BVSD Board of Education · Document
Exhibits BVSD Southern Hills MS Amendment Package No. 2.pdf (3,301 KB)
Regular Meeting, November 18, 2025 · item 8.12: Amendment to the contract for Southern Hills Middle School · 119 pages
This is the text extracted from the file, without its layout, tables, or images. Use the original for anything that matters.
Exhibit A Drawings, specifications and documents used to prepare the GMP
First Amendment to CM/GC Agreement With Turner Construction Company, dated April 25, 2017
Printed on Mon Nov 3, 2025 at 10:22 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction
Current Drawings Drawing No.
Drawing Title
Revision
Drawing Date
Received Date
Set
Cover Sheet COVER SHEET
0
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
G-001
CODE COMPLIANCE - CODE DATA AND
1
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
G-002
CODE COMPLIANCE - LEVEL 2
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
G-003
SYSTEM ASSEMBLIES FLOORS, WALLS, CEILINGS, ROOFS
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
C0.1
LEGEND NOTES & ABBREVIATIONS
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
C0.2
DEMOLITION PLAN
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
C1.0
GRADING AND EROSION CONTROL PLAN
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
C3.0
HORIZONTAL CONTROL PLAN
3
10/01/2025
2025.10.01 - CD Addendum #2 (10/ 01/25)
CD3.0
HORIZONTAL CONTROL DETAILS
3
09/25/2025
2025.09.25 - CD Addendum #1 (09/ 25/25)
CE1.1
EROSION CONTROL DETAILS
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
CE1.2
EROSION CONTROL DETAILS
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
S-001
GENERAL NOTES
1
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
S-101
PARTIAL FLOOR PLANS AND DETAILS
2
10/01/2025
A-101
LEVEL 1 OVERALL FLOOR PLAN
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
A-102
LEVEL 2 OVERALL FLOOR PLAN
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
A-111
LEVEL 1 OVERALL REFLECTED CEILING PLAN
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
A-112
LEVEL 2 OVERALL REFLECTED CEILING PLAN
4
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
CS-001 General
Civil
Structural
2025.10.01 - CD Addendum #2 (10/ 01/25)
Architectural
Page 1 of 6
Printed on Mon Nov 3, 2025 at 10:22 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction
Drawing No.
Drawing Title
Revision
Drawing Date
Received Date
Set
A-121
OVERALL ROOF PLAN
0
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
A-400
TYPICAL MOUNTING
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
A-401
CAFETERIA LARGE SCALE TOILET PLANS ANS RCPS
3
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
A-402
LOWER LEVEL LARGE SCALE TOILETS PLANS AND RCPS
4
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
A-403
LARGE SCALE FLOOR PLANS - CAFETERIA FLOOR PATTERN
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
A-415
WOOD SHOP FLOOR PLAN AND RCP
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
A-416
ART ROOM FLOOR PLAN AND RCP
3
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
A-417
FOOD LAB PLAN AND RCP
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
A-451
INTERIOR ELEVATIONS
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
A-601
DOOR AND FRAME SCHEDULE, FRAME and WINDOW TYPES
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
A-700
ROOM FINISH SCHEDULE & INTERIOR DETAILS
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
A-701
LEVEL 1 - OVERALL ROOM FINISH PLAN
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
A-702
LEVEL 2 - OVERALL ROOM FINISH PLAN
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
AD-101
LEVEL 1 OVERALL DEMOLITION FLOOR PLAN
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
AD-102
LEVEL 2 OVERALL DEMOLITION FLOOR PLAN
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
AD-111
LEVEL 1 OVERALL DEMOLITION RCP
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
AD-415
WOOD SHOP DEMOLITION PLAN AND RCP
3
09/25/2025
AD-416
ART ROOM DEMOLITION PLAN AND RCP
3
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
AD-417
FOOD LAB DEMOLITION PLAN AND RCP
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
FP-001
FIRE PROTECTION GENERAL INFORMATION
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
FP-200
PARTIAL BASEMENT FIRE PROTECTION PLAN
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
FP-201C
FIRE PROTECTION PLAN – AREA C
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
2025.09.25 - CD Addendum #1 (09/ 25/25)
Fire Protection
Page 2 of 6
Printed on Mon Nov 3, 2025 at 10:22 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction
Drawing No.
Drawing Title
Revision
Drawing Date
Received Date
Set
Plumbing P-001
PLUMBING GENERAL INFORMATION
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
P-002
PLUMBING SCHEDULES
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
P-201
LEVEL 1 PLUMBING PLAN
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
P-401
ENLARGED PLUMBING PLANS
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
P-402
ENLARGED PLUMBING PLANS
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
P-601
PLUMBING DETAILS
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
M-001
MECHANICAL
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
M-002
MECHANICAL SCHEDULES
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
M-201
LEVEL 1 OVERALL MECHANICAL PLAN
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
M-202
LEVEL 2 OVERALL MECHANICAL
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
M-203
ROOF LEVEL OVERALL MECHANICAL PLAN
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
M-401
ENLARGED CAFETERIA RESTROOMS MECHANICAL
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
M-402
ENLARGED APPLIED TECH MECHANICAL
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
M-403
1 LEVEL 1 ENLARGED ART ROOM MECHANICAL PLAN
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
M-404
ENLARGED FOOD LAB MECHANICAL PLAN
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
M-601
DUCTWORK AS NOTED ON PLANS PROVIDE ROOF JACK
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
E-001
ELECTRICAL GENERAL INFORMATION
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
E-002
ELECTRICAL PROJECT NOTES
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
E-003
ELECTRICAL SCHEDULES
3
09/25/2025
E-004
ELECTRICAL COMCHECK
0
09/12/2025
E-200
PARTIAL BASEMENT ELECTRICAL PLANS
4
10/01/2025
Mechanical
Electrical
Page 3 of 6
2025.09.25 - CD Addendum #1 (09/ 25/25) 09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25) 2025.10.01 - CD Addendum #2 (10/
Printed on Mon Nov 3, 2025 at 10:22 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction
Drawing No.
Drawing Title
Revision
Drawing Date
Received Date
Set 01/25)
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
E-201
LEVEL 1 OVERALL ELECTRICAL PLAN
3
09/12/2025
E-202
LEVEL 2 OVERALL ELECTRICAL PLAN
3
10/01/2025
2025.10.01 - CD Addendum #2 (10/ 01/25)
E-203
ROOF LEVEL OVERALL ELECTRICAL PLAN
3
09/25/2025
2025.09.25 - CD Addendum #1 (09/ 25/25)
E-301
LEVEL 1 OVERALL LIGHTING PLAN
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
E-401
ENLARGED CAFETERIA RESTROOMS POWER PLANS
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
E-402
ENLARGED APPLIED TECH POWER PLANS
3
09/25/2025
E-403
ENLARGED ART ROOM POWER PLANS
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
E-404
ENLARGED FOOD LAB POWER PLANS
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
E-405
ENLARGED CAFETERIA RESTROOMS LIGHTING PLANS
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
E-406
ENLARGED APPLIED TECH APPLIED LIGHTING PLANS
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
E-407
ENLARGED ART ROOM LIGHTING PLANS
1
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
E-408
4 ENLARGED GENDER NEUTRAL RESTROOM AND LAUNDRY LIGHTING PLAN
1
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
E-501
ELECTRICAL DEMO ONE-LINE DIAGRAM
3
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
E-502
ELECTRICAL NEW ONE-LINE DIAGRAM
4
09/25/2025
2025.09.25 - CD Addendum #1 (09/ 25/25)
E-503
PANEL SCHEDULES
2
09/25/2025
2025.09.25 - CD Addendum #1 (09/ 25/25)
E-504
PANEL SCHEDULES
2
10/01/2025
2025.10.01 - CD Addendum #2 (10/ 01/25)
ED-201
LEVEL 1 OVERALL POWER DEMOLITION PLAN
3
10/01/2025
2025.10.01 - CD Addendum #2 (10/ 01/25)
ED-202
LEVEL 2 OVERALL POWER DEMOLITION PLAN
3
10/01/2025
2025.10.01 - CD Addendum #2 (10/ 01/25)
ED-301
LEVEL 1 OVERALL LIGHTING DEMOLITION PLAN
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
T-001
COMMUNICATIONS TITLE SHEET
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
T-002
COMMUNICATIONS PROJECT NOTES
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
2025.09.25 - CD Addendum #1 (09/ 25/25)
Telecommunications
Page 4 of 6
Printed on Mon Nov 3, 2025 at 10:22 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction
Drawing No.
Drawing Title
Revision
Drawing Date
Received Date
Set
T-003
COMMUNICATIONS SCHEDULES
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
T-200
PARTIAL
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
T-201B
LEVEL 1 COMMUNICATIONS
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
T-201C
LEVEL 1 COMMUNICATIONS PLAN-AREA C
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
T-201D
LEVEL 1 COMMUNICATIONS PLAN-AREA D
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
T-201E
LEVEL 1 COMMUNICATIONS PLAN-AREA E
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
T-202A
LEVEL 2 COMMUNICATIONS PLAN-AREA A
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
T-202B
LEVEL 2 COMMUNICATIONS PLAN- AREA B
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
T-202C
LEVEL 2 COMMUNICATIONS PLAN-AREA C
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
T-503
AUDIOVISUAL SYSTEM PLAN
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
T-601
COMMUNICATIONS DETAILS
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
FA-001
FIRE ALARM
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
FA-200
PARTIAL BASEMENT FIRE ALARM PLAN
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
FA-201B
LEVLE 1 FIRE ALARM PLAN - AREA B
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
FA-201C
LEVEL 1 FIRE ALARM PLAN - AREA C
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
FA-201D
LEVEL 1 FIRE ALARM PLAN - AREA D
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
FA-201E
LEVEL 1 FIRE ALARM PLAN - AREA E
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
FA-202A
LEVEL 2 FIRE ALARM PLAN - AREA A
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
FA-202B
LEVEL 2 FIRE ALARM PLAN - AREA B
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
FA-202C
LEVEL 2 FIRE ALARM PLAN - AREA C
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
FA-202E
LEVEL 2 FIRE ALARM PLAN - AREA E
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
FAD-200
PARTIAL BASEMENT FIRE ALARM DEMOLITION PLAN
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
Fire Alarm
Page 5 of 6
Printed on Mon Nov 3, 2025 at 10:22 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction
Drawing No.
Drawing Title
Revision
Drawing Date
Received Date
Set
FAD-201B
LEVEL 1 FIRE ALARM DEMOLITION PLAN - AREA B
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
FAD-201C
LEVEL 1 FIRE ALARM DEMOLITION PLAN - AREA C
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
FAD-201D
LEVEL 1 FIRE ALARM DEMOLITION PLAN - AREA D
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
FAD-201E
LEVEL 1 FIRE ALARM DEMOLITION PLAN-AREA E
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
FAD-202A
LEVEL 2 FIRE ALARM DEMOLITION PLAN-AREA A
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
FAD-202B
LEVEL 2 FIRE ALARM DEMOLITION PLAN - AREA B
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
FAD-202C
LEVEL 2 FIRE ALARM DEMOLITION PLAN - AREA C
2
09/12/2025
09/12/2025
2025.09.12 - 100% CD Set (09/12/ 25)
Page 6 of 6
Printed on Mon Nov 3, 2025 at 10:25 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction
Current Specifications Number
Description
Revision
Issued Date
Received Date
Set
00 - Procurement and Contracting Requirements 00 1000
Performance Bond MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
00 1100
Labor and Material Payment Bond MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
00 1300
Asbestos Management Plan Contractor Responsibility MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
00 1400
Lead Based Paint Contractor Responsibility MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
000107
Seals Page BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
000110
Table of Contents
1
09/12/25
09/12/25
2025.09.12 - 100% CD's
003100
AHERA Report MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
006000
Project Forms MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
006001
RFI Form MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
006002
Substitution Request Form MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
006003
Proposal Request Form MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
006004
ASI Form MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
006005
Construction Change Directive Form MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
01 - General Requirements 011000
Summary MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
012000
Price and Payment Procedures
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
012100
Allowances MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
012300
Alternates MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
012500
Substitution Procedures MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
013000
Administrative Requirements MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
013216
Construction Progress Schedule MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
014000
Quality Requirements MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
014216
Definitions and Explanations MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
015000
Temporary Facilities and Controls MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
016000
Product Requirements MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
016116
Volatile Organic Compound (VOC) Content Restrictions MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
017000
Execution and Closeout Requirements MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
017419
Construction Waste Management and Disposal MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
017610
Temporary Protective Coverings MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
017800
Closeout Submittals MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
017900
Demonstration and Training MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
02 - Existing Conditions
Page 1 of 5
Printed on Mon Nov 3, 2025 at 10:25 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction
Number 02 41 00
Description
Revision
Issued Date
Received Date
Set
Demolition JVA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
030100
Maintenance of Concrete MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
030516
Underslab Vapor Barrier MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
033511
Concrete Floor Finishes MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
03 - Concrete
06 - Wood, Plastics, and Composites 061000
Rough Carpentry MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
066100
Cast Polymer Fabrications MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
068316
Fiberglass Reinforced Paneling MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
07 - Thermal and Moisture Protection 070553
Fire and Smoke Assembly Identification MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
072119
Foamed-In-Place Insulation MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
078400
Firestopping MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
079200
Joint Sealants MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
08 7100
Door Hardware ALLEGION
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
081113
Hollow Metal Doors and Frames MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
081416
Flush Wood Doors MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
083100
Access Doors and Panels MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
084313
Aluminum-Framed Storefronts MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
088000
Glazing MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
090561
Common Work Results for Flooring Preparation MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
092116
Gypsum Board Assemblies MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
093000
Tiling MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
096500
Resilient Flooring and Base MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
096813
Tile Carpeting MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
097200
Wall Coverings MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
099123
Interior Painting MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
099600
High-Performance Coatings MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
101100
Visual Display Units MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
101423
Panel Signage MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
102113
Toilet Compartments
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
102600
Wall and Door Protection MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
102800
Toilet, Bath, and Laundry Accessories MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
104400
Fire Protection Specialties MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
08 - Openings
09 - Finishes
10 - Specialties
Page 2 of 5
Printed on Mon Nov 3, 2025 at 10:25 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction
Number 105113
Description
Revision
Issued Date
Received Date
Set
Metal Lockers MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
113013
Residential Appliances MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
119900
Miscellaneous Equipment MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
122400
Window Shades MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
123200
Manufactured Wood Casework MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
123600
Countertops MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
124813
Entrance Floor Mats and Frames MOA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
Fire Protection BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
22 0000
Basic Plumbing Requirements BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
22 0500
Common Work Results for Plumbing BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
22 0523
General-Duty Valves for Plumbing Piping BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
22 0529
Hangers and Supports for Plumbing Piping and Equipment BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
22 0553
Identification for Plumbing Piping and Equipment BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
22 0700
Plumbing Insulation BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
22 1116
Domestic Water Piping BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
22 1119
Domestic Water Piping Specialties BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
22 1316
Sanitary Waste and Vent Piping BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
22 1319
Sanitary Waste Piping Specialties BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
22 1329
Sanitary Ejector Pumps BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
22 4000
Plumbing Fixtures BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
11 - Equipment
12 - Furnishings
21 - Fire Suppression 21 0500 22 - Plumbing
23 - Heating, Ventilating, and Air Conditioning (HVAC) 23 0000
Basic Mechanical Requirements BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
23 0100
M&E Coordination BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
23 0500
Common Work Results for HVAC BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
23 0529
Supports and Anchors BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
23 0553
Mechanical Identification BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
23 0593
Testing, Adjusting, and Balancing BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
23 0700
Mechanical Insulation BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
23 0800
Commissioning of HVAC BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
23 0900
Direct Digital Control Systems BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
23 0902
Integrated Automation Control Sequence BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
23 3113
Metal Ductwork BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
23 3300
Ductwork Accessories BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
Page 3 of 5
Printed on Mon Nov 3, 2025 at 10:25 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction
Number
Description
Revision
Issued Date
Received Date
Set
23 3413
Air Handling Fans BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
23 3713
Air Outlets and Inlets BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
26 0500
Basic Electrical Requirements BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
26 0510
Electrical Remodeling Provisions BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
26 0519
Building Wire and Cable BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
26 0526
Grounding and Bonding BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
26 0529
Supporting Devices and Seals BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
26 0532
Conduit BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
26 0534
Electrical Boxes and Fittings BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
26 0553
Electrical Identification BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
26 0580
Equipment Wiring Systems BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
26 0800
Commissioning of Electrical BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
26 0923
Lighting Control Devices BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
26 2416
Panelboards BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
26 2726
Wiring Devices BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
26 2816
Enclosed Switches BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
26 5100
Interior Lighting BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
26 7400
Electrical for Communications Systems BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
26 - Electrical
27 - Communications 27 0010
Basic Communications Requirements BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
27 0020
Contractor Qualifications BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
27 0030
Bidding BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
27 0040
Warranty BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
27 0050
Quality Assurance BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
27 0060
Training BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
27 0405
Common Work - Sleeves, Penetrations, and Firestopping BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
27 0406
Common Work - Hangers and Supports BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
27 0500
Electrical Technology - General Requirements BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
27 0533
Electrical Technology - Conduit and Boxes BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
27 1000
Communications - General Requirements BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
27 1119
Communications - Termination Equipment BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
27 1500
Communications - Horizontal Cabling BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
27 1543
Communications - Faceplates and Connectors BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
27 1619
Communications - Patch Cords BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
27 1710
Communications - Identification BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
27 1720
Communications - Testing BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
Page 4 of 5
Printed on Mon Nov 3, 2025 at 10:25 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction
Number
Description
Revision
Issued Date
Received Date
Set
27 4000
AudioVisual - General Requirements BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
27 5000
Public Address General Requirements BCER
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
31 00 00
Earthwork JVA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
31 25 00
Erosion and Sedimentation Controls JVA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
31 - Earthwork
32 - Exterior Improvements 32 12 00
Flexible Paving JVA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
32 13 00
Rigid Paving JVA
0
09/12/25
09/12/25
2025.09.12 - 100% CD's
Page 5 of 5
Exhibit B Assumptions and clarifications made in preparing the GMP Clarifications in preparing the amendment
Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20
K1224 - BVSD - SOUTHERN HILLS MIDDLE SCHOOL 1500 Knox Dr., Boulder, CO, 80305 Estimate: CD Estimate Rev. 1
PREPARED FOR:
ARCHITECT / DESIGNER:
BVSD
MOA Architecture
DATE PRINTED: 10/29/2025
Page 1 of 20
Clarifications Report General Clarifications - Any deviation from the prime contract terms may result in different costs and pricing. - Any delays or cost impacts due to pandemics have not been included in the estimate. - Prevailing wages have not been included. - Any unknown existing conditions needing rework to meet code requirements for inspection not shown in the drawings, has not been included. - An escalation allowance is not included. - This is an estimate for the cost of construction, no land fees, architectural fees, legal fees, land development fees, tap fees, etc. have been included. - Sales tax has not been included. - A&P excludes any delegated design that is not listed in the plans or specifications.
