
DATE PRINTED: 10/29/2025
$1,508,210
Page 35 of 35
Exhibit D
Contract Time Schedule Itemization ofGMP Cost Itemization of the Dollars requested for long lead equipment and material packages
Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20
RE: Schedule Narrative – October 2025 Schedule Update Narrative October 17, 2025 BVSD – Fairview High School 1515 Greenbriar Blvd. Boulder CO. 80305 The following is a schedule narrative for the BVSD – Fairview Highschool [Boulder Valley RFP 25-04 CMGC Project Scope #1 - Fairview High School 10.17.2025.pdf] is attached.
Summary: This updated schedule reflects revisions to the DD schedule and aligns with the bi-weekly OAC dashboard timelines. It outlines the project timeline from preconstruction to construction activities and provides key milestone dates during preconstruction to allow for a successful construction phase during the summer of 2026 and 2027. AP has been actively identifying long-lead procurement items starting at the Schematic Design phase. In collaboration with trade partners, AP has gathered lead times, submittal preparation costs, and material release costs.
Description of Activities on the most Critical Path The current critical path for summer of 2026 work is driven by certain areas of work. Room 408 is currently on the critical path due to the contractor coordination required in that space. Also, the Commons RTU replacement is shown on the critical path due to the level of work in the ceilings above and the installation of finishes throughout those corridors. The 200 level corridor upgrades are on the critical path for summer of 27 due to the access that is required around this space for the computer lab work that would take priority during the first summer. Currently all of these areas are on track to hit their targeted turn over dates.
Monthly Progress Description The schedule has been updated, and activities have been adjusted to reflect the latest CD documents. Tasks have been progressed since the previous update.
Current/Anticipated Problem Areas and/or Delaying Factors BVSD & AP have preordered long lead time material as noted in the Amendment 1 procurement change order. AP is tracking all long lead time material with the master schedule for completion to meet the required schedule.
Revisions to the Project Schedule The updates made to establish a targeted flow through the building, and items and areas have been adjusted to maximize the efficiency of the first summer opportunity of work.
Narrative Review To recap the attached schedule and the above update: •
Overall, the attached schedule provides a road map for the design and construction of the BVSDFairview High School. As more planning, coordination, and construction scope is defined and developed, the schedule will continue to reflect these changes and updates.
•
The current schedule has an anticipated construction completion date of August 1st 2027 with milestone completion dates for TCO by August 1st 2026.
•
The team is tracking numerous important dates: document release, funding package dates, and material release dates. AP will continue to update the team in forthcoming narratives and OAC meetings
•
Lastly, the schedule changes and modifications outlined above help to more accurately show how the project is being built and ways that BVSD,MOA, AP and their subcontractors are working to maintain or improve the project completion date.
Please feel free to contact me with any questions or comments regarding this update or anything else within the Project. Thank you, Logan Dickerman Superintendent Adolfson & Peterson Construction 720.456.1992 ldickerman@a-p.com
Line
Name
Duration
BVSD - Fairview High School
APC
Start
Finish
A 12
S 9
2024 O N 7 4
D 2
2025 J F M A M J J 30 27 24 24 21 19 16 14
781d 16.62
8/12/2024
446d 21.94
8/12/2024
5/18/2026
RFP / RFQ Information
49d 100.00
8/12/2024
10/18/2024
1
RFP Issued to Contractor
1d 100.00
8/12/2024 A
8/12/2024 A
2
RFP Site Walk
1d 100.00
8/22/2024 A
8/22/2024 A
3
RFP Inquiries Due
1d 100.00
9/4/2024 A
9/4/2024 A
4
RFP Addendum Sent
1d 100.00
9/12/2024 A
9/12/2024 A
5
RFP Submission Deadline
1d 100.00
10/3/2024 A
10/3/2024 A
6
RFP Evaluation
1d 100.00
10/11/2024 A 10/11/2024 A
RFP Evaluation
7
CMGC Contract Award
1d 100.00
10/18/2024 A 10/18/2024 A
CMGC Contract Award
Preconstruction
Document Development
390d 72.30
Schematic Design
A 11
S 8
O 6
2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13
10/21/2024
5/7/2026
150d 100.00 10/21/2024
5/27/2025
73d 100.00
1/7/2025 A
4/17/2025 A
SD- Early VFA Investigation and Verification
10
SD- Schematic Design Pricing/ Constructibility Review
23d 100.00
2/17/2025 A
3/19/2025 A
SD- Schematic Design Pricing/ Constructibility Review
11
SD- BVSD DAT & Facility Page Flip
1d 100.00
2/17/2025 A
2/17/2025 A
12
SD- Schematic Design Bid Leveling/ Review Meeting
1d 100.00
3/10/2025 A
3/10/2025 A
SD- Schematic Design Bid Leveling/ Review Meeting
13
SD- Schematic Design - Budget/ Constructibility Corrections
4d 100.00
3/11/2025 A
3/14/2025 A
SD- Schematic Design - Budget/ Constructibility Corrections
14
SD- Early Procurement Package Creation By AP
30d 100.00
3/17/2025 A
4/25/2025 A
15
SD- Early Procurement Package Review with BVSD
15d 100.00
4/28/2025 A
5/16/2025 A
16
SD- Early Procurement Package Issuance to Board
5d 100.00
5/20/2025 A
5/27/2025 A
63d 100.00
4/18/2025
7/17/2025
20d 100.00
4/18/2025 A
5/15/2025 A
28d 100.00
5/16/2025 A
6/25/2025 A
1d 100.00
5/16/2025 A
5/16/2025 A
1d 100.00
6/25/2025 A
6/25/2025 A
DD- Design Development - Pricing/ Constructibility Internal Review
9d 100.00
6/26/2025 A
7/9/2025 A
DD- Design Development - Budget/ Constructibility Corrections
1d 100.00
7/17/2025 A
7/17/2025 A
20 21 22
