BVSD Board of Education · Document
Exhibits BVSD Centennial Middle School Amendment Package No. 1.pdf (4,228 KB)
Regular Meeting, November 18, 2025 · item 8.7: Amendment to the contract for Centennial Middle School · 92 pages
This is the text extracted from the file, without its layout, tables, or images. Use the original for anything that matters.
Exhibit A Drawings, specifications and documents used to prepare the GMP
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Printed on Mon Nov 3, 2025 at 12:08 pm MST
Exhibit A
BVSD Centennial MS 2205 Norwood Ave. Boulder, Colorado 80304
Palace Construction
Current Drawings Drawing No.
Drawing Title
Revision
Drawing Date
Received Date
Set
General A0.0
Cover Sheet
2
10/24/2025
10/24/2025
Addendum No. 2 (10/24/25)
A0.2
Existing Code Plans (For Reference Only)
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
A0.3
Existing Code Plans (For Reference Only)
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
AC2.0
Site Plan
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
AC2.1
Enlarged Site Plans
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
AC2.2
Enlarged Site Plans
1
10/24/2025
10/24/2025
Addendum No. 2 (10/24/25)
C1.1
PROPOSED SIDEWALK PLAN
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
C2.1
PROPOSED SIDEWALK CONSTRUCTION DETAILS
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
Architecture Civil
Civil
Architecture Demolition AD1.0
Lower Level and Main Level Overall Demo Plans
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
AD1.1
Upper Level Overall Demo Plan
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
AD1.2
Enlarged Demo Plans
2
10/24/2025
10/24/2025
Addendum No. 2 (10/24/25)
AD1.3
Enlarged Demo Plans
1
10/24/2025
10/24/2025
Addendum No. 2 (10/24/25)
AD1.4
Enlarged Demo Plans
1
10/24/2025
10/24/2025
Addendum No. 2 (10/24/25)
A1.1
Basement and Main Level Floor Plans
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
A1.2
Upper Level Floor Plan
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
A1.3
Enlarged Student Restroom Plans & Interior Elevations
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
A1.4
Enlarged Restroom Plans, Interior Elevations, & Details
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
A1.5
Enlarged Plans & Details
2
10/24/2025
10/24/2025
Addendum No. 2 (10/24/25)
A1.6
CTE Enlarged Floor Plans
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
A5.0
Interior Elevations
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
A6.0
Door & Frame Types, Partition Types
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
A7.0
Main Level Reflected Ceiling Plan
2
10/24/2025
10/24/2025
Addendum No. 2 (10/24/25)
A7.1
Upper Level Reflected Ceiling Plan
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
A8.0
Roof Plan
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
AF1.0
Finish Plans, Schedules & Details
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
MD1.1
Main Level Demolition Plan - HVAC
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
MD1.2
Upper Level Demolition Plan - HVAC
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
MD3.1
Enlarged Mechanical Demolition Plan
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
Architectural
Mechanical
Page 1 of 3
Printed on Mon Nov 3, 2025 at 12:08 pm MST
Exhibit A
BVSD Centennial MS 2205 Norwood Ave. Boulder, Colorado 80304
Palace Construction
Drawing Date
Received Date
M1.1
Drawing No. Main Level Plan - HVAC
Drawing Title
Revision 0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
Set
M1.2
Upper Level Plan - HVAC
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
M1.3
Roof Plan - Mechanical
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
M3.0
Enlarged Mechanical Plan
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
M3.1
Enlarged Mechanical Plan
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
M4.0
HVAC Details
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
M5.0
HVAC Diagrams
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
M6.0
HVAC Schedules
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
P0.0
Plumbing Coversheet
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
PD1.0
Underfloor Demolition Plan - Plumbing
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
PD1.1
Main Level Demolition Plan - Plumbing
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
PD1.2
Upper Level Demolition Plan - Plumbing
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
P1.0
Underfloor Plan - Plumbing
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
P1.1
Main Level Plan - Plumbing
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
P1.2.
Upper Level Plan - Plumbing
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
P3.0
Enlarged Plumbing Plan
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
P3.1
Enlarged Plumbing Plan
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
P3.2
Enlarged Plumbing Plan
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
P4.0
Plumbing Details
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
P6.0
Plumbing Schedules
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
E0.0
Electrical Coversheet
1
10/24/2025
10/24/2025
Addendum No. 2 (10/24/25)
E0.1
Electrical Lighting Covershet
0
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
ED1.1
Main Level Demolition Plan - Power and Systems
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
ED1.2
Upper Level Demolition Plan - Power and Systems
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
ED2.1A
Main Level Demolition Plan - Area A - Lighting
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
ED2.1B
Main Level Demolition Plan - Area B - Lighting
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
ED2.1C
Main Level Demolition Plan - Area C - Lighting
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
ED2.1D
Main Level Demolition Plan - Area D - Lighting
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
ED2.2A
Upper Level Demolition Plan - Area A - Lighting
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
ED2.2B
Upper Level Demolition Plan - Area B - Lighting
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
ED2.2C
Upper Level Demolition Plan - Area C - Lighting
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
ED2.2D
Upper Level Demolition Plan - Area D - Lighting
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
ED3.2
Enlarged Electrical Demolition Plan
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
E1.1
Main Level Plan - Power and Systems
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
E1.2
Upper Level Plan - Power and Systems
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
E2.1A
Main Level Plan - Area A - Lighting
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
Plumbing
Electrical
Page 2 of 3
Exhibit A
Printed on Mon Nov 3, 2025 at 12:08 pm MST BVSD Centennial MS 2205 Norwood Ave. Boulder, Colorado 80304
Palace Construction
Drawing Date
Received Date
E2.1B
Drawing No. Main Level Plan - Area B - Lighting
Drawing Title
Revision 1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
Set
E2.1C
Main Level Plan - Area C - Lighting
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
E2.1D
Main Level Plan - Area D - Lighting
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
E2.2A
Upper Level Plan - Area A - Lighting
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
E2.2B
Upper Level Plan - Area B - Lighting
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
E2.2C
Upper Level Plan - Area C - Lighting
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
E2.2D
Upper Level Plan - Area D - Lighting
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
E3.0
Enlarged Electrical Plan
1
10/24/2025
10/24/2025
Addendum No. 2 (10/24/25)
E3.1
Enlarged Electrical Plan
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
E3.2
Enlarged Electrical Plan
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
E6.0
Electrical Schedules and Details
2
10/24/2025
10/24/2025
Addendum No. 2 (10/24/25)
E7.0
Electrical Panel Schedules
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
E3.3
Electrical Enlarged Plan
0
10/24/2025
10/24/2025
Addendum No. 2 (10/24/25)
TL0.0
Theatrical Lighting Cover Sheet
0
10/24/2025
10/24/2025
Addendum No. 2 (10/24/25)
TL0.1
Theatrical Lighting Layout
0
10/24/2025
10/24/2025
Addendum No. 2 (10/24/25)
TL0.2
Theatrical Lighting Riser
0
10/24/2025
10/24/2025
Addendum No. 2 (10/24/25)
TL0.3
Theatrical Lighting Controls Topology
0
10/24/2025
10/24/2025
Addendum No. 2 (10/24/25)
TL0.4
Theatrical Lighting Batten Elevations
0
10/24/2025
10/24/2025
Addendum No. 2 (10/24/25)
T0.0
Technology Coversheet
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
TD1.1
Basement and Main Level Demolition Plan - Technology
0
09/29/2025
09/29/2025
100% CD Set (09/29/25)
TD1.2
Upper Level Demolition Plan - Technology
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
T1.1
Basement and Main Level Plan - Technology
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
T1.2
Upper Level Plan - Technology
1
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
T6.0
Technology Schedules
0
10/10/2025
10/10/2025
Addendum No. 1 (10/10/25)
Technology
Page 3 of 3
Exhibit A
Printed on Mon Nov 3, 2025 at 12:02 pm MST BVSD Centennial MS 2205 Norwood Ave. Boulder, Colorado 80304
Palace Construction
Current Specifications Number
Description
Revision
Issued Date
Received Date
Set
00 - General A
Table of Contents
1
10/24/25
10/24/25
Addendum No. 2
B
Asbestos Management Plan Contractor Responsibility
0
09/29/25
09/29/25
100% CD Set
C
Lead Based Paint Contractor Responsibility
0
09/29/25
09/29/25
100% CD Set
D
Geotechnical Report
0
10/24/25
10/24/25
Addendum No. 2
01 - General Requirements 011000
Summary
0
09/29/25
09/29/25
100% CD Set
011400
Work Restrictions
0
09/29/25
09/29/25
100% CD Set
011500
Regulatory Requirements
0
09/29/25
09/29/25
100% CD Set
012300
Alternates
0
09/29/25
09/29/25
100% CD Set
012513
Product Substitution Procedures
0
09/29/25
09/29/25
100% CD Set
012600
Contract Modification Procedures
0
09/29/25
09/29/25
100% CD Set
012900
Payment Procedures
0
09/29/25
09/29/25
100% CD Set
013100
Project Management and Coordination
0
09/29/25
09/29/25
100% CD Set
013120
Project Meetings
0
09/29/25
09/29/25
100% CD Set
013200
Construction Progress Documentation
0
09/29/25
09/29/25
100% CD Set
013233
Photographic Documentation
0
09/29/25
09/29/25
100% CD Set
013300
Submittal Procedures
0
09/29/25
09/29/25
100% CD Set
013500
Alteration Project Procedures
0
09/29/25
09/29/25
100% CD Set
014000
Quality Requirements
0
09/29/25
09/29/25
100% CD Set
014200
References
0
09/29/25
09/29/25
100% CD Set
015000
Temporary Facilities and Controls
0
09/29/25
09/29/25
100% CD Set
015400
Security
0
09/29/25
09/29/25
100% CD Set
016000
Product Requirements
0
09/29/25
09/29/25
100% CD Set
016400
Owner Furnished Products
0
09/29/25
09/29/25
100% CD Set
017000
Execution Requirements
0
09/29/25
09/29/25
100% CD Set
017300
Execution
0
09/29/25
09/29/25
100% CD Set
017329
Cutting and Patching
0
09/29/25
09/29/25
100% CD Set
017419
Construction Waste Management and Disposal
0
09/29/25
09/29/25
100% CD Set
017700
Closeout Procedures
0
09/29/25
09/29/25
100% CD Set
017710
Final Cleaning
0
09/29/25
09/29/25
100% CD Set
017810
Project Record Documents
0
09/29/25
09/29/25
100% CD Set
017820
Operation and Maintenance Data
0
09/29/25
09/29/25
100% CD Set
Page 1 of 4
Exhibit A
Printed on Mon Nov 3, 2025 at 12:02 pm MST BVSD Centennial MS 2205 Norwood Ave. Boulder, Colorado 80304
Palace Construction
Number 017900
Description
Revision
Demonstration and Training
Issued Date
Received Date
Set
0
09/29/25
09/29/25
100% CD Set
Selective Demolition
0
09/29/25
09/29/25
100% CD Set
Metal Fabrications
0
09/29/25
09/29/25
100% CD Set
0
09/29/25
09/29/25
100% CD Set
02 - Existing Conditions 024119 05 - Metals 055000
06 - Wood, Plastics, and Composites 064116
Plastic-Laminate-Faced Cabinets
07 - Thermal and Moisture Protection 076200
Sheet Metal Flashing and Trim
0
09/29/25
09/29/25
100% CD Set
078413
Firestopping
0
09/29/25
09/29/25
100% CD Set
079200
Joint Sealants
0
09/29/25
09/29/25
100% CD Set
081113
Hollow Metal Doors and Frames
0
09/29/25
09/29/25
100% CD Set
081416
Flush Wood Doors
0
09/29/25
09/29/25
100% CD Set
083113
Access Doors and Frames
0
09/29/25
09/29/25
100% CD Set
084113
Aluminum-Framed Entrances And Storefronts
0
09/29/25
09/29/25
100% CD Set
084113.13
Fire-Rated Aluminum-Framed Entrances and Storefronts
0
09/29/25
09/29/25
100% CD Set
084523
2-3/4" Insulated Translucent Fiberglass Sandwich Panel Standard Skylight System
0
09/29/25
09/29/25
100% CD Set
088000
Glazing
0
09/29/25
09/29/25
100% CD Set
088300
Mirrors
0
09/29/25
09/29/25
100% CD Set
088813
Fire-Rated Glass – Pilkington Pyrostop
0
09/29/25
09/29/25
100% CD Set
092216
Non-Structural Metal Framing
0
09/29/25
09/29/25
100% CD Set
092900
Gypsum Board
0
09/29/25
09/29/25
100% CD Set
093013
Tiling
0
09/29/25
09/29/25
100% CD Set
095113
Acoustical Panel Ceiling
0
09/29/25
09/29/25
100% CD Set
096513
Resilient Base and Accessories
0
09/29/25
09/29/25
100% CD Set
096566
Resilient Athletic Flooring
0
09/29/25
09/29/25
100% CD Set
096723
Resinous Flooring
0
09/29/25
09/29/25
100% CD Set
096813
Tile Carpeting
0
09/29/25
09/29/25
100% CD Set
098433
Sound-Absorbing Wall Units
0
09/29/25
09/29/25
100% CD Set
099120
Painting
0
09/29/25
09/29/25
100% CD Set
099600
High-Performance Coatings – Miracle Method
0
09/29/25
09/29/25
100% CD Set
102123
Cubicle Curtains and Track
1
10/10/25
10/10/25
Addendum No. 1
102600
Wall Protection
0
09/29/25
09/29/25
100% CD Set
102800
Toilet, Bath, and Laundry Accessories
0
09/29/25
09/29/25
100% CD Set
08 - Openings
09 - Finishes
10 - Specialties
Page 2 of 4
Printed on Mon Nov 3, 2025 at 12:02 pm MST
Exhibit A
BVSD Centennial MS 2205 Norwood Ave. Boulder, Colorado 80304
Palace Construction
Number
Description
Revision
Issued Date
Received Date
Set
12 - Furnishings 122113
Horizontal Louver Blinds
0
09/29/25
09/29/25
100% CD Set
220500
Basic Plumbing Requirements
0
09/29/25
09/29/25
100% CD Set
220505
Plumbing Demolition for Remodeling
0
09/29/25
09/29/25
100% CD Set
220513
Motors
0
09/29/25
09/29/25
100% CD Set
220529
Plumbing Supports And Anchors
0
09/29/25
09/29/25
100% CD Set
220553
Plumbing Identification
0
09/29/25
09/29/25
100% CD Set
220593
Plumbing Testing, Adjusting, and Balancing
0
09/29/25
09/29/25
100% CD Set
220719
Plumbing Piping Insulation
0
09/29/25
09/29/25
100% CD Set
220900
Instrumentation
0
09/29/25
09/29/25
100% CD Set
221000
Plumbing Piping
0
09/29/25
09/29/25
100% CD Set
221023
Natural Gas and Propane Piping
0
09/29/25
09/29/25
100% CD Set
221200
Tanks – Plumbing
0
09/29/25
09/29/25
100% CD Set
223000
Plumbing Equipment
0
09/29/25
09/29/25
100% CD Set
224000
Plumbing Fixtures
0
09/29/25
09/29/25
100% CD Set
22 - Plumbing
23 - Heating, Ventilating, and Air Conditioning (HVAC) 230500
Basic HVAC Requirements
0
09/29/25
09/29/25
100% CD Set
230505
HVAC Demolition for Remodeling
0
09/29/25
09/29/25
100% CD Set
230513
Motors
0
09/29/25
09/29/25
100% CD Set
230529
HVAC Supports And Anchors
0
09/29/25
09/29/25
100% CD Set
230553
HVAC Identification
0
09/29/25
09/29/25
100% CD Set
230593
Testing, Adjusting, and Balancing for HVAC
0
09/29/25
09/29/25
100% CD Set
230713
Ductwork Insulation
0
09/29/25
09/29/25
100% CD Set
230719
HVAC Piping Insulation
0
09/29/25
09/29/25
100% CD Set
230900
Controls
0
09/29/25
09/29/25
100% CD Set
230913
Instrumentation
0
09/29/25
09/29/25
100% CD Set
232100
Hydronic Piping
0
09/29/25
09/29/25
100% CD Set
232116
Hydronic Specialties
0
09/29/25
09/29/25
100% CD Set
233100
Ductwork
0
09/29/25
09/29/25
100% CD Set
233300
Ductwork Accessories
0
09/29/25
09/29/25
100% CD Set
233423
Power Ventilators
0
09/29/25
09/29/25
100% CD Set
233700
Air Inlets and Outlets
0
09/29/25
09/29/25
100% CD Set
238126
Ductless Mini-Split Units
0
09/29/25
09/29/25
100% CD Set
238216
Air Coils
0
09/29/25
09/29/25
100% CD Set
Basic Electrical Requirements
0
09/29/25
09/29/25
100% CD Set
26 - Electrical 260500
Page 3 of 4
Exhibit A
Printed on Mon Nov 3, 2025 at 12:02 pm MST BVSD Centennial MS 2205 Norwood Ave. Boulder, Colorado 80304
Palace Construction
Number
Description
Revision
Issued Date
Received Date
Set
260503
Through Penetration Firestopping
0
09/29/25
09/29/25
100% CD Set
260505
Electrical Demolition for Remodeling
0
09/29/25
09/29/25
100% CD Set
260513
Wire and Cable
0
09/29/25
09/29/25
100% CD Set
260526
Grounding and Bonding
0
09/29/25
09/29/25
100% CD Set
260533
Conduit And Boxes
0
09/29/25
09/29/25
100% CD Set
260553
Electrical Identification
0
09/29/25
09/29/25
100% CD Set
260933
Lighting Control Systems
0
09/29/25
09/29/25
100% CD Set
262726
Wiring Devices
0
09/29/25
09/29/25
100% CD Set
262816
Disconnect Switches
0
09/29/25
09/29/25
100% CD Set
265119
LED Lighting
0
09/29/25
09/29/25
100% CD Set
Fire Alarm and Detection Systems
0
09/29/25
09/29/25
100% CD Set
Erosion and Sedimentation Controls
0
09/29/25
09/29/25
100% CD Set
28 - Electronic Safety and Security 283100 31 - Earthwork 312500
32 - Exterior Improvements 320505
Selective Demolition for Exterior Improvements
0
09/29/25
09/29/25
100% CD Set
321200
Hot Mix Asphalt Pavement
0
09/29/25
09/29/25
100% CD Set
321300
Concrete Paving
0
09/29/25
09/29/25
100% CD Set
321373
Concrete Paving Joint Sealants
0
09/29/25
09/29/25
100% CD Set
321723
Pavement Markings
0
09/29/25
09/29/25
100% CD Set
323113
Chain Link Fences
0
09/29/25
09/29/25
100% CD Set
Page 4 of 4
Exhibit B Assumptions and clarifications made in preparing the GMP
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit B
BVSD Centennial MS - Clarifications & Exclusions General Clarifications & Exclusions Below are exclusions, clarifications, and assumptions. In addition to this list, please refer to the comments column within the direct cost worksheet for additional exclusions, assumptions, and clarifications. Estimate is based on 100% CD Drawings & Project Manual dated 09/29/2025 Estimate acknowledges Addendum No. 1 dated 10/10/2025 Estimate acknowledges Addendum No. 2 dated 10/24/2025 Excludes any Davis Bacon or Prevailing Wages Excludes building permit and plan review fees. Excludes ROW permits and fees. We assume that all work will be private. Excludes all sales and use taxes for city, county, and state. Excludes 3rd party inspections and testing of any kind. Excludes Furniture, FFE, Equipment Excludes removal or moving of any owner furniture or equipment that would impede our work. Palace and their subcontractors will provide a 2-year workmanship warranty for all scope. Excludes any specific M/WBE requirements or percentages. We have done a good faith effort to invite several M/WBE contractors to bid. Excludes any requirements for commissioning for Energy Star, NGBS, LEED, or similar certifications. Excludes any removal or testing of hazardous materials. Excludes drilling into surfaces identified as ACMs for anchoring purposes. We are not responsible for any delays due to hazardous material removal, which is the responsibility of the owner. Excludes brining any systems up to code that are outside of our scope of work. Excludes costs for power, water, and gas We assume that we can temporarily use the existing power, water and gas from the building during construction Excludes commissioning of any existing systems. Excludes surveying and engineering.