Items by Others - All independent testing and inspections, including commissioning - Televisions - Residential Equipment (AP included range listed on the plan set) - Land Costs, Legal Fees, or Tap Fees - Architectural and Engineering Fees - Technology – Servers, computers, phones, etc. - Owner contingency - All fees associated with utilities will be paid for by the owner (water, electric, gas) - Any expenses associated with dry utilities and getting them to the site (cable, fiber, power and gas) - Removal or working with hazardous materials, including asbestos and lead abatement as defined by OSHA. - All moving costs - All artwork - purchasing, moving, and installation - Technology - Computers, Servers, phones, etc. – purchasing, moving and installation - Furniture, Desks, chairs, tables, moveable casework – purchasing, moving and installation - Audio / Visual Projectors, Projection Screens, Smart Boards (that are not specifically called out in the plans)
Documents - Drawings dated 09/12/2025 - Specifications dated 09/12/2025 - Addenda 1 dated 09/25/2025 - Addenda 2 dated 10/01/2025
B Shell - For additional scope item 'Access Fixed Ladders - Exterior Renewal', it was determined at the facilities page turn that BVSD doesn't know where these are located and to plug in the VFA allowance.
DATE PRINTED: 11/4/2025
Page 2 of 20
D Services - Dust Collectors are included as owner furnished owner installed (OFOI) per BVSD's request. - Fire alarm replacement product was included as Mircom. Bronco has included extra devices past the plans to create a complete system. - Garbage disposals are not included. - Per BVSD and drawings, no additional raceways for security cameras have been included.
E Equipment and Furnishings - We have included new trim at the wood partition between the pottery and art rooms as this will provide a better look and is more cost effective.
F Special Construction and Demolition - It is assumed that the ACM shown on the exterior wall is only a coating and AP's demo sub will be able to demo the wall after the coating has been abated.
- It is assumed that the equipment to be salvaged is attached to ACM containing material and is not included in the demo scope.
G Site Preparation - For additional scope item 'Exterior Wall - Damaged Concrete', it was determined at the facilities page turn that BVSD doesn't know where these are located and to plug in the VFA allowance.
Z General Requirements - A site security guard has not been included. - General protection of adjacent surfaces is included for the work shown in the plans.
DATE PRINTED: 11/4/2025
Page 3 of 20
Exhibit C
Itemization ofGMP Cost Itemization of the Dollars requested for long lead equipment and material packages
Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20
797 Ventura Street, Aurora, CO 80011 Project: K1224 - BVSD - Southern Hills Middle School Owner: BVSD Architect: MOA Architecture
Date: Estimator: Project SF: Duration in Months: Estimate #:
10/30/25 Karra Damiana 105,580 7.00 CD Estimate Rev. 1 Includes Alternates 3 (Additional Electrical Panels), 4 (Intercom), 16 (Exterior Plaza Upgrade)
Project Summary Sheet - Estimated Cost of the Work Division #0
Procurement and Contracting Requirements
Division #1 Division #2 Division #3 Division #4
General Requirements Existing Conditions Concrete Masonry
Division #5 Division #6 Division #7
Metals Wood, Plastics, and Composites Thermal and Moisture Protection
Division #8
Openings
Division #9 Division #10 Division #11
Finishes Specialties Equipment
Division #12 Division #13 Division #14 Division #21 Division #22 Division #23 Division #25
Furnishings Special Construction Conveying Equipment Fire Suppression Plumbing Heating, Ventilating and Air Conditioning Integrated Automation
Division #26
Electrical
Division #27
Division #28
Division #31
Division #32 Division #33
DD Estimate CD Estimate $37,140 $37,140 $162,194 $134,445
Difference $0 ($27,749)
$45,869 $14,283 $16,000 $43,116
$69,093 $20,372 $0 $19,612
$23,224 $6,089 ($16,000) ($23,504)
$51,725 $13,723 $27,967
$67,482 $20,485 $14,232
$15,757 $6,762 ($13,735)
$175,877
$236,678
$60,801
$65,575 $1,800 $4,045
$11,287 $1,841 $2,520
($54,288) $41 ($1,525)
$0 $0 $0 $255,780 $217,467 $0 $542,692
$0 $0 $10,007 $0 $428,405 $0 $562,988
$0 $0 $10,007 ($255,780) $210,938 $0 $20,296
$209,254
$204,516
($4,738)
$620,034
$432,934
($187,100)
Communications
$79,627
$77,107
($2,520)
$115,112
$130,360
$15,248
$0
$0
$0
$2,699,280
$2,481,504
($217,776)
By Owner By Owner By Owner $97,712 $97,712 $81,427 $6,406 $37,456 Not Included $22,800 $97,712 $97,712 $5,076
By Owner By Owner By Owner $0 $0 $74,445 $2,996 $29,958 Not Included $18,519 $0 $110,928 $5,076
$3,243,293
$2,723,426
Earthwork
Utility Tap & Devel. Fees Permit Allowance Use Tax Design Contingency Estimate Contingency Construction Contingency Builders Risk Insurance Comprehensive General Liability Insurance Sub Default Insurance Performance and Payment Bond Escalation Allowance Contractors Fee Preconstruction Services
/SF
1.5% of Direct Costs
$1.27
/SF
5.4% of Direct Costs
$0.65
/SF
2.8% of Direct Costs
$0.19
/SF
0.8% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$0.19
/SF
0.8% of Direct Costs
$0.64
/SF
2.7% of Direct Costs
$0.19
/SF
0.8% of Direct Costs
$0.13
/SF
0.6% of Direct Costs
$2.24
/SF
9.5% of Direct Costs
$0.11
/SF
0.5% of Direct Costs
$0.02
/SF
0.1% of Direct Costs
Base Contract Amendment 1 Amendment 2
$5,076.00 $428,686.60 $2,289,663.40
Removed CMU Patching at Restrooms Moved All DD Exterior Site Railing into Alternate 16 (Exterior Site Plaza); Removed Structural Reinforement Allowance. ADD ALTERNATE 16 ADD ALTERNATE 16 Moved Wood Shop Window into Alternate 9 Added Furred Walls at Wood Shop & Lower Level RR's; Branding Allowance Included with Division 9 Painting/Wallcovering; ADD ALTERNATE 16 Moved Lockers into Alternate 10
$0.02
/SF
0.1% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$0.09
/SF
0.4% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$4.06
/SF
17.3% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$5.33
/SF
22.7% of Direct Costs
8.2% of Direct Costs
Moved providing & installing speakers/cabling in all common spaces & hallways as well as IP Clock speackes/Cat6 cabling in classrooms, gyms, & cafeteria connected to the new Valcom system to Alternate 4. ADD ALTERNATE 4
/SF
$4.10
/SF
17.4% of Direct Costs
$0.73
/SF
3.1% of Direct Costs
$1.23
/SF
5.3% of Direct Costs
$0.00
/SF
0.0% of Direct Costs
$23.50
/SF
100.0% of Direct Costs
$0.00
/SF
$0.00
/SF
0.00% of Project
$0.00
/SF
0.00% of Project
($97,712) ($97,712) ($6,982)
$0.00
/SF
0.00% of Project
$0.00
/SF
0.00% of Project
$0.71
/SF
3.00% of Subtotal
($3,410) ($7,498)
$0.03
/SF
0.11% of Project
$0.28
/SF
1.10% of Project
$0.00
/SF
0.00% of Costs
($4,281) ($97,712) $13,216 $0
$0.18
/SF
0.68% of Project
$0.00
/SF
0.00% of Project
$1.05
/SF
4.34% of Subtotal + Contingency
$0.05
/SF
($519,867)
$25.79
/SF
Estimated Cost of Construction
CD Estimate Rev. 1
Cost Delta Comments from DD's No Change Refinement of GRs Based on Accepted Scope & Schedule ADD ALTERNATE 16
Moved Window Treatment for Wood Shop Window into Alternate 9. Moved Remove/Replace Bike Racks into Alternate 16. ADD ALTERNATE 16 Not Applicable Not Applicable Added Remove/Relocate Sprinkler Heads Moved to Mechanical DUST COLLECTORS OFOI Not Applicable Moved Some Electrical Panels into Alternate 3 ADD ALTERNATE 3
$1.94
Electronic Safety and Security
Exterior Improvements Utilities
$0.35
100.0% of Project
Bronco Carried a Plug Number at DDs to Generally Account for the Scope. At CDs, Bronco Completed a Full Design, & the Cost Decreased Accordingly. Most of the school has to be installed in surface mounted conduit which is time consuming. Moved All DD Exterior Site Work into Alternate 16 - Exterior Site Plaza; ADD ALTERNATE 16 Moved All DD Exterior Site Work into Alternate 16 - Exterior Site Plaza; ADD ALTERNATE 16 Not Applicable
Dropped to 0% from 2.5% Dropped to 0% from 2.5%
Dropped to 0% from 3%
Detail Report DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
DETAILED COST: Building 00 Procurement and Contracting Requirements
$37,140
00 72 00 AIA General Conditions 00100 General conditions of the contract
$37,140 1.00 ls
37,140.00
Subtotal 00 72 00 AIA General Conditions
$37,140
See Below, Priced per AIA 201
$37,140
Subtotal 00 Procurement and Contracting Requirements
$37,140
01 General Requirements
$134,445
01 14 00 Work Restrictions
$0
01010 Access to Site
Included
01020 Coordination with Occupants
Included
01030 Off-hours work
Not Included
01040 Works in Rights-of-Way
Not Included
01050 ROW Permits
Not Included
Subtotal 01 14 00 Work Restrictions
$0
01 20 00 Price and Payment Procedures
$0
01060 Allowances
Included
01070 Unit Prices
Not Included
Subtotal 01 20 00 Price and Payment Procedures
$0
01 32 00 Construction Progress Documentation 01180 Site Photos, Cameras, Reproductions
$1,750 7.00 mo
250.00
$1,750
01190 Drone Service
Not Included
Subtotal 01 32 00 Construction Progress Documentation
$1,750
01 33 00 Submittal Procedures
$2,050
01110 Delivery Costs
7.00 mo
150.00
$1,050
01130 Reproduction Costs
20.00 ea
50.00
$1,000
01170 Sustainability Project Requirements Subtotal 01 33 00 Submittal Procedures 01 35 53 Security Procedures
Per BVSD Standards $2,050 $0
01120 Trailer Security - Motion and Monitoring
Not Included
01150 Site Security Guard
Not Included
DATE PRINTED: 10/29/2025
Page 5 of 20
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
01160 Site Security Cameras and Monitoring
NOTES / COMMENTS Not Included
Subtotal 01 35 53 Security Procedures
$0
01 45 00 Quality Control
$0
01200 Independent Testing
Not Included
01210 Soil Compaction Tests
Not Included
01220 Concrete Tests
Not Included
01230 Steel Weld Test / Inspections
Not Included
01250 Field Quality Control Procedures
Included
01260 3rd Party Envelope Consultant
Not Included
Subtotal 01 45 00 Quality Control
$0
01 51 00 Temporary Facilities
$38,729
01270 Temporary Electricity - Jobsite
By BVSD
01280 Generators 36kw
Not Included
01290 Fuel for Generator (full load)
Not Included
01300 Generator Setup / and Containment
Not Included
01310 Temporary Fire Protection
Not Included
01340 Temp Heating Fuel
By BVSD
01350 Temporary Building Enclosure for Temp Heating
Not Included
01360 Temporary Lighting
w/ Div. 26 Lighting
01370 Temporary Water 01380 Sanitary Facilities 01390 Temporary Elevators 01400 Temporary Hoists
By BVSD 65.00 ea
380.00
$24,700 Not Included By Trade/Division
01410 Gradall and Operator for Jobsite
Not Included
01420 Bobcat and Operator Jobsite
Not Included
01430 Fuel for Equipment
Included Above
01440 Temporary Cranes
By Division
01450 Temporary Scaffolding and Platforms
By Division
01460 Temporary Stairs and Ramps
Not Included
01470 Temporary Swing Staging
Not Included
01480 Temporary Access Roads
By Division
01490 Snow and Ice Removal
Not Included
01500 Haul Routes
Not Included
01510 Temporary Parking Areas
Not Included
01520 Temporary Air & Noise Barriers
Not Included
DATE PRINTED: 10/29/2025
Page 6 of 20
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
01530 Temporary Fencing (Yard)
NOTES / COMMENTS Included
01540 Temporary Barricades
By Division
01550 Temporary Protective Walkways
Not Included
01560 Temporary Storage
7.00 mo
290.00
$2,030
01580 Barricades and Warning Lights
Not Included
01590 Environmental Protection
Not Included
01600 Exit Enclosure for Existing Exits
Not Included
01610 Project Identification - Temporary Project Signage 01620 Temporary Signage 01630 Technology for DCOW Staff
1.00 ea
2,500.00
$2,500
121,928.00 sf
0.02
$2,761
1,052.00 hr
6.40
$6,738
Subtotal 01 51 00 Temporary Facilities
$38,729
01 70 00 Execution and Closeout
$0
01640 Mobilization
Included
01660 Field Engineering
By Trade
01700 Total Station Rental
Division 2
01720 Construction Surveying
Division 2
01730 Protection of Adjacent Construction
By Division
Subtotal 01 70 00 Execution and Closeout
$0
01 74 00 Cleaning
$91,916
01630 Progress Cleaning
121,928.00 sf
0.27
$32,671
01650 Site Maintenance
1,047,353.00 sf
0.01
$10,473
01690 Final Clean Site 01710 Final Clean Building Subtotal 01 74 00 Cleaning 01 90 00 Life Cycle Activities
Not Included 121,928.00 sf
0.40
$48,771 $91,916 $0
01740 Substructure Commissioning
Not Included
01750 Structure Commissioning
Not Included
01760 Exterior Enclosure Commissioning
Not Included
01770 Roofing Commissioning
Not Included
01780 Systems Commissioning
Not Included
Subtotal 01 90 00 Life Cycle Activities
$0
Subtotal 01 General Requirements
$134,445
02 Existing Conditions
$39,165
DATE PRINTED: 10/29/2025
Page 7 of 20
DESCRIPTION
QTY UOM UNIT PRICE
02 41 00 Demolition 02300 Demo - SUB
TOTAL COST
NOTES / COMMENTS
$39,165 1.00 sub
37,824.00
$37,824 Included at non-ACM locations
02300 Demo flooring finishes 02300 Demo LVT
Included
02300 Demo wood flooring
Included Included at non-ACM locations
02301 Demolish rubber base 02302 Remove existing non load bearing walls
Included
02302 Sawcut interior SOG
Included
02303 Move refrigerators to new location
Included
02303 Remove door, frame and hardware
Included
02304 Demo casework
Included
02304 Remove equipment/furnishings - salvage
Not Included
02305 Demo HM lite and glazing
Included
02305 Remove Masonry Partition
Included
02305 Remove plumbing fixtures & restroom accessories
Included
02421 Sawcut & Demo Concrete Roof Deck for New Exhaust Fan Ducting (CTE 1.2A)
1.00 ea
1,341.27
$1,341
02425 Remove cord reel for relocation
Included
02426 Remove built in bench by entry vestibule
Included
02427 MEP Haul Off
Included
Subtotal 02 41 00 Demolition
$39,165
Subtotal 02 Existing Conditions
$39,165
03 Concrete
$20,372
03 35 00 Concrete Finishing 03351 Interior Concrete - SUB
$7,520 1.00 sub
7,519.80
$7,520
03353 Concrete Slab Infill for UGP for New Fixtures, 5" Thick SOG w/ Fibermesh, Reinf w/ #3 @ 18" OC EW (Laundry 137 & RR 139)
Included
03355 Concrete Slab Infill for UGP for New Fixtures, 5" Thick SOG w/ Fibermesh, Reinf w/ #3 @ 18" OC EW (Art 120)
Included
03357 Concrete Slab Infill for UGP for New Fixtures, 5" Thick SOG w/ Fibermesh, Reinf w/ #3 @ 18" OC EW (Food Lab 114 & 114B)
Included
Subtotal 03 35 00 Concrete Finishing
$7,520
03 35 43 Polished Concrete Finishing
$12,852
DATE PRINTED: 10/29/2025
Page 8 of 20
DESCRIPTION 03511 PC-1 Polished concrete 03513 >Power Requirements 208/3 Phase 50 amp Generator
QTY UOM UNIT PRICE
TOTAL COST
1,892.00 sf
6.00
$11,352
1.00 wk
1,500.00
$1,500
03515 Sealed concrete (Flooring is to remain in the food lab)
NOTES / COMMENTS
Not Included
Subtotal 03 35 43 Polished Concrete Finishing
$12,852
Subtotal 03 Concrete
$20,372
04 Masonry
$0
04 20 00 Unit Masonry
$0
04205 Int CMU Patching/Tooth-in (RR's 117 & 118)
Not Included
04207 Int CMU Patching/Tooth-in (Laundry 137 & RR 139)
Not Included
Subtotal 04 20 00 Unit Masonry
$0
Subtotal 04 Masonry
$0
05 Metals
$2,043
05 50 00 Metal Fabrications 05505 Access Fixed Ladders - Exterior Renewal Allowance
$2,043 1.00 allow
2,043.00
Subtotal 05 50 00 Metal Fabrications
$2,043 $2,043
Subtotal 05 Metals
$2,043
06 Woods, Plastics and Composites
$67,482
06 10 10 Rough Carpentry 06001 Interior Rough Carpentry
$10,757 3,926.00 sf
2.74
Subtotal 06 10 10 Rough Carpentry
$10,757 $10,757
06 22 00 Finish Carpentry 06320 Finish Carpentry - SUB
Allowance
$56,725 1.00 sub
48,725.00
$48,725
06320 Move existing cabinet to corner, remove open shelving
Included
06450 PL-1 - New PLAM open, adjustable shelves
Included
06450 Shelving and storage along north wall
Not Included
06451 Existing casework to remain - Relocate
Included
06451 Rolling shelving at teaching wall
Not Included
06452 PL-1 Base Cabinets
Included
06452 PL-2 Base Cabinets
Included
DATE PRINTED: 10/29/2025
Page 9 of 20
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
06453 SS-1 Countertop
Included
06453 SS-1 Countertop w/ Steel Brackets
Included
06454 PL-1 Tall Cabinet
Included
06454 PL-3 Countertop
Included
06454 SS Loop in Cable on J Screw in Hook Support
Included 1.00 allow
5,000.00
$5,000
06495 Protect casework after relocation
1.00 ls
2,000.00
$2,000
06500 Caulk casework/countertops
1.00 ls
1,000.00
$1,000
06455 Food Lab Casework Repair Allowance
Allowance
06456 Renew look of wood partition between pottery & art
Subtotal 06 22 00 Finish Carpentry
$56,725
Subtotal 06 Woods, Plastics and Composites
$67,482
07 Thermal and Moisture Protection
$16,975
07 60 00 Flashing & Sheet Metal
$16,975
07601 Roofing - SUB
1.00 sub
6,090.11
$6,090
07602 Roof Coring Investigation
1.00 ls
680.00
$680
07603 Demo Existing Roof System at New Penetrations (Remove Existing Gravel for Base Flashing Tie-in