DD- Design Development - Pricing/ Constructibility Internal Review DD- Design Development - Budget/ Constructibility Corrections DD- Design Development - Final Procurement Package Allocation Review to start Long Lead Submittals Owner Items - Xcel Upgrades
SD- BVSD DAT & Facility Page Flip
SD- Early Procurement Package Creation By AP
SD- Early Procurement Package Review with BVSD
SD- Early Procurement Package Issuance to Board
DD- Design Development - Design Development Complete
DD- Design Development - Pricing/ Constructibility Review
DD- BVSD DAT & Facility Page Flip
DD- Design Development - Final Procurement Package Allocation Review to start Long Lead Submittals
170d 17.65
9/5/2025
5/7/2026
XU-BVSD Application Creation/ Submission
10d 100.00
9/5/2025 A
9/18/2025 A
24
XU-BVSD Application Approval
60d 33.33
9/19/2025 A
12/15/2025
25
XU-Xcel Design and Review Time
60d
12/16/2025
3/12/2026
XU-Xcel Design and Review Time
26
XU-Xcel Approval
30d
3/13/2026
4/23/2026
XU-Xcel Approval
27
XU-Install New Gas Line/ Meter
10d
4/24/2026
5/7/2026
5/30/2025
12/26/2025 10/21/2025
145d 64.13
Procurement Package
101d 95.16
5/30/2025
28
C&A-PP-Board Approval
5d 100.00
5/30/2025 A
6/5/2025 A
29
C&A-PP-BVSD Contract Execution to AP
10d 100.00
6/6/2025 A
8/14/2025 A
30
C&A-PP-AP Contract Execution to Procurement Package Subs
47d 93.62
8/15/2025 A
10/21/2025
30d
11/11/2025 12/26/2025
FGMP
2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12
SD- Schematic Design Complete
23
Contracting & Award
S 6
RFP Submission Deadline
SD- Early VFA Investigation and Verification
DD- BVSD DAT & Facility Page Flip
A 9
RFP Addendum Sent
9
19
2027 D J F M A M J J 30 28 25 22 22 19 17 14 12
RFP Inquiries Due
10/21/2024 A 2/14/2025 A
DD- Design Development - Design Development Complete DD- Design Development - Pricing/ Constructibility Review
N 2
RFP Site Walk
79d 100.00
18
O 5
RFP Issued to Contractor
SD- Schematic Design Complete
17
S 7
9/14/2027
8
Design Development
A 10
Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School
XU-BVSD Application Creation/ Submission
XU-BVSD Application Approval
XU-Install New Gas Line/ Meter
C&A-PP-Board Approval
C&A-PP-BVSD Contract Execution to AP
C&A-PP-AP Contract Execution to Procurement Package Subs
Job #: Fairview High School
Rev. date: 10/17/2025 12:41:15 PM
Data Date: 10/17/2025
Page 1 of 13
3. Print View Filter: No Summary Tasks
J 10
A 7
S 4
Line
Name
Duration
APC
Start
Finish
31
C&A-FGMP-Board Approval
5d
11/11/2025
11/17/2025
32
C&A-FGMP-BVSD Contract Execution to AP
10d
11/18/2025
12/3/2025
33
C&A-FGMP-AP Contract Execution to Procurement Package Subs
15d
12/4/2025
12/26/2025
8d 100.00
7/14/2025
7/23/2025
Early Verification and Coordination
A 12
S 9
2024 O N 7 4
D 2
2025 J F M A M J J 30 27 24 24 21 19 16 14
A 11
S 8
O 6
2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13
2d 100.00
7/14/2025 A
7/15/2025 A
EI-Design/Sub Kick off Meeting
EI-Onsite Review of Electrical Scope/ Lighting Study
2d 100.00
7/16/2025 A
7/17/2025 A
EI-Onsite Review of Electrical Scope/ Lighting Study
36
EI-Onsite Review of Mechanical Scope
2d 100.00
7/18/2025 A
7/21/2025 A
EI-Onsite Review of Mechanical Scope
37
EI-Onsite Review of Remaining Scope
2d 100.00
7/22/2025 A
7/23/2025 A
EI-Onsite Review of Remaining Scope
124d 86.40
5/16/2025
11/10/2025
38
CD- Construction Documents and Drawings Complete
83d 100.00
5/16/2025 A
9/12/2025 A
39
CD- Construction Documents - Pricing Review
25d 96.00
9/15/2025 A
10/17/2025
40
CD- BVSD DAT & Facility Page Flip
1d 100.00
9/15/2025 A
9/15/2025 A
41
CD- Construction Documents - FGMP Review with BVSD PM
1d
10/20/2025
10/20/2025
CD- Construction Documents - FGMP Review with BVSD PM
42
CD- Construction Documents - FGMP Corrections
5d
10/21/2025
10/27/2025
CD- Construction Documents - FGMP Corrections
43
CD- Construction Documents - Final FGMP Amendment to District Board of Education Submission
10d
10/28/2025
11/10/2025
145d 11.71
9/15/2025
4/10/2026
Building Permit Review and Issuance
125d 19.20
9/15/2025 A
3/13/2026
45
Remaining Permit Approval
40d
1/6/2026
3/2/2026
40d
46
Local AHJ Permit Review and Issuance Long Lead Submittals & Procurement Submittals & Procurement - Fire Alarm Equipment Submittals & Procurement - Fire Alarm Equipment
2/16/2026
4/10/2026
197d 5.89
8/7/2025
5/18/2026
130d
10/22/2025
4/28/2026
130d
10/22/2025
4/28/2026
Building Permit Review and Issuance
Remaining Permit Approval
Local AHJ Permit Review and Issuance
11/18/2025
S&P - FA - Subcontractor Submittals
48
S&P - FA - AP Review
5d
11/19/2025
11/25/2025
S&P - FA - AP Review
49
S&P - FA - AHJ Review and Approval
15d
11/26/2025
12/18/2025
50
S&P - FA - A/E Review and Approval
10d
12/19/2025
1/6/2026
51
S&P - FA - Procurement
80d
1/7/2026
4/28/2026
75d
12/29/2025
4/13/2026
S&P - FA - AHJ Review and Approval
S&P - FA - A/E Review and Approval
S&P - FA - Procurement
75d
12/29/2025
4/13/2026
52
S&P - PA - Subcontractor Submittals
20d
12/29/2025
1/26/2026
S&P - PA - Subcontractor Submittals
53
S&P - PA - AP Review
5d
1/27/2026
2/2/2026
S&P - PA - AP Review
54
S&P - PA - A/E Review and Approval
10d
2/3/2026
2/16/2026
S&P - PA - A/E Review and Approval
55
S&P - PA - Procurement
40d
2/17/2026
4/13/2026
S&P - PA - Procurement
8/7/2025
4/30/2026
Submittals & Procurement - Gym RTU 901 Aaon
185d 18.67
8/7/2025
4/30/2026
56
S&P - RTU - Subcontractor Submittals
10d 100.00
8/7/2025 A
9/10/2025 A
S&P - RTU - Subcontractor Submittals
57
S&P - RTU - AP Review
1d 100.00
9/10/2025 A
9/10/2025 A
S&P - RTU - AP Review
58
S&P - RTU - A/E Review and Approval
12d 100.00
9/10/2025 A
9/25/2025 A
59
S&P - RTU - Procurement
143d 5.59
10/7/2025 A
4/30/2026
185d 15.09
8/7/2025
4/30/2026
Submittals & Procurement - Commons HVAC 1001 Aaon
Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School
2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12
CD- Construction Documents - Final FGMP Amendment to District Board of Education Submission
10/22/2025
185d 17.26
S 6
