Exhibits BVSD Southern Hills MS Amendment Package No. 2.pdf (3,301 KB)

Regular Meeting, November 18, 2025 · item 8.12: Amendment to the contract for Southern Hills Middle School · 119 pages

Open the original file

This is the text extracted from the file, without its layout, tables, or images. Use the original for anything that matters.

Exhibit A Drawings, specifications and documents used to prepare the GMP

First Amendment to CM/GC Agreement With Turner Construction Company, dated April 25, 2017

Printed on Mon Nov 3, 2025 at 10:22 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction

Current Drawings Drawing No.

Drawing Title

Revision

Drawing Date

Received Date

Set

Cover Sheet COVER SHEET

0

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

G-001

CODE COMPLIANCE - CODE DATA AND

1

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

G-002

CODE COMPLIANCE - LEVEL 2

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

G-003

SYSTEM ASSEMBLIES FLOORS, WALLS, CEILINGS, ROOFS

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

C0.1

LEGEND NOTES & ABBREVIATIONS

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

C0.2

DEMOLITION PLAN

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

C1.0

GRADING AND EROSION CONTROL PLAN

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

C3.0

HORIZONTAL CONTROL PLAN

3

10/01/2025

2025.10.01 - CD Addendum #2 (10/ 01/25)

CD3.0

HORIZONTAL CONTROL DETAILS

3

09/25/2025

2025.09.25 - CD Addendum #1 (09/ 25/25)

CE1.1

EROSION CONTROL DETAILS

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

CE1.2

EROSION CONTROL DETAILS

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

S-001

GENERAL NOTES

1

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

S-101

PARTIAL FLOOR PLANS AND DETAILS

2

10/01/2025

A-101

LEVEL 1 OVERALL FLOOR PLAN

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

A-102

LEVEL 2 OVERALL FLOOR PLAN

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

A-111

LEVEL 1 OVERALL REFLECTED CEILING PLAN

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

A-112

LEVEL 2 OVERALL REFLECTED CEILING PLAN

4

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

CS-001 General

Civil

Structural

2025.10.01 - CD Addendum #2 (10/ 01/25)

Architectural

Page 1 of 6

Printed on Mon Nov 3, 2025 at 10:22 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction

Drawing No.

Drawing Title

Revision

Drawing Date

Received Date

Set

A-121

OVERALL ROOF PLAN

0

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

A-400

TYPICAL MOUNTING

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

A-401

CAFETERIA LARGE SCALE TOILET PLANS ANS RCPS

3

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

A-402

LOWER LEVEL LARGE SCALE TOILETS PLANS AND RCPS

4

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

A-403

LARGE SCALE FLOOR PLANS - CAFETERIA FLOOR PATTERN

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

A-415

WOOD SHOP FLOOR PLAN AND RCP

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

A-416

ART ROOM FLOOR PLAN AND RCP

3

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

A-417

FOOD LAB PLAN AND RCP

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

A-451

INTERIOR ELEVATIONS

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

A-601

DOOR AND FRAME SCHEDULE, FRAME and WINDOW TYPES

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

A-700

ROOM FINISH SCHEDULE & INTERIOR DETAILS

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

A-701

LEVEL 1 - OVERALL ROOM FINISH PLAN

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

A-702

LEVEL 2 - OVERALL ROOM FINISH PLAN

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

AD-101

LEVEL 1 OVERALL DEMOLITION FLOOR PLAN

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

AD-102

LEVEL 2 OVERALL DEMOLITION FLOOR PLAN

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

AD-111

LEVEL 1 OVERALL DEMOLITION RCP

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

AD-415

WOOD SHOP DEMOLITION PLAN AND RCP

3

09/25/2025

AD-416

ART ROOM DEMOLITION PLAN AND RCP

3

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

AD-417

FOOD LAB DEMOLITION PLAN AND RCP

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

FP-001

FIRE PROTECTION GENERAL INFORMATION

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

FP-200

PARTIAL BASEMENT FIRE PROTECTION PLAN

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

FP-201C

FIRE PROTECTION PLAN – AREA C

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

2025.09.25 - CD Addendum #1 (09/ 25/25)

Fire Protection

Page 2 of 6

Printed on Mon Nov 3, 2025 at 10:22 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction

Drawing No.

Drawing Title

Revision

Drawing Date

Received Date

Set

Plumbing P-001

PLUMBING GENERAL INFORMATION

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

P-002

PLUMBING SCHEDULES

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

P-201

LEVEL 1 PLUMBING PLAN

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

P-401

ENLARGED PLUMBING PLANS

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

P-402

ENLARGED PLUMBING PLANS

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

P-601

PLUMBING DETAILS

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

M-001

MECHANICAL

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

M-002

MECHANICAL SCHEDULES

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

M-201

LEVEL 1 OVERALL MECHANICAL PLAN

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

M-202

LEVEL 2 OVERALL MECHANICAL

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

M-203

ROOF LEVEL OVERALL MECHANICAL PLAN

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

M-401

ENLARGED CAFETERIA RESTROOMS MECHANICAL

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

M-402

ENLARGED APPLIED TECH MECHANICAL

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

M-403

1 LEVEL 1 ENLARGED ART ROOM MECHANICAL PLAN

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

M-404

ENLARGED FOOD LAB MECHANICAL PLAN

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

M-601

DUCTWORK AS NOTED ON PLANS PROVIDE ROOF JACK

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

E-001

ELECTRICAL GENERAL INFORMATION

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

E-002

ELECTRICAL PROJECT NOTES

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

E-003

ELECTRICAL SCHEDULES

3

09/25/2025

E-004

ELECTRICAL COMCHECK

0

09/12/2025

E-200

PARTIAL BASEMENT ELECTRICAL PLANS

4

10/01/2025

Mechanical

Electrical

Page 3 of 6

2025.09.25 - CD Addendum #1 (09/ 25/25) 09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25) 2025.10.01 - CD Addendum #2 (10/

Printed on Mon Nov 3, 2025 at 10:22 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction

Drawing No.

Drawing Title

Revision

Drawing Date

Received Date

Set 01/25)

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

E-201

LEVEL 1 OVERALL ELECTRICAL PLAN

3

09/12/2025

E-202

LEVEL 2 OVERALL ELECTRICAL PLAN

3

10/01/2025

2025.10.01 - CD Addendum #2 (10/ 01/25)

E-203

ROOF LEVEL OVERALL ELECTRICAL PLAN

3

09/25/2025

2025.09.25 - CD Addendum #1 (09/ 25/25)

E-301

LEVEL 1 OVERALL LIGHTING PLAN

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

E-401

ENLARGED CAFETERIA RESTROOMS POWER PLANS

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

E-402

ENLARGED APPLIED TECH POWER PLANS

3

09/25/2025

E-403

ENLARGED ART ROOM POWER PLANS

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

E-404

ENLARGED FOOD LAB POWER PLANS

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

E-405

ENLARGED CAFETERIA RESTROOMS LIGHTING PLANS

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

E-406

ENLARGED APPLIED TECH APPLIED LIGHTING PLANS

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

E-407

ENLARGED ART ROOM LIGHTING PLANS

1

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

E-408

4 ENLARGED GENDER NEUTRAL RESTROOM AND LAUNDRY LIGHTING PLAN

1

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

E-501

ELECTRICAL DEMO ONE-LINE DIAGRAM

3

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

E-502

ELECTRICAL NEW ONE-LINE DIAGRAM

4

09/25/2025

2025.09.25 - CD Addendum #1 (09/ 25/25)

E-503

PANEL SCHEDULES

2

09/25/2025

2025.09.25 - CD Addendum #1 (09/ 25/25)

E-504

PANEL SCHEDULES

2

10/01/2025

2025.10.01 - CD Addendum #2 (10/ 01/25)

ED-201

LEVEL 1 OVERALL POWER DEMOLITION PLAN

3

10/01/2025

2025.10.01 - CD Addendum #2 (10/ 01/25)

ED-202

LEVEL 2 OVERALL POWER DEMOLITION PLAN

3

10/01/2025

2025.10.01 - CD Addendum #2 (10/ 01/25)

ED-301

LEVEL 1 OVERALL LIGHTING DEMOLITION PLAN

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

T-001

COMMUNICATIONS TITLE SHEET

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

T-002

COMMUNICATIONS PROJECT NOTES

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

2025.09.25 - CD Addendum #1 (09/ 25/25)

Telecommunications

Page 4 of 6

Printed on Mon Nov 3, 2025 at 10:22 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction

Drawing No.

Drawing Title

Revision

Drawing Date

Received Date

Set

T-003

COMMUNICATIONS SCHEDULES

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

T-200

PARTIAL

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

T-201B

LEVEL 1 COMMUNICATIONS

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

T-201C

LEVEL 1 COMMUNICATIONS PLAN-AREA C

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

T-201D

LEVEL 1 COMMUNICATIONS PLAN-AREA D

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

T-201E

LEVEL 1 COMMUNICATIONS PLAN-AREA E

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

T-202A

LEVEL 2 COMMUNICATIONS PLAN-AREA A

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

T-202B

LEVEL 2 COMMUNICATIONS PLAN- AREA B

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

T-202C

LEVEL 2 COMMUNICATIONS PLAN-AREA C

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

T-503

AUDIOVISUAL SYSTEM PLAN

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

T-601

COMMUNICATIONS DETAILS

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

FA-001

FIRE ALARM

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

FA-200

PARTIAL BASEMENT FIRE ALARM PLAN

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

FA-201B

LEVLE 1 FIRE ALARM PLAN - AREA B

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

FA-201C

LEVEL 1 FIRE ALARM PLAN - AREA C

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

FA-201D

LEVEL 1 FIRE ALARM PLAN - AREA D

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

FA-201E

LEVEL 1 FIRE ALARM PLAN - AREA E

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

FA-202A

LEVEL 2 FIRE ALARM PLAN - AREA A

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

FA-202B

LEVEL 2 FIRE ALARM PLAN - AREA B

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

FA-202C

LEVEL 2 FIRE ALARM PLAN - AREA C

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

FA-202E

LEVEL 2 FIRE ALARM PLAN - AREA E

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

FAD-200

PARTIAL BASEMENT FIRE ALARM DEMOLITION PLAN

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

Fire Alarm

Page 5 of 6

Printed on Mon Nov 3, 2025 at 10:22 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction

Drawing No.

Drawing Title

Revision

Drawing Date

Received Date

Set

FAD-201B

LEVEL 1 FIRE ALARM DEMOLITION PLAN - AREA B

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

FAD-201C

LEVEL 1 FIRE ALARM DEMOLITION PLAN - AREA C

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

FAD-201D

LEVEL 1 FIRE ALARM DEMOLITION PLAN - AREA D

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

FAD-201E

LEVEL 1 FIRE ALARM DEMOLITION PLAN-AREA E

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

FAD-202A

LEVEL 2 FIRE ALARM DEMOLITION PLAN-AREA A

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

FAD-202B

LEVEL 2 FIRE ALARM DEMOLITION PLAN - AREA B

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

FAD-202C

LEVEL 2 FIRE ALARM DEMOLITION PLAN - AREA C

2

09/12/2025

09/12/2025

2025.09.12 - 100% CD Set (09/12/ 25)

Page 6 of 6

Printed on Mon Nov 3, 2025 at 10:25 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction

Current Specifications Number

Description

Revision

Issued Date

Received Date

Set

00 - Procurement and Contracting Requirements 00 1000

Performance Bond MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

00 1100

Labor and Material Payment Bond MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

00 1300

Asbestos Management Plan Contractor Responsibility MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

00 1400

Lead Based Paint Contractor Responsibility MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

000107

Seals Page BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

000110

Table of Contents

1

09/12/25

09/12/25

2025.09.12 - 100% CD's

003100

AHERA Report MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

006000

Project Forms MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

006001

RFI Form MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

006002

Substitution Request Form MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

006003

Proposal Request Form MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

006004

ASI Form MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

006005

Construction Change Directive Form MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

01 - General Requirements 011000

Summary MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

012000

Price and Payment Procedures

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

012100

Allowances MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

012300

Alternates MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

012500

Substitution Procedures MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

013000

Administrative Requirements MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

013216

Construction Progress Schedule MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

014000

Quality Requirements MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

014216

Definitions and Explanations MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

015000

Temporary Facilities and Controls MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

016000

Product Requirements MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

016116

Volatile Organic Compound (VOC) Content Restrictions MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

017000

Execution and Closeout Requirements MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

017419

Construction Waste Management and Disposal MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

017610

Temporary Protective Coverings MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

017800

Closeout Submittals MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

017900

Demonstration and Training MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

02 - Existing Conditions

Page 1 of 5

Printed on Mon Nov 3, 2025 at 10:25 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction

Number 02 41 00

Description

Revision

Issued Date

Received Date

Set

Demolition JVA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

030100

Maintenance of Concrete MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

030516

Underslab Vapor Barrier MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

033511

Concrete Floor Finishes MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

03 - Concrete

06 - Wood, Plastics, and Composites 061000

Rough Carpentry MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

066100

Cast Polymer Fabrications MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

068316

Fiberglass Reinforced Paneling MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

07 - Thermal and Moisture Protection 070553

Fire and Smoke Assembly Identification MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

072119

Foamed-In-Place Insulation MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

078400

Firestopping MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

079200

Joint Sealants MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

08 7100

Door Hardware ALLEGION

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

081113

Hollow Metal Doors and Frames MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

081416

Flush Wood Doors MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

083100

Access Doors and Panels MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

084313

Aluminum-Framed Storefronts MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

088000

Glazing MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

090561

Common Work Results for Flooring Preparation MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

092116

Gypsum Board Assemblies MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

093000

Tiling MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

096500

Resilient Flooring and Base MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

096813

Tile Carpeting MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

097200

Wall Coverings MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

099123

Interior Painting MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

099600

High-Performance Coatings MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

101100

Visual Display Units MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

101423

Panel Signage MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

102113

Toilet Compartments

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

102600

Wall and Door Protection MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

102800

Toilet, Bath, and Laundry Accessories MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

104400

Fire Protection Specialties MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

08 - Openings

09 - Finishes

10 - Specialties

Page 2 of 5

Printed on Mon Nov 3, 2025 at 10:25 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction

Number 105113

Description

Revision

Issued Date

Received Date

Set

Metal Lockers MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

113013

Residential Appliances MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

119900

Miscellaneous Equipment MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

122400

Window Shades MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

123200

Manufactured Wood Casework MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

123600

Countertops MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

124813

Entrance Floor Mats and Frames MOA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

Fire Protection BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

22 0000

Basic Plumbing Requirements BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

22 0500

Common Work Results for Plumbing BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

22 0523

General-Duty Valves for Plumbing Piping BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

22 0529

Hangers and Supports for Plumbing Piping and Equipment BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

22 0553

Identification for Plumbing Piping and Equipment BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

22 0700

Plumbing Insulation BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

22 1116

Domestic Water Piping BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

22 1119

Domestic Water Piping Specialties BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

22 1316

Sanitary Waste and Vent Piping BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

22 1319

Sanitary Waste Piping Specialties BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

22 1329

Sanitary Ejector Pumps BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

22 4000

Plumbing Fixtures BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

11 - Equipment

12 - Furnishings

21 - Fire Suppression 21 0500 22 - Plumbing

23 - Heating, Ventilating, and Air Conditioning (HVAC) 23 0000

Basic Mechanical Requirements BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

23 0100

M&E Coordination BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

23 0500

Common Work Results for HVAC BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

23 0529

Supports and Anchors BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

23 0553

Mechanical Identification BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

23 0593

Testing, Adjusting, and Balancing BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

23 0700

Mechanical Insulation BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

23 0800

Commissioning of HVAC BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

23 0900

Direct Digital Control Systems BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

23 0902

Integrated Automation Control Sequence BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

23 3113

Metal Ductwork BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

23 3300

Ductwork Accessories BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

Page 3 of 5

Printed on Mon Nov 3, 2025 at 10:25 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction

Number

Description

Revision

Issued Date

Received Date

Set

23 3413

Air Handling Fans BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

23 3713

Air Outlets and Inlets BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

26 0500

Basic Electrical Requirements BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

26 0510

Electrical Remodeling Provisions BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

26 0519

Building Wire and Cable BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

26 0526

Grounding and Bonding BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

26 0529

Supporting Devices and Seals BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

26 0532

Conduit BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

26 0534

Electrical Boxes and Fittings BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

26 0553

Electrical Identification BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

26 0580

Equipment Wiring Systems BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

26 0800

Commissioning of Electrical BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

26 0923

Lighting Control Devices BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

26 2416

Panelboards BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

26 2726

Wiring Devices BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

26 2816

Enclosed Switches BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

26 5100

Interior Lighting BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

26 7400

Electrical for Communications Systems BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

26 - Electrical

27 - Communications 27 0010

Basic Communications Requirements BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

27 0020

Contractor Qualifications BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

27 0030

Bidding BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

27 0040

Warranty BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

27 0050

Quality Assurance BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

27 0060

Training BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

27 0405

Common Work - Sleeves, Penetrations, and Firestopping BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

27 0406

Common Work - Hangers and Supports BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

27 0500

Electrical Technology - General Requirements BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

27 0533

Electrical Technology - Conduit and Boxes BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

27 1000

Communications - General Requirements BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

27 1119

Communications - Termination Equipment BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

27 1500

Communications - Horizontal Cabling BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

27 1543

Communications - Faceplates and Connectors BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

27 1619

Communications - Patch Cords BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

27 1710

Communications - Identification BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

27 1720

Communications - Testing BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

Page 4 of 5

Printed on Mon Nov 3, 2025 at 10:25 am MST Job #: 8627 K1224-BVSD Southern Hills MS Remodel 1500 Knox Drive Boulder, Colorado 80305 Adolfson & Peterson Construction

Number

Description

Revision

Issued Date

Received Date

Set

27 4000

AudioVisual - General Requirements BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

27 5000

Public Address General Requirements BCER

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

31 00 00

Earthwork JVA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

31 25 00

Erosion and Sedimentation Controls JVA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

31 - Earthwork

32 - Exterior Improvements 32 12 00

Flexible Paving JVA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

32 13 00

Rigid Paving JVA

0

09/12/25

09/12/25

2025.09.12 - 100% CD's

Page 5 of 5

Exhibit B Assumptions and clarifications made in preparing the GMP Clarifications in preparing the amendment

Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20

K1224 - BVSD - SOUTHERN HILLS MIDDLE SCHOOL 1500 Knox Dr., Boulder, CO, 80305 Estimate: CD Estimate Rev. 1

PREPARED FOR:

ARCHITECT / DESIGNER:

BVSD

MOA Architecture

DATE PRINTED: 10/29/2025

Page 1 of 20

Clarifications Report General Clarifications - Any deviation from the prime contract terms may result in different costs and pricing. - Any delays or cost impacts due to pandemics have not been included in the estimate. - Prevailing wages have not been included. - Any unknown existing conditions needing rework to meet code requirements for inspection not shown in the drawings, has not been included. - An escalation allowance is not included. - This is an estimate for the cost of construction, no land fees, architectural fees, legal fees, land development fees, tap fees, etc. have been included. - Sales tax has not been included. - A&P excludes any delegated design that is not listed in the plans or specifications.