Division 02 - Demo There is a built-in bench in the music room where our new shaft wall is being installed. We are assuming this built-in bench is standard framing and drywall, with nothing underneath it that needs to be modified. Excludes removal of hazardous materials. We assume owner will remove all hazardous materials.
Exhibit B We assume the added site concrete is all private and will not be a part of any permitting. This note is in regards to surveying as we have only included basic surveying for the specific site concrete that is being added. We did not include any of the additional surveying that would be required if anything associated with this added site concrete will need to be permitted. We have included the cost to collect as-built survey data and construction staking. We will provide survey data to the design team, but design will need to be completed by Excludes final/ALTA survey of any of the site improvements We exclude the removal and reinstallation of the wall mounted workout equipment in the auxiliary gym. Shown in Addendum No. 2, but not desired by owner.
Division 03 - Concrete Excludes carbon fiber reinforcement or other structural reinforcement to slab openings for floor boxes or flue piping penetrations. No structural reinforcement indicated on plans.
Division 04 - Masonry No masonry scope has been provided in this contract. None shown.
Division 05 - Steel Excludes any structural steel or framing.
Division 06 - Rough Carpentry Excludes AWI certification requirements for P-lam cabinet fabrication and installation.
Division 07 - Thermal & Moisture Protection We exclude any repairs to any rated assemblies or sealants that are outside of our scope of work. When we open up ceilings, building inspector may require additional rated sealants to be added to existing conditions to pass inspection. We have added an allowance of $7,500 to cover these conditions. Added drip edge flashing at Rotunda is not included in this estimate. We have added an allowance of $2,500 for the supply and install of this flashing.
Division 08 - Openings Excludes box beam at skylight shown in detail 5/A8.0. Not required per manufacturer We assume the existing skylight curb will be sufficient for the new skylight. We exclude any modifications to the existing curb, except the added metal flashing shown in the detail. Excludes fire ratings for the aluminum storefront system. Spec provided, but we assume a rating is not needed at this location. Excludes fire rated glass/glazing. Spec provided, but no glazing installations appear to be in rated assemblies. Excludes aluminum storefront doors. All doors appear to be HM frames/WD doors. No hardware spec was included in this bid package. We have included a $1,000 allowance per door for hardware supply and install. Excludes any mirrors per the division 8 spec section. We have only included framed mirrors per division 10.
Division 09 - Finishes Exclude repairs to existing tile. An allowance of $10,000 has been included for misc. tile repairs, if needed.
Exhibit B Rubber Flooring called out in finish schedule is not recommended by Robbins for weight room flooring (Robbins Pulastic Classic 100); we have priced a more durable product that was recommended by Robbins (Robbins Pulastic Intense). Adder was approximately $22,000 for the new product.
Division 10 - Specialties Existing toilet partitions to be removed and re-installed. We assume all existing parts are present and functional. We have not included any replacement parts for the existing We assumed that no additional backing is needed for toilet accessories and toilet partitions. Replacements appear to be going back in same location as existing. Mural sign at front entry is priced as approximately 5' x 6'-6" to avoid a seam in the acrylic panel. Typical acrylic panel size does not exceed 5' for one of the dimension.
Division 11 - Equipment No division 11 equipment is part of this project
Division 12 - Furnishings Excludes horizontal louver blinds. Spec provided, but none shown on plans.
Division 13 - Special Construction No division 13 special construction is part of this project.
Division 14 - Conveying Systems Elevator Refurbishment has been included as an allowance. This includes all scopes of work associated with the elevator refurbishment
Division 21 - Fire Suppression Excludes any fire suppression work. Plans aren't clear on if there is a fire suppression system and where.
Division 22 - Plumbing Excludes new carriers for plumbing fixtures. We assumed existing carriers will be utilized for the new fixtures. Assumes existing rough-ins are sufficient for new fixtures. Pump out piping for grease interceptor has been priced as surface mounted on walls and ceilings of kitchen.
Division 23 - Heating, Ventilation & AC Excludes split system air conditioning units. Spec provided, but not found on plans. Excludes cleaning of any ducting except newly installed duct.
Division 26 - Electrical Theatrical lighting scope was incomplete at the time of this estimate. We have included a $190,000.00 allowance for theatrical lighting, which includes any associated scopes. We assume that any existing lighting that is to remain is properly suspended. We have not included new suspension systems for light fixtures that are to remain. Excludes any rough in support for the paging/ clock/ intercom system. It is not clear on the plans what is needed. Excludes any electrical support for the elevator system. Elevator refurbishment scope was not provided at the time of this estimate.
Exhibit B Divisions 27 & 28 - Low Voltage, Life Safety, Security, We have only included new data cabling from existing patch panel to the new data jack locations in the computer lab. We excluded any revision or addition to the patch panel or rack Excludes any new emergency radio systems or testing The paging system has been included as an allowance of $230,000.00. The allowance is for all scopes of work associated with the paging system replacement.
Division 31 - Earthwork We priced the aggregate lift in the East parking lot as 1 1/2" granite, per district request. We exclude the #411 aggregate shown in the plans. We assume that on site soils are sufficient at any new concrete and asphalt patching. We have not included importing new structural fill or aggregate to accommodate
Division 32 - Exterior Improvements Excludes local ROW permit for asphalt and site concrete work. We assumed this is private work and won't require any permits. We have included the cost for a traffic lane closure to perform the asphalt mill and overlay. Crack sealing of the asphalt prior to overlay is not included in this estimate. We have included an allowance of $8,200.00 to address crack repairs prior to overlay. Asphalt patchwork has only been included to the extent represented by the hatch pattern shown on the drawings.
Division 33 - Utilities Excludes any site utility work
Exhibit C Itemization of the GMP
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit C
BVSD - Centennial Middle School Boulder, CO 100% Construction Documents Owner/Developer: Boulder Valley School District RE-2 6500 Arapahoe Rd Boulder, CO 80303 Owner Representative: Gene Temanson
Designed By: Eidos Architects
Project Start: May-26 Project Finish: Aug-26 Duration in Months:
3.0
Bonding Required: Prevailing Wage Liquidated Damages: Taxes:
Yes No Yes Fully Exempt
TOTAL PROJECT COST: $2,733,490 PROJECT Cost per SF: Building SF:
Proposal Date:
$27.47 99,515
October 24, 2025
Prepared By: Palace Construction 7 S. Galapago Street Denver, CO 80223 Andy Del Grosso 720-456-0373 adelgrosso@palaceconst.com
Exhibit C BVSD - Centennial Middle School 100% Construction Documents
COST SUMMARY WORKSHEET Direct Costs 02 00 00 03 00 00 05 00 00 07 00 00 08 00 00 09 00 00 10 00 00 12 00 00 14 00 00 22 00 00 23 00 00 26 00 00 27 00 00 28 00 00 31 00 00 32 00 00
Gross Built Area: 99,515 SF
Cost
$/sf
$153,789 $7,962 $3,995 $106,888 $61,842 $489,246 $82,734 $53,813 $140,000 $282,079 $70,295 $317,015 $230,000 $0 $68,125 $227,340 $2,295,123
$1.55
$23.06
Duration: 3 Months
$128,662
$1.29
Not Included, By Others
$0 $0 $0 $0 $0
$0.00
$26,173 $1,240 $0 $30,798 $0 $58,211
$0.26
$124,100 $0 $0 $124,100
$1.25
$127,394
$1.28
$2,733,490
$27.47
Existing Conditions Concrete Metals Thermal and Moisture Protection Openings Finishes Specialties Furnishings Conveying Systems Plumbing Heating Ventilation Air Conditioning Electrical Communications Electronic Safety & Security Earthwork Exterior Improvements
General Requirements Design, Permit, Taxes Building Permit Plan Review Fee Professional Design Services Use Tax
Insurances & Fees General Liability Insurance Builders Risk Insurance Wrap / Project Specific Policies P&P Bonds Preconstruction Fee
Contingency & Escalation Contractor Contingency Design Contingency Escalation Allowance
Overhead and Profit TOTAL PROJECT COST: Alternates ALT 01 ALT 02 ALT 03
10/24/2025
Not Included, By Others Not Included, By Others Included in Direct Cost
Included Included N/A Included Included
5.00% 0.00% 0.00%
5.00%
Replace Lighting & Controls at Auditorium, Gyms, Cafeteria Replace Lighting & Controls at Classrooms Replace Lighting & Controls at Offices & Support Areas
Base Bid Alt 01-Accepted Alt 02-Accepted Alt 03-Accepted Total
$0.08 $0.04 $1.07 $0.62 $4.92 $0.83 $0.54 $1.41 $2.83 $0.71 $3.19 $2.31 $0.00 $0.68 $2.28
$0.00 $0.00 $0.00 $0.00
$0.01 $0.00 $0.31 $0.00 $0.58
$0.00 $0.00 $1.25
$193,347 $188,885 $120,151
$2,733,490 $ 193,347 $ 188,885 $ 120,151 $3,235,873
Exhibit C
DIRECT COST WORKSHEET BVSD - Centennial Middle School 100% Construction Documents
Project: Stage: Code
Cat
000000
Scope of Work
October 24, 2025
Qty
Unit $
Cost
Section
Division
$/sf
Comments
General Notes & Clarifications -
100% Construction Documents Estimate Based on the 100% CD Drawings & Specifications Dated 09/29/2025 Estimate Based on Addendum No. 1 dated 10/10/2025 Estimate Based on Addendum No. 2 dated 10/24/2025 See Attached Clarifications Sheet and Comments Column for Exclusions. Clarifications, and Assumptions
010000
DIRECT COST GENERAL REQUIREMENTS
015626 015626 E 015626 E 015626 E
Temporary Fencing Deliver & Remove Fencing Fence Monthly Rental Sand Bags
017123 017123 S 017123 S 017123 S
Field Engineering Surveying Base Bid As-Built Existing Conditions Staking at New Sidewalks & Bleacher Pads
017423 017423 S 017423 S 017423 S 017423 L
Final Cleaning Final Cleaning Base Bid Building Final Cleaning Window Clean Building and Site Cleanup
020000
Existing Conditions
024113 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 L 024113 S 024113 L 024113 S 024113 S 024113 X 024113 X 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S
Selective Demolition Site Demolition Base Bid Site Demolition Remove Concrete Barriers at East Parking Lot Relocate to Another BVSD School Remove And Dispose of Wooden Bleachers Remove Soil at Bleacher Concrete Pads Remove Chain Link Fencing Building Demolition Base Bid Building Demolition Aux. Gym 009 Remove Wrestling Mat - Salvage Re-install Wrestling Mat Remove Exercise/Weight Equipment - Salvage Re-install Floor Mounted Weight Equipment Remove Existing Acoustic Wall Panels Remove Snap-in Flooring Remove Tile Subfloor & Mastic Remove & Reinstall Wall Mounted Equipment Entry 95 & Adjacent Remove Walk-off Carpet in Entry 095 Remove Walk-off Carpet From Under Stairs Scrape Adhesive From Slab at Walk-off Mats Remove Existing Signage and Artwork Remove EM Lighting - Salvage Remove Wall Sconces Remove Gyp Ceiling in Entry 95B Remove Gyp Ceiling in Vest 95C
$47,291
252 lf 3 ea 42 ls
$2.35 $176.40 $7.00
$1,415
$0.01
$5,250
$0.05
$592 $529 $294
1 ls 1 ls 1 ls
$5,250.00 Included --Included ---
$5,250
1 ls 3,550 sf 1 ls 360 hr
$14,706.00 Included --Included --$72.00
$14,706
R&R At new parking lot sidewalk and bleacher pads
$40,626
$0.41 Signature Cleaning In computer lab, media room, new storefront
$25,920 $106,498 $106,498
1 ls 1 ls 1 ls 1 ls 1 ea 1 ls 1 ls 1 ls 1 ls 1 ls 1 ls 16 hr 1 ls 32 hr 28 ea 3,000 sf 3,000 sf 1 ls 1 ls 405 sf 135 sf 540 sf 4 ea 2 ea 5 ea 120 sf 65 sf
$7,088.00 Included Included Included Included Included Div 32 $87,674.00 Included Included Included $72.00 Included $72.00 Included Included Excluded Excluded Included Included Included Included Included Included Div 26 Included Included
$0.48
$1.07 $1.07
$7,088
Ground Solutions
$87,674
Removal by fence contractor Premier Environmental
-------------------
Store on site for re-installation $1,152
---
Store on site for re-installation $2,304
---------------------------
Assumed 28 existing panels Requires abatement. To be done by owner. Shown in Add. No. 2, but not desired by owner.