CD- Construction Documents - Pricing Review
20d
Submittals & Procurement - RTUs
A 9
CD- BVSD DAT & Facility Page Flip
S&P - FA - Subcontractor Submittals
Submittals & Procurement - PA Equipment
2027 D J F M A M J J 30 28 25 22 22 19 17 14 12
CD- Construction Documents and Drawings Complete
47
Submittals & Procurement - AV Equipment
N 2
C&A-FGMP-AP Contract Execution to Procurement Package Subs
EI-Design/Sub Kick off Meeting
Permitting
O 5
C&A-FGMP-BVSD Contract Execution to AP
35
44
S 7
C&A-FGMP-Board Approval
34
Construction Documents
A 10
S&P - RTU - A/E Review and Approval
S&P - RTU - Procurement
Job #: Fairview High School
Rev. date: 10/17/2025 12:41:15 PM
Data Date: 10/17/2025
Page 2 of 13
3. Print View Filter: No Summary Tasks
J 10
A 7
S 4
Line
Name
Duration
APC
Start
Finish
A 12
S 9
2024 O N 7 4
D 2
2025 J F M A M J J 30 27 24 24 21 19 16 14
A 11
S 8
O 6
2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13
60
S&P - RTU - Subcontractor Submittals
3d 100.00
8/7/2025 A
9/10/2025 A
S&P - RTU - Subcontractor Submittals
61
S&P - RTU - AP Review
1d 100.00
9/10/2025 A
9/10/2025 A
S&P - RTU - AP Review
62
S&P - RTU - A/E Review and Approval
12d 100.00
9/10/2025 A
9/25/2025 A
63
S&P - RTU - Procurement
143d 5.59
10/7/2025 A
4/30/2026
185d 15.09
8/7/2025
4/30/2026
Submittals & Procurement - Commons HVAC 1002 Aaon S&P - RTU - Subcontractor Submittals
3d 100.00
8/7/2025 A
9/10/2025 A
S&P - RTU - Subcontractor Submittals
S&P - RTU - AP Review
1d 100.00
9/10/2025 A
9/10/2025 A
S&P - RTU - AP Review
66
S&P - RTU - A/E Review and Approval
12d 100.00
9/10/2025 A
9/25/2025 A
67
S&P - RTU - Procurement
143d 5.59
10/7/2025 A
4/30/2026
140d 31.82
8/7/2025
2/26/2026
S&P - RTU - Subcontractor Submittals
22d 100.00
8/7/2025 A
9/10/2025 A
S&P - RTU - Subcontractor Submittals
S&P - RTU - AP Review
1d 100.00
9/10/2025 A
9/10/2025 A
S&P - RTU - AP Review
70
S&P - RTU - A/E Review and Approval
12d 100.00
9/10/2025 A
9/25/2025 A
71
S&P - RTU - Procurement
97d 7.22
10/8/2025 A
2/26/2026
85d
12/29/2025
4/27/2026
S&P - RTU- Subcontractor Submittals
10d
12/29/2025
1/12/2026
S&P - RTU- Subcontractor Submittals
S&P - RTU - AP Review
5d
1/13/2026
1/19/2026
S&P - RTU - AP Review
74
S&P - RTU- A/E Review and Approval
10d
1/20/2026
2/2/2026
75
S&P - RTU - Procurement
60d
2/3/2026
4/27/2026
135d
10/22/2025
5/5/2026
S&P - RTU - Procurement
135d
10/22/2025
5/5/2026
S&P - EDE - Subcontractor Submittals
20d
10/22/2025
11/18/2025
S&P - EDE - Subcontractor Submittals
77
S&P - EDE- AP Review
5d
11/19/2025
11/25/2025
S&P - EDE- AP Review
78
S&P - EDE - A/E Review and Approval
10d
11/26/2025
12/11/2025
79
S&P - EDE - Procurement
100d
12/12/2025
5/5/2026
55d
12/29/2025
3/16/2026
S&P - EDE - A/E Review and Approval
S&P - EDE - Procurement
80
S&P - EDE - Subcontractor Submittals
10d
12/29/2025
1/12/2026
S&P - EDE - Subcontractor Submittals
81
S&P - EDE- AP Review
5d
1/13/2026
1/19/2026
S&P - EDE- AP Review
82
S&P - EDE - A/E Review and Approval
10d
1/20/2026
2/2/2026
83
S&P - EDE - Procurement
30d
2/3/2026
3/16/2026
85d
12/29/2025
4/27/2026
S&P - EDE - A/E Review and Approval
S&P - EDE - Procurement
84
S&P - EDE - Subcontractor Submittals
10d
12/29/2025
1/12/2026
S&P - EDE - Subcontractor Submittals
85
S&P - EDE- AP Review
5d
1/13/2026
1/19/2026
S&P - EDE- AP Review
86
S&P - EDE - A/E Review and Approval
10d
1/20/2026
2/2/2026
87
S&P - EDE - Procurement
60d
2/3/2026
4/27/2026
100d
12/29/2025
5/18/2026
S&P - EDE - A/E Review and Approval
S&P - EDE - Procurement
100d
12/29/2025
5/18/2026
88
S&P - SB- Subcontractor Submittals
10d
12/29/2025
1/12/2026
S&P - SB- Subcontractor Submittals
89
S&P - SB- AP Review
5d
1/13/2026
1/19/2026
S&P - SB- AP Review
90
S&P - SB- A/E Review and Approval
10d
1/20/2026
2/2/2026
Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School
2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12
S&P - RTU- A/E Review and Approval
76
Submittals & Procurement - Scoreboards
S 6
S&P - RTU - Procurement
73
Submittals & Procurement - Scoreboards - NOT IN SCOPE
A 9
S&P - RTU - A/E Review and Approval
72
Submittals & Procurement - Centaurus Lighting Control Equipment
2027 D J F M A M J J 30 28 25 22 22 19 17 14 12
S&P - RTU - Procurement
69
Submittals & Procurement - Centaurus LED Lighting
N 2
S&P - RTU - A/E Review and Approval
68
Submittals & Procurement - Electrical Distribution Equipment Submittals & Procurement - Main Distribution Panel Board - BRA
O 5
S&P - RTU - Procurement
65
Submittals & Procurement - RTU Controls
S 7
S&P - RTU - A/E Review and Approval
64
Submittals & Procurement - Commons HVAC 1001 & 1002 ACCU
A 10
S&P - SB- A/E Review and Approval
Job #: Fairview High School
Rev. date: 10/17/2025 12:41:16 PM
Data Date: 10/17/2025
Page 3 of 13
3. Print View Filter: No Summary Tasks
J 10
A 7
S 4
Line 91
Name
Duration
S&P - SB- Procurement Submittals & Procurement - Division 8 Submittals & Procurement - Aluminum Windows
APC
Start
Finish
75d
2/3/2026
5/18/2026
115d
10/22/2025
4/7/2026
A 12
S 9
2024 O N 7 4
D 2
2025 J F M A M J J 30 27 24 24 21 19 16 14
A 11
S 8
O 6
2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13
110d
10/22/2025
3/31/2026
S&P - D8- Subcontractor Submittals
20d
10/22/2025
11/18/2025
S&P - D8- Subcontractor Submittals
93
S&P - D8 - AP Review
5d
11/19/2025
11/25/2025
S&P - D8 - AP Review
94
S&P - D8- A/E Review and Approval
15d
11/26/2025
12/18/2025
95
S&P - D8 - Procurement
70d
12/19/2025
3/31/2026
115d
10/22/2025
4/7/2026
S&P - D8- Subcontractor Submittals
20d
10/22/2025
11/18/2025
S&P - D8- Subcontractor Submittals
S&P - D8 - AP Review
5d
11/19/2025
11/25/2025
S&P - D8 - AP Review
98
S&P - D8- A/E Review and Approval
15d
11/26/2025
12/18/2025
99
S&P - D8 - Procurement
75d
12/19/2025
4/7/2026
135d
10/22/2025
5/5/2026
135d
10/22/2025
5/5/2026
20d
10/22/2025
11/18/2025
S&P - WH- Subcontractor Submittals
101
S&P - WH - AP Review
5d
11/19/2025