Items by Others - All independent testing and inspections, including commissioning - Televisions - Residential Equipment (AP included range listed on the plan set) - Land Costs, Legal Fees, or Tap Fees - Architectural and Engineering Fees - Technology – Servers, computers, phones, etc. - Owner contingency - All fees associated with utilities will be paid for by the owner (water, electric, gas) - Any expenses associated with dry utilities and getting them to the site (cable, fiber, power and gas) - Removal or working with hazardous materials, including asbestos and lead abatement as defined by OSHA. - All moving costs - All artwork - purchasing, moving, and installation - Technology - Computers, Servers, phones, etc. – purchasing, moving and installation - Furniture, Desks, chairs, tables, moveable casework – purchasing, moving and installation - Audio / Visual Projectors, Projection Screens, Smart Boards (that are not specifically called out in the plans)

Documents - Drawings dated 09/12/2025 - Specifications dated 09/12/2025 - Addenda 1 dated 09/25/2025 - Addenda 2 dated 10/01/2025

B Shell - For additional scope item 'Access Fixed Ladders - Exterior Renewal', it was determined at the facilities page turn that BVSD doesn't know where these are located and to plug in the VFA allowance.

DATE PRINTED: 11/4/2025

Page 2 of 20

D Services - Dust Collectors are included as owner furnished owner installed (OFOI) per BVSD's request. - Fire alarm replacement product was included as Mircom. Bronco has included extra devices past the plans to create a complete system. - Garbage disposals are not included. - Per BVSD and drawings, no additional raceways for security cameras have been included.

E Equipment and Furnishings - We have included new trim at the wood partition between the pottery and art rooms as this will provide a better look and is more cost effective.

F Special Construction and Demolition - It is assumed that the ACM shown on the exterior wall is only a coating and AP's demo sub will be able to demo the wall after the coating has been abated.

- It is assumed that the equipment to be salvaged is attached to ACM containing material and is not included in the demo scope.

G Site Preparation - For additional scope item 'Exterior Wall - Damaged Concrete', it was determined at the facilities page turn that BVSD doesn't know where these are located and to plug in the VFA allowance.

Z General Requirements - A site security guard has not been included. - General protection of adjacent surfaces is included for the work shown in the plans.

DATE PRINTED: 11/4/2025

Page 3 of 20

Exhibit C

Itemization ofGMP Cost Itemization of the Dollars requested for long lead equipment and material packages

Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20

797 Ventura Street, Aurora, CO 80011 Project: K1224 - BVSD - Southern Hills Middle School Owner: BVSD Architect: MOA Architecture

Date: Estimator: Project SF: Duration in Months: Estimate #:

10/30/25 Karra Damiana 105,580 7.00 CD Estimate Rev. 1 Includes Alternates 3 (Additional Electrical Panels), 4 (Intercom), 16 (Exterior Plaza Upgrade)

Project Summary Sheet - Estimated Cost of the Work Division #0

Procurement and Contracting Requirements

Division #1 Division #2 Division #3 Division #4

General Requirements Existing Conditions Concrete Masonry

Division #5 Division #6 Division #7

Metals Wood, Plastics, and Composites Thermal and Moisture Protection

Division #8

Openings

Division #9 Division #10 Division #11

Finishes Specialties Equipment

Division #12 Division #13 Division #14 Division #21 Division #22 Division #23 Division #25

Furnishings Special Construction Conveying Equipment Fire Suppression Plumbing Heating, Ventilating and Air Conditioning Integrated Automation

Division #26

Electrical

Division #27

Division #28

Division #31

Division #32 Division #33

DD Estimate CD Estimate $37,140 $37,140 $162,194 $134,445

Difference $0 ($27,749)

$45,869 $14,283 $16,000 $43,116

$69,093 $20,372 $0 $19,612

$23,224 $6,089 ($16,000) ($23,504)

$51,725 $13,723 $27,967

$67,482 $20,485 $14,232

$15,757 $6,762 ($13,735)

$175,877

$236,678

$60,801

$65,575 $1,800 $4,045

$11,287 $1,841 $2,520

($54,288) $41 ($1,525)

$0 $0 $0 $255,780 $217,467 $0 $542,692

$0 $0 $10,007 $0 $428,405 $0 $562,988

$0 $0 $10,007 ($255,780) $210,938 $0 $20,296

$209,254

$204,516

($4,738)

$620,034

$432,934

($187,100)

Communications

$79,627

$77,107

($2,520)

$115,112

$130,360

$15,248

$0

$0

$0

$2,699,280

$2,481,504

($217,776)

By Owner By Owner By Owner $97,712 $97,712 $81,427 $6,406 $37,456 Not Included $22,800 $97,712 $97,712 $5,076

By Owner By Owner By Owner $0 $0 $74,445 $2,996 $29,958 Not Included $18,519 $0 $110,928 $5,076

$3,243,293

$2,723,426

Earthwork

Utility Tap & Devel. Fees Permit Allowance Use Tax Design Contingency Estimate Contingency Construction Contingency Builders Risk Insurance Comprehensive General Liability Insurance Sub Default Insurance Performance and Payment Bond Escalation Allowance Contractors Fee Preconstruction Services

/SF

1.5% of Direct Costs

$1.27

/SF

5.4% of Direct Costs

$0.65

/SF

2.8% of Direct Costs

$0.19

/SF

0.8% of Direct Costs

$0.00

/SF

0.0% of Direct Costs

$0.19

/SF

0.8% of Direct Costs

$0.64

/SF

2.7% of Direct Costs

$0.19

/SF

0.8% of Direct Costs

$0.13

/SF

0.6% of Direct Costs

$2.24

/SF

9.5% of Direct Costs

$0.11

/SF

0.5% of Direct Costs

$0.02

/SF

0.1% of Direct Costs

Base Contract Amendment 1 Amendment 2

$5,076.00 $428,686.60 $2,289,663.40

Removed CMU Patching at Restrooms Moved All DD Exterior Site Railing into Alternate 16 (Exterior Site Plaza); Removed Structural Reinforement Allowance. ADD ALTERNATE 16 ADD ALTERNATE 16 Moved Wood Shop Window into Alternate 9 Added Furred Walls at Wood Shop & Lower Level RR's; Branding Allowance Included with Division 9 Painting/Wallcovering; ADD ALTERNATE 16 Moved Lockers into Alternate 10

$0.02

/SF

0.1% of Direct Costs

$0.00

/SF

0.0% of Direct Costs

$0.00

/SF

0.0% of Direct Costs

$0.09

/SF

0.4% of Direct Costs

$0.00

/SF

0.0% of Direct Costs

$4.06

/SF

17.3% of Direct Costs

$0.00

/SF

0.0% of Direct Costs

$5.33

/SF

22.7% of Direct Costs

8.2% of Direct Costs

Moved providing & installing speakers/cabling in all common spaces & hallways as well as IP Clock speackes/Cat6 cabling in classrooms, gyms, & cafeteria connected to the new Valcom system to Alternate 4. ADD ALTERNATE 4

/SF

$4.10

/SF

17.4% of Direct Costs

$0.73

/SF

3.1% of Direct Costs

$1.23

/SF

5.3% of Direct Costs

$0.00

/SF

0.0% of Direct Costs

$23.50

/SF

100.0% of Direct Costs

$0.00

/SF

$0.00

/SF

0.00% of Project

$0.00

/SF

0.00% of Project

($97,712) ($97,712) ($6,982)

$0.00

/SF

0.00% of Project

$0.00

/SF

0.00% of Project

$0.71

/SF

3.00% of Subtotal

($3,410) ($7,498)

$0.03

/SF

0.11% of Project

$0.28

/SF

1.10% of Project

$0.00

/SF

0.00% of Costs

($4,281) ($97,712) $13,216 $0

$0.18

/SF

0.68% of Project

$0.00

/SF

0.00% of Project

$1.05

/SF

4.34% of Subtotal + Contingency

$0.05

/SF

($519,867)

$25.79

/SF

Estimated Cost of Construction

CD Estimate Rev. 1

Cost Delta Comments from DD's No Change Refinement of GRs Based on Accepted Scope & Schedule ADD ALTERNATE 16

Moved Window Treatment for Wood Shop Window into Alternate 9. Moved Remove/Replace Bike Racks into Alternate 16. ADD ALTERNATE 16 Not Applicable Not Applicable Added Remove/Relocate Sprinkler Heads Moved to Mechanical DUST COLLECTORS OFOI Not Applicable Moved Some Electrical Panels into Alternate 3 ADD ALTERNATE 3

$1.94

Electronic Safety and Security

Exterior Improvements Utilities

$0.35

100.0% of Project

Bronco Carried a Plug Number at DDs to Generally Account for the Scope. At CDs, Bronco Completed a Full Design, & the Cost Decreased Accordingly. Most of the school has to be installed in surface mounted conduit which is time consuming. Moved All DD Exterior Site Work into Alternate 16 - Exterior Site Plaza; ADD ALTERNATE 16 Moved All DD Exterior Site Work into Alternate 16 - Exterior Site Plaza; ADD ALTERNATE 16 Not Applicable

Dropped to 0% from 2.5% Dropped to 0% from 2.5%

Dropped to 0% from 3%

Detail Report DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS

DETAILED COST: Building 00 Procurement and Contracting Requirements

$37,140

00 72 00 AIA General Conditions 00100 General conditions of the contract

$37,140 1.00 ls

37,140.00

Subtotal 00 72 00 AIA General Conditions

$37,140

See Below, Priced per AIA 201

$37,140

Subtotal 00 Procurement and Contracting Requirements

$37,140

01 General Requirements

$134,445

01 14 00 Work Restrictions

$0

01010 Access to Site

Included

01020 Coordination with Occupants

Included

01030 Off-hours work

Not Included

01040 Works in Rights-of-Way

Not Included

01050 ROW Permits

Not Included

Subtotal 01 14 00 Work Restrictions

$0

01 20 00 Price and Payment Procedures

$0

01060 Allowances

Included

01070 Unit Prices

Not Included

Subtotal 01 20 00 Price and Payment Procedures

$0

01 32 00 Construction Progress Documentation 01180 Site Photos, Cameras, Reproductions

$1,750 7.00 mo

250.00

$1,750

01190 Drone Service

Not Included

Subtotal 01 32 00 Construction Progress Documentation

$1,750

01 33 00 Submittal Procedures

$2,050

01110 Delivery Costs

7.00 mo

150.00

$1,050

01130 Reproduction Costs

20.00 ea

50.00

$1,000

01170 Sustainability Project Requirements Subtotal 01 33 00 Submittal Procedures 01 35 53 Security Procedures

Per BVSD Standards $2,050 $0

01120 Trailer Security - Motion and Monitoring

Not Included

01150 Site Security Guard

Not Included

DATE PRINTED: 10/29/2025

Page 5 of 20

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

01160 Site Security Cameras and Monitoring

NOTES / COMMENTS Not Included

Subtotal 01 35 53 Security Procedures

$0

01 45 00 Quality Control

$0

01200 Independent Testing

Not Included

01210 Soil Compaction Tests

Not Included

01220 Concrete Tests

Not Included

01230 Steel Weld Test / Inspections

Not Included

01250 Field Quality Control Procedures

Included

01260 3rd Party Envelope Consultant

Not Included

Subtotal 01 45 00 Quality Control

$0

01 51 00 Temporary Facilities

$38,729

01270 Temporary Electricity - Jobsite

By BVSD

01280 Generators 36kw

Not Included

01290 Fuel for Generator (full load)

Not Included

01300 Generator Setup / and Containment

Not Included

01310 Temporary Fire Protection

Not Included

01340 Temp Heating Fuel

By BVSD

01350 Temporary Building Enclosure for Temp Heating

Not Included

01360 Temporary Lighting

w/ Div. 26 Lighting

01370 Temporary Water 01380 Sanitary Facilities 01390 Temporary Elevators 01400 Temporary Hoists

By BVSD 65.00 ea

380.00

$24,700 Not Included By Trade/Division

01410 Gradall and Operator for Jobsite

Not Included

01420 Bobcat and Operator Jobsite

Not Included

01430 Fuel for Equipment

Included Above

01440 Temporary Cranes

By Division

01450 Temporary Scaffolding and Platforms

By Division

01460 Temporary Stairs and Ramps

Not Included

01470 Temporary Swing Staging

Not Included

01480 Temporary Access Roads

By Division

01490 Snow and Ice Removal

Not Included

01500 Haul Routes

Not Included

01510 Temporary Parking Areas

Not Included

01520 Temporary Air & Noise Barriers

Not Included

DATE PRINTED: 10/29/2025

Page 6 of 20

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

01530 Temporary Fencing (Yard)

NOTES / COMMENTS Included

01540 Temporary Barricades

By Division

01550 Temporary Protective Walkways

Not Included

01560 Temporary Storage

7.00 mo

290.00

$2,030

01580 Barricades and Warning Lights

Not Included

01590 Environmental Protection

Not Included

01600 Exit Enclosure for Existing Exits

Not Included

01610 Project Identification - Temporary Project Signage 01620 Temporary Signage 01630 Technology for DCOW Staff

1.00 ea

2,500.00

$2,500

121,928.00 sf

0.02

$2,761

1,052.00 hr

6.40

$6,738

Subtotal 01 51 00 Temporary Facilities

$38,729

01 70 00 Execution and Closeout

$0

01640 Mobilization

Included

01660 Field Engineering

By Trade

01700 Total Station Rental

Division 2

01720 Construction Surveying

Division 2

01730 Protection of Adjacent Construction

By Division

Subtotal 01 70 00 Execution and Closeout

$0

01 74 00 Cleaning

$91,916

01630 Progress Cleaning

121,928.00 sf

0.27

$32,671

01650 Site Maintenance

1,047,353.00 sf

0.01

$10,473

01690 Final Clean Site 01710 Final Clean Building Subtotal 01 74 00 Cleaning 01 90 00 Life Cycle Activities

Not Included 121,928.00 sf

0.40

$48,771 $91,916 $0

01740 Substructure Commissioning

Not Included

01750 Structure Commissioning

Not Included

01760 Exterior Enclosure Commissioning

Not Included

01770 Roofing Commissioning

Not Included

01780 Systems Commissioning

Not Included

Subtotal 01 90 00 Life Cycle Activities

$0

Subtotal 01 General Requirements

$134,445

02 Existing Conditions

$39,165

DATE PRINTED: 10/29/2025

Page 7 of 20

DESCRIPTION

QTY UOM UNIT PRICE

02 41 00 Demolition 02300 Demo - SUB

TOTAL COST

NOTES / COMMENTS

$39,165 1.00 sub

37,824.00

$37,824 Included at non-ACM locations

02300 Demo flooring finishes 02300 Demo LVT

Included

02300 Demo wood flooring

Included Included at non-ACM locations

02301 Demolish rubber base 02302 Remove existing non load bearing walls

Included

02302 Sawcut interior SOG

Included

02303 Move refrigerators to new location

Included

02303 Remove door, frame and hardware

Included

02304 Demo casework

Included

02304 Remove equipment/furnishings - salvage

Not Included

02305 Demo HM lite and glazing

Included

02305 Remove Masonry Partition

Included

02305 Remove plumbing fixtures & restroom accessories

Included

02421 Sawcut & Demo Concrete Roof Deck for New Exhaust Fan Ducting (CTE 1.2A)

1.00 ea

1,341.27

$1,341

02425 Remove cord reel for relocation

Included

02426 Remove built in bench by entry vestibule

Included

02427 MEP Haul Off

Included

Subtotal 02 41 00 Demolition

$39,165

Subtotal 02 Existing Conditions

$39,165

03 Concrete

$20,372

03 35 00 Concrete Finishing 03351 Interior Concrete - SUB

$7,520 1.00 sub

7,519.80

$7,520

03353 Concrete Slab Infill for UGP for New Fixtures, 5" Thick SOG w/ Fibermesh, Reinf w/ #3 @ 18" OC EW (Laundry 137 & RR 139)

Included

03355 Concrete Slab Infill for UGP for New Fixtures, 5" Thick SOG w/ Fibermesh, Reinf w/ #3 @ 18" OC EW (Art 120)

Included

03357 Concrete Slab Infill for UGP for New Fixtures, 5" Thick SOG w/ Fibermesh, Reinf w/ #3 @ 18" OC EW (Food Lab 114 & 114B)

Included

Subtotal 03 35 00 Concrete Finishing

$7,520

03 35 43 Polished Concrete Finishing

$12,852

DATE PRINTED: 10/29/2025

Page 8 of 20

DESCRIPTION 03511 PC-1 Polished concrete 03513 >Power Requirements 208/3 Phase 50 amp Generator

QTY UOM UNIT PRICE

TOTAL COST

1,892.00 sf

6.00

$11,352

1.00 wk

1,500.00

$1,500

03515 Sealed concrete (Flooring is to remain in the food lab)

NOTES / COMMENTS

Not Included

Subtotal 03 35 43 Polished Concrete Finishing

$12,852

Subtotal 03 Concrete

$20,372

04 Masonry

$0

04 20 00 Unit Masonry

$0

04205 Int CMU Patching/Tooth-in (RR's 117 & 118)

Not Included

04207 Int CMU Patching/Tooth-in (Laundry 137 & RR 139)

Not Included

Subtotal 04 20 00 Unit Masonry

$0

Subtotal 04 Masonry

$0

05 Metals

$2,043

05 50 00 Metal Fabrications 05505 Access Fixed Ladders - Exterior Renewal Allowance