For all walk-off mat removal Remove for painting of columns. Re-install Dispose
Direct Costs
Page 3
Exhibit C DIRECT COST WORKSHEET BVSD - Centennial Middle School 100% Construction Documents
Project: Stage: Code
Cat
024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 L 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S
Scope of Work Remove Exterior Gyp Soffit Outside Entry Remove Glass Block Near Entry Provide Temp Enclosure in Opening Kitchen 132 Remove Prep Sink Above Grease Interceptor Sawcut & Remove Slab/Flooring GPR Prior to Slab Removal Remove Grease Interceptor Auditorium 181 Remove Theatrical Light Fixtures Computer Lab 2103 & Conference 2104B Remove ACT System Throughout Remove Light Fixtures Remove Mechanical Devices Remove Millwork & Countertops Remove Teacher Desks Remove Carpet & Base Scrape Adhesive From Slab Remove Platform Structure Remove Existing Walls Remove Storage Room Door/Frame Remove Visual Display Boards Remove Electrical/Data Lines Remove Drywall for New Electrical Outlets Restroom Group 184/186 Remove Toilet Partitions - Salvage Remove Toilet, Sink, and Urinal Fixtures Remove Soap Dispensers & Mirrors Remove Hand Dryers - Salvage Remove Toilet Paper Dispensers - Salvage Remove Sanitary Napkin Dispensers - Salvage Remove Lighting Remove ACT System in Boys 186 Restroom Group 214/216 Remove Toilet Partitions - Salvage Remove Toilet, Sink, and Urinal Fixtures Remove Soap Dispensers & Mirrors Remove Hand Dryers - Salvage Remove Toilet Paper Dispensers - Salvage Remove Sanitary Napkin Dispensers - Salvage Remove Lighting Remove ACT System in Boys 216 Restroom Group 128/129 Remove Toilet Partitions - Salvage Remove Toilet, Sink, and Urinal Fixtures Remove Countertops & Millwork at Sinks Remove Soap Dispensers Remove Toilet Paper Dispensers - Salvage Remove Sanitary Napkin Dispensers - Salvage Remove Lighting Remove Floor Tile Remove 6" of Tile Base Restroom Group 123A/123B Remove Toilet & Sink Fixtures Remove Soap Dispensers & Mirrors Remove Toilet Paper Dispensers - Salvage Remove Floor Tile
October 24, 2025
Qty 120 sf 153 sf 153 sf 1 ls 1 ea 80 sf 1 ls 1 ea 1 ls 1 ls 1 ls 1,425 sf 18 ea 12 ea 1 ls 4 hrs 1,425 sf 1,425 sf 1 ls 32 lf 1 ea 2 ea 1 ls 1 ls 1 ls 1 ls 17 ea 1 ls 2 ea 8 ea 5 ea 1 ls 205 sf 1 ls 1 ls 20 ea 1 ls 2 ea 23 lf 5 ea 1 ls 205 sf 1 ls 1 ls 14 ea 2 ea 4 ea 8 ea 4 ea 1 ls 478 sf 150 lf 1 ls 14 ea 4 ea 2 ea 122 sf
Unit $ Included Included Included Included Div 22 Included Included Div 22 Included Div 26 Included Included Div 26 Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Div 26 Included Included Included Included Included Included Included Included Div 26 Included Included Included Included Included Included Included Included Div 26 Included Included Included Included Included Included Included
Cost
Section
-------------------------------------------------------------------------------------------------------------------
Division
$/sf
Comments
Existing partitions to be re-installed after finish upgrades
Existing partitions to be re-installed after finish upgrades
Existing partitions to be re-installed after finish upgrades
For new epoxy floor base
Direct Costs
Page 4
Exhibit C
DIRECT COST WORKSHEET BVSD - Centennial Middle School 100% Construction Documents
Project: Stage: Code
Cat
Scope of Work
024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 M 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 X 024113 S 024113 S 024113 S 024113 S 024113 S 024113 S 024113 L 024113 E 024113 E
Remove Wall Tile Remove Vinyl Flooring and Base Remove Doors & Frames Remove Walls/Framing Remove Lighting Remove ACT System Remove Gyp Ceilings Music Room 180Y Remove ACT for New Shaft Wall Remove Carpet Flooring for New Shaft Wall Remove Acoustic Wall Panels - Salvage Remove Portion of Built-in Bench Corridor 2101A Remove Wall Sconces Corridors 97,98,99,100,113,121,130,130A,150 Remove ACT Grid & Tiles Remove Light Fixtures - Salvage Remove MEP Devices - Salvage Corridor 140A Remove ACT Bulkhead Remove ACT System for New Exhaust Duct Remove 3% of 12"x12" ACT Tiles Remove 2x4 ACT System Remove Light Fixtures Restroom 141 Remove Gyp Ceiling for New Exhaust Fan Lobby 192,193B, Corridor 193C Remove ACT Tiles Only Removal of ACT Grid Mechanical 191 Remove Water Heaters Remove Storage Tanks 2nd Floor Corridor 209,220,230 Remove 3% of 12"x12" ACT Tiles Coring Demo Coordination and Layout Record Keeping for Waste Management Waste Management
024113 X
Demo of Mech. Room Door Opening
030000
Concrete
038000 038000 S 038000 S 038000 S 038000 S 038000 S 038000 S 038000 M 038000 L
Concrete Cutting and Boring Concrete Base Bid Concrete Patch in Kitchen for Grease Interceptor Dowel Into Existing - 5/8" x 2' @ 24" O.C. Welded Wire Fabric - 6x W1.4x1.4 Subgrade Prep Housekeeping Pad for Water Heaters Surface Protection - Material Surface Protection - Labor
050000
Metals
054000
Cold-Formed Metal Framing
October 24, 2025
Qty
Unit $
561 sf 20 sf 2 ea 36 lf 1 ls 54 sf 122 sf 1 ls 28 sf 4 sf 2 ea 1 ls 1 ls 7 ea 1 ls 6,910 sf 66 ls 1 ls 1 ls 60 sf 24 sf 7 sf 320 sf 7 ea 1 ls 24 sf 1 ls 2,325 ea 1 ls 1 ls 2 ea 4 ea 1 ls 95 ea 10 ea 40 hr 4 ea 8 ea 1 ls
Cost
Included Included Included Included Div 26 Included Included Included Included Included Included Included Included Div 26 Included Included Div 26 Included Included Included Included Included Included Div 26 Included Included Included Included Excluded Included Div 22 Div 22 Included Included Included $72.00 $450.00 $450.00
-----------------------------------------------------------------------
Excluded
---
Section
Division
ACT tile replacement only at these rooms
For RR 141 Exhaust, Water Heater Flues $2,880 $1,800 $3,600 We assume existing door is 36" and wide enough to remove water heaters and storage tanks
$7,962 $6,310.00 Included Included Included Included Included $500.00 $72.00
Comments
Need to confirm if the ceiling tile mastic is hot
$7,962
1 ls 80 sf 22 ea 80 sf 80 sf 52 sf 1 ls 16 hr
$/sf
$0.08 $0.08 Rocky Mountain Stonecrete
$6,310 ----------$500 $1,152 $3,995 $0 Direct Costs
$0.04 $0.00 Page 5
Exhibit C
DIRECT COST WORKSHEET BVSD - Centennial Middle School 100% Construction Documents
Project: Stage: Code
Cat
Scope of Work
October 24, 2025
Qty
Unit $
Cost
Section
054000 S
Metal Framing at New Walls
1 ls
Div 09
055000 055000 S 055000 S 055000 S 055000 S
Metal Fabrications Metal Fabrications Base Bid Remove Existing Handrail at East Plaza Ramp New Galvanized Handrail at East Plaza Ramp Supply Steel Bollards - 5'-6" Long
1 ls 17 lf 17 lf 21 ea
$3,995.00 Included --Included --Div 32 ---
070000
Thermal & Moisture Protection
072100 072100 S 072100 A
Insulation Insulation at New Walls Allowance - Insulation Replacement at Entry Soffit
072200 072200 S 072200 S
Roofing & Roof Accessories Skylight Base Bid Remove Existing Skylight
1 ls 1 ea
$76,889.00 Included ---
072200 S 072200 X 072200 S 072200 S 072200 S 072200 S 072200 A 072200 E
New Kalwall Skylight Box Beam for Skylight Roofing Base Bid Metal Flashing on Skylight Curb Flash in Water Heater Vent Penetrations Rotunda Allowance - Drip Flashing per 5/A7.0 Waste Management
1 ea 1 ea 1 ls 78 lf 4 ea 1 ls 1 ls 1 ea
Included Excluded $5,324.40 Included Included $5,324.40 $2,500.00 $450.00
078000 078000 S 078000 A
Firestopping Fire Caulk for Penetrations in Rated Walls Allowance - Sealants Required by Inspector
1 ls 1 ls
$5,500.00 $7,500.00
$5,500 $7,500
079000 079000 M
Joint Sealants Misc. Sealants
1 ls
$2,000.00
$2,000
080000
Doors & Windows
080000 080000 S 080000 S 080000 S 080000 S 080000 S 080000 S 080000 S 080000 S 080000 S 080000 A
Door and Frame Material and Install Door and Frame Base Bid Door 123A - 3070 HM Frame/WD Door Door 123B - 3070 HM Frame/WD Door Door 2104 - 3070 HM Frame/WD Door Door 2105 - 3070 HM Frame/WD Door w/ Sidelite Glazing for Sidelite Door 2106 - 3070 HM Frame/WD Door Door 128 - 3070 HM Frame/WD Door Door 129 - 3070 HM Frame/WD Door Allowance - Hardware for All Doors
1 ea 1 ea 1 ea 1 ea 1 ea 1 ea 1 ea 1 ea 1 ea 1 ea
$21,000.00 Included Included Included Included Included Included Included Included $7,000.00
084000 084000 S 084000 S 084000 S 084000 S 084000 X 084000 X
Window Systems Storefront Base Bid Storefront Window System at Entry Storefront Window at Media Room 2105 Air and Water Testing at Storefront Window Delegated Design for Storefronts Fire Rating for Storefront System
1 ls 1 ls 1 ls 1 ls 1 ls 1 ls
$23,817.00 Included Included $10,025.00 Excluded Excluded
Division
Comments
--$3,995
$0.04 Iron Hammer
$3,995
Base plate mount Included with site concrete number
$106,888 $1,400 1 ls 200 sf
$/sf
Div 09
$1.07 $0.01
--$7.00
Included with drywall contractor Where removed for install of floor boxes. Quantity and type unknown
$1,400 $90,488
$0.91
$76,889
Powers Products
$5,324
Assumes the new is the same size as old and won't require structure work. Assumes existing curb can be used. Not required per manufacturer B&M Roofing
---------
Assumed existing roof is EPDM $5,324 $2,500 $450 $13,000 If inspector requires assemblies to be sealed outside our scope $2,000
$0.02
$61,842 $28,000
$0.62 $0.28
$21,000 ----------------No hardware schedule provided. Allowance added at $1,000 per door.
$7,000 $33,842
$0.34
$23,817
Cutting Edge
$10,025
AGM Construction Services
--------Direct Costs
Page 6
Exhibit C DIRECT COST WORKSHEET BVSD - Centennial Middle School 100% Construction Documents
Project: Stage: Code
Cat
Scope of Work
090000
Finishes
092116 092116 S 092116 S 092116 S 092116 S 092116 S 092116 S 092116 S 092116 S 092116 S 092116 S 092116 S 092116 S 092116 S 092116 S 092116 S 092116 S 092116 S 092116 S 092116 S 092116 S 092116 S 092116 S 092116 S 092116 S 092116 X 092116 M 092116 M 092116 E
Drywall & Metal Framing Drywall Base Bid Frame Walls Photography, Media, & Storage Frame Walls for Restrooms 123A/123B Gyp Walls & Ceilings in RRs 123A/123B Cementitious Backer at Tile Walls Shaft Wall Framing/Drywall in Music Room Frame/Drywall Bulkheads at Restrooms 128/129 Drywall Patch At Entry Soffit - Exterior Drywall Patch At Vest 95C Ceiling Insulation for New Framed Walls Remove Damaged Drywall Soffit at Rotunda New Exterior Drywall at Rotunda Soffit Misc. Patching in Computer Lab 2103 Patching in RRs 128/129 for Lighting Replacements New Gyp Ceiling in RR 186 Patching in RR 184 for Lighting Replacements New Gyp Ceiling in RR 216 Patching in RRs 214 for Lighting Replacements Patch Ceiling for Duct Install in RR 141 Patch Gyp Substrate for 12x12 ACT in Corridor 140A Frame Openings in New Wall for HVAC Frame Openings in Existing Wall for Fire Dampers Acoustic Sealants Misc. Patching At New Storefronts Delegated Design for Metal Framing Misc Strapping/Backing in Walls Misc Containments for Drywall Work Waste Management
095100 095100 S 095100 S 095100 S 095100 S 095100 S 095100 S 095100 S 095100 S 095100 S 095100 S 095100 S 095100 S 095100 S 095100 S 095100 S 095100 A 095100 S 095100 S 095100 S 095100 S 095100 S 095100 S
Acoustical Systems Acoustical Systems Base Bid Aux. Gym 009 Acoustic Wall Panels 4'x4' Acoustic Wall Panels 4'x5' Acoustic Wall Panels 4'x6' Comp Lab 2103 & Photography 2104 New 2x4 Grid & Tile New 2x2 Grid & Tile - Grey Coordinate Cubicle Curtain Tracks Media Room 2105 & Storage 2106 New 2x4 Grid & Tile Corridor Outside RRs 123A/123B New 2x4 Grid & Tile Music Room 180Y 2x4 Grid & Tile Adjustments Allowance - Acoustic Panel Adjustment Corridors 97,98,99,100,113,121,130,130A,150 New 2x4 Grid & Tile Corridor 140A Patch 12"x12" ACT System Replace 3% of 12"x12" ACT Tiles New 2x4 Grid & Tile
October 24, 2025
Qty
Unit $
Cost
Section
Division
$489,246 $73,567 1 ls 1 ls 1 ls 1 ls 1 ls 1 ls 1 ls 200 sf 65 sf 1 ls 65 sf 65 sf 1 ls 1 ls 1 ls 1 ls 1 ls 1 ls 24 sf 24 sf 2 sf 2 ea 1 ls 1 ls 1 ls 1 ls 1 ls 1 ea
$70,717.00 Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Excluded $1,200.00 $1,200.00 $450.00
1 ls 1 ls 6 ea 15 ls 9 ls 1 ls 1,116 sf 145 sf 30 lf 1 ls 147 sf 1 ls 92 sf 1 ls 20 sf 1 ls 1 ls 6,910 sf 1 ls 24 sf 7 sf 320 sf
$120,500.00 Included Included Included Included Included Included Included Included Included Included Included Included Included Included $1,000.00 Included Included Included Included Included Included
$/sf
Comments
$4.92 $0.74 Independent Drywall
$70,717 -------------------------------------------------
R-11 Sound Batts
For new Exhaust Fans For new Exhaust Fans
Metal framing appears to be non-structural $1,200 $1,200 $450 $121,500 $120,500
----------------------------$1,000 -------------
$1.22 SRB Acoustics
To accommodate new shaft wall Modify existing panels to accommodate new shaft wall
For added exhaust ducting above
Direct Costs
Page 7
Exhibit C
DIRECT COST WORKSHEET BVSD - Centennial Middle School 100% Construction Documents
Project: Stage: Code
Cat
095100 S 095100 S 095100 X 095100 S 095100 S
Scope of Work Lobby 192,193B, Corridor 193C Replace 2x4 Tiles Only Replacement of ACT Grid 2nd Floor Corridor 209,220,230 Replace 3% of 12"x12" ACT Tiles
October 24, 2025
Qty
Unit $
1 ls 2,325 sf 1 ls 1 ls 95 sf
Included Included Excluded Included Included
096000 096000 S 096000 S 096000 S 096000 S 096000 S 096000 S 096000 S 096000 S 096000 X 096000 S 096000 S 096000 S 096000 S 096000 S 096000 S 096000 S 096000 S 096000 S 096000 S 096000 M 096000 L 096000 A
Flooring & Tile Finishes Flooring & Tile Base Bid F-2 Walk-Off Carpet at Entry & Under Stairs F-5 Rubber Flooring in Aux. Gym B-2 Rubber Base in Aux. Gym F-3 Carpet in Computer Lab & Photography F-6 Carpet in Photography F-4 LVT in Storage & Media Rooms B-2 Rubber Base in Storage, Media, Comp, Photo Floor Tile Wall Tile in Restrooms 123A/123B Wall Tile Pattern per 4/A4.1 Schluter Transitions Crack Isolation at Floors Refinish Terrazzo Flooring in RRs Epoxy Floor Patch in Kitchen - Match Existing F-1 Epoxy Floor in RRs B-1 Epoxy Floor Base W-4 Miracle Method in RRs Floor Prep at Epoxy Subfloor Floor/Surface Protection - Material Floor/Surface Protection - Labor Allowance - Misc. Tile Repairs in Restroom
1 ls 62 sy 2,998 sf 240 lf 126 sy 16 sy 146 sf 205 lf 1 ls 128 sf 1 ls 1 ls 1 ls 813 sf 120 sf 625 sf 225 lf 6,928 sf 745 sf 8,000 sf 420 hr 1 ls
$55,440.00 Included $17.65 Included Included Included Included Included Excluded Included Included Included Excluded $35.15 Included Included Included $4.12 $5.00 $2.00 $72.00 $10,000.00