Included
07605 Roof Patches at New Exhaust Fans per Sheet Keynote 171
Included
07607 Roof Patch at New Dryer Vent Stack per Sheet Keynote 172 (Laundry 137)
Included
07608 Roof Cleanup 07609 Safety Measures for Roof Work - Perimeter 07610 Protect Roof from Damage
6,500.00 sf
0.05
$325
286.00 lf
5.00
$1,430
6,500.00 sf
1.30
$8,450
Subtotal 07 60 00 Flashing & Sheet Metal
$16,975
Subtotal 07 Thermal and Moisture Protection
$16,975
08 Openings
$14,232
08 10 00 Doors and Frames
$13,550
08011 Interior 3x7 Door and HM Frame with hardware
2.00 ea
4,150.00
$8,300
08011 Interior 6x7 Door and HM Frame with Hardware
1.00 ea
5,250.00
$5,250
Subtotal 08 10 00 Doors and Frames
$13,550
08 80 00 Glazing 08801 Glazing - SUB 08803 Safety Glazing for Hollow Metal Sidelight, Type 2
DATE PRINTED: 10/29/2025
$682 1.00 sub
576.05
$576 Included
Page 10 of 20
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
08805 Safety Glazing for Wood Door Lites, FG 08807 Final Clean Glass
Included 53.00 sf
2.00
Subtotal 08 80 00 Glazing
$106 $682
Subtotal 08 Openings
$14,232
09 Finishes
$235,528
09 21 16 Gypsum Board Assemblies 09070 Drywall - SUB
NOTES / COMMENTS
$60,000 1.00 sub
35,000.00
$35,000
1.00 ls
25,000.00
$25,000
09071 FRP-1 09071 Level 5 Finish at WC Locations 09071 P-3 Wall - To Deck, 1 layer gyp both sides, STC Rated, Acoustic Insulation, Metal Stud 09072 FR3 Wall - To Deck, 1 layer gyp 1 sides,, Metal Stud 09073 G1 - Gyp Ceiling 09337 Wall Patching Subtotal 09 21 16 Gypsum Board Assemblies
$60,000
09 30 00 Tiling
$29,256
09209 TB-1 Tile Base
Included
09209 TW-1 Wall Tile
Included
09269 Miracle Method at Restrooms - SUB
1.00 sub
29,256.00
Subtotal 09 30 00 Tiling
$29,256
09 51 00 Acoustical Ceilings 09257 C2 - 2x2 flat lay-in - .55 NRC
$1,478 197.00 sf
7.50
Subtotal 09 51 00 Acoustical Ceilings
09307 >Power Requirements 208/3 Phase 50 amp Generator
$11,935 1,510.00 sf
6.91
$10,435
1.00 wk
1,500.00
$1,500
Subtotal 09 64 00 Wood Flooring
$11,935
09 65 00 Resilient Flooring 09335 Flooring - SUB
$1,478 $1,478
09 64 00 Wood Flooring 09305 Refinish wood flooring
$29,256
$68,235 1.00 sub
56,890.00
$56,890
09335 LVT-1
Included
09336 LVT-2
Included
09337 LVT-3
Included
DATE PRINTED: 10/29/2025
Page 11 of 20
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
09338 Moisture resistant adhesive
Included
09461 RB-1/VB-1 New 4" base
Included 6.00 ea
115.00
$690
09613 Floor prep and joint grinding
5,098.00 sf
1.79
$9,125
09637 Floor protection
5,098.00 sf
0.30
$1,529
09585 Moisture tests (1/1000sf)
Subtotal 09 65 00 Resilient Flooring
$68,235
09 68 00 Carpet
$0
09553 WOC-1 Walk Off Tile
Included
Subtotal 09 68 00 Carpet
$0
09 72 00 Wall Coverings
$0
00000 WC-1
Included
00000 WC-2
Included
Subtotal 09 72 00 Wall Coverings
$0
09 90 00 Painting and Coating
$64,625
09700 Branding Graphic Allowance
1.00 allow
25,000.00
$25,000
09700 Paint and Wall Covering - SUB
1.00 sub
38,350.00
$38,350
09720 Repaint walls damaged by replacement of flooring 09825 Final touch up at completion of project
Included 5,098.00 sf
0.25
$1,275
09901 Ramp/Stair Railing, Exterior, Finish Coats
Included Included
Subtotal 09 90 00 Painting and Coating
$64,625
Subtotal 09 Finishes
$235,528
10 Specialties
$11,287
10 14 00 Signage
$1,250
10005 Set Branding Allowance 10035 Signage - SUB
Allowance
Included 1.00 sub
1,250.00
$1,250
10036 Room ID Sign
Included
10037 Door Tag
Included
10037 Restroom ID
Included
Subtotal 10 14 00 Signage
$1,250
10 28 00 Toilet & Bath Accessories 10200 Specialties - SUB 10201 TA-1 42" SS Grab Bar
DATE PRINTED: 10/29/2025
$10,037 1.00 sub
9,137.31
$9,137 Included
Page 12 of 20
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
10202 TA-2 36" SS Grab Bar
Included
10203 TA-3 18" SS Grab Bar
Included
10204 TA-4 Soap Dispenser
Included
10205 TA-5 TP Dispenser OFCI
3.00 ea
150.00
$450
10206 TA-6 Framed Mirror 10207 TA-7 PT Dispenser OFCI
Included 3.00 ea
150.00
$450
10208 Mop and Broom Holder
Included
10208 TA-8 Sanitary Napkin Disposal
Included
10208 Toilet Partitions - Phenolic
Included
Subtotal 10 28 00 Toilet & Bath Accessories
$10,037
Subtotal 10 Specialties
$11,287
11 Equipment
$1,841
11 30 00 Residential Equipment (GE Equipment) 11155 GE Electric Range - 30"
$1,841 1.00 ea
1,841.00
Subtotal 11 30 00 Residential Equipment (GE Equipment)
$1,841 $1,841
Subtotal 11 Equipment
$1,841
21 Fire Suppression
$10,007
21 00 00 Fire Suppression 21000 Fire Suppression - SUB
$10,007 1.00 sub
10,007.00
$10,007
21001 Remove and Relocate Sprinkler Heads
Included
21002 Delegated Design
Included
21003 High Temperature Head at Kiln
Included
Subtotal 21 00 00 Fire Suppression Subtotal 21 Fire Suppression 22 Plumbing 22 00 00 Plumbing
$10,007 $10,007 $0 $0
22001 Plumbing - SUB
w/ Div. 23 Mechanical
22003 Plumbing Demo
Included
22005 Plumbing Piping Systems (Domestic Water, Waste, Underground Waste, Vent)
Included
22007 Plumbing Equipment
See Below
22009 >Fixtures
See Below
22011 >>Water Closet, ADA, WC-1 (RR's 117, 118, & 139)
DATE PRINTED: 10/29/2025
Included
Page 13 of 20
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
22013 >>Lavatory, ADA, L-1 (RR's 117, 118, & 139)
Included
22015 >>Sinks, S-1 (Art 120)
Included
22017 >>Sinks, S-2 (Food Lab 114)
Included
22019 >>Sink, S-3 (Art 120)
Included
22023 >>Garbage Disposals, GD-1
Not Included
22025 >>Solids Interceptor, SI-1 (Art 120)
Included
22027 >>Electric Water Cooler/Bottle Filler, ADA, EWC -1
Included
22029 >>Mop Service Basin, MSB-1 (Laundry 137)
Included
22031 >>Utility Sink, US-1 (Laundry 137)
Included
22033 >>Washer Wall Box, WWB-1 (Laundry 137)
Included
22035 >>Floor Drain, FD-1 (Laundry 137 & RR 139)
Included
22037 >Thermostatic Mixing Valve, TMV-1 (RR's 117, 118, & 139)
Included
22041 >Balance Valve Assemblies
Included
22043 Insulation, Fire Stopping/Caulking
Included
22045 Test & Balance
Included
22047 Concrete Cutting, Coring, & Xray
Included
22049 Domestic Water Chlorination
Included
22051 Pressure Testing of New Piping
Included
22053 MEP Coordination & QA/QC - Plumbing
w/ Div. 23 Mechanical
Subtotal 22 00 00 Plumbing
$0
Subtotal 22 Plumbing
$0
23 Heating, Ventilating and Air Conditioning
$428,405
23 00 00 Heating, Ventilating and Air Conditioning 23001 Mechanical - SUB
$428,405 1.00 sub
451,567.21
$451,567
23003 Mechanical Demo
See Below Included
23005 HVAC & Mechanical Equipment
See Below
23007 >Exhaust Fans, EF-14 (Restrooms), EF-16 (Laser Rm), EF-17 (Storage)
Included
23011 >Dryer Fans, F-1 (Laundry 137)
Included
23013 >Grilles, Registers, Diffusers, SG-1, EG-1, EG-2, TG-2
Included
23015 >Airking Filtration Unit, AFU-1
Included
23017 >Ruwac Stand Alone Dust Collectors, PDC-1
Included
23018 >>Ruwac Stand Alone Dust Collectors, PDC-1 Supply (OFOI) 23019 Mechanical Piping (Heating Hot Water, DATE PRINTED: 10/29/2025
-2.00 ea
17,000.00
($34,000)
OFOI Included Page 14 of 20
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
Condensate Waste) 23021 HVAC Ductwork Systems (Supply, Return, Exhaust) 23025 MEP Coordination & QA/QC -Mechanical
Included 444,621.00 ls
0.02
Subtotal 23 00 00 Heating, Ventilating and Air Conditioning
$10,838 $428,405
Subtotal 23 Heating, Ventilating and Air Conditioning
$428,405
26 Electrical
$562,988
26 00 00 Electrical 26001 Electrical - SUB
$562,988 1.00 sub
440,897.31
$440,897
26003 >Site Lighting & Power
Included
26005 >Service & Distribution
Included
26007 >Lighting
Included
26009 >Lighting Circuitry
Included
26011 >Lighting Controls
Included
26013 >Branch Power
Included
26015 >Mechanical Equipment Connections
Included
26017 >Tele/Data Raceways
Included
26019 >Audio Visual Raceways
Included
26020 Permit Fees (MEP)
Included
26021 >Clock/Paging Raceways
Included
26023 >Demolition
Included
26025 Temporary Lighting & Power
Included
26027 Fire Caulking/Fire Stopping
Included
26029 Remove/reinstall Cover Plates on Electrical Devices & Light Switches 26031 MEP Coordination & QA/QC - Electrical 26033 Replace Additional Electrical Panels 26035 >MEP Coordination & QA/QC - Electrical
130.00 ea
20.00
$2,600
432,174.00 ls
0.03
$10,838
1.00 ls
106,767.63
$106,768
Alternate 3
94,240.00 ls
0.02
$1,885
Alternate 3
Subtotal 26 00 00 Electrical
$562,988
Subtotal 26 Electrical
$562,988
27 Communications
$204,516
27 51 00 Distributed AV systems
$204,516
27501 Upgrade Intercom/Public Address System Replace Existing Intercom Head-end Equipment Only
1.00 sub
62,618.00
$62,618
27503 Provide & Install Speakers & Cabling in Common Spaces & Hallways Connected to New
1.00 sub
120,573.00
$120,573
DATE PRINTED: 10/29/2025
Alternate 4
Page 15 of 20
DESCRIPTION Common Spaces & Hallways Connected to New Valcom System
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
27505 Provide & Install IP Clock Speakers & Cat6 Cabling in Classrooms, Gyms, & Cafeteria Connected to New Valcom System
Alternate 4 - Included
27507 >Electrical Scope - Rough-In Backboxes & Conduit
w/ Div. 26 Electrical
27509 Classroom Updated to Standard Teaching. Adding Lightspeed Voice Reinforcement Sys. (Wood Shop, Art Room, Food Lab)
3.00 ea
2,503.00
$7,509
27511 New Projector & Screen (Wood Shop 124)
Included
27513 Structural Cabling - SUB
1.00 sub
7,448.00
$7,448
27515 New Ceiling Mounted Projector, New Drop Down Screen (Wood Shop 124)
1.00 ls
6,368.00
$6,368
Subtotal 27 51 00 Distributed AV systems
$204,516
Subtotal 27 Communications
$204,516
28 Electronic Safety and Security
$432,934
28 00 00 Electronic Safety and Security 28101 Fire Alarm System - Full System Replacement w/ Voice Evacuation - SUB
$432,934 1.00 sub
421,777.46
$421,777
28103 >New Intelligent, Fully Addressable Fire Alarm System
Included
28105 >Voice Evacuation System
Included
28107 >New FACP w/ Expansion Capability
Included
28109 >New Smoke Detectors, Pull Stations, & Duct Detectors
Included
28111 >Notification Appliances Throughout the Building (Speakers, Strobes)
Included
28113 MEP Coordination & QA/QC - Fire Alarm
455,240.00 ls
0.02
Subtotal 28 00 00 Electronic Safety and Security
$432,934
Subtotal 28 Electronic Safety and Security
$432,934
32 Exterior Improvements
$2,745
32 13 00 Rigid Paving 32159 Exterior Wall - Damaged Concrete Allowance
$11,157
$2,745 1.00 allow
2,745.00
$2,745
Subtotal 32 13 00 Rigid Paving
$2,745
Subtotal 32 Exterior Improvements
$2,745
Total Building
DATE PRINTED: 10/29/2025
Allowance
$2,222,106
Page 16 of 20
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
DETAILED COST: Site 02 Existing Conditions
$29,928
02 21 00 Surveys
$29,928
02201 Total Stations
2.00 mo
3,992.00
$7,984
02203 Survey - SUB
1.00 sub
6,858.00
$6,858
Alternate 16
02205 Survey Calculations & Plan Checks (IS 2)
1.00 ea
85.71
$86
Alternate 16 - Included
02207 Survey Control Points & Sawcut (IS 2)
Alternate 16 - Included
02209 Survey Grading (IS 2)
Alternate 16 - Included
02211 Survey Hanrails/Bike Racks (IS 2)
Alternate 16 - Included
02213 Survey Four Court Layout (IS 2)
Alternate 16 - Included
02215 Survey Concrete/Sidewalks, Ramps & Stairs (IS 2)
Alternate 16 - Included
02217 Survey Restaking (IS 2)
Alternate 16 - Included
02219 Survey Site Improvement As-Built (IS 2)
Alternate 16 - Included
02223 Penetrating Radar for Investigation
1.00 ls
15,000.00
$15,000
Subtotal 02 21 00 Surveys
$29,928
Subtotal 02 Existing Conditions
$29,928
05 Metals
$17,569
05 50 00 Metal Fabrications 05501 Ramp/Stair Railing, Exterior, HP Primed Steel (IS 2)
$17,569 1.00 ls
17,569.13
Subtotal 05 50 00 Metal Fabrications
$17,569 $17,569
Subtotal 05 Metals
$17,569
07 Thermal and Moisture Protection
$3,510
07 13 26 Waterproofing 07131 Drainage Board at Retaining Wall (IS 2)
$500 81.00 sf
6.17
Subtotal 07 13 26 Waterproofing
Subtotal 07 92 00 Joint Sealants
$500
$3,010 1.00 sub
3,010.00
$3,010
Alternate 16
$3,010
Subtotal 07 Thermal and Moisture Protection
$3,510
09 Finishes
$1,150
DATE PRINTED: 10/29/2025
Alternate 16
$500
07 92 00 Joint Sealants 07921 Slab to Structure Joint Sealants, Expansion Joint at Top & Bottom of Stairs (IS 2)
Alternate 16
Page 17 of 20
DESCRIPTION
QTY UOM UNIT PRICE
09 90 00 Painting and Coating 09720 Paint exterior metals
TOTAL COST $1,150
1.00 ls
1,150.00
Subtotal 09 90 00 Painting and Coating
$1,150
Alternate 16
$1,150
Subtotal 09 Finishes
$1,150
12 Furnishings
$2,520
12 93 00 Site Furnishings 12931 Remove/Reinstall Bike Racks, U-Shaped, Surface Mounted (IS 2)
NOTES / COMMENTS
$2,520 16.00 ea
157.50
Subtotal 12 93 00 Site Furnishings
$2,520
Alternate 16
$2,520
Subtotal 12 Furnishings
$2,520
31 Earthwork
$77,107
31 00 00 Earthwork
$54,968
31001 Earthwork - SUB
Alternate 16 - See Below
31003 Pothole Utilities (IS 2)
8.00 hr
641.84
$5,135
Alternate 16
31005 Private Locates (IS 2)
8.00 hr
961.73
$7,694
Alternate 16
31007 Construction Water (IS 2) 31009 Earthwork at Exterior Site Plaza - SUB
Alternate 16 - Included 1.00 sub
42,139.26
$42,139
Alternate 16 - See Below
31011 >Sawcut Concrete Paving/Sidewalk (IS 2)
Alternate 16 - Included
31013 >Remove & Dispose Concrete/Paving (IS 2)
Alternate 16 - Included
31015 >Excavate Cut to Export (IS 2)
Alternate 16 - Included
31017 >Export Material (IS 2)
Alternate 16 - Included
31019 >Import CL6 Roadbase (IS 2)
Alternate 16 - Included
31021 >Place Roadbase (IS 2)
Alternate 16 - Included
31023 >Scarify Below Concrete Paving, 12" Depth (IS 2)
Alternate 16 - Included
31025 >Rough Grade Site (IS 2)
Alternate 16 - Included
31027 >Excavate & Backfill Stairs (IS 2)
Alternate 16 - Included
Subtotal 31 00 00 Earthwork
$54,968
31 25 00 Erosion and Sedimentation Controls
$22,139
31251 Concrete Washout Area (CWA) (3 EA, 4 Months), 1.5 CY Pump Pan (IS 2)
12.00 ea
227.50
$2,730
Alternate 16
31253 Concrete Washout Area (CWA) (3 EA, 4 Months), 5.5 CY Container (IS 2)
12.00 ea
417.50
$5,010
Alternate 16
31255 Rock Socks/Filtrex Logs (Curb/Gutter, Temp. Fencing) (IS 2)
283.00 lf
13.00
$3,679
Alternate 16
31257 Vehicle Tracking Control (VTC) (4 EA, 4 Months) (IS 2)
16.00 ea
287.50
$4,600
Alternate 16
DATE PRINTED: 10/29/2025
Page 18 of 20
DESCRIPTION
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
9.00
$2,520
Alternate 16
900.00
$3,600
Alternate 16
(IS 2) 31259 Temporary Fencing (Installation/Removal/Maintenance) (IS 2) 31261 SRM - Small Projects - 1-5 Acres (IS 2)
280.00 lf 4.00 mo
Subtotal 31 25 00 Erosion and Sedimentation Controls
$22,139
Subtotal 31 Earthwork
$77,107
32 Exterior Improvements
$127,615
32 12 00 Flexible Paving
$16,204
32121 Ashpalt "T" Patch - SUB (IS 2)
1.00 sub
15,604.00
$15,604
Alternate 16
32133 Asphalt Adjustment Index Cost for Liquid Asphalt (Binder) (IS 2)
1.00 tn
600.00
$600
Alternate 16
Subtotal 32 12 00 Flexible Paving
$16,204
32 13 00 Rigid Paving 32129 Concrete at Plaza - SUB (IS 2)
$104,661 1.00 sub
89,146.74
$89,147
Alternate 16
32131 >Concrete Pavement, 5" w/ Fibermesh (IS 2)
Alternate 16 - Included
32133 >Concrete Ramp, 5" w/ Fibermesh, #4 @ 12" OCEW (IS 2)
Alternate 16 - Included
32135 >Concrete Retaining Wall Along Ramp, Reinf. with (2) #4 Cont. T&B, #4 Cont. (IS 2)
Alternate 16 - Included
32137 >>Smooth Sack Finish (IS 2)
Alternate 16 - Included
32139 >>>Continuous Footing, 8"x20", Reinf. with #4 Cont. @ 16" OC T&B, #4 Trans @ 24" OC T&B (IS 2)
Alternate 16 - Included
32141 >Stairs with (3) 5.5" Risers, Reinf. with #4 @12" OCEW (IS 2)
Alternate 16 - Included
32143 >>Turndown Edge at Steps, Reinf. With #4 @ 12" OCEW (IS 2)
Alternate 16 - Included
32145 >Concrete Material Increase After 4/1/26 (IS 2)
120.00 cy
6.87
$824
32147 >Rebar for Retaining Wall, Stairs, Turned Down Edge - Material (IS 2) 32149 Concrete Foreman (IS 2) 32151 Sweep/Clean Sitework Prior to Turnover (IS 2)
Alternate 16 - Included 1.00 mo
14,671.00
$14,671
Alternate 16
270.00 sy
0.07
$19
Alternate 16
Subtotal 32 13 00 Rigid Paving
$104,661
32 17 00 Paving Specialties 32171 Lines & Infill, 4 Square Courts, White Lines with Green Infill - SUB (IS 2) Subtotal 32 17 00 Paving Specialties Subtotal 32 Exterior Improvements
DATE PRINTED: 10/29/2025
Alternate 16
$6,750 1.00 sub
6,750.00
$6,750
Alternate 16
$6,750 $127,615
Page 19 of 20
DESCRIPTION
Total Site
DATE PRINTED: 10/29/2025
QTY UOM UNIT PRICE
TOTAL COST
NOTES / COMMENTS
$259,399
Page 20 of 20
Exhibit D
Contract Time Schedule Itemization ofGMP Cost Itemization of the Dollars requested for long lead equipment and material packages
Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20
RE: Schedule Narrative – October 2025 Schedule Update Narrative October 17, 2025 BVSD – Southern Hills Middle School 1500 Knox Drive Boulder CO. 80305 The following is a schedule narrative for the BVSD –Southern Hills Middle School [Boulder Valley RFP 25-04 CMGC Project Scope #1 – Southern Hills Middle School 10.17.2025.pdf] is attached.