$2,043 1.00 allow

2,043.00

Subtotal 05 50 00 Metal Fabrications

$2,043 $2,043

Subtotal 05 Metals

$2,043

06 Woods, Plastics and Composites

$67,482

06 10 10 Rough Carpentry 06001 Interior Rough Carpentry

$10,757 3,926.00 sf

2.74

Subtotal 06 10 10 Rough Carpentry

$10,757 $10,757

06 22 00 Finish Carpentry 06320 Finish Carpentry - SUB

Allowance

$56,725 1.00 sub

48,725.00

$48,725

06320 Move existing cabinet to corner, remove open shelving

Included

06450 PL-1 - New PLAM open, adjustable shelves

Included

06450 Shelving and storage along north wall

Not Included

06451 Existing casework to remain - Relocate

Included

06451 Rolling shelving at teaching wall

Not Included

06452 PL-1 Base Cabinets

Included

06452 PL-2 Base Cabinets

Included

DATE PRINTED: 10/29/2025

Page 9 of 20

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS

06453 SS-1 Countertop

Included

06453 SS-1 Countertop w/ Steel Brackets

Included

06454 PL-1 Tall Cabinet

Included

06454 PL-3 Countertop

Included

06454 SS Loop in Cable on J Screw in Hook Support

Included 1.00 allow

5,000.00

$5,000

06495 Protect casework after relocation

1.00 ls

2,000.00

$2,000

06500 Caulk casework/countertops

1.00 ls

1,000.00

$1,000

06455 Food Lab Casework Repair Allowance

Allowance

06456 Renew look of wood partition between pottery & art

Subtotal 06 22 00 Finish Carpentry

$56,725

Subtotal 06 Woods, Plastics and Composites

$67,482

07 Thermal and Moisture Protection

$16,975

07 60 00 Flashing & Sheet Metal

$16,975

07601 Roofing - SUB

1.00 sub

6,090.11

$6,090

07602 Roof Coring Investigation

1.00 ls

680.00

$680

07603 Demo Existing Roof System at New Penetrations (Remove Existing Gravel for Base Flashing Tie-in

Included

07605 Roof Patches at New Exhaust Fans per Sheet Keynote 171

Included

07607 Roof Patch at New Dryer Vent Stack per Sheet Keynote 172 (Laundry 137)

Included

07608 Roof Cleanup 07609 Safety Measures for Roof Work - Perimeter 07610 Protect Roof from Damage

6,500.00 sf

0.05

$325

286.00 lf

5.00

$1,430

6,500.00 sf

1.30

$8,450

Subtotal 07 60 00 Flashing & Sheet Metal

$16,975

Subtotal 07 Thermal and Moisture Protection

$16,975

08 Openings

$14,232

08 10 00 Doors and Frames

$13,550

08011 Interior 3x7 Door and HM Frame with hardware

2.00 ea

4,150.00

$8,300

08011 Interior 6x7 Door and HM Frame with Hardware

1.00 ea

5,250.00

$5,250

Subtotal 08 10 00 Doors and Frames

$13,550

08 80 00 Glazing 08801 Glazing - SUB 08803 Safety Glazing for Hollow Metal Sidelight, Type 2

DATE PRINTED: 10/29/2025

$682 1.00 sub

576.05

$576 Included

Page 10 of 20

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

08805 Safety Glazing for Wood Door Lites, FG 08807 Final Clean Glass

Included 53.00 sf

2.00

Subtotal 08 80 00 Glazing

$106 $682

Subtotal 08 Openings

$14,232

09 Finishes

$235,528

09 21 16 Gypsum Board Assemblies 09070 Drywall - SUB

NOTES / COMMENTS

$60,000 1.00 sub

35,000.00

$35,000

1.00 ls

25,000.00

$25,000

09071 FRP-1 09071 Level 5 Finish at WC Locations 09071 P-3 Wall - To Deck, 1 layer gyp both sides, STC Rated, Acoustic Insulation, Metal Stud 09072 FR3 Wall - To Deck, 1 layer gyp 1 sides,, Metal Stud 09073 G1 - Gyp Ceiling 09337 Wall Patching Subtotal 09 21 16 Gypsum Board Assemblies

$60,000

09 30 00 Tiling

$29,256

09209 TB-1 Tile Base

Included

09209 TW-1 Wall Tile

Included

09269 Miracle Method at Restrooms - SUB

1.00 sub

29,256.00

Subtotal 09 30 00 Tiling

$29,256

09 51 00 Acoustical Ceilings 09257 C2 - 2x2 flat lay-in - .55 NRC

$1,478 197.00 sf

7.50

Subtotal 09 51 00 Acoustical Ceilings

09307 >Power Requirements 208/3 Phase 50 amp Generator

$11,935 1,510.00 sf

6.91

$10,435

1.00 wk

1,500.00

$1,500

Subtotal 09 64 00 Wood Flooring

$11,935

09 65 00 Resilient Flooring 09335 Flooring - SUB

$1,478 $1,478

09 64 00 Wood Flooring 09305 Refinish wood flooring

$29,256

$68,235 1.00 sub

56,890.00

$56,890

09335 LVT-1

Included

09336 LVT-2

Included

09337 LVT-3

Included

DATE PRINTED: 10/29/2025

Page 11 of 20

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS

09338 Moisture resistant adhesive

Included

09461 RB-1/VB-1 New 4" base

Included 6.00 ea

115.00

$690

09613 Floor prep and joint grinding

5,098.00 sf

1.79

$9,125

09637 Floor protection

5,098.00 sf

0.30

$1,529

09585 Moisture tests (1/1000sf)

Subtotal 09 65 00 Resilient Flooring

$68,235

09 68 00 Carpet

$0

09553 WOC-1 Walk Off Tile

Included

Subtotal 09 68 00 Carpet

$0

09 72 00 Wall Coverings

$0

00000 WC-1

Included

00000 WC-2

Included

Subtotal 09 72 00 Wall Coverings

$0

09 90 00 Painting and Coating

$64,625

09700 Branding Graphic Allowance

1.00 allow

25,000.00

$25,000

09700 Paint and Wall Covering - SUB

1.00 sub

38,350.00

$38,350

09720 Repaint walls damaged by replacement of flooring 09825 Final touch up at completion of project

Included 5,098.00 sf

0.25

$1,275

09901 Ramp/Stair Railing, Exterior, Finish Coats

Included Included

Subtotal 09 90 00 Painting and Coating

$64,625

Subtotal 09 Finishes

$235,528

10 Specialties

$11,287

10 14 00 Signage

$1,250

10005 Set Branding Allowance 10035 Signage - SUB

Allowance

Included 1.00 sub

1,250.00

$1,250

10036 Room ID Sign

Included

10037 Door Tag

Included

10037 Restroom ID

Included

Subtotal 10 14 00 Signage

$1,250

10 28 00 Toilet & Bath Accessories 10200 Specialties - SUB 10201 TA-1 42" SS Grab Bar

DATE PRINTED: 10/29/2025

$10,037 1.00 sub

9,137.31

$9,137 Included

Page 12 of 20

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS

10202 TA-2 36" SS Grab Bar

Included

10203 TA-3 18" SS Grab Bar

Included

10204 TA-4 Soap Dispenser

Included

10205 TA-5 TP Dispenser OFCI

3.00 ea

150.00

$450

10206 TA-6 Framed Mirror 10207 TA-7 PT Dispenser OFCI

Included 3.00 ea

150.00

$450

10208 Mop and Broom Holder

Included

10208 TA-8 Sanitary Napkin Disposal

Included

10208 Toilet Partitions - Phenolic

Included

Subtotal 10 28 00 Toilet & Bath Accessories

$10,037

Subtotal 10 Specialties

$11,287

11 Equipment

$1,841

11 30 00 Residential Equipment (GE Equipment) 11155 GE Electric Range - 30"

$1,841 1.00 ea

1,841.00

Subtotal 11 30 00 Residential Equipment (GE Equipment)

$1,841 $1,841

Subtotal 11 Equipment

$1,841

21 Fire Suppression

$10,007

21 00 00 Fire Suppression 21000 Fire Suppression - SUB

$10,007 1.00 sub

10,007.00

$10,007

21001 Remove and Relocate Sprinkler Heads

Included

21002 Delegated Design

Included

21003 High Temperature Head at Kiln

Included

Subtotal 21 00 00 Fire Suppression Subtotal 21 Fire Suppression 22 Plumbing 22 00 00 Plumbing

$10,007 $10,007 $0 $0

22001 Plumbing - SUB

w/ Div. 23 Mechanical

22003 Plumbing Demo

Included

22005 Plumbing Piping Systems (Domestic Water, Waste, Underground Waste, Vent)

Included

22007 Plumbing Equipment

See Below

22009 >Fixtures

See Below

22011 >>Water Closet, ADA, WC-1 (RR's 117, 118, & 139)

DATE PRINTED: 10/29/2025

Included

Page 13 of 20

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS

22013 >>Lavatory, ADA, L-1 (RR's 117, 118, & 139)

Included

22015 >>Sinks, S-1 (Art 120)

Included

22017 >>Sinks, S-2 (Food Lab 114)

Included

22019 >>Sink, S-3 (Art 120)

Included

22023 >>Garbage Disposals, GD-1

Not Included

22025 >>Solids Interceptor, SI-1 (Art 120)

Included

22027 >>Electric Water Cooler/Bottle Filler, ADA, EWC -1

Included

22029 >>Mop Service Basin, MSB-1 (Laundry 137)

Included

22031 >>Utility Sink, US-1 (Laundry 137)

Included

22033 >>Washer Wall Box, WWB-1 (Laundry 137)

Included

22035 >>Floor Drain, FD-1 (Laundry 137 & RR 139)

Included

22037 >Thermostatic Mixing Valve, TMV-1 (RR's 117, 118, & 139)

Included

22041 >Balance Valve Assemblies

Included

22043 Insulation, Fire Stopping/Caulking

Included

22045 Test & Balance

Included

22047 Concrete Cutting, Coring, & Xray

Included

22049 Domestic Water Chlorination

Included

22051 Pressure Testing of New Piping

Included

22053 MEP Coordination & QA/QC - Plumbing

w/ Div. 23 Mechanical

Subtotal 22 00 00 Plumbing

$0

Subtotal 22 Plumbing

$0

23 Heating, Ventilating and Air Conditioning

$428,405

23 00 00 Heating, Ventilating and Air Conditioning 23001 Mechanical - SUB

$428,405 1.00 sub

451,567.21

$451,567

23003 Mechanical Demo

See Below Included

23005 HVAC & Mechanical Equipment

See Below

23007 >Exhaust Fans, EF-14 (Restrooms), EF-16 (Laser Rm), EF-17 (Storage)

Included

23011 >Dryer Fans, F-1 (Laundry 137)

Included

23013 >Grilles, Registers, Diffusers, SG-1, EG-1, EG-2, TG-2

Included

23015 >Airking Filtration Unit, AFU-1

Included

23017 >Ruwac Stand Alone Dust Collectors, PDC-1

Included

23018 >>Ruwac Stand Alone Dust Collectors, PDC-1 Supply (OFOI) 23019 Mechanical Piping (Heating Hot Water, DATE PRINTED: 10/29/2025

-2.00 ea

17,000.00

($34,000)

OFOI Included Page 14 of 20

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS

Condensate Waste) 23021 HVAC Ductwork Systems (Supply, Return, Exhaust) 23025 MEP Coordination & QA/QC -Mechanical

Included 444,621.00 ls

0.02

Subtotal 23 00 00 Heating, Ventilating and Air Conditioning

$10,838 $428,405

Subtotal 23 Heating, Ventilating and Air Conditioning

$428,405

26 Electrical

$562,988

26 00 00 Electrical 26001 Electrical - SUB

$562,988 1.00 sub

440,897.31

$440,897

26003 >Site Lighting & Power

Included

26005 >Service & Distribution

Included

26007 >Lighting

Included

26009 >Lighting Circuitry

Included

26011 >Lighting Controls

Included

26013 >Branch Power

Included

26015 >Mechanical Equipment Connections

Included

26017 >Tele/Data Raceways

Included

26019 >Audio Visual Raceways

Included

26020 Permit Fees (MEP)

Included

26021 >Clock/Paging Raceways

Included

26023 >Demolition

Included

26025 Temporary Lighting & Power

Included

26027 Fire Caulking/Fire Stopping

Included

26029 Remove/reinstall Cover Plates on Electrical Devices & Light Switches 26031 MEP Coordination & QA/QC - Electrical 26033 Replace Additional Electrical Panels 26035 >MEP Coordination & QA/QC - Electrical

130.00 ea

20.00

$2,600

432,174.00 ls

0.03

$10,838

1.00 ls

106,767.63

$106,768

Alternate 3

94,240.00 ls

0.02

$1,885

Alternate 3

Subtotal 26 00 00 Electrical

$562,988

Subtotal 26 Electrical

$562,988

27 Communications

$204,516

27 51 00 Distributed AV systems

$204,516

27501 Upgrade Intercom/Public Address System Replace Existing Intercom Head-end Equipment Only

1.00 sub

62,618.00

$62,618

27503 Provide & Install Speakers & Cabling in Common Spaces & Hallways Connected to New

1.00 sub

120,573.00

$120,573

DATE PRINTED: 10/29/2025

Alternate 4

Page 15 of 20

DESCRIPTION Common Spaces & Hallways Connected to New Valcom System

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS

27505 Provide & Install IP Clock Speakers & Cat6 Cabling in Classrooms, Gyms, & Cafeteria Connected to New Valcom System

Alternate 4 - Included

27507 >Electrical Scope - Rough-In Backboxes & Conduit

w/ Div. 26 Electrical

27509 Classroom Updated to Standard Teaching. Adding Lightspeed Voice Reinforcement Sys. (Wood Shop, Art Room, Food Lab)

3.00 ea

2,503.00

$7,509

27511 New Projector & Screen (Wood Shop 124)

Included

27513 Structural Cabling - SUB

1.00 sub

7,448.00

$7,448

27515 New Ceiling Mounted Projector, New Drop Down Screen (Wood Shop 124)

1.00 ls

6,368.00

$6,368

Subtotal 27 51 00 Distributed AV systems

$204,516

Subtotal 27 Communications

$204,516

28 Electronic Safety and Security

$432,934

28 00 00 Electronic Safety and Security 28101 Fire Alarm System - Full System Replacement w/ Voice Evacuation - SUB

$432,934 1.00 sub

421,777.46

$421,777

28103 >New Intelligent, Fully Addressable Fire Alarm System

Included

28105 >Voice Evacuation System

Included

28107 >New FACP w/ Expansion Capability

Included

28109 >New Smoke Detectors, Pull Stations, & Duct Detectors

Included

28111 >Notification Appliances Throughout the Building (Speakers, Strobes)

Included

28113 MEP Coordination & QA/QC - Fire Alarm

455,240.00 ls

0.02

Subtotal 28 00 00 Electronic Safety and Security

$432,934

Subtotal 28 Electronic Safety and Security

$432,934

32 Exterior Improvements

$2,745

32 13 00 Rigid Paving 32159 Exterior Wall - Damaged Concrete Allowance

$11,157

$2,745 1.00 allow

2,745.00

$2,745

Subtotal 32 13 00 Rigid Paving

$2,745

Subtotal 32 Exterior Improvements

$2,745

Total Building

DATE PRINTED: 10/29/2025

Allowance

$2,222,106

Page 16 of 20

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS

DETAILED COST: Site 02 Existing Conditions

$29,928

02 21 00 Surveys

$29,928

02201 Total Stations

2.00 mo

3,992.00

$7,984

02203 Survey - SUB

1.00 sub

6,858.00

$6,858

Alternate 16

02205 Survey Calculations & Plan Checks (IS 2)

1.00 ea

85.71

$86

Alternate 16 - Included

02207 Survey Control Points & Sawcut (IS 2)

Alternate 16 - Included

02209 Survey Grading (IS 2)

Alternate 16 - Included

02211 Survey Hanrails/Bike Racks (IS 2)

Alternate 16 - Included

02213 Survey Four Court Layout (IS 2)

Alternate 16 - Included

02215 Survey Concrete/Sidewalks, Ramps & Stairs (IS 2)

Alternate 16 - Included

02217 Survey Restaking (IS 2)

Alternate 16 - Included

02219 Survey Site Improvement As-Built (IS 2)

Alternate 16 - Included

02223 Penetrating Radar for Investigation

1.00 ls

15,000.00

$15,000

Subtotal 02 21 00 Surveys

$29,928

Subtotal 02 Existing Conditions

$29,928

05 Metals

$17,569

05 50 00 Metal Fabrications 05501 Ramp/Stair Railing, Exterior, HP Primed Steel (IS 2)

$17,569 1.00 ls

17,569.13

Subtotal 05 50 00 Metal Fabrications

$17,569 $17,569

Subtotal 05 Metals

$17,569

07 Thermal and Moisture Protection

$3,510

07 13 26 Waterproofing 07131 Drainage Board at Retaining Wall (IS 2)

$500 81.00 sf

6.17

Subtotal 07 13 26 Waterproofing

Subtotal 07 92 00 Joint Sealants

$500

$3,010 1.00 sub

3,010.00

$3,010

Alternate 16

$3,010

Subtotal 07 Thermal and Moisture Protection

$3,510

09 Finishes

$1,150

DATE PRINTED: 10/29/2025

Alternate 16

$500

07 92 00 Joint Sealants 07921 Slab to Structure Joint Sealants, Expansion Joint at Top & Bottom of Stairs (IS 2)

Alternate 16

Page 17 of 20

DESCRIPTION

QTY UOM UNIT PRICE

09 90 00 Painting and Coating 09720 Paint exterior metals

TOTAL COST $1,150

1.00 ls

1,150.00

Subtotal 09 90 00 Painting and Coating

$1,150

Alternate 16

$1,150

Subtotal 09 Finishes

$1,150

12 Furnishings

$2,520

12 93 00 Site Furnishings 12931 Remove/Reinstall Bike Racks, U-Shaped, Surface Mounted (IS 2)

NOTES / COMMENTS

$2,520 16.00 ea

157.50

Subtotal 12 93 00 Site Furnishings

$2,520

Alternate 16

$2,520

Subtotal 12 Furnishings

$2,520

31 Earthwork

$77,107

31 00 00 Earthwork

$54,968

31001 Earthwork - SUB

Alternate 16 - See Below

31003 Pothole Utilities (IS 2)

8.00 hr

641.84

$5,135

Alternate 16

31005 Private Locates (IS 2)

8.00 hr

961.73

$7,694

Alternate 16

31007 Construction Water (IS 2) 31009 Earthwork at Exterior Site Plaza - SUB

Alternate 16 - Included 1.00 sub

42,139.26

$42,139

Alternate 16 - See Below

31011 >Sawcut Concrete Paving/Sidewalk (IS 2)

Alternate 16 - Included

31013 >Remove & Dispose Concrete/Paving (IS 2)

Alternate 16 - Included

31015 >Excavate Cut to Export (IS 2)

Alternate 16 - Included

31017 >Export Material (IS 2)

Alternate 16 - Included

31019 >Import CL6 Roadbase (IS 2)

Alternate 16 - Included

31021 >Place Roadbase (IS 2)

Alternate 16 - Included

31023 >Scarify Below Concrete Paving, 12" Depth (IS 2)