099100 099100 S 099100 S 099100 S 099100 S 099100 S 099100 S 099100 S 099100 S 099100 S 099100 S 099100 S 099100 S 099100 S 099100 S 099100 S 099100 S 099100 S 099100 S 099100 S 099100 S 099100 S 099100 S 099100 S 099100 S 099100 S
Painting Painting Sub Bid Exterior Painting Prep and Paint Flagpole Handrail at East Plaza Ramp Sand, Prep, Paint Rooftop Gas Lines Paint Entire Exterior Soffit at Rotunda Paint Entire Exterior Soffit Outside Main Entry Interior Painting Paint All Walls in Computer Lab & Photography Green Screen Paint on One Wall Paint Walls in Storage 2106 & Media 2105 Paint South Wall of Corridor Outside Photography Paint Columns at Entry 95 Paint Columns at Corridor 2101A Sand, Prep, Paint HM Doors/Frames at Entry 95 Paint Ceilings & Walls Above Tile in RRs 128/129 Paint Ceilings & Walls Above Tile in RRs 184/186 Paint Ceilings & Walls Above Tile in RRs 214/216 Paint Ceilings & Walls in RRs 123A/123B Painting Ceiling in Restroom 141 Painting Ceiling in Entry 95B & Vest 95C Paint Select Walls in Music Room Paint Walls in Aux. Gym 009 Paint "WE ARE CENTENNIAL" Lettering Paint Gyp Soffit in Corridor 140A
1 ls 1 ls 1 ea 17 lf 810 lf 527 sf 2,640 sf 1 ls 1,550 sf 130 sf 370 sf 430 sf 290 sf 210 sf 4 ea 1,049 sf 294 sf 294 sf 90 sf 68 sf 235 sf 320 sf 3,503 sf 1 ls 2,640 ls
$57,991.00 Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included
Cost
Section
Division
$/sf
-----------
Comments
Plans call for tile replacements only
$225,438
$2.27
$55,440
FloorCrafters
$52,915
Ponder; see clarifications for product substitution information
-----------------------
Floor in RRs 123A/123B are now shown as Epoxy
No new tile at floors, not required at walls Miracle Method, Rooms 184 and 186 Due to enlarging grease interceptor Rooms 128, 129, 123A, 123B
$28,577 -------
Miracle Method, Rooms 184, 486, 214, 216
$28,541 $3,725 $16,000 $30,240 $10,000 $68,741 $57,991 -------------------------------------------------
$0.69 DaVinci Coatings 35' Tall Gas lines to be drained prior to painting
Inside room and Outside
3'-8" of wall height above tile 2'-0" of wall height above tile 2'-0" of wall height above tile 2'-0" of wall height above tile
Due to patches for access to floor boxes
Direct Costs
Page 8
Exhibit C
DIRECT COST WORKSHEET BVSD - Centennial Middle School 100% Construction Documents
Project: Stage: Code
Cat
Scope of Work
October 24, 2025
Qty
Unit $
2,640 ls 3,165 sf 665 sf 7 ea 40 lf 1 ls 1 ls 1 ls
Cost
Included Included Included Included Included $10,000.00 Excluded $750.00
-----------
Excluded
---
Section
099100 S 099100 S 099100 S 099100 S 099100 S 099100 A 099100 X 099100 E
Paint ACT Ceiling in Corridor 140A Paint ACT Ceiling in Corridor 209,220,230 Paint ACT Ceiling in Corridor 160 Paint New Hollow Metal Door Frames Paint Exposed Pump Out Piping in Kitchen Allowance - Repaint/Repair Mech. Covers in RRs Prep & Paint Tile/Glazed Block in Restrooms Lift for Flag Pole
097200 097200 X
Wall Coverings Vinyl Wall Covering at Entry
100000
Specialties
101100 101100 S 101100 S 101100 S 101100 S 101100 A
Visual Display Units Visual Display Units Base Bid Marker Board in Computer Lab - 4' x 10' Marker Board in Media Room - 4' x 4' Tack Board in Computer Lab - 4' x 4' Allowance - Projector Screen in Computer Lab
1 ls 1 ea 1 ea 1 ea 1 ea
$5,160.00 Included --Included --Included --$15,340.00
102800 102800 S 102800 S 102800 S 102800 X 102800 S 102800 S 102800 S 102800 X 102800 S 102800 S 102800 S 102800 S 102800 S 102800 S 102800 S 102800 S 102800 S 102800 S 102800 S 102800 S 102800 S
Restroom Accessories Restroom Accessories Base Bid Restrooms 128/129 Install New Soap Dispensers - OFCI All Other Accessories in this Restroom Restrooms 184/186 Install New Soap Dispensers - OFCI Supply/Install New Mirrors - CFCI - 24"x36" All Other Accessories in this Restroom Restrooms 214/216 Install New Soap Dispensers - OFCI Supply/Install New Mirrors - CFCI - 24"x36" All Other Accessories in this Restroom Restrooms 123A/123B Install Grab Bars - CFCI Sanitary Napkin Disposal - CFCI Install New Soap Dispensers - OFCI Install New Toilet Paper Dispensers - OFCI Install New Paper Towel Dispensers - OFCI Supply/Install New Mirrors - CFCI - 24"x36" All Other Accessories in this Restroom Remove & Re-install Hand Dryers
1 ls 1 ls 4 ea 1 ls 1 ls 5 ea 7 ea 1 ls 1 ls 5 ea 7 ea 1 ls 1 ls 6 ea 2 ea 5 ea 2 ea 2 ea 2 ea 1 ls 6 ea
$2,516.00 Included Included Excluded Included Included Included Excluded Included Included Included Excluded Included Included Included Included Included Included Included Excluded Included
101400 101400 S 101400 S 101400 S
Signage Signage Base Bid Signage at Media, Storage, Photography Mural at Front Entry - 5' x 6'-6"
1 ls 4 ea 1 ea
$3,741.00 Included --Included ---
$3,741
108000 108000 S 108000 S 108000 S 108000 S 108000 S 108000 S
Miscellaneous Specialties New Aluminum Bleachers at Ball Field Move Existing Bleachers and Install on New Pads Custom Graphic Wall Protection Boards Cubicle Curtains and Track Corner Guards Toilet Partition - Remove & Re-Install
1 ea 1 ea 1 ls 1 ls 4 sf 1 ls
$25,612.50 $762.50 $16,938.00 $3,964.00 Included --$8,700.00
$25,613 $763 $16,938 $3,964
Division
Comments
Grease interceptor pump out piping $10,000 This painting appears to have gone away due to Miracle Method
--$750 $0
1 ls
$/sf
$0.00 Now acrylic. Included with signage $82,734
$20,500
$0.83 $0.21
$5,160
ABS
$15,340
No spec provided. $2,516
$0.03 ABS
$2,516 -----------------------------------------
Owner Furnished, Contractor Installed Assumed Hand dryers, grab bars, toilet paper, etc. is to remain Owner Furnished, Contractor Installed Contractor Furnished, Contractor Installed
Owner Furnished, Contractor Installed Contractor Furnished, Contractor Installed
Contractor Furnished, Contractor Installed Contractor Furnished, Contractor Installed Owner Furnished, Contractor Installed Owner Furnished, Contractor Installed Owner Furnished, Contractor Installed Contractor Furnished, Contractor Installed
$3,741
$0.04 Print Partners Printed on 2nd side of acrylic panel. Graphic is TBD
$55,977
$8,700 Direct Costs
$0.56 Ground Solutions Ground Solutions ABS ABS ABS ABS - Includes R&R of Accessories attached to them Page 9
Exhibit C
DIRECT COST WORKSHEET BVSD - Centennial Middle School 100% Construction Documents
Project: Stage: Code
Cat
Scope of Work
120000
Furnishings
123216 123216 S 123216 S 123216 S 123216 S 123216 X 123216 X 123216 S 123216 S 123216 S 123216 S 123216 S
Manufactured Casework & Countertops Manufactured Casework Base Bid RRs 128/129 - Quartz Countertops P-lam Supports & Removable Panels 4" Quartz Back & End Splashes, & Trim Storage Room 2106 - P-Lam Shelving Comp. Lab 2103 - Quartz Tops at Seating/Desk Comp. Lab 2103 - Solid Surface Tops at Cabinetry Solid Surface Back & End Splashes Comp. Lab 2103 - P-lam Base Cabinets & Cubbies Comp. Lab 2103 - P-lam Upper Cabinets Comp. Lab 2103 - P-lam Storage Cabinets - 7' Tall
140000
Conveying Systems
140000 140000 S 140000 A
Elevator Renovation Elevator Renovation Base Bid Allowance - Elevator Refurbishment
220000
Plumbing
220000 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S
Plumbing Systems Plumbing Base Bid Permits Required for Scope Safe-off For Demo of Plumbing Systems Men's & Women's Restrooms 123A/123B New Water Closets New Wall Hung Lavatories/Faucets Mixing Valves Under Sink Lav Guards Girl's & Boy's Restrooms 128/129 Remove Drop-in Lavatories/Faucets - Salvage Install Salvaged Drop-in Lavatories Mixing Valves Under Sink Lav Guards New Water Closets on Existing Carriers New Urinals on Existing Carriers Adjust Floor Drains for New Floor Thickness Girl's & Boy's Restrooms 184/186 New Water Closets on Existing Carriers New Urinals on Existing Carriers New Wall Hung Sinks/Faucets on Existing Carriers Under Sink Lav Guards Mixing Valves Girl's & Boy's Restrooms 214/216 New Water Closets on Existing Carriers New Urinals on Existing Carriers New Wall Hung Sinks/Faucets on Existing Carriers Mixing Valves Under Sink Lav Guards Kitchen 132 Remove SS Prep Sink Above Grease Interceptor
October 24, 2025
Qty
Unit $
Cost
Section
Division
$53,813 $53,813 1 ls 2 ea 1 ls 1 ls 1 ls 182 sf 89 sf 89 sf 48 lf 30 lf 8 lf
$53,812.50 Included Included Included Excluded Excluded Included Included Included Included Included
$0.54 Sun Architecture
---------------------
No longer shown Computer station desk/tops to be FFE
$140,000 Pending --$140,000.00
Allowance for all work associated with the elevator refurbishment
$140,000
$282,079 $281,179.36 Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included
$1.41 $1.41
$282,079
1 ls 1 ls 1 ls 1 ls 2 ea 2 ea 2 ea 2 ea 1 ls 6 ea 6 ea 6 ea 6 ea 6 ea 2 ea 2 ea 1 ls 8 ea 2 ea 7 ea 7 ea 7 ea 1 ls 8 ea 5 ea 7 ea 7 ea 7 ea 1 ls 1 ea
Comments
$0.54
$53,813
$140,000
1 ls 1 ls
$/sf
$281,179 -----------------------------------------------------------
$2.83 $2.83 ProCraft Mechanical
Flooring going from tile to Epoxy
Direct Costs
Page 10
Exhibit C
DIRECT COST WORKSHEET BVSD - Centennial Middle School 100% Construction Documents
Project: Stage: Code
Cat
Scope of Work
220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 M 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 X 220000 E
Remove Existing Grease Interceptor Install New Grease Interceptor Excavation/Backfill for New GI Location Re-work Piping from Sinks Pump Out Kit Routed to Exterior Wall Re-install Sink Above to Grease Interceptor Two-way Cleanouts Gasketed Cover for Grease Interceptor Stainless Steel Cover for Vertical Piping Surface Protection for Kitchen Work Mechanical 191 Remove Hot Water Heaters Remove Storage Tanks New Gas Water Heaters Condensate Neutralizers New Expansion Tank New Circulation Pump New Gas Piping as Shown New Gas Pressure Regulators Media Room 2105 Hydronic Lines Extended to New Duct Coil All Associated Valves and Fittings Pipe Insulation Where Required Testing, Adjusting, Balancing Controls Via Albireo Camera Sanitary Lines at Grease Interceptor Sterilization of Water Lines Draining & Filling of Systems as Needed for Work Removal & Replacement of Fixture Carriers Waste Management
230000
HVAC
238000 238000 S 220000 S 220000 S 220000 S 220000 S 238000 S 238000 S 238000 S 220000 S 220000 S 220000 S 238000 S 238000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 220000 S 238000 S 238000 S
Heating/Cooling/Air HVAC Base Bid Permits Required for Scope Mechanical 191 Remove Existing 6" Water Heater Flues Patch Existing 26" Duct at Removed 6" WH Ducts New Flue/Combustion Piping for New Water Heaters Cores Through Floor and Roof Terminations Above Roof Restroom 141 Ceiling Mounted Exhaust Fan Ducting to Courtyard Louver/Termination at Courtyard Core Through Exterior Wall Computer Lab/Photography/Media/Storage Remove Existing Fire/Smoke Damper Remove Existing Transfer Boots New Fire/Smoke Dampers Thru Wall Sleeves 14 Gauge Angles Around Sleeves Access Doors New Duct Mounted Hydronic Coil New Transfer Ducting
October 24, 2025
Qty
Unit $ 1 ea 1 ea 1 ls 1 ls 1 ea 1 ea 2 ea 1 ea 9 lf 1 ls ls 2 ea 4 ea 2 ea 2 ea 1 ea 1 ea 1 ls 2 ea ls 2 ea 2 ea 4 ea 4 ea 2 ea 2 ea 2 ea 2 ea 1 ea 2 ea
Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Excluded $450.00
Cost
Section
Division
-------------------------------------------------------
Assumed existing carriers are to be re-used for new plumbing fixtures $900
$70,295 $70,294.84 Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included
Comments
Assumed surface mounted on wall and ceiling
$70,295
1 ls 1 ls ls 2 ea 2 ea 4 ea 8 ea 4 ea ls 2 ea 2 ea 4 ea 8 ea ls 1 ea 1 ea 2 ea 2 ea 1 ls 1 ls 1 ea 1 ls
$/sf
$70,295
$0.71 $0.71 ProCraft Mechanical
-------------
Routed through roof
-------------------------
Direct Costs
Page 11
Exhibit C
DIRECT COST WORKSHEET BVSD - Centennial Middle School 100% Construction Documents
Project: Stage: Code
Cat
Scope of Work
October 24, 2025
Qty
Unit $
238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S 238000 S
All Required Access Doors All Required Dampers All Ducting Shown All Insulation/Lining/Wrap Where Required All Required Grilles, Registers, and Diffusers Testing, Adjusting, Balancing Rebalancing of Existing Duct Coil in Comp Lab Controls Via Albireo CAD Coordination
4 ea 1 ea 2 ea 2 ea 6 ea 1 ls 1 ea 1 ls 1 ls
Included Included Included Included Included Included Included Included Included
260000
Electrical
261000 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S
Electrical Systems Electrical Base Bid Safe-off For Demo of Electrical Systems Proper Disposal of Light Fixtures, Ballasts, & Bulbs Recycling of Metal Components Mechanical 191 Disconnect Existing Water Heaters Extend Circuit/Reconnect to New Water Heaters New Circuit for Circ. Pump Restroom 141 New Circuit for New Exhaust Fan Restrooms 123A/123B,184/186,214/216,128/129 Remove Existing Light Fixtures and Wiring Devices New Lighting and Lighting Controls New Lighting and Controls in Vest 123 Removal & Reinstall of Hand Dryers Comp. Lab, Photography, Media Remove Existing Light Fixtures and Wiring Devices Remove Existing Power and Data New Power to Receptacles Coring/Cutting for New Floor Boxes Rough-in for Technology & Fire Alarm New Lighting and Lighting Controls Corridor 140A Remove Existing Light Fixtures and Wiring Devices New Lighting and Lighting Controls Corridor 97,98,99,100,113,121,130,130A,150 Remove Existing Light Fixtures - Salvage Re-Install Existing Light Fixtures in New ACT Stage 187 Remove Existing Theatrical Light Fixtures New Theatrical Light Fixtures Schedule 80 Pipe for New Wall Fixtures Theatrical Lighting Controls and Cabling
1 ls 2 ea 2 ea 2 ea 2 ea 4 ea 29 ea 1 ls 2 ea 4 ea 2 ea 1 ea 1 ea 1 ea 1 ea 1 ls 1 ls 1 ea 24 ea 24 ea 7 ea 5 ea 1 ls 1 ea 1 ea 1 ls 1 ea 1 ea 7 ea 5 ea 2 ea 2 ea 2 ea
$124,423.20 Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included
261000 A 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S 261000 S
Allowance - Theatrical Lighting System Entry 95 & Corridor 95A Remove Wall Sconces New Wall Sconces Corridor 2101A Remove Wall Sconces New Wall Sconces Scaffolding or Lifts for Lighting Replacements Components for New Fire/Smoke Dampers
1 ls 1 ls 5 ea 5 ea 1 ls 7 ea 7 ea 2 ea 1 ea
$190,000.00 Included Included Included Included Included Included Included Included
Cost
Section
Division
$/sf
Comments
------------------$317,015 $317,015
$3.19 $3.19
$124,423
ADK Electric
$190,000
Pending final design. Allowance is for all scope related to the theatrical lighting replacement.