Summary: This updated schedule reflects revisions to the DD schedule and aligns with the bi-weekly OAC dashboard timelines. It outlines the project timeline from preconstruction to construction activities and provides key milestone dates during preconstruction to allow for a successful construction phase during the summer. AP has been actively identifying long-lead procurement items starting at the Schematic Design phase. In collaboration with trade partners, AP has gathered lead times, submittal preparation costs, and material release costs.
Description of Activities on the most Critical Path The current critical path is driven by the wood shop and the art room scope. Progress in those spaces are dependent on the completion of the school year as well as the coordination of multiple trade contractors to sequence their work in those areas. This area is currently tracking in the master schedule to meet the required TCO date.
Monthly Progress Description The schedule has been updated and activities have been adjusted to reflect the latest CD documents. Tasks have been progressed since the previous update.
Current/Anticipated Problem Areas and/or Delaying Factors October 2025 – BVSD & AP have preordered long lead time material as noted in the Amendment 1 procurement change order. AP is tracking all long lead time material with the master schedule for completion to meet the required schedule.
Revisions to the Project Schedule The updates made to establish a targeted flow through the building.
Narrative Review To recap the attached schedule and the above update: •
Overall, the attached schedule provides a road map for the design and construction of the BVSDSouthern Hills Middle School. As more planning, coordination, and construction scope is defined and developed, the schedule will continue to reflect these changes and updates.
•
The current schedule is on track for TCO by August 1st 2026.
•
The project approach is to assist with coordinating owner activities for summer of 2026 and Construction work that is to be completed per the TCO date.
•
The team is tracking numerous important dates: document release, funding package dates, and material release dates. AP will continue to update the team in forthcoming narratives and OAC meetings
•
Lastly, the schedule changes and modifications outlined above help to more accurately show how the project is being built and ways that BVSD,MOA, AP and their subcontractors are working to maintain or improve the project completion date.
Please feel free to contact me with any questions or comments regarding this update or anything else within the Project. Thank you, Logan Dickerman Superintendent Adolfson & Peterson Construction 720.456.1992 ldickerman@a-p.com
Line
Name
Duration APC
Start
Finish
BVSD - Southern Hills Middle School
31.37
8/12/2024
9/30/2026
Preconstruction
36.44
8/12/2024
5/27/2026
2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5
RFP / RFQ Information
49d 100.00 8/12/2024 10/18/2024
1
RFP Issued to Contractor
1d 100.00 8/12/2024 A 8/12/2024 A
RFP Issued to Contractor
2
RFP Site Walk
1d 100.00 8/22/2024 A 8/22/2024 A
RFP Site Walk
3
RFP Inquiries Due
1d 100.00
4
RFP Addendum Sent
1d 100.00 9/12/2024 A 9/12/2024 A
5
RFP Submission Deadline
1d 100.00 10/3/2024 A 10/3/2024 A
6
RFP Evaluation
1d 100.00 10/11/2024 A 10/11/2024 A
7
CMGC Contract Award
1d 100.00 10/18/2024 A 10/18/2024 A
Document Development
9/4/2024 A
9/4/2024 A
RFP Inquiries Due
RFP Addendum Sent
RFP Submission Deadline
RFP Evaluation
CMGC Contract Award
91.99
1/6/2025
12/26/2025
Schematic Design
101d 100.00
1/6/2025
5/27/2025
8
SD-Design Advisory Team Meetings
65d 100.00
1/6/2025 A
4/4/2025 A
9
SD- Early VFA Investigation and Verification
73d 100.00
1/7/2025 A 4/17/2025 A
10
SD-Schematic Design Complete
1d 100.00 2/14/2025 A 2/14/2025 A
11
SD-Schematic Design Pricing/ Constructability Review
23d 100.00 2/17/2025 A 3/19/2025 A
SD-Schematic Design Pricing/ Constructability Review
12
SD-Schematic Design Bid Leveling/ Review Meeting
1d 100.00 3/19/2025 A 3/19/2025 A
SD-Schematic Design Bid Leveling/ Review Meeting
13
SD- Schematic Design - Budget/ Constructability Corrections
4d 100.00 3/20/2025 A 3/25/2025 A
SD- Schematic Design - Budget/ Constructability Corrections
14
SD- Early Procurement Package Creation by AP
23d 100.00 3/26/2025 A 4/25/2025 A
15
SD- Early Procurement Package Review with BVSD
15d 100.00 4/28/2025 A 5/16/2025 A
16
SD- Early Procurement Package Issuance to Board
5d 100.00 5/20/2025 A 5/27/2025 A
Design Development 17 18 19 20 21 22
112d 100.00 2/10/2025
DD-Design Development - Pricing/ Constructability Review DD-Design Development - Design Development Complete DD-Final Design Advisory Team Meeting DD-Design Development - Pricing/ Constructability Internal Review DD-Design Development - Budget/ Constructability Corrections DD-Design Development - Final Procurement Package Allocation Review to Start Long Lead Submittals
SD-Design Advisory Team Meetings
SD- Early VFA Investigation and Verification
SD-Schematic Design Complete
SD- Early Procurement Package Creation by AP
SD- Early Procurement Package Review with BVSD
SD- Early Procurement Package Issuance to Board
7/17/2025
97d 100.00 2/10/2025 A 6/25/2025 A
DD-Design Development - Pricing/ Constructability Review
20d 100.00 4/18/2025 A 5/15/2025 A
DD-Design Development - Design Development Complete
1d 100.00 5/16/2025 A 5/16/2025 A
DD-Final Design Advisory Team Meeting
1d 100.00 6/25/2025 A 6/25/2025 A
DD-Design Development - Pricing/ Constructability Internal Review
9d 100.00 6/26/2025 A 7/9/2025 A
DD-Design Development - Budget/ Constructability Corrections
1d 100.00 7/17/2025 A 7/17/2025 A
Contracting & Award
148d 75.37
5/27/2025 12/26/2025
Procurement Package
104d 97.12
5/27/2025 10/21/2025
Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School
DD-Design Development - Final Procurement Package Allocation Review to Start Long Lead Submittals
Rev. date: 10/17/2025 10:27:32 AM Job #: Southern Hills Middle School
Data Date: 10/17/2025
Page 1 of 14
3. Print View Filter: No Summary Tasks
Line
Name
Duration APC
Start
Finish
2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5
23
C&A-PP-Board Approval
8d 100.00 5/27/2025 A 6/5/2025 A
24
C&A-PP-BVSD Contract Execution to AP
49d 100.00
6/6/2025 A 8/14/2025 A
25
C&A-PP-AP Contract Execution to Procurement Package Subs
47d 93.62
8/15/2025 A 10/21/2025
FGMP
30d
11/11/2025 12/26/2025
26
C&A-FGMP-Board Approval
5d
11/11/2025 11/17/2025
27
C&A-FGMP-BVSD Contract Execution to AP
10d
11/18/2025
12/3/2025
28
C&A-FGMP-AP Contract Execution to Remaining Subs
15d
12/4/2025
12/26/2025
Electrical Metering
14d 100.00 4/18/2025
5/1/2025
29
EI-7 Day Electrical Metering
7d 100.00 4/18/2025 A 4/24/2025 A
30
EI- 30 Day Electrical Metering
14d 100.00 4/18/2025 A 5/1/2025 A
Early Investigation and Coordination
8d 100.00 7/14/2025
31
EI-Design/ Sub Kick off Meeting
2d 100.00 7/14/2025 A 7/15/2025 A
EI-Design/ Sub Kick off Meeting
32
EI-Onsite Review of Mechanical Scope
2d 100.00 7/16/2025 A 7/17/2025 A
EI-Onsite Review of Mechanical Scope
33
EI-Onsite Review of Remaining Scope
2d 100.00 7/22/2025 A 7/23/2025 A
EI-Onsite Review of Remaining Scope
C&A-PP-Board Approval
C&A-PP-BVSD Contract Execution to AP
C&A-PP-AP Contract Execution to Procurement Package Subs
C&A-FGMP-Board Approval
C&A-FGMP-BVSD Contract Execution to AP
C&A-FGMP-AP Contract Execution to Remaining Subs
EI-7 Day Electrical Metering
EI- 30 Day Electrical Metering
7/23/2025
Construction Documents
124d 86.29
5/16/2025 11/10/2025
34
Construction Documents and Drawings Complete
83d 100.00 5/16/2025 A 9/12/2025 A
35
Construction Documents - Pricing Review
25d 96.00
9/15/2025 A 10/17/2025
Construction Documents - Pricing Review
36
Construction Documents - FGMP Review with BVSD PM
1d
10/20/2025 10/20/2025
Construction Documents - FGMP Review with BVSD PM
37
Construction Documents - FGMP Corrections
5d
10/21/2025 10/27/2025
38
Construction Documents - Final FGMP Amendment to District Board of Education Submission
10d
10/28/2025 11/10/2025
Permitting
145d 11.71
9/15/2025
39
Building Permit Review and Issuance
125d 19.20
9/15/2025 A 3/13/2026
40
Remaining Permit Approval
40d
1/5/2026
2/27/2026
41
Local AHJ Permit Review and Issuance
40d
2/16/2026
4/10/2026
Long Lead Submittals & Procurement
221d 24.69
7/14/2025
5/27/2026
Submittals & Procurement - Fire Alarm Equipment
143d 17.86
9/12/2025
4/7/2026
Submittals & Procurement - Fire Alarm Equipment
143d 17.86
9/12/2025
4/7/2026
42
S&P - FA - Subcontractor Submittals
30d 83.33
9/12/2025 A 10/28/2025
43
S&P - FA - AP Review
5d
10/29/2025
11/4/2025
44
S&P - FA - AHJ Review and Approval
15d
11/5/2025
11/25/2025
Construction Documents and Drawings Complete
Construction Documents - FGMP Corrections
Construction Documents - Final FGMP Amendment to District Board of Education Submission
4/10/2026
Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School
Building Permit Review and Issuance
Remaining Permit Approval
Local AHJ Permit Review and Issuance
S&P - FA - Subcontractor Submittals
S&P - FA - AP Review
S&P - FA - AHJ Review and Approval
Rev. date: 10/17/2025 10:27:32 AM Job #: Southern Hills Middle School
Data Date: 10/17/2025
Page 2 of 14
3. Print View Filter: No Summary Tasks
Line
Name
Duration APC
Start
Finish
45
S&P - FA - A/E Review and Approval
10d
11/26/2025 12/11/2025
46
S&P - FA - Procurement
80d
12/12/2025
Submittals & Procurement - AV Equipment
75d
12/29/2025 4/13/2026
2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5 S&P - FA - A/E Review and Approval
4/7/2026
Submittals & Procurement - AV Equipment
75d
12/29/2025 4/13/2026
47
S&P - SE- Subcontractor Submittals
20d
12/29/2025
1/26/2026
48
S&P - SE- AP Review
5d
1/27/2026
2/2/2026
49
S&P - SE- A/E Review and Approval
10d
2/3/2026
2/16/2026
S&P - SE- Procurement
S&P - FA - Procurement
S&P - SE- Subcontractor Submittals
S&P - SE- AP Review
S&P - SE- A/E Review and Approval
40d
2/17/2026
4/13/2026
Submittals & Procurement - Electrical Distribution Equipment/ Panel Boards
210d 35.52
7/14/2025
5/11/2026
Submittals & Procurement - Panel G
128d 42.31
7/14/2025
1/15/2026
51
S&P - EDE - Subcontractor Submittals
29d 100.00 7/14/2025 A 8/21/2025 A
S&P - EDE - Subcontractor Submittals
52
S&P - EDE- AP Review
1d 100.00 8/21/2025 A 8/21/2025 A
S&P - EDE- AP Review
53
S&P - EDE - A/E Review and Approval
14d 100.00 8/21/2025 A 9/10/2025 A
54
S&P - EDE - Procurement
60d
10/17/2025
1/15/2026
Submittals & Procurement - Panel UV2
128d 42.31
7/14/2025
1/15/2026
55
S&P - EDE - Subcontractor Submittals
29d 100.00 7/14/2025 A 8/21/2025 A
S&P - EDE - Subcontractor Submittals
56
S&P - EDE- AP Review
1d 100.00 8/21/2025 A 8/21/2025 A
S&P - EDE- AP Review
57
S&P - EDE - A/E Review and Approval
14d 100.00 8/21/2025 A 9/10/2025 A
58
S&P - EDE - Procurement
60d
10/17/2025
1/15/2026
Submittals & Procurement - Panel K
128d 42.31
7/14/2025
1/15/2026
59
S&P - EDE - Subcontractor Submittals
29d 100.00 7/14/2025 A 8/21/2025 A
S&P - EDE - Subcontractor Submittals
60
S&P - EDE- AP Review
1d 100.00 8/21/2025 A 8/21/2025 A
S&P - EDE- AP Review
61
S&P - EDE - A/E Review and Approval
14d 100.00 8/21/2025 A 9/10/2025 A
62
S&P - EDE - Procurement
60d
10/17/2025
1/15/2026
Submittals & Procurement - Panel A
128d 42.31
7/14/2025
1/15/2026
63
S&P - EDE - Subcontractor Submittals
29d 100.00 7/14/2025 A 8/21/2025 A
S&P - EDE - Subcontractor Submittals
64
S&P - EDE- AP Review
1d 100.00 8/21/2025 A 8/21/2025 A
S&P - EDE- AP Review
65
S&P - EDE - A/E Review and Approval
14d 100.00 8/21/2025 A 9/10/2025 A
66
S&P - EDE - Procurement
60d
10/17/2025
1/15/2026
Submittals & Procurement - Panel B
127d 41.75
7/15/2025
1/15/2026
50
Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School
S&P - SE- Procurement
S&P - EDE - A/E Review and Approval
S&P - EDE - Procurement
S&P - EDE - A/E Review and Approval
S&P - EDE - Procurement
S&P - EDE - A/E Review and Approval
S&P - EDE - Procurement
S&P - EDE - A/E Review and Approval
S&P - EDE - Procurement
Rev. date: 10/17/2025 10:27:32 AM Job #: Southern Hills Middle School
Data Date: 10/17/2025
Page 3 of 14
3. Print View Filter: No Summary Tasks
Line
Name
Duration APC
Start
Finish
2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5
67
S&P - EDE - Subcontractor Submittals
28d 100.00 7/15/2025 A 8/21/2025 A
S&P - EDE - Subcontractor Submittals
68
S&P - EDE- AP Review
1d 100.00 8/21/2025 A 8/21/2025 A
S&P - EDE- AP Review
69
S&P - EDE - A/E Review and Approval
14d 100.00 8/21/2025 A 9/10/2025 A
S&P - EDE - A/E Review and Approval
S&P - EDE - Procurement
60d
10/17/2025
1/15/2026
Submittals & Procurement - Panel E
127d 41.75
7/15/2025
1/15/2026
71
S&P - EDE - Subcontractor Submittals
28d 100.00 7/15/2025 A 8/21/2025 A
S&P - EDE - Subcontractor Submittals
72
S&P - EDE- AP Review
1d 100.00 8/21/2025 A 8/21/2025 A
S&P - EDE- AP Review
73
S&P - EDE - A/E Review and Approval
14d 100.00 8/21/2025 A 9/10/2025 A
74
S&P - EDE - Procurement
60d
10/17/2025
1/15/2026
Submittals & Procurement - Panel F
127d 41.75
7/15/2025
1/15/2026
75
S&P - EDE - Subcontractor Submittals
28d 100.00 7/15/2025 A 8/21/2025 A
S&P - EDE - Subcontractor Submittals
76
S&P - EDE- AP Review
1d 100.00 8/21/2025 A 8/21/2025 A
S&P - EDE- AP Review
77
S&P - EDE - A/E Review and Approval
14d 100.00 8/21/2025 A 9/10/2025 A
78
S&P - EDE - Procurement
60d
10/17/2025
1/15/2026
Submittals & Procurement - Panel UV1
127d 41.75
7/15/2025
1/15/2026
79
S&P - EDE - Subcontractor Submittals
28d 100.00 7/15/2025 A 8/21/2025 A
S&P - EDE - Subcontractor Submittals
80
S&P - EDE- AP Review
1d 100.00 8/21/2025 A 8/21/2025 A
S&P - EDE- AP Review
81
S&P - EDE - A/E Review and Approval
14d 100.00 8/21/2025 A 9/10/2025 A
82
S&P - EDE - Procurement
60d
10/17/2025
1/15/2026