Alternate 16 - Included

31025 >Rough Grade Site (IS 2)

Alternate 16 - Included

31027 >Excavate & Backfill Stairs (IS 2)

Alternate 16 - Included

Subtotal 31 00 00 Earthwork

$54,968

31 25 00 Erosion and Sedimentation Controls

$22,139

31251 Concrete Washout Area (CWA) (3 EA, 4 Months), 1.5 CY Pump Pan (IS 2)

12.00 ea

227.50

$2,730

Alternate 16

31253 Concrete Washout Area (CWA) (3 EA, 4 Months), 5.5 CY Container (IS 2)

12.00 ea

417.50

$5,010

Alternate 16

31255 Rock Socks/Filtrex Logs (Curb/Gutter, Temp. Fencing) (IS 2)

283.00 lf

13.00

$3,679

Alternate 16

31257 Vehicle Tracking Control (VTC) (4 EA, 4 Months) (IS 2)

16.00 ea

287.50

$4,600

Alternate 16

DATE PRINTED: 10/29/2025

Page 18 of 20

DESCRIPTION

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS

9.00

$2,520

Alternate 16

900.00

$3,600

Alternate 16

(IS 2) 31259 Temporary Fencing (Installation/Removal/Maintenance) (IS 2) 31261 SRM - Small Projects - 1-5 Acres (IS 2)

280.00 lf 4.00 mo

Subtotal 31 25 00 Erosion and Sedimentation Controls

$22,139

Subtotal 31 Earthwork

$77,107

32 Exterior Improvements

$127,615

32 12 00 Flexible Paving

$16,204

32121 Ashpalt "T" Patch - SUB (IS 2)

1.00 sub

15,604.00

$15,604

Alternate 16

32133 Asphalt Adjustment Index Cost for Liquid Asphalt (Binder) (IS 2)

1.00 tn

600.00

$600

Alternate 16

Subtotal 32 12 00 Flexible Paving

$16,204

32 13 00 Rigid Paving 32129 Concrete at Plaza - SUB (IS 2)

$104,661 1.00 sub

89,146.74

$89,147

Alternate 16

32131 >Concrete Pavement, 5" w/ Fibermesh (IS 2)

Alternate 16 - Included

32133 >Concrete Ramp, 5" w/ Fibermesh, #4 @ 12" OCEW (IS 2)

Alternate 16 - Included

32135 >Concrete Retaining Wall Along Ramp, Reinf. with (2) #4 Cont. T&B, #4 Cont. (IS 2)

Alternate 16 - Included

32137 >>Smooth Sack Finish (IS 2)

Alternate 16 - Included

32139 >>>Continuous Footing, 8"x20", Reinf. with #4 Cont. @ 16" OC T&B, #4 Trans @ 24" OC T&B (IS 2)

Alternate 16 - Included

32141 >Stairs with (3) 5.5" Risers, Reinf. with #4 @12" OCEW (IS 2)

Alternate 16 - Included

32143 >>Turndown Edge at Steps, Reinf. With #4 @ 12" OCEW (IS 2)

Alternate 16 - Included

32145 >Concrete Material Increase After 4/1/26 (IS 2)

120.00 cy

6.87

$824

32147 >Rebar for Retaining Wall, Stairs, Turned Down Edge - Material (IS 2) 32149 Concrete Foreman (IS 2) 32151 Sweep/Clean Sitework Prior to Turnover (IS 2)

Alternate 16 - Included 1.00 mo

14,671.00

$14,671

Alternate 16

270.00 sy

0.07

$19

Alternate 16

Subtotal 32 13 00 Rigid Paving

$104,661

32 17 00 Paving Specialties 32171 Lines & Infill, 4 Square Courts, White Lines with Green Infill - SUB (IS 2) Subtotal 32 17 00 Paving Specialties Subtotal 32 Exterior Improvements

DATE PRINTED: 10/29/2025

Alternate 16

$6,750 1.00 sub

6,750.00

$6,750

Alternate 16

$6,750 $127,615

Page 19 of 20

DESCRIPTION

Total Site

DATE PRINTED: 10/29/2025

QTY UOM UNIT PRICE

TOTAL COST

NOTES / COMMENTS

$259,399

Page 20 of 20

Exhibit D

Contract Time Schedule Itemization ofGMP Cost Itemization of the Dollars requested for long lead equipment and material packages

Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20

RE: Schedule Narrative – October 2025 Schedule Update Narrative October 17, 2025 BVSD – Southern Hills Middle School 1500 Knox Drive Boulder CO. 80305 The following is a schedule narrative for the BVSD –Southern Hills Middle School [Boulder Valley RFP 25-04 CMGC Project Scope #1 – Southern Hills Middle School 10.17.2025.pdf] is attached.

Summary: This updated schedule reflects revisions to the DD schedule and aligns with the bi-weekly OAC dashboard timelines. It outlines the project timeline from preconstruction to construction activities and provides key milestone dates during preconstruction to allow for a successful construction phase during the summer. AP has been actively identifying long-lead procurement items starting at the Schematic Design phase. In collaboration with trade partners, AP has gathered lead times, submittal preparation costs, and material release costs.

Description of Activities on the most Critical Path The current critical path is driven by the wood shop and the art room scope. Progress in those spaces are dependent on the completion of the school year as well as the coordination of multiple trade contractors to sequence their work in those areas. This area is currently tracking in the master schedule to meet the required TCO date.

Monthly Progress Description The schedule has been updated and activities have been adjusted to reflect the latest CD documents. Tasks have been progressed since the previous update.

Current/Anticipated Problem Areas and/or Delaying Factors October 2025 – BVSD & AP have preordered long lead time material as noted in the Amendment 1 procurement change order. AP is tracking all long lead time material with the master schedule for completion to meet the required schedule.

Revisions to the Project Schedule The updates made to establish a targeted flow through the building.

Narrative Review To recap the attached schedule and the above update: •

Overall, the attached schedule provides a road map for the design and construction of the BVSDSouthern Hills Middle School. As more planning, coordination, and construction scope is defined and developed, the schedule will continue to reflect these changes and updates.

•

The current schedule is on track for TCO by August 1st 2026.

•

The project approach is to assist with coordinating owner activities for summer of 2026 and Construction work that is to be completed per the TCO date.

•

The team is tracking numerous important dates: document release, funding package dates, and material release dates. AP will continue to update the team in forthcoming narratives and OAC meetings

•

Lastly, the schedule changes and modifications outlined above help to more accurately show how the project is being built and ways that BVSD,MOA, AP and their subcontractors are working to maintain or improve the project completion date.

Please feel free to contact me with any questions or comments regarding this update or anything else within the Project. Thank you, Logan Dickerman Superintendent Adolfson & Peterson Construction 720.456.1992 ldickerman@a-p.com

Line

Name

Duration APC

Start

Finish

BVSD - Southern Hills Middle School

31.37

8/12/2024

9/30/2026

Preconstruction

36.44

8/12/2024

5/27/2026

2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5

RFP / RFQ Information

49d 100.00 8/12/2024 10/18/2024

1

RFP Issued to Contractor

1d 100.00 8/12/2024 A 8/12/2024 A

RFP Issued to Contractor

2

RFP Site Walk

1d 100.00 8/22/2024 A 8/22/2024 A

RFP Site Walk

3

RFP Inquiries Due

1d 100.00

4

RFP Addendum Sent

1d 100.00 9/12/2024 A 9/12/2024 A

5

RFP Submission Deadline

1d 100.00 10/3/2024 A 10/3/2024 A

6

RFP Evaluation

1d 100.00 10/11/2024 A 10/11/2024 A

7

CMGC Contract Award

1d 100.00 10/18/2024 A 10/18/2024 A

Document Development

9/4/2024 A

9/4/2024 A

RFP Inquiries Due

RFP Addendum Sent

RFP Submission Deadline

RFP Evaluation

CMGC Contract Award

91.99

1/6/2025

12/26/2025

Schematic Design

101d 100.00

1/6/2025

5/27/2025

8

SD-Design Advisory Team Meetings

65d 100.00

1/6/2025 A

4/4/2025 A

9

SD- Early VFA Investigation and Verification

73d 100.00

1/7/2025 A 4/17/2025 A

10

SD-Schematic Design Complete

1d 100.00 2/14/2025 A 2/14/2025 A

11

SD-Schematic Design Pricing/ Constructability Review

23d 100.00 2/17/2025 A 3/19/2025 A

SD-Schematic Design Pricing/ Constructability Review

12

SD-Schematic Design Bid Leveling/ Review Meeting

1d 100.00 3/19/2025 A 3/19/2025 A

SD-Schematic Design Bid Leveling/ Review Meeting

13

SD- Schematic Design - Budget/ Constructability Corrections

4d 100.00 3/20/2025 A 3/25/2025 A

SD- Schematic Design - Budget/ Constructability Corrections

14

SD- Early Procurement Package Creation by AP

23d 100.00 3/26/2025 A 4/25/2025 A

15

SD- Early Procurement Package Review with BVSD

15d 100.00 4/28/2025 A 5/16/2025 A

16

SD- Early Procurement Package Issuance to Board

5d 100.00 5/20/2025 A 5/27/2025 A

Design Development 17 18 19 20 21 22

112d 100.00 2/10/2025

DD-Design Development - Pricing/ Constructability Review DD-Design Development - Design Development Complete DD-Final Design Advisory Team Meeting DD-Design Development - Pricing/ Constructability Internal Review DD-Design Development - Budget/ Constructability Corrections DD-Design Development - Final Procurement Package Allocation Review to Start Long Lead Submittals

SD-Design Advisory Team Meetings

SD- Early VFA Investigation and Verification

SD-Schematic Design Complete

SD- Early Procurement Package Creation by AP

SD- Early Procurement Package Review with BVSD

SD- Early Procurement Package Issuance to Board

7/17/2025

97d 100.00 2/10/2025 A 6/25/2025 A

DD-Design Development - Pricing/ Constructability Review

20d 100.00 4/18/2025 A 5/15/2025 A

DD-Design Development - Design Development Complete

1d 100.00 5/16/2025 A 5/16/2025 A

DD-Final Design Advisory Team Meeting

1d 100.00 6/25/2025 A 6/25/2025 A

DD-Design Development - Pricing/ Constructability Internal Review

9d 100.00 6/26/2025 A 7/9/2025 A

DD-Design Development - Budget/ Constructability Corrections

1d 100.00 7/17/2025 A 7/17/2025 A

Contracting & Award

148d 75.37

5/27/2025 12/26/2025

Procurement Package

104d 97.12

5/27/2025 10/21/2025

Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School

DD-Design Development - Final Procurement Package Allocation Review to Start Long Lead Submittals

Rev. date: 10/17/2025 10:27:32 AM Job #: Southern Hills Middle School

Data Date: 10/17/2025

Page 1 of 14

3. Print View Filter: No Summary Tasks

Line

Name

Duration APC

Start

Finish

2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5

23

C&A-PP-Board Approval

8d 100.00 5/27/2025 A 6/5/2025 A

24

C&A-PP-BVSD Contract Execution to AP

49d 100.00

6/6/2025 A 8/14/2025 A

25

C&A-PP-AP Contract Execution to Procurement Package Subs

47d 93.62

8/15/2025 A 10/21/2025

FGMP

30d

11/11/2025 12/26/2025

26

C&A-FGMP-Board Approval

5d

11/11/2025 11/17/2025

27

C&A-FGMP-BVSD Contract Execution to AP

10d

11/18/2025

12/3/2025

28

C&A-FGMP-AP Contract Execution to Remaining Subs

15d

12/4/2025

12/26/2025

Electrical Metering

14d 100.00 4/18/2025

5/1/2025

29

EI-7 Day Electrical Metering

7d 100.00 4/18/2025 A 4/24/2025 A

30

EI- 30 Day Electrical Metering

14d 100.00 4/18/2025 A 5/1/2025 A

Early Investigation and Coordination

8d 100.00 7/14/2025

31

EI-Design/ Sub Kick off Meeting

2d 100.00 7/14/2025 A 7/15/2025 A

EI-Design/ Sub Kick off Meeting

32

EI-Onsite Review of Mechanical Scope

2d 100.00 7/16/2025 A 7/17/2025 A

EI-Onsite Review of Mechanical Scope

33

EI-Onsite Review of Remaining Scope

2d 100.00 7/22/2025 A 7/23/2025 A

EI-Onsite Review of Remaining Scope

C&A-PP-Board Approval

C&A-PP-BVSD Contract Execution to AP

C&A-PP-AP Contract Execution to Procurement Package Subs

C&A-FGMP-Board Approval

C&A-FGMP-BVSD Contract Execution to AP

C&A-FGMP-AP Contract Execution to Remaining Subs

EI-7 Day Electrical Metering

EI- 30 Day Electrical Metering

7/23/2025

Construction Documents

124d 86.29

5/16/2025 11/10/2025

34

Construction Documents and Drawings Complete

83d 100.00 5/16/2025 A 9/12/2025 A

35

Construction Documents - Pricing Review

25d 96.00

9/15/2025 A 10/17/2025

Construction Documents - Pricing Review

36

Construction Documents - FGMP Review with BVSD PM

1d

10/20/2025 10/20/2025

Construction Documents - FGMP Review with BVSD PM

37

Construction Documents - FGMP Corrections

5d

10/21/2025 10/27/2025

38

Construction Documents - Final FGMP Amendment to District Board of Education Submission

10d

10/28/2025 11/10/2025

Permitting

145d 11.71

9/15/2025

39

Building Permit Review and Issuance

125d 19.20

9/15/2025 A 3/13/2026

40

Remaining Permit Approval

40d

1/5/2026

2/27/2026

41

Local AHJ Permit Review and Issuance

40d

2/16/2026

4/10/2026

Long Lead Submittals & Procurement

221d 24.69

7/14/2025

5/27/2026

Submittals & Procurement - Fire Alarm Equipment

143d 17.86

9/12/2025

4/7/2026

Submittals & Procurement - Fire Alarm Equipment

143d 17.86

9/12/2025

4/7/2026

42

S&P - FA - Subcontractor Submittals

30d 83.33

9/12/2025 A 10/28/2025

43

S&P - FA - AP Review

5d

10/29/2025

11/4/2025

44

S&P - FA - AHJ Review and Approval

15d

11/5/2025

11/25/2025

Construction Documents and Drawings Complete

Construction Documents - FGMP Corrections

Construction Documents - Final FGMP Amendment to District Board of Education Submission

4/10/2026

Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School

Building Permit Review and Issuance

Remaining Permit Approval

Local AHJ Permit Review and Issuance

S&P - FA - Subcontractor Submittals

S&P - FA - AP Review

S&P - FA - AHJ Review and Approval

Rev. date: 10/17/2025 10:27:32 AM Job #: Southern Hills Middle School

Data Date: 10/17/2025

Page 2 of 14

3. Print View Filter: No Summary Tasks

Line

Name

Duration APC

Start

Finish

45

S&P - FA - A/E Review and Approval

10d

11/26/2025 12/11/2025

46

S&P - FA - Procurement

80d

12/12/2025

Submittals & Procurement - AV Equipment

75d

12/29/2025 4/13/2026

2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5 S&P - FA - A/E Review and Approval