11/25/2025
S&P - WH - AP Review
102
S&P - WH- A/E Review and Approval
10d
11/26/2025
12/11/2025
103
S&P - WH- Procurement
100d
12/12/2025
5/5/2026
114d
10/22/2025
4/6/2026
114d
10/22/2025
4/6/2026
20d
10/22/2025
11/18/2025
S&P - CW- Subcontractor Submittals
105
S&P - CW- AP Review
5d
11/19/2025
11/25/2025
S&P - CW- AP Review
106
S&P - CW- A/E Review and Approval
10d
11/26/2025
12/11/2025
107
S&P - CW- Procurement
70d
12/29/2025
4/6/2026
110d
10/22/2025
3/31/2026
S&P - CW- A/E Review and Approval
S&P - CW- Procurement
Submittals & Procurement - Graphics
110d
10/22/2025
3/31/2026
108
S&P - Graphic- Subcontractor Submittals
20d
10/22/2025
11/18/2025
S&P - Graphic- Subcontractor Submittals
109
S&P - Graphic- AP Review
5d
11/19/2025
11/25/2025
S&P - Graphic- AP Review
110
S&P - Graphic- A/E Review and Approval
20d
11/26/2025
12/29/2025
111
S&P - Graphic- Procurement
65d
12/30/2025
3/31/2026
105d
10/22/2025
3/24/2026
Submittals & Procurement - Fume Hoods
S&P - Graphic- A/E Review and Approval
S&P - Graphic- Procurement
105d
10/22/2025
3/24/2026
112
S&P - FH- Subcontractor Submittals
20d
10/22/2025
11/18/2025
S&P - FH- Subcontractor Submittals
113
S&P - FH- AP Review
5d
11/19/2025
11/25/2025
S&P - FH- AP Review
114
S&P - FH- A/E Review and Approval
20d
11/26/2025
12/29/2025
115
S&P - FH- Procurement
60d
12/30/2025
3/24/2026
95d
12/29/2025
5/11/2026
Submittals & Procurement - All Other Submittals 116
S&P - Other - Subcontractor Submittals
20d
12/29/2025
1/26/2026
117
S&P - Other - AP Review
10d
1/27/2026
2/9/2026
118
S&P - Other - A/E Review and Approval
15d
2/10/2026
3/2/2026
Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School
2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12
S&P - WH- Procurement
S&P - CW- Subcontractor Submittals
Submittals & Procurement - Fume Hoods - Not in scope
S 6
S&P - WH- A/E Review and Approval
104
Submittals & Procurement - Graphics
A 9
S&P - D8 - Procurement
S&P - WH- Subcontractor Submittals
Submittals & Procurement - Casework
2027 D J F M A M J J 30 28 25 22 22 19 17 14 12
S&P - D8- A/E Review and Approval
100
Submittals & Procurement - Casework
N 2
S&P - D8 - Procurement
97
Submittals & Procurement - Water Heaters and Boilers
O 5
S&P - D8- A/E Review and Approval
96
Submittals & Procurement - Water Heaters
S 7
S&P - SB- Procurement
92
Submittals & Procurement - Hollow Metal Doors, Frames, Hardware
A 10
S&P - FH- A/E Review and Approval
S&P - FH- Procurement
S&P - Other - Subcontractor Submittals
S&P - Other - AP Review
S&P - Other - A/E Review and Approval
Job #: Fairview High School
Rev. date: 10/17/2025 12:41:16 PM
Data Date: 10/17/2025
Page 4 of 13
3. Print View Filter: No Summary Tasks
J 10
A 7
S 4
Line 119
Name
Duration
S&P - Other - Procurement
APC
Finish
3/3/2026
5/11/2026
146d 50.00
5/13/2025
12/9/2025
50d
Board Dates
Start
120
1st May Board Date
1d 100.00
5/13/2025 A
5/13/2025 A
121
2nd May Board Date
1d 100.00
5/27/2025 A
5/27/2025 A
122
Only November Board Date
1d
11/11/2025 *
11/11/2025
123
Only December Board Date
1d
12/9/2025 *
12/9/2025
Owner Key Dates
579d 33.33
4/18/2025
8/2/2027
124
2025 Spring Break
5d 100.00
4/18/2025 A
4/24/2025 A
125
2025 End of School Year
1d 100.00
5/27/2025 A
5/27/2025 A
126
2025/2026 School Year Begin
1d 100.00
8/8/2025 A
8/8/2025 A
127
2026 Spring Break
5d
3/23/2026 *
3/27/2026
128
2026 End of School Year
1d
5/26/2026 *
5/26/2026
129
2026/2027 School Year Begins
1d
8/3/2026 *
8/3/2026
130
2027 Spring Break
5d
3/29/2027 *
4/2/2027
131
2027 End of School Year
1d
5/27/2027 *
5/27/2027
132
2027/2028 School Year Begins
1d
8/2/2027 *
8/2/2027
376d
3/23/2026
9/14/2027
5d
4/27/2026
5/1/2026
5d
4/27/2026
5/1/2026
332d
3/23/2026
7/13/2027
320d
4/8/2026
7/13/2027
320d
4/8/2026
7/13/2027
320d
4/8/2026
7/13/2027
4/8/2026
4/8/2026
Construction Site Mobilization 133
Mob - Site mobilization Intierior Finish and Fittout Cooridors Cooridor Upgrades 200 Level Cooridor Upgrades
A 12
S 9
2024 O N 7 4
D 2
2025 J F M A M J J 30 27 24 24 21 19 16 14
A 11
S 8
O 6
2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13
A 10
S 7
O 5
N 2
2027 D J F M A M J J 30 28 25 22 22 19 17 14 12
A 9
S 6
2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12
S&P - Other - Procurement
1st May Board Date
2nd May Board Date
Only November Board Date
Only December Board Date
2025 Spring Break
2025 End of School Year
2025/2026 School Year Begin
2026 Spring Break
2026 End of School Year
2026/2027 School Year Begins
2027 Spring Break
2027 End of School Year
2027/2028 School Year Begins
Mob - Site mobilization
134
IFF-200COR-ALT Replace Doors*
135
IFF-200COR-Abatement of Flooring (PH 2)
5d
5/27/2027
6/3/2027
IFF-200COR-Abatement of Flooring (PH 2)
136
IFF-200COR-MEP Safe off of Ceilings
2d
6/4/2027
6/7/2027
IFF-200COR-MEP Safe off of Ceilings
137
IFF-200COR-Demo Existing ACT
2d
6/8/2027
6/9/2027
IFF-200COR-Demo Existing ACT
138
IFF-200COR-Install new ACT
3d
6/10/2027
6/14/2027
IFF-200COR-Install new ACT
139
IFF-200COR-MEP Device Ceilings
3d
6/15/2027
6/17/2027
IFF-200COR-MEP Device Ceilings
140
IFF-200COR-White out Ceilings
1d
6/18/2027
6/18/2027
IFF-200COR-White out Ceilings
141
IFF-200COR-Install new Flooring
3d
6/21/2027
6/23/2027
IFF-200COR-Install new Flooring
142
IFF-200COR-Paint Walls
3d
6/24/2027
6/28/2027
IFF-200COR-Paint Walls
143
IFF-200COR-Install Base
2d
6/29/2027
6/30/2027
IFF-200COR-Install Base
144
IFF-200COR-Final Clean
8d
7/1/2027
7/13/2027
30d
5/26/2026
7/7/2026
300 Level Cooridor Upgrades
IFF-200COR-ALT Replace Doors*
IFF-200COR-Final Clean
145
IFF-300COR-Clean Demo Flooring
3d
5/26/2026
5/28/2026
IFF-300COR-Clean Demo Flooring
146
IFF-300COR-MEP Safe off of Ceilings
2d
5/29/2026
6/1/2026
IFF-300COR-MEP Safe off of Ceilings
147
IFF-300COR-Demo Existing ACT
2d
6/2/2026
6/3/2026
IFF-300COR-Demo Existing ACT
148
IFF-300COR-Install new ACT
3d
6/4/2026
6/8/2026