Submittals & Procurement - Panel N
127d 41.75
7/15/2025
1/15/2026
83
S&P - EDE - Subcontractor Submittals
28d 100.00 7/15/2025 A 8/21/2025 A
S&P - EDE - Subcontractor Submittals
84
S&P - EDE- AP Review
1d 100.00 8/21/2025 A 8/21/2025 A
S&P - EDE- AP Review
85
S&P - EDE - A/E Review and Approval
14d 100.00 8/21/2025 A 9/10/2025 A
86
S&P - EDE - Procurement
60d
10/17/2025
1/15/2026
Submittals & Procurement - Panel J
127d 41.75
7/15/2025
1/15/2026
87
S&P - EDE - Subcontractor Submittals
28d 100.00 7/15/2025 A 8/21/2025 A
S&P - EDE - Subcontractor Submittals
88
S&P - EDE- AP Review
1d 100.00 8/21/2025 A 8/21/2025 A
S&P - EDE- AP Review
89
S&P - EDE - A/E Review and Approval
14d 100.00 8/21/2025 A 9/10/2025 A
90
S&P - EDE - Procurement
60d
10/17/2025
1/15/2026
Submittals & Procurement - Shop Main Panel
137d 38.05
7/15/2025
1/29/2026
70
Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School
S&P - EDE - Procurement
S&P - EDE - A/E Review and Approval
S&P - EDE - Procurement
S&P - EDE - A/E Review and Approval
S&P - EDE - Procurement
S&P - EDE - A/E Review and Approval
S&P - EDE - Procurement
S&P - EDE - A/E Review and Approval
S&P - EDE - Procurement
S&P - EDE - A/E Review and Approval
S&P - EDE - Procurement
Rev. date: 10/17/2025 10:27:32 AM Job #: Southern Hills Middle School
Data Date: 10/17/2025
Page 4 of 14
3. Print View Filter: No Summary Tasks
Line
Name
Duration APC
Start
Finish
2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5
91
S&P - EDE - Subcontractor Submittals
28d 100.00 7/15/2025 A 8/21/2025 A
S&P - EDE - Subcontractor Submittals
92
S&P - EDE- AP Review
1d 100.00 8/21/2025 A 8/21/2025 A
S&P - EDE- AP Review
93
S&P - EDE - A/E Review and Approval
14d 100.00 8/21/2025 A 9/10/2025 A
S&P - EDE - A/E Review and Approval
S&P - EDE - Procurement
70d
10/17/2025
1/29/2026
Submittals & Procurement - Shop Sub Panel
137d 38.05
7/15/2025
1/29/2026
95
S&P - EDE - Subcontractor Submittals
28d 100.00 7/15/2025 A 8/21/2025 A
S&P - EDE - Subcontractor Submittals
96
S&P - EDE- AP Review
1d 100.00 8/21/2025 A 8/21/2025 A
S&P - EDE- AP Review
97
S&P - EDE - A/E Review and Approval
14d 100.00 8/21/2025 A 9/10/2025 A
98
S&P - EDE - Procurement
70d
10/17/2025
1/29/2026
Submittals & Procurement - Sub Distribuition A Wing Panel - I Line Series 800A
167d 30.07
7/15/2025
3/12/2026
99
S&P - EDE - Subcontractor Submittals
28d 100.00 7/15/2025 A 8/21/2025 A
S&P - EDE - Subcontractor Submittals
100
S&P - EDE- AP Review
1d 100.00 8/21/2025 A 8/21/2025 A
S&P - EDE- AP Review
101
S&P - EDE - A/E Review and Approval
14d 100.00 8/21/2025 A 9/10/2025 A
102
S&P - EDE - Procurement
100d
10/17/2025
3/12/2026
Submittals & Procurement - Main Distribuition Mech Sub Panel B - I Line Series 1,200A
167d 30.07
7/15/2025
3/12/2026
103
S&P - EDE - Subcontractor Submittals
28d 100.00 7/15/2025 A 8/21/2025 A
S&P - EDE - Subcontractor Submittals
104
S&P - EDE- AP Review
1d 100.00 8/21/2025 A 8/21/2025 A
S&P - EDE- AP Review
105
S&P - EDE - A/E Review and Approval
14d 100.00 8/21/2025 A 9/10/2025 A
106
S&P - EDE - Procurement
100d
10/17/2025
Submittals & Procurement - LED Lighting
65d
12/29/2025 3/30/2026
107
S&P - EDE - Subcontractor Submittals
20d
12/29/2025
1/26/2026
108
S&P - EDE- AP Review
5d
1/27/2026
2/2/2026
109
S&P - EDE - A/E Review and Approval
10d
2/3/2026
2/16/2026
S&P - EDE - A/E Review and Approval
3/30/2026
S&P - EDE - Procurement
94
S&P - EDE - Procurement
30d
2/17/2026
95d
12/29/2025 5/11/2026
111
S&P - EDE - Subcontractor Submittals
20d
12/29/2025
1/26/2026
112
S&P - EDE- AP Review
5d
1/27/2026
2/2/2026
113
S&P - EDE - A/E Review and Approval
10d
2/3/2026
2/16/2026
114
S&P - EDE - Procurement
60d
2/17/2026
5/11/2026
110d
10/22/2025 3/31/2026
Submittals & Procurement - Division 8
S&P - EDE - A/E Review and Approval
S&P - EDE - Procurement
S&P - EDE - A/E Review and Approval
S&P - EDE - Procurement
S&P - EDE - A/E Review and Approval
3/12/2026
Submittals & Procurement - Lighting Control Equipment
110
S&P - EDE - Procurement
Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School
S&P - EDE - Procurement
S&P - EDE - Subcontractor Submittals
S&P - EDE- AP Review
S&P - EDE - Subcontractor Submittals
S&P - EDE- AP Review
S&P - EDE - A/E Review and Approval
S&P - EDE - Procurement
Rev. date: 10/17/2025 10:27:32 AM Job #: Southern Hills Middle School
Data Date: 10/17/2025
Page 5 of 14
3. Print View Filter: No Summary Tasks
Line
Name
Duration APC
Start
Finish
Submittals & Procurement - HM Doors and Hardware
110d
10/22/2025 3/31/2026
115
S&P - HMDH- Subcontractor Submittals
20d
10/22/2025 11/18/2025
116
S&P - HMDH- AP Review
5d
11/19/2025 11/25/2025
117
S&P - HMDH- A/E Review and Approval
10d
11/26/2025 12/11/2025
118
S&P - HMDH- Procurement
75d
12/12/2025
Submittals & Procurement - Casework
105d
10/22/2025 3/24/2026
Submittals & Procurement - Casework
105d
10/22/2025 3/24/2026
119
S&P - CW- Subcontractor Submittals
20d
10/22/2025 11/18/2025
120
S&P - CW- AP Review
5d
11/19/2025 11/25/2025
121
S&P - CW- A/E Review and Approval
10d
11/26/2025
12/11/2025
122
S&P - CW- Procurement
70d
12/12/2025
3/24/2026
Submittals & Procurement - Graphics
100d
12/29/2025 5/18/2026
Submittals & Procurement - Graphics
100d
12/29/2025 5/18/2026
123
S&P - Graphic- Subcontractor Submittals
20d
12/29/2025
1/26/2026
124
S&P - Graphic- AP Review
5d
1/27/2026
2/2/2026
125
S&P - Graphic- A/E Review and Approval
10d
2/3/2026
2/16/2026
126
S&P - Graphic- Procurement
65d
2/17/2026
5/18/2026
Submittals & Procurement - Mechanical Equipment
150d
10/22/2025 5/27/2026
S&P - HMDH- Subcontractor Submittals
S&P - HMDH- AP Review
S&P - HMDH- A/E Review and Approval
3/31/2026
Submittals & Procurement - Sump Pumps
75d
12/29/2025 4/13/2026
127
S&P - SUMP- Subcontractor Submittals
20d
12/29/2025
1/26/2026
128
S&P - SUMP- AP Review
5d
1/27/2026
2/2/2026
129
S&P - SUMP- A/E Review and Approval
10d
2/3/2026
2/16/2026
130
S&P - SUMP- Procurement
40d
2/17/2026
4/13/2026
Submittals & Procurement - Dust Collector
150d
10/22/2025 5/27/2026
131
S&P - DC- Subcontractor Submittals
20d
10/22/2025 11/18/2025
132
S&P - DC- AP Review
5d
11/19/2025 11/25/2025
133
S&P - DC- A/E Review and Approval
10d
11/26/2025 12/11/2025
134
S&P - DC- AHJ Review and Approval
15d
12/12/2025
1/6/2026
135
S&P - DC- Procurement
100d
1/7/2026
5/27/2026
95d
12/29/2025 5/11/2026
Submittals & Procurement - All Other Submittals
2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5
Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School
S&P - HMDH- Procurement
S&P - CW- Subcontractor Submittals
S&P - CW- AP Review
S&P - CW- A/E Review and Approval
S&P - CW- Procurement
S&P - Graphic- Subcontractor Submittals
S&P - Graphic- AP Review
S&P - Graphic- A/E Review and Approval
S&P - Graphic- Procurement
S&P - SUMP- Subcontractor Submittals
S&P - SUMP- AP Review
S&P - SUMP- A/E Review and Approval
S&P - SUMP- Procurement
S&P - DC- Subcontractor Submittals
S&P - DC- AP Review
S&P - DC- A/E Review and Approval
S&P - DC- AHJ Review and Approval
S&P - DC- Procurement
Rev. date: 10/17/2025 10:27:32 AM Job #: Southern Hills Middle School
Data Date: 10/17/2025
Page 6 of 14
3. Print View Filter: No Summary Tasks
Line
Name
Duration APC
Start
Finish
136
S&P - Other - Subcontractor Submittals
20d
12/29/2025
1/26/2026
137
S&P - Other - AP Review
10d
1/27/2026
2/9/2026
138
S&P - Other - A/E Review and Approval
15d
2/10/2026
3/2/2026
139
S&P - Other - Procurement Board Dates
50d
3/3/2026
5/11/2026
146d 50.00
5/13/2025
12/9/2025
140
1st May Board Date
1d 100.00 5/13/2025 A 5/13/2025 A
141
2nd May Board Date
1d 100.00 5/27/2025 A 5/27/2025 A
142
Only November Board Date
1d
11/11/2025 * 11/11/2025
143
Only December Board Date
1d
12/9/2025 * 12/9/2025
Owner Key Dates
327d 50.00
4/18/2025
2025 Spring Break
5d 100.00 4/18/2025 A 4/24/2025 A
145
2025 End of School Year
1d 100.00 5/27/2025 A 5/27/2025 A
146
2025/2026 School Year Begin
1d 100.00
8/1/2025 A
147
2026 Spring Break
5d
3/23/2026 * 3/27/2026
148
2026 End of School Year
1d
5/26/2026 * 5/26/2026
149
2026/2027 School Year Begins
1d
8/3/2026 *
8/3/2026
135d
3/23/2026
9/30/2026
Site Mobilization
5d
5/11/2026
5/15/2026
Mob - Site mobilization
5d
5/11/2026
5/15/2026
Intierior Finish and Fittout
91d
3/23/2026
7/29/2026
Restroom Renovations
36d
5/26/2026
7/15/2026
150
S&P - Other - Subcontractor Submittals
S&P - Other - AP Review
S&P - Other - A/E Review and Approval
S&P - Other - Procurement
1st May Board Date
2nd May Board Date
Only November Board Date
Only December Board Date
8/3/2026
144
Construction
2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5
2025 Spring Break
2025 End of School Year
8/1/2025 A
2025/2026 School Year Begin
2026 Spring Break
2026 End of School Year
2026/2027 School Year Begins
Mob - Site mobilization
Restroom Renovations 118 & 117
35d
5/26/2026
7/14/2026
151
IFF-RR-MEP Safe off
1d
5/26/2026
5/26/2026
IFF-RR-MEP Safe off
152
IFF-RR-Clean Demo Flooring and Tile
3d
5/27/2026
5/29/2026
IFF-RR-Clean Demo Flooring and Tile
153
IFF-RR-Sawcut & Demo Concrete
2d
6/1/2026
6/2/2026
IFF-RR-Sawcut & Demo Concrete
154
IFF-RR-Underslab Plumbing
3d
6/3/2026
6/5/2026
IFF-RR-Underslab Plumbing
155
IFF-RR- Slab Patchbacks
1d
6/8/2026
6/8/2026
IFF-RR- Slab Patchbacks
156
IFF-RR-MEP Rough in
5d
6/9/2026
6/15/2026
IFF-RR-MEP Rough in
157
IFF-RR-Hang/Tape/Finish Drywall
6d
6/16/2026
6/23/2026
IFF-RR-Hang/Tape/Finish Drywall
158
IFF-RR-Prime and First Coat Lids
2d
6/24/2026
6/25/2026
IFF-RR-Prime and First Coat Lids
Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School
Rev. date: 10/17/2025 10:27:32 AM Job #: Southern Hills Middle School
Data Date: 10/17/2025
Page 7 of 14
3. Print View Filter: No Summary Tasks
Line
Name
Duration APC
Start
Finish
2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5
159
IFF-RR-Install Floor and Wall Tile
5d
6/26/2026
7/2/2026
IFF-RR-Install Floor and Wall Tile
160
IFF-RR-Install MEP Trim
3d
7/6/2026
7/8/2026
IFF-RR-Install MEP Trim
161
IFF-RR-Install Partitions
2d
7/6/2026
7/7/2026
IFF-RR-Install Partitions
162
IFF-RR-Install Accessories
2d
7/9/2026
7/10/2026
IFF-RR-Install Accessories
163
IFF-RR-Final Paint
3d
7/9/2026
7/13/2026
IFF-RR-Final Paint
164
IFF-SCI-Final Clean
1d
7/14/2026
7/14/2026
IFF-SCI-Final Clean
Restroom Renovations 137 & 139
35d
5/27/2026
7/15/2026
165
IFF-RR-MEP Safe off
1d
5/27/2026
5/27/2026
IFF-RR-MEP Safe off
166
IFF-RR-Clean Demo Flooring and Tile
3d
5/28/2026
6/1/2026
IFF-RR-Clean Demo Flooring and Tile
167
IFF-RR-Sawcut & Demo Concrete
2d
6/2/2026
6/3/2026
IFF-RR-Sawcut & Demo Concrete
168
IFF-RR-Underslab Plumbing
3d
6/4/2026
6/8/2026
IFF-RR-Underslab Plumbing
169
IFF-RR- Slab Patchbacks
1d
6/9/2026
6/9/2026
IFF-RR- Slab Patchbacks
170
IFF-RR-MEP Rough in
5d
6/10/2026
6/16/2026
IFF-RR-MEP Rough in
171
IFF-RR-Hang/Tape/Finish Drywall
6d
6/17/2026
6/24/2026
IFF-RR-Hang/Tape/Finish Drywall
172
IFF-RR-Prime and First Coat Lids
2d
6/25/2026
6/26/2026
IFF-RR-Prime and First Coat Lids
173
IFF-RR-Install Floor and Wall Tile
5d
6/29/2026
7/6/2026
174
IFF-RR-Install MEP Trim
3d
7/7/2026
7/9/2026
IFF-RR-Install MEP Trim
175
IFF-RR-Install Partitions
2d
7/7/2026
7/8/2026
IFF-RR-Install Partitions
176
IFF-RR-Install Accessories
2d
7/10/2026
7/13/2026
IFF-RR-Install Accessories
177
IFF-RR-Final Paint
3d
7/10/2026
7/14/2026
IFF-RR-Final Paint
178
IFF-SCI-Final Clean
1d
7/15/2026
7/15/2026
IFF-SCI-Final Clean
Electrical Upgrades
82d
3/23/2026
7/16/2026
Electrical Upgrades - Panel G
8d
5/26/2026
6/4/2026
179
IFF-EU-Shut Down and Safeoff MDC
1d
5/26/2026
5/26/2026
IFF-EU-Shut Down and Safeoff MDC
180
IFF-EU-Demo Panel G
1d
5/27/2026
5/27/2026
IFF-EU-Demo Panel G
181
IFF-EU-Install New Panel G
3d
5/28/2026
6/1/2026
IFF-EU-Install New Panel G
182
IFF-EU-Test and Inspect
2d
6/2/2026
6/3/2026
IFF-EU-Test and Inspect
183
IFF-EU-Energize MDC
1d
6/4/2026
6/4/2026
IFF-EU-Energize MDC
Electrical Upgrades - Panel UV2
8d
7/7/2026
7/16/2026
IFF-EU-Shut Down and Safeoff MDC
1d
7/7/2026
7/7/2026
184
Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School
IFF-RR-Install Floor and Wall Tile
IFF-EU-Shut Down and Safeoff MDC
Rev. date: 10/17/2025 10:27:33 AM Job #: Southern Hills Middle School
Data Date: 10/17/2025
Page 8 of 14
3. Print View Filter: No Summary Tasks
Line
Name
Duration APC
Start
Finish
2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5
185
IFF-EU-Demo Panel UV2
1d
7/8/2026
7/8/2026
IFF-EU-Demo Panel UV2
186
IFF-EU-Install New Panel UV2
3d
7/9/2026
7/13/2026
IFF-EU-Install New Panel UV2
187
IFF-EU-Test and Inspect
2d
7/14/2026
7/15/2026
IFF-EU-Test and Inspect
IFF-EU-Energize MDC
IFF-EU-Energize MDC
1d
7/16/2026
7/16/2026
Electrical Upgrades - Panel K
8d
6/9/2026
6/18/2026
189
IFF-EU-Shut Down and Safeoff MDC
1d
6/9/2026
6/9/2026
IFF-EU-Shut Down and Safeoff MDC
190
IFF-EU-Demo Panel K
1d
6/10/2026
6/10/2026
IFF-EU-Demo Panel K
191
IFF-EU-Install New Panel K
3d
6/11/2026
6/15/2026
IFF-EU-Install New Panel K
192
IFF-EU-Test and Inspect
2d
6/16/2026
6/17/2026
IFF-EU-Test and Inspect
193
IFF-EU-Energize MDC
1d
6/18/2026
6/18/2026
IFF-EU-Energize MDC
Electrical Upgrades - Panel UV1
8d
7/7/2026
7/16/2026
194
IFF-EU-Shut Down and Safeoff MDC
1d
7/7/2026
7/7/2026
IFF-EU-Shut Down and Safeoff MDC
195
IFF-EU-Demo Panel UV1
1d
7/8/2026
7/8/2026
IFF-EU-Demo Panel UV1
196
IFF-EU-Install New Panel UV1
3d
7/9/2026
7/13/2026
IFF-EU-Install New Panel UV1
197
IFF-EU-Test and Inspect
2d
7/14/2026
7/15/2026
IFF-EU-Test and Inspect
198
IFF-EU-Energize MDC
1d
7/16/2026
7/16/2026
IFF-EU-Energize MDC
Electrical Upgrades - Panel A
8d
7/7/2026
7/16/2026
199
IFF-EU-Shut Down and Safeoff MDC
1d
7/7/2026
7/7/2026
IFF-EU-Shut Down and Safeoff MDC
200
IFF-EU-Demo Panel A
1d
7/8/2026
7/8/2026
IFF-EU-Demo Panel A
201
IFF-EU-Install New Panel A
3d
7/9/2026
7/13/2026
IFF-EU-Install New Panel A
202
IFF-EU-Test and Inspect
2d
7/14/2026