4/7/2026

Submittals & Procurement - AV Equipment

75d

12/29/2025 4/13/2026

47

S&P - SE- Subcontractor Submittals

20d

12/29/2025

1/26/2026

48

S&P - SE- AP Review

5d

1/27/2026

2/2/2026

49

S&P - SE- A/E Review and Approval

10d

2/3/2026

2/16/2026

S&P - SE- Procurement

S&P - FA - Procurement

S&P - SE- Subcontractor Submittals

S&P - SE- AP Review

S&P - SE- A/E Review and Approval

40d

2/17/2026

4/13/2026

Submittals & Procurement - Electrical Distribution Equipment/ Panel Boards

210d 35.52

7/14/2025

5/11/2026

Submittals & Procurement - Panel G

128d 42.31

7/14/2025

1/15/2026

51

S&P - EDE - Subcontractor Submittals

29d 100.00 7/14/2025 A 8/21/2025 A

S&P - EDE - Subcontractor Submittals

52

S&P - EDE- AP Review

1d 100.00 8/21/2025 A 8/21/2025 A

S&P - EDE- AP Review

53

S&P - EDE - A/E Review and Approval

14d 100.00 8/21/2025 A 9/10/2025 A

54

S&P - EDE - Procurement

60d

10/17/2025

1/15/2026

Submittals & Procurement - Panel UV2

128d 42.31

7/14/2025

1/15/2026

55

S&P - EDE - Subcontractor Submittals

29d 100.00 7/14/2025 A 8/21/2025 A

S&P - EDE - Subcontractor Submittals

56

S&P - EDE- AP Review

1d 100.00 8/21/2025 A 8/21/2025 A

S&P - EDE- AP Review

57

S&P - EDE - A/E Review and Approval

14d 100.00 8/21/2025 A 9/10/2025 A

58

S&P - EDE - Procurement

60d

10/17/2025

1/15/2026

Submittals & Procurement - Panel K

128d 42.31

7/14/2025

1/15/2026

59

S&P - EDE - Subcontractor Submittals

29d 100.00 7/14/2025 A 8/21/2025 A

S&P - EDE - Subcontractor Submittals

60

S&P - EDE- AP Review

1d 100.00 8/21/2025 A 8/21/2025 A

S&P - EDE- AP Review

61

S&P - EDE - A/E Review and Approval

14d 100.00 8/21/2025 A 9/10/2025 A

62

S&P - EDE - Procurement

60d

10/17/2025

1/15/2026

Submittals & Procurement - Panel A

128d 42.31

7/14/2025

1/15/2026

63

S&P - EDE - Subcontractor Submittals

29d 100.00 7/14/2025 A 8/21/2025 A

S&P - EDE - Subcontractor Submittals

64

S&P - EDE- AP Review

1d 100.00 8/21/2025 A 8/21/2025 A

S&P - EDE- AP Review

65

S&P - EDE - A/E Review and Approval

14d 100.00 8/21/2025 A 9/10/2025 A

66

S&P - EDE - Procurement

60d

10/17/2025

1/15/2026

Submittals & Procurement - Panel B

127d 41.75

7/15/2025

1/15/2026

50

Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School

S&P - SE- Procurement

S&P - EDE - A/E Review and Approval

S&P - EDE - Procurement

S&P - EDE - A/E Review and Approval

S&P - EDE - Procurement

S&P - EDE - A/E Review and Approval

S&P - EDE - Procurement

S&P - EDE - A/E Review and Approval

S&P - EDE - Procurement

Rev. date: 10/17/2025 10:27:32 AM Job #: Southern Hills Middle School

Data Date: 10/17/2025

Page 3 of 14

3. Print View Filter: No Summary Tasks

Line

Name

Duration APC

Start

Finish

2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5

67

S&P - EDE - Subcontractor Submittals

28d 100.00 7/15/2025 A 8/21/2025 A

S&P - EDE - Subcontractor Submittals

68

S&P - EDE- AP Review

1d 100.00 8/21/2025 A 8/21/2025 A

S&P - EDE- AP Review

69

S&P - EDE - A/E Review and Approval

14d 100.00 8/21/2025 A 9/10/2025 A

S&P - EDE - A/E Review and Approval

S&P - EDE - Procurement

60d

10/17/2025

1/15/2026

Submittals & Procurement - Panel E

127d 41.75

7/15/2025

1/15/2026

71

S&P - EDE - Subcontractor Submittals

28d 100.00 7/15/2025 A 8/21/2025 A

S&P - EDE - Subcontractor Submittals

72

S&P - EDE- AP Review

1d 100.00 8/21/2025 A 8/21/2025 A

S&P - EDE- AP Review

73

S&P - EDE - A/E Review and Approval

14d 100.00 8/21/2025 A 9/10/2025 A

74

S&P - EDE - Procurement

60d

10/17/2025

1/15/2026

Submittals & Procurement - Panel F

127d 41.75

7/15/2025

1/15/2026

75

S&P - EDE - Subcontractor Submittals

28d 100.00 7/15/2025 A 8/21/2025 A

S&P - EDE - Subcontractor Submittals

76

S&P - EDE- AP Review

1d 100.00 8/21/2025 A 8/21/2025 A

S&P - EDE- AP Review

77

S&P - EDE - A/E Review and Approval

14d 100.00 8/21/2025 A 9/10/2025 A

78

S&P - EDE - Procurement

60d

10/17/2025

1/15/2026

Submittals & Procurement - Panel UV1

127d 41.75

7/15/2025

1/15/2026

79

S&P - EDE - Subcontractor Submittals

28d 100.00 7/15/2025 A 8/21/2025 A

S&P - EDE - Subcontractor Submittals

80

S&P - EDE- AP Review

1d 100.00 8/21/2025 A 8/21/2025 A

S&P - EDE- AP Review

81

S&P - EDE - A/E Review and Approval

14d 100.00 8/21/2025 A 9/10/2025 A

82

S&P - EDE - Procurement

60d

10/17/2025

1/15/2026

Submittals & Procurement - Panel N

127d 41.75

7/15/2025

1/15/2026

83

S&P - EDE - Subcontractor Submittals

28d 100.00 7/15/2025 A 8/21/2025 A

S&P - EDE - Subcontractor Submittals

84

S&P - EDE- AP Review

1d 100.00 8/21/2025 A 8/21/2025 A

S&P - EDE- AP Review

85

S&P - EDE - A/E Review and Approval

14d 100.00 8/21/2025 A 9/10/2025 A

86

S&P - EDE - Procurement

60d

10/17/2025

1/15/2026

Submittals & Procurement - Panel J

127d 41.75

7/15/2025

1/15/2026

87

S&P - EDE - Subcontractor Submittals

28d 100.00 7/15/2025 A 8/21/2025 A

S&P - EDE - Subcontractor Submittals

88

S&P - EDE- AP Review

1d 100.00 8/21/2025 A 8/21/2025 A

S&P - EDE- AP Review

89

S&P - EDE - A/E Review and Approval

14d 100.00 8/21/2025 A 9/10/2025 A

90

S&P - EDE - Procurement

60d

10/17/2025

1/15/2026

Submittals & Procurement - Shop Main Panel

137d 38.05

7/15/2025

1/29/2026

70

Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School

S&P - EDE - Procurement

S&P - EDE - A/E Review and Approval

S&P - EDE - Procurement

S&P - EDE - A/E Review and Approval

S&P - EDE - Procurement

S&P - EDE - A/E Review and Approval

S&P - EDE - Procurement

S&P - EDE - A/E Review and Approval

S&P - EDE - Procurement

S&P - EDE - A/E Review and Approval

S&P - EDE - Procurement

Rev. date: 10/17/2025 10:27:32 AM Job #: Southern Hills Middle School

Data Date: 10/17/2025

Page 4 of 14

3. Print View Filter: No Summary Tasks

Line

Name

Duration APC

Start

Finish

2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5

91

S&P - EDE - Subcontractor Submittals

28d 100.00 7/15/2025 A 8/21/2025 A

S&P - EDE - Subcontractor Submittals

92

S&P - EDE- AP Review

1d 100.00 8/21/2025 A 8/21/2025 A

S&P - EDE- AP Review

93

S&P - EDE - A/E Review and Approval

14d 100.00 8/21/2025 A 9/10/2025 A

S&P - EDE - A/E Review and Approval

S&P - EDE - Procurement

70d

10/17/2025

1/29/2026

Submittals & Procurement - Shop Sub Panel

137d 38.05

7/15/2025

1/29/2026

95

S&P - EDE - Subcontractor Submittals

28d 100.00 7/15/2025 A 8/21/2025 A

S&P - EDE - Subcontractor Submittals

96

S&P - EDE- AP Review

1d 100.00 8/21/2025 A 8/21/2025 A

S&P - EDE- AP Review

97

S&P - EDE - A/E Review and Approval

14d 100.00 8/21/2025 A 9/10/2025 A

98

S&P - EDE - Procurement

70d

10/17/2025

1/29/2026

Submittals & Procurement - Sub Distribuition A Wing Panel - I Line Series 800A

167d 30.07

7/15/2025

3/12/2026

99

S&P - EDE - Subcontractor Submittals

28d 100.00 7/15/2025 A 8/21/2025 A

S&P - EDE - Subcontractor Submittals

100

S&P - EDE- AP Review

1d 100.00 8/21/2025 A 8/21/2025 A

S&P - EDE- AP Review

101

S&P - EDE - A/E Review and Approval

14d 100.00 8/21/2025 A 9/10/2025 A

102

S&P - EDE - Procurement

100d

10/17/2025

3/12/2026

Submittals & Procurement - Main Distribuition Mech Sub Panel B - I Line Series 1,200A