IFF-300COR-Install new ACT
149
IFF-300COR-MEP Device Ceilings
3d
6/9/2026
6/11/2026
IFF-300COR-MEP Device Ceilings
150
IFF-300COR-Install new Flooring
3d
6/12/2026
6/16/2026
IFF-300COR-Install new Flooring
Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School
Job #: Fairview High School
Rev. date: 10/17/2025 12:41:16 PM
Data Date: 10/17/2025
Page 5 of 13
3. Print View Filter: No Summary Tasks
J 10
A 7
S 4
Line
Name
Duration
APC
Start
Finish
A 12
S 9
2024 O N 7 4
D 2
2025 J F M A M J J 30 27 24 24 21 19 16 14
A 11
S 8
O 6
2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13
A 10
S 7
O 5
N 2
151
IFF-300COR-White out Ceilings
1d
6/17/2026
6/17/2026
IFF-300COR-White out Ceilings
152
IFF-300COR-Paint Walls
3d
6/18/2026
6/22/2026
IFF-300COR-Paint Walls
153
IFF-300COR-Install Base
2d
6/23/2026
6/24/2026
IFF-300COR-Install Base
154
IFF-300COR-Final Clean
8d
6/25/2026
7/7/2026
31d
5/29/2026
7/13/2026
400 Level Cooridor Upgrades
2027 D J F M A M J J 30 28 25 22 22 19 17 14 12
IFF-400COR-Clean Demo Flooring
3d
5/29/2026
6/2/2026
IFF-400COR-Clean Demo Flooring
156
IFF-400COR-MEP Safe off of Ceilings
2d
6/3/2026
6/4/2026
IFF-400COR-MEP Safe off of Ceilings
157
IFF-400COR-Demo Existing ACT
2d
6/5/2026
6/8/2026
IFF-400COR-Demo Existing ACT
158
IFF-400COR-Install new ACT
3d
6/9/2026
6/11/2026
IFF-400COR-Install new ACT
159
IFF-400COR-MEP Device Ceilings
3d
6/12/2026
6/16/2026
IFF-400COR-MEP Device Ceilings
160
IFF-400COR-Install new Flooring
4d
6/17/2026
6/22/2026
IFF-400COR-Install new Flooring
161
IFF-400COR-White out Ceilings
1d
6/23/2026
6/23/2026
IFF-400COR-White out Ceilings
162
IFF-400COR-Paint Walls
3d
6/24/2026
6/26/2026
IFF-400COR-Paint Walls
163
IFF-400COR-Install Base
2d
6/29/2026
6/30/2026
IFF-400COR-Install Base
164
IFF-400COR-Final Clean
8d
7/1/2026
7/13/2026
37d
5/29/2026
7/21/2026
IFF-600COR-Clean Demo Flooring
3d
5/29/2026
6/2/2026
IFF-600COR-Clean Demo Flooring
166
IFF-600COR-MEP Safe off of Ceilings
2d
6/3/2026
6/4/2026
IFF-600COR-MEP Safe off of Ceilings
167
IFF-600COR-Demo Existing ACT
2d
6/5/2026
6/8/2026
IFF-600COR-Demo Existing ACT
168
IFF-600COR-Install new ACT
5d
6/9/2026
6/15/2026
IFF-600COR-Install new ACT
169
IFF-600COR-MEP Device Ceilings
3d
6/16/2026
6/18/2026
IFF-600COR-MEP Device Ceilings
170
IFF-600COR-Install new Flooring
3d
6/19/2026
6/23/2026
IFF-600COR-Install new Flooring
171
IFF-600COR-White out Ceilings
1d
6/24/2026
6/24/2026
IFF-600COR-White out Ceilings
172
IFF-600COR-Replace Doors
5d
6/25/2026
7/1/2026
IFF-600COR-Replace Doors
173
IFF-600COR-Paint Walls
3d
7/2/2026
7/7/2026
IFF-600COR-Paint Walls
174
IFF-600COR-Install Base
2d
7/8/2026
7/9/2026
IFF-600COR-Install Base
175
IFF-600COR-Final Clean
8d
7/10/2026
7/21/2026
IFF-600COR-Final Clean
42d
5/26/2026
7/23/2026
176
IFF-900COR-Clean Demo Flooring
3d
5/26/2026
5/28/2026
177
IFF-900COR-Install new Flooring
8d
7/9/2026
7/20/2026
IFF-900COR-Install new Flooring
178
IFF-900COR-Install Base
5d
7/16/2026
7/22/2026
IFF-900COR-Install Base
179
IFF-900COR-Final Clean
1d
7/23/2026
7/23/2026
IFF-900COR-Final Clean
270d
5/26/2026
6/17/2027
200 Level Classroom Improvements Room 225 & 228 - Classroom Improvements
IFF-900COR-Clean Demo Flooring
40d
5/26/2026
7/21/2026
180
IFF-225&228-Owner Move
1d
5/26/2026
5/26/2026
IFF-225&228-Owner Move
181
IFF-225&228-MEP Safe off
1d
5/27/2026
5/27/2026
IFF-225&228-MEP Safe off
182
IFF-225&228-Clean Demo flooring, Platform, Ceilings, Gyp
2d
5/28/2026
5/29/2026
IFF-225&228-Clean Demo flooring, Platform, Ceilings, Gyp
183
IFF-225&228-Abatement of Window Walls
4d
5/28/2026
6/2/2026
IFF-225&228-Abatement of Window Walls
184
IFF-225&228-Cut Access Hole In Slab
2d
6/1/2026
6/2/2026
IFF-225&228-Cut Access Hole In Slab
185
IFF-225&228-Install Kneewall Supports
3d
6/3/2026
6/5/2026
IFF-225&228-Install Kneewall Supports
186
IFF-225&228-Install Crawlspace Raceways
2d
6/3/2026
6/4/2026
IFF-225&228-Install Crawlspace Raceways
Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School
2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12
IFF-400COR-Final Clean
165
900 Level Cooridor Upgrades
S 6
IFF-300COR-Final Clean
155
600 Level Cooridor Upgrades
A 9
Job #: Fairview High School
Rev. date: 10/17/2025 12:41:16 PM
Data Date: 10/17/2025
Page 6 of 13
3. Print View Filter: No Summary Tasks
J 10
A 7
S 4
Line
Name
Duration
APC
Start
Finish
A 12
S 9
2024 O N 7 4
D 2
2025 J F M A M J J 30 27 24 24 21 19 16 14
A 11
S 8
O 6
2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13
A 10
S 7
O 5
N 2
2027 D J F M A M J J 30 28 25 22 22 19 17 14 12
187
IFF-225&228-Frame New Walls
2d
6/8/2026
6/9/2026
IFF-225&228-Frame New Walls
188
IFF-225&228-MEP rough In
4d
6/10/2026
6/15/2026
IFF-225&228-MEP rough In
189
IFF-225&228-H/T/F Gyp
6d
6/16/2026
6/23/2026
IFF-225&228-H/T/F Gyp
190
IFF-225&228-Prime and First Coat
1d
6/24/2026
6/24/2026
IFF-225&228-Prime and First Coat
191
IFF-225&228-Install ACT Ceilings
1d
6/25/2026
6/25/2026
IFF-225&228-Install ACT Ceilings
192
IFF-225&228-MEP Trim Out Walls & Ceilings
4d
6/26/2026
7/1/2026
IFF-225&228-MEP Trim Out Walls & Ceilings
193
IFF-225&228-White out Ceiling
1d
7/2/2026
7/2/2026
IFF-225&228-White out Ceiling
194
IFF-225&228-Polish Concrete
6d
7/6/2026
7/13/2026
IFF-225&228-Polish Concrete
195
IFF-225&228-Final Paint Walls
2d
7/14/2026
7/15/2026
IFF-225&228-Final Paint Walls
196
IFF-225&228-Install Base
1d
7/16/2026
7/16/2026
IFF-225&228-Install Base
197
IFF-225&228-Final Clean
3d
7/17/2026
7/21/2026
IFF-225&228-Final Clean
27d
5/27/2026
7/2/2026
Room 222- Classroom Improvements
A 9
S 6
2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12
198
IFF-222-Owner Move
1d
5/27/2026
5/27/2026
IFF-222-Owner Move
199
IFF-222-Abatement of Flooring
4d
5/28/2026
6/2/2026
IFF-222-Abatement of Flooring
200
IFF-222-MEP Ceiling Safe Off
1d
6/3/2026
6/3/2026
IFF-222-MEP Ceiling Safe Off
201
IFF-222-Demo Ceiling
2d
6/4/2026
6/5/2026