-----------------------------------------------------------------
----------------Direct Costs
Page 12
Exhibit C DIRECT COST WORKSHEET BVSD - Centennial Middle School 100% Construction Documents
Project: Stage: Code
Cat
261000 S
Scope of Work
261000 S 261000 S 261000 S 261000 S 261000 L 261000 X 261000 X
Ceiling Tile Cutouts for Lighting Temp Lighting in Corridors for ACT & Lighting Replacements Rough-in for Technology/Data Controlled Receptacles Where Required Components for New Fire/Smoke Dampers Coordination of Salvaged Lighting Electrical Support for Paging System Electrical Support for Elevator
270000
Communications
271000 S 271000 S 271000 S 271000 S 271000 A
Structured Cabling Structured Cabling Base Bid Demo Existing Data in Computer Lab Install Data Drops for Computer Lab Allowance - Removal & Replace Paging System
280000
Electronic Safety & Security
281000 281000 S 281000 S 281000 S 281000 S
Fire Alarm FACP Removal & Replacement Components for New Fire/Smoke Dampers Adjustments to Existing FA Devices for New Layouts Permits
310000
Earthwork
312000 312000 S 312000 S 312000 X 312000 S
Earthwork Earthwork Base Bid 4" Lift of 1 1/2" Granite at East Parking Lot 4" Lift of 1 1/2" of #411 at East Parking Lot Spoils Removal from Grease Interceptor
320000
Exterior Improvement
321213 321213 S 321213 S 321213 X 321213 S 321213 X 321213 S 321213 S 321213 A
Asphalt Paving Asphalt Paving Base Bid 2" Mill & Overlay of West Parking Lot Mesh at Crack Along North Side of Lot Patching at East End of Parking Lot "T" Patching ROW Permit for Lane Closure in 21st Traffic Control For Mill & Overlay Allowance - Crack Repairs Prior to Overlay
321723 321723 S 321723 S 321723 S 321723 S 321723 S 321723 S 321723 S 321723 S
Striping & Signage Striping Base Bid Striping at West Parking Lot Standard Parking Spaces - Yellow Handicap Parking Stencils Handicap Parking Aisles Crosswalk Striping Paint Curbs Safety Yellow Pedestrian Crossing Signs (W11-2 & W16-7PL)
October 24, 2025
Qty
Unit $
Cost
1 ea
Included
---
1 ea 24 ea 7 ea 6 ea 36 hr 1 ls 1 ls
Included Included Included Included
---------
$72.00 Excluded --Excluded ---
Section
Division
$/sf
Comments
$2,592 Scope not clear at time of this estimate. Allowance created in Div 14 Scope not clear at time of this estimate. Allowance created in Div 27 $230,000
$2.31
$230,000 1 ls 1 ls 1 ls 1 ls
Included --Included --Included --$230,000.00
Included with Electrical Bid. Remove data cables back to patch panel New Cat6 from patch panel to floor & wall boxes Allowance for all scope associated with paging system
$230,000 $0
$0.00
$0 1 ls 2 ea 1 ls 1 ls
Included Included Included Included
---------
Fire Alarm Work Included with Electrical Contractor
$68,125 $68,125 1 ls 29,705 sf 1 ls 1 ls
$68,125.00 Included --Excluded --Included ---
$0.68 Ground Solutions
$68,125
Changed to 1 1/2" granite per district request
$227,340 $103,895 1 ls 2,885 sy 1 ls 88 sy 1 ls 1 ls 2 ea 1 ls
$86,495.00 Included Excluded Included Excluded $3,500.00 $2,850.00 $8,200.00
1 ls 1 ls 66 ea 3 ea 2 ea 2 ea 650 lf 4 ea
$4,863.00 Included Included Included Included Included $2.00 Included
$0.68
$2.28 $1.04 Martin Marietta
$86,495 ---------
See voluntary alternate #4 A "T" type patch isn't needed since the asphalt will be milled down $3,500 $5,700 $8,200 $6,163 $4,863
$0.06 Precise Striping
----------$1,300 ---
Each location to get sleeve, post, pedestrian sign, direction arrow Direct Costs
Page 13
Exhibit C
DIRECT COST WORKSHEET BVSD - Centennial Middle School 100% Construction Documents
Project: Stage: Code
Cat
Scope of Work
October 24, 2025
Qty
Unit $
321723 X 321723 X
Stop Signs ADA Parking Signs
321600 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 S 321600 L 321600 S
Site Concrete Site Concrete Base Bid Repair Ramp at East Plaza Railings Fill Existing Pipe Sleeves with Grout Concrete Pads at Bleachers 10' x 20' Remove Soil and Prep for New Pads Thickened Edge at Concrete Pad Rebar at Thickened Edge Concrete Sidewalk to Bleacher Pad Remove Soil and Prep for New Pads Dowel Into Existing ROW Sidewalk Sealed Expansion Joint at ROW Sidewalk Footings for Bollards at East Parking Set and Fill Steel Bollards Bollard Covers Chain Between Bollards Concrete Sidewalks at West Parking Lot - 5" Remove Soil and Prep for New Pads Recondition Subgrade to 12" Depth Remove Curb & Gutter for New Ramps Curb Ramps at South Drive Detectable Warning Panels Curb & Gutter Transitions (E) to (N) 4" ABC Below Sidewalks Dowel Into Existing Sealed Expansion Joints Layout/Coordination/QAQC Private Locates
1 ls 1 ls 1 ls 400 sf 400 sf 120 lf 1 ls 97 sf 97 sf 3 ea 5 lf 21 ea 21 ea 21 ea 151 lf 455 sf 415 sf 455 sf 21 lf 2 ea 4 ea 4 ea 6 cy 1 ls 20 lf 36 hr 1 ls
$97,446.00 Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included Included $72.00 $2,500.00
323100 323100 S 323100 S 323100 S 323100 S 323100 S 323100 S 323100 S 323100 S 323100 S
Fencing Fencing Base Bid Demo Existing Chainlink Fence - Haul Off Remove Concrete Footers at All Posts New Chain Link Fencing - 6' New Gate at Baseball Field - 6' Tall New Terminal Posts Standard Hardware Adjust Existing 6' Fence for New Gate Remove & Re-Install Fencing for Access to Field
1 ls 110 lf 1 ls 110 lf 1 ea 1 ea 1 ea 1 ea 1 ls
$9,744.00 Included Included Included Included Included Included Included Included
324000 324000 S 324000 A
Landscape & Irrigation Sod Repairs at New Sidewalk and Bleacher Pads Allowance - Irrigation Modifications
1 ls 1 ea
$2,500.00 $2,500.00
TOTALS
1 ls 1 ls
Excluded Excluded
Cost
Section
Division
$/sf
Comments Shown in sign details, but not indicated on plans Shown in sign details, but not indicated on plans
----$102,538
$1.03 Ground Solutions
$97,446 -------------------------------------------------
18" diameter x 3'-6" 5" Diameter Steel Bollards Reliance Foundry R7551 Covers
$2,592 $2,500 $9,744
$0.10 Metro Fence
$9,744 -----------------
To create access to baseball field concrete pads & bleachers $5,000
$0.05
$2,500 $2,500
$2,295,123
At West side of parking lot At concrete pads & walks being added in sod areas
$2,295,123
Direct Costs
$2,295,123
$23.06
99,515 GSF
Page 14
Exhibit D Contract Schedule to be provided after amendment & change order for the GMP is executed
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit D
CONSTRUCTION SCHEDULE
CENTENNIAL MIDDLE SCHOOL Activity ID
Activity Name
Original Start Duration
CENTENNIAL MIDDLE SCHOOL MILESTONES
Finish
191 28-Nov-25
01-Sep-26
191 28-Nov-25
01-Sep-26
N
D
D
A1000
GMP Executed
0 28-Nov-25
GMP Executed
A1010
NTP
0 28-Nov-25
NTP
A1020
Start Of Construction
0 26-May-26*
A1030
Substantial Completion
0 31-Jul-26*
A1040
Final Completion
0 01-Sep-26*
PRECONSTRUCTION & MOBILAZATION
49 26-May-26
03-Aug-26
D
D
J
J
J
J
F
F
F
PALACE CONSTRUCTION F
M
M
M
M
M
A
A
A
A
M
M
M
M
M
J
J
J
J
J
J
J
J
23 26-May-26
25-Jun-26
3 26-May-26
28-May-26
Replace Fencing
A1060
Remove East Parking Lot Concrete Barriers
1 29-May-26
29-May-26
Remove East Parking Lot Concrete Barriers
A1070
Install Agg Paving
3 01-Jun-26
03-Jun-26
Install Agg Paving
A1080
Install New Ballard's
2 04-Jun-26
05-Jun-26
Install New Ballard's
A1090
Remove Wooden Bleachers
1 08-Jun-26
08-Jun-26
Remove Wooden Bleachers
A1100
Place New Concrete Pads
3 09-Jun-26
11-Jun-26
Place New Concrete Pads
A1110
Exterior Painting
5 12-Jun-26
18-Jun-26
Exterior Painting
A1120
Plaza Ramp Repair
5 19-Jun-26
25-Jun-26
20 29-May-26
25-Jun-26
A1130
Owner Removal Of ACM @ Gym Floor
10 29-May-26
11-Jun-26
A1140
Owner Removal Of ACM Above Ceiling
10 12-Jun-26
25-Jun-26
5 26-May-26
01-Jun-26
DEMO (LOWER LEVEL)
Owner Removal Of ACM @ Gym Floor Owner Removal Of ACM Above Ceiling
Remove Wrestling Mats
1 26-May-26
26-May-26
Remove Wrestling Mats
A1170
Remove Weight Lifting Equipment
2 27-May-26
28-May-26
Remove Weight Lifting Equipment
A1180
Remove Acoustic Wall Panels
1 29-May-26
29-May-26
Remove Acoustic Wall Panels
A1190
Remove Snap In Floor Tile
2 29-May-26
01-Jun-26
Remove Snap In Floor Tile
31 26-May-26
08-Jul-26
31 26-May-26 2 26-May-26
08-Jul-26 27-May-26
Demo Partitions & Salvage Demo Plumbing Fixtures
BATHROOM DEMO A1200 Demo Partitions & Salvage A1210
Demo Plumbing Fixtures
2 28-May-26
29-May-26
A1220
Demo Tile
2 01-Jun-26
02-Jun-26
A1230
Demo Walls & Ceilings
3 03-Jun-26
05-Jun-26
Demo Walls & Ceilings
3 01-Jun-26 2 01-Jun-26
03-Jun-26 02-Jun-26
Demo Water Heaters & Tanks
1 03-Jun-26
03-Jun-26
Demo HVAC
7 04-Jun-26 4 04-Jun-26
12-Jun-26 09-Jun-26
Demo Glass Block
MECHANICAL ROOM DEMO A1240 Demo Water Heaters & Tanks A1250
Demo HVAC
ENTRY AREA DEMO A1260 Demo Glass Block
Demo Tile
A1270
Demo Flooring
1 10-Jun-26
10-Jun-26
Demo Flooring
A1280
Demo Ceiling For New Electrical
2 11-Jun-26
12-Jun-26
Demo Ceiling For New Electrical
6 26-Jun-26 2 26-Jun-26
06-Jul-26 29-Jun-26
Demo ACT Ceiling
COORIDOR DEMO A1290 Demo ACT Ceiling A1300
Remove Lighting & Salvage
3 30-Jun-26
02-Jul-26
A1310
Demo Gyp Ceiling For New Exhaust
1 06-Jul-26
06-Jul-26
5 08-Jun-26 1 08-Jun-26
12-Jun-26 08-Jun-26
KITCHEN DEMO A1320 Demo Fixtures Actual Level of Effort
Remaining Work
Start Constraint
Actual Work
Critical Remaining Work
Baseline Milestone
A
Plaza Ramp Repair
A1160
DEMO (MAIN LEVEL)
A
Substantial Completion
Replace Fencing
ABATEMENT
A
Start Of Construction
A1050
EXTERIOR IMPROVMENTS
A
Remove Lighting & Salvage Demo Gyp Ceiling For New Exhaust Demo Fixtures Page 1 of 5
Data Date: 10/29/2025
Exhibit D
CONSTRUCTION SCHEDULE
CENTENNIAL MIDDLE SCHOOL Activity ID
Activity Name
Original Start Duration
Finish
N
D
D
D
D
J
J
J
J
F
F
F
PALACE CONSTRUCTION F
M
M
M
M
M
A
A
A
A
M
M
M
M
M
J
J
J
J
J
J
J
J
A
A1330
Demo Slab For New Grease Interceptor
2 09-Jun-26
10-Jun-26
Demo Slab For New Grease Interceptor
A1340
Demo Grease Interceptor
2 11-Jun-26
12-Jun-26
Demo Grease Interceptor
2 07-Jul-26 2 07-Jul-26
08-Jul-26 08-Jul-26
15 03-Jun-26 8 10-Jun-26 2 10-Jun-26
23-Jun-26 19-Jun-26 11-Jun-26
Demo ACT Ceiling
AUDITORIUM DEMO A1350 Demo Theater Lighting DEMO (UPPER LEVEL) Demo CTE Area A1360 Demo ACT Ceiling Demo Lighting
2 12-Jun-26
15-Jun-26
Demo Lighting
A1380
Demo Walls
1 16-Jun-26
16-Jun-26
Demo Walls
A1390
Demo Platform Structure
1 17-Jun-26
17-Jun-26
Demo Platform Structure
A1400
Demo Millwork
1 18-Jun-26
18-Jun-26
Demo Millwork
A1410
Demo Doors & Frames
1 19-Jun-26
19-Jun-26
Demo Doors & Frames
4 03-Jun-26 2 03-Jun-26
08-Jun-26 04-Jun-26
Demo Partitions & Salvage
2 05-Jun-26
08-Jun-26
Demo Plumbing Fixtures
3 09-Jun-26 1 09-Jun-26
11-Jun-26 09-Jun-26
Demo Bench
A1430
Demo Plumbing Fixtures
DEMO MUSIC ROOM A1440 Demo Bench A1450
Demo ACT Ceilings
1 10-Jun-26
10-Jun-26
Demo ACT Ceilings
A1460
Demo Acc Panel & Salvage
1 11-Jun-26
11-Jun-26
Demo Acc Panel & Salvage
8 12-Jun-26 5 12-Jun-26
23-Jun-26 18-Jun-26
Demo ACT Ceiling Demo Lighting
DEMO COORIDORS A1470 Demo ACT Ceiling A1480
Demo Lighting
INTERIOR FINISHES LOWER LEVEL FINISHES A2450 Interior Painting
3 19-Jun-26
23-Jun-26
42 04-Jun-26
03-Aug-26
12 24-Jun-26 4 24-Jun-26
10-Jul-26 29-Jun-26
A
Interior Painting
A2460
Install Rubber Flooring
3 30-Jun-26
02-Jul-26
Install Rubber Flooring
A2470
Install Wall Panels
2 06-Jul-26
07-Jul-26
Install Wall Panels
A2480
Re-Install Weight Equipment
2 08-Jul-26
09-Jul-26
Re-Install Weight Equipment
A2490
Install Wrestling Matt
1 10-Jul-26
10-Jul-26
Install Wrestling Matt
38 04-Jun-26 35 09-Jun-26 2 09-Jun-26
28-Jul-26 28-Jul-26 10-Jun-26
MAIN LEVEL FINISHES BATHROOM FINISHES A1490 Frame New Walls & HM Frames
A
Demo Theater Lighting
A1370
DEMO BATHROOMS A1420 Demo Partitions & Salvage
A
Frame New Walls & HM Frames
A1500
MEP Rough IN's
5 11-Jun-26
17-Jun-26
MEP Rough IN's
A1510
Install Backing
2 18-Jun-26
19-Jun-26
Install Backing
A1520
MEP Rough Inspections
1 18-Jun-26
18-Jun-26
MEP Rough Inspections
A1530
Framing Inspection
1 19-Jun-26
19-Jun-26
Framing Inspection
A1540
Install Insulation
1 22-Jun-26
22-Jun-26
Install Insulation
A1550
Install Drywall
3 23-Jun-26
25-Jun-26
Install Drywall
A1560
Screw Inspection
1 26-Jun-26
26-Jun-26
Screw Inspection
A1570
Tape & Finish Drywall
5 29-Jun-26
06-Jul-26
Tape & Finish Drywall
A1580
Interior Painting
5 07-Jul-26
13-Jul-26
Interior Painting
A1590
Install Tile
4 14-Jul-26
17-Jul-26
Install Tile
A1600
Epoxy Flooring
3 20-Jul-26
22-Jul-26
A1610
Install Bathroom Partitions
2 23-Jul-26
24-Jul-26
Install Bathroom Partitions
A1620
Install Wall Hung Countertops
1 23-Jul-26
23-Jul-26
Install Wall Hung Countertops
Actual Level of Effort
Remaining Work
Start Constraint
Actual Work
Critical Remaining Work
Baseline Milestone
Epoxy Flooring
Page 2 of 5
Data Date: 10/29/2025
Exhibit D
CONSTRUCTION SCHEDULE
CENTENNIAL MIDDLE SCHOOL Activity ID
Activity Name
Original Start Duration
Finish
N
D
D
D
D
J
J
J
J
F
F
F
PALACE CONSTRUCTION F
M
M
M
M
M
A
A
A
A
M
M
M
M
M
J
J
J
J
J
J
J
J
A
A
A
A
A1630
Install Bathroom Accessories
1 23-Jul-26
23-Jul-26
A1640
Install MEP Trim
3 24-Jul-26
28-Jul-26
Install MEP Trim
A1650
Install Doors & Hardware
2 24-Jul-26
27-Jul-26
Install Doors & Hardware
A1660
Install ACT Ceiling
2 24-Jul-26
27-Jul-26
Install ACT Ceiling
A1670
Install Signage
ENTRY AREA FINISHES A1680 Install Storefront System
Install Bathroom Accessories
1 24-Jul-26
24-Jul-26
10 15-Jun-26 3 15-Jun-26
26-Jun-26 17-Jun-26
Install Signage Install Storefront System Drywall Repairs
A1690
Drywall Repairs
1 18-Jun-26
18-Jun-26
A1700
Interior Painting
4 19-Jun-26
24-Jun-26
A1710
Install Flooring
2 25-Jun-26
26-Jun-26
Install Flooring
A1720
Install Signage
1 25-Jun-26
25-Jun-26
Install Signage
A1730
Remove & Replace Fire Alarm Panel
1 25-Jun-26
25-Jun-26
Remove & Replace Fire Alarm Panel
14 07-Jul-26 2 07-Jul-26
24-Jul-26 08-Jul-26
Install Exhaust Fan For RR 141
COORIDOR FINISHES A1740 Install Exhaust Fan For RR 141
Interior Painting
A1750
Install New Lighting
3 07-Jul-26
09-Jul-26
Install New Lighting
A1760
Above Ceiling Inspection
1 10-Jul-26
10-Jul-26
Above Ceiling Inspection
A1770
Drywall Patching & Soffits
4 13-Jul-26
16-Jul-26
A1780
Interior Painting
2 17-Jul-26
20-Jul-26
A1790
Install NewACT Ceiling
4 21-Jul-26
24-Jul-26
Install NewACT Ceiling
A1920
Install wall Protection Board
3 21-Jul-26
23-Jul-26
Install wall Protection Board
12 15-Jun-26 3 15-Jun-26
30-Jun-26 17-Jun-26
Install New Grease Interceptor Plumbing Inspection
KITCHEN FINISHES A1800 Install New Grease Interceptor
Drywall Patching & Soffits Interior Painting
A1810
Plumbing Inspection
1 18-Jun-26
18-Jun-26
A1820
Backfill Grease Interceptor
2 19-Jun-26
22-Jun-26
Backfill Grease Interceptor
A1830
Prep & Place SOG
2 23-Jun-26
24-Jun-26
Prep & Place SOG
A1840
Epoxy Flooring
3 25-Jun-26
29-Jun-26
Epoxy Flooring
A1850
Re-Install Kitchen Equipment
1 30-Jun-26
30-Jun-26
Re-Install Kitchen Equipment
AUDITORIUM FINISHES A1860 Install New Theater Lighting
5 09-Jul-26 5 09-Jul-26
15-Jul-26 15-Jul-26
MECHANICAL ROOM A1870 Place Mechanical Concrete Pads
12 04-Jun-26 1 04-Jun-26
19-Jun-26 04-Jun-26
Install New Theater Lighting Place Mechanical Concrete Pads
A1880
MEP Rough In's
5 05-Jun-26
11-Jun-26
A1890
Install New Water Heaters
2 12-Jun-26
15-Jun-26
Install New Water Heaters
A1900
Install HVAC
2 16-Jun-26
17-Jun-26
Install HVAC
A1910
MEP Final Inspections
2 18-Jun-26
19-Jun-26
MEP Final Inspections
39 09-Jun-26 30 22-Jun-26 2 22-Jun-26
03-Aug-26 03-Aug-26 23-Jun-26
UPPER LEVEL FINISHES CTE FINISHES A1930 Frame New Walls & HM Frames
MEP Rough In's
Frame New Walls & HM Frames
A1940
MEP Rough In's
5 24-Jun-26
30-Jun-26
MEP Rough In's
A1950
MEP Inspections
1 01-Jul-26
01-Jul-26
MEP Inspections
A1960
Frame Inspections
1 02-Jul-26
02-Jul-26
Frame Inspections
A1970
Install Insulation
1 06-Jul-26
06-Jul-26
Install Insulation
A1980
Install Backing
1 06-Jul-26
06-Jul-26
Install Backing
A1990
Install Drywall
3 07-Jul-26
09-Jul-26
Install Drywall
A2000
Screw Inspection
1 10-Jul-26
10-Jul-26
Screw Inspection
Actual Level of Effort
Remaining Work
Start Constraint
Actual Work
Critical Remaining Work
Baseline Milestone
Page 3 of 5
Data Date: 10/29/2025
Exhibit D
CONSTRUCTION SCHEDULE
CENTENNIAL MIDDLE SCHOOL Activity ID
Activity Name
Original Start Duration
Finish
N
D
D
D
D
J
J
J
J
F
F
F
PALACE CONSTRUCTION F
M
M
M
M
M
A
A
A
A
M
M
M
M
M
J
J
J
J
J
J
J
J
A
A
A
A
A2010
Tape & Finish Drywall
4 13-Jul-26
16-Jul-26
Tape & Finish Drywall
A2020
Interior Painting
4 17-Jul-26
22-Jul-26
Interior Painting
A2030
Install ACT Ceiling
3 23-Jul-26
27-Jul-26
Install ACT Ceiling
A2040
Install Millwork
3 23-Jul-26
27-Jul-26
Install Millwork
A2050
Install Ceilings Tiles
2 28-Jul-26
29-Jul-26
Install Ceilings Tiles
A2060
Install Flooring
3 30-Jul-26
03-Aug-26
Install Flooring
A2070
Cubical Track & Curtains
3 23-Jul-26
27-Jul-26
Cubical Track & Curtains
A2080
Visual Display Boards
1 28-Jul-26
28-Jul-26
Visual Display Boards
A2090
Install Doors & Hardware
1 28-Jul-26
28-Jul-26
Install Doors & Hardware
A2100
Install Signage
1 29-Jul-26
29-Jul-26
Install Signage
BATHROOM FINISHES A2110 MEP Rough In's
17 09-Jun-26 3 09-Jun-26
01-Jul-26 11-Jun-26
MEP Rough In's
A2120
MEP Inspections
1 12-Jun-26
12-Jun-26
MEP Inspections
A2130
Drywall Ceilings
2 15-Jun-26
16-Jun-26
Drywall Ceilings
A2140
Interior Painting
3 17-Jun-26
19-Jun-26
A2150
Install Plumbing Fixtures
2 22-Jun-26
23-Jun-26
Install Plumbing Fixtures
A2160
Miracle Method
2 24-Jun-26
25-Jun-26
Miracle Method
A2170
Install Bathroom Partitions
3 26-Jun-26
30-Jun-26
Install Bathroom Partitions
A2180
Install Bathroom Accessories
1 01-Jul-26
01-Jul-26
Install Bathroom Accessories
14 12-Jun-26 1 12-Jun-26
01-Jul-26 12-Jun-26
MUSIC ROOM FINISHES A2190 Install New HVAC Rough In
Interior Painting
Install New HVAC Rough In
A2200
HVAC Inspection
1 15-Jun-26
15-Jun-26
A2210
Frame New Shaftwall
4 16-Jun-26
19-Jun-26
Frame New Shaftwall
A2220
Framing Inspection
1 22-Jun-26
22-Jun-26
Framing Inspection
A2230
Install Drywall
2 23-Jun-26
24-Jun-26
Install Drywall
A2240
Interior Painting
2 25-Jun-26
26-Jun-26
Interior Painting
A2250
ACT Repairs
1 29-Jun-26
29-Jun-26
ACT Repairs
A2260
Floor Repairs
1 30-Jun-26
30-Jun-26
Floor Repairs
A2270
Re-install Acc Wall Panels
1 01-Jul-26
01-Jul-26
Re-install Acc Wall Panels
8 24-Jun-26 1 24-Jun-26
06-Jul-26 24-Jun-26
Replace Acc Tiles
COORIDOR FINISHES A2280 Replace Acc Tiles
HVAC Inspection
A2290
Interior Painting
3 25-Jun-26
29-Jun-26
Interior Painting
A2300
Install New Light Fixtures
1 30-Jun-26
30-Jun-26
Install New Light Fixtures
A2310
Install Wall Protection Board
3 01-Jul-26
06-Jul-26
4 26-Jun-26
01-Jul-26
ROOF ACTIVITIES
Install Wall Protection Board
A2330
Remove Skylight
1 26-Jun-26
26-Jun-26
A2340
Install Metal Flashing's At Curb
1 29-Jun-26
29-Jun-26
Remove Skylight Install Metal Flashing's At Curb
A2350
Install New Skylight
1 30-Jun-26
30-Jun-26
Install New Skylight
A2360
New HVAC Flashing Penetrations
1 01-Jul-26
01-Jul-26
New HVAC Flashing Penetrations
19 02-Jul-26
29-Jul-26
A2370
Start Up & Testing
5 02-Jul-26
09-Jul-26
A2380
Final MEP Inspections
2 10-Jul-26
13-Jul-26
Final MEP Inspections
A2390
Palace Punchlist
4 14-Jul-26
17-Jul-26
Palace Punchlist
A2400
Subcontractor Corrections
3 20-Jul-26
22-Jul-26
A2420
Final Cleaning
3 23-Jul-26
27-Jul-26
FINAL INSPECTIONS & CLOSEOUT