167d 30.07

7/15/2025

3/12/2026

103

S&P - EDE - Subcontractor Submittals

28d 100.00 7/15/2025 A 8/21/2025 A

S&P - EDE - Subcontractor Submittals

104

S&P - EDE- AP Review

1d 100.00 8/21/2025 A 8/21/2025 A

S&P - EDE- AP Review

105

S&P - EDE - A/E Review and Approval

14d 100.00 8/21/2025 A 9/10/2025 A

106

S&P - EDE - Procurement

100d

10/17/2025

Submittals & Procurement - LED Lighting

65d

12/29/2025 3/30/2026

107

S&P - EDE - Subcontractor Submittals

20d

12/29/2025

1/26/2026

108

S&P - EDE- AP Review

5d

1/27/2026

2/2/2026

109

S&P - EDE - A/E Review and Approval

10d

2/3/2026

2/16/2026

S&P - EDE - A/E Review and Approval

3/30/2026

S&P - EDE - Procurement

94

S&P - EDE - Procurement

30d

2/17/2026

95d

12/29/2025 5/11/2026

111

S&P - EDE - Subcontractor Submittals

20d

12/29/2025

1/26/2026

112

S&P - EDE- AP Review

5d

1/27/2026

2/2/2026

113

S&P - EDE - A/E Review and Approval

10d

2/3/2026

2/16/2026

114

S&P - EDE - Procurement

60d

2/17/2026

5/11/2026

110d

10/22/2025 3/31/2026

Submittals & Procurement - Division 8

S&P - EDE - A/E Review and Approval

S&P - EDE - Procurement

S&P - EDE - A/E Review and Approval

S&P - EDE - Procurement

S&P - EDE - A/E Review and Approval

3/12/2026

Submittals & Procurement - Lighting Control Equipment

110

S&P - EDE - Procurement

Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School

S&P - EDE - Procurement

S&P - EDE - Subcontractor Submittals

S&P - EDE- AP Review

S&P - EDE - Subcontractor Submittals

S&P - EDE- AP Review

S&P - EDE - A/E Review and Approval

S&P - EDE - Procurement

Rev. date: 10/17/2025 10:27:32 AM Job #: Southern Hills Middle School

Data Date: 10/17/2025

Page 5 of 14

3. Print View Filter: No Summary Tasks

Line

Name

Duration APC

Start

Finish

Submittals & Procurement - HM Doors and Hardware

110d

10/22/2025 3/31/2026

115

S&P - HMDH- Subcontractor Submittals

20d

10/22/2025 11/18/2025

116

S&P - HMDH- AP Review

5d

11/19/2025 11/25/2025

117

S&P - HMDH- A/E Review and Approval

10d

11/26/2025 12/11/2025

118

S&P - HMDH- Procurement

75d

12/12/2025

Submittals & Procurement - Casework

105d

10/22/2025 3/24/2026

Submittals & Procurement - Casework

105d

10/22/2025 3/24/2026

119

S&P - CW- Subcontractor Submittals

20d

10/22/2025 11/18/2025

120

S&P - CW- AP Review

5d

11/19/2025 11/25/2025

121

S&P - CW- A/E Review and Approval

10d

11/26/2025

12/11/2025

122

S&P - CW- Procurement

70d

12/12/2025

3/24/2026

Submittals & Procurement - Graphics

100d

12/29/2025 5/18/2026

Submittals & Procurement - Graphics

100d

12/29/2025 5/18/2026

123

S&P - Graphic- Subcontractor Submittals

20d

12/29/2025

1/26/2026

124

S&P - Graphic- AP Review

5d

1/27/2026

2/2/2026

125

S&P - Graphic- A/E Review and Approval

10d

2/3/2026

2/16/2026

126

S&P - Graphic- Procurement

65d

2/17/2026

5/18/2026

Submittals & Procurement - Mechanical Equipment

150d

10/22/2025 5/27/2026

S&P - HMDH- Subcontractor Submittals

S&P - HMDH- AP Review

S&P - HMDH- A/E Review and Approval

3/31/2026

Submittals & Procurement - Sump Pumps

75d

12/29/2025 4/13/2026

127

S&P - SUMP- Subcontractor Submittals

20d

12/29/2025

1/26/2026

128

S&P - SUMP- AP Review

5d

1/27/2026

2/2/2026

129

S&P - SUMP- A/E Review and Approval

10d

2/3/2026

2/16/2026

130

S&P - SUMP- Procurement

40d

2/17/2026

4/13/2026

Submittals & Procurement - Dust Collector

150d

10/22/2025 5/27/2026

131

S&P - DC- Subcontractor Submittals

20d

10/22/2025 11/18/2025

132

S&P - DC- AP Review

5d

11/19/2025 11/25/2025

133

S&P - DC- A/E Review and Approval

10d

11/26/2025 12/11/2025

134

S&P - DC- AHJ Review and Approval

15d

12/12/2025

1/6/2026

135

S&P - DC- Procurement

100d

1/7/2026

5/27/2026

95d

12/29/2025 5/11/2026

Submittals & Procurement - All Other Submittals

2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5

Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School

S&P - HMDH- Procurement

S&P - CW- Subcontractor Submittals

S&P - CW- AP Review

S&P - CW- A/E Review and Approval

S&P - CW- Procurement

S&P - Graphic- Subcontractor Submittals

S&P - Graphic- AP Review

S&P - Graphic- A/E Review and Approval

S&P - Graphic- Procurement

S&P - SUMP- Subcontractor Submittals

S&P - SUMP- AP Review

S&P - SUMP- A/E Review and Approval

S&P - SUMP- Procurement

S&P - DC- Subcontractor Submittals

S&P - DC- AP Review

S&P - DC- A/E Review and Approval

S&P - DC- AHJ Review and Approval

S&P - DC- Procurement

Rev. date: 10/17/2025 10:27:32 AM Job #: Southern Hills Middle School

Data Date: 10/17/2025

Page 6 of 14

3. Print View Filter: No Summary Tasks

Line

Name

Duration APC

Start

Finish

136

S&P - Other - Subcontractor Submittals

20d

12/29/2025

1/26/2026

137

S&P - Other - AP Review

10d

1/27/2026

2/9/2026

138

S&P - Other - A/E Review and Approval

15d

2/10/2026

3/2/2026

139

S&P - Other - Procurement Board Dates

50d

3/3/2026

5/11/2026

146d 50.00

5/13/2025

12/9/2025

140

1st May Board Date

1d 100.00 5/13/2025 A 5/13/2025 A

141

2nd May Board Date

1d 100.00 5/27/2025 A 5/27/2025 A

142

Only November Board Date

1d

11/11/2025 * 11/11/2025

143

Only December Board Date

1d

12/9/2025 * 12/9/2025

Owner Key Dates

327d 50.00

4/18/2025

2025 Spring Break

5d 100.00 4/18/2025 A 4/24/2025 A

145

2025 End of School Year

1d 100.00 5/27/2025 A 5/27/2025 A

146

2025/2026 School Year Begin

1d 100.00

8/1/2025 A

147

2026 Spring Break

5d

3/23/2026 * 3/27/2026

148

2026 End of School Year

1d

5/26/2026 * 5/26/2026

149

2026/2027 School Year Begins

1d

8/3/2026 *

8/3/2026

135d

3/23/2026

9/30/2026

Site Mobilization

5d

5/11/2026

5/15/2026

Mob - Site mobilization

5d

5/11/2026

5/15/2026

Intierior Finish and Fittout

91d

3/23/2026

7/29/2026

Restroom Renovations

36d

5/26/2026

7/15/2026

150

S&P - Other - Subcontractor Submittals

S&P - Other - AP Review

S&P - Other - A/E Review and Approval

S&P - Other - Procurement

1st May Board Date

2nd May Board Date

Only November Board Date

Only December Board Date

8/3/2026

144

Construction

2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5

2025 Spring Break

2025 End of School Year

8/1/2025 A

2025/2026 School Year Begin

2026 Spring Break

2026 End of School Year

2026/2027 School Year Begins

Mob - Site mobilization

Restroom Renovations 118 & 117

35d

5/26/2026

7/14/2026

151

IFF-RR-MEP Safe off

1d

5/26/2026

5/26/2026

IFF-RR-MEP Safe off

152

IFF-RR-Clean Demo Flooring and Tile

3d

5/27/2026

5/29/2026

IFF-RR-Clean Demo Flooring and Tile

153

IFF-RR-Sawcut & Demo Concrete

2d

6/1/2026

6/2/2026

IFF-RR-Sawcut & Demo Concrete

154

IFF-RR-Underslab Plumbing

3d

6/3/2026

6/5/2026

IFF-RR-Underslab Plumbing

155

IFF-RR- Slab Patchbacks

1d

6/8/2026

6/8/2026

IFF-RR- Slab Patchbacks

156

IFF-RR-MEP Rough in

5d

6/9/2026

6/15/2026

IFF-RR-MEP Rough in

157

IFF-RR-Hang/Tape/Finish Drywall

6d

6/16/2026

6/23/2026

IFF-RR-Hang/Tape/Finish Drywall

158

IFF-RR-Prime and First Coat Lids

2d

6/24/2026

6/25/2026

IFF-RR-Prime and First Coat Lids

Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School

Rev. date: 10/17/2025 10:27:32 AM Job #: Southern Hills Middle School

Data Date: 10/17/2025

Page 7 of 14

3. Print View Filter: No Summary Tasks

Line

Name

Duration APC

Start

Finish

2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5

159

IFF-RR-Install Floor and Wall Tile

5d

6/26/2026

7/2/2026

IFF-RR-Install Floor and Wall Tile

160

IFF-RR-Install MEP Trim

3d

7/6/2026

7/8/2026

IFF-RR-Install MEP Trim

161

IFF-RR-Install Partitions

2d

7/6/2026

7/7/2026

IFF-RR-Install Partitions

162

IFF-RR-Install Accessories

2d

7/9/2026

7/10/2026

IFF-RR-Install Accessories

163

IFF-RR-Final Paint

3d

7/9/2026

7/13/2026

IFF-RR-Final Paint

164

IFF-SCI-Final Clean

1d

7/14/2026

7/14/2026

IFF-SCI-Final Clean

Restroom Renovations 137 & 139

35d

5/27/2026

7/15/2026

165

IFF-RR-MEP Safe off

1d

5/27/2026

5/27/2026

IFF-RR-MEP Safe off

166

IFF-RR-Clean Demo Flooring and Tile

3d

5/28/2026

6/1/2026

IFF-RR-Clean Demo Flooring and Tile

167

IFF-RR-Sawcut & Demo Concrete

2d

6/2/2026

6/3/2026

IFF-RR-Sawcut & Demo Concrete

168

IFF-RR-Underslab Plumbing

3d

6/4/2026

6/8/2026

IFF-RR-Underslab Plumbing

169

IFF-RR- Slab Patchbacks

1d

6/9/2026

6/9/2026

IFF-RR- Slab Patchbacks

170

IFF-RR-MEP Rough in

5d

6/10/2026

6/16/2026

IFF-RR-MEP Rough in

171

IFF-RR-Hang/Tape/Finish Drywall

6d

6/17/2026

6/24/2026

IFF-RR-Hang/Tape/Finish Drywall

172

IFF-RR-Prime and First Coat Lids

2d

6/25/2026

6/26/2026

IFF-RR-Prime and First Coat Lids

173

IFF-RR-Install Floor and Wall Tile

5d

6/29/2026

7/6/2026

174

IFF-RR-Install MEP Trim

3d

7/7/2026

7/9/2026

IFF-RR-Install MEP Trim

175

IFF-RR-Install Partitions

2d

7/7/2026

7/8/2026

IFF-RR-Install Partitions

176

IFF-RR-Install Accessories

2d

7/10/2026

7/13/2026

IFF-RR-Install Accessories

177

IFF-RR-Final Paint

3d

7/10/2026

7/14/2026

IFF-RR-Final Paint

178

IFF-SCI-Final Clean

1d

7/15/2026

7/15/2026

IFF-SCI-Final Clean

Electrical Upgrades

82d

3/23/2026

7/16/2026

Electrical Upgrades - Panel G

8d

5/26/2026

6/4/2026

179

IFF-EU-Shut Down and Safeoff MDC

1d

5/26/2026

5/26/2026

IFF-EU-Shut Down and Safeoff MDC

180

IFF-EU-Demo Panel G

1d

5/27/2026

5/27/2026

IFF-EU-Demo Panel G

181

IFF-EU-Install New Panel G

3d

5/28/2026

6/1/2026

IFF-EU-Install New Panel G

182

IFF-EU-Test and Inspect

2d

6/2/2026

6/3/2026

IFF-EU-Test and Inspect

183

IFF-EU-Energize MDC

1d

6/4/2026

6/4/2026

IFF-EU-Energize MDC

Electrical Upgrades - Panel UV2

8d

7/7/2026

7/16/2026

IFF-EU-Shut Down and Safeoff MDC

1d

7/7/2026

7/7/2026

184

Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School

IFF-RR-Install Floor and Wall Tile

IFF-EU-Shut Down and Safeoff MDC

Rev. date: 10/17/2025 10:27:33 AM Job #: Southern Hills Middle School

Data Date: 10/17/2025

Page 8 of 14

3. Print View Filter: No Summary Tasks

Line

Name

Duration APC

Start

Finish

2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5

185

IFF-EU-Demo Panel UV2

1d

7/8/2026

7/8/2026

IFF-EU-Demo Panel UV2

186

IFF-EU-Install New Panel UV2

3d

7/9/2026

7/13/2026

IFF-EU-Install New Panel UV2

187

IFF-EU-Test and Inspect

2d

7/14/2026

7/15/2026

IFF-EU-Test and Inspect

IFF-EU-Energize MDC

IFF-EU-Energize MDC

1d

7/16/2026

7/16/2026

Electrical Upgrades - Panel K

8d

6/9/2026

6/18/2026

189

IFF-EU-Shut Down and Safeoff MDC

1d

6/9/2026

6/9/2026

IFF-EU-Shut Down and Safeoff MDC

190

IFF-EU-Demo Panel K

1d

6/10/2026

6/10/2026

IFF-EU-Demo Panel K

191

IFF-EU-Install New Panel K

3d

6/11/2026

6/15/2026

IFF-EU-Install New Panel K

192

IFF-EU-Test and Inspect

2d

6/16/2026

6/17/2026

IFF-EU-Test and Inspect

193

IFF-EU-Energize MDC

1d

6/18/2026

6/18/2026

IFF-EU-Energize MDC

Electrical Upgrades - Panel UV1

8d

7/7/2026

7/16/2026

194

IFF-EU-Shut Down and Safeoff MDC

1d

7/7/2026

7/7/2026

IFF-EU-Shut Down and Safeoff MDC

195

IFF-EU-Demo Panel UV1

1d

7/8/2026

7/8/2026

IFF-EU-Demo Panel UV1

196

IFF-EU-Install New Panel UV1

3d

7/9/2026

7/13/2026

IFF-EU-Install New Panel UV1

197

IFF-EU-Test and Inspect

2d

7/14/2026

7/15/2026

IFF-EU-Test and Inspect

198

IFF-EU-Energize MDC

1d

7/16/2026

7/16/2026

IFF-EU-Energize MDC

Electrical Upgrades - Panel A

8d

7/7/2026

7/16/2026

199

IFF-EU-Shut Down and Safeoff MDC

1d

7/7/2026

7/7/2026

IFF-EU-Shut Down and Safeoff MDC

200

IFF-EU-Demo Panel A

1d

7/8/2026

7/8/2026

IFF-EU-Demo Panel A

201

IFF-EU-Install New Panel A

3d

7/9/2026

7/13/2026

IFF-EU-Install New Panel A

202

IFF-EU-Test and Inspect

2d

7/14/2026

7/15/2026

IFF-EU-Test and Inspect

203

IFF-EU-Energize MDC

1d

7/16/2026

7/16/2026

IFF-EU-Energize MDC

Electrical Upgrades - Panel B

8d

7/7/2026

7/16/2026

204

IFF-EU-Shut Down and Safeoff MDC

1d

7/7/2026

7/7/2026

IFF-EU-Shut Down and Safeoff MDC

205

IFF-EU-Demo Panel B

1d

7/8/2026

7/8/2026

IFF-EU-Demo Panel B

206

IFF-EU-Install New Panel B

3d

7/9/2026

7/13/2026

IFF-EU-Install New Panel B

207

IFF-EU-Test and Inspect

2d

7/14/2026

7/15/2026

IFF-EU-Test and Inspect

208

IFF-EU-Energize MDC

1d

7/16/2026

7/16/2026

IFF-EU-Energize MDC

Electrical Upgrades - Panel E

8d

7/7/2026

7/16/2026

IFF-EU-Shut Down and Safeoff MDC

1d

7/7/2026

7/7/2026

188

209

Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School

IFF-EU-Shut Down and Safeoff MDC

Rev. date: 10/17/2025 10:27:33 AM Job #: Southern Hills Middle School

Data Date: 10/17/2025

Page 9 of 14

3. Print View Filter: No Summary Tasks

Line

Name

Duration APC

Start

Finish

2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5

210

IFF-EU-Demo Panel E

1d

7/8/2026

7/8/2026

IFF-EU-Demo Panel E

211

IFF-EU-Install New Panel E

3d

7/9/2026

7/13/2026

IFF-EU-Install New Panel E

212

IFF-EU-Test and Inspect

2d

7/14/2026

7/15/2026

IFF-EU-Test and Inspect

IFF-EU-Energize MDC

IFF-EU-Energize MDC

1d

7/16/2026

7/16/2026

Electrical Upgrades - Panel F

8d

7/7/2026

7/16/2026

214

IFF-EU-Shut Down and Safeoff MDC

1d

7/7/2026

7/7/2026

IFF-EU-Shut Down and Safeoff MDC

215

IFF-EU-Demo Panel F

1d

7/8/2026

7/8/2026

IFF-EU-Demo Panel F

216

IFF-EU-Install New Panel F

3d

7/9/2026

7/13/2026

IFF-EU-Install New Panel F

217

IFF-EU-Test and Inspect

2d

7/14/2026

7/15/2026

IFF-EU-Test and Inspect

218

IFF-EU-Energize MDC

1d

7/16/2026

7/16/2026

IFF-EU-Energize MDC

Electrical Upgrades - Panel N

8d

7/7/2026

7/16/2026

219

IFF-EU-Shut Down and Safeoff MDC

1d

7/7/2026

7/7/2026

IFF-EU-Shut Down and Safeoff MDC

220

IFF-EU-Demo Panel N

1d

7/8/2026

7/8/2026

IFF-EU-Demo Panel N

221

IFF-EU-Install New Panel N

3d

7/9/2026

7/13/2026

IFF-EU-Install New Panel N

222

IFF-EU-Test and Inspect

2d

7/14/2026

7/15/2026

IFF-EU-Test and Inspect

223

IFF-EU-Energize MDC

1d

7/16/2026

7/16/2026

IFF-EU-Energize MDC

Electrical Upgrades - Panel J

8d

6/2/2026

6/11/2026

224

IFF-EU-Shut Down and Safeoff MDC

1d

6/2/2026

6/2/2026

IFF-EU-Shut Down and Safeoff MDC

225

IFF-EU-Demo J

1d

6/3/2026

6/3/2026

IFF-EU-Demo J

226

IFF-EU-Install New J

3d

6/4/2026

6/8/2026

IFF-EU-Install New J

227

IFF-EU-Test and Inspect

2d

6/9/2026

6/10/2026

IFF-EU-Test and Inspect

228

IFF-EU-Energize MDC

1d

6/11/2026

6/11/2026

IFF-EU-Energize MDC

Electrical Upgrades - Shop Main & Shop Sub

10d

6/16/2026

6/29/2026

229

IFF-EU-Shut Down and Safeoff MDC

1d

6/16/2026

6/16/2026

IFF-EU-Shut Down and Safeoff MDC

230

IFF-EU-Demo Shop Main & Sub

1d

6/17/2026

6/17/2026

IFF-EU-Demo Shop Main & Sub

231

IFF-EU-Install New Shop Main & Sub

5d

6/18/2026

6/24/2026

IFF-EU-Install New Shop Main & Sub

232

IFF-EU-Test and Inspect

2d

6/25/2026

6/26/2026

IFF-EU-Test and Inspect

IFF-EU-Energize MDC

213

233

234

IFF-EU-Energize MDC

1d

6/29/2026

6/29/2026

Electrical Upgrades - Sub Distribution A Wing - I Line 800A

10d

6/16/2026

6/29/2026

IFF-EU-Shut Down and Safeoff MDC

1d

6/16/2026

6/16/2026

Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School

IFF-EU-Shut Down and Safeoff MDC

Rev. date: 10/17/2025 10:27:33 AM Job #: Southern Hills Middle School

Data Date: 10/17/2025

Page 10 of 14

3. Print View Filter: No Summary Tasks

Line

Name

Duration APC

Start

Finish

2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5

235

IFF-EU-Demo A Wing

1d

6/17/2026

6/17/2026

236

IFF-EU-Install New A Wing

5d

6/18/2026

6/24/2026

IFF-EU-Install New A Wing

237

IFF-EU-Test and Inspect

2d

6/25/2026

6/26/2026

IFF-EU-Test and Inspect

IFF-EU-Energize MDC

IFF-EU-Demo A Wing

IFF-EU-Energize MDC

1d

6/29/2026

6/29/2026

Electrical Upgrades - Sub Distribution B Wing Mech - I Line 1200A

10d

6/25/2026

7/9/2026

239

IFF-EU-Shut Down and Safeoff MDC

1d

6/25/2026

6/25/2026

IFF-EU-Shut Down and Safeoff MDC

240

IFF-EU-Demo B Wing

1d

6/26/2026

6/26/2026

IFF-EU-Demo B Wing

241

IFF-EU-Install New B Wing

5d

6/29/2026

7/6/2026

IFF-EU-Install New B Wing

242

IFF-EU-Test and Inspect

2d

7/7/2026

7/8/2026

IFF-EU-Test and Inspect

243

IFF-EU-Energize MDC

1d

7/9/2026

7/9/2026

IFF-EU-Energize MDC

Fire Alarm Upgrades

59d

4/8/2026

6/30/2026

244

IFF-FAU-Early Fire Alarm Wire Pull (Spring Break Start Night Work)

20d

4/8/2026

5/5/2026

IFF-FAU-Early Fire Alarm Wire Pull (Spring Break Start Night Work)

245

IFF-FAU-EM Battery Pack Replacements (Night Work)

10d

4/22/2026

5/5/2026

IFF-FAU-EM Battery Pack Replacements (Night Work)

246

IFF-FAU-Install New Devices

5d

5/26/2026

6/1/2026

IFF-FAU-Install New Devices

247

IFF-FAU-Demo Old Panel

5d

5/26/2026

6/1/2026

IFF-FAU-Demo Old Panel

248

IFF-FAU-Install New Panel and Terminate

10d

6/2/2026

6/15/2026

249

IFF-FAU-Program Panel

5d

6/16/2026

6/22/2026

250

IFF-FAU-Test Fire Alarm Panel

6d

6/23/2026

6/30/2026

238

IFF-FAU-Install New Panel and Terminate

IFF-FAU-Program Panel

IFF-FAU-Test Fire Alarm Panel

PA/ Sound System Upgrades

78d

3/23/2026

7/10/2026

251

IFF-EU-Pull new Wire for Speakers (Spring Break Start Night work)

10d

3/23/2026

4/3/2026

252

IFF-EU-Install New Speakers

20d

5/26/2026

6/22/2026

IFF-EU-Install New Speakers

253

IFF-EU-Install New Head End

2d

6/23/2026

6/24/2026

IFF-EU-Install New Head End

254

IFF-EU-Test New Head End and Speakers

6d

6/25/2026

7/2/2026

255

IFF-EU-Final Clean

5d

7/6/2026

7/10/2026

CTE Upgrades

46d

5/26/2026

7/29/2026

Wood Shop

46d

5/26/2026

7/29/2026

256

IFF-WS-Owner Move

1d

5/26/2026

5/26/2026

IFF-WS-Owner Move

257

IFF-WS-MEP Safeoff

1d

5/26/2026

5/26/2026

IFF-WS-MEP Safeoff

258

IFF-WS-Abatement Demo & Dust collector

5d

5/27/2026

6/2/2026

IFF-WS-Abatement Demo & Dust collector

259

IFF-WS-Clean Demo Remaining Items

2d

6/3/2026

6/4/2026

IFF-WS-Clean Demo Remaining Items

Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School

IFF-EU-Pull new Wire for Speakers (Spring Break Start Night work)

IFF-EU-Test New Head End and Speakers

IFF-EU-Final Clean

Rev. date: 10/17/2025 10:27:33 AM Job #: Southern Hills Middle School

Data Date: 10/17/2025

Page 11 of 14

3. Print View Filter: No Summary Tasks

Line

Name

Duration APC

Start

Finish

2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5

260

IFF-WS-Route New Overhead MEP

4d

6/5/2026

6/10/2026

IFF-WS-Route New Overhead MEP

261

IFF-WS-Frame New Walls & Set Door Frames

2d

6/10/2026

6/11/2026

IFF-WS-Frame New Walls & Set Door Frames

262

IFF-WS-MEP Wall Rough in

3d

6/12/2026

6/16/2026

IFF-WS-MEP Wall Rough in

263

IFF-WS-Hang/ Tape/ Finish Drywall

6d

6/17/2026

6/24/2026

IFF-WS-Hang/ Tape/ Finish Drywall

264

IFF-WS-Prime and First Coat Walls &Ceilings

4d

6/25/2026

6/30/2026

IFF-WS-Prime and First Coat Walls &Ceilings

265

IFF-WS-Set and MEP Connections to Dust Collector

5d

7/1/2026

7/8/2026

IFF-WS-Set and MEP Connections to Dust Collector

266

IFF-WS-Install ACT Grid

2d

7/1/2026

7/2/2026

IFF-WS-Install ACT Grid

267

IFF-WS-MEP Ceiling Trim Out

3d

7/6/2026

7/8/2026

IFF-WS-MEP Ceiling Trim Out

268

IFF-WS-Refinish Wood Flooring

5d

7/6/2026

7/10/2026

IFF-WS-Refinish Wood Flooring

269

IFF-WS-Above Ceiling Inspections

2d

7/9/2026

7/10/2026

IFF-WS-Above Ceiling Inspections

270

IFF-WS-White out Ceilings

1d

7/13/2026

7/13/2026

IFF-WS-White out Ceilings

271

IFF-WS-Install Casework

5d

7/13/2026

7/17/2026

IFF-WS-Install Casework

272

IFF-WS-Final Clean

3d

7/14/2026

7/16/2026

IFF-WS-Final Clean

273

IFF-WS-Dust Collector & EF Start up

2d

7/17/2026

7/20/2026

IFF-WS-Dust Collector & EF Start up

274

IFF-WS-Final Clean

1d

7/20/2026

7/20/2026

IFF-WS-Final Clean

275

IFF-WS-Final Paint

2d

7/21/2026

7/22/2026

IFF-WS-Final Paint

276

IFF-WS-Install Carpet and Base

2d

7/23/2026

7/24/2026

IFF-WS-Install Carpet and Base

277

IFF-WS-Install Doors & Hardware

3d

7/27/2026

7/29/2026

IFF-WS-Install Doors & Hardware

Culinary Arts

18d

5/26/2026

6/18/2026

278

IFF-CA-Owner Move

1d

5/26/2026

5/26/2026

IFF-CA-Owner Move

279

IFF-CA-MEP Safeoff

1d

5/28/2026

5/28/2026

IFF-CA-MEP Safeoff

280

IFF-CA-Demo Section of Flooring and Sawcut

3d

5/29/2026

6/2/2026

IFF-CA-Demo Section of Flooring and Sawcut

281

IFF-CA-Demo ADA Work

2d

5/29/2026

6/1/2026

IFF-CA-Demo ADA Work

282

IFF-CA-Install New Casework

3d

6/2/2026

6/4/2026

IFF-CA-Install New Casework

283

IFF-CA-Underground Plumbing

4d

6/3/2026

6/8/2026

IFF-CA-Underground Plumbing

284

IFF-CA-MEP Wall Casework Trim

2d

6/5/2026

6/8/2026

IFF-CA-MEP Wall Casework Trim

285

IFF-CA-Concrete Patchback

1d

6/9/2026

6/9/2026

IFF-CA-Concrete Patchback

286

IFF-CA-Paint Ceiling

5d

6/9/2026

6/15/2026

IFF-CA-Paint Ceiling

287

IFF-CA-Install New Flooring and Base

2d

6/16/2026

6/17/2026

IFF-CA-Install New Flooring and Base

288

IFF-CA-Final Clean

1d

6/18/2026

6/18/2026

IFF-CA-Final Clean

Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School

Rev. date: 10/17/2025 10:27:33 AM Job #: Southern Hills Middle School

Data Date: 10/17/2025

Page 12 of 14

3. Print View Filter: No Summary Tasks

Line

Name

2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5

Duration APC

Start

Finish

Art Room

39d

5/26/2026

7/20/2026

289

IFF-AR-Owner Move

1d

5/26/2026

5/26/2026

IFF-AR-Owner Move

290

IFF-AR-MEP Safeoff

1d

5/27/2026

5/27/2026

IFF-AR-MEP Safeoff

291

IFF-AR-Abatement Demo

5d

5/28/2026

6/3/2026

IFF-AR-Abatement Demo

292

IFF-AR-Demo Remaining Items

2d

6/4/2026

6/5/2026

IFF-AR-Demo Remaining Items

293

IFF-AR-Sawcut and Demo Concrete for Sinks

3d

6/8/2026

6/10/2026

IFF-AR-Sawcut and Demo Concrete for Sinks

294

IFF-AR-Install Underground Plumbing

4d

6/11/2026

6/16/2026

IFF-AR-Install Underground Plumbing

295

IFF-AR-FF/R/P Concrete at Sinks

2d

6/16/2026

6/17/2026

IFF-AR-FF/R/P Concrete at Sinks

296

IFF-AR-MEP Wall Rough in

3d

6/18/2026

6/22/2026

IFF-AR-MEP Wall Rough in

297

IFF-AR-Hang/ Tape/ Finish Drywall

6d

6/23/2026

6/30/2026

IFF-AR-Hang/ Tape/ Finish Drywall

298

IFF-AR-Prime and First Coat Walls

2d

6/29/2026

6/30/2026

IFF-AR-Prime and First Coat Walls

299

IFF-AR-Paint Ceiling

2d

7/1/2026

7/2/2026

IFF-AR-Paint Ceiling

300

IFF-AR-Above Ceiling Inspections

2d

7/6/2026

7/7/2026

IFF-AR-Above Ceiling Inspections

301

IFF-AR-White out Ceilings

1d

7/8/2026

7/8/2026

IFF-AR-White out Ceilings

302

IFF-AR-MEP Wall Trim out

3d

7/9/2026

7/13/2026

IFF-AR-MEP Wall Trim out

303

IFF-AR-Final Paint

2d

7/14/2026

7/15/2026

IFF-AR-Final Paint

304

IFF-AR-Install Carpet and Base

2d

7/16/2026

7/17/2026

IFF-AR-Install Carpet and Base

305

IFF-AR-Final Clean

1d

7/20/2026

7/20/2026

IFF-AR-Final Clean

Cafeteria Upgrades

16d

5/26/2026

6/16/2026

306

IFF-CU-Owner Move

1d

5/26/2026

5/26/2026

307

IFF-CU-Abatement of Flooring

6d

5/27/2026

6/3/2026

IFF-CU-Abatement of Flooring

308

IFF-CU-Paint Ceiling

4d

6/4/2026

6/9/2026

IFF-CU-Paint Ceiling

309

IFF-CU-Install Flooring and Base

4d

6/10/2026

6/15/2026

IFF-CU-Install Flooring and Base

310

IFF-CU-Final Clean

1d

6/16/2026

6/16/2026

IFF-CU-Final Clean

Mechanical Upgrades

12d

5/26/2026

6/10/2026

Sump Pump Replacement

12d

5/26/2026

6/10/2026

311

IFF-SP-MEP Safeoff Sump Pump

2d

5/26/2026

5/27/2026

IFF-SP-MEP Safeoff Sump Pump

312

IFF-SP-Evacuate Existing Material From Pit

2d

5/28/2026

5/29/2026

IFF-SP-Evacuate Existing Material From Pit

313

IFF-SP-Install New Sump Pump

2d

6/1/2026

6/2/2026

IFF-SP-Install New Sump Pump

314

IFF-SP-Hook up Electrical

2d

6/3/2026

6/4/2026

IFF-SP-Hook up Electrical

Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School

IFF-CU-Owner Move

Rev. date: 10/17/2025 10:27:33 AM Job #: Southern Hills Middle School

Data Date: 10/17/2025

Page 13 of 14

3. Print View Filter: No Summary Tasks

Line

Name

315 316

2024 2025 2026 2027 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar A 12 26 9 23 7 21 4 18 2 16 30 13 27 10 24 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 6 20 3 17 1 15 29 12 26 9 23 9 23 6 20 4 18 1 15 29 13 27 10 24 7 21 5 19 2 16 30 14 28 11 25 8 22 8 22 5