IFF-222-Demo Ceiling
202
IFF-222-Clean Gyp Demo
2d
6/8/2026
6/9/2026
IFF-222-Clean Gyp Demo
203
IFF-222-Set new Door Frame
2d
6/10/2026
6/11/2026
IFF-222-Set new Door Frame
204
IFF-222-H/T/F Gyp
5d
6/12/2026
6/18/2026
IFF-222-H/T/F Gyp
205
IFF-222-Install New ACT
2d
6/19/2026
6/22/2026
IFF-222-Install New ACT
206
IFF-222-MEP Ceiling Rough in
3d
6/23/2026
6/25/2026
IFF-222-MEP Ceiling Rough in
207
IFF-222-White out Ceilings
1d
6/26/2026
6/26/2026
IFF-222-White out Ceilings
208
IFF-222-Install New Carpet & Base
3d
6/29/2026
7/1/2026
IFF-222-Install New Carpet & Base
209
IFF-222-Final Clean
1d
7/2/2026
7/2/2026
IFF-222-Final Clean
Room 214- Classroom Improvements
10d
6/4/2027
6/17/2027
210
IFF-214-Clean Demo Gyp and Door Frame
1d
6/4/2027
6/4/2027
IFF-214-Clean Demo Gyp and Door Frame
211
IFF-214-Reinstall Door Frame
2d
6/7/2027
6/8/2027
IFF-214-Reinstall Door Frame
212
IFF-214-H/T/F Gyp
5d
6/9/2027
6/15/2027
IFF-214-H/T/F Gyp
213
IFF-214-Final Paint Interior
2d
6/16/2027
6/17/2027
IFF-214-Final Paint Interior
Room 212- Classroom Improvements
10d
6/4/2027
6/17/2027
214
IFF-212-Clean Demo Gyp and Door Frame
1d
6/4/2027
6/4/2027
IFF-212-Clean Demo Gyp and Door Frame
215
IFF-212-Reinstall Door Frame
2d
6/7/2027
6/8/2027
IFF-212-Reinstall Door Frame
216
IFF-212-H/T/F Gyp
5d
6/9/2027
6/15/2027
IFF-212-H/T/F Gyp
217
IFF-212-Final Paint Interior
2d
6/16/2027
6/17/2027
IFF-212-Final Paint Interior
36d
5/26/2026
7/15/2026
300 Level Classroom Improvements
36d
5/26/2026
7/15/2026
218
Room 317 - Classroom Improvements IFF-317-Owner Move
2d
5/26/2026
5/27/2026
IFF-317-Owner Move
219
IFF-317-MEP Safe Off
1d
5/28/2026
5/28/2026
IFF-317-MEP Safe Off
220
IFF-317-Clean Demo Gyp, Casework, Floor
4d
5/29/2026
6/3/2026
IFF-317-Clean Demo Gyp, Casework, Floor
221
IFF-317-Install ACT
2d
6/4/2026
6/5/2026
IFF-317-Install ACT
222
IFF-317-MEP Rough in Ceilings and Walls
5d
6/8/2026
6/12/2026
IFF-317-MEP Rough in Ceilings and Walls
Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School
Job #: Fairview High School
Rev. date: 10/17/2025 12:41:16 PM
Data Date: 10/17/2025
Page 7 of 13
3. Print View Filter: No Summary Tasks
J 10
A 7
S 4
Line
Name
Duration
APC
Start
Finish
A 12
S 9
2024 O N 7 4
D 2
2025 J F M A M J J 30 27 24 24 21 19 16 14
A 11
S 8
O 6
2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13
A 10
S 7
O 5
N 2
223
IFF-317-H/T/F Gyp
8d
6/15/2026
6/24/2026
IFF-317-H/T/F Gyp
224
IFF-317-Prime and First Coat
2d
6/25/2026
6/26/2026
IFF-317-Prime and First Coat
225
IFF-317-Install Casework
3d
6/29/2026
7/1/2026
IFF-317-Install Casework
226
IFF-317-MEP Trim Out
3d
7/2/2026
7/7/2026
IFF-317-MEP Trim Out
227
IFF-317-Install LVT
3d
7/8/2026
7/10/2026
IFF-317-Install LVT
228
IFF-317-Final Paint
1d
7/13/2026
7/13/2026
IFF-317-Final Paint
229
IFF-317-Install Base
1d
7/14/2026
7/14/2026
IFF-317-Install Base
230
IFF-317-Final Clean
1d
7/15/2026
7/15/2026
IFF-317-Final Clean
42d
5/26/2026
7/23/2026
400 Level Classroom Improvements Room 408 - Science Classroom Improvements
2027 D J F M A M J J 30 28 25 22 22 19 17 14 12
42d
5/26/2026
7/23/2026
231
IFF-408-Owner Move
1d
5/26/2026
5/26/2026
IFF-408-Owner Move
232
IFF-408-MEP Safe off
1d
5/27/2026
5/27/2026
IFF-408-MEP Safe off
233
IFF-408- Clean Demo Casework and Gyp & Ceiling
3d
5/28/2026
6/1/2026
IFF-408- Clean Demo Casework and Gyp & Ceiling
234
IFF-408-Abatement of Flooring and Tops
6d
6/2/2026
6/9/2026
IFF-408-Abatement of Flooring and Tops
235
IFF-408-MEP Rough in & Hood Prep
5d
6/10/2026
6/16/2026
IFF-408-MEP Rough in & Hood Prep
236
IFF-Build Chase Wall
4d
6/17/2026
6/22/2026
IFF-Build Chase Wall
237
IFF-408-H/T/F Gyp
4d
6/23/2026
6/26/2026
IFF-408-H/T/F Gyp
238
IFF-408-Prime and First Coat
1d
6/29/2026
6/29/2026
IFF-408-Prime and First Coat
239
IFF-408-Install ACT
1d
6/30/2026
6/30/2026
IFF-408-Install ACT
240
IFF-408-MEP Ceiling Trim Out
3d
7/1/2026
7/6/2026
IFF-408-MEP Ceiling Trim Out
241
IFF-408-White out Ceiling
1d
7/7/2026
7/7/2026
IFF-408-White out Ceiling
242
IFF-408-Install Casework & Hood
3d
7/8/2026
7/10/2026
IFF-408-Install Casework & Hood
243
IFF-408-MEP Trim Out
3d
7/8/2026
7/10/2026
IFF-408-MEP Trim Out
244
IFF-408-Polish Flooring
6d
7/13/2026
7/20/2026
IFF-408-Polish Flooring
245
IFF-408-Final Clean
3d
7/21/2026
7/23/2026
IFF-408-Final Clean
26d
5/26/2026
6/30/2026
Room 420 - Science Classroom Improvements 246
IFF-420-Owner Move
1d
5/26/2026
5/26/2026
IFF-420-Owner Move
247
IFF-420-MEP Safe/ Disconnect Hood
2d
5/27/2026
5/28/2026
IFF-420-MEP Safe/ Disconnect Hood
248
IFF-420-MEP Safe off of Ceiling Devices
1d
5/29/2026
5/29/2026
IFF-420-MEP Safe off of Ceiling Devices
249
IFF-420-Demo Ceiling in Room
1d
6/1/2026
6/1/2026
IFF-420-Demo Ceiling in Room
250
IFF-420-Demo Duct Above Ceiling
2d
6/2/2026
6/3/2026
IFF-420-Demo Duct Above Ceiling
251
IFF-420-Patch Roof Penetration
2d
6/4/2026
6/5/2026
IFF-420-Patch Roof Penetration
252
IFF-420-Install Grid
2d
6/8/2026
6/9/2026
IFF-420-Install Grid
253
IFF-420-MEP Install Ceiling Devices
3d
6/10/2026
6/12/2026
IFF-420-MEP Install Ceiling Devices
254
IFF-420-White Out Ceiling
2d
6/15/2026
6/16/2026
IFF-420-White Out Ceiling
255
IFF-420-Final Clean
10d
6/17/2026
6/30/2026
IFF-420-Final Clean
14d
5/27/2026
6/15/2026
Room 414- Science Classroom Improvements 256
IFF-414-Swap out Lights
3d
5/27/2026
5/29/2026
IFF-414-Swap out Lights
257
IFF-414-Electrical rough in for Teaching Wall
3d
6/1/2026
6/3/2026
IFF-414-Electrical rough in for Teaching Wall
258
IFF-414-AV Teaching wall hook ups
3d
6/4/2026
6/8/2026
IFF-414-AV Teaching wall hook ups
259
IFF-414-Final Clean
5d
6/9/2026
6/15/2026
IFF-414-Final Clean
Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School
Job #: Fairview High School
Rev. date: 10/17/2025 12:41:16 PM
Data Date: 10/17/2025
Page 8 of 13
A 9
S 6
2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12
3. Print View Filter: No Summary Tasks