7/15/2026
IFF-EU-Test and Inspect
203
IFF-EU-Energize MDC
1d
7/16/2026
7/16/2026
IFF-EU-Energize MDC
Electrical Upgrades - Panel B
8d
7/7/2026
7/16/2026
204
IFF-EU-Shut Down and Safeoff MDC
1d
7/7/2026
7/7/2026
IFF-EU-Shut Down and Safeoff MDC
205
IFF-EU-Demo Panel B
1d
7/8/2026
7/8/2026
IFF-EU-Demo Panel B
206
IFF-EU-Install New Panel B
3d
7/9/2026
7/13/2026
IFF-EU-Install New Panel B
207
IFF-EU-Test and Inspect
2d
7/14/2026
7/15/2026
IFF-EU-Test and Inspect
208
IFF-EU-Energize MDC
1d
7/16/2026
7/16/2026
IFF-EU-Energize MDC
Electrical Upgrades - Panel E
8d
7/7/2026
7/16/2026
IFF-EU-Shut Down and Safeoff MDC
1d
7/7/2026
7/7/2026
188
209
Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School
IFF-EU-Shut Down and Safeoff MDC
Rev. date: 10/17/2025 10:27:33 AM Job #: Southern Hills Middle School
Data Date: 10/17/2025
Page 9 of 14
3. Print View Filter: No Summary Tasks
Line
Name
Duration APC
Start
Finish
2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5
210
IFF-EU-Demo Panel E
1d
7/8/2026
7/8/2026
IFF-EU-Demo Panel E
211
IFF-EU-Install New Panel E
3d
7/9/2026
7/13/2026
IFF-EU-Install New Panel E
212
IFF-EU-Test and Inspect
2d
7/14/2026
7/15/2026
IFF-EU-Test and Inspect
IFF-EU-Energize MDC
IFF-EU-Energize MDC
1d
7/16/2026
7/16/2026
Electrical Upgrades - Panel F
8d
7/7/2026
7/16/2026
214
IFF-EU-Shut Down and Safeoff MDC
1d
7/7/2026
7/7/2026
IFF-EU-Shut Down and Safeoff MDC
215
IFF-EU-Demo Panel F
1d
7/8/2026
7/8/2026
IFF-EU-Demo Panel F
216
IFF-EU-Install New Panel F
3d
7/9/2026
7/13/2026
IFF-EU-Install New Panel F
217
IFF-EU-Test and Inspect
2d
7/14/2026
7/15/2026
IFF-EU-Test and Inspect
218
IFF-EU-Energize MDC
1d
7/16/2026
7/16/2026
IFF-EU-Energize MDC
Electrical Upgrades - Panel N
8d
7/7/2026
7/16/2026
219
IFF-EU-Shut Down and Safeoff MDC
1d
7/7/2026
7/7/2026
IFF-EU-Shut Down and Safeoff MDC
220
IFF-EU-Demo Panel N
1d
7/8/2026
7/8/2026
IFF-EU-Demo Panel N
221
IFF-EU-Install New Panel N
3d
7/9/2026
7/13/2026
IFF-EU-Install New Panel N
222
IFF-EU-Test and Inspect
2d
7/14/2026
7/15/2026
IFF-EU-Test and Inspect
223
IFF-EU-Energize MDC
1d
7/16/2026
7/16/2026
IFF-EU-Energize MDC
Electrical Upgrades - Panel J
8d
6/2/2026
6/11/2026
224
IFF-EU-Shut Down and Safeoff MDC
1d
6/2/2026
6/2/2026
IFF-EU-Shut Down and Safeoff MDC
225
IFF-EU-Demo J
1d
6/3/2026
6/3/2026
IFF-EU-Demo J
226
IFF-EU-Install New J
3d
6/4/2026
6/8/2026
IFF-EU-Install New J
227
IFF-EU-Test and Inspect
2d
6/9/2026
6/10/2026
IFF-EU-Test and Inspect
228
IFF-EU-Energize MDC
1d
6/11/2026
6/11/2026
IFF-EU-Energize MDC
Electrical Upgrades - Shop Main & Shop Sub
10d
6/16/2026
6/29/2026
229
IFF-EU-Shut Down and Safeoff MDC
1d
6/16/2026
6/16/2026
IFF-EU-Shut Down and Safeoff MDC
230
IFF-EU-Demo Shop Main & Sub
1d
6/17/2026
6/17/2026
IFF-EU-Demo Shop Main & Sub
231
IFF-EU-Install New Shop Main & Sub
5d
6/18/2026
6/24/2026
IFF-EU-Install New Shop Main & Sub
232
IFF-EU-Test and Inspect
2d
6/25/2026
6/26/2026
IFF-EU-Test and Inspect
IFF-EU-Energize MDC
213
233
234
IFF-EU-Energize MDC
1d
6/29/2026
6/29/2026
Electrical Upgrades - Sub Distribution A Wing - I Line 800A
10d
6/16/2026
6/29/2026
IFF-EU-Shut Down and Safeoff MDC
1d
6/16/2026
6/16/2026
Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School
IFF-EU-Shut Down and Safeoff MDC
Rev. date: 10/17/2025 10:27:33 AM Job #: Southern Hills Middle School
Data Date: 10/17/2025
Page 10 of 14
3. Print View Filter: No Summary Tasks
Line
Name
Duration APC
Start
Finish
2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5
235
IFF-EU-Demo A Wing
1d
6/17/2026
6/17/2026
236
IFF-EU-Install New A Wing
5d
6/18/2026
6/24/2026
IFF-EU-Install New A Wing
237
IFF-EU-Test and Inspect
2d
6/25/2026
6/26/2026
IFF-EU-Test and Inspect
IFF-EU-Energize MDC
IFF-EU-Demo A Wing
IFF-EU-Energize MDC
1d
6/29/2026
6/29/2026
Electrical Upgrades - Sub Distribution B Wing Mech - I Line 1200A
10d
6/25/2026
7/9/2026
239
IFF-EU-Shut Down and Safeoff MDC
1d
6/25/2026
6/25/2026
IFF-EU-Shut Down and Safeoff MDC
240
IFF-EU-Demo B Wing
1d
6/26/2026
6/26/2026
IFF-EU-Demo B Wing
241
IFF-EU-Install New B Wing
5d
6/29/2026
7/6/2026
IFF-EU-Install New B Wing
242
IFF-EU-Test and Inspect
2d
7/7/2026
7/8/2026
IFF-EU-Test and Inspect
243
IFF-EU-Energize MDC
1d
7/9/2026
7/9/2026
IFF-EU-Energize MDC
Fire Alarm Upgrades
59d
4/8/2026
6/30/2026
244
IFF-FAU-Early Fire Alarm Wire Pull (Spring Break Start Night Work)
20d
4/8/2026
5/5/2026
IFF-FAU-Early Fire Alarm Wire Pull (Spring Break Start Night Work)
245
IFF-FAU-EM Battery Pack Replacements (Night Work)
10d
4/22/2026
5/5/2026
IFF-FAU-EM Battery Pack Replacements (Night Work)
246
IFF-FAU-Install New Devices
5d
5/26/2026
6/1/2026
IFF-FAU-Install New Devices
247
IFF-FAU-Demo Old Panel
5d
5/26/2026
6/1/2026
IFF-FAU-Demo Old Panel
248
IFF-FAU-Install New Panel and Terminate
10d
6/2/2026
6/15/2026
249
IFF-FAU-Program Panel
5d
6/16/2026
6/22/2026
250
IFF-FAU-Test Fire Alarm Panel
6d
6/23/2026
6/30/2026
238
IFF-FAU-Install New Panel and Terminate
IFF-FAU-Program Panel
IFF-FAU-Test Fire Alarm Panel
PA/ Sound System Upgrades
78d
3/23/2026
7/10/2026
251
IFF-EU-Pull new Wire for Speakers (Spring Break Start Night work)
10d
3/23/2026
4/3/2026
252
IFF-EU-Install New Speakers
20d
5/26/2026
6/22/2026
IFF-EU-Install New Speakers
253
IFF-EU-Install New Head End
2d
6/23/2026
6/24/2026
IFF-EU-Install New Head End
254
IFF-EU-Test New Head End and Speakers
6d
6/25/2026
7/2/2026
255
IFF-EU-Final Clean
5d
7/6/2026
7/10/2026
CTE Upgrades
46d
5/26/2026
7/29/2026
Wood Shop
46d
5/26/2026
7/29/2026
256
IFF-WS-Owner Move
1d
5/26/2026
5/26/2026
IFF-WS-Owner Move
257
IFF-WS-MEP Safeoff
1d
5/26/2026
5/26/2026
IFF-WS-MEP Safeoff
258
IFF-WS-Abatement Demo & Dust collector
5d
5/27/2026
6/2/2026
IFF-WS-Abatement Demo & Dust collector
259
IFF-WS-Clean Demo Remaining Items
2d
6/3/2026
6/4/2026
IFF-WS-Clean Demo Remaining Items
Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School
IFF-EU-Pull new Wire for Speakers (Spring Break Start Night work)
IFF-EU-Test New Head End and Speakers
IFF-EU-Final Clean
Rev. date: 10/17/2025 10:27:33 AM Job #: Southern Hills Middle School
Data Date: 10/17/2025
Page 11 of 14
3. Print View Filter: No Summary Tasks
Line
Name
Duration APC
Start
Finish
2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5
260
IFF-WS-Route New Overhead MEP
4d
6/5/2026
6/10/2026
IFF-WS-Route New Overhead MEP
261
IFF-WS-Frame New Walls & Set Door Frames
2d
6/10/2026
6/11/2026
IFF-WS-Frame New Walls & Set Door Frames
262
IFF-WS-MEP Wall Rough in
3d
6/12/2026
6/16/2026
IFF-WS-MEP Wall Rough in
263
IFF-WS-Hang/ Tape/ Finish Drywall
6d
6/17/2026
6/24/2026
IFF-WS-Hang/ Tape/ Finish Drywall
264
IFF-WS-Prime and First Coat Walls &Ceilings
4d
6/25/2026
6/30/2026
IFF-WS-Prime and First Coat Walls &Ceilings
265
IFF-WS-Set and MEP Connections to Dust Collector
5d
7/1/2026
7/8/2026
IFF-WS-Set and MEP Connections to Dust Collector
266
IFF-WS-Install ACT Grid
2d
7/1/2026
7/2/2026
IFF-WS-Install ACT Grid
267
IFF-WS-MEP Ceiling Trim Out
3d
7/6/2026
7/8/2026
IFF-WS-MEP Ceiling Trim Out
268
IFF-WS-Refinish Wood Flooring
5d
7/6/2026
7/10/2026
IFF-WS-Refinish Wood Flooring
269
IFF-WS-Above Ceiling Inspections
2d
7/9/2026
7/10/2026
IFF-WS-Above Ceiling Inspections
270
IFF-WS-White out Ceilings
1d
7/13/2026
7/13/2026
IFF-WS-White out Ceilings
271
IFF-WS-Install Casework
5d
7/13/2026
7/17/2026
IFF-WS-Install Casework
272
IFF-WS-Final Clean
3d
7/14/2026
7/16/2026
IFF-WS-Final Clean
273
IFF-WS-Dust Collector & EF Start up
2d
7/17/2026
7/20/2026
IFF-WS-Dust Collector & EF Start up
274
IFF-WS-Final Clean
1d
7/20/2026
7/20/2026
IFF-WS-Final Clean
275
IFF-WS-Final Paint
2d
7/21/2026
7/22/2026
IFF-WS-Final Paint
276
IFF-WS-Install Carpet and Base
2d
7/23/2026
7/24/2026
IFF-WS-Install Carpet and Base
277
IFF-WS-Install Doors & Hardware
3d
7/27/2026
7/29/2026
IFF-WS-Install Doors & Hardware
Culinary Arts
18d
5/26/2026
6/18/2026
278
IFF-CA-Owner Move
1d
5/26/2026
5/26/2026
IFF-CA-Owner Move
279
IFF-CA-MEP Safeoff
1d
5/28/2026
5/28/2026
IFF-CA-MEP Safeoff
280
IFF-CA-Demo Section of Flooring and Sawcut
3d
5/29/2026
6/2/2026
IFF-CA-Demo Section of Flooring and Sawcut
281
IFF-CA-Demo ADA Work
2d
5/29/2026
6/1/2026
IFF-CA-Demo ADA Work
282
IFF-CA-Install New Casework
3d
6/2/2026
6/4/2026
IFF-CA-Install New Casework
283
IFF-CA-Underground Plumbing
4d
6/3/2026
6/8/2026
IFF-CA-Underground Plumbing
284
IFF-CA-MEP Wall Casework Trim
2d
6/5/2026
6/8/2026
IFF-CA-MEP Wall Casework Trim
285
IFF-CA-Concrete Patchback
1d
6/9/2026
6/9/2026
IFF-CA-Concrete Patchback
286
IFF-CA-Paint Ceiling
5d
6/9/2026
6/15/2026
IFF-CA-Paint Ceiling
287
IFF-CA-Install New Flooring and Base
2d
6/16/2026
6/17/2026
IFF-CA-Install New Flooring and Base
288
IFF-CA-Final Clean
1d
6/18/2026
6/18/2026
IFF-CA-Final Clean
Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School
Rev. date: 10/17/2025 10:27:33 AM Job #: Southern Hills Middle School
Data Date: 10/17/2025
Page 12 of 14
3. Print View Filter: No Summary Tasks
Line
Name
2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5
Duration APC
Start
Finish
Art Room
39d
5/26/2026
7/20/2026
289
IFF-AR-Owner Move
1d
5/26/2026
5/26/2026
IFF-AR-Owner Move
290
IFF-AR-MEP Safeoff
1d
5/27/2026
5/27/2026
IFF-AR-MEP Safeoff
291
IFF-AR-Abatement Demo
5d
5/28/2026
6/3/2026
IFF-AR-Abatement Demo
292
IFF-AR-Demo Remaining Items
2d
6/4/2026
6/5/2026
IFF-AR-Demo Remaining Items
293
IFF-AR-Sawcut and Demo Concrete for Sinks
3d
6/8/2026
6/10/2026
IFF-AR-Sawcut and Demo Concrete for Sinks
294
IFF-AR-Install Underground Plumbing
4d
6/11/2026
6/16/2026
IFF-AR-Install Underground Plumbing
295
IFF-AR-FF/R/P Concrete at Sinks
2d
6/16/2026
6/17/2026
IFF-AR-FF/R/P Concrete at Sinks
296
IFF-AR-MEP Wall Rough in
3d
6/18/2026
6/22/2026
IFF-AR-MEP Wall Rough in
297
IFF-AR-Hang/ Tape/ Finish Drywall
6d
6/23/2026
6/30/2026
IFF-AR-Hang/ Tape/ Finish Drywall
298
IFF-AR-Prime and First Coat Walls
2d
6/29/2026
6/30/2026
IFF-AR-Prime and First Coat Walls
299
IFF-AR-Paint Ceiling
2d
7/1/2026
7/2/2026
IFF-AR-Paint Ceiling
300
IFF-AR-Above Ceiling Inspections
2d
7/6/2026
7/7/2026
IFF-AR-Above Ceiling Inspections
301
IFF-AR-White out Ceilings
1d
7/8/2026
7/8/2026
IFF-AR-White out Ceilings
302
IFF-AR-MEP Wall Trim out
3d
7/9/2026
7/13/2026
IFF-AR-MEP Wall Trim out
303
IFF-AR-Final Paint
2d
7/14/2026
7/15/2026
IFF-AR-Final Paint
304
IFF-AR-Install Carpet and Base
2d
7/16/2026
7/17/2026
IFF-AR-Install Carpet and Base
305
IFF-AR-Final Clean
1d
7/20/2026
7/20/2026
IFF-AR-Final Clean
Cafeteria Upgrades
16d
5/26/2026
6/16/2026
306
IFF-CU-Owner Move
1d
5/26/2026
5/26/2026
307
IFF-CU-Abatement of Flooring
6d
5/27/2026
6/3/2026
IFF-CU-Abatement of Flooring
308
IFF-CU-Paint Ceiling
4d
6/4/2026
6/9/2026
IFF-CU-Paint Ceiling
309
IFF-CU-Install Flooring and Base
4d
6/10/2026
6/15/2026
IFF-CU-Install Flooring and Base
310
IFF-CU-Final Clean
1d
6/16/2026
6/16/2026
IFF-CU-Final Clean
Mechanical Upgrades
12d
5/26/2026
6/10/2026
Sump Pump Replacement
12d
5/26/2026
6/10/2026
311
IFF-SP-MEP Safeoff Sump Pump
2d
5/26/2026
5/27/2026
IFF-SP-MEP Safeoff Sump Pump
312
IFF-SP-Evacuate Existing Material From Pit
2d
5/28/2026
5/29/2026
IFF-SP-Evacuate Existing Material From Pit
313
IFF-SP-Install New Sump Pump
2d
6/1/2026
6/2/2026
IFF-SP-Install New Sump Pump
314
IFF-SP-Hook up Electrical
2d
6/3/2026
6/4/2026
IFF-SP-Hook up Electrical
Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School
IFF-CU-Owner Move
Rev. date: 10/17/2025 10:27:33 AM Job #: Southern Hills Middle School
Data Date: 10/17/2025
Page 13 of 14
3. Print View Filter: No Summary Tasks
Line
Name
315 316
2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5
Duration APC
Start
Finish
IFF-SP-Hook up Controls
2d
6/5/2026
6/8/2026
IFF-SP-Hook up Controls
IFF-SP- Test Controls
2d
6/9/2026
6/10/2026
IFF-SP- Test Controls
Roof Install and Improvements
33d
5/26/2026
7/10/2026
317
EFI-RII-Demo Roofs and Install EF's
2d
5/26/2026
5/27/2026
EFI-RII-Demo Roofs and Install EF's
318
EFI-RII-Set New EF's
3d
5/28/2026
6/1/2026
EFI-RII-Set New EF's
319
EFI-RII-MEP Connections to EF's
5d
7/6/2026
7/10/2026
Site Improvments
37d
5/26/2026
7/16/2026
Parking Lot
37d
5/26/2026
7/16/2026
EFI-RII-MEP Connections to EF's
Parking Lot Improvements
37d
5/26/2026
7/16/2026
320
SI-PL-Demo Concrete Walks
10d
5/26/2026
6/8/2026
SI-PL-Demo Concrete Walks
321
SI-PL-F/R/P Concrete
7d
6/9/2026
6/17/2026
SI-PL-F/R/P Concrete
322
SI-PL-Cure Time Before Paint
15d
6/18/2026
7/9/2026
SI-PL-Cure Time Before Paint
323
SI-PL-Stripe New Parking Lot
2d
7/10/2026
7/13/2026
SI-PL-Stripe New Parking Lot
324
SI-PL-Final Clean
3d
7/14/2026
7/16/2026
SI-PL-Final Clean
2026 Closeout
53d
7/17/2026
9/30/2026
325
2026-CO-Site Punchwalk
1d
7/17/2026
7/17/2026
2026-CO-Site Punchwalk
326
2026-CO-Final MEP Inspections
1d
7/21/2026
7/21/2026
2026-CO-Final MEP Inspections
327
2026-CO-Final Clean
5d
7/21/2026
7/27/2026
2026-CO-Final Clean
328
2026-CO- MEP TAB
3d
7/28/2026
7/30/2026
2026-CO- MEP TAB
329
2026-CO-Punch Walks
1d
7/28/2026
7/28/2026
2026-CO-Punch Walks
330
2026-CO-MEP Commissioning
2d
7/31/2026
8/3/2026
2026-CO-MEP Commissioning
331
2026-CO-TCO Inspections
1d
7/31/2026
7/31/2026
2026-CO-TCO Inspections
332
2026-CO-Owner Move In
1d
8/3/2026
8/3/2026
2026-CO-Owner Move In
333
2026-CO-Construction Final Completion of Documentation
41d
8/4/2026
9/30/2026
Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School
2026-CO-Construction Final Completion of Documentation
Rev. date: 10/17/2025 10:27:33 AM Job #: Southern Hills Middle School
Data Date: 10/17/2025
Page 14 of 14
3. Print View Filter: No Summary Tasks
Exhibit E
Insurance Certificate Itemization of Cost Itemization of the GMP Dollars requested for long lead equipment and material packages
Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20
Policy Number: AS2-641-445189-013 Issued By: Liberty Mutual Fire Insurance Co.