Actual Level of Effort
Remaining Work
Start Constraint
Actual Work
Critical Remaining Work
Baseline Milestone
Start Up & Testing
Subcontractor Corrections Final Cleaning Page 4 of 5
Data Date: 10/29/2025
Exhibit D
CONSTRUCTION SCHEDULE
CENTENNIAL MIDDLE SCHOOL Activity ID
Activity Name
Original Start Duration
Finish
N
D
D
D
D
J
J
J
J
F
F
F
PALACE CONSTRUCTION F
M
M
M
M
M
A
A
A
A
M
M
M
M
M
J
J
J
J
J
J
J
J
A
A
A
A
A2430
Owner Turnover
2 28-Jul-26
29-Jul-26
Owner Turnover
A2440
Life Safety Inspection
5 23-Jul-26
29-Jul-26
Life Safety Inspection
Actual Level of Effort
Remaining Work
Start Constraint
Actual Work
Critical Remaining Work
Baseline Milestone
Page 5 of 5
Data Date: 10/29/2025
Exhibit E Insurance Certificates to be provided after amendment & change order for the GMP is executed
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit F Performance Bond to be provided after amendment & change order for the GMP is executed
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit G Labor and Materials Payment Bond to be provided after amendment & change order for the GMP is executed
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit H Alternates prices not used for the amendment
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit H Schedule of Alternates Centennial Middle School Renovation
Alternate No. 01 – Replace lighting and controls in the auditorium, gyms, and cafeteria. Total added cost to the base cost in the GMP = $193,347.00 Alternate No. 02 – Replace lighting and controls in classrooms. Total added cost to the base cost in the GMP = $188,885.00 Alternate No. 03 – Replace lighting and controls in o'ices and support areas. Total added cost to the base cost in the GMP = $120,151.00
1 | Page
Exhibit I Unit prices not used for this amendment
Not Applicable No unit prices provided for this contract
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit J Allowances
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit J Allowances Centennial Middle School Renovation
Insulation replacement at entry so its, where removed for new floor boxes. = $1,400.00 Drip edge flashing at Rotunda = $2,500.00 Sealants/Code Compliance for existing-to-remain conditions above ceilings. = $7,500.00 Hardware for new doors, due to lack of specifications. = $7,000.00 Miscellaneous tile repairs = $10,000.00. Repaint or Repair Mechanical Covers in Restrooms = $10,000.00 Modify existing acoustic wall panels in music room to accommodate shaft wall. = $1,000.00 Projector Screen in Computer Lab, due to lack of specifications. = $15,340.00 Elevator Refurbishment, including all associated work. = $140,000.00 Theatrical Lighting System, including all associated work. = $190,000.00 Paging System Replacement, including all associated work. = $230,000.00 Crack sealing and crack repairs prior to asphalt overlay = $8,200.00 Irrigation Modifications, due to new concrete pads in sod areas = $2,500.00
1|Pa ge
Exhibit K Not Applicable
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit L Equipment rental rate schedule
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
Exhibit L
PALACE EQUIPMENT RENTAL RATES Unit of Measure Jobsite Trailer Delivery Setup / TieDowns (8) Dismantle/Return
Range/ Notes
2025
2026
2027
Rate
Rate $675 $415 $890 $1,000
Denver Metro Area Denver Metro Area Denver Metro Area
$660 $410 $870 $994
Rate $670 $415 $890 $1,000
Denver Metro Area
$150 $95 $320
$155 $100 $325
$160 $100 $325
$3,963 $2,463 $221 $882
$4,042 $2,513 $232 $882
$4,050 $2,525 $235 $882
$852 $596 $220
$855 $600 $220
per month
Storage Containers 40 Ft Container 20 Ft Container Delivery/Return
per month per month per trip
Skid Steer TR310 Skid Steer Case 60XT Skid Steer Delivery/Return Sweeper Attachment
per month per month per trip per month
Utility Vehicles Gator Utility Vehicle Golf Cart Delivery/Return
per month per month per trip
Denver Metro Area
$827 $579 $200
per Day Per Week per trip
plus fuel cost plus fuel cost Denver Metro Area
$207 $806 $200
$213 $830 $200
$215 $830 $200
per day per week per trip
plus fuel cost plus fuel cost Denver Metro Area
$223 $690 $200
$229 $710 $200
$230 $710 $200
Denver Metro Area
$2,200
$2,300
$2,300
Diesel Air Compressor Delivery/Return Diesel Dingo
Superintendent Truck
plus fuel cost plus fuel cost Denver Metro Area
Water Trailer
per day per week per month
plus fuel cost plus fuel cost plus fuel cost
$145 $450 $900
$145 $450 $900
$145 $450 $900
Dump Trailer
per day per week per month
Denver Metro Area Denver Metro Area Denver Metro Area
$235 $680 $1,380
$235 $680 $1,380
$235 $680 $1,380
plus cost of driver
$212
$233
$235
Intrusive Testing Trailer
Day
450 Trash/Dump Truck
per trip
Exhibit L
PALACE EQUIPMENT RENTAL RATES 2025
2026
2027
Rate
Rate
Rate
$333 $1,089 $2,400
$366 $1,198 $2,400
$370 $1,200 $2,400
per month per month per month
$445 $230 $170
$445 $230 $175
$445 $230 $175
per day per week per month
$85 $398 $1,430
$87 $410 $1,430
$87 $410 $1,430
per day per week per month
$16 $64 $133
$16 $66 $137
$17 $66 $137
per month per trip
$2,700 $380
$2,800 $380
$2,800 $380
per month per month per month per month
$80 $210 $190 $400 $200
$80 $210 $190 $400 $200
$80 $210 $190 $400 $200
Per LF Per LF/Month
$2.35 $0.70
$2.35 $0.70
$2.35 $0.70
Unit of Measure Flat Bed Truck
Scaffold (per section) Stair scaffold Frame scaffold Baker scaffold Temporary Heat Flagero Heater
Concrete Blankets (ea)
Solar powered Trailer w/ 2 Cameras Tower and camera rental delivery / pickup Security Cameras outdoor Bullet Camera Outdoor Dome multi-sensor camera Horn and Alarm Monitoring Onetime installation fee Solar Battery Pole Mount Cell service Temporary Fencing Install/Removal 12 Foot Panels
per day per week per month
Range/ Notes includes fuel, add cost of driver
Exhibit M General Conditions of the Contract
6500 East Arapahoe Road | Boulder, Colorado 80303 | 720-561-5930 | www.bond.bvsd.org
BOULDER VALLEY SCHOOL DISTRICT RE-2 BOULDER, COLORADO
GENERAL CONTRACT CONDITIONS BOND PROGRAM
GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT GENERAL CONDITIONS OF THE CONSTRUCTION AGREEMENT.................................................................................................... 2 GC 1.00
CONTRACT DOCUMENTS AND DEFINITIONS ............................................................................................................ 1
GC 2.00
REFERENCE STANDARDS .......................................................................................................................................... 2
GC 3.00
DRAWINGS AND SPECIFICATIONS ............................................................................................................................ 2
GC 4.00
ROYALTIES AND PATENTS ........................................................................................................................................ 3
GC 5.00
ITEMS COVERED BY CONTRACT PRICE ..................................................................................................................... 3
GC 6.00
EXECUTION, CORRELATION, INTENT, AND INTERPRETATION OF CONTRACT DOCUMENTS ...................................... 3
GC 7.00
MATERIALS, LABOR, FACILITIES, AND STORAGE....................................................................................................... 4
GC 8.00
PERFORMANCE AND PAYMENT BONDS ................................................................................................................... 5
GC 9.00
PERMITS AND COMPLIANCE WITH STATUTES, RULES, AND REGULATIONS .............................................................. 6
GC 10.00
SURVEYS, BENCHMARKS, MONUMENTS, STAKES, AND MEASUREMENTS ............................................................... 6
GC 11.00
CHANGED CONDITIONS ........................................................................................................................................... 7
GC 12.00
PROTECTION OF PERSONS, WORK AND PROPERTY ................................................................................................. 7
GC 13.00
WORK ON EXISTING BUILDINGS .............................................................................................................................. 8
GC 14.00
CONTRACTOR’S SUPERINTENDENCE AND SUPERVISION .......................................................................................... 8
GC 15.00
SUBSTITUTIONS ....................................................................................................................................................... 9
GC 16.00
SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES ................................................................................................. 9
GC 17.00
CASH ALLOWANCE................................................................................................................................................. 10
GC 18.00
EXPEDITING MATERIALS ........................................................................................................................................ 10
GC 19.00
BLASTING .............................................................................................................................................................. 11
GC 20.00
SOIL TEST REPORT ................................................................................................................................................. 11
GC 21.00
HAZARDOUS MATERIALS ....................................................................................................................................... 11
GC 22.00
DAMAGE TO UTILITIES ........................................................................................................................................... 11
GC 23.00
CHANGES IN THE WORK ........................................................................................................................................ 12
GC 24.00
CLAIMS FOR EXTRA COST....................................................................................................................................... 13
GC 25.00
DELAYS AND EXTENSIONS OF TIME ....................................................................................................................... 13
GC 26.00
ACCESS TO WORK .................................................................................................................................................. 14
GC 27.00
CORRECTION OF WORK ......................................................................................................................................... 14
GC 28.00
OWNER’S RIGHT TO CARRY OUT WORK ................................................................................................................. 16
GC 29.00
OWNER’S RIGHT TO TERMINATE CONTRACT ......................................................................................................... 16
GC 30.00
CONSTRUCTION SCHEDULE AND PROGRESS REPORTS ........................................................................................... 16
GC 31.00
SCHEDULE OF VALUES ........................................................................................................................................... 17
GC 32.00
PAYMENT .............................................................................................................................................................. 17
GC 33.00
INSURANCE ........................................................................................................................................................... 19
GC 34.00
SEPARATE CONTRACTS .......................................................................................................................................... 23
GC 35.00
SUBCONTRACTORS ................................................................................................................................................ 23
GC 36.00
RELATIONS OF CONTRACTOR AND SUBCONTRACTOR ........................................................................................... 24
GC 37.00
CONTRACTORS’ MUTUAL RESPONSIBILITY ............................................................................................................ 25
GC 38.00
CUTTING, PATCHING, AND EXCAVATING ............................................................................................................... 25
GC 39.00
EMPLOYEES ........................................................................................................................................................... 26
GC 40.00
CLEANING UP......................................................................................................................................................... 27
GC 41.00
USE OF PREMISES .................................................................................................................................................. 27
GC 42.00
OCCUPANCY .......................................................................................................................................................... 27
GC 43.00
TEMPORARY OR TRIAL USAGE ............................................................................................................................... 28
GC 44.00
TESTING OF BUILDING SYSTEMS ............................................................................................................................ 28
GC 45.00
LIQUIDATED DAMAGES FOR DELAY IN COMPLETION ............................................................................................. 28
GC 46.00
ACCEPTANCE AND FINAL PAYMENT ....................................................................................................................... 28
GC 47.00
WARRANTIES ON PORTIONS OF THE WORK .......................................................................................................... 29
GC 48.00
CONTRACTOR’S PROJECT GUARANTEE AFTER COMPLETION ................................................................................. 30
GC 49.00
MISCELLANEOUS KEYS, SWITCHES, ETC. ................................................................................................................ 30
GC 50.00
INDEMNIFICATION ................................................................................................................................................ 30
GC 51.00
LABOR DISPUTES ................................................................................................................................................... 31
GC 52.00
LIMITATION OF ACTIONS ....................................................................................................................................... 31
GC 53.00
PREFERENCE FOR COLORADO LABOR, MATERIALS, AND RESIDENT BIDDERS ........................................................ 31
GC 54.00
SALES AND USE TAX............................................................................................................................................... 31
GC 55.00
LIENS ..................................................................................................................................................................... 32
GC 56.00
OWNER’S INSPECTION OF CONTRACTOR’S RECORDS ............................................................................................ 32
GC 57.00
CERTIFICATION BY CONTRACTOR REGARDING PREMISES ACCESS ......................................................................... 32
GC 58.00
CONTRACTOR SAFETY RESPONSIBILITIES ............................................................................................................... 32
GC 59.00
CONTRACTOR ASBESTOS MANAGEMENT AND LEAD PAINT RESPONSIBILITIES ...................................................... 35
GC 60.00
ARCHITECT’S STATUS AND INSPECTIONS ............................................................................................................... 35
GC 61.00
ORAL STATEMENTS................................................................................................................................................ 35
GC 62.00
PROJECT SIGN ........................................................................................................................................................ 36
GC 63.00
HISTORICAL DATA .................................................................................................................................................. 36
GC 64.00
ASSIGNMENT ......................................................................................................................................................... 36
GC 65.00
TIME OF THE ESSENCE ........................................................................................................................................... 36
GC 66.00
DISPUTES ............................................................................................................................................................... 36
GC 67.00
SURVIVAL .............................................................................................................................................................. 36
GC 1.00
CONTRACT DOCUMENTS AND DEFINITIONS