J 10
A 7
S 4
Line
Name
Duration
Room 421- Science Classroom Improvements
APC
Start
Finish
A 12
S 9
2024 O N 7 4
D 2
2025 J F M A M J J 30 27 24 24 21 19 16 14
A 11
S 8
O 6
2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13
A 10
S 7
O 5
N 2
2027 D J F M A M J J 30 28 25 22 22 19 17 14 12
12d
5/27/2026
6/11/2026
260
IFF-421-Swap out Lights
3d
5/27/2026
5/29/2026
IFF-421-Swap out Lights
261
IFF-421-Electrical rough in for Teaching Wall
3d
6/1/2026
6/3/2026
IFF-421-Electrical rough in for Teaching Wall
262
IFF-421-AV Teaching wall hook ups
3d
6/4/2026
6/8/2026
IFF-421-AV Teaching wall hook ups
263
IFF-421-Lower Counter Top
2d
6/9/2026
6/10/2026
IFF-421-Lower Counter Top
264
IFF-421-Final Clean
1d
6/11/2026
6/11/2026
IFF-421-Final Clean
11d
5/26/2026
6/9/2026
Room 422- Science Classroom Improvements 265
IFF-422-Lower Counter Top
2d
5/26/2026
5/27/2026
IFF-422-Lower Counter Top
266
IFF-422-Swap out Lights
3d
5/27/2026
5/29/2026
IFF-422-Swap out Lights
267
IFF-422-Electrical rough in for Teaching Wall
3d
6/1/2026
6/3/2026
IFF-422-Electrical rough in for Teaching Wall
268
IFF-422-AV Teaching wall hook ups
3d
6/4/2026
6/8/2026
IFF-422-AV Teaching wall hook ups
269
IFF-422-Final Clean
1d
6/9/2026
6/9/2026
IFF-422-Final Clean
7d
6/1/2026
6/9/2026
Room 424- Science Classroom Improvements 270
IFF-424-Electrical rough in for Teaching Wall
3d
6/1/2026
6/3/2026
IFF-424-Electrical rough in for Teaching Wall
271
IFF-424-AV Teaching wall hook ups
3d
6/4/2026
6/8/2026
IFF-424-AV Teaching wall hook ups
272
IFF-424-Final Clean
1d
6/9/2026
6/9/2026
IFF-424-Final Clean
9d
6/1/2026
6/11/2026
Room 430- Science Classroom Improvements 273
IFF-430-Swap out Lights
2d
6/1/2026
6/2/2026
IFF-430-Swap out Lights
274
IFF-430-Electrical rough in for Teaching Wall
3d
6/3/2026
6/5/2026
IFF-430-Electrical rough in for Teaching Wall
275
IFF-430-AV Teaching wall hook ups
3d
6/8/2026
6/10/2026
IFF-430-AV Teaching wall hook ups
276
IFF-430-Final Clean
1d
6/11/2026
6/11/2026
IFF-430-Final Clean
9d
6/1/2026
6/11/2026
Room 432- Science Classroom Improvements 277
IFF-432-Swap out Lights
2d
6/1/2026
6/2/2026
IFF-432-Swap out Lights
278
IFF-432-Electrical rough in for Teaching Wall
3d
6/3/2026
6/5/2026
IFF-432-Electrical rough in for Teaching Wall
279
IFF-432-AV Teaching wall hook ups
3d
6/8/2026
6/10/2026
IFF-432-AV Teaching wall hook ups
280
IFF-432-Final Clean
1d
6/11/2026
6/11/2026
IFF-432-Final Clean
7d
6/3/2026
6/11/2026
Room 425- Science Classroom Improvements 281
IFF-435-Electrical rough in for Teaching Wall
3d
6/3/2026
6/5/2026
IFF-435-Electrical rough in for Teaching Wall
282
IFF-435-AV Teaching wall hook ups
3d
6/8/2026
6/10/2026
IFF-435-AV Teaching wall hook ups
283
IFF-435-Final Clean
1d
6/11/2026
6/11/2026
IFF-435-Final Clean
7d
6/3/2026
6/11/2026
Room 426- Science Classroom Improvements 284
IFF-426-Electrical rough in for Teaching Wall
3d
6/3/2026
6/5/2026
IFF-426-Electrical rough in for Teaching Wall
285
IFF-426-AV Teaching wall hook ups
3d
6/8/2026
6/10/2026
IFF-426-AV Teaching wall hook ups
286
IFF-426-Final Clean
1d
6/11/2026
6/11/2026
IFF-426-Final Clean
11d
6/3/2026
6/17/2026
Room 402- Science Classroom Improvements 287
IFF-402-Swap out Lights
2d
6/3/2026
6/4/2026
IFF-402-Swap out Lights
288
IFF-402-Electrical rough in for Teaching Wall
3d
6/5/2026
6/9/2026
IFF-402-Electrical rough in for Teaching Wall
289
IFF-402-AV Teaching wall hook ups
3d
6/10/2026
6/12/2026
IFF-402-AV Teaching wall hook ups
290
IFF-402-Lower Counter Top
2d
6/15/2026
6/16/2026
IFF-402-Lower Counter Top
291
IFF-402-Final Clean
1d
6/17/2026
6/17/2026
IFF-402-Final Clean
11d
6/3/2026
6/17/2026
Room 405- Science Classroom Improvements
Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School
Job #: Fairview High School
Rev. date: 10/17/2025 12:41:16 PM
Data Date: 10/17/2025
Page 9 of 13
A 9
S 6
2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12
3. Print View Filter: No Summary Tasks
J 10
A 7
S 4
Line
Name
Duration
APC
Start
Finish
A 12
S 9
2024 O N 7 4
D 2
2025 J F M A M J J 30 27 24 24 21 19 16 14
A 11
S 8
O 6
2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13
A 10
S 7
O 5
N 2
2027 D J F M A M J J 30 28 25 22 22 19 17 14 12
292
IFF-405-Swap out Lights
2d
6/3/2026
6/4/2026
IFF-405-Swap out Lights
293
IFF-405-Electrical rough in for Teaching Wall
3d
6/5/2026
6/9/2026
IFF-405-Electrical rough in for Teaching Wall
294
IFF-405-AV Teaching wall hook ups
3d
6/10/2026
6/12/2026
IFF-405-AV Teaching wall hook ups
295
IFF-405-Lower Counter Top
2d
6/15/2026
6/16/2026
IFF-405-Lower Counter Top
296
IFF-405-Final Clean
1d
6/17/2026
6/17/2026
IFF-405-Final Clean
9d
6/5/2026
6/17/2026
Room 411- Science Classroom Improvements 297
IFF-411-Swap out Lights
2d
6/5/2026
6/8/2026
IFF-411-Swap out Lights
298
IFF-411-Electrical rough in for Teaching Wall
3d
6/9/2026
6/11/2026
IFF-411-Electrical rough in for Teaching Wall
299
IFF-411-AV Teaching wall hook ups
3d
6/12/2026
6/16/2026
IFF-411-AV Teaching wall hook ups
300
IFF-411-Final Clean
1d
6/17/2026
6/17/2026
IFF-411-Final Clean
Library Improvements
19d
5/26/2026
6/19/2026
301
IFF-LI-Owner Move Furnature
8d
5/26/2026
6/4/2026
IFF-LI-Owner Move Furnature
302
IFF-LI-Clean Demo Existing Carpet
5d
6/5/2026
6/11/2026
IFF-LI-Clean Demo Existing Carpet
303
IFF-LI-Install New Carpet
5d
6/12/2026
6/18/2026
IFF-LI-Install New Carpet
304
IFF-LI- Final Clean
1d
6/19/2026
6/19/2026
IFF-LI- Final Clean
37d
5/26/2026
7/16/2026
900 Level - Senior Lounge Improvements
37d
5/26/2026
7/16/2026
305
RTU Replacement - Commons 1001 & 1002 IFF-MU-Owner Move
1d
5/26/2026
5/26/2026
IFF-MU-Owner Move
306
IFF-MU-MEP Safeoff RTU's
2d
5/27/2026
5/28/2026
IFF-MU-MEP Safeoff RTU's
307
IFF-MU-Install Scaffolding
3d
5/27/2026
5/29/2026
IFF-MU-Install Scaffolding
308
IFF-MU-Demo Ceilings Below RTU's
3d
6/1/2026
6/3/2026
IFF-MU-Demo Ceilings Below RTU's
309