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. NOTICE OF CANCELLATION TO THIRD PARTIES This endorsement modifies insurance provided under the following: BUSINESS AUTO COVERAGE PART MOTOR CARRIER COVERAGE PART GARAGE COVERAGE PART TRUCKERS COVERAGE PART EXCESS AUTOMOBILE LIABILITY INDEMNITY COVERAGE PART SELF-INSURED TRUCKER EXCESS LIABILITY COVERAGE PART COMMERCIAL GENERAL LIABILITY COVERAGE PART EXCESS COMMERCIAL GENERAL LIABILITY COVERAGE PART PRODUCTS/COMPLETED OPERATIONS LIABILITY COVERAGE PART LIQUOR LIABILITY COVERAGE PART
Schedule Name of Other Person(s)/ Organization(s): Per schedule on file
Email Address or mailing address: Per schedule on file
Number Days Notice: 45
A. If we cancel this policy for any reason other than nonpayment of premium, we will notify the persons or organizations shown in the Schedule above. We will send notice to the email or mailing address listed above at least 10 days, or the number of days listed above, if any, before the cancellation becomes effective. In no event does the notice to the third party exceed the notice to the first named insured. B. This advance notification of a pending cancellation of coverage is intended as a courtesy only. Our failure to provide such advance notification will not extend the policy cancellation date nor negate cancellation of the policy. All other terms and conditions of this policy remain unchanged.
LIM 99 01 05 11
© 2011, Liberty Mutual Group of Companies. All rights reserved. Includes copyrighted material of Insurance Services Office, Inc. with its permission.
Page 1 of 1
Policy Number EB2-641-445189-023 Issued by Liberty Mutual Fire Insurance Company THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. NOTICE OF CANCELLATION TO THIRD PARTIES This endorsement modifies insurance provided under the following: BUSINESS AUTO COVERAGE PART MOTOR CARRIER COVERAGE PART GARAGE COVERAGE PART TRUCKERS COVERAGE PART EXCESS AUTOMOBILE LIABILITY INDEMNITY COVERAGE PART SELF-INSURED TRUCKER EXCESS LIABILITY COVERAGE PART COMMERCIAL GENERAL LIABILITY COVERAGE PART EXCESS COMMERCIAL GENERAL LIABILITY COVERAGE PART PRODUCTS/COMPLETED OPERATIONS LIABILITY COVERAGE PART LIQUOR LIABILITY COVERAGE PART COMMERCIAL LIABILITY – UMBRELLA COVERAGE FORM
Schedule Name of Other Person(s) / Organization(s):
Email Address or mailing address:
Number Days Notice:
Per schedule on file with Broker
Per schedule on file with Broker
45
A. If we cancel this policy for any reason other than nonpayment of premium, we will notify the persons or organizations shown in the Schedule above. We will send notice to the email or mailing address listed above at least 10 days, or the number of days listed above, if any, before the cancellation becomes effective. In no event does the notice to the third party exceed the notice to the first named insured. B. This advance notification of a pending cancellation of coverage is intended as a courtesy only. Our failure to provide such advance notification will not extend the policy cancellation date nor negate cancellation of the policy. All other terms and conditions of this policy remain unchanged.
LIM 99 01 05 11
© 2011 Liberty Mutual Group of Companies. All rights reserved. Includes copyrighted material of Insurance Services Office, Inc., with its permission.
Page 1 of 1
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
DESIGNATED CONSTRUCTION PROJECT(S) GENERAL AGGREGATE LIMIT This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART SCHEDULE Designated Construction Project(s): All construction projects not located at premises owned, leased or rented by a Named Insured.
Information required to complete this Schedule, if not shown above, will be shown in the Declarations. A. For all sums which the insured becomes legally obligated to pay as damages caused by "occurrences" under Section I – Coverage A, and for all medical expenses caused by accidents under Section I – Coverage C, which can be attributed only to ongoing operations at a single designated construction project shown in the Schedule above: 1. A separate Designated Construction Project General Aggregate Limit applies to each designated construction project, and that limit is equal to the amount of the General Aggregate Limit shown in the Declarations. 2. The Designated Construction Project General Aggregate Limit is the most we will pay for the sum of all damages under Coverage A, except damages because of "bodily injury" or "property damage" included in the "productscompleted operations hazard", and for medical expenses under Coverage C regardless of the number of:
3. Any payments made under Coverage A for damages or under Coverage C for medical expenses shall reduce the Designated Construction Project General Aggregate Limit for that designated construction project. Such payments shall not reduce the General Aggregate Limit shown in the Declarations nor shall they reduce any other Designated Construction Project General Aggregate Limit for any other designated construction project shown in the Schedule above. 4. The limits shown in the Declarations for Each Occurrence, Damage To Premises Rented To You and Medical Expense continue to apply. However, instead of being subject to the General Aggregate Limit shown in the Declarations, such limits will be subject to the applicable Designated Construction Project General Aggregate Limit.
a. Insureds; b. Claims made or "suits" brought; or c. Persons or organizations making claims or bringing "suits".
CG 25 03 05 09
© Insurance Services Office, Inc., 2008
Page 1 of 2
B. For all sums which the insured becomes legally obligated to pay as damages caused by "occurrences" under Section I – Coverage A, and for all medical expenses caused by accidents under Section I – Coverage C, which cannot be attributed only to ongoing operations at a single designated construction project shown in the Schedule above: 1. Any payments made under Coverage A for damages or under Coverage C for medical expenses shall reduce the amount available under the General Aggregate Limit or the Products-completed Operations Aggregate Limit, whichever is applicable; and 2. Such payments shall not reduce any Designated Construction Project General Aggregate Limit.
Page 2 of 2
C. When coverage for liability arising out of the "products-completed operations hazard" is provided, any payments for damages because of "bodily injury" or "property damage" included in the "products-completed operations hazard" will reduce the Products-completed Operations Aggregate Limit, and not reduce the General Aggregate Limit nor the Designated Construction Project General Aggregate Limit. D. If the applicable designated construction project has been abandoned, delayed, or abandoned and then restarted, or if the authorized contracting parties deviate from plans, blueprints, designs, specifications or timetables, the project will still be deemed to be the same construction project. E. The provisions of Section III – Limits Of Insurance not otherwise modified by this endorsement shall continue to apply as stipulated.
© Insurance Services Office, Inc., 2008
CG 25 03 05 09
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
ADDITIONAL INSURED – OWNERS, LESSEES OR CONTRACTORS – SCHEDULED PERSON OR ORGANIZATION This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART SCHEDULE
Name of Person or Organization: Any person or organization with whom you have agreed, through written contract, agreement or permit to provide additional insured coverage but only where this specific edition of the form is contractually required. Locations: Any location where you have agreed, through written, contract, agreement or permit, to provide additional insured coverage for on-going operations
(If no entry appears above, information required to complete this endorsement will be shown in the Declarations as applicable to this endorsement.) A. Section II – Who Is An Insured is amended to include as an insured the person or organization shown in the Schedule, but only with respect to liability arising out of your ongoing operations performed for that insured. B. With respect to the insurance afforded to these additional insureds, the following exclusion is added: 2. Exclusions
(1) All work, including materials, parts or equipment furnished in connection with such work, on the project (other than service, maintenance or repairs) to be performed by or on behalf of the additional insured(s) at the site of the covered operations has been completed; or
This insurance does not apply to "bodily injury" or "property damage" occurring after:
CG 20 10 10 01
© ISO Properties, Inc., 2000
Page 1 of 2
(2) That portion of "your work" out of which the injury or damage arises has been put to its intended use by any person or organization other than another contractor or subcontractor engaged in performing operations for a principal as a part of the same project.
This endorsement is executed by the Premium $ Effective Date
Expiration Date
For attachment to Policy No. EB2-641-445189-023 Audit Basis Issued To
Countersigned by Authorized Representative
Issued
Page 2 of 2
Sales Office and No.
© ISO Properties, Inc., 2000
End. Serial No.
CG 20 10 10 01
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
ADDITIONAL INSURED – OWNERS, LESSEES OR CONTRACTORS – COMPLETED OPERATIONS This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART SCHEDULE Name of Person or Organization: Any person or organization to whom or to which you are required to provide additional insured status in a written contract, agreement or permit except where such contract or agreement is prohibited, but only where this specific edition of the form is contractually required. Location And Description of Completed Operations: Any location where you have agreed, through written, contract, agreement or permit, to provide additional insured coverage for completed operations Additional Premium:
(If no entry appears above, information required to complete this endorsement will be shown in the Declarations as applicable to this endorsement.) Section II – Who Is An Insured is amended to include as an insured the person or organization shown in the Schedule, but only with respect to liability arising out of "your work" at the location designated and described in the schedule of this endorsement performed for that insured and included in the "products-completed operations hazard".
This endorsement is executed by the Premium $ Effective Date
Expiration Date
For attachment to Policy No.EB2-641-445189-023
TB2-641-445189-028 Audit Basis Issued To
Countersigned by Authorized Representative
Issued
CG 20 37 10 01
Sales Office and No.
© ISO Properties, Inc., 2000
End. Serial No.
Page 1 of 1
WA2-64D-445189-063
03/01/2023
WC2-641-445189-073
Exhibit F
Performance Bond Itemization ofGMP Cost Itemization of the Performance Bond will befor provided afterequipment amendment and & change orderpackages for the GMP Dollars requested long lead material total amount. This will be provided once amendment two is executed.
Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20
Exhibit G
Labor and Material Payment Bond Itemization ofGMP Cost Itemization of the Labor and Material Payment Bond lead will beequipment provided after amendment & change order Dollars requested for long and material packages for the GMP total amount. This will be provided once amendment two is executed.
Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20
Exhibit H Alternates Prices
Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20
8
9
10
11
12
13
16
17
24
25
Price Options List K1224 - BVSD - Southern Hills Middle School Current Cost Estimate Target Budget
$2,723,427 Pending Cost Reduction $2,306,101
Delta (Overrun)
#REF!
$417,326
$194,670 Item Number
Date
Description of Item
Status
Pending Cost Reduction
Pending Cost Addition
$243,814 Accepted Cost
Rejected Cost
Comments
Decision Date
Alternates 001
10/17/2025 Alternate 1 - Replace corridor finishes on Level 1 and 2)
Rejected
002
10/17/2025 Alternate 2 - Admin Suite Paint Refresh
Pending
$112,971
10/24/2025
$4,266
003
10/17/2025 Alternate 3 - Replace Additional Electrical Panels
Accepted
Included in Current Cost
10/24/2025
004
10/17/2025 Alternate 4 - Replace Intercom System
Accepted
Included in Current Cost
10/24/2025
005
10/17/2025 Alternate 5 - Replace Food Lab Casework
Pending
$117,772
006
10/17/2025 Alternate 6 - Stair West of Plaza
Pending
$39,896
007
10/17/2025 Alternate 7 (CTE 1.2 - Added Window)
Rejected
One water spray test is include for the $38,636 window replacement.
10/24/2025 10/24/2025 10/24/2025
008
10/17/2025 Alternate 9 - New Window at Wood Shop
Rejected
One water spray test is include for the $36,378 window replacement.
009
10/17/2025 Alternate 10 - New Lockers
Rejected
$37,779
010
10/17/2025 Alternate 11 - Sump Pump
Rejected
$18,050
011
10/17/2025 Alternate 12 - Art Room Light Fixture
Pending
012
10/17/2025 Alternate 13 - Kiln
Pending
$8,291
013
10/17/2025 Alternate 14 - LVT Entire Food Lab
Pending
$16,677
014
10/17/2025 Alternate 15 - Hot Dip Galv Exterior Steel ILO HM Primer/Paint
Pending
015
10/17/2025 Alternate 16 - Exterior Site Plaza
Accepted
10/24/2025 AP is working on a revised price based on a less costly fixture.
$7,761
No Difference in Price for Hot Dip Galv. Included in Current Cost
10/24/2025
Exhibit IH Alternates Prices Unit Prices This exhibit is not applicable at this time.
Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20
Exhibit J H Alternates Prices Allowances
Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20
Allowances Report DESCRIPTION
QTY UOM
UNIT PRICE
TOTAL COST
NOTES / COMMENTS
ALLOWANCES: Building 05 Metals
$2,043
05 50 00 Metal Fabrications 05505 Access Fixed Ladders - Exterior Renewal Allowance
$2,043 1.00 allow
2,043.00
Subtotal 05 50 00 Metal Fabrications
$2,043 $2,043
Subtotal 05 Metals
$2,043
06 Woods, Plastics and Composites
$5,000
06 22 00 Finish Carpentry 06455 Food Lab Casework Repair Allowance
$5,000 1.00 allow
5,000.00
Subtotal 06 22 00 Finish Carpentry
$5,000
$5,000
09 Finishes
$25,000
09 90 00 Painting and Coating
$25,000 1.00 allow
25,000.00
Subtotal 09 90 00 Painting and Coating
$25,000
$25,000
32 Exterior Improvements
$2,745
32 13 00 Rigid Paving
$2,745 1.00 allow
2,745.00
$2,745
Subtotal 32 13 00 Rigid Paving
$2,745
Subtotal 32 Exterior Improvements
$2,745
TOTAL ALLOWANCES: Building
DATE PRINTED: 10/29/2025
Allowance
$25,000
Subtotal 09 Finishes
32159 Exterior Wall - Damaged Concrete Allowance
Allowance
$5,000
Subtotal 06 Woods, Plastics and Composites
09700 Branding Graphic Allowance
Allowance
Allowance
$34,788
Page 4 of 20
Exhibit K
Load Hourly Labor Rate Itemization of CostSchedule Itemization of the GMP This for exhibit not applicable at this time. Dollars requested longis lead equipment and material packages
Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20
Exhibit L
Equipment Rental Rate Schedule Itemization of Cost Itemization of the GMP Dollars requested for long lead equipment and material packages
Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20
Category Bobcat Bobcat Bobcat Bobcat Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Cleaning Equipment Cleaning Equipment Concrete Concrete Concrete Concrete Concrete Concrete Concrete Concrete Concrete Concrete Concrete Concrete Concrete Concrete Fencing Fencing Fencing Forklift Forklift Forklift Forklift
Description Bobcat Bobcat T190 Telehandler Bobcat E35 Mini-Ex Bobcat Breaker (Jackhammer) Bobcat Auger attachment drive unit lowe 1650E Bobcat Auger Bit (6" - 36") Bobcat Auger Extension (2'-4') Bobcat Forks Bobcat Rock Screen Bucket Bobcat Smooth bucket Bobcat Snow blower SR117 Caterpillar Bobcat Snow Broom Bobcat Snow Bucket Bobcat Snow Plow Caterpillar ANGLE BLADE 72IN Bobcat Sweeper Bobcat Tooth bucket Bobcat Trench Compactor Bobcat Vibratory Compactor for E35 Mini-Ex only Implement Rack Floor Buffer Floor Machine scrubber (Riding) Concrete Core Driller Concrete Georgia Buggy (Track, 14 cu-ft) Concrete Georgia Buggy (Electric, Wheeled, 12 cu-ft) Concrete Mixer Concrete Power Trowels - Walk behind Concrete Saw - Walk behind Concrete Soft Cut Saw Concrete Vibrator - high cycle Demo Saw Eco Pan Grout Pump Jumping jack Plate Compactor Rebar Cage Stands Fence Standard 6x12' per panel (.50 cents LF) Snow Fence (one time charge) T Posts (one time charge) Forklift Forklift Mover Gradall 15' Boom Gradall Material Bucket (Trash Box)
Current Charge Rate $ 2,776.00 $ 2,980.00 $ 2,627.00 $ 1,839.00 $ 1,021.00 $ 280.00 $ 26.00 $ 239.00 $ 953.00 $ 288.00 $ 1,030.00 $ 1,354.00 $ 1,545.00 $ 314.00 $ 1,368.00 $ 327.00 $ 1,746.00 $ 1,337.00 $ 515.00 $ 335.00 $ 1,669.00 $ 623.00 $ 1,133.00 $ 824.00 $ 824.00 $ 582.00 $ 1,030.00 $ 773.00 $ 639.00 $ 736.00 $ 155.00 $ 28.00 $ 568.00 $ 737.00 $ 52.00 $ 7.00 $ 10.00 $ 5.00 $ 7,264.00 $ 155.00 $ 299.00 $ 391.00
Category Forklift Forklift Gates and Barricades Gates and Barricades Gates and Barricades Gates and Barricades Gates and Barricades Gates and Barricades Generator Generator Ground Thaw Ground Thaw Office Trailer Office Trailer Office Trailer Office Trailer Accessories Office Trailer Accessories Office Trailer Accessories Office Trailer Accessories Prefab RTV Safety Safety Safety Safety Safety Safety Safety Safety Safety Safety Safety Safety Safety Safety Safety Safety Safety Small Tools Small Tools Small Tools Small Tools
Description Gradall Tipping Material Bucket (Trash Box) Spreader Bar Barricade Gates (Set of 2) Jersey Barricade Picking Tool Jersey Barriers - each Barricade Fence Panels (includes barricade) Cattle Gates (Set of 2) Man Gates Generator - (Portable) 5000k -6500k Generator - 70KW (Towable) Ground Thaw 400 (onboard generator) Ground Thaw (requires power source) Office Trailer Double wide Office Trailer Single wide Office Trailer Stairs (each, requires 2) Copier Mobile Office Cabinets Office Trailer Decking Office Trailer Handicap Ramps Fabrication & Operations Support Fee - (10% of Material Costs) Lawn Mower Zero turn 42" Baker Scaffolding Curb Ramps Steel Delineator/Traffic Cones Differential Pressure Manometer Dust Fan Fire Exinguishers Fire Extinguisher stands (plastic) Gas Monitor GX-2009 HEPACart 60 x 29 Negative Air Machine Propane Cages-Large Propane Cages-Small Road Plates Safety Roof Penetator Fall protection Slab Grabbers Stanschions (Roof Warning Line) Yellow Safety Railing and Stands Abrasive Cutoff Chop Saw Air Compressor, Hoses (Portable Porter Cable C2002) Air Conditioner/Move and Cool Banding Machine
Current Charge Rate $ 500.00 $ 129.00 $ 309.00 $ 464.00 $ 55.00 $ 82.00 $ 258.00 $ 129.00 $ 618.00 $ 2,944.00 $ 7,354.00 $ 6,705.00 $ 2,369.00 $ 1,339.00 $ 77.00 $ 393.00 $ 258.00 $ 77.00 $ 515.00 #VALUE! $ 824.00 $ 206.00 $ 162.00 $ 10.00 $ 258.00 $ 21.00 $ 15.00 $ 15.00 $ 258.00 $ 1,854.00 $ 258.00 $ 240.00 $ 155.00 $ 216.00 $ 556.00 $ 15.00 $ 15.00 $ 67.00 $ 206.00 $ 259.00 $ 515.00 $ 62.00
Category Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Storage Container Storage Container Storage Container Storage Container Stormwater Protection Stormwater Protection Stormwater Protection Stormwater Protection Survey Survey Survey Survey Vehicle Vehicle Vehicle Vehicle Vehicle Weather Protection Weather Protection Weather Protection Weather Protection Weather Protection
Description Chipping hammer Electric (Large Hilti, Bosch or other) Crane Pad Drywall Cart Evaporative Cooling Fan (4 Ft) Fence Post Pounder (gas) Firehose (Rolls) Gang Box Jackhammer Electric Hilti 3000 Ladder 20' (Extension) Ladder-4', 6' or 8' Leaf Blower Pallet Jack Power Washer Table Saw Trash Buggy Trash Pump - Large 3 phase electric Trash Pump - Small Connex 20' Built-out Connex 20' Office Connex 40' Built-out Connex 40' Office 50/50 unit Cattle Guards Fuel Cell with (3) 5gal cans and 40 gal pump Vehicle Tracking Pads FODS Water Wheel Survey - Builders level-B20 Survey - Laser & Accessories 3900 Series Survey - Robotic Total Station (Kit) Survey - Thedolite Street Sweeper Ford F-450 (per 3 Hour) Trailer Event one time charge Truck - Water Truck Vehicle (CM's, Superintendent, Project Manager) Box Truck Concrete Blanket 14x25' Heaters LP Gas small Snow Blankets Snow blower Snow Tarps
Current Charge Rate $ 417.00 $ 155.00 $ 77.00 $ 155.00 $ 573.00 $ 11.00 $ 82.00 $ 618.00 $ 227.00 $ 33.00 $ 412.00 $ 424.00 $ 626.00 $ 412.00 $ 52.00 $ 464.00 $ 592.00 $ 285.00 $ 602.00 $ 506.00 $ 602.00 $ 258.00 $ 180.00 $ 273.00 $ 1,545.00 $ 218.00 $ 591.00 $ 2,979.00 $ 218.00 $ 402.00 $ 361.00 $ 3,395.00 $ 1,645.00 $ 2,060.00 $ 35.00 $ 31.00 $ 52.00 $ 235.00 $ 82.00
Exhibit M
General Conditions Contract Itemization ofwith CostSafety Addendum Itemization of the GMP Dollars requested for long lead equipment and material packages
Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20
BOULDER VALLEY SCHOOL DISTRICT RE-2 BOULDER, COLORADO
GENERAL CONTRACT CONDITIONS BOND PROGRAM
GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT.................................................................................................... 2 GC 1.00
CONTRACT DOCUMENTS AND DEFINITIONS ............................................................................................................ 1
GC 2.00
REFERENCE STANDARDS .......................................................................................................................................... 2
GC 3.00
DRAWINGS AND SPECIFICATIONS ............................................................................................................................ 2
GC 4.00
ROYALTIES AND PATENTS ........................................................................................................................................ 3
GC 5.00
ITEMS COVERED BY CONTRACT PRICE ..................................................................................................................... 3
GC 6.00
EXECUTION, CORRELATION, INTENT, AND INTERPRETATION OF CONTRACT DOCUMENTS ...................................... 3
GC 7.00
MATERIALS, LABOR, FACILITIES, AND STORAGE....................................................................................................... 4
GC 8.00
PERFORMANCE AND PAYMENT BONDS ................................................................................................................... 5
GC 9.00
PERMITS AND COMPLIANCE WITH STATUTES, RULES, AND REGULATIONS .............................................................. 6
GC 10.00
SURVEYS, BENCHMARKS, MONUMENTS, STAKES, AND MEASUREMENTS ............................................................... 6
GC 11.00
CHANGED CONDITIONS ........................................................................................................................................... 7
GC 12.00
PROTECTION OF PERSONS, WORK AND PROPERTY ................................................................................................. 7
GC 13.00
WORK ON EXISTING BUILDINGS .............................................................................................................................. 8
GC 14.00
CONTRACTOR’S SUPERINTENDENCE AND SUPERVISION .......................................................................................... 8
GC 15.00
SUBSTITUTIONS ....................................................................................................................................................... 9
GC 16.00
SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES ................................................................................................. 9
GC 17.00
CASH ALLOWANCE................................................................................................................................................. 10
GC 18.00
EXPEDITING MATERIALS ........................................................................................................................................ 10
GC 19.00
BLASTING .............................................................................................................................................................. 11
GC 20.00
SOIL TEST REPORT ................................................................................................................................................. 11
GC 21.00
HAZARDOUS MATERIALS ....................................................................................................................................... 11
GC 22.00
DAMAGE TO UTILITIES ........................................................................................................................................... 11
GC 23.00
CHANGES IN THE WORK ........................................................................................................................................ 12
GC 24.00
CLAIMS FOR EXTRA COST....................................................................................................................................... 13
GC 25.00
DELAYS AND EXTENSIONS OF TIME ....................................................................................................................... 13
GC 26.00
ACCESS TO WORK .................................................................................................................................................. 14
GC 27.00
CORRECTION OF WORK ......................................................................................................................................... 14
GC 28.00
OWNER’S RIGHT TO CARRY OUT WORK ................................................................................................................. 16
GC 29.00
OWNER’S RIGHT TO TERMINATE CONTRACT ......................................................................................................... 16
GC 30.00
CONSTRUCTION SCHEDULE AND PROGRESS REPORTS ........................................................................................... 16
GC 31.00
SCHEDULE OF VALUES ........................................................................................................................................... 17
GC 32.00
PAYMENT .............................................................................................................................................................. 17
GC 33.00
INSURANCE ........................................................................................................................................................... 19
GC 34.00
SEPARATE CONTRACTS .......................................................................................................................................... 23
GC 35.00
SUBCONTRACTORS ................................................................................................................................................ 23
GC 36.00
RELATIONS OF CONTRACTOR AND SUBCONTRACTOR ........................................................................................... 24
GC 37.00
CONTRACTORS’ MUTUAL RESPONSIBILITY ............................................................................................................ 25
GC 38.00
CUTTING, PATCHING, AND EXCAVATING ............................................................................................................... 25
GC 39.00
EMPLOYEES ........................................................................................................................................................... 26
GC 40.00
CLEANING UP......................................................................................................................................................... 27
GC 41.00
USE OF PREMISES .................................................................................................................................................. 27
GC 42.00
OCCUPANCY .......................................................................................................................................................... 27
GC 43.00
TEMPORARY OR TRIAL USAGE ............................................................................................................................... 28
GC 44.00
TESTING OF BUILDING SYSTEMS ............................................................................................................................ 28
GC 45.00
LIQUIDATED DAMAGES FOR DELAY IN COMPLETION ............................................................................................. 28
GC 46.00
ACCEPTANCE AND FINAL PAYMENT ....................................................................................................................... 28
GC 47.00
WARRANTIES ON PORTIONS OF THE WORK .......................................................................................................... 29
GC 48.00
CONTRACTOR’S PROJECT GUARANTEE AFTER COMPLETION ................................................................................. 30
GC 49.00
MISCELLANEOUS KEYS, SWITCHES, ETC. ................................................................................................................ 30
GC 50.00
INDEMNIFICATION ................................................................................................................................................ 30
GC 51.00
LABOR DISPUTES ................................................................................................................................................... 31
GC 52.00
LIMITATION OF ACTIONS ....................................................................................................................................... 31
GC 53.00
PREFERENCE FOR COLORADO LABOR, MATERIALS, AND RESIDENT BIDDERS ........................................................ 31
GC 54.00
SALES AND USE TAX............................................................................................................................................... 31
GC 55.00
LIENS ..................................................................................................................................................................... 32
GC 56.00
OWNER’S INSPECTION OF CONTRACTOR’S RECORDS ............................................................................................ 32
GC 57.00
CERTIFICATION BY CONTRACTOR REGARDING PREMISES ACCESS ......................................................................... 32
GC 58.00
CONTRACTOR SAFETY RESPONSIBILITIES ............................................................................................................... 32
GC 59.00
CONTRACTOR ASBESTOS MANAGEMENT AND LEAD PAINT RESPONSIBILITIES ...................................................... 35
GC 60.00
ARCHITECT’S STATUS AND INSPECTIONS ............................................................................................................... 35
GC 61.00
ORAL STATEMENTS................................................................................................................................................ 35
GC 62.00
PROJECT SIGN ........................................................................................................................................................ 36
GC 63.00
HISTORICAL DATA .................................................................................................................................................. 36
GC 64.00
ASSIGNMENT ......................................................................................................................................................... 36
GC 65.00
TIME OF THE ESSENCE ........................................................................................................................................... 36
GC 66.00
DISPUTES ............................................................................................................................................................... 36
GC 67.00
SURVIVAL .............................................................................................................................................................. 36
GC 1.00
CONTRACT DOCUMENTS AND DEFINITIONS
All Work under the Construction Agreement shall be accomplished in accordance with the Contract Documents, which shall consist of the Request for Qualifications, Request for Proposals, Proposal(s), Notice of Award, Notice to Proceed, Performance Bond, Labor and Material Payment Bond, Construction Agreement, General Contract Conditions, Supplementary Conditions, Asbestos Management Plan Contractor Responsibility Form, Drawings and Specifications, tests and engineering data, approved Change Orders, Contractor’s Requests for Payment, Architect’s Certificates, and all addenda issued by the Owner or Architect prior to execution of the Construction Agreement and all modifications issued by the Owner or Architect after execution of the Construction Agreement. With respect to the Contract Documents, the following definitions and understandings shall control: 1.01 “Contract” or “Contract Documents” shall include all of the items enumerated in GC-1.00 above. 1.02 “Owner” shall mean Boulder Valley School District No. RE-2, and shall include its duly authorized representatives. 1.03 “Contractor” shall mean the corporation, company, partnership, firm, entity, or individual named and designated as such in the Construction Agreement, and any persons or entities acting on its behalf. 1.04 “Subcontractor” shall mean any corporation, partnership, entity, or individual having a direct contract with the Contractor or another subcontractor for performing Work and/or furnishing labor or material on the Project covered by the Contract. 1.05 “Architect” shall mean the corporation, partnership, entity or individual named and designated as “architect” or “engineer” in the Construction Agreement, and any persons or entities acting on the Architect’s behalf and within the scope of the particular duties properly entrusted to them in each case. In the event that there is no Architect on the Project, then “Architect” shall refer to Owner and its duly authorized representative. 1.06 “Notice to Contractor” shall be deemed to have been duly served if made in writing and delivered in person to the individual or to a member of the firm or to an officer of the corporation for which it is intended, or if sent by registered or certified mail, to Contractor’s last known business address. 1.07 “The Work” shall mean the construction and services required by the Contract Documents for completion of the Project, and includes all labor, materials, equipment and services provided or to be provided by the Contractor to fulfill the Contractor’s obligations, whether on or off the Project site, and all labor, materials equipment and services provided or to be provided by subcontractors, sub-subcontractors, or any other entity for whom the Contractor is responsible. 1.08 “The Project” is the total construction designed by the Architect of which the Work performed under the Contract Documents may be the whole or a part. 1.09 The “date of final completion” and “finally completed” shall mean the date when construction is certified by the Architect to be finally completed in accordance with the Contract Documents, as modified by any Change Orders processed under the terms of GC-23.00 below and when the Owner has fully accepted the Project for the use for which it was intended. Such date will be set forth on a letter of acceptance issued by the Owner. 1.010 “Drawings” or “plans” shall mean all (a) drawings furnished by the Owner and/or Architect as a basis for the award of Contract and for construction of the Project; (b) supplementary drawings furnished by the Owner and/or Architect to clarify and to define in greater detail the intent of the Contract drawings and specifications; (c) drawings submitted by the successful Contractor as may be required after the Contract is awarded; (d) drawings furnished by the Owner and/or Architect to the Contractor during the progress of the Work; and (e) engineering data and drawings submitted by the Contractor during the progress of the Work, provided such drawings are acceptable to the Architect and Owner. 1
1.011 “Specifications” are the written technical information concerning materials, components, systems, equipment, and manner of installation as indicated on the drawings or plans and which state the quality, performance, and characteristics to be achieved by application of construction methods. 1.012 “Change Order” shall mean a written order to the Contractor signed by the Owner or its authorized agent issued after the execution of the Construction Agreement, authorizing a change in the Work and/or adjustment in the Guaranteed Maximum Price (“GMP”) or the contract time schedule. Each adjustment in the GMP resulting from a Change Order shall clearly separate the amount attributable to the Cost of the Work and the Contractor’s Fee. 1.013 “day” or “days” shall mean calendar days. In computing a period of days, when the ending date is not specified, the first day is excluded and the last day is included. If any deadline falls on a Saturday, Sunday, or federal or Colorado state holiday, such deadline will be extended to the next day that is not a Saturday, Sunday or federal or Colorado state holiday. GC 2.00
REFERENCE STANDARDS
2.01 Reference to the standards of any technical society, organization, or association, or to codes of local or state authorities, shall mean the latest standard, code, specification, or tentative standard adopted and published as of the date of execution of the Construction Agreement, unless specifically stated otherwise. GC 3.00
DRAWINGS AND SPECIFICATIONS