All Work under the Construction Agreement shall be accomplished in accordance with the Contract Documents, which shall consist of the Request for Qualifications, Request for Proposals, Proposal(s), Notice of Award, Notice to Proceed, Performance Bond, Labor and Material Payment Bond, Construction Agreement, General Contract Conditions, Supplementary Conditions, Asbestos Management Plan Contractor Responsibility Form, Drawings and Specifications, tests and engineering data, approved Change Orders, Contractor’s Requests for Payment, Architect’s Certificates, and all addenda issued by the Owner or Architect prior to execution of the Construction Agreement and all modifications issued by the Owner or Architect after execution of the Construction Agreement. With respect to the Contract Documents, the following definitions and understandings shall control: 1.01 “Contract” or “Contract Documents” shall include all of the items enumerated in GC-1.00 above. 1.02 “Owner” shall mean Boulder Valley School District No. RE-2, and shall include its duly authorized representatives. 1.03 “Contractor” shall mean the corporation, company, partnership, firm, entity, or individual named and designated as such in the Construction Agreement, and any persons or entities acting on its behalf. 1.04 “Subcontractor” shall mean any corporation, partnership, entity, or individual having a direct contract with the Contractor or another subcontractor for performing Work and/or furnishing labor or material on the Project covered by the Contract. 1.05 “Architect” shall mean the corporation, partnership, entity or individual named and designated as “architect” or “engineer” in the Construction Agreement, and any persons or entities acting on the Architect’s behalf and within the scope of the particular duties properly entrusted to them in each case. In the event that there is no Architect on the Project, then “Architect” shall refer to Owner and its duly authorized representative. 1.06 “Notice to Contractor” shall be deemed to have been duly served if made in writing and delivered in person to the individual or to a member of the firm or to an officer of the corporation for which it is intended, or if sent by registered or certified mail, to Contractor’s last known business address. 1.07 “The Work” shall mean the construction and services required by the Contract Documents for completion of the Project, and includes all labor, materials, equipment and services provided or to be provided by the Contractor to fulfill the Contractor’s obligations, whether on or off the Project site, and all labor, materials equipment and services provided or to be provided by subcontractors, sub-subcontractors, or any other entity for whom the Contractor is responsible. 1.08 “The Project” is the total construction designed by the Architect of which the Work performed under the Contract Documents may be the whole or a part. 1.09 The “date of final completion” and “finally completed” shall mean the date when construction is certified by the Architect to be finally completed in accordance with the Contract Documents, as modified by any Change Orders processed under the terms of GC-23.00 below and when the Owner has fully accepted the Project for the use for which it was intended. Such date will be set forth on a letter of acceptance issued by the Owner. 1.010 “Drawings” or “plans” shall mean all (a) drawings furnished by the Owner and/or Architect as a basis for the award of Contract and for construction of the Project; (b) supplementary drawings furnished by the Owner and/or Architect to clarify and to define in greater detail the intent of the Contract drawings and specifications; (c) drawings submitted by the successful Contractor as may be required after the Contract is awarded; (d) drawings furnished by the Owner and/or Architect to the Contractor during the progress of the Work; and (e) engineering data and drawings submitted by the Contractor during the progress of the Work, provided such drawings are acceptable to the Architect and Owner. 1
1.011 “Specifications” are the written technical information concerning materials, components, systems, equipment, and manner of installation as indicated on the drawings or plans and which state the quality, performance, and characteristics to be achieved by application of construction methods. 1.012 “Change Order” shall mean a written order to the Contractor signed by the Owner or its authorized agent issued after the execution of the Construction Agreement, authorizing a change in the Work and/or adjustment in the Guaranteed Maximum Price (“GMP”) or the contract time schedule. Each adjustment in the GMP resulting from a Change Order shall clearly separate the amount attributable to the Cost of the Work and the Contractor’s Fee. 1.013 “day” or “days” shall mean calendar days. In computing a period of days, when the ending date is not specified, the first day is excluded and the last day is included. If any deadline falls on a Saturday, Sunday, or federal or Colorado state holiday, such deadline will be extended to the next day that is not a Saturday, Sunday or federal or Colorado state holiday. GC 2.00
REFERENCE STANDARDS
2.01 Reference to the standards of any technical society, organization, or association, or to codes of local or state authorities, shall mean the latest standard, code, specification, or tentative standard adopted and published as of the date of execution of the Construction Agreement, unless specifically stated otherwise. GC 3.00
DRAWINGS AND SPECIFICATIONS
3.01 Ownership of Drawings. All drawings, specifications, and copies thereof furnished by the Architect are the property of the Architect and the Owner, whether or not the Work for which they are made is performed, and are not to be used on other Work except by written agreement with the Architect and the Owner. 3.02 Figured Dimensions to Govern. Dimensions and elevations shown on the drawings shall be accurately followed. No Work shown on the drawings, the dimensions of which are not indicated, shall be executed until necessary dimensions have been obtained from the Architect. 3.03 Contractor to Check Drawings and Schedules. The Contractor shall check and verify all dimensions, elevations, and quantities shown on the drawings and furnished to it by the Architect, and shall notify the Architect of any discrepancy between the drawings and the conditions on the ground, or any error or omission in drawings, or in the layout as given by stakes, points, or instructions that it may discover. Before ordering any material or doing any Work, the Contractor shall verify all measurements concerning the Project and shall be responsible for the correctness of same. No extra charge or compensation shall be allowed on account of any difference between actual dimensions and the measurements indicated on the drawings. Any difference that may be found shall be submitted to the Architect for consideration and written determination before proceeding with the Work. The Contractor shall not be allowed to take advantage of any error or omission in the drawings or Contract Documents. Full written instructions shall be furnished by the Architect should such error or omission be discovered, and the Contractor shall carry out such instructions as if originally specified. 3.04 Detail Drawings and Instructions. The Architect shall furnish with reasonable promptness additional instructions, by means of drawings or otherwise, necessary for the proper execution of the Work. All such drawings and instructions shall be consistent with the Contract Documents. The Work shall be executed in conformity with the Architect’s drawings and instructions, and the Contractor shall do no Work without proper drawings and instructions. 3.05 Drawings and Specifications Available on the Site. The Contractor shall maintain at the Project site for the Owner and the Architect a Project record set of drawings, including addenda, approved shop drawings, Change Orders, and other modifications, with all changes or deviations from the original drawings neatly marked thereon in a contrasting color. The Contractor shall also maintain a Project record set of specifications at the 2
Project site, noting therein by appropriate section the names, models, and other distinguishing characteristics of the materials actually incorporated into the Work. This Project record set of drawings and specifications shall be updated daily as the Project progresses and shall be made available to the Owner and Architect for inspection at all times. Upon final completion of the Work and before final payment, three (3) copies and one (1) electronic of this Project record set of drawings and specifications shall be delivered to the Owner. One (1) copy of this Project record set of drawings and specification shall be delivered to the Architect. 3.06 Laws and Regulations. The Contractor shall give all notices and comply with all laws, ordinances, rules, and regulations bearing on the conduct of the Work as drawn and specified. If the Contractor observes that the drawings and specifications are at variance therewith, it shall promptly notify the Architect in writing, and any necessary adjustments shall be made as provided in the Contract for changes in the Work. If the Contractor performs any Work knowing it to be contrary to such laws, ordinances, rules, or regulations without giving the required notice to the Architect and receiving a written directive to proceed, it shall bear all costs arising therefrom and to correct and/or remedy same. GC 4.00
ROYALTIES AND PATENTS
The Contractor shall pay all royalties and license fees. The Contractor shall defend all suits or claims for infringement of patent rights and shall hold the Owner harmless from any and all liability or loss on account thereof. If the Contractor has information that the process or article specified involves the infringement of a patent, it shall be responsible for any and all liability or loss resulting therefrom unless it promptly furnishes such information to the Architect in writing. GC 5.00
ITEMS COVERED BY CONTRACT PRICE
5.01 Items Supplied by Owner. Owner shall supply the following items for the Project: a. Building Permit; b. Initial Survey; c. Materials Testing Including Soil Testing; d. Third Party Inspections; e. Commissioning; and f. Test and Balance as Required for Commissioning. 5.02 Items Supplied by Contractor. Unless specifically stated otherwise, the Contractor shall accept the compensation stated in the Construction Agreement as full payment for furnishing all the materials, transportation, apparatus, temporary structures, equipment, services, fuel, energy, light, water, labor and tools, and all other things necessary for the complete and proper execution of the Work contemplated by or reasonably implied from the Contract Documents, within the time limits indicated therein. Such amount shall include any loss or damage resulting from the nature of the Work, from the elements or from any unforeseen difficulties that may be encountered; all risks of every description connected with the prosecution of the Work; all expenses incurred in consequence of any suspension or discontinuance of the Work; and all other amounts necessary for completing the Work pursuant to the Contract Documents within the time limits indicated therein. GC 6.00
EXECUTION, CORRELATION, INTENT, AND INTERPRETATION OF CONTRACT DOCUMENTS
6.01 Execution. The Construction Agreement and other Contract Documents shall be signed in multiple copies as directed by the Owner. Within ten (10) days of Notice of Award, the Contractor shall submit to the Owner a minimum of five (5) fully executed original sets of the Construction Agreement; Performance Bond, and Labor and Material Payment Bond with original Power of Attorney; and certificates of required insurance coverage. The date of the Contract for purposes of these documents shall be the date of the Notice of Award letter. The Owner shall execute the Construction Agreement, assemble all copies, and distribute the Contract Documents. The Contractor shall not commence the Work until it receives the Notice to Proceed. All bonds and insurance 3
certificates shall be submitted to the Owner prior to the award of the first subcontract. 6.02 Correlation. By executing the Construction Agreement, the Contractor represents that it has visited the Project site, familiarized itself with the local conditions under which the Work is to be performed, and correlated its observations with the requirements of the Contract Documents. 6.03 Intent. The intention of the Contract Documents is to include all labor and materials, tools, equipment, construction equipment, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution and completion of the Work. Materials or Work described in words that, as applied, have a well-known technical or trade meaning shall be held to refer to such recognized meaning. The organization of the specifications into divisions, sections, and articles, as the case may be, and the arrangement of drawings shall not control the Contractor in dividing the Work among subcontractors or in establishing the extent of Work to be performed by any trade. It is intended that even though Work is not covered under any heading, division, section, article, branch, class, or trade of the specifications, it shall nevertheless be supplied if it is required elsewhere in the Contract Documents or is reasonably inferable therefrom as being necessary to produce the intended results. The specifications and drawings are intended to supplement but not necessarily duplicate each other. Any Work exhibited in the one and not in the other shall be executed as if it had been set forth in both, so that the Work will be constructed according to the complete design as determined by the Architect. 6.04 Interpretation. Should anything necessary for a clear understanding of the Work be omitted from the specifications and drawings, or should the requirements appear to be in conflict, the Contractor shall secure written interpretations or instructions from the Architect before proceeding with the Work affected thereby. The Contractor shall secure written interpretations or instructions by submitting the Owner’s form Request for Interpretation to the Architect. Oral requests shall not be acknowledged by the Architect or Owner. Additional costs incurred by the Owner as a result of unnecessary requests made by the Contractor, as determined by the Owner, shall be the responsibility of the Contractor. It is understood and agreed that the Work shall be performed according to the true intent of the Contract Documents. 6.05 Conflict in Interpretation. In the case of discrepancy or in the event of a conflict between the different Contract Documents, the documents shall take precedence in the following order: a. Change Orders; b. Written Amendments to Construction Agreement (including, if applicable, the GMP); c. Construction Agreement; d. General Conditions; e. Drawings and specifications; and f. Bid Documents, including addenda. Where two or more of the Contract Documents are complementary, the more detailed provision shall control over the more general provision. GC 7.00
MATERIALS, LABOR, FACILITIES, AND STORAGE
7.01 Contractor’s Responsibility. Unless otherwise agreed in writing, the Contractor shall provide and pay for all materials, labor, tools, equipment, machinery, transportation, and other facilities necessary for the proper execution and completion of the Work. The Contractor shall provide and pay for all the temporary facilities required to supply all the power, light, water, and heat needed by it and its subcontractors for their Work and shall install and maintain all such facilities in such manner as to protect the public and workers and to conform with any applicable laws and regulations. If temporary heat and/or protection is required for the expeditious prosecution of the Work and before the permanent heating apparatus is available for use, the temporary heating apparatus shall be installed and operated in such a manner that the finish Work and/or construction will not be damaged thereby. Unless otherwise specified, the Contractor shall pay for all the power, light, and water used by it and its subcontractors, without regard to whether such items are metered by temporary or permanent meters. The cutoff date on permanent meters shall be either the agreed date of full occupancy by 4
the Owner or the date of final acceptance of the Project, whichever shall be the earlier date. Upon completion of the Work, the Contractor shall remove all surplus materials, tools and such temporary facilities and structures, furnished by the contractor from the Project site. All debris and rubbish caused by the operations of the contractor shall be removed, and the area occupied during construction activities shall be restored to its original condition, within 48 hours of project completion, unless otherwise directed by the municipality or owner’s representative. 7.02 Materials. Unless otherwise specified, all materials shall be new and both Workmanship and materials shall be of the highest quality. The Contractor shall furnish satisfactory evidence to the Owner as to the kind and quality of materials. Samples shall be furnished, when specified, and the Work shall be in accordance with those samples that have been approved. 7.03 Toilet Facilities. The Contractor shall provide and maintain, in a neat and sanitary condition, adequate temporary toilet facilities for the use of any and all employees engaged on the Work, in strict compliance with the requirements of all applicable codes, regulations, laws, and ordinances. In no event may present toilet facilities of any existing building at the site of the Work be used by employees of the Contractor or its subcontractors. Upon final completion of the Work, the Contractor shall remove all such temporary facilities from the site and disinfect the premises. 7.04 Facilities and Storage. The Contractor shall provide suitable temporary facilities and quarters for workers, as needed, and shall maintain on premises water-tight storage sheds or tool houses for storage of building materials and tools that could be damaged by weather. The Contractor shall allow space for the erection of sheds and provide similar facilities for storage by subcontractors of their materials and tools. Storage of materials shall be confined to the site. These facilities or quarters shall further provide for protection against theft and damage of building materials and tools. Upon final completion of the Work, the Contractor shall remove all such temporary facilities from the site. 7.05 Office Space. The Contractor shall provide adequate, weatherproofed, heated and well- lighted office space at the site of the Work, for use by the Architect and the Owner and their representatives. The Contractor shall also provide telephone service at such office, which shall be available for use by the Architect, the Owner, and their representatives without charge, except for toll calls. 7.06 Quality and Location of Facilities. All of the foregoing facilities shall be of a quality and placed in locations acceptable to the Architect and the Owner. GC 8.00
PERFORMANCE AND PAYMENT BONDS
8.01 Required Bonds. The Contractor shall, within ten (10) days from the Notice of Award furnish bonds to the Owner in the full amount of the contract price, covering both the faithful performance of the Contract and the payment of all obligations for labor and materials arising thereunder, on such customary forms as the Owner may prescribe and with such sureties as it may approve. The amount of the bonds shall be increased, if necessary, to reflect approved changes in the Work that result in an increase in the total cost of the Work plus the Contractor’s fees. Such bonds shall be duly executed by a qualified surety licensed to do business in the State of Colorado, conditioned upon the true and faithful performance of the Contract, and shall provide that if the Contractor or its subcontractors fail to duly pay for any labor, materials, or other supplies used or consumed by such Contractor or its subcontractors in the performance of the Work contracted to be done, the surety will pay the same in an amount not exceeding the sum specified in the bond, as adjusted by approved Change Orders, and together with interest as provided by law. The performance bond shall additionally guarantee that the Contractor shall remedy any omissions, correct any and all defects, and adjust and make operable all component parts of Work falling under the requirements of the Contract that may be called to the Contractor’s attention within a period of twenty-four (24) months following the date of the letter of acceptance.