IFF-MU-Demo Existing Duct and Move MEP
3d
6/4/2026
6/8/2026
IFF-MU-Demo Existing Duct and Move MEP
310
IFF-MU-Demo Old RTU's & ACCU's
1d
6/9/2026
6/9/2026
IFF-MU-Demo Old RTU's & ACCU's
311
IFF-MU-Install Supporting Steel
5d
6/10/2026
6/16/2026
IFF-MU-Install Supporting Steel
312
IFF-MU-Set New RTU's
1d
6/17/2026
6/17/2026
IFF-MU-Set New RTU's
313
IFF-MU-Set New ACCU
1d
6/18/2026
6/18/2026
IFF-MU-Set New ACCU
314
IFF-MU-MEP connections to new Units
4d
6/19/2026
6/24/2026
IFF-MU-MEP connections to new Units
315
IFF-MU-Install New Duct Below Unit
8d
6/25/2026
7/7/2026
IFF-MU-Install New Duct Below Unit
316
IFF-MU-Install Ceiling Grid
2d
7/8/2026
7/9/2026
IFF-MU-Install Ceiling Grid
317
IFF-MU-MEP Device Ceiling
2d
7/10/2026
7/13/2026
IFF-MU-MEP Device Ceiling
318
IFF-MU-White Out Ceiling
2d
7/14/2026
7/15/2026
IFF-MU-White Out Ceiling
319
IFF-MU-Final Clean
1d
7/16/2026
7/16/2026
IFF-MU-Final Clean
69d
3/23/2026
6/26/2026
Gymnasium Improvements
69d
3/23/2026
6/26/2026
320
Gymnasium Improvements - RTU 901 IFF-GYM-Install New Gas Line
5d
3/23/2026
3/27/2026
IFF-GYM-Install New Gas Line
321
IFF-GYM-Grade and Prep for RTU Pad
5d
3/30/2026
4/3/2026
IFF-GYM-Grade and Prep for RTU Pad
322
IFF-GYM-F/R/P Footers for RTU
4d
4/6/2026
4/9/2026
IFF-GYM-F/R/P Footers for RTU
323
IFF-GYM-Lay Block to 100
4d
4/10/2026
4/15/2026
IFF-GYM-Lay Block to 100
324
IFF-GYM-F/R/P Pad
2d
4/16/2026
4/17/2026
IFF-GYM-F/R/P Pad
325
IFF-GYM-Build Masonry Enclosure
6d
4/20/2026
4/27/2026
IFF-GYM-Build Masonry Enclosure
326
IFF-GYM-Set Gym RTU 901
1d
5/8/2026
5/8/2026
IFF-GYM-Set Gym RTU 901
Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School
Job #: Fairview High School
Rev. date: 10/17/2025 12:41:16 PM
Data Date: 10/17/2025
Page 10 of 13
A 9
S 6
2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12
3. Print View Filter: No Summary Tasks
J 10
A 7
S 4
Line
Name
Duration
APC
Start
Finish
A 12
S 9
2024 O N 7 4
D 2
2025 J F M A M J J 30 27 24 24 21 19 16 14
A 11
S 8
O 6
2026 N D J F M A M J J 3 1 29 26 23 23 20 18 15 13
A 10
S 7
O 5
N 2
2027 D J F M A M J J 30 28 25 22 22 19 17 14 12
327
IFF-GYM- Electrical & Control Connections to RTU 901
8d
5/11/2026
5/20/2026
IFF-GYM- Electrical & Control Connections to RTU 901
328
IFF-GYM-Demo Existing MEP
2d
5/21/2026
5/22/2026
IFF-GYM-Demo Existing MEP
329
IFF-GYM-Install Flooring Protection
3d
5/26/2026
5/28/2026
IFF-GYM-Install Flooring Protection
330
IFF-GYM- Demo Old RTUs & Structure
5d
5/26/2026
6/1/2026
IFF-GYM- Demo Old RTUs & Structure
331
IFF-GYM- Cut & Reinforce for Duct Penetrations
6d
5/29/2026
6/5/2026
IFF-GYM- Cut & Reinforce for Duct Penetrations
332
IFF-GYM-Install New Duct for 901
7d
6/8/2026
6/16/2026
IFF-GYM-Install New Duct for 901
333
IFF-GYM-Install Removed MEP
3d
6/17/2026
6/19/2026
IFF-GYM-Install Removed MEP
334
IFF-GYM-Remove Floor Protection
3d
6/22/2026
6/24/2026
IFF-GYM-Remove Floor Protection
335
IFF-GYM-Final Clean
2d
6/25/2026
6/26/2026
IFF-GYM-Final Clean
84d
3/23/2026
7/20/2026
Electrical Upgrades
13d
5/27/2026
6/12/2026
336
Electrical Upgrades - BRA IFF-EU-Shut Down and Safeoff MDC
2d
5/27/2026
5/28/2026
IFF-EU-Shut Down and Safeoff MDC
337
IFF-EU-Demo BRA
2d
5/29/2026
6/1/2026
IFF-EU-Demo BRA
338
IFF-EU-Install New BRA
5d
6/2/2026
6/8/2026
IFF-EU-Install New BRA
339
IFF-EU-Test and Inspect
3d
6/9/2026
6/11/2026
IFF-EU-Test and Inspect
340
IFF-EU-Energize MDC
1d
6/12/2026
6/12/2026
IFF-EU-Energize MDC
Fire Alarm Upgrades
46d
4/29/2026
7/2/2026
341
IFF-FAU-Early Fire Alarm Wire Pull (Spring Break Start Night Work)
20d
4/29/2026
5/27/2026
IFF-FAU-Early Fire Alarm Wire Pull (Spring Break Start Night Work)
342
IFF-FAU-EM Battery Pack Replacements (Night Work)
10d
5/13/2026
5/27/2026
IFF-FAU-EM Battery Pack Replacements (Night Work)
343
IFF-FAU-Install New Devices
5d
5/28/2026
6/3/2026
IFF-FAU-Install New Devices
344
IFF-FAU-Demo Old Panel
5d
5/28/2026
6/3/2026
IFF-FAU-Demo Old Panel
345
IFF-FAU-Install New Panel and Terminate
10d
6/4/2026
6/17/2026
IFF-FAU-Install New Panel and Terminate
346
IFF-FAU-Program Panel
5d
6/18/2026
6/24/2026
IFF-FAU-Program Panel
347
IFF-FAU-Test Fire Alarm Panel
6d
6/25/2026
7/2/2026
PA Sound System Upgrades
84d
3/23/2026
7/20/2026
IFF-EU-Pull new Wire for Speakers (Spring Break Start Night work)
10d
3/23/2026
4/3/2026
349
IFF-EU-Install New Speakers
1d
5/26/2026
5/26/2026
IFF-EU-Install New Speakers
350
IFF-EU-Install New Head End
2d
5/27/2026
5/28/2026
IFF-EU-Install New Head End
351
IFF-EU-Test New Head End and Speakers
6d
5/29/2026
6/5/2026
352
IFF-EU-Final Clean
30d
6/8/2026
7/20/2026
Mechanical Upgrades
22d
5/26/2026
6/24/2026
2028 O N D J F M A M J 4 1 29 27 24 21 20 17 15 12
IFF-EU-Pull new Wire for Speakers (Spring Break Start Night work)
IFF-EU-Test New Head End and Speakers
IFF-EU-Final Clean
22d
5/26/2026
6/24/2026
353
IFF-WHR-MEP Safeoff Water Heaters
2d
5/26/2026
5/27/2026
IFF-WHR-MEP Safeoff Water Heaters
354
IFF-WHR-Demo Existing Water Heaters
5d
5/28/2026
6/3/2026
IFF-WHR-Demo Existing Water Heaters
355
IFF-WHR-Install New Water Heaters and Associated Piping
2d
6/4/2026
6/5/2026
IFF-WHR-Install New Water Heaters and Associated Piping
356
IFF-WHR-Hook up Electrical
6d
6/8/2026
6/15/2026
IFF-WHR-Hook up Electrical
357
IFF-WHR-Hook up Controls
2d
6/16/2026
6/17/2026
IFF-WHR-Hook up Controls
358
IFF-WHR- Test Controls
5d
6/18/2026
6/24/2026
IFF-WHR- Test Controls
Exterior Facaad Improvements
42d
5/26/2026
7/23/2026
800 Level - Exterior Windows
42d
5/26/2026
7/23/2026
Boulder Valley RFP 25-04 CMGC Project Scope #1 Fairview High School
S 6
IFF-FAU-Test Fire Alarm Panel
348
Water Heater Replacement
A 9
Job #: Fairview High School
Rev. date: 10/17/2025 12:41:16 PM
Data Date: 10/17/2025
Page 11 of 13
3. Print View Filter: No Summary Tasks
J 10
A 7
S 4
Line
Name
Duration
APC
Start
Finish
A 12
S 9
2024 O N 7 4
D 2
2025 J F M A M J J 30 27 24 24 21 19 16 14
A 11
S 8
O 6