Duration APC

Start

Finish

IFF-SP-Hook up Controls

2d

6/5/2026

6/8/2026

IFF-SP-Hook up Controls

IFF-SP- Test Controls

2d

6/9/2026

6/10/2026

IFF-SP- Test Controls

Roof Install and Improvements

33d

5/26/2026

7/10/2026

317

EFI-RII-Demo Roofs and Install EF's

2d

5/26/2026

5/27/2026

EFI-RII-Demo Roofs and Install EF's

318

EFI-RII-Set New EF's

3d

5/28/2026

6/1/2026

EFI-RII-Set New EF's

319

EFI-RII-MEP Connections to EF's

5d

7/6/2026

7/10/2026

Site Improvments

37d

5/26/2026

7/16/2026

Parking Lot

37d

5/26/2026

7/16/2026

EFI-RII-MEP Connections to EF's

Parking Lot Improvements

37d

5/26/2026

7/16/2026

320

SI-PL-Demo Concrete Walks

10d

5/26/2026

6/8/2026

SI-PL-Demo Concrete Walks

321

SI-PL-F/R/P Concrete

7d

6/9/2026

6/17/2026

SI-PL-F/R/P Concrete

322

SI-PL-Cure Time Before Paint

15d

6/18/2026

7/9/2026

SI-PL-Cure Time Before Paint

323

SI-PL-Stripe New Parking Lot

2d

7/10/2026

7/13/2026

SI-PL-Stripe New Parking Lot

324

SI-PL-Final Clean

3d

7/14/2026

7/16/2026

SI-PL-Final Clean

2026 Closeout

53d

7/17/2026

9/30/2026

325

2026-CO-Site Punchwalk

1d

7/17/2026

7/17/2026

2026-CO-Site Punchwalk

326

2026-CO-Final MEP Inspections

1d

7/21/2026

7/21/2026

2026-CO-Final MEP Inspections

327

2026-CO-Final Clean

5d

7/21/2026

7/27/2026

2026-CO-Final Clean

328

2026-CO- MEP TAB

3d

7/28/2026

7/30/2026

2026-CO- MEP TAB

329

2026-CO-Punch Walks

1d

7/28/2026

7/28/2026

2026-CO-Punch Walks

330

2026-CO-MEP Commissioning

2d

7/31/2026

8/3/2026

2026-CO-MEP Commissioning

331

2026-CO-TCO Inspections

1d

7/31/2026

7/31/2026

2026-CO-TCO Inspections

332

2026-CO-Owner Move In

1d

8/3/2026

8/3/2026

2026-CO-Owner Move In

333

2026-CO-Construction Final Completion of Documentation

41d

8/4/2026

9/30/2026

Boulder Valley RFP 25-04 GMGC Project Scope #1 Southern Hills Middle School

2026-CO-Construction Final Completion of Documentation

Rev. date: 10/17/2025 10:27:33 AM Job #: Southern Hills Middle School

Data Date: 10/17/2025

Page 14 of 14

3. Print View Filter: No Summary Tasks

Exhibit E

Insurance Certificate Itemization of Cost Itemization of the GMP Dollars requested for long lead equipment and material packages

Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20

Policy Number: AS2-641-445189-013 Issued By: Liberty Mutual Fire Insurance Co.

THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. NOTICE OF CANCELLATION TO THIRD PARTIES This endorsement modifies insurance provided under the following: BUSINESS AUTO COVERAGE PART MOTOR CARRIER COVERAGE PART GARAGE COVERAGE PART TRUCKERS COVERAGE PART EXCESS AUTOMOBILE LIABILITY INDEMNITY COVERAGE PART SELF-INSURED TRUCKER EXCESS LIABILITY COVERAGE PART COMMERCIAL GENERAL LIABILITY COVERAGE PART EXCESS COMMERCIAL GENERAL LIABILITY COVERAGE PART PRODUCTS/COMPLETED OPERATIONS LIABILITY COVERAGE PART LIQUOR LIABILITY COVERAGE PART

Schedule Name of Other Person(s)/ Organization(s): Per schedule on file

Email Address or mailing address: Per schedule on file

Number Days Notice: 45

A. If we cancel this policy for any reason other than nonpayment of premium, we will notify the persons or organizations shown in the Schedule above. We will send notice to the email or mailing address listed above at least 10 days, or the number of days listed above, if any, before the cancellation becomes effective. In no event does the notice to the third party exceed the notice to the first named insured. B. This advance notification of a pending cancellation of coverage is intended as a courtesy only. Our failure to provide such advance notification will not extend the policy cancellation date nor negate cancellation of the policy. All other terms and conditions of this policy remain unchanged.

LIM 99 01 05 11

© 2011, Liberty Mutual Group of Companies. All rights reserved. Includes copyrighted material of Insurance Services Office, Inc. with its permission.

Page 1 of 1

Policy Number EB2-641-445189-023 Issued by Liberty Mutual Fire Insurance Company THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. NOTICE OF CANCELLATION TO THIRD PARTIES This endorsement modifies insurance provided under the following: BUSINESS AUTO COVERAGE PART MOTOR CARRIER COVERAGE PART GARAGE COVERAGE PART TRUCKERS COVERAGE PART EXCESS AUTOMOBILE LIABILITY INDEMNITY COVERAGE PART SELF-INSURED TRUCKER EXCESS LIABILITY COVERAGE PART COMMERCIAL GENERAL LIABILITY COVERAGE PART EXCESS COMMERCIAL GENERAL LIABILITY COVERAGE PART PRODUCTS/COMPLETED OPERATIONS LIABILITY COVERAGE PART LIQUOR LIABILITY COVERAGE PART COMMERCIAL LIABILITY – UMBRELLA COVERAGE FORM

Schedule Name of Other Person(s) / Organization(s):

Email Address or mailing address:

Number Days Notice:

Per schedule on file with Broker

Per schedule on file with Broker

45

A. If we cancel this policy for any reason other than nonpayment of premium, we will notify the persons or organizations shown in the Schedule above. We will send notice to the email or mailing address listed above at least 10 days, or the number of days listed above, if any, before the cancellation becomes effective. In no event does the notice to the third party exceed the notice to the first named insured. B. This advance notification of a pending cancellation of coverage is intended as a courtesy only. Our failure to provide such advance notification will not extend the policy cancellation date nor negate cancellation of the policy. All other terms and conditions of this policy remain unchanged.

LIM 99 01 05 11

© 2011 Liberty Mutual Group of Companies. All rights reserved. Includes copyrighted material of Insurance Services Office, Inc., with its permission.

Page 1 of 1

THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

DESIGNATED CONSTRUCTION PROJECT(S) GENERAL AGGREGATE LIMIT This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART SCHEDULE Designated Construction Project(s): All construction projects not located at premises owned, leased or rented by a Named Insured.

Information required to complete this Schedule, if not shown above, will be shown in the Declarations. A. For all sums which the insured becomes legally obligated to pay as damages caused by "occurrences" under Section I – Coverage A, and for all medical expenses caused by accidents under Section I – Coverage C, which can be attributed only to ongoing operations at a single designated construction project shown in the Schedule above: 1. A separate Designated Construction Project General Aggregate Limit applies to each designated construction project, and that limit is equal to the amount of the General Aggregate Limit shown in the Declarations. 2. The Designated Construction Project General Aggregate Limit is the most we will pay for the sum of all damages under Coverage A, except damages because of "bodily injury" or "property damage" included in the "productscompleted operations hazard", and for medical expenses under Coverage C regardless of the number of:

3. Any payments made under Coverage A for damages or under Coverage C for medical expenses shall reduce the Designated Construction Project General Aggregate Limit for that designated construction project. Such payments shall not reduce the General Aggregate Limit shown in the Declarations nor shall they reduce any other Designated Construction Project General Aggregate Limit for any other designated construction project shown in the Schedule above. 4. The limits shown in the Declarations for Each Occurrence, Damage To Premises Rented To You and Medical Expense continue to apply. However, instead of being subject to the General Aggregate Limit shown in the Declarations, such limits will be subject to the applicable Designated Construction Project General Aggregate Limit.

a. Insureds; b. Claims made or "suits" brought; or c. Persons or organizations making claims or bringing "suits".

CG 25 03 05 09

© Insurance Services Office, Inc., 2008

Page 1 of 2

B. For all sums which the insured becomes legally obligated to pay as damages caused by "occurrences" under Section I – Coverage A, and for all medical expenses caused by accidents under Section I – Coverage C, which cannot be attributed only to ongoing operations at a single designated construction project shown in the Schedule above: 1. Any payments made under Coverage A for damages or under Coverage C for medical expenses shall reduce the amount available under the General Aggregate Limit or the Products-completed Operations Aggregate Limit, whichever is applicable; and 2. Such payments shall not reduce any Designated Construction Project General Aggregate Limit.

Page 2 of 2

C. When coverage for liability arising out of the "products-completed operations hazard" is provided, any payments for damages because of "bodily injury" or "property damage" included in the "products-completed operations hazard" will reduce the Products-completed Operations Aggregate Limit, and not reduce the General Aggregate Limit nor the Designated Construction Project General Aggregate Limit. D. If the applicable designated construction project has been abandoned, delayed, or abandoned and then restarted, or if the authorized contracting parties deviate from plans, blueprints, designs, specifications or timetables, the project will still be deemed to be the same construction project. E. The provisions of Section III – Limits Of Insurance not otherwise modified by this endorsement shall continue to apply as stipulated.

© Insurance Services Office, Inc., 2008

CG 25 03 05 09

THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

ADDITIONAL INSURED – OWNERS, LESSEES OR CONTRACTORS – SCHEDULED PERSON OR ORGANIZATION This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART SCHEDULE

Name of Person or Organization: Any person or organization with whom you have agreed, through written contract, agreement or permit to provide additional insured coverage but only where this specific edition of the form is contractually required. Locations: Any location where you have agreed, through written, contract, agreement or permit, to provide additional insured coverage for on-going operations

(If no entry appears above, information required to complete this endorsement will be shown in the Declarations as applicable to this endorsement.) A. Section II – Who Is An Insured is amended to include as an insured the person or organization shown in the Schedule, but only with respect to liability arising out of your ongoing operations performed for that insured. B. With respect to the insurance afforded to these additional insureds, the following exclusion is added: 2. Exclusions

(1) All work, including materials, parts or equipment furnished in connection with such work, on the project (other than service, maintenance or repairs) to be performed by or on behalf of the additional insured(s) at the site of the covered operations has been completed; or

This insurance does not apply to "bodily injury" or "property damage" occurring after:

CG 20 10 10 01

© ISO Properties, Inc., 2000

Page 1 of 2

(2) That portion of "your work" out of which the injury or damage arises has been put to its intended use by any person or organization other than another contractor or subcontractor engaged in performing operations for a principal as a part of the same project.

This endorsement is executed by the Premium $ Effective Date

Expiration Date

For attachment to Policy No. EB2-641-445189-023 Audit Basis Issued To

Countersigned by Authorized Representative

Issued

Page 2 of 2

Sales Office and No.

© ISO Properties, Inc., 2000

End. Serial No.

CG 20 10 10 01



THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

ADDITIONAL INSURED – OWNERS, LESSEES OR CONTRACTORS – COMPLETED OPERATIONS This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART SCHEDULE Name of Person or Organization: Any person or organization to whom or to which you are required to provide additional insured status in a written contract, agreement or permit except where such contract or agreement is prohibited, but only where this specific edition of the form is contractually required. Location And Description of Completed Operations: Any location where you have agreed, through written, contract, agreement or permit, to provide additional insured coverage for completed operations Additional Premium:

(If no entry appears above, information required to complete this endorsement will be shown in the Declarations as applicable to this endorsement.) Section II – Who Is An Insured is amended to include as an insured the person or organization shown in the Schedule, but only with respect to liability arising out of "your work" at the location designated and described in the schedule of this endorsement performed for that insured and included in the "products-completed operations hazard".

This endorsement is executed by the Premium $ Effective Date

Expiration Date

For attachment to Policy No.EB2-641-445189-023

TB2-641-445189-028 Audit Basis Issued To

Countersigned by Authorized Representative

Issued

CG 20 37 10 01

Sales Office and No.

© ISO Properties, Inc., 2000

End. Serial No.

Page 1 of 1

WA2-64D-445189-063

03/01/2023

WC2-641-445189-073

Exhibit F

Performance Bond Itemization ofGMP Cost Itemization of the Performance Bond will befor provided afterequipment amendment and & change orderpackages for the GMP Dollars requested long lead material total amount. This will be provided once amendment two is executed.

Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20

Exhibit G

Labor and Material Payment Bond Itemization ofGMP Cost Itemization of the Labor and Material Payment Bond lead will beequipment provided after amendment & change order Dollars requested for long and material packages for the GMP total amount. This will be provided once amendment two is executed.

Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20

Exhibit H Alternates Prices

Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20

8

9

10

11

12

13

16

17

24

25

Price Options List K1224 - BVSD - Southern Hills Middle School Current Cost Estimate Target Budget

$2,723,427 Pending Cost Reduction $2,306,101

Delta (Overrun)

#REF!

$417,326

$194,670 Item Number

Date

Description of Item

Status

Pending Cost Reduction

Pending Cost Addition

$243,814 Accepted Cost

Rejected Cost

Comments

Decision Date

Alternates 001

10/17/2025 Alternate 1 - Replace corridor finishes on Level 1 and 2)

Rejected

002

10/17/2025 Alternate 2 - Admin Suite Paint Refresh

Pending

$112,971

10/24/2025

$4,266

003

10/17/2025 Alternate 3 - Replace Additional Electrical Panels

Accepted

Included in Current Cost

10/24/2025

004

10/17/2025 Alternate 4 - Replace Intercom System

Accepted

Included in Current Cost

10/24/2025

005

10/17/2025 Alternate 5 - Replace Food Lab Casework

Pending

$117,772

006

10/17/2025 Alternate 6 - Stair West of Plaza

Pending

$39,896

007

10/17/2025 Alternate 7 (CTE 1.2 - Added Window)

Rejected

One water spray test is include for the $38,636 window replacement.

10/24/2025 10/24/2025 10/24/2025

008

10/17/2025 Alternate 9 - New Window at Wood Shop

Rejected

One water spray test is include for the $36,378 window replacement.

009

10/17/2025 Alternate 10 - New Lockers

Rejected

$37,779

010

10/17/2025 Alternate 11 - Sump Pump

Rejected

$18,050

011

10/17/2025 Alternate 12 - Art Room Light Fixture

Pending

012

10/17/2025 Alternate 13 - Kiln

Pending

$8,291

013

10/17/2025 Alternate 14 - LVT Entire Food Lab

Pending

$16,677

014

10/17/2025 Alternate 15 - Hot Dip Galv Exterior Steel ILO HM Primer/Paint

Pending

015

10/17/2025 Alternate 16 - Exterior Site Plaza

Accepted

10/24/2025 AP is working on a revised price based on a less costly fixture.

$7,761

No Difference in Price for Hot Dip Galv. Included in Current Cost

10/24/2025

Exhibit IH Alternates Prices Unit Prices This exhibit is not applicable at this time.

Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20

Exhibit J H Alternates Prices Allowances

Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20

Allowances Report DESCRIPTION

QTY UOM

UNIT PRICE

TOTAL COST

NOTES / COMMENTS

ALLOWANCES: Building 05 Metals

$2,043

05 50 00 Metal Fabrications 05505 Access Fixed Ladders - Exterior Renewal Allowance

$2,043 1.00 allow

2,043.00

Subtotal 05 50 00 Metal Fabrications

$2,043 $2,043

Subtotal 05 Metals

$2,043

06 Woods, Plastics and Composites

$5,000

06 22 00 Finish Carpentry 06455 Food Lab Casework Repair Allowance

$5,000 1.00 allow

5,000.00

Subtotal 06 22 00 Finish Carpentry

$5,000

$5,000

09 Finishes

$25,000

09 90 00 Painting and Coating

$25,000 1.00 allow

25,000.00

Subtotal 09 90 00 Painting and Coating

$25,000

$25,000

32 Exterior Improvements

$2,745

32 13 00 Rigid Paving

$2,745 1.00 allow

2,745.00

$2,745

Subtotal 32 13 00 Rigid Paving

$2,745

Subtotal 32 Exterior Improvements

$2,745

TOTAL ALLOWANCES: Building

DATE PRINTED: 10/29/2025

Allowance

$25,000

Subtotal 09 Finishes

32159 Exterior Wall - Damaged Concrete Allowance

Allowance

$5,000

Subtotal 06 Woods, Plastics and Composites

09700 Branding Graphic Allowance

Allowance

Allowance

$34,788

Page 4 of 20

Exhibit K

Load Hourly Labor Rate Itemization of CostSchedule Itemization of the GMP This for exhibit not applicable at this time. Dollars requested longis lead equipment and material packages

Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20

Exhibit L

Equipment Rental Rate Schedule Itemization of Cost Itemization of the GMP Dollars requested for long lead equipment and material packages

Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20

Category Bobcat Bobcat Bobcat Bobcat Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Bobcat Accessories Cleaning Equipment Cleaning Equipment Concrete Concrete Concrete Concrete Concrete Concrete Concrete Concrete Concrete Concrete Concrete Concrete Concrete Concrete Fencing Fencing Fencing Forklift Forklift Forklift Forklift

Description Bobcat Bobcat T190 Telehandler Bobcat E35 Mini-Ex Bobcat Breaker (Jackhammer) Bobcat Auger attachment drive unit lowe 1650E Bobcat Auger Bit (6" - 36") Bobcat Auger Extension (2'-4') Bobcat Forks Bobcat Rock Screen Bucket Bobcat Smooth bucket Bobcat Snow blower SR117 Caterpillar Bobcat Snow Broom Bobcat Snow Bucket Bobcat Snow Plow Caterpillar ANGLE BLADE 72IN Bobcat Sweeper Bobcat Tooth bucket Bobcat Trench Compactor Bobcat Vibratory Compactor for E35 Mini-Ex only Implement Rack Floor Buffer Floor Machine scrubber (Riding) Concrete Core Driller Concrete Georgia Buggy (Track, 14 cu-ft) Concrete Georgia Buggy (Electric, Wheeled, 12 cu-ft) Concrete Mixer Concrete Power Trowels - Walk behind Concrete Saw - Walk behind Concrete Soft Cut Saw Concrete Vibrator - high cycle Demo Saw Eco Pan Grout Pump Jumping jack Plate Compactor Rebar Cage Stands Fence Standard 6x12' per panel (.50 cents LF) Snow Fence (one time charge) T Posts (one time charge) Forklift Forklift Mover Gradall 15' Boom Gradall Material Bucket (Trash Box)

Current Charge Rate $ 2,776.00 $ 2,980.00 $ 2,627.00 $ 1,839.00 $ 1,021.00 $ 280.00 $ 26.00 $ 239.00 $ 953.00 $ 288.00 $ 1,030.00 $ 1,354.00 $ 1,545.00 $ 314.00 $ 1,368.00 $ 327.00 $ 1,746.00 $ 1,337.00 $ 515.00 $ 335.00 $ 1,669.00 $ 623.00 $ 1,133.00 $ 824.00 $ 824.00 $ 582.00 $ 1,030.00 $ 773.00 $ 639.00 $ 736.00 $ 155.00 $ 28.00 $ 568.00 $ 737.00 $ 52.00 $ 7.00 $ 10.00 $ 5.00 $ 7,264.00 $ 155.00 $ 299.00 $ 391.00

Category Forklift Forklift Gates and Barricades Gates and Barricades Gates and Barricades Gates and Barricades Gates and Barricades Gates and Barricades Generator Generator Ground Thaw Ground Thaw Office Trailer Office Trailer Office Trailer Office Trailer Accessories Office Trailer Accessories Office Trailer Accessories Office Trailer Accessories Prefab RTV Safety Safety Safety Safety Safety Safety Safety Safety Safety Safety Safety Safety Safety Safety Safety Safety Safety Small Tools Small Tools Small Tools Small Tools

Description Gradall Tipping Material Bucket (Trash Box) Spreader Bar Barricade Gates (Set of 2) Jersey Barricade Picking Tool Jersey Barriers - each Barricade Fence Panels (includes barricade) Cattle Gates (Set of 2) Man Gates Generator - (Portable) 5000k -6500k Generator - 70KW (Towable) Ground Thaw 400 (onboard generator) Ground Thaw (requires power source) Office Trailer Double wide Office Trailer Single wide Office Trailer Stairs (each, requires 2) Copier Mobile Office Cabinets Office Trailer Decking Office Trailer Handicap Ramps Fabrication & Operations Support Fee - (10% of Material Costs) Lawn Mower Zero turn 42" Baker Scaffolding Curb Ramps Steel Delineator/Traffic Cones Differential Pressure Manometer Dust Fan Fire Exinguishers Fire Extinguisher stands (plastic) Gas Monitor GX-2009 HEPACart 60 x 29 Negative Air Machine Propane Cages-Large Propane Cages-Small Road Plates Safety Roof Penetator Fall protection Slab Grabbers Stanschions (Roof Warning Line) Yellow Safety Railing and Stands Abrasive Cutoff Chop Saw Air Compressor, Hoses (Portable Porter Cable C2002) Air Conditioner/Move and Cool Banding Machine

Current Charge Rate $ 500.00 $ 129.00 $ 309.00 $ 464.00 $ 55.00 $ 82.00 $ 258.00 $ 129.00 $ 618.00 $ 2,944.00 $ 7,354.00 $ 6,705.00 $ 2,369.00 $ 1,339.00 $ 77.00 $ 393.00 $ 258.00 $ 77.00 $ 515.00 #VALUE! $ 824.00 $ 206.00 $ 162.00 $ 10.00 $ 258.00 $ 21.00 $ 15.00 $ 15.00 $ 258.00 $ 1,854.00 $ 258.00 $ 240.00 $ 155.00 $ 216.00 $ 556.00 $ 15.00 $ 15.00 $ 67.00 $ 206.00 $ 259.00 $ 515.00 $ 62.00

Category Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Small Tools Storage Container Storage Container Storage Container Storage Container Stormwater Protection Stormwater Protection Stormwater Protection Stormwater Protection Survey Survey Survey Survey Vehicle Vehicle Vehicle Vehicle Vehicle Weather Protection Weather Protection Weather Protection Weather Protection Weather Protection

Description Chipping hammer Electric (Large Hilti, Bosch or other) Crane Pad Drywall Cart Evaporative Cooling Fan (4 Ft) Fence Post Pounder (gas) Firehose (Rolls) Gang Box Jackhammer Electric Hilti 3000 Ladder 20' (Extension) Ladder-4', 6' or 8' Leaf Blower Pallet Jack Power Washer Table Saw Trash Buggy Trash Pump - Large 3 phase electric Trash Pump - Small Connex 20' Built-out Connex 20' Office Connex 40' Built-out Connex 40' Office 50/50 unit Cattle Guards Fuel Cell with (3) 5gal cans and 40 gal pump Vehicle Tracking Pads FODS Water Wheel Survey - Builders level-B20 Survey - Laser & Accessories 3900 Series Survey - Robotic Total Station (Kit) Survey - Thedolite Street Sweeper Ford F-450 (per 3 Hour) Trailer Event one time charge Truck - Water Truck Vehicle (CM's, Superintendent, Project Manager) Box Truck Concrete Blanket 14x25' Heaters LP Gas small Snow Blankets Snow blower Snow Tarps

Current Charge Rate $ 417.00 $ 155.00 $ 77.00 $ 155.00 $ 573.00 $ 11.00 $ 82.00 $ 618.00 $ 227.00 $ 33.00 $ 412.00 $ 424.00 $ 626.00 $ 412.00 $ 52.00 $ 464.00 $ 592.00 $ 285.00 $ 602.00 $ 506.00 $ 602.00 $ 258.00 $ 180.00 $ 273.00 $ 1,545.00 $ 218.00 $ 591.00 $ 2,979.00 $ 218.00 $ 402.00 $ 361.00 $ 3,395.00 $ 1,645.00 $ 2,060.00 $ 35.00 $ 31.00 $ 52.00 $ 235.00 $ 82.00

Exhibit M

General Conditions Contract Itemization ofwith CostSafety Addendum Itemization of the GMP Dollars requested for long lead equipment and material packages

Centennial MS - First Amendment to CM/GC Agreement With Adolfson & Peterson Construction dated 09-30-20

BOULDER VALLEY SCHOOL DISTRICT RE-2 BOULDER, COLORADO

GENERAL CONTRACT CONDITIONS BOND PROGRAM

GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT.................................................................................................... 2 GC 1.00

CONTRACT DOCUMENTS AND DEFINITIONS ............................................................................................................ 1

GC 2.00

REFERENCE STANDARDS .......................................................................................................................................... 2

GC 3.00

DRAWINGS AND SPECIFICATIONS ............................................................................................................................ 2

GC 4.00

ROYALTIES AND PATENTS ........................................................................................................................................ 3

GC 5.00

ITEMS COVERED BY CONTRACT PRICE ..................................................................................................................... 3

GC 6.00

EXECUTION, CORRELATION, INTENT, AND INTERPRETATION OF CONTRACT DOCUMENTS ...................................... 3

GC 7.00

MATERIALS, LABOR, FACILITIES, AND STORAGE....................................................................................................... 4

GC 8.00

PERFORMANCE AND PAYMENT BONDS ................................................................................................................... 5

GC 9.00

PERMITS AND COMPLIANCE WITH STATUTES, RULES, AND REGULATIONS .............................................................. 6

GC 10.00

SURVEYS, BENCHMARKS, MONUMENTS, STAKES, AND MEASUREMENTS ............................................................... 6

GC 11.00

CHANGED CONDITIONS ........................................................................................................................................... 7

GC 12.00

PROTECTION OF PERSONS, WORK AND PROPERTY ................................................................................................. 7

GC 13.00

WORK ON EXISTING BUILDINGS .............................................................................................................................. 8

GC 14.00

CONTRACTOR’S SUPERINTENDENCE AND SUPERVISION .......................................................................................... 8

GC 15.00

SUBSTITUTIONS ....................................................................................................................................................... 9

GC 16.00

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES ................................................................................................. 9

GC 17.00

CASH ALLOWANCE................................................................................................................................................. 10

GC 18.00

EXPEDITING MATERIALS ........................................................................................................................................ 10

GC 19.00

BLASTING .............................................................................................................................................................. 11

GC 20.00

SOIL TEST REPORT ................................................................................................................................................. 11

GC 21.00

HAZARDOUS MATERIALS ....................................................................................................................................... 11

GC 22.00

DAMAGE TO UTILITIES ........................................................................................................................................... 11

GC 23.00

CHANGES IN THE WORK ........................................................................................................................................ 12

GC 24.00

CLAIMS FOR EXTRA COST....................................................................................................................................... 13

GC 25.00

DELAYS AND EXTENSIONS OF TIME ....................................................................................................................... 13

GC 26.00

ACCESS TO WORK .................................................................................................................................................. 14

GC 27.00

CORRECTION OF WORK ......................................................................................................................................... 14

GC 28.00

OWNER’S RIGHT TO CARRY OUT WORK ................................................................................................................. 16

GC 29.00

OWNER’S RIGHT TO TERMINATE CONTRACT ......................................................................................................... 16

GC 30.00

CONSTRUCTION SCHEDULE AND PROGRESS REPORTS ........................................................................................... 16

GC 31.00

SCHEDULE OF VALUES ........................................................................................................................................... 17

GC 32.00

PAYMENT .............................................................................................................................................................. 17

GC 33.00

INSURANCE ........................................................................................................................................................... 19

GC 34.00

SEPARATE CONTRACTS .......................................................................................................................................... 23

GC 35.00

SUBCONTRACTORS ................................................................................................................................................ 23

GC 36.00

RELATIONS OF CONTRACTOR AND SUBCONTRACTOR ........................................................................................... 24

GC 37.00

CONTRACTORS’ MUTUAL RESPONSIBILITY ............................................................................................................ 25

GC 38.00

CUTTING, PATCHING, AND EXCAVATING ............................................................................................................... 25

GC 39.00

EMPLOYEES ........................................................................................................................................................... 26

GC 40.00

CLEANING UP......................................................................................................................................................... 27

GC 41.00

USE OF PREMISES .................................................................................................................................................. 27

GC 42.00

OCCUPANCY .......................................................................................................................................................... 27

GC 43.00

TEMPORARY OR TRIAL USAGE ............................................................................................................................... 28

GC 44.00

TESTING OF BUILDING SYSTEMS ............................................................................................................................ 28

GC 45.00

LIQUIDATED DAMAGES FOR DELAY IN COMPLETION ............................................................................................. 28

GC 46.00

ACCEPTANCE AND FINAL PAYMENT ....................................................................................................................... 28

GC 47.00

WARRANTIES ON PORTIONS OF THE WORK .......................................................................................................... 29

GC 48.00

CONTRACTOR’S PROJECT GUARANTEE AFTER COMPLETION ................................................................................. 30

GC 49.00

MISCELLANEOUS KEYS, SWITCHES, ETC. ................................................................................................................ 30

GC 50.00

INDEMNIFICATION ................................................................................................................................................ 30

GC 51.00

LABOR DISPUTES ................................................................................................................................................... 31

GC 52.00

LIMITATION OF ACTIONS ....................................................................................................................................... 31

GC 53.00

PREFERENCE FOR COLORADO LABOR, MATERIALS, AND RESIDENT BIDDERS ........................................................ 31

GC 54.00

SALES AND USE TAX............................................................................................................................................... 31

GC 55.00

LIENS ..................................................................................................................................................................... 32

GC 56.00

OWNER’S INSPECTION OF CONTRACTOR’S RECORDS ............................................................................................ 32

GC 57.00

CERTIFICATION BY CONTRACTOR REGARDING PREMISES ACCESS ......................................................................... 32

GC 58.00

CONTRACTOR SAFETY RESPONSIBILITIES ............................................................................................................... 32

GC 59.00

CONTRACTOR ASBESTOS MANAGEMENT AND LEAD PAINT RESPONSIBILITIES ...................................................... 35

GC 60.00

ARCHITECT’S STATUS AND INSPECTIONS ............................................................................................................... 35

GC 61.00

ORAL STATEMENTS................................................................................................................................................ 35

GC 62.00

PROJECT SIGN ........................................................................................................................................................ 36

GC 63.00

HISTORICAL DATA .................................................................................................................................................. 36

GC 64.00

ASSIGNMENT ......................................................................................................................................................... 36

GC 65.00

TIME OF THE ESSENCE ........................................................................................................................................... 36

GC 66.00

DISPUTES ............................................................................................................................................................... 36

GC 67.00

SURVIVAL .............................................................................................................................................................. 36

GC 1.00

CONTRACT DOCUMENTS AND DEFINITIONS

All Work under the Construction Agreement shall be accomplished in accordance with the Contract Documents, which shall consist of the Request for Qualifications, Request for Proposals, Proposal(s), Notice of Award, Notice to Proceed, Performance Bond, Labor and Material Payment Bond, Construction Agreement, General Contract Conditions, Supplementary Conditions, Asbestos Management Plan Contractor Responsibility Form, Drawings and Specifications, tests and engineering data, approved Change Orders, Contractor’s Requests for Payment, Architect’s Certificates, and all addenda issued by the Owner or Architect prior to execution of the Construction Agreement and all modifications issued by the Owner or Architect after execution of the Construction Agreement. With respect to the Contract Documents, the following definitions and understandings shall control: 1.01 “Contract” or “Contract Documents” shall include all of the items enumerated in GC-1.00 above. 1.02 “Owner” shall mean Boulder Valley School District No. RE-2, and shall include its duly authorized representatives. 1.03 “Contractor” shall mean the corporation, company, partnership, firm, entity, or individual named and designated as such in the Construction Agreement, and any persons or entities acting on its behalf. 1.04 “Subcontractor” shall mean any corporation, partnership, entity, or individual having a direct contract with the Contractor or another subcontractor for performing Work and/or furnishing labor or material on the Project covered by the Contract. 1.05 “Architect” shall mean the corporation, partnership, entity or individual named and designated as “architect” or “engineer” in the Construction Agreement, and any persons or entities acting on the Architect’s behalf and within the scope of the particular duties properly entrusted to them in each case. In the event that there is no Architect on the Project, then “Architect” shall refer to Owner and its duly authorized representative. 1.06 “Notice to Contractor” shall be deemed to have been duly served if made in writing and delivered in person to the individual or to a member of the firm or to an officer of the corporation for which it is intended, or if sent by registered or certified mail, to Contractor’s last known business address. 1.07 “The Work” shall mean the construction and services required by the Contract Documents for completion of the Project, and includes all labor, materials, equipment and services provided or to be provided by the Contractor to fulfill the Contractor’s obligations, whether on or off the Project site, and all labor, materials equipment and services provided or to be provided by subcontractors, sub-subcontractors, or any other entity for whom the Contractor is responsible. 1.08 “The Project” is the total construction designed by the Architect of which the Work performed under the Contract Documents may be the whole or a part. 1.09 The “date of final completion” and “finally completed” shall mean the date when construction is certified by the Architect to be finally completed in accordance with the Contract Documents, as modified by any Change Orders processed under the terms of GC-23.00 below and when the Owner has fully accepted the Project for the use for which it was intended. Such date will be set forth on a letter of acceptance issued by the Owner. 1.010 “Drawings” or “plans” shall mean all (a) drawings furnished by the Owner and/or Architect as a basis for the award of Contract and for construction of the Project; (b) supplementary drawings furnished by the Owner and/or Architect to clarify and to define in greater detail the intent of the Contract drawings and specifications; (c) drawings submitted by the successful Contractor as may be required after the Contract is awarded; (d) drawings furnished by the Owner and/or Architect to the Contractor during the progress of the Work; and (e) engineering data and drawings submitted by the Contractor during the progress of the Work, provided such drawings are acceptable to the Architect and Owner. 1

1.011 “Specifications” are the written technical information concerning materials, components, systems, equipment, and manner of installation as indicated on the drawings or plans and which state the quality, performance, and characteristics to be achieved by application of construction methods. 1.012 “Change Order” shall mean a written order to the Contractor signed by the Owner or its authorized agent issued after the execution of the Construction Agreement, authorizing a change in the Work and/or adjustment in the Guaranteed Maximum Price (“GMP”) or the contract time schedule. Each adjustment in the GMP resulting from a Change Order shall clearly separate the amount attributable to the Cost of the Work and the Contractor’s Fee. 1.013 “day” or “days” shall mean calendar days. In computing a period of days, when the ending date is not specified, the first day is excluded and the last day is included. If any deadline falls on a Saturday, Sunday, or federal or Colorado state holiday, such deadline will be extended to the next day that is not a Saturday, Sunday or federal or Colorado state holiday. GC 2.00

REFERENCE STANDARDS

2.01 Reference to the standards of any technical society, organization, or association, or to codes of local or state authorities, shall mean the latest standard, code, specification, or tentative standard adopted and published as of the date of execution of the Construction Agreement, unless specifically stated otherwise. GC 3.00

DRAWINGS AND SPECIFICATIONS

The rest of this document (149k more characters) is in the original file.