5
8.02 Additional Bond Requirements. The premium for all bonds shall be paid by the Contractor and included in the bid price in the bid proposal. The Owner will accept and approve bonds written by sureties legally authorized to write such bonds in the State of Colorado, provided such surety companies are rated in Best’s Insurance Guide (latest edition), not lower than A- or have Best’s Financial Rating of at least X. If, at any time a surety on such a bond becomes irresponsible or loses its right to do business in the State of Colorado, new bonds shall be provided by an alternate surety licensed to do business in the State and meeting the requirements of this Section 8.00. GC 9.00
PERMITS AND COMPLIANCE WITH STATUTES, RULES, AND REGULATIONS
9.01 Permits. Any local permits, governmental fees, and licenses necessary for the proper execution and completion of the Work shall be secured and paid for by the Contractor. Owner will pay for and secure building permit from Colorado Division of Fire Prevention and Control. Easements for permanent structures or permanent changes in existing facilities shall be secured and paid for by the Owner, unless otherwise specified in writing. The Owner is generally exempt from paying any fee for any building permit issued by any building departments or agencies located in Boulder, Broomfield, and Gilpin Counties, and the Contractor shall see that no building permit fee is paid. The Owner shall negotiate and provide for all electrical, gas, water, and sewer mains for the Contractor’s connections. The Contractor shall arrange with the utility company for actual connection, make necessary connections, and pay for all associated inspection fees and permits as required by any government agency. In addition, the Contractor shall furnish all material and items required to complete all connections. The Contractor shall call for all inspections on a timely basis by any agency having jurisdiction over the Work. 9.02 Compliance with Statutes, Rules and Regulations. The Contractor and all subcontractors shall comply with all applicable federal and state statutes, rules, regulations, and directives of the State Division of Fire Prevention and Control, and other governmental body having jurisdiction over the work to be performed. If any of the provisions of the Contract Documents are in conflict therewith, such portions shall be considered stricken and the applicable statute, ordinance, regulation, or ruling substituted therefor. All such cases of apparent conflict coming to the attention of any party shall immediately be called to the attention of the Owner. The Contractor shall strictly observe and comply with all federal and state laws pertaining to the employment and payment of labor. GC 10.00
SURVEYS, BENCHMARKS, MONUMENTS, STAKES, AND MEASUREMENTS
10.01 Surveys. As provided by the Owner, the Contractor shall obtain from the Architect a copy of all surveys describing property lines, elevation benchmarks, physical characteristics, and utility locations. 10.02 Benchmarks. The Contractor shall properly stake out the Work and provide and rigidly set benchmarks and batter boards as necessary for the proper performance of the Work. The Contractor shall remain responsible for their maintenance and their accuracy. A permanent benchmark, approved as to location and type by the Architect, from which all grades are to be taken, shall be established near the site of the Work by the Contractor. From this benchmark the Contractor shall ascertain all grades and levels to Project buildings as needed. The Contract Documents shall include all necessary information to establish the benchmark. 10.03 Preservation of Monuments and Stakes. The Contractor shall carefully preserve all monuments, benchmarks, property markers, reference points, and stakes. In case of the destruction thereof, the Contractor shall be charged with the expense of replacement and shall be responsible for any mistake or loss of time that may be caused. Permanent monuments and/or benchmarks that must be removed or disturbed shall be protected until properly referenced for relocation. The Contractor shall furnish all materials, labor and assistance for the proper replacement of such monuments and benchmarks. 10.04 Measurements. Before ordering any material or performing any Work, the Contractor shall verify all measurements on the Project and shall be responsible for the accuracy of same. No extra charge or 6
compensation shall be allowed because of any difference between actual dimensions and the measurements indicated in the drawings or specifications. Any discrepancies shall be submitted to the Architect and Owner for consideration before proceeding with the Work. GC 11.00
CHANGED CONDITIONS
The Contractor shall promptly, and before such conditions are disturbed, notify the Owner and the Architect in writing of: (1) sub-surface or latent physical conditions at the Project site differing materially from those indicated in the Contract Documents, or (2) unknown physical conditions at the Project site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in Work of the character provided for in the Contract Documents. The Owner and the Architect shall promptly investigate the conditions, and if the Owner finds that such conditions do so materially differ and cause an increase or decrease in the cost of or the time required for performance of the Work, an equitable adjustment shall be made and the Contract modified in writing accordingly. Any claim of the Contractor for adjustment hereunder shall not be allowed unless it has given notice as required. GC 12.00
PROTECTION OF PERSONS, WORK AND PROPERTY
12.01 Building Exits and Barricades. During the course of construction, the Contractor shall keep all required building exits free and unimpeded. Such exits shall not be closed at any time for any reason while the building is occupied or at any time when the building is unoccupied, except after written approval is given by the Owner and proper warning and directional signs are posted. Barricades shall be erected so that traffic is separated and protected from the construction. 12.02 Precautions. The Contractor shall take all necessary precautions to ensure the safety of all employees and other persons on the Project or who may be affected by the Contractor’s Work thereon. The Contractor shall also take all necessary precautions to protect the Work and all temporary facilities, as well as materials, tools, and equipment incorporated therein or to be incorporated therein from damage or destruction, whether in storage on or off the Project site and whether in the custody or control of the Contractor or any of its subcontractors. The Contractor shall also take all necessary precautions to protect all property at the Project site and adjacent thereto not designated for removal, relocation or replacement, including trees, shrubs, lawns, walks, pavements, roadways, structures, and utilities. 12.03 OSHA Compliance. The Contractor shall comply with all applicable provisions of the Occupational Safety and Health Administration (“OSHA”) and all laws, ordinances, rules, regulations, and orders of all governmental agencies or authorities having jurisdiction to protect the safety of employees and/or other persons who may be affected by the Work. The Contractor shall erect and maintain all necessary safeguards to protect workers on the Project site and the owners and users of adjacent property, and shall post danger signs and other warnings against hazards created by the Work including but not limited to protruding nails, hoists, well holes, elevator shafts, hatchways, scaffolding, window openings, stairways, excavations, and falling materials. The Contractor shall designate a responsible employee at the Project site as a safety officer to ensure the Contractor’s compliance with this section. Said employee shall be the Contractor’s superintendent unless otherwise designated in writing by the Contractor to the Owner and the Architect. 12.04 Contractor’s Liability. The Contractor shall be liable for all injury, damage or loss to any person or property caused in whole or in part by the Contractor, any of its subcontractors, or any person employed by or under the direction of the Contractor or any of its subcontractors. To the extent possible and unless otherwise directed by the Owner or Architect, the Contractor shall promptly repair, pay for or otherwise remedy any such injury, damage or loss and shall indemnify and hold harmless the Owner against any and all liability, claims, damages, losses and expenses arising therefrom. The terms of this section shall not apply in the case of injury, damage or loss proximately caused by the acts or omissions of the Owner and/or Architect and not attributable to any fault or negligence of the Contractor.
7
12.05 Emergencies. In the event of an emergency that threatens the safety or life of any person or threatens to damage or destroy the Project and/or any Work, materials, equipment or property thereon or to be used thereon, the Contractor shall act at its discretion to prevent such injury, death, damage or destruction. The Contractor shall immediately notify the Owner and Architect in writing of any such emergency and any action taken by the Contractor in response thereto. Any compensation due the Contractor for such emergency action shall be determined by agreement of the Contractor, Owner and Architect, and an appropriate Change Order shall be issued therefor. GC 13.00
WORK ON EXISTING BUILDINGS
13.01 Protection of Occupants. In addition to all other requirements of the Contract Documents, if the Work involves an addition or alteration to an existing building, the Contractor shall erect and maintain during the progress of the Work suitable dustproof partitions to protect such building and the occupants thereof. If necessary, in the Owner’s or Contractor’s judgment or pursuant to manufacturer’s directives or recommendations in order to protect occupants from noxious fumes, odors, or hazardous substances, the Contractor may be required to provide additional ventilation and/or work different or extended hours to avoid disruption to other activities within the existing building. Contractor shall protect and keep from harm all occupants of an existing building from construction activities, and shall include a safe pathway into and out of the school. 13.02 Partitions and Scheduling. If any portions of an existing building are to be remodeled or repaired, such portions shall be adequately partitioned off with dustproof partitions and well ventilated. All remodeling Work shall be scheduled and submitted to the Owner and Architect for approval. The various contractors shall schedule their Work jointly, in order that each may accomplish its Work within such existing building in an orderly fashion during regular school vacation periods where possible, or in such a manner as to permit full use of the building and without impairment of any existing facilities. 13.03 Existing Systems. Existing building systems, such as fire alarm, temperature controls and air distribution, security systems, public announcement systems, irrigation systems, and the like, shall be demonstrated and noted by Owner to the Contractor as operational prior to Contractor’s commencing the Work and Contractor may participate in observation of such systems. Such systems are the responsibility of the Contractor to maintain in pre-construction condition. GC 14.00
CONTRACTOR’S SUPERINTENDENCE AND SUPERVISION
14.01 Superintendent. During the progress of the Work, the Contractor shall ensure that a competent superintendent and any necessary assistants, all satisfactory to the Architect and the Owner, are on the Project site at all times while Work is in progress. The superintendent shall not be changed by the Contractor except with the written consent of the Architect and the Owner, unless the superintendent ceases to be in the Contractor’s employ. The superintendent shall represent the Contractor on the Project and all directions given to him/her shall be as binding as if given to the Contractor. The Architect and the Owner shall not be responsible for the acts or omissions of the superintendent or his/her assistants. 14.02 Supervision. The Contractor shall provide full-time, qualified, and efficient supervision of the Work, using competent skill and attention. The Contractor is responsible for determining and supervising all temporary and permanent erection and construction sequences, techniques, means, or methods. The Contractor shall direct, schedule, coordinate the Work to ensure that all parts fit together properly and in accordance with the Contract Documents. The Contractor shall carefully study and compare all Contract Documents and other instructions and shall at once report to the Architect and the Owner any error, inconsistency, or omission that Contractor may discover. 14.03 Additional Supervision Duties. The Contractor shall see that the Work is carried out in accordance with the Contract Documents and in a thorough and first-class manner in every respect. The Contractor shall 8
provide engineering, surveying, and coordination to accurately establish all lines, levels, and marks necessary to facilitate the operations of all parties involved in the Contractor’s Work. The Contractor shall lay out the Work in a manner satisfactory to the Architect, making permanent records of all lines and levels required for excavation, grading, and foundations, and for all other parts of the Work. The Contractor shall be responsible for the commencement and the proper completion of the various stages and sequences of construction. The Contractor shall strictly adhere to the approved construction schedule. GC 15.00
SUBSTITUTIONS
The Contractor shall be held to have used in its base proposal and to furnish under the Contract those items of equipment and/or materials that are specifically identified in the plans and specifications by a manufacturer’s name, model, or catalog number. Items of equipment and/or materials of the Contractor’s choice may be offered as alternates to the items named in the plans and specifications by submitting, with the proposal and on the form provided, identifying data on the articles proposed together with a statement of the amount of addition or deduction from the base bid if the bidder’s alternate is accepted. Prior approval by the Architect is not required on items submitted as alternate bids. After execution of the Construction Agreement, substitution of equipment and/or materials of makes other than those specifically named in the Contract Documents may be approved by the Owner so long as the equipment or material proposed for substitution in the opinion of the Owner is just as suitable as the equipment and/or materials named in the plans and specifications so far as performance, construction, efficiency, and utility are concerned. A request for substitution shall ordinarily be required to be based upon one or more of the following grounds: the specified equipment or material is no longer available, a substitution will improve lead time, quality will be improved (documented detail required), or the Owner will incur substantial savings. All requests for substitution must be submitted in writing with supporting documentation by or through the Contractor to the Architect for initial review and recommendation before being submitted to the Owner for evaluation and final approval. In the absence of the Owner’s written approval, no substitution of equipment or materials shall be allowed for any items specified in the Contract Documents. In case of a difference in price, occurring as a result of an approved substitution, the Owner shall receive all benefit of the difference in cost involved in the substitution. All approved substitutions shall be documented by the issuance of a formal Change Order as provided in these General Conditions. GC 16.00
SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
16.01 Shop Drawings. “Shop drawings” are drawings, diagrams, illustrations, schedules, performance charts, brochures, manufacturer’s literature, and other data that are prepared by the Contractor or any subcontractor, manufacturer, supplier, or distributor, and that illustrate some portion of the Work. Shop drawings shall be submitted in both hard copy and electronic format. 16.02 Samples. “Samples” are physical examples furnished by the Contractor to the Owner and/or Architect to illustrate materials, finishes, equipment, or Workmanship, and to establish standards by which the Work will be judged. 16.03 Product Data. “Product data” are illustrations, standard schedules, performance charts, instructions, brochures, diagrams and other information furnished by the Contractor to illustrate materials or equipment for some portion of the Work. Product data shall be submitted in both hard copy and electronic format. 16.04 Contractor’s Obligations. The Contractor shall review, approve, stamp an then submit to the Architect shop drawings, product data, samples, and similar submittals required by the Contract Documents with reasonable promptness and in such a sequence as to cause no delay in the Work or in the activities of the Owner or of separate contractors. Shop drawings, product data, samples, and similar submittal required by the Contract Documents shall properly identify specified items. At the time of submission, the Contractor shall inform the Architect in writing of any deviation in the shop drawings, product data, or samples from the requirements of the Contract Documents. Substitutions will be allowed only in accordance with the provisions of GC-15.00. The number of copies and format of submittal shall be as required by the Architect, but, at a 9
minimum, shall include three (3) copies and one (1) electronic copy of the original shop drawings and product data for the Owner. 16.05 Verification. By approving and submitting shop drawings, product data, and samples, the Contractor thereby represents that it has determined and verified all field measurements, field construction criteria, dimensions, elevations, quantities, materials, catalog numbers, and similar data, as shown on the drawings and specifications furnished by the Architect, or will do so, and that it has checked and coordinated each shop drawing, product data, and sample with the requirements of the Work and of the Contract Documents. 16.06 Architect /Owner Review. The Architect shall review and approve shop drawings, product data, and samples with reasonable promptness so as to cause no delay, but only for conformance with the design concept of the Project and with the information given in the Contract Documents. The Architect’s approval of a separate item shall not indicate approval of any assembly in which the item functions. Upon the final completion of the Work, the Contractor shall furnish to the Architect two corrected copies of all shop or setting drawings showing the as-built condition of the Work. The Architect, after review, shall submit one of these copies to the Owner. 16.07 Corrections. The Contractor shall make any corrections required by the Architect and shall resubmit the required number of corrected copies of shop drawings or new samples until approved by the Architect. The Contractor shall direct specific attention in a separate writing or on resubmitted shop drawings to revisions other than the corrections requested by the Architect on previous submissions. 16.08 Contractor’s Responsibility. The Architect’s approval of shop drawings, product data, or samples shall not relieve the Contractor of responsibility for any deviation from the requirements of the Contract Documents unless the Contractor has informed the Architect in writing of such deviation at the time of submittal and the Architect has given written approval of the specific deviation. The Architect’s approval shall also not relieve the Contractor from responsibility for errors or omissions in the shop drawings, product data, or samples. 16.09 Architect Approval Required. No portion of the Work requiring the submission of a shop drawing, product data, or sample shall be commenced until such submittal has been approved in writing by the Architect. All such portions of the Work shall be in accordance with approved shop drawings, product data, and samples. All material finishes and samples shall be approved at one time. The Contractor shall submit all items requiring approval of finishes, color, material, etc., with sufficient lead time to allow simultaneous consideration and preparation of complete finish color schedule. No approvals of single items shall be considered. 16.010 Copies to Owner. When shop drawings, product data, samples or similar submittals have been approved and stamped by both Contractor and Architect, Contractor shall immediately forward an electronic copy of each to the Owner. GC 17.00
CASH ALLOWANCE
The Contractor shall include in the Contract sum all allowances named in the Contract Documents and shall cause the work so covered to be done by such Contractors and for such sums as the Owner may direct, the Contract sum being adjusted in conformity therewith. The Contractor declares that the Contract sum includes such sums for expenses and profit on account of cash allowances as he deems proper. No demand for expenses or profit other than those included in the Contract sum shall be allowed. The Contractor shall not be required to employ for any such work persons against whom he has filed a lien or has a reasonable objection due to previous legal claims. GC 18.00
EXPEDITING MATERIALS 10
The Contractor shall, immediately after receipt of the Notice of Award and approval of its list of subcontractors and material suppliers, place orders for all equipment, materials, and supplies required for the Work. The Contractor shall, when requested, submit to the Architect evidence that such orders have been placed. The Contractor shall exercise due diligence in seeing that all equipment, materials, and supplies are delivered well in advance of the time they are needed on the Project and shall properly store and protect same at its expense and in accordance with these General Conditions, either at the Project site or elsewhere as approved by the Architect. GC 19.00
BLASTING
No explosives of any nature except for those normally employed in powder actuated tools, .38 caliber or smaller, shall be employed or used on the Project site except with the express and specific prior written approval of the Architect and the Owner and any appropriate governmental authorities, in each instance. The Contractor shall notify the Architect of need for such approval three (3) days prior to the proposed use of such explosives. GC 20.00
SOIL TEST REPORT
The Owner may arrange for a separate consultant to conduct field and laboratory soil investigations on the Project site and to prepare a report of its findings. Such a report, if prepared, shall be available for review by the Contractor in the Architect’s office. Such data is offered solely for reference and is not to be considered a part of the Contract Documents. The data contained in any such document prepared for the Owner by a separate consultant is believed to be reliable; however, the Owner and Architect do not guarantee its accuracy or completeness. All applicable subcontractors shall be fully familiar with the contents of such reports, if prepared, and shall consider and evaluate them in the performance of their contracts and the Work. GC 21.00
HAZARDOUS MATERIALS
21.01 Responsibility and Reporting. Unless otherwise provided in the Contract Documents, the Contractor shall have no responsibility for the presence, handling, removal or disposal of hazardous materials in any form at the Project site, including but not limited to asbestos, asbestos products, polychlorinated biphenyl (PCB), lead, or other hazardous materials. Prior to its commencement or continuation of any portion of the Work, the Contractor shall provide notice to the Owner of the presence, location, amount and condition of any known or suspected hazardous materials that are discovered at the Project site. Such notice shall be in writing and shall be submitted no more than twenty-four (24) hours after the presence of such materials becomes known or suspected. 21.02 Contractor’s Obligations. In the event hazardous materials become known or suspected by the Contractor as described in GC-21.01 above, the Contractor shall not proceed with or continue the Work until it has received written authorization from the Owner. If the Contractor proceeds with the Work without said authorization, it assumes any and all responsibility and liability for contamination and cleanup at the Project site according to applicable federal and state laws, and for any death or personal injury, including but not limited to medical expenses that may be incurred by any individual as a result of exposure to hazardous materials on the Project site. 21.03 Owner’s Obligations. In the event hazardous materials are identified or encountered during the course of the Project, the Owner at its expense shall take reasonable actions to properly and safely deal with such materials. 21.04 Management Plan. The Contractor acknowledges that it and its employees, agents and subcontractors have the responsibility of being fully informed of the Owner’s Management Plan as it relates to buildings located at the Project site and shall consult with the Owner about how such Plan addresses suspected or active asbestos-containing material areas within such buildings. GC 22.00
DAMAGE TO UTILITIES 11